Deep Offshore Well Metering and Permutation Testing
-
Upload
joel-cristobal -
Category
Documents
-
view
213 -
download
0
Transcript of Deep Offshore Well Metering and Permutation Testing
-
7/30/2019 Deep Offshore Well Metering and Permutation Testing
1/9
Copyright 2002, Offshore Technology Conference
This paper was prepared for presentation at the 2002 Offshore Technology Conference held inHouston, Texas U.S.A., 69 May 2002.
This paper was selected for presentation by the OTC Program Committee following review of
information contained in an abstract submitted by the author(s). Contents of the paper, aspresented, have not been reviewed by the Offshore Technology Conference and are subject tocorrection by the author(s). The material, as presented, does not necessarily reflect any
position of the Offshore Technology Conference or its officers. Electronic reproduction,distribution, or storage of any part of this paper for commercial purposes without the written
consent of the Offshore Technology Conference is prohibited. Permission to reproduce in printis restricted to an abstract of not more than 300 words; illustrations may not be copied. Theabstract must contain conspicuous acknowledgment of where and by whom the paper waspresented.
AbstractAs production in very deep waters becomes a crucial
challenge for many oil companies, a better management of the
production is constantly required. This paper presents two
complementary methodologies for operation support and
improvement of the production conditions. The first one is
based on data reconciliation between process measurements
and flow modelling. It brings an additional level of
information to the problem of continuous metering of deep-
water subsea wells. As periodic well testing is required toachieve this predictive metering, the second methodology
provides the optimal test sequences of well permutations. It
involves flow process simulation and algorithmical sorting,
according to production constraints and operating strategies.
Finally, comparisons between numerical simulations and plant
data demonstrate the ability of these two methodologies to
provide strong and reliable information for deep offshore
producers.
IntroductionThe knowledge of the phase flow rates coming from each
individual well of an oil field is mandatory for a better
production and reservoir management. Generally, thisinformation comes from a series of direct well testing, where a
single well flows directly to a test separator.
In deep offshore, this procedure turns out to be
inappropriate: production developments are based on
gathering network, where manifolds merge the production
from several wells into a single flowline. This is the case on
the Girassol oil field in Angola, see Fig. 1. Moreover, direct
well testing implies deferred production, valve reliability and
flow assurance issues: hydrate formation in dead branches,
slugging at low flow rates, etc.
Whereas conventional solutions, such as hardware
multiphase metering, supply a limited information, our
methodology works as an overall field supervisor for:
estimating individual well production with respect toappropriate pressure and temperature measurements;
detecting abnormal behavior (sensor drift forinstance);
validating hardware measurements, and replacingthem in case of failure. Typically, in deep offshore
production, hardware sensors are not replaced in case
of failure for financial and feasibility reasons.
This methodology is based on data reconciliation. It
assumes that measurements are not necessarily correct and can
be corrected within a confidence interval. Meanwhile,
unmeasured variables derive from redundancy between flow
modelling and field data.
Data reconciliation has been already successfully applied
to a small production network, see Ref. 1. Our paper intends to
go further in the study of this innovative technology andpresents its application to the Girassol field.
Well monitoringGiven a set of temperature and pressure measurements, our
methodology aims to provide an estimate of the phase flow
rates produced by each individual well of an oil field.
Problem modelling. Real-time plant data are completed with
a global steady state simulation of the production network
involving:
mass, force, and heat balance equations;
thermodynamic calculations;
hydrodynamic modelling.For instance, assuming process data at both ends of a
choke and an estimate of the fluid composition, one can derive
a local estimate of the liquid and gas mass flow rates from
hydrodynamic and thermodynamic calculations.
Combination between physical modelling and plant data is
applied to the whole production network, leading to multiple
estimates of the same information. This multiplicity derives
from our uncertain interpretation of the reality: this statement
is precisely the main strength of the data reconciliation
technology.
OTC 14009
Deep Offshore Well Metering and Permutation TestingErich Zakarian, RSI; Arnaud Constant, TotalFinaElf Exploration & Production Angola; Lionel Thomas, TotalFinaElf; MartinGainville, Institut Franais du Ptrole; Pierre Duchet-Suchaux, TotalFinaElf; and Philippe Grenier, RSI
-
7/30/2019 Deep Offshore Well Metering and Permutation Testing
2/9
2 E. ZAKARIAN, A. CONSTANT, L. THOMAS, M. GAINVILLE, P. DUCHET-SUCHAUX, AND P. GRENIER OTC 14009
Whatever the complexity of a model, one should be awarethat it always remains an approximation. However, the latter
can be restricted to a small number of modelling parameters
embedded in residual equations. Again, any hardware sensor
contribution is a residual equation weighted by vendor
uncertainty.
Both hardware measurements and modelling equations are
involved on the same level of analysis through a global datareconciliation and parameter estimate, leading to an
optimization problem. Conversely, experience feedback is
expected to get optimal values of model uncertainties.
A major innovative aspect of this work is the systematic
computation of the accuracy of any estimated variable. We
notice that the accuracy of a measured variable can be slightly
increased since data reconciliation works as a global
computation where any piece of information is likely to be
improved by the other ones.
We also emphasize that information on the solution
uncertainty is as important as the solution itself: whenever
redundancy remains, a physically incorrect solution can satisfy
the problem. Therefore, a supervisor checks the consistency ofthe solution against intuitive expectations.
Example. Let us consider the following scenario. Given one
well tubing followed by a choke, six sensors are installed
upstream and downstream these equipment to measure the
pressure and the temperature of the fluid, see Fig. 2. We derive
six equations:
Pi - Pmi = 0,.....................................................................(1)
Ti - Tmi = 0, .................................................... .................(2)
where i = 1, 2, and 3 refer respectively to the following
positions: upstream the well tubing, downstream the welltubing, and downstream the choke.
Calibrated values of the water-liquid ratio and gas-oil ratiogive two additional equations:
BSW-BSWm = 0,............................................................(3)
GOR - GORm = 0............................................................(4)
A well tubing model provides a pressure drop relation and
a heat balance between positions 1 and 2:
fWP (P1, T1, P2, T2, Flow,BSW, GOR, WP) = 0,..............(5)
fWT(P1, T1, P2, T2, Flow,BSW, GOR, WT) = 0. ..............(6)
A choke model gives the same kind of relations betweenpositions 2 and 3:
fCP (P2, T2, P3, T3, Flow,BSW, GOR, CP) = 0,...............(7)
fCT(P2, T2, P3, T3, Flow,BSW, GOR, CT) = 0................(8)
Every measurements involved in this system are not
necessarily correct since hardware sensors are subject to errors
and the flow is not perfectly stable in the entire production
system. As far as BSW and GOR, their a priori values
(calibrated) might be trusted with a relative confidence as thefluid composition may change between two consecutive
measurements performed on a test separator. Therefore,
equations (1) to (4) are replaced by residual equations and
weighted by the standard deviation (uncertainty):
ePi = (Pi - Pmi)/Pi, ........................................................ .. (9)
eTi = (Ti - Tmi)/Ti,........................... .............................. (10)
eBSW= (BSW-BSWm)/BSW, ......................................... (11)
eGOR = (GOR - GORm)/GOR, ........................................ (12)
where i = 1, 2, and 3.
As reminded before, an additional parameter calibrates
each modelling equation with respect to a reference value
(tuned from test measurements) and an uncertainty. Four
residuals complete the system:
eWP = (WP - WP,ref)/WP, ............................................. (13)
eWT= (WT- WT,ref)/WT, .............................................. (14)
eCP = (CP - CP,ref)/CP, ............................................... (15)
eCT= (CT- CT,ref)/CT,........ ........................................ (16)
We finally get 16 equations, namely (5) to (16), and 13
variables: BSW, GOR, Flow, WP, WT, CP, CT, Pi, and Ti,where i = 1, 2, and 3. The system seems redundant. However,
redundancy can only be ensured from a detailed analysis: to
avoid any singularity, the rank of the jacobian must be equal to
the number of the variables at any operating point. Note: the
jacobian of the system is the matrix given by the partial
derivatives of the equations (modelling equations andresiduals) with respect to the variables.
This condition is necessary to find a solution, which is a
minimization of an objective function given as a sum of the
squares of the residuals. Meanwhile, the modelling equations
are exactly satisfied (optimization constraints).
Three phase flow modelling. Several models are involved in
the simulation of a Girassol production loop, see Table 1. As a
mixture of oil, gas and water is expected during the field life,
intensive efforts are required to get an acceptable physical
representation, due to the complexity of three-phase flows.
A gridded modelling is used for long tubings (well, sea-
line, riser) since local effects such as slope changes maystrongly impact pressure and thermal profiles. A complex
three-phase hydraulic module ensures a correct representation
of the different flow regimes. Local flash and thermal
calculations improve the physical modelling as well.
A rather sophisticated modelling is used for the chokes
since flow criticity and gas expansion may seriously affect
pressure and temperature variations. The choke discharge
coefficient must be initially calibrated and periodically
validated against field data. Three-phase flow meters could be
used. Meanwhile, test separator instruments provide sufficient
-
7/30/2019 Deep Offshore Well Metering and Permutation Testing
3/9
OTC 14009 DEEP OFFSHORE WELL METERING AND PERMUTATION TESTING 3
and accurate information for calibration.This tuning procedure is described in a further section. In
terms of computation, tuning is a particular use case of this
well metering methodology.
Thermodynamic issues. Physical phenomena such as
vaporization in wells or expansion in chokes require accurate
thermodynamic calculations. Therefore, the mixturecomposition is tracked along the flow line, and the whole unit
operations perform local vapor/liquid/liquid equilibrium
calculations to get an estimate of the phase properties.
However, it is an illusion to believe that an accurate estimate
of the reservoir fluid molar composition can be found: neither
the system, nor the available sensors are able to catch the
effect of a composition change (at constant phase properties)
between C9 and C10 cuts, for instance. Conversely, gas
coning or water breakthrough does affect sensor data.
Therefore, the fluid composition is corrected with BSW and
GOR variations by addition or removal of water and/or gas
from the first stage separator.
Software issues. The basic domains involved in an industrial
well monitoring tool are:
compositional thermodynamic calculation;
hydrodynamic modelling in pipes and wells;
thermal modelling in pipes and wells;
valve modelling;
reservoir PI modelling;
data reconciliation;
real-time process data recording and analysis.For each domain, several approaches have to be tested and
selected. For example, a particular thermodynamic server
might be suitable for certain operating conditions butunacceptable to other cases. Note: a server is a software
component that provides services for other software
components (client components) through defined interfaces.
Therefore, it should be easy to combine different modules
with the minimum effort. In addition, many pieces of software
from different sources might fulfill our requirements. For
these reasons, we decided to build our well monitoring
simulator as an open software, using the CAPE-OPEN
(Computer-Aided Process Engineering) standard, see Ref. 2.
The compliance to this standard is another major and
innovative aspect of this work. It provides high model
flexibility for the end user, it makes implementation of new
features much easier and faster: plug and play integration ofany CAPE-OPEN compliant component is carried out with the
minimum effort.
Built on a component-based architecture, see Fig. 3, our
well monitoring simulator includes:
CAPE-OPEN compliant components: unit operations,thermodynamic servers;
external components: solver, man machine interface,data interface, supervisor.
CAPE-OPEN standard interfaces ensure the
communication between components through a simulator
executive framework. The latter runs the whole application
and its components, like the configuration of a production
network or the use cases of a well monitoring application.
Sensor failure detection. The data interface component
makes the connection between the simulator executive
framework and external components that provide hardware
measurements: Distributed Control System, database.To avoid any undesirable effect on data reconciliation, the
data interface performs a preliminary analysis to detect any
possible failure (unlikely value, excessive variation) or
unsteady behavior when the average of the measurements
depends significantly on time.
A sensor is declared invalid in case of failure and its
contribution is removed from the system. It does not
participate to the data reconciliation, leaving the determination
of the measurement to the optimizer. This preliminary
detection is as important as the data reconciliation itself. Let
us present an example to confirm this statement.
We consider a network with a well producing in a single
flowline through a choke and a manifold, see Fig. 4. Pressureand temperature sensors are located upstream and downstream
these equipment. Assuming an initial calibration of the system,
we define a particular scenario with hardware sensor failures,
see Fig. 5: at a fixed period of time (five minutes), the data
interface sends sensor measurements to the simulator
executive framework and a new solution is computed. Forty-
five minutes after starting up, the pressure sensor at the bottom
hole returns zero, which is of course an unacceptable value.
This failure lasts half an hour. Two hours after starting up,
both pressure sensors at the bottom hole and the manifold
return zero again.
First, let us consider the case where the data interface does
not perform a detection of sensor failure. At the beginning of
the run, the simulator computes reconciliated data, see Fig. 6.
The latter are very close to the real measurements reproduced
on the figure as dotted lines.
At 45 minutes where the first pressure sensor collapses, the
simulator manages to rebuild a measurement at the bottom
hole. The rebuilt value is physically acceptable but likely far
from reality. At the same time, the production is overestimated
(the productivity index remains the same in the whole run) and
the gas-oil ratio decreases, see Fig. 7. The wellhead pressure
is also strongly affected because of its direct dependence onthe bottom hole pressure through the well tubing model. The
pressure drop increases by 106 Pa.
At 75 minutes where the sensor starts running again, the
initial solution is recovered but at 120 minutes, both pressure
sensors at the tubing ends stop to run. The simulator fails to
find a solution.Let us run the same simulation but with detection of sensor
failure. We notice that the data reconciliation works perfectly
in this case, showing its ability to rebuild unmeasured
variables, see Fig. 8, 9. The sensor failure does affect the
redundancy of the problem, which is lower than before, but it
does not affect the results.
-
7/30/2019 Deep Offshore Well Metering and Permutation Testing
4/9
4 E. ZAKARIAN, A. CONSTANT, L. THOMAS, M. GAINVILLE, P. DUCHET-SUCHAUX, AND P. GRENIER OTC 14009
At 120 minutes, both sensor failures are detected at thewell tubing ends. The solution remains acceptable. However,
the manifold pressure drops significantly and its a posteriori
confidence interval as well. In other words, there is not enough
redundancy to trust the reconciliated value of the manifold
pressure.
This second computation confirms the ability of our
methodology to replace hardware sensors in a productionsystem. It also shows its weakness whenever the number of
valid sensors is not sufficient to allow redundancy.
Real-scale validationProduction at the Girassol field started in late 2001. We
propose to use a first series of measurements to validate our
methodology and confirm its ability to provide reliable
information. These measurements were recorded from
December 4th to 24th, 2001.
Calibration. We focus our presentation on a single well
flowing into the right branch of the P10 loop. We consider the
network from the well tubing to the test separator on FPSO(Floating Production Storage and Offloading), see Fig. 10.
Note that riser tubing and riser choke are not simulated in this
presentation.
Modelling parameters derive from a single simulation with
the following configuration:
At the test separator: set the uncertainties of the phaseflow-rate sensors to vendor accuracy (we assume
accurate measurements)
At the upstream equipment and inflow model: removethe residuals of the modelling parameters (GOR,BSW,
choke discharge coefficient, productivity index and
friction factors).
The vendor accuracy of the flow-rate sensors is small.
Therefore, the phase flow-rates computed by the optimizer are
necessarily close to their measured values. Meanwhile, the
phase flow-rates derived from the modelling have to match
these measured values. Assuming a small uncertainty on the
pressure/temperature measurements, the optimizer is forced to
change the values of the modelling parameters (a particular
situation occurs here since the system has no redundancy, and
solution is independent on the sensor accuracy).
Twice a day in December 2001, measurements on a test
separator were carried out at the Girassol field to estimate the
production of the well. We propose to calibrate our system on
one of these tests. Then, after a certain period of time, we will
compare the oil, water, and gas flow-rates predicted by the
simulation and those derived from real testing.
Well metering. A demonstrative test can be found from
December 7th to 12th. During this period of time, the
production of a well was progressively increased with a choke
opening from 36 % to 49 %, see Fig. 11. Meanwhile, the
pressure drop in the well tubing remained approximately
constant and the one through the choke dropped from 5 106 Pa
to 2.5 106 Pa.
We calibrate the simulator with data recorded onDecember 7th, between 02:00 and 08:00 am. Then, we run a
metering, up to December 12th.
With a sampling DCS period of five minutes, production is
estimated every thirty minutes, using data filtered on the past
hour. If we assign the same level of confidence to the models
(choke, inflow, tubings), the system overestimates the
production, but the predicted trend is consistent with reality,see Fig. 12.
A detailed analysis shows that the choke model is
responsible for this deviation: tuning with subsequent tests
shows that the discharge coefficient drops from 0.92 to 0.6 on
December 8th, see Fig. 13. Meanwhile, productivity index and
friction factors remain roughly constant. This observation
reveals some inconsistency between plant data and the choke
modelling. Further analysis will be required to get a better
understanding of the real choke behavior.
If we set a lower relative confidence on the choke model
(by increasing the discharge coefficient uncertainty), we verify
that the initial tuning is sufficient to get, five days latter, a
good estimate of the expected oil and gas production, see Fig.14. This implies that the initial tuning of the GOR was good
enough for the five following days of metering. We effectively
notice that the GOR derived from tuning remains constant, see
Fig. 15.
Permutation testing Assistance toolPeriodic calibration is required to keep the modelling close to
the real process. Three-phase flow meters could be used but
test separator measurements through well testing can also
provide sufficient and accurate information.
Production at the Girassol field is based on a loop
configuration where sea-lines are connected to each other
through subsea manifolds, see Fig. 1. Each well of a loop is
routed to a production line, either left or right. There is no
specific line for well testing.
This network architecture and flow assurance issues
strongly impact the well testing strategy:
direct testing leads to increase deferred production;
direct testing at low flow-rates may lead to instabilityin the flowlines (slugging);
direct testing at flow rates below 10 000 bbl/d maylead to a fluid temperature lower than the paraffin
formation temperature (about 40C);
direct testing for the nearest wells leaves the upstream
flowline full of dead fluid during the test, and hydrateinhibition with methanol is required.
Therefore, permutation testing (in addition to direct
testing) has been included in the Girassol well monitoring
strategy:
a direct testing connects a single well to a singleproduction line; estimating the phase flow rates of the
well is straightforward;
a permutation testing connects several wells to bothproduction lines (but a well is necessarily allocated to
a single line). A series of different permutations leads
-
7/30/2019 Deep Offshore Well Metering and Permutation Testing
5/9
OTC 14009 DEEP OFFSHORE WELL METERING AND PERMUTATION TESTING 5
to different measurements of the phase flow rates ofeach production line. The phase flow rates of each
individual well derives from solving a set of linear
equations.
Testing strategy. Since the wells of a production loop may
produce into either left or right production line, a permutation
can be considered as a set of two well arrangements, left andright. The number of possible arrangements is necessarily
much greater than the number of wells. For example, let us
consider four producers: WA, WB, WC, WD. Any sequence
involving these four wells can be acceptable. One of them is
shown on Table 2; notation: WA + WB + WD means a test with
WA, WB, and WD.
The number of possible test sequences increases drastically
with the number of wells, see Table 3. This observation and
the complexity of involved phenomena prevent us from
deriving a simple synthetic rule that could be used in operation
to select the best test sequences. The latter have to be
compliant with the whole production constraints.
A permutation testing assistance tool has been specificallydesigned to achieve this work. Basically, a steady state process
simulator is used for network and gaslift computation,
providing well production in any arrangement, see Table 4 for
few examples. Then, sequence sorting is carried out versus
user strategy, see Fig. 16.
Flow modelling. Flow rates and production losses are
estimated from a simplified flow modelling: well performance
curves and pressure loss tables derive from experiments or
simulations performed on predictive multiphase software.
Specific unit operations implement these tables in the process
simulator. Thus, any code can be used to generate the flow
modelling.
Contrary to the well monitoring tool, this permutation
testing assistant is an off-line software. However, a periodic
tuning against real process data is recommended in order to
adjustBSWor GOR of each individual well.
Sequence sorting. After network configuration and
calculations, a sorting service provides an ordered succession
of permutations.
The initial number of possible sequences is Ckj where k is
the length of the sequence and j is the total number of possiblearrangements, see Table 3. Some of them do not comply with
thermal constraints and are removed. The same applies for
singular sequences.
For one sequence of k arrangements, there are k! orders.
Applying an order-dependent criterion, the best order is
selected. The simulator computes the expected test accuracy,namely the accuracy of each individual well production, GOR,
and BSW. Finally, the remaining sequences are sorted with
respect to user strategy, see Fig. 16. Typical simulation results
are shown on Table 5.
Features. Direct testing is intuitively the best solution to reach
the maximal accuracy. For instance, if we consider aproduction loop with four wells, sixteen different sequences of
four direct tests will estimate the production, without any loss
of accuracy. But, only few of them may satisfy operation
constraints.
According to our assistance tool, only one sequence does
not require hydrate inhibition with methanol, see Fig. 17: no
dead branch is created if we consider the first arrangement asthe initial loop configuration. Conversely, if we accept a
relative loss of accuracy, permutation testing will keep the
production at its optimal level, see Fig. 18.
Since both maximal accuracy and minimal production loss
strategies may be required, a global weighted criterion is
actually used to bring all the strategies together and perform
the sequence sorting.
Theoretically, there is no limitation on the number of wells
to consider. However, let us remind that the number of
possible test sequences increases drastically with the number
of wells, see Table 3. In the case of six wells or more, the
computation time can be prohibitive unless one or several
wells are exclusively allocated to a production line.
ConclusionThis paper demonstrates the ability of a well monitoring
software to provide reliable information for producers:
production estimate of each individual well, abnormal
behavior detection, validation of hardware measurements and
replacement in case of failure.
Although the described methodology can be applied to any
type of onshore/offshore development scheme, this work is
mainly intended to deep offshore developments, such as the
Girassol field in Angola.
Based on data reconciliation between field data and flow
modelling, our well monitoring tool requires a periodic
calibration to keep its modelling close to the real process. This
tuning derives from test separator measurements.
Since a combination of direct and permutation well testing
is presently involved at the Girassol field, we also designed a
second tool to compute the optimal test sequences versus usual
production and operating constraints.
Intensive use and positive feedback will confirm the
usefulness and reliability of this work. This will be the main
topic of a second paper.
NomenclatureBSW = Basic Sediment and Water (water volume
flow/liquid volume flow), m3/m3
BSWm = Measured value ofBSW, m3/m3
Flow = Total mass flow rate, kg.s-1
GOR = Gas-Oil Ratio (gas volume flow/oil volumeflow), Sm3/m3
GORm = Measured value ofGOR, Sm3/m3
P1 = Well tubing upstream pressure, Pa
P2 = Well tubing downstream pressure, Pa
P3 = Choke downstream pressure, Pa
Pmi = Measured value ofPi, (i = 1, 2, 3), Pa
-
7/30/2019 Deep Offshore Well Metering and Permutation Testing
6/9
6 E. ZAKARIAN, A. CONSTANT, L. THOMAS, M. GAINVILLE, P. DUCHET-SUCHAUX, AND P. GRENIER OTC 14009
T1 = Well tubing upstream temperature, K
T2 = Well tubing downstream temperature, K
T3 = Choke downstream temperature, K
Tmi = Measured value ofTi, (i = 1, 2, 3), K
WP = Tuning parameter for well tubing pressure drop
WT = Tuning parameter for well tubing heat balance
CP = Tuning parameter for choke pressure drop
CT = Tuning parameter for choke heat balance
WP,ref = Calibrated value ofWP
WT,ref = Calibrated value ofWT
CP,ref = Calibrated value ofCP
CT,ref = Calibrated value ofCT
Pi = Uncertainty ofPmi (i = 1, 2, 3)
Ti = Uncertainty ofTmi (i = 1, 2, 3)
BSW = Uncertainty ofBSWm
GOR = Uncertainty ofGORm
WP = Uncertainty ofWP
WT = Uncertainty ofWT
CP = Uncertainty ofCP
CT = Uncertainty ofCT
References1. Van der Geest, R., Reliability Through Data Reconciliation,
OTC 13000 presented at the 2001 Offshore Technology
Conference held in Houston, Texas (2001).
2. Braunschweig, B., Paen, D., Roux, P., and Vacher, P., The Use of
CAPE-OPEN Interfaces for Interoperability of Unit Operations and
Thermodynamic Packages in Process Modelling, The European
Refining Technology Conference, Paris, France (2001). See also
http://www.colan.org.
Figures
Wellhead Manifold
Fig. 1: Girassol subsea loop
Well tubing
Choke
Pm1, Tm1
Pm2, Tm2
Pm3, Tm3
Fig. 2: Example of a production network
Simulator ExecutiveFramework
Solver
Man MachineInterface
DCS
Unit Operation Thermo Server
CAPE-OPENCOMPONENTS
CAPE-OPEN
SIMULATION
ENVIRONMENT
EXTERNAL
COMPONENTS
Supervisor
Fig. 3: Well monitoring software overview
Fig. 4: Sensor failure simulation
-
7/30/2019 Deep Offshore Well Metering and Permutation Testing
7/9
OTC 14009 DEEP OFFSHORE WELL METERING AND PERMUTATION TESTING 7
0.00E+00
5.00E+06
1.00E+07
1.50E+07
2.00E+07
2.50E+07
3.00E+07
0 20 40 60 80 100 120 140 160
Time (min)
Pressure
(Pa)
Bottom hole pressure
Wellhead press ure
Manifold pressure
Fig. 5: Pressure sensor measurements
0.00E+00
5.00E+06
1.00E+07
1.50E+07
2.00E+07
2.50E+07
3.00E+07
0 20 40 60 80 100 120 140 160
Time (min)
Pressure
(Pa)
Reconciliated bottom hole pressure
Reconciliated wellhead press ureReconciliated manifold press ure
Fig. 6: Reconciliated pressure sensor measurements (no
preliminary failure detection)
0.00E+00
2.00E+01
4.00E+01
6.00E+01
8.00E+01
1.00E+02
1.20E+02
1.40E+02
1.60E+02
0 20 40 60 80 100 120 140 160
Time (min)
Gas-Oil Ratio (Sm3/m3)
Total mass flow rat e (kg/s)
Fig. 7: Production estimate (no preliminary failure detection)
0.00E+00
5.00E+06
1.00E+07
1.50E+07
2.00E+07
2.50E+07
3.00E+07
0 20 40 60 80 100 120 140 160
Time (min)
Press
ure
(Pa)
Reconciliated bottom hole pressure
Reconciliated wellhead press ureReconciliated manifold press ure
Fig. 8: Reconciliated pressure sensor measurements (activated
failure detection)
0.00E+00
2.00E+01
4.00E+01
6.00E+01
8.00E+01
1.00E+02
1.20E+02
1.40E+02
1.60E+02
0 20 40 60 80 100 120 140 160
Time (min)
Gas-Oil Ratio (Sm3/m3)
Total mass flow rat e (kg/s)
Fig. 9: Production estimate (activated failure detection)
Fig. 10: Typical Girassol production line
-
7/30/2019 Deep Offshore Well Metering and Permutation Testing
8/9
8 E. ZAKARIAN, A. CONSTANT, L. THOMAS, M. GAINVILLE, P. DUCHET-SUCHAUX, AND P. GRENIER OTC 14009
Time
Bottom hole pressure
Wellhead pressure
Choke downstream pressure
Choke opening
Fig. 11: Pressure measurements and choke opening (%) at a
Girassol well
Fig. 12: Girassol well: production simulation (first case)
Fig. 13: Girassol well: calibration of the modelling parameters
Fig. 14: Girassol well: production simulation (second case)
Fig. 15: Girassol well: GOR calibration
Production
loss Oil production
uncertainty
Methanol
consumption
Subsea valve
operation
Dead branch
creation
Water production
uncertainty
Gas production
uncertainty
Fig. 16: Various strategies for well permutation sequence sorting
-
7/30/2019 Deep Offshore Well Metering and Permutation Testing
9/9
OTC 14009 DEEP OFFSHORE WELL METERING AND PERMUTATION TESTING 9
Right
P1021
P1022
Left
P1011
P1012
Right
P1021
P1022
Left
P1012
P1011
Right
P1021
P1022
Left
P1011
P1012
Right
P1021
P1022
Left
P1011
P1012
TEST
TEST
TEST
TEST
M102
M102
M102
M102
M101
M101
M101
M101
Fig. 17: direct testing sequence
Right
P1021
P1022
Left
P1012
P1011
Right
P1021
Left
P1012
P1012
Right
P1021
P1022
Left
P1012
Right
P1022
P1021
Left
P1012
TEST
TEST
TEST
TEST
M102
M102
M102
M102
M101
M101
M101
M101
P1022
P1011
P1011 Fig. 18: Permutation testing sequence
TablesUnit operation Description
Block valve Routing valve (open/closed)
Choke Three-phase model
Fluid source Gas-lift model
Manifold Connection between wells and production loop
PipelineThree-phase flow model. Gridded model.Used for well tubing, sea-line, and riser
Piping Simulation of small scale piping networks
Sensor Hardware sensor model
InflowDefinition of fluid composition and ProductivityIndex relation
Table 1: Well monitoring unit operations
Test number Well arrangement1 WC
2 WA + WB+ WD
3 WB+ WC
4 WB+ WD
Table 2: Example of a well test sequence
Number ofwells
Number of wellarrangements
Number of well testingsequences
3 12 220
4 28 20475
5 60 2.12E+06
6 124 1.52E+09
Table 3: maximal number of well testing sequences
Table 4: Well permutation tests
Table 5: Test sequences (production loss minimization)