Define plancontrol BudgetQuality Time BUS 1040 Welcome to: Project Management Week 4. Professor Fred...

20
define plan control Budget Quality Time BUS 1040 BUS 1040 Welcome to: Project Management Week 4 . Professor Fred Pentney Team slogan ? Give me a “B”?

Transcript of Define plancontrol BudgetQuality Time BUS 1040 Welcome to: Project Management Week 4. Professor Fred...

defineplan control

Budget Quality

Time

BUS 1040BUS 1040Welcome to:

Project ManagementWeek 4 . Professor Fred Pentney

Team slogan ? Give me a “B”?

defineplan control

Budget Quality

Time

Review of previous week (3)Review of previous week (3)

Terms-review to date; keep adding to your lists. R.F.P.’s and Proposals, project selection Do you have a checklist for a S.O.W.? Do you have a checklist for an R.F.P.? Did you collect some project documents of the web

ready for next week to share with your Group?

defineplan control

Budget Quality

Time

Week four agenda:Week four agenda: Review of our Lesson approach so far – feedback. Finish Decision Matrix for our dinner date. Finish Group presentations as agreed- present a project off web.

New Learning: We start Planning Stage

Risk management Hi level vs. detailed planning. Work Breakdown Structure (WBS) Group activity: Create a WBS to work package Estimating the Work Packages Scheduling introduction

Homework – find some (4) start up forms. Bring to class Wk. 5

defineplan control

Budget Quality

Time

Risk management Risk management

Must develop risk management strategy and implementation “early” in project.

Method-assess the following:Risk items or areas Probability of occurrence Impact (severity or damage)How to manage the risk

defineplan control

Budget Quality

Time

PlanningPlanning

Without a plan there is increased riskPlan is a roadmapCan measure variation from planCan refer all Stakeholders to the planCan present the plan as Proposal

defineplan control

Budget Quality

Time

Planning stage – WBS Planning stage – WBS Definition stage objectives become

WBS at the Planning stage Creating the hierarchal chart based on levels Objective. The “deliverable”- product or service First level-Summary tasks (headings indicating

completion of work packages). Second levels and further levels down to work

packages-the jobs that are actually done by the workers using the planned resources.

defineplan control

Budget Quality

Time

WBS processWBS processChoose one of two methods

1. Make a list of all the items that need to be done and then ‘chunk’ them into categories.

2. Start with the Objective and then decompose it (break it down) into major task categories and then sub tasks down to the level that team members understand what they are doing.

defineplan control

Budget Quality

Time

WBS – the processWBS – the process A dinner party

Make a list – see attached Random orderFind relationshipsChoose the top level Choose the intermediate (summary)Group the similar work items

defineplan control

Budget Quality

Time

Task (activity) listTask (activity) list1.1. Random order if necessaryRandom order if necessary

2. Next find relationships2. Next find relationships

Hi level Dinner

Party

Summary Buy Cook Serve Plan

Work

PackagesMeat/Veg. Meat

/Veg.Wine/

Dinner

Make lists

Eat

Drink

Socialize

Tasks list:Dinner party

Buy veg

Pour wine

Eat

Make my list

Cook

Buy meat

Plan

Serve

Cook meat

Serve food

Cook veggies

Drink

Socialize

defineplan control

Budget Quality

Time

From Definition to work packages. From Definition to work packages.

B uy m ea t B uy vege tab les

S hopp ingType t it le he re

C ook vegg ies C ook m ea t

C ook ingType t it le he re

E a t

S erve m ea l

D r ink

P our w ine

S ervingType t it le he re

M ake lis ts

P lan

D inner P artyType t it le he re

defineplan control

Budget Quality

Time

Estimating theEstimating the work packages – work packages – not completed yet –see task list not completed yet –see task list

and add onand add on

Activity Time Cost / hr. Labour

Costs $Materials $

Total

$

Shop

Veg

1.0 $10 $10 $13 $23

Shop

Meat

1.5 $10 $15 $27 $42

Cook

time

2.0

1.0

$15 $45 - $45

Serve 2.0 $15 $30 - $30

Plan 0.5 $10 $5 - $5

Total

defineplan control

Budget Quality

Time

Network diagramNetwork diagramNote don’t show summary tasks

Plan

Cook

Cook

Serve

Serve

Eat FinishStart

Note: BoxesHave task #Duration Hrs.ES.LS. LS. LF& Float

Buy Social

defineplan control

Budget Quality

Time

Scheduling the workScheduling the work

Look at our WBS.Choose a task that has to be done What come before that?What come after?What can be done at the same time?

(Don’t’ worry about # of people

at this point but logic of sequence).

defineplan control

Budget Quality

Time

ScheduleScheduleWe can use a Network diagramWe can use a GANTT chartWe can use a bar chart (MS XL)

We can list Predecessors to various tasks

defineplan control

Budget Quality

Time

Calculating Critical pathCalculating Critical path The longest path is the critical path.

0.5

1.5

FinishStart

Note: BoxesHave task #Duration Hrs.ES.LS. LS. LF& Float

2.0

3.0

2.50.5

defineplan control

Budget Quality

Time

GANTT or Bar chartGANTT or Bar chartOn this chart show Summary tasksOn this chart show Summary tasks

and tasks, milestones and and tasks, milestones and Activity 5pm 6 pm 7 pm 8 pm 9 pm 10pm

Dinner p

Plan

Buy Groc

Buy meat

Buy veg

Cook

Cook veg

Cook meat

Serve

defineplan control

Budget Quality

Time

Group activity-apply learningGroup activity-apply learning

Form Team of 5’s. One person is PMUse House build handout with task listArrange items into WBS format. All Team record final layout on their

diagramConvert WBS into Network diagram

defineplan control

Budget Quality

Time

MS Project software MS Project software Introduction and demonstrationFred’s MS project handout on getting starte

dEase of use.

defineplan control

Budget Quality

Time

Today - review Today - review Key learning'sLiked?Do different?

defineplan control

Budget Quality

Time

Home Assignment Home Assignment

Bring your Project start up formstemplates, samples to Class in Wk. 5 Present during Group work time to your PMReceive 2 marks