Deerfield Elementary School Modernization
description
Transcript of Deerfield Elementary School Modernization
DEERFIELD ELEMENTARY
SCHOOLMODERNIZATION
May 6, 2010
Irvine Unified School DistrictHMC Architects
What is a Modernization? Eligibility
Permanent buildings - 25 years oldPortable buildings - 20 years old
DSA RequirementsADA ComplianceFire, Life, Safety Upgrades
Maintenance Requirements
Budget and Funding Board Approved Project Budget
Construction CostsSoft Costs
○ Architect Fees○ Agency Fees (DSA, Health Dept., IRWD, etc.)○ Testing and Inspection Fees
$12,600,000 ($12.6m)○ Anticipated State Funding: $3,992,966○ Local Matching Funds: $8,607,034
Planned Scope of Work: DSA Requirements Required Fire Life Safety/ADA Compliance/Structural
components:Upgrade restrooms to ADA complianceAdd restroom fixtures based on student and staff capacityUpgrade drinking fountains for ADA complianceUpgrade fire alarm systemUpgrade ADA accessible parking stallsUpgrade path of travel (exterior)Upgrade/create updated exitingLoss of mezzanine/pit areas and current teachers loungeRelocation/replacement of shade structureRelocation/replacement of current classroom relocatables
Planned Scope of Work:Maintenance Needs Scope includes:
Roof replacementFlooring replacementNew PA/Clock systemElectrical upgradePaint all interior/exterior surfacesHVAC control replacement
Pre-Modernization Site Plan
Pre-Modernization Floor Plan
Post-Modernization Floor Plan
New Administration Floor Plan
New Classroom Layout
Interim Housing: El Camino Board Approved Transportation Zone Interior
Wall restoration Carpet repair/patch Paint Plumbing
Exterior Asphalt, concrete Playground
Childcare Restroom Facility Street Signs
Install approximately one-two weeks prior to start of school
Interim Housing: El Camino Real
Deerfield to El Camino
Childcare CDC
Closed Friday, June 25th*
Reopens at El Camino Monday, June 28th*See CDC for more information regarding
childcare and availability
Timeline Moving Out
Teachers - Friday, June 25thAdministration staff - Wednesday, June 30th
Moving InBy September 1, 2011*
ConstructionPhase I
○ July 12, 2010 - December 31,2010Phase II
○ January 3, 2011- August 19, 2011
Questions
Thank you for your continued support of
the Deerfield Elementary
School students!