Physical Layer:Fundamental Infrastructure for Top
Performance Services of a Data Center
Dimitris FilippouBusiness Development Manager
IEEE & PMI Member, BICSI Country Chair,
ELOT Technical Committee TC93 Member
CENELEC TC209 & TC215 Delegate of National Technical Committee
CENELEC BTWG 132-3 Member
![Page 2: Data Center Physical Layer](https://reader033.fdocuments.us/reader033/viewer/2022052905/55840a8ed8b42a126e8b4cab/html5/thumbnails/2.jpg)
Physical Layer & Cabling System
Application Layer
Presentation LayerSession LayerTransport Layer
Network Layer
Data Link Layer
Physical Layer
Applications
Data Transmission
Active Components
Passive Components
![Page 3: Data Center Physical Layer](https://reader033.fdocuments.us/reader033/viewer/2022052905/55840a8ed8b42a126e8b4cab/html5/thumbnails/3.jpg)
Data Center Cabling Design
• Standards.
• Cabling “Shall”.
• Future-proof Cabling.
• Certification & Warranty.
• Availability.
• Drawings.
![Page 4: Data Center Physical Layer](https://reader033.fdocuments.us/reader033/viewer/2022052905/55840a8ed8b42a126e8b4cab/html5/thumbnails/4.jpg)
Standards
Standard Bodies
GeneralElectrical
Depending on Products
TelecommunicationsDepending on Applications
International ISO IEC ITU-T & IEEE
European CEN CENELEC ETSI
U.S.A. ANSI NEC TIA/EIA
U.S.A. standards are only for informative purposes in Europe.
![Page 5: Data Center Physical Layer](https://reader033.fdocuments.us/reader033/viewer/2022052905/55840a8ed8b42a126e8b4cab/html5/thumbnails/5.jpg)
Quality of System - International
![Page 6: Data Center Physical Layer](https://reader033.fdocuments.us/reader033/viewer/2022052905/55840a8ed8b42a126e8b4cab/html5/thumbnails/6.jpg)
Quality of System - Europe
![Page 7: Data Center Physical Layer](https://reader033.fdocuments.us/reader033/viewer/2022052905/55840a8ed8b42a126e8b4cab/html5/thumbnails/7.jpg)
Site Infrastructure Requirements
• Site Selection.
• External Network Access.
• Spaces and Pathways.
![Page 8: Data Center Physical Layer](https://reader033.fdocuments.us/reader033/viewer/2022052905/55840a8ed8b42a126e8b4cab/html5/thumbnails/8.jpg)
Cabling System “Shall”
• Copper Cabling shall be … minimum CLASS EA
• Copper Cabling shall be … SHIELDED.
• Fiber Optic Cabling shall be… only:
– OM3/OM4 Multimode Fibers.
– OS1 Singlemode Fibers.
![Page 9: Data Center Physical Layer](https://reader033.fdocuments.us/reader033/viewer/2022052905/55840a8ed8b42a126e8b4cab/html5/thumbnails/9.jpg)
Future-proof Cabling
• Support today’s technologies(IEEE 802.3an 10Gbase-T, 10Gbps Ethernet).
• Support future technologies(IEEE 802.3ba 40Gbps & 100Gbps).
![Page 10: Data Center Physical Layer](https://reader033.fdocuments.us/reader033/viewer/2022052905/55840a8ed8b42a126e8b4cab/html5/thumbnails/10.jpg)
“Green” Cabling System• Directive 2002/95/EC
Restriction of Hazardous Substances (RoHS).
• Directive 2002/96/ECWaste Electrical and Electronic Equipments (WEEE).
• Directive 1907/06/ECRegistration, Evaluation, Authorization and Restriction of Chemicals (REACH).
• CENELEC, IEC StandardsLow Smoke Zero Halogen (LSZH/LSOH)
![Page 11: Data Center Physical Layer](https://reader033.fdocuments.us/reader033/viewer/2022052905/55840a8ed8b42a126e8b4cab/html5/thumbnails/11.jpg)
The Reality of Measurements
• Measurements according to
standards:
– ISO/IEC 11801, A1 & A2
– CENELEC EN 50173-1, A1
– IEEE 802.3an
• Certified Tester with the
appropriate accuracy level.
![Page 12: Data Center Physical Layer](https://reader033.fdocuments.us/reader033/viewer/2022052905/55840a8ed8b42a126e8b4cab/html5/thumbnails/12.jpg)
Cabling System Warranty
Life-time Warranty in
Application Performance.
• Today : IEEE 802.3an
(10Gbps)
Warranty shall be … only
from the component
manufacturer!
Warranty shall be … signed
only by the QD and the PM!
![Page 13: Data Center Physical Layer](https://reader033.fdocuments.us/reader033/viewer/2022052905/55840a8ed8b42a126e8b4cab/html5/thumbnails/13.jpg)
Availability (A)
timemission
timeupdaccumulateA
According to ITU-T recommendations:
timedowndaccumulatetimeupdaccumulate
timeupdaccumulateA
In case of System + System (S+S) :
%999.99A
![Page 14: Data Center Physical Layer](https://reader033.fdocuments.us/reader033/viewer/2022052905/55840a8ed8b42a126e8b4cab/html5/thumbnails/14.jpg)
Project According to Standards
Agricultural Bank of Greece (ATEbank)
– IT Headquarters.
– Data Center.
![Page 15: Data Center Physical Layer](https://reader033.fdocuments.us/reader033/viewer/2022052905/55840a8ed8b42a126e8b4cab/html5/thumbnails/15.jpg)
Questions
Dimitris FilippouBusiness Development Manager
IEEE & PMI Member, BICSI Country Chair,
ELOT Technical Committee TC93 Member
CENELEC TC209 & TC215 Delegate of National Technical Committee
CENELEC BTWG 132-3 Member