Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

26
Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Transcript of Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Page 1: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation Can Be a Moving Experience

Rob LyonsConsultant, Resilient Systems, Inc.

Page 2: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

Applies equally to various office infrastructures

− Back-office servers

− Network routers, switches, gateways

− Telephone systems

− Desktop systems

Page 3: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

• Up-front planning is the key

The farther ahead you know the details,The fewer and shorter disruptions you will have.

12-18 months is a good target

Page 4: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

• Move team partnership

− Facilities - computers are office equipment, like desks and chairs

− IS services - phones, computers, and printers – just about everything that has a wire to it

− Victims - unless its on their desk, they don't want to know things changed

− Coordinator - official organizer and keeper of the plan

Page 5: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

Relocation costs in perspective

Estimated that over 40% of a companies employees move in a year

It costs around $1000 to move an employee

IT relocation can be much higher when we factor in security, power, A/C, network wiring, fire protection

Page 6: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

1. Simple tote and cable - also call "flash cut“

2. Shift replicated resources

3. Leapfrog through data replication

4. Treat move as a mock disaster

5. Multi-site clustering allows rolling relocation

Page 7: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

1. Tote and cable

− Works best when scheduled downtime is plentiful

− Consists of• Shutdown• Un-cable• Carry it to the destination• Plug it in• Start it back up

− Used for workstations, single user or test systems

Page 8: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

Destination site needs

PowerCapacity (UPS)Connector typeCable length

ClimateA/C capacityHumidity requirements

User accessScreen, keyboard, work surfaceNetworkSpecial (FDDI, F/C, modem lines)

Page 9: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

Best practice:

Label and mark all previously used connectors

Make full data backup to protect from mechanical failures

Document verification tasks to know when system is done

Page 10: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

Gotcha's

Cabinets need to fit through doors, halls, and vehicles

Network routers must be updated for new location

Operations responsibility transition (backup, reboot, access)

There is no easy fall-back solution since the previous room is empty

Page 11: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

2. Shift replicated resources

Implemented through the use of redundant services which are placed on an extended network that spans both old and new sites

Desirable where network can bridge sites and permit multiple concurrent functions

• Internet proxy server• Print server• DNS or DHCP server• Redundant web servers

Page 12: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

Best practice:

Test with limited accessibility before enabling general public

Keep old server available for a few days in case fall-back is needed

Short term rentals may reduce costs - rental can be used as live system while real system is moved to destination

Page 13: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

Gotcha's

Some users may have set a specific IP address

Watch for performance changes due to new network topology

Page 14: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

3. Leapfrog with data replication

Based on storage controller ability to construct and maintain a remote copy

Short downtime needed to change IP address and location of disk master copy of data

Based on the idea that the key part of the move is getting the data to the new site

Preferred for use with database servers or mail server

Page 15: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

O rigina lserver

data spindles

Controller

data spindles

N ew server inS tand-by m ode

C atch-up copy

Controller

O ld site N ew site

Page 16: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

Best practice:

Use automated scripts, if possible, to effect the storage configuration steps

Create and hold full backup at original site for protection until new site is fully operational

Page 17: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

4.Treat move as a mock disaster

Schedule annual DR test to be full function relocation

May require extensive hardware investment or rented systems

Page 18: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

Best practice:Separate physical relocation from cut-over where possible

Couple technology advancements that will not create high risk

Test new system under simulated load prior to switch-over

Use incremental back-up on previous copy of data to minimize downtime

System freeze window for application changes

Page 19: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

5. Multi-site clustering allows rolling relocation

Based on O/S ability to maintain remote copy of data with simultaneous access from both sites.

Zero downtime

Prior preparation used to make single member RAID1 sets

Page 20: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

O rigina lserver

data spindles

Controller

data spindles

N ew server isactive c luster

m em ber

Shadow copyon m ount

Controller

O ld site N ew siteCluster m aintained through network

Page 21: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

Best practices:

Set initial system parameters manually to match old settings rather than use automatic tuning

Schedule cluster member reboot to clear old device names

Watch network traffic shift for any new bottlenecks

Page 22: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

General Server Relocation Milestones

Move preparation• Inventory systems• Label used ports & external cables• Construct drawing of system at initial and destination

location• Verify new site has all connections and that they are

operational

Page 23: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

Physical move tasks

• Perform full backup• Perform orderly shutdown (log system output)• Break down configuration into transportable units• Install available shipping brackets• Attach inventory labels to each unit• Move units out

Page 24: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

Physical move tasks (cont.)

• Locate and organize units at destination• Inspect units for damage or handling issues• Position equipment for re-installation• Re-cable units• Perform basic health checks• Verify environmental considerations• Initiate startup (capture system output to a log files)• Verify system is operational

Page 25: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

Final thoughts

If you must fall-back, you have still gained the knowledge of what it takes to succeed next time

If the system mostly works, it is usually better to fix the few issues than it is to fall-back and do it all over again

Page 26: Data Center Relocation Can Be a Moving Experience Rob Lyons Consultant, Resilient Systems, Inc.

Data Center Relocation

Questions