David H. Dowell [email protected] RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun...

20
David H. Dowell [email protected]. edu RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun Commissioning Experience David H. Dowell for the LCLS Injector Team Facility Advisory Committee Meeting April 16, 2007 Description of Gun Design & Parameters Results of Gun High-Power Tests in Klystron Lab Installation at S20 and Pre-Beam Testing First Photo-Beam! Results & Observations of Initial Gun Commissioning Summary
  • date post

    22-Dec-2015
  • Category

    Documents

  • view

    216
  • download

    2

Transcript of David H. Dowell [email protected] RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun...

Page 1: David H. Dowell dowell@slac.stanford.edu RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun Commissioning Experience David H. Dowell for the LCLS Injector.

David H. [email protected] Gun Commissioning

LCLS FAC April 16, 20071

RF Gun Commissioning Experience

David H. Dowellfor the LCLS Injector Team

Facility Advisory Committee Meeting April 16, 2007

•Description of Gun Design & Parameters•Results of Gun High-Power Tests in Klystron Lab•Installation at S20 and Pre-Beam Testing•First Photo-Beam!•Results & Observations of Initial Gun Commissioning•Summary

Page 2: David H. Dowell dowell@slac.stanford.edu RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun Commissioning Experience David H. Dowell for the LCLS Injector.

David H. [email protected] Gun Commissioning

LCLS FAC April 16, 20072

Z-coupling: reduces pulsed heatingincreases vacuum pumping

Racetrack to minimize quadrupole fieldsDeformation tuning to eliminate field emission from tunersIris reshaped reducing field 10% below cathodeIncrease 0-pi mode separation to 15MHzAll 3D features included in modeling:

laser port and pickup probes 3D fields used in Parmela simulation

3D RF Design of Gun

RF Parameters

f0 (GHz) 2.855987

Q0 13960

β 2.1

Mode Sep. f (MHz) 15

E0:E1 0.999:1

Slide Compliments of Z. Li & L. Xiao

C. Limborg et al., “RF Design of the LCLS Gun”, LCLS-TN-05-3β

r/m

m-0.008

-0.006

-0.004

-0.002

0.000

0.002

0.004

0.006

0.008

-180 -120 -60 0 60 120 180

rf phase

cylindrical cavity

racetrack cavity withd=0.124"racetrack cavity withd=0.14"racetrack cavity withd=0.134"β

r/m

m-0.008

-0.006

-0.004

-0.002

0.000

0.002

0.004

0.006

0.008

-180 -120 -60 0 60 120 180

rf phase

cylindrical cavity

racetrack cavity withd=0.124"racetrack cavity withd=0.14"racetrack cavity withd=0.134"

L. Xiao et al., “Dual feed rf gun design for the LCLS,” Proc. 2005 Particle Acc. Conf.

Page 3: David H. Dowell dowell@slac.stanford.edu RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun Commissioning Experience David H. Dowell for the LCLS Injector.

David H. [email protected] Gun Commissioning

LCLS FAC April 16, 20073

Gun-Solenoid AssemblyCut-away view of LCLS Gun

Cathode weld assembly

August 2005 LCLS RF Gun Mechanical Design Review

Compliments E. Jongewaard

Page 4: David H. Dowell dowell@slac.stanford.edu RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun Commissioning Experience David H. Dowell for the LCLS Injector.

David H. [email protected] Gun Commissioning

LCLS FAC April 16, 20074

Gun Design and Measured Specifications

RF Parameters Design Measured

f (GHz) 2.855987 2.855999

Q0 13960 13900

β 2.1 2.03

Mode Sep. f (MHz) 15 15.17

Field Balance 1 1Measurements compliments ofJ. Wang and J. Lewandowski

Page 5: David H. Dowell dowell@slac.stanford.edu RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun Commissioning Experience David H. Dowell for the LCLS Injector.

David H. [email protected] Gun Commissioning

LCLS FAC April 16, 20075

Conditioning Time to 120 MV/m& Dark Charge per RF Pulse

Conditioning of Gun-1 (Shemp) at 30Hz

40

50

60

70

80

90

100

110

120

130

9:36 12:00 14:24 16:48 19:12

Time on Nov 9, 2006

Ca

tho

de

Fie

ld (

MV

/m)

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

Da

rk C

ha

rge

(n

C)

Cathode Field

Dark Charge

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

80 90 100 110 120 130

Cathode Field (MV/m)

Dar

k C

har

ge

(nC

)

High-Power Gun1 Test in Klystron Lab

Page 6: David H. Dowell dowell@slac.stanford.edu RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun Commissioning Experience David H. Dowell for the LCLS Injector.

David H. [email protected] Gun Commissioning

LCLS FAC April 16, 20076

20

25

30

35

40

45

50

11/9/06 9:36 11/9/06 12:00 11/9/06 14:24 11/9/06 16:48 11/9/06 19:12

Date/Time

Pro

be

Tem

per

atu

re (

deg

rees

C)

Upper Probe, -55.4dB

Inner Probe, -54.7dBLower Probe, -59.5dB

Outer Probe, -60.3dB

0

0.2

0.4

0.6

0.8

1

1.2

0 2 4 6 8 10 12

Gun FWD Power (MW)

gu

n f

wd

/ u

pp

er

pro

be

0

5

10

15

20

25

30

35

40

45

Pro

be

te

mp

era

ture

(d

eg

C)

gun fwd/upper probe

upper probetemp(degC)

Results of Gun High-Power Tests in Klystron Lab:Only concern is the heating of the RF probes

Probe external temperatures during Nov 9 conditioning to 120MV/m

Upper probe temperature and calibration vs. RF power

Therefore, the gun rate will be limited to 30 Hz during 2007 Commissioning.New probes for Gun 2 will have -75dB coupling and be copper plated.

Page 7: David H. Dowell dowell@slac.stanford.edu RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun Commissioning Experience David H. Dowell for the LCLS Injector.

David H. [email protected] Gun Commissioning

LCLS FAC April 16, 20077

Lowering the Gun-Solenoid Assemblyinto the Sector 20 Injector Vault

Page 8: David H. Dowell dowell@slac.stanford.edu RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun Commissioning Experience David H. Dowell for the LCLS Injector.

David H. [email protected] Gun Commissioning

LCLS FAC April 16, 20078

Gun-Solenoid Assembly is Home!

Page 9: David H. Dowell dowell@slac.stanford.edu RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun Commissioning Experience David H. Dowell for the LCLS Injector.

David H. [email protected] Gun Commissioning

LCLS FAC April 16, 20079

y = -19890.437428x + 56842.867661

25

27

29

31

33

35

37

39

2.8559 2.85595 2.856 2.85605 2.8561 2.85615 2.8562 2.85625 2.8563 2.85635

gun frequency (GHz)

Gu

n b

od

y in

sid

e te

mp

(d

egC

)

temp at 2.856GHz = 35.78degC

Measurements: J. VanPelt, A. Vlieks, J. Wang, C. Rivetta

RF windows

Gun

4 gun probeswaveguide

flange

Network analyzer

Erik’s probepanel

Gun temperature

move analyzer cablefrom probe to probe

RF windows

Gun

4 gun probeswaveguide

flange

Network analyzer

Erik’s probepanel

Gun temperature

move analyzer cablefrom probe to probe

Pre-Beam RF Measurements and Water System Test

Page 10: David H. Dowell dowell@slac.stanford.edu RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun Commissioning Experience David H. Dowell for the LCLS Injector.

David H. [email protected] Gun Commissioning

LCLS FAC April 16, 200710

Gun Processed at Sector 20 to Nominal RF Power

0

2

4

6

8

10

12

14

16

18

6.0 6.5 7.0 7.5 8.0 8.5 9.0 9.5 10.0 10.5

Time (microseconds)

RF

Po

we

r (M

W)

Gun FWD Power

Gun RFL Power

Gun RF Probe

Thanks to R. Akre, B. Hong

0 2 4 6 8 10 12 14 160

50

100

150

Cathode field (MV/m)Stored energy (0.1J)

Incident power (MW)

Cat

ho

de

E (

MV

/m)

/ S

tore

d e

ner

gy*

10

12010.7

Page 11: David H. Dowell dowell@slac.stanford.edu RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun Commissioning Experience David H. Dowell for the LCLS Injector.

David H. [email protected] Gun Commissioning

LCLS FAC April 16, 200711

First Photo-Electrons!!!

It Works!!!

Dark Charge

Images of First Photo-ElectronsApril 5, 2007

Photo-Electrons:After adjusting laser-gun phase

Page 12: David H. Dowell dowell@slac.stanford.edu RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun Commissioning Experience David H. Dowell for the LCLS Injector.

David H. [email protected] Gun Commissioning

LCLS FAC April 16, 200712

Early Images of Beam on Yag01 (Gun Exit) and Yag02 (Entrance to L0a)

YAG01 YAG02

Page 13: David H. Dowell dowell@slac.stanford.edu RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun Commissioning Experience David H. Dowell for the LCLS Injector.

David H. [email protected] Gun Commissioning

LCLS FAC April 16, 200713

0

2

4

6

8

10

12

14

16

18

6.0 6.5 7.0 7.5 8.0 8.5 9.0 9.5 10.0 10.5

Time (microseconds)

RF

Po

we

r (M

W)

Gun FWD Power

Gun RFL Power

Gun RF Probe

Optimized Macropulse Timing in RF Waveform by Measuring Beam Energy vs. Gun Delay

RF Delay (ns)

Be

am

Mo

me

ntu

m (

Ge

V/c

)

Set Timing Here for Max Energy

•Used measurement to calibrate RF system (Gun RF probes)

Page 14: David H. Dowell dowell@slac.stanford.edu RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun Commissioning Experience David H. Dowell for the LCLS Injector.

David H. [email protected] Gun Commissioning

LCLS FAC April 16, 200714

Schottky Scan of Gun Phase Relative to Laser

Zero Crossing of RF Field

Optimum Launch Phase

30deg

Measurement: H. Loos, April 13, LCLS e-log

Page 15: David H. Dowell dowell@slac.stanford.edu RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun Commissioning Experience David H. Dowell for the LCLS Injector.

David H. [email protected] Gun Commissioning

LCLS FAC April 16, 200715

0 50 100 150 200 250 300 350 4000

100

200

300

400

500

600

Drive Laser Energy (microJoules)

Gu

n C

har

ge

(pic

oC

ou

lom

bs)

Beam Charge vs. Drive Laser Energy & Launch Phase:Schottky Enhancement of QE

Launch Phase at 30 degrees

Launch Phase at 85 degreesfrom zero crossing

Page 16: David H. Dowell dowell@slac.stanford.edu RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun Commissioning Experience David H. Dowell for the LCLS Injector.

David H. [email protected] Gun Commissioning

LCLS FAC April 16, 200716

Regen pockel cell delay = 300.0680 microSecRegen pockel cell delay = 300.0650 microSec

Precise Adjustment of Regenerative Amplifier Pockel Cell Timing is Crucial

measurements: B. White et al., LCLS e-log, April 11, 2007

Page 17: David H. Dowell dowell@slac.stanford.edu RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun Commissioning Experience David H. Dowell for the LCLS Injector.

David H. [email protected] Gun Commissioning

LCLS FAC April 16, 200717

YAGG1, Gun Spectrometer

~100keV

YAG01, ~50cm from cathode

YAG02, ~80cm from cathode

Beam Momentum = 4.3 MeV/c

measurements: H. Loos & J. Welch, LCLS e-log, April 13, 2007

Page 18: David H. Dowell dowell@slac.stanford.edu RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun Commissioning Experience David H. Dowell for the LCLS Injector.

David H. [email protected] Gun Commissioning

LCLS FAC April 16, 200718

Virtual Cathode Camera YAG01

E-Beam Appears to Preserve the Laser’s Spatial Fluctuations

Laser Image: S. Gilevich et al., LCLS e-log, April 2007

Page 19: David H. Dowell dowell@slac.stanford.edu RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun Commissioning Experience David H. Dowell for the LCLS Injector.

David H. [email protected] Gun Commissioning

LCLS FAC April 16, 200719

YAG01 YAG02

Images compliments of P. Emma & R. Iverson, LCLS e-log, April 13, 2007

YAG03

L0a

Gun & Solenoid

Evolution of Beam Along Injector

Page 20: David H. Dowell dowell@slac.stanford.edu RF Gun Commissioning LCLS FAC April 16, 2007 1 RF Gun Commissioning Experience David H. Dowell for the LCLS Injector.

David H. [email protected] Gun Commissioning

LCLS FAC April 16, 200720

SummaryGun is operational at Sector 20:

RF conditioning completeWater temp and LLRF control loops operatingProviding beam for injector commissioningHigh level S/W applications being implemented

Technical Issues:Gun RF probe heating limits gun operation to 115MV/m and 30 Hz. This is fixed on Gun2.Progress hindered by non-functioning, critical diagnostics!!QE is 2 to 4 times lower than expected

Plan for cathode cleaning

Gun-Solenoid assembly appears to be pointing down and to right