David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison...

19
David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison WI

Transcript of David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison...

Page 1: David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison WI.

David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003

IceTop Baseline Review

Dec. 4, Madison WI

Page 2: David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison WI.

David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003

Agenda

• Agenda (5)• Scope of review (5)• Overview of IceTop (25)

– Science– System Design– Tasks, Effort– Budget

• Engineering Requirements (10)– Status of ERDs– Overview of CI's

• Critical components (50)– Tank Assembly (15)– Deployment (20)– Cables (5)– DAQ (10)– Simulations

• WBS & Dictionary (15)– IceTop– IceTop Integration

• PY2 plan (15)– SOW– October summary

• Project plan (20)– Milestones– Schedule – Budget– Risks

• Issues, Concerns (10)• Summary & Discussion (15)

Page 3: David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison WI.

David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003

Scope

• Review IceTop Baseline– Construction phase: PY3-PY8

– Contingency & Transition: PY9-10

– WBS 1.3.2

– Interfaces/Integration

• Feedback for Director’s review Dec 18/19

Page 4: David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison WI.

David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003

Overview

• Branch to Tom Gaisser’s project level overview

(note difficulties in coordination)

Page 5: David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison WI.

David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003

Engineering requirements

• Preliminary Design Review 7/15

• Configuration Items

• Status of ERDs– Technical progress (follows)

– Document progress

• Status of action items– 9/19 Updated

• Comment: non-DAQ software not reviewed

Configuration Items for PDR

1. IceTop Station 1. Instrumented Tank Assembly

2. Target Medium

3. Lined Tank

4. IceTop DOM

5. DOM Mounting (Pevenson

6. DOM to DOM Interconnect

7. Additional Instrumentation

2. Tank to Tank / Surface Interconnect Cable

3. IceTop DAQ1. Feature Extraction Algorithm

2. IceTop Data Handler

3. IceTop Trigger

4. IceTop DOM Hub

4. IceTop Deployment Support Equipment

5. IceTop Simulations*

Page 6: David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison WI.

David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003

“Critical” components

• Branch to presentation of – Revised design for tank

– Presentation of experience at SP this year (from TG)

• Cables

• DAQ

• Simulations

Page 7: David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison WI.

David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003

Cables

• Identification– Quads for DOMs: one pair per DOM

– Coincidence cables

– Power and data cables for tank deployment

• WBS Responsibility– IceTop Requirements – 1.3.2.2

– Engineering & Production – 1.3.1.2

Page 8: David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison WI.

David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003

IceTop DAQ

• Tightly integrated with broader DAQ effort (1.3.4)• IceTop Specific (1.3.2.4.3)

– IceTop specific Firmware• Feature extraction• Coincidence• Triggering

– IDH design

• Acquiring DOM performance data important to detailed DAQ design– Current Rev 2 DOM, Rev 0 DOR card– Need Rev 3 DOM

• Validating IceTop DAQ– Currently 1 tank with AMANDA optical modules (AAOM)– Need 4 DOMs to instrument test station

Page 9: David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison WI.

David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003

Simulations

• Basic Simulations– Tank Simulations (single particle response – GEANT-4)

– DAQ, HW sim (PMT, digitizer, threshold…)

– Validating simulations with test station at UD is critical

• Mid-level– Tank reponse to air shower

– Station response to air shower

– IceTop response to air shower

• Integration with broader project effort (1.4.3)– Single muon surface tag

– Muon bundle calibration

– Composition

Page 10: David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison WI.

David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003

Break

• Questions so far ?

• Please return in 10 minutes

Page 11: David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison WI.

David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003

WBS I – IceTop 1.3.2

• Link to WBS browser… or to saved result

1.3.2.1 Tanks Design and build tanks; design and test freezing procedures to provide working ice-Cherenkov detectors for the surface array component of IceCube. Exclusion: Provision of water to fill the tanks is excluded because it will be an integral part of deployment (see 1.2.3.3.4 under 1.2.3.3 Field Season Operations). There is also a need for coordination with drilling (1.2.2) in connection with water supply.

1.3.2.2 Cables Specification of cabling to power and monitor freezing, testing and operation of tanks. Exclusion: Cabling for tank DOMs should be included in the main surface cables (1.3.1.2). We assume the surface cable will include conductors suitable for monitoring the tanks and for providing power during deployment. A connection from the end of the surface cabel needs to be provided to the DOMs in the tanks.

1.3.2.3 Optical modules

Integration of optical modules into tanks. Exclusion: Construction of DOMs is excluded because the DOMs for IceTop will be part of DOM production runs (1.3.1.1). Design of modifications that may be needed for IceTop will be carried out in collaboration with 1.3.3 and 1.3.4 as part of IceTop specific engineering (1.3.2.4).

Page 12: David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison WI.

David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003

WBS II – IceTop 1.3.2

1.3.2.4 IceTop specific engineering

Design, maintenance and operation of the surface component of IceCube to the extent that these require special procedures. This element includes: Exclusion: Integration of air shower DAQ, trigger, reconstruction and simulation into corresponding IceCube processes. IceTop is an integral component of the IceCube detector. It takes advantage of the solid surface to provide certain veto and calibration functions for the project and to peform closely related physics with downward events. To a large extent, both hardware and software components of the IceTop surface array are similar, if not identical, to those of the deep detector. Thus we expect there will be IceTop integration/implementation tasks at level 4 or 5 in 1.3.3 (Data Acquisition for implementation of hardware modifications in DOM boards); in 1.3.4 (Data Acquisition Software for integration of surface air shower triggers and data into the overall DAQ); and in 1.4 (Data Systems) and 1.5 (Detector Commissioningand Verification--except for 1.5.4). For example, 1.4.3 simulations deals with air showers which give both muons in the deep detector and events on the surface. Another example is event reconstruction (see 1.5.2.1.6), which for the surface array must include near vertical and near horizontal events in such a way that the information is available to serve as a veto for the deep detector.

1.3.2.5 Integration of SPASE

Scope definition: Maintenance and operation of the existing SPASE air shower detector to the extent it remains useful as a calibration device for IceCube.

1.3.2.6 IceTop management

Scope definition: Local project monitoring and reporting to project office.

Page 13: David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison WI.

David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003

WBS III – IceTop footprint

• icetop in wbs title

• icetop in wbs definition

Page 14: David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison WI.

David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003

Summary of PY2

• sow_py02_rev.doc

• Ice Top Status Oct03.doc

1. Tanks – OK

2. Cables – OK

3. DOMs – OK-

4. Icetop Specific Engineering1. System Design – mostly OK

2. Simulations – somewhat behind (but hired critical people)

3. DAQ – Software – ok, Firmware – lagging (Moving target)

5. Spase Integration - NA

6. Management – OK

• Integration tasks – mixed

Page 15: David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison WI.

David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003

Project Plan

• Scope: – Construction PY3-PY8

– Contingency PY9

– Transition to operations PY9.5

• Milestones - by WBS element ?

• Schedule – work from milestones and integration

• Budget – Necessary effort, transition

• Comments– Rough cut under difficult coordination constraints

– Looking for feedback to go forward to Dec18/19

Page 16: David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison WI.

David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003

Milestones

1.3.2 . IceTop PY5 10^6 in-ice muons with ice station tags (veto)

. . . PY5 10^6 IceTop Triggers (calibration)

. . . PY9 10^8 IceTop Triggers (science)

1.3.2.1 . Tanks PY4-8 Proportional Deploment

1.3.2.2 . Cables . .

1.3.2.3 . Optical modules . .

1.3.2.4 . IceTop specific engineering . .

. 1.3.2.4.1 System Design PY3 CDR

. 1.3.2.4.2 Simulations PY4 Full Intgration of IceTop simulation

. 1.3.2.4.3 DAQ PY4 IceTop DAQ fully integrated

1.3.2.5 . Integration of SPASE PY6 Report on role of SPASE

1.3.2.6 . IceTop management PY3 CDR, PRR

.   New elements ? ?

Page 17: David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison WI.

David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003

Schedule & Budget

• Schedule & Budget - – Necessary effort.

– Includes IceTop related non-1.3.2 effort at UD.

– Does .not. include IceTop related effort which is ((.not. 1.3.2) .AND. (.not. UD)).

– Outlines transition, within level effort.

Year PY2 PY3 PY4 PY5 PY6 PY7 PY8 PY9 PY 9.5

Strings 0 4 12 16 16 16 16 xx 0

Engineering 0.85 0.65 0.35 0.15 0.1 0.1 0.1 0.1 0.1

Construction 0 0.1 0.3 0.4 0.35 0.35 0.35 0.2 0

Utilization 0.05 0.1 0.2 0.3 0.4 0.4 0.4 0.55 0.75

Management 0.1 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15

Total Effort 1 1 1 1 1 1 1 1 1

Budget ($M) 0.85 1.6 1.6 1.6 1.6 1.6 1.6 1.6 0.7

• ’s – Full support for PY2 personnel ~ 3 FTE (0.18 M)

– 4.3 additional FTE (0.36 M)

– CE and Production costs (.1M)

– Travel & non-salary mgmt costs (.1M)

Page 18: David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison WI.

David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003

Detail Budget Tools

• Branch to Phil…

Page 19: David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003 IceTop Baseline Review Dec. 4, Madison WI.

David Seckel, IceTop Baseline Review, Madison, Dec. 4, 2003