Deep braced cuts utilities.pdf

download Deep braced cuts utilities.pdf

of 169

Transcript of Deep braced cuts utilities.pdf

  • 8/22/2019 Deep braced cuts utilities.pdf

    1/169

    Technical Report Documentation Page

    1. Report No. A450, A464 2. Government Accession No. 3. Recipient's Catalog No.

    5. Report Date December, 20034. Title and Subtitle Analysis of Effects of Deep Braced Excavations onAdjacent Buried Utilities

    7. Author/s Richard J. Finno, Kristin M. Molnar, Edwin C. Rossow 8. Performing Organization Report No.

    10. Work Unit No. (TRAIS)9. Performing Organization Name and AddressDepartment of Civil and Environmental Engineering

    Northwestern University

    2145 Sheridan Road

    Evanston, IL 60208

    11. Contract or Grant No.

    DTRS98-G-0016

    13. Type of Report and Period CoveredFinal Report, April 1, 2002

    September 30, 2003

    12. Sponsoring Organization Name and Address

    U.S. Department of Transportation

    Research and Special Programs

    Administration

    400 7thStreet, SW

    Washington, DC 20590-0001

    14. Sponsoring Agency Code

    15. Supplementary Notes

    16. Abstract Ground movements resulting from deep braced excavations impose the risk of damage toadjacent buried pipelines. Accurate assessment of the effects these movements have on pipelines allows

    potential damage to be avoided or mitigated. A predictive process for determining the stresses occurring

    in a pipeline adjacent to deep braced excavations is presented. The method can be used to establishrational criteria for determining allowable maximum values for excavation-induced ground movements.

    The ground movement distribution around the excavated area is predicted using a complimentary error

    function, an assessment of the maximum ground deformation, and knowledge of the geometry of the

    excavation. The pipeline is assumed to move with the ground enabling the behavior of the pipeline to be

    represented by the ground surface movements at its location. Conservative analyses for determining thebending stresses and joint rotations along a pipeline caused by its deformation are established. Allowable

    values for both the tensile bending stress and joint rotation resulting from the excavation-induced

    movements are presented for comparison with the computed maximum values. The predictive

    methodology is applied to three gas mains surrounding a deep braced excavation in downtown Chicago

    and four cast iron mains from various excavations in Chicago. For these cases, the calculated bending

    stresses in the pipelines were significantly smaller than allowable values, but the joint rotations were

    observed to be the more critical case.

    17. Key Words Excavation, Pipelines,

    Deformation, Seismicity, Infrastructure

    18. Distribution Statement No Restrictions

    9. Security Classification (of this report) Unclassified 20. Security Classification (of this page)Unclassified

    21. No. Of Pages 168 22. Price

  • 8/22/2019 Deep braced cuts utilities.pdf

    2/169

    ANALYSIS OF EFFECTS OF DEEP BRACED

    EXCAVATIONS ON ADJACENT BURIED UTILITIES

    By

    Kristin M. Molnar

    Richard J. FinnoEdwin C. Rossow

    By

    School of Civil and Environmental Engineering

    Northwestern University

    Evanston, IL

    December, 2003

  • 8/22/2019 Deep braced cuts utilities.pdf

    3/169

    ABSTRACT

    Ground movements resulting from deep braced excavations impose the risk of damage to

    adjacent buried pipelines. Accurate assessment of the effects these movements have on pipelines

    allows potential damage to be avoided or mitigated. A predictive process for determining the

    stresses occurring in a pipeline adjacent to deep braced excavations is presented. The method

    can be used to establish rational criteria for determining allowable maximum values for

    excavation-induced ground movements. The ground movement distribution around the

    excavated area is predicted using a complimentary error function, an assessment of the maximum

    ground deformation, and knowledge of the geometry of the excavation. The pipeline is assumed

    to move with the ground enabling the behavior of the pipeline to be represented by the ground

    surface movements at its location. Conservative analyses for determining the bending stresses

    and joint rotations along a pipeline caused by its deformation are established. Allowable values

    for both the tensile bending stress and joint rotation resulting from the excavation-induced

    movements are presented for comparison with the computed maximum values. The predictive

    methodology is applied to three gas mains surrounding a deep braced excavation in downtown

    Chicago and four cast iron mains from various excavations in Chicago. For these cases, the

    calculated bending stresses in the pipelines were significantly smaller than allowable values, but

    the joint rotations were observed to be the more critical case. Excessive leakage was observed at

    a rotation of 6 x 10-3

    radians for a cast iron pipeline with lead caulked joints.

    i

  • 8/22/2019 Deep braced cuts utilities.pdf

    4/169

    ACKNOWLEDGEMENTS

    A number of people and organizations were instrumental in providing the data from the

    Lurie Research Center project that form the basis of this work. Inclinometer data were obtained

    by Construction Testing & Instruments, Inc., and Professionals Associated obtained the vertical

    and lateral survey data. Turner Construction Company was the general contractor and Case

    Foundation Company was the excavation support subcontractor. The help and interest of Dr.

    Jerry Parola and Ms. Dhooli Raj of Case and Mr. Ron McAllister of Turner made this work

    possible. Mr. John Brzezinski and Ms. Jo LeMieux-Murphy of the Facility Management group

    at Northwestern provided access to the project and were very helpful throughout its duration.

    Northwestern University students who generously gave their time to assist in the field

    monitoring effort included Frank Voss, Tanner Blackburn, and Terry Holman. Jill Roboski of

    Northwestern University developed the method to estimate surface settlement profiles along

    lines parallel to an excavation. The authors also thank Professor Thomas ORourke from Cornell

    University who generously provided us with a number of reports he authored related to pipelines.

    ii

  • 8/22/2019 Deep braced cuts utilities.pdf

    5/169

    TABLE OF CONTENTS

    Abstract i

    Acknowledgements ii

    Table of Contents iii

    List of Tables iv

    List of Figures v

    List of Symbols vi

    INTRODUCTION 1

    BACKGROUND 2

    Pipe Material 2Joints 4

    Initial Stresses 5

    ANALYSIS OF PIPES 6

    Approach 6

    Bending Stresses 8Joint Rotations 11

    Allowable Stresses and Joint Rotations 12

    PREDICTION OF EXCAVATION-INDUCED MOVEMENTS 15

    Summary of Procedure 15

    CASE STUDIES 16

    Lurie Center 16

    Chicago Excavation Case Studies 19

    CONCLUSIONS 21

    REFERENCES 23

    TABLES 26

    FIGURES 32

    APPENDIX A: LURIE CENTER DATA 40

    iii

  • 8/22/2019 Deep braced cuts utilities.pdf

    6/169

    LIST OF TABLES

    Table 1 Engineering Properties for Piping Materials 26

    Table 2 Failure Rotations for Selected Cast Iron and Ductile

    Iron Joints 27

    Table 3 Allowable Bending Stresses from Excavation-Induced

    Movements 28

    Table 4 Allowable Joint Rotations for Cast Iron and Ductile

    Iron Joints 29

    Table 5 Strength Reductions at Location of Line Pipe Welded

    Joints 30

    Table 6 Description of Cast Iron Pipelines Parallel to ChicagoExcavations 31

    iv

  • 8/22/2019 Deep braced cuts utilities.pdf

    7/169

    LIST OF FIGURES

    Figure 1 Schematic of Joint Rotation for Joint j of Rigid Pipeline 32

    Figure 2 General Layout of Lurie Center Site Instrumentation and

    Adjacent Gas Mains 33

    Figure 3 Comparison of Ground and Pipeline Movement during

    Excavation at Lurie Center 34

    Figure 4 Ground Displacements at Location of Gas Mains along North,

    South and West Walls after Completion of Excavation 35

    Figure 5 Maximum Tensile Stress in Pipelines Adjacent to North, South

    and West Wall During Excavation 36

    Figure 6 Maximum Relative Rotation Encountered Along North, South,and West Pipelines During Excavation for 3.6m Pipe Sections 37

    Figure 7 Observed and Predicted Maximum Bending Stresses and Joint

    Rotations for Final Stages of Construction 38

    Figure 8 Rotations in Cast Iron Pipelines Adjacent to Excavations in

    Chicago 39

    v

  • 8/22/2019 Deep braced cuts utilities.pdf

    8/169

    LIST OF SYMBOLS

    A0, A2, B2 coefficients for no slippage between pipe and soil equations

    A0*, A2*, B2* coefficients for slippage between pipe and soil equations

    B dimensionless constant related to lateral stress ratio

    C dimensionless constant related to lateral stress ratio

    dc thickness of caulking in joint

    dc/ds rotation to cause metal binding failure in lead caulked cast iron joints

    di inner diameter of pipe cross section

    dl depth of lead

    do outer diameter of pipe cross section

    ds depth of bell

    dw depth of packing material

    distance between rubber gasket and end of pipe

    E modulus of elasticity

    EA circumferential extensional stiffness per unit length

    EI circumferential bending stiffness per unit length

    Fu ultimate stress

    Fy yield stress

    h relative distance from data point to node of grid for radial basis interpolation

    H depth of pipe

    HDB hydrostatic design basis value

    I moment of inertia of cross section

    j stress exponent

    vi

  • 8/22/2019 Deep braced cuts utilities.pdf

    9/169

    K lateral stress ratio

    L length of diagonal of extent of data range for radial basis interpolation

    original length

    Lji distance along pipeline between points i and j (i,j = 1, 2, 3, n)

    m modulus number

    M moment

    Newmark coefficient

    Ms constrained modulus of soil

    Mt tangent modulus of soil

    Mx moment around x-axis

    Mz moment around z-axis

    n number of survey points along pipeline

    N number of data points in radial basis interpolation

    thrust

    Boussinesq coefficient

    p internal pressure

    Pr interaction load at interface of pipe and soil

    q uniform pressure

    r mean radius of pipe

    R horizontal distance from top of pipe to application of load

    R2 smoothing factor for radial basis interpolation

    t wall thickness

    Tr interaction shear at interface of pipe and soil

    UF extensional flexibility ratio

    VF bending flexibility ratio

    vii

  • 8/22/2019 Deep braced cuts utilities.pdf

    10/169

    w curvature of deflection curve w

    W concentrated wheel load

    xi distance to extreme fiber at point i under Mz(i = 1, 2, 3, n)

    x(Yi) curvature of lateral movement profile at point i (i = 1, 2, 3, n)

    Xi total lateral movement at survey point i (i = 1, 2, 3, n)

    Yi distance from origin to survey point i along pipeline (i = 1, 2, 3, n)

    z distance from centroidal axis of deflection curve

    zi distance to extreme fiber at point i under Mx(i = 1, 2, 3, n)

    z(Yi) curvature of vertical movement profile at point i (i = 1, 2, 3, n)

    Zi total vertical movement at survey point i (i = 1, 2, 3, n)

    coefficient of thermal expansion

    i relative rotation between two adjacent pipe sections at joint i

    L change in length

    T change in temperature

    strain

    ji differential lateral movement between points i and j (i,j = 1, 2, 3, n)

    Poissons ratio

    angle from horizontal of pipe cross section

    ALLOW allowable joint rotation from excavation-induced ground movements

    i angle from horizontal for cross section of pipe at point i (i = 1, 2, 3, n)

    imax angle of principal plane of pipe cross section at point i (i = 1, 2, 3, n)

    L rotation to cause excessive leakage in lead caulked joint for analysis

    max rotation to cause metal binding failure in rubber gasket iron joints

    viii

  • 8/22/2019 Deep braced cuts utilities.pdf

    11/169

    M rotation to cause metal binding failure in rubber gasket joints for analysis

    radius of curvature of centroidal axis of deflection curve

    ji differential vertical movement between points i and j (i,j = 1, 2, 3, n)

    effective stress of soil

    ALLOW allowable stress from excavation-induced ground movements

    B design bending stress of pipe material

    H hoop stress (circumferential stress)

    i bending stress at point i (i = 1, 2, 3, n)

    INITIAL initial stress in pipeline prior to stress analysis

    imax maximum longitudinal bending stress in pipe cross section at point I

    r reference stress (atmospheric pressure = 100kPa = 1atm)

    v vertical soil stress

    ix

  • 8/22/2019 Deep braced cuts utilities.pdf

    12/169

    INTRODUCTION

    Buried pipelines within urban environments are exposed to large ground movements as

    the result of adjacent excavations. These excavations may include tunneling, trenching, or deep

    open cuts. The ground movements resulting from these conditions impose stresses on the

    pipeline that could lead to its failure. Deep braced excavations are known to cause significant

    ground movements at great distances away.

    Most commonly buried utilities are exposed to ground movements from trench

    construction for the installation or repair of an adjacent pipeline. Much work has been done in

    this area to determine the patterns of movement caused by trench construction and the stresses

    encountered in the pipeline. Field experiments (Carder, et al. 1982, Carder and Taylor 1983 and

    ORourke and Kumbhojkar 1984), beam on elastic foundation analysis (Crofts, et al. 1977 and

    Tarzi, et al. 1979), and finite element simulation (Nath 1983 and Ahmed, et al. 1985) have been

    performed to determine a pattern of behavior for ground movements from trench construction

    and their effects on adjacent pipelines.

    Information regarding the effects of pipelines adjacent to deep braced excavations is very

    limited. Methods for predicting the magnitude and location of maximum ground movements

    around an excavation have been determined from field observations (Clough and ORourke 1990

    and Hsieh and Ou 1998). Maynard and ORourke (1977) report field observations for four cast

    iron gas mains in Chicago exposed to ground movements from neighboring deep excavations.

    They reported excessive leakage from one of the mains making it necessary for it to be taken out

    of operation.

    If excavation-induced ground movements are sufficiently large, imposed stresses on a

    pipeline can cause failure. One therefore needs to determine the effects of an excavation on a

    1

  • 8/22/2019 Deep braced cuts utilities.pdf

    13/169

    pipeline prior to construction so that rational criteria for preventing damage can be included in

    the design of the excavation support system. A method for predicting the longitudinal bending

    stresses and joint rotations incurred by a pipeline from ground movements resulting from an

    adjacent excavation is presented. The complimentary error function (Roboski and Finno, 2004)

    is presented for producing a distribution of movements parallel to an excavation wall based on

    the excavation geometry. The ground distributions are imposed on the surrounding pipelines.

    Equations are derived for bending stress and joint rotation analyses to determine the distribution

    of stresses along the pipeline.

    Distributions of the bending stresses and joint rotations are determined by the analysis.

    The maximum values can be determined and compared to allowable values determined from

    previous experimental and empirical observations. This approach provides a rational method of

    establishing excavation-induced ground movement limits when surrounding utilities are the

    critical structure impacted by the excavation.

    BACKGROUND

    Pipe Materials

    The most common metallic materials found in pipelines in urban areas are cast iron,

    ductile iron and steel. The more modern installations use plastics because of their flexibility.

    Polyethylene is a popular material for buried utility installations for gas and water transportation.

    General engineering properties for these materials are presented in Table 1.

    Cast iron is the oldest metal found in pipelines, and is relatively common since many

    pipelines installed over 100 years ago are still in operation. Cast iron pipe was formed by pit

    casting, the predominant process until the 1930s when the centrifugal cast process was

    developed. Of the two manufacturing processes, centrifugal cast pipe has a greater strength due

    2

  • 8/22/2019 Deep braced cuts utilities.pdf

    14/169

    to a better distribution of graphite flakes within the iron matrix. The tensile stress-strain behavior

    of both types of cast iron exhibits irrecoverable deformations at low strains. There is no apparent

    yield point, and brittle failure occurs at relatively low strain values.

    Cast iron pipe was the dominant pipe material until the 1950s when ductile iron was

    introduced. The metallurgy of the materials is very similar, but ductile iron has increased

    strength and ductility from carbon that exists as small spheroids. The presence of the carbon in

    this form introduces fewer discontinuities into the matrix. Ductile iron also does not exhibit a

    yield point. Angus (1976) observed a true elastic range of stress values in which irrecoverable

    deformation did not occur. When the material begins to plastically deform, the graphite nodules

    do not deform with the matrix and the useful cross sectional area is reduced which in turn

    reduces the apparent pipe stiffness.

    At the end of the 19th

    century, steel, or line, pipe was implemented into the transport of

    gas and oil. Pipe sections are manufactured as welded or seamless. Welded pipe has two halves

    of pipe longitudinally welded together. Seamless pipe contains no welds and is produced by

    either hot piercing or cupping and drawing.

    Steel differs from cast iron and ductile iron in that it exhibits a yield point at the end of a

    region of linear elastic behavior, with a well-defined modulus elasticity. The stress-strain

    behavior is dependent on the carbon content within the alloy. The yield point becomes less

    sharp, the yield plateau becomes less prominent, and the ultimate stress increases as the carbon

    content increases.

    In the more recent installations of pipelines, plastics have been used due to the great

    lengths of pipe available and its flexibility and durability. Plastics are solid materials with one or

    more polymeric substances that can be formed by flow (Plastics Pipe Institute, 1993). Common

    3

  • 8/22/2019 Deep braced cuts utilities.pdf

    15/169

    plastics used in piping are polyvinyl chloride (PVC) and polyethylene (PE). Polyethylene pipe is

    commonly used for the transportation of water and gas. The behavior of polyethylene under

    stress is complex due to its viscoelastic properties and its dependency on the load duration,

    environment, and temperature. The shape of the stress-strain curve is highly dependent on the

    load duration due to its material rate-dependent behavior. The Plastics Pipe Institute (1993)

    define a flexural, short-term, and long-term modulus for polyethylene dependent on the nature of

    the load and the rate at which the load is applied.

    Joints

    The methods of joining pipe sections also have steadily improved over time allowing

    greater rotations without attendant loss of service. Joining mechanisms may be used to allow

    rotations or the pipe sections may be joined to one another directly.

    Table 2 show typical failure rotations for cast iron and ductile iron joints. Early

    installations of cast iron pipe were joined with rigid connections and were constructed with

    metal-to-metal contact within a bell and spigot connection to prevent leaks, while allowing very

    little rotation. Semi-rigid joints were the more predominant mode of joining cast iron pipe and

    were constructed by adding a packing and caulking material within a bell and spigot connection.

    The packing material was soft, usually jute or yarn, to permit a certain amount of flexibility

    within the joint. The caulking held the packing in the joint and, for most installations, was lead.

    These joints were able to withstand small rotations before failure was observed. Joints allowing

    exhibiting flexible behavior within a cast iron pipeline are constructed by adding a rubber gasket

    to eliminate leaks; these joints allow greater rotations without loss of service. Rubber gaskets are

    used in push-on and mechanical joints.

    4

  • 8/22/2019 Deep braced cuts utilities.pdf

    16/169

    Ductile iron pipe is predominantly joined with rubber gasket joints similar to that of cast

    iron pipes. There are rubber gasket push-on joints and bolted-gland mechanical joints. For more

    adverse conditions there is a ball and socket joint, which is free to rotate up to 0.27 radians (15

    degrees).

    Rubber gasket joints are available for steel pipe as well, but the more common method of

    joining steel pipe sections is by welding. Lap, single-butt, and double-butt welds are the more

    common types of joining welds and produce a joint with strength very similar to that of the

    strength of steel. Of the three types of welded joints, the single-welded lap joint introduces the

    greatest reduction in the strength of the steel of approximately 25 percent.

    Similar to that of welding steel pipe, polyethylene is joined by fusion, wherein two ends

    of adjacent pipes are melted to a fluid-like state and then forced together to join a continuous

    section after cooling. Melting of the ends of the pipe can be from direct heat from a hot surface

    or a coiled wire. The fusion joint is equal in strength to that of the rest of the polyethylene pipe.

    Initial Stresses

    The installation of a buried pipeline introduces stresses within the pipe upon which are

    added additional stresses caused by movements associated with excavations. These stresses can

    be a result of any combination of an operating internal pressure, the soil cover load, cyclic or

    static surface loads, the installation procedure, previous ground movements, or environmental

    effects.

    Taki and ORourke (1983) analyzed the effects internal pressure, thermal fluctuations,

    repeated loading, and installation procedures on cast iron mains. They determined typical

    amounts of tensile or bending strain induced by these conditions for low pressure pipelines.

    5

  • 8/22/2019 Deep braced cuts utilities.pdf

    17/169

    From these calculations, they suggest assuming that a buried pipeline has an initial bending

    strain value between 0.02 to 0.04 percent.

    Internal pressures can cause a circumferential tensile stress due to the imbalance of

    interior and exterior pressures (Timeshenko 1951). The stresses induced by the soil cover (e.g.

    Carder et al. 1982; Carder and Taylor 1983) and static or cyclic loads (e.g. Pocock et al. 1980)

    can cause ovalling of the pipe cross section with attendant stresses that vary around the pipe.

    The installation of pipelines in the ground can create a stress or joint rotation from uneven

    bedding or a curved laying pattern (e.g. Pocock et al. 1980). Prior to an adjacent construction,

    the previous construction history may have resulted in movements of the pipeline causing

    bending stresses and joint rotations (e.g. Maynard and ORourke 1977). The environment in

    which the pipeline is buried can cause different stresses to be imposed. A pipeline installed in a

    location with fluctuations in temperature can cause strains in the pipeline (Attewell 1986).

    Moisture changes in the soil surrounding the pipeline can cause corrosion to occur which could

    weaken the strength of the pipe walls (e.g. Sears 1986).

    ANALYSIS OF PIPES

    Approach

    Pipelines parallel to deep excavations undergo deformations due to the displacement of

    the surrounding soil. For most utilities that parallel a large excavation in an urban environment,

    the pipeline can be assumed to move with the soil. Carder, et al. (1982) and Carder and Taylor

    (1983) conducted field experiments with 100 mm diameter cast iron pipelines buried 0.75 m

    deep parallel to trench excavations in different types of soil. They determined that the

    movements of the pipelines calculated from the data obtained from strain gauges along the

    pipeline were similar to that of the ground displacements observed. Nath (1983) conducted a

    6

  • 8/22/2019 Deep braced cuts utilities.pdf

    18/169

    three-dimensional finite element analysis on cast iron pipelines ranging from 75 to 450 mm in

    diameter buried 1 m deep parallel to open trench excavations of differing dimensions. He

    concluded that pipelines with diameters of 150 mm or less move with the ground providing little

    or no restraint to movements, whereas larger pipes provided some restraint against the movement

    of the surrounding soil.

    For pipelines whose movements are consistent with the displacements of the surrounding

    soil, one can make assumptions concerning joint flexibility to analyze the effects of ground

    movements on the pipe. By assuming a pipe is either flexible, wherein it is assumed a pipe

    connection does not affect the mechanical behavior of the pipe, or rigid, where all the movement

    is assumed to occur at a joint, one can bound the response of the pipe to the imposed

    deformations. The question becomes defining the critical condition, either excessive bending

    stresses for the flexible condition or large rotation at a joint for the rigid condition, possibly

    leading to excessive leakage or fracture at a joint. Special care should be taken when applying

    this approach to larger diameter metal pipelines because they tend to restrain movements more

    than that of small diameter pipelines, and the restraint provided by the pipe will result in higher

    stresses.

    Flexible pipe is assumed herein to move along with the ground causing bending within

    the pipe sections and no rotation at the joints. With the introduction of more ductile materials,

    bending stresses have become less of a concern; however, this is still of great concern for the old

    cast iron mains that can fail as a brittle fracture at a low strain, or in cases of pipes subjected to

    high pressures. The displacements of the pipe sections are assumed to be small allowing for

    axial displacements to be neglected. The deflection within a pipe is assumed to follow the

    Bernoulli-Navier theory of bending wherein the plane normal cross sections remain plane and

    7

  • 8/22/2019 Deep braced cuts utilities.pdf

    19/169

    perpendicular to the deflected centroidal axis and the transverse normal stresses are negligible

    (Baant and Cedolin, 1991).

    Rigid pipe is assumed herein to deform along with the ground displacement profiles as

    rigid links connected by points that are free to rotate. The effects of the ground movements on

    the pipe are concentrated in the joints as relative rotations between adjacent pipe sections. The

    pipe sections are assumed to have a large flexural rigidity thus preventing any curvature to

    develop. The joints are assumed to have no rotational rigidity allowing free rotation. The

    rotation at the joints is assumed to be longitudinal due to bending of the pipeline, therefore

    torsional behavior is neglected.

    Bending Stresses

    Flexible pipes exposed to ground movements develop bending stresses within the pipe

    sections. The bending stresses obtained from this analysis should be compared to established

    allowable values to determine the structural adequacy of the pipeline. If there are high internal

    pressures, a Mohr circle analysis should be made to find the maximum of the combined stresses.

    A displacement profile of the pipeline should be established within a convenient local

    coordinate system, as shown in Figure 1a. The origin is situated adjacent to the corner of the

    excavation, the positive x-axis represents the lateral movement towards the excavation, the

    positive y-axis is the longitudinal axis of the pipeline, and the positive z-axis is directed upwards.

    Following the assumption that the pipeline moves along with the ground, the lateral and vertical

    ground surface movements at the location of the pipeline determine the lateral and vertical

    displacement profiles of the pipeline.

    Bending is of greatest concern at the location of the displacement profiles where the

    curvature is the largest. The curvature is calculated at a point j from the lateral and vertical

    8

  • 8/22/2019 Deep braced cuts utilities.pdf

    20/169

    displacement profiles causing a differential movement of point j with respect to two adjacent

    points along the pipeline by the following equations:

    ( )( )

    ( )( )

    ( )ki

    ji

    ji

    kj

    kj

    ik

    ij

    ij

    jk

    jk

    jL

    LL2

    YY

    Y-YXX

    Y-YXX2

    )Y("x

    =

    =

    (1)

    ( )( )

    ( )( )

    ( )ki

    ji

    ji

    kj

    kj

    ik

    ij

    ij

    jk

    jk

    jL

    LL2

    YY

    Y-Y

    ZZ

    Y-Y

    ZZ2

    )Y("z

    =

    =

    (2)

    where ji= Xj-Xiis the differential lateral movement between points i and j (i,j = 1,2,3,..n), Lji=

    Yj-Yiis a characteristic length defined as the distance along pipe between points i and j, and ji=

    Zj-Ziis the differential settlement between points i and j. The displacements are defined in the

    local coordinate system as Xiand Zirepresenting the total lateral and vertical movements at point

    i, respectively, and Yiis defined as the distance from the origin along the pipeline to point i. In

    defining a characteristic length, Lji, for the curvature calculations, the distance should be large

    enough to reasonably reflect the curvature in the pipeline. A characteristic length of

    approximately 6.1 m or greater has shown to give an adequate representation of the curvature

    values for a pipeline undergoing bending.

    Treating the lateral and vertical profiles separately allows a simple three-dimensional

    analysis for determining the principal planes of the pipe cross sections. This provides a more

    accurate calculation of the maximum stresses along the pipeline than calculations from the

    resultant movements due to the continual change of the angle of the principal planes along the

    pipeline.

    For a pipe in bending there is a distribution of tensile and compressive stresses within the

    cross section. The maximum tensile stress existing in the pipe is critical due to the greater

    9

  • 8/22/2019 Deep braced cuts utilities.pdf

    21/169

    strength of many pipe materials in compression. The distribution of normal stresses, i, within

    the pipe cross section exposed to both lateral movements in the x-direction and vertical

    movements in the z-direction, assuming the pipeline behaves as an elastic beam, is found by:

    I

    zM

    I

    xMixiz

    i = (3)

    in which Mxand Mzare the moments around the x- and z-axis, respectively, with the x-axis

    horizontal and the z-axis is vertical, and I is the moment of inertia about the neutral axes of the

    cross section of the pipe. The terms xiand zi represent the distance to the most extreme fiber

    with respect to the moment. Substituting the expression for bending moment with small

    deflections, M=EIw", the equation for stress at a point i along the pipeline becomes:

    )(Yx"Ez)(Yz"Exiiiii

    = (4)

    where x"(Yi) and z"(Yi) are the curvatures of the lateral and vertical displacement profiles at

    point i, respectively. To express equation (4) in terms of the pipe radius, r, and the angle from

    the positive x-axis, one can write:

    [ ]iiiii

    )cos(Yx")sin(Yz"Er += (5)

    To calculate the maximum tensile stress within the cross section, this expression has to be

    maximized. By taking the derivative of the stress with respect , the expression for the angle of

    the principal plane can be found as:

    =

    )(Yx"

    )Y(z"tan

    i

    i1

    imax (6)

    The value of the maximum tensile stress is determined by substituting the results of (6) into (5).

    10

  • 8/22/2019 Deep braced cuts utilities.pdf

    22/169

    Joint Rotations

    It is assumed in this limiting case that rigid pipelines conform to the ground movements

    through rotations at the joints due to the infinite stiffness of the pipe sections. To determine if

    there is failure at a joint, the relative rotation between the two adjacent pipe sections needs to be

    calculated. Since the pipeline is assumed to follow the ground movements, the joints are located

    along the displacement profile at distances equal to the length of the pipe sections. The

    differential movements, as defined earlier, need to be determined to determine the change in

    slope along the pipeline at the joint.

    The rotation at a joint can be calculated using vector mechanics. The pipe sections can

    be represented as vectors that intersect at the joint. The angle between them can be calculated if

    the differential movements are known. Figure 1b shows the vector representation of two

    adjacent pipe sections along a pipeline that have undergone both lateral and vertical movements

    relative to joint j. The differential lateral and vertical displacements, jiand ji, are as previously

    defined for the bending stress analysis. The characteristic length, Lji, is defined by the pipe

    section length of the pipeline. The majority of cast iron mains consist of pies 3.6 m in length.

    Ductile iron pipe sections range in length of 5.5 to 6.1 m. If the pipe section length is unknown,

    a conservative assumption of 6.1 m should be used. This will yield the largest rotations because

    of the greater differential displacements. Using this established convention, the rotation at joint

    j, j, can be calculated using the following expression:

    ( ) ( )2kj

    2

    kj

    2

    kj

    2

    ji

    2

    ji

    2

    ji

    kjjikjjikjji1

    jcos

    ++++

    ++=

    LL

    LL (7)

    For buried pipelines, the locations of the joints may be unknown. In this case, in order to

    determine the maximum potential joint rotation along a pipeline, a joint should be assumed at

    11

  • 8/22/2019 Deep braced cuts utilities.pdf

    23/169

    one end of the displacement profile. Assuming small displacements, the next joint should be

    located on the displacement profile a distance of a pipe section length along the pipeline. The

    line connecting these two points represents the pipe section between these two points. This

    should be continued to the other end of the profile. Once the rotations are calculated, the same

    procedure should be repeated after offsetting the location of the first joint. Multiple analyses

    should be completed with the offset increasing until it is as long as the length of a pipe section.

    From these analyses, the maximum potential joint rotation can be determined.

    Allowable Stresses and Joint Rotations

    The failure of the pipeline from excavation-induced ground movements can occur from

    excessive bending stresses or large rotations at the joints. Stresses and rotations from preexisting

    conditions must be considered when allowable values for imposed stresses, ALLOW, and

    rotations, ALLOW, are established, for bending stresses and rotations, respectively. These

    allowable values are presented in Tables 3 and 4.

    For cast iron pipe, the failure in a pipe due to bending occurs as an abrupt brittle fracture.

    Attewell et al. (1986) recommend a maximum design stress for cast iron under direct tensile load

    equal to one-quarter of the ultimate tensile strength of the material. For cast iron exposed to

    bending, a rupture factor of 1.6 needs to be applied which results in a maximum design stress

    equal to 40 percent of the ultimate tensile strength of the material or a factor of safety of 2.5.

    For ductile iron in bending, which is a much more flexible material than cast iron, the

    Ductile Iron Pipe Research Association (2001) recommends using a factor of safety of 2.0 for

    calculations involving bending. Attewell, et al. (1986) recommend using a value of 85 percent of

    the minimum yield strength of the material since the failure of the material would not occur at

    12

  • 8/22/2019 Deep braced cuts utilities.pdf

    24/169

    the yield point, but when plastic yielding exists through the section. This definition corresponds

    to a safety factor of 1.2.

    Steel line pipe is usually the material used in the transportation of oil and gas under

    extremely high internal pressures. Under these conditions, a combined stress analysis should be

    used to determine an allowable design stress. For safety considerations, pipelines installed in

    urban environments generally are maintained at low internal pressures and a combined stress

    analysis is unnecessary. Steel pipe for these installations can be assumed to follow the ground

    movements behaving as a continuously supported beam. For laterally supported beams

    subjected to bending moments, the allowable stress can be calculated as 60 percent of the yield

    stress which is equivalent to a factor of safety of 1.67.

    Polyethylene pipe design strengths are established through an internal pressure analysis.

    The Plastics Pipe Institute (2000) recommends using a hydrostatic design basis value to

    determine a limiting strength for the pipe material. They recommend using a factor of safety of 2

    resulting in allowable hydrostatic design values for PE80 and PE100 grades as 4.3 MPa and 5.5

    MPa.

    Failure at a pipe joint can occur in the form of an excessive amount of leakage or a

    fracture of the pipe joint itself. These are critical behaviors for only cast iron and ductile iron

    pipelines since steel and plastic pipe joining procedures ensure joints that are of equivalent

    strength to that of the material. Experimental data have been obtained to determine rotations at

    which failure of a joint could occur.

    The majority of cast iron pipe installations are joined with lead-caulked joints. These

    semi-rigid joints allow some rotation because of the soft packing material, but failure can occur

    when the packing is forced from the joint resulting in excessive leakage. Fracture of the joint

    13

  • 8/22/2019 Deep braced cuts utilities.pdf

    25/169

    can occur when the rotation is large enough to cause metal-to-metal contact between the bell and

    the spigot inducing large bending stresses. Maynard and ORourke (1977) observed excessive

    leakage from a cast iron main exposed to ground movements with a joint rotation of 0.006

    radians (0.34 degrees). With the application of a safety factor of 1.25 to be conservative, this can

    define an allowable ground movement-induced rotation of approximately 0.0048 radians (0.275

    degrees).

    For rubber gasket joints for both cast iron and ductile iron the failure at the joint occurs as

    metal-to-metal contact. This rotation is dependent on the size of the pipe leading to different

    dimensions within the joint. Leakage is no longer a primary concern due to the flexibility of the

    rubber material to seal holes that could possibly form from movement at the joint. From

    observed conditions of cast iron and ductile iron mains with flexible joints following installation,

    Attewell, et al. (1986) suggest assuming an initial rotation within the joint up to 0.026 radians

    (1.5 degrees). This value is reflected in the allowable ground movement-induced rotations

    shown in Table 4.

    The majority of steel pipe is joined by welding with a minimal loss in strength along the

    pipeline from this method. Table 5 shows typical percentages for the reduction in strength for a

    steel pipe for different welds presented by Watkins and Anderson (2000). The greatest strength

    reduction of 25 percent of the strength of the steel is for single welded lap joints. This strength

    reduction should be applied to the design bending stress for the pipe material at the location of

    the joint for the bending stress analysis.

    The thermoplastic behavior of polyethylene allows for the material to be heated and

    reformed to another shape without losing strength. The fusing of two pipes by heat or

    electrofusion produces a joint with equal or greater strength of that of the material.

    14

  • 8/22/2019 Deep braced cuts utilities.pdf

    26/169

    PREDICTION OF EXCAVATION-INDUCED GROUND MOVEMENTS

    Semi-empirical methods have been developed for determining the values of maximum

    movement resulting from a deep braced excavation. For application of the stress analysis

    presented earlier, the distribution of the movements along the excavation are necessary for

    determining the displacement profile of the pipeline.

    A method for predicting the distributions of the lateral and vertical movements by the

    application of the complementary error function is presented by Roboski and Finno (2004).

    They determined that the ground movement distribution might be adequately represented with

    the following formula:

    =B

    Ax

    2

    11)x(

    maxerfc (8)

    where (x) is the settlement or lateral movement at distance x from the corner of the wall, maxis

    the maximum movement, A is the distance to the inflection point of the function to the corner of

    the wall, and B is an empirical shape factor. Positive values of settlement should be used and

    lateral movement should be considered positive towards the excavation. The value of A is

    determined from a relationship with the ratio of the depth of the excavation to the length of the

    wall, He/L. The value of B can be calculated from the value of A from the following expression:

    8.2

    A2

    L

    B

    = (9)

    A thorough explanation of the derivation and application of this procedure is presented by

    Roboski and Finno (2004).

    Summary of Procedure

    To determine the magnitudes of stresses and rotations in a pipeline caused by excavation-

    induced movements:

    15

  • 8/22/2019 Deep braced cuts utilities.pdf

    27/169

    1. Determine the maximum lateral ground movements from semi-empirical or detailed

    methods. Estimate the maximum vertical movement from the value of the lateral

    movement, and develop a proposed ground surface settlement profile at the pipeline

    location based on procedures summarized in the previous section.

    2. The stresses and rotations in the pipeline can be determined from the two limiting

    conditions. The pipeline is assumed flexible and a bending analysis is conducted to

    determine the maximum tensile stress occurring in the pipe. The pipeline is then

    assumed to behave rigidly, and a joint rotation analysis made to determine the largest

    possible rotation along the pipeline.

    3. The maximum tensile stress and joint rotation values should then be compared to the

    allowable values given in Tables 4 and 5, respectively. If the values predicted fall below

    the minimum allowable values, the pipeline should be safe under the imposed ground

    deformations.

    CASE STUDIES

    Lurie Center

    Construction of the Lurie Medical Research Center included a deep braced excavation in

    downtown Chicago. The dimensions of the excavation were approximately 82 m by 69 m by

    12.8 m deep. The support system for the excavation was a sheet pile wall with three levels of

    tiebacks. A more complete description of the project is reported in Finno and Roboski (2004).

    The area surrounding the Lurie Center site is heavily populated with underground utilities

    transmitting water, waste, gas, electric lines, and telecommunication cables. The analyses

    16

  • 8/22/2019 Deep braced cuts utilities.pdf

    28/169

    presented herein focuses on gas mains along the north, west, and south walls of the excavation.

    The locations of the instrumentation and gas mains with respect to the excavation are shown in

    Figure 2. The instrumentation around the site consisted of eight inclinometers, 150 surface

    points, and 18 embedded soil anchors, and 30 points on utilities. Detailed ground movement

    measurements were collected throughout the excavation process and ground movement

    distributions were computed from the data by a radial basis interpolation.

    The gas mains along the west and north walls of the excavation are old ductile iron mains

    with mechanical joints. The main along the west wall is a 500 mm diameter pipeline located 5.5

    m from the excavation wall. The main along the north wall is a 150 mm diameter pipeline

    located approximately 15.5 m from the north wall of the excavation. Along the south wall, there

    is a 300 mm diameter main approximately 8.1 m from the southern edge.

    The pipelines were assumed to move with the ground and provide no restraint against the

    soil. Therefore, it was assumed that the ground displacement profiles at the locations of the gas

    mains defined their movement. To support this assumption, comparisons were made between

    settlement readings taken from the survey points located directly on the gas mains and the

    approximated settlement profile at the pipeline location. Only the values for vertical movements

    were compared because lateral readings from the gas mains were unable to be obtained. Figure 3

    shows a comparison between the pattern of the pipeline determined from a survey point located

    directly on the pipeline and that of the observed ground surface movement above for the pipeline

    located along the west wall of the Lurie Center excavation. Excluding an initial offset of the

    observed ground movement, the displacement patterns are the same within the accuracy of the

    optical survey measurements. Because the pipe along the west wall had the largest diameter, the

    17

  • 8/22/2019 Deep braced cuts utilities.pdf

    29/169

    ground displacement profiles at the locations of the three gas mains can be then assumed to be

    the movements of the pipelines.

    Figure 4 shows the ground movements observed at the locations of the gas mains at the

    end of the excavation, where the maximum vertical and lateral movements were the greatest.

    This should correspond to the maximum stresses in the pipeline. Only settlement values only for

    the gas main to the north of the excavation are reported because the pipeline was located further

    from the excavation than the furthest row of lateral survey points.

    Assuming that the pipelines behave flexibly, a bending stress analysis was completed for

    the ground displacement profiles in Figure 4. Figure 5 shows the variation in time of the

    maximum tensile stress for the three gas mains throughout the excavation process. There is a

    gradual increase in the magnitude of the maximum tensile stress for all three gas mains. The

    magnitude of the maximum tensile stress for all mains at the completion of the excavation is

    representative of the maximum stress incurred for the duration of the construction. The

    maximum tensile stresses in the north, south, and west gas mains were 2.5, 10 and 25 MPa,

    respectively. For cast iron and ductile iron pipelines, these values are well below the allowable

    stress values of the pipe for design (Table 3). From the bending stress analysis, it can be

    concluded that no failure due to bending would occur in these gas mains due to the excavation.

    Assuming the gas mains adjacent to the Lurie Center excavation behave as rigid

    pipelines, an analysis on the relative rotation at the joints must be completed to determine if the

    rotations are within the allowable limits. The joints for the north and west gas mains are known

    to be mechanically bolted joints. The type of joint for the cast iron pipeline along the south wall

    is unknown.

    18

  • 8/22/2019 Deep braced cuts utilities.pdf

    30/169

    Figure 6 shows the maximum joint rotations for the north, south, and west gas mains for

    the time length of the construction for pipe section lengths of 3.6 m. As shown in Table 4, lead

    caulked joints began to show large amounts of leakage at rotations equaling 0.006 radians (0.34

    degrees). From Figure 6, it is apparent that the rotations in the joints from the ground

    movements for the north and west gas mains remained below the critical rotations for rubber

    gasket joints. The joint rotations for the south gas main, which was cast iron, reached critical

    magnitudes for lead caulked joints.

    A comparison of the maximum stress and joint rotations obtained from the ground

    movements computed as a radial basis interpolation and of pipe displacement on the error

    function model showed very similar results. Figure 7 shows the comparison of the predicted,

    calculated, and allowable maximum bending stresses and joint rotations values for the gas main

    along the west wall of the excavation, a 500 mm diameter ductile iron gas main with mechanical

    joints. The maximum calculated stress from the complementary error function-based ground

    movements for the final stages of the construction were within 8 MPa of those computed from

    the radial basis approximation using the observed ground movements. The joint rotation analysis

    yielded similar results. The joint rotations from the complementary error function-based ground

    movements differed from those computed as a radial basis function by approximately 2.5 x 10-3

    radians (0.14 degrees). Similar conclusions concerning the effects of the excavation on the

    pipelines at this site can be drawn when computing stresses and rotations with both methods.

    Chicago Excavation Case Studies

    Maynard and ORourke (1977) present ground surface movement data for different

    braced excavations in Chicago where cast iron pipelines were impacted by the effects of

    excavations. Table 6 presents the information for the four cast iron mains and their approximate

    19

  • 8/22/2019 Deep braced cuts utilities.pdf

    31/169

    maximum movements. The ground movements were observed within a distance of

    approximately 3 m behind the pipeline to eliminate the effects of the edge of the trench on the

    data. This produced ground movement data representative of the movement of the pipelines.

    The displacement profiles for the four pipelines show the maximum movements

    occurring near the center of the excavation with large curvatures at the edge. From a bending

    stress analysis, assuming a modulus of elasticity of 100 MPa and negligible change in rotation of

    the principal planes, the largest stresses occurred at the edge of the excavation where the largest

    curvatures were located. The characteristic length for determining the curvatures for each

    pipeline was taken as the distance between the data points along that pipeline. The distances for

    the four mains ranged from 7.6 to 15.2 m, which is a reasonable characteristic length for the

    calculation of curvature being that they are greater than 5.5 m, which was determined to be the

    lower bound. For two of the pipelines the maximum calculated bending stresses proved to be

    greater than the minimum value of allowable bending stress from excavation-induced ground

    movements for cast iron presented in Table 3. However, there was no evidence of fracture of the

    pipes due to excessive bending showing the conservativeness of the bending stress analysis.

    For an analysis of the rotations at the joints along the pipelines, it was assumed that the

    joints were located at the data points. Since only the total vector movement data was available,

    the relative rotations could be calculated from the changes in slope of the displacement profiles.

    Figure 8 shows the rotations calculated at the data points. The open symbols represent

    mechanical joints and the filled symbols denote lead caulked joints.

    For the two mains joined by lead caulked joints, the 300 mm diameter pipeline showed

    the largest relative rotation at a joint of 6 x 10-3

    radians (0.34 degrees) at which leakage at the

    joints was observed and was taken out of service. The mains equipped with mechanical joints

    20

  • 8/22/2019 Deep braced cuts utilities.pdf

    32/169

    experienced a maximum rotation of 8 x 10-3

    radians (0.46 degrees). This rotation is greater than

    that observed to cause failure at a lead caulked joint, however, for mechanical joints it is within

    the allowable limits of 0.044 radians (2.5 degrees). Both pipelines joined with mechanical joints

    experienced larger relative rotations yet from observations they did not show excessive leakage,

    illustrating the benefits of the more flexible joints.

    CONCLUSIONS

    Based on the analyses presented herein and the data obtained at several deep excavations

    in Chicago, the following conclusions can be made.

    1. From comparison of ground displacements interpolated from collected

    data and field observed movements of buried utilities, it was shown that the

    pipeline tracked the movement of the surrounding soil within the accuracy of the

    optical survey data. For computation of bending stresses and joint rotations

    induced in pipelines from ground movements related to a deep braced excavation,

    the pipeline displacement profile may be assumed to be that of the displacement

    of the surrounding soil when the displacement in the pipe is small in relation to

    the length of the pipeline, i.e. sin . When utilizing this assumption, special

    consideration of construction activity, differential soil behavior, and local effects

    must be taken into account.

    2. A methodology was presented for computing the longitudinal bending

    stresses and joint rotations induced in a pipeline from an adjacent deep braced

    excavation. The validity of the method for calculating the bending stresses and

    joint rotations is illustrated by comparisons of calculated ground movement

    21

  • 8/22/2019 Deep braced cuts utilities.pdf

    33/169

    values and direct observations made in the field for the Lurie Center excavation

    and the various Chicago excavations presented by Maynard and ORourke (1977).

    The method proved to be conservative for both bending stress and joint rotation

    analysis.

    3. The more critical condition for a cast iron or ductile iron main considered

    herein is excessive rotation at a joint. The bending stress analysis on the ground

    movements presented by Maynard and ORourke (1977) showed large

    longitudinal tensile stresses with no observed cracking or rupture. The small

    calculated joint rotation of 6 x 10

    -3

    radians (0.34 degrees) proved to cause

    excessive leakage in a lead caulked joint.

    22

  • 8/22/2019 Deep braced cuts utilities.pdf

    34/169

    REFERENCES

    Ahmed, I. (1990). Pipeline Response to Excavation-Induced Ground Movements. PhD thesis,

    Department of Civil and Environmental Engineering, Cornell University, Ithaca, NY.

    American Petroleum Institute. (1991). Specification for Line Pipe, 39th

    Ed. American Petroleum

    Institute, Washington, DC.

    Attewell, P.B., Yeates J., and Selby, A. R. (1986). Soil Movements Induced by Tunneling and

    Their Effects on Pipelines and Structures. Blackie and Son, Ltd., London.

    Bonds, R. W. (2003).Ductile Iron Pipe Joint and Their Uses. Ductile Iron Pipe Research

    Association, Birmingham, AL.

    Carder, D. R., Taylor, M. E., and Pocock, R. G. (1982). Response of a Pipeline to Ground

    Movements Caused by Trenching in Compressible Alluvium.Department of the

    Environment Department of Transport, TRRL Report LR 1047, Transport and Road

    Research Laboratory, Crowthorne.

    Carder, D. R. and Taylor, M. E. (1983). Response of a Pipeline to Nearby Trenching in Boulder

    Clay.Department of the Environment Department of Transport, TRRL Report LR 1099,

    Transport and Road Research Laboratory, Crowthorne.

    Clough, G. W. and ORourke, T. D. (1990). Construction Induced Movements of In-Situ

    Walls.Design and Performance of Earth Retaining Structures, Proceedings of a

    Specialty Conference at Cornell University, ASCE, New York, 439-470.

    Croft, J. E., Menzies, B. K., and Tarzi, A. I. (1977). Lateral Displacement of Shallow Buried

    Pipelines due to Adjacent Deep Trench Excavations. Geotechnique, 27(2), 161-179.

    Finno, R. J., and Roboski, J. F. (2004). Three-Dimensional Responses to a Tied-back

    Excavation Through Clay.

    23

  • 8/22/2019 Deep braced cuts utilities.pdf

    35/169

    Hsieh, P. G. and Ou, C. Y. (1998). Shape of Ground Surface Settlement Profiles Caused by

    Excavation. Canadian Geotechnical Journal, 35, 1004-1017.

    Maynard, T. R. and ORourke, T. D. (1977). Soil Movement Effect on Adjacent Public

    Facilities. Preprint No. 3111, ASCE Annual Meeting, San Francisco, CA.

    Nath, P. (1983). Trench Excavation Effects on Adjacent Buried Pipes: Finite Element Study.

    Journal of Geotechnical Engineering, ASCE, New York, NY, 109(11), 1399-1415.

    Plastics Pipe Institute. (1993). Engineering Properties of Polyethylene. PPI Handbook of

    Polyethylene Piping, Plastics Pipe Institute, Washington, DC.

    Plastics Pipe Institute. (2003). Specifications, Test Methods and Codes for Polyethylene Piping

    Systems. PPI Handbook of Polyethylene Piping, Plastics Pipe Institute, Washingtion,

    DC.

    Plastics Pipe Institute. (2000).Model Specification for Polyethylene Plastic Pipe, Tubing and

    Fittings for Water Mains and Distribution. Plastics Pipe Institute, Washington, DC.

    Roboski, J. F., and Finno, R. J. (2004). Distributions of Ground Movements Parallel to a Deep

    Excavation.

    Salmon, C. G., and Johnson, J. E. (1996). Steel Structures: Design and Behavior, Emphasizing

    Load and Resistance Factor Design, 4th

    Ed. HarperCollins College Publishers, New

    York, NY.

    Sears, E.C. (1968). Comparison of the Soil Corrosion Resistance of Ductile Iron Pipe and Gray

    Cast Iron Pipe.Materials Protection, 7(10), 33-36.

    Tarzi, A. I., Menzies, B. K., and Crofts, J. E. (1979). Bending of Jointed Pipelines in Laterally

    Deforming Soils. Geotechnique, 29(2), 203-206.

    24

  • 8/22/2019 Deep braced cuts utilities.pdf

    36/169

    Timoshenko, S. and Goodier, J. N. (1951). Theory of Elasticity. McGraw-Hill Book Company,

    Inc., New York, NY.

    Untrauer, R. E., Lee, T. T., Sanders, Jr., W. W., and Jawad, M. H. (1970). Design Requirements

    for Cast Iron Soil Pipe.Bulletin 199, Engineering Research Institute, Iowa State

    University, Ames, IA.

    Watkins, R. K. and Anderson, L. R. (2000). Structural Mechanics of Buried Pipes, CRC Press,

    New York, NY.

    25

  • 8/22/2019 Deep braced cuts utilities.pdf

    37/169

    Tables

    Pipe Material

    207 20Centrifugally Cast Iron

    300 420Ductile Iron

    207Steel Grade A

    241Steel Grade B

    0.28

    0.29

    Poisson's

    Ratio

    Coeff. of

    Thermal Exp.(per C)

    Vertically Pit Cast Iron 0.26

    114 14

    166-180

    200

    200

    Modulus of

    Elasticity(GPa)

    83 14

    15-18 31Polyethylene PE80 0.42552-758

    414Steel Grade 414 200

    21-24 31Polyethylene PE100 0.42758-1103

    145 20 11 x 10-6

    0.26 11 x 10-6

    11 x 10-6

    0.29

    0.29

    12 x 10-6

    12 x 10-6

    12 x 10-6

    2 x 10-6

    2 x 10-6

    Reference

    Ahmed (1990)

    DIPRA (2001)

    API (1991)

    API (1991)

    Ahmed (1990)

    PPI (2003)

    API (1991)

    PPI (2003)

    331

    413

    517

    Yield

    Stress, Fy(MPa)

    Ultimate

    Stress, Fu(MPa)

    Table 1 Engineering Properties for Piping Materials

    26

  • 8/22/2019 Deep braced cuts utilities.pdf

    38/169

    Material

    Cast Iron

    Ductile Iron

    Limiting Rotation

    Leakage, rad. (deg.) Failure, rad. (deg.)

    0.09-0.1 (5-6)

    0.07-0.09 (4-5)

    0.07 (4)

    0.05-0.09 (3-5)

    0.03-0.14 (2-8)

    0.26 (15)

    Reference

    See Note 1

    Attewell, et al. (1986)

    Attewell, et al. (1986)

    Bonds (2003)

    Bonds (2003)

    Bonds (2003)

    0.0094-0.017 (0.54-1.0)

    Joint

    Lead-Caulked

    Rubber-Gasket

    Mechanical

    Rubber-Gasket

    Mechanical

    Ball and Socket

    Note 1: Adapted from Untreaur, et al. (1970), O'Rourke and Trautmann (1980), Harris and O'Rourke (1983), andAttewell, et al. (1986)

    Table 2 Failure Rotations for Selected Cast Iron and Ductile Iron Joints

    27

  • 8/22/2019 Deep braced cuts utilities.pdf

    39/169

    Pipe Material

    Pit Cast Iron

    Spun Cast Iron

    Ductile Iron

    Grade A Steel

    Grade B Steel

    YieldStrength

    (Fy), MPa

    UltimateStrength

    (Fu), MPa---

    ---

    300

    207

    241

    145

    207

    420

    331

    414

    Grade 414 Steel

    PE80

    414

    ---

    517

    8.6

    PE100 --- 11

    Initial Stress(INITIAL),

    MPa13.8 - 38.6

    20.7 - 52.4

    33.1 - 71.7

    41.4 - 82.8

    41.4 - 82.8

    41.4 - 82.8

    0.13 - 0.26

    0.28 - 0.56

    Factorof

    Safety2.5

    2.5

    1.67

    1.67

    1.67

    2.0

    2.0

    Design BendingStress (B), MPa

    0.4Fu

    0.4Fu

    0.8Fu

    0.6Fy

    0.6Fy

    0.6Fy

    0.5HDB

    0.5HDB

    58

    82.8

    124.2

    144.6

    248.4

    4.3

    5.5

    Allowable Stress(ALLOW), MPa

    19.3 - 44.1

    30.3 - 62.1

    41.4 - 82.8

    62.1 - 103.4

    165.4 - 206.8

    4.04 - 4.17

    4.94 - 5.22

    12

    Adapted from Taki and O'Rourke (1984) assumed initial longitudinal bending strain of 0.02 to 0.04%1

    Allowable bending stress from excavation-induced ground movement = ALLOW= B- INITIAL2

    Polyethylene designed for internal pressure. Allowable values expressed as Hydrostatic Design Basis (HDB).3

    3

    1.2 336 264.3 - 302.9

    Table 3 Allowable Bending Stresses from Excavation-Induced Movements

    28

  • 8/22/2019 Deep braced cuts utilities.pdf

    40/169

    Mode ofFailure

    Leakage Lead-Caulked

    Rubber-Gasket Push-on

    Mechanical

    Rubber-Gasket Push-on

    Mechanical

    Joint Type

    MetalBinding

    (metal-to-metal

    contact)

    Failure Rotations

    Radians Degrees

    0.0094 - 0.016 0.54 - 0.92

    4 - 5

    4

    3 - 5

    2 - 8

    Ball and Socket 12.5 - 15

    Lead Caulked 5 - 60.09 - 1.0

    0.07 - 0.09

    0.07

    0.05 - 0.09

    0.035 - 0.14

    0.22 - 0.26

    Allowable Rotations, ALLOWRadians Degrees

    2.5 - 3.5

    2.5

    1.5 - 3.5

    0.5 - 6.5

    11 - 13.5

    3.5 - 4.50.06 - 0.08

    0.044 - 0.06

    0.044

    0.026 - 0.06

    0.009 - 0.11

    0.19 - 0.24

    1

    2 3

    1

    Observed from laboratory tests to cause excessive leakage.2

    Observed from field data to cause excessive leakage (initial rotation already occurred).3

    Material

    Cast Iron

    Ductile Iron

    ALLOWrepresents allowable excavation-induced rotation with assumed 0.026 rad. (1.5 deg.) initial rotation (Attewell, etal., 1986) for flexible joints, ALLOW= METAL BINDING- INITIAL. ALLOW=LEAKAGE/F.S. for lead caulked joints where F.S. = 1.25.

    0.0048 0.275

    Table 4 Allowable Joint Rotations for Cast Iron and Ductile Iron Joints

    29

  • 8/22/2019 Deep braced cuts utilities.pdf

    41/169

    Butt Welded Joint

    Single Welded Lap Joint

    Double-Welded Lap Joint

    1

    2

    For a full-penetration weld through thickness of pipe.1

    For a gap smaller than 3.2 mm.2

    Welded JointPercentStrength

    Reduction

    0

    25

    20

    Table 5 Strength Reductions at Location of Line Pipe Welded Joints

    (Watkins and Anderson, 2000)

    30

  • 8/22/2019 Deep braced cuts utilities.pdf

    42/169

    Water Main

    Lead-Caulked

    Lead-Caulked

    Mechanical

    MechanicalGas Main

    1938

    pre-1900

    1960

    1935

    300

    1200

    900

    150

    2.1

    2.3

    1.7

    1.4

    207

    310.5

    207-276

    1.75

    WL-1

    WL-2

    WM-1

    GM-1

    Diameter

    (mm)

    Depth

    (m)

    InternalPressure

    (kPa)

    Main Type Year Joints Symbol

    Table 6 Description of Cast Iron Pipelines Parallel to Chicago Excavations

    (Maynard and ORourke, 1977)

    31

  • 8/22/2019 Deep braced cuts utilities.pdf

    43/169

    Figures

    Figure 1 Coordinates for Bending and Joint Rotation Analyses

    z

    x

    y

    i j

    k

    ji

    kj

    Lji

    L kjji kjj

    z

    x

    y

    i j

    k

    ji

    kj

    Lji

    L kjji kj

    b. Rotation

    a. Bending

    32

  • 8/22/2019 Deep braced cuts utilities.pdf

    44/169

    Figure 2 General Layout of Lurie Center Site Instrumentation andAdjacent Gas Mains

    N

    Gas Main

    Inclinometer

    Surface Point

    Soil AnchorUtility Point

    LEGEND

    LURIE MEDICAL RESEARCHCENTER EXCAVATION

    E. Superior St.

    N.

    FairbanksCt.

    E. Huron St.

    Existing Pedestrian Tunnel

    0 2 4 8Scale in meters

    PrenticeWomen's

    Hospital

    33

  • 8/22/2019 Deep braced cuts utilities.pdf

    45/169

    0

    10

    20

    30

    40

    50

    60

    0 50 100 150 200 250 300

    Days from Completion of Sheet Pile Wall Installation

    Settlement(mm)

    Ground Surface Settlement from Contours Survey Data from Pipe

    Figure 3 Comparison of Ground and Pipeline Movement during Excavation at Lurie Center

    34

  • 8/22/2019 Deep braced cuts utilities.pdf

    46/169

    0

    10

    20

    30

    40

    50

    60

    70

    80

    -20 0 20 40 60 80 100

    Distance from Corner of Excavation (m)

    Settlemen

    t(mm)

    North South West

    0

    1020

    30

    40

    50

    60

    70

    80

    90

    -20 0 20 40 60 80 100

    Distance from Corner of Excavation (m)

    Later

    alMovement(mm)

    South West

    Figure 4 Ground Displacements at Location of Gas Mains along North, South, and

    West Walls after Completion of Excavation

    35

  • 8/22/2019 Deep braced cuts utilities.pdf

    47/169

    0

    5

    10

    15

    20

    25

    30

    0 50 100 150 200 250 300

    Days from Completion of Sheet Pile Wall Installation

    Max.TensileStress(Mpa)

    North Pipeline South Pipeline West Pipeline

    Figure 5 Maximum Tensile Stress in Pipelines Adjacent to North, South, and West WallDuring Excavation

    36

  • 8/22/2019 Deep braced cuts utilities.pdf

    48/169

    0

    1

    2

    3

    4

    5

    6

    7

    0 50 100 150 200 250 300

    Days from Completion of Sheet Pile Wall Installation

    Rotation(x

    10-3rad.)

    North Pipeline South Pipeline West Pipeline

    Allowable Rotation Failure Rotation

    Figure 6 Maximum Relative Rotation Encountered Along North, South, and West Pipelines

    During Excavation for 3.6 m Pipe Sections

    37

  • 8/22/2019 Deep braced cuts utilities.pdf

    49/169

    0

    50

    100

    150

    200

    250

    300

    100 150 200 250 300

    Days of Construction of Sheet Pile Wall Installation

    TensileStress(MPa)

    Radial Basis Error Function Maximum Allowable Stress

    a) Maximum Tensile Bending Stresses

    0

    5

    10

    15

    20

    25

    30

    100 150 200 250 300

    Days from Completion of Sheet Pile Wall Installation

    Rotation(x10-3

    rad.)

    Radial Basis Error Function Maximum Allowable Rotation

    b) Maximum Joint Rotations

    Figure 7 Observed and Predicted Maximum Bending Stresses and Joint Rotations for Final

    Stages of Construction for Gas Main Along West Wall

    38

  • 8/22/2019 Deep braced cuts utilities.pdf

    50/169

    0

    1

    2

    3

    4

    5

    6

    7

    8

    9

    -5 0 5 10 15 20 25 30 35 40 45 50

    Distance from Corner of Excavation (m)

    Rotation(10-3 rad.)

    WL-1 WL-2 WM-1 GM-1

    Note: Leakage Observed in WL-1.

    Figure 8 Rotations in Cast Iron Pipelines Adjacent to Excavations in Chicago

    39

  • 8/22/2019 Deep braced cuts utilities.pdf

    51/169

    APPENDIX A: LURIE CENTER DATA

    TABLE OF CONTENTS

    Table of Contents 40

    List of Tables 42

    List of Figures 44

    A.1 Introduction 48

    A.2 Pipeline and Material Properties 49

    A.2.1 Cast Iron 49A.2.2 Ductile Iron 55

    A.2.3 Steel 57A.2.4 Polyethylene 60

    A.3 Case Study: Lurie Medical Research Center 63

    A.3.1 Ground Movements due to Excavation 64A.3.2 Ground Movements at Locations of Gas Mains 66

    A.3.3 Ground Movement and Pipeline Movement Comparison 69

    A.4 Stress Conditions on Buried Pipelines 73A.4.1 Initial Stresses 73

    A.4.1.1 Hoop Stress 74

    A.4.1.2 Ring Stresses from Soil Cover 75A.4.1.3 Traffic Loads 81

    A.4.1.4 Stresses from the Installation Procedure and Adjacent

    Construction History 83A.4.1.5 Environmental Effects 84

    A.4.2 Analysis of Effects of Ground Movements from Adjacent

    Excavations on Pipeline 87

    A.4.2.1 Soil Pipeline Interaction 90A.4.2.2 Sign Convention and Definition of Terms 91

    A.4.2.3 Calculation of Bending Stress for Flexible Pipeline 92

    A.4.2.4 Calculation of Relative Rotation at Joint for RigidPipeline 98

    A.5 Summary 104

    A.6 Conclusions 108

    40

  • 8/22/2019 Deep braced cuts utilities.pdf

    52/169

    References 111

    Tables 115

    Figures 126

    41

  • 8/22/2019 Deep braced cuts utilities.pdf

    53/169

    LIST OF TABLES

    Table A-1 Tensile Strength and Stress-Strain Properties for Cast Iron 115

    Table A-2 Typical Dimensions for Lead Caulked Joints 115

    Table A-3 Typical Dimensions for Flexible Joints for Cast Iron Pipe 116

    Table A-4 Experimental Results for Rotation at Leakage for Lead Caulked

    Cast Iron Pipe Joints 116

    Table A-5 Tensile Strength and Stress-Strain Properties for Ductile Iron 117

    Table A-6 Typical Dimensions for Flexible Joints for Ductile Iron Pipe 117

    Table A-7 Strength Reductions at Location of Welded Line Pipe Joints 118

    Table A-8 Typical Mechanical Properties for Polyethylene Gas Distribution

    Pipe 118

    Table A-9 Locations of Underground Utilities with Respect to Lurie Center

    Excavation 119

    Table A-10 Definitions of Stages of Construction 119

    Table A-11 Magnitudes of Maximum Ground Movements Surrounding Lurie

    Center Excavation 120

    Table A-12 Magnitudes of Maximum Ground Movements at Locations of

    Gas Mains Adjacent to Lurie Center Excavation 120

    Table A-13 Locations of Utility Survey Points with Respect to Nearest Corner

    of Excavation 121

    Table A-14 Sample Hoop Stress Calculations for Gas Mains Adjacent to

    Lurie Center Excavation 121

    Table A-15 Overpressure Stresses for Gas Mains Adjacent to Lurie CenterExcavation 122

    Table A-16 Allowable Bending Stresses from Excavation-InducedMovements 123

    42

  • 8/22/2019 Deep braced cuts utilities.pdf

    54/169

    Table A-17 Allowable Excavation-Induced Joint Rotations for Semi-Rigid

    and Flexible Cast Iron and Ductile Iron Joints 123

    Table A-18 Typical Engineering Properties for Piping Materials 124

    Table A-19 Dimensions and Maximum Tensile Stress Values in Gas Mains

    Adjacent to Lurie Center at End of Excavation 124

    Table A-20 Dimensions and Maximum Joint Rotation in Gas Mains Adjacent

    to Lurie Center at End of Excavation 125

    43

  • 8/22/2019 Deep braced cuts utilities.pdf

    55/169

    LIST OF FIGURES

    Figure A-1 Typical Stress-Strain Curves for Cast Iron 126

    Figure A-2 Typical Lead Caulked Cast Iron Joint 126

    Figure A-3 Typical Flexible Iron Joints 127

    Figure A-4 Stress-Strain for Cast Iron and Ductile Iron 127

    Figure A-5 Rotational Stiffness of Ductile Iron Rubber Gasket Joint 128

    Figure A-6 Typical Joint Welds for Line Pipe 128

    Figure A-7 Stress-Strain Curve for Polyethylene Under Controlled

    Conditions 129

    Figure A-8 Typical Joining Methods for Polyethylene Pipe 129

    Figure A-9 General Layout of Lurie Center Site Instrumentation and

    Adjacent Underground Utilities 130

    Figure A-10 Vertical Ground Movements Along North Wall on Day 146 131

    Figure A-11 Lateral Ground Movements Along North Wall on Day 146 131

    Figure A-12 Vertical Ground Movements Along North Wall on Day 192 132

    Figure A-13 Lateral Ground Movements Along North Wall on Day 192 132

    Figure A-14 Vertical Ground Movements Along North Wall at End of 133

    Excavation

    Figure A-15 Lateral Ground Movements Along North Wall at End of 133

    Excavation

    Figure A-16 Vertical Ground Movements Along South Wall on Day 157 134

    Figure A-17 Lateral Ground Movements Along South Wall on Day 157 134

    Figure A-18 Vertical Ground Movements Along South Wall on Day 203 135

    Figure A-19 Lateral Ground Movements Along South Wall on Day 203 135

    44

  • 8/22/2019 Deep braced cuts utilities.pdf

    56/169

    Figure A-20 Vertical Ground Movements Along South Wall at End of 136

    Excavation

    Figure A-21 Lateral Ground Movements Along South Wall at End of 136

    Excavation

    Figure A-22 Vertical Ground Movements Along West Wall on Day 146 137

    Figure A-23 Lateral Ground Movements Along West Wall on Day 146 137

    Figure A-24 Vertical Ground Movements Along West Wall on Day 185 138

    Figure A-25 Lateral Ground Movements Along West Wall on Day 185 138

    Figure A-26 Vertical Ground Movements Along West Wall at End of 139Excavation

    Figure A-27 Lateral Ground Movements Along West Wall at End of 139Excavation

    Figure A-28 Maximum Magnitude of Vertical Movement During Excavation

    at Location of Gas Main Adjacent to North Wall 140

    Figure A-29 Maximum Magnitudes of Movements During Excavation at

    Location of Gas Main Adjacent to South Wall 140

    Figure A-30 Maximum Magnitudes of Movements During Excavation atLocation of Gas Main Adjacent to West Wall 141

    Figure A-31 Re-zeroed Settlement Values Along North Gas Main atCompletion of Excavation 141

    Figure A-32 Re-zeroed Settlement Values Along South Gas Main atCompletion of Excavation 142

    Figure A-33 Re-zeroed Settlement Values Along West Gas Main atCompletion of Excavation 142

    Figure A-34 Comparison of Utility Survey Point U-1 Movement with

    Approximated Ground Movement Values 143

    Figure A-35 Comparison of Utility Survey Point U-2 Movement with

    Approximated Ground Movement Values 143

    Figure A-36 Comparison of Utility Survey Point U-3 Movement with

    Approximated Ground Movement Values 144

    45

  • 8/22/2019 Deep braced cuts utilities.pdf

    57/169

    Figure A-37 Comparison of Utility Survey Point U-4 Movement withApproximated Ground Movement Values 144

    Figure A-38 Comparison of Utility Survey Point U-5 Movement with

    Approximated Ground Movement Values 145

    Figure A-39 Comparison of Utility Survey Point U-6 Movement with

    Approximated Ground Movement Values 145

    Figure A-40 Free-Body Diagram of Forces Resulting from Internal Pressure 146

    Figure A-41 Sign Convention for Thrust, Moment, Displacement, and Stress

    Equations 146

    Figure A-42 Local Coordinate System Convention for Pipeline Analysis 147

    Figure A-43 Definitions of Dimensions and Differential Ground MovementDesignations 147

    Figure A-44 Pipeline Profiles with Established Local Coordinate System for

    Analysis of Bending Stress for Flexible Pipeline 148

    Figure A-45 Pipe Cross Section and Sign Convention 148

    Figure A-46 Comparison of Characteristic Lengths of 6.1, 9.2, and 15.3 m for

    Stress Analysis Along Gas Main Adjacent to North Wall DuringExcavation 149

    Figure A-47 Comparison of Characteristic Lengths of 6.1, 9.2, and 15.3 m forStress Analysis Along Gas Main Adjacent to South Wall During

    Excavation 149

    Figure A-48 Comparison of Characteristic Lengths of 6.1, 9.2, and 15.3 m for

    Stress Analysis Along Gas Main Adjacent to West Wall During

    Excavation 150

    Figure A-49 Maximum Tensile Stress in Pipelines Adjacent to North, South,

    and West Walls During Excavation 150

    Figure A-50 Maximum Tensile Stress Along North Gas Main at Completion

    of the Excavation 151

    Figure A-51 Maximum Tensile Stress Along South Gas Main at Completion

    of the Excavation 151

    46

  • 8/22/2019 Deep braced cuts utilities.pdf

    58/169

    Figure A-52 Maximum Tensile Stress Along West Gas Main at the Completion

    of the Excavation 152

    Figure A-53 Pipeline Profiles with Established Local Coordinate System for

    Analysis of Joint Rotations for Rigid Pipeline 152

    Figure A-54 Schematic of Joint Rotation at Joint j of Rigid Pipeline 153

    Figure A-55 Maximum Relative Rotation Encountered Along North, South,and West Pipelines During Excavation for 3.6 m Pipe Sections 153

    Figure A-56 Comparison of Maximum Relative Rotation in North Gas Mainfor 3.6 and 6.1 m Pipe Sections 154

    Figure A-57 Comparison of Maximum Relative Rotation in South Gas Mainfor 3.6 and 6.1 m Pipe Sections 154

    Figure A-58 Comparison of Maximum Relative Rotation in West Gas Mainfor 3.6 and 6.1 m Pipe Sections 155

    Figure A-59 Joint Rotations and Pipeline Settlement Along Pipeline Adjacent

    to North Wall at Completion of Excavation 156

    Figure A-60 Joint Rotations and Pipeline Settlement Along Pipeline Adjacent

    to South Wall at Completion of Excavation 157

    Figure A-61 Joint Rotations and Pipeline Settlement Along Pipeline Adjacentto West Wall at Completion of Excavation 158

    47

  • 8/22/2019 Deep braced cuts utilities.pdf

    59/169

    A.1 Introduction

    Within urban environments, buried pipelines may be exposed to large ground movements

    either by tunneling, mining, or open cut constructions, such as trenching or deep braced

    excavations. These large ground movements can induce deformations in pipelines resulting in

    stresses within the pipeline. These stresses, if excessive, could result in damage or complete

    failure of the pipeline.

    Failure in a pipeline due to excavation-induced ground movements could be caused by

    large bending stresses in the pipe or relative rotations between two adjacent pipe sections at a

    joint. Large bending strains in a pipe and rotations in a joint are the result of significant

    differential movements along the pipeline. This mainly occurs near the edge of an excavation

    due to the transition of the pipeline from being restrained to it being free to move with the

    ground.

    A conservative analysis of the effects of the ground movements from deep braced

    excavations is presented. The analysis considers two different methods of deformation

    separately, either curvature in the pipe or rotation at the joints. The displacements along the

    pipeline are used to calculate the maximum stresses and rotation imposed on the pipeline. These

    values can be compared to established allowable values to determine whether the pipeline could

    be damaged or remain safe and in operation.

    This analysis is presented and applied to two case studies where data was obtained from

    excavations in downtown Chicago. Maximum calculated values are computed and compared to

    the allowable values established from previous experimental and empirical studies. Conclusions

    are drawn for the stresses that were imposed on the pipeline due solely to the ground movements

    resulting from the deep braced excavations.

    48

  • 8/22/2019 Deep braced cuts utilities.pdf

    60/169

    A.2 Pipeline Material and Properties

    Four different materials used in pipeline engineering will be discussed; cast iron, ductile

    iron, steel, and polyethylene. An overview of the manufacturing methods, engineering

    properties, stress-strain behavior, standard dimensions, and joining methods for all four pipeline

    materials will be presented and compared.

    A.2.1 Cast Iron

    Many cast iron gas pipelines in use today have been in operation for over 100 years. The

    initial growth of the use of gray cast iron pipe in the pipeline industry in the United States

    occurred around 1816. Foundries for production of cast iron specifically in the form of pipe

    began in the eastern states and spread quickly westward. The metallurgic composition of cast

    iron is an alloy of iron and carbon with a percentage of silicon and manganese. The carbon

    exists in the form of graphite flakes and gives the material much of its strength.

    Two main manufacturing methods were used in the production of cast iron pipe: pit

    casting and centrifugally, or spin, casting. The majority of cast iron pipes installed during the

    duration for which cast iron was the main piping material were pit cast. This was due to the late

    introduction of centrifugal casting in the 1920s. In the pit casting process, the molten mixture of

    metals was poured into either a horizontal or vertical mold and allowed to set in place as it

    cooled. Vertical pit casting was the preferred method of manufacturing due to the longer

    sections of pipe that could be cast. Horizontal casting was limited by the flexural rigidity of the

    mold core where bending of the core could cause inconsistent wall thickness along the length of

    the pipe. Vertical pit casting increased the length of pipe sections available from 1.2 to 1.5 m to

    49

  • 8/22/2019 Deep braced cuts utilities.pdf

    61/169

    lengths of up to 3.6 m, in turn decreasing the amount of joints necessary. Both horizontal and

    vertical pit cast pipe was available in a range of diameters from 75 to 1500 mm.

    In the 1920s, the process of centrifugally casting gray cast iron pipe was introduced and

    became the primary manufacturing method of cast iron pipe by the early 1930s. This procedure

    involved the pouring of the molten material into a horizontal spinning mold. The rate of rotation

    of the mold was controlled to obtain the desired thickness of the pipe. The centrifugal forces

    generated by the spinning produced a material with a much more consistent cross section and

    even distribution of impurities within the pipe section. The graphite flakes characterizing the

    strength of the pipe were more evenly distributed to produce a much stronger and more

    consistent material. Cast iron pipe was available in pipe sections 3.6 to 6.1 m in length and in

    sizes ranging from 75 to 1200 mm diameter.

    The stress-strain behavior of cast iron exhibits a brittle behavior with no yield point and

    an abrupt fracture at failure. Under an applied stress there exists no completely elastic behavior

    for any stress value. Cast iron undergoes an amount of plastic strain under the application of an

    increment of load. The total strain at all stress values is composed of both elastic and plastic

    components. The elastic strain behavior is characterized by a curve of recoverable strain, which

    does not agree with the traditional straight-line path of linear elastic materials. Therefore, the

    definition of a modulus of elasticity of material is more challenging to calculate and is usually

    defined by an initial tangent modulus.

    A typical stress-strain curve for both pit cast and centrifugally cast iron presented by

    Attewell, et al. (1986) is shown in Figure A-1. The lack of elastic behavior by cast iron is clearly

    visible from the non-linearity of the elastic strain curves. The brittle behavior of both pit cast

    and centrifugally cast iron is apparent with rupture failure occurring at a relatively low value of

    50

  • 8/22/2019 Deep braced cuts utilities.pdf

    62/169

    axial strain. Centrifugally cast iron shows approximately a 50 percent increase in strength over

    that of pit cast. This can be attributed to its quick solidification, uniformity of its cross section,

    and the isolation of impurities accomplished through the improved method of production.

    Cast iron has been shown to behave differently in tension and compression. This can

    have a large effect on the flexural behavior of the pipe. Schlick and Moore (1936) conducted 12

    tests on specially cast plates of four different grades of strength with 13, 23, and 32 mm

    thickness in direct tension and compression. From the 12 tests, it was shown that the

    compressive strength of cast iron to be on average 3.6 times greater the tensile strength with a

    standard deviation of 0.31. The difference in the behavior of cast iron in tension and

    compression is most notable for strains above 0.1 percent, when the slope of the tensile curve

    decreases at a faster rate than that of the compression curve.

    Due to the complex behavior of cast iron, extensive testing has been done to determine

    appropriate engineering properties to represent its response to loading conditions. Ahmed (1990)

    compiled the test results and established recommended ranges for values for the ultimate stress,

    the initial tangent modulus, and the failure strain for pit cast and centrifugal cast iron. Table A-1

    shows his suggested values for both pit cast and centrifugally cast iron. The variation of the

    values is the result of the improvements in the production process from pit to centrifugal casting.

    Cast iron pipe failure due to excessive bending occurs as an abrupt brittle fracture at low

    strains. Attewell, et al. (1986) recommend a maximum design stress for cast iron under direct

    tensile load equal to one-quarter of the ultimate tensile strength of the material. For cast iron in

    bending, a rupture factor of 1.6 needs to be a