Demand Side Management
Transcript of Demand Side Management
Dr R S E T H U M A D H A V A N
P r o f e s s o r & C o - o r d i n a t o r
I n s t i t u t e f o r E n e r g y S t u d i e s A n n a U n i v e r s i t y, C h e n n a i
E N E R G Y G E N E R A T I O N – S C E N A R I O R e n e w a b l e
5 . 0 %N u c l e a r
2 . 7 %
H y d r o 2 6 . 0 %
T h e r m a l
6 6 . 3 %
T O T A L I N S T A L L E D C A P A C I T Y
= 1 3 1 0 0 0 M W
0
50000
100000
Peak Normal
E L E C T R I C I T Y E L E C T R I C I T Y P E A K v s N O R M A LP E A K v s N O R M A L
8 0 6 3 1 M W
9 . 1 %
P E A K D E M A N D D E F I C I T - 9 . P E A K D E M A N D D E F I C I T - 9 . 1 %1 %
8 8 6 6 7 M W
MW
0
250
500
G e n e r a t i o n D e m a n d
Billion un
its
G E N E R A T I O N v s D E M A N D
7 . 4 %
E N E R G Y D E F I C I T - 7 . 4 %
4 1 1 . 7
3 8 1 . 4
0
5000
10000
Peak Normal
P E A K v s N O R M A P E A K v s N O R M A LL
6 5 0 0 6 4 0 0M
W
1 . 5 %
P E A K D E M A N D D E F I C I T - 1 . P E A K D E M A N D D E F I C I T - 1 . 5 %5 %
0
20
40
60
G e n e r a t i o n D e m a n d
5 2 5 3 . 6
E N E R G Y D E F I C I T - 3 %E N E R G Y D E F I C I T - 3 %
M W
3 %
136 5 266 9 77430 000
80 000
1 38 000
70 - 71 80 - 81 90 - 91 01 - 02 03 - 04 04 - 05 10 - 11
O I LG R O W I N G I M P O R T B I L L
R s
i n
C
r o
r e s
?7 0 % of consumption imported
5 4736 693 7 758
11 500
9392854
2 317
0
5000
10000
15000
1990 1992 1994 1996 1998 2000 2002 2004 2006
Conventional
Renewable
M W
Year 1990 1995 2000 2004 2005Conventional
MW5 473 6 693 7 758 10 950 11 500
Renewable 4 285 939 1 648 2 317% 0.1 4.3 12.1 15.1 20.1
H E A R T E N I N G I N F OG R O W T H O F R E I N T N
m i l l i o n t o n s / y e a r
• P L A N N I N G• I M P L E M E N T A T I O N
&• M O N I TO R I N G
THE ACTIVITY OF ELECTRICAL UTILITIES Encourages consumers to modify their level and usage pattern of electricity
D S M C O M P R I S E S
A I M S T Y P I C A L L Y To minimize the Cost of Generation,
Transmission & Distribution of
Electricity
To meet Customer Energy Needs
a) always without Quality Deterioration &
b) at Lowest Possible Cost
A C H I E V I N G T H E T A R G E T 3 P R O N G E D A P P R O A C H
1 k V A Monitoring &
Optimization
2 Energy Efficiency Program
3 Renewable Energy usage O P T I O N S
k V A M O N I T O R I N G R E C O R D
(i) Contract Demand
(ii) Maximum Demand Reached
(iii) Average Demand
(iv) Minimum Demand
Avoidable
Can be curtailed
U s e f u l
Avoidable 5 5 . 8 %Can be Curtailed 2 4 . 2 %
Useful 2 0 . 0 %
k V A U S A G E P A T T E R N
P R O C E S S I N D U S T R Y
Useful4 6 . 4 %
Avoidable 1 1 . 8 %Can be
Curtailed 4 1 . 8 %
I T
Useful5 5 . 6 %
Avoidable7 . 3 %
Can be Curtailed 3 7 . 1 %
E L E C T R O N I C S
• Proper Scheduling of Operation
• Shifting of Peak Hour Operation to
non - Peak Hour Operation wherever
Feasible
• Possible Elimination of Operation
altogether
A c h i e v e d t h r o u g h
1 k W Saving = 1 k V A Saving
7 0 0 0 k W h Saving + 12 k V A Saving
Rs 2 9 4 0 0 / y R s 3 6 0 0 / y
7 0 0 0 h / y 1 2 m o n t h
Rs 4 . 2 / k W h Rs 3 0 0 / kVA
T O T A L S A V I N G S R s 3 3 0 0 0 / y / k W
B E F O R E O P T I M I Z A T I O N
1 3 5 . 51 7 8 . 6 8
k V A
A F T E R O P T I M I Z A T I O N
75
150
22516.30
18.00
19.30
21.00
22.30
24.00
1.30
3.00
4.30
6.00
7.30
9.00
10.30
12.00
13.30
15.00
Time
kVA
Average = 1 2 6 k V A
Maximum = 1 5 6 . 6 1 k V A
Minimum = 9 5 . 3 k V A
I N S H O R T
• A n a l y z e t h e E n e r g y B i l l
k W h C h a r g e s k V A C h a r g e s
Reduce k W h As a Fall out k V A Reduction
H I G H E R C O S T S A V I N G
HIGHER THE kVA % BETTER IS THE SCOPE k V A
1 8 . 5 %
k W h8 1 . 5 %
k V A2 4 %
k W h7 6 %
k V A3 7 %
k W h6 3 %
M O T O R S P U M P S
A I R C O M P R E S S O R S
I L L U M I N A T I O N ( Minor )
1 k W = R s 3 3 0 0 0 / yCapital Cost 1 % & Operation Cost 9 9 %
Possible to save not less than 2 0 %
I N E L E C T R I C A L U T I L I T I E S
A l l t h e s e c a n h a p p e n w i t h v e r y l e s s
i n v e s t m e n t
Operating Cost
9 9 % Capital Cost1 %
L I F E C Y C L E C O S T
1 k W = Rs 3 5 0 0 0 / y
• Even a small motor of 7 . 5 kW consumes Rs 1 5 Lakhs of Power in 1 0 years.
• Operating Cost Capital Cost within 3 weeks of usageMotor Rating kW 7.5 37Efficiency % 86 92Power Input kW 8.72 40.22Running Period h / y 6 000 6 000Energy Input kWh 52 320 2 41 320Running Cost @ Rs 3.50 / kWh 1 83 120 8 44 620Running Cost for 10 y Rs 18 31 200 84 46 200First Cost Rs 18 000 70 000First Cost as % of Running Cost 0 . 9 8 0 . 8 3
• A 3 7 kW motor consumes Rs 7 2 Lakhs in 1 0 years.
A n E x a m p l e
L I F E C Y C L E C O S T
Initial Cost + Energy Cost + Maint. Cost
Initial Cost2 %
Maintenance Cost3 %
Energy Cost 9 5 %
1 0 0 %Motor
90 %
10 % Motor Losses
90 % Pump Input
Pump
85 %
13.5 % Pump Losses
15.3 %
Throttling Valve
Losses
12.2 % Losses due to
Leakage, Extra
Flow, etc
76.5 % Pump Output
61.2 % Output
Head Lost
in Valve
s 20 %
Losses Due to
Leakage, Extra Flow etc. 20 %
4 9 %
Motor 7.85 %
Oversized Motor, Motor
with Low Efficiency
15 % Motor Losses
85 % Pump Input
85 % Pump
Losses
29.75 % Valve Losses
14.75 % Losses due to
Leakage, Excess Flow, undersized
pipe.
59.5 % Output
29.75 % Output
Pump 70 % Operation at Flow Less or
More than Design
Low Pump
Losses Due to Leakage,
Excess Flow
Undersized Pipe 50 %
Head Lost in Valves 50 %
1 5 %
W E L L D E S I G N E D P U M P I N G S Y S T E M
S
M A N Y A C T U A L I N D U S T R I A L
S Y S T E M S
A I R I S F R E E B U T N O T T H E C O M P R E S S
E D A I R
A I R C O M P R E S S O R
Rs 0.5 L
Rs 7.23 L
Rs 0.5 L
Rs 6 L
Rs1.3 L
Rs 0.5 L
Rs 6.26 L
Rs 0.97 L
Permissible Saved Excess Leakage
15th Aug 03 24th Oct 03 15th Jan 04
M A J O R L O S S T A R O L E A K A G E S
There are many more areas for E N C O N
E N C O N I N I L L U M I N A T I O N
1 Replace 4 0 W by 3 6 / 2 8 W E E L
2 Opt for C F L at Viable Locations
3 Install Electronic Ballast ( 3 W ) in Place of Conventional Copper Chokes ( 15 W )
4 U s e O c c u p a n c y
S e n s o r s i n B a t h
R o o m s & T o i l e t s
5 Prefer Task Lighting
6 A v o i d C o m m o n S w i t c h e s
T N 2 4 0 8 M W ( 5 6 . 8 % )
T N continues to be No.1 in the Country in Harnessing Wind Energy
S T A T U S as on 3 1 . 1 0 . 0 5
N A T I O N - 4 2 3 6 . 2 M W
Other States 1 8 2 8 . 2 M W
( 4 3 . 2 % )
W I N D M I L L O U T P U T Capacity
kWPower Generation
Million kWh / y2 5 0 0 . 5 0
5 0 0 1 . 1 57 5 0 2 . 0 0
1 0 0 0 2 . 8 0 1 5 0 0 4 . 5 0 2 0 0 0 6 . 0 0
1 9 5 0 0 M W
Sugarcane Trash
Sugarcane Tops
Paddy Straw
Coconut Husk
B I O M A S S P O W E RC O M B U S T I O N R O U T E
B I O M A S S P O W E RG A S I F I C A T I O N R O U T E
V I L L A G E L E V E L P O W E R G E N E R A T I O N
B I O G A S E N E R GY
T h e r m a l + P o w e r
( B u r n e r ) ( E n g i n e )
V E G G I E P O W E R
4 8 0 0 k W h / 3 0 tons V E G Waste
K O Y A M B E D U – C H E N N A I
P O W E R F R O M V E G E T A B L E W A S T E S
W A S T E W A T E R – S T A R C H
I N D U S T R Y
W A S T E W A T E R - B A G A S S E H A N D L I N G
P O U L T R Y L I T T E R F O R E N E R G Y
C O N C L U S I O N T H E F I R S T & F O R E M O S T A C T I V I T Y
I N E N C O N I S T O G O F O R D S MI t(i) Sets in Discipline(ii) Informs the Avenues for E N C O N(iii) Help in Avoiding Wastage of
Energy W I T H O U T D S M
O N L Y H A L F W O R K I S D O N E