Dd capacity scheduling

28
All material and © copyright Demand Driven Institute 2013, all rights reserved Demand Driven Capacity Scheduling and Execution Chad Smith Partner, Demand Driven Institute Co-Author Orlicky’s Material Requirement Planning 3/E Co-Author Demand Driven Performance – Using Smart Metrics

Transcript of Dd capacity scheduling

Page 1: Dd capacity scheduling

All material and © copyright Demand Driven Institute 2013, all rights reserved

Demand Driven Capacity Scheduling and Execution

Chad SmithPartner, Demand Driven InstituteCo-Author Orlicky’s Material Requirement Planning 3/ECo-Author Demand Driven Performance – Using Smart Metrics

Page 2: Dd capacity scheduling

All material and © copyright Demand Driven Institute 2013, all rights reserved

Planning and Scheduling is Harder Than Ever

• The Manufacturing and Supply Chain landscape is more volatile than ever – the bullwhip is alive and well in today’s environment

• Customer Tolerance Times have decreased substantially relative to the time it takes to procure, manufacture and distribute items

• Product variety, options and complexity has put tremendous pressure on planning and scheduling systems

• FLOW is the critical link between service, asset utilization and ROI

Page 3: Dd capacity scheduling

All material and © copyright Demand Driven Institute 2013, all rights reserved

The Demand Driven Operating Method

• The protection of FLOW is paramount• ROI is directly proportionate to the speed of flow

of relevant materials and information• Demand Driven operating methods seek to

protect the flow of both relevant information and materials

Page 4: Dd capacity scheduling

All material and © copyright Demand Driven Institute 2013, all rights reserved

DDMRP and Capacity Scheduling

• DDMRP has Implications for Capacity Scheduling• Advanced Session Webinars• Download the paper on DDMRP Master Scheduling for

more information

Page 5: Dd capacity scheduling

DDMRP Scheduling Basics

DDMRP uses buffered “Decoupling Points” to establish independent planned and scheduled horizons.

DDMRP creates resupply signals based on the “available stock” status of each buffer. This gives prioritized sequence based on actual need.

On-the-floor priority is then determined by the real time buffer status of the decoupling points that the open orders are feeding.

Page 6: Dd capacity scheduling

All material and © copyright Demand Driven Institute 2013, all rights reserved

When Will we Need More Scheduling Capability?

• When the use of better shop floor scheduling will compress lead times and reduce variability so that make item stock buffers can be reduced.

• When no decoupling point can be inserted before the shipping point. (Make or Configure to Order)

• Mixed-mode operation

Advanced Topics Webinar 3

Page 7: Dd capacity scheduling

All material and © copyright Demand Driven Institute 2013, all rights reserved

An Mixed-Mode Example

5 10 15

10 5 10

10

5

30 10 20 Customer

Supplier

Supplier

Purchased Components

Suppliers

In this case better scheduling and execution is required to synchronize and prioritize the make to stock and make to order business.

Better lead time and less variability within the plant will reduce the end item buffer.

Page 8: Dd capacity scheduling

All material copyright 2013 Constraints Management Group, LLC

Extending the Demand Driven Method

• The extension of Demand Driven methods to shop floor scheduling and execution can be seen in the new book Demand Driven Performance –Using Smart Metrics

• A series of articles in Strategic Finance Magazine previews the book – the articles are available for free download

Page 9: Dd capacity scheduling

All material copyright 2013 Constraints Management Group, LLC

Introducing Control Points

• Places to transfer, impose, and amplify control through a system. 

• The 14th edition of the APICS Dictionary defines control points as “Strategic locations in the logical product structure for a product or family that simplify the planning, scheduling, and control functions. Control points include gating operations, convergent points, divergent points, constraints, and shipping points. Detailed scheduling instructions are planned, implemented, and monitored at these locations.”(p. 33)

C

Page 10: Dd capacity scheduling

All material copyright 2013 Constraints Management Group, LLC

Placing Control Points

Placed between decoupling points with the objective of better controlling the lead‐time zones between those points. A shorter and less variable lead time results in less stock required at the decoupling point (a working capital reduction).

C

Page 11: Dd capacity scheduling

All material copyright 2013 Constraints Management Group, LLC

Placing Control Points

Placed between decoupling points and a customer when decoupling the end item is not possible or in a mixed mode operation.

Customer

Customer

Customer

C

Make/Configure to Order

Page 12: Dd capacity scheduling

All material copyright 2013 Constraints Management Group, LLC

Determining Control Points

1. Points of Scarce Capacity determine the total system output potential. The slowest resource‐‐the most loaded resource—limits or defines the system total capacity.2. Exit and Entry Points are the boundaries of your effective control. Carefully controlling that entry and exit determines whether delays and gains are generated inside or outside your system.3. Common Points are points where product structures or manufacturing routings either come together (converge) or deviate (diverge). One place controls many things. 4. Points that Have Notorious Process Instability are good candidates because being a control point provides focus and visibility to the resource and forces the organization to bring it under control or plan for, manage, and block the effect of its variability from being passed forward. 

Page 13: Dd capacity scheduling

All material copyright 2013 Constraints Management Group, LLC

Placing a Control Point

5 10 15

10 5 10

10

5

30 10 20 Customer

Supplier

Supplier

Purchased Components

Suppliers

In this case we have a resource is both the slowest pace resource as well a major integration point in the routings

C →

→ →

Page 14: Dd capacity scheduling

All material copyright 2013 Constraints Management Group, LLC

Scheduling a Control Point

5 10 15

10 5 10

10

5

30 10 20 Customer

Supplier

Supplier

Purchased Components

Suppliers

C

Replenishment orders

Sale

s O

rder

Dem

and

1 2 3 4 5 6 7 8 9 10 11 12

Capacity

The control point is finitely scheduled with both MTS and MTO orders

Sales orders→

Loading is important to see for lead time quotation

Page 15: Dd capacity scheduling

All material copyright 2013 Constraints Management Group, LLC

Synchronizing Material Release

5 10 15

10 5 10

10

5

30 10 20 Customer

Supplier

Supplier

Purchased Components

Suppliers

C

Schedule material release to the control point schedule

Work orders

Work orders

Work orders

Late release will jeopardize the control point scheduleEarly release raises WIP levels unnecessarily

Page 16: Dd capacity scheduling

All material copyright 2013 Constraints Management Group, LLC

Control Point Schedules

30 Customer

Supplier

Supplier

Purchased Components

Suppliers

C

We now have five schedules – all synchronized around a resource Control Point schedule (Drum)

DRUM

Page 17: Dd capacity scheduling

All material copyright 2013 Constraints Management Group, LLC

Protecting the Schedule

5 10 15

10 5 10

10

5

30 10 20 Customer

Supplier

Supplier

Purchased Components

Suppliers

C

We must insulate the schedules against the accumulated variability that occurs in the sequences preceding the schedule – delays are passed on, gains are not

How can we make sure that the schedules are maintained (not rescheduled)?

Note: the purchased part stock buffers protect the material release schedules against supplier variability

Page 18: Dd capacity scheduling

All material copyright 2013 Constraints Management Group, LLC

Time Buffers

Scheduled Start at Control Point

Scheduled Entry to Buffer

Early Late

WO 1595

WO 1781

WO 1601

WO 3279

WO 2001

WO 1626

C→

Upstream Processes

BUFFERGreen Yellow Red

Example: 9 hour buffer

Page 19: Dd capacity scheduling

All material copyright 2013 Constraints Management Group, LLC

Buffers Inserted

5 10 15

10 5 10

10

5

30 10 20 Customer

Supplier

Supplier

Purchased Components

Suppliers

C

Page 20: Dd capacity scheduling

All material copyright 2013 Constraints Management Group, LLC

The 10 Zone Buffer BoardScheduled Start at

Control Point

Scheduled Entry to Buffer

Early LateBUFFERGreen Yellow Red

Example: 9 hour buffer

Early LateBUFFERGreen Yellow Red

Yet to be Received

Received

WO 1626

WO 1626

Green

Yellow

Red

OK

Investigate

ACT

Page 21: Dd capacity scheduling

All material copyright 2013 Constraints Management Group, LLC

How a Buffer Board works

Received

Yet to Be Received

48709-01

Early

Early

Green

Green Yellow

Yellow Red

Red

Late

Late

9 Hours of BufferTime scheduled

on Drum(Wed 7:00 pm)

48801-01

Note: 16 hour work day

Current Day and Time: Monday, 7:00 am

Page 22: Dd capacity scheduling

All material copyright 2013 Constraints Management Group, LLC

How a Buffer Board works

48709-01

Early

Early

Green

Green Yellow

Yellow Red

Red

Late

Late

9 Hours of BufferTime scheduled

on Drum(Wed 7:00 pm)

48801-01

Current Day and Time: Wednesday, 10:00 am

Received

Yet to Be Received

Note: 16 hour work day

Page 23: Dd capacity scheduling

All material copyright 2013 Constraints Management Group, LLC

How a Buffer Board works

48709-01

Early

Early

Green

Green Yellow

Yellow Red

Red

Late

Late

9 Hours of BufferTime scheduled

on Drum(Wed 7:00 pm)

48801-01

Current Day and Time: Wednesday, 1:00 pm

Received

Yet to Be Received

Note: 16 hour work day

Page 24: Dd capacity scheduling

All material copyright 2013 Constraints Management Group, LLC

How a Buffer Board works

48709-01

Early

Early

Green

Green Yellow

Yellow Red

Red

Late

Late

9 Hours of BufferTime scheduled

on Drum(Wed 7:00 pm)

48801-01

Current Day and Time: Wednesday, 4:00 pm

Received

Yet to Be Received

Note: 16 hour work day

Page 25: Dd capacity scheduling

All material copyright 2013 Constraints Management Group, LLC

How a Buffer Board works

48709-01

Early

Early

Green

Green Yellow

Yellow Red

Red

Late

Late

9 Hours of BufferTime scheduled

on Drum(Wed 7:00 pm)

48801-01

Current Day and Time: Wednesday, 5:00 pm

Forced Reason CodeReceived

Yet to Be Received

Note: 16 hour work day

49322-0149527-03

Page 26: Dd capacity scheduling

All material copyright 2013 Constraints Management Group, LLC

How a Buffer Board works

48709-01

Early

Early

Green

Green Yellow

Yellow Red

Red

Late

Late

9 Hours of BufferTime scheduled

on Drum(Wed 7:00 pm)

48801-01

Current Day and Time: Wednesday, 7:00 pm

49322-0149527-03

Received

Yet to Be Received

Note: 16 hour work day

Page 27: Dd capacity scheduling

All material copyright 2013 Constraints Management Group, LLC

Reason Code Analysis

Page 28: Dd capacity scheduling

All material copyright 2013 Constraints Management Group, LLC

Analyzing Buffers Over Time

Early LateBUFFERGreen Yellow Red