Demo & Grading

1
Demo & Grading Pilings Form & Pour Pile Caps/Grade Beams Form & Pour 1st Flr/Columns/Walls Form & Pour 2nd Flr/Columns/Walls Form & Pour 3rd Flr/Columns/Walls Form & Pour Roof (Dry In) Bldg Specialties & Finishes Receive & Set Equipment Process Piping Process Electrical Instrumentation Checkout & Turnover Line 1 Line 2 Line 3 Planned vs Actual Critical Path 1994 1997 Demo & Grading Pilings Form & Pour Pile Caps/Grade Beams Form & Pour 1st Flr Form & Pour 2nd Flr Form & Pour 3rd Flr Form & Pour Roof (Dry In) 1995 Planned Duration Actual Duration Piling Delay Causes Acceleration Delay Acceleration 1/3/96 “Dry In ON TIME

description

1995. Demo & Grading. Demo & Grading. Pilings. Pilings. Form & Pour Pile Caps/Grade Beams. Form & Pour Pile Caps/Grade Beams. Form & Pour 1st Flr/Columns/Walls. Form & Pour 1st Flr. Form & Pour 2nd Flr/Columns/Walls. Form & Pour 2nd Flr. Form & Pour 3rd Flr/Columns/Walls. - PowerPoint PPT Presentation

Transcript of Demo & Grading

Page 1: Demo & Grading

Demo & Grading

Pilings

Form & Pour Pile Caps/Grade Beams

Form & Pour 1st Flr/Columns/Walls

Form & Pour 2nd Flr/Columns/Walls

Form & Pour 3rd Flr/Columns/Walls

Form & Pour Roof (Dry In)

Bldg Specialties & Finishes

Receive & Set Equipment

Process Piping

Process Electrical

Instrumentation

Checkout & Turnover Line 1

Line 2

Line 3

Planned vs Actual Critical Path1994 1995 1996 1997

Demo & Grading

Pilings

Form & Pour Pile Caps/Grade Beams

Form & Pour 1st Flr

Form & Pour 2nd Flr

Form & Pour 3rd Flr

Form & Pour Roof (Dry In)

1995

Planned Duration

Actual Duration

Piling Delay Causes

Acceleration

DelayAcceleration 1/3/96 “Dry In”

ON TIME