wInsight Schedule Analysis & Reporting Features
Wayne Erwin, Sr. Principal Customer Care Analyst, DeltekGC-452
2 ©2012 Deltek, Inc. All Rights Reserved
New customers unfamiliar with wInsight applications Schedule analysis and reporting capabilities that are available
Recent emphasis on schedule side of earned value reporting and analysis
Format 6 schedules DCMA Tripwires OMB FY11 Table IIA Report
Motivation for this Presentation
3 ©2012 Deltek, Inc. All Rights Reserved
C/S Glue Viewer View schedule data Link schedule data to earned value data in wInsight
Defense Contract Management Agency (DCMA) Tripwire Metrics
BEI (Baseline Execution Index) CPLI (Critical Path Length Index) Start and Completion metrics
OMB FY11 Table IIA Report
Scheduling Analysis & Reporting
C/S Glue Viewer
5 ©2012 Deltek, Inc. All Rights Reserved
Customized application to Analyze schedules Link cost & schedule Filter activities
Analyze schedule data using the Analysis Gantt Chart
Link many schedule activities to one WBS element
Filter thresholds for management by exception
C/S Glue Viewer Overview
6 ©2012 Deltek, Inc. All Rights Reserved
Analysis Gantt Chart displays schedule data related to WBS element
Baseline Current plan Drop-dead dates Consecutive slips (last 3 months projected completion date)
Analyzing Schedules
7 ©2012 Deltek, Inc. All Rights Reserved
Analysis Gantt Chart
BaselineSchedule
CurrentSchedule
Drop-Dead Date
ConsecutiveSlips
8 ©2012 Deltek, Inc. All Rights Reserved
Analysis Gantt Chart Legend
INFORMATION SYMBOL COLOR Current Schedule (Top Bar) Critical Path Task Red Non-Critical Task Blue Summary Task Green Progress Black Baseline Schedule (Bottom Bar) Green
Milestone Black, Filled-In Rolled Up Milestone Black, Hollow Drop-Dead Date (Total Slack) Red
Previous Completion Dates 3 Months Ago (first slip) Green 2 Months Ago (second slip) Yellow 1 Month Ago (third slip) Red
9 ©2012 Deltek, Inc. All Rights Reserved
Auto Sync button works as a toggle
C/S Glue Viewer automatically updated when a new element is chosen in wInsight
Linking based on WBS number
Filter button must also be used
Linking Cost & Schedule Data
10 ©2012 Deltek, Inc. All Rights Reserved
Filter buttons narrow down the activities that are displayed in the schedule
Filters only displays activities Whose WBS number matches that of the active wInsight WBS element That meet the threshold conditions That are not complete
C/S Glue Viewer Filters
11 ©2012 Deltek, Inc. All Rights Reserved
Default filter thresholds
Develop your own management thresholds
C/S Glue Viewer Filters
Filter
Button
Slips in Past
4 Months
Completion Slip
Past BaselineFloat
3 31 days or more -6 days orworse
2 15 to 30 days -1 to -5days
1 or less 14 or less days 0 or more
Displays Activities That Meet Any Condition
Red
Yellow
Green
Displays All Activities for the Active ElementWhite
12 ©2012 Deltek, Inc. All Rights Reserved
Export schedule data using provided utility Open Plan MS Project Primavera Identify field containing WBS numbers that match WBS numbers in
wInsight
Import schedule data using C/S Glue Viewer Identify matching wInsight contract and reporting period Multiple schedules can be combined!
Run processing functions Update Prior Finish Dates to capture previous completion dates Set Filter Flags to determine the Red, Yellow, and Green filters
Schedule Processing
13 ©2012 Deltek, Inc. All Rights Reserved
C/S Glue Viewer Demonstration
DCMA Tripwire Metrics
15 ©2012 Deltek, Inc. All Rights Reserved
Tripwire Data CumActualCompl, CurPlannedStarts, Critical Path Length, Number of days of float, etc. They are the values used in Tripwire Metrics They are stored in the database
Most in the BEI table
Top level data is also stored in the CPR Header spreadsheet in wInsight Administrator
Can be displayed in wInsight Sort window
Tripwire Metrics Baseline Execution Index (BEI), Monthly % Hit, and Critical Path Length Index (CPLI) They are calculations/formulas They are not stored in the database They are calculated at the time a chart or a report is displayed BEIs can be displayed in wInsight Sort window
Availability BEI, Monthly % Hit, and related data at all levels CPLI and related data only at level 1/total contract
DCMA Schedule Tripwire Data and Metrics
16 ©2012 Deltek, Inc. All Rights Reserved
In determining Tripwire Data totals, wInsight ignores the following schedule items:
All zero (0) duration tasks, even those that are not marked as milestones
Milestones Summary tasks LOE tasks (level-of-effort tasks) Tasks without a baseline Tasks that are not mapped to WBS (i.e., no WBS# in LinkVal field in
C/S Glue Viewer)
DCMA Schedule Tripwire Data Criteria
17 ©2012 Deltek, Inc. All Rights Reserved
In calculating BEI data It does not matter if tasks finish on or ahead of their baseline schedule If a task has finished (early, on time, or late), wInsight counts it
BEI can be > 1.0
Baseline Execution Index (BEI) Defined
# of Baseline Tasks Actually Finished
# of Baseline Tasks Scheduled to be Finished BEI =
18 ©2012 Deltek, Inc. All Rights Reserved
More stringent criteria than for the BEI
Monthly % Hit cannot be > 1.0
Monthly % Hit Defined
Monthly
% Hit =
# of THIS month’s tasks finished on or ahead of their baseline schedule
# of THIS month’s tasks to be finished in the baseline schedule
19 ©2012 Deltek, Inc. All Rights Reserved
Schedule Float – the difference between the amount of time available for performing a program or a milestone and the time required to complete the program or milestone
wInsight always assumes a 5-day work week in calculating CPLI
CPLI of less than 1.00 indicates that the program is not likely to achieve its baseline completion date without corrective action
Critical Path Length Index (CPLI) Defined
CPLI =Critical Path Duration + Float
Critical Path Duration
20 ©2012 Deltek, Inc. All Rights Reserved
Indicates whether the program is going well or poorly against baseline estimates
Program Tripwires Summary Report
21 ©2012 Deltek, Inc. All Rights Reserved
Setting Tripwire Thresholds wInsight Administrator 6.5 provides the capability to customize the
secondary tripwire thresholds wInsight Administrator > Data Input > Contracts Setup > Contracts
Program Tripwires Summary Report Thresholds
22 ©2012 Deltek, Inc. All Rights Reserved
Completions and Starts version of this chart Lines = CUM Data, BEI criteria Bars = CUR Data, Monthly % Hit criteria
BEI and Monthly % Hit Chart
23 ©2012 Deltek, Inc. All Rights Reserved
If the ProgramOrMilestone column is NULL, or says "Total Program" or "Milestone,“ report does not display a record
Otherwise The milestone name, critical path length, and schedule float for the
report come from the corresponding columns in the CPR Header The UID, Start, and End dates come from imported schedule data for
the milestone
CPLI Milestone Report
24 ©2012 Deltek, Inc. All Rights Reserved
Deriving Tripwire data is a 3 step process Export schedule data using provided utility and identify LOE tasks Import schedule data using C/S Glue Viewer Recalculate the contract in wInsight Administrator using the Derive
Tripwire Metrics option
Automation of Tripwire Data
25 ©2012 Deltek, Inc. All Rights Reserved
Use wInsight Administrator to recalculate the contract and Derive Tripwire Metrics (data)
Recalculate & Derive Tripwire Data
OMB FY11 Table IIA Report
27 ©2012 Deltek, Inc. All Rights Reserved
Data was previously posted yearly, now required monthly
3 Key Features Report based on imported EVM & schedule data and a WBSOMB
milestone mapping completed by the end-user Ability to export data as a .CSV file or an .XML file from wInsight only OMB Milestone Changes Report
OMB FY 11 Exhibit 300 Table IIA Report
28 ©2012 Deltek, Inc. All Rights Reserved
In wInsight Administrator Create OMB structure and OMB elements Use the WBS Mapper to map WBS elements to OMB elements Load and recalculate WBS earned value data as usual OMB Report data generated at time report is run
OMB FY 11 Report – Structure Mapping
29 ©2012 Deltek, Inc. All Rights Reserved
OMB FY 11 Report – Example of Mapping
OMB Report
MS 1 MS 2 MS 3
1000
3200 3400 3600
3000
30 ©2012 Deltek, Inc. All Rights Reserved
OMB FY 11 Report – Sample Change Report
A blue highlighted row represents a new Investment
A blue highlighted field represents a
changed value
31 ©2012 Deltek, Inc. All Rights Reserved
Exporting OMB FY 11 Report data Right-click on report Select Export OBM Table IIA Data… Select either
CSV XML
OMB FY 11 Report – Exporting Data
The Future
33 ©2012 Deltek, Inc. All Rights Reserved
New Integrated Program Management (IPMR) requirements CPR Format 1
Minor changes in report header Data in XML in whole units (no decimals). Applies to Formats 1-4 and 7.
CPR Format 2 Subcontractor and Material reported separately from OBS
CPR Format 3 Time-phasing of changes between BOP and EOP
CPR Format 6 Integrated Master Schedule (IMS)
CPR Format 7 Time-phased historical & forecasted costs
Available Q4 2012
wInsight Enhancements
34 ©2012 Deltek, Inc. All Rights Reserved
Report containing the Integrated Master Schedule (IMS)
Two electronic formats required Schedule application’s native file format (ex., .MPP file) UN/CEFACT XML transfer file generated by schedule application
Open Plan (Deltek – Available Q4 2012) MS Project (Steelray – Available now) Primavera (Oracle committed to adding)
C/S Glue Viewer Updated to import Format 6 UN/CEFACT files Database not expanded with additional fields (ex., Best/Worse duration)
CPR Format 6