DECISION MAKING FOR BRIDGE STOCK...

151
1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE STOCK MANAGEMENT Tutor: Dr. Daniele Zonta 2014

Transcript of DECISION MAKING FOR BRIDGE STOCK...

Page 1: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

1

University of Trento

Emiliano Debiasi

DECISION MAKING FOR BRIDGE STOCK

MANAGEMENT

Tutor: Dr. Daniele Zonta

2014

Page 2: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

2

UNIVERSITY OF TRENTO

Civil and Mechanical Structural Systems Engineering

XXVI Cycle

Final Examination 10/04/2014

Board of Examiners

Prof. Maurizio Piazza (Università di Trento)

Prof. Andrea Prota (Università di Napoli Federico II)

Prof. Carmelo Gentile (Politecnico di Milano)

Prof. Helmut Wenzel (Universität für Bodenkultur Wien)

Page 3: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

3

SUMMARY-SOMMARIO

Bridges in service in most Western Countries were built according to codes with

design loads that are now inconsistent with today’s traffic demands. Currently,

transportation agencies do not know how to respond to transit applications on

their bridges. This thesis focuses on the legal issues entailed by

overweight/oversize load permits issued by transportation agencies. Indeed,

correct decision-making should consider the legal liabilities involved in possible

catastrophic events. In this thesis I illustrate how this problem is guided by the

Department of Transportation of the Italian Autonomous Province of Trento

(APT’s DoT), a medium-sized agency managing approximately one thousand

bridges across its territory. In the basic approach, it does not authorize movement

of overweight loads unless it is demonstrated that their effect is less than that of

the nominal design load. When this condition is not satisfied, a formal evaluation

is carried out in an attempt to assess a higher load rating for the bridge. If, after

the reassessment, the rating is still insufficient, the bridge is classified as sub-

standard and a formal evaluation of the operational risk is performed to define a

priority ranking for future reinforcement or replacement.

Italian version

I ponti in servizio nella maggior parte dei Paesi occidentali, sono stati costruiti in

accordo a normative che prevedevano carichi di progetto che al giorno d’oggi

sono inconsistenti con l’attuale domanda di traffico. Oggigiorno, le agenzie di

trasporto non sanno come comportarsi nel caso di richieste di transito di carichi

eccezionali sui ponti di loro proprietà. Questa tesi si concentra sulle questioni

giuridiche derivanti dai permessi dei carichi eccezionali emessi dalle agenzie di

trasporto. Infatti, un corretto processo decisionale dovrebbe considerare le

responsabilità giuridiche a seguito di eventuali eventi catastrofici. In questa tesi si

illustra come questo problema è stato indirizzato nel caso del Dipartimento dei

Trasporti della Provincia Autonoma di Trento (PAT), un'agenzia di medie

dimensioni che gestisce circa un migliaio di ponti sul suo territorio. Nell'approccio

di base, non si autorizza il transito del carico eccezionale sul ponte a meno che la

sollecitazione non sia inferiore a quella prodotta dal carico nominale di progetto.

Quando questa condizione non è soddisfatta, viene effettuata una valutazione

formale nel tentativo di valutare un carico più elevato per il ponte. Se, dopo

Page 4: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

4

questa nuova valutazione il risultato è ancora negativo, il ponte viene classificato

come non conforme e viene eseguita una valutazione formale del rischio, allo

scopo di definire una classifica di priorità per il suo futuro rinforzo o sostituzione.

Page 5: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

5

DEDICATION

A Elena

Page 6: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

6

Page 7: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

7

ACKNOWLEDGEMENTS

This research was made possible thanks to the financial support of the

Department of Public Works of the Autonomous Province of Trento: Stefano De

Vigili, Luciano Martorano, Guido Benedetti, Matteo Pravda, Rosaria Fontana, Italo

Artico, and Filiberto Bolego are particularly acknowledged. I also wish to thank

Alessandro Lastei, Luca Mattiuzzi, Francesco Chesini, Francesco Demozzi,

Marco Tallandini, Alessandro Lanaro, Davide Trapani and Carlo Cappello all

collaborating in the research group at the University of Trento, for their

contribution to the development of this project.

Page 8: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

8

Page 9: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

9

CONTENTS

SUMMARY-SOMMARIO ......................................................................................... 3

DEDICATION .......................................................................................................... 5

ACKNOWLEDGEMENTS........................................................................................ 7

CONTENTS ............................................................................................................. 9

1 INTRODUCTION ............................................................................................11

1.1 Motivation/Problem statement ...............................................................11

1.2 Objectives ..............................................................................................13

1.3 Method ...................................................................................................14

1.4 Outline ...................................................................................................15

1.5 Limitations..............................................................................................15

2 PROBLEM STATEMENT ...............................................................................17

2.1 Introduction ............................................................................................17

2.2 State of the art .......................................................................................17

2.3 Current procedure .................................................................................21

2.4 Effect of vehicle velocity ........................................................................23

2.5 Travel conditions ...................................................................................24

2.6 APT overweight vehicle models ............................................................25

2.7 Conclusions ...........................................................................................27

3 CRITERIA FOR RE-ASSESSING BRIDGES FOR OVERWEIGHT LOADS .29

3.1 Introduction ............................................................................................29

3.2 Assessment principle .............................................................................29

3.3 Levels of assessment ............................................................................30

3.4 Procedures for assessment ...................................................................32

3.4.1 Girder bridges ....................................................................................32

3.4.2 Arch bridges.......................................................................................40

3.5 Lack of capacity of substandard bridges ...............................................44

3.6 Risk interpretation of parameter .........................................................50

3.7 Conclusions ...........................................................................................54

4 APPLICATION TO CASE STUDIES ..............................................................57

4.1 Introduction ............................................................................................57

Page 10: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

10

4.2 Case studies ..........................................................................................57

4.2.1 Fiume Adige.......................................................................................58

4.2.2 Rio Cavallo ........................................................................................75

4.3 Discussion of the results ........................................................................84

4.4 Conclusions ...........................................................................................86

5 DECISION MAKING .......................................................................................87

5.1 Introduction ............................................................................................87

5.2 Basic concepts ......................................................................................88

5.3 Expected utility theory ...........................................................................89

5.4 Decision tree ..........................................................................................90

5.5 Optimization of alpha thresholds .........................................................100

5.6 Bayesian updating of parameters ........................................................103

5.7 Conclusions .........................................................................................107

6 APPLICATION TO THE APT BRIDGE STOCK ...........................................109

6.1 Introduction ..........................................................................................109

6.2 Bridge Management System ...............................................................109

6.3 Strategic objective ...............................................................................117

6.4 Level 0 assessment results .................................................................119

6.5 Decision tree ........................................................................................125

6.6 Prediction of re-assessment results and costs ....................................127

6.7 Application to 20 APT bridges .............................................................131

6.8 Bayesian updating and thresholds of optimization ...........................138

6.9 Conclusions .........................................................................................142

7 CONCLUSIONS AND FURTHER WORK ....................................................143

7.1 Conclusions .........................................................................................143

7.2 Further work ........................................................................................144

REFERENCES ....................................................................................................145

Page 11: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

11

1 INTRODUCTION

1.1 Motivation/Problem statement

Managing large infrastructure systems is a multi-disciplinary activity requiring

expertise from many areas, including fields of research beyond the typical scope

of the structural engineer. The process of risk analysis and decision-making itself

involves knowledge of the cognitive mechanisms and the psychology of economic

decisions. Mere structural reliability is just one of many aspects affecting

decisions, while economic, social, ethical and legal issues must also be

considered in a risk model. In recent years, transportation agencies have focused

on the problem of overweight traffic management, due to the increase in the

nominal load of heavy vehicles and to the increasing age and deterioration of the

infrastructure.

In fact, most bridges operating today in Europe were built to old codes that

foresaw design loads inconsistent with today’s traffic demand, and currently

transportation agencies do not know how to behave in the case of applications for

transit on their bridges.

A formal re-assessment of old bridges with respect to new design codes would

require analysis of design documents that may not be available and also

structural recalculation; and very often expensive load tests. Because of the

number of old bridges, an agency cannot normally carry the overall cost of a full

analysis and will seek for simplified approaches.

In this thesis I illustrate how this problem can be managed, applying the

methodology to the stock of the Department of Transportation of the Italian

Autonomous Province of Trento (APT’s DoT). Currently, the APT manages

approximately 2410 kilometers of roadways and 953 bridges (Fig. 1).

Page 12: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

12

Fig. 1: APT bridge stock

With reference to type and year of construction, the APT’s bridge stock has

characteristics similar to those found elsewhere in Europe: most of the bridges

were built after the Second World War, peaking in the 70's (Yue et al., 2010) (Fig.

2). Approximately 66% of the bridges were built of reinforced or prestressed

concrete, 25% have an arch structure and 9% were built in steel or are composite

steel-concrete structures (Bortot et al., 2009) (Fig. 2).

Fig. 2: a) age distribution and b) typological distribution in the APT (Zonta et al., 2007)

Page 13: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

13

In order to allow effective planning of maintenance policies and to meet the new

requirements, the Department of Transportation of the APT has begun to

collaborate with the Department of Mechanical and Structural Engineering,

University of Trento, to develop a comprehensive Bridge Management System

(APT-BMS) (Bortot et al., 2009) (Fig. 3).

Fig. 3: Web application of APT-BMS (www.bms.provincia.tn.it)

1.2 Objectives

In this thesis I illustrate how the problem of applications for transit of overweight

loads can be guided. In particular, this thesis focuses on the legal issues entailed

by overweight/oversize load permits issued by transportation agencies. Indeed,

correct decision-making should consider the legal liabilities involved in possible

catastrophic events. The main objective is therefore to develop a decision support

system for the management of the transit of the overweight traffic loads on

bridges, in particular for the APT stock. This thesis provides simple, practical rules

for deciding whether an overweight load permit can be issued or not, and if so,

under what restrictions.

Moreover, I apply utility theory to optimize the expected cost in order to propose a

process to guide the APT in making the most cost effective decision when

selecting the appropriate level of verification.

Page 14: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

14

1.3 Method

In general, permits for overweight vehicles are issued by transportation agencies

based on the total gross weight, the maximum axle load, the distribution of axle

weights and on the axle spacing (see for example Federal Highway

Administration, (2012)).

One of the main problems is the high variability of axle loads and spacing. A set

of predefined overweight load configurations is therefore defined that are more

conservative than other axle combinations having the same gross weight. In the

basic approach, it does not authorize the transit of the overweight load unless it is

demonstrated that the effect is less than that of the nominal design load. It is

worth emphasizing that this approach protects transportation agencies against

legal liabilities in the case of a catastrophic event, because it has authorized the

transit of a vehicle whose effects are less than those produced under the design

assumptions. When the bridge is not verified, a formal evaluation is carried out in

an attempt to assess a higher load carrying capacity for the bridge. If, after the

reassessment, the capacity is insufficient, the bridge is classified as sub-standard

and a formal evaluation of the operational risk is performed in order to define a

priority ranking for future reinforcement or replacement.

The method is proposed as an alternative to the recent methods developed in

order to solve the problem of transit permits. In fact, the permit issuing process

would require a detailed structural analysis, which in turn would require very

laborious analyses. Furthermore, in many cases, the geometrical data necessary

to apply the analyses are not fully available. Recently, to overcome this difficulty

three methods were discussed (Vigh and Kollar, 2006). The three methods are

the following (Vigh and Kollar, 2006):

1) application of a simplified structural analysis with a comparison of the

effects (bending moment, shear force) caused by the design loads and

overweight loads (e.g. Correia and Branco, 2006);

2) comparison of the axle loads using the bridge gross weight formula

(Bridge formula weights, 1994), or their improvements (James et al. 1986;

Chou et al. 1999; Kurt 2000);

3) application of approximate transversal load distributions (Vigh and Kollar,

2007).

The three methods are discussed in detail in Section 2.2.

Page 15: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

15

1.4 Outline

In this thesis I illustrate how to guide the legal issues arising from the issue of

transit permits by the transportation agencies. In the next Chapter I first introduce

the overweight vehicle permit problem and describe how it is currently formally

managed in the APT. I then defined the travel conditions and a set of predefined

overweight load configurations that are more conservative than other axle

combinations having the same gross weight.

In Chapter 3, I show the multi-level assessment protocol conceived to estimate

the response of the bridge stock to overweight loads. In particular, three levels of

refinement of bridge assessment are foreseen to verify the bridge under

overweight loads. At the end an interpretation of the risk is proposed.

Chapter 4 applies the methodology to two case studies in order to test the

method. The sub-standard girder bridge Fiume Adige and arch bridge Rio Cavallo

are chosen to perform the levels of refinement.

In Chapter 5 I propose a decision making process to guide transportation

agencies in making the most cost effective decision. The utility theory is used to

optimize the expected cost. In addition, a methodology based on Bayesian

statistics is used to update parameters on the basis of a number of case studies.

Then, in Chapter 6 I apply the decision making process to the APT bridge stock in

accordance with the strategic objectives to assess/retrofit the APT bridge stock.

Based on the decision tree proposed, a prediction of the future demand for re-

assessment and costs is presented. Finally I illustrate the optimization of the

thresholds of the lack of capacity based on the results of 20 APT bridge case

studies.

Some concluding remarks are made in Chapter 7.

1.5 Limitations

Although the methodology proposed in this thesis can be used by any

transportation agency, the set of APT vehicle models and the decision tree

proposed (see Section 2.6) have been created following the needs of the APT

and the limitations of the Italian codes. Therefore, the reference loads must be

changed when the DoT needs or the codes are different. However, the needs of

the APT could be similar to many other transportation agencies.

Page 16: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

16

Page 17: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

17

2 PROBLEM STATEMENT

2.1 Introduction

In recent years, the APT’s DoT has focused on the problems arising from the

increase in the nominal load of heavy vehicles and the increasing age and

deterioration of the infrastructure. A formal re-assessment of old bridges with

respect to new design codes would require analysis of the original design

documents, often unavailable, and structural recalculation; and very often

expensive load tests. Because of the number of old bridges, an agency cannot

normally carry these costs and will seek simplified approaches.

To re-assess the bridges taking into account the current overweight vehicles

crossing them, it is firstly necessary to define representative loads (called

henceforth APT loads) that are more conservative than other overweight loads

having the same gross weight. This is done in order to ensure that if a bridge is

sufficient for a given APT load, it is automatically adequate for any load less than

or equal to the APT load.

Secondly, it is important to define the possible travel conditions of the vehicle on

the bridge and the potential restrictions. This is necessary because different travel

conditions can place different demands on the bridge.

Therefore, in this Chapter I define the representative loads and the travel

conditions starting from the current conservative procedure adopted by APT DoT

to release the transit permits.

2.2 State of the art

The increase in the number of overweight vehicles travelling on highways has

caused growing interest in the policies for issuing permits (Fiorillo and Ghosn,

2014). Various works on this topic have been developed in recent years and

Page 18: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

18

included optimization process to obtain optimum paths (Adams et al., 2002;

Osegueda et al., 1999) and procedures for the statistical categorization of

overweight loads (Fiorillo and Ghosn, 2014, Correia et al., 2005; Fu and Hag-

Elsafi, 2000). As mentioned in Section 1.3, three main methods were recently

developed to manage transit permits. Other studies on permit checking of

overweight vehicles were discussed by Fu and Moses (1991), Ghosn (2000),

Bakht and Jaeger (1984), Ghosn and Moses (1987). Phares et al. (2004)

presented a procedure for permit checking of overweight vehicles based on the

bridge load rating using experimental testing.

The first method (Correia et al., 2005) compares the internal forces (bending

moment, shear stress, normal force) caused by design code loads and

overweight vehicles. The methodology requires the knowledge of the transversal

section and longitudinal model of the bridge. Four transversal sections and three

longitudinal models can be chosen for the analyses (Fig. 4). The software BIST

(Bridge Investigation for Special Trucks) developed by Branco and Correia (2004)

calculates, on the basis of the transversal section and longitudinal model chosen,

the transversal distribution load factors and the influence lines necessary for the

comparison of the effects of the design load with those caused by the overweight

vehicle.

Fig. 4: a)Transversal sections and b)longitudinal model considered by software BIST

(Correia and Branco, 2006)

The analyses are performed by placing the loads in each critical section. A

simplification regarding overweight loads is assumed and consists in considering

a) b)

Page 19: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

19

each group of wheels of the vehicle, which is composed of 7 axles. All the

possible combinations of positions of the loads are tested to determine the

maximum effects in each critical section.

The method calculates the structural safety of the bridge by defining two

simplified safety factors (SSF) evaluated in the critical sections, one for bending

moment and the other for supporting reactions (1).

(1)

where γs (usually equal to γs=1.5) is the safety factor of the code loads, and S(code

loads) and S(overweight loads) are the load effects caused by design loads and overweight

loads respectively. If SSF>1.5, the structural safety of the bridge is greater than

that defined in the design code, and so the crossing of the bridge is safe. Correia

and Branco (2006) states that a lower safety factor for the overweight load may

be adopted, since the exact value of the action is known. As a consequence, the

Portuguese Expressway Authority (Brisa) allows the crossing of the bridge with a

factor of up to γs=1.1, while if γs is between 1.1 and 1.0, the engineer must decide

whether to issue the permit by evaluating the bridge conditions.

The second method, developed by FHWA (1994), estimates the equivalent load

of a generic overweight vehicle. The formula is adopted by the National System of

Interstate and Defense Highways of the U.S.. The generic vehicle is divided into

groups of axles and the equation provides the allowable weight for each group

(Kurt, 2000). The Federal Bridge Formula is the following:

[

] (2)

where W is the overall gross weight on any group of 2 or more consecutive axles,

L is the length of the group, and N is the number of axles in the group.

The allowable gross weight for the overweight vehicle is equal to the sum of the

allowable weights for each axle group (Kurt, 2000). This formula requires many

calculations that depend on the number of axles of the vehicle. In addition, the

equation does not take into account the total gross weight and the total length of

the vehicle, and can therefore be inaccurate especially for long span or multispan

bridges (Vigh and Kollar, 2007). Numerous researchers (Meyerburg et al. (1996),

Nowak et al. (1994), Nowak et al. (1991), Harmon (1982)) have observed that the

overall length of many trucks and the number of axles have significantly increased

since the original bridge formula (2) was developed. This means that the

Page 20: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

20

allowable weight has significantly increased. For this reason numerous studies to

improve the procedure for issuing transit permits have been done (e.g. Kurt,

2000; Chou, 2005; Ghosn, 2000).

The third method (Vigh and Kollar, 2007) proposes the application of approximate

transversal load distribution to estimate the effects of the loads. The principle of

the method is the following:

The bridge is safe if the internal forces caused by the overweight vehicle are

smaller than those caused by the design load vehicle (Vigh and Kollar, 2007) (3).

(3)

where n is the safety of the bridge, and Edesign load and Eoverweight load are the effects of

the design load and overweight load respectively. If n≥1 the overweight vehicle

can cross the bridge.

The method also takes into account the different location of the load through the

width of the bridge. In fact, Vigh and Kollar (2007) consider the following travel

conditions:

the overweight load is a part of the traffic and crosses close to the exterior

of the bridge;

other traffic loads are not permitted and the overweight load crosses

close to the exterior of the bridge;

the road is closed to free traffic and the overweight load crosses in the

center of the roadway.

The methodology calculates the load that acts in an arbitrary position through the

width of the bridge (Pη), multiplying the load (P) by the distribution factor η

(Goodrich and Puckett, 2000).

(4)

The distribution factors are analogous to the transverse load distribution. Several

methods are available in the literature for the calculation of these coefficients

(Massonnet & Bares, 1968; Guyon, 1946; Courbon, 1950). When the transverse

load distribution coefficients are known, the method suggests that they be used,

otherwise it recommends applying two transverse load distributions which are

Page 21: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

21

upper and lower approximations of the accurate transverse load distributions (Fig.

5). One of these, which is unknown, is a conservative estimation of the transverse

load distributions. Vigh and Kollar (2007) report the recommended value of these

limits for four different bridge typologies (two girder system, multiple girder

system, solid slab, box). These values were obtained by Janko (1998) by

considering several real bridge superstructures.

Fig. 5: Upper and lower approximation of transverse load distributions (Vigh and Kollar,

2007)

The method points out that since a comparison among loads is performed, the

numerical value of the transverse load distributions are irrelevant and only the

shapes are important.

The main advantage of the permitting procedure based on this last method, is the

minimal input data of the bridge, which are:

the span of the bridge;

the width of the bridge;

type of superstructures of the bridge.

2.3 Current procedure

Nowadays the conservative procedure adopted by the APT’s DoT foresees three

possible transit restrictions based on the total gross weight of the overweight

loads:

1) Free travel up to 44 tons: the vehicle can travel freely with no traffic

restriction – but restrictions on time and number of trips may be applied;

2) Travel with traffic restriction and vehicle speed limit to 30 km/h up

to 60 tons: the road is closed to free traffic, the vehicle is required to

cross the bridge in the center of the roadway and the maximum vehicle

speed is 30 km/h.

3) Travel with traffic restriction and vehicle speed limit to 10 km/h

beyond 60 tons: the road is closed to free traffic, the vehicle is required

Page 22: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

22

to cross the bridge in the center of the roadway and the maximum

vehicle speed is 10 km/h.

These restrictions are based on empirical information from past crossing of loads

that caused no apparent damage to the bridges. However, these restrictions do

not consider the real capacity of the bridges. In the next sections I analyze

critically this categorization of restrictions and in Chapter 3 I explain a simplified

method that takes into account the capacity of the bridge.

The possible methodologies that can be considered in the analyses are reported

in the following. The differences among the methodologies are in the safety level

that the manager wants to obtain and accept.

1) The overweight load does not cause effects that are more severe than

the original bridge design code loading (the condition satisfies both the

substantial and formal requirements of the design code);

2) the overweight load causes effects that are more severe than the original

bridge design code loading but the exact knowledge of the total gross

weight of the overweight load leads to an estimation of a reliability index

equal to or higher than that foreseen by the design code (the condition

satisfies the substantial but not the formal requirements of the design

code);

3) the manager accepts that the overweight load crosses the bridge with a

reliability index lower than that foreseen by the design code (that is, with

a higher risk), (the condition does not satisfy either the substantial or

formal requirements of the design code).

Table 1 shows the possible methodologies of analysis and travel conditions. The

aim of the present thesis is to analyze only the methodology that satisfies both the

substantial and the formal requirements of the design code (first row of Table 1)

because the APT wants to be protected by legal liabilities involved in possible

catastrophic events. The methodologies that do not satisfy the formal

requirements of the design code are not discussed in the present work (second

and third row of Table 1).

Page 23: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

23

Table 1: Possible methodologies of analysis and travel conditions

Model

Methodology

Free travel

Bridge crossed in

the center of the

roadway

Limitation of the

speed

As per design

code YES YES YES

With the principle

of the design

code

NO NO NO

Not accepted by

the design load NO NO NO

2.4 Effect of vehicle velocity

In the categorization explained in Section 2.3, the travel restrictions on overweight

loads are based on the vehicle speed. This is justified by assuming that a higher

speed entails a higher dynamic response coefficient. In fact, since the demand on

the bridge caused by a dynamic load is higher than the same load applied

statically, intuitively one can think that a higher speed entails a higher dynamic

response coefficient of the bridge. An examination of the technical literature

(Cantieni 1983, Paultre et al. 1992, Brady et al. 2006, Senthilvasan et al. 2002)

shows that in reality the speed of an overweight vehicle is not directly proportional

to the dynamic coefficient, which depends more on other factors such as

(Cantieni 1983):

the length of the bridge;

the roadway irregularities;

the stiffness of the deck;

the dynamic features of the vehicle.

There is no sense in limiting the speed of the overweight load, if there is no

evidence that by reducing speed, the dynamic coefficient and consequently the

stress on the bridge are also reduced. Moreover, under certain conditions, a lower

speed causes higher stress on the bridge (Fig. 6).

Page 24: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

24

Fig. 6: Amplification effect as a function of the vehicle velocity (Cantieni, 1983)

2.5 Travel conditions

Based on the observations in Section 2.4, I decided to disregard speed

restrictions, and to assume the following two travel conditions to be used in the

transit permit issuing process:

1) free travel;

2) road closed to free traffic and bridge crossing in the center of the roadway

without speed limits.

As discussed above, the limitation of the speed produces no benefits and so will

not be taken into account in the discussion. Therefore, in accordance with Section

2.3, the possible methodologies of analysis and travel conditions become those

shown in Table 2.

Page 25: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

25

Table 2: Possible methodologies of analysis and travel conditions considered in the

present thesis

Model

Methodology

Free travel

Bridge crossed in

the center of the

roadway

Limitation of the

speed

As per design

code YES YES NO

With the principle

of the design

code

NO NO NO

Not accepted by

the design load NO NO NO

2.6 APT overweight vehicle models

In general, permits for overweight vehicles are issued by transportation agencies

based on the total gross weight, the maximum axle load, the distribution of axle

weights and the axle spacing (see for example Federal Highway Administration

(2012)). One of the main problems is the high variability of axle loads and

spacing. A set of predefined overweight load configurations, the APT loads, is

therefore defined; these configurations are more conservative than other axle

combinations having the same gross weight. If a bridge is sufficient for a given

APT load, it is automatically adequate for any load less than or equal to the APT

load. Currently, the Italian highway code (D.L. 30/04/1992) places the following

limits on the free movement of vehicles: maximum total weight 44 tons (440 kN);

maximum axle load 13 tons (130 kN); minimum axle spacing 1.3 m. The APT

requires that these axle weight and spacing limits be respected for extra-legal

vehicles, whatever their gross weight. Therefore, the APT load model reproduces

a multi-axle load in the most unfavorable configuration considering different gross

weights: a set of 130kN concentrated loads spaced at 1.3 m, applied on a 3.0 m

wide lane. Similarly to the provisions of the 1990 Italian design code for bridges

(D.M. 04/05/1990), the overweight vehicle model is applied in conjunction with a

uniformly distributed load of 30kN m-1

, 6 m ahead of the first axle and 6 m behind

the last axle. In addition the APT DoT required that two additional models be

taken into account: 6 axles by 12 tons = 72 tons (720kN) and 56 tons (560kN) due

to specific real overweight loads. All APT loads are shown in Table 3. The

concentrated forces represent the axles of the overweight load, and the uniformly

Page 26: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

26

distributed load of 3 t/m represents the traffic in front of and behind the overweight

load.

Table 3: APT loads

APT Load APT Load pattern

56 tons

5 axles by 13

tons

65 tons

6 axles by 12

tons

72 tons

6 axles by 13

tons

78 tons

Page 27: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

27

2.7 Conclusions

The objective of the APT DoT is to provide simple and practical rules for deciding

whether an overweight load permit can be issued or not, and if so, under what

restrictions. The current procedure of the APT foresees conservative limits and

takes into account the vehicle velocity. Examining the technical literature it is clear

that there is no sense in limiting the speed of the overweight load as there is no

evidence that by reducing speed, the stress on the bridge is reduced. From these

considerations only two travel conditions are possible: free travel and crossing the

bridge in the center of carriageway.

Representative loads (APT loads), which are more conservative than other

overweight loads having the same gross weight, are defined. If a bridge is

sufficient for a given APT load it is automatically adequate for any load less than

or equal to the APT load. Following this approach it is not necessary to verify a

7 axles by 13

tons

91 tons

8 axles by 13

tons

104 tons

9 axles by 13

tons

117 tons

Page 28: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

28

bridge every time a different load distribution is acting. The definition of the

representative loads has been reached by analyzing the current Italian code and

considering the minimum axle spacing, and the maximum axle load of the

vehicles foreseen by the code.

Page 29: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

29

3 CRITERIA FOR RE-ASSESSING BRIDGES FOR

OVERWEIGHT LOADS

3.1 Introduction

In principle, assessing a bridge to any of the APT load models and travel

conditions would require full formal re-evaluation of its capacity, carried out by a

professional engineer. In practice, direct re-assessment of the 1000 bridges in the

territory is a very expensive task, and it is in many cases unnecessary. To guide

the cost issue, the approach followed is to estimate the capacity of the stock

using a simplified and conservative approach first, and then refining the analysis

only if a higher load rating is required.

In this Chapter I show the procedure to evaluate whether a bridge can withstand

the APT loads defined in Chapter 2. In particular, I illustrate the multi-level

assessment protocol conceived to estimate the response of the bridge stock to

overweight loads.

3.2 Assessment principle

The assessment procedure includes four simplified levels of refinement, from

Level 0 to Level 3, as summarized in Table 4. All methods are based on the

following principle:

The bridge is rated for an overweight load if it is demonstrated, even

conservatively, that the overweight load does not cause effects that are more

severe than the original bridge design code loading.

Page 30: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

30

In practice the procedure aims to demonstrate that the new overweight load

condition is not worse than the most critical load condition associated with the

original design assumption or as-built situation, and therefore the overweight load

does not reduce the original design safety level. It is believed that this principle

protects the APT against legal liability in the case of a failure, as following this

principle the APT authorizes travel only of those vehicles whose effects are less

than or equal to those expected under the design assumptions.

Table 4: Level of refinement of bridge assessment under overweight loads

Assessment Level Capacity Models Calculation Models

Level 0 Bridge is assumed

verified with no overstrength

Statically determinate condition is assumed

Level 1 As per design

As per design Level 2

Refined model; load

redistribution is allowed,

provided that the ductility

requirements are fulfilled.

Level 3

Material properties can

be updated based on in-

situ testing and

observations

The fundamental hypothesis of the assessments is reported in the following:

the contemporary presence of more than one overweight load on the

bridge is not allowed.

In the case of free travel we evaluate that the condition above is still valid,

because the contemporary presence of more than one overweight load is unlikely.

Moreover, if this situation of more than one vehicle is considered, the result of the

method would be too conservative. The hypothesis is automatically satisfied in

the case of bridge crossed in the center of the roadway.

3.3 Levels of assessment

As summarized in Table 4, three levels of refinement of bridge assessment are

foreseen to verify the bridge under overweight loads.

Level zero assessment is a conservative estimate of the bridge capacity based on

its geometry and the design code it was originally designed to. The fundamental

hypothesis of Level 0 assessment is reported in the following:

Page 31: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

31

the bridge was built exactly to the nominal design load (in other words,

with no overstrength).

The bridge is automatically rated for the overweight load if it can be demonstrated

that the stresses it creates are everywhere lower than or equal to those

considered at the design stage.

The APT approach:

1) replaces the design traffic lane with the APT load;

2) evaluates the difference in demand between the new and old loadings.

If the stress under the APT load is lower than the design load stress, it is logical to

infer that the bridge is able to withstand the APT load. For girder bridges, shear

and bending moment in the deck are assessed.

The basic assumption in Level 0 assessment is that the bridge was built with no

shear or moment overstrength at any section of the deck: this assumption is

extremely conservative and normally not realistic. Bridge members are normally

slightly oversized and very often the designer assumes conservative capacity

models. In addition the mechanical properties of the materials in the as-built

situation could be better than those specified by the designer. When a bridge is

not sufficient according to Level 0 assessment, the assessment proceeds to a

higher level of refinement and is carried out by a professional engineer based on

analysis of the available design documentation.

At Level 1 the evaluator is required to examine the design documents to verify

whether the critical structural members are oversized. This level of assessment is

based only on analysis of the existing documents, without revising assumed

material properties or the calculation model.

At Level 2 the evaluator reassesses the bridge capacity using more refined

models than those used by the original designer. Often, a capacity increase is

achieved by considering inelastic behavior and spatial stress redistribution.

At Level 3 the evaluator can update the characteristic values of the variables used

in the assessment, based on the results of material testing and observations. The

procedure leaves the evaluator free to test the materials, without specifying the

minimum number of samples or the type of test. However, if the evaluator wants

to use the test results quantitatively, a Bayesian probabilistic update technique

should be applied. This can be done even if the design documentation is not

available: in this case, an accurate survey of bridge geometry and extensive

material sampling are needed.

Page 32: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

32

3.4 Procedures for assessment

Although the definition of levels of assessment is general, the procedure for

assessment is different in the case of girder bridges and arch bridges. The reason

lies in the different resistance mechanisms of the two typologies. For arch

bridges, in contrast with girder bridges, the capacity is independent of the material

strength (for example the compressive strength of the masonry) but depends on

the equilibrium of the forces acting upon it. In fact, if the form of the arch bridge is

equal to the funicular form generated by the external forces, its capacity tends to

infinity. Therefore, in Section 3.4.1 and 3.4.2 the procedure for assessment of

girder and arch bridges is shown separately. In these sections only the procedure

of Level 0 assessment is reported. The other levels depend on the specific

verifications of the bridge and these are shown in the case studies of Chapter 4.

In the assessment levels we assume that the widths of the design load and the

APT load are identical (as suggested also by Vigh and Kollar, 2006). The Italian

codes (see for example Circolare 1962 or Circolare 1952) foresee two typology of

design loads:

civil loads (width=3.0m);

military loads (width=3.5m).

Therefore, in our case, the width of the APT load can be 3.0m or 3.5m.

3.4.1 Girder bridges

The procedure for assessment involves an estimation of the capacity of the

bridge, using Level 0 assessment first, and then refining the assessment level if a

higher assessed capacity is required. Level 0 analysis is simple for the free travel

condition. In this case the design situation is compared to a load condition where

one traffic lane is replaced with the APT load. As discussed above, the method is

based on the following principle:

The bridge is rated for an overweight load if it is demonstrated, even

conservatively, that the overweight load does not cause effects that are more

severe than the original bridge design code loading.

Page 33: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

33

Since the method compares effects, the following terms can be neglected in the

calculations:

dead load of the bridge;

live loads outside the lane replaced.

The reason is that these loads are the same for both the overweight and the APT

loadings, and so their effects are irrelevant to the evaluation and can be

disregarded. In fact, if S0 is the demand caused by the overweight load, which can

represent for example the bending moment or shear stress, SAPT is that caused by

the APT load, and G is that caused by the dead load, the increase in the demand

ΔS is independent of the dead load, and is equal to (5):

(5)

Similarly, the effects of live loads outside the lane replaced are identical in the two

situations, so these live loads can also be disregarded too. In fact, only one traffic

lane is replaced by the APT load and consequently the demand caused by any

live loads is the same in the two situations (6).

(6)

where S1 and S2 are the demands caused by the second and the third traffic lane

respectively.

In contrast, partial factors (γ) or dynamic coefficients (Φ) considered at the design

stage influence the increase in the demand (7).

[ Φ]

[ Φ] Φ

(7)

However, these values do not change the sign of the result but only its value. This

means that the result of the verification (positive or negative) is identical even if

partial factors or dynamic coefficients are not taken into account. For this reason

the comparison is conducted using the nominal load value, disregarding any

Page 34: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

34

another coefficient. If we need to quantify the extent of bridge understrength with

respect to the overweight load as absolute value, it is also necessary to consider

the partial factors or the dynamic coefficients. In contrast, if this deficiency is

evaluated as a relative value (ΔS/S0), as in Section 3.5, these coefficients can also

be neglected (8).

[ Φ]

Φ

[ Φ]

Φ

Φ

Φ

(8)

Moreover, when the shape of the design load and APT load are similar, the static

scheme of the bridge can also be neglected in the analyses.

Let us consider a simply supported beam and a fixed beam as shown in Fig. 7

and in Fig. 8.

Fig. 7: Distributed load on a)simply supported beam and b)fixed beam

Fig. 8: Concentrated load on a)simply supported beam and b)fixed beam

The diagram of the bending moment of the fixed beam can be seen as a shift of

that obtained for the simply supported beam. This is valid not only for distributed

loads but for each type of load (e.g. concentrated loads) (Fig. 9 and Fig. 10).

This means that when the original design load produces static stresses higher

than the new overweight vehicle in a simply supported span, the design stresses

will be higher with a statically indeterminate boundary condition. Since the method

Q

LL

Q F

LL

F

Q

LL

Q F

LL

F

Page 35: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

35

foresees a comparison between the effects caused by design and overweight

loads, the static scheme, whether continuous or simply supported, is irrelevant, so

a simply supported condition can always be assumed.

Fig. 9: Bending moment diagram caused by a distributed load in the case of a)simply

supported beam, b)fixed beam, c)comparison.

Fig. 10: Bending moment diagram caused by a concentrated load in the case of a)simply

supported beam, b)fixed beam, c)comparison.

In conclusion, in the case of free travel of an overweight load, the assessment is

made by comparing the effects of the original design and APT loads on a single

lane simply supported beam.

a)

c)

b)

a)

c)

b)

Page 36: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

36

The parameters that control the assessment are:

the span length L,

the design code adopted by the designer,

which in turn is related to the date of construction of the bridge.

In practice, Level 0 assessment foresees the calculation, for each section of the

beam, of the maximum bending moment and shear caused by the design load.

Subsequently, the design year of the bridge must be known, to obtain the design

loads provided by the design code. Then the same procedure is applied to the

APT load. If in all sections of the deck the bending moment and the shear caused

by APT load are equal to or lower than those caused by the design load, the

verification is positive (Fig. 11).

Fig. 11: Example of Level 0 assessment

In the case of restricted travel, the effects from the original traffic lanes must be

compared to the single lane APT load applied in the center of the carriageway. In

this case, to compare the effects, we must take account of the transverse load

redistribution between the various girders using, for example, the Massonnet-

Guyon-Bares theory (Massonnet C., & Bares R., 1968).

Page 37: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

37

Fig. 12 illustrates the procedure for determining whether the effect of the

overweight load centered on the carriageway is more or less critical than any

combination of design traffic lanes. Fig. 1a shows the cross section of the bridge

deck loaded with a two-lane design condition, with the Massonnet-Guyon-Bares

transverse distribution coefficients multiplied by the corresponding load

highlighted. The effect of the second design load configuration is illustrated in Fig.

12b, while Fig. 12c shows the envelope of design conditions. The maximum

allowable APT load, applied in the center of the carriageway, is that which has

effects less than or equal to the envelope of the design load effects (Fig. 12d).

Therefore, knowing the transverse distribution coefficients of the design load, the

maximum allowable APT load in the center of the carriageway can be determined

for any deck width or any bridge.

a) b)

c) d)

Fig. 12: a) Massonnet-Guyon-Bares coefficients multiplied by the relative load, first load

design condition b) second load design condition, c) envelope of design condition, d)

comparison with the effect of an APT overweight load.

Page 38: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

38

In summary, in the case of restricted traffic, Level 0 assessment requires

knowledge of:

the transverse distribution coefficients of the design load;

the span length;

the design code.

As an alternative to the Massonnet-Guyon-Bares method, the Courbon method

can be used to calculate the transverse distribution coefficients of the design load.

The Courbon method is a specific case of the Massonnet-Guyon-Bares method

(Petrangeli, 1996) in which the hypotheses are the following:

the torsional stiffness of the deck is equal to zero;

the longitudinal stiffness of the deck tends to infinity.

The method is not always in favor of safety, and therefore the final analyses

should be performed using Massonnet-Guyon-Bares method. However, the

Courbon method is a valid tool to estimate the lack of capacity of bridges, and

with this aim the results shown in Section 6.4 were obtained using this method.

When evaluating a bridge deck made with a concrete slab, the Courbon

coefficient is equal to (9):

(

) (9)

where r(x) is the transverse distribution coefficient as a function of the transverse

coordinate x (x=L/2 in the center of the carriageway), e is the load eccentricity

from the center of the carriageway, and L is the width of the deck.

Fig. 13 shows the Courbon transverse distribution of load as a function of one

moving concentrated force along the transverse section of the deck slab.

It can be noted from equation (9) and Fig. 13 that r(x) is equal to one in the center

of the carriageway (x=L/2) for each value of eccentricity e. This means (Fig. 14)

that the minimum value of the envelope caused by a number of loads is in the

center of the carriageway. Moreover it can be noticed that the minimum value of

the envelope is equal to the sum of the loads. In the case of a bridge crossed in

the center of carriageway, the allowable APT load is equal to the sum of the

design loads (Fig. 14).

Page 39: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

39

Fig. 13: Courbon transverse distribution of load as a function of one moving concentrated

force

Fig. 14: Maximum allowable APT load in the case of bridge crossed in the center of

carriageway

(10)

Equation (10) is valid only in the case of absence of the traffic divider. When a

traffic divider is present the bridge is crossed in the center of the semi-

carriageway and it is necessary to use the formulation explained in Section 3.4

replacing the Massonnet-Guyon-Bares coefficients with the Courbon coefficients

(Fig. 15).

4P

P

1P

2P

L L

0.5P

1P

P

2.5P

L/4x

L/2

P

1P

L

3/4L

2.5P

P

1P

0.5P

L L

2P

1P

P

4P

Page 40: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

40

Fig. 15: Maximum allowable APT load in the case of bridge crossed in the center of

carriageway with traffic divider

3.4.2 Arch bridges

For arch bridges, the approach shown in Section 3.4.1 has to be modified as the

resistance mechanisms of the two types of bridges is different. For girder bridges,

the procedure involves comparing, for each section of the beam, the maximum

bending moment and shear caused by the design load and by the APT load. This

procedure cannot be implemented for arch bridges because their capacity

depends only on the equilibrium of the forces acting upon them (Heyman, 1982).

The principle defined in Section 3.2 is still valid but the approach must be

changed. In fact, the capacity of the arch element is independent of the material

strength but depends on the equilibrium of the forces acting upon it. If the form of

the arch bridge is equal to the funicular form generated by the external forces, its

capacity tends to infinity. This means that the capacity depends on the form of the

load (axle spacing and axle loads) and not on the total gross weight (Fig. 16). Fig.

16 shows thrust lines generated by a uniform load q and q+q by supposing the

form of the arch equal to the funicular form (in this case a parabolic shape). It can

be noticed that in both cases the thrust line is identical.

The verification of the arch element can be performed by checking that the thrust

line is always within the middle third. This ensures that the cross-sections of the

arch are always compressed. Heyman, (1982) stated that to verify the arch

element it is sufficient demonstrate that there exist a satisfactory line of thrust that

balances the given loading. In other words it is sufficient to find a thrust line in

equilibrium with the external loading which lies everywhere within the arch ring

(Heyman, 1982). This principle is used in Level 2 assessment, where the

equilibrium analysis of the arch is performed.

Page 41: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

41

a) b)

Fig. 16: a)thrust line generated by a uniform load q, b)thrust line generated by a uniform

load q+q

For Level 0 assessment it is sufficient to compare the eccentricity of the thrust line

caused by the design load with that caused by the APT load. If in each section of

the arch, the eccentricity caused by the design load is greater than that caused by

the APT load, the bridge is safe. In fact, the eccentricity caused by the design

load represents the minimum thickness of the arch. An example of Level 0

assessment for arch bridges is reported in the following.

In the voussoir arch of Fig. 17, the connections between the arch rib and the

abutments can be considered made by frictionless pins as reported in the

literature (for example Heyman, 1982).

Fig. 17: Side view of voussoir arch bridge

If the loading F is located in the correspondence of the crown (Fig. 18), the total

bending moment M can be determined by performing the difference between the

qq

Thrust line

q

Thrust line

Page 42: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

42

bending moment caused by external forces (R·x) and by the abutment thrust (H·y)

(11).

Fig. 18: Schematization of the arch bridge

(11)

This means that the total bending moment (Fig. 19c) can be determined

graphically by minimizing the difference between the bending moment caused by

external forces (Fig. 19a) and a moment with the same shape of the arch (Fig.

19b). In fact, the shape of the arch represents the bending moment caused by the

abutment thrust.

Fig. 19: Bending moment in the arch rib, a)caused by one concentrated force, b)caused by

the horizontal component of the abutment thrust c)total bending moment.

a)

b)

c)

Page 43: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

43

Similarly to girder bridges, Level 0 assessment foresees the calculation, for each

section of the arch rib, the envelope of the bending moment (Fig. 21c) caused by

the design load (considering the worst position of the load (see for example Fig.

20)).

Fig. 20: Schematization of the arch bridge with a moving load

Fig. 21: Bending moment in the arch rib, a)caused by one moving concentrated force,

b)caused by the horizontal component of the abutment thrust c)envelope of the total

bending moment.

a)

b)

c)

Page 44: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

44

The same procedure is applied to the APT load. If in all sections of the deck the

bending moment caused by APT load is equal to or lower than that caused by the

design load, the verification is positive.

The approach discussed above requires the knowledge of the shape of the arch.

In the case of the APT bridge stock these data are not known and then an

approximation of the arch shape must be done to apply Level 0 assessment. In

this assessment a parabolic shape of the arch was chosen.

For Level 2 assessment this is not necessary because the exact shape can be

determined performing a geometric survey of the arch.

It is important to point out that for arch bridges, Level 1 assessment makes no

sense because by maintaining the same calculation model as per design the

result obtained would involve an increase either in the abutment thrust or in the

eccentricity and therefore the same results as the Level 0 assessment would be

obtained. Moreover, applying Level 3 assessment it is not possible to obtain a

decrease in the lack of capacity shown after Level 0 or Level 2 assessments. The

reason is that the mechanical properties of materials are not involved in the

resistance mechanisms of arch bridges. In fact, the capacity is independent of the

material strength but depends on the equilibrium of the forces acting upon it.

3.5 Lack of capacity of substandard bridges

To classify substandard bridges, we need to quantify the extent of their

deficiency. A useful index here is the critical live load multiplier η, defined as the

ratio between the stresses caused by the APT load and those due to the design

load (12).

(12)

where S0 is the effect of the live load and SAPT is the effect of the APT load.

For girder bridges there will be a critical load multiplier for bending moment and

shear stress, and these indices are calculated for each section of the span. The

coefficient depends on the location of the section where the ratio is calculated.

Therefore, the number of critical live load multipliers is equal to the number of

sections where the comparison is performed. However, the most significant

values are the maximum critical live load multiplier (maxη) and the critical live load

multiplier calculated where the stress is maximum (ηmax). The latter is defined as

the ratio between the maximum stress caused by the APT load and that due to

the design load, and is independent of the location where the maximum stresses

Page 45: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

45

are. ηmax gives an in depth understanding of the deficiency of the bridge even if

the location of the sections where the comparison is done is different. In fact, in

most cases, these sections are close to each other and the capacity is piecewise

constant. This means that even if the locations of the maximum stresses are not

the same, we can assume this to be the case in order to estimate the response of

the bridge. We can therefore calculate the critical live load multipliers for bending

moment and shear stress. For each bridge the following indexes were calculated:

maximum critical live load multiplier for shear stress (maxηt);

maximum critical live load multiplier for bending moment (maxηm);

critical live load multiplier for maximum shear stress (ηt,max);

critical live load multiplier for maximum bending moment (ηm,max).

As discussed in Section 3.4.1, the parameters that control the assessment are

the span length and the date of construction of the bridge. Thus, the safety

factors, the dynamic coefficient and the static scheme of the bridge are irrelevant

in the comparison. This is to say that it is possible to express the critical live load

multipliers as a function of these parameters. In fact, Fig. 22 illustrates the critical

live load multipliers as a function of the design code adopted by the designer, the

span length, and the APT load (in the case of free travel). In Fig. 22 only two

design codes are included (D.M. 1990 and Circolare 1962).

Page 46: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

46

a)

Max η ηmax Max η ηmax Max η ηmax Max η ηmax Max η ηmax Max η ηmax

V 0.533 0.533 0.650 0.650 0.650 0.650 0.650 0.650 0.650 0.650 0.650 0.650M 0.533 0.533 0.650 0.650 0.650 0.650 0.650 0.650 0.650 0.650 0.650 0.650V 0.604 0.576 0.737 0.702 0.737 0.702 0.737 0.702 0.737 0.702 0.737 0.702M 0.604 0.533 0.737 0.650 0.737 0.650 0.737 0.650 0.737 0.650 0.737 0.650V 0.604 0.586 0.737 0.737 0.737 0.737 0.737 0.737 0.737 0.737 0.737 0.737M 0.654 0.582 0.823 0.732 0.823 0.732 0.823 0.732 0.823 0.732 0.823 0.732V 0.586 0.558 0.737 0.711 0.737 0.711 0.737 0.711 0.737 0.711 0.737 0.711M 0.595 0.585 0.749 0.737 0.749 0.737 0.749 0.737 0.749 0.737 0.749 0.737V 0.586 0.546 0.755 0.755 0.755 0.755 0.755 0.755 0.755 0.755 0.755 0.755M 0.572 0.563 0.803 0.718 0.803 0.718 0.803 0.718 0.803 0.718 0.803 0.718V 0.586 0.540 0.819 0.819 0.819 0.819 0.819 0.819 0.819 0.819 0.819 0.819M 0.558 0.551 0.832 0.780 0.832 0.780 0.832 0.780 0.832 0.780 0.832 0.780V 0.568 0.535 0.867 0.867 0.886 0.886 0.886 0.886 0.886 0.886 0.886 0.886M 0.549 0.544 0.883 0.841 0.883 0.841 0.883 0.841 0.883 0.841 0.883 0.841V 0.558 0.533 0.900 0.900 0.950 0.950 0.957 0.957 0.957 0.957 0.957 0.957M 0.543 0.540 0.917 0.881 0.945 0.900 0.948 0.900 0.948 0.900 0.948 0.900V 0.551 0.550 0.924 0.924 0.997 0.997 1.031 1.031 1.031 1.031 1.031 1.031M 0.549 0.536 0.944 0.910 0.993 0.956 1.025 0.984 1.025 0.984 1.025 0.984V 0.573 0.573 0.940 0.940 1.029 1.029 1.085 1.085 1.108 1.108 1.108 1.108M 0.570 0.534 0.961 0.932 1.026 0.998 1.083 1.051 1.101 1.051 1.101 1.051V 0.594 0.594 0.947 0.947 1.049 1.049 1.121 1.121 1.164 1.164 1.178 1.178M 0.592 0.532 0.974 0.949 1.055 1.031 1.133 1.103 1.164 1.124 1.171 1.132V 0.607 0.607 0.951 0.951 1.060 1.060 1.145 1.145 1.203 1.203 1.236 1.236M 0.606 0.530 0.986 0.962 1.080 1.058 1.172 1.144 1.222 1.185 1.232 1.213V 0.620 0.620 0.953 0.953 1.065 1.065 1.159 1.159 1.230 1.230 1.277 1.277M 0.618 0.534 0.994 0.973 1.100 1.079 1.200 1.178 1.268 1.234 1.298 1.280V 0.633 0.633 0.956 0.956 1.068 1.068 1.166 1.166 1.247 1.247 1.306 1.306M 0.632 0.546 0.996 0.982 1.115 1.097 1.219 1.206 1.301 1.275 1.351 1.336V 0.642 0.642 0.958 0.958 1.071 1.071 1.171 1.171 1.257 1.257 1.326 1.326M 0.641 0.566 0.997 0.990 1.123 1.113 1.231 1.230 1.324 1.310 1.389 1.383V 0.647 0.647 0.959 0.959 1.073 1.073 1.174 1.174 1.262 1.262 1.338 1.338M 0.646 0.582 0.997 0.995 1.127 1.124 1.248 1.248 1.341 1.338 1.421 1.421V 0.649 0.649 0.961 0.961 1.074 1.074 1.176 1.176 1.266 1.266 1.345 1.345M 0.649 0.594 0.997 0.995 1.132 1.129 1.259 1.259 1.360 1.357 1.448 1.448V 0.650 0.650 0.963 0.963 1.075 1.075 1.177 1.177 1.269 1.269 1.349 1.349M 0.654 0.603 0.997 0.994 1.134 1.131 1.265 1.265 1.372 1.369 1.468 1.468V 0.650 0.649 0.964 0.964 1.076 1.076 1.178 1.178 1.270 1.270 1.353 1.353M 0.660 0.614 0.997 0.993 1.133 1.130 1.266 1.266 1.378 1.375 1.480 1.480V 0.650 0.648 0.965 0.965 1.076 1.076 1.178 1.178 1.271 1.271 1.355 1.355M 0.663 0.623 0.997 0.992 1.132 1.128 1.264 1.264 1.380 1.378 1.487 1.487V 0.650 0.648 0.967 0.967 1.077 1.077 1.178 1.178 1.271 1.271 1.355 1.355M 0.664 0.631 0.997 0.991 1.130 1.126 1.261 1.261 1.379 1.376 1.489 1.489V 0.650 0.649 0.968 0.968 1.077 1.077 1.178 1.178 1.271 1.271 1.356 1.356M 0.664 0.638 0.997 0.990 1.128 1.124 1.258 1.258 1.376 1.373 1.488 1.488V 0.651 0.651 0.969 0.969 1.077 1.077 1.178 1.177 1.271 1.270 1.356 1.355M 0.662 0.645 0.997 0.990 1.126 1.122 1.254 1.254 1.372 1.369 1.484 1.484V 0.653 0.653 0.970 0.970 1.077 1.076 1.178 1.176 1.271 1.268 1.356 1.354M 0.661 0.651 0.997 0.989 1.124 1.120 1.251 1.251 1.368 1.365 1.479 1.479V 0.655 0.655 0.971 0.971 1.077 1.076 1.178 1.175 1.271 1.267 1.356 1.352M 0.661 0.657 0.997 0.989 1.122 1.118 1.247 1.247 1.363 1.361 1.474 1.474

DM_04_05_1990

21

22

23

24

25

15

16

17

18

19

20

9

10

11

12

13

14

3

4

5

6

7

8

1

2

9x13 t56 t 5x13 t 6x13 t 7x13 t 8x13 tSPAN

(m)

Page 47: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

47

b)

Fig. 22: Critical live load multipliers as a function of the design code [a)D.M. 1990 and

b)Circolare 1962] adopted by the designer, the span length, and the APT load.

Max η ηmax Max η ηmax Max η ηmax Max η ηmax Max η ηmax Max η ηmax

V 0.561 0.561 0.684 0.684 0.684 0.684 0.684 0.684 0.684 0.684 0.684 0.684M 0.561 0.561 0.684 0.684 0.684 0.684 0.684 0.684 0.684 0.684 0.684 0.684V 0.561 0.552 0.684 0.672 0.684 0.672 0.684 0.672 0.684 0.672 0.684 0.672M 0.561 0.561 0.684 0.684 0.684 0.684 0.684 0.684 0.684 0.684 0.684 0.684V 0.598 0.598 0.752 0.752 0.752 0.752 0.752 0.752 0.752 0.752 0.752 0.752M 0.586 0.545 0.738 0.686 0.738 0.686 0.738 0.686 0.738 0.686 0.738 0.686V 0.674 0.674 0.858 0.858 0.858 0.858 0.858 0.858 0.858 0.858 0.858 0.858M 0.673 0.656 0.847 0.825 0.847 0.825 0.847 0.825 0.847 0.825 0.847 0.825V 0.716 0.716 0.990 0.990 0.990 0.990 0.990 0.990 0.990 0.990 0.990 0.990M 0.721 0.710 0.980 0.906 0.980 0.906 0.980 0.906 0.980 0.906 0.980 0.906V 0.725 0.696 1.055 1.055 1.055 1.055 1.055 1.055 1.055 1.055 1.055 1.055M 0.750 0.742 1.061 1.051 1.061 1.051 1.061 1.051 1.061 1.051 1.061 1.051V 0.725 0.668 1.081 1.081 1.106 1.106 1.106 1.106 1.106 1.106 1.106 1.106M 0.769 0.763 1.187 1.179 1.187 1.179 1.187 1.179 1.187 1.179 1.187 1.179V 0.725 0.650 1.099 1.099 1.160 1.160 1.168 1.168 1.168 1.168 1.168 1.168M 0.782 0.778 1.277 1.270 1.298 1.297 1.298 1.297 1.298 1.297 1.298 1.297V 0.725 0.658 1.108 1.105 1.191 1.191 1.232 1.232 1.232 1.232 1.232 1.232M 0.762 0.743 1.292 1.261 1.345 1.325 1.398 1.364 1.398 1.364 1.398 1.364V 0.725 0.668 1.108 1.097 1.200 1.200 1.266 1.266 1.292 1.292 1.292 1.292M 0.731 0.717 1.275 1.252 1.356 1.341 1.438 1.412 1.438 1.412 1.438 1.412V 0.715 0.675 1.108 1.077 1.201 1.193 1.275 1.275 1.323 1.323 1.339 1.339M 0.708 0.698 1.262 1.244 1.365 1.352 1.467 1.446 1.486 1.475 1.506 1.484V 0.696 0.679 1.108 1.063 1.201 1.185 1.280 1.280 1.345 1.345 1.382 1.382M 0.691 0.683 1.253 1.238 1.371 1.361 1.490 1.472 1.535 1.525 1.580 1.562V 0.687 0.687 1.108 1.056 1.201 1.180 1.284 1.284 1.363 1.363 1.415 1.415M 0.695 0.677 1.245 1.233 1.376 1.368 1.507 1.493 1.573 1.564 1.638 1.623V 0.699 0.699 1.108 1.055 1.201 1.180 1.288 1.288 1.377 1.377 1.442 1.442M 0.698 0.681 1.239 1.225 1.380 1.369 1.521 1.505 1.603 1.591 1.685 1.667V 0.704 0.704 1.107 1.051 1.201 1.175 1.288 1.284 1.379 1.379 1.454 1.454M 0.703 0.692 1.234 1.210 1.384 1.360 1.533 1.503 1.629 1.602 1.724 1.691V 0.708 0.708 1.100 1.050 1.201 1.174 1.288 1.285 1.382 1.382 1.464 1.464M 0.708 0.699 1.220 1.195 1.375 1.350 1.530 1.500 1.636 1.607 1.742 1.707V 0.711 0.711 1.093 1.053 1.198 1.177 1.289 1.289 1.387 1.387 1.474 1.474M 0.715 0.701 1.206 1.175 1.365 1.333 1.525 1.487 1.640 1.602 1.754 1.710V 0.714 0.714 1.083 1.059 1.190 1.183 1.295 1.295 1.395 1.395 1.484 1.484M 0.721 0.703 1.195 1.159 1.358 1.319 1.521 1.475 1.643 1.596 1.765 1.712V 0.717 0.717 1.067 1.066 1.190 1.190 1.303 1.303 1.405 1.405 1.496 1.496M 0.724 0.711 1.180 1.149 1.342 1.308 1.505 1.465 1.632 1.592 1.759 1.713V 0.722 0.722 1.075 1.075 1.199 1.199 1.313 1.313 1.416 1.416 1.509 1.509M 0.726 0.718 1.170 1.143 1.331 1.300 1.492 1.457 1.623 1.588 1.755 1.714V 0.728 0.728 1.086 1.086 1.209 1.209 1.323 1.323 1.428 1.428 1.523 1.523M 0.734 0.726 1.165 1.141 1.323 1.296 1.482 1.452 1.616 1.584 1.751 1.714V 0.737 0.737 1.098 1.098 1.221 1.221 1.335 1.335 1.441 1.441 1.537 1.537M 0.745 0.736 1.163 1.141 1.320 1.296 1.477 1.450 1.612 1.583 1.747 1.715V 0.746 0.746 1.110 1.110 1.233 1.233 1.348 1.348 1.455 1.455 1.552 1.552M 0.753 0.745 1.158 1.144 1.313 1.297 1.468 1.449 1.602 1.582 1.736 1.715V 0.756 0.756 1.123 1.123 1.247 1.247 1.362 1.362 1.469 1.469 1.568 1.568M 0.760 0.753 1.156 1.144 1.309 1.295 1.462 1.447 1.596 1.579 1.729 1.711V 0.768 0.768 1.137 1.137 1.260 1.260 1.376 1.376 1.484 1.484 1.584 1.584M 0.768 0.762 1.157 1.147 1.308 1.297 1.459 1.446 1.592 1.578 1.725 1.710

21

22

23

24

25

15

16

17

18

19

20

9

10

11

12

13

14

3

4

5

6

7

8

1

2

9x13 t56 t 5x13 t 6x13 t 7x13 t 8x13 t

CIRC_1962SPAN

(m)

Page 48: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

48

In Table 5 the association of the cell colors used in Fig. 22 with critical live load

multiplier (η) is shown.

Table 5: Critical live load multiplier and assigned colors

Critical live load multiplier Color

η ≤1

1 < η ≤ 1.1

1.1 < η ≤ 1.3

1.3 < η ≤ 1.6

η > 1.6

Knowing the critical live load multipliers for each bridge, it is possible to define a

priority ranking for future assessments. If η is slightly greater than 1, there is a

high probability that by applying Level 1 assessment the verifications become

positive. As η increases, this probability is smaller and smaller.

It is worth emphasizing that a critical live load multiplier η of less than 1.0 can

have different impacts on the overall safety of the bridge, depending on the

magnitude of the dead load. For example, a live load multiplier of 0.90 could be

critical for short span steel girder bridges, where the live load is dominant, but is

likely to be much less critical for a long span reinforced concrete bridge, where

the dead load dominates.

An index that better reflects bridge understrength with respect to the overweight

load is the lack of capacity factor α, defined as the percentage of additional

capacity R needed to safely carry the overweight load. For girder bridges this

coefficient indicates how much the most critical bending moment or shear stress

must increase for positive verification of the bridge. There is a direct relationship

between indices α and η. If R is the capacity of the bridge at a specific limit state

and SAPT is the overweight load demand, the lack in capacity α of the bridge can

be expressed as follows (13):

0 0

0 0

( 1) 1

1 1

APT G S G SS R S

R R G S G S

(13)

where G is the effect of the dead load and S0 is the effect of the live load. Equation

(13) shows that computing index requires knowledge of the G/S0 ratio for the

bridge, and this in turn depends on the bridge characteristics as included in the

design documentation, normally not known for a Level 0 assessment. To estimate

index at Level 0, a practical solution is to provide approximate expressions for

Page 49: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

49

the dead loads of various bridge structures and span lengths. To do this, it is

necessary to evaluate, for each main deck type, the weight of the bridge in a

number of case studies (Table 6) and then to extrapolate the relative interpolating

curve (Fig. 23a). This curve provides the weight of a lane width of 3 meters as a

function of the bridge span.

The graphs in Fig. 23 show the dead load of a 3 m wide lane calculated for a

sample of bridges of differing construction technologies, with proposed fitting

curves that can be used to estimate the dead load once the bridge span is known.

Table 6: Weight of reinforced concrete bridges

Reinforced concrete girder bridge

Span length

[m]

P/L (lane of 3m)

[kN/m]

3.0 34

7.4 36

12.4 37

20.0 37

25.0 43

33.7 67

a) reinforced concrete girder b) precast reinforced concrete girder

0

10

20

30

40

50

60

70

80

0 10 20 30 40 50

de

ad lo

ad g

[kN

∙m‾¹

]

span length L [m]

0

10

20

30

40

50

60

70

80

0 10 20 30 40

dea

d lo

ad g

[kN

∙m‾¹

]

span length L [m]

Page 50: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

50

c) steel girder d) reinforced concrete slab

e) precast reinforced concrete slab f) reinforced concrete box girder

g) steel-concrete box girder f) arch bridges

Fig. 23: Bridge span to dead load relationship for various bridge technologies: experimental

samples and fitting curves

3.6 Risk interpretation of parameter

This section provides the risk interpretation of parameter α in terms of the

probability of failure of a substandard bridge caused by the APT load.

0

10

20

30

40

50

60

70

80

0 20 40 60 80

de

ad lo

ad g

[kN

∙m‾¹

]

span length L [m]

0

50

100

150

200

250

0 5 10 15 20 25

de

ad lo

ad g

[kN

∙m‾

¹]

span length L [m]

0

10

20

30

40

50

60

70

80

0 10 20 30 40 50 60

de

ad lo

ad g

[kN

∙m‾

¹]

span length L [m]

0

10

20

30

40

50

60

70

80

0 10 20 30 40

de

ad lo

ad g

[kN

∙m‾¹

]

span length L [m]

0

10

20

30

40

50

60

70

80

0 5 10 15 20

de

ad lo

ad g

[kN

∙m‾¹

]

span length L [m]

0

10

20

30

40

50

60

70

80

15 20 25 30 35 40

de

ad lo

ad g

[kN

∙m‾

¹]

span length L [m]

Page 51: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

51

To determine the reliability index and the probability of failure caused by the APT

load on a substandard bridge, it is necessary to evaluate the reliability of the

design code. In other words, the aim is to determine the reliability index and the

probability of failure of the bridge foreseen by the design code. The fundamental

hypothesis is that the designer has strictly followed the design code. It is assumed

that the probability of failure of the bridge that is implicit in the design code (PF0) is

the following (14):

50 10FP 5

0 10FP 50 10FP 5

0 10FP (14)

Consequently, the a priori reliability index (β0) is the following (15):

26410 510

10 .

FP (15)

where Φ is the normal cumulative distribution function with mean value μ=0 and

standard deviation σ=1.

In general the a priori reliability index can be expressed as follows (16):

20

20

0500500

SR

SR

%,%, (16)

where R50% and S50% are the mean values of the normal distributions of capacity

and demand respectively, σR and σS are the standard deviation of the normal

distributions of capacity and demand respectively, and the subscript 0 indicates

the design code.

The reliability index concerning the movement of the overweight load (βOL) can be

expressed as follows (17):

20

20

50050

SR

OLOL

SR

%,%, (17)

where S50%,OL is the mean value of the normal distributions of the demand caused

by the APT load.

The ratio between the two reliability indexes can be expressed as follows (18):

Page 52: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

52

050050

50050

20

20

050050

20

20

50050

0 %,%,

%,%,

%,%,

%,%,

SR

SR

SR

SR

OL

SR

SR

OL

OL

(18)

If it is assumed that the ratio between the mean and the design value of the

demand caused by the overweight load (Sd,OL) is equal to the ratio between the

mean and the design value of the initial demand (Sd,0), we can write (19):

0

05050

,

%,

,

%,

dOLd

OL

S

S

S

S (19)

S50%,OL is expressed as follows (20):

10500

50050

0

5005050 %,

,

%,%,

,

%,%,%, S

R

SS

S

SSS

d

OL

d

OLOL (20)

where it is assumed that the design demand is equal to the design capacity

Sd0=Rd0. Equation (18) can therefore be expressed as follows (21):

1

1

1

0

0

050

050

050

050

050

050

050

050

0

m

mOL

S

S

S

R

S

S

S

R

%,

%,

%,

%,

%,

%,

%,

%,

(21)

where γm0 is the mean safety factor (22) (23).

050

095

095

0

0

0

0

05

05

050

050

0500

%,

%,

%,

,

,

,

,

%,

%,

%,

%,

%,

S

S

S

S

S

R

R

R

R

R

S

R d

d

d

dm (22)

Page 53: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

53

R

SSRm

CoVk

CoVk

1

10 (23)

where γS and γR are the partial factor for the demand and capacity respectively,

and the relationships between the characteristic and mean value of the capacity

and demand are the following (24) (25):

RR CoVkRkRR 150505 %%% (24)

SS CoVkSkSS 1505095 %%% (25)

where R5% and S95% are the characteristic values of the normal distributions of

capacity and demand respectively, CoVR and CoVS are the coefficient of variation of

the normal distributions of capacity and demand respectively, and k is the

characteristic fractile factor equal to k=1.645.

Assuming the following values for the partial factor and for the coefficient of

variation of the demand and capacity, the relationship between the failure

probability and the lack of capacity is obtained (Fig. 24).

CoVR = 7.5%

CoVS = 15%

γR = 1.2

γS = 1.4

In Table 7 the association of the failure probability (Pf) with the lack of capacity (α)

of the bridge is shown.

Page 54: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

54

Fig. 24: Relationship between failure probability and α

Table 7: Failure probability and lack of capacity

Failure probabilty Lack of capacity

Pf = 10-5

α=0

10-5

< Pf < 4∙10-5

0 < α < 0,1

4∙10-5

< Pf < 2∙10-4

0,1 < α < 0,2

2∙10-4

< Pf < 5∙10-4

0,2 < α < 0,3

Pf > 5∙10-4

α > 0,3

3.7 Conclusions

In order to limit costs, the assessment of the capacity of a bridge stock needs a

simplified and conservative approach first, and then, if a higher load rating is

required, a refining of the analysis. This Chapter has defined the assessment

procedure to manage the problem of the overweight traffic, with various simplified

levels of refinement, from Level 0 to Level 3. It has been shown that in the case of

free road traffic, the result of the assessment depends only on the maximum span

and on the year of bridge design (i.e. on the design loads of the design code).

Furthermore it is completely independent of the mechanical conditions of the

bridge. Moreover we obtained that in the case of a road closed to free traffic and

bridge transit in the center of the roadway, transit of the overweight load on the

bridge also depends on the transverse load distribution. The procedure has been

split for girder and arch bridges because of different resistance mechanisms of

the two typologies.

1.0E-05

1.0E-04

1.0E-03

1.0E-02

1.0E-01

1.0E+00

0 0.2 0.4 0.6 0.8 1 1.2

Fail

ure

Pro

bab

ilit

y

Lack of capacity α

Page 55: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

55

To quantify the extent of the deficiency of the substandard bridges, a

classification has been made by defining the lack of capacity factor α. This index

reflects bridge understrength with respect to the overweight load and has been

defined as the percentage of the additional capacity needed to safely carry the

overweight load. Finally, the risk interpretation of parameter α in terms of the

probability of failure of a substandard bridge caused by the APT load has been

provided.

Page 56: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

56

Page 57: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

57

4 APPLICATION TO CASE STUDIES

4.1 Introduction

In Chapter 3, the general method to verify bridges under overweight loads was

shown. The assessment procedure involves three levels of refinement to improve

the verification of the bridge. In this Chapter I apply the methodology to two case

studies representative of the two typologies of bridges (girder and arch bridges) in

order to test the method. Although Level 3 assessment was not considered in the

case studies due to the costs involved in obtaining the updated material

properties based on in-situ tests, a simulation of this assessment level is

performed in order to show the methodology when in-situ tests are available.

4.2 Case studies

The two case studies analyzed are:

Fiume Adige bridge, SP90 km 1.159;

Rio Cavallo bridge, SS12 km 362.164.

As discussed above these two case studies are representative of the two

typologies in which bridges can be classified. Fiume Adige is a girder bridge while

Rio Cavallo is an arch bridge. It is worth pointing out that the methodology

proposed is valid for all the typologies of bridges, which are clearly more than two

(suspension bridges, cable-stayed bridges etc.). All types of bridges, except arch

bridges, can be evaluated as they were girder bridges. In fact, the method

foresees the comparison among demands caused by design loads and reference

loads (APT loads). Therefore, as discussed in Section 3.4.1, when the original

design load produces static stresses higher than the new overweight vehicle in a

Page 58: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

58

simply supported span, the design stresses will be higher with a statically

indeterminate boundary condition. This is to say that the typology of the bridge is

irrelevant to the comparison (except arch bridges), so a simply supported

condition, choosing an appropriately span length, can always be assumed. For

instance in the case of a cable-stayed bridge the length among two cables must

be chosen for the calculation rather than the total span length, because the

cables are actually supports.

4.2.1 Fiume Adige

The bridge is located in the Municipality of Rovereto, close to the town of Trento,

Italy. The bridge is shown in Fig. 25. It is a four span prestressed concrete bridge,

built in 1980, with the maximum span L=33.12m. The deck has an overall width of

9.50m and carries a 7.50m roadway and two 1.25m sidewalks. The deck structure

of the 3 main spans is made up of 10 precast 1.44m double T girder elements per

span, with a 0.18m cast-in-place concrete deck, while the shortest span is made

up of 42 prefabricated elements pulled together with a cast-in-place concrete

deck.

The main dimensions of the structure are reported in the following:

bridge length: 106 m

first span

o length: 6.5 m:

o girder spacing and number of girders: 0.21 m / 42 elements

o total thickness of precast reinforced concrete slab: 0.45m

other spans

o length: 32.13m-33.12m

o girder spacing and number of girders: 0.92 m / 10 elements

o deck thickness: 0.18m

deck width: 9.5 m

carriageway width: 7.0 m

The design codes used by the bridge designer are the following:

D.M. 26/03/1980 “Norme tecniche per l’esecuzione delle opere in

cemento armato normale, precompresso e per le strutture metalliche.”

D.M. 02/08/1980 “Criteri generali e prescrizioni tecniche per la

progettazione, esecuzione e collaudo di ponti stradali.”

Page 59: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

59

CNR-UNI 10018/72 “Istruzioni per il calcolo e l’impiego di apparecchi di

appoggio in gomma nelle costruzioni.”

a)

b)

Fig. 25: a) and b): “Adige Bridge”, Municipality of Rovereto (TN, Italy)

Page 60: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

60

Fig. 26: Geometry of the Fiume Adige bridge

The lack of capacity () depends on the overweight load. Table 8 shows the lack

of capacity for each APT load using Level 0 assessment. These values are

calculated by a Matlab program (see Chapter 6) with the methodology described

in Chapter 3.

Table 8: Results of Level 0 assessment

APT load Level 0 assessment ()

56 tons 0.00

5x13 tons 0.14

6x12 tons 0.16

6x13 tons 0.21

7x13 tons 0.27

8x13 tons 0.33

9x13 tons 0.39

The design loads used by the bridge designer are the following:

permanent load of the deck (sum of structural and non-structural loads):

o G = 14.457t/m.

traffic loads:

32.12

2.7

0

8.5

2

9.2

26.6

76.5

6

6.4

2

106.13

32.6333.1332.687.15

1.00

1.601.60

1.60

1.80

6.44

1.00

31.68

0.60

1.05

31.63

1.00

C2 C3 C4 C5C1

Adige river

<--- p=2,1%I2I1I3 I4

P2 P3

S2S1

P1Isera

Rovereto

B

B

A

A

LONGITUDINAL SECTION

1.257.00

1.259.50

0.3

3

0.5

0

6.4

4

6.5

7

9.38

S1

1.257.00

1.259.50

0.5

0

2.0

2

9.10

7.00

0.50 0.508.00

P2

A-A TRANSVERSAL SECTION B-B TRANSVERSAL SECTION

Adige river

Page 61: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

61

o lane number 1: uniformly distributed loads q1a = 4.509 t/m;

o lane number 2: uniformly distributed loads q1b = 2.166 t/m;

o remaining area: uniformly distributed loads qf=0.4t/m2.

the dynamic response coefficient of span 2, 3 and 4 is the following:

o Φ= 1.211

The design loads and the dynamic response coefficient reported above refer only

to spans 2, 3 and 4. This is because, for the sake of brevity, in the following I

report the details of the calculations only for these spans.

Level 1 assessment

As mentioned in Section 3.3, in Level 1 assessment the evaluator is required to

examine the design documents to verify whether the critical structural members

are oversized. This level of assessment is based only on the analysis of the

existing documents, without revising the assumed material properties or

calculation model. The evaluator repeats the structural calculations, replacing the

design traffic lane with the APT load. He/she calculates the effects caused by the

new loads and verifies that they are less than the capacity of the bridge. If one

verification is negative, the evaluator calculates the lack of capacity of the bridge

(α), as reported in Section 3.5. The verifications of the following structural

elements are performed:

decks;

columns;

abutments;

supports made of neoprene.

For each element a number of verifications are performed, such as the verification

of the bending moment and shear stress. For the sake of brevity, I report the

details of the calculations of the deck element only.

Free Travel

The design documentation includes the Massonnet-Guyon-Bares transverse load

distribution. In the following it is reported the calculation of the most stressed

beam that has an eccentricity of 1.410m from the center of the deck. In Fig. 27

the transverse position of loads and resulting Massonnet-Guyon-Bares transverse

load distribution are represented, while in Table 9 their values are reported.

Page 62: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

62

Table 9: Transverse redistribution of loads for free travel

Loads Eccentricity (m) K (Massonnet) Q (t/m)

qf1 (Right side

remaining area) 4.000 1.254 0.4

q1a 1.750 1.563 4.509

q1b -1.750 0.761 2.166

qf2 (Left side

remaining area) -4.000 0.096 0.4

The total load on the most stressed beam can be calculated as follows (26):

[( ) ]

(26)

where ngirders is the number of prefabricated double T girder elements, equal to

ngirders=10.

The design value of the bending moment (Me) is the following (27):

(27)

where l is the span length.

The resistance moment reported in the design documentation is as follows (28):

(28)

Fig. 27: Transverse position of loads and resulting Massonnet-Guyon-Bares transverse

load distribution (free travel)

Page 63: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

63

If the q1a load is replaced with, for example the 6 x 13 t = 78 tons APT load (Fig.

27 and Fig. 28), the design bending moment on the most stressed beam is equal

to (29):

(29)

Fig. 28: Transverse position of loads and resulting Massonnet-Guyon-Bares transverse

load distribution obtained replacing q1a with APT load (free travel)

Table 10 shows the verifications of the bending moment on the most stressed

beam for each APT load. The resistance moment reported was calculated by the

bridge designer for the design documentation. The safety factor foreseen by the

design code is equal to ηr =1.85, and then the verification is positive if the ratio

between the resistance moment and design moment is greater than:

(30)

Table 10: Bending moment verification (free travel)

APT load Mr (tm) Me (tm) ηr lack of capacity (α)

56t 620.56 294.49 2.107 0.00

5x13t 620.56 325.78 1.905 0.00

6x12t 620.56 330.19 1.879 0.00

6x13t 620.56 338.20 1.835 0.01

7x13t 620.56 350.62 1.770 0.05

Page 64: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

64

8x13t 620.56 361.93 1.715 0.08

9x13t 620.56 373.21 1.663 0.11

The same procedure was followed to perform the shear verfication of the most

stressed beam. The shear verification involves comparing the shear stress

caused by the design load with the limit shear stress τc1=24 kg/cm2(D.M.

26/03/1980). The shear stress is equal to the sum of two contributions: the first

caused by the structural permanent loads considering only the prefabricated

double T girder elements and the second caused by the non-structural permanent

and traffic loads considering the whole cross-section (girder element + cast-in-

place concrete deck). The first contribution is independent of the traffic loads and

had been already calculated by the bridge designer. Therefore, only the second

contribution had to be calculated replacing the design load with the APT load.

For the sake of brevity the results of the verification are reported without showing

the calculations (Table 11).

Table 11: Shear verification (free travel)

APT load total shear stress τe

(Kg/cm²)

limit shear stress τc1

(Kg/cm²)

lack of capacity

(α)

56t 17.26 24 0

5x13t 17.91 24 0

6x12t 17.98 24 0

6x13t 18.12 24 0

7x13t 18.32 24 0

8x13t 18.51 24 0

9x13t 18.69 24 0

In addition to the ultimate verification here, I report also the serviceability

verification which involves checking the stress at the top (σS,TOT) and bottom (σI,TOT)

edge of the beam. The limits of compression (σc) and tension stress (σt) included

in the design code are the following:

σc < 0.38 Rck = 0.38∙460 kg/cm² = 174.8 kg/cm²

σt < 0.06 Rck = 0.06∙460 kg/cm² = (-) 27.6 kg/cm²

Also in this case the total stress is obtained by the sum of two contributions: the

first caused by the structural permanent loads considering only the girder

elements and the second caused by the non-structural permanent and traffic

loads considering the whole cross-section. Fig. 29 shows a part of the original

Page 65: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

65

design documentation where the red arrow indicates the effects of the traffic load

that has to be replaced by the APT load. Table 12 shows the results of the

verification.

Fig. 29: scan of a part of the original design documentation

Table 12: Serviceability verification (free travel)

APT

load

σS,TOT

(kg/cm²)

lack of capacity

(α)

σI,TOT

(kg/cm²)

lack of capacity

(α)

56t 162.19 0.00 -2.60 0.00

5x13t 172.04 0.00 -20.69 0.00

6x12t 173.43 0.00 -23.25 0.00

6x13t 175.95 0.01 -27.88 0.01

7x13t 179.86 0.05 -35.06 0.04

8x13t 183.43 0.08 -41.61 0.07

9x13t 186.98 0.12 -48.13 0.11

The verifications are summarized in Table 13.

Page 66: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

66

Table 13: Summary of Level 1 assessment (free travel)

APT load Level 0

()

Bending moment

Level 1

()

Shear stress

Level 1

()

serviceability verification

Level 1

()

56t 0.00 0.00 0.00 0.00

5x13t 0.14 0.00 0.00 0.00

6x12t 0.16 0.00 0.00 0.00

6x13t 0.21 0.01 0.00 0.01

7x13t 0.27 0.05 0.00 0.05

8x13t 0.33 0.08 0.00 0.08

9x13t 0.39 0.12 0.00 0.12

Bridge crossed in the center of the roadway

The verifications shown above have to be performed for traffic crossing the bridge

in the center of the roadway as well. The differences with respect to the

verification with free travel are the transverse position of the vehicle in the

carriageway and the absence of the second traffic lane.

The following shows the calculation of the most stressed beam, which, in this

case, is located in the center of the deck. Fig. 30 shows the transverse position of

loads and resulting Massonnet-Guyon-Bares transverse load distribution while in

Table 9 their values are reported.

Table 14: Transverse redistribution of loads for bridge crossed in the center of the roadway

Loads Eccentricity (m) K (Massonnet) Q (t/m)

Right side remaining area 4.000 0.748 0.4

APT load 0.000 1.467 var

Left side remaining area -4.000 0.378 0.4

Page 67: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

67

Fig. 30: Transverse position of loads and resulting Massonnet-Guyon-Bares transverse

load distribution (bridge crossed in the center of the roadway)

For the sake of brevity, only the final results of the bending moment (Table 15)

and the serviceability (Table 16) verification are reported.

Table 15: Bending moment verification (bridge crossed in the center of the roadway)

APT load Mr (tm) Me (tm) ηr lack of

capacity (α)

56t 620.56 262.81 2.36 0.00

5x13t 620.56 292.17 2.12 0.00

6x12t 620.56 296.32 2.09 0.00

6x13t 620.56 303.83 2.04 0.00

7x13t 620.56 315.49 1.97 0.00

8x13t 620.56 326.10 1.90 0.00

9x13t 620.56 336.69 1.85 0.00

Table 16: Serviceability verification (bridge crossed in the center of the roadway)

APT

load

σS,TOT

(kg/cm²)

lack of capacity

(α)

σI,TOT

(kg/cm²)

lack of capacity

(α)

56t 152.20 0.00 15.72 0.00

5x13t 161.46 0.00 -1.26 0.00

6x12t 162.76 0.00 -3.66 0.00

6x13t 165.13 0.00 -8.01 0.00

7x13t 168.80 0.00 -14.75 0.00

8x13t 172.15 0.00 -20.89 0.00

9x13t 174.48 0.00 -27.01 0.00

Page 68: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

68

As can be noticed in Table 15 and Table 16, the verifications are positive for each

APT load. The shear verification is not reported as it was already verified for free

travel.

Level 2 assessment

Level 2 assessments are needed when the verification at Level 1 is not satisfied.

In this case only the bending moment verification is required at Level 2 as the

shear verification was positive at Level 1.

As mentioned in Section 3.3, at Level 2 the evaluator reassesses the bridge

capacity using more refined models than those used by the original designer.

Often, a capacity increase is achieved by considering inelastic behavior and

spatial stress redistribution. In this case the deck is made by 10 simple supported

beams and the increase in the capacity is made possible by considering a

different transverse redistribution of the loads. In fact, the bridge designer used an

elastic transverse distribution of the loads and so it is possible to increase the

capacity by considering a plastic transverse distribution (Fig. 31).

Fig. 31: Plastic and elastic transverse distribution.

The value of qneg (Fig. 31) is equal to qneg = 0 in favor of safety, the unknowns are

x and qpos, which can be determined by imposing the equilibrium of the system.

The maximum uniformly distributed load qpos,max on the deck is equal to (33):

Page 69: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

69

[

⁄ ]

(31)

where Mr is the resistance moment of the beam, 1.85 is the partial safety factor

and i =0.95 is the spacing between two girders.

Imposing the equilibrium of the system (32) and (33):

( ) Φ (32)

(

) (

) Φ (33)

where b = 9.50m is the width of the deck, ϕ = 1.211 is the dynamic response

coefficient, qf = 0.4 t/m, qneg=0, q1b = 2.166t/m, and G = 14.457 t/m is the sum of

structural and non-structural permanent loads.

Here, in the equilibrium of the system equations the loads were imposed.

Therefore, it is necessary to determine the APT uniformly distributed load (qAPT)

that produces the same effects (in terms of maximum bending moment) as the

real APT load (for example 6x13 tons APT load). If the 6x13 tons APT load is

considered, the 6x13t APT uniformly distributed load is equal to qAPT,6x13t = 4.813

t/m, and the following results are obtained:

x=9.07 m

qpos,6x13t=2.589 t/m

where qpos,6x13t is the resultant value of qpos considering the 6x13t APT uniformly

distributed load.

The verification is positive (see equation (34)) and the new partial safety factor is

obtained from equation (30):

(

)

(34)

Table 17 and Table 18 report the final results for each APT load and assessment

level.

Page 70: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

70

Table 17: Summary of the final results (free travel)

APT load Level 0

()

Bending

moment

Level 1

()

Bending

moment

Level 2

()

Shear

stress

Level 1

()

Serviceability

verification

Level 1

()

56t 0.00 0.00 0.00 0.00 0.00

5x13t 0.14 0.00 0.00 0.00 0.00

6x12t 0.16 0.00 0.00 0.00 0.00

6x13t 0.21 0.01 0.00 0.00 0.01

7x13t 0.27 0.05 0.00 0.00 0.05

8x13t 0.33 0.08 0.03 0.00 0.08

9x13t 0.39 0.12 0.06 0.00 0.12

Table 18:Summary of the final results (bridge crossed in the center of the roadway)

APT load Level 0

()

Bending

moment

Level 1

()

Shear stress

Level 1

()

Serviceability

verification

Level 1

()

56t 0.00 0.00 0.00 0.00

5x13t 0.00 0.00 0.00 0.00

6x12t 0.00 0.00 0.00 0.00

6x13t 0.00 0.00 0.00 0.00

7x13t 0.02 0.00 0.00 0.00

8x13t 0.05 0.00 0.00 0.00

9x13t 0.08 0.00 0.00 0.00

Level 3 assessment

Level 3 assessment foresees that the evaluator can update the characteristic

values of the variables used in the assessment, based on the results of material

testing and observations. As discussed above, the procedure leaves the evaluator

free to test the materials, without specifying the minimum number of samples or

the type of test. However, if the evaluator wants to use the test results

quantitatively, a Bayesian probabilistic update technique should be applied.

In this case study, Level 3 was not considered due to the costs involved in

obtaining the updated material properties based on in-situ tests. However, a

simulation of Level 3 assessment has been performed in order to show the

methodology when in-situ tests are available.

Page 71: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

71

Bayesian inference is a tool that is able to treat various types of information

following a unified approach (Sonda et al., 2003). In our case Bayesian inference

can be used to update the a priori probability distribution function using

information obtained from experimental tests (a posteriori) In Section 5.6 a brief

introduction to Bayesian statistics is given while in the following only the

application to the updating of a random variable is described (Fig. 32).

Fig. 32: Updating of a random variable (Sonda et al., 2003)

The basic assumption in the following is that all the random variables could be

described by Gaussian likelihood functions.

The a priori information of the random variable x can be expressed as follows

(35):

data collection through quality control Bayesian analysis

Updating of prior

information

a priori distribution

a posteriori distribution

Page 72: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

72

(35)

where μ0 is the mean value and σ0 is the standard deviation of the a priori

Gaussian likelihood function. This distribution take into account all the

uncertainties that can be estimated a priori, including those regarding the mean

value. If μ1 represents the local uncertainties of the mean value μ0, μ1 can also be

considered a random value (36):

(36)

As can be noticed, the mean value is still equal to μ0, while the standard deviation

σ2 is a part of σ0, the standard deviation of the random variable x.

If μ1 is known, the conditional probability of the random variable x can be

expressed as follows (37):

(37)

where (38):

(38)

Where a sample of n observations for the random variable x is available (x ),

using Bayes’ theorem the conditional probability of μ1 can be expressed as

follows (39):

(39)

where is the likelihood and is equal to (40):

(40)

Having determined from equation (39), the updated probability distribution

function of the random variable x, is equal to (41):

Page 73: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

73

(41)

From equations (35), (36) and (37), the following equation can be obtained (42):

(42)

where:

(43)

(44)

(45)

The distribution function (42) is equal to equation (36) updated with the sample of

n observations of the random variable x. The parameters μ3 and σ4 are the

corresponding μ0 and σ2 assumed a priori.

Substituting equations (36) and (37) into (40), the updated distribution function of

the random variable x can be obtained (46):

(46)

where (47):

(47)

The methodology discussed above can be used here in the Fiume Adige case

study to update the properties of the materials. Level 3 assessment should be

used only in the case of a negative verification of Level 2 assessment. In this

case the bending moment verification provides negative results. The material that

most influences the capacity of the resistance moment of a precast girder is the

steel, as the concrete determines only the height of the neutral axis and so the

Page 74: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

74

improvement in the capacity would be very small. Therefore, it is useful to perform

experimental tests only for the strands.

Let us suppose that the evaluator samples three strands and tests them with a

tensile standard test. The characteristic value of strength of prestressing steel

obtained from the design documentation is ftk=1900 MPa. Let us suppose that the

results of the tests are those reported in Table 19.

Table 19: Results of tensile standard tests of the strands

Sample ftk (MPa)

1 2021

2 1999

3 2219

We use the methodology discussed above and assume a Gaussian distribution

function for both a priori and a posteriori distribution of strength of prestressed

steel. We assume the following values that characterize the a priori distribution,

as recommended by Zandonini et al. (2012):

fptk=1900 MPa

σ0=74 MPa

which corresponds to a mean value of fpt0=2021 MPa. Where there is no

information on the value to assume for σ1 and σ2 Zandonini et al. (2012) advises

choosing (48):

(48)

From equations (38) and (48) we obtain (49):

(49)

Substituting the values in the equations (43), (44), (45) and (47) we obtain (50),

(51), (52) and (53):

(50)

Page 75: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

75

(51)

(52)

(53)

The updated characteristic value of strength of prestressing steel can be obtained

from the equation (54):

(54)

It can be noticed that the increment in the nominal value that can be used for the

calculations is equal to 3.6%. This means that in this case, Level 3 assessment

shows a decrease in the lack of capacity of 3.6%.

4.2.2 Rio Cavallo

The bridge is located in the Municipality of Calliano, close to the town of Trento,

Italy. The bridge is shown in Fig. 33. This is a four multiple arch bridge, built in

1940, with the span length l=12m. The carriageway is 11m in overall width. The

arch thickness at the crown is 0.60m and at the abutment is 0.90m. The

maximum thickness of the backfill is 1.9m.

The main dimensions of the structure are reported in the following and in Fig. 34:

Total bridge length: 55.4 m

Number of span: 4

Arch length: 12 m

Rise: 2.4 m

Arch thickness at the crown: 0.6 m

Arch thickness at the abutment: 0.9 m

deck width: 11 m

Page 76: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

76

a)

b)

Fig. 33: a) and b): “Rio Cavallo”, Municipality of Calliano (TN, Italy)

Page 77: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

77

Fig. 34: Geometry of the Rio Cavallo bridge

Table 8 shows the lack of capacity for each APT load using Level 0 assessment.

As for Fiume Adige bridge, these values are calculated by a Matlab program with

the procedure described in Chapter 3.

Table 20: Results of Level 0 assessment of the Rio Cavallo bridge

APT load Level 0 assessment ()

56t 0.20

5x13 tons 0.33

6x12 tons 0.30

6x13 tons 0.33

7x13 tons 0.33

8x13 tons 0.33

9x13 tons 0.33

The design code used by the bridge designer is the following:

MM.LL.PP. Normale n.8 15/09/1933

The bridge designer did not use the traffic loads foreseen by the design codes but

imposed a distributed uniformly load of 1000 kg/m2. He/she justified this choice

saying that for the arch bridge this load has greater effect than the design load.

2,6

2,6

2,6

55,4

1,62 11 1,62

2,95

2,6

0,8

2,95

A-A TRANSVERSAL SECTION

122,6

2,2

12 12 12

2,2

2,95

2,95

12 2.4

0,6

0,9

S1

A1

P1 P2 P3S2

A4A3A2

A

APERSPECTIVE DRAWING

LONGITUDINAL SECTION

Page 78: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

78

The permanent loads used by the bridge designer are the following:

Arch weight: G1 = 2100 kg/m2

Backfill weight: G2 = 2100 kg/m2

Level 1 assessment

The verification of the arch is carried out with an equilibrium analysis checking the

most stressed cross-sections of the arch. This is the same procedure followed by

the bridge designer. Level 1 assessment is based only on the analysis of the

existing documents, without revising the assumed material properties or

calculation model. Although the calculation model is reported in the

documentation, it is impossible to simply replace the APT load with design load as

the verifications are obtained graphically. Since the load distributions are different,

the thrust line is different too. Automatically Level 1 assessment does not involve

improvements in the capacity and it is also necessary to make some additional

hypotheses to those made by the bridge designer. This means that Level 1

assessment is not useful for arch bridges and only Level 2 assessment can be

performed to verify the bridge.

Level 2 assessment

The equilibrium analysis made by the bridge designer foresees the verification of

the arch taking into account the loads acting on 1m of the arch width. For this

reason the verifications of the arch taking into account the free travel or the bridge

crossed in the center of the carriageway are the same. Assuming the same

hypothesis, here only half of the axle weight of the APT load is considered. In fact

the spacing between the two wheels is defined equal to 2m. This means that the

concentrated force acting on an arch of 1m width is equal to half of the axle

(13t/2=6.5t). Moreover, for the equilibrium analysis, the spread of the

concentrated forces of the APT load in the backfill is neglected. In other words, in

favor of safety, the load is considered as concentrated forces acting on the arch.

The bridge designer verified the arch with the following combination of the loads:

1) dead load (Fig. 35) that is equal to G1+ G2;

2) dead load and traffic load Q on the whole arch length (Fig. 36a);

3) dead load and traffic load Q on half arch length (Fig. 36b).

Page 79: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

79

Fig. 35: Dead load

a) b)

Fig. 36: a) Dead load and traffic load on the whole arch length, b) dead load and traffic load

on half arch length

The same load combinations are considered, replacing the traffic load with the

APT load. Clearly the first combination has not been performed in the following,

as it remains the same as that computed by the bridge designer.

Firstly, the verification considering the APT load located on the whole arch length

is performed. Only the verification of the 9x13t APT load is reported here. It

should be noticed that if the 9x13t APT load is verified the other APT loads are

verified too.

To verify the arch element it is sufficient demonstrate that there exist a

satisfactory line of thrust that balances the given loading (Heyman, 1982). In other

words it is sufficient to find a thrust line in equilibrium with the external loading

which lies everywhere within the arch ring (Heyman, 1982).

To perform the equilibrium analysis of the arch, it is possible to study only half of

the arch length, considering the symmetry of the arch. As already mentioned, the

g

q

g

q

g

q

Page 80: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

80

concentrated load is equal to half of the weight of one axle and only 1m width of

the arch is studied. Therefore, the load is equal to (55):

(55)

At the crown the load acting is equal to half of Q since only half of the arch is

studied. The numerical results and the equilibrium analyses (Fig. 37) are reported

in the following:

Fig. 37: Construction of the funicular polygon

Hs = 85351 kg

Hc = 60023 kg

where R is the resultant force of the loads, and Hs and Hc are the thrust at the

abutment and at the crown respectively. As can be seen in Fig. 37, the thrust line

is always within the middle third and consequently the cross-sections are always

compressed. Following the same procedure reported by the bridge designer, the

Hc

Hs

Page 81: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

81

compression stresses (σI,c) at the crown and at the abutment (σI,s) are checked.

The results are reported in the following:

(56)

(57)

where A is the area, I is the momentum of inertia, y is the distance between the

baricenter and the compressive edge, and the subscripts c and s represent the

cross-sections at the crown and abutment respectively.

The compression stresses are very small and therefore the verification is positive.

Secondly, the verification considering the APT load located on half of the arch

length is performed. In this case the thrust line is not symmetrical and so the

whole arch is studied. The same hypotheses are assumed as in the previous

analyses. The numerical results and the equilibrium analysis (Fig. 38) are

reported in the following:

Hs = 83206 kg

Hc = 54181 kg

Fig. 38: Resulting thrust line with traffic load on half arch length

1

2

3 4

5 67

8 9 10 11 12 1314

15

16

17

18

Page 82: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

82

As can be seen in Fig. 37, the thrust line is not always within the middle third and

consequently tension stress appears at the edge of some cross-sections. The

thrust line, however, is within the thickness of the arch and consequently the

equilibrium is guaranteed (Heyman, 1982). The results of the two most stressed

cross-sections (called section 8 and 14 for their position in the arch) and the

cross-sections at the crown and at the most unfavorable abutment are reported:

(58)

(59)

(60)

(61)

(62)

(63)

Page 83: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

83

(64)

(65)

where the subscripts 8 and 14 represent the sections 8 and 14 respectively.

The results show that the stresses in the arch are very small and therefore the

verifications are positive. Also the shear stresses in the cross-sections of the arch

are always low and therefore the verifications are satisfied.

For the sake of brevity the calculations of the verifications of the piers and

abutments are not reported here. However, the total loads acting on these

elements are lower than the design load and so the verifications are automatically

positive.

In the following (Table 21 and Table 22) the final results for each APT load and

assessment level are reported. As can be noticed, the verification is satisfied in

both travel conditions (free travel and bridge crossed in the center of the

roadway).

Table 21: Results of Level 0 assessment (free travel)

APT load Level 0

assessment ()

Level 2

assessment arch

verification

()

Level 2

assessment pier

and abutment

verification

()

56t 0.20 0.00 0.00

5x13 tons 0.33 0.00 0.00

6x12 tons 0.30 0.00 0.00

6x13 tons 0.33 0.00 0.00

7x13 tons 0.33 0.00 0.00

8x13 tons 0.33 0.00 0.00

9x13 tons 0.33 0.00 0.00

Page 84: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

84

Table 22: Results of Level 0 assessment (bridge crossed in the center of the roadway)

APT load Level 0

assessment ()

Level 2

assessment arch

verification

()

Level 2

assessment pier

and abutment

verification

()

56t 0.20 0.00 0.00

5x13 tons 0.33 0.00 0.00

6x12 tons 0.30 0.00 0.00

6x13 tons 0.33 0.00 0.00

7x13 tons 0.33 0.00 0.00

8x13 tons 0.33 0.00 0.00

9x13 tons 0.33 0.00 0.00

4.3 Discussion of the results

In Section 4.2 the results of the application of assessment Levels 1 and 2 to the

two case studies have been reported. For the girder bridge Fiume Adige, both

assessment levels have been applied while for the arch bridge Rio Cavallo only

Level 2 assessment has been performed because, as discussed above, there is

no sense in the application of Level 1 assessment for this type of bridge.

The results obtained for the Fiume Adige show that the precision of Level 1

assessment reveals a higher level of capacity than that given by the simplified

model in Level 0 assessment (i.e. verify potential reserve of capacity by

examining the design documentation). In fact, in the case of free travel and of the

9x13t APT load, the decrease in parameter α is 27% (see Table 23). This value

represents the overstrength of the bridge with respect to the design loads. The

reason of the large decrease is that there are many more reinforcing bars than

necessary. The critical verification at Level 0 assessment was the shear

verification but the design code involves a minimum transverse reinforcement

greater than necessary. It is worth emphasizing that this result could not be

obtained a priori as the extent of the excess reinforcing bars is not known. For the

limit state where Level 1 assessment provided negative results (i.e. the capacity

is still insufficient), Level 2 assessment was performed. Refining the models used

by the bridge designer, an additional decrease in the lack of capacity () has

been obtained. For the bending moment a plastic transverse distribution of the

load instead of elastic has been used. The additional decrease from Level 1 to

Level 2 assessment in the lack of capacity was of 6% (Table 23). For shear, more

Page 85: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

85

refined models have not been used as the shear verification is positive in Level 1

assessment.

Table 23: Results of the case study Fiume Adige

Free Travel Level 0

()

Level 1

()

Level 2

()

APT load

9x13t 0.39 0.12 0.06

It should be noticed that the decrease in the lack of capacity between Level 1 and

Level 2 assessment is possible only for the limit states where an ultimate analysis

or a modification of the static model is possible. In general the serviceability

verifications cannot be considered in Level 2 as the elastic hypotheses of the

bridge designer cannot be changed.

The results obtained for the Rio Cavallo show that the bridge can withstand the

new APT loads. The verifications implied a complete re-assessment of the

elements of the bridge (arch, piers and abutments). All the verifications were

performed graphically drawing the funicular polygon in the elements. Safety is

calculated by checking that the thrust line is always within the elements and the

stress in each cross section is low enough. As can be seen in Table 24 the

verifications for the 9x13=117t APT load are positive. The large decrease in the

lack of capacity can be explained by the significant intrinsic geometrical factor of

safety of arch bridges. This is guaranteed by the high value of permanent loads of

arch bridges and by the hypothesis of the design. The assumption that the

material has an infinite compressive strength (Heyman, 1982) implies that the

stress are very low and in general an increase in the live load does not cause

structural problems to the bridge.

Table 24: Results of the case study Rio Cavallo

Free Travel Level 0

()

Level 2

()

APT load

9x13t 0.33 0.00

In both case studies, for the travel condition of the bridge being crossed in the

center of the roadway, the bridges are acceptable for each APT overweight

vehicle model. The reason is that the deck width is sufficient as there is more than

one line load and consequently that the vehicle crossing the bridge alone entails

the neglect of one or more line loads in the verifications.

Page 86: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

86

4.4 Conclusions

In this Chapter Level 1 and 2 assessment of the girder bridge Fiume Adige and

the arch bridge Rio Cavallo have been applied in order to test the method. The

Chapter has shown how to apply the procedure to two real cases and the

necessity to apply the method to each design verification performed by the bridge

designer.

In the case of the girder bridge Fiume Adige, the results have shown that,

performing Level 1 assessment, all the APT loads less than or equal to the 6x12t

are acceptable, while performing Level 2 less than or equal to the 7x13t

(considering only the collapse verifications). Level 0 analysis had shown that only

the 56t APT load was acceptable for the bridge. A simulation of Level 3

assessment was shown using Bayesian probabilistic technique to update the

characteristic values of the variables used in the assessment, based on the

results of material testing and observations.

In the case of the arch bridge Rio Cavallo the results have shown that all the APT

loads, in both travel conditions, can cross the bridge without reducing the original

design safety level. Also in this case Level 0 analysis had shown that only the 56t

APT load was acceptable for the bridge.

In conclusion, Level 1 and 2 assessment can lead to good decreases in terms of

the lack of capacity of the bridge that were, for example, equal to 33% in the case

of 9x13t APT load (free travel condition, Fiume Adige bridge).

Once again, these results could not be obtained a priori as the overstrength of the

bridge and the design structural details are not known.

Page 87: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

87

5 DECISION MAKING

5.1 Introduction

Decision making under uncertainty is about making choices whose consequences

are not completely predictable, because events will happen in the future that will

affect the consequences of actions taken now (Parmigiani & Inoue, 2009).

In Chapters 3 and 4 the criteria for re-assessing bridges for overweight loads and

the application to two case studies were shown. The application of Level 1 and 2

assessment were made automatically, without considering whether it was the

most rational choice. In fact, if the objective is to allow the travel of an overweight

load without reducing the original design safety level, when Level 0 assessment

shows that the lack of capacity is very high, the most rational choice could be the

full formal re-assessment of the bridge made by a structural engineer with

possible retrofit strengthening rather than proceeding with assessment levels 1, 2

and 3.

The aim of this Chapter is to define a decisional model to support the manager in

his/her choices. Therefore, the objective is to obtain a methodology to determine

the limit values of the lack of capacity (α), which make it more cost effective to

employ a certain assessment level (Level 1, 2 or 3) or a full formal re-assessment

with possible retrofit strengthening. In other words the goal is to propose a

decision making process to guide the manager in making the most cost effective

decision when selecting the appropriate assessment level.

In particular, in Section 5.2 and 5.3, I report the basic concepts of decision theory

and of expected utility theory. In Section 5.4 I define a general decision tree for

girder and arch bridges, and in Section 5.5 I show how to optimize the thresholds

of the lack of capacity α in order to minimize the expected costs. This aim is

pursued in order to guide the decision regarding the overweight load made by the

transportation agencies. In addition, in Section 5.6, a methodology to update

Page 88: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

88

parameters on the basis of a number of case studies is proposed. Bayesian

statistics is used to implement this methodology.

5.2 Basic concepts

The symbology used in this Chapter is taken from the master’s thesis of Cappello

(2013), who studied in depth some of the aspects included in the present thesis

by applying expected utility theory with the aim of demonstrating its advantages.

The decision tree (Fig. 39) is the appropriate representation of any process

involving decisions. In Fig. 39 the action a1 starts from the decision node (a

square), and leads to the chance node (a circle), which in turn leads to two

possible consequences θ1 or θ2. The probabilities associated with the states θ1

and θ2 are the values of pθ1 and pθ2 respectively. zθ1|a1 and zθ2|a1 are the

outcomes observed after the occurrence of the situations θ1 and θ2, and u(zθ1|a1)

and u(zθ2|a1) are the utilities assigned to these outcomes.

In a general decision process it is possible to have many actions aj and the set of

these actions is called A. Similarly, the set of the states θi is represented by the

symbol Θ. One can imagine that the outcome zθi|aj corresponding to the condition

θi, observed after the action aj is chosen, is often, but not always, an amount of

money. The set of all the outcomes is called Z.

Once the utility function u(zθi|aj) is known, the utility associated with an outcome

zθi|aj can be calculated. The utility function represents the utility that a decision

maker wants to associate to an outcome. There can be several utility functions

and the result, i.e. the value of the utility, depends on which one is chosen.

Different functions u(zθi|aj) can be useful to represent different cases of decision

making process.

Fig. 39: Example of a decision tree and symbols used

Pθ1 θ1

a1

zθ1|a1, u(θ1|a1)

Pθ2 θ2

zθ2|a1, u(θ2|a1)

Decision node Chance node

Page 89: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

89

5.3 Expected utility theory

The expected utility theory is a quantitative evaluation of the utility of the

outcomes. It provides the probability that each outcome will occur (Jordaan,

2005). The action chosen is the one that has the greatest expected utility.

The expected utility assigned to an action can be considered as the sum of the

utility of the outcomes (Cappello, 2013). The expected value can be calculated as

follows (66).

(66)

where the probability of the outcome p(z), if the action a is chosen, is equal to

(67):

(67)

As the higher U(a) the better, the optimal action a*, also called Bayes action, is

the one that maximizes U(a) (68):

(68)

which corresponds to the maximum expected utility (Parmigiani & Inoue, 2009).

If the Bayes action is chosen using losses, it is necessary to define the loss

function as the opposite of the utility (69):

(69)

where the space (θ,a) (Θ,A). Unlike the utility, the definition of the loss function

predicts that at least one action should be with zero loss (Cappello, 2013). As a

consequence, the regret loss function L(θ,a) has been defined (70), obtained as a

transformation of the utility-derived loss function (Cappello, 2013).

[ ] (70)

Defining the expected loss as follows:

Page 90: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

90

(a) ∑

(71)

the Bayes action a* can be determined as follows (72), using the same principle

of the expected utility already applied (68):

(72)

5.4 Decision tree

In this Chapter, I develop a method that can support the decision-making process

for the APT bridge stock. In particular, the aim is to obtain the limit values of the

lack of capacity (α) which makes it more convenient to employ a certain

assessment level. The various simplified assessment levels that are available for

the APT, as a consequence of a negative verification, were shown in Table 4.

Firstly, the hypothesis is to use a single level tree diagram (Fig. 40), that is, to

assume that when an assessment level has been taken, the only possible results

are either the positive verification of the bridge or its replacement. The decision

tree in Fig. 40 is valid only for girder bridges, as applying Level 1 and 3

assessment to arch bridges is not useful (see Chapter 3 and 4). The methodology

explained in the following is only a simple example to introduce the problem of the

determination of the limit values of the lack of capacity. After this example the

final decision tree and a more rigorous discussion will be shown.

Fig. 40: Example of tree diagram

>t3

t2<≤t3

t1<≤t2

0<≤t1

0Level 0

Level 2

Replacement

Accept

0

1

2

3

Replacement

Accept

Replacement

Accept

Replacement

≤0

>0

Accept

Level 1

Level 3

Page 91: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

91

Table 25 shows the cost of each type of assessment level as a function of the

total bridge cost (Cc). These are plausible values chosen by the author only in

order to explain the method. In the final decision tree the details of costs will be

shown and adapted to the real needs of the APT (see Chapter 6).

Table 25: Building cost percentage of different assessment levels.

Assessment Level Cost

Level 1 0.5%Cc

Level 2 1.5%Cc

Level 3 10%Cc

Replacement 100%Cc

A basic principle of the expected utility theory is here used to determine the

appropriate assessment level. Assuming a lognormal probability distribution for

the decrease in the lack of capacity from one assessment level to another, the

inverse cumulative distribution function describes the probability that, as a result

of a given assessment level, the verification becomes positive (73).

meanα

αln

β

1Φ1P (73)

where β is the lognormal standard deviation that incorporates aspects of

uncertainty; and αmean is the decrease in the lack of capacity after using a certain

assessment level. We imposed β equal to 0.7.

Table 26 lists the values of αmean that correspond to a probability of 50% that the

verification becomes positive. These values are the decrease in the lack of

capacity after the assessment level (see equation (74)). The values were chosen

by the author a priori. The mean decrease between two consecutive assessment

levels (Δα) is reported in Table 27.

(74)

Table 26: Coefficient corresponding to different assessment levels.

Assessment level αmean (αi)

Level 1 0.08

Level 2 0.12

Level 3 0.20

Replacement ∞

Page 92: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

92

Table 27: Mean decrease between two consecutive assessment levels.

Assessment level Δαmean (Δαi)

Level 1 0.08

Level 2 0.04

Level 3 0.08

Replacement ∞

Fig. 41 shows the inverse cumulative distribution function obtained using the

values shown in Table 26. It represents the probability of obtaining a positive

verification after using a certain assessment level as a function of the lack of

capacity (α).

Fig. 41: Probability of obtaining a positive verification after using a certain assessment level

as a function of α.

Once the probability corresponding to a positive verification using a given

assessment level is obtained, the next step is to calculate the loss function. In this

case the loss function is equal to the cost, which depends on both the

assessment level and the consequence, according to equations (75) and (76).

( ) (75)

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

0 0.1 0.2 0.3 0.4 0.5 0.6

Pro

ba

bil

ity

α

Level 1 assessment

Level 2 assessment

Level 3 assessment

0.08 0.12 0.20

Page 93: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

93

( ) (76)

The expected loss is equal to the following (77).

( ) (77)

Using equation (77), the relations as a function of the bridge cost Cc (Fig. 42) can be built.

Fig. 42: Relationship between costs and lack of capacity

The lower curve, given a value of α, is the Bayes action, that which has the lower

expected loss. Looking at the graph, it is therefore possible to determine the

intervals in which it is more appropriate to choose a given assessment level.

According to equation (77) it can be noted that there is a fixed cost (depending on

the assessment level (Table 25)) and a variable cost that depends on the

probability of obtaining a positive verification. The following values are obtained

(Fig. 42):

0%<α<2% Level 1 assessment is most cost effective;

2%≤α<6% Level 2 assessment is most cost effective;

6%≤α<47% Level 3 assessment is most cost effective;

α≥47% it is most cost effective to replace the bridge.

0%

20%

40%

60%

80%

100%

0 0.1 0.2 0.3 0.4 0.5 0.6

Co

stto

tal(%

Cc)

α

Level 1 assessment

Level 2 assessment

Level 3 assessment

0.02 0.06 0.47

1

3

2

Page 94: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

94

As discussed above, in this first step the hypothesis is to use a single level tree

diagram, that is, to assume that when an assessment level has been applied, the

only possible results are the positive verification of the bridge or its replacement.

In reality it is possible that after an assessment level, the choice is to perform the

subsequent assessment level. Moreover, according to the APT (see Chapter 6),

there is no possibility of the bridge being replaced after Level 1. Replacement is

possible only after Level 2 assessment as the hypothesis is that if the result of

Level 1 assessment is negative, the only option is to perform Level 2 assessment.

Furthermore, it is not possible to perform Level 3 assessment directly without

having analyzed Level 1 and 2. These remarks are valid only for girder bridges as

for arch bridges only Level 2 assessment is possible.

The possibility of utilizing a higher assessment level, in the case of a negative

verification of a girder bridge, is illustrated in Fig. 43. The final decision tree for

girder bridges (Fig. 43) has four decision node. The possible actions are:

aa,(i): at Level i the APT load can cross the bridge, as can the overweight

loads with lower total gross weight;

ar,(i): at Level i the bridge should be replaced;

an,(i): the subsequent assessment level should be performed from Level i

to Level i+1;

while the possible outcomes are:

θs: the bridge withstands the overweight load;

θf: the bridge collapses;

θr: the bridge is replaced and the new bridge withstands the overweight

load.

Page 95: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

95

Fig. 43: Final decision tree for girder bridges with documentation

L 1

L 0

L 2

L 3

αa(0

)

θs

θf

f|αa

(0), L

(zθ

f|αa

(0))

s|αa

(0), L

(zθ

s|αa

(0))

f|αa

(0)

1-p

θf|α

a(0

)

αr(0

)

r|αa

(0), L

(zθ

r|αa

(0))

θr

αr(2

)

r|αa

(2), L

(zθ

r|αa

(2))

θr

αr(3

)

r|αa

(3), L

(zθ

r|αa

(3))

θr

αa(1

)

θs

θf

f|αa

(1), L

(zθ

f|αa

(1))

s|αa

(1), L

(zθ

s|αa

(1))

f|αa

(1)

1-p

θf|α

a(1

)

αn

(0)

αn

(1)

αn

(2)

αa(2

)

θs

θf

f|αa

(2), L

(zθ

f|αa

(2))

s|αa

(2), L

(zθ

s|αa

(2))

f|αa

(2)

1-p

θf|α

a(2

)

αa(3

)

θs

θf

s|αa

(3), L

(zθ

s|αa

(3))

f|αa

(3)

1-p

θf|α

a(3

)

Page 96: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

96

In Fig. 43 is the probability that the bridge collapses.

The symbols adopted are those used in a thesis by Cappello (2013), which as

mentioned before, studied in depth some of the aspects included in this thesis.

Cappello (2013) also studied the loss functions and the costs associated to the

possible collapse of bridges. In the decision tree of Fig. 43 the outcomes take into

account the possible collapse of the bridge after the decision to allow the crossing

of the bridge.

Unlike the decision tree of Fig. 40, in this case the expected loss as a

consequence of a given choice takes into account not only the cost of the

assessment level but also the consequences of the collapse of the bridge.

After Level 0 assessment (L0) the decision maker has three options:

aa,(0): the APT load can cross the bridge and the possible outcomes are:

o the bridge collapses;

o the bridge withstands the overweight load;

ar,(0): the bridge is replaced and the new bridge withstands the overweight

load;

an,(0): Level 1 assessment is performed and the result is α1.

After Level 1 assessment (L1) the decision maker has two options:

aa,(1): the APT load can cross the bridge and the possible outcomes are:

o the bridge collapses;

o the bridge withstands the overweight load;

an,(1): Level 2 assessment is performed and the result is α2.

After Level 2 assessment (L2) the decision maker has three options:

aa,(2): the APT load can cross the bridge and the possible outcomes are:

o the bridge collapses;

o the bridge withstands the overweight load;

ar,(2): the bridge is replaced and the new bridge withstands the overweight

load;

an,(2): Level 3 assessment is performed and the result is α3.

After the final level of assessment (L3) the decision maker has two options:

aa,(3): the APT load can cross the bridge and the possible outcomes are:

Page 97: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

97

o the bridge collapses;

o the bridge withstands the overweight load;

ar,(3): the bridge is replaced and the new bridge withstands the overweight

load.

In the final decision tree for girder bridges, of Fig. 43, it has been supposed that

the design documentation of the bridge exists. Although it should always exist, in

many cases it does not (see Chapter 6). The decision tree needs to be modified

when the design documentation is not available. Without design documentation

Level 1 and Level 2 assessment are not possible, while Level 3 assessment can

be done but with additional cost with respect to Level 3 with documentation.

Firstly, the evaluator does not know the geometry of the bridge and a detailed

survey on the bridge geometry is necessary. Secondly, the material properties are

also unknown, and an extended campaign of in-situ testing and observations

must be done. Finally, the construction date must be estimated and a simulation

of the design process is necessary.

The decision tree for girder bridges without documentation is illustrated in Fig. 44:

Fig. 44: Decision tree for girder bridges without documentation

The same symbols used in the decision tree for girder bridges with documentation

are adopted.

After Level 0 assessment (L0) the decision maker has three options:

L 0 L 3

αa(0)

θs θf

zθf|αa(0), L(zθf|αa(0))zθs|αa(0), L(zθs|αa(0))

pθf|αa(0)1-pθf|αa(0)

αr(0)

zθr|αa(0), L(zθr|αa(0))

θr αr(3)

zθr|αa(3), L(zθr|αa(3))

θr

αn(0)

αa(3)

θs θf

zθf|αa(3), L(zθf|αa(3))zθs|αa(3), L(zθs|αa(3))

pθf|αa(3)1-pθf|αa(3)

Page 98: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

98

aa,(0): the APT load can cross the bridge and the possible outcomes are:

o the bridge collapses;

o the bridge withstands the overweight load;

ar,(0): the bridge is replaced and the new bridge withstands the overweight

load;

an,(0): Level 3 assessment is performed and the result is α3.

After Level 3 assessment (L3) the decision maker has two options:

aa,(3): the APT load can cross the bridge and the possible outcomes are:

o the bridge collapses;

o the bridge withstands the overweight load;

ar,(3): the bridge is replaced and the new bridge withstands the overweight

load.

As discussed above, Level 1 and 3 assessment applied to arch bridges are not

useful. The decision tree for arch bridges is composed of only Level 0 and 2

assessment. As for girder bridges, we have to take into account whether the

design documentation exists. The difference between performing the Level 2

assessment with or without design documentation lies in the costs. The cost of

Level 2 with and without documentation (henceforth called respectively Level 2A

and Level 2B) are reported in Table 28 and Table 29 respectively:

Table 28: Costs for Level 3 assessment for arch bridges with design documentation

Item Cost

First inspection with geometric survey, assessment of

cracking, report

0.05%Cc

Calculation report 0.20%Cc

Total 0.25%Cc

Table 29: Costs for Level 3 assessment for arch bridges without design documentation

Item Cost

First inspection with geometric survey, analysis of the

cracking state, report

0.05%Cc

Geometric survey of the arch 0.20%Cc

In-situ test to check thicknesses 0.15%Cc

Calculation report 0.30%Cc

Total 0.70%Cc

Page 99: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

99

The final decision tree for arch bridges is shown in Fig. 45

Fig. 45: Decision tree for arch bridges with design documentation

Fig. 46: Decision tree for arch bridges without design documentation

L 2AL 0

αr(0)

αn(0)

αa(0)

zθr|αa(0), L(zθr|αa(0))

θr

θs θf

zθf|αa(0), L(zθf|αa(0))zθs|αa(0), L(zθs|αa(0))

pθf|αa(0)1-pθf|αa(0)

αa(2)

θs θf

zθf|αa(2), L(zθf|αa(2))

pθf|αa(2)1-pθf|αa(2)

αr(2)

zθr|αa(2), L(zθr|αa(2))

θr

zθs|αa(0), L(zθs|αa(0))

L 2BL 0

αr(0)

αn(0)

αa(0)

zθr|αa(0), L(zθr|αa(0))

θr

θs θf

zθf|αa(0), L(zθf|αa(0))zθs|αa(0), L(zθs|αa(0))

pθf|αa(0)1-pθf|αa(0)

αa(2)

θs θf

zθf|αa(2), L(zθf|αa(2))

pθf|αa(2)1-pθf|αa(2)

αr(2)

zθr|αa(2), L(zθr|αa(2))

θr

zθs|αa(0), L(zθs|αa(0))

Page 100: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

100

5.5 Optimization of alpha thresholds

The optimization of alpha thresholds has already been studied by Cappello (2013)

who based his analyses and models on the present work. However, it is worth

reporting the methodology of his thesis, which studied in depth the decision

making part of this thesis. His thesis presents the results of alpha thresholds and

Bayesian updating of parameters. In this Section and in Section 5.6 only the main

results are reported, while a comprehensive discussion of these topics are

available in the thesis by Cappello (2013). As Cappello’s thesis regards only

girder bridges, this Section reports the discussion on this typology. Therefore, the

optimization of alpha thresholds proposed in this Section is found for girder

bridges although the methodology is valid also for arch bridges. The optimization

of parameters will be applied to the APT bridge stock in Chapter 6.

The aim is to obtain the values of the possible actions aa,(i), an,(i), and ar,(i) which

minimize the expected loss. To do this, it is firstly necessary to define the

distributions for each stochastic variable (Δα)(i) that represents the decrease in the

lack of capacity shown after selected assessment level. According to Section 5.4

a lognormal distribution function is used and the mean values that correspond to a

probability of 50% that the verification becomes positive are reported in Table 26.

Secondly, the loss function should be defined and two loss functions have been

chosen to model the perception loss of the decision maker. The loss functions

chosen are reported in the following:

Bernoulli’s loss function;

probability of failure as an outcome.

In Bernoulli’s loss function the utility function proposed is as follows (78):

(

) (78)

that corresponds to the following loss function (79):

(79)

remembering that (80):

[ ] (80)

Page 101: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

101

where z is money, z0 is the maximum amount of money the APT is willing to spend

and c is a coefficient to calibrate based on boundary conditions (see Cappello,

2013).

In the case of probability of failure as an outcome, the hypothesis is that the

decision maker of the APT cannot accept a bridge collapse. In this case the loss

is +∞ if pf=1, which is the worst possible condition. Consequently, this means that

the probability of failure can be considered as an outcome. The expected loss is

reported in the following (81):

(

) (81)

where c is a constant in millions of euro.

The costs of Table 25 were recalibrated after the effective assignments of the

assessment levels to the evaluators (see Chapter 6). The new costs are reported

in Table 30.

Table 30: Costs for Level 1 + Level 2 assessment for girder bridges.

Item Cost

Level 1: First inspection with geometric survey, report 0.08%Cc

>750 €

Additional cost for Level 2 assessment +0.12%Cc

Level 1 + Level 2 0.20%Cc

>750 €

Table 31: Costs for Level 3 assessment for girder bridges with design documentation

Item Cost

First inspection with geometric survey, report 0.05%Cc

Sampling and tests on the materials involved 0.30%Cc

Integration of the calculation report 0.15%Cc

Total 0.50%Cc

Table 32: Costs for Level 3 assessment for girder bridges without design documentation

Item Cost

Complete and detailed geometry survey 0.30%Cc

Sampling of slab 0.15%Cc

Inspection of the reinforcement bars 0.30%Cc

Sampling of the concrete of the girders 0.45%Cc

Page 102: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

102

Sampling of the steel strands of the girders 0.60%Cc

Integration of the calculation report 0.50%Cc

Total 2.30%Cc

The cost for Level 0 assessment is equal to zero as the analysis is done

automatically using information contained in the APT-BMS database (see Chapter

6).

The results of the optimization of alpha thresholds for a bridge with design

documentation, performed by Cappello (2013), are reported in Table 33.

According to the APT (see Chapter 6) Cappello (2013) fixed the value of aa,(0) at

aa,(0) =0.04.

Table 33: Results of alpha thresholds for decision tree for girder bridges with

documentation

Alpha thresholds Bernoulli’s loss function Probability of failure as

an outcome

aa,(0) 0.01 0.01

an,(0) 0.55 0.28

aa,(1) 0.23 0.17

aa,(2) 0.29 0.19

an,(2) 0.55 0.28

aa,(3) 0.52 0.25

For a bridge without design documentation the results are shown in Table 34:

Table 34: Results of alpha thresholds for decision tree for girder bridges without

documentation

Alpha thresholds Bernoulli’s loss function Probability of failure as

an outcome

aa,(0) 0.04 0.04

an,(0) 1.07 1.00

aa,(3) 0.48 0.33

The total costs obtained when applying the decision trees defined in Section 5.4

are equal to € 29,200,000 (Cappello (2013)). These costs also consider the re-

construction cost of the bridge when, after the re-assessment, the verification is

negative.

Page 103: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

103

5.6 Bayesian updating of parameters

Bayesian statistics helps to solve problems that involves inductive logic (Fig. 47),

which is where the cause can be determined by observing its effects (Cappello,

2013). For instance, it provides the probability that a fair coin is used if, after ten

tosses, the number of heads is six (Sivia, 2006). In contrast, deductive logic

predicts only the effects of the cause. Fig. 47 represents the difference between

inductive and deductive logic.

Fig. 47: A schematic representation of deductive logic, and inductive logic (Sivia, 2006).

Bayesian statistics is able to update prior distribution of parameters on the basis

of new observations (Bolstad, 2007). In our case the use of Bayesian statistics is

useful in order to update the distributions of the stochastic variables Δα using the

results of a number of case studies.

The Bayes’ theorem (85), which is the single tool of Bayesian statistics (Bolstad,

2007), can be obtained as follows:

(82)

where Pr(x,y) is the probability of observing both x and y, Pr(y) is the probability of

observing y, and Pr(x|y) is the probability of observing x given y. Since (83)

(83)

Page 104: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

104

the following equations can be written (84) (85):

(84)

(85)

where Pr(y|x) is the likelihood probability function, Pr(x) is the prior probability

function, Pr(y) is the evidence and Pr(x|y) is the posterior probability function.

As reported in Section 5.4 a lognormal distribution function has been used for

each stochastic variable (Δα)(i). This means that we can write the associated

normal distribution function with mean μln(Δα),i=ln[(Δα)(i)] and standard deviation

σln(Δα)i=0.40 as follows (86):

[ ]

{

[

]

} (86)

where σln(Δα)i=0.40 results from β =0.7 as imposed in Section 5.4. Equation (86)

represents the a priori distribution of (Δα)(i). According to Section 5.4 the standard

deviation σln(Δα)i is the same for all assessment levels, while the mean μln(Δα),i is

reported in Table 35.

Table 35: Mean decrease from one assessment level to another.

Assessment level Δαmean (Δαi) μln(Δα),i

Level 1 0.08 -2.526

Level 2 0.04 -3.219

Level 3 0.08 -2.526

If the bridge is without design documentation (Level 3 assessment is carried out

after Level 0 assessment), equation (86) is still valid but in this case the mean

value of μln(Δα),3 is equal to the sum of μln(Δα),i , which is μln(Δα),3=ln[0.08+0.04+0.08]=

ln[0.20]. The distributions of (Δα)(i) are shown in Fig. 48.

Page 105: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

105

Fig. 48: Distributions of (Δα)(i)

The Bayes’ theorem (85) can be rewritten as follows (Cappello, 2013) (87):

(87)

where g is the posterior distribution without the constant Pr(y), fp is the prior

distribution, and fl is the likelihood distribution defined as follows (Cappello, 2013)

(88):

∏ ( [ ]

)

(88)

where equation (89)

( [ ]

) (89)

provides the probability density of a normal distribution with mean μ*ln(Δα),i and

standard deviation σ*ln(Δα),i at the point ln[(Δα)(i)]k.

The prior distribution according to equation (86) is reported in the following (90):

0

0.2

0.4

0.6

0.8

1

1.2

0 0.1 0.2 0.3 0.4 0.5

pd

f[Δα

(i)]

Δα(i)

i=1,3

i=2

Page 106: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

106

( | |)

( ( ) ( ) | ( )|) (90)

where the values of μln(Δα),i are presented in Table 26 and σln(Δα),i=0.4. As can be

noted, fp is a prior distribution of the parameters. The prior distribution is obtained

by multiplying two normal distributions as μ*ln(Δα),i and σ*

ln(Δα),i are independent

(Cappello, 2013). Cappello (2013) imposed the coefficients of variation as follows

(91) (92):

(91)

(92)

which represent respectively the coefficient of variation of the mean and the

coefficient of variation of the standard deviation of the prior distribution.

Solving equation (87) with a Markov Chain Monte Carlo (MCMC) method, it is

possible to obtain the updated values of Δα (μ*ln(Δα),i) and β (σ*

ln(Δα),i). MCMC

methods are numerical methods developed to obtain samples from the posterior

distribution. The Metropolis-Hastings algorithm, which will be used in Section 6.8

for the updating of parameters, is an MCMC method. The steps of Metropolis-

Hastings algorithm are reported below (Bolstad, 2010):

1) start with an initial value θ(0);

2) do from n=1 to n:

draw θ’ from q(θ(n-1),θ’);

calculate the probability α(θ(n-1),θ’);

draw u from U(0,1);

if u< α(θ(n-1),θ’) then let θ(n)= θ’, or else let θ(n)= θ(n-1).

where q(θ,θ’) is a candidate distribution that generates a candidate θ’ given a

starting value θ, U(0,1) is a uniform distribution, and α(θ(n-1),θ’) is the acceptance

probability that is equal to (93):

Page 107: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

107

{

} (93)

where g(θ|y) is the posterior distribution.

5.7 Conclusions

The aim of this Chapter was to define a decisional model to support the manager

in his/her choices. Different decision trees have been defined for arch and girder

bridges with and without design documentation. The separation of decision trees

is necessary due to the different costs of the assessment levels with or without

design documentation and the different assessment methodologies for arch and

girder bridges. Furthermore, a methodology has been defined to determine the

limit values of the lack of capacity (α) that make it more cost effective to employ a

certain assessment.

In addition, a methodology has been proposed to optimize these thresholds of the

lack of capacity α, and a method to update these parameters when a number of

case studies are available. These methodologies will be applied to the APT bridge

stock in Chapter 6.

Page 108: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

108

Page 109: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

109

6 APPLICATION TO THE APT BRIDGE STOCK

6.1 Introduction

As discussed in Chapter 2, transportation agencies do not know how to respond

to transit applications on their bridges. In particular, The Department of

Transportation of the Autonomous Province of Trento adopts a conservative

procedure to release permits based on empirical information from past crossings

of loads that caused no apparent damage to the bridges. Chapter 3 illustrated a

methodology that takes into account the real capacity of the bridges. Moreover a

decisional model to support the manager in his/her choices was defined.

In this Chapter, I apply both the procedure defined in Chapter 3 and the

decisional model shown in Chapter 5 to the APT bridge stock.

In Section 6.2 I report a brief introduction to the APT’s Bridge Management

System (APT-BMS) while in Sections 6.3 I report the strategic objectives to

assess/retrofit the APT bridge stock to allow free or restricted travel of minimum

overweight load vehicles over the entire network. Then, in Section 6.4 the

consequent results obtained by applying Level 0 assessment are shown. Section

6.5 shows the final decision tree adopted by APT in order to guide their choices.

Based on this decision tree a prediction of re-assessment results and costs is

performed in Section 6.6.

In the last Sections the optimization of the thresholds of the lack of capacity

(Section 6.8) based on the results of 20 APT bridge case studies (Section 6.7) is

performed.

6.2 Bridge Management System

Since 1998, following a policy of decentralization that has relocated state

responsibilities to the provinces, the number of bridges managed by the

Page 110: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

110

Department of Transportation of the Autonomous Province of Trento, a medium-

sized public agency, has increased from 412 to approximately 1000 (Bortot et al.,

2009).

As discussed in Section 1.1, in order to allow effective planning of maintenance

policies and to meet the new requirements, the Department of Transportation of

the APT has begun to collaborate with our Department of the University of Trento

(DIMS), to develop a comprehensive Bridge Management System (APT-BMS)

(Bortot et al., 2009).

The objective was to develop a management tool which was able to determine

present and future needs for maintenance, reinforcement and replacement of

APT bridges (Zonta et al., 2007). Moreover the aim was to provide a prioritization

system to guide the APT in the effective utilization of available funds. The result

has been the development of a management system fully available on the web

(www.bms.provincia.tn.it). Fig. 49 shows the main components and the

information flow of the APT-BMS. The system is based on a set of components:

database, cost, deterioration, repair and maintenance models, inspection data,

and decision making. Each component consists of a procedure package and is

divided into modules. The modules can operate on a project level (single bridge)

or network level (bridge stock) (Zonta et al., 2007).

The database consists of:

Inventory data;

Condition State (CS) data;

Reliability data.

Inventory data includes all the information and a simplified model of the bridge,

representing the logical distribution of its elementary units (Zonta et al., 2007).

Page 111: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

111

Fig. 49: Main components and information flows of the APT-BMS (Zonta et al., 2007)

The model consists of structural units (SU) which in turn are divided into standard

elements (SE), most of which coincides with AASHTO CoRe elements (AASHTO,

1997) (Fig. 50). This division allows the definition of the Condition State evaluated

during inspections.

The data of the Condition State provide information about the deterioration of

standard elements and their intensity (Bortot et al., 2009). The condition state of

the bridge is detected by the evaluators, following the procedures of the APT-

BMS. The condition state is represented by an integer. The minimum value, which

represents the optimum situation, is equal to 1 while the maximum can vary to 3,

4 or 5 depending on the type of standard element. This methodology was defined

in order to maintain the same evaluation models used by one of the most

common management systems, PONTIS (Thompson, 1998) (Bortot et al, 2007).

Page 112: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

112

Fig. 50: Example of bridge representation as implemented in the APT-BMS (Zonta et al.,

2007)

In addition to this heuristic condition index, another condition index, the Apparent

Age (AA) index, is introduced in the APT-BMS reflecting the specific view of the

agency on the concept of bridge deterioration. The AA index calculates the most

likely age of the bridge, given the condition state of its elements. The index,

compared to the real age, shows whether the bridge deterioration is normal, or if

the structure has suffered abnormal degradation (Zonta et al., 2008).

Moreover, the APT-BMS involves a specific section for the formal assessment of

the reliability of bridge structures. Reliability data directly concerns the capacity of

the bridge, and consists of a set of reliability indexes β, each associated with an

ultimate limit state and a specific structural unit or substructure. Further

information on reliability and the APT-BMS is given in Zonta et al., (2007); .

In the APT-BMS there are three types of inspections:

Inventory inspections;

Routine inspections;

Special inspections.

Inventory inspections collect all data required for the operation of the system and

if possible include attachments, such as pictures, design documents, FEM

models, and AutoCad files, while routine inspections are used to update the

condition state of the bridge. Routine inspections are divided into simplified and

principal inspections depending on the level of detail and the frequency of the

assessment. Special inspections are performed only when, a routine inspection

identifies structural anomalies, or the inspector was unable to evaluate one or

more elements of the bridge.

Page 113: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

113

The prioritization approach adopted in the APT-BMS is based on the following

principle: priority is given to those actions that, given a certain budget, will

minimize the risk due to a number of unacceptable events in the whole network in

a specific timespan (for example: in the next tL=5 years) (Zonta et al., 2009).

The ranking of any intervention using a priority index can be expressed as

follows (94):

(94)

where RTOT(tL) is the total risk of unacceptable events over the time span (0,tL]

when the intervention is not undertaken, and C is the cost of bridge reconstruction

(Zonta et al., 2009).

The unacceptable events considered in the APT-BMS are:

failure of a principal element;

failure of a secondary element;

pile collapse due to scour;

accidents due to sub-standard guardrails;

loss of life due to an earthquake.

Assuming that the unacceptable events Ei are non-correlated, the total

cumulative-time risk can be evaluated as the sum of risks associated with each

event considered (95):

(95)

where Ri is the risk associated with the unacceptable event Ei, PE is the probability

of occurrence of the unacceptable event and PX|E is the magnitude of the expected

damage if the event occurs.

The system operates entirely on the web, and is based on an SQL database,

accessible over the Internet. The database can be modified through a web-based

user-friendly interface. Inspectors and evaluators can find the appropriate

procedures on the same web application, and can upload the results of condition

assessments or of safety evaluations. The manager can view the result of the

analysis on the same web-interface. The system is continuously updated by our

research group at the University of Trento.

Page 114: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

114

The system is supported by a number of separate servers which are hosted on

different machines and can be managed by different actors (Zonta et al., 2006). In

its initial configuration the system includes (Fig. 51):

a database server;

a web server application;

the data analysis application server.

Fig. 51: Architecture of the APT-BMS in the single agency configuration (Zonta et al.,

2006).

The web application consists in a user-friendly portal that provides access for

data management to users. Users are:

system managers (full control on the stock information);

inspectors and evaluators (access limited to bridges and inspections

under their responsibility);

guests.

One of the most interesting aspects of the APT-BMS is its fully web-based

operation. The various site sections include: Inventory, Inspections, People,

Roads and Network.

The Inventory is the first section of the web application (Fig. 52) and includes a

basic search engine, a result list including the important characteristics of the

bridges, and a multi-tab window showing information on the selected bridge

(Zonta et al., 2006). Inventory data include all the information regarding the

bridge, namely identification, administrative issues, geographical location,

construction and previous retrofits, and also a number of multimedia attachments

(e.g. pictures, documents, FEM models, AutoCAD files). The tab II livello shows

DB

WEB

INTERFACE

ANALYSIS

APPLICATION

SERVER

MANAGER

WEB

INTERFACE

WEB

INTERFACE

WEB

APPLICATION

SERVER

INSPECTORS

GUESTS

SYSTEM

UPDATE

GROUP

Page 115: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

115

the elementary model of the bridge, broken down into Standard Units, and

Standard Elements. Moreover, an advanced search engine and a complete report

generator are included in the section (Zonta et al., 2006).

Fig. 52: Display of the Inventory section (Zonta et al., 2006).

The Inspections section allows the manager to organize the inventory, routine

inspections, and safety evaluations (Fig. 53). The manager assigns tasks to each

inspector/evaluator, and validates the results uploaded by them at the end of their

job. In the case of an inspection that foresees a condition assessment, the

evaluator assigns a condition index to each Standard Element of the bridge.

When there are anomalies, the evaluator inserts a detailed description and a

number of digital pictures. For safety assessment, the evaluator fills in a table with

the results, where each limit state considered in the evaluation has an associated

load rating factor or a reliability index (Fig. 54). After entering data, the evaluator

should attach a detailed report of the calculations done, including all electronic

files used during the analysis (e.g. the input file of a Finite Element program).

inventory module

sample multimedia record

Page 116: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

116

Fig. 53: Display of Inspections section (Zonta et al., 2006).

Fig. 54: Display of the evaluations section (Zonta et al., 2006).

In the People and Roads sections the manager can list the people involved in the

process (including the application users), and the APT road network, respectively.

In the Network section there are the results of the risk analysis of all the

unacceptable events of the bridge stock. The users can visualize the results on

Google Earth maps.

inspections management

inspection attachment

evaluator reports the results of the evaluation in a table

a detailed technical report is also attached

Page 117: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

117

6.3 Strategic objective

The APT has defined a ten-year objective to assess/retrofit its bridge stock to

allow free or restricted travel of minimum overweight load vehicles over the entire

network. In particular, the road system has been divided into two different

networks: a strategic network and a non-strategic network. The strategic network

(see Table 36) includes all inter-regional highway links, with 574 km of highways,

264 girder bridges and 87 arch bridges; the non-strategic network is the

remaining 1836 km of local road links, including 428 girder bridges and 174 arch

bridges (Fig. 55).

Table 36: Strategic network

Links Start kilometer End kilometer

SP59 - -

SP71 4.000 40.000

SP72 - -

SP76 - -

SP79 10.200 13.200

SP80 - -

SP83 0.000 7.700

SP90 tronco1 3.200 14.000

SP90 tronco dir Ala - -

SP90 tronco2 - -

SP90 dir SS12 - -

SP90 dir Rover - -

SP90 tronco3 5.700 7.510

SP101 - -

SP104 - -

SP118 3.700 6.367

SP232 - -

SP232 dir - -

SP235 0.000 17.400

SP254 Rupe - -

SS12 326.181 350.300

357.300 383.000

387.300 401.275

Page 118: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

118

SS12svincoli - -

SS42 147.846 170.900

SS43 0.000 30.650

SS45bis 112.000 116.800

119.100 154.160

SS47 73.014 130.8 (ex 131.800)

ex SS47 Martignano - -

SS48 16.430 20.400

35.000 63.800

SS48 var Predazzo - -

SS50 61.057 74.400

SS237 - -

SS239 - -

SS240 0.000 16.800

SS240 dir - -

SS249 96.500 101.130

SS347 0.000 11.780

Fig. 55: Girder and arch bridges on a)strategic and b)non-strategic network

The mid-term objective for the strategic network is to allow the free travel of 6-

axle overweight vehicles with a maximum axle weight of 12 tons (120 kN) and

total weight 72 tons (720 kN), and the restricted travel (bridge crossed in the

center of the roadway) of 8-axle overweight vehicles with a maximum axle weight

of 13 tons (130 kN) and a total weight of 104 tons (1040 kN). Similarly, for non-

264

87

girder bridges arch bridges

428

174

girder bridges arch bridges

a) b)

Page 119: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

119

strategic bridges, the targets are the free travel of any 56 ton vehicles and the

restricted travel of 72 ton vehicles.

Table 37: Strategic objective

Free travel Center of roadway

Strategic network 6x12t=72t 8x13t=104t

Non-strategic network 56t 6x12t=72t

6.4 Level 0 assessment results

Level 0 assessment involves the verification of the bridge assuming no

overstrength. As already discussed in Chapter 3, in practice the assessment

consists in the calculation, for each section of the deck, of the maximum bending

moment and shear caused by the design load (or the eccentricity of the thrust line

in the case of arch bridges) and the subsequent comparison with the APT loads.

In the case of free travel, the APT-BMS database contains the required data to

perform the assessment of each bridge, which are the following:

maximum span length;

year of the bridge design (required to infer the design code).

The assessment in the case of crossing the bridge in the center of the roadway

would require the Massonet-Guyon-Bares coefficients to evaluate the transverse

distribution of the loads. As an alternative, all the geometrical and mechanical

details of the deck must be known. Currently, the APT-BMS database does not

contain this information although it has been planned to enter the values of the

Massonnet-Guyon-Bares coefficients for each bridge in the next two years. For

this reason, the transverse distribution of the loads has been calculated using the

Courbon method, which requires only the deck width as input data, which is

contained in the APT-BMS database.

The analysis of Level 0 assessment was done automatically using the information

contained in the APT-BMS database (see Chapter 6). A Matlab® program (Matlab

v. 7.0.1) was implemented which automatically reads the geometrical data of

each bridge and calculates, in each section of the bridge, the maximum bending

moment and the maximum shear stress caused by the design loads and the APT

loads. The design loads are calculated by inferring the design code from the year

of the design of the bridge. The following design codes are implemented in the

program:

Page 120: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

120

Normale n.8 15/09/1933

Normale n.6018 09/06/1945 and n.772 12/06/1946

Circolare n.820 15/03/1952

Circolare n.384 14/02/1962

D.M. 02/08/1980

D.M. 04/05/1990

D.M. 14/01/2008

For bridges designed before 1933, the program implements the traffic loads

included in Jorini (1918), which reports the reference loads to be used in the

design of bridges.

Fig. 56 and Fig. 57 show the flowcharts implemented in the Matlab program in the

case of free travel and bridge crossed in the center of the carriageway

respectively. The details and a comprehensive discussion of the Matlab program

can be found in the master’s thesis of Lastei (2011).

Fig. 56: Flowchart of the Matlab program implemented for Level 0 assessment in the case

of free travel

Initialization

Uploading data from BMS database

(span length, design year, width of the deck,

typology of superstructure, type of network)

Uploading design loads

END

arch bridge?NOYES

Calculation of the envelope of

the eccenticity

Uploading APT loads

Uploading design loads

Calculation of the envelope of

bending moment and shear

stress

Uploading APT loads

Calculation of the envelope of

bending moment and shear

stress

Creation of Google Earth Maps

Comparison and calculation of the lack of

capacity

for i=1 to n_bridges

Calculation of the envelope of

the eccenticity

Page 121: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

121

Fig. 57: Flowchart of the Matlab program implemented for Level 0 assessment in the case

of bridge crossed in the center of the carriageway

Fig. 58 shows the results of Level 0 assessment using the desired overweight

loads for both the strategic and the non-strategic network. Each dot on the map

corresponds to one bridge, while the dot color encodes the assessment result in

terms of the index with the following meanings:

Table 38: Lack of capacity and assigned colors

Lack of capacity Color

α =0

0 < α < 0.1

0.1 < α < 0.2

0.2 < α < 0.3

α > 0.3

Fig. 58a plots the distribution of the lack of capacity in the case of strategic

network of the bridges located in the APT, using the higher value of alpha

between that relative to free travel (with the 6x12t APT load) and that a relative to

Initialization

Uploading data from BMS database

(span length, design year, width of the deck,

typology of superstructure, type of network,

traffic divider)

END

traffic divider?NOYES

Creation of Google Earth Maps

for i=1 to n_bridges

Uploading design loads

calculation of the envelope of

bending moment and shear

stress (Courbon method)

Uploading APT loads

calculation of the envelope of

bending moment and shear

stress (Courbon method)

Uploading design loads

arch bridge?

NOYES

Calculation of the envelope of

the eccenticity

Uploading APT loads

Uploading design loads

calculation of the envelope of

bending moment and shear

stress (modified Courbon

method)

Uploading APT loads

calculation of the envelope of

bending moment and shear

stress (modified Courbon

method)

Calculation of the envelope of

the eccenticity

Comparison and calculation of the lack of

capacity

Page 122: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

122

bridge crossed in the center of the roadway (with the 8x13t APT load). Fig. 58b

shows the results for the non-strategic network with the desired overweight loads.

a) b)

Fig. 58: deficiencies for target APT load models on a)strategic and b)non-strategic

networks (maps)

a) b)

Fig. 59: deficiencies for target APT load models on a)strategic and b)non-strategic

networks

The analysis of the strategic bridges shows that the verification is positive for 29%

(103/351 bridges) of the bridges of the APT stock. For these bridges, the APT can

authorize the transit of overweight loads up to 72 tons in the case of free travel,

and up to 104 tons in the case of bridge crossed in the center of the roadway. For

non-strategic bridges, Level 0 assessment is positive for 58% (347/602).

The remaining bridges (71% for strategic and 42% for non-strategic network)

have been classified as sub-standard, in order to define a priority ranking for

specific verification or for future reinforcement or replacement.

The results of assessment levels were inserted in the APT-BMS database

through three tables (Table 39, Table 40, and Table 41). In particular, the table

10369

98

16

65

0

50

100

150

200

250

300

350

400

α=0 0<α<0.1 0.1<α<0.2 0.2<α<0.3 α>0.3

347

5369

45

88

0

50

100

150

200

250

300

350

400

α=0 0<α<0.1 0.1<α<0.2 0.2<α<0.3 α>0.3

Page 123: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

123

Transitabilità (Table 39) contains the results of all the assessments (Level 0,

Level 1, Level 2, Level 3) and from this table the data are uploaded to the web

application.

Table 39: Example of the new table Transitabilità implemented in the APT-BMS

Oid Oid_B Tip_APT

load

Trav_

Cond α

Tip_Design

_code Ass_L Lim_state Tip_Us Des

1 1 1 1 0 3 0 3 6 -

2 1 2 1 0.23 3 0 4 10 -

3 1 3 1 0.23 3 1 2 5 -

4 1 4 1 0.28 3 1 6 4 -

5 1 5 1 0.34 3 2 7 2 -

6 1 6 1 0.53 3 3 5 1 -

7 1 7 1 0.55 3 3 5 7 -

8 1 1 2 0 3 0 9 6 -

9 1 2 2 0 3 0 5 4 -

10 1 3 2 0 3 1 1 9 -

11 1 4 2 0 3 1 4 11 -

12 1 5 2 0.10 3 1 8 4 -

13 1 6 2 0.15 3 1 3 3 -

14 1 7 2 0.25 3 1 1 2 -

Oid is a progressive number, while Oid_B is the Oid number of the bridge.

Tip_APT_load, Trav_Cond, and α are the APT load, the travel condition, and the

lack of capacity corresponding to the assessment. Tip_Design_code is the design

code used in the evaluation, Ass_L is the assessment level used in the

evaluation, and Lim_state is the limit state that caused the highest lack of

capacity, Tip_Us is the element where this value of α is calculated, and Des is a

detailed description of the verification.

The results of Level 0 assessment are automatically implemented in the

database, while for the other assessment levels the evaluator can insert the data

directly from the web application.

The results of assessment levels for each bridge are shown in the web application

in the new Tab Transitabilità (Fig. 60).

Page 124: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

124

Fig. 60: New tab Transitabilità (rio delle Seghe bridge) (www.bms.provincia.tn.it)

Page 125: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

125

The other two tables were implemented separately from the table Transitabilità, in

order to ensure that it is possible to add other APT loads or design codes in the

future.

Table 40: New table APT loads implemented in the APT-BMS database

Oid APT_load

1 56t

2 13x5=65t

3 12x6=72t

4 13x6=78t

5 13x7=91t

6 13x8=104t

7 13x9=117t

Table 41: New table Design Code implemented in the APT-BMS database

Oid Design_code

1 DM_14/01/2008

2 DM_04/05/1990

3 NT_02/08/1980

4 Circ_1962

5 Circ_1952

6 Circ_1945-1946

7 Norm_1933

8 Ante_1933

6.5 Decision tree

In Section 5.4, a general decision tree was defined to guide the APT manager in

making the most cost effective decision when selecting the appropriate

assessment level and in Section 5.5, the values of α thresholds were found.

The APT decided not to perform any assessment levels if the value of α, after

whatever assessment level, is less than 4%. The reason is that even if the

verification is negative, the value of α is acceptably small and no further

assessment is required. This limit value was obtained by imposing the probability

of collapse caused by the APT load on a substandard bridge equal to twice the

probability of collapse foreseen by the design code. According to Section 3.6,

which shows the risk interpretation of parameter α, the value of the lack of

capacity that corresponds to twice the original probability of collapse is equal to

Page 126: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

126

equation (97). This equation is obtained from equation (96), whose meaning is

explained in Section 3.6.

The APT decided to follow an heuristic method, rather than using the alpha

thresholds of Chapter 5. However, the values chosen are partly based on the first

example of a decision tree shown in Section 5.4.

Φ Φ( [(

) ]) (96)

( Φ

) ( Φ

) (97)

Fig. 61: Final APT decision tree for girder bridges

In the case of arch bridges the final APT decision tree is reported in Fig. 62. In

this case the alpha thresholds were also chosen by the APT following an heuristic

method.

L 1

OK OK OK OKα<0.04

Full formal

assessment

Full formal

assessment

Full formal

assessment

OK

Full formal

assessment

With design documentation

Without design documentation

L 0 L 2 L 3

L 3

α<0.04 α<0.04

α<0.04

α <0.04α <0α <0 α <0 α <0.04

α >0.40

α <0.04α <0

α <0.04α <0

α >0.47

Page 127: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

127

Fig. 62: Final APT decision tree for arch bridges

6.6 Prediction of re-assessment results and costs

The aim of this Section is to predict the results and costs when the decision trees

shown in Section 6.5 are applied. The prediction is based on the lack of capacity

shown in the results of Level 0 assessment. Table 27 shows the decrease in α

from one assessment levels to another.

Fig. 63 outlines the decision-making scheme and shows the prediction of re-

assessment results for girder bridges. The results show both strategic and non-

strategic bridges. More specifically, after Level 0 analysis, 433 bridges are

automatically assessed, including 49 bridges with α<0.04, while 22 others are

unlikely to pass any further level of simplified assessment and so must be

formally reassessed and possibly strengthened. 139 bridges, out of the remaining

237, have no design documents and must be directly assessed under a Level 3

procedure. The other 98 bridges, with design documents, can undergo the multi-

level assessment procedure. After the reassessment, the APT estimates that

there will be 72 substandard bridges out of the 692 total bridges. These bridges

will be analyzed individually and possibly strengthened to resist higher loads.

L 2A

Full formal

assessment

OK

Full formal

assessment

With design documentation

Without design documentation

L 0

L2B

α<0.04

α <0.04α <0

OK

Full formal

assessment

α<0.04

α <0.04

OK α<0.04

α <0.04α <0 α <0

α > 1.51

Page 128: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

128

Fig. 63: Anticipated results of re-assessment for girder bridges

Fig. 64 shows the prediction of re-assessment results for arch bridges. As for

girder bridges, the results show both the strategic and non-strategic networks.

Fig. 64: Anticipated results of re-assessment for arch bridges

After Level 0 analysis, 69 bridges are automatically assessed. Among the

remaining 192 bridges, 175 have no design documents; the other 17 bridges, with

design documents, can undergo the multi-level assessment procedure. After

L 1

OK

(384)

OK

(27)

OK

(39)

OK

(7)

α<0.04

(49)

Full formal

assessment

(22)

Full formal

assessment

(4)

Full formal

assessment

(6)

OK

(76)

Full formal

assessment

(40)

L 0 L 2 L 3

L 3

α<0.04

(14)

α<0.04

(1)

α<0.04

(23)

237692 1471

α <0

139

98

With design documentation

Without design documentation

L 2A

Full formal

assessment

(0)

OK

(165)

Full formal

assessment

(10)

With design documentation

Without design documentation

L 0

L2B

α<0.04

(0)

175

OK

(17)

Full formal

assessment

(0)

α<0.04

(0)OK

(66)

α<0.04

(3)

261 17192

Page 129: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

129

reassessment, the APT estimates that there will be 10 substandard bridges out of

the 261 total.

Table 42 and Table 43 show the total costs for each assessment level for girder

and arch bridges respectively (see Chapter 5 for itemized costs). Level 3S

indicates the cost of Level 3 whether the design documentation is not available.

Table 42: Total cost of assessment levels for girder bridges

Action Cost

Level 1 0.08%Cc

Level 1 + Level 2 0.18%Cc

Level 3 0.50%Cc

Level 3S 2.30%Cc

Table 43: Total cost of assessment levels for arch bridges

Action Cost

Level 2A 0.25%Cc

Level 2B 0.70%Cc

These costs (Table 42 and Table 43) can be applied to estimate the total cost of

decision trees. Table 44 and Table 45 show the expected cost obtained by

applying decision tree for girder bridges and arch bridges respectively. The total

cost for girder bridges is equal to € 2,118,000 while for arch bridges it is €

699,000. It can be noted that there is a high number of bridges without

documentation, both for girder (139, which corresponds to 58%) and arch bridges

(175, which corresponds to 91%). In addition these numbers are calculated

among sub-standard bridges and so the number of bridges without design

documentation is higher. The main reason is the policy of decentralization that

has relocated state responsibilities to the provinces with a consequent transfer of

the design documentation that has not happened yet. For arch bridges, however,

the absence of the design documentation is due to the year of the design, which

in almost all cases is before the second world war, and in many cases the

documentation has been lost.

Page 130: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

130

Table 44: Expected cost applying decision tree for girder bridges

Action No. bridges Total

(k€)

Total per bridge

(k€)

Level 1 27 36 1.33

Level 1 + Level 2 71 105 1.48

Level 3 14 47 3.36

Level 3S 139 1930 13.88

TOTAL

2118

Table 45: Expected cost applying decision tree for arch bridges

Action No. bridges Total

(k€)

Total per bridge

(k€)

Level 2A 17 27 1.59

Level 2B 175 672 3.84

TOTAL

699

Missing design documentation adds extra cost. In fact, the main part of the total

cost is due to Level 3S assessment (or Level 2B for arch bridges), which is, for

girder bridges, one order of magnitude higher than the cost of assessment levels

with design documentation. Although for arch bridges the difference is smaller,

the cost per bridge of Level 2B assessment (€ 3,840) is more than double that of

Level 2A assessment (€ 1,590). Table 46 and Table 47 show the comparison

between costs with and without documentation for girder and arch bridges

respectively. These estimated costs were obtained applying the decision tree of

Fig. 61 and Fig. 62 supposing that the design documentation of all bridges is

available. It can be noted that the saving by owning the design documentation of

all bridges would be equal to € 2,097,000 (€ 1,650,000 and € 447,000 for girder

and arch bridges respectively). In the case of girder bridges the value of a single

design documentation is € 11,800, and for arch bridges is € 2,600. This means

that it is worth focusing efforts to look for the design documentation of bridges.

Table 46: Comparison between costs with and without documentation for girder bridges

Girder bridges

Cost without documentation 2118 k€

Cost with documentation 468 k€

Saving 1650 k€

Number of bridges without documentation 139

Value of documentation 11.8 k€

Page 131: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

131

Table 47: Comparison between costs with and without documentation for arch bridges

Arch bridges

Cost without documentation 699 k€

Cost with documentation 252 k€

Saving 447 k€

Number of bridges without documentation 175

Value of documentation 2.6 k€

Table 48 illustrates the total costs obtained by adding the costs for arch and

girder bridges. As in Section 5.5, these costs also consider the reconstruction

cost of the bridge when, after the re-assessment, the verification is negative.

Table 48: Total costs

Arch bridges Girder bridges Total

Re-assessment

cost

0.699 M€ 2.118 M€ 2.817 M€

Reconstruction

cost

8.610 M€ 61.990 M€ 70.6 M€

TOTAL 9.309 M€ 64.108 M€ 73.417 M€

6.7 Application to 20 APT bridges

In this Section the APT decision trees defined in Section 6.5 are applied to 20

APT bridges, using the same assessment procedure discussed in Chapter 3 and

showed in detail in the two case studies Fiume Adige and Rio Cavallo. The aim is

to verify the bridges with the APT loads defined in the strategic objectives of

Section 6.3. Therefore, as explained in Section 6.5, Level 2 assessment is

applied when the lack of capacity after Level 1 assessment is more than 4%.

Table 49 and Table 50 list, for strategic and non-strategic bridges respectively,

the APT substandard bridges selected for the assessments and show the lack of

capacity after Level 0 assessment.

Page 132: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

132

Table 49: 8 strategic bridges selected for assessments

Bridge Identification Year Typology α

rio Secco SS12 km 364.745 1950 Precast reinforced concrete

slab 75%

Rio delle Pile SP 79 km 12.00 1984 Precast reinforced concrete

slab 30%

Rocchetta SS43 km 23.400

Dx 1950 Concrete arch 27%

rio Ala SS12 km 337.442 1937 Concrete arch 16%

Fiume Adige SP 59 km 0.255 1978 Precast reinforced concrete

girder 15%

Rio delle

Seghe SP 71 km 32.705 1969

Precast reinforced concrete

girder 12%

rio Silla SP 104 km 1.150 1982 Precast reinforced concrete

slab 8%

fiume Sarca SS 240 km 16.5 1961 Reinforced concrete girder 8%

Table 50: 12 non-strategic bridges selected for assessments

Bridge Identification Year Typology α

Fiume Adige SP 21 km 2.895 1943 Reinforced concrete

girder

84%

Torrente Maso SP 65 km 12.89 1966 Reinforced concrete

girder

33%

torrente Arione -

Aldeno

SP 25 km 0.525 1971 Precast reinforced

concrete girder

12%

rio Piazzina SP 31 km

35.191

1971 Precast reinforced

concrete girder

12%

rio delle Stue SP 31 km 31.63 1972 Precast reinforced

concrete girder

11%

rio Val della Setta a

Bondone

SP 69 km 9.19 1969 Reinforced concrete

girder

11%

rio Lenzi SP 135 km

11.920

1976 Precast reinforced

concrete girder

10%

rio Redebus SP 8 km 13.580 1973 Precast reinforced

concrete girder

10%

Torrente Grigno SP 78 km

13.310

1972 Precast reinforced

concrete girder

10%

Page 133: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

133

rio Loner SP 89 km

20.420

1977 Precast reinforced

concrete slab

10%

torrente Arione-

Covelo

SP 25 km 3.49 1975 Precast reinforced

concrete girder

10%

Echernachel SP 8 km

14.320

1973 Precast reinforced

concrete girder

10%

Table 51 and Table 52 list the results of assessment for strategic and non-

strategic bridges respectively.

In a number of sets of design documentation the verification of piers and

abutments was not reported. In these cases it is possible to compare the design

and the APT load. This assessment represents an advanced Level 0 as, in

contrast with the normal Level 0, the permanent loads are known exactly.

Table 51: Results for strategic bridges

Bridge Year Typology α α_new Assessment

Level

rio Secco 1950 Precast reinforced

concrete slab 75% 3% Level 1

Rio delle Pile 1984 Precast reinforced

concrete slab 30% 0% Level 1

Rocchetta 1950 Concrete arch 27% 10% Level 2

rio Ala 1937 Concrete arch 16% 12% Level 2

Rio delle

Seghe 1969

Precast reinforced

concrete girder 12% 0% Level 2

Fiume Adige 1978 Precast reinforced

concrete girder 15% 1% Level 1

rio Silla 1982 Precast reinforced

concrete slab 8% 5% Level 2

fiume Sarca 1961 Reinforced concrete

girder 8% 8% Level 2

Page 134: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

134

Table 52: Results for non-strategic bridges

Bridge Year Typology α α_new Assessment

Level

Torrente Maso 1966 Reinforced

concrete girder 33% 1% Level 1

Fiume Adige 1943 Reinforced

concrete girder 84% 47% Level 2

torrente Arione -

Aldeno 1971

Precast reinforced

concrete girder 12% 5% Level 1

rio Piazzina 1971 Precast reinforced

concrete girder 12% 0% Level 1

rio delle Stue 1972 Precast reinforced

concrete girder 11% 0% Level 1

rio Val della Setta

a Bondone 1969

Reinforced

concrete girder 11% 0% Level 1

rio Lenzi 1976 Precast reinforced

concrete girder 10% 0% Level 1

rio Redebus 1973 Precast reinforced

concrete girder 10% 0% Level 1

Torrente Grigno 1972 Precast reinforced

concrete girder 10% 2% Level 1

rio Loner 1977 Precast reinforced

concrete slab 10% 0% Level 2

torrente Arione-

Covelo 1975

Precast reinforced

concrete girder 10% 0% Level 1

Echernachel 1973 Precast reinforced

concrete girder 10% 2% Level 1

The results obtained show that 19/20 (95%) bridges have decreased and only

one bridge has maintained the lack of capacity estimated after Level 0 analysis.

The mean decrease in α was equal to 12% (16% for strategic network and 9% for

non-strategic network). For 7 bridges (Fig. 65), Level 2 assessment was

necessary and possible, while for 2 bridges it was not possible to complete Level

1 or Level 2 assessment because of the lack of the design documentation of piers

or abutments. For these elements only an advanced Level 0 has been done. In

the case of the non-strategic network, 7/12 bridges (58%) are safe, and 10/12

have a lack of capacity less than 4%. For the strategic network, 2/8 bridges (25%)

are formally verified and 4/8 (50%) have a lack of capacity that is less than 4%.

Page 135: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

135

Fig. 65: Results of the application of the decision tree to 20 APT bridges

The results show that:

with the exception of particular cases, the strategic objectives in the case

of the non-strategic network are satisfied;

in the case of the strategic network the verification of strategic objectives

is more difficult and Level 2 assessments are often required;

in some cases Level 1 and Level 2 assessments are not very useful due

to the lack of the design documentation of piers or abutments, which in

many cases are the most unfavorable elements.

It is interesting to look at the decrease in the lack of capacity as a function of the

design year of the bridge (Fig. 66).

L 1

OK (7)

20 7L 0 L 2

α<0.04 (5)

no verification

of piers or

abutments

(1)

OK (2)

α<0.04 (0)

no verification

of piers or

abutments

(1)

α<0.08 (1)

α<0.14 (2)

α<0.47 (1)

α<0.08 (1)α<0.08 (1)

Page 136: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

136

Fig. 66: Decrease in the lack of capacity as a function of the design year of the bridge

As can be noticed, the variability of the decrease in the lack of capacity is higher

for bridges designed before the 1960s. For bridges designed from 1960 onwards,

the mean decrease in the lack of capacity is 10%.

It is important to point out that in four cases the decrease in the lack of capacity is

very large (>30%). In the case of Rio Secco bridge (Fig. 67), Δα from Level 0 to

Level 1 assessment is equal to Δα=72%. The reason is that the Italian Army

Authority (Ispettorato Arma del Genio) imposed design loads (military load)

greater than those foreseen by the design code (civil load). The Rio Secco bridge

was built immediately after the Second World War (1950), and the Italian Army

Authority wanted to preserve its strategic networks.

0%

10%

20%

30%

40%

50%

60%

70%

80%

1930 1940 1950 1960 1970 1980 1990

Δα

design year of the bridge

Page 137: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

137

Fig. 67: Rio Secco bridge (www.bms.provincia.tn.it)

As can be noticed in Fig. 67, two signposts placed by NATO at the beginning of

the bridge indicate the maximum loads that can cross the bridge in the case of

free travel and bridge crossed in the center of the roadway. If there are NATO

signposts, we can infer that the design loads are military. In conclusion, in these

cases the design load could be higher than that foreseen by the design code and

therefore we suggest that those particular cases should be analyzed in depth.

In the other three cases (Torrente Maso bridge, Rio delle Pile bridge, Fiume

Adige bridge), the reason for the large decrease in the lack of capacity is that

there was some incorrect data within the APT-BMS database. The inventory

inspector had classified the bridges as second category, which means the design

loads are lower than those effectively used, although they should have been

classified as first category.

This demonstrates that the automatic program used to perform Level 0

assessment cannot recognize the rough mistakes contained in the APT-BMS

database. This could become a significant problem if the bridge was classified as

first category but it was in reality a second category. The solution to this problem

could be investigated in future work.

The assessment results have been implemented in the web application of the

APT-BMS (www.bms.provincia.tn.it). Fig. 60 shows the summary of the results in

the web application (in the inventory section) of rio delle Seghe bridge for each

APT load, for both free travel and bridge crossed in the center of the carriageway.

Page 138: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

138

This table is generated automatically by the web application, summarizing the

results inserted in the inspection section by the evaluator. In fact, he or she

completes a more detailed table that contains the results of all the verifications

performed for each transit condition, assessment level, structural element, and

limit state. In this manner the APT-BMS manager can quickly check the reason

for any lack of capacity summarized in the inventory section. In the APT-BMS

application can also be downloaded the assessment report of the evaluator.

It is important to highlight that even though the procedure requires only the

strategic objectives to be verified, the other APT loads should also be analyzed.

This means that in the same assessment level, the evaluator must analyze each

APT load, while the decision to apply the subsequent assessment level depends

only on the result of the APT load chosen in the strategic objectives. This is

because the cost of the assessment level is independent of the number of loads

to verify. The APT could authorize, in the case of positive verification, the crossing

of overweight loads higher than those defined in the strategic objectives.

6.8 Bayesian updating and thresholds of optimization

In Section 6.7, 20 APT bridges are analyzed and the decrease in the lack of

capacity from one assessment level to another is obtained. In this Section I use

these data to update the distribution of (Δα)(i) (see equation (86)) in order to

optimize the alpha thresholds (Section 6.8) to minimize the expected cost. Only

the results concerning girder bridges are used to update the values, as only the

thresholds for girder bridges are shown in the following. The methodology has

been already described in Section 5.6.

Table 53 shows the mean and the standard deviation of (Δα)(i) for each

assessment level after the evaluations.

Table 53: Mean and standard deviation of (Δα)(i) for each assessment level after the

evaluations

Assessment Level Δαmean (Δαi) σ(Δαi)

Level 1 0.16 0.17

Level 2 0.045 0.059

Applying the Bayes updating (87) the following results are obtained (Fig. 68 and

Table 54).

Page 139: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

139

Fig. 68: Updated distributions of (Δα)(i)

Table 54: Updated distributions of (Δα)(i)

Assessment Level Δαmean (Δαi) σln(Δα)i

Level 1 0.076 1.27

Level 2 0.005 2.26

As can be noticed, the updated value of the mean in the case of Level 1

assessment is close to that a priori (which was equal to 0.08), while for Level 2

assessment it is less, (0.04). In contrast, the updated values of standard deviation

σln(Δα)i are both larger than those a priori. This means that the variability of Δαi is

large and consequently the probability of obtaining a large decrease is also high.

The shape of the lognormal distribution is wider for values greater than the mean

value. In conclusion, the updated mean values are smaller than those a priori (in

particular for Level 2 assessment), but the standard deviations are larger and so

we can expect a larger decrease in the lack of capacity when an assessment

level is performed.

Applying the same methodology and costs already shown in Section 5.5, the

results shown in Table 55 are obtained.

0

0.05

0.1

0.15

0.2

0.25

0.3

0.35

0 0.5 1 1.5 2 2.5 3 3.5

pd

f[Δα

(i)]

Δα(i)

i=1

i=2

Page 140: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

140

Table 55: Results of optimization of alpha thresholds (decision tree for girder bridges with

documentation)

Alpha thresholds Bernoulli’s loss function Probability of failure as

an outcome

αa,(0) 0.15 0.00

αn,(0) 0.55 0.28

αa,(1) 0.20 0.16

αa,(2) 0.29 0.19

αn,(2) 0.55 0.28

αa,(3) 0.52 0.25

The results are quite different using Bernoulli’s loss function or the probability of

failure as an outcome. The reason is that the loss functions are very different from

each other. As can be noticed, in both cases the thresholds αa,(i) increase during

the transition to the following assessment level, while αa,(i) is constant.

Fig. 69 shows the decision tree for girder bridges with documentation and the

results of optimization of alpha thresholds using Bernoulli’s loss function.

Page 141: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

141

Fig. 69: Results of optimization of alpha thresholds using Bernoulli’s loss function (decision

tree for girder bridges with documentation)

L 1

L 0

L 2

L 3

αa(0

) < 0

.15

αr(0

) > 0

.55

θr

αr(2

)>

0.5

r(3)

>0

.52

θr

αa(1

) <0

.20

αa(2

)<

0.2

9

L (α

a(0

),α(0

))

r|αa

(0), L

(zθ

r|αa

(0))

r|αa

(2), L

(zθ

r|αa

(2))

r|αa

(3), L

(zθ

r|αa

(3))

L (α

a(1

),α(1

))L

(αa

(2),α

(2))

L (α

a(3

),α(3

))

Page 142: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

142

6.9 Conclusions

In this Chapter I apply the decisional model to the APT bridge stock after having

described the strategic objectives of the APT. The mid-term APT objective is to

assess in the next 10 years: the strategic road network for 72 ton free travel

vehicles, and 104 ton restricted travel vehicles; and the non-strategic network for

56 ton free travel vehicles, and 72 ton restricted travel vehicles. The final decision

tree adopted by the APT has been defined for reassessing existing bridges using

a multi-level verification procedure. Based on Level 0 analysis, of the 953 bridges

in the stock, 502 are automatically acceptable, while 429 need further re-

assessment before being formally acceptable. To re-assess substandard bridges,

the APT has launched a re-assessment program, expecting to find about 82

substandard bridges that need retrofit strengthening. The prediction of costs

shows that, with the current design documentation available, the total re-

assessment cost is equal to € 2,817,000. If the design documentation of all

bridges were available the total re-assessment cost would be equal to € 720,000

with a total saving equal to € 2,097,000. Hence it is very important to endeavor to

locate for the design documentation of bridges.

Finally, this Chapter has also described the optimization of the thresholds of the

lack of capacity based on the results of 20 APT bridge case studies. The results

show that as the number of assessment increases, the thresholds α can be

updated in order to optimize the choices of the decision maker. In comparison to

the a priori distribution, the updated probability distribution function shows that the

updated mean values are smaller than those a priori (in particular for Level 2

assessment), but the standard deviations are larger.

Page 143: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

143

7 CONCLUSIONS AND FURTHER WORK

7.1 Conclusions

In this thesis I illustrated how the problem of overweight traffic management can

guide transportation agencies, focusing on the legal issues entailed by

overweight/oversize load permits. More specifically, practical criteria have defined

for issuing overweight load permits, based on the definition of a number of

reference load models and on two travel conditions (free and restricted traffic). It

has been demonstrated that in the case of free road traffic, the transit of the

overweight load on the bridge depends only on the maximum span and on the

year of bridge design. Furthermore it is completely independent of the mechanical

conditions of the bridge. Moreover it has been obtained that when of a road is

closed to free traffic and the bridge is crossed in the center of the roadway, transit

of the overweight load on the bridge also depends on the transversal load

distribution.

A protocol has been defined for reassessing existing bridges using a multi-level

verification procedure and, tested with two case studies. The results show that the

decrease in terms of the lack of capacity of the bridge can be great. In fact, for

both cases, it was equal to 33% in the case of a 9x13t APT load (free travel

condition).

I applied utility theory to optimize the expected cost in order to propose a process

to guide the APT in making most cost effective decision when selecting the

appropriate level of verification. The choices of the decision maker depend on the

lack of capacity of the bridge obtained from Level 0 analyses. Different decision

trees have been defined for arch and girder bridges with and without design

documentation. The separation of decision trees is necessary due to the different

costs of the assessment levels with or without design documentation and the

different assessment methodologies for arch and girder bridges. In addition, a

Page 144: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

144

methodology has been proposed to optimize these thresholds of the lack of

capacity α, along with a method to update these parameters when a number of

case studies are available. These methodologies have been applied to the APT

bridge stock in accordance with the strategic objectives to assess/retrofit the APT

bridge stock. Based on the decision tree proposed and Level 0 analysis 502 of

the 953 bridges are automatically acceptable, while 451 need further re-

assessment. It is worth emphasizing that the APT is protected against legal

liability because the APT authorizes the transit of an overweight load that the

bridge designer would have allowed. The prediction of costs shows that, with the

current design documentation available, the total cost for reassessment of the

APT bridge stock is equal to € 2,817,000 (Table 56). If the maximum expected

utility principle was applied to determine the thresholds of the lack of capacity of

the decision trees instead of using an heuristic approach, the total saving would

be equal to 44,300,000 €, which corresponds to a 60% less.

Moreover, a methodology has been proposed for the optimization of the

thresholds of the lack of capacity based on a number of bridge case studies.

Table 56: Comparison between costs with and without documentation

Cost without documentation 2817 k€

Cost with documentation 720 k€

Saving 2097 k€

Number of bridges without documentation 314

Value of documentation 6.7 k€

7.2 Further work

The methodology proposed in this thesis has been applied to the APT stock using

information contained in the APT-BMS database. It was necessary to implement

the Courbon coefficient to obtain the transversal load distribution required to

calculate the lack of capacity in the case of bridge crossed in the center of the

carriageway. This was due to the absence of all the geometrical and mechanical

details of the deck in the APT-BMS database necessary to calculate the

Massonnet-Guyon-Bares coefficients. However, as it is planned to enter the data

of the Massonnet-Guyon-Bares coefficients for each bridge in the next two years,

it is recommended to re-assess Level 0 analyses using these more accurate

coefficients. Although the overall results should remain similar, the lack of

capacity of a number of particular cases could change.

Page 145: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

145

REFERENCES

American Association of State Highway and Transportation Officials (AASHTO),

(1997), Guide for Commonly Recognized (CoRe) Structural Elements (AASHTO:

Washington D.C.).

Adams T. M.,Malaikrisanachalee S., Blazquez C., Lueck S., Vonderohe A.,

(2002), Enterprise-wide data integration and analysis for oversize/overweight

permitting, J. Comput. Civ. Eng., 16(1), 11-22.

Bakht, B., Jaeger, L.G. (1984), A rational procedure for overweight permits,

Transportation Research Record 950, Transportation Research Board,

Washington D.C..

Bolstad W. M., (2007), Introduction to Bayesian Statistics, Wiley.

Bolstad W. M., (2010), Understanding Computational Bayesian Statistics, Wiley.

Bortot F., Zonta D., Zandonini R., (2009), La vulnerabilità sismica dei ponti della

Provincia Autonoma di Trento, XIII Convegno ANIDIS 2009 Bologna.

Brady S.P., Obrien E.J., and Znidaric A., (2006), The effect of vehicle velocity on

the dynamic amplification of a vehicle crossing a simply supported bridge, Journal

of Bridge Engineering, Vol. 11, Issue 2, pp. 241-249.

Branco, F. A., Correia, J. R. (2004), Software BIST – bridge investigation for

special heavy trucks. Study developed to Brisa, Report ICIST EP nº 33/04,

Lisbon.

Page 146: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

146

Bridge formula weights, (1994), United States Department of Transportation,

Federal Highway Administration, Washington, D.C.

Cantieni R., (1983), Dynamic Load Tests on Highway Bridges in Switzerland - 60

Years Experience of EMPA, EMPA Report No. 211, Swiss Federal Laboratories

for Materials Testing and Research, Dübendorf, Switzerland.

Cappello C., (2013), An implementation of expected utility theory in a civil

engineering decision problem, Master Thesis, University of Trento.

Chou K. C., Deatherage J. H., Leatherwood T. D., and Khayat A. J. (1999).

Innovative method for evaluating overweight vehicle permits. J. Bridge Eng., 4(3),

221–227.

Circolare M.LL.PP. n. 384 del 14/02/1962, (1962), Norme relative ai carichi per il

calcolo dei ponti stradali.

Circolare A.N.A.S. N° 820 DEL 15/03/1952, (1952), Carichi militari da considerare

nel calcolo dei ponti stradali.

CNR-UNI 10018/72, (1972), Istruzioni per il calcolo e l’impiego di apparecchi di

appoggio in gomma nelle costruzioni.

Correia J.P.R.R, Branco F. A. B. B., (2006), New methodology: Permit checking

of vehicular loads, Journal of Bridge Engineering, 11(3), 274-281.

Correia J.P.R.R, Branco F. A. B. B., Franco F., Matos J., (2005), Permit checking

of vehicular loads: A new methodology:, IABSE Symposium Lisbon 2005.

Courbon J., (1950), Application de la Resistance des Materiaux an Calculdes

Ponts, Dunod, Paris.

Crim M., (2005), Probabalistic assessment of bridge loading concurrent with

permit vehicles, Master thesis, University of Florida.

D.M. 26/03/1980, (1980) Norme tecniche per l’esecuzione delle opere in cemento

armato normale, precompresso e per le strutture metalliche.

Page 147: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

147

D.M.LL.PP. 02/08/1980, (1980), Criteri generali e prescrizioni tecniche per la

progettazione, esecuzione e collaudo di ponti stradali.

D.M.LL.PP. : 04/05/1990, (1990) Criteri generali e prescrizioni tecniche per la

progettazione, esecuzione e collaudo di ponti stradali.

Federal Highway Administration, (2012), Oversize/Overweight Load Permits,

http://ops.fhwa.dot.gov/freight/sw/permit_report, assessed 30 Oct. 2012.

Fiorillo, G. and Ghosn, M. (2014), Procedure for Statistical Categorization of

Overweight Vehicles in a WIM Database, J. Transp. Eng.

Fu, G. and O. Hag-Elsafi. (2000), Vehicular Overloads: Load Model, Bridge

mSafety and Permit Checking, Journal of Bridge Engineering, ASCE, 5(1), 49-57.

Fu, G., Moses, F. (1991), Overload permit checking based on structural reliability,

Transportation Research Record 1290, Transportation Research Board,

Washington, D.C..

Ghosn, M. (2000), Development of Truck Weight Regulations Using Bridge

Reliability Model, Journal of Bridge Engineering, ASCE, 5(4), 293-303.

Ghosn, M., Moses, F. (1987) Calibration of a bridge rating formula for overload

permits, Proc., ASCE Struct. Congr., Ed. L. Tall, 15-25.

Goodrich, B.L.; Puckett, J.A., (2000), Simplified load distribution for vehicles with

nonstandard axle gauges, Transportation research record, issue: 1696, pages:

158-170.

Guyon Y., (1946), Calcul des ponts larges a pouters multiples solidarisees par

des entretoises, Annalles des ponts et chausses, 533-612.

Harmon (1982), Surveys of Commercial Vehicles Weights 1975 to 1982, Report

Number RR-236. Ontario Ministry of Transportation. Ontario, Canada.

Heyman J., (1982), The masonry arch, Ellis Horwood Ltd.

Page 148: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

148

http://www.bms.provincia.tn.it

James, R. W., Noel, J. S., Furr, H. L., and Bonilla, F. E. (1986), Proposed new

truck weight limit formula, J. Struct. Eng., 112(7) 1589–1604.

Janko L., (1998), Reinforced concrete bridge structures, Muegyetemi kiado,

Budapest, Hungary.

Jordaan I., (2005), Decision under uncertainty Probabilistic analysis for

engineering decisions, Cambridge University Press.

Jorini, A.F., (1918),Costruzioni di ponti, Ed. Ulrico Hoepli, Milano.

Kurt C.E. (2000), A Proposed Modification of the Bridge Gross Weight Formula,

Mid-Continent Transportation Symposium 2000, pages 104-108.

Lastei A., (2011), Analisi dell’affidabilità dei ponti della Provincia Autonoma di

Trento in condizioni di transito di carichi eccezionali, Master Thesis, University of

Trento.

Massonnet, C. & Bares, R., (1968), Analysis of beam grids and orthotropic plates

by the Guyon-Massonnet-Bareš method. London: Lockwood; Prague: SNTL.

Meyerburg, A.H., J. Saphores, and R. Schuler, (1996), Collecting Usage Data for

Analyzing a Heavy-Vehicle, Divisible-Load Permit System. In Transportation

Research Record 1522, TRB, National Research Council, Washington, D.C., pp.

9-17.

MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI, (1992), Nuovo

codice della strada, D.L. 30 aprile 1992 n.285 e successive modificazioni,

Gazzetta Ufficiale della Repubblica Italiana, n. 114 ,18 maggio 1992.

MINISTERO DEI LAVORI PUBBLICI, (1991), Aggiornamento delle norme

tecniche per la progettazione, la esecuzione e il collaudo dei ponti stradali, D.M. 4

maggio 1990, Gazzetta Ufficiale della Repubblica Italiana, n.24 – Serie Generale

- 29 gennaio 1991.

Page 149: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

149

Normale n.6018 09/06/1945, (1945), e n.772 12/06/1946 M.LL.PP. (1946)

Norme relative ai carichi per il calcolo dei ponti stradali.

Normale n.8 DEL 15/09/1933 M.LL.PP. (1933), Carichi da considerare nel

calcolo dei ponti per strada ordinarie.

Nowak, A.S., H. Nassif, and L. DeFrain, (1991), Truck Loads on Michigan

Highways, Great Lakes Center for Truck Transportation Research, The University

of Michigan. Ann Arbor, MI.

Nowak, A.S., S. Kim, J.A. Laman, V. Saraf, and A.F. Sololik, (1994), Truck Loads

on Selected Bridges in the Detroit Area, Great Lakes Center for Truck and Transit

Research, Ann Arbor, MI.

Osegueda, R., Garcia-Diaz, A., Ashur, S., Melchor, O., Chang, S., Carrasco, C.,

and Kuyumcu, A., (1999), GIS-based network routing procedures for overweight

and oversized vehicles, Journal of Transportation Engineering, Vol. 125, No. 4,

July/August 1999, pp. 324-331.

Parmigiani G. and Inoue L., (2009), Decision theory: principles and approaches,

Wiley.

Paultre P., Chaallal O., and Proulx J., (1992), Bridge dynamic and dynamic

amplification factor – a review of analytical and experimental findings, Canadian

Journal of Civil Engineering, No.19, pp. 260-278.

Petrangeli M. P., (1996), Costruzione e progettazione di ponti con cenni di

patologia e diagnostica delle opere esistenti, Casa Editrice Ambrosiana.

Phares, B.M., Wipf, T.J., Klaiber, F.W., Wood, D.L., (2004), Bridge load rating for

superloads using testing, Second International Conference on Bridge

Maintenance, Safety, Management and Cost – IABMAS (International Association

for Bridge Maintenance and Safety), Eds. Watanabe, E., Frangopol, D.M.,

Utsunomiya, T.. Conference Proceedings. Kyoto.

Page 150: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

150

Senthilvasan J., Thambiratnam D.P., and Brameld G.H., (2002), Dynamic

response of a curved bridge under moving truck load, Engineering Structures,

Vol. 24, pp. 1283-1293.

Sonda D., Zonta D., Zandonini R., (2003), Stati dell'arte: valutazione dello stato di

sicurezza, BMS Report, Prodotto 1.4, BMS_SdA_4(1).

Thompson PD., Small EP., Johnson M., Marshall AR. (1998), The Pontis bridge

management system, Structural Engineering International 8(4): 303-308.

Sivia D., (2006), Data Analyses: A Bayesian Tutorial, Oxford University Press.

Vigh, A. and Kollár, L. (2006), Approximate Analysis of Bridges for the Routing

and Permitting Procedures of Overweight Vehicles, Journal of Bridge

Engineering, 11(3), 282–292.

Vigh, A. and Kollár, L. (2007), Routing and permitting techniques of overweight

vehicles, Journal of Bridge Engineering, 12(6), 774–784.

Yue Y. C., Zonta D., Bortot F., Zandonini R., (2010) Assessment of the operation

level of a bridge network in post–earthquake scenarios, Proc. 5th International

Conf. on Bridge Maintenance, Safety and Management (IABMAS2010),

Philadelphia, 11-15 Jul.

Zandonini R., Zonta D., Debiasi E., (2012), Valutazione della capacità al transito

di carichi eccezionali su ponti a travata: livelli 1, 2 e 3, Procedura BMS PR.CE.01

vers.1.1.

Zonta D., Zandonini R., Bortot F., (2009), Risk informed management of road

infrastructure, Safety and Reliability of Engineering Systems and Structures,

Rotterdam: MILL Press, 2009. Proc. "10th International Conference on Structural

Safety and Reliability (ICOSSAR 2009)", Osaka, 13-17 Sep.

Zonta D., Bortot F., Zandonini R., (2008) A condition index based on the concept

of Apparent Age, Bridge Maintenance, Safety, Management, Life-Cycle

Performance and Cost, Rotterdam: Balkema, 2008. Proc. "4th International Conf.

on Bridge Maintenance, Safety and Management (IABMAS08)", Seoul, 13-17 Jul.

Page 151: DECISION MAKING FOR BRIDGE STOCK MANAGEMENTeprints-phd.biblio.unitn.it/1193/1/Phd_thesis_Emiliano_Debiasi-(2).pdf · 1 University of Trento Emiliano Debiasi DECISION MAKING FOR BRIDGE

151

Zonta D., Zandonini R., Bortot F., (2007), A reliability-based bridge management

concept, Structure and Infrastructure Engineering, v. 3, n. 3, p.215-235.

Zonta D., Zandonini R., Bortot F., De Col R., Nicolussi Paolaz P., (2006), An

outline of the APT bridge management software, Bridge Maintenance, Safety,

Management, Life-Cycle Performance and Cost, Rotterdam:Balkema, 2006. Proc.

"3th International Conf. on Bridge Maintenance, Safety and Management

(IABMAS06)", Porto, 16-19 Jul.