DDG 51 Flight III RTC (Final)
-
Upload
samlagrone -
Category
Documents
-
view
492 -
download
39
Transcript of DDG 51 Flight III RTC (Final)
-
8/9/2019 DDG 51 Flight III RTC (Final)
1/33 Distribution Statement A
! Approved for Public Release.
REPORT TO CONGRESS
DDG 51 FLIGHT III SHIPS AIR AND MISSILE DEFENSE RADAR
ENGINEERING CHANGE PROPOSAL
Prepared by:
Assistant Secretary of the Navy
Research, Development, and Acquisition
1000 Navy Pentagon
Washington, DC 20350"1000
FEBRUARY 2015
The estimated cost of report or study for the Departmentof Defense is approximately $15030 for the 2015 FiscalYear. This includes $30 in expenses and $15000 in DoD
labor.
Generated on 2015Jan26 RefID: 4"42B2CD8
-
8/9/2019 DDG 51 Flight III RTC (Final)
2/33 Distribution Statement A
! Approved for Public Release.
2
Introduction
The Department of the Navy (DoN) submits this Report to Congress on the DDG 51 Flight III de-
sign status as directed by the Senate Armed Services Committee (S.Rept.112"173). The Depart-
ment is committed to the acquisition of the DDG 51 Flight III destroyers with an integrated Air and
Missile Defense Radar (AMDR) to meet the requirements for Integrated Air and Missile Defense(IAMD) capabilities. After several years of study, analysis, requirements validation, and prototype
testing, the AMDR S"Band system is poised for successful integration into the DDG 51 Class ships
as the Flight III upgrade.
This report summarizes the background of the DDG 51 Class program, explains the new AMDR
system, describes the final scope of the engineering change proposal (ECP) required to field the
ADMR on a DDG 51 hull, depicts the resulting Flight III ship configuration, and outlines the way
forward to ensure this vital capability reaches the Fleet as quickly as possible. This report will also
show that with respect to systems and equipment levels of maturity for Flight III, the AMDR is the
only new development technology. The AMDR has successfully completed Milestone B, a fullsystem Preliminary Design Review, a hardware Critical Design Review, and will deliver its first
full ship set of production equipment by early FY 2020. The remaining equipment required to pro-
vide power and cooling to the AMDR are all based on currently existing equipment and therefore
induce low technical risk to the program. Given the tremendous capability improvement AMDR
provides to defeat emerging air and ballistic missile threats over current radars, the low to moderate
technical risk associated with implementing this radar on an FY 2016 DDG 51 justifies execution
of the ECP during the FY 2013"2017 multiyear procurement contract.
The specific language in the NDAA for FY13, section 125, is as follows:
“Multiyear procurement authority for Arleigh Burke!class destroyers and associated systems (sec.
125). The committee believes that continued production of Arleigh Burke!class destroyers is criti-
cal to provide required forces for sea based ballistic missile defense (BMD) capabilities. The Navy
envisions that, if research and development activities yield an improved radar suite and combat
systems capability, they would like to install those systems on the destroyers in fiscal years 2016
and 2017, at which time the designation for those destroyers would be Flight III. Should the Navy
decide to move forward with the integration of an engineering change proposal (ECP) to incorpo-
rate a new BMD capable radar and associated support systems during execution of this multiyear
procurement, the Secretary of the Navy shall submit a report to the congressional defense commit-
tees, no later than with the budget request for the year of contract award of such an ECP. The re-
port will contain a description of the final scope of this ECP, as well as the level of maturity of thenew technology to be incorporated on the ships of implementation and rationale as to why the ma-
turity of the technology and the capability provided justify execution of the change in requirements
under that ECP during the execution of a multiyear procurement contract.”
-
8/9/2019 DDG 51 Flight III RTC (Final)
3/33 Distribution Statement A
! Approved for Public Release.
3
Background & Requirements
The ARLEIGH BURKE (DDG 51) Class ship is a multi"mission surface combatant capable of
meeting 21st century warfighting requirements. It operates offensively and defensively, inde-
pendently, or as part of Carrier Strike Groups (CSG), Expeditionary Strike Groups (ESG), and Mis-
sile Defense Action Groups in multi"threat environments that include Air, Surface, and Subsurface
threats. Ships will respond to Low Intensity Conflict / Coastal and Littoral Offshore Warfare (LIC/
CALOW) Scenarios as well as Open Ocean Conflict providing and augmenting Power Projection,
Forward Presence Requirements, and Escort Operations at sea. DDG 51 Class primary missions
are to:
Conduct simultaneous Anti"Air Warfare (AAW) and Ballistic Missile Defense (BMD) op-
erations
Detect, track, and identify air targets, and acquire and engage hostile targets with weapons
Detect, track, and identify ballistic missile targets, and acquire and engage hostile targets
with anti"
ballistic missile weapons
Conduct Electronic Warfare
Conduct Strike Warfare against land targets
Detect, locate, classify, and track submarines and conduct Anti"Submarine Warfare (ASW)
operations and engagements
Detect, locate, classify, and track surface contacts and conduct Anti "Surface Warfare
(ASUW) operations and engagements
Gather, display, and evaluate surface, subsurface, and air intelligence
!"#$%& ( ) !*"#+, --- ./&%0,"120* 3"&4
-
8/9/2019 DDG 51 Flight III RTC (Final)
4/33 Distribution Statement A
! Approved for Public Release.
4
The DDG 51 Class Program has awarded a total of 76 ships from 1985 to 2017 between two ship-
builders, General Dynamics Bath Iron Works (BIW) and Huntington Ingalls Industries (HII). Most
recently, 10 were awarded in June 2013 under Multi"Year Procurement (MYP) authority for FY13"
17. Sixty"two ships have been delivered. Of the remaining 14, six are in various stages of con-
struction and will deliver in 2016 and beyond. The Flight III configuration will be integrated viathe Engineering Change Proposal (ECP) process onto the last three ships of the FY13"17 MYP: one
ship in FY16 and both FY17 ships. A follow"on FY18 MYP will continue the production line.
Prior to Flight III, the program has produced three flights (I, II and IIA). Flights II and IIA included
important modifications for changing mission requirements and technology updates, thus demon-
strating the substantial capacity and flexibility of the base DDG 51 hull form. Flight II introduced
enhanced capability in Combat Systems and Electronic Warfare. Flight IIA constituted a more sig-
nificant change to the ship by incorporation of an organic dual hangar/dual helicopter aviation facil-
ity, extended transom, zonal electrical power distribution (ZEDS), enhanced missile capacity, and
reconfigured primary radar arrays. The combined scope and means for integrating the changes for
Flight III is similar to the approach used in the Flight IIA upgrade. Additionally, during Flight IIA production in the middle of the FY98"01 MYP, the class was significantly upgraded with a new ra-
dar, the AN/SPY"1D(V), and an improved combat management computing plant, AEGIS Baseline
7.1. The previous ship system changes were successfully executed by ECPs introduced via the ex-
isting systems engineering processes on both Flight II and IIA in support of the ongoing construc-
tion program. This methodology takes advantage of Navy and prime contractor experience with the
proven processes while offering effective and efficient introduction of the desired configuration
changes. It also provides the more affordable and effective approach toward producing this en-
hanced ship capability in lieu of starting a new ship design to incorporate the same capabilities into
a new production line for ship construction.
DDG 51 Flight III will be the third evolution of the original DDG 51 Class and will achieve the
U.S. Navy’s critical need for an enhanced surface combatant integrated IAMD capability. Flight III
will build on the warfighting capabilities of DDG 51 Flight IIA ships, providing this capability at
the earliest feasible time. Its defining characteristics include integration of the AMDR, associated
Combat Systems elements, and related Hull, Mechanical, and Electrical (HM&E) changes into a
modified repeat Flight IIA design. AMDR will give Flight III ships the ability to conduct simulta-
neous AAW and BMD operations. Flight III will contribute to mitigating the capability gaps identi-
fied in the Maritime Air and Missile Defense of the Joint Force (MAMDJF) Initial Capabilities
Document (ICD). The integrated Flight III ship system as delivered will meet the program require-
ments as stated in the DDG 51 Class Flight III Capabilities Development Document (CDD).
DDG 51 Flight III will execute four primary missions: (1) Integrated Air and Missile Defense, (2)
Anti"Surface Warfare, (3) Anti"Submarine Warfare, and (4) Strike Warfare, and will have the abil-
ity to plan, coordinate and execute alternate warfare commander responsibilities for either anti"air
warfare or ballistic missile defense.
-
8/9/2019 DDG 51 Flight III RTC (Final)
5/33 Distribution Statement A
! Approved for Public Release.
5
!"#$%& 5 ) 6%"70%8 !*"#+, --- 9+02#&:
The core changes between Flight IIA and Flight III and the systems technological maturity for
those changes are shown in Figure 2 and below. In addition to the incorporation of AMDR "S and
HM&E upgrades, the AMDR system will be integrated into the AEGIS Combat System. The evo-
lution of the AEGIS Combat System as it pertains to the DDG 51 Class is shown in Figure 3, a pro-
gression that will continue with the incorporation of AMDR and other technologies as shown inFigure 4.
!"#$%& ((( )*+&,-+ .,/%01"1$#/2" 32&45#&*
AMDR In Engineering & Manufacturing Development,
LRIP scheduled for FY 2017
MT"5 Gas Turbine Generator
Fielded on DDG 1000 class
4160VAC Electric Plant Fielded on LHA 6 Class
300 Ton A/C Plant In operation at vendor plant, environmental
qualification in progress
4160VAC to 1000VDC Power Conversion
Module
Fielded on DDG 1000 Class
-
8/9/2019 DDG 51 Flight III RTC (Final)
6/33
!"#$%& ; — -? 90/0@"*","&: =A1*$,"12
-
8/9/2019 DDG 51 Flight III RTC (Final)
7/33 Distribution Statement A
! Approved for Public Release.
7
Flight III Chronology
Flight III is an incremental upgrade to the DDG 51 Class, and includes tailored engineering modifi-
cations to this proven ship class to accommodate the larger, more powerful, and enhanced AMDR S"Band system. The shipboard changes are driven by the need for more electrical power, increased
system cooling capability, re"arrangements and added volume to make room for the AMDR system,
and structural changes to restore acceptable growth margin for the life of the ship. All major equip-
ment development is on track to support DDG 51 Class implementation of the AMDR in FY16.The current baseline design for the DDG 51 Flight III has traceability back to the DDG 113 design
and the Radar Hull Study performed in 2009 that evaluated the DDG 51 Class and resulted in selec-
tion of the preferred hull for the AMDR. The timeline below depicts the key studies, importantanalysis results, supporting design reviews, and Navy leadership decisions that led to restarting theDDG 51 production line and to the anticipated Detail Design of the Flight III ECPs over the past
five years.
!"#$%& B ) C1:, D&E&2, -? F0:&*"2&:
-
8/9/2019 DDG 51 Flight III RTC (Final)
8/33 Distribution Statement A
! Approved for Public Release.
8
DDG 51 Selected
Radar Hull Study (June – November 2009)
Evaluated incorporating IAMD capabilities into DDG 51 and DDG 1000 hull
DDG 51 with 14 foot AMDR "S w/ SPY"3 and AEGIS Combat System selected
Additional power generation and cooling required " Recommended additional study in
power and AMDR Integration
DDG 51 Restart CNO’s Evaluation Board (CEB) (23 December 2009)
Endorsed Flight III Upgrade Study
MAMDJF Gate 2 Review/ Resources & Requirements Review Board (R3B) (2 March 2010)
Validated results and findings of MAMDJF Analysis of Alternatives (AoA)
Approved AMDR program to proceed to Gate 2
Approved DDG 51 Flight III as preferred hull to proceed to Gate 2
Cancelled CG(X) program
DDG 51 Flight III Defined
Flight Upgrade Study, Year 1 (February 2010 – January 2011)
Technology Characterization
Trade Studies (assessed technology options for cost benefit)
Ship Concept Studies
Cost Analysis Comparison of the Flight III (IAMD) Ship Concepts
R3B held 11 February 2011
Approved 4,160 VAC power architecture on Flight III option with AMDR S and XBands
Flight Upgrade Study, Year 2 (February – May 2012)
Refined DDG 51 Flight III Ship Concepts
Evaluated 450 VAC architecture without AMDR X"Band, but with SPQ"9B
Supported Flight III CDD Requirements
Cost Analysis Comparison of Flight III Concepts
R3B held 11 June and 24 July 2012
Approved to proceed to Gate 3
Approved 4,160 VAC power architecture over the legacy 450 VAC distribution
system
Approved SPQ"9B as the X"Band radar
-
8/9/2019 DDG 51 Flight III RTC (Final)
9/33 Distribution Statement A
! Approved for Public Release.
9
DDG 51 Flight III Approved
Flight III, Gate 3 R3B (October 2012)
Approved Flight III CDD and Concept of Operations (CONOPs) for Joint Staffing
Flight III Preliminary Design (May 2012 – April 2014)
In Progress Reviews (IPRs) A, B, C, and D conducted to converge design, manage
changes, and retain Space, Weight, Power, and Cooling Service Life Allowance
(SWaP"C SLA)
Flight III Contract Design (July 2013 – October 2015)
Develop Engineering Change Proposals (ECPs)
AMDR Capability Development Document (CDD) Approved
Signed by CNO (20 April 2013)
Validated and signed by the JROC (27 June 2013)
AMDR Vendor Selected
Award Contract for AMDR S"Band and Radar Suite Controller (October 2013)
Award protested, start of work delayed
Protest withdrawn, work started (January 2014)
DDG 51 Flight III Preliminary Design Concurrence
Flight III Total Ship Design Review (TSDR) (18 March 2014)
Tailored Systems Engineering Technical Review (SETR) event to evaluate Flight III
Preliminary Design and early Contract Design deliverables
Report Stakeholder Steering Board’s concurrence and approval for the Flight III Pre-liminary Design to proceed to System Functional Review (SFR)
DDG 51 Flight III ECPs Approved
Flight III Gate 4/5 R3B (20 March 2014)
Approved core change ECPs for Flight III
Flight III Overarching Integrated Product Team (OIPT) (06 May 2014)
Concurrence on Flight III readiness for Defense Acquisition Board (DAB) IPR
-
8/9/2019 DDG 51 Flight III RTC (Final)
10/33
-
8/9/2019 DDG 51 Flight III RTC (Final)
11/33 Distribution Statement A
! Approved for Public Release.
11
Systems Engineering Approach
ECP development is a fundamental systems engineering approach; an approach currently imple-mented in the DDG 51 program that has been continuously updated and improved since the pro-
gram’s inception in the early 1980s and has resulted in the successful delivery of 62 DDG 51 Class
destroyers. The last three ships of the FY13"17 MYP are designated as Flight III beginning with
one of the FY16 ship. The Flight III is a modified repeat of the existing baseline and will be cen-tered on the addition of an IAMD capability in the form of the AMDR "S, associated enhanced com-
bat systems elements and requisite supporting HM&E changes. These changes will be incorporated
via discrete ECPs with the same proven processes and rigor that produced successful Flight II andIIA upgrades to the class. The list of the specific ECPs and the full scope of the Flight III change is
shown on the following page.
G0@*& ( ) !*"#+, --- 9HH D&I$"%&7&2,: ?$770%8
!"# %"&'(&)*+," %*&*)"-"&.
/!%%.0 !"# 1#.-") 2--&345-". /!12.0
6-7"& 1#.-") 2--&345-".
/612.0
8+-"9&*-": 23& *+: ;3..3(3+- ?(&,".
@"&-3,*< A*5+,73+9 1#.-") /@A10 B",-234-1#( *&%' 67)13. 889 :5;
-
8/9/2019 DDG 51 Flight III RTC (Final)
12/33 Distribution Statement A
! Approved for Public Release.
12
Mandatory Flight III Core IAMD Changes
Install AMDR S"Band System and Radar Suite Control (RSC)
Replace the AN/SPY"1D(V) Radar with the AMDR S"Band and Radar Suite Controller,
including related processors, cooling equipment, and power distribution equipment
Add (3) Electronic Equipment Fluid Coolers (EEFC) to support AMDR "S equipment
Install Technology Insertion 16 Upgrades (TI 16+)
Modify Common Data Link Management System (CDLMS) with Tech Refresh due to Ob-
solescence
Deckhouse structure redesign changes to support array system weight
Roll"down habitability changes to accommodate AMDR S"Band equipment
Mandatory Flight III Core IAMD Changes (continued)
Electrical Plant Upgrades
Procure and Install (3) 4,160 VAC Ship Service Gas Turbine Generators (SSGTGs)
Modify 450 VAC distribution equipment and protection scheme
Procure and Install 4,160 VAC distribution equipment and protection schemes
Procure and Install (3) 4,160 to 450 VAC Ship Service Transformers
Procure and Install (2) 4,160 VAC to 1,000 VDC Power Conversion Modules (PCM)
Modify seawater pump for 4,160 VAC SSGTGs
Install HeptaFluoroPropane (HFP) firefighting system for SSGTG modules
Redesign the Fire Control System water cooler
Replace 5x 200 rTon Air Conditioning (AC) plants with 5x 300 rTon HES/C AC plants
Install flooding cross"connects & expand hull in way of flight deck (FLODES)
Increase inner " bottom structure
Other Directed Changes
Install habitability changes to increase accommodations
Changes that will be effected to the AEGIS combat system to integrate AMDR into AEGIS will be
included in the Advanced Capability Build (ACB) represented in the AEGIS Combat Systems Evo-
lution, as shown in Figure 4.
-
8/9/2019 DDG 51 Flight III RTC (Final)
13/33 Distribution Statement A
! Approved for Public Release.
13
AMDR System Description
The AMDR suite consists of an S"Band radar (AMDR "S), X"Band radar (SPQ"9B), and a Radar
Suite Controller (RSC). AMDR "S is a new development IAMD radar providing sensitivity for long
range detection and engagement of advanced threats. The X"Band radar is a horizon"search radar
based on existing technology. The RSC provides radar resource management and coordination for
both S and X"Band, and interface to the combat system. The SPQ"9B, radar is already slated for
installation on the FY14 Flight IIA ships, and will not be further addressed in this report. Figure 5
shows the primary components of the AMDR system.
The AMDR "S and RSC development is managed by PEO Integrated Warfare Systems (IWS) 2.0(Above Water Sensors), and is contracted to Raytheon Integrated Defense Systems. The planar ar-
ray faces employ a digital beam"forming architecture, which replaces the analog waveguide system
!"#$%& J –
-
8/9/2019 DDG 51 Flight III RTC (Final)
14/33 Distribution Statement A
! Approved for Public Release.
14
of the legacy DDG 51 Class AN/SPY"1D(V) ar-
rays. Enhanced power and multi" beam operation
provides advanced, robust BMD detection and
discrimination. AMDR "S will be capable of de-tecting a target half the size at twice the distance
compared with its predecessor.
Physically arranging all the AMDR equipment
into the DDG 51 ship was a major portion of the
preliminary design effort. Much of the equip-
ment needs to be in close proximity to the array
faces to minimize high data rate cabling lengths.
This required placement of most of the pro-
cessing and control cabinets in the combat tower,
on the 03 Level. A key advantage of AMDR is
the elimination of radar waveguides. In previous
shipboard radars, the installation of waveguides
require significant material and manpower.
Figures 6 and 7 show the AMDR planar array and its components. Each of the four arrays is made
up of 37 building blocks called Radar Module Assemblies (RMAs). Each of these two foot RMA
cubes is a self "contained radar transmitter and receiver and are stacked together to form the re-
quired size array. The array employs an egg"crate structure to maintain flatness and hold the array
components. Liquid cooling is embedded within the system, and allows for Transmit"Receive Inte-
grated Multichannel Module (TRIMM) replacement without the need for liquid disconnects. Mod-
ular radiator/radome panels can be replaced using simple tools while at sea. Although only slightly
larger than the AN/SPY"1D(V), the
AMDR array is con-
siderably heavier and
deeper. Fitting the
new AMDR arrays
into the deckhouse
requires ship struc-
tural modifications to
accommodate the
arrays. Use of small-
er section modulus,
high strength beams
plus some local bulk
bulkead details
(notching) provide
sufficient clearance
without the need for
a major structural
redesign.
!"#$%& N )
-
8/9/2019 DDG 51 Flight III RTC (Final)
15/33 Distribution Statement A
! Approved for Public Release.
15
Figure 8 provides a general view of
the primary structural elements of
the DDG 51 deckhouse in the area
of the array installation. To accom-
modate the size and weight of the
AMDR arrays, resizing of many of
the structural elements was neces-
sary.
Other ship impacts, including the
arrangements, electrical, and cooling
requirements of the AMDR are ad-
dressed later in this report.
AMDR development has been ongo-
ing since 2006, with critical technol-
ogy elements as well as some sub-
systems developed prior to the Engi-
neering Development Model (EDM)
development phase. Since contract
award, multi"disciplinary incremen-
tal preliminary and critical design
reviews have been conducted on all
items (e.g. component, subassembly,
or configuration item), and have
been chaired and moderated by in-
dependent reviewers. Navy and in"
house independent subject matter
experts participated in all reviews.
Within these reviews, the topic areas
map to the Navy’s Technical Review Manual (TRM) and the conduct and closure of these interim
Critical Design Reviews (iCDRs) are formally tracked and reported at monthly reviews. Table 2
lists the iCDRs performed, all of which included Navy participation.
AMDR Hardware and Systems Preliminary Design Reviews were conducted 21 May and 27 Au-
gust 2014, respectively. On 3 December 2014, a Hardware CDR was successfully completed
which demonstrated that all Technical Performance Measures are compliant with requirements and
that the hardware design is of sufficient maturity to complete detail design and proceed to produc-
tion of the Engineering Development Model array.
The AMDR program is on track to deliver a substantial performance improvement over the current-
ly fielded AN/SPY"1D(V), with 30 times greater sensitivity. In order to deliver this needed capa-
bility on time and to mitigate development risk, the AMDR acquisition approach includes Agile
software development and a robust testing strategy that includes modeling and simulation anchored
Component Status
Radar Modular Assembly Complete
Radiator Complete
Radar Control Processing Cabinet Complete
Array Interface Unit Cabinet
Complete Digital Signal Processing Cabinet Complete
Digital Beam Forming Cabinet Complete
RSC Cabinet Complete
RTSS Cabinet Complete
Ship Wiring Complete
OLBFN Complete
Inertial Navigation System Complete
Array Integration Components Complete
Non RF LRU
Complete Array Mechanical Structure Complete
Array NFR Fixture Complete
Calibration Radar Modular Assembly Complete
Digital Beamformer (DBF) Complete
Digital Receiver Exciter (DREX) Complete
Transmit@Receive Integrated Multi-channel Module
Complete
Array Cooling System Complete
Low Rate Initial Production Cabinet Complete
DREX & DBF CDR
Complete
Power Distribution System Complete
G0@*& 5 ) 917/12&2, "9HD ?,0,$:
-
8/9/2019 DDG 51 Flight III RTC (Final)
16/33 Distribution Statement A
! Approved for Public Release.
16
with live flight tests. Raytheon has implemented
an Agile software development process for im-
proved productivity, earliest possible delivery of
tactical software, and improved testability. Ad-
ditionally, an AMDR Hardware in"the"Loop
(HWIL) facility, which includes a fully function-
ing portion of an AMDR array as well as all the
back "end processing equipment, and a Software
Integration Lab (SIL), consisting of another set
of AMDR back "end processing equipment, have
been installed and are operating at the contractor
facility in Sudbury, MA. The purpose of these
facilities, shown in Figure 9, is to support itera-
tive hardware and software testing ahead of, and
then in support of, the EDM array. AMDR is on
schedule to meet delivery dates for land basedtesting.
!"#$%& P ) H&EQ+1$:& ?,%$E,$%&
!"#$%& R )
-
8/9/2019 DDG 51 Flight III RTC (Final)
17/33 Distribution Statement A
! Approved for Public Release.
17
Electric Plant and Cooling Upgrades
Second to the AMDR instal-
lation, the Electric Plant
(EP) upgrades yield the next
largest change and ship im-
pact, and have been an area
of focus for the Flight III
design team.
The DDG 51 Flight IIA
SSGTGs generate 450 VAC
power, while the Flight III
SSGTGs will create 4,160
VAC; providing the addi-
tional electrical power nec-essary to meet the perfor-
mance requirements of the
more powerful AMDR system. Figure 10 depicts the Flight III EP and distribution system with
4,160 VAC power that is converted to both 1,000 VDC for the AMDR System and stepped down
to 450 VAC for all other electrical ship systems. Total installed EP power for the existing Flight
IIA ships is 9.0 MW (3x 3,000 KW) while the Flight III ships will have 11.5 MW (3x 3,850 KW).
To minimize both risk and cost, the 4,160 VAC SSGTGs are derived from the Rolls Royce MT"5
developed for DDG 1000, reducing development cost and providing commonality. The new 4,160
VAC (termed “high"side”) equipment and cabling imposes additional protection and increased
standoff clearances for safety and survivability. While 4,160 VAC is new to DDG 51 Class, within
the Navy the 4,160 VAC system and equipment is used in many other ship classes and the DDG 51
program has leveraged the existing high voltage requirements, standards, and other ship program
experiences. Additionally, the EP in-
corporates the existing Flight IIA 450
VAC power distribution system
(termed “low"side”) to save substan-
tial cost in complete redesign and test-
ing. Figure 12 shows the Electrical
Plant one line diagram, with the 450
VAC system shown in black and the4,160 VAC side depicted in blue.
To integrate the 4,160 VAC into the
DDG 51 EP, modifications to the
SSGTG technical and performance
specifications were necessary to ac-
!"#$%& (S ) !*"#+, --- =*&E,%"E 6*02, 912E&/,
!"#$%& (( ) BT(NS 3G> 9
-
8/9/2019 DDG 51 Flight III RTC (Final)
18/33
!"#$%& (5 ) !*"#+, --- =*&E,%"E 6*02, .2&)U"2& H"0#%07V WX"#+):"M& &I$"/7&2, "2 @*$&Y
-
8/9/2019 DDG 51 Flight III RTC (Final)
19/33 Distribution Statement A
! Approved for Public Release.
19
count for differences between the DDG
1000 and DDG 51 Class electric plants.
Modification to the DDG 1000 SSGTG
(MT"5) is necessary to meet the electric
power quality performance measures of the
AMDR suite and the existing Flight IIA
capability requirements. These changes are
already under government contract, man-
aged by the Electric Ships Office (PMS
320), with CDR completed in January 2015.
The generator modifications are underway
with PDR scheduled for February 2015.
SSGTG production contract was awarded in
January 2015, with the first hardware deliv-
eries in fall 2017. Shore power for the
Flight III is provided via existing low"side connection, although provisions have been made to ena-
ble high"side shore power should 4,160 VAC pier service becomes more common in the future.
High"side power is not available when on 450 VAC shore power; in the event that AMDR arrays
need to be activated, the ship will need to bring one of the three SSGTGs online.
In concert with the development of the revised 4,160 VAC SSGTGs, two types of power conver-
sion are required for the Flight III electrical distribution system. PCMs are being introduced to sup-
ply 1,000 VDC to the AMDR system. Two, 1.4 megawatt PCMs are being procured to convert
4,160 VAC from the SSGTGs to 1,000 VDC for the AMDR arrays. These machines have been
competitively awarded under the contract management of PMS 320. Like the SSGTGs, these units
are similar to those used on DDG 1000, but have been modified to meet the power quality require-
ments for the AMDR. The
two fully redundant units will
be installed on the Flight III
ships, located fore and aft for
maximum survivability. Op-
eration of these two PCMs
will allow load sharing be-
tween the two for maximum
redundancy, or isolated opera-
tion by only one unit for max-
imum survivability and im- proved fuel economy. The
other power conversion in-
volves three 4,160 VAC to
450 VAC step"down trans-
formers. These units are
standard equipment on larger
!"#$%& (B )
-
8/9/2019 DDG 51 Flight III RTC (Final)
20/33 Distribution Statement A
! Approved for Public Release.
20
ships, and the transformers specifical-
ly used for the Flight III are modified
units based on the LHD 8 design.
These units are planned to be con-
tracted as Class Standard Equipment
(CSE) using the DDG 51 Class ship-
builder’s procurement process and
will be competitively awarded. The
three transformers will be arranged to
allow any combination of SSGTGs and
transformers to provide power to the
legacy 450 VAC electric distribution
system. This flexibility allows the
operator to select the best plant con-
figuration depending on the need to balance fuel economy, redundancy, and survivability (battle
damage) while providing power to any and all portions of the ship’s combat and HM&E systems.
The AMDR system requires power to the processing cabinets at 208 VAC. Conditioning equip-
ment is provided by the AMDR vendor as a complete system, as depicted in Figure 14. First con-
verted through a single transformer, the power is filtered and conditioned by three notch filters and
three UPS cabinets to provide power conditioning and control. The UPS units also provide uninter-
rupted power via the battery cabinets, in the event of a loss of ship’s power. The conditioned pow-
er is then distributed to the various AMDR processing cabinets, and to the AMDR arrays.
Steady state analysis of the Electric Plant in various configurations has shown the architecture to be
sound, safe, and capable of providing sufficient power for all Flight III needs. Extensive analysis is
underway by the Flight III team to ensure all transient plant reactions and abnormal configurationsare accounted for, using a Dynamic Model Analysis (DMA) tool. A study guide was established by
the Navy team including PMS 400D, PMS 320, and SEA05 to define the effort. Figure 15 shows a
typical analysis output. The overall approach for each investigation concentrates on applying worst
case assumptions, identifying potential issues, then refining the modeling parameters for more ac-
curate analysis. The DMA study analyzes transients, power quality, power continuity, and surviva-
bility. The results provide guidance to refine the plant configurations and amend the CONOPS to
afford the best practices which will be the basis of ships operations and crew training.
To date the DMA has completed the studies on transient analysis, power quality analysis, and work
is underway for the continuity analysis. The continuity analysis will look at any scenario, includingload shedding, where predicted transients are outside the design parameters, to ensure that the EP
protection gear will prevent system damage. The final phase of the study, scheduled for summer
2015, is a survivability analysis that will look at battle damage and recovery.
More electrical power is nearly always associated with increased heat loads, and the addition of
AMDR to the DDG 51 Class requires upgrades to the ship’s cooling capability. The existing Flight
IIA Air Conditioning (AC) plants, or chillers, are replaced with a modified system that increases
!"#$%& (J ) G8/"E0* H8207"E C1M&*"2#
-
8/9/2019 DDG 51 Flight III RTC (Final)
21/33 Distribution Statement A
! Approved for Public Release.
21
Combat System Integration
AMDR will be integrated into the AEGIS combat system via the software in ACB 20. The hard-
ware will remain the TI"16 suite, with added processors and consoles to meet the Flight III require-
ments.
The inclusion of AMDR into AEGIS ACB 20 was based on the extensive analysis through the PEO
IWS led Capability Phasing Plan (CPP) process. The CPP utilizes disciplined, analytical, coordi-nated processes to assess capability gaps and identify and prioritize combat system solutions for
ACB 20. CPP analytical factors include:
Threat Assessment
Fleet Warfighting Capability Gaps
Kill Chains
Schedules
Cost Estimates
External Reliance
Risks
Concept of Employment (CONEMP), Concept of Integration (COI).
The CPP working group coordinated across the Fleet, PEOs, System Commands (SYSCOMs),
Missile Defense Agency (MDA), Science and Technology (S&T) and Industry. The CPP process
mapped the results of the gap assessments with candidate warfighter capabilities, applying kill"
chain analysis and cost estimation for integration into the AEGIS combat system. The result
cooling from five 200 refriger-
ation ton (rTon) units to five
300 rTon units. Flight III will
leverage the new 300 rTon
High Efficiency Small Capaci-
ty (HES"C) system already
being developed and scheduled
for installation in the LPD
Class ships. Based on the ex-
isting 200 rTon AC plant con-
denser, the HES"C employs oil
free magnetic bearings for re-
duced friction and reduced
maintenance. The HES"C
chiller fits within the footprint of the existing unit, but Variable Speed Drive (VSD) cabinets are a
new addition to the machinery space arrangements. The VSD improves system efficiency, reducesinrush currents, and improves reliability. An economizer is added for improved efficiency when
seawater temperature is above 75 degrees F. Figure 16 shows the prototype HES"C 300 rTon AC
unit.
!"#$%& (N ) 6%1,1,8/& X=?Z9 ;SS %,12
-
8/9/2019 DDG 51 Flight III RTC (Final)
22/33 Distribution Statement A
! Approved for Public Release.
22
!"#$%& (O ) 917@0, -2L1%70,"12 9&2,&% W9-9YT [1,"120* ?"2#*& ?+"/-
-
8/9/2019 DDG 51 Flight III RTC (Final)
23/33 Distribution Statement A
! Approved for Public Release.
23
!"#$%& (P ) 9-9
-
8/9/2019 DDG 51 Flight III RTC (Final)
24/33 Distribution Statement A
! Approved for Public Release.
24
ing skids, used on CG 47 Class ships, with improvements for corrosion control and user inter-
face. This reduces developmental efforts and maximizes parts commonality for the Fleet.
Electronic Equipment Fluid Coolers (EEFCs) are introduced on Flight IIA ships on DDG 119 toeliminate two large cooling skids. The EEFCs are point of service coolers for the combat system
equipment throughout the ship. The implementation of this change enabled removal of the SonarEquipment Cooling Skid and the Control and Display (C&D) Cooling Skid. The removal of thisequipment is necessary to make room for the Flight III 4,160 VAC switchgear and other equip-
ment.
Another enabling technology being incorporated prior to Flight III is Integrated Power Node
Center (IPNC). Implemented on DDG 121 and follow ships as a cost reduction initiative, the IP- NCs will replace the current DDG 51 400Hz electrical service architecture, removing the single
large converter, over 100 pieces of support equipment, and a large amount of cabling. The IP-
NCs are point of service converters (there will be eight on the Flight IIA ships), which will retain
the same functionality as displaced equipment. Space vacated by the older 400 Hz frequency
converter allows optimal location of the Flight III PCMs.
Figure 19 diagrams the significant integration testing of AMDR with the AEGIS Weapon Sys-
tem.
-
8/9/2019 DDG 51 Flight III RTC (Final)
25/33
!"#$%& (R )
-
8/9/2019 DDG 51 Flight III RTC (Final)
26/33 Distribution Statement A
! Approved for Public Release.
26
Ship Integration and Impacts
Flight III configuration with AMDR and necessary electric plant and cooling upgrades impose a
number of ship arrangement changes to the DDG 51 Class ship. Additional equipment requires the
representative number of machinery arrangements or relocations of displaced equipment in several
ship spaces, as well as the expansion of deckhouse volume by adding a starboard enclosure similar
to what was done on DDG 91 through DDG 96 for the Remote Minehunting System (RMS). The
added weight of these systems and structural impacts require additional efforts to retain sufficient
future growth margins for ship stability in terms of weight and KG (center of gravity). A rigorous
systems engineering effort was undertaken during preliminary design to mitigate these impacts.
Growth margins will be successfully obtained by executing the modifications described in the para-
graphs below. Figure 20 shows the arrangement of the AMDR array rooms, and the processing
cabinets in Radar Room 2. The two fan rooms outboard of Radar Room 2 will be upsized to handle
the added cooling needs of this equipment.
Two propylene glycol based Cooling Equipment Units (CEUs) are added below decks on the 2ndPlatform, as shown in Figure 21. The CEUs are based on existing DDG 1000 units. PCMs andswitchgear for 1,000 VDC are placed in the two power conversion rooms, with the forward space
shown in Figure 21. Additional equipment is located in Combat System Equipment Room (CSER)
#2 and the Power Supply Room, shown in Figure 22.
!"#$%& 5S ) S; U&A&* 6%&*"7"20%8
-
8/9/2019 DDG 51 Flight III RTC (Final)
27/33 Distribution Statement A
! Approved for Public Release.
27
The CEU equipment dis-
places crew bunks previous-
ly in Crew Living Space 2.
The Flight III CDD requiresincreased accommodations,
which is accomplished byadding a starboard side en-closure on the 01 Level, and
by increasing most officer
staterooms to a three"rackconfiguration. The new star-
board side enclosure is
shown in Figure 23, just aft
of the now stacked RigidHull Inflatable Boat (RHIB)
configuration. The existing
boat davit retained thestacked boat height require-ment even after the RMS
was removed, so no new procurement is required for this change.
There are also arrangements changes in the machinery spaces as a result of the additional switch-
gear and EP protection gear. Preliminary design efforts have shown feasible locations for all major
equipment. General arrangements will be further refined in Detail Design.
!"#$%& 55 ) 6%&*"7"20%8 0%%02#&7&2,: 1L 9?=D]5 02M 614&% ?$//*8 D117
!"#$%& 5( ) 6%&*"7"20%8
-
8/9/2019 DDG 51 Flight III RTC (Final)
28/33 Distribution Statement A
! Approved for Public Release.
28
Beyond arrangement there are associated effects to the ship’s weight and KG. To maintain ac-ceptable margin for future growth, the Flight III team was able to improve the ship’s reserve buoy-
ancy by increasing the flight deck beam above the waterline, combined with cross flooding ducts to
raise the ship’s limiting displacement to 10,700 tons (increased from 10,300 tons). This designchange allowed an increase in inner " bottom structural weight to lower the ship’s center of gravity
(KG), an approach that was also used for the design of the Flight IIA ships. Increased inner " bottom
structure has the added benefit of further strengthening the hull girder, thereby improving resistance
to underwater explosives.
The DDG 51 Class ships have been densely outfitted and internal space (volume) limited for sometime. Other SWaP"C allowances are within reasonable design practices and the CDD requirements.
Current ship design parameters are listed below.
Select Flight III Characteristics and Service Life Margins
Displacement: 9709 ltons Displacement SLA: 991 ltons (10.2%)
KG: 24.96 ft KG SLA: .62 ft
Electric Load: 5,458 kW Electric SLA: 1,904 kW (40%)
Cooling Load: 1,206 rtons Cooling SLA: 294 rtons (20%)
Impacts to all subsystems continues to be refined, with the DDG 51 Class Design Agent (BIW)now maintaining configuration control of the ECP packages. The design agents from both DDG
51 shipbuilders, BIW and HII, are under contract to continue development of the Flight III ECPs.
!"#$%& 5; ) S( U&A&* 0%%02#&7&2,: :+14"2# 2&4 &2E*1:$%&
-
8/9/2019 DDG 51 Flight III RTC (Final)
29/33 Distribution Statement A
! Approved for Public Release.
29
Flight III Program Execution and Risk Management
The Flight III program is supported by appropriate design execution, Systems Engineering Tech-
nical Reviews, and stakeholder relationships consistent with meeting requirements and overall pro-
gram schedule. Major supporting component developments for AMDR "S, PCMs, and SSGTGs are
well underway by the associated Participating Resource Managers (PARMs) with schedules andmilestones that support the overall Flight III delivery targets. Detail design was started in FY14
with the Program Office delivering Government Furnished Information (GFI) to the shipyard ser-vices to support continued Flight III development. Continued development of GFI will support de-
tail design fidelity leading to successful Preliminary Design Review (PDR), Critical Design Review
(CDR), and Production Readiness Review(PRR) targeting 90% design completion sup-
porting start of construction. Significant Flight
III milestone dates for design and construction
are captured in Table 3. PARM schedules areintegrated with anticipated in"yard need dates
for construction and testing resulting in suc-cessful light"off and delivery targeted for
FY22. Management approach to supportingconstruction, test, and delivery will be con-
sistent with multi"year procedures already in
place.
The DDG 51 AEGIS program office employs a risk management plan based on the guidance pro-vided in applicable Defense Acquisition documents, which were then tailored specifically to the
DDG 51 Flight III program. Risk management occurs in main areas for Flight III: AMDR/RSC
development, combat system development and total ship design, including HM&E modifications
necessary to support AMDR and the combat system.
DDG 51 Flight III risk management is tracked internally by a Risk Management Board (RMB)which meets quarterly. Participants of the RMB include the AEGIS program office, shipyard rep-
resentatives, and PARM (AMDR, SSGTG, and PCM) representatives, along with combat system
and ship design team members. The purpose of these meetings is to discuss and track the status on
current risks, along with introducing any additional risks that may need to be added to the risk reg-ister. Once a risk is entered into the risk register, it is tracked through the life of the program.
Quarterly RMB reviews and numerical rescoring of the risk show trends and effectiveness of miti-
gation efforts.
Conclusion
This report has provided a description of the final scope of the ECP required to field the ADMR on
a DDG 51 hull, and has detailed the level of maturity of the new technology to be incorporated on
these ships, beginning with one of the two DDG 51s in FY 2016. With respect to Flight III systems
level of maturity, the AMDR is the only new development technology. The AMDR has successful-
ly completed Milestone B, a full system Preliminary Design Review, a hardware Critical Design
Review, and will deliver its first full ship set of production equipment by early FY 2020. The re-
Event Schedule
Begin Detail Design Q4 2014
Start Construcon Q3 2017
AEGIS Light"Of Q3 2020
Delivery Q3 2021
G0@*& ; ) !*"#+, --- ?E+&M$*&
-
8/9/2019 DDG 51 Flight III RTC (Final)
30/33 Distribution Statement A
! Approved for Public Release.
30
maining equipment required to provide power and cooling to the AMDR are all based on currently
existing equipment and therefore induce low technical risk to the program. Given the tremendous
capability improvement AMDR provides to defeat emerging air and ballistic missile threats over
current radars, the low to moderate technical risk associated with implementing this radar on an FY
2016 DDG 51 justifies execution of the ECP during the FY 2013"2017 multiyear procurement con-
tract.
This report has assembled the latest available design and integration information based on the re-
cent design reviews, assumptions, decisions, and sources provided to address the questions posed.
In summary, the AMDR technology has matured, ship impacts are clearly understood, and design
efforts are underway for ECP development. The Navy's intention, as stated and supported by the
contents of this report, is to integrate AMDR "S into the DDG 51 ARLEIGH BURKE Class ships
beginning with the last ship of FY16. The AMDR "S integration with the proven AEGIS Combat
System into the DDG 51 Flight IIA by ECP is the shortest path to meet fleet requirements for cost
effective IAMD capability with the lowest technical and cost risk.
-
8/9/2019 DDG 51 Flight III RTC (Final)
31/33 Distribution Statement A
! Approved for Public Release.
31
Additional Reading:
Commander, Naval Sea Systems Command (SEA 05D), DDG 51 Class Flight Upgrade Tech-
nical Concept Study, Year 1, Ser 05D/054, 23 Feb 2011. (FOUO, Limited Distribution)
Commander, Naval Sea Systems Command (SEA 05D), DDG 51 Class Flight Upgrade Tech-
nical Concept Study, Year 2, Ser 05D/434, 14 Dec 2012. (FOUO, Limited Distribution)
Capabilities Development Document (CDD) for the DDG 51 Flight III, JROCM 122"14, 28 Oc-
tober 2014
Future DDG (Radar/Hull) Study Final Report (U), Dated 10 November 2009 (CLASSIFIED
Document)
Maritime Air and Missile Defense of the Joint Forces (MAMJDF) Initial Capabilities Document
(ICD) Dated 01 May 2006 (CLASSIFIED Document)
Air and Missile Defense Radar (AMDR) Top Level Radar Performance (TLRP) for AMDR S"
Band, Appendix F document, dated 10 November 2009 (CLASSIFIED Document)
Air and Missile Defense Radar (AMDR) Capability Development Document (CDD), JROCM
123"13, 27 June 2013 (CLASSIFIED Document)
Surface Ship Theater Air and Missile Defense Assessment (SSTAMDA) Summary Study Re-
port, N86/8S177518, 09 Jul 08 (CLASSIFIED Document)
-
8/9/2019 DDG 51 Flight III RTC (Final)
32/33
-
8/9/2019 DDG 51 Flight III RTC (Final)
33/33
rTons Tons of Refrigeration Capability
RTSS Real"Time Simulation Subsystem
S&T Science and Technology
SETR
Systems Engineering Technical Review
SEWIP Surface Electronic Warfare Improvement
Program
SFR System Functional Review
SIL Software Integration Lab
SLA Service Life Allowance
SSGTG Ship Service Gas Turbine Generator
SWaP"C Space, Weight, Power, and Cooling
SWTRG Surface Warfare Tactical Requirements
Group
SYSCOM System Command
TI
Technology Insertion
TRIMM Transmit"Receive Integrated Multichannel
Module
TRM Technical Review Manual
TSDR Total Ship Design Review
UAV Unmanned Aerial Vehicle
UPS Uninterruptible Power Supply
USW Undersea Warfare
VLS Vertical Launching System
VSD Variable Speed Drive
ZEDS Zonal Electrical Distribution System