EXECUTIVE SUMMARY Project Definition
– Improve European reviews process in order to generate greater media coverage and increase leads
Key Customers—Customers for this plan?? Not sure what this section is for???????– Jerele Neeld, EMEA Communcations; Per Lund, Inspiron Marketing; Mike Watson, Dimension
Marketing; Marisa Manheimer, Transactional product group
Problem statement– Lack of a clearly defined WW product reviews process and dedicated resources to support
such a process has resulted in resulting in inefficiencies and missed or poor reviews (Front end)
– EMEA Rap lab missteps in recent launch coverage on Dimension & Inspiron due to lack of resources, skillset deficiencies and process issues (Back end)
Project Plan– Contain and fix current backend issues for Transactional products Feb 28
Owner: Fiona McCallig EMEA project Manager & Marisa Manheimer WW project Manager – Secure funding for RAP & EMEA PR heacount and RAP Lab relo/expansion Mar
01Owner: Jerele Neelde EMEA Communications Director, Gene Leonard EMF Engineering Director
– Improve products reviews process for Transactional products April 30Owner: Fiona, Marisa, and Sarah Lavender Interim EMEA Transactional Reviews
– Expand to all LOB’s / BU’s May - June
Dell Confidential
THE TEAMS
Core TeamResponsible for defining and driving Enhancements to the Reviews Process.
Steering CommitteeGene Leonard, Engineering Director, EMF
Denis Lucey, PDG, Personal systems Director, EMFJerele Neeld, EMEA Communications Director
Per Lund, Transactional Product Group, Inspiron International Business DevelopmentBob Ashenbrenner, Transactional Product Group, Americas RAP Lab
Eval TeamDedicated to honing press configs/pricing, setting priorities between BUs, conducting reviews post-mortems
Fiona McCalligEMEA RAP Lab
Project Lead
Sarah LavenderInterim EMEA Transactional
Reviews Manager(Represents COC/PR; 2/00-4/00)
Fiona McCalligEMEA RAP Lab
Project Lead
Product GroupMarketing Manager
COC ProductManagers
BU Marketing And/or
PR Manager
Sarah LavenderInterim EMEA TransactionalReviews Mgr
Marisa ManheimerWW Project
Manager
Dell Confidential
PHASE 1 – CONTAIN AND FIX PHASE 1 Contain and fix current issues (backend)
– Establish processes to contain current reported customer issues– Set expectations with BU’s and CoC’s on systems delivery
ACTIONS – CORE TEAMKick off meeting Core Team Jan 15Fiona and Marisa to set up and co-ordinate frequency
Create quality checklist for evals shipping from RAP LAB Fiona Jan 12Send to Customers for Feedback and execute Fiona/Review Mgr Jan 19Create and publish escalation process for Customers Fiona/Review Mgr Jan 19Specialise resources by product Fiona Jan 19Train and mentor using AMF expertise Marisa
Jan 26EMF RAP Lab capacity analysis – by product by week Fiona Jan 19Forecasted Workload analysis – by month per launch..this is done, right?Marisa Jan 26Establish Metrics for quality, cost and productivity Fiona/Marisa Jan 31Publish systems coverage capacity Review Mgr Jan 31
Notes and AssumptionsA resource from AMF RAP will be in EMF for January to train and mentor personnelAction: Marisa/Per Lund Due: Jan 19A EMEA Reviews manager will be appointed for EMEAAction: Jerele Neeld Due: Jan 19
Status:closed
Dell Confidential
PHASE 1 Contain current issues / Set expectationsACTIONS – CORE TEAM
Map current Process & identify weaknesses Core Team Jan 26Meet Eval Team Members in BUs Core Team Feb 5
ACTIONS – EVAL TEAM
Kick off meeting – establish frequency Sarah Feb 12Determine Priorities/Top 10 Target Lists by BU Sarah Feb 12Determine hot BU issues with RAP Lab/Process Sarah/Fiona Feb 19Implement containment fixes Core Team Feb 28
ACTIONS – STEERING TEAM
Kick off bi-weekly newsletter Marisa/Fiona Jan 19Agree project plan Gene/Per/Denis/JereleJan 31Kick off monthly conference call Core Team Jan 31
RED/YELLOW FLAGS– Reviews Manager required on Core Team to ensure communciation flows through CoC’s and BU’s
• Action: Jerele Neele Due: Jan 31– Eval team members must be sourced, named and sponsored by their Management
• Action: Marisa/Per Lund/Jerele Neeld Due: Jan 26– Forecasted workload may reveal capacity issues in Americas & EMF RAP LAB
• Action: Marisa/Fiona to publish capacity to steering team Due: Jan 19
PHASE 1 – CONTAIN AND FIX
Dell Confidential
PHASE 2 - IMPROVE PHASE 2 Improve product reviews process for Transactional Products
– Core Team & Eval Team process review & enhancement– Secure funding where necessary
ACTIONS – CORE TEAMEstablish customer priorities Sarah/Fiona Feb 15Determine if current database tools can be rolled out to Bus All Feb 15Synch BU priorities (Top 10 list/editorial calendars) to product launches All Feb 21Map new Transactional process All Feb 21Create and publish plan and costing for approval to steering team All Feb 28(tools, infrastructure, facilities/people, communication)
Implement and measure Core team April 30Note: all plans should include costing for expansion
ACTIONS – EVAL TEAM
Create and publish plan and costing for approval to steering team Marisa Feb 21Implement and measure Eval Team Mar 31Note: all plans should include costing for expansion
ACTIONS – STEERING TEAM
Review Process Improvement Plans Steering teamMar 01
Secure Funding necessary for permanent PR headcount Jerele Neeld Mar 15Secure Funding necessary for additional RAP lab headcount & relo Gene Leonard Mar 15Secure Funding for enhancements to database tools Bob/Per Feb 1
Dell Confidential
PHASE 3 - EXPAND PHASE 3
– Expansion plan - Publish and seek approval– Extend to additional BU’s & LOB’s
ACTIONS – CORE TEAMPublish expansion plan to steering committee for approval Jerele/Sarah/Fiona
April 20Execute and Measure June 30
Project sign-off by Steering team July 10