Deep Offshore Well Metering and Permutation Testing

download Deep Offshore Well Metering and Permutation Testing

of 9

Transcript of Deep Offshore Well Metering and Permutation Testing

  • 7/30/2019 Deep Offshore Well Metering and Permutation Testing

    1/9

    Copyright 2002, Offshore Technology Conference

    This paper was prepared for presentation at the 2002 Offshore Technology Conference held inHouston, Texas U.S.A., 69 May 2002.

    This paper was selected for presentation by the OTC Program Committee following review of

    information contained in an abstract submitted by the author(s). Contents of the paper, aspresented, have not been reviewed by the Offshore Technology Conference and are subject tocorrection by the author(s). The material, as presented, does not necessarily reflect any

    position of the Offshore Technology Conference or its officers. Electronic reproduction,distribution, or storage of any part of this paper for commercial purposes without the written

    consent of the Offshore Technology Conference is prohibited. Permission to reproduce in printis restricted to an abstract of not more than 300 words; illustrations may not be copied. Theabstract must contain conspicuous acknowledgment of where and by whom the paper waspresented.

    AbstractAs production in very deep waters becomes a crucial

    challenge for many oil companies, a better management of the

    production is constantly required. This paper presents two

    complementary methodologies for operation support and

    improvement of the production conditions. The first one is

    based on data reconciliation between process measurements

    and flow modelling. It brings an additional level of

    information to the problem of continuous metering of deep-

    water subsea wells. As periodic well testing is required toachieve this predictive metering, the second methodology

    provides the optimal test sequences of well permutations. It

    involves flow process simulation and algorithmical sorting,

    according to production constraints and operating strategies.

    Finally, comparisons between numerical simulations and plant

    data demonstrate the ability of these two methodologies to

    provide strong and reliable information for deep offshore

    producers.

    IntroductionThe knowledge of the phase flow rates coming from each

    individual well of an oil field is mandatory for a better

    production and reservoir management. Generally, thisinformation comes from a series of direct well testing, where a

    single well flows directly to a test separator.

    In deep offshore, this procedure turns out to be

    inappropriate: production developments are based on

    gathering network, where manifolds merge the production

    from several wells into a single flowline. This is the case on

    the Girassol oil field in Angola, see Fig. 1. Moreover, direct

    well testing implies deferred production, valve reliability and

    flow assurance issues: hydrate formation in dead branches,

    slugging at low flow rates, etc.

    Whereas conventional solutions, such as hardware

    multiphase metering, supply a limited information, our

    methodology works as an overall field supervisor for:

    estimating individual well production with respect toappropriate pressure and temperature measurements;

    detecting abnormal behavior (sensor drift forinstance);

    validating hardware measurements, and replacingthem in case of failure. Typically, in deep offshore

    production, hardware sensors are not replaced in case

    of failure for financial and feasibility reasons.

    This methodology is based on data reconciliation. It

    assumes that measurements are not necessarily correct and can

    be corrected within a confidence interval. Meanwhile,

    unmeasured variables derive from redundancy between flow

    modelling and field data.

    Data reconciliation has been already successfully applied

    to a small production network, see Ref. 1. Our paper intends to

    go further in the study of this innovative technology andpresents its application to the Girassol field.

    Well monitoringGiven a set of temperature and pressure measurements, our

    methodology aims to provide an estimate of the phase flow

    rates produced by each individual well of an oil field.

    Problem modelling. Real-time plant data are completed with

    a global steady state simulation of the production network

    involving:

    mass, force, and heat balance equations;

    thermodynamic calculations;

    hydrodynamic modelling.For instance, assuming process data at both ends of a

    choke and an estimate of the fluid composition, one can derive

    a local estimate of the liquid and gas mass flow rates from

    hydrodynamic and thermodynamic calculations.

    Combination between physical modelling and plant data is

    applied to the whole production network, leading to multiple

    estimates of the same information. This multiplicity derives

    from our uncertain interpretation of the reality: this statement

    is precisely the main strength of the data reconciliation

    technology.

    OTC 14009

    Deep Offshore Well Metering and Permutation TestingErich Zakarian, RSI; Arnaud Constant, TotalFinaElf Exploration & Production Angola; Lionel Thomas, TotalFinaElf; MartinGainville, Institut Franais du Ptrole; Pierre Duchet-Suchaux, TotalFinaElf; and Philippe Grenier, RSI

  • 7/30/2019 Deep Offshore Well Metering and Permutation Testing

    2/9

    2 E. ZAKARIAN, A. CONSTANT, L. THOMAS, M. GAINVILLE, P. DUCHET-SUCHAUX, AND P. GRENIER OTC 14009

    Whatever the complexity of a model, one should be awarethat it always remains an approximation. However, the latter

    can be restricted to a small number of modelling parameters

    embedded in residual equations. Again, any hardware sensor

    contribution is a residual equation weighted by vendor

    uncertainty.

    Both hardware measurements and modelling equations are

    involved on the same level of analysis through a global datareconciliation and parameter estimate, leading to an

    optimization problem. Conversely, experience feedback is

    expected to get optimal values of model uncertainties.

    A major innovative aspect of this work is the systematic

    computation of the accuracy of any estimated variable. We

    notice that the accuracy of a measured variable can be slightly

    increased since data reconciliation works as a global

    computation where any piece of information is likely to be

    improved by the other ones.

    We also emphasize that information on the solution

    uncertainty is as important as the solution itself: whenever

    redundancy remains, a physically incorrect solution can satisfy

    the problem. Therefore, a supervisor checks the consistency ofthe solution against intuitive expectations.

    Example. Let us consider the following scenario. Given one

    well tubing followed by a choke, six sensors are installed

    upstream and downstream these equipment to measure the

    pressure and the temperature of the fluid, see Fig. 2. We derive

    six equations:

    Pi - Pmi = 0,.....................................................................(1)

    Ti - Tmi = 0, .................................................... .................(2)

    where i = 1, 2, and 3 refer respectively to the following

    positions: upstream the well tubing, downstream the welltubing, and downstream the choke.

    Calibrated values of the water-liquid ratio and gas-oil ratiogive two additional equations:

    BSW-BSWm = 0,............................................................(3)

    GOR - GORm = 0............................................................(4)

    A well tubing model provides a pressure drop relation and

    a heat balance between positions 1 and 2:

    fWP (P1, T1, P2, T2, Flow,BSW, GOR, WP) = 0,..............(5)

    fWT(P1, T1, P2, T2, Flow,BSW, GOR, WT) = 0. ..............(6)

    A choke model gives the same kind of relations betweenpositions 2 and 3:

    fCP (P2, T2, P3, T3, Flow,BSW, GOR, CP) = 0,...............(7)

    fCT(P2, T2, P3, T3, Flow,BSW, GOR, CT) = 0................(8)

    Every measurements involved in this system are not

    necessarily correct since hardware sensors are subject to errors

    and the flow is not perfectly stable in the entire production

    system. As far as BSW and GOR, their a priori values

    (calibrated) might be trusted with a relative confidence as thefluid composition may change between two consecutive

    measurements performed on a test separator. Therefore,

    equations (1) to (4) are replaced by residual equations and

    weighted by the standard deviation (uncertainty):

    ePi = (Pi - Pmi)/Pi, ........................................................ .. (9)

    eTi = (Ti - Tmi)/Ti,........................... .............................. (10)

    eBSW= (BSW-BSWm)/BSW, ......................................... (11)

    eGOR = (GOR - GORm)/GOR, ........................................ (12)

    where i = 1, 2, and 3.

    As reminded before, an additional parameter calibrates

    each modelling equation with respect to a reference value

    (tuned from test measurements) and an uncertainty. Four

    residuals complete the system:

    eWP = (WP - WP,ref)/WP, ............................................. (13)

    eWT= (WT- WT,ref)/WT, .............................................. (14)

    eCP = (CP - CP,ref)/CP, ............................................... (15)

    eCT= (CT- CT,ref)/CT,........ ........................................ (16)

    We finally get 16 equations, namely (5) to (16), and 13

    variables: BSW, GOR, Flow, WP, WT, CP, CT, Pi, and Ti,where i = 1, 2, and 3. The system seems redundant. However,

    redundancy can only be ensured from a detailed analysis: to

    avoid any singularity, the rank of the jacobian must be equal to

    the number of the variables at any operating point. Note: the

    jacobian of the system is the matrix given by the partial

    derivatives of the equations (modelling equations andresiduals) with respect to the variables.

    This condition is necessary to find a solution, which is a

    minimization of an objective function given as a sum of the

    squares of the residuals. Meanwhile, the modelling equations

    are exactly satisfied (optimization constraints).

    Three phase flow modelling. Several models are involved in

    the simulation of a Girassol production loop, see Table 1. As a

    mixture of oil, gas and water is expected during the field life,

    intensive efforts are required to get an acceptable physical

    representation, due to the complexity of three-phase flows.

    A gridded modelling is used for long tubings (well, sea-

    line, riser) since local effects such as slope changes maystrongly impact pressure and thermal profiles. A complex

    three-phase hydraulic module ensures a correct representation

    of the different flow regimes. Local flash and thermal

    calculations improve the physical modelling as well.

    A rather sophisticated modelling is used for the chokes

    since flow criticity and gas expansion may seriously affect

    pressure and temperature variations. The choke discharge

    coefficient must be initially calibrated and periodically

    validated against field data. Three-phase flow meters could be

    used. Meanwhile, test separator instruments provide sufficient

  • 7/30/2019 Deep Offshore Well Metering and Permutation Testing

    3/9

    OTC 14009 DEEP OFFSHORE WELL METERING AND PERMUTATION TESTING 3

    and accurate information for calibration.This tuning procedure is described in a further section. In

    terms of computation, tuning is a particular use case of this

    well metering methodology.

    Thermodynamic issues. Physical phenomena such as

    vaporization in wells or expansion in chokes require accurate

    thermodynamic calculations. Therefore, the mixturecomposition is tracked along the flow line, and the whole unit

    operations perform local vapor/liquid/liquid equilibrium

    calculations to get an estimate of the phase properties.

    However, it is an illusion to believe that an accurate estimate

    of the reservoir fluid molar composition can be found: neither

    the system, nor the available sensors are able to catch the

    effect of a composition change (at constant phase properties)

    between C9 and C10 cuts, for instance. Conversely, gas

    coning or water breakthrough does affect sensor data.

    Therefore, the fluid composition is corrected with BSW and

    GOR variations by addition or removal of water and/or gas

    from the first stage separator.

    Software issues. The basic domains involved in an industrial

    well monitoring tool are:

    compositional thermodynamic calculation;

    hydrodynamic modelling in pipes and wells;

    thermal modelling in pipes and wells;

    valve modelling;

    reservoir PI modelling;

    data reconciliation;

    real-time process data recording and analysis.For each domain, several approaches have to be tested and

    selected. For example, a particular thermodynamic server

    might be suitable for certain operating conditions butunacceptable to other cases. Note: a server is a software

    component that provides services for other software

    components (client components) through defined interfaces.

    Therefore, it should be easy to combine different modules

    with the minimum effort. In addition, many pieces of software

    from different sources might fulfill our requirements. For

    these reasons, we decided to build our well monitoring

    simulator as an open software, using the CAPE-OPEN

    (Computer-Aided Process Engineering) standard, see Ref. 2.

    The compliance to this standard is another major and

    innovative aspect of this work. It provides high model

    flexibility for the end user, it makes implementation of new

    features much easier and faster: plug and play integration ofany CAPE-OPEN compliant component is carried out with the

    minimum effort.

    Built on a component-based architecture, see Fig. 3, our

    well monitoring simulator includes:

    CAPE-OPEN compliant components: unit operations,thermodynamic servers;

    external components: solver, man machine interface,data interface, supervisor.

    CAPE-OPEN standard interfaces ensure the

    communication between components through a simulator

    executive framework. The latter runs the whole application

    and its components, like the configuration of a production

    network or the use cases of a well monitoring application.

    Sensor failure detection. The data interface component

    makes the connection between the simulator executive

    framework and external components that provide hardware

    measurements: Distributed Control System, database.To avoid any undesirable effect on data reconciliation, the

    data interface performs a preliminary analysis to detect any

    possible failure (unlikely value, excessive variation) or

    unsteady behavior when the average of the measurements

    depends significantly on time.

    A sensor is declared invalid in case of failure and its

    contribution is removed from the system. It does not

    participate to the data reconciliation, leaving the determination

    of the measurement to the optimizer. This preliminary

    detection is as important as the data reconciliation itself. Let

    us present an example to confirm this statement.

    We consider a network with a well producing in a single

    flowline through a choke and a manifold, see Fig. 4. Pressureand temperature sensors are located upstream and downstream

    these equipment. Assuming an initial calibration of the system,

    we define a particular scenario with hardware sensor failures,

    see Fig. 5: at a fixed period of time (five minutes), the data

    interface sends sensor measurements to the simulator

    executive framework and a new solution is computed. Forty-

    five minutes after starting up, the pressure sensor at the bottom

    hole returns zero, which is of course an unacceptable value.

    This failure lasts half an hour. Two hours after starting up,

    both pressure sensors at the bottom hole and the manifold

    return zero again.

    First, let us consider the case where the data interface does

    not perform a detection of sensor failure. At the beginning of

    the run, the simulator computes reconciliated data, see Fig. 6.

    The latter are very close to the real measurements reproduced

    on the figure as dotted lines.

    At 45 minutes where the first pressure sensor collapses, the

    simulator manages to rebuild a measurement at the bottom

    hole. The rebuilt value is physically acceptable but likely far

    from reality. At the same time, the production is overestimated

    (the productivity index remains the same in the whole run) and

    the gas-oil ratio decreases, see Fig. 7. The wellhead pressure

    is also strongly affected because of its direct dependence onthe bottom hole pressure through the well tubing model. The

    pressure drop increases by 106 Pa.

    At 75 minutes where the sensor starts running again, the

    initial solution is recovered but at 120 minutes, both pressure

    sensors at the tubing ends stop to run. The simulator fails to

    find a solution.Let us run the same simulation but with detection of sensor

    failure. We notice that the data reconciliation works perfectly

    in this case, showing its ability to rebuild unmeasured

    variables, see Fig. 8, 9. The sensor failure does affect the

    redundancy of the problem, which is lower than before, but it

    does not affect the results.

  • 7/30/2019 Deep Offshore Well Metering and Permutation Testing

    4/9

    4 E. ZAKARIAN, A. CONSTANT, L. THOMAS, M. GAINVILLE, P. DUCHET-SUCHAUX, AND P. GRENIER OTC 14009

    At 120 minutes, both sensor failures are detected at thewell tubing ends. The solution remains acceptable. However,

    the manifold pressure drops significantly and its a posteriori

    confidence interval as well. In other words, there is not enough

    redundancy to trust the reconciliated value of the manifold

    pressure.

    This second computation confirms the ability of our

    methodology to replace hardware sensors in a productionsystem. It also shows its weakness whenever the number of

    valid sensors is not sufficient to allow redundancy.

    Real-scale validationProduction at the Girassol field started in late 2001. We

    propose to use a first series of measurements to validate our

    methodology and confirm its ability to provide reliable

    information. These measurements were recorded from

    December 4th to 24th, 2001.

    Calibration. We focus our presentation on a single well

    flowing into the right branch of the P10 loop. We consider the

    network from the well tubing to the test separator on FPSO(Floating Production Storage and Offloading), see Fig. 10.

    Note that riser tubing and riser choke are not simulated in this

    presentation.

    Modelling parameters derive from a single simulation with

    the following configuration:

    At the test separator: set the uncertainties of the phaseflow-rate sensors to vendor accuracy (we assume

    accurate measurements)

    At the upstream equipment and inflow model: removethe residuals of the modelling parameters (GOR,BSW,

    choke discharge coefficient, productivity index and

    friction factors).

    The vendor accuracy of the flow-rate sensors is small.

    Therefore, the phase flow-rates computed by the optimizer are

    necessarily close to their measured values. Meanwhile, the

    phase flow-rates derived from the modelling have to match

    these measured values. Assuming a small uncertainty on the

    pressure/temperature measurements, the optimizer is forced to

    change the values of the modelling parameters (a particular

    situation occurs here since the system has no redundancy, and

    solution is independent on the sensor accuracy).

    Twice a day in December 2001, measurements on a test

    separator were carried out at the Girassol field to estimate the

    production of the well. We propose to calibrate our system on

    one of these tests. Then, after a certain period of time, we will

    compare the oil, water, and gas flow-rates predicted by the

    simulation and those derived from real testing.

    Well metering. A demonstrative test can be found from

    December 7th to 12th. During this period of time, the

    production of a well was progressively increased with a choke

    opening from 36 % to 49 %, see Fig. 11. Meanwhile, the

    pressure drop in the well tubing remained approximately

    constant and the one through the choke dropped from 5 106 Pa

    to 2.5 106 Pa.

    We calibrate the simulator with data recorded onDecember 7th, between 02:00 and 08:00 am. Then, we run a

    metering, up to December 12th.

    With a sampling DCS period of five minutes, production is

    estimated every thirty minutes, using data filtered on the past

    hour. If we assign the same level of confidence to the models

    (choke, inflow, tubings), the system overestimates the

    production, but the predicted trend is consistent with reality,see Fig. 12.

    A detailed analysis shows that the choke model is

    responsible for this deviation: tuning with subsequent tests

    shows that the discharge coefficient drops from 0.92 to 0.6 on

    December 8th, see Fig. 13. Meanwhile, productivity index and

    friction factors remain roughly constant. This observation

    reveals some inconsistency between plant data and the choke

    modelling. Further analysis will be required to get a better

    understanding of the real choke behavior.

    If we set a lower relative confidence on the choke model

    (by increasing the discharge coefficient uncertainty), we verify

    that the initial tuning is sufficient to get, five days latter, a

    good estimate of the expected oil and gas production, see Fig.14. This implies that the initial tuning of the GOR was good

    enough for the five following days of metering. We effectively

    notice that the GOR derived from tuning remains constant, see

    Fig. 15.

    Permutation testing Assistance toolPeriodic calibration is required to keep the modelling close to

    the real process. Three-phase flow meters could be used but

    test separator measurements through well testing can also

    provide sufficient and accurate information.

    Production at the Girassol field is based on a loop

    configuration where sea-lines are connected to each other

    through subsea manifolds, see Fig. 1. Each well of a loop is

    routed to a production line, either left or right. There is no

    specific line for well testing.

    This network architecture and flow assurance issues

    strongly impact the well testing strategy:

    direct testing leads to increase deferred production;

    direct testing at low flow-rates may lead to instabilityin the flowlines (slugging);

    direct testing at flow rates below 10 000 bbl/d maylead to a fluid temperature lower than the paraffin

    formation temperature (about 40C);

    direct testing for the nearest wells leaves the upstream

    flowline full of dead fluid during the test, and hydrateinhibition with methanol is required.

    Therefore, permutation testing (in addition to direct

    testing) has been included in the Girassol well monitoring

    strategy:

    a direct testing connects a single well to a singleproduction line; estimating the phase flow rates of the

    well is straightforward;

    a permutation testing connects several wells to bothproduction lines (but a well is necessarily allocated to

    a single line). A series of different permutations leads

  • 7/30/2019 Deep Offshore Well Metering and Permutation Testing

    5/9

    OTC 14009 DEEP OFFSHORE WELL METERING AND PERMUTATION TESTING 5

    to different measurements of the phase flow rates ofeach production line. The phase flow rates of each

    individual well derives from solving a set of linear

    equations.

    Testing strategy. Since the wells of a production loop may

    produce into either left or right production line, a permutation

    can be considered as a set of two well arrangements, left andright. The number of possible arrangements is necessarily

    much greater than the number of wells. For example, let us

    consider four producers: WA, WB, WC, WD. Any sequence

    involving these four wells can be acceptable. One of them is

    shown on Table 2; notation: WA + WB + WD means a test with

    WA, WB, and WD.

    The number of possible test sequences increases drastically

    with the number of wells, see Table 3. This observation and

    the complexity of involved phenomena prevent us from

    deriving a simple synthetic rule that could be used in operation

    to select the best test sequences. The latter have to be

    compliant with the whole production constraints.

    A permutation testing assistance tool has been specificallydesigned to achieve this work. Basically, a steady state process

    simulator is used for network and gaslift computation,

    providing well production in any arrangement, see Table 4 for

    few examples. Then, sequence sorting is carried out versus

    user strategy, see Fig. 16.

    Flow modelling. Flow rates and production losses are

    estimated from a simplified flow modelling: well performance

    curves and pressure loss tables derive from experiments or

    simulations performed on predictive multiphase software.

    Specific unit operations implement these tables in the process

    simulator. Thus, any code can be used to generate the flow

    modelling.

    Contrary to the well monitoring tool, this permutation

    testing assistant is an off-line software. However, a periodic

    tuning against real process data is recommended in order to

    adjustBSWor GOR of each individual well.

    Sequence sorting. After network configuration and

    calculations, a sorting service provides an ordered succession

    of permutations.

    The initial number of possible sequences is Ckj where k is

    the length of the sequence and j is the total number of possiblearrangements, see Table 3. Some of them do not comply with

    thermal constraints and are removed. The same applies for

    singular sequences.

    For one sequence of k arrangements, there are k! orders.

    Applying an order-dependent criterion, the best order is

    selected. The simulator computes the expected test accuracy,namely the accuracy of each individual well production, GOR,

    and BSW. Finally, the remaining sequences are sorted with

    respect to user strategy, see Fig. 16. Typical simulation results

    are shown on Table 5.

    Features. Direct testing is intuitively the best solution to reach

    the maximal accuracy. For instance, if we consider aproduction loop with four wells, sixteen different sequences of

    four direct tests will estimate the production, without any loss

    of accuracy. But, only few of them may satisfy operation

    constraints.

    According to our assistance tool, only one sequence does

    not require hydrate inhibition with methanol, see Fig. 17: no

    dead branch is created if we consider the first arrangement asthe initial loop configuration. Conversely, if we accept a

    relative loss of accuracy, permutation testing will keep the

    production at its optimal level, see Fig. 18.

    Since both maximal accuracy and minimal production loss

    strategies may be required, a global weighted criterion is

    actually used to bring all the strategies together and perform

    the sequence sorting.

    Theoretically, there is no limitation on the number of wells

    to consider. However, let us remind that the number of

    possible test sequences increases drastically with the number

    of wells, see Table 3. In the case of six wells or more, the

    computation time can be prohibitive unless one or several

    wells are exclusively allocated to a production line.

    ConclusionThis paper demonstrates the ability of a well monitoring

    software to provide reliable information for producers:

    production estimate of each individual well, abnormal

    behavior detection, validation of hardware measurements and

    replacement in case of failure.

    Although the described methodology can be applied to any

    type of onshore/offshore development scheme, this work is

    mainly intended to deep offshore developments, such as the

    Girassol field in Angola.

    Based on data reconciliation between field data and flow

    modelling, our well monitoring tool requires a periodic

    calibration to keep its modelling close to the real process. This

    tuning derives from test separator measurements.

    Since a combination of direct and permutation well testing

    is presently involved at the Girassol field, we also designed a

    second tool to compute the optimal test sequences versus usual

    production and operating constraints.

    Intensive use and positive feedback will confirm the

    usefulness and reliability of this work. This will be the main

    topic of a second paper.

    NomenclatureBSW = Basic Sediment and Water (water volume

    flow/liquid volume flow), m3/m3

    BSWm = Measured value ofBSW, m3/m3

    Flow = Total mass flow rate, kg.s-1

    GOR = Gas-Oil Ratio (gas volume flow/oil volumeflow), Sm3/m3

    GORm = Measured value ofGOR, Sm3/m3

    P1 = Well tubing upstream pressure, Pa

    P2 = Well tubing downstream pressure, Pa

    P3 = Choke downstream pressure, Pa

    Pmi = Measured value ofPi, (i = 1, 2, 3), Pa

  • 7/30/2019 Deep Offshore Well Metering and Permutation Testing

    6/9

    6 E. ZAKARIAN, A. CONSTANT, L. THOMAS, M. GAINVILLE, P. DUCHET-SUCHAUX, AND P. GRENIER OTC 14009

    T1 = Well tubing upstream temperature, K

    T2 = Well tubing downstream temperature, K

    T3 = Choke downstream temperature, K

    Tmi = Measured value ofTi, (i = 1, 2, 3), K

    WP = Tuning parameter for well tubing pressure drop

    WT = Tuning parameter for well tubing heat balance

    CP = Tuning parameter for choke pressure drop

    CT = Tuning parameter for choke heat balance

    WP,ref = Calibrated value ofWP

    WT,ref = Calibrated value ofWT

    CP,ref = Calibrated value ofCP

    CT,ref = Calibrated value ofCT

    Pi = Uncertainty ofPmi (i = 1, 2, 3)

    Ti = Uncertainty ofTmi (i = 1, 2, 3)

    BSW = Uncertainty ofBSWm

    GOR = Uncertainty ofGORm

    WP = Uncertainty ofWP

    WT = Uncertainty ofWT

    CP = Uncertainty ofCP

    CT = Uncertainty ofCT

    References1. Van der Geest, R., Reliability Through Data Reconciliation,

    OTC 13000 presented at the 2001 Offshore Technology

    Conference held in Houston, Texas (2001).

    2. Braunschweig, B., Paen, D., Roux, P., and Vacher, P., The Use of

    CAPE-OPEN Interfaces for Interoperability of Unit Operations and

    Thermodynamic Packages in Process Modelling, The European

    Refining Technology Conference, Paris, France (2001). See also

    http://www.colan.org.

    Figures

    Wellhead Manifold

    Fig. 1: Girassol subsea loop

    Well tubing

    Choke

    Pm1, Tm1

    Pm2, Tm2

    Pm3, Tm3

    Fig. 2: Example of a production network

    Simulator ExecutiveFramework

    Solver

    Man MachineInterface

    DCS

    Unit Operation Thermo Server

    CAPE-OPENCOMPONENTS

    CAPE-OPEN

    SIMULATION

    ENVIRONMENT

    EXTERNAL

    COMPONENTS

    Supervisor

    Fig. 3: Well monitoring software overview

    Fig. 4: Sensor failure simulation

  • 7/30/2019 Deep Offshore Well Metering and Permutation Testing

    7/9

    OTC 14009 DEEP OFFSHORE WELL METERING AND PERMUTATION TESTING 7

    0.00E+00

    5.00E+06

    1.00E+07

    1.50E+07

    2.00E+07

    2.50E+07

    3.00E+07

    0 20 40 60 80 100 120 140 160

    Time (min)

    Pressure

    (Pa)

    Bottom hole pressure

    Wellhead press ure

    Manifold pressure

    Fig. 5: Pressure sensor measurements

    0.00E+00

    5.00E+06

    1.00E+07

    1.50E+07

    2.00E+07

    2.50E+07

    3.00E+07

    0 20 40 60 80 100 120 140 160

    Time (min)

    Pressure

    (Pa)

    Reconciliated bottom hole pressure

    Reconciliated wellhead press ureReconciliated manifold press ure

    Fig. 6: Reconciliated pressure sensor measurements (no

    preliminary failure detection)

    0.00E+00

    2.00E+01

    4.00E+01

    6.00E+01

    8.00E+01

    1.00E+02

    1.20E+02

    1.40E+02

    1.60E+02

    0 20 40 60 80 100 120 140 160

    Time (min)

    Gas-Oil Ratio (Sm3/m3)

    Total mass flow rat e (kg/s)

    Fig. 7: Production estimate (no preliminary failure detection)

    0.00E+00

    5.00E+06

    1.00E+07

    1.50E+07

    2.00E+07

    2.50E+07

    3.00E+07

    0 20 40 60 80 100 120 140 160

    Time (min)

    Press

    ure

    (Pa)

    Reconciliated bottom hole pressure

    Reconciliated wellhead press ureReconciliated manifold press ure

    Fig. 8: Reconciliated pressure sensor measurements (activated

    failure detection)

    0.00E+00

    2.00E+01

    4.00E+01

    6.00E+01

    8.00E+01

    1.00E+02

    1.20E+02

    1.40E+02

    1.60E+02

    0 20 40 60 80 100 120 140 160

    Time (min)

    Gas-Oil Ratio (Sm3/m3)

    Total mass flow rat e (kg/s)

    Fig. 9: Production estimate (activated failure detection)

    Fig. 10: Typical Girassol production line

  • 7/30/2019 Deep Offshore Well Metering and Permutation Testing

    8/9

    8 E. ZAKARIAN, A. CONSTANT, L. THOMAS, M. GAINVILLE, P. DUCHET-SUCHAUX, AND P. GRENIER OTC 14009

    Time

    Bottom hole pressure

    Wellhead pressure

    Choke downstream pressure

    Choke opening

    Fig. 11: Pressure measurements and choke opening (%) at a

    Girassol well

    Fig. 12: Girassol well: production simulation (first case)

    Fig. 13: Girassol well: calibration of the modelling parameters

    Fig. 14: Girassol well: production simulation (second case)

    Fig. 15: Girassol well: GOR calibration

    Production

    loss Oil production

    uncertainty

    Methanol

    consumption

    Subsea valve

    operation

    Dead branch

    creation

    Water production

    uncertainty

    Gas production

    uncertainty

    Fig. 16: Various strategies for well permutation sequence sorting

  • 7/30/2019 Deep Offshore Well Metering and Permutation Testing

    9/9

    OTC 14009 DEEP OFFSHORE WELL METERING AND PERMUTATION TESTING 9

    Right

    P1021

    P1022

    Left

    P1011

    P1012

    Right

    P1021

    P1022

    Left

    P1012

    P1011

    Right

    P1021

    P1022

    Left

    P1011

    P1012

    Right

    P1021

    P1022

    Left

    P1011

    P1012

    TEST

    TEST

    TEST

    TEST

    M102

    M102

    M102

    M102

    M101

    M101

    M101

    M101

    Fig. 17: direct testing sequence

    Right

    P1021

    P1022

    Left

    P1012

    P1011

    Right

    P1021

    Left

    P1012

    P1012

    Right

    P1021

    P1022

    Left

    P1012

    Right

    P1022

    P1021

    Left

    P1012

    TEST

    TEST

    TEST

    TEST

    M102

    M102

    M102

    M102

    M101

    M101

    M101

    M101

    P1022

    P1011

    P1011 Fig. 18: Permutation testing sequence

    TablesUnit operation Description

    Block valve Routing valve (open/closed)

    Choke Three-phase model

    Fluid source Gas-lift model

    Manifold Connection between wells and production loop

    PipelineThree-phase flow model. Gridded model.Used for well tubing, sea-line, and riser

    Piping Simulation of small scale piping networks

    Sensor Hardware sensor model

    InflowDefinition of fluid composition and ProductivityIndex relation

    Table 1: Well monitoring unit operations

    Test number Well arrangement1 WC

    2 WA + WB+ WD

    3 WB+ WC

    4 WB+ WD

    Table 2: Example of a well test sequence

    Number ofwells

    Number of wellarrangements

    Number of well testingsequences

    3 12 220

    4 28 20475

    5 60 2.12E+06

    6 124 1.52E+09

    Table 3: maximal number of well testing sequences

    Table 4: Well permutation tests

    Table 5: Test sequences (production loss minimization)