DAR_Vol_1

1085
GOVERNMENT OF INDIA CENTRAL PUBLIC WORKS DEPARTMEN ANALYSIS OF RAT FOR DELHI (V0L.1)

Transcript of DAR_Vol_1

Page 1: DAR_Vol_1

GOVERNMENT OF INDIA

CENTRAL PUBLIC WORKS DEPARTMENT

ANALYSIS OF RATES

FOR DELHI

(V0L.1)

Page 2: DAR_Vol_1

###PUBLISHED BY:

DIRECTOR GENERAL OF WORKS, CPWD, NIRMAN BHAWAN, NEW DELHI

© All rights reserved. No part of this publication, either in English or in Hindi, may be reproduced inany form or by any means, electronic or mechanical, including photocopy, recording or anyinformation storage and retrieval system, without permission, in writing, from the Director General(Works), CPWD, New Delhi. Photocopying of this book is strictly prohibited

A GOVERNMENT OF INDIA PUBLICATION

Published byDIRECTOR GENERAL (WORKS)

CPWD, NIRMAN BHAWAN, NEW DELHI-110 011&

Printed & Marketed byJAIN BOOK AGENCY

Authorised Dealers of Govt. PublicationsC-9, Connaught Place, New Delhi-110001Phones : 23416390 upto 97, 41513852

E-mail : [email protected] : www.jainbookagency.com

Distributed byJBA DISTRIBUTORS

N-67, First Floor, Munshiram Building,Connaught Place, New Delhi-110001

Phone : 41523870, 23354824 Fax : 41513850E-mail : [email protected] : www.jba.in

JAIN BOOK AGENCY (SOUTHEND) JAIN BOOK AGENCY (GURGAON)1, Aurobindo Place Market, 12, Central Plaza Mall, Sector 53,Hauz Khas, New Delhi-110016 Golf Course Road,Phone : 26567066, 26566113,41758700 Gurgaon 122002 HaryanaE-mail : [email protected] Phone : 4143020,Website : www.jainbookagency.com Moblile 9810666810

DIAL-A-BOOK

Page 3: DAR_Vol_1

011-4175 8700Books will be delivered next day by COURIER

(Payment to courier-boy)in Delhi, Noida, Ghaziabad, Faridabad &Gurgaon (nominal courier charges extra)

Also available atAll Leading Booksellers & Authorised Govt. Dealers In India

Price : Rs. 3000/- per set of two volumes (excluding postage and forwarding charges etc.)

Page 4: DAR_Vol_1

FOREWORD

Central Public Works Department Analysis of Rates for Delhi is a very comprehensive anduseful document. It is based on scientific assessment of inputs of materials, labour and machineryin various items of work normally encountered in a project.

It was first compiled in the year 1950, followed by publication or revisions in 1955, 1962, 1972,1977, 1985 and 1997. Since publication of DAR, 1997, prices of labour and materials have registeredsubstantial increase. Besides the increased cost, there has been a spurt of new constructionmaterials and introduction of mechanised construction techniques for speedier construction. Thishas necessitated revision of existing DAR, 1997 to include the above changes. Accordingly, thisAnalysis of Rates for Delhi, 2007 has been prepared incorporating element of machinery andprefabricated building components, wherever applicable.

Earlier C.P.W.D. Analysis of Rates for Delhi was a confidential document and was issued toCPWD Officers and Government Departments only. In this age of transparency, we feel that thisis an anachronism. Therefore, for the first time DAR, 2007 is being published as an open documentand shall be available in two volumes. This will facilitate in obtaining feed back from the constructionindustry and the professionals for continuous updation and improvement in the document.

Although DAR, 2007 contains most of the items of DAR, 1997, analysis of items which areeither obsolete or are not in use have been deleted. Similarly, analysis of many items have beenmodified to correspond to itemSeveral new analysis of items pertaining to newmaterials and new technologies in the construction sector have Analysisof rates of many items also incorporate element of machinery instead of the lump sum provisions.

I wish to place on record the technical input and the effective coordination on the part of ShriD.S.Sachdev, ADG(TD) and the efforts put in by Shri Suresh Kumar, CE(CSQ) and his team ofofficers in TAS unit in finalising DAR, 2007 in a record time.

I am sure that C.P.W.D. Analysis of Rates for Delhi, 2007 along with Delhi Schedule of Rates,2007 shall be a useful document to a number of departments, public sector undertakings, privatesector builders and architects etc.

(K. Srinivasan)DIRECTOR GENERAL (WORKS)

New DelhiFebruary, 2008

Page 5: DAR_Vol_1

PREFACE

1 C.P.W.D. Analysis of Rates for Delhi, 2007 is the revised edition of C.P.W.D. Analysis ofRates for Delhi, 1997.

2.0DAR, 2007 incorporates most of the analysis of DAR, 1997 with all correction slips up-todate and will replace DAR, 1997.

3 DAR, 2007 is a bilingual document (Hindi version will follow).

4 DAR, 2007 is published in two volumes as under:

Volume Sub-head Contents/ Chapters0 Basic Rates1 Carriage of materials2 Earth Work3 Mortars4 Concrete Work5 Reinforced Cement Concrete Work

One 6 Brick Work7 Stone Work8 Marble Work9 Wood and PVC Work10 Steel Work11 Flooring12 Roofing13 Finishing

Page 6: DAR_Vol_1

14 Repairs to Buildings15 Dismantling and Demolishing

Two 16 Road Work17 Sanitary Installation18 Water Supply19 Drainage20 Pile Work21 Aluminium Work22 Water Proofing23 Horticulture and Landscape

5 Analysis of many items in DAR, 2007, which are either obsolete or are not in use, havebeen deleted. Similarly, analysis of many items have been modified to correspond to itemsof DSR, 2007. Several new analysis of items pertaining to new materials and newtechnologies in the construction sector have also been included. Analysis of rates of manyitems also incorporate element of machinery instead of lump sum provisions.

6 Analysis have been modified to include execution of different works by using variouselectrical and mechanical equipments i.e. excavators, tower cranes, mobile cranes,mechanical platforms, Batch Mix plant, transit mixers and pumps, piling rigs, pneumaticcutters, chisels, chippers, hammers etc. Built-in provision has been taken in the analysisof rates for new construction technology/ mechanisation.

37 Analysis of dry work using prefabricated materials and pre-finished elements for speedier

construction are included viz gypsum block walls, calcium silicate and non-asbestos cementboard partitions, pre-finished counter tops for kitchen and washbasins, pre-moulded andpre-finished stone work in risers and treads of steps and window sills, dry stone cladding,sub-frames for windows, use of chemical and mechanical fasteners, laying of tiles in flooringand dado with polymer based adhesives etc.

8 DAR, 2007 is based on the study of current market rates of materials at Delhi, collectedduring the period of April, 2007 to October, 2007. Generally, the basic rates of materials,incorporated in the analysis, pertain to materials conforming to BIS Standards/CPWDSpecifications/Materials of best quality available in the market.

Labour rates are the minimum wages issued by the Government of Delhi w.e.f. 01-09-2007.9 Lump sum provision of labour/ T& P is replaced with mechanisation inputs. Prominent

items incorporating mechanization are earth-work in excavation, RMC / BMC, brick workin superstructure above floor V level, road work, dismantling of R.C.C. work, dismantlingof C.C. and flexible pavements, pile work etc.

10 Number of uses of steel and wooden shuttering have been reduced from 80 and 16 timesto 40 and 8 times respectively, so that proper quality of shuttering is put to use.

11 Contractor’s profit and Overheads @ 15% ( CP=7.5% & OH 7.5%) has been adopted asapproved by the DGW vide Office Memorandum no. DG(W)MAN/150 dated 14-12-2007.

12 Sundries have been considered as 1.00 times based on Cost Index of Delhi as 100 over

Page 7: DAR_Vol_1

DPAR 01-10-2007.

13 A lot of effort has gone into the preparation of this Analysis of Rates. I convey mydeep appreciation and sincere thanks to Shri Suresh Kumar, CE, CSQ, Shri MayankTilak, S.E. (TAS), Sh. S.K.Jain EE(S&S) –I, Sh.S.C. Malik EE (S&S) -II,Sh. A.V.R.Bhat EE (S&S) – III, Sh. V.P.Singh AE, Sh. H.N.Singh AE, Sh. S.K.SarkarAE, Sh.L.C.Gothwal AE, Sh.G.K. Jindal AE, Sh. S.S.Pal AE, Sh. Bahal SinghD/Man Gr-I, Sh Upender Walia D/Man Gr.-I and other officers and staff of TAS Unitfor sincere efforts made in the preparation of this document in such a short time.

14 Due care has been taken to print the C.P.W.D. Analysis of Rates for Delhi as correctly aspossible. It is, however possible that some errors might have crept in. In case any error oromission is noticed, it may be broug Superintending Engineer(TAS), CPWD, Room no. 418, A- wing, Nirman Bhawan, New Delhi.

15 In case of any discrepancy between English and Hindi versions, the English version shallbe held valid. Suggestions for improvement are welcome.

(D.S.SACHDEV)ADG (TD), CPWD,Nirman Bhawan, New Delhi

New DelhiFebruary, 2008

Contents

Vol. 1SH.NAME OF SUB HEAD PAGE NO.

BASIC RATES

0 Hire Charges of Plants 1-2

0 Labour 3-4

0 Materials 5-47

0 Carriage 48-50

SUB - HEADS

Page 8: DAR_Vol_1

1 Carriage of Material 51-60

2 Earth Work 61-104

3 Mortars 105-115

4 Concrete Work 117-145

5 Reinforced Cement Concrete Work 147-198

6 Brick Work 199-227

7 Stone Work 229-280

8 Marble Work 281-292

9 Wood and PVC Work 293-431

### Steel Work 433-461

### Flooring 463-517

### Roofing 519-578

Note: For remaning Sub Heads refer to Vol.2

Page 9: DAR_Vol_1

BASIC

RATES

1BASIC RATES

0.1 HIRE CHARGES OF PLANTS

Co Description Unit RateNo Rs.1 Hire charges of Coaltar Boiler 900 to 1400 litres Day 595

2 Hire charges of Concrete Mixer 0.14 cubic metre Day 4003 Hire charges of Diesel Road Roller - 8 to 10 tonne Day 1,0004 Production cost of concrete by batch mix plant. cum 200

5 Hire charges of Diesel Truck - 9 tonne Day 1,0086 Hire charges of Spraying machine including electric charges Day 1737 Hire charges of Coaltar Sprayer Day 2508 Hire charges of Barber green, drying, mixing and Asphalt Plant,

with accessories, capacity 30/45 tonne Day 7,050

9 Pumping charges of concrete including Hire charges of pump,piping work & accessories etc. cum 80

10 Hire charges of Derrick monkey rope Day 50011 Hire charges of Pump set of capacity 4000 litres/hour. Day 30012 Vibrator (Needle type 40mm) Day 200

13 Machine for rubbing of floors Day 20014 Front end loader Day 6,00016 Mastic Cooker Day 51517 Hire and running charges of tipper Day 1,030

18 Hire and running charges of loader. Day 80019 Hand Grinder For mirror polish Day 10020 Hydraulic Excavator (3D) with driver and fuel. Day 6,000

21 Pin vibrator Day 28822 Surface Vibrator Day 33024 Hire and running charges of hydraulic piling rig with power unit etc.

including complete accessories and shifting at site. per day 28,00025 Hire and running charges of light crane. per day 2,000

26 Hire and running charges of bentonite pump. per day 4,000

Page 10: DAR_Vol_1

27 Hire and running charges of vibrating pile driving hammer completewith power unit and accessories. per day 28,000

28 Hire and running charges of crane 20 tonne capacity. per day 8,00029 Carriage of concrete by transit mixer. km/ cum 18

30 Generator 250 KVA. per day 1,60033 Paint applicator. per day 680

2Co Description Unit RateNo Rs.

37 Mobile crane. per day 5,00038 Tractor with ripper attachment. per day 1,00039 Tractor with trolley. per day 1,000

40 Air compressor 250 cfm with two leads for pneumatic cutters/hammers. day 1,600

41 Joint cutting machine with 2-3 blades per day 80042 C.C .batch mix plant. day 88,00043 Road sweeper day 480

45 Slip form paver with sensor. day 12,00046 Water tanker. day 80047 Concrete joint cutting machine. day 80048 Texturing machine. day 800

Notes:- Above hire - charges include cost of services of operating staff and supply of lubricating oil.

3BASIC RATES0.2 LABOUR

Note :- These rates are exclusive of contractor’s profit and over heads and are inclusive of wages for weeklyday of rest

Co Description Unit RateNo Rs.###Bandhani Day 138.45###Bhisti Day 138.45

###Blacksmith 1st class Day 151.5###Blacksmith 2nd class Day 141.6###Carpenter 1st class Day 151.5

Page 11: DAR_Vol_1

###Carpenter 2nd class Day 141.6

###Chowkidar Day 135.25###Beldar Day 135.25###Coolie Day 135.25

###Fitter (grade 1) Day 151.5###Assistant Fitter or 2nd class Fitter Day 141.6###Glazier Day 141.6###Mason (for plaster of paris work) 1st class Day 151.5

###Mason (brick layer) 1st class Day 151.5###Mason (brick layer) 2nd class Day 141.6###Mason (for plain stone work) 2nd class) Day 141.6

###Mason (for ornamental stone work) 1st class Day 151.5###Driver (for Road Roller, Concrete Mixer, Truck etc.) Day 151.5###Mate Day 138.45

###Mistry Day 151.5###Painter Day 141.6###Rock Excavator Day 135.25###Rock Breaker Day 135.25

###Rock Hole Driller Day 135.25###Stone Chiseller Day 138.45###Sprayer (for bitumen, tar etc.) Day 138.45

###Skilled Beldar (for floor rubbing etc.) Day 138.45###White Washer Day 138.45015Mason (average) Day 146.55

4

Co Description Unit RateNo Rs.015Carpenter (average) Day 146.55

###Operator (Pile/ Special machine) Day 166###Skilled torch operator for laying tack Day 151.5

Note :- * These rates are average of 1st class and 2nd class categories. This is for use in the analysis ofrate only.

5BASIC RATES0.3 MATERIALS

Page 12: DAR_Vol_1

Note :- These rates are exclusive of contractor’s profit, over heads and carriage but include octroi, royalty,sales tax (VAT) etc.

Co Description Unit RateNo Rs.

###Seam bolts and nuts 6 mm dia and 25 mm long 10 Nos 30###Non - Asbestos fibre cement corrugated sheet 6mm thick. sqm 205###Non - Asbestos fibre cement close fitting adjustable ridge. metre 203

###Non - Asbestos fibre cement corrugate serrated adjustable ridgemetre 174###Non - Asbestos fibre cement plain wing adjustable ridge. metre 188###Non - Asbestos fibre cement unserrated adjustable ridge for hip metre 195

###Non - Asbestos fibre cement corrugated apron piece. metre 126###Non - Asbestos fibre cement eaves filler piece. each 93###Non - Asbestos fibre cement north light curves. metre 197###Non - Asbestos fibre cement ventilator curves. each 267

###Non - Asbestos fibre cement barge boards 6 mm thick. metre 232###Non - Asbestos fibre cement ridge finial . pair 84###Non - Asbestos fibre cement special north light curves. each 275

###Non - Asbestos fibre cement S type louvers. each 161###Non - Asbestos multi purpose fibre cement board 6mm thick. sqm 180###Non - Asbestos multi purpose fibre cement board 8mm thick. sqm 239###Brick Aggregate (Single size) : 63 mm nominal size cum 350

###Brick Aggregate (Single size) : 50 mm nominal size cum 355###Brick Aggregate (Single size) : 40 mm nominal size cum 360###Stone Aggregate (Single size) : 63 mm nominal size cum 600

###Stone Aggregate (Single size) : 50 mm nominal size cum 625###Stone Aggregate (Single size) : 40 mm nominal size cum 650###Stone Aggregate (Single size) : 25 mm nominal size cum 675###Stone Aggregate (Single size) : 20 mm nominal size cum 700

###Stone Aggregate (Single size) : 12.5 mm nominal size cum 700###Stone Aggregate (Single size) : 10 mm nominal size cum 700###Stone Aggregate (Single size) : 06 mm nominal size cum 750

###Safeda ballies 125 mm diameter metre 29###Bajri cum 510###Bamboo 25 mm dia 2.5 metre long score 192

6Co Description Unit RateNo Rs.

###Bhusa quintal 200###Paving bitumen S-90 of approved quality tonne 22,500

Page 13: DAR_Vol_1

###Bitumen emulsion tonne 19,500

###Bitumen grade PMB - 40 M.T. 30,000###Blown type petroleum bitumen of penetration 85/25 of approved

quality tonne 25,000###Bitumen hot sealing compound : grade A kilogram 20###Bitumen solution primer of approved quality litre 28

###Premoulded joint filler 12 mm thick sqm 300###Bitumen felt fibre base (vegetable or animal):Type 2 grade 1 sqm 45###Bitumen felt :Type 3 grade 1 sqm 45###Coal Tar litre 16

###Blasting powder kilogram 25###Blasting fuse (fuse wire) each 10###White face insulating board:12 mm thick sqm 239

###Natural colour insulating board:12 mm thick sqm 175###Flame retardant face insulating board: 12 mm thick sqm 208###Flame retardant face insulating, Impregnated fibre board 12 mmsqm 279###Flat pressed 3 layer particle board (medium density) Grade I :12 mm

thick sqm 258

###Extra for veneered particle board with : Teak veneering on one sideand commercial veneered on other side sqm 198

###Extra for veneered particle board with : Commercial veneering onboth sides sqm 102

###Extra for veneered particle board with : Teak veneering on both sqm 366###Brick bats cum 253###Wire brush each 15

###Soft brush each 12###Portland Cement tonne 4,500###White Cement tonne 9,700

###Coal (steam) quintal 300###Cramp Gun metal 25x6x300 mm each 53###Brass butt hinges (light/ordinary type) : 125x70x4 mm 10 Nos 450###Brass butt hinges (light/ordinary type) : 100x70x4 mm 10 Nos 300

###Brass butt hinges (light/ordinary type) : 75x40x2.5 mm 10 Nos 160###Brass butt hinges (light/ordinary type) : 50x40x2.5 mm 10 Nos 90

7Co Description Unit RateNo Rs.

###Brass butt hinges (heavy type) : 125x85x5.5 mm(.70)kg 10 Nos 1,500###Brass butt hinges (heavy type) : 100x85x5.5 mm(.56)kg 10 Nos 1,300###Brass butt hinges (heavy type) :75x65x4.0 mm(.20)kg 10 Nos 450

###Brass parliamentary hinges 150x125x27x5 mm 10 Nos 1,650###Brass parliamentary hinges 125x125x27x5 mm 10 Nos 1,450###Brass parliamentary hinges 100x125x27x5 mm 10 Nos 1,175

Page 14: DAR_Vol_1

###Brass parliamentary hinges75x100x20x3.2 mm 10 Nos 888###Brass single acting spring hinges 150 mm each 200###Brass single acting spring hinges 125 mm each 158###Brass single acting spring hinges 100 mm each 106

###Brass double acting spring hinges 150 mm each 317###Brass double acting spring hinges 125 mm each 216###Brass double acting spring hinges 100 mm each 173

###Brass tower bolt (barrel type) 250x10 mm each 123###Brass tower bolt (barrel type) 200x10 mm each 100###Brass tower bolt (barrel type) 150x10 mm each 75###Brass tower bolt (barrel type) 100x10 mm each 51

###Brass flush bolt 250 mm each 84###Brass flush bolt 150 mm each 65###Brass flush bolt 100 mm each 44

###Brass handles 125 mm with plate 175x32 mm each 85###Brass handles 100 mm with plate 150x32 mm each 75###Brass handles75 mm with plate 125x32 mm each 55

###Brass door latch 300x16x5 mm (0.380 kg) each 85###Brass door latch 250x16x5 mm (0.350 kg) each 82###Brass mortice latch and lock 100x65 mm with6 levers and a pair of

brass lever handles each 257###Brass mortice latch 100x65mm with a pair of brass lever handle each 235

###Brass 150 mm floor door stopper (0.357kg) each 104###Brass hard drawn hooks and eyes 300 mm 10 Nos 457###Brass hard drawn hooks and eyes 250 mm 10 Nos 423###Brass hard drawn hooks and eyes 200 mm 10 Nos 390

###Brass hard drawn hooks and eyes 150 mm 10 Nos 364###Brass hard drawn hooks and eyes 100 mm 10 Nos 300###Brass casement window fastener Each 26

8Co Description Unit RateNo Rs.

###Brass casement stays (straight peg type ) 300 mm weighing not lessthan 0.33 kg each 66

###Brass casement stays (straight peg type ) 250 mm weighing not lessthan 0.28 kg Each 55

###Brass casement stays (straight peg type ) 200 mm weighing not lessthan 0.24 kg each 46

###Brass quadrant stays 300 mm each 73###Brass fanlight catch 10 Nos 109

###Brass fanlight pivot 10 Nos 128###Brass chain with hook for fan light catch each 13###Brass hasps and staples (safety type) 300 mm 10 Nos 458

Page 15: DAR_Vol_1

###Brass hasps and staples (safety type) 115 mm 10 Nos 378###Brass hasps and staples (safety type)90 mm 10 Nos 300###Brass Night latch each 338###Brass helical spring 150 mm each 185

###Brass curtain rod 20 mm dia 1.25 mm thick metre 63###Brass curtain rod 25 mm dia 1.25 mm thick metre 79###Brass brackets (curtain rods) 20 mm each 24

###Brass cupboard knob or ward robe knob 50 mm each 18###Brass screws 50 mm 100 Nos 107###Brass screws 40 mm 100 Nos 96###Brass screws 30 mm 100 Nos 86

###Brass screws 25 mm 100 Nos 76###Brass screws 20 mm 100 Nos 53###Chromium plated Brass butt hinges (heavy) type 75x65x4 .0 mm

(200gms) 10 Nos 430###Chromium plated Brass butt hinges (light/ordinary) type 125x70x4

mm 10 Nos 433

###Chromium plated Brass butt hinges (light/ordinary) type 100x70x4mm 10 Nos 385

###Chromium plated Brass butt hinges (light/ordinary) type 75x40x2.5mm 10 Nos 135

###Chromium plated Brass butt hinges (light/ordinary) type 50x40x2.5mm 10 Nos 105

###Chromium plated Brass handles 125 mm with plate 175 x32 mmEach 92###Chromium plated Brass handles 100 mm with plate 150 x 32 m Each 79

###Chromium plated Brass handles 75mm with plate 125x32 mm Each 68

9Co Description Unit RateNo Rs.

###Chromium plated Brass mortice latch and lock 100x65 mm with6levers and a pair of brass lever handles each 323

###Chromium plated brass casement window fastener each 55###Chromium plated Brass casement stays (straight peg type ) 300 mm

weighing not less than 0.33 kg each 73###Chromium plated Brass casement stays (straight peg type ) 250 mm

weighing not less than 0.28 kg each 67

###Chromium plated Brass casement stays (straight peg type ) 200 mmweighing not less than 0.24 kg each 56

###Chromium plated Brass Night latch each 383###Chromium plated Brass Wardrobe Knob 50 mm each 25###Chromium plated Brass screws 50 mm 100 Nos 123

###Chromium plated Brass screws 40 mm 100 Nos 150###Chromium plated Brass screws 30 mm 100 Nos 90###Chromium plated Brass screws 25 mm 100 Nos 83

Page 16: DAR_Vol_1

###Chromium plated Brass screws 20 mm 100 Nos 63

###Chromium plated Brass curtain rod 12 mm dia 1.25mm thick metre 122###Chromium plated Brass curtain rod 20 mm dia 1.25mm thick metre 143###Chromium plated Brass curtain rod 25 mm dia 1.25mm thick metre 239

###Bright finished or black enameled mild steel butt hinges 125x65x2.12mm 10 Nos 78

###Bright finished or black enameled mild steel butt hinges 100x58x1.90mm 10 Nos 54

###Bright finished or black enameled mild steel butt hinges75x47x1.70mm 10 Nos 34

###Bright finished or black enameled mild steel butt hinges50x37x1.50mm 10 Nos 28

###Nickel plated mild steel piano hinges 1 mm thick 35 mm wide metre 21###Bright finished or black enameled mild steel screws 50 mm 100 Nos 40

###Bright finished or black enameled mild steel screws 40 mm 100 Nos 30###Bright finished or black enameled mild steel screws 30 mm 100 Nos 24###Bright finished or black enameled mild steel screws 25 mm 100 Nos 15

###Bright finished or black enameled mild steel screws 20 mm 100 Nos 15###Bright finished or black enameled mild steel bolts and nuts 50 each 4###Oxidised mild steel butt hinges 125x65x2.12 mm 10 Nos 92###Oxidised mild steel butt hinges 100x58x1.90 mm 10 Nos 53

###Oxidised mild steel butt hinges75x47x1.70 mm 10 Nos 32

10Co Description Unit RateNo Rs.

###Oxidised mild steel butt hinges50x37x1.50 mm 10 Nos 27###Oxidised mild steel parliamentary hinges150x125x27x2.8 mm 10 Nos 255###Oxidised mild steel parliamentary hinges 125x125x27x2.8 mm 10 Nos 205

###Oxidised mild steel parliamentary hinges 100x125x27x2.8 mm 10 Nos 165###Oxidised mild steel parliamentary hinges 75x100x20x2.24 mm 10 Nos 122###Oxidised mild steel single acting spring hinges 150 mm each 71

###Oxidised mild steel single acting spring hinges 125 mm each 66###Oxidised mild steel single acting spring hinges 100 mm each 51###Oxidised mild steel double acting spring hinges 150 mm each 73

###Oxidised mild steel double acting spring hinges 125 mm each 63###Oxidised mild steel double acting spring hinges 100 mm each 47###Nickel plated mild steel piano hinges 1 mm thick 35 mm wide metre 24###Oxidised mild steel sliding door bolt 300x16 mm each 45

###Oxidised mild steel sliding door bolt 250x16 mm each 37###Oxidised mild steel door latch 300x20x6 mm each 25###Oxidised mild steel door latch 250x20x6 mm each 25

###Oxidised mild steel tower bolt (barrel type) 250x10 mm each 25

Page 17: DAR_Vol_1

###Oxidised mild steel tower bolt (barrel type) 200x10 mm each 21###Oxidised mild steel tower bolt (barrel type) 150x10 mm each 17###Oxidised mild steel tower bolt (barrel type) 100x10 mm each 12

###Oxidised mild steel handles 125 mm each 7###Oxidised mild steel handles 100 mm each 5###Oxidised mild steel handles75 mm each 3

###Oxidised mild steel hasps and staples(safety type) 150 mm 10 Nos 79###Oxidised mild steel hasps and staples(safety type) 115 mm 10 Nos 70###Oxidised mild steel hasps and staples(safety type)90 mm 10 Nos 52###Oxidised mild steel screws 50 mm 100 Nos 40

###Oxidised mild steel screws 40 mm 100 Nos 35###Oxidised mild steel screws 30 mm 100 Nos 24###Oxidised mild steel screws 25 mm 100 Nos 16

###Oxidised mild steel screws 20 mm 100 Nos 15###Anodised Aluminium butt hinges 125x75x4 mm 10 Nos 478###Anodised Aluminium butt hinges 125x63x4 mm 10 Nos 447###Anodised Aluminium butt hinges 100x75x4 mm 10 Nos 416

11Co Description Unit RateNo Rs.

###Anodised Aluminium butt hinges 100x63x3.2 mm 10 Nos 390###Anodised Aluminium butt hinges 100x63x4 mm 10 Nos 354###Anodised Aluminium butt hinges 75x63x4 mm 10 Nos 281

###Anodised Aluminium butt hinges 75x63x3.2 mm 10 Nos 215###Anodised Aluminium butt hinges 75x45x3.2 mm 10 Nos 98###Anodised Aluminium sliding door bolt 300x16 mm each 125###Anodised Aluminium sliding door bolt 250x16 mm each 104

###Anodised Aluminium tower bolt (barrel type)300x10 mm 10 Nos 520###Anodised Aluminium tower bolt (barrel type)250x10 mm 10 Nos 440###Anodised Aluminium tower bolt (barrel type)200x10 mm 10 Nos 354

###Anodised Aluminium tower bolt (barrel type)150x10 mm 10 Nos 281###Anodised Aluminium tower bolt (barrel type)100x10 mm 10 Nos 208###Anodised Aluminium handles 125 mm with plate 175 x 32 mm 10 Nos 375###Anodised Aluminium handles 100 mm with plate 150 x 32 mm 10 Nos 260

###Anodised Aluminium handles 75mm with plate 125 x 32 mm 10 Nos 208###Anodised Aluminium kicking plate 50 cm long100x3.15 mm each 94###Block board construction flush door with teak wood ply on both faces

35 mm thick sqm 1,100###Block board construction flush door with teak wood ply on both faces

30 mm thick sqm 1,050

###Block board construction flush door with teak wood ply on both faces25 mm thick sqm 1,000

###Block board construction flush door with commercial ply on both faces

Page 18: DAR_Vol_1

35 mm thick sqm 632###Block board construction flush door with commercial ply on both faces

30 mm thick sqm 610###Block board construction flush door with commercial ply on both faces

25 mm thick sqm 600###Block board construction flush door lipping sqm of

door area 245###Square vision panel in Block board construction flush door sqm of

door area 86###Circular vision panel in Block board construction flush door Sqm of

door area 118

###Decorative type Louvers in Block board construction flush doorsqm ofdoor area 210

###Rebate cutting in Block board construction flush door sqm ofdoor area 57

12Co Description Unit RateNo Rs.

###Decorative plywood 4 mm sqm 250###Fuel wood quintal 265

###Glue kilogram 50###Hessian cloth sqm 10###Cement Concrete Jali 50 mm thick sqm 145###Cement Concrete Jali 40 mm thick sqm 115

###Cement Concrete Jali 25 mm thick sqm 92###Kerosene oil litre 19###Unslaked lime quintal 260

###Dehradun white lime quintal 295###Satna lime quintal 178###Dry hydrated lime (factory made) quintal 177###Marble dust/ powder cum 800

###Marble chips up to 4mm and downsize White & black quintal 115###Marble chips large size above 4 mm White & black quintal 115###Moorum cum 310

###Mud (dry) cum 20###Dry distemper kilogram 26###Oil bound washable distemper/ Acrylic distemper kilogram 40###Linseed oil (double boiled) litre 80

###Cement primer litre 70###Distemper primer litre 73###Pink primer (for wood) litre 72

###Aluminium paint litre 89###Acid proof paint (chocolate or black) litre 93###Anticorrosive bituminous paint (black) litre 52

Page 19: DAR_Vol_1

###Black Japan litre 65

###Enamel paint litre 115###Floor enamel paint in all shades except green litre 100###Synthetic enamel paint in black or chocolate shade litre 115

###Synthetic enamel paint in all shades except black or chocolate litre 120###Plastic emulsion paint litre 140###Roofing paint for iron sheets in red colour litre 95###White lead kilogram 60

13Co Description Unit RateNo Rs.

###Water proofing cement paint kilogram 36###Wax polish (ready made) kilogram 150###Ordinary varnish litre 49

###Superior copal varnish litre 100###Superior spar varnish litre 105###Oil type wood preservative litre 60

###Putty for wood work kilogram 24###Pig lead kilogram 58###Premixed super white gypsum plaster. kg 5.2###Plaster of Paris kilogram 2.5

###Plug each 6###Copper pins 6 mm dia 7.5 cm long each 7.5###Black colour dark shade pigment kilogram 42

###Red, chocolate, orange, buff or yellow (red oxide of iron) light shadepigment kilogram 65

###Green or blue medium shade pigment kilogram 45###Standard holder bat clamps for sand cast iron or cast iron pipes 150

mm dia each 20###Sand Cast iron plain shoe 150 mm dia each 222###Copper plate kilogram 195

###Pulley 25 mm dia each 18###Rolling shutter made of 80x1.25 mm machine rolled laths sqm 767###Top cover for rolling shutters metre 400

###27.5 cm long wire spring grade no 2 for rolling shutters each 170###Ball bearing for rolling shutters each 280###Extra for mechanical devices chain and cranked operation for

operating rolling shutters : exceeding 10.00 sq.m and up to 16.80sq.m area of door sqm 400

###Extra for mechanical devices chain and cranked operation foroperating rolling shutters : exceeding 16.80 sq.m area of door sqm 450

###Royalty for good earth cum 11

###Royalty for sludge cum 60

Page 20: DAR_Vol_1

###Coarse sand (zone III) cum 600###Fine sand (zone IV) cum 320###Galvanised steel plain sheets quintal 3,450

###Standard quality hard board sheet 3 mm thick sqm 103

14Co Description Unit RateNo Rs.

###Standard quality hard board sheet 4.5 mm thick sqm 120###Shellac kilogram 192###Spirit litre 37

###Spun yarn kilogram 30###Mild steel round bar 12 mm dia and below quintal 3,100###Mild steel round bar above 12 mm dia quintal 3,050###Average rate of Mild steel round bars for reinforcements quintal 3,075

###Twisted steel / deformed bars quintal 3,175###Mild steel square bars quintal 3,175###Structural steel such as tees, angles channels and R.S. joists quintal 3,100

###Flats up to 10 mm in thickness quintal 2,900###Flats exceeding 10 mm in thickness quintal 2,875###Mild steel plates quintal 3,400###Mild steel sheets for tanks quintal 3,475

###Mild steel expanded metal 20x60 mm strands sqm 200###Mild steel hooks each 22###Mild steel rivets quintal 3,500

###Hard drawn steel wire fabric sqm 310###Galvanised steel bolts & nuts 6 mm dia and 25 mm long round head

with slots 10 Nos 9###Galvanised steel J or L hooks 8 mm dia 10 Nos 58###Galvanised steel bolts & nuts 10 mm dia and 125 mm long round

head with slots each 7###Mild stel bolts 6 mm dia and 25 mm long with hexagonal head 10 Nos 18

###Straining bolts each 50###Galvanised steel barbed wire quintal 4,400###Galvanised steel turn buckles each 9

###Galvanised steel bolts & nuts 10 mm dia and 27 cm long both sidesthreaded with 4 galvanised steel nuts each 13

###Galvanised steel bolts 10 mm dia and 7 cm long with nuts each 9###Bolts and nuts up to 300 mm in length quintal 4,300###Bolts and nuts above 300 mm in length quintal 4,300

###Iron pintels including welded pin each 28###Steel beading metre 15###Aluminium Plain Strip edging 38x12x3 mm metre 78

Page 21: DAR_Vol_1

15Co Description Unit RateNo Rs.

###Glass strip 4 mm thick40 mm deep metre 6###Boundary stone top chisel dressed 15x15x90 cm each 46###Through and bond stone 100 Nos 970

###Stone for masonry work cum 332###Stone for pitching 15 cm x 22.5 cm cum 332###Stone dust cum 700###Red sand stone block 10 cudm 45

###White sand stone block 10 cudm 50###White sand stone slab 75 mm thick (un-dressed) sqm 256###Red sand stone slab 40 mm thick (un-dressed) sqm 120

###White sand stone slab 40 mm thick (un-dressed) sqm 140###Red sand stone slab 30 mm thick (un-dressed) sqm 97###Kota stone slab 20 mm to 25 mm thick (semi-polished) sqm 239###Kota stone slab 25mm thick (rough chiseled) Sq.m. 150

###Red sand stone slab 45 mm and 50 mm thick (un-dressed) sqm 145###White sand stone slab 45 mm and 50 mm thick (un-dressed) sqm 160###Stone grit 6 mm and down size or pea sized gravel cum 717

###Crushed stone 2.36 mm to 12.5 mm size cum 675###Superior class teak wood such as Dandeli, Balarshah or Malabar in

planks 10 cudm 895###First class teak wood in scantling 10 cudm 492###First class teak wood in planks 10 cudm 506

###Second class teak wood in scantling 10 cudm 394###Second class teak wood in planks 10 cudm 410###Second class deodar wood in planks 10 cudm 335

###First class kail wood in planks 10 cudm 186###Second class kail wood in scantling 10 cudm 160###Second class kail wood in planks 10 cudm 178###Sal wood in scantling 10 cudm 218

###Precast terrazzo tiles 22 mm thick (light shade) sqm 198###Precast terrazzo tiles 22 mm thick(medium shade) sqm 175###Precast terrazzo tiles 22 mm thick (dark shade) sqm 170###G.I. Limpet washer 100 Nos 20

###Bitumen washer 100 Nos 18###G.I. plain washer thick 100 Nos 27

Page 22: DAR_Vol_1

16Co Description Unit RateNo Rs.

###G.I. plain washer thin 100 Nos 20###G.I. plain washer for seam bolts 100 Nos 21###Water proofing materials kilogram 20

###Welding by gas plant cm 1###Welding by electric plant cm 1###Whiting quintal 329

###Wire nails kilogram 40###Wire mesh (rabbit) sqm 38###20 mm dia holding down bolts quintal 3,800###Mild steel sheets with bolts and nuts to rest on pintels each 75

###Hard drawn steel wire quintal 3,100###Mild steel flat strap fitting quintal 2,900###Chequered terrazzo tiles 22 mm thick(light shade) sqm 230

###Chequered terrazzo tiles 22 mm thick(medium shade) sqm 200###Chequered terrazzo tiles 22 mm thick (dark shade) sqm 170###Extra for selected planks of second class teakwood 10 cudm 72###Aluminium Plain Strip edging 57x12x3 mm metre 105

###Diesel oil litre 30.25###Cutting marble or sand stone slab up to 50 mm thick by mechanical

device metre 6###Extra for selected planks of first class teakwood 10 cudm 80###Commercial LPG in cylinder. kg 35

###Bleaching powder quintal 1,550###Surface box for stop cock each 72###Surface box for sluice valve each 140

###Surface box for water meter each 185###C.I. bracket for wash basin and sinks pair 48###C.P.brass chain with 32 mm dia rubber plug each 21###C.P.brass chain with 40 mm dia rubber plug each 22

###Clamps and M.S. stays including bolts and nuts for 100 mm pip each 28###M.S.Holder bat clamp of approved design for 100 mm S.C.I. pip each 13###M.S.Holder bat clamp of approved design for75 mm S.C.I. pipe each 11

###Clamps and M.S. stays including bolts and nuts for 50 mm pipe each 20###Clamps and M.S. stays including bolts and nuts for 75 mm pipe each 25###Clearing eye with chain and lid 100 mm dia each 37

17Co Description Unit RateNo Rs.

Page 23: DAR_Vol_1

###Clearing eye with chain and lid 150 mm dia each 41###Brass bib-cock 15 mm dia each 157

###Brass bib-cock 20 mm dia each 193###Brass stop-cock 15 mm dia each 157###Brass stop-cock 20 mm dia each 193###Mosquito proof coupling of approved design each 23

###C.I. cover and frame 300x300 mm inside each 265###C.I.cover without frame 300x300mm inside i/c cover of 4.50 keach 170###Rectangular cover 455x610 mm with frame (low duty) each 1,395

###Rectangular cover 455x610mm without frame (low duty) each 844###500 mm dia cover with frame (medium duty) each 4,257###500 mm dia cover without frame (medium duty) each 2,129###C.I.mouth, brass ferrule 15 mm dia each 80

###C.I.mouth, brass ferrule 20 mm dia each 114###C.I.mouth, brass ferrule 25 mm dia each 156###Vitreous china foot rests 250x130x30 mm pair 79

###C.I. grating 100x100 mm each 10###C.I. grating 150x150 mm each 19###C.I. grating 180x180 mm each 23###S.C.I. gully or nahani grating 100 mm dia each 10

###Rubber insertions for80 mm dia pipe joints each 9###Rubber insertions for 100 mm dia pipe joints each 12###Rubber insertions for 125 mm dia pipe joints each 13

###Rubber insertions for 150 mm dia pipe joints each 15###Rubber insertions for 200 mm dia pipe joints each 20###Rubber insertions for 250 mm dia pipe joints each 30###Rubber insertions for 300 mm dia pipe joints each 38

###Rubber insertions for 350 mm dia pipe joints each 45###Rubber insertions for 400 mm dia pipe joints each 66###Rubber insertions for 450 mm dia pipe joints each 83

###Rubber insertions for 500 mm dia pipe joints each 106###Rubber insertions for 600 mm dia pipe joints each 118###Mirror of superior make glass 60x45 cm each 249###Vitreous china pedestal for wash basin each 527

18Co Description Unit RateNo Rs.

###Pig lead kilogram 58###S & S.C.I.standard specials up to 300 mm dia (heavy class) quintal 2,400###S & S.C.I.standard specials over 300 mm dia (heavy class) quintal 2,595

###Flanged C.I. standard specials up to 300 mm dia(heavy class) quintal 4,320

Page 24: DAR_Vol_1

###Flanged C.I. standard specials over 300 mm dia(heavy class) quintal 4,772###Casing pipe 100 mm dia metre 292

###Flush pipe with union spreaders and clamps all in C.P. brass forsingle stall each 204

###Flush pipe with union spreaders and clamps all in C.P. brass fordouble stall each 333

###Flush pipe with union spreaders and clamps all in C.P. brass forrange of three stall each 415

###Flush pipe with union spreaders and clamps all in C.P. brass forrange of four stall each 465

###Flush pipe and spreaders G.I.for single set of one squatting plate urinal eac 138###Flush pipe and spreaders G.I.for range of two squatting plates ueach 203

###Flush pipe and spreaders G.I.for range of three squatting plates each 255###Flush pipe and spreaders G.I.for range of four squatting plates each 320###G.I. pipes 15 mm dia metre 58

###G.I. pipes 20 mm dia metre 77###G.I. pipes 25 mm dia metre 109###G.I. pipes 32 mm dia metre 140###G.I. pipes 40 mm dia metre 160

###G.I. pipes 50 mm dia metre 211###G.I. pipes 65 mm dia metre 269###G.I. pipes 80 mm dia metre 355

###G.I. back (jam) nuts25 mm dia each 5###G.I. back (jam) nuts65 mm dia each 15###G.I. tees (equal) 25 mm each 38###G.I. tees (equal) 65 mm each 215

###G.I. inlet connection each 50###S.C.I. soil, waste and vent single socketed pipe1.80 metres

long:75mm dia each 537###S.C.I. soil, waste and vent single socketed pipe1.80 metres long:

100mm dia each 610###S.C.I. soil, waste and vent single socketed pipe1.80 metres long:

150mm dia each 1,205

19Co Description Unit RateNo Rs.

###S.C.I. plain bend75mm dia each 140###S.C.I. plain bend 100mm dia each 178###S.C.I. plain bend 150mm dia each 407

###S.C.I. bend with access door 75mm dia each 161###S.C.I. bend with access door 100mm dia each 194###S.C.I. plain single equal junctions75x75x75 mm dia each 205

###S.C.I. plain single equal junctions100x100x100 mm dia each 265###S.C.I. single equal junctions75x75x75 mm dia with access door. each 224

Page 25: DAR_Vol_1

###S.C.I. single equal junctions 100x100x100 mm dia with access doeach 297

###S.C.I. plain double equal junctions 75x75x75x75 mm dia each 296###S.C.I. plain double equal junctions100x100x100x100 mm dia each 394###S.C.I. double equal junctions75x75x75x75 mm dia with access deach 333###S.C.I. double equal junctions 100x100x100x100 mm dia with access

door. each 417

###Slotted cowl (terminal guard )75 mm dia each 109###Slotted cowl (terminal guard ) 100 mm dia each 152###G.I. Union 15 mm nominal bore each 32###G.I. Union 20 mm nominal bore each 50

###G.I. Union 25 mm nominal bore each 59###G.I. Union 32 mm nominal bore each 73###G.I. Union 40 mm nominal bore each 108

###G.I. Union 50 mm nominal bore each 158###G.I. Union 65 mm nominal bore each 324###G.I. Union 80mm nominal bore each 392###Polyethylene water storage tank with cover and suitable locking

arrangement per litre 4

###Sand cast iron S&S plain single unequal junctions : 100x100x75 mmdia each 288

###Sand cast iron S&S single unequal junctions: 100x100x75 mm diawith access door. each 321

###Sand cast iron S&S plain double unequal junctions : 100x100x75x75mm dia each 423

###Sand cast iron S&S double unequal junctions: 100x100x75x75 mmdia with access door. each 453

###Sand cast iron heel rest bend75mm dia each 165

20Co Description Unit RateNo Rs.

###Sand cast iron heel rest bend 100mm dia each 197###S.C.I. single equal invert branch of required degree75x75x75 m each 239###S.C.I. single equal invert branch of required degree 100x100x100 mm

dia each 321

###S.C.I. double equal invert branch of required degree 75x75x75x75mm dia each 314

###S.C.I. double equal invert branch of required degree100x100x100x100 mm dia each 422

###S.C.I. single unequal invert branch of required degree100x100x75 mm dia each 382

###S.C.I. double unequal invert branch of required degree100x100x75x75 mm dia each 458

###S.C.I. door pieces 75 mm dia each 211###S.C.I. door pieces 100 mm dia each 291

###S.C.I. collar 75 mm dia each 82

Page 26: DAR_Vol_1

###S.C.I. collar 100 mm dia each 110###Unplasticised P.V.C. connection pipe with brass union 30 cm long 15

mm bore each 18###Unplasticised P.V.C. connection pipe with brass union 30 cm long 20

mm bore each 25

###Unplasticised P.V.C. connection pipe with brass union 45 cm long 15mm bore each 25

###Unplasticised P.V.C. connection pipe with brass union 45 cm long 20mm bore each 35

###S.C.I. hand pump each 450###R.C.C. pipes NP2 class 100 mm dia metre 118###R.C.C. pipes NP2 class 150 mm dia metre 135

###R.C.C. pipes NP2 class 250 mm dia metre 157###R.C.C. pipes NP2 class 300 mm dia metre 228###R.C.C. pipes NP2 class 450 mm dia metre 333

###R.C.C. pipes NP2 class 500 mm dia metre 398###R.C.C. pipes NP2 class 600 mm dia metre 642###R.C.C. pipes NP2 class 700 mm dia metre 719###R.C.C. pipes NP2 class 800 mm dia metre 836

###R.C.C. pipes NP2 class 900 mm dia metre 986###R.C.C. pipes NP2 class 1000 mm dia metre 1,243###R.C.C. pipes NP2 class 1100 mm dia metre 1,500

21Co Description Unit RateNo Rs.

###R.C.C. pipes NP2 class 1200 mm dia metre 1,543###R.C.C. collarsNP2 class 100 mm dia each 16

###R.C.C. collarsNP2 class 150 mm dia each 21###R.C.C. collarsNP2 class 250 mm dia each 34###R.C.C. collarsNP2 class 300 mm dia each 42###R.C.C. collarsNP2 class 450 mm dia each 63

###R.C.C. collarsNP2 class 500 mm dia each 73###R.C.C. collarsNP2 class 600 mm dia each 92###R.C.C. collarsNP2 class 700 mm dia each 102

###R.C.C. collarsNP2 class 800 mm dia each 146###R.C.C. collarsNP2 class 900 mm dia each 178###R.C.C. collarsNP2 class 1000 mm dia each 210

###R.C.C. collarsNP2 class 1100 mm dia each 241###R.C.C. collarsNP2 class 1200 mm dia each 280###Stoneware pipes grade A (60 cm long) 100 mm dia each 30###Stoneware pipes grade A (60 cm long) 150 mm dia each 42

###Stoneware pipes grade A (60 cm long) 200 mm dia each 80###Stoneware pipes grade A (60 cm long) 230 mm dia each 85

Page 27: DAR_Vol_1

###Stoneware pipes grade A (60 cm long) 250 mm dia each 113

###Stoneware pipes grade A (60 cm long) 300 mm dia each 165###Fire clay kitchen sink: 600x450x250 mm each 1,192###White vitreous china laboratory sink450x300x150 mm each 664###White vitreous china laboratory sink600x450x200 mm each 1,400

###White plastic seat (solid)with lid C.P.brass hinges and rubber bufeach 275###Black plastic seat (solid) with lid C.P.brass hinges and rubber bufeach 250###Shower rose C.P.brass for 15 to 20 mm inlet 100 mm dia each 28

###Shower rose C.P.brass for 15 to 20 mm inlet 150 mm dia each 40###Spun yarn kilogram 30###Strainer brass 40 mm dia 1.5 metre long each 405###15 mm C.P.brass tap each 103

###C.P.brass toilet paper holder of standard size each 70###C.I. trap for standard urinal with vent arm with operating and other

couplings in C.P.brass: 50 mm dia each 125###C.I. trap for standard urinal with vent arm with operating and other

couplings in C.P.brass: 80 mm dia each 158

22Co Description Unit RateNo Rs.

###C.P.brass trap40 mm dia each 99###100 mm S.C.I. trap with vent heel each 260

###100 mm S.C.I. trap with 100 mm inlet and 100 mm outlet each 221###100 mm S.C.I. trap with 100 mm inlet and75 mm outlet each 164###S.W. gully trap P type 100x100 mm each 55

###S.W. gully trap P type 150x100 mm each 86###S.W. gully trap P type 180x150 mm each 160###Vitreous china lipped front urinal each 380###Vitreous china squatting plate urinal each 610

###H.P. or L.P. ball valve with polythene floats: 15 mm dia each 175###H.P. or L.P. ball valve with polythene floats: 20 mm dia each 260###H.P. or L.P. ball valve with polythene floats: 25 mm dia each 300

###Brass full way valve with C.I. wheel (screwed end) 25 mm dia each 235###Brass full way valve with C.I. wheel (screwed end) 32 mm dia each 296###Brass full way valve with C.I. wheel (screwed end) 40 mm dia each 330

###Brass full way valve with C.I. wheel (screwed end) 50 mm dia each 483###Brass full way valve with C.I. wheel (screwed end) 65 mm dia each 700###Brass full way valve with C.I. wheel (screwed end) 80 mm dia each 1,160###Gunmetal non-return valve-horizontal (screwed end) 25 mm diaeach 238

###Gunmetal non-return valve-horizontal (screwed end) 32 mm diaeach 305###Gunmetal non-return valve-horizontal (screwed end) 40 mm diaeach 410###Gunmetal non-return valve-horizontal (screwed end) 50 mm diaeach 618

Page 28: DAR_Vol_1

###Gunmetal non-return valve-horizontal (screwed end) 65 mm diaeach 1,085###Gunmetal non-return valve-horizontal (screwed end) 80 mm diaeach 1,540###C.I.sluice valve (with caps) class I : 100 mm dia each 1,890###C.I.sluice valve (with caps) class I : 125 mm dia each 2,365

###C.I.sluice valve (with caps) class I : 150 mm dia each 2,840###C.I.sluice valve (with caps) class I : 200 mm dia each 5,405###C.I.sluice valve (with caps) class I : 250 mm dia each 8,050

###C.I.sluice valve (with caps) class I : 300 mm dia each 9,920###Vitreous china flat back wash basin 630x450 mm each 585###Vitreous china angle back wash basin 600x480 mm each 540###Vitreous china angle back wash basin 400x400 mm each 347

###C.P. brass waste 32 mm each 48

23Co Description Unit RateNo Rs.

###C.P. brass waste 40 mm each 53###Vitreous china Indian type w.c. pan size 580 mm each 290###Vitreous china orrisa type w.c. pan size 580 mm each 700

###Vitreous china pedestal type water closet each 554###Bolts and nuts 16 mm dia 60 mm long each 8###Bolts and nuts 16 mm dia 65 mm long each 8###Bolts and nuts 20 mm dia 65 mm long each 12

###Bolts and nuts 20 mm dia 70 mm long each 12###Bolts and nuts 20 mm dia 75 mm long each 12###Bolts and nuts 20 mm dia 80 mm long each 13

###Bolts and nuts 24 mm dia 85 mm long each 24###Bolts and nuts 24 mm dia 90 mm long each 26###Bolts and nuts 27 mm dia 100 mm long each 30###White vitreous china dual purpose closet (Anglo Indian W.C.) suitable

for use as squatting pan or European type water closet as permanufacturer’s specifications each 796

###Vitreous china foot rests 250x125x25 mm pair 80

###Fly ash cum 6###F.P.S. bricks tile class designation 100 1000 Nos 1,950.00###Modular bricks class designation75 1000 Nos 2,700.00

###Strips-Aluminium fluted 3.15mm thick and 150mm wide metre 216###Strips Aluminium fluted 3.15mm thick and 200mm wide metre Metre 288###Float glass sheet of nominal thickness 4 mm (weight not less than

10kg/sqm). sqm 248###Float glass sheet of nominal thickness 5.5 mm.(weight not less than

13.50 kg/sqm). sqm 340###Ply wood 5 ply with commercial ply on both faces 6 mm thick sqm 282

Page 29: DAR_Vol_1

###Hollock ballies 125 mm diameter metre 27###Oxidised mild steel pull bolt lock (locking bolt) of size 85 mm x 42 mm

with screws, bolts, nuts and washers complete each 27###Brass cupboard lock 6 levers (best make of approved quality) 40 mm

size each 36###Brass cupboard lock 6 levers (best make of approved quality) 50 mm

size each 43###Brass cupboard lock 6 levers (best make of approved quality) 65 mm

size each 55

###Brass cupboard lock 6 levers (best make of approved quality) 75 mmsize each 70

24Co Description Unit RateNo Rs.

###Brass hanging type door stopper 150 mm each 46###Hydraulic door closer bottle type M.S. body with necessary

accessories and screws complete each 506###Anodised Aluminium hanging type door stopper each 14###Anodised Aluminium pull bolt lock (locking bolt) of size 85 mmx42

mm with screws, bolts ,nuts and washers complete each 34

###Anodised Aluminium Casement stay 250 mm each 36###Hollock wood in scantling 10 cudm 217###Chromium plated Brass pull bolt lock (locking bolt) of size 85 mmx42

mm with screws, bolts, nuts and washers complete each 130###Nickeled Chromium Brass cupboard lock 40 mm size each 38###Nickeled Chromium Brass cupboard lock 50 mm size each 53

###Nickeled Chromium Brass cupboard lock 65 mm size each 64###Nickeled Chromium Brass cupboard lock 75 mm size each 75###Ply wood 5 ply with teak ply on both faces 9 mm thick sqm 693

###Ply wood 5 ply with teak ply on one face and commercial ply onanother face 9 mm thick sqm 550

###Ply wood 7 ply with teak ply on one face and commercial ply onanother face 9 mm thick sqm 585

###Extra for selected planks of second class deodar wood 10 cudm 59###Kiln seasoning of timber cum 539###Hollock wood in planks 10 cudm 230

###F.P.S. bricks class designation75 1000 Nos 1,900###F.P.S. bricks class designation50 1000 Nos 1,700###Aluminium Strip 40 mm wide and 2 mm thick kilogram 195

###White marble makrana second quality plain veined stone pieces forcrazy flooring quintal 105

###8 mm thick granite stone tiles (mirror polished of all shades) sqm 555###8 mm thick marble tiles (polished) Raj Nagar sqm 294###Stone Aggregate (Single size) : 100 mm nominal size cum 575

###Stone Aggregate (Single size) : 80 mm nominal size cum 575

Page 30: DAR_Vol_1

###Stone chippings/ screenings 4.75 mm nominal size cum 800###Stone chippings/ screenings 150 micron nominal size cum 800

###Over burnt (Jhama) Brick Aggregate: 120 mm to 40 mm size cum 285###Over burnt (Jhama) Brick Aggregate: 90 mm to 40 mm size cum 320

25Co Description Unit RateNo Rs.

###Stone chippings/ screenings 12.5/ 13.2 mm nominal size cum 700###Stone chippings/ screenings 10/ 11.2 mm nominal size cum 700

###Solvent kilogram 18###Paving Asphalt 80/100 penetration tonne 22,500###Polyvinyl chloride sheet 400 micron thick sqm 26

###Stone ware spouts 100 mm dia 60 cm long each 28###Galvanised steel corrugated sheets quintal 3,650###Gunmetal non-return valve-horizontal (screwed end) 25 mm diaeach 260###Gunmetal non-return valve-horizontal (screwed end) 32 mm diaeach 385

###Gunmetal non-return valve-horizontal (screwed end) 40 mm diaeach 505###Gunmetal non-return valve-horizontal (screwed end) 50 mm diaeach 712###Gunmetal non-return valve-horizontal (screwed end) 65 mm diaeach 1,245

###Vitreous china Surgeon type wash basin of size 660x460 mm each 810###600x120 mm glass shelf with anodised aluminium angle frame, C.P.

brass brackets and guard rail of standard size each 95###Vitreous china flat back wash basin 550x400 mm each 450###Gunmetal non-return valve-horizontal (screwed end) 80 mm diaeach 2,038

###C.I.sluice valve (with caps) class II : 100 mm dia each 1,950###C.I.sluice valve (with caps) class II : 125 mm dia each 2,465###C.I.sluice valve (with caps) class II : 150 mm dia each 3,000

###C.I.sluice valve (with caps) class II : 200 mm dia each 5,800###C.I.sluice valve (with caps) class II : 250 mm dia each 8,200###C.I.sluice valve (with caps) class II : 300 mm dia each 10,250###C.P. Brass union 40 mm dia each 130

###C.C.I.(spun) socketed soil, waste and vent pipe 1.80 metreslong:100mm dia each 978

###C.C.I.(spun) socketed soil, waste and vent pipe 1.80 metreslong:75mm dia each 846

###S.C.I. S&S bends with access door100mm dia each 225###S.C.I. S&S bends with access door75mm dia each 179

###S.C.I. S&S bend100mm dia each 190###S.C.I. S&S bend75mm dia each 143###S.C.I. S&S heel rest sanitary bend 100mm dia each 233###S.C.I. S&S heel rest sanitary bend 75mm dia each 204

###S.C.I. S&S single equal junctions100x100x100 mm each 367

Page 31: DAR_Vol_1

26Co Description Unit RateNo Rs.

###S.C.I. S&S single equal junctions75x75x75 mm each 276###S.C.I. S&S single equal junctions with access door 100x100x10 each 396

###S.C.I. S&S single equal junctions with access door 75x75x75 mmeach 294###S.C.I. S&S double equal junctions100x100x100x100 mm each 467###S.C.I. S&S double equal junctions75x75x75x75 mm each 373

###S.C.I. S&S double equal junctions with access door100x100x100x100 mm. each 502

###S.C.I. S&S double equal junctions with access door 75x75x75x75mm. each 400

###S.C.I. S&S single unequal junctions100x100x75 mm each 461###S.C.I. S&S single unequal junctions with access door

100x100x75 mm each 523###S.C.I. S&S double unequal junctions100x100x75x75 mm each 639

###S.C.I. S&S double unequal junctions with access door100x100x75x75 mm each 700

###S.C.I. S&S single equal invert branch of required degree100x100x100 mm dia each 325

###S.C.I. S&S single equal invert branch of required degree 75x75x75mm dia each 247

###S.C.I. S&S double equal invert branch of requireddegree100x100x100x100 mm dia each 414

###S.C.I. S&S double equal invert branch of required degree75x75x75x75 mm dia each 334

###S.C.I. S&S single unequal invert branch of requireddegree100x100x75 mm dia each 422

###S.C.I. S&S double unequal invert branch of requireddegree100x100x75x75 mm dia each 574

###S.C.I. S&S, 75 mm offset for75 mm dia pipe each 179###S.C.I. S&S, 150 mm offset for75 mm dia pipe each 223###S.C.I. S&S, 150 mm offset for100 mm dia pipe each 306###S.C.I. S&S, 114 mm offset for75 mm dia pipe each 220

###S.C.I. S&S, 114 mm offset for100 mm dia pipe each 289###S.C.I. S&S, 152 mm offset for75 mm dia pipe each 275###S.C.I. S&S, 152 mm offset for100 mm dia pipe each 361

###S.C.I S&S door pieces 100 mm dia each 230###S.C.I S&S door pieces 75 mm dia each 176###S.C.I S&S, Slotted Cowl (Terminal Guard) 100 mm each 154###S.C.I S&S, Slotted Cowl (Terminal Guard) 75 mm each 142

Page 32: DAR_Vol_1

27Co Description Unit RateNo Rs.

###S.C.I S&S, collars 100 mm each 161

###S.C.I S&S, collars 75 mm each 115###S.C.I. S&S, 76 mm offset for75 mm dia pipe each 126###S.C.I. S&S, 76 mm offset for100 mm dia pipe each 220###Vitreous china toilet paper holder of standard size each 89

###560 mm dia cover with frame (Heavy duty) each 7,634###560 mm dia cover without frame (Heavy duty) each 3,664###Pressed steel door frames (mild steel sheet 1.25mm) Profile “B metre 170

###Pressed steel door frames (mild steel sheet 1.25mm) Profile “C metre 187###Pressed steel door frames (mild steel sheet 1.25mm) Profile “E metre 214###Mild steel tubes hot finished welded type kilogram 38###Mild steel tubes hot finished seamless type kilogram 42

###Mild steel tubes electric resistant or induction butt welded kilogram 53###Circular C.I. Box for ceiling fan each 35###Pulley 40 mm dia each 19

###Ready made steel door with necessary hinges, lugs and glazing clipsexcluding other fittings & their fixing sqm 1,406

###Aluminium primer litre 63###Red oxide Zinc chromate primer litre 58###Copper acetate kilogram 228

###Hydrochloric acid kilogram 27###Copper chloride kilogram 244###Copper nitrate kilogram 173###Ammonium chloride kilogram 12

###Mobil oil litre 95###White marble slab Makrana second quality plain veined 18 mm sqm 1,722###Pink marble slab plain 18mm thick sqm 546

###Udaypur green marble slab plain 18mm thick sqm 580###Black Zebra marble slab plain 18mm thick sqm 415###Sand zone V (Jamuna) cum 175###Brass 100mm mortice latch and lock with6 levers without pair of

handles each 150

###Pair of Anodised Aluminium lever handles for 100mm mortice latchand lock each 195

###Vitreous china flat back wash basin 450x300 mm each 360

28Co Description Unit Rate

Page 33: DAR_Vol_1

No Rs.

###Vitreous china 10 litres low level cistern without fittings each 824

###Vitreous china 10 litres low level cistern with fittings each 1,390###F.P.S. clay fly ash bricks class designation 75 1000 Nos 1,412###Gypsum board sqm 140

###Ceiling sections metre 36###Perimeter channel metre 23###Intermediate channel metre 38###Ceiling angle metre 16

###Connecting clips each 5###Soffit cleat each 3###Joint filler kilogram 19

###Joint finisher kilogram 22###Joint tape roll roll 120###Dash fastener/ Chemical fastener each 8###All drive screws ( for gypsum board) 100 Nos 40

###Primer ( for gypsum board) litre 76###Chlorpyriphos 20% E.C. / Lindane 20% E.C. litre 150###Chromium plated brackets ( curtain rods) each 5

###Acid Proof cement tonne 7,400###M.S. Butt hinges 125x90x4 mm 10 Nos 80###Galvanised wire mesh of average width of aperture 1.4 mm and

nominal dia. of wire 0.63 mm sqm 142###Frosted glass sheet of nominal thickness 4 mm (weighing not less

than 10 kg/sqm) sqm 257###Nickel plated M.S. pipe 20 mm dia. metre 54

###Nickel plated M.S. Brackets for curtain rod 20 mm each 3###Nickel plated M.S. Brackets for curtain rod 25 mm each 4###Oxidised mild steel screws 35 mm 100 Nos 28

###Mild steel conduit pipe (heavy type) ISI marked-20 mm dia. metre 44###Mild steel conduit pipe (heavy type) ISI marked-25 mm dia. metre 49###Rolling shutters of 80x0.90 mm laths sqm 576###Rolling shutters of 80x1.2 mm laths sqm 615

###Top cover of Rolling shutters 0.90 mm thick metre 205###Top cover of Rolling shutters 1.20 mm thick metre 228###Rawl plug 50 mm (designation 10 no.) each 7

29Co Description Unit RateNo Rs.

###Teak wood lipping of size 25x3 mm in pelmets metre 16

###Flat pressed 3 layer and graded particle board (medium density)

Page 34: DAR_Vol_1

Grade 1 conforming to IS : 3087 - 18 mm thick sqm 301###Aluminium tee channel (heavy duty) with rollers and stop end metre 35###Aluminium hanging floor door stopper with twin rubber & stoppeach 44###Hydraulic door closer tubular type Aluminium section body each 765

###Oxidised M.S.casement stay (straight peg type) 300 mm not less than0.33 kg each 14

###Oxidised M.S.casement stay (straight peg type) 250 mm not less than0.28 kg each 12

###Oxidised M.S.casement stay (straight peg type) 200 mm not less than0.24 kg each 11

###Extra for providing grilled rolling shutters with 8 mm dia M.S. ro sqm 185###Chequered precast cement concrete tiles 22mm thick using marble

chips of size 6mm - Light shade using white Cement. sqm 415

###White marble Raj Nagar plain 20 mm thick (slab area 0.10 sqm to0.20 sqm) sqm 415

###Acid and alkali resistant tiles 300x300 mm size, 10 mm thick 10 Nos 460###S.C.I. Tee 150 mm each 460###Expanded polystyrene type N- Normal sqm 108

###Expanded polystyrene type - SE sqm 131###Stainless steel kitchen sink - with drain board bowl depth 250 each 4,900###Stainless steel kitchen sink - with drain board 510 x 1040mm bowl

depth 225 mm. each 4,600###Stainless steel kitchen sink - with drain board 510 x 1040mm bowl

depth 200 mm. each 4,100###Stainless steel kitchen sink - with drain board 510x1040mm bowl

depth 178 mm each 2,600

###Stainless steel kitchen sink - without drain board 610x510mm bowldepth 200 mm each 2,700

###Stainless steel kitchen sink - without drain board 610x460mm bowldepth 200 mm. each 2,500

###Stainless steel kitchen sink - without drain board 470x420mm bowldepth 178 mm each 1,600

###Coloured Orissa pattern W.C. pan 580x440 mm each 1,043###Coloured Pedestal type W.C. pan 580x440 mm (European type) each 865

###Coloured Vitreous china 10 lit. low level cistern each 1,268###Coloured (other than black) solid P.V.C. seat in European W.C. each 380

30Co Description Unit RateNo Rs.

###Circular shape 450 mm dia Mirror with Plastic moulded frame each 370

###Rectangular shape 453x357 mm Mirror with Plastic moulded fr each 245###Oval shape 450x350 mm (outer dimensions) Mirror with Plastic

moulded frame each 280###Rectangular shape 1500x450 mm Mirror with Plastic moulded f each 635###Hard board 6 mm thick sqm 151

Page 35: DAR_Vol_1

###Semi Rigid PVC waste pipe for sink and wash basin 32 mm dia withlength not less than 700 mm i/c PVC waste fittings each 16

###Semi Rigid PVC waste pipe for sink and wash basin 40 mm dia withlength not less than 700 mm i/c PVC waste fittings each 21

###Flexible (coil shaped) PVC waste pipe for sink and wash basin 32mm dia with length not less than 700 mm i/c PVC waste fittings each 20

###Flexible (coil shaped) PVC waste pipe for sink and wash basin 40mm dia with length not less than 700 mm i/c PVC waste fittings each 22

###Coloured High density polyethylene/ poly propylene 10 lit. (full flush)capacity controlled low level flushing cistern with fittings each 632

###White Vitreous china 10 lit. (full flush) capacity controlled low levelflushing cistern with all fittings each 858

###Coloured Vitreous china 10 lit. (full flush) capacity controlled low levelflushing cistern with all fittings each 1,277

###S.W. intercepting trap 100 mm dia each 144###S.W. intercepting trap 150 mm dia each 202###Rectangular shape 600x450 mm precast R.C.C. manhole cover with

frame - L.D. - 25 each 628###Square shape 350x350 mm precast R.C.C. manhole cover with frame

- L.D. - 25 each 540###Circular shape 450 mm dia precast R.C.C. manhole cover with frame

- L.D. - 25 each 474

###Rectangular shape 500x500 mm precast R.C.C. manhole coverwith frame - M.D. - 10 each 575

###Circular shape 500 mm dia precast R.C.C. manhole cover with frame- M.D. - 10 each 575

###Circular shape 560 mm dia precast R.C.C. manhole cover with frame- H.D. - 20 each 838

###Circular shape 560 mm dia precast R.C.C. manhole cover with frame- E.H.D. - 35 each 935

###Factory made 35 mm thick shutters with laminated veneer lumberstyles rails as per TADS IS:1995 and panels of 12 mm thick plaintype-I, medium density flat pressed three layer, graded particle board(FPT-I) as per IS:3087-1985 bonded with BWP type synthetic resinadhesive, as per IS:848-1974 sqm 1,500

31Co Description Unit RateNo Rs.

###Factory made 35 mm thick shutters with laminated veneer lumberstyles rails as per TADS IS:1995 and panels of 12 mm thick bothsides prelaminated type-I, medium density flat pressed three layer,graded particle board (FPT-I) as per IS:3087-1985 bonded with BWPtype synthetic resin adhesive, as per IS:848-1974 sqm 1,618

###Factory made 35 mm thick shutters with laminated veneer lumberstyles rails as per TADS IS:1995 and panels of 12 mm thick one sideprelaminated type-I, and other side balancing lamination, mediumdensity flat pressed three layer, graded particle board (FPT-I) as perIS:3087-1985 bonded with BWP type synthetic resin adhesive, as perIS:848-1974 sqm 1,572

Page 36: DAR_Vol_1

###Factory made 30 mm thick shutters with laminated veneer lumberstyles rails as per TADS IS:1995 and panels of sheet glass using 10kg/ sqm glass panes sqm 1,290

###Factory made 35 mm thick shutters with laminated veneer lumberstyles rails as per TADS IS:1995 and panels of galvanised wiregauge with average width of aperture 1.4 mm on both directions withwire of dia 0.63 mm sqm 1,328

###Factory made 30 mm thick shutters with laminated veneer lumberstyles rails as per TADS IS:1995 and panels of galvanised wiregauge with average width of aperture 1.4 mm on both directions withwire of dia 0.63 mm sqm 1,150

###Laminated veneer lumber confirming to TADSS IS:1995manufactured in factory in frames of doors, windows 10 cudm 540

###C.I. pile shoe kilogram 40###M.S. clamps for pile shoe kilogram 35###Bentonite tonne 2,700###Oxidised M.S. safety chain (weighing not less than 450 gms) for each 43###C.I. grating 150 mm dia. (Weighing not less than 440 gm) each 16###U-PVC pipes (working pressure 4 kg / cm2) Single socketed pipe 75

mm dia. metre 58###U-PVC pipes (working pressure 4 kg / cm2) Single socketed pipe 110

mm dia. metre 112###U-PVC pipes (working pressure 4 kg / cm2) Rubber (Seal) Ring 75

mm dia. metre 14###U-PVC pipes (working pressure 4 kg / cm2) Rubber (Seal) Ring 110

mm dia. metre 17

###UPVC coupler for UPVC drainage pipes 75 mm each 30###UPVC coupler for UPVC drainage pipes 110 mm each 40###UPVC pushfit coupler (single) 75 mm thick each 47

32Co Description Unit RateNo Rs.

###UPVC pushfit coupler (single) 110 mm thick each 72###UPVC single equal Tee (with door) 75x75x75 mm each 83###UPVC single equal Tee (with door) 110x110x110 mm each 115###UPVC single equal Tee (with door) 75x75x75 mm each 100

###UPVC single equal Tee (with door) 110x110x110 mm each 160###UPVC bend 87.5o 75 mm bend each 50###UPVC bend 87.5o 110 mm bend each 85

###UPVC plain shoe 75 mm bend each 105###UPVC plain shoe 110 mm bend each 196###UPVC pipe clip 75 mm bend each 15###UPVC pipe clip 110 mm bend each 30

###Resin Bonded Glass wool 16 kg/m³ 50 mm thick sqm 114###Resin Bonded Glass wool 24 kg/m³ 50 mm thick sqm 163###Fibre glass tissue reinforcement Type II Grade I sqm 55

###Precast chequered cement tiles 22 mm thick Dark shade using

Page 37: DAR_Vol_1

ordinary cement sqm 193###Precast chequered cement tiles 22 mm thick Medium shade using

50% White cement & 50% Ordinary cement sqm 305###Epoxy paint litre 280###Fire retardant paint litre 318###Melamine polish litre 228

###Table rubbed polished stone 18 mm thick (75x50cm) Agaria Marblestone - 18 mm thick sqm 1,440

###Table rubbed polished stone 18mm thick (75x50cm) Granite stone- 18mm thick sqm 1,670

###Vertical load testing (INITIAL) of piles in accordance with IS : 2911(Part-IV) including installation of loading platform and preparation ofpile head or construction of test cap and dismantling of test cap aftertest etc. complete as per specification and up to 50MT capacity per test 19,500

###Vertical load testing (INITIAL) of piles in accordance with IS : 2911(Part-IV) including installation of loading platform and preparation ofpile head or construction of test cap and dismantling of test cap aftertest etc. complete as per specification & above 50MT and up to100MT. per test 27,500

###Vertical load testing (INITIAL) of piles in accordance with IS : 2911(Part-IV) including installation of loading platform and preparation ofpile head or construction of test cap and dismantling of test cap aftertest etc. complete as per specification & group of two or more up to50MT. per test 37,500

###Cyclic vertical load testing of piles in accordance with IS : 2911(Part-IV) including preparation of pile head etc. for Single pile up to 50tonne capacity per test 11,500

33Co Description Unit RateNo Rs.

###Cyclic vertical load testing of piles in accordance with IS : 2911(Part-IV) including preparation of pile head etc. for Single pile above 50tonne capacity pile and up to 100 tonne capacity pile per test 18,000

###Cyclic vertical load testing of piles in accordance with IS : 2911 (Part-IV) including preparation of pile head etc. for Group of two piles up to50 tonne capacity each per test 23,000

###Lateral load testing of single pile in accordance with IS : 2911part -IV for determining safe allowable lateral load on pile. Up to 50tonne capacity per test 11,500

###Lateral load testing of single pile in accordance with IS : 2911part -IV for determining safe allowable lateral load on pile. Above50 tonne capacity per test 18,000

###Hardening Compound litre 29

###Road marking paint (spirit based) litre 97###Superior quality road marking paint litre 148###C.P. Brass bibcock 15 mm each 258

###C.P. Brass long nose bibcock 15 mm each 220###C.P. Brass long body bibcock 15 mm each 258###C.P. Brass stop cock (concealed) 15 mm each 258

Page 38: DAR_Vol_1

###C.P. Brass angle valve 15 mm each 288

###Pressed clay tiles 1000 Nos 8,900###Plain ceiling tiles (BWP type phenol formaldehyde synthetic resin

bonded) (600x600x12 mm) each 90###Semi perforated ceiling tiles (600x600x12 mm) each 90###25 mm thick particle board sqm 390

###30 mm thick prelaminated flush door shutter sqm 716###IInd class teak wood lipping 25 mm wide x 12 mm thick metre 28###25 mm thick melamine faced prelaminated three layer particle sqm 708

###Granite Black marble, 18 mm thick slab, above 0.2 sqm up to 0.5 sqm(areawise) sqm 1,500

###Granite Black marble, 18 mm thick slab, above 1.0 sqm up to 2.0 sqm(areawise) sqm 1,615

###Aluminium T or L sections kilogram 195###For flush door shutters Extra for providing teak veneering on one side

instead of commercial veneering sqm 225###Paving Asphalt 60/70 penetration tonne 23,200

###Expandable fastener with plastic sleeve and M.S. screws. 25 mmlong each 6

###Expandable fastener with plastic sleeve and M.S. screws. 32 mmlong each 7

34Co Description Unit RateNo Rs.

###Expandable fastener with plastic sleeve and M.S. screws. 40 mmlong each 9

###Expandable fastener with plastic sleeve and M.S. screws. 50 mmlong each 11

###Plasticizer / super plasticizer kilogram 30###Wall form panel 1250x500 mm each 980###Tie bolt 12 mm dia 100 mm length each 31

###Tie bolt 12 mm dia 150 mm length each 42###Tie bolt 20 mm dia 150 mm length each 57###Tie bolt 20 mm dia 225 mm length each 72###Spring coil 12 mm each 10

###Plastic cone 12 mm dia each 12###Corner angle 45x45x5 mm 1.50 m long each 280###100 mm channel shoulder 2.5 m long each 1,000

###Double clip ( bridge clip) each 75###Single clip each 60###M.S. tube 40 mm dia metre 225

###Wall form panel 1250x450 mm each 900###Corner angle 45x45x5 m 2.50 m long each 275

Page 39: DAR_Vol_1

###Column clamp 450x1070 m each 1,100###Prop 2 m ( 2-3.5m) each 750

###Binding wire kilogram 40###Gun metal cramp kilogram 270###Stainless steel cramp kilogram 280###Stainless steel pin . kg 130

###Adjustable span ESO+SI (2.35-3.40) each 1,600###Adjustable telescopic prop 3 m (2.02-3.75 m) each 1,000###Beam clamp 300-380 mm (450-1070 mm) each set 375

###Prop 4 m each 1,030###Double coupler each 45###Cadmium plated full threaded steel screws (30x4 mm dia.) 100 Nos 23

###Aluminium washer 2 mm thick 15 mm dia 100 Nos 7###12 mm M.S. ‘U’ beading metre 9###Plastic encapsulated M.S. foot rest 30x20x15 cm each 93

35Co Description Unit RateNo Rs.

###Flushing Cistern P.V.C. 10 lts capacity ( low level ) (White) ( withfittings, accessories and flush pipe) each 570

###P.V.C. automatic flushing cistern 5 lts capacity each 430###P.V.C. automatic flushing cistern 10 lts capacity each 465

###15 mm C.P. brass tap with elbow operation lever each 396###White glazed fire clay draining board 600x450x25 mm each 390###Glass reinforced Gyp sum ( GRG) board 8.5 mm thick sqm 190

###Galvanised M.S. sheet 0.5 mm thick pressed channel section of size50x32 mm metre 48

###Galvanised M.S. sheet 0.50 mm thick pressed stud. 48x34x36 metre 55###G.I. flush pipe and C.P. brass spreader including C.P. connecting

pipe Single lipped urinal each 352###G.I. flush pipe and C.P. brass spreader including C.P. connecting

pipe Range of two lipped urinals each 880###G.I. flush pipe and C.P. brass spreader including C.P. connecting

pipe Range of three lipped urinals each 1,070###G.I. flush pipe and C.P. brass spreader including C.P. connecting

pipe Range of four lipped urinals each 1,530###White vitreous china clay half stall urinal flat back 580x380x350 mm

or angle back 450x375x350 mm with waste fittings as per IS : 2 each 1,224

###Precast R.C.C. grating with frame 500x450 mm horizontal gratin each 533###Precast R.C.C. grating with frame 450x100 mm vertical grating each 250###Bitumen emulsion rapid setting (R.S.) confirming to IS : 8887-19 tonne 32,000###3 mm thick translucent white acrylic plastic sheet sqm 515

###12 thick particle board ceiling tile sqm 225###Dash hold fastener 12.5 mm dia, 40 mm long with 6 mm dia bol each 30

Page 40: DAR_Vol_1

###Anodising 15 microns on aluminium sections kilogram 32

###Neoprene/EPDM rubber gasket metre 22###Anodising 25 microns on aluminium sections kilogram 40###Powder coating 50 microns on aluminium sections. kilogram 45

###Polyester powder coating 50 microns on aluminium sections kilogram 50###Double action hydraulic floor spring with stainless steel cover each 1,400###6 mm dia. G.I. adjustable hangers including clips (up to 1.2 m le each 25###Double action hydraulic floor spring with brass cover plate each 1,550

###15 mm PTMT bib cock each 96###15 mm PTMT bib cock with flange (fancy) each 220###15 mm PTMT bib cock long body with flange each 155

36Co Description Unit RateNo Rs.

###15 mm dia PTMT stop cock(male thread) each 96###20 mm dia. PTMT stop cock each 120###PTMT pillar cock each 150###PTMT push cock 15 mm dia. each 90

###PTMT push cock 12 mm dia. 20 mm BSP each 75###PTMT grating 100 mm dia. each 30###125 mm grating with waste hole each 36

###Rectangular type with openable circular lid 150 mm size 18 mm highwith 100 mm dia. (110 gm) each 90

###Double acting air valve 50 mm each 3,050###Double acting air valve 80 mm each 4,480###Double acting air valve 100 mm each 5,800

###Water meter (including testing charges) 80 mm each 1,800###Water meter (including testing charges) 100 mm each 2,800###Water meter (including testing charges) 150 mm each 4,000###Water meter (including testing charges) 200 mm each 4,500

###Dirt box strainer 80 mm each 2,500###Dirt box strainer 100 mm each 3,750###Dirt box strainer 150 mm each 4,850

###Dirt box strainer 200 mm each 6,800###Cat’s eye each 450###Water stops Serrated with central bulb (225 mm wide, 8-11 mm metre 330###Water stops Dumb bell with central bulb metre 306

###Kickers metre 325###Wedge expansion hold fastener 1/4\" or 6 mm each 10###Wedge expansion hold fastener 3/8\" or 10 mm each 12

###Wedge expansion hold fastener 1/2\" or 12 mm each 23

Page 41: DAR_Vol_1

###8mm thick (mirror polished tiles machine cut edge) Raj Nagar w sqm 430###Wheel 75 mm dia. 40 mm wide each 52

###Aluminium single cleat of size 30x32x3 each 10###Aluminium grip strip of size 50x12x2 each 7###25 mm prelaminated flush door both side decorative sqm 650###Aluminium U beading kilogram 195

###Glass sheet (Pin headed) 4 mm thick sqm 160###Raj nagar plain white marble (table rubbed and polished) 18 mm thick

above 0.10 sqm up to 0.20 sqm sqm 540

37Co Description Unit RateNo Rs.

###Raj nagar plain white marble (table rubbed and polished) 18 mm thickabove 0.20 sqm up to 0.50 sqm sqm 580

###Second class deodar teak wood lipping 30 mm widthx12mm metre 15###Veneered particle board with commercial veneering on both sides 12

mm thick sqm 418###Prelaminated particle board with one side decorative and other side

balancing lamination, flat pressed 3 layer & graded (medium density)Grade I, Type II conforming to IS : 12823 (exterior grade)12 mm sqm 595

###Prelaminated particle board with one side decorative and other sidebalancing lamination, flat pressed 3 layer & graded (medium density)Grade I, Type II conforming to IS : 12823 (exterior grade)18 mm sqm 716

###Prelaminated particle board with one side decorative and other sidebalancing lamination, flat pressed 3 layer & graded (medium density)Grade I, Type II conforming to IS : 12823 (exterior grade)25 mm sqm 775

###Prelaminated particle board with both sides decorative lamination, flatpressed 3 layer & graded (medium density) Grade I, Type IIconforming to IS : 12823 (exterior grade)12 mm thick sqm 625

###Oxidised M. S. hinges finished with nickel plating 50 mm (Over all width) metre29###Oxidised M. S. hinges finished with nickel plating 65 mm (Over all width) metre34###PTMT Waste Coupling 31/32MM Each 45

###PTMT Waste Coupling 38/40MM Each 66###PTMT Bottle Trap 31/32MM Each 295###PTMT Bottle Trap 38/40MM Each 320

###PTMT Ball Cock 15mm Complete with Epoxy Coated Aluminium Road &H.D. Ball Each 121

###PTMT Ball Cock 20mm Complete with Epoxy Coated Aluminium Road &H.D. Ball Each 175

###PTMT Ball Cock 25mm Complete with Epoxy Coated Aluminium Road &H.D. Ball Each 396

###PTMT Ball Cock 40mm Complete with Epoxy Coated Aluminium Road &H.D. Ball Each 745

###PTMT Ball Cock 50mm Complete with Epoxy Coated Aluminium Road &H.D. Ball Each 1,120

Page 42: DAR_Vol_1

###PTMT Angle Stop cock with Flange 15mm Each 120

###PTMT Swiveling shower 15mm Each 81###PTMT Liquid Soap Container of 400ml capacity Each 135###PTMT Towel Ring 215xd200x37mm Each 108

38Co Description Unit RateNo Rs.

###PTMT Towel Rail (450MM) Each 180###PTMT Towel Rail (600MM) Each 210###PTMT Shelf 450x124x36mm Each 245###PTMT Urinal Spreader 15MM Each 120

###PTMT Soap Dish/Holder 138x102x75mm Each 108###PTMT handle 125x34x24mm Each 27###PTMT handle 150x34x24mm Each 30

###PTMT butt hinges 75x60x10mm Each 36###PTMT butt hinges 100x75x10mm Each 48###PTMT Tower bolt 152x42x18mm Each 60###PTMT Tower bolt 202x42x18mm Each 72

###PTMT door catcher 72x42mm Each 24###Coir veneered board 4mm thick sqm 235###Coir veneered board 6mm thick sqm 308

###Coir veneered board 12mm thick sqm 548###Coir veneered board 18mm thick sqm 820###Ductile Iron class K - 9 pipe Conforming to I.S. 8329 100mm dia Metre 658###Ductile Iron class K - 9 pipe Conforming to I.S. 8329 150mm dia Metre 978

###Ductile Iron class K - 9 pipe Conforming to I.S. 8329 200mm dia Metre 1,348###Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - 250mm di Metre 1,743###Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - 300mm di Metre 2,238

###Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - 350mm di Metre 2,625###Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - 400mm di Metre 3,763###Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - 450mm di Metre 4,175###Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - 500mm di Metre 5,600

###Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - 600mm di Metre 6,275###Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - 700mm di Metre 8,538###Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - 750mm di Metre 9,725

###Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - 800mm di Metre 10,000###Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - 900mm di Metre 11,663###Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - 1000mm d Metre 13,125###Rubber Gaskets Conforming to I.S 5382 of S.B.R quality 100mm Each 25

###Rubber Gaskets Conforming to I.S 5382 of S.B.R quality 150mm Each 35###Rubber Gaskets Conforming to I.S 5382 of S.B.R quality 200mm Each 62

Page 43: DAR_Vol_1

39Co Description Unit RateNo Rs.

###Rubber Gaskets Conforming to I.S 5382 of S.B.R quality 250mm Each 68

###Rubber Gaskets Conforming to I.S 5382 of S.B.R quality 300mm Each 98###Rubber Gaskets Conforming to I.S 5382 of S.B.R quality 350mm Each 123###Rubber Gaskets Conforming to I.S 5382 of S.B.R quality 400mm Each 248

###Rubber Gaskets Conforming to I.S 5382 of S.B.R quality 450mm Each 275###Rubber Gaskets Conforming to I.S 5382 of S.B.R quality 500mm Each 285###Rubber Gaskets Conforming to I.S 5382 of S.B.R quality 600mm Each 348###Rubber Gaskets Conforming to I.S 5382 of S.B.R quality 700mm Each 550

###Rubber Gaskets Conforming to I.S 5382 of S.B.R quality 750mm Each 648###Rubber Gaskets Conforming to I.S 5382 of S.B.R quality 800mm Each 725###Rubber Gaskets Conforming to I.S 5382 of S.B.R quality 900mm Each 968

###Rubber Gaskets Conforming to I.S 5382 of S.B.R quality 1000mmEach 1,188###Ductile Iron K - 12 specials suitable for push on jointing up to 600mm

dia Quintal 8,938###Ductile Iron K - 12 specials suitable for push on jointing over 600mm

dia Quintal 13,413###Ductile Iron specials suitable for mechanical jointing as per I.S. 9523 -

up to 600mm dia Quintal 9,400###Ductile Iron Specials suitable for mechanical jointing as per I.S. 9523

over 600mm dia Quintal 14,239###Ductile Iron Pipe Class K-9 flanges and welding 100mm dia Metre 1,888

###Ductile Iron Pipe Class K-9 flanges and welding 150 dia metre 2,613###Ductile Iron Pipe Class K-9 flanges and welding 200mm dia Metre 3,388###Ductile Iron Pipe Class K-9 flanges and welding 250mm dia Metre 4,498

###Ductile Iron Pipe Class K-9 flanges and welding 300mm dia metre 5,788###Ductile Iron Pipe Class K-9 flanges and welding 350mm dia Metre 7,210###Ductile Iron Pipe Class K-9 flanges and welding 400mm dia Metre 8,613###Ductile Iron Pipe Class K-9 flanges and welding 450mm dia Metre 10,413

###Ductile Iron Pipe Class K-9 flanges and welding 500mm dia Metre 12,625###Ductile Iron Pipe Class K-9 flanges and welding 600mm dia Metre 17,125###Ductile Iron Pipe Class K-9 flanges and welding 700mm dia Metre 21,125

###S&S Centrifugally (Spun) C.I. Pipe class LA 100mm dia Metre 624###S&S Centrifugally (Spun) C.I. Pipe class LA 125mm dia metre 763###S&S Centrifugally (Spun) C.I. Pipe class LA 150mm dia metre 901###S&S Centrifugally (Spun) C.I. Pipe class LA 200mm dia Metre 1,252

###S&S Centrifugally (Spun) C.I. Pipe class LA 250mm dia Metre 1,779

Page 44: DAR_Vol_1

40Co Description Unit RateNo Rs.

###S&S Centrifugally (Spun) C.I. Pipe class LA 300mm dia Metre 2,366###S&S Centrifugally (Spun) C.I. Pipe class LA 350mm dia metre 2,918###S&S Centrifugally (Spun) C.I. Pipe class LA 400mm dia Metre 3,574###S&S Centrifugally (Spun) C.I. Pipe class LA 450mm dia Metre 4,276

###S&S Centrifugally (Spun) C.I. Pipe class LA 500mm dia Metre 5,211###S&S Centrifugally (Spun) C.I. Pipe class LA 600mm dia Metre 6,884###S&S Centrifugally (Spun) C.I. Pipe Specials as per IS 1538 suitable

for lead jointing up to 300mm dia Quintal 3,530###S&S Centrifugally (Spun) C.I. Pipe Specials as per IS 1538 suitable

for lead jointing over 300mm dia Quintal 3,988

###S&S Centrifugally (Spun) C.I. Pipe specials suitable for mechanicaljoint as per I.S. 13382 up to 300mm dia Quintal 5,338

###S&S Centrifugally (Spun) C.I. Pipe Specials suitable for mechanicaljoint as per IS 13382 over 300mm dia Quintal 5,580

###Screwed double flanged centrifugally cast (spun) C.I. Pipe of Class Bconforming to I.S. 1536, - 100mm dia Metre 977

###Screwed double flanged centrifugally cast (spun) C.I. Pipe of Class Bconforming to I.S. 1536, - 150mm dia Metre 1,511

###Screwed double flanged centrifugally cast (spun) C.I. Pipe of Class Bconforming to I.S. 1536, - 200mm dia Metre 2,092

###Screwed double flanged centrifugally cast (spun) C.I. Pipe of Class Bconforming to I.S. 1536, - 250mm dia Metre 2,800

###Screwed double flanged centrifugally cast (spun) C.I. Pipe of Class Bconforming to I.S. 1536, - 300mm dia Metre 3,559

###Screwed double flanged centrifugally cast (spun) C.I. Pipe of Class Bconforming to I.S. 1536, - 350mm dia Metre 4,553

###Screwed double flanged centrifugally cast (spun) C.I. Pipe of Class Bconforming to I.S. 1536, - 400mm dia metre 5,885

###Screwed double flanged centrifugally cast (spun) C.I. Pipe of Class Bconforming to I.S. 1536, - 450mm dia Metre 7,627

###Screwed double flanged centrifugally cast (spun) C.I. Pipe of Class Bconforming to I.S. 1536, - 500mm dia metre 9,962

###Screwed double flanged centrifugally cast (spun) C.I. Pipe of Class Bconforming to I.S. 1536, - 600mm dia Metre 12,992

###Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - 100mm dia Metre 597

###Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - 150mm dia Metre 870###Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - 200mm dia Metre 1,237###Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - 250mm dia Metre 1,675###Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - 300mm dia Metre 2,369

41

Page 45: DAR_Vol_1

Co Description Unit RateNo Rs.

###Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - 350mm dia Metre 2,728###Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - 400mm dia Metre 3,256###Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - 450mm dia Metre 3,861###Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - 500mm dia Metre 4,557

###Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - 600mm dia metre 6,011###Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - 700mm dia Metre 7,463###Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - 800mm dia Metre 10,405

###Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - 900mm dia metre 12,798###Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - 1000mm di metre 15,505###Extruded burnt flyash clay sewer bricks conforming to I.S 4885 1000 Nos 3,550###Fly ash lime bricks (FALG Bricks) conforming to I.S. 12894-1989 1000 Nos 1,792

###Calcium Silicate Bricks machine moulded confirming to I.S. 4139 -1989 1000 Nos 3,083

###Modified Bitumen Refinery produced CRMB - 55 Tonne 26,000###Modified Bitumen Refinery produced CRMB - 60 tonne 26,300###Bitumen emulsion medium setting (M.S.) confirming to IS : 888 tonne 19,500

###Ceramic Glazed Tiles Ist quality minimum thickness 5mm in allcolours shades and designs except burgundy, bottle green, blac Sq.m. 268

###Ceramic Glazed Tiles Ist quality 300 x 300mm in all shades anddesigns of White, Ivory, grey, Fume Red brown etc. Sq.m. 320

###Ceramic Glazed Tiles Ist quality 300 x 300 in all shades designsexcept White, Ivory, Grey, Fume Red Brown etc. Sq.m. 347

###Rectified Ceramic Glazed Tiles Ist quality 300x 300 or more in all shades designs White, Ivory, Grey, Fume Red Brown etc. Sq.m. 462###Rectified Ceramic Glazed Tiles Ist quality 300 x 300 or more in all shades designs except White, Ivory, Grey, Fume Red Brow Sq.m. 496###Salem Stainless steel AISI - 304 (18/8) Orrisa pattern W.C. pan

724mm X 578mm each 3,350###Salem Stainless steel AISI - 304 (18/8) Round basin 405mm X

355mm each 1,500###Salem Stainless steel AISI - 304 (18/8) Wash basin 530mm X 3 each 1,350###Centrifugally cast (spun) iron S&S 100 mm inlet and 100 mm outeach 309###Centrifugally cast (spun) iron S&S 100 mm inlet and 75 mm outl each 334

###Agaria White marble slab plain 18mm thick sqm 1,000###P.T.M.T. Grating square slit 150mm each 70###P.T.M.T. Urinal cock 15mm dia each 90###P.T.M.T. Bib cock with nozzle 15mm each 110

###P.T.M.T. Stop cock (concealed) 15mm each 160

42Co Description Unit RateNo Rs.

Page 46: DAR_Vol_1

###15 mm nominal bore and 30 cm length PVC connection pipe withP.T.M.T. Nuts each 27

###15 mm nominal bore and 45 cm length PVC connection pipe withP.T.M.T. Nuts each 32

###P.T.M.T. extension nipple 15mm each 30

###P.T.M.T. extension nipple 20mm each 36###P.T.M.T. extension nipple 25mm each 54###Modular bricks of class designation 75 1000 Nos 2,050###Machine moulded perforated FPS bricks of class designation 1 1000 Nos 3,233

###Machine moulded modular perforated bricks of class designatio 1000 Nos 3,200###Machine moulded FPS bricks of class designation 125 1000 Nos 2,767###Machine moulded tile bricks of class designation 125 1000 Nos 2,717

###24 mm thick Factory made shutters with frame, rails and panels ofPVC extruded sections in white, grey or wooden finish sqm 1,830

###30 mm thick Factory made shutters with frame, rails and panels ofPVC extruded sections in white, grey or wooden finish sqm 1,900

###Factory made PVC rigid foam paneled shutter i/c carriage sqm 1,743###Factory made PVC rigid foam paneled shutter as per IS : 4020 i/c

carriage sqm 2,148###Factory made PVC rigid foam sheet 1mm thick sqm 145

###Factory made PVC rigid foam sheet 5mm thick sqm 558###Factory made prelaminated PVC rigid foam sheet 5mm thick sqm 660###48mmX40mmX1.5mm thick Factory made door frame of PVC

extruded sections in white, grey or wooden finish metre 112###Factory made door frame PVC extruded sheet i/c carriage metre 294

###Adhesive solvent cement kg 150###Powder coated M.S. butt hinges 100mm X58mmX1.9mm 10 Nos 66###A.P.P. modified polymeric felt (two layers) 1.5 mm thick sqm 50###A.P.P. modified polymeric felt (two layers) 2 mm thick sqm 85

###A.P.P. modified 2 mm thick membrane reinforced with glass fibrematt sqm 147

###A.P.P. modified 3 mm thick membrane reinforced with glass fibrematt sqm 185

###A.P.P. modified 3 mm thick membrane reinforced with polyestermatt sqm 221

###Bitumen primer for bitumen membrane litre 54###Geotextile 120 gsm membrane sqm 25

###Stainless steel screws 50 mm 100 Nos 213

43Co Description Unit RateNo Rs.

###Stainless steel screws 40 mm 100 Nos 157###Stainless steel screws 30 mm 100 Nos 98

###Stainless steel screws 20 mm 100 Nos 63

Page 47: DAR_Vol_1

###Stainless steel butt hinges 125x64x1.9 mm IS : 12817 marked 10 Nos 200###Stainless steel butt hinges 100x58x1.9 mm IS : 12817 marked 10 Nos 143###Stainless steel butt hinges 75x47x1.8 mm IS : 12817 marked 10 Nos 112

###Stainless steel butt hinges 50x37x1.5 mm IS : 12817 marked 10 Nos 90###Stainless steel butt hinges (heavy weight) 125x64x2.5 mm IS : 12817

marked 10 Nos 261###Stainless steel butt hinges (heavy weight) 100x60x2.5 mm IS : 12817

marked 10 Nos 185###Stainless steel butt hinges (heavy weight) 75x50x2.5 mm IS : 12817

marked 10 Nos 155###M.S. heavy weight but hinges 125x90x4.0mm IS : 1341 marked.10 Nos 256

###M.S. heavy weight butt hinges 100x75x3.5 mm IS: 1341 marke 10 Nos. 133###M.S. heavy weight butt hinges 75x60x3.1 mm IS: 1341 marked 10 Nos 67###M.S. heavy weight butt hinges 50x40x2.5 mm IS : 1341 marked 10 Nos 52

###1216 mm PE-AL-PE Composite pressure pipe Metre 79###1620 mm PE-AL-PE Composite pressure pipe Metre 97###2025 mm PE-AL-PE Composite pressure pipe Metre 126###2532 mm PE-AL-PE Composite pressure pipe Metre 172

###3240 mm PE-AL-PE Composite pressure pipe Metre 227###4050 mm PE-AL-PE Composite pressure pipe Metre 304###Polymer modified cementation coating kilogram 114

###Fibre glass cloth sqm 33###Multi surface paint litre 264###Acrylic exterior paint litre 123###Premium Acrylic exterior paint litre 202

###Textured exterior paint litre 183###Primer for cement paint litre 52###Special Primer (C.W.) litre 76

###Metal Primer (U.G.) litre 91###Main T ceiling sections 24x38x0.3 mm (3 metre long) each 162###Perimeter wall angle 21x21 mm (3 metre long) each 102###Intermediate cross channel (1.2 mtrs) each 62

44Co Description Unit RateNo Rs.

###Intermediate cross channel (1.6 mtrs) each 29

###Hanger rod 0.5 mm thick each 5###Adjustment clip each 4.4###Soffit cleat each 2.3###Dash fastener 6 mm dia 50 mm long each 8

###Vitrified floor tile 50x50 cm sqm 645###Vitrified floor tile 60x60 cm sqm 700###Vitrified floor tile 80x80 cm sqm 1,076

Page 48: DAR_Vol_1

###Vitrified floor tile 100x100 cm sqm 1,290###Poly propylene- Random - Co - Polymer (PPR) pipes SDR 7.4 - 16

Outer dia metre 29###Poly propylene - Random - Co - Polymer (PPR) pipes SDR 7.4 -

20mm Outer dia. metre 44###Poly propylene - Random - Co - polymer (PPR) pipes SDR 7.4 - 25

mm outer dia. metre 68###Poly propylene - Random - Co - poymer (PPR) pipes SDR 7.4 -

32 mm Outer dia. metre 111###Poly propylene - Random - Co - polymer (PPR) pipes SDR 7.4 -

40mm Outer dia. metre 176###Poly propylene - Random - Co - polymer (PPR) pipes SDR 7.4 -

50mm Outer dia. metre 257

###Poly propylene - Random - Co - polymer (PPR) pipes SDR 7.4 -63mm Outer dia. metre 400

###Poly propylene - Random - Co - polymer (PPR) pipes SDR 7.4 -75mm Outer dia. metre 575

###Poly propylene - Random - Co - polymer (PPR) pipes SDR 7.4 -90mm Outer dia. metre 917

###Poly propylene - Random - Co - polymer (PPR) pipes SDR - 11 -110mm Outer dia. metre 962

###Poly propylene - Random - Co - polymer (PPR) pipes SDR - 11-160mm Outer dia. metre 2,028

###Chlorinated Polyvinyl - chloride (CPVC) pipe 15 mm outer dia. metre 45

###Chlorinated Polyvinyl - chloride (CPVC) pipe 20 mm outer dia. metre 55###Chlorinated Polyvinyl - chloride (CPVC) pipe 25 mm outer dia. metre 78###Chlorinated Polyvinyl - chloride (CPVC) pipe 32 mm outer dia. metre 105###Chlorinated Polyvinyl - chloride (CPVC) pipe 40 mm outer dia. metre 150

###Chlorinated Polyvinyl - chloride (CPVC) pipe 50 mm outer dia. metre 245###Chlorinated Polyvinyl - chloride (CPVC) pipe 62.5mm inner dia. metre 783

45Co Description Unit RateNo Rs.

###Chlorinated Polyvinyl - chloride (CPVC) pipe 75 mm inner dia. metre 1,030

###Chlorinated Polyvinyl - chloride (CPVC) pipe 100 mm inner dia. metre 1,430###Chlorinated Polyvinyl - chloride (CPVC) pipe 150 mm inner dia. metre 2,490###Silicon sealant. cartridge 281###Stainless steal screws 30mm x4mm. cent 25

###Hermetically sealed double glazed unit made with 6mm thick clearfloat glass both side having 12 mm air gap. sqm 1,980

###Stainless steel (SS 304 grade) adjustable friction window stay. 205 x19mm each 145.6

###Stainless steel (SS 304 grade) adjustable friction window stay 255 x19mm each 161.2

###Stainless steel (SS 304 grade) adjustable friction window stay. 355 x19mm each 208

Page 49: DAR_Vol_1

###Stainless steel (SS 304 grade) adjustable friction window stay. 510 x19mm each 390

###Stainless steel (SS 304 grade) adjustable friction window stay. 710 x19mm each 715

###Masking tape. metre 1.4

###Autoclaved aerated cement (AAC) blocks. cum 1,650###Gypsum panel 666 X 500 X 100 mm size. sqm 544###Bonding plaster for Gypsum panel. kg 50

###Mechanised Autoclaved fly ash lime bricks. 1000 Nos 2,200###Water proof ply 12mm thick. sqm 572###Aluminium casement window fastener (Anodised AC 15 ) each 30###Aluminium casement window fastener (powder coated ). each 33

###Aluminium casement window fastener (polyester powder coatedeach 35###Aluminium round shape handle (anodised AC 15) each 37###Aluminium round shape handle (powder coated) each 41

###Aluminium round shape handle (polyester powder coated). each 43###Stainless steel screws 25mm x4mm cent 21###UV stabilised 2 mm thick plain FRP sheet . sqm 400

###UV stabilised 2 mm thick corrugated FRP sheet . sqm 474###Mangalore ridge tiles 20mm thick. each 25###Mangalore tiles 20mm thick. each 9.5###Precoated galvanised iron profile sheet 0.50 mm TCT sqm 325

###Precoated galvanised steel plain ridges. metre 330

46Co Description Unit RateNo Rs.

###Precoated galvanised steel flashings/aprons. metre 330###Precoated galvanised steel gutter metre 360###Precoated galvanised steel north light curves. metre 360

###Precoated galvanised steel barge board. metre 330###Precoated galvanised steel crimp curve sqm 420###1mm thick 35mm wide bright finished stainless steel piano hingmetre 30

###Red sand stone gang saw cut 30mm thick. sqm 325###White sand stone gang saw cut 30mm thick. sqm 360###Delineator each 560###Precast C.C. Kerb stone M - 25 cum 3,500

###Thermoplastic paint kg 67.22###Glass beads kg 68###Interlocking C.C. paver block ( 60 mm thick, M-30 ) sqm 225

###High intensity retro - reflective sheet. sqm 1,400###Punched tape concertina coil 600 m dia. 10m openable length (Total

Page 50: DAR_Vol_1

length 90m) bundle 650###RBT reinforced barbed wire. metre 7.5###Turn buckle and strengthening bolt. each set 35

###Precast pavement slab 450 x 450 x 50mm (M - 30). each 40###Chain link fabric fencing mesh of size 50x50mm made of G.I. wire of

dia. 4mm. sqm 225###Chain link fabric fencing mesh of size 50x50mm made of G.I. wire of

dia. 4mm, PVC coated to outer dia. 5mm. sqm 250###Chain link fabric fencing mesh of size 25x25mm made of G.I. wire of

dia. 3mm. sqm 300###Stainless steel cramps with nuts, bolts and washer for dry stone

cladding . each 200###8 mm thick tapered edge calcium silicate board . sqm 194

###10 mm thick calcium silicate board. sqm 323###Telescopic drawer channels 300mm long . set 92###Stainless steel roller for sliding arrangement in racks/ cupboards/

cabinets shutter . each 5###50mmX42mmX2mm thick Factory made door frame of PVC extruded

sections in white, grey or wooden finish metre 117

###25mm thick factory made PVC flush door shutter i/c carriage. sqm 1,975###Factory made glass reinforced plastic door frame 90x45 mm i/c

carriage. metre 333###30 mm thick factory made glass fiber reinforced plastic panel door

shutter i/c carriage. sqm 1,580

47Co Description Unit RateNo Rs.

###Factory made solid PVC door frame 60 x 30mm i/c carriage. metre 223###28mm factory made solid PVC panel door shutter i/c carriage. sqm 1,975###Fiber glass reinforced plastic chajja. sqm 3,520

###Magnetic catcher triple strip vertical type. each 13.5###Magnetic catcher double strip horizontal type. each 10###100 mm mortice lock with 6 levers for aluminium door. each 152.5

###12.5 mm thick Glass fibre reinforced Gypsum board . sqm 130###2nd class teak wood lipping/ moulded beading or Taj beading of size

18X5mm metre 19###Ceiling sections 0.55 mm thick having a knurled web of 51.55mm and

two flanges of 26mm each with lips of 10.55mm. metre 34###Perimeter channel having one flange of 20mm and another flange of

30mm with thickness of 0.55mm and web of length 27mm. metre 20###Nylon sleeves & wooden screws (40mm) each 1.5

###Counter sunk ribbed head screw 25mm. cent 60###12mm thick marine plywood conforming to IS:710 sqm 740###12mm thick fire retardant plywood conforming to IS: 5509. sqm 690###1.5mm thick decorative laminated sheet sqm 405

Page 51: DAR_Vol_1

###1.0mm thick decorative laminated sheet sqm 330###30 mm thick factory made glass fiber reinforced plastic flush door

shutter i/c carriage. sqm 1,960###High polymer modified quickset tile adhesive. per kg 13.75###Sundries L.S. 1

48BASIC RATES0.4 CARRIAGE CODES

(Carriage by Mechanical Transport including loading, Unloading and stacking)Note: - These rates are exclusive of contractor’s profit and overhead charges.

Co Description Unit RateNo Rs.

###Steam coal tonne 60.81###Bricks 1000 Nos 141.88###Stone aggregate below 40 mm nominal size cum 53.21###Coarse sand cum 53.21

###Timber cum 60.81###Steel tonne 47.29###Stone aggregate 40 mm nominal size and above cum 57.83

###Brick tiles 1000 Nos 85.13###Lime cum 53.21###Cement tonne 47.29

###Tar bitumen tonne 53.21###Soling stone & masonry stone cum 62.6###Stone blocks white & red sand stone & kota stone slab tonne 47.29###S.W. pipes100 mm dia 100 metre 70.94

###S.W. pipes150 mm dia 100 metre 141.88###S.W. pipes200 mm dia 100 metre 236.47###S.W. pipes230 mm dia 100 metre 337.82###S.W. pipes250 mm dia 100 metre 405.38

###S.W. pipes300 mm dia 100 metre 506.73###Good earth cum 66.51###Dump manure cum 57.83

###Brick aggregate cum 57.83###Fine sand (1 part badarpur sand : 2 parts jamuna sand) cum 53.21###Fly ash cum 53.21

###Rubbish cum 53.21###Moorum cum 53.21###Surkhi cum 53.21

Page 52: DAR_Vol_1

49Co Description Unit RateNo Rs.

###Stone dust cum 53.21###Marble dust and marble chips cum 53.21

###G.I. pipes below 100 mm dia tonne 47.29###A.C.sheet and accessories tonne 47.29###R.C.C. pipes 100 mm dia 100 metre 116.3###R.C.C. pipes 150 mm dia 100 metre 193.83

###R.C.C. pipes 250 mm dia 100 metre 448.05###R.C.C. pipes 300 mm dia 100 metre 553.8###R.C.C. pipes 450 & 500 mm dia 100 metre 1,292.2

###G.I.sheet and accessories tonne 47.29###R.C.C. pipes 600, 700, 750 & 800 mm dia 100 metre 1,938.3###Plaster of paris tonne 47.29###Cast iron fittings tonne 47.29

###Red bajri cum 53.21###Barbed wire tonne 47.29###Sludge cum 57.83

###Spun iron S & S pipes 100 mm dia 100 metre 116.3###Spun iron S & S pipes 125 mm dia 100 metre 155.35###Spun iron S & S pipes 150 mm dia 100 metre 193.83###Spun iron S & S pipes 200 mm dia 100 metre 315.3

###Spun iron S & S pipes 250 mm dia 100 metre 448.05###Spun iron S & S pipes 300 mm dia 100 metre 553.8###Spun iron S & S pipes 350 mm dia 100 metre 775.32

###Spun iron S & S pipes 400 mm dia 100 metre 1,057.26###Spun iron S & S pipes 450 mm dia 100 metre 1,292.2###Spun iron S & S pipes 500 mm dia 100 metre 1,292.2###Spun iron S & S pipes 600mm dia 100 metre 1,938.3

###C.I. pipes 500 mm dia 100 metre 1,292.2###R.C.C. pipes 900 mm dia 100 metre 2,907.45###R.C.C. pipes 1000 mm dia 100 metre 3,876.61

###R.C.C. pipes 1100 mm dia 100 metre 3,876.61###R.C.C. pipes 1200 mm dia 100 metre 3,876.61

50

Page 53: DAR_Vol_1

Co Description Unit RateNo Rs.

###Jamuna sand cum 53.21###Pig lead tonne 47.29

###Solvent/ Diesel. quintal 5.32###Ductile iron pipes (k7) 100 mm dia 100 metre 116.3###Cast iron pipes 150 mm dia 100 metre 193.83###Cast iron pipes 200 mm dia 100 metre 315.3

###Cast iron pipes 250 mm dia 100 metre 448.05###Cast iron pipes 300 mm dia 100 metre 553.8###Cast iron pipes 350 mm dia 100 metre 775.32

###Cast iron pipes 400 mm dia 100 metre 1,057.26###Cast iron pipes 450 mm dia 100 metre 1,292.2###Cast iron pipes 500 mm dia 100 metre 1,292.2###Cast iron pipes 600 mm dia 100 metre 1,938.3

###Cast iron pipes 700 mm dia 100 metre 1,938.3###Cast iron pipes 800 mm dia 100 metre 1,938.3###Cast iron pipes 900 mm dia 100 metre 2,907.45

###Cast iron pipes 1000 mm dia 100 metre 3,876.61

51

Page 54: DAR_Vol_1

SUB HEAD : 1.0

CARRIAGE OF MATERIALS

531.0 Carriage of Materials

Data Sheet No 1 for Analysis of Rates

1.1 By Mechanical Transport including loading, unloading and stacking:

Code Material Name Unit5 Hire Charges of truck Day114 Beldar Day115 Coolie Day1235 High Speed Diesel Litre5001 Mobil Oil Litre

Lead Ave- Nos of Nos of Litres of Cost of Litres of Cost of Cost ofin km rage Trips km Diesel Diesel Mobil oil Mobil oil 6 Beldars

speed N=8/ Done consum -1235 consumed -5001 -114(2L/S)+1 in one ed @ Rs per @ 140 km @ Rs per @ Rs per

Day @ 5 km Litre per Litre Litre Day(2NL+6) per Litre

1 2 3 4 5 6 7 8 91 Km 16.00 Km 7.11 20.22 4.04 122.21 .144 13.68 811.52 Km 17.00 Km 6.48 31.92 6.38 193 .228 21.66 811.53 Km 17.50 Km 5.96 41.76 8.35 252.59 .298 28.31 811.54 Km 18.00 Km 5.54 50.32 10.06 304.32 .359 34.11 811.55 Km 18.50 Km 5.19 57.9 11.58 350.3 .414 39.33 811.56 Km 19.00 Km 4.9 64.8 12.96 392.04 .463 43.99 811.57 Km 19.50 Km 4.66 71.24 14.25 431.06 .509 48.36 811.58 Km 20.00 Km 4.44 77.04 15.41 466.15 .55 52.25 811.59 Km 20.50 Km 4.26 82.68 16.54 500.34 .591 56.15 811.510Km 21.00 Km 4.1 88 17.6 532.4 .629 59.76 811.511Km 21.50 Km 3.95 92.9 18.58 562.05 .664 63.08 811.512Km 22.00 Km 3.83 97.92 19.58 592.3 .699 66.41 811.513Km 22.50 Km 3.71 102.46 20.49 619.82 .732 69.54 811.514Km 23.00 Km 3.61 107.08 21.42 647.96 .765 72.68 811.515Km 23.50 Km 3.51 111.3 22.26 673.37 .795 75.53 811.516Km 24.00 Km 3.43 115.76 23.15 700.29 .827 78.57 811.517Km 24.50 Km 3.35 119.9 23.98 725.4 .856 81.32 811.518Km 25.00 Km 3.28 124.08 24.82 750.81 .886 84.17 811.519Km 25.50 Km 3.21 127.98 25.6 774.4 .914 86.83 811.520Km 26.00 Km 3.15 132 26.4 798.6 .943 89.59 811.5

54

1 2 3 4 5 6 7

21 Km 26.5 Km 3.09 135.78 27.16 821.59 .9722 Km 27 Km 3.04 139.76 27.95 845.49 .99823 Km 27.5 Km 2.99 143.54 28.71 868.48 1.02524 Km 28 Km 2.95 147.6 29.52 892.98 1.05425 Km 28.5 Km 2.9 151 30.2 913.55 1.07926 Km 29 Km 2.86 154.72 30.94 935.94 1.105

Page 55: DAR_Vol_1

27 Km 29.5 Km 2.83 158.82 31.76 960.74 1.13428 Km 30.00 Km 2.79 162.24 32.45 981.61 1.15929 Km 30.50 Km 2.76 166.08 33.22 1,004.91 1.18630 Km 31.00 Km 2.73 169.8 33.96 1,027.29 1.213Notes

81. Number of trips in working day of 8 hours N= where L= Load in km., S= Speed in km per hour, 1 hour is allowed for loading /unloading.

2L + 12. Consumption of diesel taken at 5 km per litre s3. Consumption of mobile oil taken at 140 km per litre.4. In column 4 of ‘km done’ an allowance of 6.0 km has been made for movement of truck from parking place to duty & back.5. (i) Cost of disel @ (12 35) per litre

(ii) Cost of moble oil @ (5001) per litre(iii) Hire charges of truck @ (0005) for a day of 8 hours.

55

1.0 Carriage of Materials

1.1 By Mechanical Transport

C.P. &S.No Material capacity Net Qty Unit Over Cost per Trip per unit

per Trip Payable of heads 1km 2km 3kmafter rates @ 15%dedu-ctionforloose- Cost per Trip as per Col. 12 of Data sheetness Net Qty Payable

1 2 3 4 5 6 7 8 9

1.1.1 Lime, moorum8 8 cum 1,500% 39.53 45.13 55.99rubbish

1.1.2 Earth 8 6.4 cum 1,500% 49.42 56.41 69.991.1.3 Manure or sl 8 7.36 cum 1,500% 42.97 49.05 60.861.1.4 Excavated ro 8 4 cum 1,500% 79.07 90.25 111.991.1.5 Sand, stone 8 8 cum 1,500% 39.53 45.13 55.99

below 40 mm nominal size1.1.6 Stone aggreg 8 7.36 cum 1,500% 42.97 49.05 60.86

nominal size and above1.1.7 Soling stone 8 6.8 cum 1,500% 46.51 53.09 65.871.1.8 Bricks 3000 3000 1000 1,500% 105.42 120.33 149.32

Nos1.1.9 Brick Tiles 5000 5000 1000 1,500% 63.25 72.2 89.59

Nos1.1.10 Cement, ston9 9 tonne 1,500% 35.14 40.11 49.77

G.I.. C.I., A.C., & C.C.pipes below 100 mm diaand other heavy materials

1.1.11 Steel 9 9 tonne 1,500% 35.14 40.11 49.771.1.12 Timber 7 7 cum 1,500% 45.18 51.57 63.99

56

Page 56: DAR_Vol_1

1 2 3 4 5 6 7 81.1.13 Tar bitumen 8 8 tonne 1,500% 39.53 45.131.1.14 Solvent 80 80 qtl 1,500% 3.95 4.511.1.15 Steam coal 7 7 tonne 1,500% 45.18 51.571.1.16 S.W. pipe1.1.16.1 100 mm dia 600 600 100 m 1,500% 52.71 60.171.1.16.2 150 mm dia 300 300 100 m 1,500% 105.42 120.331.1.16.3 200 mm dia 180 180 100 m 1,500% 175.71 200.561.1.16.4 230 mm dia 126 126 100 m 1,500% 251.01 286.511.1.16.5 250 mm dia 105 105 100 m 1,500% 301.21 343.811.1.16.6 300 mm dia 84 84 100 m 1,500% 376.52 429.761.1.16.7 350 mm dia 60 60 100 m 1,500% 527.12 601.671.1.16.8 400 mm dia 42 42 100 m 1,500% 753.03 859.531.1.16.9 450 mm dia 33 33 100 m 1,500% 958.4 1,093.941.1.16.10 500 mm dia 30 30 100 m 15% 1054.24 1,203.341.1.16.11 600 mm dia 24 24 100 m 15% 1317.80 1,504.171.1.17 R.C.C. pipes, A.C. pipes,

steel cylinder, R.C. pipes,C.I. pipes, C.I. pipes andunreinforced cement pipes

1.1.17.1 100 mm dia 366 366 100 m 1,500% 86.41 98.631.1.17.2 125 mm dia 274 274 100 m 1,500% 115.43 131.751.1.17.3 150 mm dia 219.6 219.6 100 m 1,500% 144.02 164.391.1.17.4 200 mm dia 135 135 100 m 1,500% 234.28 267.411.1.17.5 250 mm dia 95 95 100 m 1,500% 332.92 3801.1.17.6 300 mm dia 76.86 76.86 100 m 1,500% 411.49 469.691.1.17.7 350 mm dia 54.9 54.9 100 m 1,500% 576.09 657.561.1.17.8 400 mm dia 40.26 40.26 100 m 1,500% 785.58 896.671.1.17.9 450 mm & 500 mm dia 32.94 32.94 100 m 1,500% 960.15 1,095.931.1.17.10 600, 700, 750 & 800 m 21.96 21.96 100 m 15% 1440.22 1,643.91.1.17.11 900 mm dia 14.64 14.64 100 m 15% 2160.33 2,465.851.1.17.12 1000, 1100 & 1200 mm 10.98 10.98 100 m 15% 2880.44 3,287.8

dia

571.0 Carriage of Materials

1.2 By Manual Labour including loading, unloading and stacking for lead less than 0.5 KMData Sheet for Analysis of Rates

Code Name Unit Rate114 Beldar Day 135.25115 Coolie Day 135.25

The following labour work for 8 hours a day will carry following material upto 1st 50 m as given below :0114/0115 Beldars (Male/ Female) 7 .67 Nos @ Rs 135.25 1037.37 (X)

1 Lime, mooram, earth, building rubbish etc. 35 cum2 Sand, ballast and boulders 28 cum3 Bricks 15000 nos4 Brick Tiles, Allabad roofing tiles (Flat or round) 24000 nos5 Steam coal 30 tonnes

NOTE : 1.67 extra coolie (Female coolie) will be required forevery additional lead of 50 M0115 Coolie 1.67 Nos @ Rs 135.25 225.87 (Y)

Page 57: DAR_Vol_1

Lead Cost per 8 hours dayIncrease in cost forin Metres every additional 50 metre

or part thereof

(X) (Y)50 metre 1,037.37 225.87

S. No Material Capacity Net Qty Unit of C.P. & Cost per Cost per unitper Trip to be pai Rates Over 8 hours cost for

after dedu- heads day 1st 50ction for @ 15% metreslooseness

(X)1 2 3 4 5 6 7 81.2.1 Lime, mooram buildi 35 cum 35 cum 1 cum 1,500% 1,192.97 34.08

rubbish1.2.2 Earth 35 cum 28 cum 1 cum 1,500% 1,192.97 42.611.2.3 Manure or sludge 35 cum 32.2 cum1 cum 1,500% 1,192.97 37.051.2.4 Excavated rock 35 cum 17.5 cum1 cum 1,500% 1,192.97 68.171.2.5 Sand, stone aggregat 28 cum 28 cum 1 cum 1,500% 1,192.97 42.61

below 40 mm nominalsize

1.2.6 Stone aggregate 40 mm 28 cum 25.9 cum1 cum 1,500% 1,192.97 46.06nominal size and above

1.2.7 Soling stone 28 cum 23.8 cum1 cum 1,500% 1,192.97 50.121.2.8 Bricks 15000 Nos 15000 Nos 1000 Nos 15% 1,192.97 79.531.2.9 Brick Tiles, Allahabad24000 Nos 24000 Nos 1000 Nos 15% 1,192.97 49.71

roofing tiles (Flat orround)

1.2.10 Steam coal 30 tonne 30 tonne 1 tonne 1,500% 1,192.97 39.77

581.0 Carriage of Materials

1.2 Carraige of material by Manual Labour including loading, unloading and stacking for lead lessthen 0.5 KM.

Data Sheet for Analysis of Rates

Code Material Name Unit Rate114 Beldar Day 135.25115 Coolie Day 135.25

The following labour works for 8 hours a day and will carry following material as given below:

###Beldars 9.2 Nos @ 135. = 1244.30 (X)Quantity of material as per column 3 of table below will be carried in 50 metres lead including loading andunloadingNotes: 1.35 extra Beldar will be required for every additional

lead of 50 m 1.35 Beldar @ 135.25 = 182.59 (Y)

C.P.&

Page 58: DAR_Vol_1

S. Material Capacity Net Qty Unit of Over Cost per Cost per unitper Trip to be paid Rates head 8 hours cost for cost for

after dedu- @ 15% day 1st 50 addl. 50ction for metres m or partlooseness thereof

stbeyond 150 m upto0.5 km

1 2 3 4 5 6 7 8 91.2 Stone blocks, G.I., 46 t 46 t 1 tonne 15% 1,430.95 31.11 4.56

C.I.pipes below 100 mmdia and other heavymaterials

1.2 Cement 57.99 t 57.99 t 1 cum 1,500% 1,430.95 24.68 3.621.2 Steel 27 t 27 t 1 tonne 15% 1,430.95 53 7.781.2 Timber 42 cum 42 cum 1 cum 1,500% 1,430.95 34.07 51.2 Tar bitumen etc 46 t 46 t 1 tonne 15% 1,430.95 31.11 4.561.2 S.W. pipe1.2 100 mm dia 2298 m 2298 m 100 m 1,500% 1,430.95 62.27 9.141.2 150 mm dia 1398 m 1398 m 100 m 1,500% 1,430.95 102.36 15.021.2 200 mm dia 999 m 999 m 100 m 1,500% 1,430.95 143.24 21.021.2 230 mm dia 780 m 780 m 100 m 1,500% 1,430.95 183.45 26.921.2 250 mm dia 600 m 600 m 100 m 1,500% 1,430.95 238.49 351.2 300 mm dia 420 m 420 m 100 m 1,500% 1,430.95 340.7 49.991.2 350 mm dia 300 m 300 m 100 m 1,500% 1,430.95 476.98 69.991.2 400 mm dia 240 m 240 m 100 m 1,500% 1,430.95 596.23 87.491.2 450 mm dia 198 m 198 m 100 m 1,500% 1,430.95 722.7 106.051.2 500 mm dia 162 m 162 m 100 m 1,500% 1,430.95 883.3 129.611.2 600 mm dia 132 m 132 m 100 m 1,500% 1430.95 1084.05 159.071.2 R.C.C. pipes, steel

cylinder, R.C. pipes, C.I.pipes, and unrein-forcedcement pipes

1.2 100 mm dia 1702 m 1702 m 100 m 1,500% 1,430.95 84.07 12.341.2 125 mm dia 1391 m 1391 m 100 m 1,500% 1,430.95 102.87 15.11.2 150 mm dia 1208 m 1208 m 100 m 1,500% 1,430.95 118.46 17.381.2 200 mm dia 805 m 805 m 100 m 1,500% 1,430.95 177.76 26.08

591 2 3 4 5 6 7 8 91.2 250 mm dia 458 m 458 m 100 m 1,500% 1,430.95 312.43 45.851.2 300 mm dia 366 m 366 m 100 m 1,500% 1,430.95 390.97 57.371.2 350 mm dia 256 m 256 m 100 m 1,500% 1,430.95 558.96 82.021.2 400 mm dia 220 m 220 m 100 m 1,500% 1,430.95 650.43 95.441.2 450 mm dia & 500 mm 165 m 165 m 100 m 1,500% 1,430.95 867.24 127.261.2 600, 700, 750 & 800 mm dia 150 150 m 100 m 1,500% 1,430.95 953.96 139.981.2 Asbestors cement pipes1.2 50 mm dia 10064 m 10064 m 100 m 1,500% 1,430.95 14.22 2.091.2 80 mm dia 3660 m 3660 m 100 m 1,500% 1,430.95 39.1 5.741.2 100 mm dia 2562 m 2562 m 100 m 1,500% 1,430.95 55.85 8.21.2 150 mm dia 1830 m 1830 m 100 m 1,500% 1,430.95 78.19 11.47

Page 59: DAR_Vol_1

61

SUB HEAD : 2.0

EARTH WORK

632.1Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in

width as well as 10 sqm on plan including disposal of excavated earth upto 50 m and liftupto 1.5 m, disposed soil to be levelled and neatly dressed:

2.1All Kinds of soilCodDescription Unit Quantity Rate Amount

Details of cost for 100 sqm. and averagedepth 15cm.Labour-

###Beldars Day 7.2 135.25 973.8###Coolies Day 6 135.25 811.5

TOTAL 1 785.30Add I % for water charges 17.85TOTAL 1 803.15Add 15% for contractor’s profit and overheads 270.47

Page 60: DAR_Vol_1

Cost of 100 sqm. 2 073.62Say 2 073.60

2.2Earth work in rough excavation, banking excavated earth in layers not exceeding 20cm in depth, breaking clods watering, rolling each layer with ½ tonne roller or woodenor steel rammers, and rolling every 3rd and top-most layer with power roller of minimum8 tonnes and dressing up in embankments for roads, flood banks, marginal banks andguide banks or filling up ground depressions, lead upto 50 m and lift upto 1.5 m :

2.2All kinds of soil

CodDescription Unit Quantity Rate Amount

Details of cost for 10 cum.Labour-

###Beldars Day 5.9 135.25 797.98###Coolies Day 3.6 135.25 486.9###Bhishti Day .4 138.45 55.38###Chokidar Day .008 135.25 1.08

Roller charges (one roller does 1850 sqm. ofconsolidation per day)

3 Hire Charges Day 0.008 1000.00 8###Diesel litre .144 30.25 4.36###Carriage of diesel quintal .0014 5.32 .01###Sundries L.S. 2.73 1 2.73

TOTAL 1 356.44Add 1 % for water charges 13.56TOTAL 1 370.00Add 15% for contractor’s profit and overheads 205.5Cost of 10 cum. 1 575.50Cost of 1 cum. 157.55Say 157.55

642.3Banking excavated earth in layers not exceeding 20 cm. in depth, breaking clods,

watering, rolling each layer with ½ tonne roller, or wooden or steel rammers, and rollingevery 3rd and top-most layer with power roller of minimum 8 tonnes and dressing up, inembankments for roads, flood banks, marginal banks, and guide banks etc., lead upto50 m and lift upto 1.5 m.

2.3All kinds of soilCodDescription Unit Quantity Rate Amount

Detais of cost for 10 cum.Labour-

###Beldars Day 2.2 135.25 297.55###Coolies Day 3.6 135.5 486.9###Bhishti Day .4 138.45 55.38

Roller charges (one roller does 1850 sqmof consolidation per day)

3 Hire Charges Day .008 1,000 8###Chokidar Day .008 135.25 1.08###Diesel litre .144 30.25 4.36###Carriage of diesel quintal .0014 5.32 .01

Page 61: DAR_Vol_1

###Sundries L.S. 2.73 1 2.73TOTAL 856.01Add 1% for water charges 8.56TOTAL 864.57Add 15% for contractor’s profit andoverheads 129.69Cost of 10 cum. 994.26Cost of 1 cum. 99.43Say 99.45

### Deduct for not rolling with power roller of minimum 8 tonnes for banking excavatedearth in layers not exceeding 20 cm in depth.

CodDescription Unit Quantity Rate AmountDetails of cost for 10 cum.Labour-

###Chokidar Day .008 135.25 1.083 Roller charges & Hire Charges Day .008 1,000 8###Diesel litre .144 30.25 4.36###Carriage of diesel quintal .0014 5.32 .01###Sundries L.S. 1.82 1 1.82

TOTAL 15.27Add 1 % for water charges .15TOTAL 15.42Add 15% for contractor’s profit andoverheads 2.31Cost of 10 cum. 17.73Cost of 1 cum. 1.77Say 1.75

65### Deduct for not watering the excavated earth for banking

CodDescription Unit Quantity Rate Amount

Details of cost for 10 cum.Labour-

###Bhishti Day 0.4O 138.45 55.38TOTAL 55.38Add 1% for water charges .55TOTAL 55.93Add 15% for contractor’s profit andoverheads 8.39Cost of 10 cum. 64.32Cost of 1 cum. 6.43Say 6.45

### Earth work in excavation by mechanical means (Hydraulic excavator)/ manual meansover areas (exceeding 30cm in depth. 1.5m in width as well as 10 sqm on plan) includingdisposal of excavated earth, lead upto 50m and lift upto 1.5m, disposed earth to belevelled and neatly dressed.

2.6All kinds of soilCodDescription Unit Quantity Rate Amount

Details of cost for 10 cum.Average output of Hydraulic Excavator perhour = 30cum.

Page 62: DAR_Vol_1

MACHINERY20 Hydraulic Excavator (3D) with driver and fueDay .04125 6,000 247.518 Hire and running charges of loader. Day .04125 800 33

Labour-###Mate Day 0.40 138.45 55.38###Beldar/Coolies Day 4.00 135.25 541

TOTAL 876.88Add 1 % for water charges 8.77TOTAL 885.65Add 15% for contractor’s profit and overheads 132.85Cost of 10 cum. 1,018.5Cost of 1 cum. 101.85Say 101.85

### Earth work in excavation/ by mechanical means (Hydraulic Excavator)/ manual meansover areas (exceeding 30 cm in depth, 1.5m in width as well as-10 sqm on plan) includingdisposal of excavated earth, lead upto 50 m and lift upto 1.5 m, disposed earth to belevelled and neatly dressed.

2.7Ordinary rockCodDescription Unit Quantity Rate Amount

Details of cost for 10 cum.MACHINERY

20 Hydraulic Excavator (3D) with dri Day .0625 6 000.00 375fuel.

17 Hire and running charges of tippeDay .0625 1 030.00 64.38###Excavators Day 0.705 135.25 95.35###Breakers Day 1.59 135.25 215.05###Hole driller Day 0.355 135.25 48.01

66CodDescription Unit Quantity Rate Amount###Beldars Day 1.415 135.25 191.38###Coolies Day 2.32 135.25 313.78###Sundries L.S. 10.79 1.00 10.79

TOTAL 1 313.74Add 1% for water charges 13.14TOTAL 1 326.88Add 15% for contractor’s profit and overheads 199.03Cost of 10 cum. 1 525.91Cost of 1 cum. 152.59Say 152.6

2.7 Earth work in excavation/ by mechanical means (Hydraulic Excavator)/ manual meansover areas (exceeding 30 cm in depth, 1.5m in width as well as 10 sqm on plan) includingdisposal of excavated earth, lead upto 50 m and lift upto 1.5 m, disposed earth to belevelled and neatly dressed.

2.7Hard rock (requiring blasting)

CodDescription Unit Quantity Rate Amount

Details of cost for 10 cum.Machinery

20 Hydraulic Excavator (3D) with driver and Day .125 6 000.00 750fuel.

Page 63: DAR_Vol_1

17 Hire and running charges of tipper Day .125 1 030.00 128.75###Excavators Day 1.06 135.25 143.36###Breakers Day 2.825 135.25 382.08###Hole driller Day .885 135.25 119.7###Beldars Day 1.325 135.25 179.21###Coolies Day 2.32 135.25 313.78###Powder kilogram 3.93 25.00 98.25###Fuse each 4.00 10.00 40###Sundries L.S. 16.12 1.00 16.12

TOTAL 2 171.25Add 1 % for water charges 21.71TOTAL 2 192.96Add 15% for contractor’s profit and overheads 328.94Cost of 10 cum. 2 521.90Cost of 1 cum. 252.19Say 252.2

2.7 Earth work in excavation/ by mechanical means (Hydraulic Excavator)/ manual meansover areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) includingdisposal of excavated earth, lead upto 50 m and lift upto 1.5 m, disposed earth to belevelled and neatly dressed.

2.7Hard rock (blasting prohibited)CodDescription Unit Quantity Rate Amount

Details of cost for 10 cum.MACHINERY

20 Hydraulic Excavator (3D) with driver and fuel. Day .125 6 000.00 75017 Hire and running charges of tippeDay .125 1 030.00 128.75###Excavators Day 2.47 135.25 334.07###Breakers Day 6 135.25 811.5

67CodDescription Unit Quantity Rate Amount###Chisellers Day 1.06 138.45 146.76###Black smith II class Day .175 141.6 24.78###Beldars Day 1.5 135.25 202.88###Coolies Day 2.85 135.25 385.46###Sundries L.S. 16.12 1 16.12

TOTAL 2 800.32Add 1% for water charges 28TOTAL 2 828.32Add 15% for contractor’s profit and overheads 424.25Cost of 10 cum. 3 252.57Cost of 1 cum. 325.26Say 325.25

### Earth work in excavation by mechanical means (Hydraulic Excavator )/ manual meansin foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan)including dressing of sides and ramming of bottoms, lift upto 1.5 m, including gettingout the excavated soil and disposal of surplus excavated soil as directed, within a leadof 50 m.

2.8All kinds of soil.CodDescription Unit Quantity Rate Amount

Details of cost for 10 cum.

Page 64: DAR_Vol_1

MACHINERY20 Hydraulic Excavator (3D) with dri Day .04125 6 000.00 247.518 Hire and running charges of loadeDay .04125 800 33

Labour-###Mate Day .4 138.45 55.38###Beldars/Coolies Day 4.1 135.25 554.52

TOTAL 890.4Add 1% for water charges 8.9TOTAL 899.3Add 15% for contractor’s profit and overheads 134.9Cost of 10 cum. 1,034.2Cost of 1 cum. 103.42Say 103.4

### Excavation work by mechanical means (Hydraulic Excavator)/ manual means infoundation trenches or drains not exceeding 1.5 m in width or 10 sqm on plan includingdressing of sides and ramming of bottoms lift upto 1.5 m, including getting out theexcavated soil and disposal of surplus excavated soils as directed, within a lead of 50m.

2.9Ordinary rockCodDescription Unit Quantity Rate Amount

“Details of cost for 10 cum.MACHINERY

20 Hydraulic Excavator (3D) with dri Day .0625 6 000.00 375fuel.

17 Hire and running charges of tippeDay .0625 1 030.00 64.38Labour-

###Excavators Day .885 135.25 119.7###Breakers Day 1.765 135.25 238.72###Hole driller Day .53 135.25 71.68

68CodDescription Unit Quantity Rate Amount###Beldars Day 1.415 135.25 191.38###Coolies Day 2.41 135.25 325.95###Sundries L.S. 13.52 1 13.52

TOTAL 1 400.33Add 1 % for water charges 14TOTAL 1 414.33Add 15% for contractor’s profit and overheads 212.15Cost of 10 cum. 1 626.48Cost of 1 cum. 162.65Say 162.65

### Excavation work by mechanical means (Hydraulic Excavator)/ manual means infoundation trenches or drains not exceeding 1.5 m in width or 10 sqm on plan includingdressing of sides and ramming of bottoms lift upto 1.5 m, including getting out theexcavated soil and disposal of surplus excavated soils as directed, within a lead of 50m.

2.9Hard rock (requiring blasting)CodDescription Unit Quantity Rate Amount

Details of cost for 10 cum.MACHINERY

20 Hydraulic Excavator (3D) with dri Day .125 6 000.00 750fuel.

17 Hire and running charges of tippeDay .125 1 030.00 128.75

Page 65: DAR_Vol_1

Labour-###Excavators Day 1.24 135.25 167.71###Breakers Day 3 135.25 405.75###Hole driller Day 1.06 135.25 143.36###Beldars Day 1.325 135.25 179.21###Coolies Day 2.41 135.25 325.95###Powder kilogram 6.42 25 160.5###Fuse each 7 10 70###Sundries L.S. 18.85 1 18.85

TOTAL 2 350.08Add 1 % for water charges 23.5TOTAL 2 373.58Add 15% for contractor’s profit and overheads 356.04Cost of 10 cum. 2 729.62Cost of 1 cum. 272.96Say 272.95

### Excavation work by mechanical means (Hydraulic Excavator)/ manual means infoundation trenches or drains not exceeding 1.5 m in width or 10 sqm on plan includingdressing of sides and ramming of bottoms lift upto 1.5 m, including getting out theexcavated soil and disposal of surplus excavated soils as directed, within a lead of 50m.

2.9Hard rock (blasting prohibited)CodDescription Unit Quantity Rate Amount

Details of cost for 10 cum.MACHINERY

20 Hydraulic Excavator (3D) with dri Day .125 6 000.00 750fuel.

17 Hire and running charges of tippeDay .125 1 030.00 128.75Labour-

69CodDescription Unit Quantity Rate Amount###Excavators Day 2.65 135.25 358.41###Breakers Day 6.175 135.25 835.17###Chisellers Day 1.06 138.45 146.76###Black smith II class Day .175 141.6 24.78###Beldars Day 1.5 135.25 202.88###Coolies Day 2.94 135.25 397.64###Sundries L.S. 17.94 1 17.94

TOTAL 2 862.33Add 1 % for water charges 28.62TOTAL 2 890.95Add 15% for contractor’s profit and overheads 433.64Cost of 10 cum. 3 324.59Cost of 1 cum. 332.46Say 332.45

2.10 Excavating trenches of required width for pipes, cables, etc including excavation forsockets and dressing of sides, ramming of bottoms, depth upto 1.5 m including gettingout the excavated soil and then returning the soil as required, in layers not exceeding 20cm in depth including consolidating each deposited layer by ramming, watering, etc.and disposing of surplus excavated soil as directed, within a lead of 50 m :

2.1All kinds of soil

Page 66: DAR_Vol_1

2.10.1.1 Pipes, cables etc, not exceeding 80 mm dia.CodDescription Unit Quantity Rate Amount

Details of cost for 180m length of a pipe of anaverage dia. say 40mm.Slope assumed 1 in 200.Earth work and filling-Minimum depth of trench 60cm.Average depth = (0.6+1.50)/2 = 1.05Width for this depth 0.45 cm180x0.45xl.05 = 85.05 cumRate vide item no. 2.8.1 cum 85.05 103.4 8 794.17Rate vide item no. 2.25 cum 85.05 45.7 3 886.78TOTAL 12 680.95Cost of 180m length of pipes 12 680.95Cost for lm. length of pipe 70.45Say 70.45

### Excavating trenches of required width for pipes, cables, etc including excavation forsockets and dressing of sides, ramming of bottoms, depth upto 1.5 m including gettingout the excavated soil and then returning the soil as required, in layers not exceeding20 cm in depth including consolidating each deposited layer by ramming, watering, etc.and disposing of surplus excavated soil as directed, within a lead of 50 m :

2.1All kinds of soil2.10.1.2 Pipes, cables etc. exceeding 80 mm dia. but not exceeding 300 mm dia.CodDescription Unit Quantity Rate Amount

Details of cost for 110m length of a pipe of anaverage dia. say 200mmSlope assumed 1 in 200.Earth work and filling-

70Code Description Unit Quantity Rate Amount

Minimum depth of trench = 0.75+0.20 = 0.95mAverage depth = (1.50+0.95)/2 = 1.225MWidth = 0.40 + 0.20 = 0.60 m110x0.60x1.225 = 80.85 cum5% for collars = 4.04 cumTotal = 84.89 cumRate vide item no. 2.8.1 cum 84.89 103.4 8 777.63Rate vide item no. 2.25 cum 84.89 45.7 3 879.47TOTAL 12 657.10Cost of 110m length of pipe 12 657.10Cost for lm length of pipe 115.06Say 115.05

### Excavating trenches of required width for pipes, cables, etc including excavation forsockets, and dressing of sides, ramming of bottoms, depth upto 1.5 m including gettingout the excavated soil, and then returning the soil as required, in layers not exceeding20 cm in depth including consolidating each deposited layer by ramming, watering, etc.and disposing of surplus excavated soil as directed, within a lead of 50 m :2.10.1 All kinds of soil2.10.1.3 Pipes, cables etc. exceeding 300 mm dia but not exceeding 600 mm.

Page 67: DAR_Vol_1

Code Description Unit Quantity Rate Amount

Details of cost for 60m length of a pipe of anaverage dia. say 450mm.Slope assumed 1 in 200.Earth work and filling-Minimum depth of trench 0.75+0.45= 1.20mAverage depth = (1.50+1.20)/2 =1.35Width = 0.40 + 0.45 = 0.85 m60x0.85xl.35 = 68.85 cum5% for collars = 3.44 cumTotal = 72.29 cumRate vide item no. 2.8.1 cum 72.29 103.4 7 474.79Rate vide item no. 2.25 cum 72.29 45.7 3 303.65TOTAL 10 778.44Cost of 60m length of pipe 10 778.44Cost for lm length of pipe 179.64Say 179.65

### Extra for excavating trenches for pipes, cables etc. in all kinds of soil for depth exceeding1.5 m, but not exceeding 3 m.(Rate is over corresponding basic item for depth upto 1.5 metre).

Code Description Unit Quantity Rate AmountDetails of cost for 300m length of pipe of anaverage dia. say 200mmSlope assumed 1 in 200.100x0.60x1.75= 105.00 cum200x0.60x2.00 = 240.00 cum.= 345.00 cum.Collars 5% = 17.25 cum.= 362.25 cum.

71Code Description Unit

Rate vide item no. 2.8.1Rate vide item no. 2.25 cum1/2x200xx1.60x1.00=160 cum cum=362.25 cum.Rate vide item no. 2.6.1 cumRate vide item no.2.25 cumExtra for addition lift1

/ x200x0.2Collar 5% = 6.75= 141.75 cum.Rate vide item no. 2.26.1 cumCost for 300 m. length of pipeExtra over item 2.10.1.2 i.e.Cost for 300 m. length of pipe upto 1.50 m. metredepthExtra cost for 300 metre= B-AExtra cost for one metre= C/300Percentage increase over item no 2.101.2=(Cx100)/A

Page 68: DAR_Vol_1

say

### Extra for excavating trenches for pipes, cables, etc, in all kinds of soil for depth exceeding3 m in depth, but not exceeding 4.5 m.(Rate is over corresponding basic item for depth upto 1.5 metre.)

Code Description UnitDetails of cost for 100m length of pipe of anaverage dia. say 200mmSlope assumed 1 in 200.Earth work and filling-1x100x0.60x2= 120 cumCollars 5% = 6 cum.=126 cum.Rate vide item no. 2.8.1 cumRate vide item no. 2.25 cumEarth work100x1.60x1.25= 200 cumRate vide item no. 2.6.1 cumRate vide item no.2.25 cumExtra for additional lift1x100x0.60x1.50 = 90 cum2x0.50x100x0.60x0.50 = 30 cum=120 cumCollare 5% = 6= 126 cum.Rate vide item no. 2.26.1 cumCsot for 300 m. length of pipeExtra over item 2.10.1.2 i.e.Cost for 100 m. length of pipe upto 1.50 m. metredepthExtra cost for 100 metre= B-AExtra cost for one metre= C/100Percentage increase over item no 2.101.2=(Cx100)/Asay

72### Excavating trenches of required width for pipes, cables, etc, including excavation for

sockets, depth upto 1.5 m including getting out the excavated materials, returning thesoil as required in layers not exceeding 20 cm in depth including consolidating eachdeposited layers by ramming, watering etc. stacking serviceable material formeasurements and disposal of unserviceable material as directed, within a lead of 50m :

2.1Ordinary rock :2.13.1.1 Pipes, cables etc. not exceeding 80 mm dia.

CodDescription Unit Quantity Rate AmountDetails of cost for 180 m length of a pipe of aaverage dia. say 40mm.Slope assumed 1 in 200Excavation-Quantity same as in item No.2.10.1.1

Page 69: DAR_Vol_1

Rate vide item no. 2.9.1 cum 85.05 162.65 13 833.38Refilling, ramming and wateringRate vide item no. 2.25 cum 85.05 45.7 3 886.78Extra labour for ramming of rock

###Beldars Day 2 135.25 270.5TOTAL 17 990.66 (A)Add for water charges @ 1% on (A) 2.70 (B)TOTAL 17 993.36Add for contractor’s profit and overheads @ 40.9815% onRs. (A+B)Cost for 180 m. length of pipe 18 034.34Cost for 1 m. length of pipe 100.19Say 100.2

### Excavating trenches of required width for pipes, cables, etc, including excavation forsockets, depth upto 1.5 m including getting out the excavated materials, returning thesoil as required in layers not exceeding 20 cm in depth including consolidating eachdeposited layers by ramming, watering etc. stacking serviceable material formeasurements and disposal of unserviceable material as directed, within a lead of 50m :

2.1Hard rock (requiring blasting)2.13.2.2 Pipes, cables etc. exceeding 80 mm dia. but not exceeding 300 mm dia.CodDescription Unit Quantity Rate Amount

Details of cost for 80 m length of pipe of anaverage dia. Say 200mm.Slope assumed 1 in 200Excavation-Minimum depth of trench.0.75+0.15+0.20 = 1.10mAverage depth = ( 1.10 + 1.50)/2 = 1.30mMinimum width of trench = 0.90m80x0.90x1.30 = 93.60 cum.Rate vide item no. 2.9.1 cum 93.6 162.65 15,224.04Refilling, ramming and wateringRate vide item no. 2.25 cum 93.6 45.7 4,277.52Extra labour for ramming of rock

###Beldars Day 2.2 135.25 297.55 (A)TOTAL 19.799.11

73CodDescription Unit Quantity Rate Amount

Add for water charges @ 1% on A 2.98 (B)TOTAL 19,802.09Add for contractor’s profit and overheads @ 45.0815% on A+BCost for 80 m. length of pipe 19 847.17Cost for 1.00 m length of pipe 248.09Say 248.1

### Excavating trenches of required width for pipes, cables, etc, including excavation forsockets, depth upto 1.5 m including getting out the excavated materials, returning thesoil as required in layers not exceeding 20 cm in depth including consolidating eachdeposited layers by ramming, watering etc. stacking serviceable material formeasurements and disposal of unserviceable material as directed, within a lead of 50m :

Page 70: DAR_Vol_1

2.1Ordinary rock :2.13.1.3 Pipes, cables exceeding 300 mm dia but not exceeding 600mm dia

CodDescription Unit Quantity Rate AmountDetails of cost for 30 m. length of a pipe of anaverage dia. say 450mm.Slope assumed 1 in 200.Excavation-Minimum depth of trench 0.75+0.15+0.15= 1.35m.Average depth = 1.35+ 1.50 = 1.425 m.2Width of trench = 0.90 m.30x0.90x1.425 =30.475 cum.5% for collors = 1.924 cum 40.399 cumRate vide item no. 2.9.1 cum 40.399 162.65 6 570.90Refilling, ramming and wateringRate vide item no. 2.25 cum 40.399 45.7 1 846.23

###Beldars Day .94 135.25 127.14 (A)TOTAL 8 544.27Add for water charges @ 1 % on (A) 1.27 (B)TOTAL 8 545.54Add for contractor’s profit and overheads @ 19.2615% on (A+B)Cost for 30 m length of a pipe 8 564.80Cost for one m length of a pipe 285.49Say 285.5

### Excavating trenches of required width for pipes, cables, etc, including excavation forsockets, depth upto 1.5 m including getting out the excavated materials, returning thesoil as required in layers not exceeding 20 cm in depth including consolidating eachdeposited layers by ramming, watering etc. stacking serviceable material formeasurements and disposal of unserviceable material as directed, within a lead of 50m :

2.1Hard rock (requiring blasting)2.13.2.1 Pipes, cables etc. not exceeding 80 mm dia.CodDescription Unit Quantity Rate Amount

Details of cost for 180 m length of apipe of a average dia. say 40mm.Slope assumed 1 in 200

74CodDescription Unit Quantity Rate Amount

Excavation-Quantity same as in item No.2.10.1.1Rate vide item no. 2.9.2 cum 85.05 272.95 23,214.4Refilling, ramming and wateringRate vide item no. 2.25 cum 85.05 45.7 3,886.79Extra labour for ramming of rock

###Beldars Day 2.5 135.25 38.12 (A)TOTAL 27,439.31Add for water charges @ 1 % on A 3.38 (B)TOTALAdd for contractor’s profit and overheads @ 27,442.69

Page 71: DAR_Vol_1

15% on (A+B) 51.22Cost for 180 m. length of pipe 27,493.91Cost for lm. length of pipe 152.74Say 152.75

### Excavating trenches of required width for pipes, cables, etc, including excavation forsockets, depth upto 1.5 m including getting out the excavated materials, returning thesoil as required in layers not exceeding 20 cm in depth including consolidating eachdeposited layers by ramming, watering etc. stacking serviceable material formeasurements and disposal of unserviceable material as directed, within a lead of 50m :

2.1Hard rock (requiring blasting)2.13.2.2 Pipes, cables etc. exceeding 80 mm dia. but not exceeding 300 mm dia.

CodDescription Unit Quantity Rate AmountDetails of cost for 80 m length of a pipe of anaverage dia. say 200mm.Slope assumed 1 in 200Excavation-Quantity same as in item No.2.13.1.2Rate vide item no. 2.92 cum 93.6 272.95 25,548.12Refilling, ramming and wateringRate vide item no. 2.25 cum 93.6 45.7 4,277.52Extra labour for ramming of rock

###Beldars Day 2.75 135.25 371.94TOTAL 30,197.58Add for water charges @ 1 % on A 3.72 (B)TOTAL 30,201.3Add for contractor’s profit and overheads @ 56.3515% on Rs. (A+B)Cost for 80 m. length of pipe 30,257.65Cost for lm. length of pipe 378.22Say 378.2

75### Excavating trenches of required width for pipes, cables, etc, including excavation for

sockets, depth upto 1.5 m including getting out the excavated materials, returning thesoil as required in layers not exceeding 20 cm in depth including consolidating eachdeposited layers by ramming, watering etc. stacking serviceable material formeasurements and disposal of unserviceable material as directed, within a lead of 50m :

2.1Hard rock (requiring blasting)2.13.2.3 Pipes, cables etc. exceeding 300 mm dia but not exceeding 600mm dia.CodDescription Unit Quantity Rate Amount

Details of cost for 30 m length of a pipe of anaverage dia. Say 450mm.Slope assumed 1 in 200Excavation-Quantity same as in item No.2.13.1.3Rate vide item no. 2.9.2 cum 40.399 272.95 11,026.91Refilling, ramming and wateringRate vide item no. 2.25 cum 40.399 45.7 1,846.23Extra labour for ramming of rock

Page 72: DAR_Vol_1

###Beldars Day 1.17 135.25 158.24(A)TOTAL 13,031.38Add for water charges @ 1 % on A 1.58(B)TOTAL 13,032.96Add for contractor’s profit and overheads @ 23.9715% on (A+B)Cost for 30 m. length of pipe 13,056.93Cost for lm. length of pipe 435.23Say 435.25

### Excavating trenches of required width for pipes, cables, etc, including excavation forsockets, depth upto 1.5 m including getting out the “excavated materials, returning thesoil as required in layers not exceeding 20 cm in depth including consolidating eachdeposited layers by ramming, watering etc. stacking serviceable material formeasurements and disposal of unserviceable material as directed, within a lead of 50m :

2.1Hard rock (blasting prohibited)2.13.3.1 Pipes, cables etc. not exceeding 80 mm dia.CodDescription Unit Quantity Rate Amount

Details of cost for 180 m length of apipe of a average dia. say 40mm.Slope assumed 1 in 200Excavation-Quantity same as in item No.2.10.1.1Rate vide item no. 2.9.3 cum 85.05 332.45 28,274.87Refilling, ramming and wateringRate vide item no. 2.25 cum 85.05 45.7 3,886.78Extra labour for ramming of rock

###Beldars Day 2.5 135.25 338.12 (A)TOTAL 32,499.77Add for water charges @ 1 % on A 3.38 (B)TOTAL 32,503.15Add for contractor’s profit and overheads @ 51.2215% on (A+B)Cost for 180 m. length of pipe 32,554.37Cost for lm. length of pipe 180.86Say 180.85

76### Excavating trenches of required width for pipes, cables, etc, including excavation for

sockets, depth upto 1.5 m including getting out the excavated materials, returning thesoil as required in layers not exceeding 20 cm in depth including consolidating eachdeposited layers by ramming, watering etc. stacking serviceable material formeasurements and disposal of unserviceable material as directed, within a lead of 50m :

2.1Hard rock (blasting prohibited)2.13.3.2 Pipes, cables etc. exceeding 80 mm dia. but not exceeding 300 mm dia.CodDescription Unit Quantity Rate Amount

Details of cost for 80 m length of a pipe of anaverage dia. say 200mm.Slope assumed 1 in 200Excavation-Quantity same as in item No.2.13.1.2

Page 73: DAR_Vol_1

Rate vide item no. 2.9.3 cum 93.6 332.45 31,117.32Refilling, ramming and wateringRate vide item no. 2.25 cum 93.6 45.7 4,277.52Extra labour for ramming of rock

###Beldars Day 2.75 135.25 371.94 (A)TOTAL 35,766.78Add for water charges @ 1 % on (A) 3.72 (B)TOTAL 35,770.5Add for contractor’s profit and overheads @ 56.3515% on (A+B)Cost for 80 m. length of pipe 35,826.85Cost for lm. length of pipe 447.84Say 447.85

### Excavating trenches of required width for pipes, cables, etc, including excavation forsockets, depth upto 1.5 m including getting out the excavated materials, returning thesoil as required in layers not exceeding 20 cm in depth including consolidating eachdeposited layers by ramming, watering etc. stacking serviceable material formeasurements and disposal of unserviceable material as directed, within a lead of 50m :

2.1Hard rock (blasting prohibited)2.13.3.3 Pipes, cables etc. exceeding 300 mm dia but not exceeding 600mm dia.CodDescription Unit Quantity Rate Amount

Details of cost for 30 m length of a pipe of anaverage dia. say 450mm.Slope assumed 1 in 200Excavation-Quantity same as in item No. 2.13.1.3Rate vide item no. 2.9.3 cum 40.399 332.45 13,430.65Refilling, ramming and wateringRate vide item no. 2.25 cum 40.399 45.7 1,846.23Extra labour for ramming of rock

###Beldars Day 1.17 135.25 158.24TOTAL 15,435.12Add for water charges @ 1 % on (A ) 1.58TOTAL 15,436.7Add for contractor’s profit and overheads @ 23.9715% on (A+B)Cost for 80 m. length of pipe 15,460.67Cost for lm. length of pipe 515.36Say 515.35

77### Extra for excavating trenches for pipes, cables, etc. in ordinary/hard rock exceeding 1.5

m in depth but not exceeding 3 m.(Rate is over corresponding basic item for depth upto 1.5 metre.)

Code Description Unit Quantity Rate AmountDetails of cost for 300m length of a pipe of anaverage dia. say 200mm.Slope assumed 1 in 200.Excavation-100x0.90x1.50 =157.50 cum.200x0.90x20.00 = 360.00 cum.

Page 74: DAR_Vol_1

= 517.50 cum.Rate vide item no. 2.9.2 cum 517.5 272.95 ###0.50x200x1.9x1 = 190 cum.Rate vide item no. 2.7.2 cum 190.00 252.20 47,918

Refilling, ramming and watering517.50+190.00 = 707.50 cum.Rate vide item no. 2.25 cum 707.5 45.7 32,332.75Extra for additional lift0.50x300x0.90x1.50 = 202.50 cum.Rate vide item no.2.26.2 cum 202.5 33.85 6,854.62Extra labour for ramming of rock.

### Beldars Day 16.5 135.25 2321.62 (A)TOTAL ###Add for water charges @ 1 % on (A) 22.32 (B)TOTAL ###Add for contractor’s profit and overheads @ 338.0915%on (A+B)Cost for 300m length of pipe 230926.71 (X)Exta over item 2.13.2.2Less cost of 300 m length of pip Metre 300 378.2 -113460.00 (Y)depth 117466.71(Z)Extra cost for 300 m = X - Y 391.56Extra cost for one m 103.53%Percentage increase over item 2.13.2.2 =(Zxl00)/Y 104%Say per metre.

2.15 : Extra for excavating trenches for pipes, cables, etc. in ordinary/hard rock exceeding3m in depth but not exceeding 4.5 m.(Rate is over corresponding basic item for depth upto 1.5 metre.)

CodDescription Unit Quantity Rate AmountDetails of cost for 100m length of a pipe of anaverage dia. say 200mm. Slope assumed 1 in

200Max, depth assumed 3.50mExcavation-100x0.90x2 =180.00 cum.Rate vide item no. 2.9.2 cum 180 272.95 49,131100x1.90x1.25 = 237.50 cumRate vide item no. 2.7.2 cum 237.5 252.2 59 897.50Extra for additional lift1x100x0.90x1.50= 135.002x0.50x100x0.90x0.5=45

78CodDescription Unit Quantity Rate Amount Total = 180 cum.

Ratevide item no. 2.26.2 cum 180 33.85 6 093.00Refilling, ramming and watering180+237.50 = 417.50 cum.Rate vide item no. 2.25 cum 417.5 45.7 19 079.75Extra labour for ramming of rock

0114 Beldars Day 9.25 135.25 1251.06(A)TOTAL ###

Page 75: DAR_Vol_1

Add for water charges.® 1% on (A) 12.51 (B)TOTAL ###Add for contractor’s profit and overheads @ 189.5415% on A+BCost for 100m length of pipe 135654.36(x)Exta over item 2.13.2.2Less cost of 100 m length of pip Metre 100 378.2 37820.00(Y)1.5 m and upto 3 m depthExtra cost for 100 m = X - Y 97834.36(Z)Extra cost for 1 m 978.34Percentage increase over item 2.13.2.2 = 258.68(Zxl00)/YSay 25,900%

2.1Close timbering in trenches including strutting, shoring and packing cavities(wherever required) complete. (Measurements to be taken of the face area timbered).

2.16.1 : Depth not exceeding 1.5 m.CodDescription Unit Quantity Rate Amount

Details of cost for a trench 30m long and 1.5mdeep area 2x30x1.5=90 sqm-MATER1ALSThe Material can be used four times on thesame work and after use of material credit isgiven @ 75% of cost

###Poling boards of 2nd class Kail wood planks 213.75 178 3 804.753

90x0.038 = 3.42 cum = 3420 dmQty taken for cost of using once afterdeducting for credit = 3420x¼x¼ = 213.753dm

###Wallings l00mmx 100mm of 2nd cl10 cudm 75 160 1 200.00wood in scantling: 4x30x0.10x0.10 = 1.20cum

3= 1200 dmQty taken for cost of using once after

3deducting for credit = 1200x¼x¼ = 75 dm

###Safeda Balli struts (12.5mm dia metre 3.1875 29 92.44long): 2x17x1.50 = 51mQty taken for cost of using once afterdeducting for credit = 51 x¼x¼ = 3.1875 mCARRIAGEPoling boards = 3.42 cumWalling =1.20 cum.

3Balli struts: 3.14/4x(0.125) x51 = 0.63 cum

###Total of carriage = 5.25x¼ = 1.3 cum 1.3125 60.81 79.81###Carpenter llnd class Day .05 141.6 70.8###Beldars Day 1 135.25 135.25

79CodDescription Unit Quantity Rate Amount###Sundries L.S. 26.91 1 26.91

Page 76: DAR_Vol_1

TOTAL 5 409.96Add for water charge @ 1 % 54.1TOTAL 5 464.06Add for contractor’s profit and over-heads @ 819.611,500%Costof90Sqm. 6 283.67Cost per sqm. 69.82Say 69.8

2.1Close timbering in trenches including strutting, shoring and packing cavities(wherever required) complete.(Measurements to be taken of the face area timbered).

2.16.2 : Depth exceeding 1.5 m but not exceeding 3 m.CodDescription Unit Quantity Rate Amount

Details of cost for a trench 30m long and 1.5mdeep area 2x30x 1.50=90.00 sqm-MATERIALSThe Material can be used four times on thesame work and after use of material credit isgiven @ 75% of cost

###Poling boards of 2nd class Kail wood planks: 10 cudm 213.75 178 3 804.753

90x0.038 = 3.42 cum = 3420 dmQty taken for cost of using once afterdeducting for credit = 3420x¼x¼ = 213.753dm

###Walings 100 mmx 100mm of 2nd class kail 10 cudm 75 160 1 200.00wood in scantling: 4x30x0.10x0.10 = 1.20cum

3= 1200 dmQty taken for cost of using once after

3deducting for credit = 1200x¼x¼ = 75 dm

###Safeda Balli struts (12.5mm dia and 1.50m metre 3.1875 29 92.44long): 2x17x1.50 = 51mQty taken for cost of using once afterdeducting for credit = x x = 3.1875 mCARRIAGEPoling boards = 3.42 cumWalling =1.20 cum.

3Balli struts: 3.14/4x(0.125) x51 =0.63 cum

###Total of carriage = 5.25x/4 = 1.3125 cum. cum 1.3125 60.81 79.81###Carpenter Ilnd class Day .75 141.6 106.2###Beldars Day 2 135.25 270.5###Sundries L.S. 40.43 1 40.43

TOTAL 5 594.13Add for water charge @ 1 % 55.94TOTAL 5 650.07Add for contractor’s profit and over-heads @ 847.511,500%Costof90Sqm. 6 497.58Cost per sqm. 72.2Say 72.2

Page 77: DAR_Vol_1

802.1Close timbering in trenches including strutting, shoring and packing cavities

(wherever required) complete. (Measurements to be taken of the face area timbered).2.16.3 : Depth exceeding 3 m but not exceeding 4.50 m.CodDescription Unit Quantity Rate

Details of cost for a trench 30m long and 1.50mdeep area 2x30x 1.5=90 sqm-MATERIALSThe Material can be used four times on thesame work and after use of material credit isgiven @ 75% of cost

###Poling boards of 2nd class Kail wood planks :10 cudm 213.75 1783

90x0.038 = 3.42 cum = 340 dmQty taken for cost of using once afterdeducting for credit = 3420x¼x¼ = 213.753dm

###Wallings 100mmx 100mm of 2nd class kail 10 cudm 75 00 0.0 160wood in scantling: 4x30x0.10x0.10 = I.20cum

3= 1200 dmQty taken for cost of using once after

3deducting for credit = 1200x¼x¼ = 75 dm

###Safeda Balli struts (12.5mm dia and 1.5m metre 3.1875 29long): 2x17x1.5 = 51mQty taken for cost of using once afterdeducting for credit = 51x¼x¼ = 3.1875 mCARRIAGEPoling boards = 3.42 cumWalling - = 1.20 cum.

3Balli struts: 3.14/4x(0.125) x51 =0.63 cum

###Total of carriage = 5.25x¼ = 1.3125 cum. cum 1.3125 60.81Labour

###CarpenferTmd class Day 1.5 141.6###Beldars Day 4 135.25###Sundries L.S. 80.73 1

TOTALAdd for water charge @ 1%TOTALAdd for contractor’s profit and over-heads @1,500%Costof90Sqm.Cost per sqm.Say

2.17 : Close timbering in case of shafts, wells, cesspits, manholes and the like includingstrutting, shoring and packing cavities (wherever required) etc. complete.(Measurements to be taken of the face area timbered).

2.17.1 : Depth not exceeding 1.5 m.CodDescription Unit Quantity Rate

Details of cost for a manhole 1.2m x 1.0mx1.5m- Surface area: 2x(1.2+1.0)x1.5 =6.6sqmMATERIALSThe Material can be used four times on the

Page 78: DAR_Vol_1

same work and after use of material credit isgiven @ 75% of cost

81CodDescription Unit Quantity Rate Amount###Poling boards of 2nd class Kail wood planks: 10 cudm 15.6875 178 279.24

36.60x0.038 = 0.251 cum = 251 dmQty taken for cost of using once afterdeducting for credit = x x 3dm

###Walling of 2nd class kail wood scantling 10 cudm 5.125 160 822x2x1.124x0.10x0.10 =0.045 cum2x2x0.924x0.10x0.10 = 0.037 cum.

3Total Kail wood = 0.082 cum. = 82dmQty taken for cost of using once after

3deducting for credit = 82x¼x¼ = 5.125 dm

###Safeda Balli struts (125mm dia and 1.50m metre .4118 29 11.94long)2x2x0.924 = 3.6962x2x0.724 = 2.896Total of balli = 6.592mQty taken for cost of using once afterdeducting for credit = 6.592x¼x¼ = 0.1035 m

###CARRIAGE cum .1035 60.81 6.29Poling boards = 0.251 cumWalling =0.082 cum.

2Balli struts 3.14/4x(0.125) x6.59 = 0.081 cum.Total of carriage = 0.4 x LABOUR:

###Carpenter Ilnd class Day .06 141.6 8.5###Beldars Day .12 135.25 16.23###Sundries L.S. 2.73 1 2.73

TOTAL 406.93Add for water charge @ 1 % 4.07TOTAL 411Add for contractor’s profit and over-heads @ 61.651,500%Cost of 6.6 sqm. 472.65Cost per sqm. 71.61Say 71.6

2.17 : Close timbering in case of shafts, wells, cesspits, manholes and the like includingstrutting, shoring and packing cavities (wherever required) etc. complete.(Measurements to be taken of the face area timbered).

2.17.2 : Depth exceeding 1.5 m but not exceeding 3 m.CodDescription Unit Quantity Rate Amount

Details of cost for a manhole 1.2m x 1.0mx1.5m- Surface area: 2x(1.20+1.0)x1.50 =6.6 sqm

Page 79: DAR_Vol_1

MATERIALSThe Material can be used four times on thesame work and after use of material credit isgiven @ 75% of cost

###Poling boards of 2nd class Kail wood planks: 10 cudm 15.6875 178 279.243

6.6x0.038 = 0.251 cum = 251 dmQty taken for cost of using once afterdeducting for credit = x x 3dm

82CodDescription Unit Quantity Rate Amount###Walling of 2nd class kail wood scantling 10 cudm 5.125 160 82

2x2x1.124x0.10x0.10 = 0.045 cum2x2x0.924x0.10x0.10 = 0.037 cum.

3Total Kail wood = 0.082 cum. = 82dmQty taken for cost of using once after

3deducting for credit = 82x¼x¼ = 5.125 dm

###Safeda Balli struts (125mm dia and 1.5m metre .4118 29 11.94long)2x2x0.924 = 3.6962x2x0.724 = 2.896Total of balli = 6.592mQty taken for cost of using once after-deducting for credit = 6.592x¼x¼ = 0.1035 m

###CARRIAGE cum .1035 60.81 6.29Poling boards = 0.251 cumWalling = 0.082 cum.

2Balli struts 3.14/4x(0.125) x6.59 = 0.081 cum.Total of carriage = 0.414 cum x¼ = 0.1035 cumLABOUR:

###Carpenter Ilnd class Day .12 141.6 16.99###Beldars Day .25 135.25 33.81###Sundries L.S. 5.46 1 5.46

TOTAL 435.73Add for water charge @ 1% 4.36TOTAL 440.09Add for contractor’s profit and over-heads @ 66.011,500%Cost of 6.60 sqm. 506.1Cost per sqm. 76.68Say 76.7

2.1Close timbering in case of shafts, wells, cesspits, manholes and the like includingstrutting, shoring and packing cavities (wherever required) etc. complete.(Measurements to be taken of the face area timbered).

2.17.3 : Depth exceeding 3 m but not exceeding 4.5 m.CodDescription Unit Quantity Rate Amount

Details of cost for a manhole 1.2m x 1,0m

Page 80: DAR_Vol_1

x 1.5m- Surface area: 2x( 1.2+1.0)x 1.5 =6.6sqmMATERIALSThe Material can be used four times on thesame work and after use of material credit isgiven @ 75% of cost

###Poling boards of 2nd class Kail wood planks: 10 cudm 15.6875 178 279.243

6.6x0.038 = 0.251 cum = 251 dmQty taken for cost of using once after

3deducting for credit = 251x¼x¼ = 15.6875 dm

###Walling of 2nd class kail wood scantling 10 cudm 5.125 160 822x2x1.124x0.10x0.10 = 0.045 cum2x2x0.924x0.10x0.10 = 0.037 cum.

3Total Kail wood = 0.082 cum. = 82 dmQty taken for cost of using once after

3deducting for credit = 82x¼x¼ = 5.125 dm

83CodDescription Unit Quantity Rate Amount###Safeda Balli struts (12.5mm dia metre .4118 29 11.94

long)2x2x0.924 = 3.6962x2x0.724 = 2.896Total of balli = 6.592mQty taken for cost of using once after-deducting for credit = 6.592x¼x¼ = 0.1035 m

###CARRIAGE cum .1035 60.81 6.29Poling boards = 0.251 cumWalling = 0.082 cum.

2Balli struts 3.14/4x(0.125) x6.59 = 0.081 cum.Total of carriage = 0.414 cum x¼ = 0.1035cumLABOUR:

###Carpenter Ilnd class Day .19 141.6 26.9###Beldars Day .38 135.25 51.4###Sundries L.S. 8.06 1 8.06

TOTAL 465.83Add for water charge @ 1 % 4.66TOTAL 470.49Add for contractor’s profit and over-heads @ 70.571,500%Cost of 6.6 sqm. 541.06Cost per sqm. 81.98Say 82

2.1Close timbering over areas including strutting, shoring and packing, cavities(wherever required) etc. complete. (Measurements to be taken of the face areatimbered):

2.18.1 : Depth not exceeding 1.5 m.

Page 81: DAR_Vol_1

CodDescription Unit Quantity Rate AmountDetails of cost for an area 30m long and 1.50mdeep-Area -30x1.50m = 45 sqm.MATERIALSThe Material can be used four times on thesame work and after use of material credit isgiven @ 75% of cost

###Poling boards of 2nd class Kail wood planks 10 cudm 106.875 178 1 902.383

250x38mm : 45x0.038 = 1.71 cum = 1.710 dmQty taken for cost of using once after

3deducting for credit = 1710x¼x¼ = 106.875 dm

###Walling of Ilnd class kail wood in 10 cudm 18.75 160 300100x100mm : 30x0.10x0.10 = 0.30cum = 3003dmQty taken for cost of using once after

3deducting for credit = 300x¼x¼ = 18.75 dm

###Raking struts Safeda balleis 12mmmetre 1.59 29 46.111.50 =25.5mQty taken for cost of using once afterdeducting for credit = 25.5x¼x¼ = 1.59 m

###CARRIAGE cum .581 60.81 35.33Poling boards = 1.71 cumWalling “ = 0.30cum:Rakingstruts3.14/4x(0.125)2 = 0.313cum

84CodDescription Unit Quantity Rate Amount

Total of carriage = 2.323 cum x¼ = 0.581cumLABOUR:

###Carpenter Ilnd class Day .25 141.6 35.4###Beldars Day .5 135.25 67.62###Sundries L.S. 31.46 1 31.46

TOTAL 2 418.30Add for water charge @ 1 % 24.18TOTAL 2 442.48Add for contractor’s profit and over-heads @ 366.371,500%Cost of 45 Sqm. 2 808.85Cost per sqm. 62.42Say 62.4

2.1Close timbering over areas including strutting, shoring and packing, cavities(wherever required) etc. complete. (Measurements to be taken of the face areatimbered) :

2.18.2 : Depth exceeding 1.5 m but not exceeding 3 m.CodDescription Unit Quantity Rate Amount

Details of cost for an area 30m long and 1.5mdeep-Area -30x 1,5m = 45 sqm.MATERIALS

Page 82: DAR_Vol_1

The Material can be used four times on thesame work and after use of material credit isgiven @ 75% of cost

1198 Poling boards of 2nd class Kail wood 106.875 178 1 902.38250x38mm : 45x0.038 = 1.71 cum3=1710 dmQty taken for cost of using once after

3deducting for credit = 1710x¼x¼ = 106.875 dm

1197 Walling of Ilnd class kail wo 10 cudm 18.75 160 300100x100mm : 30x0.10x0.10 = 0.30cum3= 300 dmQty taken for cost of using once after

3deducting for credit = 300x¼x¼ = 18.75 dm

0302 Raking struts Safeda balle metre 1.59 29 46.111.5 = 25.5mQty taken for cost of using once afterdeducting for credit = 25.5x¼x¼ = 1.59 m

###CARRIAGE cum .581 60.81 35.33Poling boards = 1.71 cumWalling = 0.30 cum

2Raking struts 3.14/4x(0.125) = 0.313 cumTotal of carriage = 2.323 cum x¼ = 0.581 cumLABOUR:

0112 Carpenter Ilnd class Day .5 141.6 70.80114 Beldars Day 1 135.25 135.259,999 Sundries L.S. 34.06 1 34.06

TOTAL 2 523.93Add for water charge @ 1 % 25.24TOTAL 2 549.17Add for contractor’s profit and over-heads @ 382.381,500%Cost of 45 Sqm. 2 931.55Cost per sqm. 65.15Say 65.15

852.1Close timbering over areas including strutting, shoring and packing, cavities

(wherever required) etc. complete. (Measurements to be taken of the face areatimbered):

2.18.3 : Depth exceeding 3 m but not exceeding 4.5 m.

CodDescription Unit Quantity Rate AmountDetails of cost for an area 30m long and 1.5mdeep-Area -30x 1.5m = 45 sqm.MATERIALSThe Material can be used four times on thesame work and after use of material credit isgiven @ 75% of cost

Page 83: DAR_Vol_1

1198 Poling boards of 2nd class Kail wood 106.875 178 1,902.383

250x38mm : 45x0.038 = 1.71 cum = 1710 dmQty taken for cost of using once after

3deducting for credit = 1710x¼x¼ = 106.875 dm

1197 Walling of Ilnd class kail wo 10 cudm 18.75 160 300100x100mm : 30x0.10x0.10 = 0.30cum3= 300 dmQty taken for cost of using once after

3deducting for credit = 300x¼x¼ metre 1.59 29 46.1

0302 Raking struts Safeda balleis 12mm dia : 17 x1.50 = 25.5mQty taken for cost of using once afterdeducting for credit = 25.5x¼x¼ = 1.59 m

###CARRIAGE cum .581 60.81 35.33Poling boards = 1.71 cumWalling =0.30 cum.

2Raking struts 3.14/4x(0.125) = 0.313 cumTotal of carriage = 2.323 cum x¼ = 0.581cumLABOUR:

###Carpenter Ilnd class Day .75 141.6 106.2###Beldars Day 1.5 135.25 202.88###Sundries L.S. 47.58 1 47.58

TOTAL 2 640.48Add for water charge @ 1 % 26.4TOTAL 2 666.88Add for contractor’s profit and over-heads @ 400.031,500%Cost of 45 Sqm. 3 066.91Cost per sqm. 68.15Say 68.15

2.19 : Extra for planking, strutting and packing materials for cavities (in close timbering) ifrequired to be left permanently in position.(Face area of timber permanently left to be measured).

CodDescription Unit Quantity Rate AmountDetails of cost for a trench 30m long and 1.5mdeep area 2x30x1.5=90 sqm-MATERIALS

1198 Poling boards of 2nd class Kail wood planks :3

90x0.038 = 3.42 cum = 3420 dmLess @ 1/8 of Qty as timber is supposed to be

3used once before = 3420 - 427.5 = 2992.5 2,992.5 178 53,266.5

86CodDescription Unit Quantity Rate Amount1197 Walings 100mmx100mm of 2nd class kail

Page 84: DAR_Vol_1

wood in scantling: 4x30x0.10x0.10 = 1.20c 10 cudm 1,050 160 16 800.00= 1200 dm3Less @ 1/8 of Qty as timber is supposed to be

3used once before = 1200 - 150 = 1050 dm

###Safeda Balli struts (12.5mm dia and 1.5mlong): 2x17x1.5 = 51mLess @ 1/8 of Qty as timber is supposed to metre 44.63 29 1,294.27used once before = 51 - 6.37 = 44.63 m

###CARRIAGE:Poling boards = 3.42 cumWalling =1.20 cum.

2Balli struts: 3.14/4x(0.125) x 51 = 0.63 cum cum 2.675 60.81 162.67= 5.25 cum Taking half = 5.25 x 14 = 2.675cumTOTAL 71,523.44Add for water charge @ 1 % 715.23TOTAL 72 238.67Add for contractor’s profit and over-heads @ 10 835.801,500%Cost of 90Sqm. 83 074.47Cost per sqm. 923.05Say 923.05

2.2Open timbering in trenches including strutting and shoring complete(measurements to be taken of the face area timbered):

2.20.1 : Depth not exceeding 1.5 m.CodDescription Unit Quantity Rate Amount

Details of cost for a trench of length 30m and1.5m deep surface area - 2x30x 1.50 = 90 sqm.MATERIALS:The Material can be used four times on thesame work and after use of material credit isgiven @ 75% of cost

1198 Poling board 1.5mx0.25x0.038m : 10 cudm 71.25 178 1,268.253

2x40x1.5x0.25x0.038= 1.14cum = 1140 dmQty taken for cost of using once after

3deducting for credit = x x (Rate per II class kail wood planks)

1197 Walling l00mmxl00mm : 4x30mx0.lmx10 cudm 75 160 1 200.003

= 1.20cum= 1200 dmQty taken for cost of using once after

3deducting for credit = 1200x¼x¼ = 75 dm(Rate per II class kail wood scantling)

0302 Safeda Bailies struts (125mm dia. And metre 3.18 29 92.22long)-2x17x1.50 = 51mQty taken for cost of using once afterdeducting for credit = = 3.18 m

###CARRIAGE: cum .74 60.81 45Poling boards =1.14 cumWalling =1.20 cum

2Bailies struts-3.14/4x(0.125) = 0.63 cumTotal of carriage = 2.97 cum x¼ = 0.74LABOUR:

Page 85: DAR_Vol_1

87CodDescription Unit Quantity Rate Amount###Carpenter Ilnd class Day .25 141.6 35.4###Beldars Day .5 135.25 67.629999 Sundries L.S. 19.76 1 19.76

TOTAL 2,728.25Add for water charge @ 1 % 27.28TOTAL 2,755.53Add for contractor’s profit and over-heads @ 413.331,500%Cost of 90 Sqm 3,168.86Cost per sqm. 35.21Say 35.2

2.2Open timbering in trenches including strutting and shoring complete(measurements to be taken of the face area timbered):

2.20.2 : Depth exceeding 1.5 m but not exceeding 3 m.CodDescription Unit Quantity Rate Amount

Details of cost for a trench of length 30m and1.5m deep surface area - 2x30x1.5 = 90 sqm.MATERIALS:The Material can be used four times on thesame work and after use of material credit isgiven @ 75% of cost

1198 Poling board 1.50mx0.25x 10 cudm 71.25 178 1,268.253

2x40x1.5x0.25x0.038= 1.14cum= 1140 dmQty taken for cost of using once after

3deducting for credit = x x (Rate per II class kail wood planks)

1197 Walling 100mmx 100mm: 4x30mx0.lmx0.lm 10 75 160 1,2003

= 1.20cum= 1200 dmQty taken for cost of using once after

3deducting for credit = 1200x¼x¼ = 75 dm(Rate per II class kail wood scantling)

0302 Safeda Ballies struts (12 metre 3.18 29 92.22long)-2x17x1.5 = 51mQty taken for cost of using once afterdeducting for credit = 51x¼x¼ = 3.18 m

2,204 CARRIAGE: cum .74 60.81 45Poling boards = 1.14 cum-Walling = 1.20 cum

2Ballies struts 3.14/4x(0.125) = 0.63 cumTotal of carriage = 2.97 cum x¼ = 0.74 cumLABOUR:

###Carpenter Ilnd class Day .5 141.6 70.8###Beldars Day 1 135.25 135.25###Sundries L.S. 33.15 1 33.15

TOTAL 2 844.67Add for water charge @ 1 % 28.45

Page 86: DAR_Vol_1

TOTAL 2 873.12Add for contractor’s profit and over-heads @ 430.971,500%Cost of 90 Sqm 3 304.09Cost per sqm. 36.71Say 36.7

882.2Open timbering in trenches including strutting and shoring complete

(measurements to be taken of the face area timbered):2.20.3 : Depth exceeding 3 m but not exceeding 4.5 m.CodDescription Unit Quantity Rate Amount

Details of cost for a trench of length 30m and1.5m deep surface area - 2x30x1.5 = 90 sqm.MATERIALS:The Material can be used four times on thesame work and after use of material credit isgiven @ 75% of cost

1198 Poling board 1.50mx0.25x0 10 cudm 71.25 178 1,268.253

2x40x1.5x0.25x0.038= 1.14 cum = 1140 dmQty taken for cost of using once after

3deducting for credit = x x (Rate per II class kail wood planks)

1197 Walling l00mmxl00mm : 10 cudm 75 160 1 200.003

= 1.20cum= 1200 dmQty taken for cost of using once after

3deducting for credit = 1200x¼x¼ = 75 dm(Rate per II class kail wood scantling)

0302 Safeda Ballies struts (12 metre 3.18 29 92.22long)-2x17x1.5 = 51mQty taken for cost of using once afterdeducting for credit = x x

2204 CARRIAGE: cum .74 60.81 45Poling boards =1.14 cumWalling = 1.20 cum

2Bailies struts 3.14/4x(0.125) = 0.63 cumTetal of carriage = 2.97 cum x¼ = 0.74 cumLABOUR:

0112 Carpenter Ilnd class Day 1 141.6 141.60114 Beldars Day 1.75 135.25 236.699999 Sundries L.S. 46.67 1 46.67

TOTAL 3 030.43Add for water charge @ 1% 30.3TOTAL 3 060.73Add for contractor’s profit and over-heads @ 459.111,500%Cost of 90 Sqm 3 519.84Cost per sqm. 39.11

Page 87: DAR_Vol_1

Say 39.1

2.2Open timbering in case of shafts, wells, cesspits, manholes and the like includingstrutting and shoring complete (Measurements to be taken of the face areatimbered):

2.21.1 : Depth not exceeding 1.5 m.CodDescription Unit Quantity Rate Amount

Details of cost for a manhole 1.2x lm x 1.5m -Surface area 2( 1.2+1.0)x 1.5 = 6.6 sqmMATERIALS :The Material can be used four times on thesame work and after use of material credit isgiven @ 75% of cost

###Polling boards of 2nd class kail 10 cudm 5.375 178 95.68250mm wide and 38mm thick :

89CodDescription Unit Quantity Rate Amount

36x0.25xl.5x0.038 = 0.086 cum = 86dmQty taken for cost of using once after

3deducting for credit = 86x¼x¼ = 5.3755 dm

###Walling l00mmxl00mm II class ka 10 cudm 3 160 48wood in scantling

34x 1.2x0.1 x0.1 = 0.048 cum = 48 dmQty taken for cost of using once after

3deducting for credit = 486x¼x¼ = 3 dm

###Safeda Balli struts 125mm dia. metre .4 29 11.6(4x1.0=4.0)+(2x1.2=2.4) = 6.4mQty taken for cost of using once afterdeducting for credit = 6.4x¼x¼ = 0.40 m

###CARRIAGE : cum .053 60.81 3.22Poling boards = 0.086 cumWalling = 0.048 cum

2Bailies struts 3.14/4x(0.125) x 6.4 = 0.079cumTotal of carriage = 0.213 cum x¼ = 0.053 cumLABOUR:

###Carpenter Ilnd class Day .03 141.6 4.25###Beldars Day .06 135.25 8.12###Sundries L.S. 1.82 1 1.82

TOTAL 172.69Add for water charge @ 1 % 1.73TOTAL 174.42Add for contractor’s profit and over-heads @ 26.161,500%Cost of 6.6 sqm. 200.58Cost per sqm. 30.39Say 30.4

2.2Open timbering in case of shafts, wells, cesspits, manholes and the like including

Page 88: DAR_Vol_1

strutting and shoring complete (Measurements to be taken of the face areatimbered):

2.21.2 : Depth exceeding 1.5 m but not exceeding 3 m.CodDescription Unit Quantity Rate Amount

Details of cost for a manhole 1.2x 1mx 1.5mSurface area2(1.2+1.0)xl.5 = 6.6 sqmMATERIALS :The Material can be used four times on thesame work and after use of material credit isgiven @ 75% of cost

1198 Polling boards of 2nd class 10 cudm 5.375 178 95.68250mm wide and 38mm thick :

36x0.25x1.5x0.038 = 0.086 cum = 86dmQty taken for cost of using once after

3deducting for credit = 86x¼x¼ = 5.3755 dm

###Walling 100mmxl00mm IInd clas10 cudm 3 160 48wood in scantling

34x1.2x0.1 x0.1 = 0.048 cum = 48 dmQty taken for cost of using once after

3deducting for credit = 486x¼x¼ = 3 dm

0302 Safeda Balli struts 125mm dmetre .4 29 11.6(4x1.0=4.0)+(2x1.2=2.4) = 6.4mQty taken for cost of using once afterdeducting for credit = 6.4x¼x¼ = 0.40 m

90CodDescription Unit Quantity Rate Amount2204 CARRIAGE: cum .053 60.81 3.22

Poling boards = 0.086 cumWalling = 0.048 cum

2Bailies struts 3.14/4x(0.125) x 6.4 = 0.079cumTotal of carriage = 0.213 cum x¼ = 0.053 cumLABOUR:

0112 Carpenter Ilnd class Day .06 141.6 8.50114 Beldars Day .12 135.25 16.239999 Sundries L.S. 2.73 1 2.73

TOTAL 185.96Add for water charge @ 1 % 1.86TOTAL 187.82Add for contractor’s profit and over-heads @ 28.171,500%Cost of 6.6 sqm. 215.99Cost per sqm. 32.73Say 32.75

2.2Open timbering in case of shafts, wells, cesspits, manholes and the like includingstrutting and shoring complete (Measurements to be taken of the face area timbered):

2.21.3 : Depth exceeding 3 m but not exceeding 4.5 m.

Page 89: DAR_Vol_1

CodDescription Unit Quantity Rate AmountDetails of cost for a manhole 1.2x1lmx 1.5mSurface area 2(1.2+1.0)x1.5 = 6.6 sqmMATERIALS :The Material can be used four times on thesame work and after use of material credit isgiven @ 75% of cost

###Polling boards of 2nd class kail 10 cudm 5.375 178 95.68250mm wide and 38mm thick :

36x0.25x1.5x0.038 = 0.086 cum = 86dmQty taken for cost of using once after

3deducting for credit = 86x¼x¼ = 5.3755 dm

1197 Walling 100mmx 100mm IIn10 cudm 3 160 48kail wood scantling

34x1.2x0.10 x0.10 = 0.048 cum = 48 dmQty taken for cost of using once after

3deducting for credit = 48x¼x¼ = 3 dm

0302 Safeda Balli struts 125mm dmetre .4 29 11.6(4x1.0=4.0)+(2x1.2=2.4) = 6.4mQty taken for cost of using once afterdeducting for credit = 6.4x¼x¼ = 0.4 m

###CARRIAGE: cum .053 60.81 3.22Poling boards = 0.086 cumWalling = 0.048 cum

2Bailies struts 3.14/4x(0.125) x 6.4 = 0.079cumTotal of carriage = 0.213 cum x¼ = 0.053cumLABOUR:

0112 Carpenter Ilnd class Day .1 141.6 14.16###Beldars Day .2 135.25 27.059999 Sundries L.S. 3.64 1 3.64

91CodDescription Unit Quantity Rate Amount

TOTAL 203.35Add for water charge @ 1 % 2.03TOTAL 205.38Add for contractor’s profit and over-heads @ 30.811,500%Cost of 6.6 sqm. 236.19Cost per sqm. 35.79Say 35.8

2.2Open timbering over areas including strutting, shoring etc. complete.(Measurements to be taken of the face area timbered):

2.22.1 : Depth not exceeding 1.5 m.

CodDescription Unit Quantity Rate Amount

Page 90: DAR_Vol_1

Details of cost for an area 30m long and 1.5mdeep Area = 30 x 1.50 = 45 sqm.MATERIALS :The Material can be used four times on thesame work and after use of material credit isgiven @ 75% of cost

###Polling boards of 2nd class kail wood planks250mm x 38mm

340x1.5x0.25x0.038 = 0.57cum. = 10 cudm 35.625 178 634.12Qty taken for cost of using once after

3deducting for credit = 570x¼x¼ = 35.625 dm

###Raking struts- Safeda Bailies125mm dia 40x1.50 = metre 3.75 29 108.75Qty taken for cost of using once afterdeducting for credit = 60x¼x¼ = 3.75 m

###CARRIAGE : cum .3275 60.81 19.92Poling boards = 0.57 cum

2Bailies 40x1.5x3.14/4x(0.125) = 0.40 cum.Total for carriage =1.31 cum x¼ = 0.3275 cumLABOUR:

###Carpenter Ilnd class Day .12 141.6 16.99###Beldars Day .25 135.25 33.81###Sundries L.S. 19.76 1 19.76

TOTAL 833.35Add for water charge @ 1 % 8.33TOTAL 841.68Add for contractor’s profit and over-heads @ 126.251,500%Cost of 45 sqm. 967.93Cost per sqm. 21.51Say 21.5

2.2Open timbering over areas including strutting, shoring etc. complete.(Measurements to be taken of the face area timbered):

2.22.2 : Depth exceeding 1.5 m but not exceeding 3 m.CodDescription Unit Quantity Rate Amount

Details of cost for an area 30m long and 1,5mdeep Area = 30 x 1.5 = 45 sqm.MATERIALS :

92CodDescription Unit Quantity Rate Amount

The Material can be used four times on thesame work and after use of material credit isgiven @ 75% of cost

###Polling boards of 2nd class kail wood planks250mm x 38mm

340x1.5x0.25x0.038 = 0.57cum. = 10 cudm 35.625 178 634.12Qty taken for cost of using once after

3

Page 91: DAR_Vol_1

deducting for credit = 570x¼ x¼ = 35.625 dm###Raking struts- Safeda Bailies

125mm dia 40x1.5 = 60m metre 3.75 29 108.75Qty taken for cost of using once afterdeducting for credit = 60x¼x¼ = 3.75 m

###CARRIAGE: cum .3275 60.81 19.92Poling boards = 0.57 cum

2Bailies 40x1.5x3.14/4x(0.125) = 0.40 cum.Total for carriage =1.31 cum x¼ = 0.3275cumLABOUR:

###Carpenter Ilnd class Day .25 141.6 35.4###Beldars Day .5 135.25 67.629999 Sundries L.S. 33.15 1 33.15

TOTAL 898.96Add for water charge @ 1 % 8.99TOTAL 907.95Add for contractor’s profit and over-heads @ 136.191,500%Cost of 45 sqm. 1 044.14Cost per sqm. 23.2Say 23.2

2.2Open timbering over areas including strutting, shoring etc. complete.(Measurements to be taken of the face area timbered):

2.22.3 : Depth exceeding 3 m but not exceeding 4.5 m.CodDescription Unit Quantity Rate Amount

Details of cost for an area 30m long and 1.5mdeep, Area = 30 x 1.50 = 45 sqm.MATERIALS :The Material can be used four times on thesame work and after use of material credit isgiven @ 75% of cost

###Polling boards of 2nd class kail wood planks250mm x 38mm

340x1.5x0.25x0.038 = 0.57cum. = 10 cudm 35.625 178 634.12Qty taken for cost of using once after

3deducting for credit = 570x¼x¼ = 35.625 dm

###Raking struts- Safeda Bailies125mm dia 40x1.50 = 60m metre 3.75 29 108.75Qty taken for cost of using once afterdeducting for credit = 60x¼x¼ = 3.75 m

###CARRIAGE: cum .3275 60.81 19.92Poling boards = 0.57 cum

2Bailies 40x1.5x3.14/4x(0.125) = 0.40 cum.Total for carriage = 131 cum x¼ = 0.3275cum

93CodDescription Unit Quantity Rate Amount

Page 92: DAR_Vol_1

LABOUR:###Carpenter Ilnd class Day .5 141.6 70.8###Beldars Day .88 135.25 119.02###Sundries L.S. 47.58 1 47.58

TOTAL 1 000.19Add for water charge @ 1% 10TOTAL 1 010.19Add for contractor’s profit and over-heads @ 151.531,500%Cost of 45 sqm. 1 161.72Cost per sqm. 25.82Say 25.8

2.23 Extra for planking and strutting in open timbering if required to be left permanentlyin position. (Face area of the timber permanently left to be measured).CodDescription Unit Quantity Rate Amount

Details of cost for a trench of length 30m and1.5m deep surface area - 2x30x1.50 = 90 sqm.MATERIALS:

###Poling board 1.50mx0.25x0.038 10 cudm 997.5 178 17 755.503

2x40xl.5x0.25x0.038 = 1.14cum = 1140 dm(Rate per II class kail wood planks)Less @ 1/8 of Qty as timber is supposed to be

3used once before = 1140 -142.50 = 997.50 dm

###Walling 100mmx 100mm : 4x30mx0.10 mx0 1,050 160 16 800.003

= 1.20cum= 1200 dm(Rate per II class kail wood in scantling)Less @ 1/8 of Qty as timber is supposed to be

3used once before = 1200 - 150 = 1050 dm

###Safeda Bailies struts (125mm di metre 44.63 29 1 294.27long)-2x17x1.5= 51mLess @ 1/8 of Qty as timber is supposed to beused once before = 51- 6.37 = 44.63 m

###CARRIAGE: cum 1.485 60.81 90.3Poling boards =1.14 cumWalling =1.20 cum

2Bailies struts 51x3.14x¼x(0.125) = 0.63 cumTotal of carriage = 2.97 cum Taking half =2.97 x½ =.1.485 cum 35,940.07TOTAL 359.4Add for water charge @ 1 % 36 299.47TOTAL 5 444.92Add for contractor’s profit and over-heads @1,500%Cost of 90 sqm. 41 744.39Cost per sqm. 463.83Say 463.85

94

Page 93: DAR_Vol_1

2.2Extra rates for quantities of works, executed: (The extra percentage rate is appli-cable in respect of each item but limited to quantities of work executed in thesedifficult conditions).

2.24.1 : In or under water and/ or liquid mud, including pumping out water as required.

CodDescriptio Unit Quantity Rate AmountExtra due t Metre (20% of the rate of the item. Thedewatering:depth extra percentage in rate is appli-the item cable in respect of each item but

ltd. To quantities of work excutedin difficult condition.)

### Extra rates for quantities of works, executed: . (The extra percentage rate isapplicable in respect af each item but limited to quantities of work executed inthese difficult conditions).

2.24.2 In or under foul position,including pumping out water as required.

CodDescriptio Unit Quantity Rate Amount

Extra due t Metre (25% of the rate of the item. Thisdewatering:depth pertains to only such. Pumping ofthe item - water as is envisaged at the time

of tendering and don't includethose that covered under contrac-tual risk.)

Note for item n The extra percentage rate is applicable in respect of each item but limited toquantities of work executed in these difficult conditions. The unit, namely, metre depth, to be considered forpayment, shall be the depth measured from the sub soil water level up to the centre of gravity of the qtyexecuted in difficult condition. The depth shall be reckoned correct to 0.10m, 0.05m or more shall be taken as0.10m and less than 0.05m ignorel.

2.25 : Filling available excavated earth (excluding rock) in trenches, plinth, sides offoundations etc. in layers not exceeding 20cm in depth, consolidating each depositedlayer by ramming and watering, lead up to 50 m and lift upto 1.5 m.

CodDescriptio Unit Quantity Rate AmountDetails of cost for 10 cum.Labour-

###Mate Day .2 138.45 27.69###Coolies Day 2.5 135.25 338.12###Bhishti Day .2 138.45 27.69

TOTAL 393.5Add for water charge @ 1 % 3.94TOTAL 397.44Add for contractor’s profit and over-heads @ 59.621,500%Cost of 10 cum. 457.06Cost of 1 cum. 45.71Say 45.7

952.26 : Extra for every additional lift of 1.5 m or part thereof in.2.2All kinds of soil.

Page 94: DAR_Vol_1

CodDescription Unit Quantity Rate AmountDetails of cost of 10 cum.Labour:-

0128 Mate Day .1 138.45 13.840114 Beldars Day 1.1.10 135.25 148.78

TOTAL 162.62Add for water charge @ 1% 1.63TOTAL 164.25Add for contractor’s profit and over-heads @ 24.641,500%Cost of 10 cum. 188.89Cost of 1 cum. 18.89Say 18.9

2.2Extra for every additional lift of 1.5 m or part thereof in.2.2Ordinary or hard rock.CodDescription Unit Quantity Rate Amount

Details of cost of 10 cum.Labour:-

###Mate Day .2 138.45 27.69###Beldars Day 1.95 135.25 263.74

TOTAL 291.43Add for water charge @ 1% 2.91TOTAL 294.34Add for contractor’s profit and over-heads @ 44.151,500%Cost of 10 cum. 338.49Cost of 1 cum. 33.85Say 33.85

2.27 : Supplying and filling in plinth with Jamuna sand under floors including, watering,ramming consolidating and dressing complete.

CodDescription Unit Quantity Rate AmountDetails of cost for 10 cum.Materials:

###Jamuna sand cum 10 175 1 750.00###Carriage of Jamuna sand cum 10.6 53.21 532.1

Labour:###Beldars Day .89 135.25 120.37###Coolies Day 1.07 135.25 144.72###Bhishti Day .35 138.45 48.46

TOTAL 2 595.65Add for water charge @ 1 % 25.96TOTAL 2 621.61Add for contractor’s profit and over-heads @ 393.241,500%Cost of 10 cum. 3 014.85Cost of 1 cum. 301.49Say 301.5

962.2Surface dressing of the ground including removing vegetation and in-equalities not

exceeding 15 cm deep and disposal of rubbish, lead upto 50 m and lift upto 1.5 m.

Page 95: DAR_Vol_1

2.28.1 : All kinds of soil.

CodDescription Unit Quantity Rate AmountDetails of cost for 100 sqm.Labour:

0114 Beldars Day 1.97 135.25 266.440115 Coolies Day 1.29 135.25 174.47

TOTAL 440.91Add for water charge @ 1 % 4.41TOTAL 445.32Add for contractor’s profit and over-heads @ 66.81,500%Cost of 100 sqm. 512.12Say 512.1

2.2Ploughing the existing ground to a depth of 15 cm to 25 cm and watering the same.2.29.1 : All kinds of soil.CodDescription Unit Quantity Rate Amount

Details of cost for 100 sqm.Labour:

###Beldars Day 2.75 135.25 371.94###Bhishti Day .5 138.45 69.22

TOTAL 441.16Add for water charge @ 1 % 4.41TOTAL 445.57Add for contractor’s profit and over-heads @ 66.841,500%Cost of 100 sqm. 512.41Say 512.4

2.3Excavating holes upto 0.5 cum including getting out the excavated soil, thenreturning the soil as required in layers not exceeding 20 cm in depth, includingconsolidating each deposited layer by ramming, watering etc, disposing of surplusexcavated soil; as directed within a lead of 50 m and lift upto 1.5 m.

2.30.1 : All kinds of soil.CodDescription Unit Quantity Rate Amount

Details of cost for 6 holes-Earth work 6x0.50 = 3.0 cum.Rate vide item no. 2.8.1 cum 3 103.4 310.2Extra labour for filling and ramming

###Sundries L.S. 13.52 1 13.52(B)TOTAL 323.72Add for water charges @ 1% on B 0.14(C)TOTAL 323.86Add for contractor’s profit and over-heads @ 2.0515%on (B+C)Cost of 6 holes 325.91Cost of 1 hole 54.32Say 54.3

972.3Excavating holes upto 0.5 cum including getting out the excavated soil, then

returning the soil as required in layers not exceeding 20 cm in depth, includingconsolidating each deposited layer by ramming, watering etc, disposing of surplus

Page 96: DAR_Vol_1

excavated soil; as directed within a lead of 50 m and lift upto 1.5 m. 2.30.2 : Ordinary rock

CodDescription Unit Quantity Rate AmountDetails of cost for 6 holes-Excavation -6x0.50 = 3.0 cum.Rate vide item no. 2.9.1 cum 3 162.65 487.95Extra labour for filling and ramming

###Sundries L.S. 7.8 1 7.80(B)TOTAL 495.75Add for water charges % on B 0.08(C)TOTAL 495.83Add for contractor’s profit and over-heads 1.1815% on B+CCost of 6 holes 497.01Cost of 1 hole 82.84Say 82.85

### Excavating holes upto 0.5 cum including getting out the excavated soil, thenreturning the soil as required in layers not exceeding 20 cm in depth, includingconsolidating each deposited layer by ramming, watering etc, disposing of surplusexcavated soil; as directed within a lead of 50 m and lift upto 1.5 m.

2.3Hard rock (requiring blasting)CodDescription Unit Quantity Rate Amount

Details of cost for 6 holes6x0.50 = 3.0 cum.Rate vide item no. 2.9.2 cum 3 272.95 818.85Extra labour for filling and ramming

###Sundries L.S. 80.73 1 80.73(B)TOTAL 899.58Add for water charges @ 1 % on B 0.81(C)TOTAL 900.39Add for contractor’s profit and over-heads@ 12.2315% on B+CCost of 6 holes 912.62Cost of 1 hole 152.1Say 152.1

2.3Excavating holes upto 0.5 cum including getting out the excavated soil, thenreturning the soil as required in layers not exceeding 20 cm in depth, includingconsolidating each deposited layer by ramming, watering etc, disposing of surplusexcavated soil; as directed within a lead of 50 m and lift upto 1.5 m.

2.30.4 : Hard rock (blasting prohibited)CodDescription Unit Quantity Rate Amount

Details of cost for 6 holes-Excavation- 6x0.50 = 3.0cum.Rate vide item no. 2.9.3 cum 3 332.45 997.35Extra labour for filling and ramming

###Sundries L.S. 80.73 1 80.73(B)TOTAL 1,078.08

98Code Description Unit Quantity Rate Amount

Page 97: DAR_Vol_1

Add for water charges @ 1 % on B 0.81(C)TOTAL 1,078.89Add for contractor’s profit and over-heads @ 12.2315% on B+CCost of 6 holes 1,091.12Cost of 1 hole 181.85Saycum L.S. 181.85

Note :-(I) Carriage of excavated material beyond the first 50m will be paid under carriage of materials” vide sub-head(II) Carriage by animal and mechanical transport will be reckoned in terms of nearest km. distance of 0.5

km or more will be taken as 1 km and distance of less than 0.5 km ignored, However, when the totallead is less than 0.5 km it will not be ignored but paid for separately in successive stages of 50msubject to the conditions that the total rate worked out on these bases does not exceed the rate forinitial lead of 1km.

2.31 : Clearing jungle including uprooting of rank vegetation, grass, brush wood, treesand saplings of girth upto 30 cm measured at a height of 1 m above ground leveland removal of rubbish upto a distance of 50 m outside the periphery of the areacleared.

Code Description Unit Quantity Rate AmountDetails of cost for 100 sqm.Labour:

114 Beldars Day 1.08 135.25 146.07115 Coolies Day .6 135.25 81.15

TOTAL 227.22Add 1 % for water charges 2.27TOTAL 229.49Add 15% for contractor’s profit and overheads 34.42Cost of 100 sqm. 263.91Say 263.9

2.32 : Clearing grass and removal of the rubbish upto a distance of 50 m outside theperiphery of the area cleared.

Code Description Unit Quantity Rate AmountDetails of cost for 100 sqm.Labour:

114 Beldars Day .6 135.25 81.15115 Coolies Day .25 135.25 33.819999 Sundries L.S. 1.82 1 1.82

TOTAL 116.78Add 1% for water charges 1.17TOTAL 117.95Add 15% for contractor’s profit and overheads 17.69Cost of 100 sqm. 135.64Say 135.65

992.3Felling trees of the girth (measured at a height of 1 m above ground level) including

cutting of trunks and branches removing the roots and stacking of serviceablematerial and disposal of unserviceable material.

2.33.1 : Beyond 30 cm girth upto and including 60 cm girth

Page 98: DAR_Vol_1

CodDescription Unit Quantity Rate AmountDetails of cost of tree of 15cm.in. dia. Ht. = av. 3mquantity of wood-3.14/4x0.15x0.15x3 = 0.053 cum.Add 20% for branches = 0.011 cum.Total = 0.064 cum.Labour for cutting in trees removingthe roots from the soil and then fillingin Pit and depresions.

###Beldars Day .33 135.25 44.63###Coolies Day .17 135.25 22.99###Sundries L.S. 2.73 1 2.73

TOTAL 70.35Add 1 % for water charges .7TOTAL 71.05Add 15% for contractor’s profit and overheads 10.66Cost of one tree 81.71Say 81.7

2.3Felling trees of the girth (measured at a height of 1 m above ground level) includingcutting of trunks and branches removing the roots and stacking of serviceablematerial and disposal of unserviceable material.

2.33.2 : Beyond 60 cm girth upto and including 120 cm girthCodDescription Unit Quantity Rate Amount

Details of cost of a tree-of av. girth = 90cmof av. dia. = 0.3mand length = 5m(22x0.3x0.3x5)/7x4 = 0.35 cum20% branches = 0.07 cumTotal = 0.42 cumLabour for cutting the trees andremoving in roots from the soilfilling in pit and the depresions

###Beldars Day 1.5 135.25 202.88###Coolies Day .75 135.25 101.44###Sundries L.S. 5.46 1 5.46

TOTAL 309.78Add 1% for water charges 3.1TOTAL 312.88Add 15% for contractor’s profit and overheads 46.93Cost of one tree 359.81Say 359.8

1002.3Felling trees of the girth (measured at a height of 1 m above ground level) including

cutting of trunks and branches removing the roots and stacking of serviceablematerial and disposal of unserviceable material.

2.33.3 : Beyond 120 cm girth upto and including 240 cm girthCodDescription Unit Quantity Rate Amount

Details of cost for a tree-

Page 99: DAR_Vol_1

avg. girth = 180cmand avg. length = 7m(22x0.6x0.6x7)/7x4 = 1.98 cum.+20% branches = 0.40 cum.Total = 2.38 cum.Labour for cutting the trees andremoving in roots from the soilfilling in pit and the depresions

###Beldars Day 7 135.25 946.75###Coolies Day 3.5 135.25 473.38###Sundries L.S. 8.06 1 8.06

TOTAL 1 428.19Add 1 % for water charges 14.28TOTAL 1 442.47Add 15% for contractor’s profit and overheads 216.37Cost of one tree 1 658.84Say 1 658.85

### Felling trees of the girth (measured at a height of 1 m above ground level) includingcutting of trunks and branches removing the roots and stacking of serviceablematerial and disposal of unserviceable material.

2.3Above 240 cm girthCodDescription Unit Quantity Rate Amount

Details of cost for a tree of average 300cm.girth and length 10m3.142/4x1x1x10 = 7.86 cum20% Branches = 1.57 cum.Total = 9.43 cum.Labour for cutting the trees andremoving in roots from the soilfilling in pit and the depresions.

###Beldars Day 14 135.25 1,893.5###Coolies Day 7 135.25 946.75###Sundries L.S. 26.91 1 26.91

TOTAL 2 867.16Add 1% for water charges 28.67TOTAL 2 895.83Add 15% for contractor’s profit and overheads 434.37Cost of one tree 3 330.20Say 3 330.20

2.3Supplying chemical emulsion in sealed containers including delivery as specified.2.34.1 : Chlorpyriphos/Lindane emulsifiable concentrate of 20%CodDescription Unit Quantity Rate Amount

Details of cost of 100 litres###Chlorpyriphos E.C. 20% “ litre 100 150 15 000.00###Carriage of chemical quintal 1 5.32 5.32

TOTAL 15 005.32

101CodDescription Unit Quantity Rate Amount

Add 1% for water charges 150.05TOTAL 15 155.37Add for contractor’s profit and overheads @ 2 273.311,500%

Page 100: DAR_Vol_1

Cost for 100 litres 17 428.68Cost for 1 litre 174.29Say 174.3

2.3Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termitetreatment (excluding the cost of chemical emulsion):

2.35.1 : Along external wall where the apron is not provided using chemical emulsion @7.5 litres / sqm of the vertical surface of the substructure to a depth of 300 mmincluding excavation channel along the wall & rodding etc. complete:

2.35.1.1: With Chlorpyriphos/Lindane E.C. 20% with 1% concentration.

CodDescription Unit Quantity Rate AmountDetails of cost for 10 metresMaterials:Chlorpyriphos 1% concentration =10.0x0.30x7.5 = 22.5 litres

###Chlorpyriphos 20% E.C. required litre 1.125 to be 0.01.125 litres. supplied

free of costLabour

###Beldars (for excavating channel ) roddingin chemical spraying the emulssion andrefilling the same Day .33 135.25 44.63

###Sundries and rent of sprayer etc L.S. 13.52 1 13.52TOTAL 58.15Add 1 % for water charges .58TOTAL 58.73Add for contractor’s profit and overheads @ 8.811,500%Cost for 10 metres 67.54Cost for 1 metre 6.75Say 6.75

2.3Diluting and injecting chemica emulsion for POST-CONSTRUCTIONAL anti-termitetreatment (excluding the cost of chemical emulsion) :

2.35.2 : Along the external wall below concrete or masonry apron using chemical emulsion@ 2.25 litres per linear metre including drilling and plugging holes etc.

2.35.2.1 : With Chlorpyriphos/Lindane E.C. 20% with 1% concentration.CodDescription Unit Quantity Rate Amount

Details of cost for 10 metresMaterials:

###Chlorpyriphos 1% concentration litre 1.125 to be 0.022.5 litres supplied

free of costChlorpyriphos 20% required = 22.5/20 =1.125 litresLabour:

###Beldar (for drilling holes and inje Day .4 135.25 54.1chemical)

102CodDescription Unit Quantity Rate Amount###Sundries and rent of a sprayer a L.S. 35.88 1 35.88

making good the holes

Page 101: DAR_Vol_1

TOTAL 89.98Add 1 % for water charges .9TOTAL 90.88Add for contractor’s profit and overheads @ 13.631,500%Cost for 10 metres 104.51Cost for 1 metre 10.45Say 10.45

2.3Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termitetreatment (excluding the cost of chemical emulsion):

2.35.3 : Treatment of soil under existing floors using chemical emulsion @ one litre perhole, 300 mm apart including drilling 12 mm diameter holes and plugging withcement mortar 1 :2 (1 cement : 2 Coarse sand) to match the existing floor:

2.35.3.1 : With Chlorpyriphos/Lindane E.C. 20% with 1% concentration.CodDescription Unit Quantity Rate Amount

Details of cost for 9 sqm. (3 metre x 3 metre)No. of holes - 100 nos.Materials:Chlorpyriphos 1% required100x1 litre = 100 litres

###Chlorpyriphos 20% E.C. = 100/20 =litre 5 to be 0.0suppliedfree of cost

Labour:(For making holes & spraying)

###Beldars Day 2 135.25 270.5###Mason Ilnd class Day .5 141.6 70.8###Sundries, rent of sprayer and mo L.S. 35.88 1 35.88

TOTAL 377.18Add 1 % for water charges 3.77TOTAL 380.95Add for contractor’s profit and overheads @ 57.141,500%Cost for 9 square metre 438.09Cost per square metre 48.68Say 48.7

2.3Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termitetreatment (excluding the cost of chemical emulsion):

2.35.4 : Treatment of existing masonry using chemical emulsion @ one litre per hole at300 mm interval including drilling holes at 45 degree and plugging them with cementmortar 1:2 (1 cement: 2 coarse sand) to the full depth of the hole:

2.35.4.1: With Chlorpyriphos/Lindane E.C. 20% with 1% concentration.CodDescription Unit Quantity Rate Amount

Details of cost for 10 metresMaterials:No. of holes 10.0/0.30 = 33.33+1 = 34.33holesSay 34 holes

103

Page 102: DAR_Vol_1

CodDescription Unit Quantity Rate Amountchlorpyriphos 1% concentration required= 34x1.0 = 34.00 litresChlorpyriphos 20% E.C. required34.00/20= 1.70 litres

###Chlorpyriphos 20% concentrates litre 1.7 to be 0.0suppliedfree of cost

Labour:###Beldar (for making holes at 45 d Day .3 135.25 40.57

spraying the emulsion)###Mason Ilnd class Day .05 141.6 7.08###Sundries, rent of pump etc. L.S. 17.94 1 17.94

TOTAL 65.59Add 1% for water charges .66TOTAL 66.25Add for contractor’s profit and overheads @ 9.94Cost for 10 metres 76.19Cost for 1 metre 7.62Say 7.6

2.3Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termitetreatment (excluding the cost of chemical emulsion):

2.35.5: Treatment at points of contact of wood work by chemical emulsion Chlorpyriphos/Lindane (in oil or kerosene based solution) @ 0.5 litres per hole by drilling 6 mmdia holes at downward angle of 45 degree at 150 mm centre to centre and sealingthe same.

CodDescription Unit Quantity Rate AmountDetails of cost for 10 metresMaterials:No. of holes 10.0/0.15 = 66.67+1 = 67.67holesSay 68 holesChlordane 1% concentration required= 68 x 0.5 = 34.00 litres litre 1.7 to be 0.0

suppliedfree of cost

Chlordane 20% E.C. required34.00/20=1.70 litresChlordane 20% E.C. required = 34/20 = 1.7

###Kerosene oil = 34-1.7 = 32.30 litr litre 32.3 19 613.7Labour:

###Carpenter 2nd class (For making Day .2 141.6 28.32plugging the same)

###Beldar for injecting chemical Day .2 135.25 27.05###Sundries L.S. 17.94 1 17.94

TOTAL 687.01Add 1% for water charges 6.87TOTAL 693.88Add for contractor’s profit and overheads @ 104.081,500%Cost for 10 metres 797.96Cost for 1 metre 79.8Say 79.8

Page 103: DAR_Vol_1

1042.36 : Deduct for disposed soil not levelled and neatly dressed (against Item No. 2.6,&2.7)

CodDescription Unit Quantity Rate AmountDetails of cost for 10 cum.Labour-

###Mate Day .08 138.45 11.08###Beldar/Coolies Day .8 135.25 108.2

TOTAL 119.28Add 1 % for water charges 1.19TOTAL 120.47Add 15% for contractor’s profit and overheads 18.07Cost of 10 cum. 138.54Cost of 1 cum. 13.85Say 13.85

105

SUB HEAD : 3.0

MORTARS

Page 104: DAR_Vol_1

107### Cement Mortar 1 : 1 (1 cement : 1 fine sand)

Code Discription Unit Quantity Rate Amount

Details of cost for 1 cumMATERIALS(0.7175 cum. of cement = 1.02 tonne)

### Cement tonne 1.02 4 500.00 4 590.00### Carriage of Cement tonne 1.02 47.29 48.24### Fine sand cum .7125 320 228### Carriage of Fine sand cum .7125 53.21 37.91

LABOURFor measuring, carrying, depositing andmixing-

### Beldar Day .75 135.25 101.44### Bhisti Day .07 138.45 9.69### Hire and running charL.S. 26.9 1 26.91### Sundries L.S. 13.52 1 13.52

Cost of 1.00 cum 5 055.71Say 5 055.70

Notes:-1 Cement required for cement mortar is 71.25%2 1 Cum of cement weight is 1.1286 Tonne

### Cement Mortar 1 : 2 (1 cement : 1 fine sand)

Code Discription Unit Quantity Rate Amount

Details of cost for 1 cumMATERIALS(0.475 cum. of cement = 0.68 tonne)

### Cement tonne .68 4 500.00 3 060.00### Carriage of Cement tonne .68 47.29 32.16### Fine sand cum .95 320 304### Carriage of fine sand cum .95 53.21 50.55

LABOURFor measuring, carrying, depositing andmixing-

### Beldar Day .75 135.25 101.44### Bhisti Day .07 138.45 9.69### Hire and running charL.S. 26.91 1 26.91### Sundries L.S. 13.52 1 13.52

Cost of 1.00 cum 3 598.27Say 3 598.25

Note:-1 Cement required is 47.50%

108### Cement Mortar 1 : 3(1 cement : 3 fine sand)

Code Discription Unit Quantity Rate Amount

Page 105: DAR_Vol_1

Details of cost for 1 cumMATERIALS(0.375 cum. of cement = 0.51 tonne)

### Cement tonne .51 4 500.00 2,295### Carriage of Cement tonne .51 47.29 24.12### Fine sand cum 1.07 320 342.4### Carriage of fine sand cum 1.07 53.21 56.93

LABOURFor measuring, carrying, depositing andmixing-

### Beldar Day .75 135.25 101.44### Bhisti Day .07 138.45 9.69### Hire and running charL.S. 26.91 1 26.91### Sundries L.S. 13.52 1 13.52

Cost of 1.00 cum 2,870.01Say 2,870

Note:-1 Cement required is 35.70%

### Cement Mortar 1 : 4(1 cement : 4 fine sand)

Code Discription Unit Quantity Rate Amount

Details of cost for 1 cumMATERIALS(0.268 cum. of cement = 0.38 tonne)

### Cement tonne .38 4 500.00 1,710### Carriage of Cement tonne .38 47.29 17.97### Fine sand cum 1.07 320 342.4### Carriage of fine sand cum 1.07 53.21 56.93

LABOURFor measuring, carrying, depositing andmixing-

### Beldar Day .75 135.25 101.44### Bhisti Day .07 138.45 9.69### Hire and running charL.S. 26.91 1 26.91### Sundries L.S. 13.52 1 13.52

Cost of 1.00 cum 2,278.86Say 2,278.85

Note:-1 Cement required is 26.80%

109### Cement Mortar 1 : 5 (1 cement : 5 fine sand)

Code Discription Unit Quantity Rate Amount

Details of cost for 1 cumMATERIALS(0.214 cum. of cement = 0.31 tonne)

### Cement tonne .31 4 500.00 1,395### Carriage of Cement tonne .31 47.29 14.66### Fine sand cum 1.07 320 342.4### Carriage of fine sand cum 1.07 53.21 56.93

Page 106: DAR_Vol_1

LABOURFor measuring, carrying, depositing andmixing-

### Beldar Day .75 135.25 101.44### Bhisti Day .07 138.45 9.69### Hire and running charges of mec L.S. 26.91 1 26.91### Sundries L.S. 13.52 1 13.52

Cost of 1.00 cum 1,960.55Say 1,960.55

Note:-1 Cement required is 21.40%

### Cement Mortar 1 : 6 (1 cement : 6 fine sand)

Code Discription Unit Quantity Rate AmountDetails of cost for 1 cumMATERIALS(0.178 cum. of cement = 0.25 tonne)

### Cement tonne .25 4 500.00 1,125### Carriage of Cement tonne .25 47.29 11.82### Fine sand cum 1.07 320 342.4### Carriage of fine sand cum 1.07 53.21 56.93

LABOURFor measuring, carrying, depositing andmixing-

### Beldar Day .75 135.25 101.44### Bhisti Day .07 138.45 9.69### Hire and running charges of mec L.S. 26.91 1 26.91### Sundries L.S. 13.52 1 13.52

Cost of 1.00 cum 1,687.71Say 1,687.7

Note:-1 Cement required is 17.80%

110### Cement Mortar 1 : 2 (1 Cement : 2 Coarse sand)

Code Discription Unit Quantity Rate Amount

Details of cost for 1 cumMATERIALS(0.476 cum. of cement = 0.68 tonne)

### Cement tonne .68 4 500.00 3,060### Carriage of Cement tonne .68 47.29 32.16### Coarse sand cum 1.95 600 570### Carriage of Coarse sa cum 1.95 53.21 50.55

LABOURFor measuring, carrying, depositing andmixing-

### Beldar Day .75 135.25 101.44### Bhisti Day .07 138.45 9.69### Hire and running charL.S. 26.91 1 26.91

Page 107: DAR_Vol_1

### Sundries L.S. 13.52 1 13.52Cost of 1.00 cum 3,864.27Say 3,864.25

Note:-1 Cement required is 47.50%

### Cement Mortar 1 : 3 (1 Cement : 3 Coarse sand)

Code Discription Unit Quantity Rate Amount

Details of cost for 1 cumMATERIALS(0.357 cum. of cement = 0.51 tonne)

### Cement tonne .51 4 500.00 2,295### Carriage of Cement tonne .51 47.29 24.12### Coarse sand cum 1.07 600 642### Carriage of Coarse sa cum 1.07 53.21 56.93

LABOURFor measuring, carrying, depositing andmixing-

### Beldar Day .75 135.25 101.44### Bhisti Day .07 138.45 9.69### Hire and running charL.S. 26.91 1 26.91### Sundries L.S. 13.52 1 13.52

Cost of 1.00 cum 3,169.61Say 3,169.6

Note:-1 Cement required is 35.70%

111### Cement Mortar 1 : 4 (1 cement : 4 coarse sand)

Code Discription Unit Quantity Rate Amount

Details of cost for 1 cumMATERIALS(0.214 cum. of cement = 0.31 tonne)

### Cement tonne .38 4 500.00 1,710### Carriage of tonne .38 47.29 17.97### Coarse sandcum 1.07 600 642### Carriage of cum 1.07 53.21 56.93

LABOURFor measuring, carrying, depositing andmixing-

### Beldar Day .75 135.25 101.44### Bhisti Day .07 138.45 9.69### Hire and ru L.S. 26.91 1 26.91### Sundries L.S. 13.52 1 13.52

Cost of 1.00 cum 2,578.46Say 2,578.45

Note:-1 Cement required is 26.80%

Page 108: DAR_Vol_1

### Cement Mortar 1 : 5 (1 cement : 5 coarse sand)

Code Discription Unit Quantity Rate Amount

Details of cost for 1 cumMATERIALS(0.214cum. of cement = 0.31 tonne)

### Cement tonne .31 4 500.00 1,395### Carriage of tonne .31 47.29 14.66### Coarse sandcum 1.07 600 642### Carriage of cum 1.07 53.21 56.93

LABOURFor measuring, carrying, depositing andmixing-

### Beldar Day .75 135.25 101.44### Bhisti Day .07 138.45 9.69### Hire and ru L.S. 26.91 1 26.91### Sundries L.S. 13.52 1 13.52

Cost of 1.00 cum 2,260.15Say 2,260.15

Note:-1 Cement required is 21.40%

112### Cement Mortar 1 : 6 (1 cement : 6 coarse sand)

Code Discription Unit Quantity Rate Amount

Details of cost for 1 cumMATERIALS(0.178 cum. of cement = 0.25 tonne)

### Cement tonne .25 4 500.00 1,125### Carriage of Cement tonne .25 47.29 11.82### Coarse sand cum 1.07 600 642### Carriage of Coarse sa cum 1.07 53.21 56.93

LABOURFor measuring, carrying, depositing andmixing-

### Beldar Day .75 135.25 101.44### Bhisti Day .07 138.45 9.69### Hire and running charL.S. 26.91 1 26.91### Sundries L.S. 13.52 1 13.52

Cost of 1.00 cum 1,987.31Say 1,987.3

Note:-1 Cement required is 17.80%

### Cement Mortar 1 : 2(1 cement : 2 stone dust)

Code Discription Unit Quantity Rate Amount

Details of cost for 1 cum

Page 109: DAR_Vol_1

MATERIALS(0.475 cum. of cement = 0.68 tonne)

### Cement tonne .68 4 500.00 3,060### Carriage of Cement tonne .68 47.29 32.16### Stone dust cum .95 700 665### Carriage of stone dus cum .95 53.21 50.55

LABOURFor measuring, carrying, depositing andmixing-

### Beldar Day .75 135.25 101.44### Bhisti Day .07 138.45 9.69### Hire and running charL.S. 26.91 1 26.91### Sundries L.S. 13.52 1 13.52

Cost of 1.00 cum 3,959.27Say 3,959.25

Note:-1 Cement required is 47.50%

113### Cement Mortar 1 : 2(1 cement : 2 marble dust)

Code Discription Unit Quantity Rate Amount

Details of cost for 1 cumMATERIALS(0.475 cum. of cement = 0.68 tonne)

### Cement tonne .68 4 500.00 3,060### Carriage of Cement tonne .68 47.29 32.16### Marble dust cum .95 800 760### Carriage of Marble ducum .95 53.21 50.55

LABOURFor measuring, carrying, depositing andmixing-

### Beldar Day .75 135.25 101.44### Bhisti Day .07 138.45 9.69### Hire and running charL.S. 26.91 1 26.91### Sundries L.S. 13.52 1 13.52

Cost of 1.00 cum 4,054.27Say 4,054.25

Note:-1 Cement required is 47.50%

### Cement Mortar 1 : 5(1 cement : 5marble dust)

Code Discription Unit Quantity Rate AmountDetails of cost for 1 cumMATERIALS(0.214 cum. of cement = 0.31 tonne)

### Cement tonne .31 4 500.00 1,395### Carriage of Cement tonne .31 47.29 14.66### Marble dust cum 1.07 800 856### Carriage of Marble ducum 1.07 53.21 56.93

LABOUR

Page 110: DAR_Vol_1

For measuring, carrying, depositing andmixing-

### Beldar Day .75 135.25 101.44### Bhisti Day .07 138.45 9.69### Hire and running charL.S. 26.91 1 26.91### Sundries L.S. 13.52 1 13.52

Cost of 1.00 cum 2,474.15Say 2,474.15

Note:-1 Cement required is 21.40%

114### White Cement Mortar 1 : 2 (1 White cement : 2 marble dust)

Code Discription Unit Quantity Rate Amount

Details of cost for 1 cumMATERIALS(0.475 cum. of white cement = 0.68 tonne)

### White Cement tonne .68 9,700 6,596### Carriage of White Ce tonne .68 47.29 32.16### Marble dust cum .95 800 760### Carriage of Marble ducum .95 53.21 50.55

LABOURFor measuring, carrying, depositing andmixing-

### Beldar Day .75 135.25 101.44### Bhisti Day .07 138.45 9.69### Hire and running charL..S 26.91 1 26.91### Sundries L..S 13.52 1 13.52

Cost of 1.00 cum 7,590.27Say 7,590.25

Note:-1 White Cement required is 47.50%

### White Cement Mortar 1 : 3(1 white cement : 3 marble dust)

Code Discription Unit Quantity Rate Amount

Details of cost for 1 cumMATERIALS(0.357 cum. of white cement = 0.51 tonne)

### White Cement tonne .51 9,700 4,747### Carriage of White Ce tonne .51 47.29 24.12### Marble dust cum 1.07 800 856### Carriage of Marble ducum 1.07 53.21 56.93

LABOUR Day .75 135.25 101.44For measuring, carryi Day .07 138.45 9.69mixing- L.S. 26.91 1 26.91

### Beldar L.S. 13.52 1 13.52### Bhisti 6,035.61### Hire and running charges of mechanical mixer 6,035.6### Sundries

Page 111: DAR_Vol_1

Cost of 1.00 cumSay

Note:-1 White Cement required is 35.70%

115### White Cement Mortar 1 : 5 (1 white cement : 5 marble dust)

Code Discription Unit Quantity Rate Amount

Details of cost for 1 cumMATERIALS(0.214 cum. of white cement = 0.31 tonne)

### White Cement tonne .31 9,700 3,007### Carriage of White Ce tonne .31 47.29 14.66### Marble dust cum 1.07 800 856### Carriage of Marble ducum 1.07 53.21 56.93

LABOURFor measuring, carrying, depositing andmixing-

### Beldar Day .75 135.25 101.44### Bhisti Day .07 138.45 9.69### Hire and running charL.S. 26.91 1 26.91### Sundries L.S. 13.52 1 13.52

Cost of 1.00 cum 4,086.15Say 4,086.15

Note:-1 White Cement required is 21.40%

### Mud mortar

Code Discription Unit Quantity Rate Amount

Detail of cost for one cumMATERIALS

### Mud (dry) cum 1.08 20 21.6LABOUR

### Beldar Day .63 135.25 85.21### Bhisti Day .315 138.45 43.61### Sundries L.S. 6.45 1 6.45

TOTAL 156.87Cost of one cum 156.87Say 156.85

117

Page 112: DAR_Vol_1

SUB HEAD : 4.0

CONCRETE WORK

119### Providing and laying in position cement concrete of specified grade excluding the

cost of centring and shuttering --All work upto plinth level:

4.11:1:2 ( 1 Cement: 1 coarse sand : 2 graded stone aggregate 20 mm nominal size)

Code Discription Unit Quantity Rate

Details of cost for 1 cumMATERIALS

###Stone aggregate 20mm cum .64 700###Stone aggregate 10mm cum 0.21 700.00 147.00###Carriage of aggregate 20mm and 10 mm cum .85 53.21###Coarse sand cum 0.425 600.00 255.00###Carriage of coarse sand cum 0.425 53.21###Cement (0.425 cum) tonne .61 4,500###Carriage of cement tunne .61 47.29

Labour;###Mason Day .1 146.55###Beldar Day 1.63 135.25###Bhishti Day .7 138.452 Mixer Day .07 40012 Vibrator Day .07 200###Sundries L.S 14.3 1

TOTAL

Page 113: DAR_Vol_1

Add 1% for water chargesTOTALAdd 15 % for contractor’s profit and overheadsCost of 1 cum.Say

### Providing and laying in position cement concrete of specified grade excluding thecost of centring and shuttering --All work upto plinth level:1 1

4.11:1 / :3 2 2Code Discription Unit Quantity Rate

Details of cost for 1 cum.Materials :

### Stone aggregate 20mm cum .57 700### Stone aggregate 10mm cum .28 700### Carriage of aggregate cum .85 53.21### Coarse sand cum .425 600### Carriage of coarse sand cum .425 53.21### Cement (0.2833 cum) tonne 0.40 4,500.00### Carriage of cement tonne .4 47.29

Labour:### Mason Day .1 146.55### Beldar Day 1.63 135.25### Bhishti Day .7 138.452 Mixer Day 0.07 40012 Vibrator Day .07 200### Sundries L.S. 14.30 1

TOTALAdd 1 % for water chargesTOTAL, 15 % for contractor’s profit andoverheads Cost of 1 cum.Say

120### Providing and laying in position cement concrete of specified grade excluding the

cost of centring and shuttering --All work upto plinth level:

4.11:2:4 ( 1 Cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)

CodDiscription Unit Quantity Rate Amount

Details of cost for 1 cum.Materials:

###Stone aggregate 20mm cum .67 700 469###Stone aggregate 10 mm cum .22 700 154###Carriage of aggregate cum .89 53.21 47.36###Coarse sand cum .445 600 2672203 Carriage of coarse sand cum .445 53.21 23.68###Cement (0.2833 cum) tonne .32 4,500 1,440###Carriage of cement tonne .32 47.29 15.13

Labour:

Page 114: DAR_Vol_1

###Mason Day .1 146.55 14.66###Beldar Day 1.63 135.25 220.46###Bhishti Day .7 138.45 96.922 Mixer Day .07 400 2812 Vibrator Day .07 200 14###Sundries L.S 14.3 1 14.3

TOTAL 2,804.54Add 1 % for water charges 28.05TOTAL 2,832.56Add. 15% for contractor’s profit and overheads 424.88Cost of 1 cum. 3,257.44Say 3,257.45

### Providing and laying in position cement concrete of specified grade excluding thecost of centring and shuttering --All work upto plinth level:

4.11:2:4 ( 1 Cement: 2 coarse sand : 4 graded stone aggregate 40 mm nominal size)CodDiscription Unit Quantity Rate Amount

Details of cost for 1 cum.Materials :

###Stone aggregate 40mm (one size)cum .52 650 338for voids) i.e. 0.04 = 0.52 cum)

###Stone aggregate 20mm (one size cum .22 700 154###Stone aggregate 10mm (one size cum .11 700 77###Carriage of aggregate 40mm cum .52 57.83 30.07###Carriage of aggregate below 40mm size cum .33 53.21 17.56###Coarse sand cum 0.445 600 267###Carriage of coarse sand cum .445 53.21 23.68###Cement (0.2225 cum) tonne 0.32 4500.00 1,440###Carriage of cement tonne .32 47.29 15.13

Labour:###Mason Day .1 146.55 14.66###Beldar Day 1.63 135.55 220.46###Bhishti Day .7 138.45 96.922 Mixer Day .07 400 2812 Vibrator Day .07 200 14###Sundries L.S. 13.52 1 13.52

TOTAL 2,750Add 1% for water charges 27.5TOTAL 2,777.5Add 15% for contractor’s profit and overheads 416.62Cost of 1 cum. 3,194.12Say 3,194.1

121### Providing and laying in position cement concrete of specified grade excluding the

cost of centring and shuttering --All work upto plinth level:

4.11:3:6 ( 1 Cement: 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)CodDiscription Unit Quantity Rate Amount

Details of cost for 1 cum.Materials :

Page 115: DAR_Vol_1

###Stone aggregate 20mm cum .7 700 490###Stone aggregate 10 mm cum .24 700 168###Carriage of aggregate cum .94 53.21 50.02###Coarse sand cum .47 600 282###Carriage of coarse sand cum .47 53.21 25.01###Cement (0.15674 cum) tonne .22 4,500 990###Carriage of cement tonne .22 47.29 10.4

Labour:###Mason Day .1 146.55 14.66###Beldar Day 1.63 135.25 220.46###Bhishti Day .7 138.45 96.922 Mixer Day .07 400 2812 Vibrator Day .07 200 14###Sundries L.S. 13.52 2.6 13.52

TOTAL 2,402.99Add 1 % for water charges 24.03TOTAL, 2,427.02Add 15% for contractor’s profit and overheads 364.05Cost of 1 cum. 2,791.07Say 2,791.05

### Providing and laying in position cement concrete of specified grade excluding thecost of centring and shuttering --All work upto plinth level:

4.11:3:6 ( 1 Cement: 3 coarse sand : 6 graded stone aggregate 40 mm nominal size)CodDiscription Unit Quantity Rate Amount

Details of cost for 1 cum.Materials :

###Stone aggregate 40mm (one size)cum .65 650 422.5cum-7.5% for voids i.e. 0.05 = 0.65 cum

###Stone aggregate 20mm cum .24 700 168###Carriage of aggregate 40mm cum .65 57.83 37.59###Carriage of aggregate 20mm cum .24 53.21 12.77###Coarse sand cum .47 600 282###Carriage of coarse sand cum .47 53.21 25.01###Cement (0.15674 cum) tonne .22 4,500 990###Carriage of cement tonne .22 47.29 10.4

Labour:###Mason Day .1 146.55 14.66###Beldar Day 1.63 135.25 220.46###Bhishti Day .7 138.45 96.922 Mixer Day .07 400 2812 Vibrator Day .07 200 14###Sundries L.S. 13.52 1 13.52

TOTAL 2,335.83Add 1% for water charges 23.36TOTAL 2,359.19Add 15% for contractor’s profit and overheads 353.88Cost of 1 cum. 2,713.07Say 2,713.05

122### Providing and laying in position cement concrete of specified grade excluding the

cost of centring and shuttering -

Page 116: DAR_Vol_1

-All work upto plinth level:4.11:3:6 ( 1 Cement: 3 fine sand : 6 graded stone aggregate 40 mm nominal size)

CodDiscription Unit Quantity Rate AmountDetails of cost for 1 cum.Materials :

###Stone aggregate 40mm (one size)cum .65 650 422.5cum-7.5% for voids i.e. 0.05 = 0.65 cum

###Stone aggregate 20 mm (one sizecum .24 700 168###Carriage of aggregate 40mm cum .65 57.83 37.59###Carriage of aggregate 20mm cum .24 53.21 12.77###Fine sand cum .47 320 150.4###Carriage of fine sand cum .47 53.21 25.01###Cement (0.15674 cum) tonne .22 4,500 990###Carriage of cement tonne .22 47.29 10.4

Labour:###Mason Day .1 146.55 14.66###Beldar Day 1.63 135.25 220.46###Bhishti Day .7 138.45 96.922 Mixer Day .07 400 2812 Vibrator Day .07 200 14###Sundries L.S. 13.52 1 13.52

TOTAL 2,204.23Add 1% for water charges 22.04TOTAL 2,226.27Add 15% for contractor’s profit and overheads 333.94Cost of 1 cum. 2,560.21Say 2,560.2

### Providing and laying in position cement concrete of specified grade excluding thecost of centring and shuttering -All work upto plinth level:

4.11:4:8 ( 1 Cement: 4 coarse sand : 8 graded stone aggregate 40 mm nominal size)CodDiscription Unit Quantity Rate Amount

Details of cost for 1 cum.Materials :

###Stone aggregate 40mm (one size)cum .65 650 422.5cum-7.5% for voids i.e. 0.05 = 0.65 cum

###Stone aggregate 20 mm cum .24 700 168###Carriage of aggregate 40mm cum .65 57.83 37.59###Carriage of aggregate 20mm cum .24 53.21 12.77###Corase sand cum .47 600 282###Carriage of coarse sand cum .47 53.21 25.01###Cement (0.1175 cum) tonne .17 4,500 765###Carriage of cement tonne .17 47.29 8.04

Labour:###Mason Day .1 146.55 14.66###Beldar Day 1.63 135.25 220.46###Bhishti Day .7 138.45 96.922 Mixer Day .07 400 2812 Vibrator Day .07 200 14###Sundries L.S. 13.52 1 13.52

TOTAL 2,208.47Add 1% for water charges 21.08TOTAL 2,129.55Add 15% for contractor’s profit and overheads 319.43Cost of 1 cum. 2,448.98Say 2,449

Page 117: DAR_Vol_1

123

### Providing and laying in position cement concrete of specified grade excluding thecost of centring and shuttering --All work upto plinth level:

4.11:4:8 ( 1 Cement: 4 fine sand : 8 graded stone aggregate 40 mm nominal size)CodDiscription Unit Quantity Rate

Details of cost for 1 cum.Materials :

###Stone aggregate 40mm (one size)cum .65 650cum-7.5% for voids i.e. 0.05 = 0.65 cum

###Stone aggregate 20 mm (One sizecum .24 700###Carriage of aggregate 40mm cum .65 57.83###Carriage of aggregate 20mm cum .24 53.21###Fine sand cum .47 320###Carriage of fine sand cum .47 53.21###Cement (0.1175 cum) tonne .17 4,500###Carriage of cement tonne .17 47.29

Labour:###Mason Day .1 146.55

###Beldar Day 1.63 1 135.25###Bhishti Day .7 138.452 Mixer Day .07 40012 Vibrator Day .07 200###Sundries L.S. 13.52 1

TOTALAdd 1% for water chargesTOTALAdd 15% for contractor’s profit and overheadsCost of 1 cum.Say

### Providing and laying in position cement concrete of specified grade excluding thecost of centring and shuttering --All work upto plinth level:

4.1.10 1:5:10 ( 1 Cement: 5 coarse sand : 10 graded stone aggregate 40 mm nominal size)CodDiscription Unit Quantity Rate

Details of cost for 1 cum.Materials :

###Stone aggregate 40mm (one size)cum .65 650cum-7.5% for voids i.e. 0.05 = 0.65 cum

###Stone aggregate 20 mm (One sizecum .24 700###Carriage of aggregate 40mm cum .65 57.83###Carriage of aggregate 20mm cum .24 53.21###Coarse sand cum .47 320###Carriage of coarse sand cum .47 53.21###Cement (0.2225 cum) tonne .13 4,500###Carriage of cement tonne .13 47.29

Labour:###Mason Day .1 146.55###Beldar Day 1.63 135.25

###Bhishti Day .7 1 138.452 Mixer Day .07 400

Page 118: DAR_Vol_1

12 Vibrator Day .07 200###Sundries L.S. 13.52 1

TOTALAdd 1% for water chargesTOTALAdd 15% for contractor’s profit and overheadsCost of 1 cum.Say

124### Providing and laying in position cement concrete of specified grade excluding the

cost of centring and shuttering --All work upto plinth level:

4.1.11 1:5:10 ( 1 Cement: 5 fine sand : 10 graded stone aggregate 40 mm nominal size)CodDiscription Unit Quantity Rate Amount

Details of cost for 1 cum.Materials :

###Stone aggregate 40mm (one size)cum .65 650 422.5cum-7.5% for voids i.e. 0.05 = 0.65 cum

###Stone aggregate 20 mm (One sizecum .24 700 168###Carriage of aggregate 40mm cum .65 57.83 37.59###Carriage of aggregate 20mm cum .24 53.21 12.77###Fine sand cum .47 320 150.4###Carriage of fine sand cum .47 53.21 25.01###Cement (0.2225 cum) tonne .13 4,500 585###Carriage of cement tonne .13 47.29 6.15

Labour:###Mason Day .1 146.55 14.66

###Beldar Day 1.63 1 135.25 220.46###Bhishti Day .7 138.45 96.922 Mixer Day .07 400 2812 Vibrator Day .07 200 14###Sundries L.S. 8.97 1 8.97

TOTAL 1,790.43Add 1% for water charges 17.9TOTAL 1,808.33Add 15% for contractor’s profit and overheads 271.25Cost of 1 cum. 2,079.58Say 2,079.6

### Providing and laying in position cement concrete of specified grade excluding thecost of centring and shuttering --All work upto plinth level:1 1

4.12 2

aggregate 40 mm nominalCodDiscription Unit Quantity Rate Amount

Details of cos tfor 1 cum.Materials:

###Stone aggregate 40mm (one size)cum .65 650 422.5cum-7.5% for voids i.e. 0.05-0.65 cum)

###Stone aggregate 20 mm (one sizecum .24 700 168

Page 119: DAR_Vol_1

###Carriage of aggregate 40 mm cum .65 57.83 37.5###Carriage of agregate 20 mm cum .24 53.21 12.77###Coarse sand cum .37 600 222###Carriage of coarse sand cum .37 53.21 19.69###Fly ash cum .21 6 1.26###Carriage of fly ash cum .21 53.21 11.17###Cement tonne 0.17 4,500.00 765###Carriage of cement tonne .17 47.29 8.04

LABOUR;###Mason Day .1 146.55 14.66###Beldar Day 1.63 135.25 220.46###Bhishti Day .7 138.45 96.922 Mixer Day .07 400 2812 Vibrator Day 14.30 200 14.1###Sundries L.S. 1 14.3 14.3

125

CodDiscription Unit Quantity Rate AmountTOTAL 2,056.3Add 1% for water charges 20.56TOTAL 2,076.92Add 15% for contractor’s profits and overheads 311.54Cost of 1 cum. 2,388.46Say 2,388.45

### Providing and laying in position cement concrete of specified grade excluding thecost of centring and shuttering --All work upto plinth level:

1

4.1.13 1:2 1/2:4:11( 1 Ordinar2

stone aggregate 40 mm nominalCodDiscription Unit Quantity Rate Amount

Details of cost for 1 cum.Materials :

###Stone aggregate 40mm (one size)cum .65 650 422.5cum-7.5% for voids i.e. 0.05 - 0.65 cum)

###Stone aggregate 20 mm (one sizecum .24 700 168###Carriage of aggregate 40mm cum .65 57.83 37.59###Carriage of aggregate 20mm cum .24 53.21 12.77###Coarse sand cum .34 600 204###Carriage of coarse sand cum .34 53.21 18.09###Fly ash cum .21 6 1.26###Carriage of fly ash cum .21 53.21 11.17###Cement tonne .13 4,500 585###Carriage of cement tonne .13 47.29 6.15

LABOUR:###Mason Day .1 146.55 14.66###Beldar Day 1.63 135.25 220.46###Bhishti Day .7 138.45 96.922 Mixer Day .07 400 2812 Vibrator Day .07 200 14###Sundries L.S. 14.3 2.6 14.3

Page 120: DAR_Vol_1

TOTAL 1,854.87Add 1% for water charges 18.55TOTAL 1,873.42Add 15% for contractor’s profit and overheads 281.01Cost of 1 cum. 2,154.43Say 2,154.45

126### Providing and laying cement concrete in retaining walls, return walls (any thick-

ness) including attached pilasters, columns, piers, abutmets, pillars, posts, struts,buttresses, string or lacing courses, parapets, coping bed blocks, anchor blocks,plain window sills, fillets etc upto floor five level, excluding the cost of centring,shuttering and finishing:

4.21:1:2 (1 cement: 1 coarse sand : 2 graded stone aggregate 20 mm nominal size)CodDiscription Unit Quantity Rate Amount

Details of cost for 1 cum.Materials:

###Stone aggregate 20mm cum .64 700 448###Stone aggregate 10 mm cum .21 700 147###Carriage of aggregate 20mm an cum .85 53.21 45.23###Coarse sand cum .425 700 255###Carriage of coarse sand cum .425 53.21 22.61###Cement (0.425 cum) tonne .61 4,500 2,745###Carriage of cement tonne .61 47.29 28.85

Labour:###Beldar Day .9 135.25 121.72###Coolie Day .78 135.25 105.5###Bhishti Day .7 138.45 96.92###Mason 1st class Day .06 151.5 9.09###Mason Ilnd class Day .06 141.6 8.52 Mixer Day .07 400 2812 Vibrator Day .07 200 14###Scaffolding L.S. 114.4 1 114.4###Sundries L.S. 14.3 1 14.3###(Extra labour for lifting.material Day 1.13 135.25 152.83

level) Coolie (0.75x1.50)TOTAL 4,356.95Add 1 % for water charges 43.57TOTAL 4,400.52Add 15% for contractor’s profit and overheads 660.08Cost of 1 cum. 5,060.6Say 5,060.6

### Providing and laying cement concrete in retaining walls, return walls (any thick-ness) including attached pilasters, columns, piers, abutmets, pillars, posts, struts,buttresses, string or lacing courses, parapets, coping bed blocks, anchor blocks,plain window sills, fillets etc upto floor five level, excluding the cost of centring,shuttering and finishing:1 1

4.21:1 / :3 2 2CodDiscription Unit Quantity Rate Amount

Page 121: DAR_Vol_1

Details of cost for 1 cum.Materials:

###20mm stone aggregate cum .57 700 399###Stone aggregate 10mm cum .28 700 196###Carriage of aggregate cum .85 53.21 45.23###Coarse sand cum .425 600 255###Carriage of coarse sand cum .425 53.21 22.61###Cement (0.2833 cum) tonne .4 4,500 1,800###Carriage of cement tonne .4 47.29 18.92

Labour:###Beldar Day .9 135.25 121.72

127CodDiscription Unit Quantity Rate Amount###Coolie Day .78 135.25 105.5###Bhishti Day .7 138.45 96.92###Mason 1st class Day .06 151.5 9.09###Mason Ilnd class Day .06 141.6 8.52 Mixer Day .07 400 2812 Vibrator Day .07 200 14###Scaffolding L.S. 114.4 1 114.4###Sundries L.S. 14.3 1 14.3###(Extra labour for lifting.material Day 1.13 135.25 152.83

level) Coolie (0.75x1.50)TOTAL 3,402.02Add 1 % for water charges 34.02TOTAL 3,436.04Add 15% for contractor’s profit and overheads 515.41Cost of 1 cum. 3,951.45Say 3,951.45

### Providing and laying cement Concrte in retaining walls, return walls (any thickness)including attached pilasters, columns, piers, abutmets, pillars, posts, struts, buttresses,string or lacing courses, parapets, coping bed blocks, anchor blocks, plain windowsills, fillets etc upto floor five level, excluding the cost of centring, shuttering andfinishing:

4.21:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)CodDiscription Unit Quantity Rate Amount

Details of cost for 1 cum.Materials:

###Stone aggregate 20 mm cum .67 700 469###Stone aggregate 10 mm cum .22 700 154###Carriage of aggregate cum .89 53.21 47.36###Coarse sand cum .445 600 267###Carriage of coarse sand cum .445 53.21 23.68###Cement (0.2833 cum) tonne .32 4,500 1,440###Carriage of cement tonne .32 47.29 15.13

Labour:###Beldar Day .9 135.25 121.72###Coolie Day .78 135.25 105.5###Bhishti Day .7 138.45 96.92###Mason 1st class Day .06 151.5 9.09

Mason Ilnd class Day .06 141.6 8.5###

Page 122: DAR_Vol_1

2 Mixer Day .07 400 28Vibrator Day .07 200 14

12###Scaffolding L.S. 114.4 1

Sundries L.S. 14.3 1 14.3######(Extra labour for lifting.material Day 1.13 135.25 152.83

level) Coolie (0.75x1.50)TOTAL 3,081.43Add 1 % for water charges 30.81TOTAL 3,112.24Add 15% for contractor’s profit and overheads 466.84Cost of 1 cum. 3,579.08Say 3,579.1

128### Providing and laying cement Concrte in retaining walls, return walls (any thickness)

including attached pilasters, columns, piers, abutmets, pillars, posts, struts, buttresses,string or lacing courses, parapets, coping bed blocks, anchor blocks, plain windowsills, fillets etc upto floor five level, excluding the cost of centring, shuttering andfinishing:

4.21:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate 40 mm nominal size)CodDiscription Unit Quantity Rate Amount

Details of cost for 1 cum.Materials:

###Stone aggregate 40 mm (one sizecum .52 650 338for voids i.e. 0.04 = 0.52 cum)

###Stone aggregate 20 mm (one zizecum .22 700 154###Stone aggregate 10 mm (one sizecum .11 700 77###Carriage of aggregate 40 mm cum .52 57.83 30.07###Carriage of aggregate 20 mm an cum .33 53.21 17.56###Coarse sand cum .445 600 267###Carriage of coarse sand cum .445 53.21 23.68###Cement (0.2225 cum) tonne .32 4,500 1,440###Carriage of cement tonne .32 47.29 15.13

Labour:###Beldar Day .9 135.25 121.72###Coolie Day .78 135.25 105.5###Bhishti Day .7 138.45 96.92###Mason 1st class Day .06 151.5 9.09###Mason Ilnd class Day .06 141.6 8.52 Mixer Day .07 400 2812 Vibrator Day .07 200 14###Scaffolding L.S. 114.4 1###Sundries L.S. 13.52 1###(Extra labour for lifting.material Day 1.13 135.25 152.83

level) Coolie (0.75x1.50)TOTAL 3,026.92Add 1 % for water charges 30.27TOTAL 3,057.19Add 15% for contractor’s profit and overheads 458.58Cost of 1 cum. 3,515.77

114.40

114.40 13.52

Page 123: DAR_Vol_1

Say 3,515.75

129### Providing and laying cement Concrte in retaining walls, return walls (any thickness)

including attached pilasters, columns, piers, abutmets, pillars, posts, struts, buttresses,string or lacing courses, parapets, coping bed blocks, anchor blocks, plain windowsills, fillets etc upto floor five level, excluding the cost of centring, shuttering andfinishing:

4.21:3:6 (1 cement: 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)CodDiscription Unit Quantity Rate Amount

Details of cost for 1 cum.Materials:

###Stone aggregate 20 mm cum .7 700 490###Stone aggregate cum .24 700 168###Carriage of aggregate cum .94 53.21 50.02###Coarse sand cum .47 600 282###Carrage of Coarse sand cum .47 53.21 25.01###Cement tonne .22 4,500 990###Carriage of cement tonne .22 47.29 10.4

Labour:###Beldar Day .9 135.25 121.72###Coolie Day .78 135.25 105.5###Bhishti Day .7 138.45 96.92###Mason 1st class Day .06 151.5 9.09###Mason Ilnd class Day .06 141.6 8.52 Mixer Day .07 400 2812 Vibrator Day .07 200 14###Scaffolding L.S. 114.4 1 114.4###Sundries L.S. 13.52 1 13.52###(Extra labour for lifting.material Day 1.13 135.25 152.83

level) Coolie (0.75x1.50)TOTAL 2,679.91Add 1 % for water charges 26.8TOTAL 2,706.71Add 15% for contractor’s profit and overheads 406.01Cost of 1 cum. 3,112.72Say 3,112.7

### Providing and laying cement Concrte in retaining walls, return walls (any thickness)including attached pilasters, columns, piers, abutmets, pillars, posts, struts, buttresses,string or lacing courses, parapets, coping bed blocks, anchor blocks, plain windowsills, fillets etc upto floor five level, excluding the cost of centring, shuttering andfinishing:

4.21:3:6 (1 cement: 3 coarse sand : 6 graded stone aggregate 40 mm nominal size)CodDiscription Unit Quantity Rate Amount

Details of cost for 1 cum.Materials:

###Stone aggregate 40 mm (one sizecum .65 650 422.5cum 7.5% for voids i.e. 0.05 = 0.65 cum)

###Stone aggregate 20 mm (One sizecum .24 700 168###Carriage of aggregate 40 mm cum .65 57.83 37.59

Page 124: DAR_Vol_1

###Carriage of aggregate 20 mm cum .24 53.21 12.77###Coarse sand cum .47 600 282###Carriage of coarse sand cum .47 53.21 25.01###Cement (0.15674 cum) tonne .22 4,500 990###Carriage of cement tonne .22 47.29 10.4

Labour:

130CodDiscription Unit Quantity Rate Amount

###Beldar Day .9 135.25 121.72###Coolie Day .78 135.25 105.5###Bhishti Day .7 138.45 96.92###Mason 1st class Day .06 151.5 9.09###Mason Ilnd class Day .06 141.6 8.52 Mixer Day .07 400 2812 Vibrator Day .07 200 14###Scaffolding L.S. 114.4 1 114.4###Sundries L.S. 13.52 1 13.52###(Extra labour for lifting.material Day 1.13 135.25 152.83

level) Coolie (0.75x1.50)TOTAL 2,612.75Add 1 % for water charges 26.13TOTAL 2,638.88Add 15% for contractor’s profit and overheads 395.83Cost of 1 cum. 3,034.71Say 3,034.7

### Providing and laying cement Concrte in retaining walls, return walls (any thickness)including attached pilasters, columns, piers, abutmets, pillars, posts, struts, buttresses,string or lacing courses, parapets, coping bed blocks, anchor blocks, plain windowsills, fillets etc upto floor five level, excluding the cost of centring, shuttering andfinishing:

4.21:3:6 (1 cement: 3 fine sand : 6 graded stone aggregate 40 mm nominal size)CodDiscription Unit Quantity Rate Amount

Details of cost for 1 cum.Materials:

###Stone aggregate 40 mm(one size)cum .65 650 422.5cum 7.5% for voids i.e. 0.05 = 0.65 cum)

###Stone aggregate 20 mm cum .24 700 168###Carriage of aggregate 40 mm cum .65 57.83 37.59###Carriage of aggregate 20 mm cum .24 53.21 12.77###Fine sand cum .47 320 150.4###Carriage of fine sand cum .47 53.21 25.01###Cement (0.15674 cum) tonne .22 4,500 990###Carriage of cement tonne .22 47.29 10.4

Labour:###Beldar Day .9 135.25 121.72###Coolie Day .78 135.25 105.5###Bhishti Day .7 138.45 96.92###Mason 1st class Day .06 151.5 9.09###Mason Ilnd class Day .06 141.6 8.52 Mixer Day .07 400 2812 Vibrator Day .07 200 14

Page 125: DAR_Vol_1

###Scaffolding L.S. 114.4 1 114.4###Sundries L.S. 13.52 1 13.52###(Extra labour for lifting.material Day 1.13 135.25 152.83

level) Coolie (0.75x1.50)TOTAL 2,481.15Add 1 % for water charges 24.81TOTAL 2,505.96Add 15% for contractor’s profit and overheads 375.89Cost of 1 cum. 2,881.85Say 2,881.85

131### Centering shuttering including struttings, propping etc. and removal of form work

for:4.3Foundations, footings, bases for columns.

CodDiscription Unit Quantity Rate AmountDetails of cost for footing size2.7mx2.7mxl.00mContact area = 10.8 sqm.Material: Assuming shuttering material will becomeunserviceable after use of 40 timesAdding for maintenance @ 10% of costTaking salvage value after full use of material@ 25% of cost

###Wall form panel 1250x500mm each .34 980 333.2Qty taken for cost of using once = 16x0.85/40= 0.34

###Corner angle (1.5m long) each .085 280 23.8Qty taken for cost of using once = 4x0.85/40 =

.085###100mm channel shoulders 2.5m each .17 1,000 170

Qty taken for cost of using once = 8x0.85/40=.17

###Double clip (bridge clip) each .34 75 25.5Qty taken for cost of using once = 16x0.85/40= 0.34

###Single clip each .17 60 10.2Qty taken for cost of using once = 8x0.85/40 =

.17###MS tube 40mm - 4x2.7m = 10.8 metre .2295 225 51.64

Qty taken “for cost of using once =10.8x0.85/40 = 0.2295

###Assembly nuts & bolts L.S 22.1 1 22.1###Carriage L.S 78 1 78

Labour:###Fitter Grade-I Day .75 151.5 113.62###Beldar Day 1.5 135.25 202.88###Shuttering oil L.S 52 1 52###Sundries L.S 26 1 26

TOTAL 1,108.94Add 1% for water charges 11.09

Page 126: DAR_Vol_1

TOTAL ]S-%% 1,120.03Add-WMrfor contractor’s profit and overheads 168Cost for 10.8 sqm. 1,288.03Cost per sqm. 119.26Say 119.25

132### Centering shuttering including struttings, propping etc. and removal of form work

for:4.3Retaining walls, return walls, walls (any thickness) including attached pilasters, but-

tresses plinth and string courses fillets etc.

CodDiscription Unit Quantity Rate Amount

Details for 7.9m long and 1.00m high wallArea of contact 2x7.9x1.0 = 15.8 sqm. ——Materials:Assuming shuttering material will be unsevicea-ble after use of times Adding for maintenance @ 10% of costTaking salvage value after full use of material@ 25% of cost

7319 Wall form Panel (1.25x0.5) 2x3 each .51 98 499.8Nos.Qty taken for cost of using once = 24x0.85/40= 0.51 each .17 1,000 170

7327 100mm channel shoulder 2.5m long, 4x2 = 8Qty taken for cost of using once = 8x0.85/40 =

.177328 Bridge clip 2x6x2 = 24

Qty taken for cost of using once each .51 75 38.25= 0.51

7329 Single clip 2x3x2 = 12 each .255 60 15.3Qty taken for cost of using once = 12x0.85/40= 0.255

7330 M.S. Tube 40mm 2x2x8m = 32 metre .68 225 153Qty taken for cost of using once = 32x0.85/40= 0.68

9999 Nut & Bolts L.S 27.62 1 27.629999 Carriage L.S 78 1 78

Labour:###Fitter Grade-I Day 3.5 151.5 530.25###Beldar Day 6 135.25 811.5###Shuttering oil L.S 78 1 78###Sundries L.S 52 1 52

TOTAL 2,453.72Add 1 % for water charges 24.54TOTAL 2,478.26Add 15% for contractor’s profit and overheads 371.74Cost for 15.8 sqm. 2,850Cost per sqm. 180.38Say 180.4

### Centering shuttering including struttings, propping etc. and removal of form work

Page 127: DAR_Vol_1

for:4.3Columns, piers, abutments, pillaras, posts and struts.CodDiscription Unit Quantity Rate Amount

Detail of cost forSize of column 450x450mm and 2.5m highArea of contact = 4x0.45x2.5 = 4.5 sqm.

133CodDiscription Unit Quantity Rate Amount

Assuming shuttering will becomeunserviceable after use of 40 timesAdd maintenance charges @ 10% of cost ofMaterialLess salvage value of material after full use @25% of cost of material

###Wall form panel (1250x450) each .17 900 153Qty taken for cost of using once = 8x0.85/40 =

.17Corner angle 2.5m long each .085 275 23.38

###Qty taken for cost of using once = 4x0.85/40 =.085

Column clamp (450-1070mm) each .1063 1,100 116.93###Qty taken for cost of using once = 5x0.85/40 =

.1063Prop. 2m (2.0-3.5m) each .085 750 63.75

###Qty taken for cost of using once = 4x0.85/40 =.085

###Assembly nut & bolt L.S 27.62 1 27.62###Carriage L.S 52 1 52

Labour###Fitter Grade-I Day 1 151.5 151.5###Beldar Day 2 135.25 270.5###Shuttering oil L.S 39 1 39###Carriage L.S 26 1 26

TOTAL 923.68Add 1% for water charges 9.24TOTAL 932.92Add for contractor’s profit and overheads @ 139.941,500%Cost for 4.5 sqm. 1,072.86Cost per sqm. 238.41Say 238.4

### Providing and laying cement concrete in kerbs, steps and the like at or near groundlevel excluding the cost of centring, shuttering and finishing.

4.41:2:4 (1 Cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size).CodDiscription Unit Quantity Rate Amount

Details of cost for kerb :100m long 20cm deep and 30cm wide ).100m x 30m x 0.20m = 6.00 cum.Cement 1:2:4 cum 6 3,257.45 19,544.7(Rate as per item no 4.1.3Cost for 6 cum. 19,544.7Cost per cum. 3,257.45

Page 128: DAR_Vol_1

Say 3,257.45

134### Providing and laying cement concrete in kerbs, steps and the like at or near ground

level excluding the cost of centring, shuttering and finishing.4.41:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size).

Code Discription Unit Quantity Rate Amount

Details of cost for kerb :100m long 20cm deep and 30cm wide ).100m x 30m x 0.20m = 6.00 cum.Cement concrete 1:3:6 cum 6 2,791.05 16,746.3(Rate as per item no 4.1.5Cost for 6 cum. 16,746.3Cost per cum. 2,791.05Say 2,791.05

### Providing and fixing upto floor five level precast cement concrete string or lacingcourses, copings, bed plates, anchor blocks, plain window sills, shelves, louvers,steps, stair cases, etc. including hoisting and setting in position with cement mortar1:3 (1 Cement: 3 coarse sand), cost of required centring, shuttering and finishingsmooth with 6mm thick cement plaster 1:3 (1 Cement: 3 fine sand)

4.51:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate 20mm nominal size).

Code Discription Unit Quantity Rate AmountDetails of cost for Plain window sill 15 nos.15x1m x 0.20m x 0.15m = 0.45cum.Materials :Cement concrete 1:2:4

(A) (Rate as per Item No. 4.2.3 ) cum .45 3,579.1 1,610.6Centering and shuttering(1) Mould(i) Plate 3mm thick-(2x1xO.15)+(2xO.15xO.2O) = 0.36 sqm. @23.55kg/m2 = 8.48 kg.(ii) Flat 10x5mm4x1.0 = 4.0m8x0.2 = 1.6m4x0.15 = 0.60mHandle 2x0.25 = 0.5m=6.70 m @ 0.4kg/m = 2.68 kg.Total = 11.16kg. or 0.112 qtl.Assuming shuttering will becomeunserviceable after use of 40 times andtaking 75% credit.Qty taken for cost of using once =

(B) 0.112x0.75/40 = 0.0021 qtl kg .21 42.15 8.85(Rate as per item no.10.1 S.H. steel work)2. Moulding PlatformAssuming platform will becomeunserviceable after use of 40 times,(i) Brick on edge flooring cement mortar 1-:6

Page 129: DAR_Vol_1

1x2.0x2.0m = 4 sqm. Qty taken for cost ofusing once = 4/40 = 0.1 sqm

135Code Discription Unit Quantity Rate Amount

(C) Rate as per item no. 11.1.2 (S.H.: Flooring sqm .1 296.2 29.62work)(ii) 25mm thick cement concrete 1:2:4 inpavement2.00x2.00x0.025 = 0.10cumQty taken for cost of using once = 0.100/40= 0.0025 cum

(D) Rate as per item no. 16.42 (Road work) cum .0025 3,638.55 9.1Finishing15x0.50 = 7.50sqm.

(E) Rate as per item No. 13.16 sqm 7.5 62.15 466.13(G) Mortar and labour for hoisting and finishing L.S 36.3 1 36.3

TOTAL 2,160.59(H) Add for water charges @ 1 % on (G) .36

TOTAL 2,160.95Add for contractor’s profit and overheads @15%on(G+H) 5.5Cost for 0.45 cum. 2,133.45Cost per cum. 4,814.33Say 4,814.35

### Providing and fixing upto floor five level precast cement concrete string or lacingcourses, copings, bed plates, anchor blocks, plain window sills, shelves, louvers,steps, stair cases, etc. including hoisting and setting in position with cement mortar1:3 (1 Cement: 3 coarse sand), cost of required centring, shuttering and finishingsmooth with 6mm thick cement plaster 1:3 (1 Cement: 3 fine sand) on exposedsurfaces complete.

4.51:3:6 (1 cement: 2 coarse sand : 4 graded stoneaggregate 20mm nominal size).

Code Discription Unit Quantity Rate AmountDetails of cost for Plain window sill 15 nos.

15x1m x 0.20m x 0.15m = 0.45cum.Materials :Cement concrete 1:3:6

(A) (Rate as per Item No. 4.2.5 ) of (S.Hconcrete work cum .45 3,112.7 1,400.72Centering and shuttering(1) Mould(i) Plate 3mm thick(2x1x0.15)+(2x0.15x0.20) = 0.36 sqm. @23.55kg/m2 = 8.48 kg.(ii) Flat 10x5mm4x1.0 = 4.0m

Page 130: DAR_Vol_1

136CodDiscription Unit Quantity Rate Amount

8x0.2 = 1.6m4x0.15 = 0.60mHandle 2x0.25 = 0.5m=6.70m@ 0.4kg/m = 2.68 kg.Total = 11.16kg. or 0.112 qtl.Assuming shuttering will becomeunserviceable after use of 40 times andtaking 75% credit.Qty taken for cost of using once =0.112x0.75/40 = 0.0021 qtl(B) (Rate as per item no.10.1 S.H.kg .21 42.15 8.852. Moulding PlatformAssuming platform will becomeunserviceable after use of 40 times,(i) Brick on edge flooring cement mortar1:61x2.0x2.0m = 4 sqm Qty taken for cost of using once = 4/40 =0.1 sqm(C) Rate as per item no. 11.1.2 (S sqm .1 296.2 29.62work)(ii) 25mm thick cement concrete 1:2:4 inpavement2.00 x2.00x0.025 = 0.1Qty taken for cost of using once = 0.100/40 =0.0025 cum(D) Rate as per item no. 16.42 ( cum .0025 3,688.55 9.1Finishing15x0.50 = 7.50sqm.(E) Rate as per item No. 13.16 sqm 7.5 62.15 466.13(G) Mortar and labour for hoistin L.S 36.3 1 36.3TOTAL 1,950.71(H) Add for water charges @ 1 % on (G) .36TOTAL 1,951.07Add for contractor’s profit and overheads @15%on(G+H) 5.5Cost for 0.45 cum. 1,956.57Cost per cum. 4,347.93Say 4,347.95

137### Providing and fixing at or near ground level precast cement concrete in kerbs, edgings

etc. as per approved pattern and setting in position with cement mortar 1:3 (1 Ce-ment: 3 coarse sand) including the cost of required centring, shuttering and finish-ing smooth with 6mm thick cement plaster 1:3 (1 cement: 3 fine sand) on exposedsurfaces complete.

4.61:2:4 ( 1 cement: 2 coarse sand : 4 graded stone aggregate 20mm nominal size).Code Description Unit Quantity Rate Amount

Page 131: DAR_Vol_1

Details of cost for 25 no kerbs,40x30x20cm=25 no x 0.40m x 0.30m x 0.20m = 0.6 cumMaterials :Cement concrete 1:2:4

(A) Rate as per Item Nono. 4.1.3 cum .6 3,257.45 1,954.47Centering and shuttering(1) Mould(i) Plate 3mm thick0.28 sqm. @ 23.55kg/m2 = 6.59 kg.(ii) Flat 10x5mmHandle2x0.25 x0.4 = @ 0.4kg/m = 0.20 kg.= 6.79kg. or 0.068 qtl.Assuming shuttering will becomeunserviceable after use of 40 times andtaking 75% credit.Qty taken for cost of using once= 0.068x0.75/40 = 0.001275 qtl

(B) (Rate as per item no. 10.1 S.H. steel wor kg .1275 42.15 5.372. Moulding PlatformAssuming platform will becomeunserviceable after use of 40 times.(i) Brick on edge flooring cement mortar 1:61x2.0x2.0m = 4 sqm.Qty taken for cost of using once = 4/40= 0.1 sqm

(C ) Rate as per item no. 11.1.2 S.H.: Floorin kg .1 296.2 29.62work.(ii) 25mm thick cement concrete 1:2:4 inpavement2.00x2.00x0.025 = 0.10Qty taken for cost of using once = 0.100/40= 0.0025 cum

(D) (Rate as per item no. 16.42 (Road work) cum .0025 3,638.55 9.1Finishing0.4(0.3+0.2+0.20)=0.28x25 = 7.0sqm.

(E) (Rate as per item no. 13.16) sqm 7 62.15 435.05###(G) Mortar and labour for finishing L.S. 30.54 1 30.54

TOTAL 2,464.15(H) Add for water charges @ 1% on (G) .31

TOTAL 2,464.46Add for contractor’s profit and overheads @15%on(G+H) 4.63Cost for 0.60 cum. 2,469.09Cost per cum. 4,113.15Say 4,115.15

138### Providing and fixing upto floor five level precast cement concrete solid block

including hoisting and setting in position with cement mortar 1:3 (1 cement: 3 coarsesand), cost of required centring, shuttering and finishing smooth with 6mm thickcement plaster 1:3 (1 cement: 3 fine sand) on exposed surfaces complete :

Page 132: DAR_Vol_1

4.71:2:4 ( 1 cement: 2 coarse sand : 4 graded stone aggregate 20mm nominal size).

CodDescription Unit Quantity Rate AmountDetails of cost for 25 no blocks,40x20x30cm=25 no x 0.40m x 0.30m x 0.20m = 0.60 cumMaterials:Cement concrete 1:2:4Rate as per Item Nono. 4.1.3 cum .6 3,257.45 1,954.47Centering and shuttering(1) Mould(i) Plate 3mm thick0.28 sqm. @ 23.55kg/m2 = 6.59 kg.(ii) Flat 10x5mmHandle2x0.25 x0.4 = @ 0.4kg/m = 0.20 kg.= 6.79kg. or 0.068 qtl.Assuming shuttering will becomeunserviceable after use of 40 times andtaking 75% credit.Qty taken for cost of using once =0.068x0.75/40 = 0.001275 qtl(Rate as per item no. 10.1 S.H. st kg .1275 42.15 5.372. Moulding PlatformAssuming platform will becomeunserviceable after use of 40 times,(i) Brick on edge flooring cement mortar 1:61x2.0x2.0m = 4 sqm.Qty taken for cost of using once = 4/40 =0.1 sqmRate as per item no. 11.1.2 S.H.: Flooringwork. kg .1 296.2 29.62(ii) 25mm thick cement concrete 1:2:4 inpavement2.00x2.00x0.025 = 0.10Qty taken for cost of using once = 0.100/40= 0.0025 cum(Rate as per item no. 16.42 (Roa cum .0025 3,638.55 9.1Mortar 1:3 for Fixing(D) 0.202/100x25=0.051Rate as per item no 3.8 cum .051 3,169.6 161.65Extra for Labour for fixing(27/100x25=0.675 or 0.68)

###(D) Coolie day .68 135.25 91.97Labour for hoisting and setting in position

###(D) Mason 1st class day .6 151.5 90.9###(D) Beldar day 3.6 135.25 486.9

Finishing25x2(0.4x0.3) =6.0sqm.(Rate as per item no. 13.16) sqm 6 62.15 372.9TOTAL 320.88(E) Add for water charges @ 1 % on (D) 8.31TOTAL 3,211.19Add for contractor’s profit and overheads @15%on(D+E) 125.96Cost for 0.60 cum. 3,337.15Cost per cum. 5,561.62Say 5,561.9

Page 133: DAR_Vol_1

139### Providing and fixing upto floor five level precast cement concrete solid block

including hoisting and setting in position with cement mortar 1:3 (1 cement: 3 coarsesand), cost of required centring, shuttering and finishing smooth with 6mm thickcement plaster 1:3 (1 cement: 3 fine sand) on exposed surfaces complete :

4.71:3:6 (1 cement: 3 coarse sand : 6 graded stone aggregate 20mm nominal size).

CodDescription Unit Quantity Rate AmountDetails of cost for 25 no blocks,40x20x30cm=25 no x 0.40m x 0.30m x 0.20m = 0.6 cumMaterials:(A) Cement concrete 1:3:6(Rate as per Item no. 4.1.5 ) cum .6 2,791.05 1,674.63(B) Mortar for Fixing cement morcum .051 3,169.6 161.65(Rate as per item no. 3.8)Centering and shuttering(1) Mould(i) Plate 3mm thick.0.28 sqm. @ 23.55kg/m2 = 6.59 kg.(ii) Flat 10x5mm Handle2x0.25 xO.4 = @ 0.4kg/m = 0.20 kg.= 6.79kg. or 0.068 qtl.Assuming shuttering will becomeunserviceable after use of 40 times andtaking 75% credit.Qty taken for cost of using once= 0.068x0.75/40 = 0.001275 qtl(Rate as per item no.10.1 S.H. st kg .1275 42.15 5.372. Moulding PlatformAssuming platform will becomeunserviceable after use of 40 times,(i) Brick on edge flooring cement mortar 1:61x2.0x2.0m = 4 sqm.Qty taken for cost of using once = 4/40 =0.1 sqmRate as per item no. 11.1.2 S.H.: Flooringwork. sqm .1 296.2 29.62(ii) 25mm thick cement concrete 1:2:4 inpavement2.00x2.00x0.025 = 0.100Qty taken for cost of using once = 0.100/40= 0.0025 cum(Rate as per item no. 16.42 (Roa cum .0025 3,638.55 9.1Finishing sqm 6 62.15 372.9(Rate as per item no. 13.16Extra Labour for lifting material upto floor Vlevel

(C) Labour### Coolie day .68 135.25 91.97

(C) Labour for hoisting and setting in position### Mason 1st class day .6 151.5 90.9### Beldar day 3.6 135.25 486.9

TOTAL 2,923.04

Page 134: DAR_Vol_1

(D) Add for water charges @ 1 % on (B+C) 8.31TOTAL 2,931.35Add for contractor’s profit and overheads @15% on (B+C+D) 125.96Cost for 0.60 cum. 3,057.31Cost per cum. 5, 095.52Say 5,095.5

140### Providing and fixing upto floor five level precast cement concrete hollow block

including hoisting and setting in position with cement mortar 1:3 (1 cement : 3 coarsesand), cost of required centring, shuttering and finishing smooth with 6mm thickcement plaster 1:3 (1 cement: 3 fine sand) on exposed surfaces complete :

4.81:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate 20mm nominal size).CodDescription Unit Quantity Rate Amount

Details of cost for one block of overall size1m x 0.50m and 0.10m thick having 6 verticalhollows, 40x20x30cmfinished contents = 1mx0.5mx0.1m = 0.05cumMaterials:Cement concrete 1:2:4(A) Netqty = 0.05 [6x0.5x{2x1/2(0.05+7)}x0.074] cum .023 3,257.45 74.92= 0.023cum(Rate as per Item no. 4.1.3)

###(B) Centering and shuttering including T&P L.S. 26.91 1 26.91charges, hire charges of steel mould, tablevibrator, rammer, bolts nuts & washers etc.Extra for Finishing sqm 1 62.15 62.15(Rate as per item no.13.16)(C) Extra Labour for lifting material upto floor Vlevel

### Coolie day .056 135.25 7.57(C) Labour for hoisting and setting in position

### Mason 1st class day .05 151.5 7.58### Beldar day .3 135.25 40.57

(D) Mortar for fixing cement mortar 1:2 cum 0.002 3,864.25 7.73(Rate as per item No. 3.7)TOTAL 227.43(E)) Add for water charges @ 1% on (B+C+D) .9TOTAL 228.33 Add for contractor’s profit and overheads @ 13.6915% on (B+C+D+E)Cost for 0.05 cum. 242.02Cost per cum. 4,840.4Say 4,840.4

### Providing and fixing upto floor five level precast cement concrete hollow blockincluding hoisting and setting in position with cement mortar 1:3 (1 cement : 3 coarsesand), cost of required centring, shuttering and finishing smooth with 6mm thickcement plaster 1:3 (1 cement: 3 fine sand) on exposed surfaces complete :

4.81:3:6 (1 Cement: 3 coarse sand : 6 graded stone aggregate 20mm nominal size).CodDescription Unit Quantity Rate Amount

Details of cost for one block of overall size

Page 135: DAR_Vol_1

1m x 0.50m and 0.10m thick having 6 verticalhollows, 40x20x30cmfinished contents = lmx0.5mx0.lm = 0.05cumMaterials :Cement concrete 1:3:6(A) Net qty = 0.05 [6x0.5x{2xl/2(0.05+7)}x6.074] cum .023 2 91.05 64.19= 0.023cum(Rate as per Item no. 4.1.5 )(B) Centering and shuttering including T&P L.S. 26.91 1 26.91charges, hire charges of steel mould, tablevibrator, rammer, bolts nuts & washers etc.

141CodDescription Unit Quantity Rate Amount

(C) Extra for Finishing sqm 1 62.15 62.15(Rate as per item no. 13.16)(D) Extra Labour for lifting material upto floor VlevelCoolie day .056 135.25 7.57(D) Labour for hoisting and setting in positionMason 1 st class day .05 151.5 7.58Beldar day .3 135.25 40.57(E) Mortar for fixing c cum 0.002 3,864.25 7.73(Rate as per item No. 3.7)TOTAL 216.7Add for water charges @ 1% on (B+D+E) .9TOTAL 217.7Add for contractor’s profit and overheads @ 13.6915% on(B+D+E+F)Cost for 0.05 cum. 231.29Cost per cum. 4,625.8Say 4,625.8

### Precasting and placing in position 125 mm dia Bollards 600 mm high of requiredshape including providing M.S. Pipe Sleeve 50 mm dia 300 mm long in the Bollardand M.S. Pipes 40 mm dia and 450 mm long with 150xl50x6mm M.S. plate welded atbottom and embedded 150mm in cement concrete 1:3:6 (1 Cement: 3 coarse sand :6 graded stone aggregate 20 mm nominal size) including necessary excavation ofsize 250x250x450mm^deep for the same in bitumen/concrete pavement at specifiedspacing.

CodDescription Unit Quantity Rate AmountDetails of cost for one bollardMaterials :ement concrete 1:2:4p/4x0.125x0.60 = .00 cum .007 3 359.60 23.52Rate as per Item no. 5.1.3 SH : RCC )Centering and shuttering3.14x(0.125)x0.60 = 0 sqm .24 119.25 28.62(Rate as per Item no. 5.9.1 SH : RCC)M.S. pipes (medium class)50 mm dia sleeve =1x0.30x5.10=1.53 kg40 mm dia pipe =1x0.45x3.61 =1.62 kgM.S. plate 3mm thick =(0.15x0.15)x23.55

Page 136: DAR_Vol_1

=0.53 kg=3.68 kg kg 3.68 42.15 155.11(Rate as per Item no. 10.1 SH : Steel work)Excavation0.25x0.25x0.45 = 0.03 cum .03 103.4 3.1(Rate as per Item no. 2.8.1 SH : Earth work)Cement concrete 1:3:6 cum .03 2 791.05 83.73(Rate as per Item no. 4.1.5 SH : Cementconcrete)6 mm rendering (1:3) ( sqm .25 62.15 15.54(Rate as per Item no.5.53 : RCC)Carriage and fixing cha L.S. 13 1 13.00 (A)TOTAL 322.62Add for water charges @ 1 % on (A) 0.13 (B)TOTAL 322.75Add for contractor’s profit and overheads @ 1.9715% on (A+B)Cost for one bollard 324.72Say 324.7

142### Providing and laying damp-proof course 40mm thick with cement concrete 1:2:4 (1

cement: 2 coarse sand : 4 graded stone aggregate 12.5mm nominal size).CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqmCement concrete 1:2:4 (1 cement: 2 coarsesand : 4 graded stone aggregate 12.5 mmnominal size)10x0.040 = 0.40 cumRate for Cement concrete 1:2:4 ( cum .4 3 257.45 1 302.98coarse sand : 4 graded stone aggregate 20 mmnominal size)(As per item no 4.1.3)Add Dedut for diffence of cost between 20mmSize and 12.5mm size cum .67 0.0 0.0Add for delay:

###(A) Mason 1st class day .4 151.5 60.6###(A) Mason 2nd class day .4 141.6 56.64###(A) Sundries (Form work etc.) L.S. 1.95 1 1.95

TOTAL 1,422.17(B) Add for water charges @ 1% on (A) 1.19TOTAL 1,423.36Add for contractor’s profit and overheads @ 18.0610% on (A+B)Cost for 10 sqm 1,441.42Cost for 1 sqm 144.14Say 144.15

### Providing and laying damp-proof course 50mm thick with cement concrete 1:2:4 (1cement: 2 coarse sand : 4 graded stone aggregate 20mm nominal size).

CodDescription Unit Quantity Rate AmountDetails of cost for 10sqm.Materials :Cement concrete 1:2:4 = 10x0.05cum 0.50 3,257.45 1 628.72

Page 137: DAR_Vol_1

(Rate as per item no. 4.1.3)Add for delay :

###(A) Mason 1st class day .4 151.5 60.6###(A) Mason 2nd class day .4 141.6 56.64###(A) Sundries (Form work etc.) L.S. 13.52 1 13.52

TOTAL 1,759.48(B) Add for water charges @ 1 % on ‘A’ 1.31TOTAL 1,760.79Add for contractor’s profit and overheads @ 19.8115% on ‘A’+’B’Cost for 10 sqm. 1,780.6Cost of 1 sqm. 178.06Say 178.05

### Extra for providing and mixing water proofing material in cement concrete work @1 kg per 50 kg of cement.

CodDescription Unit Quantity Rate AmountDetails of cost for per bag of 50kg. of cementMaterials :

###Approved water proofing’materiakg 1 20 20to the recommended proportions

143CodDescription Unit Quantity Rate Amount###Carriage of water proofing mater L.S. 3.64 1 3.64

for mixing etc. 23.64TOTAL .24Add for water charges @ 1% 23.88TOTAL 3.58Add for contractor’s profit and overheads @1,500%Cost per bag of cement of 50kg. 27.46Say 27.45

### Applying a coat of residual petroleum bitumen of penetration 80/100 of approvedquality using 1.7kg per square metre on damp proof course after cleaning the surfacewith brushes and finally with a piece of cloth lightly soaked in kerosene oil.

CodDescription Unit Quantity Rate Amount

Details of cost for 10sqm.Materials:

###Paving Bitumen S-90 tonne 0.017 22 500.00 382.5###Kerosene oil Litre 1.23 19 23.37###Fuel (steam coal) for heating quintal .035 300 10.5###Carriage of Bitumen tonne .017 53.21 .9

Labour:###Cleaning surface and applying kerosene oil

Beldar Day .12 135.25 16.23###Heating the material-Beldar Day .07 135.25 9.47###Spreading hot tar over damp pro Day .2 141.6 28.32

course-Painter###Sundries (Carriage of kerosene, L.S. 33.15 1 33.15

brushes, T&P etc.)TOTAL 504.44Add 1 % for water charges 5.04

Page 138: DAR_Vol_1

TOTAL 509.48Add 15% for contractor’s profit and overheads 76.42Cost for 10 sqm. 585.9Cost of 1 sqm. 58.59Say 58.6

4.14 Extra for concrete work in superstructure above floor V level for each four floors orpart thereof.

CodDescription Unit Quantity Rate AmountDetails of cost per cum.Extra labour element required for lifting ofmaterials (0.75x2.00 = 1.50)

###Coolie Day 1.5 135.25 202.88TOTAL 202.88Add 1% for water charges 2.03TOTAL 204.91Add 15% for contractor’s profit and overheads 30.74Cost for 1 cum. 235.65Say 235.65

144### Extra for laying concrete in or under water and/or liquid mud including cost of

pumping or bailing out water and removing slush etc. complete.

CodDescription Unit Quantity Rate AmountDetails of cost for depth of water 0.30 m.Quantity of concrete = 14 cum.pumping hours = 3 hrs. or 0.75 day.

11 Cost of pumping water with 3636.Day .375 300 112.5per hour capacity pump

###Beldar for cleaning slush Day 4 135.25 541TOTAL 653.5Add 1% for water charges 6.54TOTAL 660.04Add for contractor’s profit and overheads @ 99.011,500%Cost of 14cum. per 0.30 m depth 759.05Cost of cum. per m depth 180.73Say 180.75

4.16 Extra for laying concrete in or under foul positions.CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.Extra labour due to slow progress-

###Mason 1st class Day .02 151.5 3.03###Mason 2nd class Day .02 141.6 2.83###Beldar Day .25 135.25 33.81###Coolie Day .15 135.25 20.29

TOTAL 59.96Add 1% for water charges .6TOTAL 60.56Add for contractor’s profit and overheads 9.081,500%Cost for 1 cum. 69.64Say 69.65

Page 139: DAR_Vol_1

### Making plinth protection 50mm thick of cement concrete 1:3:6 (1 cement : 3 coarsesand : 6 graded stone aggregate 20 mm nominal size) over 75mm bed of dry brickballast 40mm nominal size well rammed and consolidated and grouted with finesand including finishing the top smooth.

CodDescription Unit Quantity Rate AmountDetail of cost for 10 sqmMaterials

###Brick aggregate 40 mm size cum .75 360 270###Carriage of brick aggregate cum .75 57.83 43.37###Fine sand 60 cu.dm. per 10 sqm cum .06 320 19.2###Carriage of fine sand cum .06 53.21 3.19

Dressing the gound including cutting andfilling upto 15cm

###Beldar Day .16 135.25 21.64###Coolie Day .11 135.25 14.88

Cement concrete 1:3:6 Qty. of cementconcrete 1:3:6 on 10 sqm. area = 0.5cum.Materials (for C.C 1:3:6)

145CodDescription Unit Quantity Rate Amount###Stone aggregate 20 mm nominal cum .35 700 245###Stone aggregate 10 mm nominal cum .12 700 84###Carriage of stone aggregate cum .47 53.21 25.01###Coarse sand cum .23 600 138###Carriage of coarse sand cum .23 53.21 12.24###Cement tonne 0.11 4,500.00 495###Carriage of cement tonne .11 47.29 5.2

Labour (for C.C 1:3:6)###Beldar Day 1 135.25 135.25###Mason 1st class Day .05 151.5 7.58###Bhisti Day .33 138.45 45.69###Hire and runing charges of mechaL.S. 13.39 1 13.39###Sundries L.S. 6.76 1 6.76

Labour0 1 Mason Day .27 146.55 39.57###Beldar Day 1.08 135.25 146.07###Coolie Day 1.08 135.25 146.07

TOTAL 1,917.11Add 1% for water charges 19.17TOTAL 1,936.28Add 15% for contractor’s profit and overheads 290.44Cost of 10.00 sqm 2,226.72Cost of 1.00 sqm 222.67Say 222.65

147

Page 140: DAR_Vol_1

SUB HEAD : 5.0

REINFORCED CEMENT

CONCRETE

149### Providing and laying in position specified grade of reinforced cement concrete

excluding the cost of centring, shuttering, finishing and reinforcement - All workupto plinth level:

5.11:1:2 (1 cement: 1 coarse sand : 2 graded stone aggregate 20 mm nominal size).

CodDescription Unit Quantity Rate AmountDetails of cost for 1 cum.Materials:

###Stone aggregate 20mm cum .64 700 448###Stone aggregate 10mm cum .21 700 147###Carriage of aggregate 20mm an cum .85 53.21 45.23###Coarse sand cum .425 600 255###Carriage of coarse sand cum .425 53.21 22.61###Cement (0.425 cum) tonne .61 4,500 2,745###Carriage of cement tonne .61 47.29 28.85

Labour:###Mason Day .17 146.55 24.91###Beldar Day 2 135.25 270.5###Bhishti Day 138.45 .9 124.6

Page 141: DAR_Vol_1

2 Mixer Day .07 400 2812 Vibrator Day .07 200 14###Sundries L.S. 14.3 1 14.3

TOTAL 4168.00Add 1% for water charges 41.68TOTAL 4209.68Add 15% for contractor’s profit and overheads 631.45Cost of 1 cum. 4841.13Say 4841.15

### Providing and laying in position specified grade of reinforced cement concreteexcluding the cost of centring, shuttering, finishing and reinforcement - All workupto plinth level :

5.11:1.5:3 (1 cement: 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.Materials :

###20mm stone aggregate cum .57 700 399###10mm stone aggregate cum .28 700 196###Carriage of aggregate cum .85 53.21 45.23###Coarse sand cum .425 600 255###Carriage of coarse sand cum .425 53.21 22.61###Cement (0.2833 cum) tonne .4 4,500 1,800###Carriage of cement tonne .4 47.29 18.92

Labour:###Mason Day .17 146.55 24.91###Beldar Day 2 135.25 270.5###Bhishti Day 0.9 0 138.45 124.62 Mixer Day .07 400 2812 Vibrator Day .07 200 14###Sundries L.S. 14.3 1 14.3

TOTAL 3213.07Add 1% for water charges 32.13TOTAL 3245.20Add 15% for contractor’s profit and overheads 486.78Cost of 1 cum. 3731.98Say 3732.00

150### Providing and laying in position specified grade of reinforced cement concrete

excluding the cost of centring, shuttering, finishing and reinforcement - All workupto plinth level :

5.11:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)

CodDescription Unit Quantity Rate AmountDetails of cost for 1 cum.Materials:

###Stone aggregate 20mm cum .67 700 469###Stone aggregate 10mm cum .22 700 154###Carriage of aggregate cum .89 53.21 47.36###Coarse sand cum .445 600 267###Carriage of coarse sand cum .445 53.21 23.68###Cement (0.2225 cum) tonne .32 4,500 1,440

Page 142: DAR_Vol_1

###Carriage of cement tonne .32 47.29 15.13Labour:

###Mason Day .17 146.55 24.91###Beldar Day 2 135.25 270.5###Bhishti Day .9 138.45 124.62 Mixer Day .07 400 2812 Vibrator Day .07 200 14###Sundries L.S. 14.3 1 14.3

TOTAL 2,892.48Add 1% for water charges 28.92TOTAL 2,921.4Add 15% for contractor’s profit and overheads 438.21Cost of 1 cum. 3,359.61Say 3,359.6

### Reinforced cement concrete work in walls (any thickness), including attachedpilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers,abutments, posts and struts etc. upto floor five level excluding cost of centring,shuttering, finishing and reinforcement :

5.21:1:2 (1 cement: 1 coarse sand : 2 graded stone aggregate 20 mm nominal size)CodDescription Unit Quantity Rate Amount

Details of cost for counterfost

Base- 1x6x1.5x0.2 = 1.80 cum.Heel - 1x6x0.3x0.2 = 0.36 cum.1x6x0.3x0.3 = 0.54 cum.Stem - 1x6x4.3x0.2 (Avg.) = 5.16 cum.triangular counterfost- 2x1/2x4.4x1.5x0.2 = 1.32 cum.= 9.18 cum.Materials:

###Stone aggregate 20mm cum 5.8752 700 4 112.64###Stone aggregate 10mm cum 1.9278 700 1 349.46###Carriage of aggregate 20mm an cum 7.803 53.21 415.2###Coarse sand cum 3.9015 600 2,340.9###Carriage of coarse sand cum 3.9015 53.21 207.6###Cement (0.425/ cum) tonne 5.5998 4,500 25,199.1###Carriage of cement tonne 5.5998 47.29 264.81

Labour:###Beldar Day 11.29 135.25 1,526.97

151CodDescription Unit Quantity Rate Amount###Coolie Day 7.53 135.25 1 018.43###Bhishti Day 8.26 138.45 1 143.60###Mason 1st class Day .92 151.5 139.38###Mason 2nd class Day .92 141.6 130.272 Mixer Day .64 400 25612 Vibrator Day .64 200 128###Sundries L.S. 131.82 1 131.82###Scaffolding L.S. 420.03 1 420.03###Extra labour for lifting of materia Day 17.20 135.25 2,326.3

V level: Coolie (0.75x9.18x2.5)TOTAL 41,110.51

Retaining wall 4.5m high and 6m long.

Page 143: DAR_Vol_1

Add 1 % for water charges 411.11TOTAL 41521.62Add for contractor’s profit and overheads @1 6 228.241,500%Cost for 9.18 cum. 47,749.86Cost for 1 cum. 5,201.51Say 5 201.50

### Reinforced cement concrete work in walls (any thickness), including attachedpilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers,abutments, posts and struts etc. upto floor five level excluding cost of centring,shuttering, finishing and reinforcement:

5.21:1.5:3 (1 cement: 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)CodDescription Unit Quantity Rate Amount

Details of cost for 9.18 cum.Materials :

###20mm stone aggregate cum 5.2326 700 3 662.82###10mm stone aggregate cum 2.5704 700 1 799.28###Carriage of aggregate cum 7.803 53.21 415.2###Coarse sand cum 3.9015 600.00 2,340.9###Carriage of coarse sand cum 3.9015 53.21 207.6###Cement (0.2833 cum) tonne 3.672 4500.00 16 524.00###Carriage of cement tonne 3.672 47.29 173.65

Labour:###Beldar Day 11.29 135.25 1 526.97###Coolie Day 7.53 135.25 1 018.43###Bhishti Day 8.26 138.45 1 143.60###Mason 1st class Day .92 151.5 139.38###Mason 2nd class Day .92 141.6 130.272 Mixer Day .64 400 25612 Vibrator Day .64 200 128###Sundries L.S. 131.82 1 131.82###Scaffolding L.S. 420.03 1 420.03###Extra labour for lifting of materia Day 17.20 135.25 2,326.3

V level: Coolie (0.75x9.18x2.5)TOTAL 32 344.25Add 1% for water charges 323.44TOTAL 32 667.69Add for contractor’s profit and 4,900.15overheads @ 15 %Cost for 9.18 cum. 37 567.84Cost for 1 cum. 4,092.36Say 4,092.35

152### Reinforced cement concrete work in walls (any thickness), including attached

pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers,abutments, posts and struts etc. upto floor five level excluding cost of centring,shuttering, finishing and reinforcement:

5.21:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size).

CodDescription Unit Quantity Rate AmountDetails of cost for 9.18 cum.

Page 144: DAR_Vol_1

Materials :###Stone aggregate 20mm cum 6.1506 700 4 305.42###Stone aggregate 10mm cum 2.0196 700 1 413.72###Carriage of aggregate cum 8.1702 53.21 434.74###Coarse sand cum 4.0851 600 2 451.06###Carriage of coarse sand cum 4.0851 53.21 217.37###Cement (0.02225/cum) tonne 2.9376 4500.00 13 219.20###Carriage of cement tonne 2.9376 47.29 138.92

Labour:###Beldar Day 11.29 135.25 1,526.97###Coolie Day 7.53 135.25 1 018.43###Bhishti Day 8.26 138.45 1 143.60###Mason 1 st class Day .92 151.5 139.38###Mason 2nd class Day .92 141.6 130.272 Mixer Day .64 400 25612 Vibrator Day .64 200 128###Sundries L.S. 131.82 1 131.82###Scaffolding L.S. 420.03 1 420.03###Extra labour for lifting of materi Day 17.20 135.25 2,326.3

V level: Coolie (0.75x9.18x2.5)TOTAL 29 401.23Add 1 % for water charges 294.01TOTAL 29 695.24Add for contractor’s profit and overheads @ 4,454.291,500%Cost for 9.18 cum. 34 149.53Cost for 1 cum. 3 719.99Say 3,720

### Reinforced cement concrete work in beams, suspended floors, roofs having slopeupto 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills,staircases and spiral stair cases upto floor five level excluding the cost of centring,shuttering, finishing and reinforcement with 1:2:4 (1 cement : 2 coarse sand : 4 gradedstone aggregate 20 mm nominal size).

CodDescription Unit Quantity Rate AmountDetails of cost for 1 cum.Materials:

###Stone aggregate 20mm cum .67 700 469###Stone aggregate 10mm cum .22 700 154###Carriage of aggregate cum .89 53.21 47.36###Coarse sand cum .445 600 267###Carriage of coarse sand cum .445 53.21 23.68###Cement (0.02225/ cum) tonne 0.32 4500.00 1440.00###Carriage of cement tonne .32 47.29 15.13

Labour:###Mason Day .24 146.55 35.17###Beldar Day 2.75 135.25 371.94

153CodDescription Unit Quantity Rate Amount###Bhishti Day .9 138.45 124.62 Mixer Day .08 400 3212 Vibrator Day .08 200 16###Sundries L.S. 14.30 1 14.3

Page 145: DAR_Vol_1

Extra labour for lifting material upto floor Vlevel:

###Coolie (1.5x0.75) Day 1.13 135.25 152.83TOTAL 3163.01Add 1% for water charges 31.63TOTAL 3194.64Add for contractor’s- profit and overheads @ 479.21,500%Cost for 1 cum. 3 673.84Say 3673.85

### Providing and laying upto floor five level reinforced cement concrete in kerbs, stepsand the like excluding the cost of centring, shuttering, finishing and reinforcementwith 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominalsize).

CodDescription Unit Quantity Rate AmountDetails of cost for 1 cum.(A) Materials: Cement concrete 1:cum 1 3,257.45 3,257.45per item no 4.4.1)Labour:Extra labour for laying CC in RCC work :

###(B) Beldar Day .1 135.25 13.52###(B) Bhishti Day .2 138.45 27.69###(B) Mason 1st class Day .04 151.5 6.06###(B) Mason 2nd class Day .04 141.6 5.66###(B) Mate Day .04 138.45 5.54###(B) Extra labour for lifting materi Day 1.13 135.25 152.83

level: Coolie (1.5x0.75)TOTAL 3,468.75(C) Add 1 % for water charges on (B) 2.11TOTAL 3,470.86Add for contractor’s profit and overheads @ 32.0115% on (B+C)Cost for 1 cum. 3,502.87Say 3,502.85

### Reinforced cement concrete work in arches, arch ribs, domes, vaults, shells, foldedplate and roofs having slope more than 15° upto floor five level excluding the cost ofcentring, shuttering, finishing and reinforcement with 1:2:4 (1 cement: 2 coarse sand:4 graded stone aggregate 20 mm nominal size).

CodDescription Unit Quantity Rate AmountDetails of Cost for semicircular arch 6m clearspan and 9m long and 30cm thick.Cement concrete 1:2:4= 1x0.50x3.14x6.30x9.00x0.30 = 26.73cum.Details of cost for 26.73 cum.Material

###Stone aggregate 20mm cum 17.9091 700 12,536.37###Stone aggregate 10mm cum 5.8806 700 4,116.42###Carriage of aggregate cum 23.7897 53.21 1,265.85

154CodDescription Unit Quantity Rate Amount###Coarse sand cum 11.8948 600 7,136.88

Page 146: DAR_Vol_1

###Carriage of coarse sand cum 11.8948 53.21 632.92###Cement (0.02225/ cum) tonne 8.5536 4500.00 38,491.2###Carriage of cement tonne 8.5536 47.29 404.5

Labour:###Mason Day 2.673 146.55 391.73###Beldar Day 45.57 135.25 6,163.34###Bhishti Day 18.711 138.45 2,590.542 Mixer Day 1.8711 400 748.4412 Vibrator Day 1.8711 200 374.22###Sundries L.S. 401.89 1 401.89

Extra for laying CC over curved surfaces###Mason 1st class Day 5 151.5 757.5###Mason 2nd class Day 5 141.6 708###Bhishti Day 1.5 138.45 207.68###Coolie Day 4.5 135.25 608.62

Extra labour for lifting materi Day 30.07 135.25 4,066.97level: Coolie (1.50x0.75x26.73)TOTAL 81,603.07Add 1% for water charges 816.03TOTAL 82 419.10Add15% for contractor’s profit and overheads @ 12 362.86Cost for 26.73 cum. 94 781.96Cost for 1 cum. 3,545.9Say 3,545.9

### Reinforced cement concrete work in chimneys, shafts, upto floor five level excludingthe cost of centring, shuttering, finishing and reinforcement with 1:2:4 (1 cement: 2coarse sand : 4 graded stone aggregate 20 mm nominal size).

CodDescription Unit Quantity Rate AmountDetails of cost for 1 cum.Materials :R.C.C. 1:2:4 in.chimneys & shafts(A) Rate as per item no. 5.2.3 cum 1 3,720 3,720Extra labour involved for lifting materials :

###(B) Coolie Day .26 135.25 35.16TOTAL 3 755.16(C) Add 1% for water charges on B .35TOTAL 3 755.51Add 15%for contractor’s profit and overheads @ 5.33on B+CCost for 1 cum. 3 760.84Say 3 760.85

### Reinforced cement concrete work in well-steining excluding the cost of centring,shuttering, finishing and reinforcement with 1:2:4 (1 cement: 2 coarse sand : 4 gradedstone aggregate 20 mm nominal size).

CodDescription Unit Quantity Rate AmountDetails of cost for 1 cum.Materials:R.C.C. 1:2:4 in well steiningRate as per item no 4.1.3 cum 1 3,257.45 3,257.45

155CodDescription Unit Quantity Rate Amount

Labour.

Page 147: DAR_Vol_1

Extra labour involved :###(B) Coolie Day 0.08 135.25 10.82

TOTAL 3,268.27(C) Add 1% for water charges on B .11TOTAL 3 268.38Add 15%for contractor’s profit and overheads @ 1.64on B+CCost for 1 cum. 3 270.02Say 3 270.00

### Reinforced cement concrete work in vertical and horizontal fins individually orforming box louvers, facias and eaves boards upto floor five level excluding thecost of centring, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement: 1.5coarse sand : 3 graded stone aggregate 20mm nominal size).

CodDescription Unit Quantity Rate AmountDetails of cost for 4 RCC Vertical fins 4mhigh and lm center with 2 horizontal fins, allprojecting 60cm from face of wall and 5cmthick = 0.66 cum.Cement Concrete 1:1.5.34x4x0.60x0.05 = 0.48 cum2x3x0.06x0.05 = 0.18 cumTotal = 0.66 cum.Materials:

###Stone aggregate 20mm cum .3762 700 263.340 2 Stone aggregate 10mm cum .1848 700 129.36###Carriage of aggregate cum .561 53.21 29.85###Coarse sand cum .2805 600 168.3###Carriage of coarse sand cum .2805 53.21 14.93###Cement (0.2833 cum) tonne 0.264 4500.00 1188.00###Carriage of cement tonne .264 47.29 12.48

Labour:###Beldar Day .79 135.25 106.85###Coolie Day .56 135.25 75.74###Bhishti Day .6 138.45 83.07###Mason 1 st class Day .06 151.5 9.09###Mason 2nd class Day .06 141.6 8.5###Scafolding L.S. 30.16 1 30.16###Sundries L.S. 9.49 1 9.492 Mixer Day .05 400 2012 Vibrator Day .05 200 10###Extra for lifting materials upto fl Day .18 135.25 24.34

: CoolieExtra for restricted working in fins

###Mason 1st class Day .05 151.5 7.58Mason 2nd class Day .05 141.6 7.08

###Beldar Day .1 135.25 13.52###Bhishti Day .15 138.45 20.77

TOTAL 2 232.45Add 1% for water charges 22.32TOTAL 2 254.77Add for contractor’s profit and overheads @ 338.221,500%Cost for 0.66 cum. 2 592.99Cost for 1 cum. 3 928.77Say 3 928.75

0124

Page 148: DAR_Vol_1

156### Centring and shuttering including strutting, propping etc. and removal of form for :

5.9Foundations, footings, bases of columns, etc. for mass concrete.

CodDescription Unit Quantity Rate AmountDetails of cost for footing size2.7mx2.7mx 1.00mContact area = 10.8 sqm.Materials:–Assuming shuttering material will becomeunserviceable after use of 40 timesAdding for maintenance @ 10% of costTaking salvage value after full use of material@ 25% of cost

###Wall form panel 1250x500mm each .34 980 333.2Qty taken for cost of using once = 16x0.85/40= 0.34

###Corner angle (1.5m long) each .085 280 23.8Qty taken for cost of using once = 4x0.85/40= 0.085

###100mm channel shoulders 2.5m each 0.17 1000.00 170Qty taken for cost of using once = 8x0.85/40= 0.17

###Double clip (bridge clip) each .34 75 25.5Qty taken for cost of using once = 16x0.85/40= 0.34

###Single clip each .17 60 10.2Qty taken for cost of using once = 8x0.85/40= 0.17

###MS tube 40mm - 4x2.7m = 10.8 metre 0.2295 225.00 51.64Qty taken for cost of using once =10.8x0.85/40 = 0.2295

###Assembly nuts & bolts L.S. 22.10 1 22.1 Qty taken for cost of using once =1040x0.85/40 = 8.50

###Carriage L.S. 78 1 78Labour:

0 Fitter Grade-I Day 0.75 151.50 113.620 1 Beldar Day 1.50 135.25 202.88###Shuttering oil L.S. 52.00 1.00 52###Sundries L.S. 26 1 26

TOTAL 1,108.94Add 1 % for water charges 11.09TOTAL 1,120.03Add 15% for contractor’s profit and overheads 168Cost for 10.8 sqm. 1,288.03Cost per sqm. 119.26Say 119.25

157

Page 149: DAR_Vol_1

### Centring and shuttering including strutting, propping etc. and removal of form for :5.9Walls (any thickness) including attached pilasters, buttresses, plinth and string

courses etc.CodDescription Unit Quantity Rate Amount

Details for 7.9m long and 1,00m high wallArea of contact 2x7.9x1.0 = 15.8 sqm.Materials :Assuming shuttering material will becomeunserviceable after use of 40 timesAdding for maintenance @ 10% of costTaking salvage value after full use of material@ 25% of cost

###Wall form Panel (1.25x0.5) 2x3x2x2 = 24Noseach .51 980 499.8

Qty taken for cost of using once = 24x0.85/40= 0.51

###100mm channel shoulder 2.5m long, 4x2 = 8each .17 1 000.00 170.00Qty taken for cost of using once = 8x0.85/40= 0.17

###Bridge clip 2x6x2 = 24 each .51 75.00 38.25Qty taken for cost of using once = 24x0.85/40= 0.51

###Single clip 2x3x2 = 12 each .255 60.00 15.30Qty taken for cost of using once = 12x0.85/40= 0.255

###M.S. Tube 40mm 2x2x8m = 32m metre 0.68 225 153Qty taken for cost of using once = 32x0.85/40= 0.68

###Nut & Bolts L.S. 27.62 1 27.62Qty taken for cost of using once =1300x0.85/40 = 27.62

###Carriage L.S. 78.00 1 78Labour:

###Fitter Grade-I Day 3.50 151.5 530.25###Beldar Day 6.00 135.25 811.5###Shuttering oil L.S. 78.00 1 78###Sundries L.S. 52.00 1 52

TOTAL 2,453.72Add 1 % for water charges 24.54TOTAL 2 478.26Add 15% for contractor’s profit and overheads 371.74Cost for 15.8 sqm. 2 850.00Cost per sqm. 180.38Say 180.4

158### Centring and shuttering including strutting, propping etc. and removal of form for:

5.9Suspended floors, roofs, landings, balconies and access platform.

CodDescription Unit Quantity Rate AmountDetail of cost for a room4.50x3 = 13.50 sqm, height 3.5 m

Page 150: DAR_Vol_1

Materials :Adding for maintenance @ 10% of costTaking salvage value after full use of material@ 25% of cost1. Plates (size 0.75x0.60)Angle 40x40x5mm2x0.75= 1.50 m2x0.60= 1.20 m= 2.70 m @ 3.00 kg/m = 8.10 kgsheet 1.6 mm thick0.75x0.60 = 0.45 sqm0.45 sqm @ 12.55kg/sqm = 5.65kgWeight of one plate = 13.75kgAdd for wastage @ 5% = 0.69 kgTotal = 14.44kgTotal weight of all plates = 5x6x14.44 =433.20 kg.Qty taken for cost using once = 433.2x0.85/40= 9.2055 kg.(X) Rate as per item no 10.1 kg 9.2055 42.15 388.01

###2. Adjustable span- ESOSI (2.35- each .1063 1 600.00 170.08Qty taken for cost using once = 5x0.85/40 =

.1063###3. Adjustable telescopi prop 3m each .1275 1 000.00 127.5

Qty taken for cost using once = 6x0.85/40 =.1275

###4. Assembly nut & bolts etc. L.S. 22.1 1 22.1Qty taken for cost using once = 1040x0.85/40 =

22.1999Carriage L.S. 130.00 1 130

Labour:###Fitter grade-I Day 3 151.5 454.5###Beldar Day 6 135.25 811.5###Shuttering oil L.S. 78 1 78###Sundries, paper tape etc L.S. 49.7 1 50.02

TOTAL 2,231.71Add 1% for water charges except on ‘X’ 18.44TOTAL 2,250.15Add for contractor’s profit and overheads @ 279.3215% except on ‘X’Cost for 13.50 sqm. 2,529.47Cost per sqm. 187.37Say 187.35

1595.9 Centring and shuttering including strutting, propping etc. and removal of form for :5.9 Shelves (Cast in situ)CodDescription Unit Quantity Rate Amount

Detail of cost for a room4.50x3 =13.50 sqm, height 3.5 mMaterials:Adding for maintenance @ 10% of costTaking salvage value after full use of material@ 25% of cost

Page 151: DAR_Vol_1

1. Plates (size 0.75 x 0.60)Angle 40x40x5mm2x0.75= 1.50 m2x0.60 = 1.20 m= 2.70 m @ 3.00 kg/m = 8.1 kgsheet 1.6 mm thick0.75x0.60 = 0.45 sqm0.45 sqm @ 12.55kg/sqm = 5.65kgWeight of one plate = 13.75kgAdd for wastage @ 5% = 0.69 kgTotal = 14.44kgTotal weight of all plates = 5x6x14.44 =433.20 kg.Qty taken for cost using once = 433.2x0.85/40= 9.2055 kg.(X) Rate as per item no the 10.1 kg 9.2055 42.15 388.01

###2. Adjustable span- ESOSI (2.35- each .1063 1 600.00 170.08Qty taken for cost using once = 5x0.85/40 =0.1063 “

###3. Adjustable telescopi prop 3m each .1275 1 000.00 127.5Qty taken for cost using once = 6x0.85/40 =

.1275###4. Assembly nut & bolts etc. L.S. 22.1 1 22.1

Qty taken for cost using once = 1040x0.85/40 =22.1

###Carriage L.S. 130.00 1 130Labour:

###Fitter grade-I Day 6 151.5 454.5###Beldar Day 6 135.25 811.5###Shuttering oil L.S. 78.00 1 78###Sundries,paper tape etc L.S. 49.7 1 50.02

‘TOTAl 2,231.71Add 1% for water charges except on ‘X’ 18.44TOTAL 2,250.15Add for contractor’s profit and overheads @ 279.3215% except on ‘X’Cost for 13.50 sqm. 2,529.47 Cost per sqm. 187.37Say 187.35

160### Centring and shuttering including strutting, propping etc. and remova of form for:

5.9Lintels, beams, plinth beams, girders, bressumers and cantilevers.

CodDescription Unit Quantity Rate AmountConsider a beam of 6 m clear span, 0.50 mdeep 0.30 m wide and height 3.5 m from floorCubical contents6.60x0.5x0.3 = 0.99 cum “”1x1.30x6.00 = 7.80 sqm “Materials :Assuming shuttering will becomeunserviceable after use of 40 timesAdd maintenance charges @ 10% of cost of

Page 152: DAR_Vol_1

materialLess salvage value of material after full use @25% of cost of material1. Steel plates for side and bottom (plate size1.20 x 0.50m)Angle 40x40x5mm2x1.20 = 2.40 m ^3x0.50= 1.50 mTotal 3.90 m @ 3.00 kg/m = 11.70 kgsheet 1.6 mm thick1.20m x 0.50 m= 0.60 sqm.0.60 sqm @ 12.55 kg/sqm. = 7.53 kg.””Weight of one plate = 19.23 kg. -””Add for wasdge 5% 0.96 kg.Total =20.19 Kg.Total weight of all plates3x5x20.19 = 302.85 kg or 3.03 q’Qty taken for cost of using once =302.85 x 85/40 = 6.4356 kg.(X) Rate as per item no 10.1 kg 6.4356 42.15 271.26

###(ii) Props 3m (adjustable telescopic 2.02 - each .1275 1 000.00 127.503.75m)Qty taken for cost of using once = 6x0.85/40 =0.1275 m

###(iii) Beam clamp 300-380 mm(450-1070mmeach .1063 375 39.86Qty taken for cost of using once = 5/0.85/4 set0.1063 m

###(iv) Assembly nut & bolts etc. L.S. 22.1 1 22.1Qty taken for cost of using once =1040x0.85/40 = 22.10

###Carriage L.S. 78 1 78Labour:

###Fitter Grade-I Day 1.25 151.50 189.38###Beldar Day 2.5 135.25 338.12###Shuttering oil L.S. 39.00 1.00 39###Sundries, paper tape etc. L.S. 24.39 1 24.61

TOTAL 1,129.53Add 1% for water charges except on ‘X’ 8.59TOTAL 1,138.42Add for contractor’s profit and overheads @ 130.0715% except on ‘X’ 1,268.49Cost for 7.80 sqm. 162.63Cost per sqm. 162.65Say

161### Centring and shuttering including strutting, propping etc. and removal of form for:

5.9Columns, Pillars, Piers, Abutments, Posts and Struts.

CodDescription Unit Quantity Rate AmountDetail of cost forSize of column 450x450mm and 2.5m highArea of contact = 4x0.45x2.5 = 4.5 sqm.Assuming shuttering will become

Page 153: DAR_Vol_1

unserviceable after use of 40 timesAdd maintenance charges @ 10% of cost ofmaterialLess salvage value of material after full use @25% of cost of material

###Wall form panel (1250x450) x each .17 900 153Qty taken for cost of using once = 8x0.85/40 =

.17###Corner angle 2.5m long each .085 275 23.38

Qty taken for cost of using once = 4x0.85/40 =.085

###Column clamp (450-1070mm) each 0.1063 1100.00 116.93Qty taken for cost of using once = 5x0.85/40 =

.1063###Prop. 2m(2.0-3.5m) each 0.085 750.00 63.75

Qty taken for cost of using once = 4x0.85/40 =.085

###Assembly nut & bolt L.S. 27.62 1 27.62Qty taken for cost of using once =1300x0.85/40 = 27.62

###Carriage L.S. 52.00 1 52Labour

0 1 Fitter Grade-I Day 1.00 151.50 151.5###Beldar Day 2 135.25 270.5###Shuttering oil L.S. 39.00 1 39###Carriage L.S. 26.00 1 26

TOTAL 923.68Add 1% for water charges 9.24TOTAL 932.92Add for contractor’s profit and overheads @ 139.941,500%Cost for 4.5 sqm. 1072.86Cost per sqm. 238.41Say 238.4

### Centring and shuttering including strutting, propping etc and removal or form tor:5.9Stairs, (excluding landings) except spiral-staircases.CodDescription Unit Quantity Rate Amount

Details of cost for 5.79 sqm.Details of staircase, 3.40m clear spanincluding lm landing.Material:(i) Cost of plank 38mm (2nd class kail wood)Waist 2.69x1.30 = 3.50sqm.Side shuttering of steps and side ofwaist-Steps= 8x1.30x1.15= 1.56 sqm.

162CodDescription Unit Quantity Rate Amount

Face of landing1x1.30x0.15 = 0.20 sqm.Side of waist2.69x0.13 =0.35 sqm.Side of steps-

Page 154: DAR_Vol_1

8x0.50x0.30x0.15 = 0.18sqm.Total = 5.79 sqm.Wastage 5% = 0.29sqm.Total = 6.08 sq.Cubical content-6.08x0.038 = 0.231 cum = 231 dm3

###Qty taken for cost using once = 231/8= 28. 10 cudm 28.875 178 513.98dm3(ii) Batten 100mm x 75mm(2nd class kail wood in scantling)4x1.30x0.100x0.075=0.039 cum = 39 dm3

###Qty taken for cost using once = 39/8 = 4.87510 cudm 4.875 160 78dm3(iii) Safeda Bailies 125mm dia.2x4x0.80 = 6.40m

###Qty taken for cost using once = 6.4/8 = 0.8 metre .8 29 23.2Carriage of timber-Planks = 0.231 cum.Battens = 0.039 cum.

2Bailies 6.4x3.142/4x(0.125) = 0.079cum.Total =0.349 cum.

###Qty taken for cost using once = 0.349/8 = cum .04363 60.81 2.650.04363 cumLabour:For assembling, erection, dismantling andcleaning

###Carpenter 2nd class Day 1.75 141.6 247.8###Beldar Day 1 135.25 135.25###Sundries L.S. 16.12 1 16.12

TOTAL 1,017Add 1% for water charges 10.17TOTAL 1,027.17Add 15% for contractor’s profit and overheads 154.08Cost of 5.79 sqm. 1,181.25Cost per sqm. 204.02Say 204

### Centring and shuttering including strutting, propping etc. and removal of form for:5.9Spiral staircases (including landing).CodDescription Unit Quantity Rate Amount

Detail of cost for 6.28 sqm (For 10 steps)Treads10x0.70x0.20(av.) = 1.40 sqm sqm 1.4 162.65 227.71(Rate as per item no 5.9.5)Riser2x 10x0.70x0.23 = 3.22 sqm sqm 3.22 180.4 580.89(Rate as per item no 5.9.2)Newal Post (Column)10x3.14x0.232 = 1.66 sqm(Rate as per item no 5.9.7) sqm 1.66 204 338.64Cost of 6.28 sqm 1,147.24Cost of 1 sqm 182.68Say 182.7

Page 155: DAR_Vol_1

163### Centring and shuttering including strutting, propping etc. and removal of form for:

5.9Arches, domes, vaults upto 6 m span

CodDescription Unit Quantity Rate AmountDetails of cost for a semicircular arch 3.6mclear span and 3.6m long.Area of centering = 22x1.8x3.6=20.37sqm.Material:Frame work in 2nd class kail woodTie-1x3.6x0.15x0.20 = 0.108cum.Struts-3xl.8x0.10x0.10 =0.054cumStruts-2x2.55x0.10x0.10=0.051 cum.Ribs-4xl.38x.075x0.075=0.031cum.Total = 0.244 cum.Quantity for 7 such frames7x0.244 =1.708cum.Strips 5cmx2.5cm = 7.5cmcenter to center5.66/0.075x0.05x0.025x3.6 = 0.342cum.Total = 2.050 cum = 2050 cudm

###Qty taken for cost using once = 10 cudm 256.25 160 4,100256.25 cudmSafeda Balli supports 12.5cm dia7x4x3.6= 100.8m

###Qty taken for cost using once = 1 metre 12.6 29 365.4in G.I. Plain sheet 20.37 sqm = 116kg. Or 1.16quintal

###Qty taken for cost using once =1 quintal .145 3,450 500.25qtlCarriage-Kail wood = 2.05cum.

2Bailies- 100.8x(. 125) /4x3.142 = 1.24cum.Total = 3.29 cum.-

###Qty taken for cost using once = cum .4112 60.81 25.010.4112 cumG.I. Sheet = 0.116 t

###Qty taken for cost using once = 0 tonne .0145 47.29 .690.0145 tLabour:

0 1 Carpenter Ilnd class Day 16 141.6 2 265.60###Beldar Day 13 135.25 1,758.25###Sundries L.S. 11.7 1 11.7

TOTAL 9,026.9Add 1 % for water charges 90.27TOTAL 9,117.17Add 15%for contractor’s profit and overheads 1,367.58Costof20.37sqm. 10 484.75Cost per sqm. 514.72Say 514.7

164

Page 156: DAR_Vol_1

### Centring and shuttering including strutting, propping etc. and removal of form for5.9.10 Extra for arches, domes, vaults exceeding 6 m span

CodDescription Unit Quantity Rate AmountDetails of cost per sqm.Centering and shuttering for arches and carvedsurface exceeding 6m in span (an average of8m)Radius R = 5m 2R-2=4+4

-1 4tan ( ) = 53.28°

3o

“2x53.2 = 106°Surface area=2x22/7x5x3.6x106/360=33.3lsqm.Arc=9.25mMaterial:Tie-2x8xO. 18x0.05 =0.144cumStruts-2x2.5x0.1x0.1 =0.050cum.Struts-2xl .77x0.1 xO. 1 =0.035cum.Ribs-6x 1.54x0.23x0.1 =0.213cum.Struts-2x 1.72x0.1 xO. 1 =0.034cum.Total=0.476cum.For four such frames=0.476x4= 1.904 cum.laggings-75x3.6x0.125x0.075=2.531cum.Tie-2x3.6xO.225xO.O38=O.O62cum.Brace-3x2x2.14x0.225x0.038=0.110cumBrace-3x4x3.8x0.225x0.038=0.390 cumSleepers-4x3.6x0.20x0.15=0.432 cumSleepers-2x4x3.6xO. 175x0.075=0.378Vertical post-4x4x-3.6x0.15x0.15=1.296 “Total =7.103cum. or 7103 cudm

###Qty taken l/8th of qty for cost u 10cudm 887.9 160.00 14206.407.103/8 = cum = 887.9 Cudm

###Carriage of wood cum .8879 60.81 53.99Fittings:3 way straps 50mmxl 0mm = 32 Nos.32 no. @0.50cm each = 16mStraps-50mmxl0mm = 8 Nos. @0.25cm each= 2m= 18m

###18m, wt @ 3.9kg/m = 70.2 kg. = quintal 0.0878 2900.00 254.62Qty taken l/8th of qty for cost using once =0.702/8 = 0.08775

###Bolts 160 Nos. 254 mm long 16mquintal .08 4,300 344160x.254x 1.58=64.21 kg=0.64q. sQty taken l/8th of qty for cost using once =0.64/8 = 0.08

###Carriage of steel = 0.1342t tonne .0168 47.29 .79Qty taken l/8th of qty for cost using once =0.1342/8 = 0.01677 cumLabour:

###Carpenter 2nd class Day 28 141.6 3,964.8###Beldar Day 24 135.25 3,246###Sundries L.S. 134.55 1 134.55

Less Cost of shuttering etc. for an archexceeding 6 m span i.e. for an average of 8 mspan

Page 157: DAR_Vol_1

165CodDescription Unit Quantity Rate Amount

(A) Rate as per item no 5.9.9 sqm 33.31 514.70 (-)17144.66TOTAL 5,060.49Add 1% for water charges on all exept ‘A’ 222.05TOTAL 5,282.54Add 15%for contractor’s profit and overheads @ 3,364.08on all exept ‘A’cost of 33.31 sgm. 8,646.62cost per sgm of soffit area 259.58Say 259.6

### Centring and shuttering including strutting, propping etc. and removal of form for :5.9.11 Chimneys and shafts

CodDescription Unit Quantity Rate AmountDetails for 7.9m long and 1.00m high wallArea of contact 2x7.9x1.0 = 15.8 sqm.Materials :Adding for maintenance @ 10% of costTaking salvage value after full use of material@ 25% of cost

###Wall form Panel (1.25x0.5) 2x3x2each .51 980 499.8Qty taken for cost of using once = 24x0.85/40= 0.51

###100 mm channel shoulder 2.5m loeach .17 1,000 170Qty taken for cost of using once = 8x0.85/40== 0.17

###Bridge clip 2x6x2 = 24 each .51 75 38.25Qty taken for cost of using once = 24x0.85/40= 0.51

###Single clip 2x3x2 = 12 each .255 60 15.3Qty taken for cost of using once = 12x0.85/40= 0.255

###M.S. Tube 40mm 2x2x8m = 32m metre .68 225 153Qty taken for cost of using once = 32x0.85/40= 0.68

###Nut & Bolts L.S. 27.63 1 27.63Qty taken for cost of using once =1300x0.85/40= 27.63

###Carriage L.S. 78 1 78Labour:

###Fitter Grade-I Day 3.5 151.5 530.25###Beldar Day 6 135.25 811.5###Shuttering oil L.S. 78 1 78###Sundries L.S. 52 1 52

TOTAL 2,453.73Add 1 % for water charges 24.54TOTAL 2,478.27Add 15% for contractor’s profit and overheads 371.74Cost for 15.8 sqm. 2,850.01Cost per sqm. 180.38Say 180.4

Page 158: DAR_Vol_1

166### Centring and shuttering including strutting, propping etc. and removal of form for :

5.9.12 Well steiningCode Description Unit Quantity Rate Amount

Details of cost 26.39 sqm.Surface areaOutside area =22/7x4.40x1.00 - 13.82sqm.= 26.39 sqm. “Assuming that the timber will becomeunserviceable after being used 8 timesAdd for carriage, labour for erection anddismantling etc. @ l/6th of the cost ofmaterialPlanks 38 mm (Seconti class kail wood)26.39x0.038= 1.00cum.Wastage 20% = 0.20cum.= 1.20cum. or 1200 cudm.

### Qty for cost using once = 1200 x 10 cudm 350 178 6,230350 Cudm2nd class kail wood battensInside = 2x25x0.50x0.075x0.038 =0.0712cum.Outside = 2x28x0.50x0.075x0.038 =0.0798cum.= 0.1510cum.Wastage 5% = 0.0076 cum.= 0.1586cum. or 158.60 cudm

### Qty for cost using once = 0.1586 10 cudm 46.26 160 740.16= 46.26 cudmSafeda bailies 125mm dia.Inside: 25x1.00 = 25.00mOutside: 28x1.00 = 28.00m= 53.00m

0 302 Qty for cost using once = 53 x (1 metre 15.46 29 448.1615.46 m 7,418.5TOTAL 74.18Add 1% for water charges 7,492.68TOTAL 1,123.9Add 15% for contractor’s profit and overheads 8,616.58Cost for 26.39sqm. 326.51Cost per sqm. 326.5Say

### Centring and shuttering including strutting, propping etc. and removal of form for :5.9.13 Vertical and horizontal fins individually or forming box louvers band, facias and

eaves boards.

Code Description Unit Quantity Rate AmountDetails of cost for fins 4 vertical fins 4 metrehigh and at 1 metre centres, with two

Page 159: DAR_Vol_1

167CodDescription Unit Quantity Rate Amount

horizontal fins all projecting 60cm from faceof wall and 5 cm thick-i.e.4x4x1.215+2x3x0.65=23.90 sqmMaterials :(i) Planks 2nd class kail wood 38mmthick-4x4x1.25=20.0023x0.65 =3.90= 23.90Wastage @ 5% = 1.20= 25.10sqm.25.10x0.038=.954 cum or 954 cudm

###Qty for cost using once = 954/8 10 cudm 119.25 178 2,122.65(ii) Battens (2nd class kail wood)-4x2x5x0.60x0.075x0.050=0.0903x2x5x1.00x0.075x0.050=0.1122x6x0.60x0.075x0.100=0.054= 0.256 Cum.Wastage® 5% =0.013 cum= 0.269 cum= 269 cudm

###Qty for cost using once = 269/8 10 cudm 33.625 160 538(iii) Safeda Bailies 125mm dia-2x2x6x4.00 =96mWastage @5% = 4.8m= 100.8 m

###Qty for cost using once = 100.8/ meter 12.6 29 365.4(iv) Carriage timber-Planks = 0.954Battens = 0.269

2Bailies 100.8x(.125) /4x3.142=1.238cum.= 2.461 cum

###Qty for cost using once = 2.461/ cum .3076 60.81 18.71Labour:For assembling, erection, dismantling andcleaning

###Carpenter 2nd class Day 11 141.6 1,557.6###Beldar Day 11 35.25 1,487.75###Sundries L.S. 80.73 1 80.73

TOTAL 6,170.84Add 1% for water charges 61.71TOTAL 6,232.55Add 15% for contractor’s profit and overheads 934.88Cost for 25.10 sqm. 7,167.43Cost per sqm. 285.56Say 285.55

5.9.14 Extra for shuttering in circular work sqm 20% of respective centring & shotting

168

Page 160: DAR_Vol_1

### Centring and shuttering including strutting, propping etc. and removal of form for :5.9.15 Small lintels not exceeding 1.5m clear span, moulding as in cornices, window sills,

string courses, bands, copings, bed plates, anchor blocks and the like.

CodDescription Unit Quantity Rate AmountDetails of cost for footing size2.7mx2.7mxl.00mContact area = 10.8 sqm.Assuming shuttering material will becomeunserviceable after use of 40 timesAdding for maintenance @ 10% of costTaking salvage value after full use of material@ 25% of cost

###Wall form panel 1250x500mm each .34 980 333.2Qty taken for cost of using once = 16x0.85/40= 0.34

###Corner angle (1.5m long) each .085 280 23.8Qty taken for cost of using once = 4x0.85/40 =

.085###100mm channel shoulders 2.5m each .17 1,000 170

Qty taken for cost of using once = 8x0.85/40 =.17

###Double clip (bridge clip) each .34 75 25.5Qty taken for cost of using once = 16x0.85/40= 0.34

### Single clip each .17 60 10.2Qty taken for cost of using once = 8x0.85/40 =

.17###MS tube 40mm - 4x2.7m = 10.8 metrer .2295 225 51.64

Qty taken for cost of using once =10.8x0.85/40 =0.2295

###Assembly nuts & bolts L.S. 22.1 1 22.1Qty taken for cost of using once =1040x0.85/40 = 22.10

###Carriage L.S. 78 1 78Labour:

###Fitter Grade-I Day .75 151.5 113.621###Beldar Day 1.5 135.25 202.88###Shuttering oil L.S. 52 1 52###Sundries L.S. 26 1 26

TOTAL 1,108.94Add 1% for water charges 11.09TOTAL 1,120.03

Add 15% for contractor’s profit and overheads 168Cost for 10.8 sqm. 1,288.03Cost per sqm. 119.26Say 119.25

169### Centring and shuttering including strutting, propping etc. and removal of form for :

5.9.16 Edges of slabs and breaks in floors and walls.

Page 161: DAR_Vol_1

5.9.16.1Under 20 cm wide

CodDescription Unit Quantity Rate AmountUnder 20cms wideConsider a 3mx3m slab 15cms thick12m edge LengthAssuming that the timber will becomeunserviceable after being used 8 times.(i) Planks 30mm thick (2nd class Kail wood orequivalent local soft wood)4x3x0.15x0.030=0.054cum

###Wastage @5% = 0.003 cum. 10 cudm 7.125 178 126.82Total = 0.057 cum 57 cudmQty taken for cost of using once = 57/8 =7.125 cudm(ii) Battens 75mmxl00mm (2nd class Kailwood)Horizontal 2x4x0.075x0.1x0.5=0.030Horizontal 2x4x0.075x0.1 x 1.5=0.090(iii) Vertical battens16x0.15x0.075x0.030M=O.0054(iv) Struts16x0.25x0.075x0.075=0.0225Total = 0.1479\"’Wastage @5% =0.0074Total = 0.1553 cum’= 155 cudm

###Qty taken for cost ef using once 10 cudm 19.375 160 31019.375 cudmCarriage of timberPlanks = 0.057 cum.Battens = 0.155 cum.Total = 0.212 cum.

###Qty taken for cost of using once cum .0265 60.81 1.610.0265 cumLabour:For assembling erection dismantling &cleaning.

###Carpenter Ilnd class Day .81 141.6 114.7###Mazdoor (Male) Day .54 135.25 73.04###Sundries L.S. 5.2 1 5.2

TOTAL 631.37Add 1% for water charges 6.31TOTAL 637.68Add 15% for contractor’s profit and overheads 95.65Cost of 12 metres 733.33Cost of one meter 61.11Say 61.1

170### Centring and shuttering including strutting, propping etc. and removal of form for :

5.9.16 Edges of slabs and breaks in floors and walls.5.9.16.2 Above 20 cm wide

Page 162: DAR_Vol_1

CodDescription Unit Quantity Rate AmountAbove 20cm wideConsider a 4mx4xslab 25cms thick 16 metreedge lengthMaterials :(i) Planks 38mm thick4x4x0.25x0.038 = 0.152Wastage @ 5% = 0.008Total = 0.160 cum. = 160 cudm

###Qty taken for cost of using once = 160/8 = 20 cudm 20 178 356(ii) Battens06x2x0.6 x0.075x0.100=0.0545x2x1.5x0.075x0.100=0.113Total =0.167Wastage @ 5% = 0.008Total =0.175 cum. = 175 cudm

###Qty taken for cost of using once 10 cudm 21.88 160 350.0821.88 cudmCarriage of timberPlanks = 0.16 cum.Battens = 0.175 cum.Total = 0.335 cum.

###Qty taken for cost of using once cum .0419 60.81 2.550.0419 cumLabour-For assembling erection dismantling &cleaning.

###Carpenter Ilnd class Day 1 141.6 141.6###Mazdoor (Male) Day .75 135.25 101.44###Sundries L.S. 6.5 1 6.5

TOTAL 958.17Add 1% for water charges 9.58TOTAL 967.75Add 15% for contractor’s profit and overheads 145.16Cost of 4 sqm. 1 112.91Cost of 1 sqm. 278.23Say 278.25

### Centring and shuttering including strutting, propping etc. and removal of form for :5.9Cornices and mouldingsCodDescription Unit Quantity Rate Amount

Details of cost for 10m long moulding 10cmprojection,20cm depth and 40cm girthArea in contact 10x0.40 = 4.00 sqm.Assuming that the timber will becomeunserviceable after being used 8 times.(I) Planking 30mm thick = 4sqm.Extra & Wastage 20% = 0.8 sqm.Total = 4.8 sqm.4.8x0.038 = 0.182 cum = 182 cudm’

171CodDescription Unit Quantity Rate Amount

Page 163: DAR_Vol_1

###Qty taken for cost using once = 182/8 = 22.75 10 cud 22.75 178 404.95cudm(ii) Battens-Joining to Planking1x10x0.1x0.075 = 0.075 cum.From bottom shuttering10xl.5x0.lx0.075 = 0.113 cum.Wales10x0.4mx0.1x0.075 = 0.030 cum.Total = 0.218 cum = 218 cudm

### Qty taken for cost using once 10 cudm 27.25 160 436cudm(iii) Bailies 125 mm dia.Slant 10x0.3 =3.00 mver. 6x3.5 = 21.00mTotal = 24.00 mWastage @ 5% = 1.20 mTotal = 25.20 m

###Qty taken for cost using once = metre 3.15 27 85.05Carriage:Planking = 0.188 cum.Battens & Wales = 0.218 cum.Bailies

225.2x22/7x(0.125) /4 = 0.310 cum.Total = 0.710 cum.

###Qty taken for cost using once = cum .0888 60.81 5.40.0888 cumLabour for assembling, erection, dismantling& cleaning

###Carpenter Ilnd class Day .63 141.6 89.21###Mazdoor (Male) Day .63 135.25 85.21###Sundries L.S. 6.5 1 6.5

TOTAL 1 112.32Add 1% for water charges 11.12TOTAL 1 123.44Add 15% for contractor’s profit and overheads 168.52Cost of 4 sqm. 1 291.96Cost of 1 sqm. 322.99Say 323

### Centring and shuttering including strutting, propping etc. and removal of form for :5.9Small surfaces such as cantilever ends, brackets and ends of steps, caps and

bases to pilasters and columns and the like.CodDescription Unit Quantity Rate Amount

Details of cost for a bracket1.20m projected Front area 0.50x0.60mEnd area 0.50x0.75mArea in contact with concrete

22x{(0.60+0.75)/2x1.2}= 1.62 MFront 0.5x0.6 = 0.30 sqm.Bottom 0.5x1.21 = 0.605 sqm.Total = 2.525 sqm.Materials:Assuming that the timber will becomeunserviceable after being used 8 times.

Page 164: DAR_Vol_1

172CodDescription Unit Quantity Rate Amount

Timber Ilnd class kail wood or equivalentlocal soft wood(I) Plank 30mm thick.Sides 2{(0.60\"0.75)/2xl.238} = 1.6713 sqmBattens 0.576x1.21 =0.697Front 0.5x0.638 =0.319Total = 2.687 sqm.Cubical contents2.687x0.038 =0.102 cum.Wastage @ 5% = 0.005 cum.Total =0.107 cum.

### Qty taken for cost using once = 10 cudm 13.375 178 238.0813.375 cudm(ii) Battens-0.05x0.052x1.238 = 2.476m2x1.21 = 2.42m2x0.688 = 1.376m2x0.838 = 1.676m3x0.5 = 1.50mTotal = 9.448mCubical contents9.448x0.05x0.05 = 0.024 cumWastage 5% = 0.0012 cum.Total = 0.0252 cum = 25.2 cudm

###Qty taken for cost using once = 25.2/8 = 3.15 cudm 3.15 160 50.4(iii) Bailies 125mm dia.1x2.5 = 2.50m1x2.65 = 2.65mTotal = 5.15 mWastage 5% = 0.26mTotal =5.41 m

###Qty taken for cost using once = metre .6763 27 18.260.6763 mCarriage:Planks =0.107 cum.Battens = 0.0252 cumBailies

25.41x22/7x(0.125) /4 = 0.066 cum

###Qty taken for cost using once = cum .0248 60.81 1.510.0248 cudmLabour for assembling, erection, dismantling& cleaning

###Carpenter Ilnd class Day .8 141.6 113.28###Mazdoor (Male) Day .8 135.25 108.2###Sundries L.S. 7.15 1 7.15

TOTAL 536.88Add 1% for water charges 5.37TOTAL 542.25Add 15% for contractor’s profit and overheads 81.34Cost of 2.525 sqm. 623.59Cost of 1 sqm. 246.97Say 246.95

Total = 0.198 cum

Page 165: DAR_Vol_1

173### Centring and shuttering including strutting, propping etc. and removal of form for:

5.9.19 Weather shade, Chajjas, corbels etc., including edges.

CodDescription Unit Quantity Rate AmountConsider a weather shade over a window ofsize1.5mxl.2mSize of weather shade 1.80x0.45mThickness at front = 0.05mThickness at fixed edge = 0.07mArea in contact with concrete Bottom1x0.45x1.80 = 0.8101x0.05x1.80 = 0.0942x0.45x0.06 = 0.027Total = 0.954 sqm.Materials :Assuming that the timber will becomeunserviceable after being used 8 times.Ilnd class kail wood(i) Planking 38mm thick.Bottom 1x1.876x0.488 = 0.915 sqm.1x1.876x0.05 =0.94 sqm.2x0.45x0.06 = 0.027 sqm.Total =1.036 sqm.Add 5% wastage = 0.052 sqm.Total = 1.088 sqm.Cubic contains1.088x0.038 =0.041 cum = 41 cudm

###Qty taken for cost using once = 4 10 cudm 5.125 178 91.22cudm(ii) Battens-2x0.60x0.075x0.10 = 0.009Ends with bearing center1x0.45x0.075x0.10 = 0.003Total = 0.012 cum = 12 cudm

###Qty taken for cost using once 10 cudm 1.5 160 24cudm(iii) Bailies 125mm dia.2x2.1 =4.2mWastage 5% = 0.21mTotal = 4.41 m

###Qty taken for cost using once = metre .5513 27 14.890.5513 mCarriage:Plank = 0.041 cum.Battens = 0.012 cum.Bailies

24.41x22/7x(0.125) /4 = 0.054 cum.Total = 0.107 cum

###Qty taken for cost using once = 0 cum .01338 60.81 .810.01338 cumLabour for assembling, erection, dismantling

Page 166: DAR_Vol_1

& cleaning0 1 Carpenter II class Day .3 141.6 42.48###Mazdoor (Male) Day .25 135.25 33.81###Sundries L.S 5.2 1 5.2

TOTAL 212.41

174CodDescription Unit Quantity Rate Amount

Add 1% for water charges 2.12TOTAL 214.53Add 15% for contractor’s profit and overheads 32.18Cost for 0.954 sqm. 246.71Cost of 1 sqm. 258.61Say 258.6

### Centring and shuttering including strutting, propping etc. and removal of form for:5.9.20 Suspended floors, roofs, landings, balconies and access platform, with water proof

ply 12mm thick.CodDescription Unit Quantity Rate Amount

Detail of cost for a room4.50x3 = 13.50 sqm, height 3.5 mMaterials:Adding for maintenance @ 10% of costTaking salvage value after full use of material@ 25% of cost1. Plates (size 0.75x0.60)Angle 40x40x5mm2x0.75= 1.50 m2x0.60= 1.20 m= [email protected]/m = 8.I kgWeight of one plate =8.1 OkgAdd for wastage @ 5% = 0.41 kgTotal = 8.51kgTotal weight of all plates = 5x6x8.51 = 255.30 kgQty taken for cost using once.= 255.30x0.85/8= 27.13kg(X) Rate as per item no 10.1 kg 27.13 42.15 1143.53 (X)

###Water proof ply 12mm thick. sqm 1.77 572 1,012.441x4.50x3.00=13.50sqm Add wastage5% =0.68sqmTotal 14.18sqmQty taken for cost using once 14.18/8 = 1.77sqm

###2. Adjustable span- ESOSI (2.35- each .1063 1 600.00 170.08Qty taken for cost using once = 5x0.85/40= 0.531

###3. Adjustable telescope prop 3m each .1275 1 000.00 127.5Qty taken for cost using once = 6xO.85/40

.6375###4. Assembly nut & bolts etc. L.S. 12.63 1 12.63###Carriage L.S. 130 1 130

Labour:###Fitter grade-I Day 3 151.5 454.5###Beldar Day 6 135.25 811.5

Page 167: DAR_Vol_1

###Shuttering oil L.S. 78 1 78###Sundries L.S. 52 1 52

TOTAL 3 992.18Add 1 % for water charges except on ‘X’ 28.49TOTAL 4,020.67Add for contractor’s profit and overheads @ 431.5715% except on’X’Cost for 13.50 sqm. 4 452.24Cost per sqm. 329.8Say 329.8

175### Centring and shuttering including strutting, propping etc. and removal of form for :

5.9.21 Lintels, beams, plinth beams, girders, bressumers and cantilevers, with water proofply 12mm thick.

CodDescription Unit Quantity Rate AmountConsider a beam of 6 m clear span, 0.50 mdeep 0.30 m wide and height 3.5 m from floorCubical contents6.60x0.5x0.3 = 0.99 cum1x1.30x6.00 = 7.80 sqmMaterials :Assuming shuttering will becomeunserviceable after use of 8 timesAdd maintenance charges @ 10% of cost ofmaterialLess salvage value of material after full use @25% of cost of material1. Steel plates for side and bottom (plate size1.20 x 0.50m)Angle 40x40x5mm2x1.20 = 2.40 m3x0.50= 1.50 m3.90 m @ 3.00 kg/m = 11.70 kgWeight of one plate = 11.70 kg.Add for wastage = 0.585kg.Total =12.285 kg.Total weight of all plates3x5x12.285 = 184.275 kgQty taken for cost of using once =184.275*x0.85/8 =19.58 kgRate as per item no 10.1 kg 19.58 42.15 825.3

###Water proof ply 12mm thick, 1x1.30x6.00 = sqm 1.02 572 583.447.80 sqm Add 5% wastage 0.39 sqmTotal 8.19 sqmQty taken for cost of using once8.19/8 = sqm= 1.02 sgm

###(ii) Props 3m (adjustable telesco each .1275 1,000 127.53.75m)Qty taken for cost of using once = 6 x0.85/40=0.1275 m

###(iii) Beam clamp 300-380 mm( each set .1063 375 39.86Qty taken for cost of using once = 5x0.85/40

Page 168: DAR_Vol_1

= 0.1063m###(iv) Assembly nut & bolts etc. L.S. 11.05 1 11.05###Carriage L.S. 78 1 78

Labour:###Fitter Grade-1 Day 1.25 151.5 189.38###Beldar Day 2.5 135.25 338.12###Shuttering oil L.S. 39 1 39###Sundries, paper tape etc. L.S. 26 1 26

TOTAL 2,257.65Add 1% for water charges except on ‘X’ 14.32TOTAL 2,271.97Add for contractor’s profit and overheads @ 21715% except on ‘X’Cost for 7.80 sqm. 2,488.97Cost per sqm. 319.1Say 319.1

176### Providing and fixing tie bolt, spring coil and plastic cone in wall shuttering complete

as per the Engineer-in-charge5.10.1 12 mm dia. & 100 mm length.

CodDescription Unit Quantity Rate AmountDetails of cost for wall length 7.90mxlm (24set)Material:

###Tie bolt 12mm dia & 100 mm len each 24 31 744###Spring Coil 12mm dia. each 48 10 4807325 Plastic cone 12mm dia. each 48 12 576###Carriage: L.S. 13 1 13

Labour :###Sundries L.S. 26 1 26

TOTAL 1 839.00Add 1 % for water charges 18.39TOTAL 1 857.39Add 15% for contractor’s profit and overheads 278.61Cost for 24 sets 2 136.00Cost of 1 each set 89Say 89

### Providing and fixing tie bolt, spring coil and plastic cone in wall shuttering completeas per the direction of Engineer-in-charge

5.10.2 12 mm dia. & 150 mm length.CodDescription Unit Quantity Rate Amount

Details of cost for wall length 7.90mxlm (24set)Material:

###Tie bolt 12mmjda& 150mm lengteach 24 42 1,008###spring coil 12 mm dia each 48 10 480###Plastic cone 12mm dia. each 48 12 576###Carriage: L.S. 13 1 13

Labour:Sundries L.S. 26 1 26TOTAL 2,103

Page 169: DAR_Vol_1

Add 1 % for water charges 21.03TOTAL 2,124.03Add 15% for contractor’s profit and overheads 318.6Cost for 24 sets 2,442.63Cost of 1 each set 101.78Say 101.8

### Providing and fixing tie bolt, spring coil and plastic cone in wall shuttering completeas per the direction of Engineer-in-charge

5.10.3 20mmdia. & 150 mm length.CodDescription Unit Quantity Rate Amount

Details of cost for wall length 7.90mxlm (24set)Material:

###Tie bolt 20mm ida & 150mm lengeach 24 57 1,368###Spring coil 12 mm dia each 48 10 480###Plastic cone 12 mm dia each 48 12 576

177CodDescription Unit Quantity Rate Amount###Carriage: L.S. 5 2.6 13

Labour:###Sundries L.S. 10 2.6 26

TOTAL 2,463Add 1% for water charges 24.63TOTAL 2,487.63Add 15% for contractor’s profit and overheads 373.14Cost for 24 sets 2,860.77Cost of 1 each set 119.2Say 119.2

### Providing and fixing tie bolt, spring coil and plastic cone in wall shuttering completeas per the direction of Engineer-in-charge

5.10.4 20 mm dia.& 225 mm length.CodDescription Unit Quantity Rate Amount

Details of cost for wall length 7.90mxlm (24set)Material:

###Tie bott.20mm dia & 225mm len each 24 72 1,728###Spring coil 12 mm dia each 48 10 576###Plastic cone 12mm dia. each 48 12 576###Carriage: L.S. 5 2.6 13

Labour:9999 Sundries L.S. 10 2.6 26

TOTAL 2 823.00Add 1 % for water charges 28.23TOTAL 2 851.23Add 15% for contractor’s profit and overheads 427.68Cost for 24 sets 3 278.91Cost of 1 each set 136.62Say 136.6

### Extra for additional height in centring, shuttering where ever required with adequatebracing, propping etc. including cost of de-shuttering and decentring at all levels,

Page 170: DAR_Vol_1

over a height of 3.5 m, for every additional height of 1 metre or part thereof (Planarea to be measured)

5.11.1 Suspended floors, roofs, landing, beams and balconies (Plan area rCodDescription Unit Quantity Rate Amount

Details of cost for a Room of size 6mx4.8m =28.8 sqm. Material:Assuming that shuttering material will becomeunserviceable after use 40 timesLess salvage value of material after full use @25% of cost materialAdd 10% of cost of material for maintenance1. Prop 4m

###Qty taken for cost using once = 21 x0.85/40 = each .4463 1,030 459.69.4463

2. Prop 3m###Qty taken for cost using once = 21x0.85/40 = each .4463 1,000 446.3

Difference of rate between 4m prop and 3mprop. 7x3

178CodDescription Unit Quantity Rate Amount

2.BracingMS tube 40mm7x4.8m = 33.60m3x6.0m= 18.00mTotal = 51.60m

###Qty taken for cost using once = meter 1.0965 1.0965 246.71= 1.09653. Double coupler (40x40)

###Qty taken for cost using once = 2 each .4463 45 20.08.4463

###Carriage L.S. 65 1 65Labour:

###Fitter Grade-I Day 3 151.5 454.5###Beldar Day 6 135.25 811.5###Sundries L.S. 130 1 130

TOTAL 2,633.78Add 1 % for water charges 26.34TOTAL 2,660.12Add 15% for contractor’s profit and overheads 399.02Cost for 28.8 sqm. 3,059.14Cost per sqm. 106.22Say 106.2

### Providing, hoisting and fixing upto floor five level precast reinforced cement concretework in string courses, bands, copings, bed plates, anchor blocks, plain windowsills and the like including the cost of required centring, shuttering, finishing smoothwith 6 mm thick cement plaster 1:3 (1 cement: 3 fine sand) on exposed surfacescomplete but excluding cost of reinforcement with 1:2:4 (1 cement: 2 coarse sand: 4graded stone aggregate 20mm nominal size).

CodDescription Unit Quantity Rate AmountDetails of cost for 1 cum. Materials :(A) Cement concrete 1:2:4 in stri cum 1 cum 4 814.35 4 814.35

Page 171: DAR_Vol_1

course etc-(A) (Rate as per item no 4.5)(NB : Rate has been taken including cost offixing in CM 1:2 as precast members are to befixed in CM 1:2)(1 cement: 2 coarse sand) asper CPWD specificationsLabour:Extra labour for laying CC in RCC work

###(B) Beldar Day .1 135.25 13.52 (B)###(B) Bhishti Day .2 138.45 27.69 (B)###(B) Mason 1st class Day .04 151.5 6.06 (B)###(B) Mason 2nd class Day .04 141.6 5.66 (B)###(B) Mate Day .04 138.45 5.54 (B)

TOTAL 4,872.82(C) Add for water charges @ 1 % on B .58TOTAL 4,873.4Add for contractor’s profit and overheads @ 8.8615% on B+CCost for 1 cum. 4,882.26Say 4,882.25

179### Providing, hoisting and fixing upto floor five level precast reinforced cement

concrete in small lintels not exceeding 1.5m clear span upto floor five levelincluding the cost of required centring, shuttering and finishing smooth with 6mm thick cement plaster 1:3 (1 cement : 3 fine sand) on exposed surfaces butexcluding the cost of reinforcement with 1:2:4 (1 cement: 2 coarse sand : 4 gradedstone aggregate 20mm nominal-size).

CodDescription Unit Quantity Rate Amount

Details of cost for a lintel:Materials:1.5m clear span = 1.8x0.20x0.15 = 0.054 cum.Cement Concrete 1:2:4 cum .054 3,579.1 193.27(Rate as per item no. 4.2.3) sqm .6 119.25 71.55Centring and shuttering(Rate as per item no. 4.3.1) sqm .9 62.15 55.94Finishing(Rate as per item no. 13.24.1)Labour:Add extra labour for laying CC in RCC work

###(B) Beldar Day .005 135.25 .68###(B) Bhishti Day .01 138.45 1.38###(B) Mason lstclass Day .002 151.5 .3###(B) Mason 2nd class Day .002 141.6 .28###(B) Mate Day .002 38.45 .28

TOTAL 323.68Add for water charges @ 1% on ‘B’ .03TOTAL 323.71Add for contractor’s profit and overheads @ .4415% on ‘B+CCost for 0.054 cum. 324.15

Page 172: DAR_Vol_1

Cost per cum 6,002.78Say 6,002.8

### Providing, hoisting and fixing upto floor five level precast reinforced cementconcrete in mouldings as in cornices, windows sills etc. including setting incement mortar 1:3 (1 cement : 3 coarse sand) cost of required centring, shutteringand finishing smooth with 6 mm thick cement plaster 1:3 (1 cement : 3 fine sand)on exposed surfaces complete but excluding the cost of reinforcement with 1:2:4(1 cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size).

CodDescription Unit Quantity Rate AmountDetails of cost forlmx0.20x0.15=0.03 cumCement concrete 1:2:4(Rate as per item No. 4.2.3) cum .03 3,579.1 107.37

###(A) Mortar and labour for hoistingL.S. 2.73 1 2.73Finishing sqm .5 62.15 31.08(Rate same as per item no. 13.24.1)Centring and shuttering sqm .36 119.25 42.93(Rate same as per item no.4.3.1)

###(A) Add for extra labour for hois L.S. 1.61 1 1.61Add Extra labour for moulding :

###(A) Mason 1st class 0.58x0.03 Day .0174 151.5 2.64###(A) Mason 2nd class 0.58x0.03 Day .0174 141.6 2.46###(A) Coolie 1.5x0.03 Day .045 135.25 6.09

180CodDescription Unit Quantity Rate Amount###(A) Bhishti 0.06x0.03 Day .0018 138.45 .25

Extra labour for laying CC in RCC###(A) Beldar 0.1x0.03 Day .003 135.25 .41###(A) Bhishti 0.2x0.03 .006 138.45 .83###(A) Mason 1st class 0.04x0.03 .0012 151.5 .18###(A) Mason 2nd class 0.04x0.03 .0012 141.6 .17###(A) Mate 0.04x0.03 .0012 138.45 .17

TOTAL 198.92(B) Add for water charges @ 1 % on ‘A’ .18TOTAL 199.1Add for contractor’s profit and overheads @ 2.6615% on ‘C+D’Cost for 0.03 cum 201.76Cost for 1 cum. 6,725.33Say 6,725.35

5.15 : Providing, hoisting and fixing upto floor five level precast reinforced cement concretein lintels, beams and bressumers including setting in cement mortar 1:3 (1 cement :3 coarse sand), cost of required centring and shuttering and finishing smooth with6 mm thick cement plaster 1:3(1 cement: 3 fine sand) on exposed surfaces butexcluding the cost of reinforcement with 1:2:4 (1 cement: 2 coarse sand : 4 gradedstone aggregate 20 mjn nominal size).

CodDescription Unit Quantity Rate AmountDetails of cost for beam 6.60m long 0.50mdeep and 0.30m wide = 6.60x0.50x0.30 = 0.99 cum.(A) Cement concrete 1:2:4 cum .99 3 257.45 3 224.88

Page 173: DAR_Vol_1

(Rate as per item No.4.1.3) sqm 7.8 62.15 484.77(Rate same as per item no. 13.16.1)Finishing(A) Centring and shuttering sqm 6.9 119.25 822.82(Rate same as per iterh no. 4.3.1)Extra labour for lifting material upto floor Vlevel

###(B) Coolie Day 1.11 135.25 150.13LABOURExtra labour for layin cement concrete in RCCwork

###(B) Beldar 0.10x0.99 Day .099 135.25 13.39###(B) Bhishti 0.20x0.99 Day .198 138.45 27.41###(B) Mason 1st class 0.04x0.99 Day .0396 1 51.50 6###(B) Mason 2nd class 0.04x0.99 Day .0396 141.6 5.61###(B) Mate 0.04x0.99 Day .0396 138.45 5.48###(B) Cement mortar 1:3 for fixing L.S. 89.7 1 89.7###(B) Labour for hoisting, TransportL.S. 269.1 1 269.1

in positionTOTAL 5 099.29(C) Add for water charges @1% on ‘B’ 5.67TOTAL 5 104.96Add for contractor’s profit and overheads @ 15% 85.87Cost for 0.99 cum 5 190.83Cost for 1 cum. 5 243.26Say 5 243.25

1815.16 : Providing, hoisting and fixing upto floor five level precast reinforced cement concrete

in shelves including setting in cement mortar 1:3 (1 cement : 3 coarse sand), cost ofrequired centring, shuttering and finishing with neat cement punning on exposedsurfaces but excluding the cost of reinforcement with 1:2:4 (1 cement: 2 coarsesand : 4 graded stone aggregate 12.5mm nominal size).

CodDescription Unit Quantity Rate AmountDetails of cost for one shelf0.90x0.45x0.04m thick= 0.90x0.45x0.04m = 0.0162 cumCement concrete 1:2:4Rate as per Item No 4.1.3 cum .0162 3,257.45 52.77Finisihing(Rate same as per iem no. 13.18) sqm .85 21.4 18.19(A) Centring and shuttering:2x(0 sqm .108 119.25 12.880.108 sqm(Rate same as per item no. 4.3.1)Extra labour for lifting material upto floor Vlevel

###(B) Coolie Day .018 135.25 2.43LABOURExtra labour for laying cement concrete inRCC work due to delay etc.

###(B) Beldar Day .016 135.25 2.16###(B) Bhishti Day .0032 138.45 .44###(B) Mason 1st class Day .0006 151.5 .09

Page 174: DAR_Vol_1

###(B) Mason 2nd class Day .0006 141.6 .08###(B) Mate Day .0006 138.45 .08###(B) Cement mortar 1:3 for fixing L.S. 4.42 1 4.42###(B) Labour for hoisting, TransportL.S. 13.52 1 13.52

in positionTOTAL 107.06(C) Add for water charges @ 1 % on ‘B’ .23TOTAL 107.29Add for contractor’s profit and overheads @ 3.52Cost for 0.0162 cum 110.81Cost for 1 cum. 6 840.12Say 6 840.10

5.17 : Providing, hoisting and fixing upto floor five level precast reinforced cement concretein vertical & horizontal fins individually or forming box louvers setting in cement mortar1:2 (1 cement : 2 coarse sand) including the cost of required centring, shuttering andfinishing smooth with 6mm thick cement plaster 1:3 (1 cement : 3 fine sand) on exposedsurfaces complete but excluding the cost of reinforcement with 1:2:4 (1 cement: 2coarse sand : 4 graded stone aggregate 20 mm nominal size).

CodDescription Unit Quantity Rate AmountDetails of cost for 4 RCC vertical fins 4m highat lm centre to centre with two horizontal fins,all projecting 60cm from face of wall and 5cmthick cubical contents = 0.66 cum.Material:(A) Cement concrete l:2:4 (Rate acum .66 3 257.45 2 149.92(A) Finishing sqm 27.5 62.15 1 709.12(Rate same as per item no. 4.3.1)(A) Centering and shuttering sqm 2.56 119.25 305.28(Rate same as per item no. 4.3.1)

182CodDescription Unit Quantity Rate Amount

Extra labour for lifting material upto floor Vlevel

###(B) Coolie Day .75 135.25 101.44LABOURExtra labour for laying cement concrete inRCC work due to delay etc.

###(B) Beldar Day .066 135.25 8.93###(B) Bhishti Day .132 138.45 18.28###(B) Mason 1st class Day .0264 151.5 4###(B) Mason 2nd class Day .0264 141.6 3.74###(B) Mate Day .0264 138.45 3.66###(B) Cement mortar 1:2 for fixing L.S 17.94 1 17.94###(B) Labour for hoisting, TransportL.S. 71.76 1 71.76

in position###(B) Sundries L.S. 17.94 1 17.94

TOTAL 4 412.01Add for water charges @ 1 % on ‘B’ 2.48TOTAL 4 414.49Add for contractor’s profit and overheads @ 37.5315% on’BC’

Page 175: DAR_Vol_1

Cost for 0.66 cum 4 452.02Cost for 1 cum. 6 745.48Say 6 745.50

5.18 : Providing precast cement concrete Jali 1:2:4 (1 cement: 2 coarse sand : 4 gradedstone aggregate 6mm nominal size) reinforced with 1.6 mm dia mild steel wireincluding centring and shuttering, roughening cleaning, fixing and finishing incement mortar 1:3 (1 cement: 3 fine sand) etc. complete excluding plastering ofthe jambs, sills and soffits.

5.18.1 : 50 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for jali2.00mx0.75m = 1.50 sqm. of jali

###Cost of jail sqm 1.5 145 217.5###Mortar for fixing L.S 6.24 1 6.24###Carriage and sundries L.S 6.2 1 6.2

Labour (for fixing):###Mason 1st class Day .3 151.5 45.45###Mason 2nd class Day .3 141.6 42.48###Beldar Day 1.08 135.25 146.07

TOTAL 463.94Add 1% for water charges 4.64TOTAL 468.58Add 15% for contractor’s profit and overheads 70.29Cost of 1.50 sqm. 538.87Cost of 1 sqm. 359.24Say 359.2

1835.18 : Providing precast cement concrete Jali 1:2:4 (I cement: 2 coarse sand : 4 graded

stone aggregate 6mm nominal size) reinforced with 1.6 mm dia mild steel wireincluding centring and shuttering, roughening cleaning, fixing and finishing in cementmortar 1:3 (1 cement: 3 fine sand) etc. complete excluding plastering of the jambs,sills and soffits.

5.18.2 :40 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 1.2mx0.60m = 0.75 sqm. ofjali.

###Cost of jali sqm .75 115 86.25###Mortar for fixing L.S. .364 1 .364###Carriage and sundries L.S. .364 1 .364

Labour (for fixing):###Mason 1st class Day .12 151.5 18.18###Mason 2nd class Day .12 141.6 16.99###Beldar Day .5 135.25 67.62

TOTAL 196.32Add 1 % for water charges 1.96TOTAL 198.28Add 15% for contractor’s profit and overheads 29.74Cost For 75sqm. 228.02Cost of 1 sqm. 304.03Say 304.05

Page 176: DAR_Vol_1

5.1Providing precast cement concrete Jali 1:2:4 (1 cement: 2 coarse sand : 4 gradedstone aggregate 6mm nominal size) reinforced with 1.6 mm dia mild steel wireincluding centring and shuttering, roughening cleaning, fixing and finishing incement mortar 1:3 (1 cement: 3 fine sand) etc. complete excluding plastering ofthe jambs, sills and soffits.

5.18.3 : 25 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for jali 0.75mx0.5m = 0.375 sqm###Cost of jali sqm .375 92 34.5###Mortar for fixing L.S 1.82 1 1.82###Carriage and sundries L.S 1.82 1 1.82

Labour (for fixing):###Mason lstclass Day .06 151.5 9.09###Mason 2nd class Day .06 141.6 8.5###Beldar Day .25 135.25 33.81

TOTAL 89.54Add 1% for water charges .9TOTAL 90.44Add 15% for contractor’s profit and overheads 13.57Cost of 0.375 sqm 104.01Cost of 1 sqm. 277.36Say 277.35

1845.19 : Encasing rolled steel sections, in beams and columns, with cement concrete 1:2:4

(1 cement: 2 coarse sand : 4 graded stone aggregate 12.5mm nominal size) includingcentring and shuttering complete but excluding cost of reinforcement.

CodDescription Unit Quantity Rate AmountDetails of cost for 0.424 cum.Consider 2 R.S. Joist (150mmx80mm) 4.88mlong placed 30cm apart centre to centreOverall dimensions of the beam 43cmx20cm-(Rate as per item no. 4.16.1)Materials:Concrete work-4.93x0.43x0.20 = 0.424 cumFor 1:2:4 Cement Concrete (1 cement: 2coarse sand : 4 stone aggregate 20mm NS)Rate as per item no. 4.1.3 cum .424 3 257.45 1,381.16Extra labour for laying C.C. in RCC work(Rate as (B) in item No.512)

###(A) Beldar Day .1 135.25 15.52###(A) Bhishti Day .2 138.45 27.69###(A) Mason 1st class Day .04 151.5 6.06###(A) Mason 2nd class Day .04 141.6 5.66###(A) Mate Day .04 138.45 5.54

Form work-4.93x0.83 girth = 4.09 sqm. sqm 4.09 162.65 665.24(Rate as per item N . 5. O

###(B) Sundries and for lifting materiL.S. 21.58 1 21.58

Page 177: DAR_Vol_1

TOTAL 2,126.45Add for water charges @ 1% on A+B .8TOTAL 2,127.35(C) Add for contractor’s profit and overheads @ 12.1315 % onA+B+CCost of 0.424 cum 2,139.48Cost of 1 cum. 5,045.94Say 5,045.95

5.20 : Encasing rolled steel section in grillages with cement concrete 1:2:4 (1 cement: 2coarse sand : 4 graded stone aggregate 12.5mm nominal size) including centringand shuttering but excluding cost of expanded metal and hangers.

CodDescription Unit Quantity Rate AmountDetails of cost for the grillage3.50mx3.50mxl.00mCement concrete 1:2:43.50mx3.50xl.00=12.25cum-Cement concrete 1:2:4Rate as per item no. 4.1.3 cum 12.25 3 257.45 39,903.76Extra labour for laying C.C. in RCC work(Rate as (B) in item 5.12)

###Beldar Day .1 135.25 13.52###Bhishti Day .2 138.45 27.69###Mason 1st class Day .04 151.5 6.66###Mason 2nd class Day .04 141.6 5.66###Mate Day .04 138.45 5.54

Shuttering :2(3.50+3.50)x1.00= 14.00 sqm. sqm 14 162.65 2,277.1(Rate as per item 5. 9.5)TOTAL 42,239.33

185CodDescription Unit Quantity Rate Amount

(B) Add for water charges @ 1% on “A” .58(A) TOTAL 42,239.91Add for contractor’s profit and overheads @ 8.8615 % on “A+B”Cost of 12.25 cum. 42,248.77Cost of 1 cum. 3,448.88Say 3,448.9

5.21 : Extra for providing and fixing expanded metal mesh of size 20x60mm and strands3.25mm wide 1.6mm thick weighing 3.64 kg. per sqm. for encasing of rolled steelsections in beams, columns and grillages excluding cost of hangers.

CodDescription Unit Quantity Rate AmountDeatail of cost for 10 sqmMaterials:Expended metal 20 mm x 60 mm and 1.6 mmthick = 10 sqmwastage 5 % = 0.50 sqm

###Total =10.50 sqm sqm 10.5 200 2,100###Carriage of expended metal L.S 13.52 1 13.52###Wire for tieing L.S 13.52 1 13.52

Cost of bending and placing in position###Blacksmith 1st class Day .25 151.5 37.88

Page 178: DAR_Vol_1

###Beldar Day .25 135.25 33.81TOTAL 2,198.73Add for water charges @ 1 % 21.99TOTAL 2,220.72Add for contractor’s profit and overheads 333.11

15%Cost of 10 sqm 2,553.83Cost of 1 sqm. 255.38Say 255.4

5.2Reinforcement for R.C.C. work including straightening, cutting, bending, placingin position and binding all complete.

5.22.1 : Mild steel and Medium\Tensile steel bars.CodDescription Unit Quantity Rate Amount

Details of cost for 1 quintal-Materials:Mild steel bars = 1.00 qAdd 5% wastage = 0.05

###Total = 1.05 q quintal 1.05 3,075 3 228.75###Carriage of steel 1.05/10 = 0.105 tonne .105 47.29 4.97###Cover block L.S. 26 1 26

26Labour:For straightening, cutting, bending, bindingand placing in position-

###Blacksmith 1st class Day 1 151.5 151.5###Beldar Day 1 135.25 135.25###Sundries and binding wire L.S. 26.91 1 26.91

TOTAL 3,573.38Add 1% for water charges 35.73TOTAL 3,609.11Add 15% for contractor’s profit and overheads 541.37Cost of one quintal 4,150.48Cost of 1 Kg. 41.5Say 41.5

1865.2Reinforcement for R.C.C. work including straightening, cutting\

position and binding all complete.5.22.2 : Hard drawn steel wireCodDescription Unit Quantity Rate Amount

Details of cost for 1 quintal-Materials:Hard drawn steel wire = 1.00 qwastage 5%=0.05q

###Total = 1.05 q quintal 1.05 3,100 3,255###Carriage 1.05q = 0.105 tonne tonne .105 47.29 4.97

Labour:For cutting and laying in position etc-

###Blacksmith 1st class Day 1 151.5 151.5###Beldar Day 1 135.25 135.25###Sundries L.S. 26.91 1 26.91

TOTAL 3,573.63

Page 179: DAR_Vol_1

Add 1% for water charges 35.74TOTAL 3,609.37Add 15 % for contractor’s profit and overheads 541.41Cost of one quintal 4,150.78Cost of 1 Kg. 41.5Say 41.5

5.2Reinforcement for R.C.C. work including straightening, cutting, bending, placingin position and binding all complete.

5.22.3 : Cold twisted barsCodDescription Unit Quantity Rate Amount

Details of cost for 1 quintal-Materials:Deformed twisted steel bars = 1.00 qwastage 5% = 0.05q

###Total = 1.05q quintal 1.05 3,175 3,333.75###Carriage of steel 1.05/10 = 0.105 tonne .105 47.29 4.97###Cover block L.S. 26 1 26

Labour:For straightening, cutting, bending, bindingand placing in position-

###Blacksmith 1st class Day 1 151.5 151.5###Beldar Day 1 135.25 135.25###Sundries and binding wire L.S. 26.91 1 26.91

TOTAL 3,678.38Add 1 % for water charges 36.78TOTAL 3,715.16Add 15% for contractor’s profit and overheads 557.27Cost of one quintal 4,272.43Cost of 1 Kg. 42.72Say 42.7

1875.2Reinforcement for R.C.C. work including straightening, cutting, bending, placing

in position and binding all complete.5.22.4 : Hot rolled deformed barsCodDescription Unit Quantity Rate Amount

Details of cost for 1 quintal-Materials:Deformed twisted steel bars = 1.00 qwastage 5 % =0.05q

###Total = 1.05q quintal 1.05 3,175 3 333.75###Carriage of steel 1.05/10 = 0.105 tonne .105 47.29 4.97###Cover block L.S. 26 1 26

Labour:For straightening, cutting, bending, bindingand placing in position-

###Blacksmith 1st class Day 1 151.5 151.5###Beldar Day 1 135.25 135.25###Sundries and binding wire L.S. 26.91 1 26.91

TOTAL 3678.38Add 1 % for water charges 36.78TOTAL 3,715.16

Page 180: DAR_Vol_1

Add 15% for contractor’s profit and overheads 557.27Cost of one quintal 4,272.43Cost of 1 Kg. 42.72Say 42.7

5.2Reinforcement for R.C.C. work including straightening, cutting, bending, placingin position and binding all complete.

5.22.5 : Hard drawn steel wire fabricCodDescription Unit Quantity Rate Amount

Details of cost for 1 quintal-Materials:Hard drawn steel wire fabric 100kg/7.75kg= 12.903 sqm., wastage 5 % = 0.64 sqm

###Total =13.548 sqm. sqm 13.548 310 4,199.88###Carriage 1.05q = 0.105 tonne tonne .105 47.29 4.97###Cover block L.S. 26 1 26

Labour:For cutting and laying in position.

###Blacksmith 2nd class Day .2 141.6 28.32###Beldar Day 1.5 135.25 202.88###Sundries and binding wire L.S. 13.52 1 13.52

TOTAL 4,475.57Add 1% for water charges 44.76TOTAL 4,520.33Add 15 % for contractor’s profit and overheads 678.05Cost of one quintal 5,198.38Cost of 1 Kg. 51.98Say 52

1885.2Reinforcement for R.C.C. work including straightening, cutting, bending, placing

in position and binding all complete.5.22.6 : Thermo-Mechanically Treated bars.CodDescription Unit Quantity Rate Amount

Details of cost for 1 quintal-Materials:Deformed twisted steel bars = 1.00 qAdd 5% wastage =0.05

###Total =1.05q quintal 1.05 3 175.00 3 333.75###Carriage of steel 1.05/10 = 0.105 tonne .105 47.29 4.97###Cover block L.S. 26 1 26

Labour:For straightening, cutting, bending, bindingand placing in position-

###Blacksmith 1 st class Day 1 151.5 151.5###Beldar Day 1 135.25 135.25###Sundries L.S 26.91 1 26.91

TOTAL 3 678.38Add 1% for water charges 36.78TOTAL 3 715.16Add 10% for contractor’s profit and overheads 557.27Cost of one quintal 4 272.43Cost of 1 Kg. 42.72

Page 181: DAR_Vol_1

Say 42.7

5.23 : Deduct for omitting in R.C.C. work smooth finishing of the exposed surface with6mm thick cement mortar 1:3 (1 Cement: 3 fine sand)

CodDescription Unit Quantity Rate AmountDetails of cost for lOsqm.Materials:Cement mortar 1:3 (cement:3 f cum .072 2,870 206.64(Rate as per items No. 3.3)

###Mason Day .51 146.55 74.74###Coolie Day .75 135.25 101.44###Bhisti Day .92 138.45 127.37###Extra for removing burrs, cleanin L.S. 13.39 1 13.39

brushes pock marking with pointed tool etc.complete

###Scaffolding and Sundries L.S. 11.7 1 11.7TOTAL 535.28Add 1 % for water charges 5.35TOTAL 540.63Add ld^& for contractor’s profit and overheads 81.09Cost of 10 Sqm. 621.72Cost per sqm. 62.17Say 62.15

1895.24 : Extra for rendering smooth the top of suspended floors, landings and staircases (treads

and risers) with cement mortar 1:2 (1 cement: 2 coarse sand) including a floating coatof neat cement and protecting the surface with a layer of 7.5 cm of earth laid over 15mm of fine sand in case of suspended floor and bricks laid in mud mortar in case oflandings and steps including subsequent removal and cleaning of the same.

CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials:Cement mortar 1:2 (1 Cement: 2 cum .03 3 864.25 115.93(Rate as per item No. 3.2

###finishing (Floating coat) cement tonne .0213 4,500 95.85###Carriage of cement tonne .0213 47.29 1.01

Labour:###Mason I class Day .2 151.5 30.3###Mason II class Day .2 141.6 28.32###Beldar Day .25 135.25 33.81###Spreading earth on floor (7.5mmL.S. 35.49 1 35.49

Spreading sand 15mm thick on floor###Fine sand cum .15 320 48###Carriage of sand cum .15 53.21 7.98

Labour:###Disposal of earth spread over flo L.S. 5.33 1 5.33###Sundries L.S. 6.24 1 6.24

TOTAL 408.26Add 1 % for water charges 4.08TOTAL 412.34

Page 182: DAR_Vol_1

Add 15% for contractor’s profit and overheads 61.85Cost of 10 Sqm. 474.19Cost per sqm. 47.42Say 47.4

5.25 : Providing and fixing in position copper plate as per design for expansion joints.CodDescription Unit Quantity Rate Amount

Details of cost for 3.0 m lenght, width 250mmand 1.6 mm thick = 0.750 sqm

2###Weight of copper plate @ 14.08 kg 10.56 195 2,059.2

Labour###Blacksmith 2nd class Day .25 141.6 35.4###Sundries L.S 6.24 1 6.24

TOTAL 2,100.84Add 1 % for water charges 21.01TOTAL 2,121.85Add 15% for contractor’s profit and overheads 318.28Cost of 10.56 kg 2,440.13Cost per kg. 231.07Say 231.05

1905.26 : Providing and filling in position, blown bitumen in expansion joints.CodDescription Unit Quantity Rate Amount

Details of cost for a joint - 2.5cm wide 15cmdeep and 300m in length-Cubical content of joint-300x0.025x0.150=1.125cum. **Material :-

###Bitumen 85/25 @ 1050kg per cum.1.25x1050kg = 1181.25kgAdd wastage @ 5% = 59.06 kg.= 1240.31 kg = 1.2401 tonne 1.24 25 000.00 31 000.00

###Carriage of bitumen tonne 1.246 53.21 5.98###Steam coal for heating of bitumen @ 2.0 quintal 2.48 300 744

quintal per tonne of bitumen.1.240x2.0=2.48q=0.248t

###Carriage of steam coal tonne .248 60.81 15.08Labour for heating, mixing and filling-

###Mason 1 st class Day 2.52 151.5 381.78###Mason 2nd class Day 2.52 141.6 356.83###Beldar Day 8.06 135.25 1 090.12###Sundries L.S. 121.16 1 121.16

TOTAL 33 774.95Add 1% for water charges 337.75TOTAL 34 112.70Add 15% for contractor’s profit and overheads 5 116.90Cost of 300m length 2.5cm wide and 15cm 39 229.60depthCost per cm. depth, per cm width per 100m 348.71lengthSay 348.7

Page 183: DAR_Vol_1

5.27 : Providing and filling in position bitumen mix filler of Proportion 80 kg. of hot bitumen,1 kg. of cement and 0.25 cubic metre of coarse sand for expansion joints.

CodDescription Unit Quantity Rate AmountDetails of cost for a joint - 2.5cm wide 15cmdeep and 300m in length-Cubical content of joints-300x0.150x0.025= 1.125cum.MaterialsBitumen S-90 = 256.30 kg per cum.256.30xl.125 = 288.34 kg. —Add for wastage @ 5% = 14.42 kg. ‘

1= 302.76 kg. or = 0.303 tonne.

###Bitumen tonne .303 22,500 6 817.50###Carriage of bitumen tonne .303 53.21 16.12###Stem coal for heating of bitumen @ 2.0 quintal .606 300 181.8

quintal per tonne of bitumen, i.e.0.303x2.0=0.606q

###Carriage of steam coal tonne .061 60.81 3.71Cement:

###1/80x228.34=3.6 kg = 0.0036 Tonne tonne .0036 500 16.2###Carriage of cement tonne .0036 47.29 .17###Coarse sand l/4th of the quantity of cement cum .9 600 540

191CodDescription Unit Quantity Rate Amount

kg = 3.6/4 = 0.90 cum. -###Carriage of coarse sand cum .9 53.21 47.89

Labour for heating and filling :###Mason 1 st class Day 2.52 151.5 381.78###Mason 2nd class Day 2.52 141.6 356.83###Beldar Day 8.06 135.25 1,090.12###Sundries L.S 121.16 1 121.16

TOTAL 9,573.28Add 1% for water charges 95.73TOTAL, 9,669.01Add 15% for contractor’s profit and overheads 1,450.35Cost of 300m length 2.5cm wide and 15cm 11,119.36depthCost per cm. depth, per cm width per 100m 98.84lengthSay 98.85

5.28 : Providing and fixing in position 12mm thick bitumen impregnated fibre boardconforming to IS: 1838 including cost of primer, sealing compound in expansion joints.

CodDescription Unit Quantity Rate AmountDetails of cost for joint 100m long 10cm deepand 12mm thickMaterial:

###(i) Impregnated fibre board sqm 7.5 279 2,092.5lxl00x0.075=7.5sqm.

###(ii) Primere 80m/litter 100m=100Ltrs. 1.25 28 35###(iii) Sealing compound @ 3 per litrer for

Page 184: DAR_Vol_1

100m = 100/3x1 =33.3 litres+Wastage @ 5% =1.67 = 35.00 litre (1 litre = 0.9 Kg Kg 31.5 20 63035.00x0.9 = 31.5 Kg.

###Carriage L.S. 26.91 1 26.91Labour:

###Mason 1 st class Day .12 151.5 18.18###Mason 2nd class Day .12 141.6 16.99###Beldar Day .25 135.25 33.81###Sundries L.S. 26.91 1 26.91

TOTAL 2,880.3Add 1 % for water charges 28.8TOTAL 2,909.1Add 15% for contractor’s profit and overheads 436.36Cost of 100m long 10cm deep 3,345.46Cost per cm depth per 100m 334.55Say 334.55

5.2Providing and fixing sheet covering over expansion joints with iron screws asper design to match the colour /shade of wall treatment.

5.29.1 : Non-asbestos fibre cement board 6 mm thick as per IS: 14862.5.29.1.1 : 150mm wide.CodDescription Unit Quantity Rate Amount

Details of cost for 3 m lengthMaterials:

###Non - Asbestos multi purpose fib sqm .47 180 84.6board 6mm thick.

192CodDescription Unit Quantity Rate Amount###Carriage of sheets- 0.45sqm = 0. tonne .0049 47.29 .23###50mm iron screws with washer a L.S. 40.3 1 40.3

Labour:

###Carpenter 2nd class Day .2 141.6 28.32###Beldar Day .2 135.25 27.05

TOTAL 180.5Add 1 % for water charges 1.8TOTAL 182.3Add 15% for contractor’s profit and overheads 27.34Cost for 3 m 209.64Cost per meter 69.88Say 69.9

5.29 : Providing and fixing sheet covering over expansion joints with iron screws as perdesign to match the colour / shade of wall treatment.

5.29.1 : Non-asbestos fibre cement board 6 mm thick as per IS: 14862.5.29.1.2 :200mm wide.

CodDescription Unit Quantity Rate AmountDetails of cost for 3m lengthMaterials:

###Non - Asbestos multi purpose fib sqm .63 180 113.4board 6mm thick.

Page 185: DAR_Vol_1

###Carriage of sheet 0.60sqm. = 0.0 tonne .0065 47.29 .31

###50mm iron screws with washer a L.S. 53.82 1 53.82Labour:

###Carpenter 2nd class Day .27 141.6 38.23###Beldar Day .27 135.25 36.52

TOTAL 242.28Add 1 % for water charges 2.42TOTAL 244.7Add lfei for contractor’s profit and overheads 36.7Cost for 3m 281.4Cost per meter 93.8Say 93.8

5.2Providing and fixing sheet covering over expansion joints with iron screws as perdesign to match the colour / shade of wall treatment.

5.29.2 : Aluminium fluted strips 3.15mm thick.

5.29.2.1: 150 mm wide.CodDescription Unit Quantity Rate Amount

Details of cost for 1 meterMaterials:

###3.15mm thick aluminium fluted metre 1 216 216strips-1 m x 15cm wide

193CodDescription Unit Quantity Rate Amount###Iron screws 25mm 100Nos 6 15 .9###Carriage of materials L.S. 1.04 1 1.04

Labour:###Carpenter 2nd class Day .067 141.6 9.49###Beldar Day .067 135.25 9.06###Sundries L.S. 1.82 1 1.82

TOTAL 238.31Add 1% for water charges 2.38TOTAL 240.69

Add 10% for contractor’s profit and overheads 36.1Cost for 1 metre 276.79Say 276.8

5.2Providing and fixing sheet covering over expansion joints with iron screws as perdesign to match the colour / shade of wall treatment.

5.29.2 : Aluminium fluted strips 3.15mm thick.5.29.2.2: 200 mm wide.CodDescription Unit Quantity Rate Amount

Details of cost for 1 meterMaterials:

###Strips Aluminium fluted 3.15mmMetre 1 288 288200mm wide metre

###Iron serews 25mm 100Nos 6 Nos 15 .9

Page 186: DAR_Vol_1

###Carriage of materials L.S. 1.3 1 1.3Labour:

###Carpenter 2nd class Day .089 141.6 12.60 1 Beldar Day .089 135.25 12.04###Sundries L.S. 2.34 1 2.34

TOTAL 317.18Add 1% for water charges 3.17TOTAL 320.35Add 15% for contractor’s profit and overheads 48.05Cost for 1 metre 368.4Say 368.4

5.30 : Add or deduct for plaster drip course/ groove in plastered surface or moulding toR.C.C. projections.

CodDescription Unit Quantity Rate AmountDetails of cost for 30 metre long throating orplaster or moulding-Labour :

###Mason 1st class Day .5 151.5 75.75###Mason 2nd class Day .5 141.6 70.8###Coolie Day 1 135.25 135.25###Add for materials (cement mortarL.S. 26.91 1 26.91

TOTAL 308.71Add 1 % for water charges 3.09

194CodDescription Unit Quantity Rate Amount

TOTAL 311.8Add 15% for contractor’s profit and overheads 46.77Cost for 30 metre 358.57Cost per meter 11.95Say 11.95

5.31 : Extra for laying reinforced cement concrete in or under water and/ or liquid mudincluding cost of pumping or bailing out water and removing slush etc., complete.

CodDescription Unit Quantity Rate AmountAnalysis Same As As Per Item No 4.15Details of cost for depth of water 0.30m.Quantity of concrete = 14 cum.pumping hours = 3 hrs. or 0.375 day.

11 Cost of pumping water with Day .375 300 112.53636.7 litres per hour capacity pump

###Beldar for cleaning slush Day 4 135.25 541TOTAL 653.5Add 1 % for water charges 6.54TOTAL 660.04Add for contractor’s profit and overheads @ 99.011,500%Cost of 14cum. per 0.30m depth 759.05Cost of cum. per m depth 180.73Say 180.75

### Extra for laying reinforced cement concretein orunder foul positions.CodDescription Unit Quantity Rate Amount

Page 187: DAR_Vol_1

Analysis Same As Item No 4.16Details of cost for 1 cum.Extra labour due to slow progress-

###Mason 1 st class Day .02 151.5 3.03###Mason 2nd class Day .02 141.6 2.83###Beldar Day .25 135.25 33.81###Coolie Day .15 135.25 20.29

TOTAL 59.96Add 1% for water charges .6TOTAL 60.56Add for contractor’s profit and overheads @ 9.081,500%Cost for 1 cum. 69.64Say 69.65

5.33 : Providing and laying in position machine batched, machine mixed and machinevibrated design mix cement concrete of specified grade for reinforced cementconcrete work including pumping of concrete to site of laying but excluding thecost of centring, shuttering, finishing and reinforcement, including Admixtures inrecommended proportions as per IS 9103 to accelerate, retard setting of concrete,improve workability without impairing strength and durability as per direction ofEngineer-in-charge. M-25 grade reinforced cement concrete by using 410kg. of cementper cum of concrete.All work upto floor V level.

CodDescription Unit Quantity Rate AmountDetails of cost for 1.00 cumMaterials.

###Stone Aggregate 20 mm . cum .57 700 399

195CodDescription Unit Quantity Rate Amount###Stone aggregate 10mm cum .28 700 196###Carriage of aggregate . cum .85 53.21 45.23###Coarse sand cum .425 600 255###Carriage of Coarse sand cum .425 53.21 22.61###Cement tonne .41 4 500.00 1 845.00###Carriage of Cement tonne .41 47.29 19.39###Plasticizer 0.50% of cement kilogram 2.05 30 61.5

Production cost, pumping to respectivefloors and laying in position

4 Production cost of concrete by cum 1 200 200plant.

9 Pumping charges of concrete. cum 1 80 80Labour for pouring, consolidating & curing

###Mason Day .17 146.55 24.91###Beldar Day 2 135.25 270.5###Bhisti Day .9 138.45 124.612 Vibrator Day .07 200 14###Sundries L.S. 13 1 13

Total 3,570.74Add 1% for water charges. 35.71Total 3,606.45Add 15% for contractor’s profit and 540.97

Page 188: DAR_Vol_1

overheads.Cost per 1.00 cum 4,147.42Say 4,147.4

5.34 : Add or deduct for providing richer or leaner mixes respectively at all floor levels.5.34.1 : Providing M-30 grade concrete by using 420kg of Cement per cum of concrete

instead of M-25 grade B.M.C./Rmc.CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.Cement for M-30 mix = 0.420 tCement for M-25 mix = 0.410 t

###Difference 0.010t tonne .01 4,500 45###Carnage of Cement tonne .01 47.29 .47

Plasticizer for M-30 mix = 2.10 KgPlasticizer for M-25 mix = 2.05 KgDiffevence =0.05 kg.

###Plasticizer / super plasticizer kilogram .05 30 1.5TOTAL 46.97Add 1 % for water charges .47TOTAL 47.44Add for contractor’s profit and overheads 7.121,500%Cost per cum. 54.56Say 54.55

5.34 : Add or deduct for providing richer or leaner mixes respectively at all floor levels.5.34.2 : Providing M-35 grade concrete by using 428kg ofcement per cum of concrete

instead of M-25 grade B.M.C./R.M.C...CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.Cement for M-35 mix = 0.428 tCement for M-25 mix = 0.410 t

196CodDescription Unit Quantity Rate Amount

###Difference 0.01 t tonne .018 4,500 81###Carriage of cement tonne .018 27.29 .85

Plasticizer for M-35 mix = 2.140 KgPlasticizer for M-25mix = 2.05 KgDiffevence =0.09 kg.

###Plasticizer / super plasticizer kilogram .09 30 2.7TOTAL 84.55Add 1 % for water charges .85TOTAL 85.4Add for contractor’s profit and overheads @ 12.811,500%Cost per cum. 98.21Say 98.2

### Add or deduct for providing richer or leaner mixes respectively at all floor levels.5.34.3 Providing M-30 grade concrete by using 435kg of cement per cum of concrete instead

of M-25 grade B.M.C/R.M.C..CodDiscription Unit Quantity Rate Amount

Details of cost for 1 cum.

Page 189: DAR_Vol_1

Cement for M-40 mix = 0.435 tCement for M-25 mix = 0.410 t

###Difference = 0.025 t tonne .025 4,500 112.5###Carriage of cement tonne .025 47.29 1.18

Plasticizer for M-40 mix = 2.175 KgPlasticizer for M-25 mix = 0.125 KgDifference =0.125kg. kilogram .125 30 3.75

###Plasticizer / super plasticizer 117.43TOTAL 1.17Add 1 % for water charges 118.6TOTAL 17.79Add for contractor’s profit and overheads1,500% 136.39Cost per cum. 136.4Say

### Deduct for using less cement than the quantity as provided in the item of batch mixconcrete/RMC as arrived as per mix design.Details of cost for 1 quintal

CodDiscription Unit Quantity Rate Amount###Cement M.T .1 4,500 450###Carriage of cement M.T .1 47.29 4.73

454.73Add 1% for water charges 4.55

459.28Add for contrator profit & overheads @ 15% 68.89Cost for 1 Quintal 528.17

528.15

197### Providing and placing in position precast reinforced cement concrete waffle units square

or rectangular as per design and shape for floors and roofs in 1:1 1/2:3 (1 Cement: 1/2coarse sand : 3 graded stone aggregate 10mm nominal size) including flush or deepruled pointing at joints in Cement mortar 1:2 (1 Cement : 2 Fine sand), making neces-sary holes of required sizes for carrying through service lines etc., providing steel hooksfor lifting etc, form work in precasting, handling, hoisting, centering and erection com-plete for all floor levels but excluding the cost of reinforcement

Code Discription Unit Quantity Rate Amount

Details for wafle 09. x 0.9 x 0.3mTotal area covered 4.548 x 3.636 = 16.54 sqm.Cement concrete in 1unitTop 0.8 x 0.8 x 0.035 = 0.0224sides 2(0.8 x 0.265 x 0.0325) = 0.01382(0.735 x 0.265 x 0.0325) = 0.0127Total = 0.0489Flange 4 x 0.85 x 0.05 x 0.035 = 0.0060Total = 0.0549Add for Fillets 25% = 0.0137Total = 0.069 cum.Quantity for 20 such units = 1.38 cumRate as per item no. 5.2.2 of SH : RCC cum 1.38 4,092.35 5,647.44(i) Shuttering and centring

Page 190: DAR_Vol_1

Face in contact4 x 0.8 x 0.265 = 0.848Inner 4 x 0.735 x 0.265 = 0.779Top (inside) 1 x 0.735 x 0.735 = 0.540Flange 4 x 0.9 x 0.035 = 0.126Total = 2.293 sqm.Quantity 20 such units 45.86 sqm.Rate as per item no. 5.9.15 of sqm 45.86 119.25 5,468.8Hooks for lifting2 x 1.5 = 3.0 m4 x 0.01 = 0.04 m= 3.04 m@ 3 kg per m 9.12 kg or 0.009 tRates as per item no 10.2 of s kg 9 46.35 417.15

(ii) 10 mm dia. Bolts 60 mm long with nutsand washers 2 x 2 = 4Nos.

9999 (A) including carriage of bolts L.S 13 1 139999 (A) Sundries etc. L.S 79.95 1 79.95

(IV) Transportation and erection labour for 20units

0125 (A) Mason (for ornamental stone Day 1 151.5 151.50115 (A) Beldar Day 6 135.25 811.5

(V) Cost of pointing flush or deep ruled in cement mortar 1:2 (1 Cement : 2 fine sand)Rate as per item no. 13.35.1 sqm 16.54 36.45 602.88

(B) TOTAL 13,192.22Add for water charges @ 1% on ‘A’ 10.56TOTAL 13,202.78Add for contractor’s profit and overheads @ 159.9815% on A+BTotal for 20 unitsCost for 1.38 cum. 13,362.76Cost for 1 cum. 9,683.16Say 9,683.15

198### Providing and laying in position ready mixed concrete manufactured in fully

automatic batching plant and transported to site of work in transit mixer for a leadupto 10kms having continuous agitated mixer, manufactured as per mix design ofspecified grade for reinforced cement concrete work including pumping of R.M.C.from transit mixer to site of laying , excluding the cost of centering, shutteringfinishing and reinforcement including cost of admixtures in recommendedproportions as per IS : 9103 to accelerate/ retard setting of concrete, improveworkability without impairing strength and durability as per direction of the Engineer- in - charge. M-25 grade Reinforced cement concrete by using 410kg of cement percum of concrete. All works upto floor V level.

CodDescriptio Unit Quantity Rate AmountDetails of cost for 1.00 cumMaterials.

###Stone aggr cum .57 700 399###Stone aggr cum .28 700 196###Carriage of cum .85 53.21 45.23

Page 191: DAR_Vol_1

###Coarse san cum .425 600 225###Carriage of cum .425 53.21 22.61###Cement tonne .41 4,500 1,845###Carriage o tonne .41 47.29 19.39###Plasticizer kilogram 2.05 30 61.5

Production cost, carriage to site, pumping torespective floors and laying in position

4 Production cum km/ 10 200 20029 Carriage of cum 10 18 1809 Pumping chacum 80 80

charges of pump, pipig work & accessories etc.###Labour for pouring, consolidating & curing###Mason Day 1 146.55 24.91###Beldar Day .17 135.25 270.512 Bhisti Day 2 138.45 124.6###Vibrator Day .9 200 14

Sundries L.S .07 1 13Total 13 3,750.74Add 1% for water charges. 37.51Total 3,788.25Add 15% for contractor’s profit and 568.24overheads.Cost per 1.00 cum 4,356.49Say 4,356.5

### Extra for R.C.C./ B.M.C/ R.M.C. work above floor V level for each four floors or partthereof.

CodDescriptio Unit Quantity Rate AmountCost for 1 cumMaterials

9 Pumping chacum 1 80 80charges of pump, piping work & accessories etc.Total 80Add 1% for water charges. .8Total 80.8Add 15% for contractor’s profit and overheads. 12.12Cost for 1 cum 92.92Say 92.9

### Extra for carriage of R.M.C. beyond the initial lead of 10 km.CodDescriptio Unit Quantity Rate Amount

Details of cost for 1 cum per km.29 Carriage p cum/km 1 18 18

Total 18Add 1% water charges .18Total 18.18Add 15% for contractor profit and overheads. 2.73Cost for 1 cum per km. 20.91Say 20.9

199

Page 192: DAR_Vol_1

SUB HEAD : 6.0

BRICK WORK

201### Brick work with F.P.S. bricks of class designation 75 in foundation and plinth in:

6.1Cement mortar 1:4 (1 cement : 4 coarse sand)

CodDescription Unit Quantity Rate AmountDetails of cost for 1 cum.MATERIALS :

###Bricks of class designation 75 1000 Nos 494 1 900.00 938.6Cement mortar 1:4 (Rate as per i cum .25 2 578.45 644.61

###Carriage of bricks 1000 Nos 494 141.88 70.09###Sundries L.S. 2.73 1 2.73

LABOUR:###Mason 1st Class Day .36 151.5 54.54###Mason Ilnd Class Day .36 141.6 50.98###Coolie Day 1.37 135.25 185.29###Bhishti Day .2 138.45 27.69

TOTAL Day 1,974.53

Add 1% for water charges L.S. 1 19.75TOTAL 1,994.28Add for contractor’s profit and overheads @ 299.141,500%Cost of 1 Cum. 2,293.42Say 2,293.4

### Brick work with F.P.S. bricks of class designation 75 in foundation and plinth in:6.1Cement mortar 1:6 (1 cement : 6 coarse sand)CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.MATERIALS :

###Bricks of class designation 75 1000 Nos 4.94 1 900.00 938.6Cement mortar 1:6 (Rate as per i cum .25 1 987.30 496.82

Page 193: DAR_Vol_1

###Carriage of bricks 1000 Nos 4.94 141.88 70.09###Sundries L.S. 2.73 1 2.73

LABOUR:###Mason 1st Class Day .36 151.5 54.54###Mason Ilnd Class Day .36 141.6 50.98###Coolie Day 1.37 135.25 185.29###Bhishti Day .2 138.45 27.69

TOTAL 1,826.74

Add 1% for water charges 1 18.27TOTAL 1,845.01Add for contractor’s profit and overheads @ 276.751,500%Cost of 1 Cum. 2,121.76Say 2,121.75

### Brick work with modular bricks of class designation 75 in foundation and plinth in:6.2Cement mortar 1:4 (1 cement : 4 coarse sand)CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.MATERIALS :

###Modular bricks of class designa 1000 Nos 487 2 050.00 998.35###Carriage of bricks 1000 Nos 487 141.88 69.1

Cement mortar 1 :4 (1 cement : 4cum .22 2 578.45 567.26(Rates as per item no. 3.9)

202CodDescription Unit Quantity Rate Amount###Sundries L.S. 2.73 1 2.73

LABOUR:###Mason 1st Class Day .33 151.5 50###Mason Ilnd Class Day .33 141.6 46.73###Coolie Day 1 135.25 135.25###Bhishti Day .18 138.45 24.92

TOTAL 1,894.34Add 1% for water charges 18.94TOTAL 1,913.28Add for contractor’s profit and overheads @ 286.991,500% 2,200.27Cost of 1 Cum. 2,200.25Say

### Brick work with modular bricks of class designation 75 in foundation and plinth in:6.2Cement mortar 1:6 (1 cement : 6 coarse sand)CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.MATERIALS :

###Modular bricks of class designat1000 Nos 487 2 050.00 998.35###Carriage of Bricks 1000 Nos 487 141.88 69.1

Cement mortar 1 :6 (1 cement : 6cum .22 1,987.3 437.21(Rates as per item no. 3.11)

###Sundries L.S. 2.73 1 2.73LABOUR:

###Mason 1st Class Day .33 151.5 50###Mason Ilnd Class Day .33 141.6 46.73###Coolie Day 1 135.25 135.25

Page 194: DAR_Vol_1

###Bhishti Day .18 138.45 24.92

TOTAL 1 1,764.29Add 1% for water charges 17.64TOTAL 1,781.93Add for contractor’s profit and overheads @ 267.291,500%Cost of 1 Cum. 2,049.22Say 2,049.2

6.3 Brick work with machine moulded perforated bricks of class designation 125conforming to IS: 2222 -1991 in superstructure above plinth level upto floor fivelevel in cement mortar 1:6(1 cement : 6 coarse sand):

6.3.1 With F.P.S. bricks.CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.MATERIALS :

###Machine moulded perforated FPS1000 Nos 494 3 233.00 1 597.10class designation 125

###Carriage of Bricks 1000 Nos 494 141.88 70.09Cement mortar 1:6(1 cement: 6 cCum .25 1 987.30 496.82(Rates as per item no. 3.11)

###Sundries L.S 2.73 1 2.73LABOUR:

203CodDescription Unit Quantity Rate Amount

###Mason 1st Class Day .47 151.5 71.2###Mason Ilnd Class Day .47 141.6 66.55###Coolie Day 1.8 135.25 243.45###Bhishti Day .2 138.45 27.69###Scaffolding L.S 22.36 1 22.36

Extra labour element required for lifting ofmaterials (above floor two level upto floorfive level)

###Coolie Day 1.13 135.25 152.83TOTAL 2,750.82Add 1 % for water charges 27.51TOTAL 2,778.33

Add for contractor’s profit and overheads @ 1 416.7515Cost of 1 Cum. Say 3,195.08Say 3,195.1

6.3 Brick work with machine moulded perforated bricks of class designation 125 con-forming to IS: 2222 -1991 in superstructure above plinth level upto floor five level incement mortar 1:6(1 cement : 6 coarse sand):

6.3.2 With Modular bricks.CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.MATERIALS :

###Machine moulded perforated FPS 1000 Nos 487 3 200.00 1 558.40class designation 125

###Carriage of Bricks 1000 Nos 487 141.88 69.1

Page 195: DAR_Vol_1

Cement mortar 1:6(1 cement: 6 cCum .22 1 987.30 437.21(Rates as per item no. 3.11)

###Sundries L.S 2.73 1 2.73LABOUR:

###Mason 1st Class Day .44 151.5 66.66###Mason Ilnd Class Day .44 141.6 62.3###Coolie Day 1.43 135.25 193.41

###Bhishti Day .18 1 138.45 24.92###Scaffolding L.S 16.38 1 16.38

Extra labour element required for lifting ofmaterials (above floor two level upto floorfive level)

###Coolie Day 1.13 135.25 152.83TOTAL 2,583.94Add 1 % for water charges 25.84TOTAL 2,609.78Add for contractor’s profit and overheads @ 391.471,500%Cost of 1 Cum. Say 3,001.25Say 3,001.25

204### Brick work with F.P.S. bricks of class designation 75 in superstructure above plinth

level upto floor V level in all shapes and sizes in :6.4Cement mortar 1:4 (1 cement: 4 coarse sand)CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.MATERIALS :

###Bricks of class designation 75 1000 494 1,900 938.6Nos

Cement mortar 1:4 (Rate as per i Cum .25 2,578.45 644.61###Carriage of bricks 1000 494 141.88 70.09

NosSundries L.S 2.73 1 2.73LABOUR:

###Mason 1 st Class Day .47 151.5 71.21###Mason Ilnd Class Day .47 141.6 66.55###Coolie Day 1.8 135.25 243.45### Bhishti Day .2 138.45 27.69###Scaffolding L.S 22.36 1 22.36

Extra labour element required for lifting ofmaterials (above floor two level upto floorfive level)

###Coolie Day 1.13 135.25 152.83TOTAL 2,240.12Add for water charges @ 1% 22.4TOTAL 2,262.52Add for contractor’s profit and over-heads 339.83

2,601.9Say 2,601.9

### Brick work with F.P.S. bricks of class designation 75 in superstructure above plinth

@15%Cost of 1 cum.

Page 196: DAR_Vol_1

level upto floor V level in all shapes and sizes in :6.4Cement mortar 1:4 (1 cement: 4 coarse sand)CodDiscription Unit Quantity Rate Amount

Details of cost for 1 cum.MATERIALS :

###Bricks of class designation 75 Nos 494 1,900 938.6Cement mortar 1:6 (Rate as per i Cum .25 1,987.3 496.02

###Carriage of bricks 1000 Nos 494 141.88 70.09Sundries L.S 2.73 1 2.73LABOUR:

###Mason 1 st Class Day .47 151.5 71.21###Mason Ilnd Class Day .47 141.6 66.55###Coolie Day 1.8 135.25 243.45###Bhishti Day .2 138.45 27.69###Scaffolding L.S 22.36 1 22.36

Extra labour element required for lifting ofmaterials (above floor two level upto floorfive level)

###Coolie Day 1.13 135.25 152.83TOTAL 2,092.63Add for water charges @ 1% 20.93TOTAL 2,113.56Add for contractor’s profit and over-heads 317.03

2,463.59Say 2,463.6

205### Extra for brick work in superstructure above floor V level for each four floors or part

thereof by mechanical means by lifting material using mobile crane.CodDescription Unit Quantity Rate Amount

Details of cost for 5.3 cum per four floors .37 Mobile crane. per day .125 5,000 625

Fuel consumption per hour = 8 litre.###Diesel oil litre 8 30.25 242

TOTAL 867Add 1 % for water charges 8.67TOTAL 875.67Add for contractor’s profit and overheads @ 131.351,500%Cost of 5.3 Cum. 1 007.02Cost for 1 cum 190Say 190

### Extra for forming cavity 5cm to 7.5cm wide in cavity walls with necessary weep andvent holes including use of cores and cost of providing and fixing bitumastic coatedM .S. ties 300mm long of 25x3mm section at not less than 3 ties per sqm as perapproved design.

CodDescription Unit Quantity Rate Amount

Details of cost for 10sqm.Materials :

@15%Cost of 1 cum.

Page 197: DAR_Vol_1

###Mild steel 25mmx3mm section quintal .054 2 900.00 156.6No. = 9 metres @ 0.6kg/m = 5.40 kg.

###Painting the steel Bitumen L.S 13.52 1 13.52###Carriage of mild steel tonne .005 47.29 .24

Extra labour for keeping cavity clear andfixing wall ties and delay caused:

###Mason 1st class Day .37 151.5 56.06###Mason 2nd Class Day .37 141.6 52.39###Beldar Day .92 135.25 124.43###Add for use of Core L.S 4.55 1 4.55

TOTAL 407.79

Add 1 % for water charges 1 4.08TOTAL 411.87Add for contractor’s profit and overheads @ 61.781,500%Cost for 10 sqm. 473.65Cost for 1 sqm. 47.37Say 47.35

### Providing half brick masonry with F.P.S. bricks of class designation 75 in cementmortar 1:3 (1 Cement : 3coarse sand) in superstructure for closing cavity 5 to 7.5 cmwide in cavity wall complete with 10 cm / 11.4 cm wide bitumen felt type 3 grade 1.

CodDescription Unit Quantity Rate AmountDetails of cost for 10m lengthMaterials :Half brick masonry 1:3 (Average)1x10x0.27 = 2.7

206Code Description Unit Quantity Rate Amount

Rate as per item No.6.12.1 sqm 2.7 289.6 781.92Bitumen felt type- 3 grade 1lxl0mx11.4m =1.14 sqm.Add for wastage and overlapping @ 5% =0.06 sqm.

0322 (B) Total = 1.20 sqm. sqm 1.2 45 54Labour:

0123 (B) Mason 1st class Day .12 151.5 18.180124 (B) Mason 2nd class Day .12 141.6 16.990114 (B) Beldar Day .06 135.25 8.12

TOTAL 879.21(C) Add for water charges @ 1 % on B .97

TOTAL 880.18Add for contractor’s profit and overheads at 14.7415% on (B+C)Cost of 10 metre 894.92Cost for 1 metre 89.49Say 89.5

### Brick work 7 cm thick with F.P.S. brick of class designation 75 in cement mortar 1:3(1 cement: 3 coarse sand) in superstructure.

Code Description Unit Quantity Rate AmountDetails of cost for 10sqm.Materials:

Page 198: DAR_Vol_1

### Bricks of class designation 75 1 000 Nos 377 1 900.00 716.3Cement mortar 1:3 (Rate as per i cum .181 3 169.60 573.7

### Carriage of bricks 1 000 Nos 377 141.88 53.49LABOUR:

### Mason 1st class Day .72 151.5 109.08### Mason 2nd class Day .72 141.6 101.95###Coolie Day 1.76 135.25 238.04### Bhishti Day .36 138.45 49.84### Sundries and scaffolding L.S. 7.15 1 7.15

TOTAL 1 849.55Add 1 % for water charges 18.5TOTAL 1 868.05Add for contractor’s profit and overheads @ 280.211,500% 2 148.26Cost for 10 sqm. 214.83Cost for 1 sqm. 214.85Say

### Brick work in plain arches in superstructure including centring and shuttering com-plete for span upto 6 metres with F.P.S. bricks of class designation 75 in cementmortar 1:3 (1 cement: 3 coarse sand).

Code Description Unit Quantity Rate AmountDetails of cost for 1 cum.Materials :

### Bricks of class designation 75 1 000 Nos 494 1 900.00 938.6Cement mortar 1:3 (Rate as pecum .25 3 169.60 792.4

### Carriage of bricks 1 000 Nos 494 141.88 70.09

207Code Description Unit Quantity Rate Amount

### Sundries L.S 2.73 1 2.73Centering and Shuttering:Taking a semi circular arch 3.6m span,3.6m long and 0.40m thick Area of centering =3.142 x 1.8 x 3.6 = 20.37 sqm.Brick work in Arch.3.142x2.00x0.4x3.6 = 9.05cum.Area per cum.(B) 20.37/9.05 = 2.25 sqm. sqm 2.25 514.7 1,158.08(Rate same as in item 5.9.9

### Scaffolding L.S 18.85 1 18.85Labour:

### Mason 1st class Day .53 151.5 80.3### Mason 2nd class Day .53 141.6 75.05### Coolie Day 2.29 135.25 309.72### Bhishti Day .2 138.45 27.69

TOTAL 3,473.51Add for water charges @ 1% on all except B 23.15TOTAL 3,496.66Add for contractor’s profit and overheads at 350.7915% on all except BCost for 1 cum. 3,847.45

Page 199: DAR_Vol_1

Say 3,847.45

6.10 Brick work in gauged arches in superstructure in cement mortar 1:3 (1 cement : 3coarse sand) including centring and shuttering complete, for span upto 6 meterswith F.P.S. bricks of class designation 75

Code Description Unit Quantity Rate AmountDetails of cost for 1 cum.Materials :

### Bricks of class designation 75 1 000 Nos 538 1 900.00 1 022.20Cement mortar 1:3 (Rate as per i cum .25 3 169.60 792.4

### Carriage of bricks 1 000 Nos 538 141.88 76.33### Sundries L.S 2.73 1 2.73

Centring and shuttering (Area same as in itemNo. 6.9

### (B) (Rate same as per item No. 5.sqm 2.25 514.7 1 158.08Scaffolding L.S. 18.85 1 18.85LABOUR:

### Mason 1 st class Day 1.13 151.5 171.2### Mason 2nd class Day 1.13 141.6 160.01### Coolie Day 4.42 135.25 597.8### Bhishti Day .2 138.45 27.69

TOTAL 4,027.29Add for water charges @ 1% on all except B 28.69TOTAL 4,055.98Add for contractor’s profit and overheads at 434.6815%on all except BCost for 1 cum. 4,490.66Say 4,490.65

208### Extra for additional cost of centring for arches exceeding 6m span including all

shuttering, bolting, wedging and removal (Area of the soffit to be measured).CodDescription Unit Quantity Rate Amount

Details of cost per sqm.Centering and shuttering for arches and carvedsurface exceeding 6m in span (an average of8m)Radius R = 5m 2R-2=4+4-1tan (4/3)=53.28°2x53.28°=106°Surface area=2x22/7x5x3.6x106/360=33.3 sqm.Arc=9.25mMaterial:Tie-2x8x0.18x0.05 =0.144cumStruts-2x2.5x0.1x0.1 =0.050cum.Struts-2x1.77x0.1x0.1 =0.035cum.Ribs-6x1.54x0.23x0.1 =0.213cum.Struts-2x1.72x0.1x0.1 =0.034cum.Total=0.476cum.For four such frames =0.476x4= 1.904 cum.laggings-75x3.6x0.125x0.075=2.531 cum.Tie-2x3.6x0.225x0.038=0.062cum.

Page 200: DAR_Vol_1

Brace-3x2x2.14x0.225x0.038=0.110Brace-3x4x3.8x0.225x0.038=0.390Sleepers-4x3.6x0.20x0.15=0.432Sleepers-2x4x3.6x0.175x0.075=0.378Vertical post-4x4x3.6x0.15x0.15=1.296

###Total =7.103cum.Qty taken l/8th of qty for cost us 10 cum 887.9 160 14,206.47.103/8 = 0.8885 cum (887.90 cudm)

###Carriage of wood cum .8879 60.81 53.99Fittings:3 way straps 50mmxl0mm = 32 Nos.32 no. @0.50cm each = 16mStraps-50mmx 10mm = 8 Nos. @0.25cm each = 2mTotal = 18m18m @ 3.9kg/m = 70.2 kg. = 0.702qtl.Qty taken l/8th of qty for cost using once =

###0.702/8 = 0.0878 qtl. quintal .0878 2,900 254.62Bolts 160 Nos. 254 mm long 16mm dia.-160x 0.254x 1.58=64.21 kg=0.64qtl.Qty taken 1/8th of qty for cost using once =

###0.64/8 = 0.08 qtl. quintal .08 4,300 344Carriage of steel = 0.1342 tQty taken 1/8th of qty for cost using once =

###0.1342/8 = 0.0168 tonne tonne .0168 47.29 .79Labour:

###Carpenter 2nd class Day 28 141.6 3,964.8###Beldar Day 24 135.25 3,246###Sundries L.S 134.55 1 134.55

Less Cost of shuttering etc. for an archexceeding 6 m span i.e. for an average of 8 mspan(A) Rate as per item no- 5.9.9 sqm 33.31 514.7 ###TOTAL 5,060.49Add 1% for water charges on all exept ‘A’ 222.05TOTAL 5,282.54

209CodDescription Unit Quantity Rate Amount

Add for contractor’s profit and overheads @15% on all except ‘A’ 3,364.08Cost of 33.31 sqm. 8,646.62Cost per sqm. 259.58Say 259.6

6.12 Half brick masonry with F.P.S. bricks of class designation 75 in foundation and plinthin:

6.12.1 Cement mortar 1 : 3 (1 cement : 3 coarse sand)CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials :

###Brick of class designation 75 1 000 Nos 565 1 900.00 1 073.50

Page 201: DAR_Vol_1

Cement mortar 1:3 (Rate as per i cum .28 3 169.60 887.49###Carriage of bricks 1 000 Nos 565 141.88 80.16###Sundries & Scaffolding L.S 13.52 1 13.52

LABOUR:###Mason 1 st class Day .45 151.5 68.18###Mason 2nd class Day .45 141.6 63.72###Coolie Day 1.55 135.25 209.64###Bhishti Day .7 138.45 96.92

TOTAL 2 493.13Add 1% for water charges 24.93TOTAL 2 518.06Add for contractor’s profit and overheads @ 377.711,500%Cost for 10 sqm. 2 895.77Cost for 1 sqm. 289.58Say 289.6

6.12 Half brick masonry with F.P.S. bricks of class designation 75 in foundation and plinthin:

6.12.2 Cement mortar 1 : 4 (1 cement : 4coarse sand)CodDiscription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials :

###Brick of class designation 75 1 000 Nos 565 1 900.00 1 073.50Cement mortar 1:3 (Rate as per i cum .28 2,578.45 721.97

###Carriage of bricks 1 000 Nos 565 141.88 80.16###Sundries & Scaffolding L.S 13.52 1 13.52

LABOUR:###Mason 1 st class Day .45 151.5 68.18###Mason 2nd class Day .45 141.6 63.72###Coolie Day 1.55 135.25 209.64###Bhishti Day .7 138.45 96.92

TOTAL 2 327.61Add 1% for water charges 23.28TOTAL 2 350.89Add for contractor’s profit and overheads @ 352.631,500%Cost for 10 sqm. 2 703.52Cost for 1 sqm. 270.35Say 270.35

210### Half brick masonry with F.P.S. bricks of class designation 75 in superstructure above

plinth level upto floor V level in6.13.1 Cement mortar 1 : 3 (1 cement : 3 coarse sand)

CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials :

###Brick of class designation 75 1 000 Nos 565 1 900.00 1 073.50Cement mortar 1:3 (Rate as per i cum .28 3,169.6 887.49

###Carriage of bricks 1 000 Nos 565 141.88 80.16###Sundries & Scaffolding Day 13.52 1 13.52

Page 202: DAR_Vol_1

LABOUR:###Mason 1st class Day .6 151.5 90.9###Mason 2nd class Day .6 141.6 84.96###Coolie Day 2 135.25 270.5###Bhishti Day .7 138.45 96.92

Extra labour for lifting materials:###Coolie Day 1.29 135.25 174.47

10 x 0.115 x 0.75 x1.5TOTAL 2 772.42Add 1% for water charges 27.72TOTAL 2 800.14Add for contractor’s profit and overheads @ 420.021,500%Cost for 10 sqm. 3 220.16Cost for 1 sqm. 322.02Say 322

### Half brick masonry with F.P.S. bricks of class designation 75 in superstructure aboveplinth level upto floor V level in

6.13.2 Cement mortar 1 : 4 (1 cement : 4 coarse sand)CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials :

###Brick of class designation 75 1 000 Nos 565 1,900 1,073.5Cement mortar 1:4 (Rate as per i cum .28 2,578.45 721.97

###Carriage of bricks 1 000 Nos 565 141.88 80.16###Sundries & Scaffolding Day 13.52 1 13.52

LABOUR:###Mason 1st class Day .6 151.5 90.9###Mason 2nd class Day .6 141.6 84.96###Coolie Day 2 135.25 270.5###Bhishti Day .7 138.45 96.92

Extra labour for lifting materials:###Coolie Day 1.29 135.25 174.47

10 x 0.115 x 0.75 x1.5TOTAL 2,606.9Add 1% for water charges 26.07TOTAL 2,632.97Add for contractor’s profit and overheads @1,500% 394.95Cost for 10 sqm. 3,027.92Cost for 1 sqm. 302.79Say 302.8

211### Extra for half brick masonry in superstructure, above floor V level for every four

floors or part thereof by mechanical means by lifting material using mobile crane.CodDescription Unit Quantity Rate Amount

Details of cost for 59.83 sqm per four floors37 Mobile crane. per day .125 5,000 625

Fuel consumption per hour = 8 litre.###Diesel oil litre 8 30.25 242

TOTAL 867Add 1% for water charges 8.67

Page 203: DAR_Vol_1

TOTAL 875.67Add for contractor’s profit and overheads @15% 131.35Cost of 59.83 sqm. 1 007.02Cost for 1 sqm 16.83Say 16.85

### Extra for providing and placing in position 2 Nos. 6mm dia. M.S. bars at every thirdcourse of half brick masonry (with F.P.S. bricks)

CodDescription Unit Quantity Rate Amount

Details of cost for 10sqm.###(a) 6mm dia. M.S. bars (round) 2 quintal .132 3,100 409.2

meter/10sqm. = 60 metre @ 0.22kg/m =13.2kg-

###(B) Carriage of M.S. Bars tonne .0132 47.29 .62###Sundries L.S. 1.82 1 1.82

TOTAL 411.64Add 1% for water charges 4.12TOTAL 415.76Add for contractor’s profit and overheads @ 62.361,500%Cost for 10 sqm. 478.12Cost for 1 sqm. 47.81Say 47.8

### Tile brick masonry with tite bricks of class designation 100 in foundation and plinth in:6.16.1 Cement mortar 1 : 4 (1 cement : 4 coarse sand)CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.Materials :

###Brick tiles of class designation 1 1000 Nos 777 1,950 1 515.15Cement mortar 1:4(1 Cement: 4 ccum .4 2,578.45 1 031.38(Rate as per item no. 3.9)

###Carriage or brick tiles 1000 Nos 777 85.13 66.15###Sundries L.S. 4.55 1 4.55

Labour:###Mason 1st class Day .7 151.5 106.05###Mason 2nd class Day .7 141.6 99.12###Coolie Day 1.54 135.25 208.28###Bhishti Day .2 138.45 27.69

TOTAL 3 058.37Add 1 % for water charges 30.58TOTAL 3 088.95Add for contractor’s profit and overheads @ 463.341,500%Cost for 1 cum. 3 552.29Say 3,552.3

212### Tile brick masonry with tite bricks of class designation 100 in foundation and plinth in:

6.16.2 Cement mortar 1 : 6 (1 cement : 6 coarse sand)

CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.

Page 204: DAR_Vol_1

Materials :###Brick tiles of class designation 1000 Nos 777 1,950 1 515.15

Cement mortar 1:6(Rate as per itcum .4 2,578.45 794.92###Carriage or brick tiles 1000 Nos 777 85.13 66.15###Sundries L.S. 4.55 1 4.55

Labour:###Mason 1st class Day .7 151.5 106.05###Mason 2nd class Day .7 141.6 99.12###Coolie Day 1.54 135.25 208.28###Bhishti Day .2 138.45 27.69

TOTAL 2 821.91Add 1 % for water charges 28.22TOTAL 2 850.13Add for contractor’s profit and overheads @ 427.521,500%Cost for 1 cum. 3 277.65Say 3 277.65

### Tile brick masonry with machine moulded tile bricks of class designation 125conforming to IS : 2690 (Part I) -1993 in foundation and plinth in cement mortar1:6 (1 cement: 6 coarse sand)

CodDescription Unit Quantity Rate AmountDetails of cost for 1 cum.MATERIALS

###Machine moulded tile bricks of 1000 Nos 777 2 717.00 2,111.11designation 125

###Carriage of Brick tiles 1000 Nos 777 85.13 66.15Cement mortar 1:6 (1 cement: 6 cum .4 1 987.30 794.92(Rates as per item no. 3.11)

###Sundries L.S. 4.55 1 4.55LABOUR:

###Mason 1st Class Day .7 151.5 106.05###Mason Ilnd Class Day .7 141.6 99.12###Coolie Day 1.54 135.25 208.28###Bhishti Day .2 138.45 27.69

TOTAL 3,417.87Add 1% for water charges 34.18TOTAL 3,452.05Add for contractor’s profit and overheads @ 517.811,500%Cost of 1 Cum. 3,969.86Say 3,969.85

213### Tile brick masonry with tile brick of class designation 100 in superstructure above

Plinth level upto floor V level in cement mortar 1:6 (1 cement :6coarse sand).

CodDiscription Unit Quantity Rate Amount

Details of cost for 1 cum.MATERIALS :

###Tile bricks of class designation 1 1000 777 1,950 1,515.15Nos

Page 205: DAR_Vol_1

###Carriage of Brick tiles 1000 777 85.13 66.15Nos

Cement mortar 1:6 (1 cement: 6 cum .4 1,987.3 794.92sand).(Rate as item no. 3.11)

###Sundries L.S. 4.55 1 4.55LABOUR:

###Mason 1st Class Day .9 151.5 136.35###Mason Ilnd Class Day .9 141.6 127.44###Coolie Day 1.8 135.25 243.45###Bhishti Day .2 138.45 27.69

Extra labour for lifting of materials###Coolie Day 1.13 135.25 152.83###Cost of scaffolding L.S. 33.8 1 33.8

TOTAL 3,074.65Add for water charges @ 1 % 30.75TOTAL 3,105.39Add for contractor’s profit and over-heads 465.81

3,571.2Say 3,571.2

### Extra for tile brick masonry with tile bricks of class designation 100 in superstruc-ture above floor five level for every four floors or part thereof.

CodDiscription Unit Quantity Rate AmountDetails of cost for 1 cum.Extra labour element for lifting of materials(upto floor V level)0.75x2.00= 1.50

### Coolie Day 1.5 135.25 202.88TOTAL 202.88Add 1% for water charges 2.03TOTAL 204.91Add for contractor’s profit and overheads @ 30.741,500%Cost for 1 cum. 235.65Say 235.65

214### Tile brick masonry with tite bricks of class designation 100 in plain arch work in

superstructure in cement mortar 1 : 4 ( 1 cement : 4 coarse sand) including centeringand shuttering complete.

CodDescription Unit Quantity Rate AmountDetails of cost for 1 cum.MATERIALS

###Tile bricks 1000 Nos 777 1,950 1,515.15###Carriage of Brick tiles 1000 Nos 777 85.13 66.15

Cement mortar 1:4 (Rate as per i cum .35 2,578.45 902.46###Sundries L.S. 5.46 1 5.46

Centering and shutteringArea same as in item no 6.9 sqm 2.25 514.7 1,158.08

Rate as per item no. 5.9.9###Scaffolding L.S. 18.85 1 18.85

Labour:

@15%Cost of 1 cum.

Page 206: DAR_Vol_1

###Mason 1st Class Day .79 151.5 119.68###Mason Ilnd Class Day .79 141.6 111.86###Coolie Day 3.21 135.25 434.15###Bhishti Day .2 138.45 27.69

TOTAL 4,359.53Add 1% for water charges on all except A 32.01TOTAL 4,391.54Add for contractor’s profit and overheads @15% on all except A 485.02Cost of 1 Cum. 4,876.56Say 4,876.55

### Tile brick masonry with tile bricks of class designation 100 in gauged arch work insuperstructure in cement mortar 1:4 (1 cement: 4 coarse sand) including centringand shuttering complete.

CodDescription Unit Quantity Rate AmountDetails of cost for 1 cum.MATERIALS

###Tile bricks 1000 Nos 791 1,950 1,542.45###Carriage of tiles Brick 1000 Nos 791 85.13 67.34

Cement mortar 1:4 (Rate as per i cum .35 2,578.45 902.46###Sundries and shuttering L.S. 5.46 1 5.46

Centering and shutteringArea same as in item no 6.9

Rate as per item no. 5.9.9 sqm 2.25 514.7 1,158.08###Scaffolding L.S. 18.85 1 18.85

Labour:###Mason 1st Class Day 1.5 151.5 227.25###Mason Ilnd Class Day 1.5 141.6 212.4###Coolie Day 5.33 135.25 720.88###Bhishti Day .2 138.45 27.69

TOTAL 4,882.86Add for water charges @1% on all except ‘A’ 37.25TOTAL 4,920.11Add for contractor’s profit and overheads @ 564.315% on all except ‘A’Cost of 1 Cum. 5,484.41Say 5,484.4

215### Tile brick masonry work 5 cm thick with tile bricks of class designation 100 in

cement mortar in 1:3 (1 cement: 3 coarse sand) in superstructure.

Code Description Unit Quantity Rate AmountDetails of cost for 10 sqm.

###Tile bricks (22.9cmx 11.2cmx5cm1000 Nos 377 1,950 735.15###Carriage of tile bricks 1000 Nos 377 85.13 32.09

Cement mortar 1:3 (Rate as per i cum .15 3,169.6 475.44###Sundries and scaffolding L.S. 8.06 1 8.06

LABOUR:###Mason 1st class Day .94 151.5 142.41###Mason 2nd class Day .94 141.6 133.1###Coolie Day 1.88 135.25 254.27###Bhishti Day .33 138.45 45.69

Page 207: DAR_Vol_1

TOTAL 1,826.21Add 1% for water charges 18.26TOTAL 1,844.47Add 15% for contractor’s profit and overheads 276.67Cost of 10 Sqm. 2,121.14Cost per sqm. 212.11Say 212.1

### Honey-comb brick work 10/11.4 cm thick with bricks of class designation 75 in ce-ment mortar in 1:4 (1 cement : 4 coarse sand)

Code Description Unit Quantity Rate AmountDetails of cost for 1sqm. of Honey combbrick works-Materials :(1) Brick work, with bricks of classdesignation 75, in cement mortar 1:4 (1Cement: 4 Coarse sand) in superstructure1 m x 1 x 0.143 m x 4 cum .069 2,601.9 179.53Rate as per item no 6.4.1

###(A) (2) Extra for delay due to fine work L.S 20.67 1 20.67TOTAL 200.2

(B) Add for water charges @ 1 % on ‘A’ .21TOTAL 200.41Add for contractor’s profit and overheads @ 3.1315% on A+BCost for 1 sqm. 203.54Say 203.55

6.24 Extra for laying brick work in or under water and/or liquid mud including cost ofpumping or bailing out water and removing slush etc. complete.

Code Description Unit Quantity Rate AmountDetails of cost for depth of water 0.30m.Quantity of concrete = 14 cum.Pumping hours = 3 hrs. or 0.375 days.

11 Hire charge of pump set of capacDay .375 300 112.5###Beldar for cleaning slush Day 4 135.25 541

TOTAL 653.5Add 1% for water charges 6.54TOTAL 660.04

216CodDescription Unit Quantity Rate Amount

Add for contractor’s profit and overheads @ 15% 99.01Cost of 14 cum. per 0.30m depth 759.05Cost of 1 cum. per m depth 180.73Say 180.75

NOTE :- The quantity will be calculated by multiplying the depth measured from sub - soilwater level upto the centre of gravity of brick work under sub - water with the quantityof brick work in cum executed under the sub - soil water. The depth of cento ofgravity shall be reckoned correct to 0.1m, 0.05m or more shall be taken as 0.1 m andless than 0.05m ignored.

6.25 Extra for laying brick work in or under foul position.CodDescription Unit Quantity Rate Amount

Page 208: DAR_Vol_1

Details of cost for 1 cum.Extra labour due to slow progress-Mason 1st class Day .02 151.5 3.03

###Mason 2nd class Day .02 141.6 2.83###Beldar Day .25 135.25 33.81###Coolie Day .15 135.25 20.29###TOTAL 59.96

Add 1% for water charges .6TOTAL 60.56Add for contractor’s profit and overheads @ 9.081,500%Cost for 1 cum. 69.64Say 69.65

### Brick work with selected F.P.S. bricks of class designation 75 in exposed brick workincluding making horizontal and vertical grooves 10mm wide 12mm deep completefrom ground level upto plinth level in cement mortar 1:6 (1 cement: 6 coarse sand)

CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.###Bricks of class designation 75 1000 Nos 494 1,900 938.6###Carriage of bricks 1000 Nos 494 141.88 70.09

Cement mortar 1:6(1 cement: 6 cum .25 1,987.3 496.82sand) (Rate as per item no. 3.11)

###Sundries including steel/wooden L.S. 16.38 1 16.38making grooves.Labour:For selection of bricks

###Beldar Day .5 135.25 67.62###Mason 1 st class Day .35 151.5 53.02###Mason 2nd class Day .35 141.6 49.56###Coolie Day 1.07 135.25 144.72###Bhishti Day .2 138.45 27.69

TOTAL 1,864.5Add 1 % for water charges 18.64TOTAL 1,883.14Add for contractor’s profit and overheads @ 282.471,500%Cost per cum. 2,165.61Say 2,165.6

217### Brick work with modular bricks of class designation 75 in exposed brick work in-

cluding making horizontal and vertical grooves 10mm wide 12mm deep completefrom ground level upto plinth level in cement mortar 1:6 (1 cement: 6 coarse sand).

CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.MATERIALS :

###Modular bricks of class designati 1000 Nos 487 2,050 998.35###Carriage of Bricks 1000 Nos 487 141.88 69.1

Cement mortar 1:6 (1 cement: 6 cum .22 1,987.3 437.21sand (Rate as per item no. 3.11)

Page 209: DAR_Vol_1

###Sundries l/c steel/ wooden strip L.S. 16.38 1 16.38groovesLABOUR:

###Mason 1st Class Day .33 151.5 50###Mason Ilnd Class Day .33 141.6 46.73###Coolie Day 1 135.25 135.25###Bhishti Day .18 138.45 24.92

TOTAL 1,777.94Add 1% for water charges 17.78TOTAL 1,795.72Add for contractor’s profit and overheads @ 269.361,500%Cost of 1 Cum. 2,065.08Say 2,065.1

### Brick work with machine moulded modular bricks of class designation 125 in ex-posed brick work including making horizontal and vertical grooves 10mm wide 12mmdeep complete from ground level upto plinth level in cement mortar 1:6 (1 cement: 6coarse sand).

CodDescription Unit Quantity Rate AmountDetails of cost for 1 cum.

###Modular Bricks of class designat 1000 Nos 487 2,700 1,314.9###Carriage of bricks 1000 Nos 487 141.88 69.1

Cement mortar 1:6(1 cement: 6 cum .22 1,987.3 437.21sand (Rate as per item no 3.11)

###Sundries including steel/wooden s L.S. 16.38 1 16.38making grooves.Labour:

###Mason 1 st class Day .33 151 50###Mason 2nd class Day .33 141.6 46.73###Coolie Day 1 135.25 135.25###Bhishti Day .18 138.45 24.92

TOTAL 2,094.49Add 1 % for water charges 20.94TOTAL 2,115.43Add for contractor’s profit and overheads @ 317.311,500%Cost per cum. 2,432.74Say 2,432.75

218### Brick work with machine moulded F.P.S. bricks of class designation 125 in ex-

posed brick work including making horizontal and vertical grooves 10mm wide 12mm deep complete from ground level upto plinth level in cement mortar 1:6(1 ce-ment: 6 coarse sand).

CodDiscription Unit Quantity Rate AmountDetails of cost for 1 cum.MATERIALS :

###Machine moulded modular perfor1000 Nos 494 2,767 1,366.9of class designation 125

###Carriage of Bricks 1000 Nos 494 14.88 70.09Cement mortar 1:6,(1 cement: 6 cum .25 1,987.3 496.82

Page 210: DAR_Vol_1

(Rate as per item no 3.11)###Sundries i/c steel /wooden strip L.S. 16.38 1 16.38

groovesLABOUR:

###Mason 1st Class Day .36 151.5 54.54###Mason Ilnd Class Day .36 141.6 .98###Coolie Day 1.37 135.25 185.29###Bhishti Day .2 138.25 27.69

TOTAL 2,268.69Add 1 % for water charges 22.69TOTAL 2,291.38Add for contractor’s profit and overheads @ 343.711,500%Cost of 1 Cum. 2,635.09Say 2,635.1

### Brick work with machine moulded perforated F.P.S. bricks of class designation 125conforming IS : 2222-1991 in exposed brick work including making horizontal andvertical grooves 10mm wide 12 mm deep complete from ground level upto plinthlevel in cement mortar 1:6(1 cement: 6 coarse sand).

CodDiscription Unit Quantity Rate AmountDetails of cost for 1 cum.MATERIALS :

###Machine moulded modular perfor1000 Nos 494 3,233 1 597.10of class designation 125

###Carriage of Bricks 1000 Nos 494 141.88 70.09###Cement mortar 1:6,(1 cement: 6 cum .25 1,987.3 496.82

(Rate as per item no 3.11)###Sundries i/c steel /wooden strips L.S. 16.38 1 16.38

groovesLABOUR:

###Mason 1st Class Day .35 151.5 54.54###Mason Ilnd Class Day .35 141.6 50.98###Coolie Day 1.07 135.25 185.29###Bhishti Day .2 138.45 27.69

TOTAL 2,498.89Add 1 % for water charges 24.99TOTAL 2,523.88Add for contractor’s profit and overheads @ 378.581,500%Cost of 1 Cum. 2,902.46Say 2,902.45

219### Brick work with machine moulded perforated modular bricks of class designation

125 conforming to IS : 2222 -1991 in exposed brick work including making horizontaland vertical grooves 10 mm wide 12mm deep complete from ground level upto plinthlevel in cement mortar 1:6 (1 cement: 6 coarse sand).

CodDiscription Unit Quantity Rate AmountDetails of cost for 1 cum.MATERIALS :

###Machine moulded modular perfor1000 Nos 487 3,200 1,558.4

Page 211: DAR_Vol_1

of class designation 125###Carriage of Bricks 1000 Nos 487 141.88 69.1

Cement mortar 1:6 (1 cement: 6 cum .22 1,987.3 437.21(Rate as per item no 3.11)

###Sundries i/c steel /wooden strip L.S. 16.38 1 16.38groovesLABOUR:

###Mason 1st Class Day .33 151.5 50###Mason Ilnd Class Day .33 141.6 46.73###Coolie Day 1 135.25 135.25###Bhishti Day .18 138.45 24.92

TOTAL 2,337.99Add 1 % for water charges 23.38TOTAL 2,361.37Add for contractor’s profit and overheads @ 354.211,500%Cost of 1 Cum. 2,715.58Say 2,715.6

### Brick work with clay fly-ash F.P.S. brick of class designation 75 in superstructureabove plinth level upto floor five level in :

6.32.1 Cement mortar 1:4(1 cement : 4 coarse sand)CodDiscription Unit Quantity Rate Amount

Details of cost for 1 cum.Materials :

###Clay flyash bricks of class desi 1000 Nos 494 1,412 697.53Cement mortar1: 4 (1 cement: 4 cum .25 2,578.45 644.61(Rate as per item no 3.11)

###Carriage of bricks ‘ 1000 Nos. 494 141.88 70.09###Sundries L.S. 2.75 1 2.73

Labour:###Mason 1st class Day .47 151.5 71.2###Mason 2nd class Day .47 141.6 66.55###Coolie Day 1.8 135.25 243.45###Bhishti Day .2 138.45 27.69###Scaffolding L .S. 8.97 1 8.97

Extra labour element required for lifting ofmaterials above floor two level upto floor Vlevel (0.75 x 1.5 = 1.13)

###Coolie Day 1.13 135.25 152.83TOTAL 1,985.65Add 1 % for water charges 19.86TOTAL 2,005.51Add for contractor’s profit and overheads @ 300.831,500%Cost per cum. 2,306.34Say 2,306.35

220### Brick work with clay flyash F.P.S. brick of class designation 75 in superstructure

above plinth level upto floor five level in :6.32.2 Cement mortar 1:6(1 cement: 6 coarse sand)

CodDescription Unit Quantity Rate Amount

Page 212: DAR_Vol_1

Details of cost for 1 cum.Materials :

###Clay flyash bricks of class desi 1000 Nos 494 1,412 697.53Cement mortar 1 : 6(1 cement: 6 cum .25 1,987.3 496.82 (Rate as per item no 3.11)

###Carriage of bricks 1000 Nos 494 141.88 70.09###Sundries L.S. 2.73 1 2.73

Labour:###Mason 1st class Day .47 151.5 71.2###Mason 2nd class Day .47 141.6 66.55###Coolie Day 1.8 135.25 243.45###Bhishti Day .2 138.45 27.69###Scaffolding L.S 8.97 1 8.97

Extra labour element required for lifting ofmaterials above floor two level upto floor Vlevel (0.75x1.5= 1.13)

###Coolie Day 1.13 135.25 152.83TOTAL 1,837.86Add 1% for water charges 18.38TOTAL 1,856.24Add for contractor’s profit and overheads @ 278.441,500%Cost per cum. 2,134.68Say 2,134.7

### Extra for exposed brick work/clay flyash brick work in superstructure above floorfive level, for each four floors or part thereof.

CodDescription Unit Quantity Rate AmountDetails of cost for per cum. per four floorExtra labour element required for lifting ofmaterials

###0.75x2.00=1.50 Day 1.5 135.25 202.88Coolie

202.88TOTAL

2.03Add 1 % for water charges

204.91TOTAL

30.74Add for contractor’s profit and overheads @1,500%

235.65Cost of 1 Cum.

235.65Say

221### Brick work with modular fly ash lime bricks (FALG Bricks) conforming to IS: 12894-

2002, class designation 100 average compressive strength in super structure aboveplinth level upto floor V level in :

6.34.1 Cement mortar 1:4 (1 cement: 4 coarse sand)CodDescription Unit Quantity Rate Amount

Page 213: DAR_Vol_1

Details of cost for 1 cum.Materials:

###Fly ash bricks of class designati 1000 Nos 487 1,792 872.7Cement mortar 1 : 4 (1 cement: 4cum .22 2,578.45 567.26(Rate as per Item No. 3.9)

###Carriage of bricks’ 1000 Nos 487 141.88 69.1###Sundries L.S. 2.73 1 2.73

Labour:###Mason 1st class Day .47 151.5 71.2###Mason 2nd class Day .47 141.6 66.55###Coolie Day 1.8 135.25 243.45###Bhishti Day .2 138.45 27.69###Scaffolding L.S. 22.36 1 22.36

Extra labour element required for lifting ofmaterials above floor two level upto floor Vlevel (0.75x1.5 =1.13)

###Coolie Day 1.13 135.25 152.83TOTAL 2,095.87Add 1 % for water charges 20.96TOTAL 2,116.83Add for contractor’s profit and overheads @ 317.521,500%Cost per cum. 2,434.35Say 2,434.35

### Brick work with modular fly ash lime bricks (FALG Bricks) conforming to IS: 12894-2002, class designation 100 average compressive strength in super structure aboveplinth level upto floor V level in :

6.34.2 Cement mortar 1:6(1 cement: 6 Coarse sand)CodDescription Unit Quantity Rate Amount

Details of cost for 1 cumMaterials :

###Fly ash bricks of class designati 1000 Nos 487 1,792 872.7Cement.mortar 1:6 (1 cement: 6 cum .22 1,987.3 437.21Rate as per Item No. 3.11

###Carriage of brick’s 1000 Nos 487 141.88 69.1###Sundries

Labour: L.S. 2.73 1 2.73###Mason 1st class Day .47 151.5 71.2###Mason 2nd class Day .47 141.6 66.55###Coolie Day 1.8 135.25 243.45###Bhishti Day .2 138.45 27.69###Scaffolding L.S. 22.36 1 22.36

Extra labour element required for lifting ofmaterials above floor two level upto floor V level

###Coolie (0.75x1.5= 1.13) Day 1.13 135.25 152.83TOTAL 1,965.82Add 1% for water charges 19.66TOTAL 1,985.48Add for contractor’s profit and overheads @ 297.821,500%Cost per cum. 2,283.3Say 2,283.3

Page 214: DAR_Vol_1

222### Brick work with modular calcium silicate bricks machine moulded conforming to

IS:4139-1989, class designation 100 average compressive strength in super structureabove plinth level upto floor V level in :

6.35.1 Cement mortar 1:4 (1 cement: 4 coarse sand)CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.Materials :

###Calcium silicate bricks of class designation100 1000 N 487 3,083 501.42Cement mortar 1 : 4 (1 cement : cum .22 2,578.45 567.26(Rate as per item No 3.9)

###Carriage of bricks 1000 Nos 487 141.88 69.1###Sundries L.S. 2.73 1 2.73

Labour:###Mason 1st class Day .47 151.5 71.20 1 Mason 2nd class Day .47 141.6 66.55###Coolie Day 1.8 135.25 243.45###Bhishti Day .2 138.45 27.69###Scaffolding L.S. 22.36 1 22.36

Extra labour element required for lifting ofmaterials above floor two level upto floor Vlevel

O11Coolie (0.7 x 1.5 = 1.13) Day 1.13 135.25 152.83TOTAL 2,724.59Add 1 % for water charges 27.25TOTAL 2,751.84Add for contractor’s profit and overheads @ 412.781,500%Cost per cum. 3,164.62Say 3,164.6

### Brick work with modular calcium silicate bricks machine moulded conforming toIS:4139-1989, class designation 100 average compressive strength in super structureabove plinth level upto floor V level in :

6.35.2 Cement mortar 1:6 (1 cement: 6 Coarse sand)CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.Materials :

###Calcium silicate bricks of class designation 100 1000 487 3,083 1,501.42Cement .mortar 1:6(1 cement: 6 cum .22 1,987.3 437.21(Rate as per item No. 3.9)

###Carriage of bricks 1000 Nos 487 141.88 69.1###Sundries L.S. 2.73 1 2.73

Labour:###Mason 1st class Day .47 151.5 71.2###Mason 2nd class Day .47 141.6 66.55###Coolie Day 1.8 135.25 243.45###Bhishti Day .2 138.45 27.69###Scaffolding L.S. 22.36 1 22.36

Extra labour element required for lifting ofmaterials above floor two level upto floor Vlevel

###Coolie (0.75 x 1.5 = 1.13) Day 1.13 135.25 152.83TOTAL 2,594.54

Page 215: DAR_Vol_1

223CodDescription Unit Quantity Rate Amount

Add 1 % for water charges 25.95TOTAL 2,620.49Add for contractor’s profit and overheads @ 393.071,500%Cost per cum. 3,013.56Say 3,013.55

### Brick work with modular extruded burnt fly ash clay sewer bricks (Conforming toIS: 4885 - 1988) in foundation and plinth :

6.36.1 Cement Mortar 1:4(1 cement: 4 coarse sand)CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.Materials :

###Extruded burnt flyash clay sewer 1000 Nos 487 3,550 1,728.85Cement mortar 1:4(1 cement: 4 ccum .22 2,578.45 567.26(Rate as per item No. 3.9)

###Carriage of bricks 1 000 Nos 487 141.88 69.1###Sundries L.S. 2.73 1 2.73

Labour:###Mason 1st class Day .33 151.5 50###Mason 2nd class Day .33 141.6 46.73###Coolie Day 1 135.25 135.25###Bhishti Day .18 138.45 24.92

TOTAL 2,624.84Add 1 % for water charges 26.25TOTAL 2,651.09Add for contractor’s profit and overheads @ 397.661,500%Cost per cum. 3,048.75Say 3,048.75

### Brick work with modular extruded burnt fly ash clay sewer bricks (conforming to IS: 4885-1988) in arches in foundation and plinth in cement mortar 1:3(1 cement: 3 finesand).

CodDescription Unit Quantity Rate AmountDetails of cost for 1 cum.Materials :

###Extruded burnt flyash clay sewer 1000 Nos 487 3,550 1,728.85Cement mortar 1: 3 (1 cement: 3 cum .25 2,870 717.5(Rate as per item No. 3.3)

###Carriage of bricks 1000 Nos 487 141.88 69.1###Sundries L.S. 2.73 1 2.73 (A Centering and shuttering

(Rate as per item no 5.9.9 SH : R sqm 2.25 514.7 1 158.08Labour:

###Mason 1st class Day .42 151.5 63.63###Mason 2nd class Day .42 141.6 59.47###Coolie Day 1.86 135.25 251.57###Bhishti Day .2 138.45 27.69

TOTAL 4,078.62Add 1 % for water charges except on A 29.21TOTAL 4,107.83Add for contractor’s profit and overheads @ 442.4615% except on ACost per cum 4,550.29Say 4,550.3

Page 216: DAR_Vol_1

224### Providing and laying autoclaved aerated cement blocks masonry with 100mm thick

AAC blocks in super structure above plinth level upto floor V level in cement mortar1:4 (1 cement : 4 coarse sand ) The rate includes providing and placing in position 2Nos. 6 mm dia M.S. bars at every third course of masonry work.

CodDescription Unit Quantity Rate AmountDetails of cost for 1 cum.MATERIALS :

###Autoclaved aerated cement (AACcum 1 1,650 1,650Cement mortar 1:4 cum .15 2,578.45 386.77(Rate as per Item No. 3.9)

###Carriage of AAC blocks cum 1 53.21 53.21###Sundries L.S 2.73 1 2.73

LABOUR:###Mason 1st Class Day .36 151.5 54.54###Mason Ilnd Class Day .36 141.6 50.98###Coolie Day 1.37 135.25 185.29###Bhishti Day .2 138.45 27.69 Reinforcement bars

Rate as per item no 5.22.1 of SH : RCC kg 13.2 41.5 547.8TOTAL 2,959.01Add 1 % for water charges except on (A) 24.11TOTAL 2,983.12Add for contractor’s profit and overheads @ 365.315% except on (A)Cost of 1 Cum. 3,348.42Say 3,348.4

### Extra for AAC block masonry in superstructure above floor V level for every fourfloors or part there of.

CodDescription Unit Quantity Rate AmountDetails of cost for 1 cum per floorExtra labour element required for lifting ofmaterials.

###Coolie (0.75 x 2 = 1.50) Day 1.5 135.25 202.88TOTAL 202.88Add 1% for water charges 2.03TOTAL 204.91Add for contractor’s profit and overheads @ 30.741,500%Cost per cum. 235.65Say 235.65

### Providing and laying Gypsum panel partitions 100mm thick with water proof Gypsumpanels of size 666x500x100mm, made of ‘calcite phosphor of Gypsum fixed withtongue and groove, jointed with bonding plaster as per manufacturers specificationsin superstructure above plinth level upto floor V level. Gypsum blocks will have a

2

minimum compressive strength of 9.3 kg/cmCodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.MATERIAL

###Gypsum panel 666 X 500 X 100 msqm 10 544 5,440

Page 217: DAR_Vol_1

###Bonding plaster for Gypsum panel. kg 25 50 1,250###Sundries & scaffolding L.S. 13.52 1 13.52

LABOUR

225CodDescription Unit Quantity Rate Amount###Mason (brick layer) 1st class Day .5 151.5 75.75###Beldar Day 1 135.25 135.25

TOTAL 6,914.52Add 1 % for water charges 69.15TOTAL 6,983.67Add 15% for contractor’s profit and overheads 1,047.55Cost for 10 sqm 8,031.22Cost for 1 sqm 803.12Say 803.1

### Extra for Gypsum panel Partitions in superstructure above floor V level for everyfour floors or part thereof.

CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm. per four floorExtra labour element for lifting of materialsabove floor V level.

###Coolie Day 1.73 135.25 233.98Total 233.98Add for water charges @ 1% 2.34Total 236.32Add for contractor’s profit and overheads @ 15% 35.45Cost for 10 sqm. 271.77Cost for 1 sqm 27.18Say 27.2

### Brick work with mechanised autoclaved flyash lime bricks conforming to I:S 12894 :2002 of class designation 100 in superstructure above plinth level upto floor Vlevel in.

6.42.1 Cement mortar 1:4 (1 cement :4 coarse sand).CodDescription Unit Quantity Rate Amount

Details of Cost for 10 cumMATERIALS

###Mechanised Autoclaved flyash lim1000 Nos 494 2,200 1,086.8Cement morter 1:4 (1 cement: 4 cum .25 2,578.45 644.61(Rate as per item no 3.9)

###Carriage of Bricks 1000 Nos 494 141.8 70.09###Sundries L.S. 2.73 1 2.73###Mason 1st class Day .36 151.5 54.54###Mason 2nd class Day .36 141.6 50.98###Coolie Day 1.37 135.25 185.29###Bhisti Day .2 138.45 27.69

TOTAL 2,122.73Add for water charges @ 1 % 21.23TOTAL 2,143.96Add for contractor’s profit and overheads @15% 321.59Cost for 1 cum 2,465.55Say 2,465.55

Page 218: DAR_Vol_1

226### Brick work with mechanised autoclaved flyash lime bricks conforming to IS: 12894 :2002

of class designation 100 in superstructure above plinth level upto floor V level in.6.42.2 Cement mortar 1:6 (1 cement :6 coarse sand).CodDescription Unit Quantity Rate Amount

Details of Cost for 10 cumMATERIALS

###Mechanised Autoclaved flyash lim1000 Nos 494 2,200 1,086.8Cement morter 1:6 (1 cement: 6 cum .25 1,987.3 496.82(Rate as per item no 3.11)

###Carriage of Bricks 1000 Nos 494 141.88 70.09###Sundries L.S. 2.73 1 2.73###Mason 1st class Day .36 151.5 54.54###Mason 2nd class Day .36 141.6 50.98###Coolie Day 1.37 135.25 185.29###Bhisti Day .21 138.45 27.69

TOTAL 1,974.94Add for water charges @ 1% 19.75TOTAL 1,994.69Add for contractor’s profit and overheads @ 15% 299.2Cost for 1 cum 2,293.89Say 2,293.9

### Extra for mechanised autoclave flyash lime bricks conforming to IS: 12894- 1990 ofclass designation 100 in superstructure above floor V level for each four floors orpart thereof.

CodDescription Unit Quantity Rate AmountDetails of cost for per cum. per four floorsExtra labour element required for lifting ofmaterials0.75x2.00= 1.50

###Coolie Day 1.5 135.25 202.88TOTAL 202.88Add 1 % for water charges 2.03TOTAL 204.91Add for contractor’s profit and overheads @ 15% 30.74Cost of 1 Cum. 235.65Say 235.65

### Brick edging 7cm wide 11.4cm deep to plinth protection with bricks of classdesignation 75 including grouting with cement mortar 1:4(1 cement: 4 fine sand).

CodDescription Unit Quantity Rate Amount

Details of cost for 10m length###Excavation and disposal of surpl L.S. 2.73 1 2.73

2nd class bricks = 42 nos. +Add wastage @ 10% = 4.2 nos.= 46.2 nos.Say 46.00 nos.

###Bricks of class designation 75 1000 Nos 46 1 900.00 87.4###Carriage of bricks 1000 Nos 46 141.88 6.53

Cement mortat 1:4 (Rate as per i cum .0036 2 278.85 8.2Labour

Page 219: DAR_Vol_1

###Mason Day .1 146.55 14.66

227CodDescription Unit Quantity Rate Amount###Beldar Day .1 135.25 13.52###Bhisti Day .03 138.45 4.15###Sundries L.S. 2.73 1 2.73

TOTAL 139.92Add 1 % for water charges 1.4TOTAL 141.32Add 15% for contractor’s profit and overheads 21.2Cost of 10 metres 162.52Cost of 1 metre 16.25Say 16.25

229

SUB HEAD : 7.0

STONE WORK

Page 220: DAR_Vol_1

2317.1Random rubble masonry with hard stone in foundation and plinth including

levellingup with cement concrete 1:6:12 (1 cement: 6 coarse sand : 12 graded stoneaggregate 20mm nominal size) at plinth level with :

7.1Cement mortar 1:6(1 cement: 6 coarse sand)CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.Materials :

###Stone at quarry cum 1 332 332###Through and bond stones 7 nos. 100 Nos 7 970 67.9

Carriage of stone-7.00x24cmx24cmx39cm = 0.16 cum.

###1 .OOcum. + 0.16 cum. = 1.16 cu cum 1.16 62.6 72.62Cement mortar 1:6 (1 cement: 6 cum .33 1,987.3 655.81LABOURRate as per item no. 3.11

###Mason 2nd class Day 1.07 141.6 151.51###Beldar Day 1.07 135.25 144.72###Coolie Day .71 135.25 96.03###Bhishti Day .09 138.45 12.46###Cement concrete 1:6:12 L.S. 45.76 1 45.76###Sundries L.S. 4.42 1 4.42

TOTAL 1 583.23Add 1% for water charges 15.83TOTAL 1 599.06Add ,15% for contractor’s profit and overheads 239.86Cost of 1 cum. 1 838.92Say 1 838.90

7.2Extra for random rubble masonry with hard stone in superstructure above plinthlevel and upto floor five level, including levelling up with cement concrete 1:6:12 (1cement: 6 coarse sand : 12 graded stone aggregate 20mm nominal size) at windowsills, ceiling level and the like.

CodDescription Unit Quantity Rate AmountDetails of cost for 1 cum.

###Scaffolding etc. L.S. 67.34 1 67.34Labour:

###Labour for laying cement concre L.S. 10.79 1 10.79###Mason (2nd class) Day .27 141.6 38.23###Beldar Day .38 135.25 51.4

Extra labour for lifting of materials upto floorV level-0.75xl.50= 1.13

###Coolie Day 1.13 135.25 152.83TOTAL 320.59Add 1% for water charges 3.21TOTAL 323.8Add 15% for contractor’s profit and overheads 48.57Cost of 1 cum. 372.37Say 372.35

Page 221: DAR_Vol_1

2327.3 : Extra for random rubble masonry with hard stone in superstructure above floor V

level for every four floors or part thereofCodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.Labour required for lifting of materials1.0x2.0 = 2.00

###Beldar Day 2 135.25 270.5TOTAL 270.5Add 1% for water charges 2.7TOTAL 273.2Add 15% for contractor’s profit and overheads 40.98Cost of 1 cum. 314.18Say 314.2

7.4Extra for random rubble masonry with hard stone in7.4Square or rectangular pillarsCodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.Labour:

###Mason (2nd class) Day .58 141.6 82.13###Coolie Day .27 135.25 36.52

TOTAL 118.65Add 1% for water charges 1.19TOTAL 119.84Add 15% for contractor’s profit and overheads 17.98Cost of 1 cum. 137.82Say 137.8

7.4Extra for random rubble masonry with hard stone in7.4Circular pillars.CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.###Extra stone cum .29 332 96.28###Carriage. cum .29 62.6 18.15

Labour:Labour for cutting and dressing stones-

###Mason (2nd class) Day 1.42 141.6 201.07###Coolie Day .35 135.25 47.34

Total 362.84Add 1 % for water charges 3.63Total 366.47Add 15% for contractor’s profit and 54.97overheads.Cost of 1 cum 421.44Say 421.45

2337.5 : Extra for random rubble masonry with hard stone curved on plan for a mean radius

not exceeding 6 m.CodDescription Unit Quantity Rate Amount

Page 222: DAR_Vol_1

Details of cost for 1 cum.###Extra stone cum .1 332 33.2###Carriage of stone cum .1 62.6 6.26

Labour for cutting and dressing stones-###Mason (2nd class) Day .27 141.6 38.23###Coolie Day .53 135.25 71.68

TOTAL 149.37Add 1 % for water charges 1.49TOTAL \" 150.86Add 15% for contractor’s profit and overheads 22.63Cost of 1 cum. 173.49Say 173.5

7.6Coursed rubble masonry (first sort) with hard stone in foundation and plinth with :7.6Cement mortar 1:6 (1 cement: 6 coarse sand)CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.Materials-Cement mortar l:6 (Rate as per i cum .3 1 987.30 596.19

###Stone at quarry cum 1.21 332 401.72###Through and bond stone 7 nos. 100 Nos 7 970 67.9

Carriage of stone7.00x24cmx24cmx39cm = 0.16 cum.

###1.21+0.16=1.37 cum. cum 1.37 62.6 85.76Labour:

###Mason (2nd class) Day 2.12 141.6 300.19###Beldar Day 1.24 135.25 167.71###Coolie Day .71 135.25 96.03###Bhisti Day .09 138.45 12.46###Sundries L.S. 13.52 1 13.52

TOTAL 1 741.48Add 1% for water charges 17.41TOTAL 1 758.89Add 15% for contractor’s profit and overheads 263.83Cost of 1 cum. 2 022.72Say 2 022.70

7.7Coursed rubble masonry (second sort) with hard stone in foundation & plinth with:7.7.1 : Cement mortar 1:6 (1 cement: 6 coarse sand)CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.Materials-Cement mortar l:6 (Rate as per i cum .3 1,987.3 596.19

###Stone at quarry cum 1.1 332 365.2###Through and bond stones 7 nos. 100 Nos 7 970 67.9

Carriage of stone7.00x24cmx24cmx39cm = 0.16 cum.

###1.10+0.16 cum = 1.26 cum. cum 1.26 62.6 78.88Labour:

###Mason (2nd class) Day 1.76 141.6 249.22###Beldar Day 1.24 135.25 167.71###Coolie Day .71 135.25 96.03

234CodDescription Unit Quantity Rate Amount

Page 223: DAR_Vol_1

###Bhisti Day .09 138.45 12.46###Sundries L.S. 13.52 1 13.52

TOTAL 1 647.11Add 1% for water charges 16.47TOTAL 1 663.58Add 15% for contractor’s profit and overheads 249.54Cost of 1 cum. 1 913.12Say 1 913.10

7.8Extra for coursed rubble masonry with hard stone (first or second sort) insuperstructure above plinth level and upto floor five level.

CodDescription Unit Quantity Rate AmountDetails of cost for 1 cum.

###Scaffolding etc. L.S. 9.3 2.6 24.18Labour:

###Mason (2nd class) Day .26 141.6 36.82###Beldar Day .35 135.25 47.34

Extra labour for lifting of materials upto floorV level1.0x1.50= 1.50

###Coolie Day 1.5 135.25 202.88TOTAL 311.22Add 1 % for water charges 3.11TOTAL 314.33Add 15 %for contractor’s profit and overheads 47.15Cost of 1 cum. 361.48Say 361.5

7.9Extra for coursed rubble masonry with hard stone (first or second sort) in

CodDescription Unit Quantity Rate AmountDetails of cost per floor per cum.Labour required for lifting of material1.00x2.00=2.00

###Beldar Day 2 135.25 270.5TOTAL 270.5Add 1% for water charges 2.7TOTAL 273.2Add 15% for contractor’s profit and overheads 40.98Cost of 1 cum. 314.18Say 314.2

### Extra for coursed rubble masonry with hard stone (first or second sort) in :7.1Square or rectangular pillarsCodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.Labour:

###Mason (2nd class) Day .67 141.6 94.87###Coolie Day .27 135.25 36.52

TOTAL 131.39Add 1% for water charges 1.31TOTAL 132.7Add. 15% for contractor’s profit and overheads 19.9Cost of 1 cum. 152.6Say 152.6

superstructure above floor V level for every four floors or part thereof.

Page 224: DAR_Vol_1

2357.1Extra for coursed rubble masonry with hard stone (first or second sort) in :7.10.2 : Circular pillars.CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.###Extra stones. cum .32 332 106.24###Carriage of stone cum .32 62.6 20.03

Labour:Labour for cutting and dressing :

###Mason (2nd class) Day 1.67 141.6 236.47###Coolie Day .35 135.25 47.34

Total 410.08Add 1 % for water charges. 4.1Total 414.18Add 15% for contractor’s profit and 62.13overheads.Cost of 1 cum 476.31Say 476.3

7.11 : Extra for coursed rubble masonry with hard stone (first or second sort) curved onplan for a mean radius not exceeding 6 m.

CodDescription Unit Quantity Rate AmountDetails of cost for 1 cum.

###Extra stones cum .11 332 36.52###Carriage of stone cum .11 62.6 6.89

Labour for cutting and dressing:###Mason (2nd class) Day .33 141.6 46.73###Coolie Day .53 135.25 71.68

TOTAL 161.82Add 1% for water charges 1.62TOTAL 163.44Add. 15% for contractor’s profit and overheads 24.52Cost of 1 cum. 187.96Say 187.95

7. Stone work in plain ashlar in super structure upto floor five level in cement mortar1:6 (1 cement : 6 coarse sand) including pointing with cement mortar 1:2 (1 whitecement: 2 stone dust) with an admixture of pigment matching the stone shade :

7.12.1 : One face dressed.7.12.1.1 : Red sand stoneCodDescription Unit Quantity Rate Amount

Details of cost for 10 cudm.Materials-Red sand stoneFinished work = 10 cudm.+Add wastage @ 33.3% = 3.33 cudm.

###Total = 13.33 cudm. 10 cudm 13.33 45 59.98Cost of stone

###Carriage of stone @ 2.30kg/cudmtonne .031 47.29 1.4713.33x2.30 = 30.659 kg = tonne0.031 t.Extra labour for lifting of materials upto floorV level0.01x1.50 = 0.015

###Coolie Day .015 135.25 2.03Dressing chargesLabour:

Page 225: DAR_Vol_1

236CodDescription Unit Quantity Rate Amount###Stone mason (plane work) 2nd cl Day .088 141.6 12.46###Black smith 1 st class Day .006 151.5 .91###Beldar Day .044 135.25 5.95###Coolie Day .022 135.25 2.98###Bandhani Day .044 138.45 6.09

Fixing chargesLabour:

###Stone mason (plan work) 2nd cla Day .044 141.6 6.23###Blacksmith 1st class Day .006 151.5 .91###Beldar Day .022 135.25 2.98###Coolie Day .022 135.25 2.98###Bandhani Day .022 138.45 3.05###Bhishti Day .022 138.45 3.05###Scafolding L.S. 2.73 1 2.73###Mortar for laying and pointing L.S. 8.06 1 8.06

TOTAL 121.86Add 1% for water charges 1.22TOTAL 123.08Add 15% for contractor’s profit and overheads 18.46Cost of 10 cudm. 141.54Cost of 1 cum. 14,154Say 14,154

7.1Stone work in plain ashlar in super structure upto floor five level in cement mortar1:6 (1 cement : 6 coarse sand) including pointing with cement mortar 1:2(1 whitecement: 2 stone dust) with an admixture of pigment matching the stone shade :

7.12.1 : One face dressed.7.12.1.2 : White sand stoneCodDescription Unit Quantity Rate Amount

Details of cost for 10 cudm.Materials-White sand stoneFinished work = 10 cudm.+Add wastage @ 33.3% = 3.33 cudm.Total = 13.33 cudm.

###Cost of stone 10 cudm 13.33 50 66.65###Carriage of stone @ 2.30kg/cudmtonne .031 47.29 1.47

13.33x2.30 = 30.659 kg = tonne0.031 t.Extra labour for lifting of materials upto floorV level.0.01x1.50=0.015

###Coolie Day .015 135.25 2.03Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day .088 141.6 12.46###Blacksmith 1st class Day .006 151.5 .91###Beldar Day .044 135.25 5.95###Coolie Day .022 135.25 2.98###Bandhani Day .044 138.45 6.09

Fixing chargesLabour:

###Stone mason (plane work) 2nd cl Day .044 141.6 6.23

Page 226: DAR_Vol_1

###Blacksmith 1st class Day .006 151.5 .91###Beldar Day .022 135.25 2.98

237CodDescription Unit Quantity Rate Amount###Coolie Day .022 135.25 2.98###Bandhani Day .022 138.45 3.05###Bhishti Day .022 138.45 3.05###Scaffolding L.S. 2.73 1 2.73###Mortar for laying and pointing L.S. 8.06 1 8.06

TOTAL 128.53Add 1% for water charges 1.29TOTAL 129.82Add.15% for contractor’s profit and overheads 19.47Cost of 10 cudm. 149.29Cost of 1 cum. 14,929Say 14,929

7.1Stone work in plain ashlar in super structure upto floor five level in cement mortar1:6 (1 cement : 6 coarse sand) including pointing with cement mortar 1:2 (1 whitecement: 2 stone dust) with an admixture of pigment matching the stone shade :

7.1Both face dressed.7.12.2.1 : Red sand stone.CodDescription Unit Quantity Rate Amount

Details of cost for 10 cudm.Materials-Red sand stoneFinished work = 10 cudm.+Add wastage @ 33.3% = 3.33 cudm.

###Total = 13.33 cudm. 10 cudm 13.33 45 59.98Cost of stone

###Carriage of stone @ 2.30kg/cudmtonne .031 47.29 1.4713.33x2.30 = 30.659 kg = tonne say0.031 t.Extra labour for lifting of materials upto floorV level0.01x1.50 = 0.015

###Coolie Day .015 135.25 2.03Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day .176 141.6 24.92###Blacksmith 1st class Day .012 151.5 1.82###Beldar Day .088 135.25 11.9###Coolie Day .044 135.25 5.95###Bandhani Day .088 138.45 12.18

Fixing chargesLabour:

###Stone mason (plan work) 2nd cla Day .044 141.6 6.23###Blacksmith 1st class Day .006 151.5 .91###Beldar Day .022 135.25 2.98###Coolie Day .022 135.25 2.98###Bandhani Day .022 138.45 3.05###Bhishti Day .022 138.45 3.05###Scafolding L.S. 2.73 1 2.73

Page 227: DAR_Vol_1

###Mortar for laying and pointing L.S. 8.06 1 8.06TOTAL 150.24Add 1 % for water charges 1.5TOTAL 151.74Add 15% for contractor’s profit and overheads 22.76Cost of 10 cudm. 174.5Cost of 1 cum. 17, 450.00Say 17, 450.00

2387.1Stone work in plain ashlar in super structure upto floor five level in cement mortar

1:6 (1 cement : 6 coarse sand) including pointing with cement mortar 1:2 (1 whitecement: 2 stone dust) with an admixture of pigment matching the stone shade :

7.12.2 : Both face dressed.7.12.2.2: White sand stoneCodDescription Unit Quantity Rate Amount

Details of cost for 10 cudm.Materials-White sand stoneFinished work = 10 cudm.+Add wastage @ 33.3% = 3'.33 cudm.Total = 13.33 cudm.

###Cost of stone 10 cudm 13.33 50 66.65###Carriage of stone @ 2.30kg/cudmtonne .031 47.29 1.47

13.33x2.30 = 30.659 kg = tonne say0.031 t.Extra labour for lifting of material upto floorV level.0.01x1.50 = 0.015

###Coolie Day .015 135.25 2.03Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day .176 141.6 24.92###Blacksmith 1st class Day .012 151.5 1.82###Beldar Day .088 135.25 11.9###Coolie Day .044 135.25 5.95###Bandhani Day .088 138.45 12.18

Fixing chargesLabour:

###Stone mason (plane work) 2nd cl Day .044 141.6 6.23###Blacksmith 1st class Day .006 151.5 .91###Beldar Day .022 135.25 2.98###Coolie Day .022 135.25 2.98###Bandhani Day .022 138.45 3.05###Bhishti Day .022 138.45 3.05###Scaffolding L.S. 2.73 1 2.73###Mortar for laying and pointing L.S. 8.06 1 8.06

TOTAL 156.91Add 1 % for water charges 1.57TOTAL 158.48Add 15% for contractor’s profit and overheads 23.77Cost of 10 cudm. 182.25

Page 228: DAR_Vol_1

Cost of 1 cum. 18, 225.00Say 18, 225.00

2397.1Stone work plain ashlar in arches in cement mortar 1:3 (1 cement: 3 coarse sand)

including centring, shuttering and pointing with white cement mortar 1:2 (1 whitecement : 2 stone dust) with an admixture of pigment matching the stone shade.

7.13.1 : Red sand stoneCodDescription Unit Quantity Rate Amount

Details of cost for 10 cudm.Materials-Red sand stoneFinished work = 10 cudm.+Add wastage @ 33.3% = 3.33 cudm.Total = 13.33 cudm.

###Cost of Stone 10 cudm 13.33 45 59.98###Carriage of stone @ 2.30kg/cudmtonne .031 47.29 1.47

13.33x2.30 = 30.659 kg = tonne say0.031 t.Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day .088 141.6 12.46###Blacksmith 1st class Day .006 151.5 .91###Beldar Day .044 135.25 5.95###Coolie Day .022 135.25 2.98###Bandhani Day .044 138.45 6.09

Fixing chargesLabour:

###Stone mason (plane work) 2nd cl Day .044 141.6 6.23###Blacksmith 1st class Day .006 151.5 .91###Beldar Day .022 135.25 2.98###Coolie Day .022 135.25 2.98###Bandhani Day .022 138.45 3.05###Bhishti Day .022 138.45 3.05###Scaffolding L.S. 2.73 1 2.73###Mortar for laying and pointing L.S 8.06 1 8.06###Centering and shuttering L.S 13.52 1 13.52###Extra for using white cement L.S 8.06 1 8.06

TOTAL 141.41Add 1% for water charges 1.41TOTAL 142.82Add 15% for contractor’s profit and overheads 21.42Cost of 10 cudm. 164.24Cost of 1 cum. 16 ,424.00Say 16 ,424.00

7.1Stone work plain ashlar in arches in cement mortar 1:3 (1 cement: 3 coarse sand)i/c centring and shuttering and pointing with white cement mortar 1:2 ( 1 whitecemetn: 2 stone dust) with an admixture of pigment matching the stone shade:

7.13.2 : White sand stoneCodDescription Unit Quantity Rate Amount

Details of cost for 10 cudm.Materials-

Page 229: DAR_Vol_1

White sand stoneFinished work = 10 cudm.Add wastage @ 33.3% = 3.33 cudm.Total = 13.33 cudm.

###Cost of stone 10 cudm 13.33 50 66.65###Carriage of stone @ 2.30kg/cudmtonne .031 47.29 1.47

240CodDescription Unit Quantity Rate Amount

13.33x2.30=30.659 kg = tonne say0.031 tDressing chargesLabour:

###Stone mason (plane work) 2nd cl Day .088 141.6 12.46###Blacksmith st class Day .006 151.5 .91###Beldar Day .044 135.25 5.95###Coolie Day .022 135.25 2.98###Bandhani Day .044 138.45 6.09

Fixing chargesLabour:

###Stone mason (plane work) 2nd cl Day .044 141.6 6.23###Blacksmith 1st class Day .006 151.5 .91###Beldar Day .022 135.25 2.98###Coolie Day .022 135.25 2.98###Bandhani Day .022 138.45 3.05###Bhishti Day .022 138.45 3.05###Scaffolding L.S. 2.73 1 2.73###Mortar for laying and pointing L.S. 8.06 1 8.06###Centering and shuttering L.S. 13.52 1 13.52###Extra for using white cement L.S. 8.06 1 8.06

TOTAL 148.08Add 1 % for water charges 1.48TOTAL 149.56Add 15% for contractor’s profit and overheads 22.43Cost of 10 cudm. 171.99Cost of 1 cum. 17, 199.00Say 17, 199.00

7.1Stone work plain ashlar in domes in cement mortar 1:3 (1 cement: 3 coarse sand)including centring, shuttering and pointing with white cement mortar 1:2 (1 whitecement : 2 stone dust) with an admixture of pigment matching the stone shade.

7.14.1 Red sand stoneCodDescription Unit Quantity Rate Amount

Details of cost for 10 cudm.Materials-Red sand stoneFinished work = 10 cudm.+Add wastage @ 33.3% = 3.33 cudm.Total = 13.33 cudm.

###Cost of stone 10 cudm 13.33 45 59.98###Carriage of stone @ 2.30kg/cudmtonne .031 47.29 1.47

13.33x2.30=30.659 kg=tonne say 0.031 tDressing chargesLabour:

Page 230: DAR_Vol_1

###Stone mason (plane work) 2nd cl Day .176 141.6 24.92###Blacksmith 1st class Day .006 151.5 .91###Stone mason (ornamental work) Day .176 151.5 26.66###Beldar Day .044 135.25 5.95###Coolie Day .022 135.25 2.98###Bandhani Day .044 138.45 6.09

Fixing chargesLabour:

###Stone mason (plane work) 2nd cl Day .044 141.6 6.23###Blacksmith 1st class Day .006 151.5 .91

241CodDescription Unit Quantity Rate Amount###Beldar Day .022 135.25 2.98###Coolie Day .022 135.25 2.98###Bandhani Day .022 138.45 3.05###Bhishti Day .022 138.45 3.05###Scaffolding L.S. 2.73 1 2.73###Mortar for laying and pointing L.S. 8.06 1 8.06###Centring and shuttering L.S. 33.15 1 33.15###Extra for using white cement L.S. 8.06 1 8.06

TOTAL 200.16Add 1 % for water charges 2TOTAL 202.16Add 15%”Tor contractor’s profit and overheads 30.32Cost of 10 cudm. 232.48Cost of 1 cum. 23, 248.00Say 23, 248.00

7.1Stone work plain ashlar in domes in cement mortar 1:3 (1 cement: 3 coarse sand)including c;entring shuttering and pointing with white cement mortar 1:2 (1 whitecement : 2 stone dust) with an admixture of pigment matching the stone shade.

7.14.2 : White sand stoneCodDescription Unit Quantity Rate Amount

Details of cost for 10 cudm.Materials-White sand stoneFinished work = 10 cudm.+Add wastage @ 33.3% = 3.33 cudm.Total = 13.33 cudm.

###Cost of stone 10 cudm 13.33 50 66.65###Carriage of stone @ 2.30kg/cudmtonne .031 47.29 1.47

13.33x2.30=30.659 kg=tonne say 0.031 tDressing chargesLabour:

###Stone mason (plane work) 2nd cl Day .176 141.6 24.92###Blacksmith 1st class Day .006 151.5 .91###Stone mason (ornamental work) Day .176 151.5 26.66###Beldar Day .044 135.25 5.95###Coolie Day .022 135.25 2.98###Bandhani Day .044 138.45 6.09

Fixing chargesLabour:

###Stone mason (plane work) 2nd cl Day .044 141.6 6.23

Page 231: DAR_Vol_1

###Blacksmith 1st class Day .006 151.5 .91###Beldar Day .022 135.25 2.98###Coolie Day .022 135.25 2.98###Bandhani Day .022 138.45 3.05###Bhishti Day .022 138.45 3.05###Scaffolding L.S. 2.73 1 2.73###Mortar for laying and pointing L.S. 8.06 1 8.06###Centring and shuttering L.S. 33.15 1 33.15###Extra for using white cement L.S. 8.06 1 8.06

TOTAL 206.83Add 1 % for water charges 2.07TOTAL 208.9Add 15% for contractor’s profit and overheads 31.34Cost of 10 cudm. 240.24Cost of 1 cum. 24, 024.00Say 24, 024.00

2427.1Stone work ashlar punched (ordinary) in superstructure upto floor five level in

cement mortar 1:6 (1 white cement: 6 coarse sand) including pointing with cementmortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matchingthe stone shade.

7.15.1 : Red sand stone.7.15.1.1:One faced punched.CodDescription Unit Quantity Rate Amount

Details of cost for 10 cudm.Materials-Red sand stoneFinished work = 10 cudm.Add wastage @ 33.3% = 3.33 cudm.Total = 13.33 cudm.

###Cost of stone 10 cudm 13.33 45 59.98###Carriage of stone @ 2.30kg/cudmtonne .031 47.29 1.47

13.33x2.30=30.659 kg= tonne say 0.031 tDressing chargesLabour:

###Stone mason (plane work) 2nd cl Day .059 141.6 8.35###Blacksmith 1st class Day .006 151.5 .91###Beldar Day .044 135.25 5.95###Coolie Day .022 135.25 2.98###Bandhani Day .044 138.45 6.09

Fixing chargesLabour:

###Stone mason (plane work) 2nd cl Day .044 141.6 6.23###Blacksmith 1st class Day .006 151.5 .91###Beldar Day .022 135.25 2.98###Coolie Day .022 135.25 2.98###Bandhani Day .022 138.45 3.05###Bhishti Day .022 138.45 3.05###Scaffolding L.S. 2.73 1 2.73###Mortar for laying and pointing L.S. 8.06 1 8.06

Extra labour for lifting of materials upto floorV level= 0.01x1.50 = 0.015

Page 232: DAR_Vol_1

###Coolie Day .015 135.25 2.03TOTAL 117.75Add 1 % for water charges 1.18TOTAL 118.93Add 15% for contractor’s profit and overheads 17.84Cost of 10 cudm. 136.77Cost of 1 cum. 13,677Say 13,677

7.1Stone work ashlar punched (ordinary) in superstructure upto floor five level incement mortar 1:6 (1 white cement: 6 coarse sand) including pointing with cementmortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matchingthe stone shade.

7.1Red sand stone.7.15.1.2 : Double faced punched.CodDescription Unit Quantity Rate Amount

Details of cost for 10 cudm.Materials-Red sand stoneFinished work = 10 cudm.

243CodDescription Unit Quantity Rate Amount

Add wastage @ 33.3% = 3.33 cudm.###Total = 13.33 cudm. 10 cudm 13.33 45 59.98

Cost of stone###Carriage of stone @ 2.30kg/cud tonne .031 47.29 1.47

13.33x2.30 = 30.659 kg = tonne say0.031 t.Extra labour for lifting of materials upto floorV level0.01x1.50 = 0.015

###Coolie Day .015 135.25 2.03Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day .118 141.6 16.71###Black smith 1st class Day .012 151.5 1.82###Beldar Day .088 135.25 11.9###Coolie Day .044 135.25 5.95###Bandhani Day .088 138.45 12.18

Fixing chargesLabour:

###Stone mason (plan work) 2nd cla Day .044 141.6 6.23###Blacksmith 1st class Day .006 151.5 .91###Beldar Day .022 135.25 2.98###Coolie Day .022 135.25 2.98###Bandhani Day .022 138.45 3.05###Bhishti Day .022 138.45 3.05###Scafolding L.S. 2.73 1 2.73###Mortar for laying and pointing L.S. 8.06 1 8.06

TOTAL 142.03Add 1 % for water charges 1.42TOTAL 143.45Add 15% for contractor’s profit and overheads 21.52

Page 233: DAR_Vol_1

Cost of 10 cudm. 164.97Cost of 1 cum. 16,497Say 16,497

7.1Stone work ashlar punched (ordinary) in superstructure upto floor five level incement mortar 1:6 (1 white cement: 6 coarse sand) including pointing with cementmortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matchingthe stone shade.

7.15.2 : White sand stone.7.15.2.1:Single face punched.CodDescription Unit Quantity Rate Amount

Details of cost for 10 cudm.Materials-Red sand stoneFinished work = 10 cudm.+Add wastage @ 33.3% = 3.33 cudm.Total = 13.33 cudm.

###Cost of stone 10 cudm 13.33 50 66.65###Carriage of stone @ 2.30kg/cudmtonne .031 47.29 1.47

13.33x2.30=30.659 kg= tonne say 0.031 tDressing chargesLabour:

###Stone mason (plane work) 2nd cl Day .059 141.6 8.35

244CodDescription Unit Quantity Rate Amount###Blacksmith 1st class Day .006 151.5 .91###Beldar Day .044 135.25 5.95###Coolie Day .022 135.25 2.98###Bandhani Day .044 138.45 6.09

Fixing chargesLabour:

0 1 Stone mason (plane work) 2nd cl Day .044 141.6 6.23###Blacksmith 1st class Day .006 151.5 .91###Beldar Day .022 135.25 2.98###Coolie Day .022 135.25 2.98###Bandhani Day .022 138.45 3.05###Bhishti Day .022 138.45 3.05###Scaffolding L.S. 2.73 1 2.73###Mortar for laying and pointing L.S. 8.06 1 8.06

Extra labour for lifting of materials upto floorVlevel=0.01xl.50 = 0.015

###Coolie Day .015 135.25 2.03TOTAL 124.42Add 1% for water charges 1.24TOTAL 125.66Add 15% for contractor’s profit and overheads 18.85Cost of 10 cudm. 144.51Cost of 1 cum. 14,451Say 14,451

7.1Stone work ashlar punched (ordinary) in superstructure upto floor five level incement mortar 1:6 (1 white cement: 6 coarse sand) including pointing with cementmortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching

Page 234: DAR_Vol_1

the stone shade. 7.15.2 : White sand stone.7.15.2.2:Double faced punched.CodDescription Unit Quantity Rate Amount

Details of cost for 10 cudm.Materials-White sand stoneFinished work = 10 cudm.Add wastage @ 33.3% = 3.33 cudm.Total = 13.33 cudm.

###Cost of stone 10 cudm 13.33 50 66.65###Carriage of stone @ 2.30kg/cudmtonne .031 47.29 1.47

13.33x2.30 = 30.659 kg = tonne kg say0.031 t.Extra labour for lifting of material upto floorV level.0.01 x 1.50 = 0.015

###Coolie Day .015 135.25 2.03Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day .118 141.6 16.71###Blacksmith 1st class Day .012 151.5 1.82###Beldar Day .088 135.25 11.9###Coolie Day .044 135.25 5.95###Bandhani Day .088 138.45 12.18

Fixing chargesLabour:

245CodDescription Unit Quantity Rate Amount###Stone mason (plane work) 2nd cl Day .044 141.6 6.230 1 Blacksmith 1st class Day .006 151.5 .91###Beldar Day .022 135.25 2.98###Coolie Day .022 135.25 2.98###Bandhani Day .022 138.45 3.05###Bhishti Day .022 138.45 3.05###Scaffolding L.S. 2.73 1 2.73###Mortar for laying and pointing L.S. 8.06 1 8.06

0.0TOTAL 148.7Add 1 % for water charges 1.49TOTAL 150.19Add 15% for contractor’s profit and overheads 22.53Cost of 10 cudm. 172.72Cost of 1 cum 17,272Say 17,272

7.16 : Extra for stone work, plain ashlar or ashlar punched above floor V level for everyfour floors or part thereof.

CodDescription Unit Quantity Rate AmountDetails of cost for 10 cudm above floor V levelLabour required for lifting of material(above floor five level for each additional fourfloors) or part thereof.

Page 235: DAR_Vol_1

Extra labour for lifting of materials above floorV level (0.01 x 2.00 = 0.020)

###Beldar Day .02 135.25 2.7TOTAL 2.7Add 1 % for water charges, .03TOTAL 2.73Add 15% for contractor’s profit and overheads .41Cost of 10 cudm. 3.14Cost of 1 cum. 314Say 314

7.1Extra for plain ashlar or ashlar punched in :7.17.1 : Square or rectangular pillars.CodDescription Unit Quantity Rate Amount

Details of cost for 10 cudm.###Labour and materials L.S. 8.97 1 8.97

TOTAL 8.97Add 1% for water charges .09TOTAL 9.06Add 15% for contractor’s profit and overheads 1.36Cost of 10 cudm. 10.42Cost of 1 cum. 1 042.00Say 1 042.00

7.18 : Extra for stone work; plain ashlar or ashlar punched curved on plan with a meanradius not exceeding 6 m.

CodDescription Unit Quantity Rate AmountDetails of cost for 10 cudm.

###Labour and materials L.S. 6.24 1 6.24TOTAL 6.24Add 1% for water charges .06

246CodDescription Unit Quantity Rate Amount

TOTAL 6.3Add 15 % for contractor’s profit and overheads .94Cost of 10 cudm. 7.24Cost of 1 cum. 724Say 724

### Extra for additional cost of centring for arches exceeding 6m span including allstrutting, bolting, wedging etc. and removal (area of soffit to be measured),

CodDescription Unit Quantity Rate AmountDetails of cost per sqm.Centering and shuttering for arches and carvedsurface exceeding 6m in span (an average of8m)Radius R = 5m 2R-2=4+4tan-’(4/3)=53.28°2x53.28°=106°Surface area=2x22/7x5x3.6x106/360=33.3lsqm.Arc=9.25mMaterial:Tie-2x8x0. 18x0.05 =0.144cum

Page 236: DAR_Vol_1

Struts-2x2.5x0.1x0.1 =0.050cum.Struts-2x 1.77x0.1x0. l=0.035cum.Ribs-6x 1.54x0.23x0.1 =0.213cum.Struts-2xl .72x0.1x0.1 =0.034cum.Total=0.476cum.For four such frames=0.476x4= 1.904 cum.Iaggings-75x3.6x0.125x0.075=2.531 cum.Tie-2x3.6x0.225x0.038=0.062cum.Brace-3x2x2.14x0.225x0.038=0.110Brace-3x4x3.8x0.225x0.038=0.390Sleepers-4x3.6x0.20x0.15=0.432Sleepers-2x4x3.6xO. 175x0.075=0.378Vertical post-4x4x3.6x0.15x0.15=1.296Total =7.103cum. -

###Qty taken l/8th of qty for cost using once = 10 cudm 887.9 160 14 206.407.103/8 = 0.8879 cum

###Carriage of wood cum .8879 60.81 53.99Fittings:3 way straps 50mmxl0mm = 32 Nos.32 no. @0.50cm each = 16mStraps-50mmxl0mm = 8 Nos. @0.25cm each= 2mTotal = 18m

###18m, wt @ 3.9kg/m = 70.2 kg. = 0.702q quintal .0878 2 900.00 254.62Qty taken l/8th of qty for cost using once =0.702/8 = 0.08775 Qtl.

###Bolts 160 Nos. 254 mm long 16mm dia.- quintal .08 4 300.00 344160x.254xl .58=64.21 kg=0.64q.Qty taken l/8th of qty for cost using once =0.64/8 = 0.08 Qtl.

###Carriage of steel = 0.1342t tonne .0168 47.29 .79Qty taken l/8th of qty for cost using once =0.1342/8 = 0.01677 tLabour:

247CodDescription Unit Quantity Rate Amount###Carpenter 2nd class Day 28 141.6 3 964.80###Beldar Day 24 135.25 3 246.00###Sundries L.S. 134.55 1 134.55

Less Cost of shuttering etc. for an archexceeding 6 m span i.e. for an average of 8 mspan(A) Rate as per item 5.9.9 sqm 33.31 514.7 (-)17 144.66TOTAL 5 060.49Add 1 % for water charges on all exept ‘A’ 222.05TOTAL 5 282.54Add for contractor’s profit and overheads 3 364.08

15 % on all exept ‘A’Cost of 33.31 sqm. 8 646.62Cost per sqm of soffit area 259.58Say 259.6

7.2Stone work sunk or moulded or sunk and moulded upto floor five level in cement

@

Page 237: DAR_Vol_1

mortar 1:6 (1 cement: 6 coarse sand) including pointing with white cement mortar1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching thestone shade :

7.20.1 : Red sand stoneCodDescription Unit Quantity Rate Amount

Details of cost for 10 cudm.Materials-Red sand stoneFinished work = 10 cudm.Add wastage @ 33.3% = 3.33 cudm.Total = 13.33 cudm.

###Cost of red sand stone 10 cudm 13.33 45 59.98###Cement mortar : Carriage of stone @ tonne .031 47.29 1.47

2.30kg/cudm= 13.33x2.30 = 30.659 kg =0.031 t.

###Extra for using white cement L.S. 8.06 1 8.06Dressing chargesLabour:

###Stone mason (plane work) 2nd class Day .291 141.6 41.21###Blacksmith 1 st class Day .006 151.5 .91###Beldar Day .044 135.25 5.95###Coolie Day .022 135.25 2.98###Bandhani Day .044 138.45 6.09

Fixing chargesLabour:

###Stone mason (plane work) 2nd class Day .044 141.6 6.23###Blacksmith 1st class Day .006 151.5 .91###Beldar Day .022 135.25 2.98###Coolie Day .022 135.25 2.98###Bandhani Day .022 138.45 3.05###Bhishti Day .022 138.45 3.05###Scaffolding L.S. 2.73 1 2.73###Mortar for laying and pointing L.S. 8.06 1 8.06

Extra labour for lifting of materials upto floorV level0.01x1.50=0.015

###Coolie Day .015 135.25 2.03TOTAL 158.67

248CodDescription Unit Quantity Rate Amount

Add 1% for water charges 1.59TOTAL 160.26AddJWo for contractor’s profit and overheads 24.04Cost of 10 cudm. 184.3Cost of 1 cum. 18,430Say 18,430

7.2Stone work sunk or moulded or sunk and moulded upto floor five level in cementmortar 1:6 (1 cement : 6 coarse sand) including pointing with white cement mortar1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching thestone shade

Page 238: DAR_Vol_1

7.20.2 : White sand stoneCodDescription Unit Quantity Rate Amount

Details of cost for 10 cudm.Materials-Red sand stoneFinished work = 10 cudm.+Add wastage @ 33.3% = 3.33 cudm.Total = 13.33 cudm.

###Cost of stone 10 cudm 13.33 50 66.65###Carriage of stone @ 2.30kg/cudmtonne .031 47.29 1.47

13.33x2.30=30.659kg=0.031t.###Extra for using white cement L.S. 8.06 1 8.06

Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day .291 141.6 41.21###Blacksmith 1 st class Day .006 151.5 .91###Beldar Day .044 135.25 5.95###Coolie Day .022 135.25 2.98###Bandhani Day .044 138.45 6.09

Fixing chargesLabour:

###Stone mason (plane work) 2nd cl Day .044 141.6 6.23###Blacksmith 1 st class Day .006 151.5 .91###Beldar Day .022 135.25 2.98###Coolie Day .022 135.25 2.98###Bandhani Day .022 138.45 3.05###Bhishti Day .022 138.45 3.05###Scaffolding L.S. 2.73 1 2.73###Mortar for laying and pointing L.S. 8.06 1 8.06

Extra labour for lifting of materials upto floorV level0.01x1.50=0.015

###Coolie Day .015 135.25 2.03TOTAL 165.34Add 1% for water charges 1.65TOTAL. 166.99Add 15%”for contractor’s profit and overheads 25.05Cost of 10 cudm. 192.04Cost of 1 cum. 19 204.00Say 19 204.00

2497.2Extra for stone work sunk or moulded or sunk and mlded or carved in :7.21.1 : Triangular or Square or rectangular pillarsCodDescription Unit Quantity Rate Amount

Details of cost for 10 cudm.###Labour L.S. 11.7 1 11.7

TOTAL 11.7Add 1 % for water charges .12TOTAL 11.82Add. 15% for contractor’s profit and overheads 1.77Cost of 10 cudm. 13.59Cost of 1 cum. 1 359.00

Page 239: DAR_Vol_1

Say 1 359.00

7.2Extra for stone work sunk or moulded or sunk and moulded or carved in :7.21.2 : Circular or polygonal pillars -CodDescription Unit Quantity Rate Amount

Details of cost for 10 cudm.9999 Labour L.S. 33.15 1 33.15

TOTAL 33.15Add 1% for water charges .33TOTAL 33.48Add 15% for contractor’s profit and overheads 5.02Cost of 10 cudm. 38.5Cost of 1 cum. 3 850.00Say 3 850.00

7.22 : Extra for stone work sunk or moulded in cornices.CodDescription Unit Quantity Rate Amount

Details of cost for a cornice 30cm long 60cmdeep and 15cm projectionExtra labour:

###Stone mason (2nd class) Day .5 141.6 70.80114 Beldar Day .75 135.25 101.44

TOTAL 172.24Add 1% for water charges 1.72TOTAL 173.96Add 15% for contractor’s profit and overheads 26.09Cost of 30cm long 60cm deep and 15cm girth 200.05Cost of per metre per cm girth 8.89Say 8.9

7.2Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) includingpointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixtureof pigment matching the stone shade : (To be secured to the backing by means ofcramps which shall be paid for separately):

7.23.1 : Red sand stone - exposed face fine dressed with rough backing.7.23.1.1 : 70 mm thick.CodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm.Materials-Finished work = 70 cudm. +Add wastage @ 33.3% = 23.33 cudm.Total = 93.33 cudm.

250CodDescription Unit Quantity Rate Amount###Cost of stone 10 cudm 93.33 45 419.98###Carriage of stone @ 2.30kg/cud tonne .215 47.29 10.17###Extra for using white cement L.S. 1 26.91

Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day 1.35 141.6 191.16###Blacksmith 1st class Day .032 151.5 4.85###Beldar Day .224 135.25 30.3###Coolie Day .112 135.25 15.15

26.91

Page 240: DAR_Vol_1

oio Bandhani Day .224 138.45 31.01Fixing chargesLabour:

###Stone mason (for plain work) 2ndDay .448 141.6 63.44###Bandhani Day .336 138.45 46.52###Beldar Day .336 135.25 45.44###Coolie Day .336 135.25 45.44###Bhisti Day .336 138.45 46.52###Cutting sand stone slab by mech metre 4 6 24###Scaffolding L.S. 19.76 1 19.76###Mortar for laying and pointing cum .018 3 169.60 57.05

(Rate as per item No 3.8 of S.H. mortar)TOTAL 1 077.70Add 1% for water charges 10.78TOTAL 1 088.48Add 15% for contractor’s profit and overheads 163.27Cost of 1 sqm. 1,251.75Say 1 251.75

7.2Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) includingpointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with anadmixture of pigment matching the stone shade : (To be secured to the backing bymeans of cramps which shall be paid for separately):

7.23.1 : Red sand stone - exposed face fine dressed with rough backing.7.23.1.2:60 mm thick.CodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm.Materials-Finished work = 60 cudm.Add wastage @ 33.3% = 20 cudm.Total = 80 cudm.

###Cost of stone 10 cudm 80 45 360###Carriage of stone @ 2.30kg/cud tonne .184 47.29 8.7###Extra for using white cement L.S. 26.91 1 26.91

Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day 1.35 141.6 191.16###Blacksmith 1st class Day .032 151.5 4.85###Beldar Day .224 135.25 30.3###Coolie Day .112 135.25 15.15###Bandhani Day .224 138.45 31.01

Fixing chargesLabour:

###Stone mason (for plain work) 2ndDay .448 141.6 63.44O10Bandhani Day .336 138.45 46.52

251CodDescription Unit Quantity Rate Amount###Beldar Day .336 135.25 45.44###Coolie Day .336 135.25 45.44###Bhisti Day .336 138.45 46.52###Cutting sand stone slab by mech metre 4 6 24

Page 241: DAR_Vol_1

###Scaffolding L.S. 19.76 1 19.76###Mortar for laying and pointing cum .018 3 169.60 57.05

TOTAL 1 016.25Add 1% for water charges 10.16TOTAL 1 026.41Add 15% for contractor’s profit and overheads 153.96Cost of 1 sqm. 1 180.37Say 1 180.35

7.2Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) includingpointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with anadmixture of pigment matching the stone shade : (To be secured to the backing bymeans of cramps which shall be paid for separately):

7.23.1 : Red sand stone - exposed face fine dressed with rough backing.7.23.1.3:50 mm thick.CodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm.Materials-Finished work = 50 cudm.Add wastage @ 33.3% = 16.7 cudm.Total = 66.7 cudm.

###Cost of stone 10 cudm 66.7 45 300.15###Carriage of stone @ 2.30kg/cud tonne .153 47.29 7.24###Extra for using white cement L.S. 26.91 1 26.91

Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day 1.35 141.6 191.16###Blacksmith 1st class Day .032 151.5 4.85###Beldar Day .224 135.25 30.3###Coolie Day .112 135.25 15.15###Bandhani Day .224 138.45 31.01

Fixing chargesLabour:

###Stone mason (for plain work) 2ndDay .448 141.6 63.44###Bandhani Day .336 138.45 46.52###Beldar Day .336 135.25 45.44###Coolie Day .336 135.25 45.44###Bhisti Day .336 138.45 46.52###Cutting sand stone slab by mech metre 4 6 24###Scaffolding L.S. 19.76 1 19.76

Mortar for laying and pointing cum .018 3 169.60 57.05(Rate as per item No 3.8 fo SH- mortar)TOTAL 954.94Add 1 % for water charges 9.55TOTAL 964.49Add 15% for contractor’s profit and overheads 144.67Cost of 1 sqm. 1 109.16Say 1 109.15

2527.2Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled

with a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including

Page 242: DAR_Vol_1

pointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with anadmixture of pigment matching the stone shade : (To be secured to the backing bymeans of cramps which shall be paid for separately):

7.23.1 : Red sand stone - exposed face fine dressed with rough backing.7.23.1.4:40 mm thick.CodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm.Materials-Finished work = 40 cudm.Add wastage @ 33.3% = 13.33 cudm.Total = 53.33 cudm.

###Cost of stone 10 cudm 53.33 45 239.98###Carriage of stone @ 2.30kg/cud tonne .123 47.29 5.82###Extra for using white cement L.S. 26.91 2.6 26.91

Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day 1.35 141.6 191.16###Blacksmith 1st class Day .032 151.5 4.85###Beldar Day .224 135.25 30.3###Coolie Day .112 135.25 15.15###Bandhani Day .224 138.45 31.01

Fixing chargesLabour:

###Stone mason (for plain work) 2ndDay .448 141.6 63.44###Bandhani Day .336 138.45 46.52###Beldar Day .336 135.25 45.44###Coolie Day .336 135.25 45.44###Bhisti Day .336 138.45 46.52###Cutting sand stone slab by mech metre 4 6 24###Scaffolding L.S. 19.76 2.6 19.76

Mortar for laying and pointing cum .018 3 169.60 57.05(Rate as per item No 3.8 of SH - mortar)TOTAL 893.35Add 1% for water charges 8.93TOTAL 902.28Add 15% for contractor’s profit and overheads 135.34Cost of 1 sqm. 1 037.62Say 1 037.60

7.2Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) includingpointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with anadmixture of pigment matching the stone shade : (To be secured to the backing bymeans of cramps which shall be paid for separately):

7.23.1 : Red sand stone - exposed face fine dressed with rough backing.7.23.1.5:30 mm thick.CodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm.Materials-Finished work = 30 cudm.Add wastage @ 33.3% = 9.99cudm.Total = 39.99 cudm.

###Cost of stone 10 cudm 39.99 45 179.96

Page 243: DAR_Vol_1

253CodDescription Unit Quantity Rate Amount###Carriage of stone @ 2.30kg/cud tonne .092 47.29 4.35###Extra for using white cement L.S. 26.91 1 26.91

Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day 1.35 141.6 191.16###Blacksmith 1 st class Day .032 151.5 4.85###Beldar Day .224 135.25 30.3###Coolie Day .112 135.25 15.15###Bandhani Day .224 138.45 31.01

Fixing chargesLabour:

###Stone mason (for plain work) 2ndDay .448 141.6 63.44###Bandhani Day .336 138.45 46.52###Beldar Day .336 135.25 45.44###Coolie Day .336 135.25 45.44###Bhisti Day .336 138.45 46.52###Cutting sand stone slab by mechametre 4 6 24###Scaffolding L.S. 19.76 1 19.76

Mortar for laying and pointing cum .018 3 169.60 57.05(Rate as per item No 3.8 of SH. mortar)TOTAL 831.86Add 1% for water charges 8.32TOTAL 840.18Add 15% for contractor’s profit and overheads 126.03Cost of 1 sqm. 966.21Say 966.2

7.2Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) includingpointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with anadmixture of pigment matching the stone shade : (To be secured to the backing bymeans of cramps which shall be paid for separately):

7.23.2 : Red sand stone - Exposed face machine cut and table rubbed with rough backing.7.23.2.1:70 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm.Materials-Finished work = 70 cudm. +Add wastage @ 33.3% = 23.33 cudm.Total = 93.33 cudm.

###Cost of stone 10 cudm 93.33 45 419.98###Carriage of stone @ 2.30kg/cud tonne .215 47.29 10.17###Extra for using white cement L.S. 26.91 1 26.91

Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day 2.7 141.6 382.32###Blacksmith 1st class Day .064 151.5 9.7###Beldar Day .448 135.25 60.59###Coolie Day .224 135.25 30.3###Bandhani Day .448 138.45 62.03

Fixing chargesLabour:

###Stone mason (for plain work) 2ndDay .448 141.6 63.44###Bandhani Day .336 138.45 46.52###Beldar Day .336 135.25 45.44

Page 244: DAR_Vol_1

254CodDescription Unit Quantity Rate Amount###Coolie Day .336 135.25 45.44###Bhisti Day .336 138.45 46.52###Cutting sand stone slab by mechametre 4 6 24###Scaffolding L.S. 19.76 1 19.76

Mortar for laying and pointing cum .018 3 169.60 57.05(Rate as per item No. 3.8 of SH- mrtar)TOTAL 1 350.17Add 1% for water charges 13.5TOTAL 1 363.67Add 15 % for contractor’s profit and overheads 204.55Cost of 1 sqm. 1 568.22Say 1 568.20

7.2Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) includingpointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with anadmixture of pigment matching the stone shade : (To be secured to the backingby_ means of cramps which shall be paid for separately):

7.23.2 : Red sand stone - Exposed face machine cut and table rubbed with rough backing.7.23.2.2:60 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm.Materials-Finished work = 60 cudm.Add wastage @ 33.3% = 20 cudm.Total = 80 cudm.

###Cost of stone 10 cudm 80 45 360###Carriage of stone @ 2.30kg/cud tonne .184 47.29 8.7###Extra for using white cement L.S. 10.35 2.6 26.91

Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day 2.7 141.6 382.32###Blacksmith 1st class Day .064 151.5 9.7###Beldar Day .448 135.25 60.59###Coolie Day .224 135.25 30.3###Bandhani Day .448 138.45 62.03

Fixing chargesLabour:

###Stone mason (for plain work) 2ndDay .448 141.6 63.44###Bandhani Day .336 138.45 46.52###Beldar Day .336 135.25 45.44###Coolie Day .336 135.25 45.44###Bhisti Day .336 135.25 46.52###Cutting sand stone slab by mech metre 4 6 24###Scaffolding L.S. 19.76 1 9.76

Mortar for laying and pointing cum .018 3 169.60 57.05(Rate as per item No. 3.8 of SH- mortar)TOTAL 1 288.72Add 1 % for water charges 12.89TOTAL 1 301.61

Page 245: DAR_Vol_1

Add 15% for contractor’s profit and overheads 195.24Cost of 1 sqm. 1 496.85Say 1 496.85

2557.2Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled

with a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) includingpointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with anadmixture of pigment matching the stone shade : (To be secured to the backing bymeans of cramps which shall be paid for sepr

7.23.2 : Red sand stone - Exposed face machine cut and table rubbed with rough backing.7.23.2.3:50 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm.Materials-Finished work = 50 cudm. +Add wastage @ 33.3% = 16.7 cudm.Total = 66.7 cudm.

###Cost of stone 10 cudm 66.7 45 300.15###Carriage of stone @ 2.30kg/cudm tonne .153 47.29 7.24###Extra for using white cement L.S. 26.91 2.6 26.91

Dressing chargesLabour:

###Stone mason (plane work) 2nd class Day 2.7 141.6 382.32###Blacksmith 1st class Day .064 151.5 9.7###Beldar Day .448 135.25 60.59###Coolie Day .224 135.25 30.3###Bandhani Day .448 138.45 62.03

Fixing chargesLabour:

###Stone mason (for plain work) 2nd class Day .448 141.6 63.44###Bandhani Day .336 138.45 46.52###Beldar Day .336 135.25 45.44###Coolie Day .336 135.25 45.44###Bhisti Day .336 138.45 46.52###Cutting sand stone slab by mechanical devic metre 4 6 24###Scaffolding L.S. 19.76 1 19.76

Mortar for laying and pointing cum .018 3 169.60 57.05(Rate as per item No. 3.8 of SH- mortar)TOTAL 1 227.41Add 1% for water charges 12.27TOTAL 1 239.68Add 15% for contractor’s profit and overheads 185.95Cost of 1 sqm. 1 425.63Say 1 425.65

7.2Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thickcement mortar 1:3 (1 cement : 3 coarse sand) includingpointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with anadmixture of pigment matching the stone shade : (To be secured to the backing bymeans of cramps which shall be paid for separately):

7.23.2 : Red sand stone - Exposed face machine cut and table rubbed with rough backing.

Page 246: DAR_Vol_1

7.23.2.4: 40 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm.Materials-Finished work = 40 cudm. +Add wastage @ 33.3% = 13.33 cudm.Total = 53.33 cudm.

###Cost of stone 10 cudm 53.33 45 239.98

256CodDescription Unit Quantity Rate Amount###Carriage of stone @ 2.30kg/cudm tonne .123 47.29 5.82###Extra for using white cement L.S. 26.41 1 26.91

Dressing chargesLabour:

###Stone mason (plane work) 2nd class Day 2.7 141.6 382.32###Blacksmith 1st class Day .064 151.5 9.7###Beldar Day .448 135.25 60.59###Coolie Day .224 135.25 30.3###Bandhani Day .448 138.45 62.03

Fixing chargesLabour:

###Stone mason (for plain work) 2nd class Day .448 141.6 63.44###Bandhani Day .336 138.45 46.52###Beldar Day .336 135.25 45.44###Coolie Day .336 135.25 45.44###Bhisti Day .336 138.45 46.52###Cutting sand stone slab by mechanical devi metre 4 6 24###Scaffolding L.S. 19.76 1 19.76

Mortar for laying and pointing cum .018 3 169.60 57.05(Rate as per item No. 3.8 of SH- mortar)TOTAL 1 165.82Add 1 % for water charges 11.66TOTAL 1 177.48Add 1 5% for contractor’s profit and overheads 176.62Cost of 1 sqm. 1 354.10Say 1 354.10

7.2Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) includingpointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with anadmixture of pigment matching the stone shade : (To be secured to the backing bymeans of cramps which shall be paid for separately):

7.23.2 : Red sand stone - Exposed face machine cut and table rubbed with rough backing.7.23.2.5:30 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm.Materials-Finished work = 30 cudm. +Add wastage @ 33.3% - 9.99cudm.Total - 39.99 cudm.

###Cost of stone 10 cudm 39.99 45 179.96###Carriage of stone @ 2.30kg/cudm tonne .092 47.29 4.35

Page 247: DAR_Vol_1

###Extra for using white cement L.S. 26.91 1 26.91Dressing chargesLabour:

###Stone mason (plane work) 2nd class Day 2.7 141.6 382.32###Blacksmith 1st class Day .064 151.5 9.7###Beldar Day .448 135.25 60.59###Coolie Day .224 135.25 30.3###Bandhani Day .448 138.45 62.03

Fixing chargesLabour:

###Stone mason (for plain work) 2nd class Day .448 141.6 63.44###Bandhani Day .336 138.45 46.52###Beldar Day .336 135.25 45.44

257CodDescription Unit Quantity Rate Amount###Coolie Day .336 135.25 45.44###Bhisti Day .336 138.45 46.52###Cutting sand stone slab by mech metre 4 6 24###Scaffolding L.S. 19.76 1 19.76

Mortar for laying and pointing cum .018 3 169.60 57.05(Rate as per item No. 3.8 of SH- mortar)TOTAL 1 104.33Add 1 % for water charges 11.04TOTAL I 115.37Add 15% for contractor’s profit and overheads 167.31Cost of 1 sqm. 1 282.68Say 1 282.70

7.2Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) includingpointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with anadmixture of pigment matching the stone shade : (To be secured to the backing bymeans of cramps which shall be paid for separately):

7.23.3 : White sand stone - exposed face fine dressed with rough backing .7.23.3.1:70 mm thick.CodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm.Materials-Finished work = 70 cudm. +Add wastage @ 33.3% = 23.33 cudm.Total = 93.33 cudm.

###Cost of stone 10 cudm 93.33 50 466.65###Carriage of stone @ 2.30kg/cud tonne .215 47.29 10.17###Extra for using white cement L.S. 26.91 1 26.91

Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day 1.35 141.6 191.16###Blacksmith 1st class Day .032 151.5 4.85###Beldar Day .224 135.25 30.3###Coolie Day .112 135.25 15.15###Bandhani Day .224 138.45 31.01

Fixing charges

Page 248: DAR_Vol_1

Labour:###Stone mason (for plain work) 2ndDay .448 141.6 63.44###Bandhani Day .336 138.45 46.52###Beldar Day .336 135.25 45.44###Coolie Day .336 135.25 45.44###Bhisti Day .336 138.45 46.52###Cutting sand stone slab thick by metre 4 6 24

device###Scaffolding L.S. 19.76 1 19.76

Mortar for laying and pointing cum .018 3 169.60 57.05(Rate as per item No. 3.8 of SH- mortar)TOTAL 1 124.37Add 1% for water charges 11.24TOTAL 1 135.61Add 15% for contractor’s profit and overheads 170.34Cost of 1 sqm. 1 305.95Say 1 305.95

2587.2Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled

with a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) includingpointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with anadmixture of pigment matching the stone shade : (To be secured to the backing bymeans of cramps which shall be paid for separately):

7.23.3 : White sand stone - exposed face fine dressed with rough backing .7.23.3.2: 60 mm thick.CodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm.Materials-Finished work = 60 cudm.Add wastage @ 33.3% = 20 cudm.Total = 80 cudm.

###Cost of stone 10 cudm 80 50 400###Carriage of stone @ 2.30kg/cud tonne .184 47.29 8.7###Extra for using white cement L.S. 26.91 1 26.91

Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day 1.35 141.6 191.16###Blacksmith 1st class Day .032 151.5 4.85###Beldar Day .224 135.25 30.3###Coolie Day .112 135.25 15.15###Bandhani Day .224 138.45 31.01

Fixing chargesLabour:

###Stone mason (for plain work) 2ndDay .448 141.6 63.44C10Bandhani Day .336 138.45 46.52###Beldar Day .336 135.25 45.44###Coolie Day .336 135.25 45.44###Bhisti Day .336 138.45 46.52###Cutting sand stone slab thick by metre 4 6 24

device###Scaffolding L.S. 19.76 1 19.76

Page 249: DAR_Vol_1

Mortar for laying and pointing cum .018 3 169.60 57.05(Rate as per item No. 3.8 of SH- mortar)TOTAL 1 056.25Add 1 % for water charges 10.56TOTAL 1 066.81Add 15% for contractor’s profit and overheads 160.02Cost of 1 sqm. 1 226.83Say 1 226.85

7.2Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) includingpointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with anadmixture of pigment matching the stone shade : (To be secured to the backing bymeans of cramps which shall be paid for separately):

7.23.3 : White sand stone - exposed face fine dressed with rough backing .7.23.3.3:50 mm thick.CodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm.Materials-Finished work = 50 cudm.Add wastage @ 33.3% = 1,6.7 cudm.Total = 66.7 cudm.

259CodDescription Unit Quantity Rate Amount###Cost of stone 10 cudm 66.7 50 333.5###Carriage of stone @ 2.30 kg/cud tonne .153 47.29 7.24###Extra for using white cement L.S. 26.91 1 26.91

Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day 1.35 141.6 191.16###Blacksmith 1st class Day .032 151.5 4.85###Beldar Day .224 151.5 30.3###Coolie Day .112 135.25 15.15###Bandhani Day .224 138.45 31.01

Fixing chargesLabour:

###Stone mason (for plain work) 2ndDay .448 141.6 63.44###Bandhani Day .336 138.45 46.52###Beldar Day .336 135.25 45.44###Coolie Day .336 135.25 45.44###Bhisti Day .336 138.45 46.52###Cutting sand stone slab thick by metre 4 6 24

device###Scaffolding L.S. 19.76 1 19.76

Mortar for laying and pointing cum .018 3 169.60 57.05(Rate as per item No. 3.8 of SH- mortar)TOTAL 988.29Add 1 % for water charges 9.88TOTAL 998.17Add 15 % for contractor’s profit and overheads 149.73Cost of 1 sqm. 1 147.90Say 1 147.90

Page 250: DAR_Vol_1

7.2Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) includingpointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with anadmixture of pigment matching the stone shade : (To be secured to the backing bymeans of cramps which shall be paid for separately):

7.23.3 : White sand stone - exposed face fine dressed with rough backing .7.23.3.4:40 mm thick.CodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm.Materials-Finished work = 40 cudm.Add wastage @ 33.3% = 13.3 cudm.Total = 53.3 cudm.

###Cost of stone 10 cudm 53.3 50 266.5###Carriage of stone @ 2.30 kg/cud tonne .123 47.29 5.82###Extra for using white cement L.S. 26.91 1 26.91

Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day 1.35 141.6 191.16###Blacksmith 1st class Day .032 151.5 4.85###Beldar Day .224 135.25 30.3###Coolie Day .112 135.25 15.15###Bandhani Day .224 138.45 31.01

Fixing chargesLabour:

###Stone mason (for plain work) 2ndDay .448 141.6 63.44

260CodDescription Unit Quantity Rate Amount###Bandhani Day .336 138.45 46.52###Beldar Day .336 135.25 45.44###Coolie Day .336 135.25 45.44###Bhisti Day .336 138.45 46.52###Cutting sand stone slab thick by metre 4 6 24

device###Scaffolding L.S. 19.76 1 19.76

Mortar for laying and pointing cum .018 3 169.60 57.05(Rate as per item No. 3.8 of SH- mortar)TOTAL 919.87Add 1% for water charges 9.2TOTAL 929.07Add 10% for contractor’s profit and overheads 139.36Cost of 1 sqm. 1 068.43Say 1 068.45

7.2Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) includingpointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with anadmixture of pigment matching the stone shade : (To be secured to the backing bymeans of cramps which shall be paid for separately):

7.23.3 : White sand stone - exposed face fine dressed with rough backing .7.23.3.5: 30 mm thick.

Page 251: DAR_Vol_1

CodDescription Unit Quantity Rate AmountDetails of cost for 1 sqm.Materials-Finished work = 30 cudm. +Add wastage @ 33.3% = 9.99 cudm.Total = 39.99 cudm.

###Cost of stone 10 cudm 39.99 50 199.95###Carriage of stone @ 2.30 kg/cud tonne .092 47.29 4.35###Extra for using white cement L.S. 26.91 1 26.91

Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day 1.35 141.6 191.16###Blacksmith 1st class Day .032 151.5 4.85###Beldar Day .224 135.25 30.3###Coolie Day .112 135.25 15.15###Bandhani Day .224 138.45 31.01

Fixing chargesLabour:

###Stone mason (for plain work) 2ndDay .448 141.6 63.44###Bandhani Day .336 138.45 46.52###Beldar Day .336 135.25 45.44###Coolie Day .336 135.25 45.44###Bhisti Day .336 138.45 46.52###Cutting sand stone slab thick by metre 4 6 24

device###Scaffolding L.S. 19.76 1 19.76

Mortar for laying and pointing cum .018 3 169.60 57.05(Rate as per item No. 3.8 of SH.Mortar)TOTAL 851.85Add 1% for water charges 8.52TOTAL 860.37Add 15% for contractor’s profit and overheads 129.06Cost of 1 sqm. 989.43Say 989.45

2617.2Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled

with a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) includingpointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with anadmixture of pigment matching the stone shade : (To be secured to the backing bymeans of cramps which shall be paid for separately):

7.23.4 : White sand stone - Exposed face machine cut and table rubbed with rough backing.7.23.4.1:70 mm thick.CodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm.Materials-Finished work = 70 cudm.Add wastage @ 33.3% = 23,.33 cudm.Total = 93.33 cudm.

###Cost of stone 10 cudm 93.33 50 466.65###Carriage of stone @ 2.30kg/cud tonne .215 47.29 10.17

Page 252: DAR_Vol_1

###Extra for using white cement L.S. 26.91 1 26.91Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day 2.7 141.6 382.32###Blacksmith 1st class Day .064 151.5 9.7###Beldar Day .448 135.25 60.59###Coolie Day .224 135.25 30.3###Bandhani Day .448 138.45 62.03

Fixing chargesLabour:

###Stone mason (for plain work) 2ndDay .448 141.6 63.44###Bandhani Day .336 138.45 46.52###Beldar Day .336 135.25 45.44###Coolie Day .336 135.25 45.44###Bhisti Day .336 138.45 46.52###Cutting sand stone slab thick by mechanical

device metre 4 6 24###Scaffolding L.S. 19.76 1 19.76

Mortar for laying and pointing cum .018 3 169.60 57.05(Rate as per item No. 3.8 of SH.Mortar)TOTAL 1,396.84Add 1% for water charges 13.97TOTAL 1,410.81Add 15% for contractor’s profit and overheads 211.62Cost of 1 sqm. 1,622.43Say 1,622.45

### Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) includingpointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with anadmixture of pigment matching the stone shade : (To be secured to the backing bymeans of cramps which shall be paid for separately):

7.2White sand stone - Exposed face machine cut and table rubbed with rough backing.7.23.4.2 60 mm thick.CodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm.Materials-Finished work = 60 cudm.Add wastage @ 33.3% = 20 cudm.Total = 80 cudm.

262CodDescription Unit Quantity Rate Amount###Cost of stone 10 cudm 80 50 400###Carriage of stone @ 2.30kg/cud tonne .184 47.29 8.7###Extra for using white cement L.S. 20.91 1 26.91

Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day 2.7 141.6 382.32###Blacksmith 1st class Day .064 151.5 9.7###Beldar Day .448 135.25 60.59###Coolie Day .224 135.25 30.3###Bandhani Day .448 138.45 62.03

Page 253: DAR_Vol_1

Fixing chargesLabour:

###Stone mason (for plain work) 2ndDay .448 141.6 63.44###Bandhani Day .336 138.45 46.52###Beldar Day .336 135.25 45.44###Coolie Day .336 135.25 45.44###Bhisti Day .336 138.45 46.52###Cutting sand stone slab thick by metre 4 6 24

device###Scaffolding L.S. 19.76 1 19.76

(Rate as per item No. 3.8 of SH.Mortar)Mortar for laying and pointing cum .018 3,169.6 57.05TOTAL 1 328.72Add 1 % for water charges 13.29TOTAL 1 342.01Add 15% for contractor’s profit and overheads 201.3Cost of 1 sqm. 1 543.31Say 1 543.30

### Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) includingpointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with anadmixture of pigment matching the stone shade : (To be secured to the backing bymeans of cramps which shall be paid for separately):

7.2White sand stone - Exposed face machine cut and table rubbed with rough backing.7.23.4.3 50 mm thick.CodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm.Materials-Finished work = 50 cudm.Add wastage @ 33.3% = 16.7 cudm.Total = 66.7 cudm.

###Cost of stone 10 cudm 66.7 50 333.5###Carriage of stone @ 2.30 kg/cud tonne .153 47.29 7.24###Extra for using white cement L.S. 26.91 1 26.91

Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day 2.7 141.6 382.32###Blacksmith 1st class Day .064 151.5 9.7###Beldar Day .448 135.25 60.59###Coolie Day .224 135.25 30.3###Bandhani Day .448 138.45 62.03

Fixing chargesLabour:

263CodDescription Unit Quantity Rate Amount

###Stone mason (for plain work) 2ndDay .448 141.6 63.44###Bandhani Day .336 138.45 46.52###Beldar Day .336 135.25 45.44###Coolie Day .336 135.25 45.44###Bhisti Day .336 138.45 46.52

Page 254: DAR_Vol_1

###Cutting sand stone slab thick by metre 4 6 24device

###Scaffolding L.S. 19.76 1 19.76Mortar for laying and pointing cum .018 3,169.6 57.05(Rate as per item No. 3.8 of SH.Mortar)TOTAL 1,260.76Add 1% for water charges 12.61TOTAL 1 273.37Add 15% for contractor’s profit and overheads 191.01Cost of 1 sqm. 1 464.38Say 1 464.40

264### Stone work (machine cut edges) for wall lining etc. (veneer work) backing filled

with a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) includingpointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with anadmixture of pigment matching the stone shade : (To be secured to the backing bymeans of cramps which shall be paid for separately):

7.2White sand stone - Exposed face machine cut and table rubbed with rough backing.7.23.4.4 40 mm thick.CodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm.Materials-Finished work = 40 cudm.Add wastage @ 33.3% = 1,3.3 cudm.Total = 53.3 cudm.

###Cost of stone 10 cudm 53.3 50 266.5###Carriage of stone @ 2.30 kg/cud tonne .123 47.29 5.82###Extra for using white cement L.S. 26.91 1 26.91

Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day 2.7 141.6 382.32###Blacksmith 1st class Day .064 151.5 9.7###Beldar Day .448 135.25 60.59###Coolie Day 135.25 .224 30.3###Bandhani Day .448 138.45 62.03

Fixing chargesLabour:

###Stone mason (for plain work) 2ndDay .448 141.6 63.44###Bandhani Day .336 138.45 46.52###Beldar Day .336 135.25 45.44###Coolie Day .336 135.25 45.44###Bhisti Day .336 138.45 46.52###Cutting sand stone slab thick by metre 4 6 24

device###Cutting sand stone slab thick by metre 4 6 24

device###Scaffolding L.S. 19.76 1 19.76

Mortar for laying and pointing cum .018 3,169.6 57.05(Rate as per item No. 3.8 of SH.Mortar)TOTAL 1,216.34Add 1% for water charges 12.16

Page 255: DAR_Vol_1

TOTAL 1,228.5Add 15% for contractor’s profit and overheads 184.28Cost of 1 sqm. 1,412.78Say 1,412.8

### Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) includingpointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with anadmixture of pigment matching the stone shade : (To be secured to the backing bymeans of cramps which shall be paid for separately):

7.2White sand stone - Exposed face machine cut and table rubbed with rough backing.7.23.4.5 30 mm thick.CodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm.Materials-Finished work = 30 cudm.

265CodDescription Unit Quantity Rate Amount

Add wastage @ 33.3% = 9.99 cudm.Total = 39.99 cudm.

###Cost of stone 10 cudm 39.99 50 199.95###Carriage of stone @ 2.30 kg/cud tonne .092 47.29 4.35###Extra for using white cement L.S. 26.91 1 26.91

Dressing chargesLabour:

###Stone mason (plane work) 2nd cl Day 2.7 141.6 382.32###Blacksmith 1st class Day .064 151.5 9.7###Beldar Day .448 135.25 60.59###Coolie Day .224 135.25 30.3###Bandhani Day .448 138.45 62.03

Fixing chargesLabour:

###Stone mason (for plain work) 2ndDay .448 141.6 63.44###Bandhani Day .336 138.45 46.52###Beldar Day .336 135.25 45.44###Coolie Day .336 135.25 45.44###Bhisti Day .336 138.45 46.52###Cutting sand stone slab thick by metre 4 6 24

device###Scaffolding L.S. 19.76 1 19.76

Mortar for laying and pointing cum .018 3,169.6 57.05(Rate as per item No. 3.8 of SH.Mortar)TOTAL 1 124.32Add 1% for water charges 11.24TOTAL 1 135.56Add 15% for contractor’s profit and overheads 170.33Cost of 1 sqm. 1 305.89Say 1 305.90

7.2Extra for stone work (veneer work) curved on plan with a mean radius notexceeding 6 m.

CodDescription Unit Quantity Rate AmountDetails of cost for 10 cudm.

Page 256: DAR_Vol_1

###Labour and materials L.S. 8.97 1 8.97TOTAL 8.97Add 1% for water charges .09TOTAL 9.06Add l5% for contractor’s profit and overheads 1.36Cost of 10 cudm. 10.42Cost of 1 cum. 1,042Say 1,042

7.25 : Providing and fixing stainless steel cramps of required size and shape for anchoringstone wall lining to the backing or securing adjacent stones in stone wall lining incement mortar 1:2(1 cement: 2 coarse sand) including making the necessary chasesin stone and holes in walls wherever required.

CodDescription Unit Quantity Rate AmountDetails of cost for one crampMaterials:Stainless steel cramp12.4x10-6 x7850 = 0.097kgAdd wastage @ 10% = 0.010kg.= 0.107 kg.

266CodDescription Unit Quantity Rate Amount

###Stainless steel cramp kilogram .107 280 29.96###Carriage L.S. 3.9 1 3.9

CM. 1:2 (lcement :2 Coarse sand)cum .001 3,864.25 3.86(Rate as per this No. 3.7)

###Labour iorfixing m position L.S. 6.5 1 6.5TOTAL 44.22Add 1% for water charges .44TOTAL 44.66Add 15% for contractor’s profit and overheads 6.7Cost for 0.097 kg. 51.36Cost per kg 529.48Say 529.5

7.26 : Providing and fixing stone dowels 10x5x2.50 cm cut to double wedge shape as perdesign in cement mortar 1:2 (1 cement: 2 coarse sand) including making the necessarychases.

CodDescription Unit Quantity Rate AmountDetails of cost for one dowel

###Cost of stone including carriage L.S. 9.1 1 9.1Labour for dressing dowel cutting chase andfixing etc.

###Labour for dressing dowel cuttin L.S. 5.33 1 5.33fixing etc.CM. 1:2 (1cement: 2 coarse sand)cum .0001 3,864.25 3.86( Rate as per items No. 3.7)TOTAL 18.29Add 1% for water charges .18TOTAL 18.47Add 15% for contractor’s profit and overheads 2.77Cost of each dowel 21.24

Page 257: DAR_Vol_1

Say 21.25

7.27 : Providing and fixing copper pins 7.5 cm long 6 mm diameter for securing adjacentstones in stone wall lining in cement mortar 1:2(1 cement: 2 coarse sand) includingmaking the necessary chases.

CodDescription Unit Quantity Rate AmountDetails of cost for one copper pin-Materials-

###Copper pins 6 mm dia 7.5 cm lon each 1 7.5 7.5###Labour for making pin in to requ L.S. 3.9 1 3.9

and size, cutting chases in stone and fixing inpositionCM. 1:2 (1 cement: 2 coarscum .001 3 864.25 3.86

###Sundries including hire charges o cum .001 1 1.95machine etc.TOTAL 17.21Add 1 % for water charges .17TOTAL 17.38Add 15% for contractor’s profit and overheads 2.61Cost of one copper pin 19.99Say 20

2677.2Providing and fixing sloping chajja of stone 40 mm thick and upto 80 cm wide

beyond the wall as measured along the slope in cement mortar 1:4 (1 cement : 4coarse sand) with 12mm diameter anchoring steel bar 45 cm long fixed in eachstone and supported on and including with bricks cove of class designation 75 incement mortar 1:4 (1 cement : 4 coarse sand) including pointing in cement mortar1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching thestone shade:

7.28.1 : Red sand stone:7.28.1.1: With F.P.S BricksCodDescription Unit Quantity Rate Amount

Details of cost for a chajja 2.00 sqm. (finishedwork)Materials-Red sand stone slab 40mm (averagethickness)-Chisel dressed 80cm sloping lengthplus 20cm bearing Area = 2.5xl.00=2.50sqm.

###Cost of stone sqm 2.75 120 330###Carriage @ 2.3kg/cudm. tonne .253 47.29 11.96

Labour for dressing:0 1 Mason (2nd class) Day .5 141.6 70.8###Anchoring steel bars 12mm dia. quintal .02 3,100 62

nos. @ 0.80kg/m = 0.02q###Cutting threads and cost of nuts, L.S. 67.34 1 67.34

Mortar for pointing 1:2(1 Cementcum .009 3 959.25 35.63dust) (Rate as per items no. 3.12)

###Pigment L.S. 6.24 1 6.24###Extra cost of white cement L.S. 26.91 1 26.91

Labour:###Stone mason (Plain) 2nd class Day 1 141.6 141.6

Page 258: DAR_Vol_1

###Beldar Day 1.5 135.25 202.88###Scaffolding and sundries etc. L.S. 16.12 1 16.12

Brick cover support 4 courses with bricks ofclass designation 754x7+5+5=38cm girth 2.5m length=38cmx2.5m=95cm

###Cost of Brick cover support. L.S. 104 1 104Brick work in triangular gap above cover withbricks of class designation 7.5 in cementmortar 1:4-1/2x2.5x0.2x0.07=0.018cum.(B) Rate as per Item no. 6.1.2 SH:cum .018 2,121.75 38.19TOTAL 1 113.67Add for water charges @ 1% on all except 10.75(B)TOTAL 1 124.42Add for contractor’s profit and overheads @ 162.9315% on all except (B)Cost of 2 sqm. 1 287.35Cost of 1 sqm. 643.68Say 643.7

2687.2Providing and fixing sloping chajja of stone 40 mm thick and upto 80 cm wide

beyond the wall as measured along the slope in cement mortar 1:4 (1 cement : 4coarse sand) with 12mm diameter anchoring steel bar 45 cm long fixed in eachstone and supported on and including with bricks cove of class designation 75 incement mortar 1:4 (1 cement : 4 coarse sand) including pointing in cement mortar1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching thestone shade:

7.28.2 : White sand stone:7.28.2.1: With F.P.S. bricksCodDescription Unit Quantity Rate Amount

Details of cost for a chajja 2.00 sqm. (finishedwork)Materials-White sand stone slab 40mm (averagethickness)-Chisel dressed 80cm sloping lengthplus 20cm bearing Area = 2.5x1.00=2.50sqm.

###Cost of stone sqm 2.75 140 385###Carriage @ 2.3kg/cudm. tonne .253 47.29 11.96

Labour for dressing:###Mason (2nd class) Day .5 141.6 70.8###Anchoring steel bars 12mm dia. quintal .02 3,100 62

nos. @ 0.80kg/m = 0.02q###Cutting threads and cost of nuts, L.S. 25.9 1 67.34

Mortar for pointing 1:2 (1 Cemencum .009 3 959.25 35.63dust)

###Pigment L.S. 6.24 1 6.24###Extra cost of white cement L.S. 26.91 1 26.91

Labour:###Stone mason (Plain) 2nd class Day 1 141.6 141.6###Beldar Day 1.5 135.25 202.88

Page 259: DAR_Vol_1

###Scaffolding and sundries etc. L.S. 16.12 1 16.12Brick cover support 4 courses with bricks ofclass designation 754x7+5+5=38cm girth 2.5m length=38cmx2.5m=95cm

###Cost for Brick cover support . L.S. 104 1 104Brick work in triangular gap above cover withbricks of class designation 5 in cement mortar1:4-1 /2x2.5x0.2x0.07=0.018cum.(B) Rate as per Item no. 6.1.2 SH:cum .018 2,121.75 38.19TOTAL 1 168.67Add for water charges @ 1% on all except 11.3(B)TOTAL 1 179.97Addfor contractor’s profit and overheads @ 171.271 15% on all except (B)Cost of 2 sqm. 1 351.24Cost of 1 sqm. 675.62Say 675.6

2697.2Providing and fixing horizontal chajja of stone 40 mm thick and upto 80 cm

projection in cement mortar 1:4 (1 cement: 4 coarse sand) including pointing inwhite cement mortar 1:2 (1 white cement: 2 stone dust) with an admixture ofpigment matching the stone shade.:

7.29.1 : Red sand stoneCodDescription Unit Quantity Rate Amount

Details of cost for (2.5xO.75m) 1.875 sqm.Materials-Taking 2.5mx75cm projection + 15cm bearing= 2.5x0.9 = 2.25 sqm.

###Cost of stone sqm 2.25 120 270###Carriage @ 2.3kg/cudm. tonne .227 47.29 10.73

Labour for dressing:###Mason (2nd class) for stone workDay .45 141.6 63.72###Mortar for pointing 1:2 L.S. 53.82 1 53.82###Pigment L.S. 6.24 1 6.24###Extra cost of white cement L.S. 26.91 1 26.91

Labour:###Mason (2nd class) Day .6 141.6 84.96###Beldar Day .8 135.25 108.2###Scaffolding and sundries etc. L.S. 13.52 1 13.52

TOTAL 638.1Add for water charges @ 1% 6,38TOTAL 644.48Add for contractor’s profit and overheads @ 96.671,500%Cost of 1.875 sqm. 741.15Cost of 1 sqm. 395.28Say 395.3

7.2Providing and fixing horizontal chajja of stone 40 mm thick and upto 80 cmprojection in cement mortar 1:4 (1 cement: 4 coarse sand) including pointing in

Page 260: DAR_Vol_1

white cement mortar 1:2(1 white cement: 2 stone dust) with an admixture of pigmentmatching the stone shade.

7.29.2 : White sand stoneCodDescription Unit Quantity Rate Amount

Details of cost for (2.5xO.75m) 1.875 sqm.Materials-Taking 2.5mx75cm projection + 15cm bearing= 2.5x0.9 = 2.25 sqm.

###White sand stone slab 40 mm thi sqm 2.25 140 315(un-dressed)

###Carriage @ 2.3kg/cudm. tonne .227 47.29 10.73Labour for dressing:

###Mason (2nd class) for stone workDay .45 141.6 63.72###Mortar for pointing 1:2 L.S. 53.82 1 53.82###Pigment L.S. 6.24 1 6.24###Extra cost of white cement L.S. 26.91 1 26.91

Labour:###Mason (2nd class) Day .6 141.6 84.96###Beldar Day .8 135.25 108.2###Scaffolding and sundries etc. 1 L.S. 13.52 13.52

TOTAL 683.1Add for water charges @ 1 % 6.83TOTAL 689.93

270CodDescription Unit Quantity Rate Amount

Add for contractor’s profit and overheads @ 103.491,500%Cost of 1.875 sqm. 793.42Cost of 1 sqm. 423.16Say 423.15

7.30 : 30mm red sand stone sun-shade (chisel-dressed) supported on red sand stonebrackets, fixed in walls with cement mortar 1:4(1 cement: 4 coarse sand) includingfinishing complete.

CodDescription Unit Quantity Rate AmountDetail of cost for window 1.6m length and0.70m width = 1.12 sqm.Materials:Red stone slab (chisel dressed) 30mm averagethickness overall width 0.70+0.15=0.85metresTotal area = 1.6x0.85=1.36sqm.Red stone brackets (chisel dressed) 30mmaverage thickness over all width of brackets0.53+0.23=0.76m2x0.3x0.76=0.46Total 1.36+0.46 =1.82sqm.Add wastage @10% = 0.18sqm.

###Total = 2.00 sqm. sqm 2 97 194###carriage tonne .14 47.29 6.62###Cement mortar 1 :4 L.S. 13.52 1 13.52

Labour for dressing and fixing

Page 261: DAR_Vol_1

###Stone mason (plainy2nd class Day .86 141.6 121.78###Beldar Day .5 135.25 67.62

TOTAL 403.54Add for water charges @ 1 % 4.04TOTAL 407.58Add for contractor’s profit and overheads @1,500% 61.14Cost for 1.12 sqm. 468.72Cost of 1 sqm. 418.5Say 418.5

7.31 : Providing and fixing red sand stone brackets 55x22.5x45cm sunk and mouldedincluding providing and fixing with 4 Nos. gun metal cramp 25x6mm 30 cm long anddowel bars 7.5 cm long 6 mm dia as per design.

CodDescription Unit Quantity Rate AmountDetails of cost for 1 bracketQuantity of stone for 1 bracket1 x 55 x 22.5 x 45cm = 0.056cum or 56 cudm.Red sand stone = 56 cudm.Add wastage 10% = 5.6 cudm.Total =61.6 cudm.

###Cost of stone 10 cudm 61.6 45 277.2###Carriage @ 2.3kg/ cudm. tonne .14 47.29 6.62

Dressing chargesLABOUR

###Stone mason (plain work) 2nd claDay 1.7926 141.6 253.83###Blacksmith 1st class Day .037 151.5 5.61

271CodDescription Unit Quantity Rate Amount

###Beldar Day .271 135.25 36.65###Coolie Day .1355 135.25 18.33###Bandhani Day .271 138.45 37.52###Cost of Gun metal cramps 25x6 each 4 53 212

longFixing chargesLabour

###stone mason (plain work) 2nd claDay .2464 141.6 34.89###Blacksmith 1st class Day .0336 151.5 5.09###Beldar Day .1232 135.25 16.66###Coolie Day .1232 135.25 16.66###Bandhani Day .1232 138.45 17.06###Bhisti Day .1232 138.45 17.06###Scaffolding L.S. 15.29 1 15.29###Mortar for laying and pointing L.S. 45.14 1 45.14

Extra labour for ornamental finish :###Stone mason (ornamental) Day .95 151.5 143.92

TOTAL 1 159.53Add 1 % for water charges 11.6TOTAL 1 171.13Add 15% for contractor’ s profit and 175.67overheadsCost for 1 Bracket 1 346.80

Page 262: DAR_Vol_1

Say 1 346.80

7.32 : Stone work, plain in copings, cornices, string courses and plinth courses, upto 75mm thick in Cement mortar 1:6 (1 cement : 6 coarse sand) including pointing withwhite cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigmentmatching the stone shade.

7.32.1: Red sand stoneCodDescription Unit Quantity Rate Amount

Details of cost for cornices (30cm long 30cmdeep and 7.5cm project-iron) = 6.75cudm.Materials:Stone work plain ashlar cyclopean3x3x0.75 - 6.75 cudmRate as per item no 7.12.1.1 of S 1000 cudm 6.75 14,154 95.54Work

###(A) Extra for using white cement L.S. 5.33 1 5.33Extra labour for making the cornices

###(A) Stone mason (2nd class) Day .07 141.6 9.91###(A) Beldar Day .07 135.25 9.47

TOTAL 120.25(B) Add for water charges @ 1 % on ‘A’ .25TOTAL 120.5Add for contractor’s profit and overheads @ 3.7415% on (A+B)Cost of 6.75 cudm. 124.24Cost per cum. 18 405.93Say 18 406.00

2727.3Stone work, plain in copings, cornices, string courses and plinth courses, upto 75

mm thick in Cement mortar 1:6 (1 cement : 6 coarse sand) including pointing withwhite cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture ofpigment matching the stone shade.

7.32.2 : White sand stoneCodDescription Unit Quantity Rate Amount

Details of cost for cornices (30cm long 30cmdeep and 7.5cm project-iron) = 6.75cudm.Materials:Stone work plain ashlar cyclopean3x3x0.75 = 6.75 cudmRate as per item no 7.12.1.2 of 1000cudm 6.75 14,929 100.77

###(A) Extra for using white cement L.S. 5.33 1 5.33Extra labour for making the cornices

###(A) Stone mason (2nd class) Day .07 141.6 9.91###(A) Beldar Day .07 135.25 9.47

TOTAL 125.48Add for water charges @ 1 % on ‘A’ .25TOTAL 125.73Add for contractor’s profit and overheads @ 3.7415 % on (A+B)Cost of 6.75 cudm. 129.47Cost per cum. 19,180.74Say 19,181

Page 263: DAR_Vol_1

7.3Providing and fixing stone jali 40mm thick throughout in cement mortar 1:3 (1cement : 3 coarse sand) including pointing in white cement mortar 1:2(1 whitecement: 2 stone dust) with an admixture of pigment, matching the stone shade, jalislab without any chamfers etc.

7.33.1 : Red sand stoneCodDescription Unit Quantity Rate Amount

Details of cost for lsqm-Materials:Red sand stone slab 40mm=1.00 sqmAdd 10% wastage Total =0.10/1.10

###Red sand stone slab 40mm sqm 1.1 120 132###Carriage of stone slab tonne .101 47.29 4.78

Labour:For making, dressing and fixing

###Mason (plain) 2nd class Day 12.7 141.6 1 798.32###Beldar Day 8.45 135.25 1 142.86###Mortar and Sundries L.S. 80.73 1 80.73

TOTAL 3 158.69Add 1% for water charges 31.59TOTAL 3 190.28Add 15% for contractor’s profit and overheads 478.54Cost of 1 sqm. 3 668.82Say 3 668.80

2737.3Providing and fixing stone jali 40mm thick throughout in cement mortar 1:3 (1

cement : 3 coarse sand) including pointing in white cement mortar 1:2(1 whitecement: 2 stone dust) with an admixture of pigment, matching the stone shade, jalislab without any chamfers etc.

7.33.2 : White sand stoneCodDescription Unit Quantity Rate Amount

Details of cost for lsqm-Materials:White sandstone slaJx40mm = 1.00 sqmAdd 10% wastage Total =0.10/1.10 sqm

###White sand stone slab 40mm sqm 1.1 140 154###Carriage of stone slab tonne .101 47.29 4.78

Labour:For making, dressing and fixing

###Mason (plain) 2nd class Day 12.7 141.6 1 798.32###Beldar Day 8.45 135.25 1 142.86###Mortar and Sundries L.S. 80.73 1 80.73

TOTAL 3 180.69Add 1 % for water charges 31.81TOTAL 3 212.50Add 15 % for contractor’s profit and overheads 481.88Cost of 1 sqm. 3 694.38Say 3 694.40

7.34 : Extra for laying stone work in or under water and/or liquid mud including cost ofpumping or bailing out water and removing slush etc. complete.

CodDescription Unit Quantity Rate Amount

Page 264: DAR_Vol_1

Details of cost for depth of water 0.30m.Quantity of concrete = 14 cum.

11 pumping hours = 3 hrs. on 0.375 Day .375 300 112.5###Beldar for cleaning slush Day 4 135.25 541

TOTAL 653.5Add 1 % for water charges 6.54TOTAL 660.04Add for contractor’s profit and overheads 99.011,500%Cost of 14cum. per 0.30m depth 759.05Cost of cum. per m depth 180.73Say 180.75

7.35 : Extra for laying stone work in or under foul position.”CodDescription Unit Quantity Rate Amount

Details of cost for 1 cum.Extra labour due to slow progress-

###Mason 1st class Day .02 151.5 3.03###Mason 2nd class Day .02 141.6 2.03###Beldar Day .25 135.25 33.81###Coolie Day .15 135.25 20.29

TOTAL 59.96Add 1% for water charges .6TOTAL 60.56Add for contractor’s profit and overheads 9.081,500%Cost for 1 cum. 69.64Say 69.65

2747.36 : Wall lining butch work upto 10.00m height with Dholpur stone 40 mm thick rough

facing on the exposed surface with stone strips of minimum length 300 mm andrequired width including embedding every tenth layer and bottom most layer inmasonry or concrete after making necessary chases of size 75x75mm and byproviding layer of 75mm thick strips i/c 12mm thick bed of cement mortar 1:3(1 Cement : 3 coarse sand) i/c ruled pointing in cement mortar 1:2 (1 white cement :2 stone dust) with an admixture of pigment to match the shade of stone complete asper direction of Engineer-in-charge.

CodDescription Unit Quantity Rate AmountDetails of cost for lsqm.Dholpur stone 40mm thickWall face = l.OOsqm.Deduct for embed within 3x0.04x0.10=0.12 sqm= 0.88sqm.Add wastage 5% = 0.04sqm.Total = 0.92 sqm.

###Cost of stone sqm .92 140 128.875mm thick 3x0.04x1.0 = 0.12 sqm.Add wastage 5% = 0.01 sqm.Total =0.13 sqm.

###Cost of stone sqm .13 256 33.28Carriage of stone0.92x0.04 =0.0368 cum.

Page 265: DAR_Vol_1

0.13x0.075 =0.0100 cum.= 0.0468 cum. or 468 cudm.468 cudm @ 2.3 kg/cudm = 108 kg = 0.108tonne

###Carriage of stone tonne .108 47.29 5.11###Cutting stips of stone and giving metre 20 6 120

assuming 50mm thick strips 20x1.0 = 20metreMortar with coarse sand 1:3 for(a) stone backing 12mm thick = 0.0144 cum.(b) for fixing of stone = 0.40/25 - 0.0160 cum.Total = 0.0304 cum.Cement Mortar (Rate as per itemscum 0.0304 3 169.60 96.36Cutting chases and making good with mortarafter insurting stone etc.(A) Rate as per item no. 18.78 of metre 3 36.65 109.95Miscellaneous

###White cement and pigment for poL.S. 40.43 1 40.43Labour:

###Mason 1 st class Day .25 151.5 37.88###Mason 2nd class Day .25 141.6 35.4###Beldar Day .5 135.25 67.62###Bhisti Day .03 138.45 4.15###Sundries and scaffolding brushes L.S. 26.91 1 26.91

TOTAL 705.89Add for water charges @ 1% on all except ‘A’ 5.96TOTAL 711.85Add for contractor’s profit and overheads @ 90.2815 % on all except ‘A’Cost of 1 sqm. 802.13Say 802.15

2757.3Stone work ( machine cut edges) for wall lining upto 10 m height etc. (Veneer

work) backing filled with a grout of 12mm thick cement mortar 1:3 (1 Cement : 3coarse sand) and jointed with Cement mortar 1:2 (1 cement : 2 stone dust) includingrubbing and polishing complete. (To be secured to the backing by means of crampswhich shall be paid for separately)

7.37.1: Kota stone slabs exposed face dressed and rubbed.7.37.1.1: 25 mm thick.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials :25mm thids. kota stoneslabs = 10 sqm.Add 15% wistage = 1.50 sqmTotal 11.50 sqm

###Kotastone slab 25mm thick. Sqm. 11.5 150 1,725###Carriage tonne .67 47.29 31.68

Cement Mortar 1 : 3 cum .144 3,169.6 456.42(Rate as per item 3.8 of S.H. mortar)

###Cement mortar for pointing. L.S. 40.43 1 40.43

Page 266: DAR_Vol_1

Labour:###Mason 2nd class Day 6.5 141.6 920.4###Beldar Day 6.5 135.25 879.12###Coolie Day 4.33 135.25 581.57###Beldar for rubbing and polishing (Day 10.8 138.45 1,495.26###Sundries L.S. 111.54 1 111.54

TOTAL 6,241.42Add 1% for water charges 62.41TOTAL 6,303.83Add 15% for contractor’s profit and overheads 945.57Cost for 10 sqm. 7,249.4Cost of 1 sqm. 724.94Say 724.95

276### Stone tile work for wall lining upto 10 m height with special adhesive over 12mm

thick bed of cement mortar 1:3 (1 cement : 3 coarse sand) including pointing inwhite cement with an admixture of pigment to match the stone shade.

7.38mm thick (mirror polished and machine cut edge)7.38.1.1 Granite stone of any colour and shade.CodDescription Unit Quantity Rate Amount

Details of cost for lOsqm.Materials :ton thickgranite stone tile =10.OOsqm.+Add 2.5% westage = 0.25 sqm

###Ttofal =210 sqm 10.25 555 5,688.75###Carriage of granite tiles L.S. 40.04 2.6 40.04

Cement mortar 1:3 cum .14 3,169.6 443.74(Rate as per item 3.8 of S.H. mortar)

###Cement slurry @ 3.3 kg/sqm. tonne .033 4,500 148.5###Mortar for pointing in white ce L.S. 25.74 10 25.74

Labour for placing and fixing :###Mason 1st class Day 7.7 151.5 1,166.55

Beldar Day 7.7 135.25 1,041.42###Granular sand particles mixed witL.S. 260 1 260

be pasted on each side to form interlockingarrangement with cement plaster

###Sundries L.S. 171.6 1 171.6TOTAL 8,986.34Add 1 % for water charges 89.86TOTAL 9,076.2Add 15% for contractor’s profit and overheads 1,361.43Cost for 10 sqm. 10,437.63Cost of 1 sqm. 1,043.76Say 1,043.75

7.3Stone tile work for wall lining upto 10 m height with special adhesive over 12mmthick bed of cement mortar 1:3 (1 cement : 3 coarse sand) including pointing inwhite cement with an admixture of pigment to match the stone shade.

7.38.1: 8mm thick (mirror polished and machine cut edge)7.38.1.2:Raj Nagar plain white marble/ Udaipur green marble/ Zebra black marble,CodDescription Unit Quantity Rate Amount

Page 267: DAR_Vol_1

Details of cost for 10 sqm.Materials :8mm thick Raj Nagar white stone tile =10.00sqm.+Add 2.5% westage = 0.25 sqm

###Total = 10.25sqm. sqm 10.25 430 4 407.50###Carriage of Raj Nagar white stoneL.S. 40.04 1 40.04

Cement mortar 1:3 cum 443.74 3,169.6(Rate as per item 3.8 of S.H. mortar)

###Cement slurry @ 3.3 kg/sqm. tonne .033 4,500 148.5###Mortar for pointing in white ce L.S. 25.74 1 25.74

Labour for placing and fixing :###Mason 1st class Day 7.7 151.5 1 166.55###Beldar Day 7.7 135.25 1 041.42###Granular sand particles mixed witL.S. 260 1 260

be pasted on each side to form interlockingarrangement with cement plaster

###Sundries L.S. 171.6 1 171.6

277CodDescriptio Unit Quantity Rate Amount

TOTAL 7 705.09Add 1 % for water charges 77.05TOTAL 7 782.14Add 15%for contractor’s profit and overhea 1 167.32Cost for 10 sqm. 8 949.46Cost of 1 sqm. 894.95Say 894.95

### Extra for stone work for wall lining on exterior walls of height more than 10 m fromground level for every additional height of 3 m or part there of.

CodDescriptio Unit Quantity Rate AmountANALYSIS SAME AS ITEM NO 13.114Detail of cost for 10 sqmMATERIALS

###Scaffolding L.S. 215.28 1 215.2811 Hire charg Day .375 300 112.5

4000 it/per hour###Mason 1st Day .3 151.5 45.45###Belder Day .3 151.5 45.45###Bhisti Day .15 138.45 20.77###Sundries L.S. 28.6 1 28.6

TOTAL 350.67Add 1 % for water charges 3.51TOTAL 354.18Add 15% for contractor’s profit and overheads 53.13Cost of 10.00 sqm 4.7.31Cost of 1.00 sqm 40.73Say 40.75

### Providing and fixing dry cladding upto 10 metre heights with 30mm thick gang sawcut stone with (machine cut edges) of uniform colour and size upto lmxlm, fixed tostructural steel frame work and/ or with the help of cramps, pins etc. and sealingthe joints with approved weather sealant as per Architectural drawing and

Page 268: DAR_Vol_1

direction of Engineer-in-charge. (The steel frame work, stainless steel cramps andpins etc. shall be paid for separately.)

7.40.1 Red sand stone.CodDescriptio Unit Quantity Rate Amount

Details of cost for 3 sqm.Materials-Red sand stoge = 3 X1.00 sqm = 3.00 sqmAdd wastage 25% = 0.75 sqm total=3.75Add 20% wastage infixing due to broken edge= 0.60 sqmTotal = 4.35 sqm

###Red sand s sqm 4.35 325 ######Cutting marble or sand 10 6 60

thick by mechanical device16 Carriage o tonne .215 47.29 10.17###backing ro L.S. 30.68 1. 00 30.68###Fixing incl L.S. 153.4 1. 00 153.4###Double scaL.S. 204.75 1 204.75###Mason (for Day 2 151.5 303

278CodDescription Unit Quantity Rate Amount###Beldar Day 4 135.25 541

Labour for lifting stone###Beldar Day 1 135.25 135.25###Silicon gun/ pump etc. L.S. 204.75 1 204.75

Labour for sealing###Fitter (grade 1) Day .25 151.5 37.88###Beldar Day .5 135.25 67.62###Sundries L.S. 204.75 1 204.75###Rubing and polishing vertical su L.S. 51.22 1 51.22

claddingTOTAL 3 418.22Add 1% for water charges 34.18TOTAL 3 452.40Add 15% for contractor’s profit and overheads 517.86Cost of 3 sqm 3 970.26Cost of 1 sqm 1 323.42Say 1 323.40

### Providing and fixing dry cladding upto 10 metre heights with 30mm thick gang saw cut stonewith (machine cut edges) of uniform colour and size upto lmxlm, fixed to structural steelframe work and/ or with the help of cramps, pins etc. and sealing the joints withapproved weather sealant as per Architectural drawing and direction of Engineer-in-charge. (The steel frame work, stainless steel cramps and pins etc. shall be paid forseparately.)

7.40.2 White sand stoneCodDescription Unit Quantity Rate Amount

Details of cost for 3 sqm.Materials-White sand stone = 3.00sqmAdd wastage 25% = 0.75 sqm =3.75 sqm.Add 20% wastage infixing due to broken edge

Page 269: DAR_Vol_1

= 0.60 sqmTotal = 4.35 sqm

###White sand stone gang saw cut 3 sqm 4.35 360 1 566.00###Cutting marble or sand stone sl metre 10 6 60

thick by mechanical deviceCarriage of stone @ 2.30kg/cud tonne .215 47.29 10.17

###backing rod L.S. 30.68 1 30.68###Fixing including weather sealant L.S. 153.4 1 153.4###Double scafolding L.S. 204.75 1 204.75###Mason (for ornamental stone worDay 2 151.5 303###Beldar Day 4 135.25 541

Labour for lifting stone###Beldar Day 1 135.25 135.25###Silicon gun/ pump etc. L.S. 204.75 1 204.75

Labour for sealing###Fitter (grade 1) Day .25 151.5 37.88###Beldar Day .5 135.25 67.62###Sundries L.S. 204.75 1 204.75###Rubing and polishing vertical su L.S 51.22 1 51.22

claddingTOTAL 3 570.47Add 1 % for water charges 35.7TOTAL 3 606.17Add 15% for contractor’s profit and overheads 540.93Cost of 3 sqm 4 147.10Cost of 1 sqm 1 382.37Say 1 382.35

279

### Providing and fixing structural steel frame (for dry cladding with 30 mm thick gangsaw cut with machine cut edges sand stone) on walls at all heights using M.S. square/rectangular tube in the required pattern as per architectural drawing including costof cutting, bending, welding etc. The frame work shall be supported in wall with thehelp of MS brackets/ lugs of angle iron/ flats etc. which shall be welded to the frameand embedded in brick wall with cement concrete block 1:2:4 (1 cement :2 coarsesand :4 graded stone aggregate 20mm nominal size) of size 300x230x300mmincluding cost of necessary centring and shuttering and with approved expansionhold fasteners on CC/RCC surface including drilling necessary holes. Approvedcramps/ pins etc. shall be welded to the frame work to support stone cladding thesteel work will be given a priming coat of “ZINC” primer as approved by Engineer-in-charge and painted with two or more coats of epoxy paint (Shop drawings shallbe submitted by the contractor to the Engineer-in-charge for approval beforeexecution). The frame work shall be fixed in true horizontal & vertical lines/planes.(Only structural steel frame work shall be measured for the purpose of payment,stainless steel cramps shall be paid for separately and nothing extra shall be paid.)

CodDescription Unit Quantity Rate Amount

Details of cost for 9 sqm or 88.79 kg.

Page 270: DAR_Vol_1

M.S. tube 50x25x18mmvertical=4x3.0=12.00m.Vertical=3x4x0.93=11.16mTotal= 23.16m.Add 10% wastage = 2.32Total 25.48 [email protected] kg/m=51.47 kg

###Mild steel tubes Kilogram 51.47 38 1,955.86Angle iron 50x50x6mm16x0.60=9.6016x0.15=2.40Total= 12.00Add 10% wastage = 1.20mTotal= [email protected]/m=46.20kg or 0.462 q23.50 kg/m=46.20kg.

###Cost of angle iron quintal .462 3,100 1,432.2Cement concrete 1:2:4= 16x0.15x0.15x0.15=0.054 cum(Rate as per item no 4.1.3 of SH cum .054 3257.45 175.90 (A)Work)Making holes in brick work=16nos.Labour

###Mason 1st class Day .26 151.5 39.39###Mason 2nd class Day .26 141.6 36.82###Beldar Day 2 135.25 270.5

Welding for frame welding16x(2.5+5+2.5+5) = 240 cmFor hold fast 16x20cm = 320cmTotal =560cm

###Welding by electric plant cum 560 1 560LABOUR

###Blacksmith 1 st class Day 1.34 151.5 203.01###Bandhani Day .67 138.45 92.76###Beldar Day 4.92 135.25 665.43

280CodDescription Unit Quantity Rate Amount###Sundries L.S. 31.05 2.6 80.73

Painting with epoxy paint over and includingpriming coat area 22.80x0.15 = 3.4212x0.2=2.40Total = 5.82sqm(Rate as per Item no. 13.52.1 of sqm 5.82 75.25 437.96(A)Finishing.)

###For labour scaffocaling etc L.S. 31.05 2.6 80.73Total 6,257.65Add 1 % for water charges except on (A) 56.44Total 6,314.09Add 15% for contractor’s profit and overheads 855.03except on (A)Cost for 88.79 kg 7,169.12Cost for 1 kg 80.74Say 80.75

### Providing and fixing adjustable stainless steel cramps of approved quality and of

Page 271: DAR_Vol_1

required shape and size adjustable with stainless steel nuts bolts and washer (totalweight not less than 260 gms) for dry stone cladding fixed on frame work at suitablelocation including making necessary recesses in stone slab, drilling required holesetc complete as per direction of the Engineer-in-charge.

CodDescription Unit Quantity Rate AmountDetails of cost for 10 Nos.

###Stainless steel cramps with nuts,each 10 200 2,000washer for dry stone cladding .LABOURfor making holes, recesses etc. and fixingof stainless stul cramps

###Blacksmith 2nd class Day .1 141.6 14.16###Mason 2nd class Day 1 141.6 141.6###Beldar Day 1.1 135.25 148.78###Scaffolding, hire charges of drill L.S. 20.8 1 20.8###Sundries L.S. 20.8 1 20.8

Total 2,346.14Add 1% for water charges. 23.46Total 2,369.6Add 10% for contractor’s profit and overheads 355.44charges.Cost for 10 Nos. 2,725.04Cost for 1 Nos. 272.5Say 272.5

281

SUB HEAD : 8.0

MARBLE WORK

Page 272: DAR_Vol_1

283### Marble work gang saw cut (polished and machine cut) of thickness 18mm for wall

lining (veneer work) in cement mortar 1:3 (1 cement : 3 coarse sand) includingpointing with white cement mortar 1:2 (1 white cement : 2 marble dust) with anadmixture of pigment to match the marble shade: (To be secured to the backing bymeans of cramps, which shall be paid for separately).

8.1Raj Nagar Plain white marble/ Udaipur green marble/ Zebra black marble.8.1.1.1 Area of slab upto 0.50 sqmCodDescription Unit Quantity Rate Amount

Details of cost for 0.50 sqm.Finished work = 0.50sqm.+Add for wastage @ 20% = 0.10 sqm.Total = 0.60 sqm.

###Raj Nagar plain white marble (po sqm .6 540 324machine cut) 18 mm thick upto 0.50sqm

###Carriage of marble tonne .03 47.29 1.42Cement mortar 1:3 (1 Cement: 3 cum .008 3,169.6 25.36Rate as per item No. 3.8White 1:2 (1 white cement: 2 cum .0012 7,590.25 9.11marble dust)( Rate as per item No.3.15 )Labour:For fixing

###Stone Mason (ornamental) Day .335 151.50 50.75###Bandhani Day .335 138.45 46.38###Beldar Day .335 135.25 45.31###Coolie Day .335 135.25 45.310 1 Bhishti Day .335 138.45 46.38###Mate Day .165 138.45 22.84###Blacksmith 1st class Day .135 151.5 20.45###Scaffolding L.S. 13.39 1 13.39

TOTAL 650.7Add 1 % for water charges 6.51TOTAL 657.21Add 15% for contractor’s profit and overheads 98.58Cost for 0.50 sqm. 755.79Cost for one sqm. 1 511.58Say 1 511.60

### Marble work gang saw cut (polished and machine cut) of thickness 18mm for walllining (veneer work) in cement mortar 1:3 (1 cement : 3 coarse sand) including pointingwith white cement mortar 1:2 (1 white cement : 2 marble dust) with an admixture ofpigment to match the marble shade: (To be secured to the backing by means ofcramps, which shall be paid for separately).

8.1Raj Nagar Plain white marble/ Udaipur green marble/ Zebra black marble.8.1.1.2 Area of slab over 0.50 sqmCodDescription Unit Quantity Rate Amount

Details of cost for 1.00 sqm.Finished work = 1.00sqm.+Add for wastage @ 20% = 0.20 sqm.Total = 1.20sqm.

Page 273: DAR_Vol_1

###Raj Nagar plain white marble (Po sqm 1.2 580 696machine cut) 18 mm thick above 0.50 sqm

###Carriage of marble tonne .06 47.29 2.84###Cement mortar 1:3 (Cement: 3 C cum .0144 3,169.6 45.64

(Rate as per item No. 3.8)

284CodDescription Unit Quantity Rate Amount

white’cement mortar 1:2 (1 whit cum .0025 7,590.25 18.98marble dust) (Rate as per item No. 3.13)Labour:For fixing

###Stone Mason (ornamental) Day .67 151.5 101.51###Bandhani Day .67 138.45 92.76###Beldar Day .67 135.25 90.62###Coolie Day .67 135.25 90.62###Bhishti Day .67 138.45 92.760 1 Mate Day .33 138.45 45.69###Blacksmith 1st class Day .27 151.5 40.9###Scaffolding L.S. 26.91 1 26.91

TOTAL 1,345.23Add 1% for water charges 13.45 TOTAL 1,358.68Add 15% for contractor’s profit and overheads 203.8Cost for 1.00 sqm 1,562.48Say 1,562.5

### Providing and fixing 18mm thick gang saw cut mirror polished (premoulded andprepolished) machine cut for kitchen platforms, vanity counters ,window sills , faciasand similar locations of required size of approved shade, colour and texture laidover 20mm thick base cement mortar 1:4 (1 cement : 4 coarse sand) with jointstreated with white cement, mixed with matching pigment, epoxy touch ups, includingrubbing, curing moulding and polishing to edge to give high gloss finish etc. completeat all levels.

8.2Raj Nagar Plain white marble/ Udaipur green marble/ Zebra black marble.8.2.1.1 Area of slab upto 0.50 sqm.CodDescription Unit Quantity Rate Amount

Details of cost for 0.50 sqm.Mirror polished Abu plain white = 0.50sqm.+Wastage 5% 0.025 sqm. = 0.525 sqm

7452 Raj nagar plain white marble sqm .525 540 283.5machine cut) 18 rnm. thick upto 0.50 sqmCement morter 1:4(1 cement: 4 cum .012 2,578.45 30.94sand) (Rate as per item No. 3.9)Labour:

###Mason (brick layer) 1st class Day .7 151.5 106.05###Beldar Day .325 135.25 43.96###Coolie Day .325 135.25 43.96###Moulding and edge polishing L.S. 39 1 39###Sundries apoxy resin & cutting mL.S. 16.25 1 16.25

TOTAL 563.66Add 1% for water charges 5.64TOTAL 569.3

Page 274: DAR_Vol_1

Add 15% for contractor’s profit and overheads 85.4Cost for 0.50 sqm. 654.7Cost for 1.00 sqm 1,309.4Say 1,309.4

285### Providing and fixing 18mm thick gang saw cut mirror polished (premoulded and

prepolished) machine cut for kitchen platforms, vanity counters ,window sills , faciasand similar locations of required size of approved shade, colour and texture laidover 20mm thick base cement mortar 1:4 (1 cement : 4 coarse sand) with jointstreated with white cement, mixed with matching pigment, epoxy touch ups, includingrubbing, curing moulding and polishing to edge to give high gloss finish etc. completeat all levels.

8.2Raj Nagar Plain white marble/ Udaipur green marble/ Zebra black marble.8.2.1.2 Area of slab over 0.50 sqm.CodDescription Unit Quantity Rate Amount

Details of cost for 1.00 sqm.Mirror polished Abu plain white = 1.00sqm.+Wastage 5% 0.10 sqm.=1.05 sqm

###Raj nagar plain white marble (po sqm 1.05 580 609machine cut )18 mm thick above 0.50 sqmCement mortar 1:4(1 cement: 4 coarsesand).(Rate as per item No. 3.9) cum .024 2,578.45 61.88Labour:

st ###Mason (brick layer) 1 class Day 1.4 151.5 212.1###Beldar Day .65 135.25 87.91###Coolie Day .65 135.25 87.91###Moulding and edge polishing L.S. 78 1 78###Sundries apoxy resin & cutting mL.S. 32.5 1 32.5

TOTAL 1,169.3Add 1% for water charges 11.69TOTAL 1,180.99Add 15% for contractor’s profit and overheads 177.15Cost for.1.00 sqm. 1,358.14Say 1,358.15

### Providing and fixing 18mm thick gang saw cut mirror polished (premoulded andprepolished) machine cut for kitchen platforms, vanity counters ,window sills , faciasand similar locations of required size of approved shade, colour and texture laidover 20mm thick base cement mortar 1:4 (1 cement : 4 coarse sand) with jointstreated with white cement, mixed with matching pigment, epoxy touch ups, includingrubbing, curing moulding and polishing to edge to give high gloss finish etc. completeat all levels.

8.2Granite of any colour and shade8.2.2.1 Area of slab upto 0.50 sqmCodDescription Unit Quantity Rate Amount

Details of cost for 0.50 sqm.Mirror polished granite= 0.50 sqm.+Wastage5% 0.025 sqm.= 0.525 sqm

Page 275: DAR_Vol_1

###Granite 18 mm thick slab, upto sqm .525 1,500 787.5awise)Cement mortar 1:4 (1 cement: 4 cum .012 2,578.45 30.94sand). (Rate as per item No. 3.9)Labour:

###Mason (brick layer) 1st class Day .7 151.5 106.05###Beldar Day .325 135.25 43.96###Coolie Day .325 135.25 43.96###Moulding and edge polishing L.S. 39 1 39

286CodDescription Unit Quantity Rate Amount###Sundries apoxy resin & cutting mL.S. 16.25 1 16.25

TOTAL 1,067.66Add 1% for water charges 10.68TOTAL 1,078.34Add 15% for contractor’s profit and overheads 161.75Cost for 0.50 sqm. 1,240.09Cost for 1.00 sqm 2,480.18Say 2,480.2

### Providing and fixing 18mm thick gang saw cut mirror polished (premoulded andprepolished) machine cut for kitchen platforms, vanity counters ,window sills , faciasand similar locations of required size of approved shade, colour and texture laidover 20mm thick base cement mortar 1:4 (1 cement : 4 coarse sand) with jointstreated with white cement, mixed with matching pigment, epoxy touch ups, includingrubbing, curing moulding and polishing to edge to give high gloss finish etc. completeat all levels.

8.2Granite of any colour and shade8.2.2.2 Area of slab over 0.50 sqm.CodDescription Unit Quantity Rate Amount

Details of cost for 2.00 sqm.Mirror polished granite= 2.00 sqm.+Wastage5%0.10sqm.= 2.10sqm

###Granite 18 mm thick slab, above sqm 2.1 1 615.00 3 391.50Cement montar 1:4 (1 cement : cum .027 2,578.45 69.62sand). (Rate as per item No. 3.9)Labour:

###Mason (brick layer) 1st class Day 2.8 151.5 424.2###Beldar Day 1.3 135.25 175.82###Coolie Day 1.3 135.25 175.82###Moulding and edge polishing L.S. 39 1 78###Sundries apoxy resin & cutting mL.S. 16.25 1 65

TOTAL 4,379.96Add 1 % for water charges 43.8TOTAL 4,423.76Add 15% for contractor’s profit and overheads 663.56Cost for 2.00 sqm. 5,087.32Cost for 1.00 sqm 2,543.66Say 2,543.65

### Extra for providing edge moulding to 18mm thick marble stone counters, Vanitiesetc. including machine polishing to edge to give high gloss finish etc. complete as

Page 276: DAR_Vol_1

per design approved by Engineer-in-Charge.8.3Marble workCodDescription Unit Quantity Rate Amount

Details of cost for 10.00 mLabour:

19 Hand Grinder for-mirror-polish Day 1.5 100 150###Beldar Day 3.5 135.25 270.5###Sundries Blades & Polished etc. L.S. 78 1 78

TOTAL 498.5Add 1 % for water charges 4.99TOTAL 503.49

287CodDescription Unit Quantity Rate Amount

Add 15% for contractor’s profit and overheads 75.52Cost for 10 metre 579.01Cost per metre 57.9Say 57.9

### Extra for providing edge moulding to 18mm thick marble stone counters, Vanitiesetc. including machine polishing to edge to give high gloss finish etc. complete asper design approved by Engineer-in-Charge.

8.3Granite work.

CodDescription Unit Quantity Rate AmountDetails of cost for 10.00 mLabour:

19 Hand Grinder for mirror polish Day 2.5 100 250###Beldar Day 3.5 135.25 117###Sundries Blades & Polish etc. L.S. 117 1 117

TOTAL 840.38Add 1 % for water charges 8.4TOTAL 848.78Add 15% for contractor’s profit and overheads 127.32Cost for 10 metre 976.1Cost per metre 97.61Say 97.6

### Extra for fixing marble /granite stone over and above corresponding basic item, infacia and drops of width upto 150 mm with epoxy resin based adhesive includingcleaning etc. complete.

CodDescription Unit Quantity Rate AmountDetails of cost for facia 1.5m long and 0.15mwideLabour:

###Mason 1st class Day .3 151.5 45.45###Beldar Day .3 135.25 40.57###Scaffolding, expoxy etc. L.S. 39 1 39

Cement mortar 1:4 (1 Cement: 4 cum .005 2,578.45 12.89(Rate as per item No. 3.9)1.5x0.15x0.02 = 0.005 cum.TOTAL 137.91Add 1 % for water charges 1.38TOTAL 139.29

Page 277: DAR_Vol_1

Add 15% for contractor’s profit and overheads 20.89Cost for 10 metre 160.18Cost per metre 106.79Say 106.8

### Extra for providing opening of required size & shape for wash basins/ kitchen sinkin kitchen platform, vanity counters and similar location in marble/Granite/stonework including necessary holes for pillar taps etc. including rubbing and polishingof cut edges etc. complete.

CodDescription Unit Quantity Rate AmountDetails of cost for providing one opening ofrequired size and shape.Labour:

###Mason (for ornamental stone worDay .4 151.5 60.6

288CodDescription Unit Quantity Rate Amount###Beldar Day .4 135.25 54.1

Sundries L.S. 15.3 1 15.3TOTAL 130Add 1% for water charges 1.3TOTAL 131.3Add 15% for contractor’s profit and overheads 19.7Cost per opening 151Say 151

### Mirror polishing on marble work/Granite work/stone work where ever required togive high gloss finish complete.

CodDescription Unit Quantity Rate AmountDetails of cost for 10 sqm.Labour:

13 Floor grinder machine (Granite) Day 1 200 200###Beldar Day 2.5 135.25 338.12###Bhishti Day 1.5 138.45 207.68###Sundries grease, mop grinding stones etc. L.S. 65 1 65

TOTAL 810.8Add 1% for water charges 8.11TOTAL 818.91Add 15% for contractor’s profit and overheads 122.84Cost for 10 sqm. 941.75Cost per sqm. 94.18Say 94.2

### Providing and fixing cramps of required size & shape in RCC/ CC backing withcement mortar 1:2(1 cement :2 coarse sand) including drilling necessary hole instones and embedding the cramp in the hole (fastener to be paid separately).

8.7Gunmetal cramps.CodDescription Unit Quantity Rate Amount

Details of cost for one crampMaterials:Gun Metal cramp

-60.064x0.025x0.006 = 9.6x10 +

-60.025x0.025x0.006 =3.7x10 +

Page 278: DAR_Vol_1

-6pin 2 x 22/28 x (0.006)2 + 0.02 = 0.5x10

-6= 13.8x10Less hole

-60.024x0.010x0.006 = (-) 1.4x 10

-6= 12.4x10-612.4x10 x 8640 = 0.107kg+Add wastage @ 10% = 0.011 kg.= 0.118 kg.

###Gun metal cramp Kg. .118 270 31.86###Carriage L.S. 3.9 1 3.9

Cement montar 1:2 (1 cement: 2 coarse sandcum .001 3,864.25 3.86(Rate as per item No. 3.7)

###Labour for fixing in position L.S. 6.5 1 6.5TOTAL 46.12Add 1 % for water charges .46TOTAL 46.58Add 15% for contractor’s profit and overheads 6.99Cost for 0.107 kg. 53.57Cost per kg 500.65Say 500.65

289### Providing and fixing cramps of required size & shape in RCC/ CC backing with

cement mortar 1:2 ( 1 cement :2 coarse sand) including drilling necessary hole instones and embedding the cramp in the hole (fastener to be paid separately).

8.7Stainless steel cramps.

CodDescription Unit Quantity Rate AmountDetails of cost for one crampMaterials:Stainless steel cramp-612.4x10 x7850 = 0.097kg+Add wastage @ 10% = 0.01 Okg.= 0.107 kg.

###Stainless steel cramp Kg. .107 280 29.96###Carriage L.S. 3.9 1 3.9

Cement montar 1:2 (1 cement: 2cum .001 3,864.25 3.86(Rate as per item No. 3.7)

###Labour for fixing in position L.S. 6.5 1 6.5TOTAL 44.22Add 1 % for water charges .44TOTAL 44.66Add 15% for contractor’s profit and overheads 6.7Cost for 0.097 kg. 51.36Cost per kg 529.48Say 529.5

### Providing and fixing expansion hold fasteners on C.C. /R.C.C. surface backing

Page 279: DAR_Vol_1

including drilling necessary holes and the cost of bolt etc complete.8.8Wedge expansion type8.8.1.1 Fastener with threaded dia 6 mm.CodDescription Unit Quantity Rate Amount

Details of cost for 30nos. W.E.H. fastenerMaterials:

###Wedge expansion hold fastener each 30 10 30036.5mm length

###Bolt 6mm dia. Length (36.5+10m quintal .0045 4,300 19.35Labour:

###Fitter Grade-I Day .25 151.5 37.88###Beldar Day .25 135.25 33.81###Hire and running charges for handL.S. 32.5 1 32.5

machine Sundries, drilling bit scaffolding etc.TOTAL 423.54Add 1 % for water charges 4.24TOTAL. 427.78Add 15% for contractor’s profit and overheads 64.17Cost for 30 nos. 491.95Cost for one no. 16.4Say 16.4

290### Providing and fixing expansion hold fasteners on C C/R.C.C. surface backing

including drilling necessary holes and the cost of bolt etc complete.8.8Wedge expansion type8.8.1.2 Fastener with threaded dia 10 mm.

CodDescription Unit Quantity Rate AmountDetails of cost for 30nos. W.E.H. fastenerMaterials:

###Wedge expansion hold fastener each 30 12 36044.5mm length

###Bolt 10mm dia. Length (44.5+1 quintal .006 4,300 25.8Labour:

###Fitter Grade-I Day .25 151.5 37.88###Beldar Day .25 135.25 33.81###Hire and running charges for handL.S. 32.5 1 32.5

machine Sundries, drilling bit scaffolding etc.TOTAL 489.99Add 1% for water charges 4.9TOTAL 494.89Add 15% for contractor’s profit and overheads 74.23Cost for 30 nos. 569.12Cost for one no. 18.97Say 18.95

### Providing and fixing expansion hold fasteners on C.C./ R.C.C. surface backingincluading drilling necessary holes and the cost of bolt etc complete.

8.8Wedge expansion type8.8.1.3 Fastener with threaded dia 12 mm.CodDescription Unit Quantity Rate Amount

Page 280: DAR_Vol_1

Details of cost for 30nos. W.E.H. fastenerMaterials:

###Wedge expansion hold fastener each 30 23 69058.7mm length

###Bolt 12mm dia. Length (58.7+1 quintal .0075 4 300.00 32.25kg./eachLabour:

###Fitter Grade-I Day .25 151.5 37.88###Beldar Day .25 135.25 33.81###Hire and running charges for handL.S. 32.5 1 32.5

machine, Sundries, drilling bit scaffolding etc.TOTAL 826.44Add 1% for water charges 8.26TOTAL 834.7Add 15% for contractor’s profit and overheads 125.2Cost for 30 nos. 959.9Cost for one no. 32Say 32

2918.9 Stone tile (polished) work for wall lining over 12mm thick bed of cement mortar 1:3

(1 cement: 3 coarse sand) and cement slurry @ 3.3 kg/sqm including pointing inwhite cement complete.

8.98 mm thick.8.9.1.1 Raj Nagar plain white marble/ Udaipur green marble/ Zebra black marble.

CodDescription Unit Quantity Rate AmountDetails of cost for 1 sqm.8mm thick marble tiles.Qty. = 1.00 sqm. + Add wastage @2.5% = 0.025 sqm Total = 1.025 sqm.

###8 mm thick marble tiles (polishe sqm 1.025 294 301.35###Carriage of tiles L.S. 3.95 1 3.95

Cement mortar 1:3 (1 Cement: 3 cum .014 3,169.6 44.37(Rate as per item no. 3.8)

###Mortar for pointing L.S. 25.38 1 25.380 3 Cement for slurry tonne .0033 4,500 14.85###Mason 1 st class Day 1 151.5 151.5###Beldar Day 1 135.25 135.25###Sundries etc. L.S. 16.9 1 16.9

TOTAL 693.55Add 1 % for water charges 6.94TOTAL 700.49Add 15% for contractor’s profit and overheads 105.07Cost for 1 sqm. 805.56Say 805.55

8.9 Stone tile (polished) work for wall lining over 12mm thick bed of cement mortar 1:3(1 cement: 3 coarse sand) and cement slurry @ 3.3 kg/sqm including pointing inwhite cement complete.

8.98mm thick.8.9.1.2 Granite of any colour and shade.CodDescription Unit Quantity Rate Amount

Page 281: DAR_Vol_1

Details of cost for 1 sqm.8mm thick Granite tiles.Qty. = 1.00 sqm. + Add wastage [email protected]% = 0.025sqm

Total = 1.025 sqm.###8 mm thick granite stone tiles (m sqm 1.025 555 568.88

of all shades)###Carriage of tiles L.S. 3.95 1 3.95

Cement mortar 1:3 (1 Cement: 3 cum .014 3,169.6 44.37(Rate as per item No. 3.8)

###Mortarr for pointing L.S. 25.38 1 25.38###Cement for slurry tonne .0033 4,500 14.85Mason 1st class Day 1 151.5 151.5###Beldar Day 1 135.25 135.25###Sundries etc. L.S. 16.9 1 16.9

TOTAL 961.08Add 1 % for water charges 9.61TOTAL 970.69Add 15% for contractor’s profit and overheads 145.6Cost for 1 sqm. 1,116.29Say 1,116.3

292### Providing and fixing 18 mm thick stone slab table rubbed, edges rounded and polished

of size 75x50 cm deep and 1.8 cm thick fixed in urinal partitions by cutting a chase ofappropriate width with chase cutter and embedding the stone in the chase withepoxy grout or with cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 gradedstone aggregate 6 mm nominal size) as per direction of Engineer-in-charge andfinished smooth.

8.10.1 White Agaria Marble Stone.

CodDescription Unit Quantity Rate AmountDetails of cost for one No or 0.375 sqm.Materials :-Agaria Marble Stone 1 x 0.75 x0.50 = 0.375 +Add wastage @ 20% = 0.075 sqm.

Total = 0.45sqm.###Agaria Marble Stone sqm .45 1,440 648###Cement concrete 1:2:4 for filling L.S. 21.58 1 21.58###Labour for fixing, edge rounding L.S. 43.16 1 43.16

polishing.###Sundries L.S. 21.58 1 21.58

TOTAL 734.32Add 1 % for water charges 7.34TOTAL 741.66Add 15% for contractor’s profit and overheads 111.25Cost of 0.375sqm 852.91Cost of 1.00 sqm 2 274.43Say 2 274.45

### Providing and fixing 18 mm thick stone slab table rubbed, edges rounded and polishedof size 75x50 cm deep and 1.8 cm thick fixed in urinal partitions by cutting a chase ofappropriate width with chase cutter and embedding the stone in the chase withepoxy grout or with cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded

Page 282: DAR_Vol_1

stone aggregate 6 mm nominal size) as per direction of Engineer-in-charge andfinished smooth.

8.10.2 Granite Stone of approved shade.CodDescription Unit Quantity Rate Amount

Details of cost for one No or 0.375 sqm.Materials :-Granite Stone 1x0.75x0.50 = 0.375sqm.+Add wastage @ 20% = 0.075 sqm

Total = 0.45 sqm.###Granite Stone sqm .45 1,670 751.5###Cement concrete 1:2:4 for fixing L.S. 21.58 1 21.58###Labour for fixing, edge rounding L.S. 43.16 1 43.16

polishing.###Sundries L.S. 21.58 1.00 21.58

TOTAL 837.82Add 1% for water charges 8.38TOTAL 846.2Add 15% for contractor’s profit and overheads 126.93Cost of 0.375 sqm 973.13Cost of 1.00 sqm 2,595.01Say 2,595

293

SUB HEAD : 9.0

WOOD WORK

&

Page 283: DAR_Vol_1

PVC WORK

295### Providing wood work in frames of doors, windows, clerestory windows and other

frames, wrought framed and fixed in position :9.1Second class teak wood

CodDescription Unit Quantity Rate Amount

Details of cost for Chowkhat of a door206.75x117.5cmMaterialsSuperior class teakwood such as DandeliBalarshah or Malabar2x206.75x9.5x7.0cm =0.028cum+1x117.5x9.5x7.0cm = 0.008cum.= 0.036cum.+Add for wastage @ 5% = 0.002cum.Grand Total = 0.038cum.

###Second class teakwood 10 cudm 38 394 1 497.20###Carriage of material (timber) cum .038 60.81 2.31

Labour:###Carpenter (avg.) Day .72 146.55 105.52###Beldar Day .07 135.25 9.47

TOTAL 1 614.50Add 1 % for water charges 16.14TOTAL 1 630.64Add 15% for contractor’s profit and overheads 244.6Cost of 36 cudm. 1 875.24Cost per cum. 52,090Say 52,090

### Providing wood work in frames of doors, windows, clerestory windows and otherframes, wrought framed and fixed in position :

9.1Sal woodCodDescription Unit Quantity Rate Amount

Details of cost for Chowkhat of a door206.75x117.5cmMaterialsSalwood2x206.75x9.5x7.0cm =0.028cum+1x117.50x9.5x7.0cm = 0.008cum.= 0.036cum.+Add for wastage @ 5% = 0.002cum.Grand Total = 0.038cum.Salwood

###Carriage of material (timber) 10 cudm 38 218 828.4###Labour: cum .038 60.81 2.31

Carpenter (avg.)###Beldar Day .72 146.55 105.52###TOTAL Day .07 135.25 9.47

Page 284: DAR_Vol_1

Add 1 % for water charges 945.7TOTAL 9.46Add 15% for contractor’s profit and overheads 955.16Cost of 36 cudm. 143.27Cost per cum. 1 098.43Say 30 511.94

30,511.95

296### Providing wood work in frames of doors, windows, clerestory windows and other

frames, wrought framed and fixed in position :9.1Kiln seasoned and chemically treated Hollock wood.

CodDescription Unit Quantity Rate Amount

Details of cost for Chowkhat of a door206.75x117.5cmMaterialsHollock wood2x206.75x9.5x7.0cm =0.028cum+1x117.50x9.5x7.0cm = 0.008cum.= 0.036cum.+Add for wastage @ 5% = 0.002cum.Grand Total = 0.038cum.

###Hollock wood 10 cudm 38 217 824.6###Carriage of timber cum .038 60.81 2.31###Kiln seasoning of timber cum .038 539 20.48###Chemical treatment L.S. 8.97 1 8.97

Labour:###Carpenter (average) Day .72 146.55 105.52###Beldar Day .07 135.25 9.47

TOTAL 971.35Add 1 % for water charges 9.71TOTAL 981.06Add 15% for contractor’s profit and overheads 147.16Cost of 36 cudm. (finished work) 1,128.22Cost per cum. 31,339.44Say 31,339.45

### Providing laminated veneer lumber conforming to IS: 14616 and TAD -15: 2001( PartB) in factory made frames of doors, windows, clerestory windows and other frames,wrought framed and fixed in position as per directions of Engineer-in-charge.

CodDescription Unit Quantity Rate AmountDetails of cost for Chowkhat of a door206.75x117.5cmMaterialsLaminated veneer lumber including wastage@ 5%2x206.75x9.5x7.0cm =0.028cum+1x117.50x9.5x7.0cm = 0.008cum.= 0.036cum.+Add for wastage @ 5% = 0.002cum.Grand Total = 0.038cum.

###Laminated veneer lumber 10 cudm 38 540 2,052

Page 285: DAR_Vol_1

###Carriage of timber cum .038 60.81 2.31Labour:

###Carpenter Ist Class Day .2 151.5 30.3###Carpenter IInd Class Day .2 141.6 28.32###Beldar Day .2 135.25 27.05

TOTAL 2,139.98Add 1 % for water charges 21.4TOTAL 2,161.38Add 15% for contractor’s profit and overheads 324.21Cost of 36 cudm 2,485.59Cost per cum 69,044.17Say 69,044.2

297### Providing wood work in frames of false ceiling, partitions etc. sawn and put up in

position :9.3Sal woodCodDescription Unit Quantity Rate Amount

Details of cost for ceiling for a room 3x3mMaterials:Salwood= 6x3.30x(50/1000)x(125/1000)= 0.1238cum. +Cross battens 60mm centre to center38x50mm.6x3x(38/1000)x(50/1000)=0.0342cum.= 0.1580 cum.+Add for wastage @ 5% = 0.0079 cum.= 0.1659 cum. say 166 cudm.

###Salwood 10 cudm 166 218 3,618.8###Carriage of timber cum .166 60.81 10.09

Labour:###Carpenter Ilnd Class Day 1 141.6 141.6###Beldar Day 1 135.25 135.25###Sundries screws etc. L.S. 53.82 1 53.82

TOTAL 3,959.56Add 1 % for water charges 39.6TOTAL 3,999.16Add 15% for contractor’s profit and overheads 599.87Cost of 158 cudm. 4,599.03Cost per cum. 29,107.78Say 29,107.8

### Providing wood work in frames of false ceiling, partitions etc. sawn and put up inposition :

9.3Kiln seasoned and chemically treated Hollock wood.CodDescription Unit Quantity Rate Amount

Details of cost for ceiling for a room 3x3mMaterials:Hollock wood= 6x3.30x(50/1000)x(125/1000)= 0.1238cum. +Cross battens 60mm centre to center

Page 286: DAR_Vol_1

38x50mm.6x3x(38/1000)x(50/1000)=0.0342cum.= 0.1580 cum.+Add for wastage @ 5% = 0.0079 cum.= 0.1659 cum. say 166 cudm.

###Hollock wood 10 cudm 166 217 3,602.2###Carriage of timber cum .166 60.81 10.09###Kiln seasoning of timber cum .166 539 89.47###Chemical treatment L.S 18.2 1 18.2

Labour:###Carpenter Ilnd Class Day 1 141.6 141.6###Beldar Day 1 135.25 135.25###Sundries screws etc. L.S. 53.82 1 53.82

TOTAL 4,050.63Add 1 % for water charges 40.51TOTAL 4,091.14Add 15% for contractor’s profit and overheads 613.67Cost of 158 cudm. 4,704.81Cost per cum. 29,777.28Say 29,777.3

298### Extra for additional labour for circular works, such as in frames of fan light:

9.4Second class teak wood

CodDescription Unit Quantity Rate Amount

Details of cost for Chowkhat of a door206.75x117.5cmExtra Materials and labour for wastage @10% on quantity of item no 9.1.1Materials :

###Second class teakwood 10 cudm 3.8 394 149.72###Carriage of material (timber) cum .0038 60.81 .23

Labour:###Carpenter (avg.) Day .072 146.55 10.55###Beldar Day .007 135.25 .95

TOTAL 161.45Add 1% for water charges 1.61TOTAL 163.06Add 15% for contractor’s profit and overheads 24.46Cost of 36 cudm. 187.52Cost per cum. 5,208.89Say 5,208.9

### Extra for additional labour for circular works, such as in frames of fan light:9.4Sal woodCodDescription Unit Quantity Rate Amount

Details of cost for Chowkhat of a door206.75x117.5cmExtra Materials and labour for wastage @10% on quantity of item no 9.1.2Materials :

###Sal wood in scantling 10 cudm 3.8 218 82.84

Page 287: DAR_Vol_1

###Carriage of material (timber) cum .0038 60.81 .23Labour:

###Carpenter (avg.) Day .072 146.55 10.55###Beldar Day .007 135.25 .95

TOTAL 94.57Add 1% for water charges .95TOTAL 95.52Add 15% for contractor’s profit and overheads 14.33Cost of 36 cudm. 109.85Cost per cum. 3,051.39Say 3,051.4

### Extra for additional labour for circular works, such as in frames of fan light:9.4Kiln seasoned and chemically treated Hollock wood.CodDescription Unit Quantity Rate Amount

Details of cost for Chowkhat of a door206.75x117.5cmExtra Materials and labour for wastage @10% on quantity of item no 9.1.3Materials :

###Hollock wood 10 cudm 3.8 217 82.46###Carriage of timber cum .0038 60.81 .23

299CodDescription Unit Quantity Rate Amount###Kiln seasoning of timber cum .0038 539 2.05###Chemical treatment L.S .9 1 .9

Labour:###Carpentr I class Day .072 146.55 10.55###Beldar Day .007 135.25 .95

TOTAL 97.14Add 1% for water charges .97TOTAL 98.11Add 15% for contractor’s profit and overheads 14.72Cost of 36 cudm. (finished work) 112.83Cost per cum. 3,134.17Say 3,134.15

### Providing and fixing panelled or panelled and glazed shutters for doors, windowsand clerestory windows including ISI marked black enamelled M.S butt hinges withnecessary screws excluding panelling which will be paid for separately.

9.5Second class teak wood9.5.1.1 35 mm thick shuttersCodDescription Unit Quantity Rate Amount

Details of cost for shutters of a Door(l/3rd glazed and 2/3rd panelled) 200xl08cm= 2.16sqm)Materials:Teak woodStyles 4x200x10.0x3.5cm = 0.028cum+RailsTop rails1x110.5x3.5cm = 0.004cum.+Bottom rails 1x110.5x20x3.5cm = 0.008cum+

Page 288: DAR_Vol_1

Lock rails 1x110.5x15x3.5cm = 0.006cum+Beading 2x186. 1x1. 9x1.2cm = 0.001cum.Total = 0.047 cum+Add for wastage @ 10% = 0.005cumGrand Total = 0.051 cum.

###Teak wood 10 cudm 51 410 2,091###Carriage of timber cum .051 60.81 3.1###Black enemelled M.S. Butt 10 Nos 6 54 32.4

hinges-100x5 8x1.9mm###Black enemelled M.S. Butt 10 Nos 2 28 5.6

hinges-50x37xl.5mm###M.S. Screws 40mm 100 Nos 48 30 14.4###M.S. Screws 20mm 100 Nos 8 15 1.2

Labour:###Carpenter (average) Day 1.83 146.55 268.19###Beldar Day .76 135.25 102.79###Sundries L.S. 35.88 1 35.88

TOTAL 2,554.56Add 1% for water charges 25.55TOTAL 2,580.11Add 15% for contractor’s profit and overheads 387.02Cost of 2.16 sqm. 2,967.13Cost of 1 sqm. 1,373.67Say 1,373.65

300### Providing and fixing panelled or panelled and glazed shutters for doors, windows

and clerestory windows including ISI marked black enamelled M.S butt hinges withnecessary screws excluding, panelling which will be paid for separately.

9.5Second class teak wood9.5.1.2 30 mm thick shutters

CodDescription Unit Quantity Rate Amount

Details of cost for shutters of a Door(l/3rd glazed and 2/3rd panelled) 200x108cm= 2.16 sqmMaterials:Teak woodStyles : 4x200x10.0x3.0cm = 0.024 cum+Top rails :1x110.5x9.5x3.0cm = 0.003cum+Bottom rails: 1x110.5x19.7x3.0cm =0.007cum+Lockrails: 1x110.5xl5.0x3.0cm =0.005cum+Beading : 2x186.lxl.9x1.2cm = 0.001 cum.Total = 0.040 cum. +Add for wastage @ 10% = 0.004 cum.Grand Total = 0.044 cum.

###Teak wood 10 cudm 44 410 1,804###Carriage of timber cum .044 60.81 2.68###Bright finished or black enamelle 10 Nos 6 54 32.4

butt hinges 100x58x1.90 mm

Page 289: DAR_Vol_1

###Bright finished or black enamelle 10 Nos 2 28 5.6butthinges5Ox37xl.5O mm

###M.S. Screws 40mm 100 Nos 48 30 14.4###M.S. Screws 20mm 100 Nos 8 15 1.2

Labour:###Carpenter (avg) Day 1.83 146.55 268.19###Beldar Day .76 135.25 102.79###Sundries L.S. 35.88 1 35.88

TOTAL 2,267.14Add 1% for water charges 22.67TOTAL 2,289.81Add 15% for contractor’s profit and overheads 343.47Cost of 2.16 sqm. 2,633.28Cost of 1 sqm. 1,219.11Say 1,219.1

### Providing and fixing panelled or panelled and glazed shutters for doors, windowsand clerestory windows including ISI marked black enamelled M.S butt hinges withnecessary screws excluding panelling which will be paid for separately.

9.5Kiln seasoned and chemically treated Hollock wood.9.5.2.1 35 mm thick shuttersCodDescription Unit Quantity Rate Amount

Details of cost for shutters of a Door(l/3rd glazed and 2/3rd panelled) 200x108cm= 2.16 sqmMaterials:Hollock wood

301CodDescription Unit Quantity Rate Amount

Styles 4x200x10.0x3.5cm = 0.028cum+RailsTop rails 1x110.5x10.0x3.5cm = 0.004cum.+Bottom rails 1x110.5x20.0x3.5cm = 0.008cum+Lock rails 1x110.5x15.00x3.5cm = 0.006cum+Beading2xl86.1xl.9xl.2cm = 0.001cum.Total = 0.047 cum+Add for wastage @ 10% = 0.005cumGrand Total = 0.051 cum.

###Hollock wood 10 cudm 51 230 1,173###Carriage of timber cum .051 60.81 3.1###Kiln seasoning cum .051 539 27.49###Chemical treatment L.S 9.1 1 9.1###Black enamelled M.S. Butt 10 Nos. 6 54 32.4

hinges-100x58xl.9mm###Black enamelled M.S. Butt 10 Nos. 2 28 5.6

hinges-50x37xl .5mm###M.S. Screws 40mm 100 Nos 48 30 14.4###M.S. Screws 20mm 100 Nos 8 15 1.2

Labour:###Carpenter (Avg.) Day 1.83 146.55 268.19

Page 290: DAR_Vol_1

###Beldar Day .76 135.25 102.79###Sundries L.S. 35.88 1 35.88

TOTAL 1,673.15Add 1% for water charges 16.73TOTAL 1,689.88Add 15% for contractor’s profit and 253.48overheadsCost of 2.16 sqm. 1,943.36Cost of 1 sqm. 899.7Say 899.7

### Providing and fixing panelled or panelled and glazed shutters for doors, windowsand clerestory windows including ISI marked black enamelled M.S butt hinges withnecessary screws excluding panelling which will be paid for separately.

9.5Kiln seasoned and chemically treated Hollock wood.9.5.2.2 30 mm thick shuttersCodDescription Unit Quantity Rate Amount

Details of cost for shutters of a door (l/3rdglazed and 2/3rd panelled)200xl08cm = 2.16sqm.Materials:Hollock woodStyles 4x200xl0.0x3.0cm = 0.024cum+RailsTop rails 1x110.5x9.50x3.0cm = 0.003cum.+Lock rails 1x110.5x15.0x3.0cm = 0.005cum+Bottom rails 1x110.5xl9.7x3.0cm = 0.007cum+Beading2xl86.1xl.9xl.2cm = 0.001cumTotal = 0.040 cum.+

302CodDescription Unit Quantity Rate Amount

Add for wastage @ 10% = 0.004cumGrand Total = 0.044 cum or = 44 cudm

###Hollock wood 10 cudm 44 230 1,012###Carriage of timber cum .044 60.81 2.68###Kiln seasoning cum .044 539 23.72###Chemical treatment L.S 9.1 1 9.1###Black enemelled M.S. Butt 10 Nos. 6 54 32.4

hinges-100x58xl.9mm###Black enemelled M.S. Butt 10 Nos. 2 28 5.6

hinges-50x37xl .5mm###M.S. Screws 40mm 100 Nos 48 30 14.4###M.S. Screws 20mm 100 Nos 8 15 1.2

Labour:###Carpenter (Avg.) Day 1.83 146.55 268.19###Beldar Day .76 135.25 102.79###Sundries L.S. 35.88 1 35.88

TOTAL 1,507.96Add 1% for water charges 15.08TOTAL 1,523.04

Page 291: DAR_Vol_1

Add 15% for contractor’s profit and overheads 228.46Cost of 2.16 sqm. 1,751.5Cost of 1 sqm. 810.88Say 810.9

### Providing and fixing 35 mm thick factory made laminated veneer lumber door shutterconforming to IS : 14616 and TADS 15:2001 (Part B) including ISI marked blackenamelled M.S. butt hinges with necessary screws as per directions of Engineer-in-charge and panelling with panels of:

9.612mm thick plain grade - 1, medium density flat pressed three layer particle boardFPT - I or graded wood particle board FPT - I, IS : 3087 marked bonded with BWPtype synthetic resin adhesive as per IS : 848 :

CodDescription Unit Quantity Rate AmountDetails of cost of one shutter220xl08cm = 2.38sqm.Materials:Factory made shutters LVL syles, rails andpanels

###Plain particle board sqm 2.38 1,500 3,570###Carriage of shutters L.S. 29.64 1 29.64

Fittings:###Black enamelled M.S. Butt 10 Nos 6 54 32.4

hinges-100x58x 1.9mm###Black enamelled M.S. Butt hinges10 Nos 2 28 5.6###M.S. Screws 40mm 100 Nos 48 30 14.4###M.S. Screws 20mm 100 Nos 8 15 1.2

Labour:###Carpenter Average Day .52 146.55 76.21###Beldar Day .6 135.25 81.15###Sundries L.S. 35.88 1 35.88

TOTAL 3,846.48Add 1% for water charges 38.46TOTAL 3,884.94Add 15% for contractor’s profit and overheads 582.74Cost of 2.38 sqm. 4,467.68Cost of 1 sqm. 1,877.18Say 1,877.2

303### Providing and fixing 35 mm thick factory made laminated veneer lumber door shutter

conforming to IS : 14616 and TADS 15:2001 (Part B) including ISI marked blackenamelled M.S. butt hinges with necessary screws as per directions of Engineer-in-charge and panelling with panels of:

9.612 mm thick prelaminated (with particle board decorative lamination on both sides)grade - 1, medium density flat pressed, three layer particle board FPT - I or gradedwood particle board FPT - 1, conforming to IS : 3087 bonded with BWP type syntheticresin adhesive as per IS : 848 and prelamination conforming to IS : 12823 Grade 1,Type - II marked:

CodDescriptio Unit Quantity Rate Amount

Page 292: DAR_Vol_1

Details of cost of one shutter220xl08cm = 2.38sqm.Materials:Factory made shutters LVL styles, rails andpanels

###Plain parti sqm 2.38 1,618 ######Carriage of L.S. 29.64 1 29.64

Fittings:###Black enam10 Nos 6 54 32.4

hinges-100x58x 1.9mm###Black ename10 Nos 2 28 5.6###M.S. Scre 100 Nos 48 30 14.4###M.S. Scre 100 Nos 8 15 1.2

Labour:###Carpenter Day .52 146.55 76.21###Beldar Day .6 135.25 81.15###Sundries L.S. 35.88 1 35.88

TOTAL ###Add 1% for water charges 41.27TOTAL ###Add 15% for contractor’s profit and overheads 625.29Cost of 2.38 sqm. ###Cost of 1 sqm. ###Say ###

### Providing and fixing 35 mm thick factory made laminated veneer lumber door shutterconforming to IS : 14616 and TADS 15:2001 (Part B) including ISI marked blackenamelled M.S. butt hinges with necessary screws as per directions of Engineer-in-charge and panelling with panels of:

9.612 mm thick one side prelaminated (with particle board decorative lamination onother sides) and balancing lamination grade - 1 medium density flat pressed, threelayer particle board FPT - I or graded wood particle board FPT-1 conforming to IS :3087 bonded with BWP type synthetic resin adhesive as per IS : 848 and prelaminationconforming to IS : 12823 Grade -1, Type II marked:

CodDescriptio Unit Quantity Rate AmountDetails of cost of one shutter220xl08cm = 2.38sqm.Materials:Factory made shutters LVL syles, rails andpanels

304CodDescription Unit Quantity Rate Amount###Plain particle board sqm 2.38 1,572 3 741.36###Carriage of shutters L.S. 29.64 1 29.64

Fittings:###Black enamelled M.S. Butt 10 Nos 6 54 32.4

hinges-100x58x 1.9mm###Black enamelled M.S. Butt hinge 10 Nos 2 28 5.6###M.S. Screws 40mm 100 48 30 14.4###M.S. Screws 20mm Nos 8 15 1.2

Labour: 100###Carpenter Average Nos .52 146.55 76.21

Page 293: DAR_Vol_1

###Beldar .6 135.25 81.15###Sundries Day 35.88 1 35.88

TOTAL Day 4 017.84Add 1% for water charges L.S. 40.18TOTAL 4 058.02Add 15% for contractor’s profit and overheads 608.7Cost of 2.38 sqm. 4 666.72Cost of 1 sqm. 1 960.81Say 1 960.80

### Providing and fixing panelling or panelling and glazing in panelled or panelled andglazed shutters for doors, windows and clerestory windows (Area of opening forpanel inserts excluding portion inside grooves or rebates to be measured). Panel-ling for panelled or panelled and glazed shutters 25 mm to 40 mm thick :

9.7Second class teak woodCodDescription Unit Quantity Rate Amount

Details of cost for shutters of a door with2/3rd panelling...200x 108cm = 2.16sqm.Panel area = 4x45.1x36.55cm = 0.067 sqmMaterials:Panels4x47.2x38.65xl.6cm = 0.0117cum+Add for wastage @ 10% = 0.0012cum.= 0.0129 cum.

###Second class teak wood 10 cudm 12.9 410 528.9###Carriage of timber cum .0129 60.81 .78

Labour:###Carpenter 1st class Day .57 151.5 86.35###Sundries L.S 4.42 1 4.42

TOTAL 620.45Add 1 % for water charges 6.2TOTAL 626.65Add 15% for contractor’s profit and overheads 94Cost of 0.67 sqm. 720.65Cost of 1 sqm. 1,075.6Say 1,075.6

305### Providing and fixing panelling or panelling and glazing in panelled or panelled and

glazed shutters for doors, windows and clerestory windows (Area of opening forpanel inserts excluding portion inside grooves or rebates to be measured). Panel-ling for panelled or panelled and glazed shutters 25 mm to 40 mm thick :

9.7kiln seasoned and chemically treated Hollock woodCodDescription Unit Quantity Rate Amount

Details of cost for shutters of a door200x108cm = 2.16 sqm.Panel area 4x45.1x36.55cm=0.66sqm.Materials:Hollock woodpanels 4x45.1x36.55cm = 0.0117 cum+Add for wastage @ 10% = 0.0012cum.= 0.0129 cum.

Page 294: DAR_Vol_1

###Hollock wood 10 cudm 12.9 230 296.7###Carriage of timber cum .0129 60.81 .78###Kiln seasoning cum .0129 539 6.95###Chemical treatment L.S 8.97 1 8.97

Labour & sundries###Carpenter 1 st class Day .57 151.5 86.35###Sundries L.S 4.42 1 4.42

TOTAL 404.17Add 1 % for water charges 4.04TOTAL 408.21Add 15% for contractor’s profit and overheads 61.23Cost of 0.66 sqm. 469.44Cost of 1 sqm. 711.27Say 711.25

### Providing and fixing panelling or panelling and glazing in panelled or panelled andglazed shutters for doors, windows and clerestory windows (Area of opening forpanel inserts excluding portion inside grooves or rebates to be measured). Panellingfor panelled or panelled and glazed shutters 25 mm to 40 mm thick :

9.7Ply wood 5 ply, 9 mm thick :9.7.3.1 Decorative plywood both side decorative veneer (Type -1) conforming to IS 1328

BWR type.CodDescription Unit Quantity Rate Amount

Details of cost for shutters of a door with2/3 rd panelling. ..200x108cm = 2.16sqm.Panel area = 4x45.1x36.55cm = 0.67sqm.Materials:Plywood (9mm thick) 4x47.2x38.65cm =0.73sqm+Add for wastage @ 10% = 0.07sqm.Total = 0.80 sqm.

###Ply wood 5 ply with teak ply on b sqm .8 693 554.4mm thick

###Carriage of Plywood L.S 1.82 1 1.82Labour:

###Carpenter 1 st class Day .57 151.5 86.35###Sundries L.S 4.42 1 4.42

TOTAL 646.99Add 1 % for water charges 6.47TOTAL 653.46Add 15% for contractor’s profit and overheads 98.02Cost of 0.67 sqm. 751.48Cost of 1 sqm. 1,121.61Say 1,121.6

306### Providing and fixing panelling or panelling and glazing in panelled or panelled and

glazed shutters for doors, windows and clerestory windows (Area of opening forpanel inserts excluding portion inside grooves or rebates to be measured). Panellingfor panelled or panelled and glazed shutters 25 mm to 40 mm thick :

9.7Ply wood 5 ply, 9 mm thick :9.7.3.2 Decorative plywood one side decorative veneer and commercial veneer on other

Page 295: DAR_Vol_1

face (Type 1) conforming to IS 1328 BWR Type

CodDescription Unit Quantity Rate AmountDetails of cost for shutters of a door with2/3rd panelling.. .200x 108cm = 2.16sqm.Panel area = 4x45.1x36.55cm = 0.67sqm.Materials:Plywood (9mm thick) 4x47.2x38.65cm =0.73sqm+Add for wastage @ 10% = 0.07sqm.Total = 0.80 sqm.

###Ply wood 5 ply with teak ply on b sqm .8 550 440mm thick

###Carriage of Plywood L.S 1.82 1 1.82Labour:

###Carpenter 1 st class Day .57 151.5 86.35###Sundries L.S 4.42 1 4.42

TOTAL 532.59Add 1 % for water charges 5.33TOTAL 537.92Add 15% for contractor’s profit and overheads 80.69Cost of 0.67 sqm. 618.61Cost of 1 sqm. 923.3Say 923.3

### Providing and fixing panelling or panelling and glazing in panelled or panelled andglazed shutters for doors, windows’ and clerestory windows (Area of opening forpanel inserts excluding portion inside grooves or rebates to be measured). Panellingfor panelled or panelled and glazed shutters 25 mm to 40 mm thick :

9.7Ply wood 7 ply, 9 mm thick :9.7.4.1 Decorative plywood one side decorative veneer and commercial veneer on other

face (Type 1) conforming to IS 1328 BWR TypeCodDescription Unit Quantity Rate Amount

Details of cost for shutters of a door with2/3rd panelling.. .200x 108cm = 2.16sqm.Panel area = 4x45.1x36.55cm = 0.67sqm.Materials:Plywood (9mm thick) 4x47.2x38.65cm =0.73sqm+Add for wastage @ 10% = 0.07sqm.Total = 0.80 sqm.

###Ply wood 7 ply with teak ply on b sqm .8 550 4689 mm thick

###Carriage of Plywood L.S 1.82 1 1.82Labour:

###Carpenter 1 st class Day .57 151.5 86.35###Sundries L.S 4.42 1 4.42

307CodDescription Unit Quantity Rate Amount

TOTAL 560.59Add 1 % for water charges 5.61

Page 296: DAR_Vol_1

TOTAL 566.2Add 15% for contractor’s profit and overheads 84.93Cost of 0.67 sqm. 651.13Cost of 1 sqm. 971.84Say 971.85

### Providing and fixing panelling or panelling and glazing in panelled or panelled andglazed shutters for doors, windows and clerestory windows (Area of opening forpanel inserts excluding portion inside grooves or rebates to be measured). Panellingfor panelled or panelled and glazed shutters 25 mm to 40 mm thick :

9.7Particle Board 12 mm thick9.7.5.1 Plain particle board flat pressed, 3 layer or graded wood particle board medium

density Grade I, IS : 3087 marked.

CodDescription Unit Quantity Rate Amount

Details of cost for shutters of a door with2/3rd panelling...200x108cm = 2.16sqm.Panel area = 4x45.1x36.55cm = 0.67sqm.Materials:Plywood 4x47.2x38.65cm = 0.73sqm+Add for wastage @ 10% = 0.07sqm.Total = 0.80 sqm.

###Particle board 12mm thick sqm .8 258 206.4###Carriage of Plywood L.S 1.82 1 1.82

Labour:###Carpenter 1st class Day .57 151.5 86.35###Sundries L.S 4.42 1 4.42

TOTAL 298.99Add 1 % for water charges 2.99TOTAL 301.98Add 15% for contractor’s profit and overheads 45.3Cost of 0.67 sqm. 347.28Cost of 1 sqm. 518.33Say 518.35

### Providing and fixing panelling or panelling and glazing in panelled or panelled andglazed shutters for doors, windows and clerestory windows (Area of opening forpanel inserts excluding portion inside grooves or rebates to be measured). Panellingfor panelled or panelled and glazed shutters 25 mm to 40 mm thick :

9.7Particle Board 12 mm thick9.7.5.2 Veneered flat pressed three layer or graded wood particle board with commercial

veneering on both sides conforming to IS:3097, grade I.CodDescription Unit Quantity Rate Amount

Details of cost for shutters of a door with2/3rd panelling.. .200x108cm = 2.16sqm.Panel area = 4x45.1x36.55cm = 0.67sqm.Materials:Particle board 4x47.2x38.65cm = 0.73sqm+

308CodDescription Unit Quantity Rate Amount

Add for wastage @ 10% = 0.07sqm.

Page 297: DAR_Vol_1

###Total = 0.80 sqm. sqm .8 418 334.4###Carriage of Plywood L.S 1.82 1 1.82

Labour:###Carpenter 1st class Day .57 151.5 86.35###Sundries L.S 4.42 1 4.42

TOTAL 426.99Add 1 % for water charges 4.27TOTAL 431.26Add 15% for contractor’s profit and overheads 64.69Cost of 0.67 sqm. 495.95Cost of 1 sqm. 740.22Say 740.2

### Providing and fixing panelling or panelling and glazing in panelled or panelled andglazed shutters for doors, windows and clerestory windows (Area of opening forpanel inserts excluding portion inside grooves or rebates to be measured). Panellingfor panelled or panelled and glazed shutters 25 mm to 40 mm thick :

9.7Particle Board 12 mm thick9.7.5.3 Prelaminated particle board with decorative lamination on one side and balancing

lamination on other side,Grade I, Type II IS: 12823 marked.

CodDescription Unit Quantity Rate AmountDetails of cost for shutters of a door with2/3rd panelling.. .200x108cm = 2.16sqm.Panel area = 4x45.1x36.55cm = 0.67sqm.Materials:Particle board 4x47.2x38.65cm = 0.73sqm+

###Add for wastage @ 10% = 0.07sqm.###Total = 0.80 sqm. sqm .8 595 476

Carriage of Plywood L.S 1.82 1 1.82###Labour:###Carpenter 1st class Day .57 151.5 86.35

Sundries L.S 4.42 1 4.42TOTAL 568.59Add 1 % for water charges 5.69TOTAL 574.28Add 15% for contractor’s profit and overheads 86.14Cost of 0.67 sqm. 660.42Cost of 1 sqm. 985.7Say 985.7

### Providing and fixing panelling or panelling and glazing in panelled or panelled andglazed shutters for doors, windows and clerestory windows (Area of opening forpanel inserts excluding portion inside grooves or rebates to be measured). Panellingfor panelled or panelled and glazed shutters 25 mm to 40 mm thick :

9.7Particle Board 12 mm thick9.7.5.4 Prelaminated particle board with decorative lamination on both sides, Grade I, Type

II, IS: 12823 marked.CodDescription Unit Quantity Rate Amount

Details of cost for shutters of a door with2/3rd panelling.. .200x108cm = 2.16sqm.Panel area = 4x45.1x36.55cm = 0.67sqm.Materials:

Page 298: DAR_Vol_1

309CodDescription Unit Quantity Rate Amount

Particale board 4x47.2x38.65cm = 0.73sqm+Add for wastage @ 10% = 0.07sqm.

###Total = 0.80 sqm. sqm .8 625 500###Carriage of Plywood L.S 1.82 1 1.82

Labour:###Carpenter 1st class Day .57 151.5 86.35###Sundries L.S 4.42 1 4.42

TOTAL 592.59Add 1 % for water charges 5.93TOTAL 598.52Add 15% for contractor’s profit and overheads 89.78Cost of 0.67 sqm. 688.3Cost of 1 sqm. 1 027.31Say 1 027.30

### Providing and fixing panelling or panelling and glazing in panelled or panelled andglazed shutters for doors, windows and clerestory windows (area of opening forpanel inserts excluding portion inside grooves or rebates to be measured). Panellingfor panelled or panelled and glazed shutters 25 mm to 40 mm thick. Coir veneerboard (conforming to IS : 14842-2000):

9.812 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for shutters of a door with2/3rd panelling...200x108cm = 2.16sqm.Panel area = 4x45.1x36.55cm = 0.67sqm.Materials:Coir veneered board 12 mm thick4x47.2x38.65cm = 0.73sqmAdd for wastage @ 10% = 0.07sqm.Total = 0.80 sqm.

###Coir veneered board 12mm thick sqm .8 548 438.4###Carriage L.S 1.82 1 1.82

Labour:###Carpenter 1 st class Day .57 151.5 86.35###Sundries L.S 4.42 1 4.42

TOTAL 530.99Add 1 % for water charges 5.31TOTAL 536.3Add 15% for contractor’s profit and overheads 80.44Cost of 0.67 sqm. 616.74Cost of 1 sqm. 920.51Say 920.5

### Providing and fixing glazed shutters for doors, windows and clerestory windowsusing 4 mm thick float glass panes including black enamelled ISI marked MS butthinges with necessary screws.

9.9Second class teak wood9.9.1.1 35 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for shutter of a door (glazed)200xl08cm = 2.16 sqm.Materials :(i) Teak wood (2nd class)

Page 299: DAR_Vol_1

310CodDescription Unit Quantity Rate Amount

Styles : 4x200x9.5x3.5cm = 0.027cumRailsTop & intermediate rails2x110.5x9.5x3.5cm = 0.008cumLock and bottom rails2x110.5xl9.7x3.5cm = 0.015cumBeadings-2x186.1x1.9x1.2cm = 0.001cum4x 171.70x 1.9x 1.2cm = 0.002cum.Total = 0.053 cum.Add for wastage @ 10% = 0.005cum.Grand Total = 0.058 cum.

###Teak wood (2nd Class) 10 cudm 58 410 2,378###(ii) Float glasses 4.0mm thick sqm 1.27 248 314.96###(iii) Black enamelled M.S. butt 10 Nos 6 54 32.4

hinges-100x58x1.90mm###Black enamelled M.S. butt 10 Nos 2 28 5.6

hinges-50x37xl .50mm###M.S. Screws 40mm 100 Nos 48 30 14.4###M.S. Screws 20mm 100 Nos 8 15 1.2###Carriage of Timber cum .058 60.81 3.53

Labour:###Carpenter (Avg.) Day 1.83 146.55 268.19###Glazier Day .23 141.6 32.57###Beldar Day .77 135.25 104.14###Sundries L.S. 40.43 1 40.43

TOTAL 3,195.42Add 1 % for water charges 31.95TOTAL 3,227.37Add 15% for contractor’s profit and overheads 484.11Cost of 2.16 sqm. 3,711.48Cost of 1 sqm. 1,718.28Say 1,718.3

### Providing and fixing glazed shutters for doors, windows and clerestory windowsusing 4 mm thick float glass panes including black enamelled ISI marked MS butthinges with necessary screws.

9.9Second class teak wood9.9.1.1 30 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for shutter of a door (glazed)200x108cm = 2.16 sqm.Materials :(i) Teak woodStyles : 4x200x9.5x3.0cm = 0.023cum+RailsTop & intermediate rails2x110.5x9.5x3.0cm = 0.006cum+Lock and bottom rails2x110.5x19.7x3.0cm = 0.013cum+Beadings-2x186.1xl.9xl.2cm = 0.001cum+4x 171.70x 1.9x 1.2cm = 0.002cum.

Page 300: DAR_Vol_1

Total = 0.045 cum.+

311CodDescription Unit Quantity Rate Amount

Add for wastage @ 10% = 0.005cum.Grand Total = 0.050 cum.

###Teak wood 10 cudm 50 410 2 050.00###(ii) Float glasses 4.0mm thick sqm 1.27 248 314.96###(iii) Black enamelled M.S. butt 10 Nos 6 54 32.4

hinges-100x58x1.90mm###Black enamelled M.S. butt 10 Nos 2 28 5.6

hinges-50x3 7x 1.50mm###M.S. Screws 40mm 100 Nos 48 30 14.4###M.S. Screws 20mm 100 Nos 8 15 1.2###(iv) Carriage of timber cum .05 60.81 3.04

Labour:###Carpenter (Avg.) Day 1.83 146.55 268.19###Glazier Day .23 141.6 32.57###Beldar Day .77 135.25 104.14###Sundries L.S. 40.43 1 40.43

TOTAL 2 866.93Add 1 % for water charges 28.67TOTAL 2 895.60Add 15% for contractor’s profit and overheads 434.34Cost of 2.16 sqm. 3 329.94Cost of 1 sqm. 1 541.64Say 1 541.65

### Providing and fixing glazed shutters for doors, windows and clerestory windowsusing 4 mm thick float glass panes including black enamelled ISI marked M.S butthinges with necessary screws.

9.9Kiln seasoned and chemically treated Hollock wood9.9.2.1 35 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for shutter of a door (glazed)200x108cm = 2.16 sqm.Materials :(i) Hollock woodStyles : 4x200x9.5x3.5cm = 0.027 cum+RailsTop & intermediate rails2x110.5x9.5x3.50cm = 0.008cum+Lock and bottom rails2x110.5x19.7x3.50cm = 0.015cum+Beadings-2xl86.1x1.9x1.2cm = 0.001cum+4x 171.70x 1.9x 1.2cm = 0.002cum.Total = 0.053 cum.+Add for wastage @ 10% = 0.005cum.Grand Total = 0.058 cum or = 58 cudmHollock wood

###(ii) Kiln seasoning 10 cudm 58 230 1,334###(iii) Chemical treatment cum .058 539 31.26###(iv) Float glassess 4.0 mm thick L.S 9.1 1 9.1

Page 301: DAR_Vol_1

###(v) Black enamelled M.S. Butt sqm 1.27 248 314.96###hinges-100x58x1.90mm 10 Nos 6 54 32.4

Black enamelled M.S. butt###hinges 50x37x 1.50mm 10 Nos 2 28 5.6###M.S. Screws 40mm 100 Nos 48 30 14.4

312CodDescription Unit Quantity Rate Amount###M.S. Screws 20mm 100 Nos 8 15 1.2###(iv) Carriage of timber cum .058 60.81 3.53

Labour:###Carpenter (Avg.) Day 1.83 146.55 268.19###Glazier Day .23 141.6 32.57###Beldar Day .77 135.25 104.14###Sundries L.S. 40.43 1 40.43

TOTAL 2,191.78Add 1 % for water charges 21.92TOTAL 213.7Add 15% for contractor’s profit and overheads 332.06Cost of 2.16 sqm. 2,545.76Cost of 1 sqm. 1,178.59Say 1,178.6

### Providing and fixing glazed shutters for doors, windows and clerestory windowsusing 4 mm thick float glass panes including black enamelled ISI marked M.S butthinges with necessary screws.

9.9Kiln seasoned and chemically treated Hollock wood9.9.2.2 30 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for shutter of a door (glazed)200x108cm = 2.16 sqm.Materials :(i) Hollock woodStyles : 4x200x9.50x3.0cm = 0.023cum+RailsTop & intermediate rails2x110.5x9.50x3.0cm = 0.006cum+Lock and bottom rails2x110.5x19.70x3.0cm = 0.013cum+Beadings-2x186.1x1.9x1.2cm = 0.001cum+4x 171.70x 1.9x 1.2cm = 0.002cum.Total = 0.045 cum.+Add for wastage @ 10% = 0.005cum.Grand Total = 0.050

###Hollock wood 10 cudm 50 230 1 150.00###(ii) Kiln seasoning cum .058 539 26.95###(iii) Chemical treatment L.S 9.1 1 9.1###(iv) Float glassess 4.0 mm thick sqm 1.27 248 314.96###(v) Black enamelled M.S. Butt 10 Nos 6 54 32.4

hinges 100x58x1.90mm###Black enamelled M.S. butt 10 Nos 2 28 5.6

hinges 50x37x 1.50mm###M.S. Screws 40mm 100 Nos 48 30 14.4

Page 302: DAR_Vol_1

###M.S. Screws 20mm 100 Nos 8 15 1.2###(iv) Carriage of timber cum .05 60.81 3.04

Labour:###Carpenter (Avg.) Day 1.83 146.55 268.19###Glazier Day .23 141.6 32.57###Beldar Day .77 135.25 104.14###Sundries L.S. 40.43 1 40.43

TOTAL 2,002.98Add 1 % for water charges 20.03TOTAL 2,023.01Add 15% for contractor’s profit and overheads 303.45Cost of 2.16 sqm. 2,326.46Cost of 1 sqm. 1,077.07Say 1,077.05

313### Providing and fixing factory made laminated veneer lumber glazed shutter conforming

to IS 14616 and TADS 15:2001 (Part B), using 4mm thick float glass panes for doors,windows and clerestory windows including ISI marked black enamelled M.S butthinges with necessary screws as per directions of Engineer-in-charge

9.10.1 30 mm thick shutters

CodDescription Unit Quantity Rate Amount

Details of cost of one shutter220x108cm = 2.38sqm.Materials:

###Factory, made shutters glazed sqm 2.38 1,290 3 070.20veneer lumber door shutter

###Carriage of shutters L.S. 29.64 1 29.64Fittings:

###Black enamelled M.S. butt 10 Nos 6 54 32.4hinges 100x58x1.90mm

###Black enamelled M.S. butt 10 Nos 2 28 5.6hinges 50x37x 1.50mm

###M.S. Screws-40mm 100 Nos 48 30 14.4###M.S. Screws-20mm 100 Nos 8 15 1.2

Labour:###Carpenter (Avg.) Day .52 146.55 76.21###Beldar Day .6 135.25 81.15###Sundries L.S. 35.88 1 35.88

TOTAL 3 346.68Add 1% for water charges 33.47TOTAL 3 380.15Add 15% for contractor’s profit and overheads 507.02Cost of 2.38 sqm. 3 887.17Cost of 1 sqm. 1 633.26Say 1 633.25

### Extra for providing heavy sheet float glass panes instead of ordinary float glass inglazed doors, window and clereslory window shutters (Area of opening of glasspanes excluding portion inside rebate shall be measured)

9.11.1 5.5mm thick instead of 4mm thick.

Page 303: DAR_Vol_1

CodDescription Unit Quantity Rate Amount

Details of cost for one sqm.Materials:

###Glasse Panes of 13.75 kg per sqmsqm 1 340 340###Deduct panels of 10 kg per sqm. sqm 1 248 248

Net Cost 92Add 1 % for water charges .92TOTAL 92.92Add 15% for contractor’s profit and overheads 13.94Cost of 1 sqm. 106.86Say 106.85

314### Extra for providing frosted glass panes 4 mm thick instead of ordinary float glass

panes 4 mm thick in doors, windows and clerestory window shutters. (Area ofopening for glass panes excluding portion inside rebate shall be measured).

CodDescription Unit Quantity Rate Amount

Cost for 1 sqm.Materials:

###Froasted glass panes (4.0mm) sqm 1 257 257###Deduct cost of ordinary glass p sqm 1 248 – 248.00

thick)Net Cost 9Add 1 % for water charges .09TOTAL 9.09Add 15% for contractor’s profit and overheads 1.36Cost of 1 sqm. 10.45Say 10.45

9. Deduct for providing pin headed glass panes instead of ordinary float glass panesweighing 4 mm thick in doors, windows and clerestory windows, shutters (Area ofopening for glass panes excluding portion inside rebate shall be measured).

CodDescription Unit Quantity Rate Amount

Cost for 1 sqm.Materials:

###Pin headed glass panes (4.0mm) sqm 1 160 –160.00###Deduct cost of ordinary glass p sqm 1 248 248

thick)Net Cost 88Add 1 % for water charges .88TOTAL 88.88Add 15% for contractor’s profit and overheads 13.33Cost of 1 sqm. 102.21Say 102.2

9. Extra for providing ISI marked Stainless Steel butt hinges instead of black enamelledM.S. butt hinges with necessary screws. (Shutter area to be measured).

CodDescription Unit Quantity Rate Amount

Details of cost for one door shutter of a door

Page 304: DAR_Vol_1

200xl08cm = 2.16 sqm.stainless steel butt hinges-

###100x60x2.5 mm 10 Nos 6 185 111###50x37x1.5 mm 10 Nos 2 90 18###Stainless steel screws 40 mm 100 Nos 48 157 75.36###Stainless steel screws 20 mm 100 Nos 8 63 5.04

DeductBlack enameled butt hinges

###100x58x1.90mm 10 Nos 6 54 -32.4###50x37x1.5mm 10 Nos 2 28 -5.6

Black enameled Iron###Screws-40mm 100 Nos 48 30 -14.4###Screws-20mm 100 Nos 8 15 -1.2

TOTAL 155.8Add 1 % for water charges 1.56TOTAL 157.36

315CodDescription Unit Quantity Rate Amount

Add 15% for contractor’s profit and overheads 23.6Extra cost of 2.16sqm. of shutter area 180.96Extra cost of 1 sqm. of shutter area 83.78Say 83.8

9. Deduct if fixed shutters (without hinges) are provided instead of openable shuttersfor doors, windows or clerestory windows with :

9.1Stainless steel butt hinges with stainless steel screws:9.15.1.1 For 2nd class teak wood and other inferior class of wood shutters.

CodDescription Unit Quantity Rate AmountDetails of cost of fittings for shutter of size200x108cm = 2.16 sqm.Materials:Anodised aluminum butt hinges

###Stainless steel butt hinges (heav 10 Nos 6 185 111100x60x2.5 mm IS : 12817 marked

###Stainless steel butt hinges 50x37 10 Nos 2 90 1812817 marked

###Stainless steel screws 40 mm 100 Nos 48 157 75.36###Stainless steel screws 20 mm 100 Nos 8 63 5.04

TOTAL 209.4Add 1% for water charges 2.09TOTAL 211.49Add 15% for contractor’s profit and overheads 31.72Cost of 2.16 sqm. 243.21Cost of 1 sqm. 112.6Say 112.6

9. Deduct if fixed shutters (without hinges) are provided instead of openable shuttersfor doors, windows or clerestory windows with :

9.15.2 Black enamelled M.S. butt hinges with necessary screws.9.15.2.1 For 2nd class teak wood and other inferior class of wood shutters.

Page 305: DAR_Vol_1

CodDescription Unit Quantity Rate AmountDetails of cost of hinges with screws forshutters of size200x108cm = 2.16 sqm.Materials:

###Iron butt hinges 100x58x1.90 m 10 Nos 6 54 32.4###Iron butt hinges 50x37x1.50 m 10 Nos 2 28 5.6###Iron screws 40 mm 100 Nos 48 30 14.4###Iron screws 20 mm 100 Nos 8 15 1.2

TOTAL 53.6Add 1% for water charges .54TOTAL 54.14Add 15% for contractor’s profit and overheads 8.12Cost of 2.16 sqm. 62.26Cost of 1 sqm. 28.82Say 28.8

3169. Providing and fixing 25 mm thick shutters for cup board etc. :9.1Panelled or panelled & glazed shutters :9.1Second class teak wood including ISI marked anodised aluminium butt hinges

with necessary screws.

CodDescription Unit Quantity Rate Amount

Details of cost for shutters of a cup-board (halfglazed and half panelled) 200x108cm = 2.16sqm.Materials: Styles-4x200x8.0x2.5cm = 0.016 cum+Rails-Top rail-1x1 10.5x8.0x2.5cm = 0.0022cum+Lock and bottom rail-2x110.5x8.0x2.5cm =0.0044 cum.+ Panels-2x48x41 x 1.6cm = 0.006cum+ Sash bars-2x114x3.8x2.5cm = 0.003cum+6x48x3.8x2.5cm = 0.003 cum+ Beading-16x92x 1.4x 1.2cm = 0.002cumTotal = 0.0366Add for wastage @ 10% = 0.0037 cum. GrandTotal = 0.0403 cum or 40 cudm

###Second class teak wood . 10 cudm 40 410 1,640###Carriage of timber cum .04 60.81 2.43###Float glasses 4.0mm thick sqm .99 248 245.52

Fittings-###Anodised aluminium butt hinges 10 Nos 6 98 58.8

mm###C.P. brass screws 40mm 100 Nos 48 150 72

Labour-###Carpenter 1st class Day 2.4 151.5 363.6###Glazier Day .18 141.6 25.49###Beldar Day .77 135.25 104.14###Sundries L.S 40.43 1 40.43

TOTAL 2,552.41

Page 306: DAR_Vol_1

Add 1 % for water charges 25.52TOTAL 2,577.93Add 15% for contractor’s profit and overheads 386.69Cost of 2.16 sqm. 2,964.62Cost of 1 sqm. 1,372.51Say 1,372.5

### Providing and fixing 25 mm thick shutters for cup board etc. :9.1Glazed shutters:9.16.2.1 Second class teak wood including ISI marked anodised aluminium butt hinge with

necessary screws.CodDescription Unit Quantity Rate Amount

Details of cost for shutter of cup-board200xl08cm = 2.16 sqm.Materials :(i) Teak wood second classStyles : 4x200x9.5x2.5 cm = 0.019 cumRailsTop & intermediate rails2x110.5x9.5x2.5 cm = 0.006 cum

317CodDescription Unit Quantity Rate Amount

Lock and bottom rails2x110.5x19.7x2.5 cm = 0.011 cumBeadings-2x186.1x1.9xl.2cm = 0.001cum+4x171.70x1.9x1.2cm = 0.002cum.Total = 0.039 cum.Add for wastage @ 10% = 0.004 cum.Grand Total = 0.043 cum. 43 cudm

###Teak wood second class 10 cudm 43 410 1,763###(ii) Glasses (10kg/sqm) 4.0mm t sqm 1.27 248 314.96###(iii) Piano hinges 75x45x3.2 mm metre 6 21 12.6###(iv)M.S. screws 25 mm 100 Nos 48 15 7.2###(v) Carriage of timber cum .043 60.81 2.61

Labour:###Carpenter (Avg.) Day 1.83 146.55 268.19###Glazier Day .23 141.6 32.57###Beldar Day .77 135.25 104.14###Sundries L.S 40.43 1 40.43

TOTAL 2,545.7Add 1 % for water charges 25.46TOTAL 2,571.16Add 15% for contractor’s profit and overheads 385.67Cost of 2.16 sqm. 2,956.83Cost of 1 sqm. 1,368.9Say 1,368.9

9. Providing and fixing flat pressed 3 layer particle board medium density exteriorgrade (Grade I) or graded wood particle board IS : 3087 marked to frame, backing orstudding with screws etc. complete (Frames, backing or studding to be paidseparately):

9.17.1 12 mm thick

Page 307: DAR_Vol_1

CodDescription Unit Quantity Rate AmountDetails of cost for 350x200cm = 7sqm.Materials-12mm thick particle board = 7.00sqm.+Add wastage @ 5% = 0.35 sqm.

###Total = 7.35 sqm. sqm 7.35 258 1,896.3###Carriage of particle board L.S 13.52 1 13.52###Sundries and screws L.S 26.91 1 26.91

Labour-###Carpenter 2nd class Day .9 141.6 127.44###Beldar Day 1 135.25 135.25

TOTAL 2,199.42Add 1 % for water charges 21.99TOTAL 2,221.41Add 15% for contractor’s profit and overheads 333.21Cost of 7 sqm. 2,554.62Cost of 1 sqm. 364.95Say 364.95

3189. Providing and fixing flat pressed 3 layer particle board medium density exterior

grade (Grade I) or graded wood particle board IS : 3087 marked to frame, backing orstudding with screws etc. complete (Frames, backing or studding to be paidseparately):

9.17.2 18 mm thick

CodDescription Unit Quantity Rate Amount

Details of cost for 350x200cm = 7sqm.Materials-12mm thick particle board = 7.00sqm.+Add wastage @ 5% = 0.35 sqm.

###Total = 7.35 sqm. sqm 7.35 301 2 212.35###Carriage of particle board L.S 19.76 1 19.76###Sundries and screws L.S 26.91 1 26.91

Labour-###Carpenter 2nd class Day .9 141.6 127.44###Beldar Day 1 135.25 135.25

TOTAL 2 521.71Add 1 % for water charges 25.22TOTAL 2 546.93Add 15% for contractor’s profit and overheads 382.04Cost of 7 sqm. 2 928.97Cost of 1 sqm. 418.42Say 418.4

9. Providing and fixing prelaminated flat pressed 3 layer (medium density) particleboard or graded wood particle board IS: 3087 marked with one side decorative andother side balancing lamination Grade I,Type II exterior grade IS : 12823 marked inshelves with screws and fittings wherever required, edges to be painted withpolyurethene primer (fittings to be paid separately).

9.118mm thick

Page 308: DAR_Vol_1

CodDescription Unit Quantity Rate AmountDetails of cost for 4 nos.75x20cm shelves = 0.60 sqm.Materials-18mm thick particle board =4x75x20cm = 0.60sqm.+Wastage @ 5% = 0.03sqm:

###Total = 0.63 sqm. sqm .63 716 451.08###Carriage of board L.S .91 1 .91

Labour-###Carpenter 2nd class Day .11 141.6 15.58###Beldar Day .06 135.25 8.12###Sundries, Painting edges & ScrewL.S 7.8 1 7.8

TOTAL 483.49Add 1 % for water charges 4.83TOTAL 488.32Add 15% for contractor’s profit and overheads 73.25Cost of 0.60 sqm. 561.57Cost per sqm. 935.95Say 935.95

319### Providing and fixing prelaminated flat pressed 3 layer (medium densitly) particle

board or graded wood particle board IS: 3087 marked with one side decorative andother side blancing lamination Grade I, Type II exterior grade IS: 12823 marked inshelves with screws abnd fittings wherever required, edges to be painted withpolyurethene primer (fittings to be paid separately).

9.125 mm thick

CodDiscription Unit Quantity Rate Amount

Details of cost for 4 nos.75x20cm shelves = 0.60 sqm.Materials-25mm thick particle board =4x75x20cm = 0.60sqm.+Wastage @ 5% = 0.03sqm:

###Total = 0.63 sqm. sqm .63 775 488.25###Carriage of board L.S 1.82 1 1.82

Labour-###Carpenter 2nd class Day .11 141.6 15.58###Beldar Day .06 135.25 8.12###Sundries, Painting edges & ScrewL.S 7.8 1 7.8

TOTAL 521.57Add 1 % for water charges 5.22TOTAL 526.79Add 15% for contractor’s profit and overheads 79.02Cost of 0.60 sqm. 605.81Cost per sqm. 1,009.68Say 1,009.7

### Providing and fixing 25 mm thick shutters for cupboards etc. including ISl markedblack enamelled M.S. butt hinges with necessary screws :

Page 309: DAR_Vol_1

9.1Panelled or panelled and glazed shutters9.19.1.1 Second class teak woodCodDescription Unit Quantity Rate Amount

Details of cost for shutters of a cup board (halfpanelled and half glazed) 200x108cm = 2.16sqm.Materials-Teak wood (2nd class)Styles 4x2.00m = 8.00m+Rails 3x1.105m = 3.315m= 11.315m11.315x0.08x0.025 = 0.023 cum.Panels - 2x0.48x0.41x0.016 = 0.006 cum.Sash bars 2x1.14 = 2.28+6x0.48 = 2.88= 5.165.16x0.038x0.025 = 0.005 cum.Beadings 16x0.92x0.014x0.012 = 0.002cum.total = 0.036 cum.+Add wastage @ 10% = 0.004 cum.Total = 0.040 cum. Say 40 cudm

320CodDescription Unit Quantity Rate Amount

###Teak wood (2nd class) 10 cudm 40 410 1,640###Carriage of timber cum .04 60.81 2.43###Iron hinges-75x47xl .70mm 10 Nos 6 34 20.4###Screws 30mm 100 Nos 48 24 11.52###Glasses 10kg/sqm (4.0mm thick sqm .99 248 245.52

Labour-###Carpenter (Average) Day 2.4 146.55 351.72###Beldar Day .77 135.25 104.14###Glazier Day .18 141.6 25.49###Sundries L.S. 40.43 1 40.43

TOTAL 2,441.65Add 1 % for water charges 24.42TOTAL 2,466.07Add 15% for contractor’s profit and overheads 369.91Cost of 2.16sqm. 2,835.98Cost of 1 sqm. 1,312.95Say 1,312.95

9.19 Providing and fixing 25 mm thick shutters for cupboards etc. including ISI markedblack enamelled M.S. butt hinges with necessary screws :

9.1Glazed shutters9.19.2.1 Second class teak woodCodDescription Unit Quantity Rate Amount

Details of cost for shutter of a door (glazed)200xl08cm = 2.16 sqm.Materials :(i) Teak wood (2nd class)Styles : 4x200x9.5x2.5cm = 0.019cum+

Page 310: DAR_Vol_1

RailsTop & intermediate rails2x110.5x9.5x2.5cm = 0.006cum+Lock and bottom rails2x110.5x19.7x2.5cm = 0.011cum+Beadings-2x186.1x1.9x1.2cm = 0.001cum+4x171.70x1.9x1.2cm = 0.002cum.Total = 0.039 cum.+Add for wastage @ 10% = 0.004cum.Grand Total = 0.043 cum. Say 43 cudm

###Teak wood (2nd class) 10 cudm 43 410 1,763###(ii) Glasses (10 kg/sqm) 4.0mm t sqm 1.27 248 314.96###(iii) Black enamelled M.S. butt 10 Nos 6 54 32.4

hinges 100x58x1.90mm###Black enamelled M.S. butt 10 Nos 2 28 5.6

hinges 50x37x 1.50mm###M.S. Screws 40mm 100 Nos 48 30 14.4###M.S. Screws 20mm 100 Nos 8 15 1.2###(iv) Carriage of timber cum .043 60.81 2.61

Labour:###Carpenter (Avg.) Day 1.83 146.55 268.19###Glazier Day .23 141.6 32.57###Beldar Day .77 135.25 104.14###Sundries L.S. 40.43 1 40.43

TOTAL 2,579.5Add 1% for water charges 25.8TOTAL 2,605.3Add 15% for contractor’s profit and overheads 390.8Cost of 2.16 sqm. 2,996.1Cost of 1 sqm. 1,387.08Say 1,387.1

321### Providing and fixing ISI marked flush door shutters conforming to IS: 2202 (Part I)

decorative type, core of block board construction with frame of 1st class hardwood and well matched teak 3 ply veneering with vertical grains or cross bandsand face veneers on both faces of shutters.

9.235 mm thick including ISI marked Stainless Steel butt hinges with necessary screws.CodDescription Unit Quantity Rate Amount

Details of cost for 2.20 sqm.Materials-

###35mm thick door shutters sqm 2.2 1,100 2,420###Carriage of door L.S. 29.64 1 29.64###Stainless steel butt hinges (heav 10 Nos 6 185 111

100x60x2.5 mm IS : 12817 marked###Stainless steel screws 40 mm 100 Nos 48 157 75.36

Labour-For fixing shutter and fittings

###Carpenter (Average) Day .55 146.55 80.6###Beldar Day .55 135.25 74.39

TOTAL 2,790.99Add 1% for water charges 27.91

Page 311: DAR_Vol_1

TOTAL 2,818.9Add 15% for contractor’s profit and overheads 422.84Cost for 2.2 sqm. 3,241.74Cost of 1 sqm. 1,473.52Say 1,473.5

9.20 Providing and fixing ISI marked flush door shutters conforming to IS: 2202 (PartI) decorative type, core of block board construction with frame of 1st class hardwood and well matched teak 3 ply veneering with vertical grains or cross bandsand face veneers on both faces of shutters.

9.230 mm thick including ISI marked Stainless Steel butt hinges with necessaryscrews.

CodDescription Unit Quantity Rate AmountDetails of cost for 2.2 sqm.Materials-

###30mm thick door shutters sqm 2.2 1,050 2,310###Carriage of door L.S. 29.64 1 29.64###Stainless steel butt hinges (heav 10 Nos 6 185 111

100x60x2.5 mm IS : 12817 marked###Stainless steel screws 40 mm 100 Nos 48 157 75.36

Labour-For fixing shutter and fittings.

###Carpenter (Average) Day .55 146.55 80.6###Beldar Day .55 135.25 74.39

TOTAL 2,680.99Add 1 % for water charges 26.81TOTAL 2,707.8Add 15% for contractor’s profit and overheads 406.17Cost for 2.2 sqm. 3,113.97Cost of 1 sqm. 1,415.44Say 1,415.45

322### Providing and fixing ISI marked flush door shutters conforming to IS: 2202 (Part I)

decorative type, core of block board construction with frame of 1st class hardwood and well matched teak 3 ply veneering with vertical grains or cross bandsand face veneers on both faces of shutters.

9.225 mm thick (for cupboard) including ISI marked nickel plated bright finished M.S.Piano hinges IS : 3818 marked with necessary screws.

CodDescription Unit Quantity Rate AmountDetails of cost for 2.2 sqm.Materials-

###25mm thick door shutters sqm 2.2 1 000.00 2,200###Carriage of door L.S. 29.64 1 29.64

Fittings-For a door 2.2x1.00m = 2.20 sqm.###Nickel plated bright finished M.S metre 4.4 21 92.4###Screws 25mm 100 Nos 125 15 18.75

Labour-For fixing shutter and fittings.

###Carpenter (Average) Day .55 146.55 80.6###Beldar Day .55 135.25 74.39

TOTAL 2,495.78

Page 312: DAR_Vol_1

Add 1% for water charges 24.96TOTAL 2,520.74Add 15% for contractor’s profit and overheads 378.11Cost for 2.2 sqm. 2,898.85Cost of 1 sqm. 1,317.66Say 1,317.65

9.21 Providing and fixing ISI marked flush door shutters conforming to IS: 2202 (Part I)non-decorative type, core of block board construction with frame of 1st class hardwood and well matched commercial 3 ply veneering with vertical grains or crossbands and face veneers on both faces of shutters:

9.235 mm thick including ISI marked Stainless Steel butt hinges with necessaryscrews.

CodDescription Unit Quantity Rate AmountDetails of cost for 2.2 sqm.Materials-

###35mm thick door shutters sqm 2.2 632 1,390.4###Carriage of door L.S. 29.64 1 29.64

Fittings-For a door 2.2x1.0m = 2.20 sqm.###Stainless steel butt hinges (heav 10 Nos 6 185 111

100x60x2.5 mm IS : 12817 marked###Stainless steel screws 40 mm 100 Nos 48 157 75.36

Labour-For fixing shutter and fittings.

###Carpenter (Average) Day .55 146.55 80.6###Beldar Day .55 135.25 74.39

TOTAL 1,761.39Add 1 % for water charges 17.61TOTAL 1,779Add 15% for contractor’s profit and overheads 266.85Cost for 2.2 sqm. 2,045.85Cost of 1 sqm. 929.93Say 929.95

3239.21 Providing and fixing ISI marked flush door shutters conforming to IS: 2202 (Part I)

non-decorative type, core of block board construction with frame of 1st classhard wood and well matched commercial 3 ply veneering with vertical grains orcross bands and face veneers on both faces of shutters:

9.230 mm thick including ISI marked Stainless Steel butt hinges with necessary screws.CodDescription Unit Quantity Rate Amount

Details of cost for 2.2 sqm.Materials-

###30mm thick door shutters sqm 2.2 610 1 342.00###Carriage of door L.S. 29.64 1 29.64

Fittings-For a door 2.2x1.0m = 2.20 sqm.###Stainless steel butt hinges (heav 10 Nos 6 185 111

100x60x2.5 mm IS : 12817 marked###Stainless steel screws 40 mm 100 Nos 48 .00 157 75.36

Labour-For fixing shutter and fittings.

###Carpenter (Average) Day .55 146.55 80.6###Beldar Day .55 135.25 74.39

Page 313: DAR_Vol_1

TOTAL 1 712.99Add 1 % for water charges 17.13TOTAL 1 730.12Add 15% for contractor’s profit and overheads 259.52Cost for 2.2 sqm. 1 989.64Cost of 1 sqm. 904.38Say 904.4

### Providing and fixing ISI marked flush door shutters conforming to IS: 2202 (Part I)non-decorative type, core of block board construction with frame of 1st class hardwood and well matched commercial 3 ply veneering with vertical grains or crossbands and face veneers on both faces of shutters :

9.225mm thick (for cupboard) including ISI marked nickel plated bright finished M.S.piano hinges with necessary screws.

CodDescription Unit Quantity Rate AmountDetails of cost for 2.2 sqm.Materials-

###25mm thick door shutters sqm 2.2 600 1,320###Carriage of door L.S. 29.64 1 29.64

Fittings-For a door 2.2x1.0m = 2.20 sqm.###Nickel plated bright finished M.S metre 4.4 21 92.4###Screws 25mm 100 Nos 125 15 18.75

Labour-For fixing shutter and fittings.

###Carpenter (Average) Day .55 146.55 80.6###Beldar Day .55 135.25 74.39

TOTAL 1,615.78Add 1% for water charges 16.16TOTAL 1,631.94Add 15% for contractor’s profit and overheads 244.79Cost for 2.2 sqm. 1,876.73Cost of 1 sqm. 853.06Say 853.05

324### Extra for Providing and fixing flush doors with decorative veneering

9.2On one side in item no. 9.21CodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm.###Extra for providing teak veneerin sqm 1 225 225

instead of commercial veneeringTOTAL 225Add 1% for water charges 2.25TOTAL 227.25Add 15% for contractor’s profit and overheads 34.09Cost for one sqm. 261.34Say 261.35

### Extra for providing lipping with 2nd class teak wood battens 25 mm minimumdepth on all edges of shutters (over all area of door shutter to be measured) Overitem no. 9.20 and 9.21.

CodDescription Unit Quantity Rate AmountDetails of cost for 1 sqm. of door area

###Door area sqm of door 1 245 245

Page 314: DAR_Vol_1

area.TOTAL 245Add 1 % for water charges 2.45TOTAL 247.45Add 15% for contractor’s profit and overheads 37.12Cost for one sqm. of door area 284.57Say 284.55

### Extra for providing vision panel not exceeding 0.1 sqm in all type of flush doors(cost of glass excluded) (overall area of door shutter to be measured):

9.2Rectangular or square.CodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm. of door area0753 Rectangular or square per sqm of door 1 86 86

areaTOTAL 86Add 1 % for water charges .86TOTAL 86.86Add 15% for contractor’s profit and overheads 13.03Cost for one sqm. of door area 99.89Say 99.9

### Extra for providing vision panel not exceeding 0.1 sqm in all type of flush doors(cost of glass excluded) (overall area of door shutter to be measured):

9.2Circular.CodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm. of door area0754 Circular panel door area sqm of door 1 118 118

areaTOTAL 118Add 1% for water charges 1.18TOTAL 119.18Add 15% for contractor’s profit and overheads 17.88Cost for one sqm. of door area 137.06Say 137.05

325### Extra if louvers (not exceeding 0.2 sqm) are provided in flush door shutters (overall

area of door shutters to be measured).9.2Decorative type door.CodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm. of door area###Decorative type door sqm of 1 210 210

door areaTOTAL 210Add 1 % for water charges 2.1TOTAL 212Add 15% for contractor’s profit and overheads 31.82Cost for one sqm. of door area 243.92Say 243.9

### Extra for cutting rebate in flush door shutters (Total area of the shutter to bemeasured).

CodDescription Unit Quantity Rate Amount

Page 315: DAR_Vol_1

Details of cost for 1 sqm. of door area0757 Door area sqm of 1 57 57

door areaTOTAL 57Add 1% for water charges .57TOTAL 57.57Add 15% for contractor’s profit and overheads 8.64Cost for one sqm. of door area 66.21Say 66.2

### Providing and fixing 35mm thick wire gauze shutters using galvanised M.S. wiregauze of average width of aperture 1.4mm with wire of dia. 0.63 mm for doors,windows and clerestory windows including ISI marked bright finished or/andblack enamelled M.S. butt hinges with necessary screws:

9.27.1 Second class teak wood.

CodDescription Unit Quantity Rate AmountDetails of cost for door shutters2.00x1.08m = 2.16 sqm.Materials-Teak wood (2nd class)Styles 4x200x9.5x3.5cm = 0.0266cum+Top Rail - 1x110.5x9.5x3.5cm = 0.0036cum+Lock and bottom rail2x110.5x 19.7x3.5cm = 0.0152 cum.+Beadings - (2x312+2x150)x(1.2)x(1.2)cm =0.001 cum.Total = 0.0464 cum.+Add for wastage @ 10% = 0.005 cum.= 0.0514 cum.Say 51.4 cudm.

326CodDescription Unit Quantity Rate Amount###Teak wood (2nd class) 10 cudm 51.4 410 2 107.40

Wire gauge 2x160x40cm = 1.28 sqm.+Add wastage @ 10% = 0.13 sqm.Total= 1.41 sqm.

###Wire gauge sqm 1.41 142 200.22###M.S. butt hinges 100x58x1.90 10 Nos 6 54 32.4###M.S. butt hinges 50x37x1.50 10 Nos 2 28 5.6###M.S. screws 40 mm 100 Nos 48 30 14.4###M.S. screws 20 mm 100 Nos 8 15 1.2###Carriage of timber cum .0514 60.81 3.13

Labour-###Carpenter 1st class Day 1.3 151.5 196.95###Carpenter 2nd class Day .9 141.6 127.44###Beldar Day 1.05 135.25 142.01###Mistry Day .105 151.5 15.91###Sundries L.S. 33.8 1 33.8

TOTAL 2 880.46Add 1 % for water charges 28.8TOTAL 2 909.26

Page 316: DAR_Vol_1

Add 15% for contractor’s profit and overheads 436.39Cost of 2.16 sqm. 3 345.65Cost of 1 sqm. 1 548.91Say 1 548.90

### Providing and fixing 35mm thick wire gauze shutters using galvanised M.S. wiregauze of average width of aperture 1.4mm with wire of dia. 0.63 mm for doors,windows and clerestory windows including ISI marked bright finished or/andblack enamelled M.S. butt hinges with necessary screws:

9.27.2 Kiln seasoned and chemically treated Hollock wood.CodDescription Unit Quantity Rate Amount

Details of cost for door shutters2.00x1.08m = 2.16sqm.Materials-Hollock woodStyles 4x200x9.5x3.5cm = 0.0266cum+Top Rail - 1x110.5x9.5x3.5cm = 0.0036cum+Lock and bottom rail2x110.5xl9.7x3.5cm = 0.0152 cum.+Beadings - (2x312+2x 150)x( 1.2)x( 1.2)cm =0.001 cum.Total = 0.0464 cum.+Add for wastage @ 10% = 0.005 cum.= 0.0514 cum.Say 51.4 cudm.

###Hollock wood 10 cudm 51.4 230 1,182.2###Carriage of timber cum .0514 60.81 3.13###Kiln seasoning of timber cum .0514 539 27.7###Chemical treatment L.S. 8.97 1 8.97

Wire gauge 2xl60x40cm = 1.28 sqm.+Add wastage @ 10% = 0.13 sqm.Total= 1.41 sqm.

###Wire gauge sqm 1.41 142 200.22###Iron butt hinges 100x58x1.90 m 10 Nos 6 54 32.4###Iron butt hinges 50x37x1.50 mm10 Nos 2 28 5.6###M.S. screws 40 mm 100 Nos 48 30 14.4

327CodDescription Unit Quantity Rate Amount###M.S. screws 20 mm 100 Nos 8 15 1.2

Labour-###Carpenter 1st class Day 1.3 151.5 196.95###Carpenter 2nd class Day .9 141.6 127.44###Beldar Day 1.05 135.25 142.01###Mistry Day .105 151.5 15.91###Sundries L.S. 33.8 1 33.8

TOTAL 1 991.93Add 1 % for water charges 19.92TOTAL 2 011.85Add 15% for contractor’s profit and overheads 301.78Cost of 2.16 sqm. 2 313.63Cost of 1 sqm. 1 071.13Say 1 071.10

### Providing and fixing 35mm thick wire gauze shutters using galvanised M.S.

Page 317: DAR_Vol_1

wire gauze of average width of aperture 1.4mm with wire of dia. 0.63 mm fordoors, windows and clerestory windows including ISI marked stainless steelbutt hinges with necessary screws :

9.2Second class teak wood.CodDescription Unit Quantity Rate Amount

Details of cost for door shutters2.00x1.08m = 2.16sqm.Materials-Second class Teak woodStyles 4x200x9.5x3.5cm = 0.0266cum+Top Rail - 1x110.5x9.5x3.5cm = 0.0036cum+Lock and bottom rail2x110.5x19.7x3.5cm = 0.0152 cum.+Beadings - (2x312+2x 150)x( 1.2)x( 1.2)cm =0.001 cum.Total = 0.0464 cum.+Add for wastage @ 10% = 0.005 cum.= 0.0514 cum.Say 51.4 cudm.

###Second class Teak wood 10 cudm 51.4 410 2 107.40Wire gauge 2x160x40cm = 1.28 sqm.+Add wastage @ 10% = 0.13 sqm.Total= 1.41 sqm.

###Wire gauge sqm 1.41 142 200.22###Stainless steel butt hinges (hea 10 Nos 6 185 111

100x60x2.5 mm IS : 12817 marked###Stainless steel butt hinges 50x37x1.5 mm IS : 10 No 2 90 18

12817 marked###Stainless steel screws 40 mm 100 Nos 48 157 75.36###Stainless steel screws 20 mm 100 Nos 8 63 5.04###Carriage of timber cum .0514 60.81 3.13

Labour-###Carpenter 1st class Day 1.3 151.5 196.95###Carpenter 2nd class Day .9 141.6 127.44###Beldar Day 1.05 135.25 142.01###Mistry Day .105 151.5 15.919s9Sundries L.S. 33.8 1 33.8

TOTAL 3 036.26Add 1 % for water charges 30.36TOTAL 3 066.62Add 15% for contractor’s profit and overheads 459.99Cost of 2.16 sqm. 3 526.61Cost of 1 sqm. 1 632.69Say 1 632.70

328### Providing and fixing 35mm thick wire gauze shutters using galvanised M.S. wire

gauze of average width of aperture 1.4mm with wire of dia. 0.63 mm for doors,windows and clerestory windows including ISI marked stainless steel butthinges with necessary screws :

9.2Kiln seasoned and chemically treated Hollock wood.

Page 318: DAR_Vol_1

CodDescription Unit Quantity Rate AmountDetails of cost for door shutters2.00x1.08m = 2.16 sqm.Materials-Hollock woodStyles 4x200x9.5x3.5cm = 0.0266cum+Top Rail - 1x1 10.5x9.5x3.5cm = 0.0036cum+Lock and bottom rail2x110.5x19.7x3.5cm = 0.0152 cum.+Beadings - (2x312+2x 150)x( 1.2)x( 1.2)cm =0.001 cum.Total = 0.0464 cum.+Add for wastage @ 10% = 0.005 cum.= 0.0514 cum.Say 51.4 cudm.

###Hollock wood 10 cudm 51.40 230 1 182.20###Kiln seasoning cum .0514 539 27.7###Chemical treatment L.S. 8.97 1 8.97

Wire gauge 2x160x40cm = 1.28 sqm.+Add wastage @ 10% = 0.13 sqm.Total= 1.41 sqm.

###Wire gauge sqm 1.41 142 200.22###Stainless steel butt hinges (hea 10 Nos 6 185 111

100x60x2.5 mm IS : 12817 marked###Stainless steel butt hinges 50x3 10 Nos 2 90 18

12817 marked###Stainless steel screws 40 mm 100 Nos 48 157 75.36###Stainless steel screws 20 mm 100 Nos 8 63 5.04###Carriage of timber cum .0514 60.81 3.13

Labour-###Carpenter 1st class Day 1.3 151.5 196.95###Carpenter 2nd class Day .9 141.6 127.44###Beldar Day 1.05 135.25 142.01###Mistry Day .105 151.5 15.91###Sundries L.S. 33.8 1 33.8

TOTAL 2 147.73Add 1 % for water charges 21.48TOTAL 2 169.21Add 15% for contractor’s profit and overheads 325.38Cost of 2.16 sqm. 2 494.59Cost of 1 sqm. 1 154.90Say 1 154.90

329### Providing and fixing 30mm thick wire gauge shutters using galvanised M.S. wire

gauge of average width of aperture 1.4mm with wire of dia. 0.63 mm for doors,windows and clerestory windows including ISI marked Stainless Steel butthinges with necessary screws :

9.29.1 Second class teak wood.

CodDescription Unit Quantity Rate AmountDetails of cost for door shutters2.00x1.08m = 2.16 sqm.

Page 319: DAR_Vol_1

Materials-Teak wood (2nd class)Styles 4x209x9.5x3cm = 0.023 cum+Top Rail - 1x110.5x9.5x3cm = 0.003cum+Lock and bottom rail2x110.5xl9.7x3cm = 0.013 cum+Beadings - (2x312+2x150)x(1.2)x(1.2)cm =0.001 cum.Total = 0.040 cum+Add for wastage @ 10% = 0.004 cum.= 0.044 cum.Say 44 cudm.

###Teak wood (2nd class) 10 cudm 44. 00 410 1 804.00###Carriage of timber cum .044 60.81 2.68

Wire gauge 2xl60x40cm = 1.28 sqm.+Add wastage @ 10% = 0.13 sqm.Total= 1.41 sqm.

###Wire gauge sqm 1.41 142 200.22###Stainless steel butt hinges (hea 10 Nos 6 155 93

75x50x2.5 mm IS : 12817 marked###Stainless steel screws 40 mm 100 Nos 48 157 75.36

Labour-###Carpenter 1st class Day 1.2 151.5 181.8###Carpenter 2nd class Day .8 141.6 113.28###Beldar Day .95 135.25 128.49###Mistry Day .08 151.5 12.12###Sundries L.S. 33.8 1 33.8

TOTAL 2 644.75Add 1% for water charges 26.45TOTAL 2 671.20Add 15% for contractor’s profit and overheads 400.68Cost of 2.16 sqm. 3 071.88Cost of 1 sqm. 1 422.17Say 1 422.15

### Providing and fixing 30mm thick wire gauge shutters using galvanised M.S. wiregauge of average width of aperture 1.4mm with wire of dia. 0.63 mm for doors,windows and clerestory windows including ISI marked Stainless Steel butthinges with necessary screws :

9.29.2 Kiln seasoned and chemically treated Hollock wood.CodDescription Unit Quantity Rate Amount

Details of cost for door shutters2.00x1.08m = 2.16sqm.Materials-Hollock woodStyles 4x209x9.5x3cm = 0.023 cum+

330CodDescription Unit Quantity Rate Amount

Top Rail - 1x110.5x9.5x3cm = 0.003cum+Lock and bottom rail2x110.5x19.7x3cm = 0.013 cum+Beadings - (2x312+2x 150)x( 1.2)x( 1.2)cm =0.001 cum.

Page 320: DAR_Vol_1

Total = 0.040 cum+Add for wastage @ 10% = 0.004 cum.= 0.044 cum.Say 44 cudm.

###Hollock wood 10 cudm 44 230 1 012.00###Kiln seasoning cum .044 539 23.72###Chemical treatment L.S. 8.97 1 8.97###Carriage of timber cum .044 60.81 2.68

Wire gauge 2x160x40cm = 1.28 sqm.+Add wastage @ 10% = 0.13 sqm.Total= 1.41 sqm.

###Wire gauge sqm 1.41 142 200.22###Stainless steel butt hinges (hea 10 Nos 6 155 93

75x50x2.5 mm IS : 12817 marked###Stainless steel screws 40 mm 100 Nos 48 157 75.36

Labour-###Carpenter 1st class Day 1.2 151.5 181.8###Carpenter 2nd class Day .8 141.6 113.28###Beldar Day .95 135.25 128.49###Mistry Day .08 151.5 12.12###Sundries L.S. 33.8 1 33.8

TOTAL 1 885.44Add 1% for water charges 18.85TOTAL 1 904.29Add 15% for contractor’s profit and overheads 285.64Cost of 2.16 sqm. 2 189.93Cost of 1 sqm. 1 013.86Say 1 013.85

### Providing and fixing 30mm thick wire gauze shutters using galvanised M.S. wiregauze of average width of aperture 1.4mm with wire of dia 0.63 mm for doors,windows and clerestory windows including ISl marked bright finished or /andblack enamelled M.S. butt hinges with necessary screws :

9.3Second class teak wood.CodDescription Unit Quantity Rate Amount

Details of cost for door shutters2.00x1.08m = 2.16 sqm.Materials-Teak wood (2nd class)Styles 4x209x9.5x3cm = 0.023 cum+Top Rail - 1x110.5x9.5x3cm = 0.003cum+Lock and bottom rail2x110.5xl9.7x3cm = 0.013 cum+Beadings - (2x312+2x150)x(1.2)x(1.2)cm =0.001 cum.Total = 0.040 cum+Add for wastage @ 10% = 0.004 cum.= 0.44 cum.Say 44 cudm.

331CodDescription Unit Quantity Rate Amount###Teak wood (2nd class) 10 cudm 44 410 1 804.00###Carriage of timber cum .044 60.81 2.68

Page 321: DAR_Vol_1

Wire gauge 2x160x40cm = 1.28 sqm.+Add wastage @ 10% = 0.13 sqm.= 1.41 sqm.

###Wire gauge sqm 1.41 142 200.22###Iron butt hinges 100x58x1.90 m 10 Nos 6 54 32.4###Iron butt hinges 50x37x1.50 mm10 Nos 2 28 5.6###M.S. screws 40 mm 100 Nos 48 30 14.4###M.S. screws 20 mm 100 Nos 8 15 1.2

Labour-###Carpenter 1st class Day 1.2 151.5 181.8###Carpenter 2nd class Day .8 141.6 113.28###Beldar Day 1 135.25 135.25###Mistry Day .1 151.5 15.15###Sundries L.S. 33.8 1 33.8

TOTAL 2 539.78Add 1% for water charges 25.4TOTAL 2 565.18Add 15% for contractor’s profit and overheads 384.78Cost of 2.16 sqm. 2 949.96Cost of 1 sqm. 1 365.72Say 1 365.70

### Providing and fixing 30mm thick wire gauze shutters using galvanised M.S. wiregauze of average width of aperture 1.4mm with wire of dia 0.63 mm for doors,windows and clerestory windows including ISI marked bright finished or/and blackenamelled M.S. butt hinges with necessary screws:

9.30.2 Kiln seasoned and chemically treated Hollock wood.CodDescription Unit Quantity Rate Amount

Details of cost for door shutters2.00x1.08m = 2.16sqm.Materials-Hollock woodStyles 4x209x9.5x3cm = 0.023 cum+Top Rail - 1x110.5x9.5x3cm = 0.003cum+Lock and bottom rail2x110.5x19.7x3cm = 0.013 cum+Beadings - (2x312+2x150)x( 1.2)x( 1.2)cm =0.001 cum.Total = 0.040 cum+Add for wastage @ 10% = 0.004 cum.= 0.44 cum.Say 44 cudm.

###Hollock wood 10 cudm 44 230 1,012###Carriage of timber cum .044 60.81 2.68###Kiln seasoning cum .044 539 23.72###Chemical treatment L.S. 9.1 1 9.1

Wire gauge 2xl60x40cm = 1.28 sqm.+Add wastage @ 10% = 0.13 sqm.= 1.41 sqm.

###Wire gauge sqm 1.41 142 200.22###Iron butt hinges 100x58x 1.90 m 10 Nos 6 54 32.4###Iron butt hinges 50x37x1.50 mm 10 Nos 2 28 5.6

332

Page 322: DAR_Vol_1

CodDescription Unit Quantity Rate Amount

###M.S. screws 40 mm 100 Nos 48 30 14.4###M.S. screws 20 mm 100 Nos 8 15 1.2

Labour-###Carpenter 1st class Day 1.2 151.5 181.8###Carpenter 2nd class Day .8 141.6 113.28###Beldar Day 1 135.25 135.25###Mistry Day .1 151.5 15.15###Sundries L.S. 33.8 1 33.8

TOTAL 1,780.6Add 1 % for water charges 17.81TOTAL 1,798.41Add 15% for contractor’s profit and overheads 269.76Cost of 2.16 sqm. 2,068.17Cost of 1 sqm. 957.49Say 957.5

### Providing and fixing wire gauze laminated veneer lumber shutters conforming to IS :14616, and as per TADS 15 :2001 (Part B) using galvanised wire gauze with averagewidth of aperture 1.4mm in both directions with wire of dia 0.63mm as per IS : 1568for doors, windows and clerestory windows including ISI marked bright finishedor/ and black enamelled M.S. butt hinges with necessary screws as per directionsof Engineer-in-charge:

9.31.1 35 mm thick shuttersCodDescription Unit Quantity Rate Amount

Details of cost of one shutter220xl08cm = 2.38sqm.Materials:

###Factory made shutters LVL syles, sqm 2.38 1,328 3 160.64panels of galvanised wire gauge

###Carriage of shutters L.S. 29.64 1 29.64Fittings :

###Black enamelled M.S. Butt 10 Nos 6 54 32.4hinges-100x58x1.9mm

###Black enamelled M.S. Butt hing 10 Nos 2 28 5.6###M.S. Screws 40mm 100 Nos 48 30 14.4###M.S. Screws 20mm 100 Nos 8 15 1.2

Labour:###Carpenter Average Day .52 146.55 76.21###Beldar Day .6 135.25 81.15###Sundries L.S. 35.88 1 35.88

TOTAL 3 437.12Add 1 % for water charges 34.37TOTAL 3 471.49Add 15% for contractor’s profit and overheads 520.72Cost of 2.38 sqm. 3 992.21Cost of 1 sqm. 1 677.40Say 1 677.40

333### Providing and fixing wire gauze laminated veneer lumber shutters conforming to

IS : 14616, and as per TADS 15 :2001 (Part B) using galvanised wire gauze with

Page 323: DAR_Vol_1

average width of aperture 1.4mm in both directions with wire of dia 0.63mm as perIS : 1568 for doors, windows and clerestory windows including ISI marked brightfinished or/ and black enamelled M.S. butt hinges with necessary screws as perdirections of Engineer-in-charge:

9.31.2 30 mm thick shutters

CodDescription Unit Quantity Rate AmountDetails of cost of one shutter220xl08cm = 2.38sqm.Materials:

###Factory made shutters LVL syles, sqm 2.38 1,150 2 737.00panels of galvanised wire gauge

###Carriage of shutters L.S. 29.64 1 29.64Fittings:

###Black enamelled M.S. Butt 10 Nos 6 54 32.4hinges-100x5 8x1.9mm

###Black enamelled M.S. Butt hinges10 Nos 2 28 5.6###M.S. Screws 40mm 100 Nos 48 30 14.4###M.S. Screws 20mm 100 Nos 8 15 1.2

Labour:###Carpenter Average Day .52 76.21###Beldar Day .6 135.25 81.15###Sundries L.S. 35.88 1 35.88

TOTAL 3,013.48Add 1% for water charges 30.13TOTAL 3,043.61Add 15% for contractor’s profit and overheads 456.54Cost of 2.38 sqm. 3,500.15Cost of 1 sqm. 1,470.65Say 1,470.65

### Providing 50x50x50mm 2nd class teak wood plugs including cutting brick work andfixing in cement mortar 1:3 (1 cement: 3 fine sand) and making good the walls etc.

CodDescription Unit Quantity Rate AmountDetails of cost for 100 Nos.Materials:Teak wood (2nd class) 100x(50x50x50)mm =0.0125cumAdd wastage @ 10% = 0.0013 cum.Total =0.0138 cum.Say 14 cudm.

###Teak wood (2nd class) 10 cudm 14 394 551.6###Carriage of timber cum .014 60.81 .85

Cement mortar 1:3(1 cement: 3 fcum .002 2,870 5.74(Rate as per item No. 3.3)Labour:

###Carpenter 2nd class Day .75 141.6 106.2###Mason 2nd class Day .75 141.6 106.2###Beldar Day .75 135.25 101.44

TOTAL 872.03Add 1 % for water charges 8.72TOTAL 880.75Add 15% for contractor’s profit and overheads 132.11Cost of 100 nos. 1 012.86Cost of 1 no. 10.13Say 10.15

146.55

Page 324: DAR_Vol_1

334### Providing and fixing expandable fasteners of specified size with necessary plastic

sleeves and galvanised M.S. screws including drilling holes in masonry work/CC/R.C.C. and making good etc. complete.

9.33.1 25 mm long

CodDescription Unit Quantity Rate AmountDetails of cost of 10 nos.Materials:

###Expandable fastner 25 mm long wieach 10 6 60sleeve and M.S. screws

###Labour for drilling holes and mak L.S. 20.8 1 20.8and sundriesTOTAL 80.8Add 1 % for water charges .81TOTAL 81.61Add 15% for contractor’s profit and overheads 12.24Cost of 10 nos. 93.85Cost of 1 no. 9.39Say 9.4

### Providing and fixing expandable fasteners of specified size with necessary plasticsleeves and galvanised M.S. screws including drilling holes in masonry work /CC/R.C.C. and making good etc. complete.

9.33.2 32 mm longCodDescription Unit Quantity Rate Amount

Details of cost of 10 nos.Materials:

###Expandable fastner 32 mm long wieach 10 7 70sleeve and M.S. screws

###Labour for drilling holes and mak L.S. 26 1 26and sundriesTOTAL 96Add 1% for water charges .96TOTAL 96.96Add 15% for contractor’s profit and overheads 14.54Cost of 10 nos. 111.5Cost of 1 no. 11.15Say 11.15

### Providing and fixing expandable fasteners of specified size with necessary plasticsleeves and galvanised M.S. screws including drilling holes in masonry work /CC/R.C.C. and making good etc. complete.

9.33.3 40 mm longCodDescription Unit Quantity Rate Amount

Details of cost of 10 nos.Materials:

###Expandable fastner 40 mm long wieach 10 9 90sleeve and M.S. screws

###Labour for drilling holes and mak L.S. 26 1 26and sundriesTOTAL 116Add 1 % for water charges 1.16TOTAL 117.16Add 15% for contractor’s profit and overheads 17.57Cost of 10 nos. 134.73

Page 325: DAR_Vol_1

Cost of 1 no. 13.47Say 13.45

335### Providing and fixing expandable fasteners of specified size with necessary plastic

sleeves and galvanised M.S. screws including drilling holes in masonry work /CC/R.C.C. and making good etc. complete.

9.33.4 50 mm long

CodDescription Unit Quantity Rate AmountDetails of cost of 10 nos.Materials:

###Expandable fastner 50 mm long wieach 10 11 110sleeve and M.S. screws

###Labour for drilling holes and mak L.S. 26 1 26and sundriesTOTAL 136Add 1 % for water charges 1.36TOTAL 137.36Add 15% for contractor’s profit and overheads 20.6Cost of 10 nos. 157.96Cost of 1 no. 15.8Say 15.8

### Providing and fixing 2nd class teak wood plain lining tongued and grooved on andincluding wooden plugs complete with necessary screws and priming coat onunexposed surface.

9.34.1 40 mm thick.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials:Teak wood (2nd class) 10x0.04m = 0.40cum+Add wastage @ 10% = 0.04 cum.= 0.44 cum.Say 440 cudm.

###Teak wood (2nd class) 10 cudm 440 410 18,040###Extra for selected planks 10 cudm 440 80 3,520

Second class teak wood plugs includingcutting brick work and fixing in cement mortar1:3 (1 cement: 3 fine sand)

( (Rate as per item no 9.32 of SH: 9each 55 10.15 558.25 ( Priming coat (Rate as per item nosqm 10 16.55 165.5###Carriage of timber cum .44 60.81 26.76

Labour:For planning and fixing

###Carpenter 1st class Day 2.15 151.5 325.72###Beldar Day 1.62 135.25 219.1###Sundries & screws etc. L.S. 53.82 1 53.82

TOTAL 22,909.15Add for water charges @ 1 % except (B+A) 221.85TOTAL 23,131Add for contractor’s profit and overheads @ 3,361.0915% except (B+A)

Page 326: DAR_Vol_1

Cost of 10 sqm. 26 492.09Cost of 1 sqm. 2,649.21Say 2,649.2

336### Providing and fixing 2nd class teak wood plain lining tongued and grooved on and

including wooden plugs complete with necessary screws and priming coat onunexposed surface.

9.34.2 25 mm thick.

CodDescription Unit Quantity Rate AmountDetails of cost for 10 sqm.Materials:Teak wood 2nd class 10x0.025 = 0.25cum+Add wastage @ 10% = 0.025 cum.= 0.275 cum.Say 275 cudm.

###Teak wood (2nd class) 10 cudm 275 410 11,275###Extra for selected planks 10 cudm 275 80 2,200###Carriage of timber cum .275 60.81 16.72

Second class teak wood plugs includingcutting brick work and fixing in cement mortar1:3 (1 cement: 3 fine sand)

(A (Rate as per item no 9.32 of SH: 9each 55 10.15 558.25 (B Priming coat (Rate as per item nosqm 10 16.55 165.5

Labour:###Carpenter 1 st class Day 2.15 151.5 325.72###Beldar Day 1.62 135.25 219.1###Sundries & screws etc. L.S. 53.82 1 53.82

TOTAL 14,814.11Add for water charges @ 1 % except (B+A) 140.9TOTAL 14,955.01Add for contractor’s profit and overheads @ 2,134.6915% except (B+A)Cost of 10 sqm. 17,089.7Cost of 1 sqm. 1,708.97Say 1,708.95

### Providing and fixing 2nd class teak wood plain lining tongued and grooved on andincluding wooden plugs complete with necessary screws and priming coat onunexposed surface.

9.34.3 20 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials:Teak wood (2nd class) 10x0.02m = 0.20cum.+Add wastage @ 10% = 0.02 cum.= 0.22 cum.Say 220 cudm.

###Teak wood (2nd class) 10 cudm 220 410 9,020###Extra for selected planks 10 cudm 220 72 1,584###Carriage of timber cum .22 60.81 13.38

Second class teak wood plugs including

Page 327: DAR_Vol_1

cutting brick work and fixing in cement mortar1:3 (1 cement: 3 fine sand)

(A (Rate as per item no 9.32 of SH: 9each 55 10.15 558.25 (B Priming coat (Rate as per item nosqm 10 16.55 165.5

Labour:###Carpenter 1 st class Day 1.08 151.5 163.62###Carpenter 2nd class Day .8 141.6 113.28###Beldar Day 1.08 135.25 146.07###Sundries & screws etc. L.S. 53.82 1 53.82

337CodDescription Unit Quantity Rate Amount

TOTAL 11 817.92Add for water charges @ 1 % except (A+B) 110.94TOTAL 11 928.86Add for contractor’s profit and overheads @ 1 680.7715% except (A+B)Cost of 10 sqm. 13 609.63Cost of 1 sqm. 1 360.96Say 1 360.95

### Providing and fixing 2nd class teak wood plain lining tongued and grooved on andincluding wooden plugs complete with necessary screws and priming coat onunexposed surface.

9.34.4 12 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Wood-Second class teak wood 10x0.012 = 0.12cum+Add wastage @ 10% = 0.012 cum.= 0.132 cum.Say 132 cudm.

###Second class teak wood 10 cudm 132 410 5,412###Extra for selected planks 10 cudm 132 72 950.4###Carriage of timber cum .132 60.81 8.03

Second class teak wood plugs includingcutting brick work and fixing in cement mortar1:3 (1 cement: 3 fine sand)

(A (Rate as per item no 9.32 of SH: 9each 55 10.15 558.25Labour:

###Carpenter 1 st class Day 1.08 151.5 163.62###Carpenter 2nd class Day .8 141.6 113.28###Beldar Day 1.08 135.25 146.07 (B Priming coat (Rate as per item nosqm 10 16.55 165.5

SH : Finishing)###Sundries & screws etc. L.S. 53.82 1 53.82

TOTAL 7,570.97Add for water charges @ 1 % except (A+B) 68.47TOTAL 7,639.44Add for contractor’s profit and overheads @ 1,037.3515% except (A+B)Cost of 10 sqm. 8,676.79Cost of 1 sqm. 867.68Say 867.7

Page 328: DAR_Vol_1

### Providing and fixing in wall lining flat pressed three layer (medium density) particleboard or graded wood prelaminated one side decorative lamination on other sidebalancing lamination Grade I,Type II, IS : 12823 marked including priming coat onunexposed surface, with necessary fixing arrangement and screws etc. complete:

9.35.1 12 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-Particle board (three layer medium density)12mm thick = 10 sqm.+Add wastage @ 10% = 1 sqm.= 11 sqm.

###Particle board (three layer medi sqm 11 595 6 545.00###Carriage of particle board L.S. 13.52 1 13.52###Sundries and screws L.S. 26.91 1 26.91

Priming coat ( (Rate as per item no 13.50.1 of SHsqm 10 16.55 165.5

Labour:

338CodDescription Unit Quantity Rate Amount###Carpenter 2nd class Day 1.28 141.6 181.25###Beldar Day 1.43 135.25 193.41###Rawl plug 50 mm (designation 10each 55 7 385

TOTAL 7,510.59Add for water charges @ 1% on all except on (A) 73.45TOTAL 7,584.04

1,112.7815% except (A)Cost of 10 sqm. 8,696.82Cost of 1 sqm. 869.68Say 869.7

### Providing and fixing in wall lining flat pressed three layer (medium density) particleboard or graded wood prelaminated one side decorative lamination on other sidebalancing lamination Grade I, Type II, IS : 12823 marked including priming coat onunexposed surface, with necessary fixing arrangement and screws etc. complete :

9.35.2 18 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-Particle board (three layer medium density)18 mm thick = 10 sqm.+Add wastage @ 10% = 1 sqm.= 11 sqm.

###Particle board (three layer medi sqm 11 716 7,876###Carriage of particle board L.S. 13.52 1 13.52###Sundries and screws L.S. 26.91 1 26.91

Priming coat ( (Rate as per item no 13.50.1 of SHsqm 10 16.55 165.5

Labour:###Carpenter 2nd class Day 1.28 141.6 181.25###Beldar Day 1.43 135.25 193.41

Add for contractor’s profit and overheads @

Page 329: DAR_Vol_1

###Rawl plug 50 mm (designation 10each 55 7 385TOTAL 8,841.59Add for water charges @ 1% on all except on ‘A’ 86.76TOTAL 8 928.35Add for contractor’s profit and overheads @ 1,314.4315% except (A)Cost of 10 sqm. 10 242.78Cost of 1 sqm. 1,024.28Say 1,024.3

### Providing and fixing in wall lining flat pressed three layer (medium density) particleboard or graded wood prelaminated one side decorative lamination on other sidebalancing lamination Grade I, Type II, IS : 12823 marked including priming coat onunexposed surface, with necessary fixing arrangement and screws etc. complete:

9.35.3 25 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-Particle board (three layer medium density)25 mm thick = 10 sqm.+Add wastage @ 10% = 1 sqm.= 11 sqm.

###Prelaminated particle board withsqm 11 775 8,525decorative and other side balancing

339CodDescription Unit Quantity Rate Amount

lamination, flat pressed 3 layer & graded(medium density) Grade I, Type II conformingto IS : 12823 (exterior grade)25 mm thick

###Carriage of particle board L.S. 13.52 1 13.52###Sundries and screws L.S. 26.91 1 26.91

Priming coat (A (Rate as per item no 13.50.1 of SHsqm 10 16.55 165.5

Labour:###Carpenter 2nd class Day 1.28 141.6 181.25###Beldar Day 1.43 135.25 193.41###Rawl plug 50 mm (designation 10each 55 7 385

TOTAL 9,490.59Add for water charges @ 1% on all except on’A’ 93.25ATOTAL 9,583.84Add for contractor’s profit and overheads @ 1,412.7515% except (A)Cost of 10 sqm. 10,996.59Cost of 1 sqm. 1,099.66Say 1,099.65

### Providing and fixing specified wood frame work consisting of battens 50x25mmfixed with rawl plug and drilling necessary holes for rawl plug etc. including primingcoat complete.

9.36.1 Holl 0.0CodDescription Unit Quantity Rate Amount

Details of cost for 5 no. battens of size500cmx50mmx25mm (31.25 cudm)

Page 330: DAR_Vol_1

Materials-Hollock wood- 5x5.00x0.50x0.025 = 0.03125cum+Add wastage @ 5% = 0.00156 cum.= 0.03281 cum.Say 33 cudm.

###Hollock wood 10 cudm 33 230 759###Carriage of timber cum .033 60.81 2.01

Labour:###Carpenter 1 st class Day 1 151.5 151.5###Beldar Day .25 135.25 33.81###Sundries L.S. 6.76 1 6.76

Painting with ready mixed priming coat onground 5x500x15 cm =3.75 sqm

( (Rate as per item no 13.50.1) sqm 3.75 16.55 62.06###Rawl plug 50 mm (designation 10each 55 7 385###Labour for drilling holes steel ta L.S. 71.5 1 71.5

etc.TOTAL 1,471.64Add water charges @ 1 % on all except on cost 14.1of priming coat (A)TOTAL 1,485.74Add contractor’s profit and overheads @ 15% 213.55on all except on cost of priming coat (A)Cost of 31.25 cudm. 1,699.29Cost of 1 cum. 54,377.28Say 54,377.3

340### Providing and fixing decorative plywood 4 mm thick one side decorative veneer

conforming to IS: 1328 (type-1) for plain lining / cladding with necessary screws,priming coat on unexposed surface with:

9.3Decorative veneer facings of approved manufacture.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-Teak ply wood = 10sqm.+Add for wastage @ 20% = 2 sqm.= 12 sqm.

###teak ply wood sqm 12 250 3 000.00###Carriage of ply wood L.S. 5.46 1 5.46

Wooden plugs including cutting brick workand fixing in cement mortar

(B) (Rate as per item no 9.32 of SH each 55 10.15 558.25Labour-

###Carpenter 1st class Day 3.8 151.5 575.7###Beldar Day 4.6 135.25 622.15###Mistry Day .6 151.5 90.9###20mm nails without head for fixinL.S. 53.82 1 53.82

Painting with ready mixed priming coat(A) (Rate as per item no 13.50.1 of SH : Finishin 10 16.55 165.5

TOTAL 5 071.78Add for water charges @ 1% on all except (B+A) 43.48

Page 331: DAR_Vol_1

TOTAL 5 115.26Add for contractor’s profit and overheads @ 658.7315% on all except (B+A)Cost of 10 sqm. 5 773.99Cost of 1 sqm. 577.4Say 577.4

### Providing and fixing 4mm thick coir veneer board, ISI marked IS : 14842 Plainlining with necessary screws, priming coat on unexposed surface etc., complete.

CodDescription Unit Quantity Rate AmountDetails of cost for 10 sqm.Materials-Coir veneered board 4mm thick = 10sqm.+Add for wastage @ 20% = 2 sqm.= 12 sqm.

###Coir veneered board 4mm thick sqm 12 235 2 820.00###Carriage of Coir veneered board L.S. 5.46 1 5.46

Wooden plugs including cutting brick workand fixing in cement mortar

(B) (Rate as per item no 9.32 of SH each 55 10.15 558.25Labour-

###Carpenter 1st class Day 3.8 151.5 575.7###Beldar Day 4.6 135.25 622.15###Mistry Day .6 151.5 90.9###20mm nails without head for fixinL.S. 53.82 1 53.82

Painting with ready mixed priming coat(A) (Rate as per item no 13.50.l of SH : Finishin 10 16.55 165.5

TOTAL 4 891.78Add for water charges @ 1% on all except (B+A) 41.68TOTAL 4 933.46Add for contractor’s profit and overheads @ 631.4615% on all except (B+A)Cost of 10 sqm. 5 564.92Cost of 1 sqm. 556.49Say 556.5

3419.39 Providing and fixing skirting of prelaminated with (one side decorative and other

side balancing lamination) flat pressed, 3 layer or graded particle board (mediumdensity) Grade I, Type II, IS : 12823 marked, with necessary fixing arrangementsand screws including drilling necessary holes for rawl plugs etc. and priming coaton unexposed surface complete :

9.318 mm thickCodDescriptio Unit Quantity Rate Amount

Details of cost for skirting 200mm wide and30m long Area = 0.2x30= 6 sqm.Area = 0.2x30= 6 sqm.Materials-Teak shade prelaminated Particle board(three layer medium density) = 6.0 sqm.+Add wastage @ 10% = 0.6sqm.= 6.6 sqm.

Page 332: DAR_Vol_1

###Particle bo sqm 6.6 716 4,725.6###Carriage of L.S. 8.11 1 8.11###Rawl plug each 102 7 714###Labour for L.S. 130 1 130

Labour:-For dressing and fixing particle board toskirting

###Carpenter Day .77 141.6 109.03###Beldar Day .86 135.25 116.32###Sundries (S L.S. 53.82 1 53.82

Painting with ready mixed priming coat atback(Rate as per item no 13. 6 16.55 99.30 (A)TOTAL ###Add for water charges @ 1% on all except ‘A’ 58.57TOTAL ###Add for contractor’s profit and overheads @ 887.3215% on all except ‘A’Cost of 6 sqm. ###Cost of 1 sqm. ###Say ###

### Providing and fixing skirting of prelaminated with (one side decorative and otherside balancing lamination) flat pressed, 3 layer or graded particle board (mediumdensity) Grade I, Type II, IS : 12823 marked, with necessary fixing arrangementsand screws including drilling necessary holes for rawl plugs etc. and priming coaton unexposed surface complete :

9.325 mm thickCodDescriptio Unit Quantity Rate Amount

Details of cost for skirting 200mm wide and30m long Area = 0.2x30= 6 sqm.Area = 0.2x30= 6 sqm.Materials-Teak shade prelaminated Particle board(three layer medium density) = 6.0 sqm.+Add wastage @ 10% = 0.6sqm.= 6.6 sqm.

###Particle bo sqm 6.6 775 5 115.00###Carriage of L.S. 8.11 1 8.11

342CodDescription Unit Quantity Rate Amount

###Rawl plug 50 mm (designation 10each 102 7 714###Labour for drilling holes L.S. 130 1 130

Labour:-For dressing and fixing particle board toskirting

###Carpenter 2nd class Day .77 141.6 109.03###Beldar Day .86 135.25 116.32###Sundries (Screws, sand paper) L.S. 53.82 1 53.82

Painting with ready mixed priming coat atback

(A) (Rate as per item no 13.50.1 of SHsqm 6 16.55 99.3

Page 333: DAR_Vol_1

TOTAL 6 345.58Add for water charges @ 1% on all except ‘A’ 62.46TOTAL 6 408.04Add for contractor’s profit and overheads @ 946.3115% on all except ‘A’Cost of 6 sqm. 7 354.35Cost of 1 sqm. 1 225.73Say 1 225.70

### Providing and fixing wooden moulded beading to door and window frames withiron screws, plugs and priming coat on unexposed surface etc. complete :

9. 2nd class teak wood9.40.1.1 50x12 mmCodDescription Unit Quantity Rate Amount

Details of cost for beading for a window ofsize 140x110cm i.e. 500cm long (5 metre)Materials-Teak wood Ilnd class in planks500x5x1.2cm = 0.003 cum+Add for wastage @ 10% = 0.0003 cum.= 0.0033 cum. Say 3.3 cudm.

###Second class teak wood 10 cudm 3.3 410 135.3###Carriage of timber cum .0033 60.81 .2###Iron screws 40 mm 100 Nos 36 30 10.8

Painting with priming coat Area =500(5+1.2+1.2) = 0.37 sqm

(B) (Rate as per item no 13.50.1 of SHsqm .37 16.55 6.12Labour-For plaining, fixing and making design

###Carpenter 1st class Day .53 151.5 80.3TOTAL 232.72Add for water charges @ 1% on all except (B) 2.27TOTAL 234.99Add for contractor’s profit and overheads @ 34.3315% on all except (B)Cost of 5 m. 269.32Cost of 1m 53.86Say 53.85

343### Providing and fixing wooden moulded beading to door and window frames with

iron screws, plugs and priming coat on unexposed surface etc. complete :9.42nd class teak wood9.40.1.2 50x20 mmCodDescription Unit Quantity Rate Amount

Details of cost for beading of a window of size140x110cm i.e. 500cm. long (5metre)Materials-Teak wood Ilnd class in planks500x5x2.0cm = 0.005cum+Add for wastage @ 10% = 0.0005 cum.= 0.0055 cum. Say 5.5 cudm.

###Second class teak wood 10 cudm 5.5 410 225.5

Page 334: DAR_Vol_1

###Carriage of timber cum .0055 60.81 .33###Iron screws 40 mm 100 Nos 36 30 10.8

Painting with priming coat Area = 500(5+2+2)= 0.45 sqm

(B) (Rate as per item no 13.50.1 of SH : Finishing) sqm .45 16.55 7.45Labour-For plaining, fixing and making design

###Carpenter 1 st class Day .53 151.5 80.3TOTAL 324.38Add for water charges @ 1% on all except (B) 3.17TOTAL 327.55Add for contractor’s profit and overheads @ 48.0215% on all except (B)Cost of 5 m. 375.57Cost of 1m 75.11Say 75.1

9.40 Providing and fixing wooden moulded beading to door and window frames withiron screws, plugs and priming coat on unexposed surface etc. complete :

9.4Hollock wood9.40.2.1 50x12 mmCodDescription Unit Quantity Rate Amount

Details of cost for beading for a window ofsize 140x110cm i.e. 500cm long (5 metre)Materials-Hollock wood500x5x1.2cm = 0.003 cum+Add for wastage @ 10% = 0.0003 cum.= 0.0033 cum. Say 3.3 cudm.

###Hollock wood 10 cudm 3.3 230 75.9###Carriage of timber cum .0033 60.81 .2###Iron screws 40 mm 100 Nos 36 30 10.8

Painting with priming coat Area =500(5+1.2+1.2) = 0.37 sqm

(B) (Rate as per item no 13.50.l of SH : Finishing) sqm .37 16.55 6.12Labour-For plaining, fixing and making design

###Carpenter 1 st class Day .53 151.5 80.3TOTAL 173.32Add for water charges @ 1% on all except (B) 1.67TOTAL 174.99Add for contractor’s profit and overheads @ 25.3315% on all except (B)Cost of 5 m. 200.32Cost of 1m 40.06Say 40.05

344### Providing and fixing wooden moulded beading to door and window frames with

iron screws, plugs and priming coat on unexposed surface etc. complete :9.4Hollock wood9.40.2.2 50x20 mmCodDescription Unit Quantity Rate Amount

Page 335: DAR_Vol_1

Details of cost for beading for a window ofsize 140x110cm i.e. 500cm long (5 metre)Materials-Hollock wood500x5x200cm = 0.005 cum+Add for wastage @ 10% = 0.0005 cum.= 0.0055 cum. Say 5.5 cudm.

###Hollock wood 10 cudm 5.5 230 126.5###Carriage of timber cum .0055 60.81 .33###Iron screws 40 mm 100 Nos 36 30 10.8

Painting with priming coat Area = 500(5+2+2)= 0.45 sqm

(B) (Rate as per item no 13.50.1 of SHsqm .45 16.55 7.45Labour-For plaining, fixing and making design

###Carpenter 1 st class Day .53 151.5 80.3TOTAL 225.38Add for water charges @ 1% on all except (B) 2.18TOTAL 227.56Add for contractor’s profit and overheads @ 33.0215% on all except (B)Cost of 5 m. 260.58Cost of lm 52.12Say 52.1

### Providing and fixing plain jaffri of 35x10 mm laths placed 35 mm apart (frames tobe paid separately) including fixing 50x12 mm beading complete with :

9.4Second class teak wood.CodDescription Unit Quantity Rate Amount

Details of cost of a jaffri 200x110cm =2.2sqm.Materials-Teakwood Ilnd classJaffri 210x120x1.0cm = 0.025cum.+Beading 660x5x1.2cm = 0.004cum.= 0.029 cum.+Add wastage @ 10% = 0.003 cum.= 0.032 cum. Say 32 cudm.

###Second class teak wood 10 cudm 32 410 1 312.00###Carriage of timber cum .032 60.81 1.95

Labour-###Carpenter 1 st class Day .75 151.5 113.62###Carpenter 2nd class Day 1 141.6 141.6###Beldar Day .5 135.25 67.62###Mistry Day .1 151.5 15.15###Sundries L.S. 33.8 1 33.8

TOTAL 1 685.74Add 1% for water charges 16.86TOTAL 1 702.60Add 15% for contractor’s profit and overheads 255.39Cost of 2.2 sqm. 1 957.99Cost of 1 sqm. 890Say 890

Page 336: DAR_Vol_1

345### Providing and fixing 18 mm thick, 150 mm wide pelmet of flat pressed 3 layer or

graded wood particle board medium density grade I, IS : 3087 marked includingtop cover of 6 mm commercial ply wood conforming to IS: 303 BWR grade, nickelplated M.S. pipe 20 mm dia ( heavy type ) curtain rod with nickel plated bracketsincluding fixing with 25x3 mm M.S. flat 10 cm long and rawl plugs 50 mm long(designation 10 no.) etc all complete

CodDescription Unit Quantity Rate AmountDetails of cost for a pelmet 2m longMaterials-

###(i) 18mm thick particle board (medium densityexterior grade)Front-1x1.7x0.15=0.255sqm.+Sides-2xO. 15x0.15= 0.045sqm.= 0.300sqm.+Add wastage @5% = 0.015sqm.= 0.315sqm. Say 0.32 sqm. sqm .32 301 96.326mm thick commercial ply woodTop-lxl.7x0.15= 0.255sqm.+Add wastage @ 5% = 0.013 sqm.= 0.268 sqm. Say 0.27 sqm.

###Ply wood 5 ply with commercial psqm .27 282 76.14faces 6 mm thick

###Nickle plated M.S. pipe 20 mm dimetre 1.65 54 89.1###Nickle plated M.S. Brackets for curtain rod 2 3 6

mm###Carriage of material L.S. .52 1 .52###M.S. flat 25x3mm and 10cm longL.S. 8.06 1 8.06

brackets###Rawl plug 50 mm (designation 10each 2 7 14

Labour-###Carpenter 2nd class Day .18 141.6 25.49###Beldar Day .18 135.25 24.34###Mistry Day .11 151.5 16.66###Sundries L.S. 2.73 1 2.73

TOTAL 359.36Add for water charge @ 1% 3.59TOTAL 362.95Add for contractor’s profit and overheads @ 54.441,500%Cost of 2 m 417.39Cost of lm. 208.7Say 208.7

### Providing and fixing 18 mm thick, 150 mm wide pelmet of coir veneer board ISImarked IS : 14842 - 2000, including top cover of 6 mm coir veneer board, nickelplated M.S. Pipe 20 mm dia (heavy type) curtain rod with nickel plated bracketsincluding fixing with 25x3 mm M.S. Flat 10 cm long and rawl plug 50 mm long(designation 10 No.) etc., all complete

CodDescription Unit Quantity Rate AmountDetails of cost for a pelmet 2m longMaterials-(i) 18mm thick Coir veneered boardFront-1 x 1.7x0.15= 0.255sqm.+Sides-2xO. 15x0.15= 0.045sqm.= 0.300sqm.+

Page 337: DAR_Vol_1

346CodDescription Unit Quantity Rate Amount

Add wastage @5% = 0.015sqm.= 0.315sqm. Say 0.32 sqm.

###Coir veneered board 18mm thick sqm .32 820 262.46mm thick commercial ply woodTop-1 x 1.7x0.15= 0.255sqm.+Add wastage @ 5% = 0.013 sqm.= 0.268 sqm. Say 0.27 sqm.

###Coir veneered board 6mm thick sqm .27 308 83.16###Nickle plated M.S. pipe 20 mm dimetre 1.65 54 89.1###Nickle plated M.S. Brackets for curtain rod 2 3 6

mm###Carriage of material L.S. .52 1 .52###M.S. flat 25x3mm and 10cm longL.S. 8.06 1 8.06

brackets###Rawl plug 50 mm (designation 10each 2 7 14

Labour-###Carpenter 2nd class Day .18 141.6 25.49###Beldar Day .18 135.25 24.34###Mistry Day .11 151.5 16.66###Sundries L.S. 2.73 1 2.73

TOTAL 532.46Add for water charge @ 1% 5.32TOTAL 537.78Add for contractor’s profit and overheads @ 80.671,500%Cost of 2 m 618.45Cost of lm. 309.23Say 309.2

### Extra for using veneered particle board conforming to IS 3097 Grade I, in item ofpelmet 18mm thick 150mm wide.

9.4Non decorative veneer on both sides.CodDescription Unit Quantity Rate Amount

Details of cost for a pelmet 2m longMaterials-(i) 18mm thick particle board (medium densityexterior grade)Front-lxl.7x0.15= 0.255sqm.+Sides-2xO. 15x0.15= 0.045sqm.= 0.300sqm.+ Add wastage @5% = 0.015sqm.= 0.315sqm. Say 0.32 sqm.

0347 Extra cost for commercial sqm .32 102 32.64sidesTOTAL 32.64Add for water charge @ 1% .33TOTAL 32.97Add for contractor’s profit and overheads @ 4.951,500%Cost of 2m 37.92Cost of lm. 18.96Say 18.95

Page 338: DAR_Vol_1

3479.44 Extra for using veneered particle board conforming to IS 3097 Grade I, in item of

pelmet 18mm thick 150mm wide.9.4Particle board with decorative veneering on both sides.CodDescription Unit Quantity Rate Amount

Details of cost for a pelmet 2m longMaterials-(i) 18mm thick particle board (medium densityexterior grade)Front-lxl.7x0.15= 0.255sqm.+Sides-2xO. 15x0.15= 0.045sqm.= 0.300sqm.+Add wastage @5% = 0.015sqm.= 0.315sqm. Say 0.32 sqm.

0348 Extra cost for prelaminated particle .32 366 117.12teak finish both sidesTOTAL 117.12Add for water charge @ 1 % 1.17TOTAL 118.29Add for contractor’s profit and overheads @ 17.741,500%Cost of 2m 136.03Cost of lm. 68.02Say 68

### Providing and fixing teak wood lipping of size 25x3 mm in pelmet.CodDescription Unit Quantity Rate Amount

Details of cost for 10 metreMaterials-

###Lipping with teak wood 25x3 mmmetre 10 16 160Labour-

###Carpenter 2nd class Day .25 141.6 35.4###Beldar Day .25 135.25 33.81

TOTAL 229.21Add for water charge @ 1 % 2.29TOTAL 231.5Add for contractor’s profit and overheads @ 34.721,500%Cost for 10 meter 266.22Cost of lm. 26.62Say 26.6

### Providing and fixing curtain rods of 1.25 mm thick chromium plated brass plate,with two chromium plated brass brackets fixed with C.P. brass screws and woodenplugs, etc., wherever necessary complete :

9.412 mm dia.CodDescription Unit Quantity Rate Amount

Details of cost for 2m longMaterials-

###C.P. brass curtain rod 12 mm dia metre 2 122 244###C.P. brass brackets each 2 5 10###C.P. brass screws L.S. 4.03 1 4.03###Carriage L.S. 1.56 1 1.56

Wooden plugs including cutting brick work

Page 339: DAR_Vol_1

and fixing in cement mortar 1:3 (1 cement: 3fine sand)

348CodDescription Unit Quantity Rate Amount ( (Rate as per item no 9.32 of SH each 2 10.15 20.3###Labour L.S. 2.73 1 2.73###Sundries L.S. 1.56 1 1.56

TOTAL 284.18Add for water charge @ 1% on all except (B) 2.64TOTAL 286.82Add for contractor’s profit and overheads @ 39.9815% on all except (B)Cost of 2m 326.8Cost of lm. 163.4Say 163.4

### Providing and fixing curtain rods of 1.25 mm thick chromium plated brass plate,with two chromium plated brass brackets fixed with C.P. brass screws and woodenplugs, etc., wherever necessary complete :

9.420 mm dia.CodDescription Unit Quantity Rate Amount

Details of cost for 2m longMaterials-

###C.P. brass curtain rod 20 mm dia metre 2 143 286###C.P. brass brackets each 2 5 10###C.P. brass screws L.S. 4.03 1 4.03###Carriage L.S. 1.56 1 1.56

Wooden plugs including cutting brick workand fixing in cement mortar 1:3 (1 cement: 3fine sand)

(B (Rate as per item no 9.32 of SH each 2 10.15 20.3###Labour L.S. 2.73 1 2.73###Sundries L.S. 1.56 1 1.56

TOTAL 326.18Add for water charge @ 1% on all except (B) 3.06TOTAL 329.24Add for contractor’s profit and overheads @ 46.3415% on all except (B)Cost of 2m 375.58Cost of lm. 187.79Say 187.8

### Providing and fixing curtain rods of 1.25 mm thick chromium plated brass plate,with two chromium plated brass brackets fixed with C.P. brass screws and woodenplugs, etc., wherever necessary complete :

9.425 mm dia.CodDescription Unit Quantity Rate Amount

Details of cost for 2m longMaterials-

###C.P. brass curtain rod 25 mm dia metre 2 239 478###C.P. brass brackets each 2 5 10###C.P. brass screws L.S. 4.03 1 4.03###Carriage L.S. 1.56 1 1.56

Page 340: DAR_Vol_1

Wooden plugs including cutting brick workand fixing in cement mortar 1:3 (1 cement: 3fine sand)

(B) (Rate as per item no 9.32 of SH each 2 10.15 20.3

349CodDescription Unit Quantity Rate Amount###Labour L.S. 2.73 1 2.73###Sundries L.S. 1.56 1 1.56

TOTAL 518.18Add for water charge @ 1% on all except (B) 4.98TOTAL 523.16Add for contractor’s profit and overheads @ 75.4315% on all except (B)Cost of 2m 598.59Cost of lm. 299.3Say 299.3

### Providing and fixing nickel plated M.S. pipe curtain rods with nickel plated brackets:9.420 mm dia (heavy type)CodDescription Unit Quantity Rate Amount

Details of cost for 2m long.Materials :

###(i) Nickel plated M.S. pipe 20 mmmetre 2 44 88###(ii) Nickel plated M.S. bracket each 2 3 6###(iii) Screws L.S. 4.03 1 4.03###(iv) Carriage L.S. 1.56 1 1.56###(v) Rawl plug 50 mm (designationeach 2 7 14###(vi) Labour including fixing rawl pL.S. 5.2 1 5.2###(vii) Sundries L.S. 1.56 1 1.56

TOTAL 120.35Add for water charge @ 1 % 1.2TOTAL 121.55Add for contractor’s profit and overheads @ 18.231,500%Cost for 2 meter 139.78Cost of lm. 69.89Say 69.9

### Providing and fixing nickel plated M.S. pipe curtain rods with nickel plated brackets :9.425 mm dia (heavy type)CodDescription Unit Quantity Rate Amount

Details of cost for 2m long.Materials:

###(i) Nickel plated M.S. pipe 25 mmmetre 2 49 98###(ii) Nickel plated M.S. bracket each 2 4 8###(iii) Screws L.S. 4.03 1 4.03###(iv) Carriage L.S. 1.56 1 1.567048 (v) Rawl plug 50 mm (desi each 2 7 149999 (vi) Labour including fixing L.S. 5.2 1 5.29999 (vii) Sundries L.S. 1.56 1 1.56

TOTAL 132.35Add for water charge @ 1% 1.32TOTAL 133.67Add for contractor’s profit and overheads @ 20.05

Page 341: DAR_Vol_1

1,500%Cost for 2 meter 153.72Cost of lm. 76.86Say 76.85

350### Providing and fixing M.S. grills of required pattern in frames of windows etc. with

M.S. flats, square or round bars etc. all complete.9.4Fixed to steel windows by welding.CodDescription Unit Quantity Rate Amount

Details of cost for a grill 90x120cm =1.08sqm.Material-M.S. bar 16mm diameter- 11x86cm = 9.46m.@ 1.58kg/m= 14.95kg+Add wastage @ 10% = 1.50kg.= 16.45kg. Say 0.165 quintal

###M.S.bar quintal .165 3 050.00 503.25M.S. flat 25x3.15mm2xl20cm = 2.40m+2x90cm= 1.80m+lxl20cm= 1.20m+2x15cm = 0.30m=5.70m5.70m @ 0.63kg/m = 3.59kg+Add wastage @ 10% = 0.36kg.= 3.95kg. Say 4 kg. or 0.04 quintal

###M.S. flat quintal .04 2 900.00 116###Carriage of steel 0.165 + 0.04 = 0 tonne .02 47.29 .95

0.0205 t Say 0.02 tonne###Sundries L.S. 26.91 1 26.91###Welding charges L.S. 19.76 1 19.76

Labour-###Blacksmith 1st class Day .86 151.5 130.29###Beldar Day 1.1 135.25 148.78

TOTAL 945.94Add for water charge @ 1 % 9.46TOTAL 955.4Add for contractor’s profit and overheads @ 143.311,500%Cost for 18.54 kg. 1 098.71Cost for 1 kg. 59.26Say 59.25

### Providing and fixing M.S. grills of required pattern in frames of windows etc. withM.S. flats, square or round bars etc. all complete.

9.4Fixed to openings /wooden frames with rawl plugs screws etc.CodDescription Unit Quantity Rate Amount

Details of cost for a grill 90x120cm =1.08sqm.Material-M.S. bar 16mm dia. 11x86cm = 9.46m.@ 1.58kg/m= 14.95kg+Add wastage @ 10% = 1.50kg.

Page 342: DAR_Vol_1

= 16.45kg. Say 0.165quintal###M.S. bar quintal .165 3 050.00 503.25

M.S. flat 25x3.15mm2xl20cm = 2.40m+2x90cm= 1.80m+lxl20cm= 1.20m+2xl5cm = 0.30m=5.70m

351CodDescription Unit Quantity Rate Amount

5.70m @ 0.63kg/m = 3.59kg+Add wastage @ 10% = 0.36kg.= 3.95kg. Say 4 kg. or 0.04 quintal

###M.S. flat quintal .04 2 900.00 116###Carriage of steel 0.165 + 0.04 = 0 tonne .02 47.29 .95

0.0205 tonne. Say 0.02 tonne###Sundries L.S. 26.91 1 26.91###Welding charges L.S. 19.76 1 19.76

Labour-###Blacksmith 1st class Day .86 151.5 130.29###Beldar Day 1.1 135.25 148.78###Rawl plug 50 mm (designation 10each 8 7 56###Fixing of rawl plugs L.S. 26 1 26

TOTAL 1 027.94Add for water charge @ 1 % 10.28TOTAL 1 038.22Add for contractor’s profit and overheads @ 155.731,500%Cost for 18.54 kg. 1 193.95Cost for 1 kg. 64.4Say 64.4

### Providing and fixing expanded metal 20x60mm strands 3.25mm wide and 1.6mmthick for windows etc. including 62x19mm beading of Ilnd class teak wood.

CodDescription Unit Quantity Rate AmountDetails of cost for a window of size140x110cm =1.54sqm.Materials-Expended metal -20x60mm mesh 3.2mm wide= 1.4x1.1m = 1.54sqm.+Add wastage @ 10% = 0.15sqm.= 1.69 sqm.

###Expended metal -. sqm 1.69 200 338###Carriage L.S. 1.82 1 1.82

Second class teak wood beading5mx62mmx19mm = 0.0059cum.+Add wastage @ 10% = 0.00059cum.= 0.00649cum. Say 6 cudm.

###Second class teak wood 10 cudm 6 410 246###Carriage of timber cum .006 60.81 .36

Labour-###Carpenter 2nd class Day .33 141.6 46.73###Beldar Day .25 135.25 33.81###Sundries L.S. 26.91 1 26.91

Page 343: DAR_Vol_1

TOTAL 693.63Add for water charge @ 1 % 6.94TOTAL 700.57Add for contractor’s profit and overheads @ 105.091,500%Cost of 1.54 sqm. 805.66Cost of 1 sqm. 523.16Say 523.15

352### Providing and fixing hard drawn steel wire fabric 75x25 mm mesh of weight not

less than 7.75 Kg per sqm to window frames etc. including 62x19 mm beading ofsecond class teak wood.

CodDescription Unit Quantity Rate AmountDetails of cost for a window of size140x110cm =1.54sqm.Materials-Hard drawn steel wire fabric -20x60mm mesh3.2mm wide = 1.4x1.1m= 1.54sqm.+Add wastage @ 10% = 0.15sqm.= 1.69 sqm.

###Hard drawn steel wire fabric sqm 1.69 310 523.9###Carriage of wire fabric L.S. 1.82 1 1.82

Second class teak wood beading5mx62mmx19mm = 0.00059cum.+Add wastage @ 10% = 0.00059cum.= 0.000649cum. Say 6 cudm.

###Second class teak wood 10 cudm 6 410 246###Carriage of timber cum .006 60.81 .36

Labour-###Carpenter 2nd class Day .33 141.6 46.73###Beldar Day .25 135.25 33.81###Sundries L.S. 19.76 1 19.76

TOTAL 872.38Add for water charge @ 1 % 8.72TOTAL 881.1Add for contractor’s profit and overheads @ 132.161,500%Cost of 1.54 sqm. 1 013.26Cost of 1 sqm. 657.96Say 657.95

### Providing and fixing fly proof galvanised M.S. wire gauge to windows and clerestorywindows using galvanised M.S. wire gauge with average width of aperture 1.4 mmin both directions with wire of dia. 0.63 mm.

9.5With 2nd class teak wood beading 62X19 mm.CodDescription Unit Quantity Rate Amount

Details of cost for a window of size140x110cm =1.54sqm.Materials-Wire gauge -20x60mm mesh 3.2mm wide =1.4x1.1 m = 1.54sqm.+Add wastage @ 10% = 0.15sqm.

Page 344: DAR_Vol_1

= 1.69 sqm.###Wire gauge sqm 1.69 142 239.98###Carriage of wire fabric L.S. 1.82 1 1.82

Second class teak wood beading5mx62mmx19mm = 0.0059cum.+Add wastage @ 10% = 0.00059cum.= 0.00649cum. Say 6 cudm.

###Second class teak wood 10 cudm 6 410 246###Carriage of timber cum .006 60.81 .36

Labour-###Carpenter 2nd class Day .33 141.6 46.73###Beldar Day .25 135.25 33.81

353CodDescription Unit Quantity Rate Amount###Sundries L.S. 19.76 1 19.76

TOTAL 588.46Add for water charge @ 1% 5.88TOTAL 594.34Add for contractor’s profit and overheads @ 89.151,500%Cost of 1.54 sqm. 683.49Cost of 1 sqm. 443.82Say 443.8

### Providing and fixing fly proof galvanised M.S. wire gauge to windows and clerestorywindows using galvanised M.S. wire gauge with average width of aperture 1.4 mmin both directions with wire of dia. 0.63 mm.

9.5With 12 mm mild steel U beading.CodDescription Unit Quantity Rate Amount

Details of cost for a window of size140x110cm =1.54sqm.Materials-Wire gauge -20x60mm mesh 3.2mm wide =1.4x1.1m = 1.54sqm.+Add wastage @ 10% = 0.15sqm.= 1.69 sqm.

###Wire gauge sqm 1.69 142 239.98###Carriage of wire fabric L.S. 1.82 1 1.82###12 mm mild steel U beading metre 5 9 45

Labour-###Carpenter 2nd class Day .33 141.6 46.73###Beldar Day .25 135.25 33.81###Sundries L.S. 19.76 1 19.76

TOTAL 387.1Add for water charge @ 1 % 3.87TOTAL 390.97Add for contractor’s profit and overheads @ 58.651,500%Cost of 1.54 sqm. 449.62Cost of 1 sqm. 291.96Say 291.95

### Deduct for fixing 75x25 mm hard drawn steel wire fabric of weight not less than7.75 Kg. per sqm in panelled and glazed door and window shutter instead of glass

Page 345: DAR_Vol_1

sheet 4 mm thick.CodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm.Materials-

###Hard drawn steel wire fabric sqm 1 310.00 310.00###Glass 10 kg/sqm (4 mm) sqm 1 248 248

Difference of cost 62Add for water charge @ 1 % .62TOTAL 62.62Add for contractor’s profit and overheads @ 9.391,500%Extra cost for 1 sqm. 72.01Say 72

354### Providing 40x5 mm flat iron hold fast 40 cm long including fixing to frame with 10

mm diameter bolts, nuts and wooden plugs and embedding in cement concreteblock 30x10 x 15cm 1:3:6 mix (1 cement : 3 coarse sand : 6 graded stone aggregate20mm nominal size)

CodDescription Unit Quantity Rate AmountDetails of cost for 1 hold fastMaterials-

###M.S.flat 40x5mm 40cm long @ 1quintal .0067 2 900.00 19.43 0.672 kg = 0.0067 qunital###Carriage of steel L.S. 1.82 1 1.82

Cement concrete 1:3:630xl0xl5cm= 0.0045cum.+Add wastage @ 10% = 0.00045cum.= 0.00495cum. Say 0.005cum.

(A (Rate as per item no 4.2.5) cum .005 3 112.70 15.56###Bolts and nuts L.S. 5.46 1 5.46

Labour-###Blacksmith 2nd class Day .03 141.6 4.25###Mason 1st class Day .03 151.5 4.54###Beldar Day .03 135.25 4.06

TOTAL 55.12Add for water charge @ 1% on all except (A) .4TOTAL 55.52Add for contractor’s profit and overheads @ 5.9915% on all except (A)Cost for 1 hold fast 61.51Say 61.5

### Providing beams including hoisting, fixing in position and applying woodpreservative for the unexposed surfaces, etc. complete with :

9.5Sal wood.CodDescription Unit Quantity Rate Amount

Details of cost for a beam450x30x15cm = 0.203cum. or203cudm.Materials-Sal wood = 203 cudm.+Add wastage @ 2% = 4.06cudm.= 207.06cudm. Say 207.1 cudm.

Page 346: DAR_Vol_1

###Sal wood 10 cudm 207.1 218 4,514.78###Carriage of timber cum .207 60.81 12.59

Priming coat (wood preservative) (A (Rate as per item no 13.57.1) sqm .54 12.8 6.91

Labour-###Carpenter 2nd class Day .7 141.6 99.12###Beldar Day 1.45 135.25 196.11###Bandhani Day .7 138.45 96.92###Sundries L.S. 26.91 1 26.91

TOTAL 4,953.34Add for water charge @ 1 % on all except (A) 49.46TOTAL 5,002.8Add for contractor’s profit and overheads @ 749.3815% on all except (A)Cost for 203 cudm. 5,752.18Cost of 1 cum. 28,335.86Say 28,335.9

355### Providing beams including hoisting, fixing in position and applying wood

preservative for the unexposed surfaces, etc. complete with :9.5Hollock wood.CodDescription Unit Quantity Rate Amount

Details of cost for a beam450x30x15cm = 0.203cum. or203cudm.Materials-Hollock wood = 203 cudm.+Add wastage @ 2% = 4.06cudm.= 207.06cudm. Say 207.1 cudm.

###Hollock wood 10 cudm 207.1 217 4,494.072204 Carriage of timber cum .207 60.81 12.59

Priming coat (wood preservative) (A (Rate as per item no 13.57.1) sqm .54 12.8 6.91

Labour-0112 Carpenter 2nd class Day .7 141.6 99.120114 Beldar Day 1.45 135.25 196.110100 Bandhani Day .7 138.45 96.929999 Sundries L.S. 26.91 1 26.91

TOTAL 4,932.63Add for water charge @ 1% on all except (A) 49.26TOTAL 4,981.89Add for contractor’s profit and overheads @ 746.2515% on all except (A)Cost for 203 cudm. 5,728.14Cost of 1 cum. 28,217.44Say 28,217.4

### Providing and fixing ISI marked M.S. pressed butt hinges bright finished withnecessary screws etc. complete :

9.5125x65x2.12 mmCodDescription Unit Quantity Rate Amount

Details of cost for ten

Page 347: DAR_Vol_1

Materials-###Butt hinges 125x65x2.12 mm 10 Nos 10 78 78###Iron screws 50 mm 100 Nos 80 40 32###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 2nd class Day .14 141.6 19.82###Beldar Day .09 135.25 12.17

TOTAL 144.72Add for water charge @ 1% 1.45TOTAL 146.17Add for contractor’s profit and overheads @ 21.931,500%Cost of 10 hinges 168.1Cost of 1 butt hinge 16.81Say 16.8

356### Providing and fixing ISI marked M.S. pressed butt hinges bright finished with

necessary screws etc. complete :9.5100x58x1.90 mmCodDescription Unit Quantity Rate Amount

Details of cost for tenMaterials-

0595 Butt hinges 100x58x1.9 m 10 Nos 10 54 540637 Iron screws 40 mm 100 Nos 80 30 24###Carriage of materials L.S 2.73 1 2.73

Labour-###Carpenter 2nd class Day .14 141.6 19.820114 Beldar Day .09 135.25 12.17

TOTAL 112.72Add for water charge @ 1% 1.13TOTAL 113.85Add for contractor’s profit and overheads @ 17.081,500%Cost of 10 hinges 130.93Cost of 1 butt hinge 13.09Say 13.1

### Providing and fixing ISI marked M.S. pressed butt hinges bright finished withnecessary screws etc. complete :

9.575x47x1.70 mmCodDescription Unit Quantity Rate Amount

Details of cost for tenMaterials-

###Butt hinges 175x47x1.7 mm 10 Nos 10 34 34###Iron screws 30 mm 100 Nos 60 24 14.4###Carriage of materials L.S. 1.82 1 1.82

Labour-###Carpenter 2nd class Day .14 141.6 19.82###Beldar Day .09 135.25 12.17

TOTAL 82.21Add for water charge @ 1 % .82TOTAL 83.03Add for contractor’s profit and overheads @ 12.45

Page 348: DAR_Vol_1

1,500%Cost of 10 hinges 95.48Cost of 1 butt hinge 9.55Say 9.55

### Providing and fixing ISI marked M.S. pressed butt hinges bright finished withnecessary screws etc. complete :

9.550x37x1.50 mmCodDescription Unit Quantity Rate Amount

Details of cost for tenMaterials-

0597 Butt hinges 50x37x1.5 mm 10 Nos 10 28 280640 Iron screws 20 mm 100 Nos 40 15.00 6.009999 Carriage of materials L.S. .91 1 .91

Labour-0112 Carpenter 2nd class Day .08 141.60 11.33

TOTAL 46.24

357CodDescription Unit Quantity Rate Amount

Add for water charge @ 1% .46TOTAL 46.7Add for contractor’s profit and overheads @ 71,500%Cost of 10 hinges 53.7Cost of 1 butt hinge 5.37Say 5.35

### Providing and fixing IS : 1341 marked M.S. heavy weight butt hinges with necessaryscrews etc. complete :

9.5125x90x4.00 mm

CodDescription Unit Quantity Rate AmountDetails of cost for tenMaterials-

###M.S. heavy weight but hinges 10 Nos 10 256 256IS: 1341 marked.

###Iron screws 50 mm 100 Nos 80 40 32###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 2nd class Day .14 141.6 19.82###Beldar Day .09 135.25 12.17

TOTAL 322.72Add for water charge @ 1 % 3.23TOTAL 325.95Add for contractor’s profit and overheads @ 48.891,500%Cost of 10 hinges 374.84Cost of 1 butt hinge 37.48Say 37.5

### Providing and fixing IS : 1341 marked M.S. heavy weight butt hinges with necessaryscrews etc. complete :

9.5100x75x3.50 mmCodDescription Unit Quantity Rate Amount

Page 349: DAR_Vol_1

Details of cost for tenMaterials-

###M.S. heavy weight butt hinges 10 Nos. 10 133 133mm IS: 1341 marked

###Iron screws 40 mm 100 Nos 80 30 24###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 2nd class Day .14 141.6 19.82###Beldar Day .09 135.25 12.17

TOTAL 191.72Add for water charge @ 1% 1.92TOTAL 193.64Add for contractor’s profit and overheads @ 29.051,500%Cost of 10 hinges 222.69Cost of 1 butt hinge 22.27Say 22.25

358### Providing and fixing IS : 1341 marked M.S. heavy weight butt hinges with necessary

screws etc. complete :9.575x60x3.10 mmCodDescription Unit Quantity Rate Amount

Details of cost for tenMaterials-

###M.S. heavy weight butt hinges 10 Nos 10 67 67IS: 1341 marked

###Iron screws 30 mm 100 Nos 60 24 14.4###Carriage of materials L.S. 1.82 1 1.82

Labour-###Carpenter 2nd class Day .14 141.6 19.82###Beldar Day .09 135.25 12.17

TOTAL 115.21Add for water charge @ 1 % 1.15TOTAL 116.36Add for contractor’s profit and overheads @ 17.451,500%Cost of 10 hinges 133.81Cost of 1 butt hinge 13.38Say 13.4

### Providing and fixing IS : 1341 marked M.S. heavy weight butt hinges with necessaryscrews etc. complete :

9.550x40x2.50 mmCodDescription Unit Quantity Rate Amount

Details of cost for tenMaterials-

###M.S. heavy weight butt hinges 10 Nos 10 52 52IS: 1341 marked

###Iron screws 20 mm 100 Nos 40 15 6###Carriage of materials L.S. .91 1 .91

Labour-###Carpenter 2nd class Day .08 141.6 11.33

TOTAL 70.24

Page 350: DAR_Vol_1

Add for water charge @ 1 % .7TOTAL 70.94Add for contractor’s profit and overheads @ 10.641,500%Cost of 10 hinges 81.58Cost of 1 butt hinge 8.16Say 8.15

### Providing and fixing ISI marked oxidised M.S. pressed butt hinges with necessaryscrews etc. complete.

9.5125x65x2.12 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###M.S. butt hinges (oxidised) 125 10 Nos 10 92 92###Iron screws (oxidised) 50 mm 100 Nos 80 40 32###Carriage of materials L.S. 3.64 1 3.64

Labour-###Carpenter II class Day .14 141.6 19.82

359CodDescription Unit Quantity Rate Amount

###Beldar Day .09 135.25 12.17TOTAL 159.63Add for water charge @ 1 % 1.6TOTAL 161.23Add for contractor’s profit and overheads @ 24.181,500%Cost of 10 nos. 185.41Cost of 1 no 18.54Say 18.55

### Providing and fixing ISI marked oxidised M.S. pressed butt hinges with necessaryscrews etc. complete.

9.5100x58x1.90 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###M.S. butt hinges (oxidised) 100 10 Nos 10 53 53###Iron screws (oxidised) 40 mm 100 Nos 80 35 28###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter II class Day .14 141.6 19.82###Beldar Day .09 135.25 12.17

TOTAL 115.72Add for water charge @ 1 % 1.16TOTAL 116.88Add for contractor’s profit and overheads @ 17.531,500%Cost of 10 nos. 134.41Cost of 1 no 13.44Say 13.45

### Providing and fixing ISI marked oxidised M.S. pressed butt hinges with necessary

Page 351: DAR_Vol_1

screws etc. complete.9.575x47x1.70 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###M.S. butt hinges (oxidised) 75x 10 Nos 10 32 32###Iron screws (oxidised) 30 mm 100 Nos 60 24 14.4###Carriage of materials L.S. 1.82 1 1.82

Labour-###Carpenter II class Day .14 141.6 19.82###Beldar Day .09 135.25 12.17

TOTAL 80.21Add for water charge @ 1 % .8TOTAL 81.01Add for contractor’s profit and overheads @ 12.151,500%Cost of 10 nos. 93.16Cost of 1 no 9.32Say 9.3

360### Providing and fixing ISI marked oxidised M.S. pressed butt hinges with necessary

screws etc. complete.9.550x37x1.50 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

0645 M.S. butt hinges (oxidise 10 Nos 10 27 270686 Iron screws (oxidised) 20 100 Nos 40 15 6###Carriage of materials L.S .91 1 .91

Labour-###Carpenter II class Day .08 141.6 11.33

TOTAL 45.24Add for water charge @ 1 % .45TOTAL 45.69Add for contractor’s profit and overheads @ 6.851,500%Cost of 10 nos. 52.54Cost of 1 no 5.25Say 5.25

### Providing and fixing ISI marked oxidised M.S. pressed Parliamentary hinges withnecessary screws etc. complete :

9.5150x125x27x2.80 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###M.S. parliamentary hinges (oxidi 10 Nos 10 255 255150x125x27x2.8 mm

###Iron screws (oxidised) 40 mm 100 Nos 80 35 28###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter II class Day .14 141.6 19.82

Page 352: DAR_Vol_1

###Beldar Day .14 135.25 18.94TOTAL 324.49Add for water charge @ 1 % 3.24TOTAL 327.73Add for contractor’s profit and overheads @ 49.161,500%Cost of 10 nos. 376.89Cost of 1 no 37.69Say 37.7

### Providing and fixing ISI marked oxidised M.S.pressed Parliamentary hinges withnecessary screws etc. complete :

9.5125x125x27x2.80 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###M.S. parliamentary hinges (oxidi 10 Nos 10 205 205125x125x27x2.8 mm

###Iron screws (oxidised) 40 mm 100 Nos 80 35 28###Carriage of materials L.S. 2.73 1 2.73

Labour-

361CodDescription Unit Quantity Rate Amount

###Carpenter II class Day .14 141.6 19.82###Beldar Day .14 135.25 18.94

TOTAL 274.49Add for water charge @ 1 % 2.74TOTAL 277.23Add for contractor’s profit and overheads @ 41.581,500%Cost of 10 nos. 318.81Cost of 1 no 31.88Say 31.9

### Providing and fixing ISI marked oxidised M.S. pressed Parliamentary hinges withnecessary screws etc. complete :

9.5100x125x27x2.80 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###M.S. parliamentary hinges (oxidi 10 Nos 10 165 165100x125x27x2.8 mm

###Iron screws (oxidised) 40 mm 100 Nos 80 35 28###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter II class Day .14 141.6 19.82###Beldar Day .14 135.25 18.94

TOTAL 234.49Add for water charge @ 1 % 2.34TOTAL 236.83Add for contractor’s profit and overheads @ 35.521,500%Cost of 10 nos. 272.35

Page 353: DAR_Vol_1

Cost of 1 no 27.24Say 27.25

### Providing and fixing ISI marked oxidised M.S. pressed Parliamentary hinges withnecessary screws etc. complete :

9.575x100x20x2.24 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###M.S. parliamentary hinges (oxidi 10 Nos 10 122 12275x100x20x2.24 mm

###Iron screws (oxidised) 30 mm 100 Nos 60 24 14.4###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 2nd class Day .14 141.6 19.82###Beldar Day .14 135.25 18.94

TOTAL 177.89Add for water charge @ 1 % 1.78TOTAL 179.67Add for contractor’s profit and overheads @ 26.951,500%Cost of 10 nos. 206.62Cost of 1 no 20.66Say 20.65

362### Providing and fixing ISI marked oxidised M.S. single acting spring hinges with

necessary screws etc. complete :9.5150 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###M.S. single acting spring hinges ( each 10 71 710150 mm

###Iron screws (oxidised) 50 mm 100 Nos 80. 00 40 32###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter II class Day .4 141.6 56.64###Beldar Day .2 135.25 27.05

TOTAL 828.42Add for water charge @ 1 % 8.28TOTAL 836.7Add for contractor’s profit and overheads @ 125.51,500%Cost of 10 nos. 962.2Cost of 1 no 96.22Say 96.2

### Providing and fixing ISI marked oxidised M.S. single acting spring hinges withnecessary screws etc. complete :

9.5125 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

Page 354: DAR_Vol_1

###M.S. single acting spring hinges ( each 10 66 660125 mm

###Iron screws (oxidised) 50 mm 100 Nos 80 40 32###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter II class Day .4 141.6 56.64###Beldar Day .2 135.25 27.05

TOTAL 778.42Add for water charge @ 1% 7.78TOTAL 786.2Add for contractor’s profit and overheads @ 117.931,500%Cost of 10 nos. 904.13Cost of 1 no 90.41Say 90.4

### Providing and fixing ISI marked oxidised M.S. single acting spring hinges withnecessary screws etc. complete :

9.5100 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###M.S. single acting spring hinges ( each 10 51 510100 mm

###Iron screws (oxidised) 40 mm 100 Nos 80 35 28###Carriage of materials L.S. 2.73 1 2.73

Labour-

363CodDescription Unit Quantity Rate Amount

###Carpenter II class Day .4 141.6 56.64###Beldar Day .2 135.25 27.05

TOTAL 624.42Add for water charge @ 1 % 6.24TOTAL 630.66Add for contractor’s profit and overheads @ 94.61,500%Cost of 10 nos. 725.26Cost of 1 no 72.53Say 72.55

### Providing and fixing oxidised M.S. double acting spring hinges with necessaryscrews etc. complete.

9.6150 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###M.S. double acting spring hinges each 10 73 730150 mm

###Iron screws (oxidised) 50 mm 100 Nos 80 40 32###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter II class Day .4 141.6 56.64###Beldar Day .2 135.25 27.05

Page 355: DAR_Vol_1

TOTAL 848.42Add for water charge @ 1% 8.48TOTAL 856.9Add for contractor’s profit and overheads @ 128.541,500%Cost of 10 nos. 985.44Cost of 1 no 98.54Say 98.55

### Providing and fixing oxidised M.S. double acting spring hinges with necessaryscrews etc. complete.

9.6125 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###M.S. double acting spring hinges each 10 63 630125 mm

###Iron screws (oxidised) 50 mm 100 Nos 80 40 32###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter II class Day .4 141.6 56.64###Beldar Day .2 135.25 27.05

TOTAL 748.42Add for water charge @ 1 % 7.48TOTAL 755.9Add for contractor’s profit and overheads @ 113.381,500%Cost of 10 nos. 869.28Cost of 1 no 86.93Say 86.95

364### Providing and fixing oxidised M.S. double acting spring hinges with necessary

screws etc. complete.9.6100 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###M.S. double acting spring hinges each 10 47 470100 mm

###Iron screws (oxidised) 40 mm 100 Nos 80 35 28###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter II class Day .4 141.6 56.64###Beldar Day .2 135.25 27.05

TOTAL 584.42Add for water charge @ 1 % 5.84TOTAL 590.26Add for contractor’s profit and overheads @ 88.541,500%Cost of 10 nos. 678.8Cost of 1 no 67.88Say 67.9

Page 356: DAR_Vol_1

### Providing M.S. Piano hinges ISI marked IS : 3818 finished with nickel plating andfixing with necessary screws etc., complete.

9.6Overall width 35 mm.CodDescription Unit Quantity Rate Amount

Details of cost for 1 meterMaterials-

###M.S. piano hinges (oxidised) 35 metre 1 24 24###Iron screws (oxidised) 20 mm 100 Nos 30 15 4.5###Carriage of materials L.S. 1.82 1 1.82

Labour-###Carpenter II class Day .14 141.6 19.82###Beldar Day .09 135.25 12.17

TOTAL 62.31Add for water charge @ 1 % .62TOTAL 62.93Add for contractor’s profit and overheads @ 9.441,500%Cost for 1 metre 72.37Say 72.35

### Providing M.S. Piano hinges ISI marked IS : 3818 finished with nickel plating andfixing with necessary screws etc., complete.

9.6Overall width 50 mm.CodDescription Unit Quantity Rate Amount

Details of cost for 1 meterMaterials-

###M.S. piano hinges (oxidised) 50 metre 1 29 29###Iron screws (oxidised) 20 mm 100 Nos 30 15 4.5###Carriage of materials L.S. 1.82 1 1.82

Labour-###Carpenter II class Day .14 141.6 19.82###Beldar Day .09 135.25 12.17

365CodDescription Unit Quantity Rate Amount

TOTAL 67.31Add for water charge @ 1 % .67TOTAL 67.98Add for contractor’s profit and overheads @ 10.21,500%Cost for 1 metre 78.18Say 78.2

### Providing M.S. Piano hinges ISI marked IS : 3818 finished with nickel plating andfixing with necessary screws etc., complete.

9.6Overall width 65 mm.CodDescription Unit Quantity Rate Amount

Details of cost for 1 meterMaterials-

###M.S. piano hinges (oxidised) 65 metre 1 34 34###Iron screws (oxidised) 20 mm 100 Nos 30 15 4.5###Carriage of materials L.S. 1.82 1 1.82

Labour-

Page 357: DAR_Vol_1

###Carpenter II class Day .14 141.6 19.82###Beldar Day .09 135.25 12.17

TOTAL 72.31Add for water charge @ 1 % .72TOTAL 73.03Add for contractor’s profit and overheads @ 10.951,500%Cost for 1 metre 83.98Say 84

### Providing and fixing ISI marked oxidised M.S.sliding door boltnuts andscrews etc. complete

9.6300x16 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

0660 M.S. ‘sliding door bolts ( each 10 45 450###Iron screws (oxidised) 35 mm 100 Nos 120 28 33.60641 Bolts and nuts 50x6 mm each 40 4 160###Carriage of materials & sundries L.S. 6.37 1 6.37

Labour-###Carpenter II class Day .25 141.6 35.4

TOTAL 685.37Add for water charge @ 1 % 6.85TOTAL 692.22Add for contractor’s profit and overheads @ 103.831,500%Cost of 10 nos. 796.05Cost of 1 no. 79.61Say 79.6

366### Providing and fixing ISI marked oxidised M.S. sliding door bolts with nuts and

screws etc. complete :9.62.2 250x16 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###M.S. ‘sliding door bolts (oxidis each 10 37 370###Iron screws (oxidised) 35 mm 100 Nos 100 28 28###Bolts and nuts 50x6 mm each 40 4 160###Carriage of materials & sundries L.S. 6.37 1 6.37

Labour-###Carpenter II class Day .25 141.6 35.4

TOTAL 599.77Add for water charge @ 1 % 6TOTAL 605.77Add for contractor’s profit and overheads @ 90.871,500%Cost of 10 nos. 696.64Cost of 1 no. 69.66Say 69.65

### Providing and fixing ISI marked oxidised M.S. tower bolt black finish, (Barrel type)

Page 358: DAR_Vol_1

with necessary screws etc. complete :9.6250x10 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###M.S. tower bolts (oxidised) 250 each 10 25 250###Iron screws (oxidised) 30 mm 100 Nos 100 24 24###Carriage of material L.S. 3.64 1 3.64

Labour-###Carpenter II class Day .1 141.6 14.16

TOTAL 291.8Add for water charge @ 1 % 2.92TOTAL 294.72Add for contractor’s profit and overheads 44.211,500%Cost of 10 nos. 338.93Cost of 1 no. 33.89Say 33.9

### Providing and fixing ISI marked oxidised M.S. tower bolt black finish, (Barrel type)with necessary screws etc. complete :

9.6200x10 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###M.S. tower bolts (oxidised) 200 each 10 21 210###Iron screws (oxidised) 30 mm 100 Nos 80 24 19.2###Carriage of material L.S. 2.73 1 2.73

Labour-###Carpenter II class Day .1 141.6 14.16

TOTAL 246.09Add for water charge @ 1% 2.46

367CodDescription Unit Quantity Rate Amount

TOTAL 248.55Add for contractor’s profit and overheads @ 37.281,500%Cost of 10 nos. 285.83Cost of 1 no. 28.58Say 28.6

### Providing and fixing ISI marked oxidised M.S. tower bolt black finish, (Barrel type)with necessary screws etc. complete :

9.6150x10 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###M.S. tower bolts (oxidised) 150 each 10 17 170###Iron screws (oxidised) 30 mm 100 Nos 60 24 14.4###Carriage of material L.S. 2.73 1 2.73

Labour-###Carpenter II class Day .1 141.6 14.16

Page 359: DAR_Vol_1

TOTAL 201.29Add for water charge @ 1% 2.01TOTAL 203.3Add for contractor’s profit and overheads @ 30.51,500%Cost of 10 nos. 233.8Cost of 1 no. 23.38Say 23.4

### Providing and fixing ISI marked oxidised M.S. tower bolt black finish, (Barrel type)with necessary screws etc. complete :

9.6100x10 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

0667 M.S. tower bolts (oxidise each 10 12 1200684 Iron screws (oxidised) 30 100 Nos 60 24 14.4###Carriage of material L.S. 2.73 1 2.73

Labour-0112 Carpenter II class Day .08 141.6 11.33

TOTAL 148.46Add for water charge @ 1 % 1.48TOTAL 149.94Add for contractor’s profit and overheads @ 22.491,500%Cost of 10 nos. 172.43Cost of 1 no. 17.24Say 17.25

368### Providing and fixing ISI marked 85x42mm oxidised M.S. pull bolt lock conforming

to IS : 7534 with necessary screws bolts, nut and washers etc. complete.CodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

2449 M.S. pull bolts (oxidised) each 10 27 270with bolts and nuts complete

9999 Carriage of materials & sun L.S. 6.37 1 6.37Labour-

0112 Carpenter II class Day .25 141.6 35.4TOTAL 311.77Add for water charge @ 1 % 3.12TOTAL 314.89Add for contractor’s profit and overheads @ 47.231,500%Cost of 10 nos. 362.12Cost of 1 no. 36.21Say 36.2

### Providing and fixing ISI marked oxidised M.S. door latches conforming to IS:5930with screws etc. complete :

9.6300x20x6 mmCodDescription Unit Quantity Rate Amount

Page 360: DAR_Vol_1

Details of cost for 10 nos.Materials-

###M.S. door latches (oxidised) 30 each 10 25 250###Iron screws (oxidised) 25 mm 100 Nos 90 16 14.4###Carriage of materials L.S. 3.64 1 3.64

Labour-###Carpenter II class Day .12 141.6 16.99

TOTAL 285.03Add for water charge @ 1 % 2.85TOTAL 287.88Add for contractor’s profit and overheads @ 43.181,500%Cost of 10 nos. 331.06Cost of 1 no. 33.11Say 33.1

### Providing and fixing ISI marked oxidised M.S. door latches conforming to IS:5930with screws etc. complete :

9.65.2 250x20x6 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###M.S. door latches (oxidised) 25 each 10 25 250###Iron screws (oxidised) 25 mm 100 Nos 90 16 14.4###Carriage of materials L.S. 3.64 1 3.64

Labour-###Carpenter II class Day .12 141.6 16.99

TOTAL 285.03

369CodDescription Unit Quantity Rate Amount

Add for water charge @ 1 % 2.85TOTAL 287.88Add for contractor’s profit and overheads @ 43.181,500%Cost of 10 nos. 331.06Cost of 1 no. 33.11Say 33.1

### Providing and fixing ISI marked oxidised M.S. handles conforming to IS:4992 withnecessary screws etc. complete :

9.6125 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###M.S. handle (oxidised) 125 mm each 10 7 70###Iron screws (oxidised) 25 mm 100 Nos 40 16 6.4###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter II class Day .06 141.6 8.5

TOTAL 87.63Add for water charge @ 1 % .88TOTAL 88.51

Page 361: DAR_Vol_1

Add for contractor’s profit and overheads @ 13.281,500%Cost of 10 nos. 101.79Cost of 1 no. 10.18Say 10.2

### Providing and fixing ISI marked oxidised M.S. handles conforming to IS:4992 withnecessary screws etc. complete:

9.66.2 100 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###M.S. handle (oxidised) 100 mm each 10 5 50###Iron screws (oxidised) 25 mm 100 Nos 40 16 6.4###Carriage of materials L.S. 1.82 1 1.82

Labour-###Carpenter II class Day .06 141.6 8.5

TOTAL 66.72Add for water charge @ 1 % .67TOTAL 67.39Add for contractor’s profit and overheads @ 10.111,500%Cost of 10 nos. 77.5Cost of 1 no. 7.75Say 7.75

370### Providing and fixing ISI marked oxidised M.S. handles conforming to IS:4992 with

necessary screws etc. complete :9.675 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###M.S. handle (oxidised) 75 mm each 10 3 30###Iron screws (oxidised) 25 mm 100 Nos 40 16 6.4###Carriage of materials L.S. 1.82 1 1.82

Labour-###Carpenter II class Day .06 141.6 8.5

TOTAL 46.72Add for water charge @ 1% .47TOTAL 47.19Add for contractor’s profit and overheads @ 7.081,500%Cost of 10 nos. 54.27Cost of 1 no. 5.43Say 5.45

### Providing and fixing oxidised M.S. hasp and staple (safety type) con363 withnecessary screws etc. complete :

9.6150 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.

Page 362: DAR_Vol_1

Materials-###M.S. hasp and staple (safety type)10 Nos 10 79 79

150 mm###Iron screws (oxidised) 25 mm 100 Nos 80.00 16 12.8###Carriage of materials L.S. 1.82 1 1.82

Labour-###Carpenter II class Day .08 141.6 11.33

TOTAL 104.95Add for water charge @ 1 % 1.05TOTAL 106Add for contractor’s profit and overheads @ 15.91,500%Cost of 10 nos. 121.9Cost of 1 no. 12.19Say 12.2

### Providing and fixing oxidised M.S. hasp and staple (safety type) con363 withnecessary screws etc. complete :

9.6115 mm

CodDescription Unit Quantity Rate AmountDetails of cost for 10 nos.Materials-

371CodDescription Unit Quantity Rate Amount###M.S. hasp and staple (safety type)10 Nos 10 70 70

115 mm###Iron screws (oxidised) 25 mm 100 Nos 70 16 11.2###Carriage of materials L.S. 1.82 1 1.82

Labour-###Carpenter II class Day .08 141.6 11.33

TOTAL 94.35Add for water charge @ 1 % .94TOTAL 95.29Add for contractor’s profit and overheads @ 14.291,500%Cost of 10 nos. 109.58Cost of 1 no. 10.96Say 10.95

### Providing and fixing oxidised M.S. hasp and staple (safety type) con 363 withnecessary screws etc. complete :

9.690 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###M.S. hasp and staple (safety type)10 Nos 10 52 5290 mm

###Iron screws (oxidised) 25 mm 100 Nos 70 16 11.2###Carriage of materials L.S. 1.82 1 1.82

Labour-

Page 363: DAR_Vol_1

###Carpenter II class Day .08 141.6 11.33TOTAL 76.35Add for water charge @ 1% .76TOTAL 77.11Add for contractor’s profit and overheads @ 11.571,500%Cost of 10 nos. 88.68Cost of 1 no. 8.87Say 8.85

### Providing and fixing oxidised M.S. casement stays (straight peg type) with necessaryscrews etc. complete.

9.6300 mm weighing not less than 200 gms.

CodDescription Unit Quantity Rate AmountDetails of cost for 10 nos.Materials-

###Oxidised M.S. casement stay 3 each 10 14 140###Screws 30 mm 100 Nos 40 24 9.6###Carriage of materials L.S. .91 1 .91

Labour-

372CodDescription Unit Quantity Rate Amount

###Carpenter II class Day .1 141.6 14.16TOTAL 164.67Add for water charge @ 1 % 1.65TOTAL 166.32Add for contractor’s profit and overheads @ 24.951,500%Cost of 10 nos. 191.27Cost of 1 no. 19.13Say 19.15

### Providing and fixing oxidised M.S. casement stays (straight peg type) with necessaryscrews etc. complete.

9.6250 mm weighing not less than 150 gms.CodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Oxidised M.S. casement stay 2 each 10 12 120###Screws 25 mm 100 Nos 40 16 6.4###Carriage of materials L.S. .91 1 .91

Labour-###Carpenter II class Day .1 141.6 14.16

TOTAL 141.47Add for water charge @ 1 % 1.41TOTAL 142.88Add for contractor’s profit and overheads @ 21.431,500%Cost of 10 nos. 164.31

Page 364: DAR_Vol_1

Cost of 1 no. 16.43Say 16.45

### Providing and fixing oxidised M.S. casement stays (straight peg type) with necessaryscrews etc. complete.

9.6200 mm weighing not less than 120 gms.CodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Oxidised M.S. casement stay 2 each 10 11 110###Screws 25 mm 100 Nos 40 16 6.4###Carriage of materials L.S. .91 1 .91

Labour-###Carpenter II class Day .1 141.6 14.16

TOTAL 131.47Add for water charge @ 1 % 1.31TOTAL 132.78

373CodDescription Unit Quantity Rate Amount

Add for contractor’s profit and overheads @ 19.921,500%Cost of 10 nos. 152.7Cost of 1 no. 15.27Say 15.25

### Providing and fixing oxidised M.S. Safety chain with necessary fixtures for doors.(Weighing not less than 450 gms.)

CodDescription Unit Quantity Rate AmountDetails of cost for 10 nos.Materials-

###Oxidised M.S. safety chain each 10 43 430###Iron screws 25 mm 100 Nos 60 16 9.6###Carriage of materials L.S. .91 1 .91

Labour-###Carpenter II class Day .1 141.6 14.16

TOTAL 454.67Add for water charge @ 1 % 4.55TOTAL 459.22Add for contractor’s profit and overheads @ 68.881,500%Cost of 10 nos. 528.1Cost of 1 no. 52.81Say 52.8

### Providing and fixing IS : 12817 marked stainlesssteel butt hin stainlesssteel screws etc. complete :

9.7125x64x1.90 mmCodDescription Unit Quantity Rate Amount

Page 365: DAR_Vol_1

Details of cost for 10 NosMaterials-

8215 S.S. butt hinges 125x64x 10 Nos 10 200 200###Stainless steel screws 50 mm 100 Nos 80 213 170.4###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 2nd class Day .14 141 19.82###Beldar Day .09 135.25 12.17

TOTAL 405.12Add for water charge @ 1% 4.05TOTAL 409.17Add for contractor’s profit and overheads @ 61.381,500%Cost of 10 hinges 470.55Cost of 1 butt hinge 47.06Say 47.05

3749.70 : Providing and fixing IS : 12817 marked stainless steel butt hinges with stainless

steel screws etc. complete :9.70.2 : 100X58X1.90 mm

CodDescription Unit Quantity Rate AmountDetails of cost for 10 NosMaterials-

###S.S. butt hinges 100x58x1.9 mm 10 Nos 10 143 143###Stainless steel screws 40 mm 100 Nos 80 157 125.6###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 2nd class Day .14 141.6 19.82###Beldar Day .09 135.25 12.17

TOTAL 303.32Add for water charge @ 1 % 3.03TOTAL 306.35Add for contractor’s profit and overheads @ 45.951,500%Cost of 10 hinges 352.3Cost of 1 butt hinge 35.23Say 35.25

### Providing and fixing IS : 12817 marked stainless steel butt hinges with stainlesssteel screws etc. complete :

9.775x47x1.80 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 NosMaterials-

###S.S. butt hinges 75x47x1.8 mm 10 Nos 10 112 112###Stainless steel screws 30 mm 100 Nos 60 98 58.8###Carriage of materials L.S. 1.82 1 1.82

Labour-0112 Carpenter 2nd class Day .14 141.6 19.820114 Beldar Day .09 135.25 12.17

TOTAL 204.61Add for water charge @ 1 % 2.05

Page 366: DAR_Vol_1

TOTAL 206.66Add for contractor’s profit and overheads @ 311,500%Cost of 10 hinges 237.66Cost of 1 butt hinge 23.77Say 23.75

9.7Providing and fixing IS : 12817 marked stainless steel butt hinges with stainlesssteel screws etc. complete :

9.70.4 : 50x37x1.50 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 NosMaterials-

###S.S. butt hinges 50x37x1.5 mm 10 Nos 10 90 90###Stainless steel screws 20 mm 100 Nos 40 63 25.2###Carriage of materials L.S. .91 1 .91

Labour- 41.6

375CodDescription Unit Quantity Rate Amount###Carpenter 2nd class Day .08 141.6 11.33

TOTAL 127.44Add for water charge @ 1% 1.27TOTAL 128.71Add for contractor’s profit and overheads @ 19.311,500% 148.02Cost of 10 hinges 14.8Cost of 1 butt hinge 14.8Say 14.8

9.7Providing and fixing IS : 12817 marked stainless steel butt hinges (heavy weight)with stainless steel screws etc. complete :

9.71.1 : 125x64x2.50 mm

CodDescription Unit Quantity Rate AmountDetails of cost for 10 NosMaterials-

###S.S. butt hinges 125x64x2.5 mm 10 Nos 10 261 261###Stainless steel screws 50 mm 100 Nos 80 213 170.4###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 2nd class Day .14 141.6 19.82###Beldar Day .09 135.25 12.17

TOTAL 466.12Add for water charge @ 1% 4.66TOTAL 470.78Add for contractor’s profit and overheads @ 70.621,500%Cost of 10 hinges 541.4Cost of 1 butt hinge 54.14Say 54.15

9.7Providing and fixing IS : 12817 marked stainless steel butt hinges (heavy weight)with stainless steel screws etc. complete:

9.71.2 : 100x60x2.50 mm

Page 367: DAR_Vol_1

CodDescription Unit Quantity Rate AmountDetails of cost for 10 NosMaterial

###S.S. butt hinges 100x60x2.5 mm 10 Nos 10 185 185###Stainless steel screws 40 mm 100 Nos 80 157 125.6###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 2nd class Day .14 141.6 19.82###Beldar Day .09 135.25 12.17

TOTAL 345.32Add for water charge @ 1 % 3.45TOTAL 348.77Add for contractor’s profit and overheads @ 52.321,500%Cost of 10 hinges 401.09Cost of 1 butt hinge 40.11Say 40.1

3769.71: Providing and fixing IS : 12817 marked stainless steel butt hinges (heavy weight)

with stainless steel screws etc. complete :9.71.3 ; 75x50x2.50 mm

CodDescription Unit Quantity Rate AmountDetails of cost for 10 NosMaterials-

###S.S. butt hinges 75x50x2.5 mm 10 Nos 10 155 155###Stainless steel screws 30 mm 100 Nos 60 98 58.8###Carriage of materials L.S. 1.82 1 1.82

Labour-###Carpenter 2nd class Day .14 141.6 19.82###Beldar Day .09 135.25 12.17

TOTAL 247.61Add for water charge @ 1% 2.48TOTAL 250.09Add for contractor’s profit and overheads @ 37.511,500%Cost of 10 hinges 287.6Cost of 1 butt hinge 28.76Say 28.75

9.7Providing and fixing bright finished brass butt hinges with necessaryscrews etc.complete :

9.72.1: 125x85x5.5 mm (heavy type)CodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Brass butt hinges 125x85x5.5 10 Nos 10 1 500.00 1 500.00###Brass screws 50 mm 100 Nos 100 107 107###Carriage of material L.S. 3.64 1 3.64

Labour-###Carpenter 1 st class Day .14 151.5 21.21###Beldar Day .1 135.25 13.52

TOTAL 1 645.37

Page 368: DAR_Vol_1

Add for water charge @ 1 % 16.45TOTAL 1 661.82Add for contractor’s profit and overheads @ 249.271,500%Cost for 10 nos. 1 911.09Cost of 1 no. 191.11Say 191.1

9.72 : Providing and fixing bright finished brass butt hinges with necessary screws etc.complete :

9.72.2 : 125x70x4 mm (ordinary type)CodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Brass butt hinges 125x70x4 m 10 Nos 10 450 450###Brass screws 50 mm 100 Nos 100 107 107###Carriage of material L.S. 3.64 1 3.64

Labour-

377CodDescription Unit Quantity Rate Amount###Carpenter 1 st class Day .14 151.5 21.21###Beldar Day .1 135.25 13.52

TOTAL 595.37Add for water charge @ 1% 5.95TOTAL 601.32Add for contractor’s profit and overheads @ 90.21,500%Cost for 10 nos. 691.52Cost of 1 no. 69.15Say 69.15

9.7Providing and fixing bright finished brass butt hinges with necessary screws etc.complete :

9.72.3 : 100x85x5.5 mm (heavy type)CodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Brass butt hinges 100x85x5.5 10 Nos 10 1,300 1,300###Brass screws 40 mm 100 Nos 80 96 76.8###Carriage of material L.S. 2.73 1 2.73

Labour-###Carpenter 1 st class Day .14 151.5 21.21###Beldar Day .1 135.25 13.52

TOTAL 1,414.26Add for water charge @ 1 % 14.14TOTAL 1,428.4Add for contractor’s profit and overheads @ 214.261,500%Cost for 10 nos. 1,642.66Cost of 1 no. 164.27Say 164.25

9.7Providing and fixing bright finished brass butt hinges with necessary screws etc.

Page 369: DAR_Vol_1

complete :9.72.4 : 100x70x4 mm (ordinary type)CodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Brass butt hinges 100x70x4 m 10 Nos 10 300 300###Brass screws 40 mm 100 Nos 80 96 76.8###Carriage of material L.S. 2.73 1 2.73

Labour-###Carpenter 1 st class Day .14 151.5 21.21###Beldar Day .1 135.25 13.52

TOTAL 414.26Add for water charge @ 1% 4.14TOTAL 418.4Add for contractor’s profit and overheads @ 62.761,500%Cost for 10 nos. 481.16Cost of 1 no. 48.12Say 48.1

3789.7Providing and fixing bright finished brass butt hinges with necessary screws etc.

complete :9.72.5 : 75x65x4 mm (heavy type)

CodDescription Unit Quantity Rate AmountDetails of cost for 10 nos.Materials-

###Brass butt hinges 75x65x4 mm 10 Nos 10 450 450###Brass screws 30 mm 100 Nos 60 86 51.6###Carriage of material L.S. 2.73 1 2.73

Labour-###Carpenter 1st class Day .14 151.5 21.21###Beldar Day .1 135.25 13.52

TOTAL 539.06Add for water charge @ 1% 5.39TOTAL 544.45Add for contractor’s profit and overheads @ 81.671,500%Cost for 10 nos. 626.12Cost of 1 no. 62.61Say 62.6

9.7Providing and fixing bright finished brass butthinges with necessaryscrews etc.complete :

9.72.6 : 75x40x2.5 mm (ordinary type)CodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Brass butt hinges 75x40x2.5 m 10 Nos 10 160 160###Brass screws 30 mm 100 Nos 60 86 51.69999 Carriage of material L.S. 2.73 1 2.73

Labour-

Page 370: DAR_Vol_1

0111 Carpenter 1st class Day .14 151.5 21.21###Beldar Day .1 135.25 13.52

TOTAL 249.06Add for water charge @ 1% 2.49TOTAL 251.55Add for contractor’s profit and overheads @ 37.731,500%Cost for 10 nos. 289.28Cost of 1 no. 28.93Say 28.95

9.72 : Providing and fixing bright finished brass butt hinges with necessary screws etc.complete :

9.72.7 : 50x40x2.5 mm (ordinary type)CodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Brass butt hinges 50x40x2.5 m 10 Nos 10 90 90###Brass screws 20 mm 100 Nos 40 53 21.2###Carriage of material L.S. 1.82 1 1.82

Labour-

379CodDescription Unit Quantity Rate Amount###Carpenter 1st class Day .08 151.5 12.12

TOTAL 125.14Add for water charge @ 1 % 1.25TOTAL 126.39Add for contractor’s profit and overheads @ 18.961,500%Cost for 10 nos. 145.35Cost of 1 no. 14.54Say 14.55

9.7Providing and fixing bright finished brass parliamentary hinges with necessaryscrews etc. complete :

9.73.1 : 150x125x27x5 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Parliamentary hingesl50xl25x27 10 Nos 10 1,650 1,6500450 Brass screws 40 mm 100 Nos 80 96 76.8###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 1 st class Day .14 151.5 21.210114 Beldar Day .14 135.25 18.94

TOTAL 1,769.68Add for water charge @ 1% 17.7TOTAL 1,787.38Add for contractor’s profit and overheads @ 268.111,500%Cost of 10 hinges 2,055.49Cost of 1 hinge 205.55Say 205.55

Page 371: DAR_Vol_1

9.7Providing and fixing bright finished brass parliamentary hinges with necessaryscrews etc. complete :

9.73.2 : 125x125x27x5 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Parliamentary hinges 125x125x 10 Nos 10 1,450 1,450###Brass screws 40 mm 100 Nos 80 96 76.8###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 1 st class Day .14 151.5 21.21###Beldar Day .14 135.25 18.94

TOTAL 1,569.68Add for water charge @ 1% 15.7TOTAL 1,585.38Add for contractor’s profit and overheads @ 237.811,500%Cost of 10 hinges 1,823.19Cost of 1 hinge 182.32Say 182.3

3809.7Providing and fixing bright finished brass parliamentary hingeswith necessary

screws etc. complete :9.73.3 : 100x125x27x5 mm

CodDescription Unit Quantity Rate AmountDetails of cost for 10 nos.Materials-

0387 Parliamentary hinges 100 10 Nos 1 1,175 1,175###Brass screws 40 mm 100 Nos 80 96 76.8###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 1 st class Day .14 151.5 21.21###Beldar Day .14 135.25 18.94

TOTAL 1,294.68Add for water charge @ 1 % 12.95TOTAL 1,307.63Add for contractor’s profit and overheads @ 196.141,500%Cost of 10 hinges 1,503.77Cost of 1 hinge 150.38Say 150.4

9.7Providing and fixing bright finished brass parliamentary hinges with necessaryscrews etc. complete :

9.73.4 : 75x100x20x3.2 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Parliamentary hinges 75x100x2 10 Nos 10 888 888###Brass screws 30 mm 100 Nos 60 86 51.6###Carriage of materials L.S. 2.73 1 2.73

Page 372: DAR_Vol_1

Labour-###Carpenter 1 st class Day .14 151.5 21.21###Beldar Day .14 135.25 18.94

TOTAL 982.48Add for water charge @ 1 % 9.82TOTAL 992.3Add for contractor’s profit and overheads @ 148.841,500%Cost of 10 hinges 1,141.14Cost of 1 hinge 114.11Say 114.1

9.7Providing and fixing bright finished brass towerbolts (barrel type)with necessaryscrews etc. complete :

9.74.1 : 250x10 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Brass barrel bolts 250x 10 mm each 10 123 1,230###Brass screws 30 mm 100 Nos 100 86 86###Carriage of materials L.S. 4.55 1 4.55

Labour-

381CodDescription Unit Quantity Rate Amount###Carpenter 1st class Day .1 151.5 15.15

TOTAL 1,335.7Add for water charge @ 1% 13.36TOTAL 1,349.06Add for contractor’s profit and overheads@ 202.361,500%Cost of 10 tower bolts 1,551.42Cost of 1 tower bolt 155.14Say 155.15

9.74 : Providing and fixing bright finished brass tower bolts (barrel type) with necessaryscrews etc. complete :

9.74.2 : 200x10 mm

CodDescription Unit Quantity Rate AmountDetails of cost for 10 nos.Materials-

###Brass barrel bolts 200x10 mm each 10 100 1,000###Brass screws 30 mm 100 Nos 80 86 68.8###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 1 st class Day .1 151.5 15.15

TOTAL 1,086.68Add for water charge @ 1 % 10.87TOTAL 1,097.55Add for contractor’s profit and overheads @ 164.631,500%Cost of 10 tower bolts 1,262.18Cost of 1 tower bolt 126.22Say 126.2

Page 373: DAR_Vol_1

9.74 : Providing and fixing bright finished brass tower bolts (barrel type) with necessaryscrews etc. complete :

9.74.3 : 150x10 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Brass barrel bolts 150x10 mm each 10 75 750###Brass screws 30 mm 100 Nos 80 86 68.8###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 1 st class Day .1 151.5 15.15

TOTAL 836.68Add for water charge @ 1 % 8.37TOTAL 845.05Add for contractor’s profit and overheads @ 126.761,500%Cost of 10 tower bolts 971.81Cost of 1 tower bolt 97.18Say 97.2

3829.74 : Providing and fixing bright finished brass tower bolts (barrel type) with necessary

screws etc. complete :9.7100x10 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Brass barrel bolts 100x10 mm each 10 51 510###Brass screws 30 mm 100 Nos 60 86 51.6###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 1 st class Day .1 151.5 15.15

TOTAL 579.48Add for water charge @ 1% 5.79TOTAL 585.27Add for contractor’s profit and overheads @ 87.791,500%Cost of 10 tower bolts 673.06Cost of 1 tower bolt 67.31Say 67.3

9.7Providing and fixing bright finished brass door latch with necessary screws etc.complete :

9.75.1 : 300x16x5 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Brass door latch 300x16x5 mm each 10 85 850###Brass screws 25 mm 100 Nos 90 76 68.4###Carriage of materials L.S. 3.64 1 3.64

Labour-###Carpenter 1 st class Day .12 151.5 18.18

Page 374: DAR_Vol_1

TOTAL 940.22Add for water charge @ 1 % 9.4TOTAL 949.62Add for contractor’s profit and overheads @ 142.441,500%Cost of 10 nos. 1,092.06Cost of 1 no. 109.21Say 109.2

9.7Providing and fixing bright finished brass door latch with necessary screws etc.complete :

9.75.2 : 250x16x5 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Brass door latch 250x16x5 mm each 10 82 820###Brass screws 25 mm 100 Nos 90 76 68.4###Carriage of materials L.S. 3.64 1 3.64

Labour-

383CodDescription Unit Quantity Rate Amount###Carpenter 1st class Day .12 151.5 18.18

TOTAL 910.22Add for water charge @ 1 % 9.1TOTAL 919.32Add for contractor’s profit and overheads @ 137.91,500%Cost of 10 nos. 1,057.22Cost of 1 no. 105.72Say 105.7

9.76 : Providing and fixing bright finished brass 100 mm mortice latch and lock with 6levers and a pair of lever handles with necessary screws etc. complete (best makeof approved quality).

CodDescription Unit Quantity Rate AmountDetails of cost for 1 No.Materials-

###100 mm mortice latch & lock witeach 1 257 257Labour-

###Carpenter 1st class Day .17 151.5 25.76###Sundries (screws, carriage etc.) L.S. 3.64 1 3.64

TOTAL 286.4Add for water charge @ 1 % 2.86TOTAL 289.26Add for contractor’s profit and overheads @ 43.391,500%Cost of 1 mortice latch and lock 332.65Say 332.65

9.77 : Providing and fixing bright finished brass 100 mm mortice latch with one dead boltand a pair of lever handles with necessary screws etc. complete (best make ofapproved quality).

CodDescription Unit Quantity Rate AmountDetails of cost for 1 No.

Page 375: DAR_Vol_1

Materials-###100 mm mortice latch each 1 235 235

Labour-###Carpenter 1st class Day .17 151.5 25.76###Sundries (screws, carriage etc.) L.S. 3.64 1 3.64

TOTAL 264.4Add for water charge @ 1 % 2.64TOTAL 267.04Add for contractor’s profit and overheads @ 40.061,500%Cost of 1 mortice latch and lock 307.1Say 307.1

9.78 : Providing and fixing bright finished brass night latch including necessary screwsetc. complete (best make of approved quality).

CodDescription Unit Quantity Rate AmountDetails of cost for 1 No.Materials-

###Brass night latch each 1 338 338Labour-

384CodDescription Unit Quantity Rate Amount###Carpenter 1st class Day .17 151.5 25.76###Sundries (screws, carriage etc.) L.S. 3.64 1 3.64

TOTAL 367.4Add for water charge @ 1 % 3.67TOTAL 371.07Add for contractor’s profit and overheads @ 55.661,500%Cost of 1 mortice latch and lock 426.73Say 426.75

9.7Providing and fixing special quality bright finished brass cupboard or ward robelocks with four levers including necessary screws etc. complete (best make ofapproved quality):

9.79.1 : 40 mm

CodDescription Unit Quantity Rate Amount

Details of cost for 1 No.Materials-

###40 mm lock each 1 36 36Labour-

###Carpenter 1 st class Day .17 151.5 25.76###Sundries & screws L.S. 3.64 1 3.64

TOTAL 65.4Add for water charge @ 1 % .65TOTAL 66.05Add for contractor’s profit and overheads @ 9.911,500%Cost of 1 mortice latch and lock 75.96Say 75.95

9.79 : Providing and fixing special quality bright finished brass cupboard or ward robe

Page 376: DAR_Vol_1

locks with four levers including necessary screws etc. complete (best make ofapproved quality):

9.79.2 : 50 mmCodDescription Unit Quantity Rate Amount

Details of cost for 1 No.Materials-

###50 mm lock each 1 43 43Labour-

###Carpenter 1st class Day .17 151.5 25.76###Sundries & screws L.S. 3.64 1 3.64

TOTAL 72.4Add for water charge @ 1 % .72TOTAL 73.12Add for contractor’s profit and overheads @ 10.971,500%Cost of 1 mortice latch and lock 84.09Say 84.1

3859.7Providing and fixing special quality bright finished brass cupboard or ward robe

locks with four levers including necessary screws etc. complete (best make ofapproved quality):

9.79.3 : 65 mmCodDescriptio Unit Quantity Rate Amount

Details of cost for 1 No.Materials-

###65 mm lo each 1 55 55Labour-

###Carpenter Day .17 151.5 25.76###Sundries & L.S. 3.64 1 3.64

TOTAL 84.4Add for water charge @ 1% .84TOTAL 85.24Add for contractor’s profit and overheads @ 12.791,500%Cost of 1 mortice latch and lock 98.03Say 98.05

9.79 Providing and fixing special quality bright finished brass cupboard or ward robelocks with four levers including necessary screws etc. complete (best make ofapproved quality):

9.775 mmCodDescriptio Unit Quantity Rate Amount

Details of cost for 1 No.Materials-

###75 mm lo each 1 70 70Labour-

###Carpenter Day .17 151.5 25.76###Sundries & L.S. 3.64 1 3.64

TOTAL 99.4Add for water charge @ 1 % .99TOTAL 100.39

Page 377: DAR_Vol_1

Add for contractor’s profit and overheads @ 15.061,500%Cost of 1 mortice latch and lock 115.45Say 115.45

9.80 : Providing and fixing 50 mm bright finished brass cup board or wardrobe knob withnecessary screws (best make of approved quality)

CodDescriptio Unit Quantity Rate AmountDetails of cost for 10 nos.Materials-

###Cupboard each 10 18 180###Carriage of L.S. 2.73 1 2.73

Labour-###Carpenter Day .14 151.5 21.21

TOTAL 203.94Add for water charge @ 1% 2.04TOTAL 205.98Add for contractor’s profit and overheads @ 30.91,500%Cost of 10 cupboard knob 236.88Cost of 1 cupboard knob 23.69Say 23.7

3869.8Providing and fixing bright finished brass handles with screws etc. complete :9.81.1 : 125 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Bright finished brass handles 1 each 10 85 850###Brass screws 25 mm 100 Nos 40 76 30.4###Carriage of material L.S. 2.73 1 2.73

Labour-###Carpenter 1 st class Day .06 151.5 9.09

TOTAL 892.22Add for water charge @ 1 % 8.92TOTAL 901.14Add for contractor’s profit and overheads @ 135.171,500%Cost of 10 handles 1 036.31Cost of 1 handle 103.63Say 103.65

9.81 : Providing and fixing bright finished brass handles with screws etc. complete :9.8100 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Bright finished brass handles 1 each 10 75 750###Brass screws 25 mm 100 Nos 40 76 30.4###Carriage of material L.S. .91 1 .91

Labour-###Carpenter 1st class Day .06 151.5 9.09

TOTAL 790.4

Page 378: DAR_Vol_1

Add for water charge @ 1 % 7.9TOTAL 798.3Add for contractor’s profit and overheads @ 119.741,500%Cost of 10 handles 918.04Cost of 1 handle 91.8Say 91.8

9.81 : Providing and fixing bright finished brass handles with screws etc. complete :9.81.3 : 75 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Bright finished brass handles 75 each 10 55 550l

###Brass screws 25 mm 100 Nos 40 76 30.4###Carriage of material L.S. .91 1 .91

Labour-###Carpenter 1 st class Day .06 151.5 9.09

TOTAL 590.4Add for water charge @ 1 % 5.9TOTAL 596.3Add for contractor’s profit and overheads @ 89.441,500%Cost of 10 handles 685.74Cost of 1 handle 68.57Say 68.55

3879.8Providing and fixing bright finished brass hanging type floor door stopper with

necessary screws, etc. complete.

CodDescription Unit Quantity Rate AmountDetails of cost for 10 hanging floor doorstopperMaterials-

###Bright finished brass floor door each 10 46 460###Brass screws 25 mm 100 Nos 20 76 15.2###Carriage of material L.S. 2.73 1 2.73

Labour-###Carpenter 1st class Day .03 151.5 4.54

TOTAL 482.47Add for water charge @ 1% 4.82TOTAL 487.29Add for contractor’s profit and overheads @ 73.091,500%Cost of 10 floor door stoppers 560.38Cost of 1 floor door stopper 56.04Say 56.05

9.8Providing and fixing IS : 3564 marked Aluminium die cast body tubular type universalhydraulic door closer with necessary accessories and screws etc. complete.

CodDescription Unit Quantity Rate AmountDetails of cost for 10 nos.Materials-

Page 379: DAR_Vol_1

###Hydraulic door closer with neces each 10 506 5,060accessories

###Brass screws 30 mm 100 Nos 60 86 51.6###Carriage of material L.S. 3.64 1 3.64

Labour-###Carpenter 2nd class Day 1 141.6 141.6

TOTAL 5,256.84Add for water charge @ 1 % 52.57TOTAL 5,309.41Add for contractor’s profit and overheads @ 796.411,500%Cost of 10 floor door closers 6,105.82Cost of 1 floor door closer 610.58Say 610.6

9.8Providing and fixing IS : 3564 marked aluminium extruded section body tubulartype universal hydraulic door closer with double speed adjustment with necessaryaccessories and screws etc. complete.

CodDescription Unit Quantity Rate AmountDetails of cost for 10 nos.Materials-

###Hydraulic door closer each 10 765 7,650###Brass screws 30 mm 100 Nos 60 86 51.6###Carriage of material L.S. 1 1.04 1.04

Labour-###Carpenter 2nd class Day 1 141.6 141.6

TOTAL 7,844.24

388CodDescription Unit Quantity Rate Amount

Add for water charge @ 1% 78.44TOTAL 7,922.68Add for contractor’s profit and overheads @ 1,188.41,500%Cost of 10 floor door closers 9,111.08Cost of 1 floor door closer 911.11Say 911.1

9.85 : Providing and fixing bright finished brass casement window fastener with necessaryscrews etc. complete.

CodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Brass casement window fastne each 10 26 260###Brass screws 25 mm 100 Nos 40 76 30.4###Carriage of material L.S. .91 1 .91

Labour-###Carpenter 1 st class Day .1 151.5 15.15

TOTAL 306.46Add for water charge @ 1 % 3.06TOTAL 309.52Add for contractor’s profit and overheads @ 46.431,500%

Page 380: DAR_Vol_1

Cost of 10 floor window fastners 355.95Cost of 1 floor window fastner 35.6Say 35.6

9.8Providing and fixing bright finished brasscasement stays (straight peg type) withnecessary screws etc. complete :

9.86.1: 300 mm weighing not less than 330 gmsCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Brass casement stayes 300 mm each 10 66 660###Brass screws 30 mm 100 Nos 40 86 34.4###Carriage of material L.S. .91 1 .91

Labour-###Carpenter 1 st class Day .1 151.5 15.15

TOTAL 710.46Add for water charge @ 1% 7.1TOTAL 717.56Add for contractor’s profit and overheads @ 107.631,500%Cost of 10 casement stayes 825.19Cost of 1 casement staye 82.52Say 82.5

3899.8Providing and fixing bright finished brass casement stays (straight peg type) with

necessary screws etc. complete :9.86.2 : 250 mm weighing not less than 280 gms

CodDescription Unit Quantity Rate AmountDetails of cost for 10 nos.Materials-

###Brass casement stayes 250 mm each 10 55 550###Brass screws 25 mm 100 Nos 40 76 30.4###Carriage of material L.S. .91 1 .91

Labour-###Carpenter 1 st class Day .1 151.5 15.15

TOTAL 596.46Add for water charge @ 1 % 5.96TOTAL 602.42Add for contractor’s profit and overheads @ 90.361,500%Cost of 10 casement stayes 692.78Cost of 1 casement staye 69.28Say 69.3

9.8Providing and fixing bright finished brass casement stays (straight peg type) withnecessary screws etc. complete :

9.8200 mm weighing not less than 240 gmsCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Brass casement stayes 200 mm each 10 46 460###Brass screws 25 mm 100 Nos 40 76 30.4

Page 381: DAR_Vol_1

###Carriage of material L.S. .91 1 .91Labour-

###Carpenter 1 st class Day .1 151.5 15.15TOTAL 506.46Add for water charge @ 1 % 5.06TOTAL 511.52Add for contractor’s profit and overheads @ 76.731,500%Cost of 10 casement stayes 588.25Cost of 1 casement staye 58.83Say 58.8

9.8Providing and fixing bright finished brass hasp and staple (safety type) withnecessary screws etc. complete:

9.8150 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Brass Safety hasps & staples 1 10 Nos 10 458 458###Brass screws 25 mm 100 Nos 80 76 60.8###Carriage of material L.S. 1.82 1 1.82

Labour-###Carpenter 1st class Day .08 151.5 12.12

TOTAL 532.74

390CodDescription Unit Quantity Rate Amount

Add for water charge @ 1% 5.33TOTAL 538.07Add for contractor’s profit and overheads @ 80.711,500%Cost of 10 hasps and staples 618.78Cost of 1 hasps and staple 61.88Say 61.9

9.8Providing and fixing bright finished brass hasp and staple (safety type) withnecessary screws etc. complete:

9.87.2 : 115 mm

CodDescription Unit Quantity Rate AmountDetails of cost for 10 nos.Materials-

###Brass Safety hasps & staples 11 10 Nos 10 378 378###Brass screws 20 mm 100 Nos 70 53 37.1###Carriage of material L.S. 1.82 1 1.82

Labour-###Carpenter 1st class Day .08 151.5 12.12

TOTAL 429.04Add for water charge @ 1% 4.29TOTAL 433.33Add for contractor’s profit and overheads @ 651,500%Cost of 10 hasps and staples 498.33Cost of 1 hasps and staple 49.83Say 49.85

Page 382: DAR_Vol_1

9.8Providing and fixing bright finished brass hasp and staple (safety type) withnecessary screws etc. complete:

9.890 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Brass Safety hasps & staples 9 10 Nos 10 300 300###Brass screws 20 mm 100 Nos 70 53 37.1###Carriage of material L.S. 1.82 1 1.82

Labour-###Carpenter 1 st class Day .08 151.5 12.12

TOTAL 351.04Add for water charge @ 1 % 3.51TOTAL 354.55Add for contractor’s profit and overheads @ 53.181,500%Cost of 10 hasps and staples 407.73Cost of 1 hasps and staple 40.77Say 40.75

3919.8Providing and fixing chromium plated brass 100 mm mortice latch and lock with 6

levers and a pair of lever handles with necessary screws etc. complete (best makeof approved quality).

CodDescription Unit Quantity Rate Amount

Details of cost for 1 No.Materials-

###100 mm mortice latch & lock witeach 1 323 323Labour-

###Carpenter 1 st class Day .17 151.5 25.76###Sundries (screws, carriage etc.) L.S. 3.64 1 3.64

TOTAL 352.4Add for water charge @ 1% 3.52TOTAL 355.92Add for contractor’s profit and overheads @ 53.391,500%Cost of 1 mortice latch and lock 409.31Say 409.3

9.8Providing and fixing chromium plated brass night latch including necessary screwsetc. complete (Best make of approved quality).

CodDescription Unit Quantity Rate AmountDetails of cost for 1 No.Materials-

###Brass night latch each 1 383 383Labour-

###Carpenter 1st class Day .17 151.5 25.76###Sundries (screws, carriage etc.) L.S. 3.64 1 3.64

TOTAL 412.4Add for water charge @ 1 % 4.12TOTAL 416.52Add for contractor’s profit and overheads @ 62.48

Page 383: DAR_Vol_1

1,500%Cost of 1 mortice latch and lock 479Say 479

9.9Providing and fixing special quality chromium plated brass cupboard locks withsix levers including necessary screws etc. complete (Best make of approvedquality) of :

9.9Size 40 mmCodDescription Unit Quantity Rate Amount

Details of cost for 1 No.Materials-

###40 mm lock each 1 38 38Labour-

###Carpenter 1st class Day .17 151.5 25.76###Sundries & screws L.S. 3.64 1 3.64

TOTAL 67.4Add for water charge @ 1 % .67TOTAL 68.07Add for contractor’s profit and overheads @ 10.211,500%Cost of 1 mortice latch and lock 78.28Say 78.3

3929.9Providing and fixing special quality chromium plated brass cupboard locks with

six levers including necessary screws etc. complete (Best make of approvedquality) of :

9.9Size 50 mm

CodDescription Unit Quantity Rate AmountDetails of cost for 1 No.Materials-

###50 mm lock each 1 53 53Labour-

###Carpenter 1st class Day .17 151.5 25.76###Sundries & screws L.S. 3.64 1 3.64

TOTAL 82.4Add for water charge @ 1 % .82TOTAL 83.22Add for contractor’s profit and overheads @ 12.481,500%Cost of 1 mortice latch and lock 95.7Say 95.7

9.9Providing and fixing special quality chromium plated brass cupboard locks withsix levers including necessary screws etc. complete (Best make of approvedquality) of :

9.9Size 65 mmCodDescription Unit Quantity Rate Amount

Details of cost for 1 no.Materials-

###65 mm lock each 1 64 64Labour-

Page 384: DAR_Vol_1

###Carpenter 1 st class Day .17 151.5 25.76###Sundries & screws L.S. 3.64 1 3.64

TOTAL 93.4Add for water charge @ 1 % .93TOTAL 94.33Add for contractor’s profit and overheads @ 14.151,500%Cost of 1 mortice latch and lock 108.48Say 108.5

9.9Providing and fixing special quality chromium plated brass cupboard locks withsix levers including necessary screws etc. complete (Best make of approvedquality) of :

9.90.4 : Size 75 mmCodDescription Unit Quantity Rate Amount

Details of cost for oneMaterials-

###75 mm lock each 1 75 75Labour-

###Carpenter 1st class Day .17 151.5 25.76###Sundries & screws L.S. 3.64 1 3.64

TOTAL 104.4Add for water charge @ 1 % 1.04

393CodDescription Unit Quantity Rate Amount

TOTAL 105.44Add for contractor’s profit and overheads @ 15.821,500%Cost of 1 mortice latch and lock 121.26Say 121.25

9.9Providing and fixing chromium plated brass 50 mm cupboard or wardrobe knobswith nuts complete.

CodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Cupboard knob each 10 25 250###Carriage of material L.S. 2.73 1 2.73

Labour-###Carpenter 1 st class Day .14 151.5 21.21

TOTAL 273.94Add for water charge @ 1 % 2.74TOTAL 276.68Add for contractor’s profit and overheads @ 41.51,500%Cost of 10 cupboard knob 318.18Cost of 1 cupboard knob 31.82Say 31.8

9.9Providing and fixing chromium plated brass handles with necessary screws etc.complete:

9.9125 mm

Page 385: DAR_Vol_1

CodDescription Unit Quantity Rate AmountDetails of cost for 10 nos.Materials-

###Chromium plated brass handles each 10 92 920###Brass screws 25 mm 100 Nos 40 76 30.4###Carriage of material L.S. 2.73 1 2.73

Labour-###Carpenter 1 st class Day .06 151.5 9.09

TOTAL 962.22Add for water charge @ 1 % 9.62TOTAL 971.84Add for contractor’s profit and overheads @ 145.781,500%Cost of 10 handles 1 117.62Cost of 1 handle 111.76Say 111.75

9.92 : Providing and fixing chromium plated brass handles with necessary screws etc.complete:

9.92.2 : 100 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Chromium plated brass handles each 10 79 790###Brass screws 25 mm 100 Nos 40 76 30.4

394CodDescription Unit Quantity Rate Amount###Carriage of material L.S. .91 1 .91

Labour-###Carpenter 1 st class Day .06 151.5 9.09

TOTAL 830.4Add for water charge @ 1% 8.3TOTAL 838.7Add for contractor’s profit and overheads @ 125.81,500%Cost of 10 handles 964.5Cost of 1 handle 96.45Say 96.45

9.92 : Providing and fixing chromium plated brass handles with necessary screws etc.complete:

9.92.3 : 75 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Chromium plated brass handles each 10 68 680###Brass screws 25 mm 100 Nos 40 76 30.4###Carriage of material L.S. .91 1 .91

Labour-###Carpenter 1st class Day .06 151.5 9.09

TOTAL 720.4Add for water charge @ 1% 7.2TOTAL 727.6Add for contractor’s profit and overheads @ 109.14

Page 386: DAR_Vol_1

1,500%Cost of 10 handles 836.74Cost of 1 handle 83.67Say 83.65

9.93 : Providing and fixing chromium plated brass casement window fastener withnecessary screws etc. complete.

CodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###C.P. brass window fastner each 10 55 550###C.P. brass screws 25 mm 100 Nos 40 83 33.2###Carriage of material L.S. .91 1 .91

Labour-###Carpenter 1st class Day .1 151.5 15.15

TOTAL 599.26Add for water charge @ 1 % 5.99TOTAL 605.25Add for contractor’s profit and overheads @ 90.791,500%Cost of 10 window fasteners 696.04Cost of 1 window fastener 69.6Say 69.6

3959.9Providing and fixing chromium plated brass casement stays (straight peg type)

with necessary screws etc. complete :9.94.1 : 300 mm weighing not less than 330 gmsCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Material s-

###C.P. brass casement stays 300 m each 10 73 730###C.P. brass screws 25 mm 100 Nos 40 83 33.2###Carriage of material L.S. .91 1 .91

Labour-###Carpenter 1 st class Day .1 151.5 15.15

TOTAL 779.26Add for water charge @ 1 % 7.79TOTAL 787.05Add for contractor’s profit and overheads @ 118.061,500%Cost of 10 window fasteners 905.11Cost of 1 window fastener 90.51Say 90.5

9.9Providing and fixing chromium plated brass casement stays (straight peg type)with necessary screws etc. complete :

9.94.2 : 250 mm weighing not less than 280 gmsCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###C.P. brass casement stays 250 m each 10 67 670

Page 387: DAR_Vol_1

###C.P. brass screws 25 mm 100 Nos 40 83 33.2###Carriage of material L.S. .91 1 .91

Labour-###Carpenter 1st class Day .1 151.5 15.15

TOTAL 719.26Add for water charge @ 1 % 7.19TOTAL 726.45Add for contractor’s profit and overheads @ 108.971,500%Cost of 10 window fasteners 835.42Cost of 1 window fastener 83.54Say 83.55

### Providing and fixing chromium plated brass casement stays (straight peg type)with necessary screws etc. complete :

9.94.3 200 mm weighing not less than 240 gmsCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###C.P. brass casement stays 200 m each 10 56 560###C.P. brass screws 25 mm 100 Nos 40 83 33.2###Carriage of material L.S. .91 1 .91

Labour-###Carpenter 1st class Day .1 151.5 15.15

TOTAL 609.26

396CodDescription Unit Quantity Rate Amount

Add for water charge @ 1 % 6.09TOTAL 615.35Add for contractor’s profit and overheads @ 92.31,500%Cost of 10 window fasteners 707.65Cost of 1 window fastener 70.77Say 70.75

9.9Providing and fixing ISI marked aluminium butt hinges anodised (anodic coatingnot less than grade AC 10 as per IS : 1868) transparent or dyed to required colouror shade with necessary screws etc. complete:

9.9125x75x4 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Aluminium butt hinges 125x75x 10 Nos 10 478 478###C.P.brass screws 50 mm 100 Nos 100 123 123###Carriage of materials L.S. 3.64 1 3.64

Labour-###Carpenter 1st class Day .14 151.5 21.21###Beldar Day .09 135.25 12.17

TOTAL 638.02Add for water charge @ 1 % 6.38TOTAL 644.4

Page 388: DAR_Vol_1

Add for contractor’s profit and overheads @ 96.661,500%Cost of 10 nos. 741.06Cost of 1 no. 74.11Say 74.1

9.9Providing and fixing ISI marked aluminium butt hinges anodised (anodic coatingnot less than grade AC 10 as per IS : 1868) transparent or dyed to required colouror shade with necessary screws etc. complete:

9.95.2 : 125x63x4 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Aluminium butt hinges 125x63x 10 Nos 10 447 447###C.P.brass screws 50 mm 100 Nos 100 123 123###Carriage of materials L.S. 3.64 1 3.64

Labour-###Carpenter 1 st class Day .14 151.5 21.21###Beldar Day .09 135.25 12.17

TOTAL 607.02Add for water charge @ 1 % 6.07TOTAL 613.09Add for contractor’s profit and overheads @ 91.961,500%Cost of 10 nos. 705.05Cost of 1 no. 70.51Say 70.5

397 9. Providing and fixing ISI marked aluminium butt hinges anodised (anodic coating

not less than grade AC 10 as per IS : 1868) transparent or dyed to required colouror shade with necessary screws etc. complete:

9.9100x75x4 mm

CodDescription Unit Quantity Rate AmountDetails of cost for 10 nos.Materials-

###Aluminium butt hinges 100x75x 10 Nos 10 416 416###C.P.brass screws 40 mm 100 Nos 80 150 120###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 1 st class Day .14 151.5 21.21###Beldar Day .09 135.25 12.17

TOTAL 572.11Add for water charge @ 1% 5.72TOTAL 577.83Add for contractor’s profit and overheads @ 86.671,500%Cost of 10 nos. 664.5Cost of 1 no. 66.45Say 66.45

9.9Providing and fixing ISI marked aluminium butt hinges anodised (anodic coatingnot less than grade AC 10 as per IS : 1868) transparent or dyed to required colour

Page 389: DAR_Vol_1

or shade with necessary screws etc. complete:9.9100x63x4 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Aluminium butt hinges 100x63x 10 Nos 10 354 354###C.P.brass screws 40 mm 100 Nos 80 150 120###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 1st class Day .14 151.5 21.21###Beldar Day .09 135.25 12.17

TOTAL 510.11Add for water charge @ 1% 5.1TOTAL 515.21Add for contractor’s profit and overheads @ 77.281,500%Cost of 10 nos. 592.49Cost of 1 no. 59.25Say 59.25

9.9Providing and fixing ISI marked aluminium butt hinges anodised (anodic coatingnot less than grade AC 10 as per IS : 1868) transparent or dyed to required colouror shade with necessary screws etc. complete:

9.95.5 : 100x63x3.2 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Aluminium butt hingesl00x63x3 10 Nos 10 390 390###C.P.brass screws 40 mm 100 Nos 80 150 120

398CodDescription Unit Quantity Rate Amount###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 1 st class Day .14 151.5 21.21###Beldar Day .09 135.25 12.17

TOTAL 546.11Add for water charge @ 1 % 5.46TOTAL 551.57Add for contractor’s profit and overheads @ 82.741,500%Cost of 10 nos. 634.31Cost of 1 no. 63.43Say 63.45

9.9Providing and fixing ISI marked aluminium butt hinges anodised (anodic coatingnot less than grade AC 10 as per IS : 1868) transparent or dyed to required colouror shade with necessary screws etc. complete:

9.95.6 : 75x63x4 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Aluminium butt hinges 75x63x4 10 Nos 10 281 281###C.P.brass screws 30 mm 100 Nos 60 90 54

Page 390: DAR_Vol_1

###Carriage of materials L.S. 1.82 1 1.82Labour-

###Carpenter 1st class Day .14 151.5 21.21###Beldar Day .09 135.25 12.17

TOTAL 370.2Add for water charge @ 1 % 3.7TOTAL 373.9Add for contractor’s profit and overheads @ 56.081,500%Cost of 10 nos. 429.98Cost of 1 no. 43Say 43

9.9Providing and fixing ISI marked aluminium butt hinges anodised (anodic coatingnot less than grade AC 10 as per IS : 1868) transparent or dyed to required colouror shade with necessary screws etc. complete:

9.975x63x3.2 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Aluminium butt hinges 75x63x3 10 Nos 10 215 215###C.P.brass screws 30 mm 100 Nos 60 90 54###Carriage of materials L.S. 1.82 1 1.82

Labour-###Carpenter 1st class Day .14 151.5 21.21###Beldar Day .09 135.25 12.17

TOTAL 304.2Add for water charge @ 1% 3.04TOTAL 307.24Add for contractor’s profit and overheads @ 46.091,500%Cost of 10 nos. 353.33Cost of 1 no. 35.33Say 35.35

3999.9Providing and fixing ISI marked aluminium butt hinges anodised (anodic coating

not less than grade AC 10 as per IS : 1868) transparent or dyed to required colouror shade with necessary screws etc. complete: .

9.95.8 : 75x45x3.2 mm

CodDescription Unit Quantity Rate AmountDetails of cost for 10 nos.Materials-

###Aluminium butt hinges 75x45x3 10 Nos 10 98 98###C.P.brass screws 30 mm 100 Nos 60 90 54###Carriage of materials L.S. 1.82 1 1.82

Labour-###Carpenter 1 st class Day .14 151.5 21.21###Beldar Day .09 135.25 12.17

TOTAL 187.2Add for water charge @ 1% 1.87TOTAL 189.07

Page 391: DAR_Vol_1

Add for contractor’s profit and overheads @ 28.361,500%Cost of 10 nos. 217.43Cost of 1 no. 21.74Say 21.75

### Providing and fixing aluminium sliding door bolts ISI marked anodised (anodiccoating not less than grade AC 10 as per IS : 1868) transparent or dyed to requiredcolour or shade with nuts and screws etc. complete :

9.96.1 300x16 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Aluminium sliding bolt 300x16 each 10 125 1 250.00###C.P. brass screws 25 mm 100 Nos 40 83 33.2###Carriage of materials L.S. 5.46 1 5.46

Labour-###Carpenter 1st class Day .5 151.5 75.75

TOTAL 1 364.41Add for water charge @ 1% 13.64TOTAL 1 378.05Add for contractor’s profit and overheads @ 206.711,500%Cost of 10 sliding bolts 1 584.76Cost of 1 sliding bolt 158.48Say 158.5

### Providing and fixing aluminium sliding door bolts ISI marked anodised (anodiccoating not less than grade AC 10 as per IS : 1868) transparent or dyed to requiredcolour or shade with nuts and screws etc. complete :

9.96.2 250x16 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Aluminium sliding bolt 250x16 each 10 104 1 040.00###C.P. brass screws 25 mm 100 Nos 40 83 33.2

400CodDescription Unit Quantity Rate Amount###Carriage of materials L.S. 5.46 1 5.46

Labour-###Carpenter 1st class Day .5 151.5 75.75

TOTAL 1,154.41Add for water charge @ 1 % 11.54TOTAL 1,165.95Add for contractor’s profit and overheads @ 174.891,500%Cost of 10 sliding bolts 1,340.84Cost of 1 sliding bolt 134.08Say 134.1

9.9Providing and fixing aluminium tower bolts ISI marked anodised (anodic coatingnot less than grade AC 10 as per IS : 1868 ) transparent or dyed to required colouror shade with necessary screws etc. complete :

Page 392: DAR_Vol_1

9.9300x10 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Aluminium tower bolt (barrel ty 10 Nos 10 520 520mm

###C.P. brass screws 30 mm 100 Nos 80 90 72###Carriage of materials L.S. 4.42 1 4.42

Labour-###Carpenter 1st class Day .125 151.5 18.94

TOTAL 615.36Add for water charge @ 1% 6.15TOTAL 621.51Add for contractor’s profit and overheads @ 93.231,500%Cost of 10 tower bolts 714.74Cost of 1 tower bolt 71.47Say 71.45

9.9Providing and fixing aluminium tower bolts ISI marked anodised (anodic coatingnot less than grade AC 10 as per IS : 1868 ) transparent or dyed to required colouror shade with necessary screws etc. complete :

9.97.2 : 250x10 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Aluminium tower bolt (barrel ty 10 Nos 10 440 440mm

###C.P. brass screws 30 mm 100 Nos 80 90 72###Carriage of materials L.S. 4.42 1 4.42

Labour-###Carpenter 1st class Day .125 151.5 18.94

TOTAL 535.36Add for water charge @ 1 % 5.35TOTAL 540.71Add for contractor’s profit and overheads @ 81.111,500%Cost of 10 tower bolts 621.82Cost of 1 tower bolt 62.18Say 62.2

4019.9Providing and fixing aluminium tower bolts ISI marked anodised (anodic coating

not less than grade AC 10 as per IS : 1868 ) transparent or dyed to required colouror shade with necessary screws etc. complete :

9.97.3 : 200x10 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Aluminium tower bolt (barrel ty 10 Nos 10 354 354mm

###C.P. brass screws 30 mm 100 Nos 80 90 72

Page 393: DAR_Vol_1

###Carriage of materials L.S. 2.73 1 2.73Labour-

###Carpenter 1 st class Day .125 151.5 18.94TOTAL 447.67Add for water charge @ 1% 4.48TOTAL 452.15Add for contractor’s profit and overheads @ 67.821,500%Cost of 10 tower bolts 519.97Cost of 1 tower bolt 52Say 52

9.9Providing and fixing aluminium tower bolts ISI marked anodised (anodic coatingnot less than grade AC 10 as per IS : 1868 ) transparent or dyed to required colouror shade with necessary screws etc. complete :

9.97.4 : 150x10 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Aluminium tower bolt barrel typ 10 Nos 10 281 281mm

###C.P. brass screws 30 mm 100 Nos 80 90 72###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 1st class Day .08 151.5 12.12

TOTAL 367.85Add for water charge @ 1% 3.68TOTAL 371.53Add for contractor’s profit and overheads @ 55.731,500%Cost of 10 tower bolts 427.26Cost of 1 tower bolt 42.73Say 42.75

9.9Providing and fixing aluminium tower bolts ISI marked anodised (anodic coatingnot less than grade AC 10 as per IS : 1868 ) transparent or dyed to required colouror shade with necessary screws etc. complete :

9.97.5 : 100x10 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Aluminium tower bolt (barrel t 10 Nos 10 208 208###C.P. brass screws 30 mm 100 Nos 60 90 54

402CodDescription Unit Quantity Rate Amount###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 1st class Day .08 151.5 12.12

TOTAL 276.85Add for water charge @ 1 % 2.77TOTAL 279.62Add for contractor’s profit and overheads @ 41.941,500%

Page 394: DAR_Vol_1

Cost of 10 tower bolts 321.56Cost of 1 tower bolt 32.16Say 32.15

9.9Providing and fixing aluminium pull bolt lock anodised ISI marked (anodic coatingnot less than grade AC 10 as per IS : 1868) transparent or dyed to required colourand shade with necessary screws bolts, nuts and washers etc. complete.

CodDescription Unit Quantity Rate Amount

Details of cost for 10 pull bolt lockMaterials-

###aluminum Pull bolt lock with nec each 10 34 340bolts, eachnuts and washers complete

###Carriage of materials L.S. 6.37 1 6.37Labour-

###Carpenter 2nd class Day .25 141.6 35.4TOTAL 381.77Add for water charge @ 1% 3.82TOTAL 385.59Add for contractor’s profit and overheads @ 57.841,500%Cost of 10 pull bolt locks 443.43Cost of 1 pull bolt lock 44.34Say 44.35

9.99 : Providing and fixing 50cm long aluminium kicking plate 100x3.15 mm anodised(anodic coating not less than grade AC 10 as per IS : 1868) transparent or dyed torequired colour or shade with necessary screws etc. complete.

CodDescription Unit Quantity Rate AmountDetails of cost for 10 nos.Materials

###Kicking plate 50 cm long - 100x each 10 94 940###C.P. brass screws 25 mm 100 Nos 40 83 33.2###Carriage of materials L.S. 5.46 1 5.46

Labour-###Carpenter 1 st class Day .07 151.5 10.6###Beldar Day .05 135.25 6.76

TOTAL 996.02Add for water charge @ 1 % 9.96TOTAL 1,005.98Add for contractor’s profit and overheads @ 150.91,500%Cost of 10 kicking plates 1,156.88Cost of 1 kicking plate 115.69Say 115.7

4039.1Providing and fixing aluminium handles ISI marked anodised (anodic coating not

less than grade AC 10 as per IS : 1868) transparent or dyed to required colour orshade with necessary screws etc. complete :

9.100.1 : 125 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.

Page 395: DAR_Vol_1

Materials-###Aluminium handles 125 mm 10 Nos 10 375 375###C.P. brass screws 25 mm 100 Nos 40 83 33.2###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 1st class Day .06 151.5 9.09

TOTAL 420.02Add for water charge @ 1% 4.2TOTAL 424.22Add for contractor’s profit and overheads @ 63.631,500%Cost of 10 handles 487.85Cost of 1 handle 48.79Say 48.8

9.1Providing and fixing aluminium handles ISI marked anodised (anodic coating notless than grade AC 10 as per IS : 1868) transparent or dyed to required colour orshade with necessary screws etc. complete :

9.100.2 : 100 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Aluminium handles 100 mm 10 Nos 10 260 260###C.P. brass screws 25 mm 100 Nos 40 83 33.2###Carriage of materials L.S. 1.82 1 1.82

Labour-###Carpenter 1 st class Day .06 151.5 9.09

TOTAL 304.11Add for water charge @ 1 % 3.04TOTAL 307.15Add for contractor’s profit and overheads @ 46.071,500%Cost of 10 handles 353.22Cost of 1 handle 35.32Say 35.3

9.100 : Providing and fixing aluminium handles ISI marked anodised (anodic coating notless than grade AC 10 as per IS : 1868) transparent or dyed to required colour orshade with necessary screws etc. complete :

9.100.3 : 75 mmCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Aluminium handles 75 mm 10 Nos 10 208 208###C.P. brass screws 25 mm 100 Nos 40 63 25.2

404CodDescription Unit Quantity Rate Amount###Carriage of materials L.S. 1.82 1 1.82

Labour-###Carpenter 1st class Day .06 151.5 9.09

TOTAL 244.11Add for water charge @ 1 % 2.44TOTAL 246.55

Page 396: DAR_Vol_1

Add for contractor’s profit and overheads @ 36.981,500%Cost of 10 handles 283.53Cost of 1 handle 28.35Say 28.35

9.1Providing and fixing aluminium hanging floor door stopper ISI marked anodised(anodic coating not less than grade AC 10 as per IS : 1868) transparent or dyed torequired colour and shade with necessary screws etc. complete.

9.101.1: Single rubber stopperCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Aluminium hanging floor door s each 10 14 140###C.P. brass screws 25 mm 100 Nos 20 83 16.6###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 1 st class Day .03 151.5 4.54

TOTAL 163.87Add for water charge @ 1 % 1.64TOTAL 165.51Add for contractor’s profit and overheads @ 24.831,500%Cost of 10 door stoppers 190.34Cost of 1 stopper 19.03Say 19.05

### Providing and fixing aluminium hanging floor door stopper ISI marked anodised(anodic coating not less than grade AC 10 as per IS : 1868) transparent or dyed torequired colour and shade with necessary screws etc. complete.

9.101.2: Twin rubber stopperCodDescription Unit Quantity Rate Amount

Details of cost for 10 nos.Materials-

###Aluminium hanging floor door st each 10 44 440twin rubber stopper

0588 C.P. brass screws 25 mm 100 Nos 20 83 16.6###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 1st class Day .03 51.5 4.54

TOTAL 463.87Add for water charge @ 1 % 4.64TOTAL 468.51Add for contractor’s profit and overheads @ 70.281,500%Cost of 10 door stoppers 538.79Cost of 1 stopper 53.88Say 53.9

405### Providing and fixing aluminium casement stays ISI marked anodised (anodic coating

not less than grade AC 10 as per IS : 1868) transparent or dyed to required colourand shade with necessary screws etc. complete.

CodDescription Unit Quantity Rate Amount

Page 397: DAR_Vol_1

Details of cost for 10 nos.Materials-

###Aluminium casement stays each 10 36 360###C.P. brass screws 25 mm 100 Nos 40 83 33.2###Carriage of materials L.S. .91 1 .91

Labour-###Carpenter 1 st class Day .1 151.5 15.15

TOTAL 409.26Add for water charge @ 1 % 4.09TOTAL 413.35Add for contractor’s profit and overheads @ 621,500%Cost of 10 casement stays 475.35Cost of 1 casement stay 47.54Say 47.55

9.103 :Providing and fixing bright finished brass 100 mm mortice latch and lock ISI markedwith six levers and a pair of anodised (anodic coating not less than grade AC 10 asper IS : 1868) aluminium lever handles with necessary screws etc. complete (Bestmake of approved quality).

CodDescription Unit Quantity Rate AmountDetails of cost for 1 lockMaterials-

###100 mm mortice latch and lock each 1 150 150handles)

###Pair of aluminium handles each 1 195 195Labour-

###Carpenter 1 st class Day .17 151.5 25.76###Sundries including carriage of maL.S. 4.55 1 4.55

TOTAL 375.31Add for water charge @ 1% 3.75TOTAL 379.06Add for contractor’s profit and overheads @ 56.861,500%Cost of 1 lock 435.92Say 435.9

9.104 : Providing and fixing aluminium tee channels (heavy duty) with rollers, stop end inpelmets as curtain rod.

CodDescription Unit Quantity Rate AmountDetails of cost for 2m longMaterials-

###Aluminium channel (heavy duty) metre 2 35 70stop end as curtain rod

###Labour L.S. 2.73 1 2.73###Sundries L.S. 1.43 1 1.43

TOTAL 74.16Add for water charge @ 1% .74TOTAL 74.9Add for contractor’s profit and overheads @ 11.241,500%Cost of 2 m 86.14Cost of 1 m 43.07Say 43.05

Page 398: DAR_Vol_1

4069.105 : Providing and fixing partition upto ceiling height consisting of G.I. frame and

required board including providing and fixing of frame work made of special sectionpower pressed/ role form G.I. sheet with zinc coating of grade 175 consisting offloor and ceiling channel 50mm wide having equal flanges of 32mm and 0.5mmthick fixed to the floor and ceiling at the spacing of 610mm centre to centre withdash fastener of 12.5mm dia-meter,40mm length and the studs 48mm wide havingone flange of 34mm and other flange 36mm and 0.50mm thick fixed vertically withinflanges of floor and ceiling channel and placed at a spacing of 610mm centre tocentre by 6mm dia bolts and nuts at both ends of partition fixed flush to wall withrawl plugs at spacing 450mm centre to centre and fixing of boards to either side offrame work by 25mm drive all screws on studs, floor and ceiling channels at thespacing of 300mm centre to centre, including jointing and finishing to a flush finishwith recommended jointing compound, jointing tape, joint finisher and two coatsof primer suitable for board as per manufacture’s specificatior and direction ofengineer-in-charge all complete.

9.105.1: 67mm overall thickness partition with 8.5 mm thick double skin Glass reinforcedGypsum (GRG) board conforming to IS: 2095: part III

CodDescriptio Unit Quantity Rate Amount

Materials for 6.00x3.65 = 21.9 sqm. (PartitionPanel)

###(i)Glass re sqm 43.8 190 8,322mm thick

###(ii) 50mm f metre 12 48 576=12m

###(iii) 48mm metre 40.15 55 2,208.25(6.00/0.61)+1 = 11x3.65 = 40.15m

###(iv) Screw 100 Nos 392 40 156.8[(3.65/0.30)+1]x11x2 = 308[(6.00/0.30)+1]x2x2=84 = 392

###(v) Dash f each 22 8 176###(vi) Rawl p each 18 7 126###(vii) Plast kilogram 19.27 2.5 48.18###(viii) Glu kilogram 4.82 50 241###(ix) Paper roll .584 120 70.08

(300/100)x21.90/120 = 0.584 Nos.###(x) Primer litre 7.88 76 598.88###(xi) Galvan 10 Nos 44 9 39.6

25mm Long 11x2x2=44###(xii) G.I. P 100 Nos 44 21 9.24###Sundries caL.S. 52 1 52###Sundries s L.S. 130 1 130

Labour for 21.90 sqm.###Carpernter Day 6.57 151.5 995.36###Carpenter Day 2.847 141.6 403.14###Painter 0. Day 1.095 141.6 155.05###Beldar 0. Day 7.665 135.25 1,036.69

TOTAL ###Add for water charge @ 1 % 153.44TOTAL ###Add for contractor’s profit and overheads @ 2,324.661,500%Cost for 21.90 sqm ###Cost for 1 sqm. 813.81

Page 399: DAR_Vol_1

Say 813.8

4079.1Providing and fixing partition upto ceiling height consisting of G.I. frame and

required board including providing and fixing of frame work made of special sectionpower pressed/ role form G.I. sheet with zinc coating of grade 175 consisting offloor and ceiling channel 50mm wide having equal flanges of 32mm and 0.5mmthick fixed to the floor and ceiling at the spacing of 610mm centre to centre withdash fastener of 12.5mm dia meter 40mm length and the studs 48mm wide havingone flange of 34mm and other flange 36mm and 0.50mm thick fixed vertically withinflanges of floor and ceiling channel and placed at a spacing of 610mm centre tocentre by 6mm dia bolts and nuts at both ends of partition fixed flush to wall wtihrawl plugs at spacing of 450mm centre to centre and fixing of boards to either sideof frame work by 25mm, drive all screws on studs, floor and ceiling channels at thespacing of 300mm centre to centre, including jointing and finishing to a flush finishwith recommended jointing compound, jointing tape, joint finisher and two coatsof primer suitable for board as per manufacture’s specificatior and direction ofengineer-in-charge all complete,

9.105.2: 75mm overall thickness partition with 12.5mm thick double skin plain Gypsumboard conforming to IS: 2095: part I

CodDescriptio Unit Quantity Rate Amount

Materials for 6.00x3.65 = 21.9 sqm. (PartitionPanel)

###(i) 12.5mm sqm 43.8 130 5694. 00Gypsum board -2x6.00x3.65=43.80sqm.

###(ii) 50mm floor and cei 12 48 576###(iii) 48mm metre 40.15 55 2 208.25

(6.00/0.61)+1 = 11x3.65 = 40.15m###(iv) Screw 100 Nos 392 40 156.8

[(3.65/0.30)+1]x11x2 = 308[(6.00/0.30)+1]x2x2=84 = 392

###(v) Dash f each 22 8 176###(vi) Rawl p each 18 7 126###(vii) Plast kilogram 19.27 2.5 48.18###(viii) Glu kilogram 4.82 50 241###(ix) Paper roll .584 120 70.08

(300/100)x21.90/120 = 0.584 Nos.###(x) Primer litre 7.88 76 598.88###(xi) Galvan 10 Nos 44 9 39.6

25mm Long 11x2x2=44###(xii) G.I. P 100 Nos 44 21 9.24###Sundries caL.S. 52 1 52###Sundries s L.S. 130 1 130

Labour for 21.90 sqm.###Carpernter Day 6.57 151.5 995.36###Carpenter Day 2.847 141.6 403.14###Painter 0. Day 1.095 141.6 155.05###Beldar 0. Day 7.665 135.25 1,036.69

TOTAL ###

Page 400: DAR_Vol_1

Add for water charge @ 1% 127.16TOTAL ###Add for contractor’s profit and overheads @ 1,926.511,500%Cost for 21.90 sqm ###Cost for 1 sqm. 674.43Say 674.45

408### Providing and fixing partition upto ceiling height consisting of G.I. frame and

required board including providing and fixing of frame work made of special sectionpower pressed/ role form G.I. sheet with zinc coating of grade 175 consisting offloor and ceiling channel 50mm wide having equal flanges of 32mm and 0.5mmthick fixed to the floor and ceiling at the spacing of 610mm centre to centre withdash fastener of 12.5mm dia meter 40mm length and the studs 48mm wide havingone flange of 34mm and other flange 36mm and 0.50mm thick “fixed verticallywithin flanges of floor and ceiling channel and placed at a spacing of 610mm centreto centre by 6mm dia bolts and nuts at both ends of partition fixed flush to wallwith rawl plugs at spacingt of 450mm centre to centre and fixing of boards toeither side of frame work by 25mm drive all screws on studs, floor and ceilingchannels at the spacing of 300mm centre to centre, including jointing and finishingto a flush finish with recommended jointing compound, jointing tape, joint finisherand two coats of primer suitable for board as per manufacture’s specificatior anddirection of enginner-in-charge all complete.

9.105.3: 66mm overall thickness Partition with 8mm thick double skin Calcium SilicateBoard made with Calcareous & Siliceous materials reinforced with cellulose fibermanufactured through autoclaving process to give stable crystalline structure.Non Combustible & Spread of Flame (as per BS standard 476 Part IV & VII), Water,Termite & Fungus Resistant, Compressive Strength 225 kg/sq.cm, BendingStrength 100 kg/ sqcm.

CodDescriptio Unit Quantity Rate AmountMaterials for 6.00x3.65 = 21.9 sqm. (PartitionPanel)

###(i) 8 mm th sqm 43.8 194 8 497.20board .

###(ii) 50mm f metre 12 48 576= 12m

###(iii) 48mm metre 40.15 55 2 208.25(6.00/0.61)+1 = 11x3.65= 40.15m

###(iv) Screw 100 Nos 392 40 156.8[(3.65/0.30)+1]x11x2 = 308[(6.00/0.30)+1]x2x2=84 = 392

###(v) Dash f each 22 8 176###(vi) Rawl p each 18 7 126###(vii) Plast kilogram 19.27 2.5 48.18###(viii) Glu kilogram 4.82 50 241###(ix) Paper roll .584 120 70.08

(300/100)x21.90/120 = 0.584 Nos###(x) Primer litre 7.88 76 598.88

Page 401: DAR_Vol_1

###(xi) Galvan 10 Nos 44 9 39.625mm Long 11x2x2=44

###(xii) G.I. P 100 Nos 44 21 9.24###Sundries caL.S. 52 1 52###Sundries s L.S. 130 1 130

Labour for 21.90 sqm.###Carpernter Day 6.57 151.5 995.36###Carpenter Day 2.847 141.6 403.14###Painter 0. Day 1.095 141.6 155.05###Beldar 0. Day 7.665 135.25 1 036.69

TOTAL 15 519.47Add for water charge @ 1% 155.19TOTAL 15 674.66Add for contractor’s profit and overheads @ 2 351.201,500%Cost for 21.90 sqm 18 025.86Cost for 1 sqm. 823.1Say 823.1

4099.1Providing and fixing partition upto ceiling height consisting of G.I. frame and required

board including providing and fixing of frame work made of special section powerpressed/ role form G.I. sheet with zinc coating of grade 175 consisting of floor andceiling channel 50mm wide having equal flanges of 32mm and 0.5mm thick fixed tothe floor and ceiling at the spacing of 610mm centre to centre with dash fastener of12.5mm dia meter 40mm length and the studs 48mm wide having one flange of 34mmand other flange 36mm and 0.50mm thick fixed vertically within flanges of floor andceiling channel and placed at a spacing of 610mm centre to centre by 6mm dia boltsand nuts at both ends of partition fixed flush to wall with rawl plugs at spacing of450mm centre to centre and fixing of boards to either side of frame work by 25mmdrive all screws on studs, floor and ceiling channels at the spacing of 300mm centreto centre, including jointing and finishing to a flush finish with recommended jointingcompound, jointing tape, joint finisher and two coats of primer suitable for board asper manufacture’s specification and direction of Enginner-in-charges all complete

9.105.4: 66mm overall thickness partition using 8mm thick double skin non- asbestosmultipurpose cement board reinforced with cellulose fibre manufactured throughautoclaving process (High pressure steam cured) as per IS: 14862, non combustible,non ignitable ,fire propagation index and surface spread of flame (as per BS 476 partIV, V, VI and VII), moisture, termite & fungus resistant, with suitable fibre cement screw.

CodDescription Unit Quantity Rate AmountMaterials for 6.00x3.65 =21.9 sqm. (PartitionPanel)

###(i) 8 mm thick multipurpose non sqm 43.8 239 10,468.2cement board.

###(ii) 50mm floor and ceiling chann metre 12 48 576=12m

###(iii) 48mm stud-72x34x36x0.5m metre 40.15 55 2,208.25(6.00/0.61)+1 = 11x3.65 = 40.15m

###(iv) Screw 20mm long (drive all s 100 Nos 392 40 156.8[(3.65/0.30)+1]x11x2 = 308

Page 402: DAR_Vol_1

[(6.00/0.30)+1]x2x2=84 = 392###(v) Dash fastner [(6.00/0.61)+1 each 22 8 176###(vi) Rawl plug [(3.65/0.45)+1]x2= each 18 7 126###(vii) Plaster of paris, (88/100)x21 kilogram 19.27 2.5 48.18###(viii) Glue (22/100)x21.90=4.82 kilogram 4.82 50 241###(ix) Paper tape (120m roll) roll .584 120 70.08

(300/100)x21.90/120 = 0.584 No.###(x) Primer (36/100)21.90 = 7.88 l litre 7.88 76 598.88###(xi) Galvanised steel bolts & nu 10 Nos 44 9 39.6

25mm Long 11x2x2=44###(xii) G.I. Plain washer for seam bo100 Nos 44.9 21 9.24###Sundries carriage L.S. 52 1 52###Sundries scaffolding L.S. 130 1 130

Labour for 21.90 sqm.###Carpernter 1st class 0.3x21.90 Day 6.57 151.5 995.36###Carpenter Ilnd class 0.13x21.90 Day 2.847 141.6 403.14###Painter 0.05x21.90 Day 1.095 141.6 155.05###Beldar 0.35x21.90 Day 7.665 135.25 1,036.69

TOTAL 17,490.47Add for water charge @ 1% 174.9TOTAL 17,665.37Add for contractor’s profit and overheads @ 2,649.811,500%Cost for 21.90 sqm 20,315.18Cost for 1 sqm. 927.63Say 927.65

4109.106 : Providing and fixing PTMT handles with necessary screws etc. complete.9.106.1: 125x34x24 mm weighing not less than 23 gms.CodDescription Unit Quantity Rate Amount

Details of cost for tenMaterials-

###PTMT handle 125x34x24mm Each 10 27 270###Mild steel screws 25 mm 100 Nos 40 15 6###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 2nd class Day .06 141.6 8.5

TOTAL 287.23Add for water charge @ 1% 2.87TOTAL 290.1Add for contractor’s profit and overheads @ 43.521,500%Cost of 10 Nos 333.62Cost of 1 No 33.36Say 33.35

9.106 : Providing and fixing PTMT handles with necessary screws etc. complete.9.106.2 :150x34x24 mm weighing not less than 26 gms.CodDescription Unit Quantity Rate Amount

Details of cost for tenMaterials-

###PTMT handle 150x34x24mm Each 10 30 300

Page 403: DAR_Vol_1

###Mild steel screws 25 mm 100 Nos 40 15 6###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 2nd class Day .06 141.6 8.5

TOTAL 317.23Add for water charge @ 1 % 3.17TOTAL 320.4Add for contractor’s profit and overheads @ 48.061,500%Cost of 10 Nos 368.46Cost of 1 No 36.85Say 36.85

### Providing and fixing PTMT Butt hinges with necessary screws etc. complete.9.107.1 75x60x10 mm fitted with 5.5 mm dia M.S.Bright Bar Rod weighing not less than 34 gms.CodDescription Unit Quantity Rate Amount

Details of cost for tenMaterials-

###PTMT butt hinges 75x60x10mm Each 10 36 360###Iron screws 30 mm 100 Nos 60 24 14.4###Carriage of materials L.S. 1.82 1 1.82

Labour-###Carpenter 2nd class Day .14 141.6 19.82###Beldar Day .09 135.25 12.17

TOTAL 408.21Add for water charge @ 1 % 4.08TOTAL 412.29Add for contractor’s profit and overheads @ 61.841,500%Cost of lONos 474.13Cost of 1 No 47.41Say 47.4

411### Providing and fixing PTMT Butt hinges with necessary screws etc. complete.

9.107.2 100x75x10 mm fitted with 5.5 mm dia MSBright Bar Rod weighing not less than 53gms.CodDescription Unit Quantity Rate Amount

Details of cost for tenMaterials-

###PTMT butt hinges 100x75x 10m Each 10 48 480###Iron screws 40 mm 100 Nos 80 30 24###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 2nd class Day .14 141.6 19.82###Beldar Day .09 135.25 12.17

TOTAL 538.72Add for water charge @ 1% 5.39TOTAL 544.11Add for contractor’s profit and overheads 81.621,500%Cost of lONos 625.73Cost of 1 No 62.57Say 62.55

### Providing and fixing PTMT Tower Bolts with 12 mm one piece rod inside and

Page 404: DAR_Vol_1

necessary screws etc., complete.9.108.1 152x42x18 mm weighing not less than 60 gms.CodDescription Unit Quantity Rate Amount

Details of cost for tenMaterials-

###PTMT Tower bolt 152x42x18mm Each 10 60 600###Mild steel screws 30 mm 100 Nos 60 24 14.4###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 2nd class Day .08 141.6 11.33

TOTAL 628.46Add for water charge @ 1 % 6.28TOTAL 634.74Add for contractor’s profit and overheads @ 95.211,500%Cost of lONos 729.95Cost of 1 No 73Say 73

### Providing and fixing PTMT Tower Bolts with 12 mm one piece rod inside andnecessary screws etc., complete.

9.108.2 202x42x18 mm weighing not less than 78 gms.CodDescription Unit Quantity Rate Amount

Details of cost for tenMaterials-

###PTMT Tower bolt 202x42x 18mmEach 10 72 720###Mild steel screws 30 mm 100 Nos 80 24 19.2###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 2nd class Day .1 141.6 14.16

TOTAL 756.09Add for water charge @ 1% 7.56TOTAL 763.65Add for contractor’s profit and overheads @ 114.551,500%Cost of lONos 878.2Cost of 1 No 87.82Say 87.8

4129.109 Providing and fixing PTMT door catcher of length 72 mm and dia. of 42 mm with

suitable washers weighing not less than 33 gms.

CodDescription Unit Quantity Rate AmountDetails of cost for tenMaterials-

###PTMT door catcher 72x42mm Each 10 24 240###Mild steel screws 25 mm 100 Nos 20 15 3###Carriage of materials L.S. 2.73 1 2.73

Labour-###Carpenter 1st class Day .03 151.5 4.54

TOTAL 250.27Add for water charge @ 1% 2.5

Page 405: DAR_Vol_1

TOTAL 252.77Add for contractor’s profit and overheads @ 37.921,500%Cost of 10 Nos 290.69Cost of 1 No 29.07Say 29.05

9.110 Providing and fixing Bamboo jaffery/ fencing consisting of superior quality 25mmdia (Average) half cut bamboo placed vertically and fixed together with three numbershorizontal running members of hollock wood in scantling of section 50X25mm fixedwith nails and G.I wire to existing support complete as per direction of Engineer-in-charge.

CodDescription Unit Quantity Rate AmountDetails of cost for a bamboo jaffery of size1.00m x 2.10m = 2.10 sqmMATERIALS(I) Bamboo 25mm of 100/ 2.50 = 40 nosHalf cut off = 40/2 .=20 nos. x 2.10 = 42.00mAdd wastage @ 15% = 6.30 mTotal = 48.30m

###Bamboo 25 mm dia 2.5 metre lo Metre 48.3 3.84 185.47###Carriage of Bamboo L.S. 4.83 1 4.83

Hollock wood scantling3 nos. (1.00 x 0.05 x 0.025) = 0.00375 cumAdd wastage @ 5% = 0.00019 cumTotal = 0.00394 cum or 3.94 cudm

###Hollock wood in scantling 10 cudm 3.94 217 85.5###Carriage of Timber cum .00394 60.81 .24### Nails and wire L.S. 20.25 1 20.25

LABOUR###Carpenter 2nd class Day .25 141.6 35.4###Beldar Day .25 135.25 33.81###Sundries L.S. 10.05 1 10.05

TOTAL 375.55Add 1 % for water charges. 3.76TOTAL 379.31Add 15% for contractor’s profit and 56.9overheads.Cost for 2.10 sqm 436.21Cost for 1 sqm 207.72Say 207.7

413### Providing and fixing wooden moulded corner beading of triangular shape to the

junction of panelling etc. with iron screws, plugs and priming coat on unexposedsurface etc. complete 2nd class teak wood.

9.111.1 50x50 mm (base and height).

CodDescription Unit Quantity Rate AmountDetails of cost for beading = 5.00 mMATERIALSTeak wood 2nd class in plan ks 5.00x.05x.05/2= 0.00625 cum

Page 406: DAR_Vol_1

Add wastage @10% = 0.00063total = 0.00688 cum say 6.88 cudm

###Second class teak wood in planks10 cudm 6.88 410 282.08###Carriage of Timber cum .00688 60.81 .42###Iron screws 100 Nos 6 30 1.8

Priming coatArea 5.0 x (.05 +.05) = 0.50 sqmRate as per item no 13.50.1 of SH sqm .5 16.55 8.28Labour:-For plaining, fixing & making design

###Carpenter 1st class Day .75 151.5 113.62TOTAL 406.2Add 1% for water charges 3.98TOTAL 410.18Add 15% for contractor’s profit and overhead’s 60.28Cost for 5 metre 470.46Cost for 1 metre 94.09Say 94.1

9.112 Providing and fixing 2nd class teak wood lipping/ moulded beading or Taj beadingof size 18X5mm fixed with wooden adhesive like fevicol etc and screws/ nails on theedges of the prelaminated particle board as per direction of Engineer-in-charge.

CodDescription Unit Quantity Rate AmountDetails of cost for 10.00 mMATERIALS

###2nd class teak wood lipping/ moulded beadibg metre 10 19 190or Taj beading of size 18X5mmLABOUR

###Carpenter 2nd class Day .25 141.6 35.4###Beldar Day .25 135.25 33.81

TOTAL 259.21Add 1 % for water charges 2.59TOTAL 261.8Add 15% for contractor’s profit and overheads 39.27Cost for 10.00m 301.07Cost for 1.00m 30.11Say 30.1

4149.113 Providing and fixing bright finished 100mm mortice lock with 6 levers without pair

of handles for aluminium door with necessary screws etc complete (Best make ofapproved quality) as per direction of Engineer-in-charge.

CodDescription Unit Quantity Rate AmountDetails of cost for 1 no.

###100 mm mostice lock with 6 le each 1 152.5 152.5aluminium door.LABOUR

###Carpenter 1st class Day .13 151.5 19.7###Sundries(screws, carriage etc) L.S. 2.6 1 2.6

TOTAL 174.8Add 1% for water charges 1.75TOTAL 176.55

Page 407: DAR_Vol_1

Add 15% for contractor’s profit and overheads 26.48Cost for 1 no 203.03Say 203.05

### Providing and fixing magnetic catcher in cupboard / ward robe shutters includingfixing with necessary screws etc. complete (Best make of approved quality.

9.114.1 Triple strip vertical type.

CodDescription Unit Quantity Rate AmountDetails of cost for 1 No.MATERIALS

###Magenatic catcher triple strip veeach 1 13.5 13.5###Sundries including screws and fixing charges. L.S. 2.6 1 2.6

TOTAL 16.1Add 1% for water charges .16TOTAL 16.26Add 15% for contractor’s profit and overheads 2.44Cost for 1 No. 18.7Say 18.7

### Providing and fixing magnetic catcher in cupboard / ward robe shutters includingfixing with necessary screws etc. complete (Best make of approved quality.

9.114.2 Double strip (horizontal type).

CodDescription Unit Quantity Rate AmountDetails of cost for 1 No.MATERIALS

###Magenatic catcher double strip heach 1 10 10type.

###Sundries including screws and fixing charges. L.S. 2.6 1 2.6TOTAL 12.6Add 1% for water charges .13TOTAL 12.73Add 15% for contractor’s profit and overheads 1.91Cost for 1 No. 14.64Say 14.65

4159.115 Providing and fixing powder coated telescopic drawer channels 300mm long with

necessary screws etc. complete as per directions of Engineer-in-charge.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sets.MATERIALS

8703 Telescopic drawer chann set 10 92 9209999 Carriage L.S. 19.5 1 19.59999 Sundries including screws L.S. 100.1 1 100.1

TOTAL 1 039.60Add 1 % for water charges 10.4TOTAL 1 050.00Add 15% for contractor’s profit and overheads 157.5Cost for 10 sets 1 207.50Cost for 1 sets 120.75Say 120.75

Page 408: DAR_Vol_1

9.116 Providing and fixing sliding arrangement in racks/ cupboards/cabinets shutter byP/F stainless steel rollers to run inside C or E aluminium channel section (The paymentof C or E channel shall be made separately)

CodDescription Unit Quantity Rate AmountDetails of cost for 1 No.MATERIALS

8704 Stainless steel roller for s each 1 5 5racks/ cupboards/ cabinets shutter.

9999 Labour for fixing L.S. 1.04 1 1.04TOTAL 6.04Add 1% for water charges .06TOTAL 6.1Add 15% for contractor’s profit and overheads .92Cost for I No. 7.02Say 7

### Providing and fixing factory made UPVC door frame made of UPVC extruded, sectionhaving an overall dimension, as below (tolerance +/- 1mm) with wall thickness2.0mm+/- 02mm. corners of the door frame to be jointed with galvanized bracketsand stainless steel screws, joint mitred and plastic wilded. The hinge side verticalof the frames reinforced by galvanized M.S. tube of size 19X19mm and 1 mm +/- 0.1mm wall thickness and 3 nos. stainless steel hinges fixed to the frame complete asper manufacturers specification and direction of Engineer-in-charge

9.117.1 Extruded section Profile size 48x40 mm.CodDescription Unit Quantity Rate Amount

Detail of cost for 5 metreMATERIALS

###48mmX40mmX2mm thick Factorymetre 5 112 560frame of PVC extruded sections in white, greyor wooden finishLABOUR

###Carpenter (average) Day .15 146.55 21.98###Beldar Day .15 135.25 20.29###Sundries L.S. 4.68 1 4.68

TOTAL 606.95Add 1% for water charges 6.07TOTAL 613.02Add 15% for contractor’s profit and overheads 91.95Cost of 5 metre 704.97Cost of 1.00 metre 140.99Say 141

416### Providing and fixing factory made UPVC door frame made of UPVC extruded section

having an overall dimension as. below (tolerance +lmm) with wall thickness 2.0mm+/;0.2mm, corners of the door frame to be jointed with galvanized brackets andstainless steel screws, joint mitred and plastic wilded. The hinge side vertical ofthe frames reinforced by galvanized M.S. tube of size 19 X 19mm and lmm +/-0.1mm wall thickness and 3 nos. stainless steel hinges fixed to the frame completeas per manufacturers specification and direction of Engineer-in-charge

9.117.2 Extruded section Profile size 42x50 mm.

Page 409: DAR_Vol_1

CodDescription Unit Quantity Rate Amount

Detail of cost for 5 metreMATERIALS

###50mmX42mmX 1.5mm thick Facmetre 5 117 585door frame of PVC extruded sections in white,grey or wooden finishLABOUR

###Carpenter (average) Day .15 146.55 21.98###Beldar Day .15 135.25 20.29###Sundries L.S. 4.68 1 4.68

TOTAL 631.95Add 1 % for water charges 6.32TOTAL 638.27Add 15% for contractor’s profit and overheads 95.74Cost of 5 metre 734.01Cost of 1.00 metre 146.8Say 146.8

### Providing and fixing to existing door frames.9.118.1 24 mm thick factory made PVC door shutters made of styles and rails of a UPVC

hollow section of size 59x24 mm and wall thickness 2 mm ± 0.2 mm with inbuiltedging on both sides. The styles and rails mitred and joined at the corners by meansof M.S. galvanised/plastic brackets of size 75x220 mm having wall thickness 1.0mm and stainless steel screws. The styles of the shutter reinforced by insertinggalvanised M.S. tube of size 20x20 mm and 1 mm ± 0.1 mm wall thickness. The lockrail made up of’H’ section, a UPVC hollow section of size 100x24 mm and 2 mm ±0.2 mm wall thickness fixed to the shutter styles by means of plastic/galvanisedM.S. ‘U’ cleats. The shutter frame filled with a UPVC multi-chambered single panelof size not less than 620 mm, having over all thickness of 20 mm and 1 mm ± 0.1 mmwall thickness . The panels filled vertically and tie bar at two places by insertinghorizontally 6 mm galvanised M.S. rod and fastened with nuts and washers, completeas per manufacturer’s specification and direction of Engineer-in-charge. (For W.C.and bathroom door shutter).

CodDescription Unit Quantity Rate AmountDetail of cost for 2.38 sqmone door shutter 2.20x1.08m = 2.38 sqmMATERIALS

###24 mm thick Factory made shutt sqm 2.38 1 830.00 4,355.4frame, rails and panels of PVC extrudedsections in white, grey or wooden finish i/ccarriageLABOUR

###Carpenter (average) Day .4 146.55 58.62

417CodDescription Unit Quantity Rate Amount

###Beldar Day .4 135.25 54.1###Sundries L.S. 20.36 1 20.36

TOTAL 4,488.48Add 1 % for water charges 44.88

Page 410: DAR_Vol_1

TOTAL 4,533.36Add 15% for contractor’s profit and overheads 680Cost of 2.38 sqm 5,213.36Cost of 1.00 sqm 2,190.49Say 2,190.5

9.118 Providing and fixing to existing door frames.9.118.2 30mm thick factory made Polyvinyl Chloride (PVC) door shutter made of styles

and rails of a UPVC profile section of size 30mm x 60mm and wall thickness 2mm±0.2mm with inbuilt decorative moulding edging on one side. The styles and railswith plastic brackets of size 75x220mm mitre and welded at the corners. The- stilesof the shutter reinforced by inserting galvanized M.S. tube of size 25x20mm and1mm ± 0.1mm wall thickness. The lock rail made up of ‘H’ section, a UPVC profilesection of size 30mm x 100mm and 2mm±0.2mm wall thickness welded to theshutter style with a UPVC profile section single panel of size not less than 620mm,having overall thickness of 20 mm and 1 mm±0.1 mm wall thickness with 20 mmpanel beading of suitable size /Glass(4mm thick plain glass)/louver section, louverframe of suitable size, as per manufactures specification and direction of Engineer-in-charge. (For W.C. and bathroom door Shutter)

CodDescription Unit Quantity Rate AmountDetail of cost for 2.38 sqm.one door shutter 2.20x1.08m = 2.38 sqmMATERIALS

###30 mm thick Factory made shutt sqm 2.38 1 900.00 4 522.00frame, rails and panels of PVC extrudedsections in white, grey or wooden finishLABOUR

###Carpenter (average) Day .4 146.55 58.62###Beldar Day .4 135.25 54.1###Sundries L.S. 20.36 1 20.36

Total 4 655.08Add 1% for water charges 46.55TOTAL 4 701.63Add 15% for contractor’s profit and 705.24overheads.Cost of 2.38 sqm 5 406.87Cost of 1.00 sqm 2 271.79Say 2 271.80

### Providing and fixing to existing door frames.9.118.3 25mm thick PVC flush door shutters upto 737mm width of colour and shade as

approved by Engineer-in-charge made out of a one piece Multi chamber extrudedPVC section of the size of 762mm X 25mm or less as per requirement with anaverage wall thickness of 1mm ± 0.3mm. PVC foam end cap of size 23x10mm areprovided on both vertical edges to ensure the overall thickness of 25mm. An MStube having dimensions 19mm x 19mm is inserted along the hinge side of thedoor. Core of the door shutter should be filled with High Density Polyurethane

418foam. The Top & Bottom edges of the shutter are covered with an end-cap of thesize 25mm X 11mm. Door shutter shall be reinforced with special polymeric

Page 411: DAR_Vol_1

reinforcements as per manufactures’ specification and drawing to take upnecessary hardware and fixtures. Stickers indicating the locations of hardwarewill be pasted at appropriate places

CodDescription Unit Quantity Rate AmountDetail of cost for 2.38 sqmone door shutter 2.20x1.08m = 2.38 sqmMATERIALS

###25mm thick factory made PVC flsqm 2.38 1 975.00 4 700.50shutter.LABOUR

###Carpenter (average) Day .4 146.55 58.62###Beldar Day .4 135.25 54.1###Sundries L.S. 20.36 1 20.36

TOTAL 4,833.58Add 1% for water charges 48.34TOTAL 4,881.92Add 15% for contractor’s profit and overheads 732.29Cost of 2.38 sqm 5,614.21Cost of 1.00 sqm 2,358.91Say 2,358.9

### Providing and fixing factory made P.V.C. door frame of size 50x47mm with a wallthickness of 5mm, made out of extruded 5mm rigid PVC foam sheet mitred at cornersand joined with 2 Nos. of 150mm long brackets of 15x15mm M.S. square tube, thevertical door profiles to be reinforced with 19x19mm M.S. square tube of 19 gauge,EPDM rubber gasket weather seal to be provided through out the frame. The doorframe to be fixed to the wall using M.S. screws of 65/100mm size complete as permanufacturers specification and direction of Engineer-in-Charge.

CodDescription Unit Quantity Rate AmountDetails of cost for one door frame of 5 metreMaterials-

###Factory made door frame PVC extruded sheet metre 5 294 1,470i/c carriageLabour-

###Carpenter (average) Day .15 146.55 21.98###Beldar Day .15 135.25 20.29###Sundries L.S. 7.8 1 7.8

TOTAL 1,520.07Add for water charge @ 1 % 15.2TOTAL 1,535.27Add for contractor’s profit and overheads @ 230.291,500%Cost of 5 metres 1,765.56Cost of 1 metre 353.11Say 353.1

### Providing and fixing to existing door frames.9.120.1 30mm thick factory made solid panel PVC door shutter consisting of frame made

out of M.S. tubes of 19 gauge thickness and size of 19mm x 19mm for stiles, top &bottom rails. M.S .frame shall have a coat of steel primers of approved make andmanufacture M.S. frame covered with 5mm thick heat moulded PVC ‘C channel of

Page 412: DAR_Vol_1

419size 30mm thickness, 110mm width out of which 90mm shall be flat and 20mmshall be tapered in 45 degree angle on either side forming stiles; and 5mm thick,110mm wide PVC sheet out of which 90mm shall be flat and 20mm shall be taperedon the inner side to form top and bottom rail and 130mm wide PVC sheet out ofwhich 90mm shall be flat and 20mm shall be tapered on both sides to form lock rail.Top bottom and lock rails shall be provided either side of the panel. 10mm (5mm x2) thick, 20mm wide cross PVC sheet shall be provided as gap insert for top rail &bottom rail. Panelling of 5mm thick PVC sheet to be fitted in the M.S. frame welded/sealed to the stiles & rails with 7mm (5mm +2mm) thick x 15mm wide PVC sheetbending on inner side, and joined together with solvent cement adhesive. Anadditional 5mm thick PVC strip of 20mm width is to be stuck on the interior side ofthe ‘C Channel using PVC solvent adhesive etc. complete as per direction ofEngineer-in-charge, manufacture’s specification & drawing.

CodDescriptio Unit Quantity Rate Amount

Details of cost of one shutter 2.20x1.08m= 2.38 sqmMaterials-

###Factory madsqm 2.38 1,743 ######Powder coa10 Nos 4 66 26.4

X 58mm X 1.9mm###M.S. scre 100 Nos 48 30 14.4###M.S. scre 100 Nos 8 15 1.2

Labour-###Carpenter Day .4 146.55 58.62###Beldar Day .4 135.25 54.1###Sundries L.S. 20.36 1 20.36

TOTAL ###Add for water charge @ 1% 43.23TOTAL ###Add for contractor’s profit and overheads @ 6551,500%Cost of 2.38 sqm ###Cost per sqm ###Say ###

### Providing and fixing to existing door frames.9.120.2 30mm thick factory made solid both side prelam panel PVC door shutter consisting

of frame made out of M.S. tubes of 19 gauge thickness and size of 19mm x 19mmfor stiles, top & bottom rails. M.S. frame shall have a coat of steel primers of approvedmake and manufacture . M.S. frame covered with 5mm thick heat moulded prelamPVC ‘C channel of size 30mm thickness, 70mm width out of which 50mm shall beflat and 20mm shall be tapered in 45degree angle on either side forming stiles; and5mm thick, 95mm wide PVC sheet out of which 75mm shall be flat and 20mm shallbe tapered in 45 degree on the inner side to form top and bottom rail and 115mmwide PVC sheet out of which 75mm shall be flat and 20mm shall be tapered onboth sides to form lock rail. Top, button and lock rails shall be provided either sideof the panel. 10mm (5mm x 2 ) thick, 20mm wide cross PVC sheet be provided asgap insert for top rail & bottom rail, panelling of 5mm thick both side Prelam PVCsheet to be fitted in the M.S. frame welded/ sealed to the stiles & rails with 7mm(5mm+2mm) thick x 15mm wide PVC sheet beading on inner side, and joinedtogether with solvent cement adhesive. An additional 5mm thick PVC strip of 20mmwidth is to be stuck on the interior side of the ‘C Channel using PVC solvent adhesive

Page 413: DAR_Vol_1

etc. complete as per direction of Engineer-in-charge. manufacturer’s specification& drawing.

420CodDescription Unit Quantity Rate Amount

Details of cost of one shutter 2.20x1.08m= 2.38 sqmMaterials-

###Factory made PVC shutter i/c car sqm 2.38 2,148 5,112.24###Powder coated M.S. butt hinge 10 Nos 4 66 26.4

X58mmX1.9mm###M.S. screws 40mm 100 Nos 48 30 14.4###M.S. screws 20mm 100 Nos 8 15 1.2

Labour-###Carpenter (average) Day .4 146.55 58.62###Beldar Day .4 135.25 54.1###Sundries L.S. 20.36 1 20.36

TOTAL 5 287.32Add for water charge @ 1 % 52.87TOTAL 5 340.19Add for contractor’s profit and overheads @ 801.031,500%Cost of 2.38 sqm 6,141.22Cost per sqm 2,580.34Say 2,580.35

### Providing and fixing Fiber Glass Reinforced plastic (FRP) Door Frames of cross-section 90mm x 45mm having single rebate of 32mm x 15mm to receive shutter of30mm thickness .The laminate shall be molded with fire resistant grade unsaturatedpolyester resin and chopped mat .Doorframe laminate shall be 2mm thick and shallbe filled with suitable wooden block in all the three legs. The frame shall be coveredwith fibreglass from all sides. MS stay shall be provided at the bottom to steady theframe.

CodDescription Unit Quantity Rate AmountDetails of cost for one door frame of 5 metreMaterials-

8707 Factory made glass reinfor metre 5 333 1,665frame 90x45 mm i/c carriage.Labour-

###Carpenter (average) Day .15 146.55 21.98###Beldar Day .15 135.25 20.29###Sundries L.S. 7.8 1 7.8

TOTAL 1,715.07Add for water charge @ 1% 17.15TOTAL 1,732.22Add for contractor’s profit and overheads @ 259.831,500%Cost of 5 metres 1,992.05Cost of 1 metre 398.41Say 398.4

### Providing and fixing to existing door frames.9.122.1 30 mm thick Glass Fibre Reinforced Plastic (FRP) panelled door shutter of required

Page 414: DAR_Vol_1

colour and approved brand and manufacture, made with fire - retardant gradeunsaturated polyester resin, moulded to 3 mm thick FRP laminate for forming hollowrails and styles, with wooden frame and suitable blocks of seasoned wood inside at

421required places for fixing of fittings, cast monolithically with 5mm thick FRP laminatefor panels confirming to TADS 6: 1993 and / or IS: 14856 - 2000 including fixing toframes.

CodDescription Unit Quantity Rate AmountDetails of cost of one shutter 2.20x1.08m= 2.38sqmMaterials-

###30 mm thick factory made glass sqm 2.38 1,580 3,760.4reinforced plastic panel door shutter i/ccarriage.

###Powder coated M.S. butt hinge 10 Nos 4 66 26.4X58mmX1.9mm

###M.S. screws 40mm 100 Nos 48 30 14.4###M.S. screws 20mm 100 Nos 8 15 1.2

Labour-###Carpenter (average) Day .4 146.55 58.62###Beldar Day .4 135.25 54.1###Sundries L.S. 20.36 1 20.36

TOTAL 3,935.48Add for water charge @ 1% 39.35TOTAL 3,974.83Add for contractor’s profit and overheads @ 596.221,500%Cost of 2.38 sqm 4,571.05Cost per sqm 1,920.61Say 1,920.6

### Providing and fixing to existing door frames.9.122.2 30mm thick fibreglass reinforced plastice (F.R.P.) flush door shutter in different

plain and wood finish made with fire retardant grade unsaturated polyster resin,moulded to 3mm thick FRP laminate all around, with suitable wooden blocks insideat required places for fixing of fittings and polyurethane foam (PUF) / Polystyrenefoam to be used as filler material throughout the hollow panel, casted monolithicallywith testing parameters of F.R.P. laminate conforming to table - 3 of IS: 14856 : 2000,complete as per direction of Engineer-in-charge.

CodDescription Unit Quantity Rate AmountDetails of cost of one shutter 2.20x1.08m= 2.38 sqmMaterials-

###30 mm thick factory made glass sqm 2.38 1,960 4,664.8reinforced plastic flush door shutter i/ccarriage.

###Powder coated M.S. butt hinge 10 Nos 4 66 26.4X58mmX 1.9mm

###M.S. screws 40mm 100 Nos 48 30 14.4###M.S. screws 20mm 100 Nos 8 15 1.2

Page 415: DAR_Vol_1

Labour-###Carpenter (average) Day .4 146.55 58.62###Beldar Day .4 135.25 54.1###Sundries L.S. 20.36 1 20.36

TOTAL 4,839.88Add for water charge @ 1 % 48.4TOTAL 4,888.28

422CodDescription Unit Quantity Rate Amount

Add for contractor’s profit and overheads @ 733.241,500%Cost of 2.38 sqm 5 621.52Cost per sqm 2 361.98Say 2 362.00

9.123 Providing and fixing factory made door frame (single rebate) made of solid PVCfoam profile with homogenous fine cellular structure having smooth outer integralskin having 60mm width & 30mm thickness and shall be fixed to wall as perinstructions of engineer-in-charge using 100x8 sheet metal CSK screws.

CodDescription Unit Quantity Rate Amount

Details of cost for one door frame of 5 metreMaterials-

###Factory made solid PVC door fr metre 5 223 1,115i/c carriage.Labour-

###Carpenter (average) Day .15 146.55 21.98###Beldar Day .15 135.25 20.29###Sundries L.S. 7.8 1 7.8

TOTAL 1,165.07Add for water charge @ 1 % 11.65TOTAL 1,176.72Add for contractor’s profit and overheads @ 176.511,500%Cost of 5 metres 1,353.23Cost of 1 metre 270.65Say 270.65

9.124 Providing and fixing 28 mm thick door shutter made of solid PVC foam profile withhomogenous fine cellular structure having smooth outer integral skin having 71mmwidth & 28mm thick as vertical & horizontal styles. Joints are made using solventadhesive and GI ‘C sections (39mm x 19mm x 0.6mm thick) or M S pipe (40mm x20mm ) stiffener frame insert & telescopic polymeric ‘L’ corners .The panel shall befilled with 3mm thick high - pressure compact laminate as per manufacturer’sspecifications and directions of the Engineer-in-charge, cover moulding shall beprovided for covering fixing screws and elegant look.( for W.C. bathroom doorshutter).

CodDescription Unit Quantity Rate AmountDetails of cost of one shutter 2.20x1.08m= 2.38 sqmMaterials-

Page 416: DAR_Vol_1

###28mm factory made solid PVC pasqm 2.38 1 975.00 4,700.5shutter i/c carriage.

###Powder coated M.S. butt hinge 10 Nos 4 66 26.4X58mmX 1.9mm

###M.S. screws 40mm 100 Nos 48 30 14.4###M.S. screws 20mm 100 Nos 8 15 1.2

Labour-###Carpenter (average) Day .4 146.55 58.62###Beldar Day .4 135.25 54.1###Sundries L.S. 20.36 1 20.36

423CodDescription Unit Quantity Rate Amount

TOTAL 4,875.58Add for water charge @ 1 % 48.76TOTAL 4,924.34Add for contractor’s profit and overheads @ 738.651,500%Cost of 2.38 sqm 5,662.99Cost per sqm 2,379.41Say 2,379.4

9.125 Providing and fixing PVC rigid foam sheet 1mm thick on existing door shutters(bathroom and W.C. doors) using synthetic rubber based adhesive.

CodDescription Unit Quantity Rate AmountDetails of cost for 1.0x0.3m = 0.3 sqmMaterials-

###PVC rigid foam sheet1mm thick = 0.30 sqmAdd wastage @ 10% = 0.03 sqmTotal = 0.33 sqm sqm .33 145 47.85

###Rubber adhesive L.S. 21.84 1 21.84Labour-

###Carpenter 1 st class Day .11 151.5 16.66###Beldar Day .14 135.25 18.94###Mistry Day .02 151.5 3.03

TOTAL 108.32Add for water charge @ 1 % 1.08TOTAL 109.4Add for contractor’s profit and overheads @ 16.411,500%Cost of 0.30 sqm 125.81Cost per sqm 419.37Say 419.35

### Providing and fixing 12mm thick panelling or panelling and glazing in panelled orpanelled and glazed shutters for doors, windows and clerestory windows (area ofopening for panel inserts excluding portion inside grooves or rebates to bemeasured). Panelling for panelled or panelled and glazed shutters 25mm to 40mmthick.

9.126.1 Marine plywood conforming to IS: 710CodDescription Unit Quantity Rate Amount

Details of cost for shutters of a door with2/3rd panelling...200x 108cm = 2.16sqm.

Page 417: DAR_Vol_1

Panel area = 4x45.1x36.55cm = 0.67sqm.Materials:Plywood 4x47.2x38.65cm = 0.73sqm+Add for wastage @ 10% = 0.07sqm.Total = 0.80 sqm.

8724 12mm thick marine plywo sqm .8 740 592IS:710

9999 Carriage of Plywood L.S. 1.82 1 1.82Labour:

0111 Carpenter 1 st class Day .57 151.5 86.359999 Sundries L.S. 4.42 1 4.42

TOTAL 684.59

424CodDescription Unit Quantity Rate Amount

Add 1% for water charges 6.85TOTAL 691.44Add 15% for contractor’s profit and overheads 103.72Cost of 0.67 sqm. 795.16Cost of 1 sqm. 1 186.81Say 1 186.80

### Providing and fixing 12mm thick panelling or panelling and glazing in panelled orpanelled and glazed shutters for doors, windows and clerestory windows (area ofopening for panel inserts excluding portion inside grooves or rebates to bemeasured). Panelling for panelled or panelled and glazed shutters 25mm to 40mmthick.

9.126.2 Fire retardant plywood conforming to IS: 5509.

CodDescription Unit Quantity Rate AmountDetails of cost for shutters of a door with2/3rd panelling.. .200x 108cm = 2.16sqm.Panel area = 4x45.1x36.55cm = 0.67sqm.Materials:Plywood 4x47.2x38.65cm = 0.73sqm+Add for wastage @ 10% = 0.07sqm.Total = 0.80 sqm.

###12mm thick fire retardant plywo sqm .8 690 552conforming to IS: 5509.

###Carriage of Plywood L.S. 1.82 1 1.82Labour:

###Carpenter 1 st class Day .57 151.5 86.35###Sundries L.S. 4.42 1 4.42

TOTAL 644.59Add 1 % for water charges 6.45TOTAL 651.04Add 15% for contractor’s profit and overheads 97.66Cost of 0.67 sqm. 748.7Cost of 1 sqm. 1,117.46Say 1,117.45

### Providing & Fixing decorative high pressure laminated sheet of plain / wood grainin gloss / matt / suede finish with high density protective surface layer and reverseside of adhesive bonding quality conforming to IS : 2046 Type S including cost of

Page 418: DAR_Vol_1

adhesive of aproved quality9.127.1 1.5 mm thick.CodDescription Unit Quantity Rate Amount

Details of cost for 5.00 sqmMATERIALSDecorative laminate = 5.00 sqmAdd wastage @ 10% = 0.50 sqmTotal = 5.50 sqm

###1.5mm thick decorative laminat sqm 5.5 405 2,227.5###Adhesive L.S. 195 1 195

LABOUR:-###Carpenter 1 st class Day .5 151.5 75.75###Beldar Day .5 135.25 67.62###Sundries i/c nails etc. L.S. 52 1 52

425CodDescriptio Unit Quantity Rate Amount

TOTAL 2,617.87Add for water charges @ 1% 26.18TOTAL 2,644.05Add for contractors profit and overheads @ 396.611,500%Cost for 5.00 sqm 3,040.66Cost for 1 sqm 608.13Say 608.15

9.127 Providing & Fixing decorative high pressure laminated sheet of plain / wood grainin gloss / matt / suede finish with high density protective surface layer and reverseside of adhesive bonding quality conforming to IS : 2046 Type S including cost ofadhesive of aproved quality

9.127.2 1.0 mm thick.

CodDescriptio Unit Quantity Rate AmountDetails of cost for 5.00 sqmMATERIALSDecorative laminate = 5.00 sqmAdd wastage @ 10% = 0.50 sqmTotal = 5.50 sqm

###1.0mm thicsqm 5.5 330 1,815###Adhesive L.S. 195 1 195

LABOUR:-###Carpenter 1Day .5 151.5 75.75###Beldar Day .5 135.25 67.629999 SundrL.S. 52 1 52

TOTAL 2,205.37Add for water charges @ 1 % 22.05TOTAL 2,227.42Add for contractors profit and overheads @ 334.111,500%Cost for 5.00 sqm 2,561.53Cost for 1 sqm 512.31Say 512.3

### Providing and fixing factory made Fibreglass Reinforced plastics (F.R.P.) chajja

Page 419: DAR_Vol_1

4mm thick of required colour, size and design made by Resin Transfer Moulding(RTM) Machine Technology, resulting in void free compact laminate in single piece,having smooth gradual slope curvature for easy drainage of water and dulyreinforced by 50x2mm thick M.S. flat with 12mm in built hole for grouting on theexisting wall along with the flanges duly inserted and sealed in the wall completein one single piece casted monolithically, including all necessary fittings . The FRPChajja should be manufactured using unsaturated Polyester resin as per IS: 11551complete with protective Gelcoat U/V coating on Top for complete resistance fromthe extreme of temperature, weather & sunlight,

CodDescriptio Unit Quantity Rate AmountDetail of cost for a chajja 0.90 x 0.60 = 0.54sqmMATERIALS

###Fiber glass .54 3 520.00 1 900.80accessories.

426CodDescription Unit Quantity Rate Amount###Carriage L.S. 26 1 26###fixing charges including sundries L.S. 143 1 143

TOTAL 2 069.80Add 1% for water charges 20.7Total 2 090.50Add 15% for contractor’s profit and overheads 313.58Cost for 0.54 sqm 2 404.08Cost for 1 sqm 4 452.00Say 4 452.00

### Providing and fixing cup board shutters 25mm thick, with prelaminated flat pressedthree layer particle board or graded wood particle board IS: 12823 marked exteriorgrade (Grade 1 Type II) having one side decorative lamination and other sidebalancing lamination including Ilnd class teak wood lipping of 25mm wide xl2 mmthick with necessary screws and bright finished stainless steel piano hingescomplete as per direction of the Engineer-in-Charge

CodDescription Unit Quantity Rate AmountDetails of cost for one shutter 2.20x1.00m =2.20sqm.Materials

###25 mm thick cup board shutter sqm 2.2 708 1,557.6###Carriage L.S. 29.64 1 29.64###lmm thick 35mm wide bright fin metre 4.4 30 132

stainless steel piano hinges .###Screws 25 mm long 100 Nos 125 16 20

Labour###Carpenter 1 st class Day .5 151.5 75.75###Beldar Day .5 135.25 67.62###Mistry Day .07 151.5 10.6###Add for wooden lipping 25 mm metre 7 28 196

thickTOTAL 2,089.21Add 1 % for water charges 20.89

sqm

Page 420: DAR_Vol_1

TOTAL 2,110.1Add 15% for contractor’s profit and overheads 316.52Cost for2.20sqm. 2,426.62Cost per sqm. 1,103.01Say 1,103

### Providing and fixing cup board shutters with 25mm thick veneered particle boardIS : 3097 marked exterior grade (Grade I) of approved make including Ilnd classteak wood lipping of 25mm wide x 12 mm thick with necessary screws and brightfinished stainless steel piano hinges complete as per direction of Engineer-in-Charge.

9.130.1 With decorative veneering on one side and commercial veering on other side.CodDescription Unit Quantity Rate Amount

Details of cost for one shutter 2.20x1.00m =2.20sqm.Materials

###25 mm thick cup board shutter sqm 2.2 390 858###Extra for teak veneering on one sqm 2.2 198 435.6

commercial veneereing on other side

427CodDescription Unit Quantity Rate Amount###Carriage L.S. 29.64 1 29.64###lmm thick 35mm wide bright fin metre 4.4 30 132

stainless steel piano hinges.###Screws 25 mm long 100 Nos 125 16 20

Labour###Carpenter 1st class Day .5 151.5 75.75###Beldar Day .5 135.25 67.62###Mistry Day .07 151.5 10.6###Add for wooden lipping 25 mm metre 7 28 196

thickTOTAL 1,825.21Add 1 % for water charges 18.25TOTAL 1,843.46Add 15% for contractor’s profit and overheads 276.52Cost for 2.20sqm. 2,119.98Cost per sqm. 963.63Say 963.65

### Providing and fixing cup board shutters with 25mm thick veneered particle boardIS : 3097 marked exterior grade (Grade I) of approved make including Ilnd classteak wood lipping of 25mm wide x 12 mm thick with necessary screws and brightfinished stainless steel piano hinges complete as per direction of Engineer-in-Charge.

9.130.2 With non decorative veneering on both sides.CodDescription Unit Quantity Rate Amount

Details of cost for one shutter 2.20x1.00m =2.20sqm.Materials

###25 mm thick particle board sqm 2.2 390 858###Extra for commercial veneering osqm 2.2 102 224.4###Carriage L.S. 29.64 1 29.64

Page 421: DAR_Vol_1

###1mm thick 35mm wide bright finmetre 4.4 30 132stainless steel piano hinges.

###Screws 25 mm long 100 Nos 125 16 20Labour

###Carpenter 1 st class Day .5 151.5 75.75###Beldar Day .5 135.25 67.62###Mistry Day .07 151.5 10.6###Add for wooden lipping 25 mm metre 7 28 196

thickTOTAL 1 614.01Add 1% for water charges 16.14TOTAL 1 630.15Add 15% for contractor’s profit and overheads 244.52Cost for 2.20sqm. 1 874.67Cost per sqm. 852.12Say 852.1

### Providing and fixing factory made prelaminated particle board flat pressed threelayer or graded wood particle board with one side decorative finish and other sidebalancing lamination conforming to IS: 12823 Grade 1 Type II, of approved design,and edges sealed with water resistant paint and lipped with aluminium ‘U’ typeedge beading alround the shutter, including fixing with angle cleat, grip strip,

428cadmium plated steel screws including fixing of aluminium hinges 100x63x4 mmetc. complete as per architectural drawing and direction of Engineer-in-Charge (Costof’U’ beading and hinges will be paid for separately).

9.131.1 25 mm thick.

CodDescription Unit Quantity Rate AmountDetails of cost for 2.10 sqm.(Door size 2.1x1.00 = 2.10 sqm.)MaterialsPrelaminated particle board = 2.10sqm. +Add for wastage @ 5% = 0.11 sqm.= 2.21sqm.

###Prelaminated particle board sqm 2.21 650 1,436.5###Aluminium single cleat of size 3 each 4 10 40###Aluminium grip strip of size 50x each 8 7 56###Edge sealing water resistant pai litre .15 120 18###Carriage of materials including l L.S. 19.5 1 19.5

unloading9999 Sundries and screws etc. L.S. 39 1 39

Labour0112 Carpenter 2nd class Day .27 141.6 38.23###Beldar Day .3 135.25 40.57

TOTAL 1,687.8Add 1 % for water charges 16.88TOTAL 1,704.68Add 15% for contractor’s profit and overheads 255.7Cost for 2.1 Osqm. 1,960.38Cost per sqm. 933.52Say 933.5

Page 422: DAR_Vol_1

9.132 Providing and fixing aluminum U beading of required size to prelaminated /flushdoor shutter including fixing etc. complete as per direction of Engineer-in-charge.

CodDescription Unit Quantity Rate AmountDetails of cost for 1 kg.MaterialAluminum U beading = 1.00kg +Add 10% wastage = 0.10= 1.10kg.

###Aluminium ‘U’ Beading kilogram 1.1 195 214.5###Anodized 15 micron L.S. 65 1 65###Sundries including screws, fixing, carriage etc. L.S. 13 1 13

TOTAL 292.5Add 1 % for water charges 2.92TOTAL 295.42Add 15% for contractor’s profit and overheads 44.31Cost per kg. 339.73Say 339.75

### Providing and fixing, in position concealed G.I. section for wall panelling usingboard of required thickness fixed on the ‘W profile (0.55mm thick ) having a knurledweb of 51.55mm and two flanges of 26mm each with lips of 10.55 mm placed @610mm C/C in perimeter channel having one flange of 20mm and another flange of30mm with thickness of 0.55mm and web of length 27mm. Perimeter channel isfixed on the floor and the ceiling with the nylon sleeves @ 610mm C/C with fully

429threaded self-tapping drive all screws. Board is fixed to the ‘Wprofile with 25 mmcountersunk ribbed head screws @ 200mm C/C, all complete as per the drawing &directions of engineer-in-charge the joints of the boards are finished with speciallyformulated jointing compound and 48mm wide fiber tape to provide seamless finish.

9.133.1 Tapered edge calcium silicate board made with calcareous & siliceous materialsreinforced with cellulose fiber manufactured through autoclaving process to givestable crystalline structure, Non combustible & spread of Flame (as per BS standard476 Part IV & VII), Water, Termite & Fungus resistant, compressive strength 225 kg/sq.cm, Bending strength 100 kg/sq.cm.

9.133.1.1 10mm thick.CodDescription Unit Quantity Rate Amount

Details of cost for 3.66 mx 3.05 m =11.16sqm.MATERIALSCalcium silicate board 10mm thick.= 11.16sqmAdd wastage @ 10% = 1.12 sqm.Total = 12.28 sqm

###10 mm thick calcium silicate boasqm 12.28 323 3 966.44###Ceiling sections. metre 19.66 34 668.44###Perimeter channel metre 9.6 20 192###Nylon sleeves & wooden screws each 42 1.5 63###Counter sunk ribbed head screw cent 1.76 60 105.6###Jointing compound L.S. 20.8 1 20.8

Page 423: DAR_Vol_1

###Joint tape roll roll .19 120 22.8###Sundries i/c rawl plug, scaffoldi L.S. 52 1 52###Carriage of materials L.S. 26 1 26

LABOUR:-###Carpenter 1st class Day 3.8 151.5 575.7###Beldar Day 4.6 135.25 622.15

TOTAL 6 314.93Add for water charges @ 1% 63.15TOTAL 6 378.08Add for contractors profit and overheads @ 956.711,500%Cost for 11.16 sqm 7 334.79Cost for 1 sqm 657.24Say 657.25

### Providing and fixing, in position concealed G.I. section for wall panelling usingboard of required thickness fixed on the ‘W profile (0.55mm thick ) having a knurledweb of 51.55mm and two flanges of 26mm each with lips of 10.55 mm placed @610mm C/C in perimeter channel having one flange of 20mm and another flangeof 30mm with thickness of 0.55mm and web of length 27mm. Perimeter channel isfixed on the floor and the ceiling with the nylon sleeves @ 610mm C/C with fullythreaded self-tapping drive all screws. Board is fixed to the ‘W^rofile with 25 mmcountersunk ribbed head screws @ 200mm C/C, all complete as per the drawing& directions of engineer-in-charge the joints of the boards are finished withspecially formulated jointing compound and 48mm wide fiber tape to provideseamless finish.

9.133.2 Non -asbestos multipupose cement board reinforced with cellulose fibremanufactured through autoclaving process (high pressure steam cured) as per IS14862 non combustible , non ignitable, fire propagation index and surface spread

430of flame (as per BS 476 part IV, V, VI, and VII) moisture , termite & fungus resistantwith suitable fibre cement screw.

9.133.2.1 8 mm thick.

CodDescription Unit Quantity Rate AmountDetails of cost for 3.66 m x 3.05 m =11.16sqm.MATERIALSMultipurpose non asbestos fibre cement board8mm thick.= 11.16 sqmAdd wastage @ 10% =1.12 sqm.Total = 12.28 sqm

###8 mm thick multipurpose non asbsqm 12.28 239 2,934.92cement board.

###Ceiling sections. metre 19.66 34 668.44###Perimeter channel metre 9.6 20 192###Nylon sleeves & wooden screws each 42 1.5 63###Counter sunk ribbed head screw cent 1.76 60 105.6###Jointing compound L.S. 20.8 1 20.8###Joint tape roll roll .19 120 22.8

Page 424: DAR_Vol_1

###Sundries i/c rawl plug, scaffolfingL.S. 52 1 52###Carriage of materials L.S. 26 1 26

LABOUR:-###Carpenter 1st class Day 3.8 151.5 575.7###Beldar Day 4.6 135.25 622.15

TOTAL 5,283.41Add for water charges @ 1 % 52.83TOTAL 5,336.24Add for contractors profit and overheads @ 800.441,500%Cost for 11.16 sqm 6,136.68Cost for 1 sqm 549.88Say 549.9

### Providing and fixing, in position concealed G.I. section for wall panelling usingboard of required thickness fixed on the ‘W profile (0.55mm thick ) having a knurledweb of 51.55mm and two flanges of 26mm each with lips of 10.55 mm placed @610mm C/C in perimeter channel having one flange of 20mm and another flangeof 30mm with thickness of 0.55mm and web of length 27mm. Perimeter channel isfixed on the floor and the ceiling with the nylon sleeves @ 610mm C/C with fullythreaded self-tapping drive allscrews. Board is fixed to the ‘W’profile with 25 mmcountersunk ribbed head screws @ 200mm C/C, all complete as per the drawing& directions of engineer-in-charge the joints of the boards are finished withspecially formulated jointing compound and 48mm wide fiber tape to provideseamless finish.

9.133.3 Gypsum board conforming to IS: 2095- 1996: Part - I .9.133.3.1 12.5 mm thick.CodDescription Unit Quantity Rate Amount

Details of cost for 3.66 m x 3.66 m - 11.16sqm.MATERIALSGlass fibre reinforced gypsum board 12.5 mmthick.= 11.16 sqmAdd wastage @ 10% = 1.12 sqm.

431CodDescription Unit Quantity Rate Amount

Total = 12.28 sqm###12.5 mm thick Glass fibre reinf sqm 12.28 130 1,596.4

board.###Ceiling sections. metre 19.66 34 668.44###Perimeter channel metre 9.6 20 192###Nylon sleeves & wooden screws each 42 1.5 63###Counter sunk ribbed head screw cent 1.76 60 105.6###Jointing compound L.S. 20.8 1 20.8###Joint tape roll roll .19 120 22.8###Sundries i/c rawl plug, scaffolfingL.S. 52 1 52###Carriage of materials L.S. 26 1 26

LABOUR:-###Carpenter 1st class Day 3.8 151.5 575.7###Beldar Day 4.6 135.25 622.15

TOTAL 3,944.89

Page 425: DAR_Vol_1

Add for water charges @ 1% 39.45TOTAL 3,984.34Add for contractors profit and overheads @ 597.651,500%Cost for 11.16 sqm 4,581.99Cost for I sqm 410.57Say 410.55

433

SUB HEAD : 10.0

STEEL WORK

43510.1 : Structural steel work in single section fixed with or without connecting plate includ-

ing cutting, hoisting, fixing in position and applying coat of approved steel primer allcomplete.

CodDescription Unit Quantity Rate AmountDetails of cost for one quintalMaterials

Page 426: DAR_Vol_1

Steel = 1.00qAdd wastage @ 5% = 0.05q= 1.05q

###Steel quintal 1.05 3,100 3,255###Carriage tonne .105 47.29 4.97

Labour:###Fitter (Grade I) day .5 151.5 75.75###Blacksmith 2nd class day .75 141.6 106.2###Beldar day 1 135.25 135.25

(A) Priming cost-(Rate vide sqm 3 12.65 37.95item no. 13.50.3 finishing)

###Sundries L.S 20.67 1 20.67TOTAL 3,635.75Add 1% for water charges on all except ‘A’ 35.98TOTAL 3,671.77Add 15% for contractor’s profit andoverheads on all except ‘A” 545.07Cost of 1 qunital 4,216.84Cost of 1 kg. 42.17Say 42.15

10.2 : Structural steel work riveted, bolted or welded in built up sections, trusses and framedwork, including cutting, hoisting, fixing in position and applying a priming coat of approvedsteel primer all complete:

CodDescription Unit Quantity Rate AmountDetails of cost for a truss 7.6m clear spanMaterials-(i) Principal rafter (T-iron)100x 100x 10mm @ 15kg/m = 142.50Kg+Struts (angles)40x40x6mm2xl.35=2.70m @ 3.5kg/m = 9.45kg= 15l.95kg+Add wastage @ 5% = 7.60kg= 159.55kg. = 1.60q

###Principal rafter (T-iron) quintal 1.6 3,100 4,960(ii) Ties (flats) 50x12mm2x2.7 = 5.4m @4.7kg/m = 25.38kg+Ties central (flats) 50x10mm1x2.80 = 2.8m @3.90kg/m = 10.92kg.+Braces (flats)40x 10mm2x1.84 = 3.68m @3.9kg/m = 14.35kg.= 50.65kg+Add wastage @ 5% = 2.53kg.= 53.18kg. =0.53q

436CodDescription Unit Quantity Rate Amount###Ties (flats) 50x12mm quintal .53 2,875 1,523.75

(iii) Gusset plates 10mm thick1x0.74x0.35m = 0.259sqm.+shoe 4x0.46x0.46 = 0.845sqm.= 1.104 sqm.1.104sqm.@ 78.4kg/m = 86.55kg.12mm plates at the point of principal rafter

Page 427: DAR_Vol_1

and strut-2x0.3x0.2 = 0.12sqm.+Tie beam, brace and strut-2x0.5x0.3 = 0.30sqm.+Sole plates-2x0.46x0.46 = 0.42sqm.+Anchor plate-2x0.46x0.1 =0.09sqm.= 0.93 sqm.Say 1.00 sqm.1.00 sqm. @ 94.4kg/m = 94.40kg.= 180.95kg.Add wastage @ 5% = 9.05kg.= 190.00kg or 1.90q

###Gusset plates 10mm thick quintal 1.9 3,400 6,460(iv) 16mm dia. 50mm long rivets = 56 nos.+Add wastage @ 5 % = 2.8 nos.= 58.8 nos.

###16mm dia. 50mm long rivets quintal .0684 3,500 239.4(v) 20mm dia. holding down bolts4 Nos.x460mm = 1840mm +Add wastage @ 5% = 92mm= 1932 mm

###20mm dia. Holding down bolts quintal .0529 3,800 201.02###Carriage of tonne .415 47.29 19.63

steel-(0.160+0.053+0.091 +0.099+0.007+0.005)=0.415 tonneLabour-

###Fitter (Grade I) Day 2.7 151.5 409.05###Blacksmith 2nd class Day 3.6 141.6 509.76###Beldars (Special) Day 5.4 138.45 747.63###Beldar Day 3.6 135.25 486.9###Bandhani Day .44 138.45 60.92

Applying priming coat-T.Iron 9.5x0.4 = 3.80sqm.+Struts 2.70x0.16 = 0.43sqm.+Ties 5.4x0.124 = 0.67sqm.+Braces 2x 1.84x0.12 = 0.44 sqm.+Ties 2.8x0.12 = 0.34 sqm.= 5.68 sqm.

###(A) (Rate as per item 13.50.3 S.H.sqm 5.68 12.65 71.85Sundries L.S 80.73 1 80.73TOTAL 15 770.64Add for water charges @ 1% on all except ‘A’ 156.99TOTAL 15 927.63Add for contractor’s profit and overheads @ 2 378.3715% on all except ‘A’Quantity of net steel(151.95+50.65+180.95+6.5+5.04) = 395.09

437CodDescription Unit Quantity Rate Amount

kg = 3.95 quintalCost for 3.95 quintal 18 306.00

Page 428: DAR_Vol_1

Cost of per kg. 46.34Say 46.35

10.3 : Providing and fixing in position collapsible steel shutters with vertical channels20xl0x2mm and braced with flat iron diagonals 20x5mm size with top and bottom railof T-iron 40x40x6mm with 40mm dia, steel pulleys complete with bolts, nuts, lockingarrangement, stoppers, handles, including applying a priming coat of approved steelprimer.

CodDescription Unit Quantity Rate Amount

Details of cost for a gate2.4mxl.5m = 3.6sqm.Materials-M.S. channels 18 Nos. on both sides20xl0x2mm @ 0.56kg/m2x18x2.4 = 86.40m+Add wastage @ 10% = 8.64m= 95.04m

###[email protected]/m =53.22kg=0. quintal .53 3 100.00 1 643.00M.S. Tee-40x40x6mmfor bottom-1.5 70m+for top = 1.725m=3.295m Say 3.3m3.3m @ 3.5kg/m = 11.55kg+Add wastage @ 10% = 1.155 Kg.= 12.705Kg. SayO.I3q

###M.S. Tee quintal .13 3,100 40320mmx5mm flat iron diagonals 4 Nos.4x32x0.5334 = 68.275m68.275m @ 0.8kg/m = 54.62kg+Add wastage @ 10% = 5.46kg= 60.08kg = 0.60q

###Flat iron diagonals quintal .6 2,900 1 740.00###Carriage-(0.053+0.013+0.060=0.1tonne .126 47.29 5.96###Cost of rivets fixing hooks and w L.S. 269.1 1 269.1###Cost of locking arrangements andL.S. 67.34 1 67.34###Pulleys 40mm dia. each 10 19 190

Priming coat-Channel - 36x0.076x2.4 = 6.57sqm.+Tee-0.16x3.3=0.53sqm.+Flats-0.05x68 = 3.40sqm.= 10.50sqm.(A) (Rate as per item No. 13.50.3 sqm 10.5 12.65 132.82Labour-

###Fitter (Grade I) Day 3 151.5 454.5###Blacksmith 1st class Day 6 151.5 909###Blacksmith 2nd class Day 6 141.6 849.6###Mason 1st class Day .5 151.5 75.75###Mason 2nd class Day .5 141.6 70.8###Beldar Day 8 135.25 1,082

438CodDescription Unit Quantity Rate Amount

Page 429: DAR_Vol_1

###Sundries L.S. 161.46 1 161.46TOTAL 8,054.33Add for water charges @ 1% on all except ‘A’ 79.22TOTAL 8 133.55Add for contractor’s profit and overheads @ 1 200.1115%on all except’A’Cost of 3.6sqm. 9 333.66Cost per sqm. 2 592.68Say 2 592.70

10.4 : Providing and fixing 1mm thick M.S. sheet sliding-shutters with frame and diagonalbraces of 40x40x6mm angle 3mm M.S. gusset plates at the junction and corners25mm dia pulley, 40x40x6mm angle and T-iron guide at the top and bottom respectivelyincluding applying a priming coat of approved steel primer.

CodDescription Unit Quantity Rate AmountDetails of cost for one double leaf door size2.4x2.4m = 5.76sqm.Materials-(i) M.S. sheet lmm thick5.76sqm. @ 7.85kg/sqm. = 45.2I6kg.+Add wastage @ 10% = 4.522kg.= 49.738kg = 0.497 q

###M.S. Sheet 2x5.76= 11.52+ quintal .497 3,475 1,727.08(ii) Gusset plates 3.00mm thickArea of one gusset plates0.3x0.04 = 0.0120+1/2x0.26(0.04+0.3) = 0.0442= 0.0562sqm.+8x0.0562 = 0.4496sqm.+2x22/7x1/4x0.3x0.3=0.1414sqm.= [email protected]/sqm.= 13.92kg.+Add wastage @ 10% = 1.39kg- 15.31kg. or 0.153q

###Gusset plates quintal .153 3,400 520.2(iii) Angle iron40x40x6mm @ 3.5kg/mSides-4x2.4=9.6m+Bottom & top 4xi.2 = 4.8m+Diagonals-2x2.5=5.0m+2x2.45 = 4.9m+Top and bottom guides2x4.8 = 9.6mTop guide supports7x0.8 = 2.1m= 36.0m36m @3.5kg. per m. = 126kg.+Add wastage® 10%= 12.6kg.= 138.6kg. or 1.39q

###Angle iron quintal 1.39 3,100 4,309(iv)Channel 25x25x6mm @ 3.05kg/mBottom-2.4m : 2.4x3.05

Page 430: DAR_Vol_1

439CodDescription Unit Quantity Rate Amount

Channel 40x40x6mm @ 5.56kg/m0.5x5.56 = 2.78kg.= 10.1kg.+Add wastage @ 10% = 1.101 kg.= 11.11kg. or 0.11q

###Channel quintal .11 3,100 341###Carriage-(0.0497+0.015+0.139+0tonne .216 47.29 10.21

tonne)###(v) Pully guide blocks including drL.S. 269.1 1 269.1###(vi) 25mm dia. Pully each 8 18 144###(vii) Handles and locking arrang L.S. 167.75 1 167.75###(viii) Bolts and rivets L.S. 269.1 1 269.1###(ix)Cement concrete L.S. 13.52 1 13.52

Priming coat-M.S. Sheet 2x5.76 = 11.52+Angle iron 0.16x36 = 5.76+Channel-0.15x2.4=0.36+0.24x0.5=0.12= 17.76 Say 18.0sqm(A) (Rate as per item 13.50.3 of S.sqm 18 12.65 227.7Labour-

###Fitter (Grade 1) Day 2 151.5 303###Blacksmith 1st class Day 3 151.5 454.5###Blacksmith 2nd class Day 4 141.6 566.4###Beldar Day 4 135.25 541###Mason 1st class Day .06 151.5 9.09###Mason 2nd class Day .06 141.6 8.5###Sundries L.S. 161.46 1 161.46

TOTAL 10,042.61Add for water charges @ 1% on all except ‘A’ 98.15TOTAL 10,140.76Add for contractor’s profit and overheads @ 1,486.9615% on all except’A’Cost of 5.76 sqm. 11,627.72Cost per sqm. 2,018.7Say 2,018.7

10.5 : Providing and fixing 1mm thick M.S. sheet door with frame of 40x40x6mm angle ironand 3mm M.S. gusset plates at the junctions and corners, all necessary fittingscomplete, including applying a priming coat of approved steel primer.

10.5.1 : Using M.S. angels 40x40x6 mm for diagonal braces.CodDescription Unit Quantity Rate Amount

Details of cost for a double leaf door of size2.4mx2.4m=5.76sqm.Materials-(i) M.S. sheet lmm thick5.76sqm. @ 7.85kg/sqm. = 45.216kg.+Add wastage @ 10% = 4.522kg.= 49.738kg = 0.497 q

###M.S. Sheet 2x5.76= 11.52+ quintal .497 3 475.00 1,727.08(ii) Gusset plates 3.00mm thickArea of one gusset plates0.3x0.04 = 0.0120+

Page 431: DAR_Vol_1

440CodDescription Unit Quantity Rate Amount

1/2x0.26(0.04+0.3) = 0.0442= 0.0562sqm.+8x0.0562 = 0.4496sqm.+2x22/7xl/4x0.3x0.3=0.1414sqm.= [email protected]/sqm.= l3.92kg.+Add wastage @ 10% = 1.39kg= 15.31kg. or 0.153q

###Gusset plates quintal .153 3 475.00 531.67(iii) Angle iron:40x40x6mm @3.5kg/mSides-4x2.40 = 9.6m+Top & bottom-4xl.20=4.8m+Diagonals-2x2.5=5.0m+2x2.45 = 4.9m+= 24.30m+Add wastage @ 10% = 2.43m=26.73m26.73m @ 3.5kg. per m. = 93.56kg=0.936q

###Angle iron quintal .936 3 100.00 2 901.60###Carriage-(0.0497+0.0153+0.0936 tonne .1586 47.29 7.5

0.1586 t###(iv) Pintles including welded pin each 4 28 112###M.S. cleats with bolts an nuts to rest on pintles each 4 75 300###Hooks each 2 22 44###Locking arrangements and handl L.S. 167.7 1 167.7###Rivets L.S. 269.1 1 269.1

Priming coat-M.S. sheet = 11.52Angle iron-0.16x24.3 = 3.89(A) Rate As per items No. 13.50.3sqm 15.41 12.65 194.94Labour-

0 1 Fitter (Grade I) Day 2 151.5 303###Blacksmith 1st class Day 3 151.5 454.5###Blacksmith 2nd class Day 4 141.6 566.4###Mason 1st Class Day .06 151.5 9.09###Mason 2nd class Day .06 141.6 8.5###Beldar Day 5 135.25 676.25###Sundries L.S. 161.46 1.43 161.46

TOTAL 8 434.79Add for water charges @ 1% on all except ‘A’ 82.4TOTAL 8,517.19Add for contractor’s profit and overheads @ 1 248.3415% on all except ‘A’ 9 765.53Cost of 5.76 sqm. 1,695.4Cost per sqm. 1,695.4

10.5 : Providing and fixing 1mm thick M.S. sheet door with frame of 40x40x6mm angle ironand 3mm M.S. gusset plates at the junctions and corners, all necessary fittingscomplete, including applying a priming coat of approved steel primer.

10.5.1 : Using M.S. angels 40x40x6 mm for diagonal braces.CodDescription Unit Quantity Rate Amount

Details of cost for a double leaf door of size2.4mx2.4m=5.76sqm.Materials-

Page 432: DAR_Vol_1

441CodDescription Unit Quantity Rate Amount

(i) M.S. sheet lmm thick5.76sqm. @ 7.85kg/sqm. = 45.216kg.+Add wastage @ 10% = 4.522kg.= 49.738kg = 0.497 q

###M.S. Sheet 2x5.76= 11.52+ quintal .497 3 475.00 1 727.08(ii) Gusset plates 3.00mm thickArea of one gusset plates0.3x0.04 = 0.0120+1/2x0.26(0.04+0.3) = 0.0442= 0.0562sqm.+8x0.0562 = 0.4496sqm.+2x22/7xl/4x0.3x0.3=0.1414sqm.= [email protected]/sqm.= l3.92kg.+Add wastage @ 10% = 1.39kg= 15.31kg. or 0.153q

###Gusset plates quintal .153 3 475.00 531.67(iii) Angle iron:40x40x6mm @3.5kg/mSides-4x2.40 = 9.6m+Top & bottom-4xl.20=4.8m+Diagonals-2x2.5=5.0m+2x2.45 = 4.9m+= 24.30m+Add wastage @ 10% = 2.43m=26.73m26.73m @ 3.5kg. per m. = 93.56kg=0.936q

###Angle iron quintal .936 3 100.00 2 901.60###Carriage-(0.0497+0.0153+0.0936 tonne .1586 47.29 7.5

0.1586 t###(iv) Pintles including welded pin each 4 28 112###M.S. cleats with bolts an nuts to each 4 75 300###Hooks each 2 22 44###Locking arrangements and handl L.S. 167.7 1 167.7###Rivets L.S. 269.1 1 269.1

Priming coat-M.S. sheet = 11.52Angle iron-0.16x24.3 = 3.89(A) Rate As per items No. 13.50.3sqm 15.41 12.65 194.94Labour-

0 1 Fitter (Grade I) Day 2 151.5 303###Blacksmith 1st class Day 3 151.5 454.5###Blacksmith 2nd class Day 4 141.6 566.4###Mason 1st Class Day .06 151.5 9.09###Mason 2nd class Day .06 141.6 8.5###Beldar Day 5 135.25 676.25###Sundries L.S. 161.46 1.43 161.46

TOTAL 8 434.79Add for water charges @ 1% on all except ‘A’ 82.4TOTAL 8,517.19Add for contractor’s profit and overheads @ 1 248.3415% on all except ‘A’ 9 765.53Cost of 5.76 sqm. 1,695.4

Page 433: DAR_Vol_1

Cost per sqm. 1,695.4

44210. Providing and fixing lmm thick M.S. sheet door with frame of 40x40x6mm angle iron and

3mm M.S. gusset plates at the junctions and corners, all necessary fittings complete, includingapplying a priming coat of approved steel primer.

10.5.2 : Using flats 30x6mm for diagonal braces and central cross piece.CodDescription Unit Quantity Rate Amount

Details of cost for a double leaf door of size2.40m x 2.40m= 5.76 sqmMaterials-(i) M.S. sheet lmm thick5.76sqm. @ 7.85kg/sqm. = 45.216kg.Add wastage @ 10% = 4.522kg.= 49.738kg = 0.497 q

###M.S. Sheet quintal .497 3 475.00 1,727.08(ii) Gussets plates-3.00mm thick vide (ii) initem 10.4 = 0.5910sqm.at mid height = 4x0.0528 = 0.2112sqm.= 0.8022sqm.Add wastage @ 10% = 0.0802sqm.=0.8824sqm. @ 23.55 kg/sqm =20.78 kg= 0.2078 qtl

###Gussets plates-3.00mm thick quintal .2078 3 400.00 706.52(iii) Angle iron:40x40x6mm @3.5kg/mSides-4x2.40 = 9.6mTop & bottom-4xl.20=4.8m= 14.40mAdd wastage @ 10% = 1.44m= 15.84m15.84m @ 3.5kg. per m..= 55.44kg =0.554qtl

###Angle iron quintal .554 3,100 1,717.4(iv) Flats 30x6mm @1.4kg/m4x2.45=9.80m+2xl.20=2.40m= 12.20m+Add wastage @ 10% = 1.22m= 13.42m13.42m @ 1.4kg. per m. = 18.788kg. = 0.188q

###Flats quintal .188 2 900.00 545.2###Carriage of (i) (ii) and tonne .1447 47.29 6.84

(iv)-0.0497+0.0208+0.0554+0.0188=0.1447tonne

###Pintles including welded pin each 4 28 112###M.S. Cleats with bolts and nuts t each 4 75 300

pintles###Hooks each 2 22 44###Locking arrangements and handl L.S. 167.7 1 167.7###Rivets L.S. 269.1 1 269.1

Applying priming coat-M.S. sheet = 11.52Angle iron-0.16x24.3 = 3.890.16x14.40 = 2.30+Flats 0.072x12.2 = 0.88

Page 434: DAR_Vol_1

= 14.70sqm.(A) Rates as per Item No. 13.50.3sqm 14.7 185.96Labour-

###Fitter (Grade I) Day 2 151.5 303###Blacksmith 1st class Day 3 151.5 454.5###Blacksmith 2nd class Day 4 141.6 566.4

443CodDescription Unit Quantity Rate Amount###Mason 1st Class Day .06 151.5 9.09###Mason 2nd class Day .06 141.6 8.5###Beldar Day 5 135.25 676.25###Sundries L.S. 161.46 1 161.46

TOTAL 7 961.00Add for water charges @ 1% on all except ‘A’ 77.75TOTALAdd for contractor’s profit and overheads @ 8,038.7515% on all except ‘A’ 1,177.92Cost of 5.76 sqm. 9,216.67Cost per sqm. 1 600.12Say 1,600.1

10.6 : Supplying and fixing rolling shutters of approved make, made of required size M.S.laths interlocked together through their entire length and jointed together at theend by end locks mounted on specially designed pipe shaft with brackets, side guidesand arrangements for inside and outside locking with push and pull operationcomplete including the cost of providing and fixing necessary 27.5cm long wiresprings grade No.2 and M.S. top cover of required thickness for rolling shutters.

10.6.1: 80xl.25mm M.S. laths with 1.25 mm thick top cover.

CodDescription Unit Quantity Rate AmountDetails of cost for a shutter of size3mx2.5m = 7.5sqm.Materials-

0 9 Cost of Rolling shutter sqm 7.5 767 5,752.50 9 Top Cover metre 2.5 400 1,0000 9 Coiled type spring each 1 170 170###Carriage L.S. 53.82 1 53.82

Labour-###Fitter (Grade 1) Day 2.55 151.5 386.32###Beldar Day 2.55 135.25 344.89###Mason 1st Class Day .12 151.5 18.18###Mason 2nd class Day .12 141.6 16.99###Sundries L.S. 60.58 1 60.58

TOTAL 7,803.28Add for water charges @ 1 % 78.03TOTAL 7,881.31Add for contractor’s profit and overheads @ 1,182.21,500%Cost of 7.5sqm. 9,063.51Cost per sqm. 1,208.47Say 1,208.45

12.65

Page 435: DAR_Vol_1

44410.6 : Supplying and fixing rolling shutters of approved make, made of required size M.S.

laths interlocked together through their entire length and jointed together at theend by end locks mounted on specially designed pipe shaft with brackets, sideguides and arrangements for inside and outside locking with push and pull operationcomplete including the cost of providing and fixing necessary 27.5cm long wiresprings grade No.2 and M.S. top coypr of required thickness for rolling shutters.

10.6.2 :80x1.20 mm M.S. laths with 1.20 mm thick top cover.Code Description Unit Quantity Rate Amount

Details of cost for a shutter of size3mx2.5m = 7.5sqm.Materials-

### Cost of Rolling shutter sqm 7.5 615 4 612.50### Top Cover metre 2.5 228 570### Coiled type spring each 1 170 170### Carriage L.S. 53.82 1 53.82

Labour-### Fitter (Grade I) Day 2.55 151.5 386.32### Beldar Day 2.55 135.25 344.89

### 123 Mason 1st Class Day .12 151.5 18.18### 124 Mason 2nd class Day .12 141.6 16.99### Sundries L.S. 60.58 1 60.58

TOTAL 6 233.28Add for water charges @ 1% 62.33TOTAL 6 295.61Add for contractor’s profit and overheads @ 944.341,500%Cost of 7.5sqm. 7 239.95Cost per sqm. 965.33Say 965.35

10.6 : Supplying and fixing rolling shutters of approved make, made of required size M.S.laths interlocked together through their entire length and jointed together at theend by end locks mounted on specially designed pipe shaft with brackets, sideguides and arrangements for inside and outside locking with push and pull operationcomplete including the cost of providing and fixing necessary 27.5cm long wiresprings grade No.2 and M.S. top’cover of required thickness for rolling shutters.

10.6.3 : 80x0.90 mm M.S. laths with 0.90 mm thick top cover.Code Description Unit Quantity Rate Amount

Cost of Rolling shutterDetails of cost for a shutter of size3mx2.5m = 7.5sqm.Materials-

### Cost of Rolling shutter sqm 7.5 576 4,320### Top Cover metre 2.5 205 512.5### Coiled type spring each 1 170 170### Carriage L.S. 60.58 1 60.58

Labour-### Fitter (Grade I) Day 2.55 151.5 386.32### Beldar Day 2.55 135.25 344.89

Page 436: DAR_Vol_1

### Mason 1st Class Day .12 151.5 18.18### Mason 2nd class Day .12 141.6 16.99### Sundries L.S. 60.58 1 60.58

TOTAL 5,883.28

445CodDescription Unit Quantity Rate Amount

Add for water charges @ 1 % 58.83 TOTAL 5,942.11Add for contractor’s profit and overheads @ 891.321,500%Cost of 7.5sqm. 6,833.43Cost per sqm. 911.12Say 911.1

10.Providing and fixing ball bearing for rolling shutters

CodDescription Unit Quantity Rate AmountDetails of cost for 1 No.

###Ball bearing each 1 280 280###Sundries L.S. 26.91 1 26.91

TOTAL 306.91Add for water charges @ I % 3.07TOTAL 309.98Add for contractor’s profit and overheads@ 46.51,500%Cost of 1 no. 356.48Say 356.5

10.8: Extra for providing mechanical device chain and crank operation for operating rollingshutters.

10.8.1:Exceeding 10.00 sqm and upto 16.80 sqm in the area.CodDescription Unit Quantity Rate Amount

Details of cost for one sqm.###Extra for mechanical devices chasqm 1 400 400

cranked operation for operating rolling shutters: exceeding 10.00 sq.m and upto 16.80 sq.marea of door

###Sundries L.S. 13.52 1 13.52TOTAL 413.52Add for water charges @ 1 % 4.14TOTAL 417.66Add for contractor’s profit and overheads @ 62.651,500%Cost of 1 sqm. 480.31Say 480.3

10.8: Extra for providing mechanical device chain and crank operation for operating rollingshutters.

10.8.2:Exceeding 16.80 sqm in area.CodDescription Unit Quantity Rate Amount

Details of cost for one sqm.###Extra for mechanical devices chasqm 1 450 450

cranked operation for operating rolling

Page 437: DAR_Vol_1

shutters : exceeding 16,80 sq.m area of door###Sundries L.S. 13.52 1 13.52

TOTAL 463.52Add for water charges @ 1% 4.64TOTAL 468.16

446CodDescription Unit Quantity Rate Amount

Add for contractor’s profit and overheads @ 70.221,500%Cost of 1 sqm. 538.38Say 538.4

10.Extra for providing grilled rolling shutters manufactured out of 8 mm dia. M.S. barinstead of laths as per design approved by Engineer-in-charge. (area of grill to bemeasured).

CodDescription Unit Quantity Rate Amount

Details of cost for a shutter of width 2.5m andgrill height 0.6mGrill Area = 1.50sqm.Materials-

###Extra for providing grilled rolling sqm 1.5 185 277.5manufactured out of 8mm dia. M.S. barinstead of lathsTOTAL 277.5Add for water charges @ 1 % 2.78TOTAL 280.28Add for contractor’s profit and overheads @ 42.041,500%Cost of 1.5sqm. 322.32Cost per sqm. 214.88Say 214.9

10.10: Fixing standard steel glazed doors, windows and ventilators in walls with 15x3mmlugs 10 cm long embedded in cement concrete blocks 15xl0xl0cm of 1:3:6 (I cement:3 coarse sand : 6 graded stone aggregate 20 mm nominal size) or with woodenplugs and screws or rawl plugs and screws or with fixing clips or with bolts andnuts as required, including fixing of float glass panes with glazing clips and specialmetal-sash putty of approved make, or metal beading with screws (only steel windowswith lugs, glass panes cut to size and glazing clips or metal beading with screws,shall be supplied by department free of cost.)

CodDescription Unit Quantity Rate AmountDetails of cost for one door 2x0.76m =1.52sqm.(weight 15 kg)Materials-(A) Cement concrete blocks 15x10x10cm = 0.009 c .009 3,112.7 28.01cum (Rate as per item No. 4.2.5 of S.H. C.C.)Labour-

###Blacksmith 1st class Day .17 151.5 25.76###Mason 1st Class Day .08 151.5 12.12###Mason 2nd class Day .08 141.6 11.33

Page 438: DAR_Vol_1

###Beldar Day .5 135.25 67.62###Glazier Day .17 141.6 24.07###Putty and sundries L.S. 134.55 1 134.55

TOTAL 303.46Add for water charges @ 1% on all except ‘A’ 2.75TOTAL 306.21

447CodDescription Unit Quantity Rate Amount

Add for contractor’s profit and overheads @ 41.7315% on all except ‘A’Cost of 15 kg 347.94Cost per kg 23.2Say 23.2

10.11 Providing and fixing factory made ISI marked steel glazed doors, windows andventilators side /top /centre hung with beading and all members such as KlIB andK12 B etc. complete of standard rolled steel sections, joints mitred and flash buttwelded and sash bars tenoned and rivetted with 15x3mm lugs, 10cm long, embeddedin cement concrete blocks 15x10x 10cm of 1:3:6 (1 cement : 3 coarse sand : 6 gradedstone aggregate 20mm nominal size) or with wooden plugs and screws or rawlplugs and screws or with fixing clips or with bolts and nuts as required, includingproviding and fixing of hinges, pivots, float glass panes with glazing clips and specialmetal sash putty of approved make and a priming coat of approved steel primerexcluding the cost of metal beading and other fittings except necessary hinges orpivots complete as per approved design.

CodDescription Unit Quantity Rate Amount

Details of cost for a double leaf door of size2.075x1.175m = 2.44 sqm. (weight 30 kg).Materials-

###Readymade steel door with necessqm 2.44 1 406.00 3 430.64lugs and glazing clips but excluding otherfittings and their fixing to hold glass panes etc.2.075xl.l75m = 2.44 sqm.

###Float glass panes 4 mm thick (Ar sqm 1.95 248 483.6opening

###Carriage of steel door and glass L.S. 80.73 1 80.73Fixing with CC 1:3:6 blocks, wooden plugsand screws or rawl plugs and screws or withfixing clips and bolts and nuts as requiredincluding metal sash putty for glass fixing(A)Rate as per item no 10.10 of S kg 30 23.2 696(B)Apply steel primer (2.44x 1.00 sqm 2.44 12.65 30.87sides =2.44 sqm (Rate as per code No.13.50.3 of SH finishing)TOTAL 4,721.84Add for water charges @ 1% on all items 39.95except (A+B)TOTAL 4,761.79Add for contractor’s profit and overhead @ 605.24

Page 439: DAR_Vol_1

15% on all except (A+B)Cost for 30 kg. 5,367.03Cost of 1 kg. 178.9Say 178.9

44810.12: Extra for providing and fixing steel beading of approved shape and section with

screws instead of glazing clips and metal sash putty in steel doors, windows,ventilators and composite units.

CodDescription Unit Quantity Rate Amount

Details of cost for 1 metrebeading for doors, windows,Ventilatators and composit units

###Cost of 1 metre beading metre 1 15 15Applying priming coat L.S. .46 1 .46Fixing charges L.S. 3.01 1 3.01TOTAL 18.47Add water charges @ 1% .18TOTAL 18.65Add contractor’s profit and 2.8overhead @ 15% 21.45say 21.45

10.13: Providing and fixing T-iron frames for doors, windows and ventilators of mild steelTee-sections, joints mitred and welded with 15x3 mm lugs, 10cm long embedded incement concrete blocks 15x10x10 cm of 1:3:6 (1 cement : 3 coarse sand : 6 gradedstone aggregate 20 mm nominal size) or with wooden plugs and screws or withdash fastener or rawl plugs and screws or with fixing clips or with bolts and nuts asrequird including fixing.of necessary butt hinges and screws and applying a primingcoat of approved steel primer.

CodDescription Unit Quantity Rate AmountDetails of cost for 17.5Kg.MaterialsTee iron 40x40x6mm = 2m+2m+lm = 5metres5 metres @3.5Kg/m = 17.5kg.+Add wastage @ 5% = 0.87Kg.= 18.37 kg. Say 0.18 qunital

###Tee iron quintal .18 3 100.00 558M.S. bars 10mm = Ixlm = 1 metre1 metre @ 0.60kg/m = 0.60Kg.+Add wastage @ 5% = 0.03Kg.= 0.63 Kg. Say = 0.006 qunital

###M.S. bars quintal .006 3 100.00 18.6M.S. flat 15x3mm = 6x10cm = 0.60 metre0.6 metre @ O.35kg/m = 0.21 Kg+Add wastage @ 5% = 0.01 Kg.= 0.22 kg.

###M.S. fiat quintal .002 2 900.00 5.8Cement concrete block 1:3:6-6x15x10x10cm= 0.009 cum(A)(Rate as per item no.4.2.5 of cum .009 3 112.70 28.01

Page 440: DAR_Vol_1

0 5 Butt hinges-100x58x 1.90mm 10 Nos 6 54 32.4###For screws and nuts and bolts L.S. 35.88 1 35.88###For applying steel primer L.S. 17.94 1 17.94###Carriage of material L.S. 5.33 1 5.33

Labour-###Blacksmith 2nd class Day .1 141.6 14.16###Fitter (Grade 1) Day .15 151.5 22.72###Beldar Day .2 135.25 27.05

449CodDescription Unit Quantity Rate Amount

###Sundries L.S. 8.97 1 8.97TOTAL 774.86Add for water charges @ 1% on all except ‘A’ 7.47TOTAL 782.33Add for contractor’s profit and overheads @ 113.1515% on all except’A’Cost for 17.5 Kg. 895.48Cost for 1 Kg. 51.17Say 51.15

### Providing and fixing pressed steel door frames confirming to IS: 4351 manufacturedfrom commercial mild steel sheet of 1.25 mm thickness including hinges jamb, lockjamb, bead and if required angle threshold of mild steel angle of section 50x25mm,or base ties of 1.25mm pressed mild steel welded or rigidly fixed together bymechanical means, adjustable lugs with split end tail to each jamb including steel

butt hinges 2.5mm thick with mortar guards, lock strike-plate and shock absorbersas specified and applying a coat of approved steel primer after pre-treatment of thesurface as directed by Engineer-in-charge:

10.14.1 Profile BCodDescription Unit Quantity Rate Amount

Details of cost for 5 metreMaterials-

###Pressed steel frame =2+2+lm=5 metre 5 170 850###Butt hinges-100x58x1.90mm 10 Nos 6 80 48:00###50x25x5mm. M.S. Angle for thresquintal .03 3,100 93

metre @ 2.75kg per metre =2.75kg. Say 0.03q###Carriage of material L.S. 5.33 1 5.33

Labour-###Fitter (Grade I) Day .15 151.5 22.72###Beldar Day .2 135.25 27.05###Sundries L.S. 8.97 1 8.97

Steel primer-500x2(2x1.2+2x6.0+1 x 12.50cm)=2.69 sqm(A) Rate as per item no I3.50.3 of SH : Finishing sqm 2.69 12.65 34.03TOTAL 1 089.10Add for water charges @ 1% on all except A 10.55TOTAL 1 099.65Add for contractor’s profit and overheads @ 159.8415% on all except A

Page 441: DAR_Vol_1

Cost for 5m 1 259.49Cost for 1 m 251.9Say 251.9

450### Providing and fixing pressed steel door frames confirming to IS: 4351 manufactured

from commercial mild steel sheet of 1.25 mm thickness including hinges jamb, lockjamb, bead and if required angle threshold of mild steel angle of section 50x25mm,or base ties of 1.25mm pressed mild steel welded or rigidly fixed together bymechanical means, adjustable lugs with split end tail to each jamb including steelbutt hinges 2.5mm thick with mortar guards, lock strike-plate and shock absorbersas specified and applying a coat of approved steel primer after pre-treatment of thesurface as directed by Engineer-in-charge:

10.14.2 Profile C

CodDescription Unit Quantity Rate AmountDetails of cost for 5 metreMaterials-

###Pressed steel frame =2+2+lm=5 metre 5 187 935###Butt hinges-100x58x1.90mm 10 Nos 6 80 48###50x25x5mm. M.S. Angle for thresquintal .03 3,100 93

metre @ 2.75kg per metre =2.75kg. Say 0.03q###Carriage of material L.S. 5.33 1 5.33

Labour-###Fitter (Grade I) Day .15 151.5 22.72###Beldar Day .2 135.25 27.05###Sundries L.S. 8.97 1 8.97

Steel primer-500x2(2x 1.2+2x6.0+1 x 12.50cm)sqm =2.69(A) Rate as per item no 13.50.3 of SH : Finishing sqm 2.69 12.65 34.03TOTAL 1,174.1Add for water charges @ 1% on all except ‘A’ 11.4TOTAL 1,185.5Add for contractor’s profit and overheads @ 172.7215% on all except ‘A’Cost for 5 m 1,358.22Cost for 1 m 271.64Say 271.65

### Providing and fixing pressed steel door frames confirming to IS: 4351 manufacturedfrom commercial mild steel sheet of 1.25 mm thickness including hinges jamb,lock jamb, bead and if required angle threshold of mild steel angle of section50x25mm, or base ties of I.25tnm pressed mild steel welded or rigidly fixed togetherby mechanical means, adjustable lugs with split end tail to each jamb includingsteel butt hinges 2.5mm thick’with mortar guards, lock strike-plate and shockabsorbers as specified and applying a coat of approved steel primer after pre-treatment of the surface as directed by Engineer-in-charge:

10.14.3 Profile ECodDescription Unit Quantity Rate Amount

Details of cost for 5 metreMaterials-

Page 442: DAR_Vol_1

###Pressed steel frame =2+2+lm=5 metre 5 214 1 070.00###Butt hinges-100x58x1.90mm 10 Nos 6 80 48###50x25x5mm. M.S. Angle for thresquintal .03 3 100.00 93

metre @ 2.75kg per metre =2.75kg. Say 0.03q###Carriage of material L.S. 5.33 1 5.33

Labour-###Fitter (Grade I) Day .15 151.5 22.72###Beldar Day .2 135.25 27.05

451CodDescription Unit Quantity Rate Amount###Sundries L.S. 8.97 1 8.97

Steelprimer-500x2(2x 1.2+2x6.0+1x12.50cm)=2.69sqm(A)Rate as per item no 13.50.3 of SH : Finishing sqm 2.69 12.65 34.03TOTAL 1,309.1Add for water charges @ 1% on all except ‘A’ 12.75TOTAL 1,321.85Add for contractor’s profit and overheads @ 193.1715% on all except ‘A’Cost for 5m 1,515.02Cost for 1 m 303Say

10.15 Providing and fixing M.S. Tubular frames for doors, windows, ventilators andcupboard with L-Type section made of 1.60mm thick M.S. Sheet, joints mitred andwelded and grinded finish,with profiles of required size with 15x3mm lugs 10cmlong embedded in cement concrete blocks 15x10x10cm of 1:3:6 (1 cement : 3 coarsesand: 6 graded stone aggregate 20mm nominal size) or with wooden plugs andscrews or rawl plugs and screws or with fixing clips or with bolts and nuts as requiredincluding fixing of necessary butt hinges and screws and applying a priming coat ofapproved steel primers.

CodDescription Unit Quantity Rate AmountDetails of cost for 7.13Kg. MaterialsL- section - 32x22x28mm 1.60mm thick2.00+2.00+1.00 = 5.00 mWidth of MS sheet =32+24.80+22+24.80+10mm = 113.60mm =0.1136mArea of MS sheet = 0.1136x5.00x0.0016 =0.0009088 sqmWeight of Sheet = 0.0009088x7850 = 7.134 kgAdd wastage @ 5% = 0.357Kg.

###Total = 7.491 kg Say 7.49 kg kg 7.49 53 396.97M.S. bars 10mm = lxlm = 1 metre1 metre @ 0.60kg/m = 0.60Kg.Add wastage @ 5% = 0.03 Kg.= 0.63 Kg. Say = 0.006 qunital

###M.S. bars quintal .006 3,100 18.6M.S. flat 15x3mm = 6x10cm = 0.60 metre0.6 metre @ 0.35kg/m = 0.21 KgAdd wastage @ 5% = 0.01 Kg. “

Page 443: DAR_Vol_1

= 0.22 kg.###M.S. flat quintal .002 2,900 5.8

Cement concrete block 1:3:6-6x15x10x10cm= 0.009 cum(A)(Rate as per item no 4.2.5 of cum .009 3,112.7 28.01

###Butt hinges-100x58x1.90mm 10 Nos 6 54 32.4###For screws and nuts and bolts L.S. 35.88 1 35.88###For applying steel primer L.S. 17.94 1 17.94###Carriage of material L.S. 5.33 1 5.33

Labour-###Blacksmith 2nd class Day .04 141.6 5.66

452CodDescription Unit Quantity Rate Amount###Fitter (Grade I) Day .06 151.5 9.09###Beldar Day .08 135.25 10.82###Sundries L.S. 3.64 1 3.64

TOTAL 570.14Add for water charges @ 1% on all except ‘A’ 5.42TOTAL 575.56Add for contractor’s profit and overheads @ 82.1315% on all except ‘A’Cost for 7.13 Kg. 657.69Cost for 1 Kg. 92.24Say 92.25

### Steel work in built up tubular trusses including cutting, hoisting fixing in positionand applying a priming coat of approved steel primer, welded and bolted includingspecial shaped washers etc. complete.

10.16.1 Hot finished welded type tubesCodDescription Unit Quantity Rate Amount

Details of cost for a truss of span 8 metreweight = 119 kg.Materials-50mm dia. tubeTie beam-lx8.0m = 8.00m+Principal rafter 2x4.30m = 8.60m= 16.60m16.60m @ 5.10kg./m = 84.66kg.40mm dia. tubeMembers = 2(0.45+1.25+0.90+2.15)= 2x4.75=9.50m9.50m @ 3.61kg/m = 34.60Kg.Total = 118.96kg.Add wastage @ 5% = 5.94Kg.= 124.90Kg. say 125 kg

###Hot finished welded tubes kilogram 125 .00 38 4 750.00###Carriage of tubes tonne .125 47.29 5.91

Priming coat50mm dia. tube 16.60x0.157m = 1.61 sqm.40mm dia. tube 9.50x0.125m = 1.91 sqm.= 2.80 sqm.(A)(Rate as per item 13.50.3 of S.H. finishing) sqm 2.8 12.65 35.42

Page 444: DAR_Vol_1

Welding charges:-Rafter:- 4x22/7x6.03 = 75.80cm.+Ties:- 2x22/7x6.03=37.90cm.+Members:-2x4x2x22/7x4.83=242.87cm= 356.57cm say 357cm

###Welding cm 357 1 357Labour-For cutting, assembling & erection

###Blacksmith 1st class Day 1.5 151.5 227.25###Bandhani Day .75 138.45 103.84###Beldar Day 5.5 135.25 743.88###Sundries L.S. 80.73 1 80.73

TOTAL 6 304.03Add for water charges @ 1% on all except ‘A’ 62.69

453CodDescription Unit Quantity Rate Amount

TOTAL 6 366.72Add for contractor’s profit and overheads @ 949.715% on all except ‘A’Cost for 119 Kg. 7 316.42Cost for 1 Kg. 61.488Say 61.5

10.16 Steel work in built up tubular trusses including cutting, hoisting fixing in positionand applying a priming coat of approved steel primer, welded and bolted includingspecial shaped washers etc. complete.

10.16.2 Hot finished seamless type tubes

CodDescription Unit Quantity Rate Amount

Details of cost for a truss of span 8 metreweight = 119 kg.Materials50mm dia. tubeTie beam- I x 8.0m = 8.00m +Principal rafter 2x4.30m = 8.60m = 16.60m16.60m @ 5.10kg./ m = 84.66 kg.40mm dia. tubeMembers = 2(0.45+1.25+0.90+2.15)= 2x4.75 = 9.50m9.50m @ 3.61kg/m = 34.60kg.Total = 118.96kg.Add wastage @ 5% = 5.94kg.= 124.90kg. say 125 Kg.

###Mild steel tubes hot finished s kilogram 125 42 5 250.00###Carriage of tubes tonne .125 47.29 5.91

Priming coat50mm dia. tube 16.60x0.157 m = 1.61 sqm.40mm dia. tube 9.50x 10125m = 1.91 sqm.=2.80 sqm.(A) Rate as per item no 13.50.3 ofsqm 2.8 12.65 35.42Welding charges:-Rafter:- 4x22/7x6.03 = 75.80cm.+

Page 445: DAR_Vol_1

Ties :- 2x22/7x6.03=37.90cm.+Members :- 2x4x2x22/7x4.83 = 242.87cm= 356.57 cm say 357 cm

###Welding cm 357 1 357LABOUR

###Blacksmith 1st class Day 1.5 151.5 227.25###Bandhani Day .75 138.45 103.84###Beldar Day 5.5 135.25 743.88###Sundries L.S. 80.73 1 80.73

TOTAL 6,804.03Add for water charges @ 1% on all except ‘A’ 67.69TOTAL 6,871.72Add for contractor’s profit and overheads @ 1,025.4515% on all except ‘A’Cost for 119 Kg. 7,897.17Cost for 1 Kg. 66.36Say 66.35

454### Steel work in built up tubular trusses including cutting, hoisting fixing in position

and applying a priming coat of approved steel primer, welded and bolted includingspecial shaped washers etc. complete.

10.16.3 Electric resistance or induction butt welded tubes.CodDescription Unit Quantity Rate Amount

Details of cost for a truss of span 8 metreweight = 119 kg.Materials-50mm dia. tubeTie beam-1x8.0m = 8.00m+Principal rafter 2x4.30m = 8.60m= 16.60m16.60m @ 5.10kg./m = 84.66kg.40mm dia. tubeMembers = 2(0.45+1.25+0.90+2.15)= 2x4.75=9.50m9.50m @ 3.61kg/m = 34.60Kg.Total = 118.96kg.Add wastage @ 5% = 5.94Kg.= 124.90Kg. say 125 kg.

### Electric resistance or Ind Kilogram 125 53 6 625.00

on butt welded tubes###Carriage of tubes tonne .125 47.29 5.91

Priming coat50mm dia. tube 16.60x0.157 m = 1.61 sqm.40mm dia. tube 9.50x 10125m = 1.91 sqm.=2.80 sqm.(A) Rate as per item no 13.50.3 ofsqm 2.8 12.65 35.42Welding charges:-Rafter:- 4x22/7x6.03 = 75.80cm.+Ties :- 2x22/7x6.03=37.90cm.+Members :- 2x4x2x22/7x4.83 = 242.87cm= 356.57 cm say 357 cm

###Welding cm 357 1 357

Page 446: DAR_Vol_1

LABOUR###Blacksmith 1st class Day 1.5 151.5 227.25###Bandhani Day .75 138.45 103.84###Beldar Day 5.5 135.25 743.88###Sundries L.S. 80.73 1 80.73

TOTAL 8 179.03Add for water charges @ 1% on all except ‘A’ 81.44TOTAL 8 260.47Add for contractor’s profit and overheads @ 1 233.7615% on all except ‘A’Cost for 119 Kg. 9 494.23Cost for 1 Kg. 79.78Say 79.8

10.17 Providing and fixing M.S. fan clamp type I or II of 16 mm dia M.S. bar bent to shapewith hooked ends in R.C.C. slabs, beams during laying including painting the exposedportion of loop, all as per standard design complete.

CodDescription Unit Quantity Rate AmountDetails of cost for 1 clampMateriats-16mm dia. M.S. bar 1m @ 1.58 kg/m

455CodDescription Unit Quantity Rate Amount

1x1.58 = 1.58Kg+Add wastage @ 5% = 0.08 Kg.= 1.66 Kg.Say 1.70kg. or 0.017q

###M.S. bar quintal .017 3 050.00 51.85Labour-

###Blacksmith 2nd class Day .04 141.6 5.66###Beldar Day .04 135.25 5.41###Sundries (Carriage, fixing and pai L.S. 1.82 1 1.82

TOTAL 64.74Add for water charges @ 1% .65TOTAL 65.39Add for contractor’s profit and overheads @ 9.811,500%Cost for I clamp 75.2Say 75.2

10.18 Providing and fixing circular/ Hexagonal cast iron or M.S. sheet box for ceiling fanclamp of internal dia 140mm, 73mm height, top lid of 1:5mm thick M.S. sheet with itstop surface hacked for proper bonding, top lid shall be screwed into the cast iron/M.S. sheet box by means of 3.3mm dia. round headed screws, one lock at the corners.Clamp shall be made of 12mm dia M.S. bar bent to shape as per standard drawing,

CodDescription Unit Quantity Rate AmountDetails of cost of one box clampMaterials-

###Circular C.I. Box including botto each 1 35 35lids

Page 447: DAR_Vol_1

12mm dia. M.S. bar 80cm @ 0.9kg/m -0.72kg+Add wastage @ 5% - 0.036

###0.756 kg. Say 0.008 q quintal .008 3,100 24.8Labour-

###Blacksmith 2nd class Day .03 141.5 4.25###Beldar Day .03 135.5 4.06###Sundries (Carriage, fixing and pai L.S. 1.82 1 1.82

TOTAL 69.93Add for water charges @ 1% .7TOTAL 70.63Add for contractor’s profit and overheads @ 10.591,500%Cost for 1 box clamp 81.22Say 81.2

45610.19 Providing and fixing M.S. round holding down with nuts and wahser plates completes.

CodDiscription Unit Quantity Rate Amount

Details of cost for one bolt 16mm dia. and1200mm long.Materials-

###l .2m @ 1.58kg/m = 1.895 kg = 0 quintal .019 4,300 81.7Plate-100xl00x6mm @ 47kg/sqm.

###Wt. = 0.47kg. = 0.005q quintal .005 3,400 17Labour-

###Blacksmith 2nd class day .03 141.6 4.25###Carriage and labour for fixing L.S 4.55 1 4.55

TOTAL 107.5Add for water charges @ 1 % 1.08TOTAL 108.58Add for contractor’s profit and overheads @ 16.291,500%Costof0.024q 124.87Cost of 1 kg. 52.03Say 52.05

10. 20 Providing and fixing bolts including nuts and washers complete.

CodDiscription Unit Quantity Rate Amount

Details of cost for 0.10q of nuts andwashersMaterials-

###Bolts, nuts and washers quintal .1 4,300 430###Carriage tonne .01 47.29 .47

Labour-###Blacksmith 2nd class day .38 141.6 53.81###Beldar day .38 135.25 51.4###Sundries L.S 4.55 1 4.55

TOTAL 40.23Add for water charges @ 1 % 5.4TOTAL 545.63

Page 448: DAR_Vol_1

Add for contractor’s profit and overheads @ 81.841,500%Cost of 0.l0q 627.47Cost of 1 kg. 62.75Say 62.75

45710.21 Providing and fixing M.S. rivets of sizes in positionCodDiscription Unit Quantity Rate Amount

Details of cost for 0.10q of rivetsMaterials-

###Rivets###Carriage quintal .1 3,500 350

Labour- tonne .01 47.29 .47###Fitter (Grade I)###Beldar special day .83 151.5 125.74###Sundries day .83 138.45 114.91

TOTAL L.S. 10.79 1 10.79Add for water charges @ 1 % 601.91TOTAL 6.02Add for contractor’s profit and overheads 607.93

91.191,500%Costof 0.l0q 699.12Cost of 1 kg. 69.91Say 69.9

10.22 Welding by gas or electric plant including transportion of plant at site etc. complete.CodDiscription Unit Quantity Rate Amount

Details of cost for one cm.###Welding by gas electric plant inc cm 1 1 1

transportation of welding plant at site etc.complete

###Sundries L.S. .26 1 .26TOTAL 1.26Add for water charges @ 1 % .01TOTAL 1.27Add for contractor’s profit and overheads .19@ 15%Cost of 1 cm. 1.46Say 1.45

### Providing and fixing bright finished brass casement window fasterners or peg stays to win-dows/ventilators with necessary welding and machine screws etc. complete.

CodDiscription Unit Quantity Rate Amount

Details for ten (10 x 0.20 = 2.00 kg)Materials-

###Brass casement window fastener each 10 26 260###Fixing charges including welding L.S 125.58 1 125.58

materials etc.###Carriage of materials L.S 1 3.64 3.64

TOTAL 389.22Add for water charges @ 1 % 3.89

@

Page 449: DAR_Vol_1

TOTAL 393.11Add for contractor’s profit and overheads @ 58.971,500%Cost of 2.00kg window fasteners 452.08Cost of 1 kg window fastener 226.04Say 226.05

45810.24 Providing and fixing 14 mm bright finished brass spring catch to steel centre hung

ventilators with necessary welding and machine screws etc. complete.

CodDiscription Unit Quantity Rate Amount

Details for tenMaterials-

###Brass casement spring catch 10 Nos. 10 109 109###Fixing charges including welding L.S 125.58 1 125.58

materials etc.###Carriage of materials L.S 3.64 1 3.64

TOTAL 238.22Add for water charges @ 1% 2.38TOTAL 240.6Add for contractor’s profit and overheads 36.09

276.69Cost of 1 window catch 27.67Say 27.65

### Steel work welded in built up section/framed work including cutting, hoisting, fixingin position and applying a priming coat of approved steel primer using steel etc. asrequired.

10.25.1 In stringers, treads, landing etc. of stair cses including use of chequered plate wher-ever required, all complete.

CodDiscription Unit Quantity Rate AmountConsider a flight of staircase of 2.8m heightwith tread and riser of 200mm & 0.60m wide.Materials-(i) Unequal angles as stringers-75x50x6mm4x12.69x5.6 = 284.25 Kg.Add wastage @ 5% =14.21 Kg.= 298.46kg. Say 2.985q(ii) unequal angles at sides 50x30x5mm2xl4x0.2x3.00=I6.8kg.Add wastage @ 5% = 0.84kg.= 17.64 kg. Say 0.176q = 3.161q

###Unequal angles quintal 3.161 3,100 9,799.1(iii) plate for tread 8mm thick14x7.5= 105.00kg+Add wastage @ 5% = 5.25kg.= 110.25kg. Say 1.103q

###Plate for tread quintal 1.103 3,400 3,750.2(iv) G. pipe for railing 40mm2xl2.69m = 25.38m+

@15% Cost of 10 window spring catch

Page 450: DAR_Vol_1

Add wastage @ 5% = 1.27m = 26.65m###G.I. Pipe for railing metre 26.65 160 4,264

(v) M.S. round bars 16mm dia.15x0.75x2xl.58 = 35.55kg.+Add wastage @ 5% = 1.78kg.= 37.33 Kg. Say O.373q

###M.S. round bars quintal .373 3,050 1,137.65Carriage of steel

###(3.I61 + 1.103+0.373)=4.637q = tonne .4637 47.29 21.93###Carriage of g.I. Pipe approx. wt. tonne .0991 47.29 4.69

459CodDiscription Unit Quantity Rate Amount

3.72x26.65=99.14kg.###Welding charge (electric) 23.20mcm 2,320 1 1,220

Labour:###Blacksmith 1st class day 1.85 151.5 280.28###Beldar day 1.25 135.25 169.06###Bandhani day .6 138.45 83.07

Applying priming coat(i) steps 2.4x 14 = 33.60sqm.+(ii) angles 4x 12.69x0.25 = 12.69sqm.+(iii) Bars and other components = 2.00 sqm.(L.S.)(A) (Rate as per item no. 13.50.3)sqm 48.29 12.65 610.87

###Sundries L.S. 1 110.89 110.89TOTAL 22,551.74Add for water charges @ 1% on all except ‘A’ 219.41TOTAL 22,771.15Add for contractor’s profit and overheads @ 3,324.0415% on all except ‘A’Cost of 5.331 qunital 26,095.19Cost per kg 48.95say 48.95

10.25 Steel work welded in built up section / framed work including cutting, hoisting, fixingin position and applying a priming coat of approved steel primer usin’g structuralsteel etc. as required. 10.25.2 In grating, frames, guard bar, ladder, railings, brackets,gates and similar works.

10.25.2 In grating, frames, guard bar, railing, brackets, gates and similar works.CodDescription Unit Quantity Rate Amount

Details of Imxlm framed guard bar grating.(i) M.S. flat 50x6 mm 2.4kg/per metre5.75x2.40 = 13.8kg. + Add wastage@ 5%= 0.69kg., Total = 14.49kg. say quintal .145 2,900 420.5

###M.S. Flat (ii) 12mm dia. Bars @ 0.89 kg/m9x1 = 9 metre @ 0.89kg/m = 8.01 kg+Addwastage @ 5% = 0.40kg. Total=8.41 kg.say 0.084q

###M.S. bar quintal .084 3,100 260.4###Carriage of steel tonne .0229 47.29 1.08###Welding charges (electric) 60cm Cm 60 1 60

Labour###Blacksmith 1st class Day .7 151.5 106.05

Page 451: DAR_Vol_1

###Beldar Day .5 135.25 67.62###Bandhani Day .25 138.45 34.61

Applying priming coat 0.65 sqm‘A’ (Rate as per item no. 13.50.3 Sqm .6 12.65 7.59###Sundries L.S. 4.55 1 4.55

Total 962.4Add for water charges @ 1% on all except ‘A’ 9.55Total 971.95Add for contractor’s profit and overheads@ 15% on all except ‘A’ 144.65Costof0.218qunital 1,116.6Cost per kg 51.22say 51.2

460### Providing and fixing hand rail of approved size by welding etc. to steel ladder rail-

ing, balcony railing and staircase railing including applying a priming coat of ap-proved steel primer.

10.26.1 M.S. tube

CodDiscription Unit Quantity Rate Amount

Details of cost for hand rail of railing of twoflights of staircase, length of hand rail =5.40mMaterials-M.S. tube 40mm nominal bore (medium) =

###5.40m @ 3.6lkg/m= 19.49kg kilogram 20.46 38 777.48Add wastage @ 5% =0.097Total = 20.46 kg.

###Carriage of tube tonne .0205 47.29 .97Priming coat 40mmdia.Tube-5.4x22/7x0.0483= 0.82 sqm

(A) Rate as per item no 13.50.3 SH Fisqm .82 12.65 10.37Welding charges (joints of hand rcm 72 1 72ballustards) 18x4x1.00 = 72cmLabour for cutting assembling & erection

###Blacksmith 1st class day .24 1,515.5 36.36###Beldar day .9 135.25 121.72###Bandhani day .12 138.45 16.61###Sundries L.S. 12.48 1 12.48

TOTAL 1,047.99Add for water charges @ 1% on all except 10.38‘A’ 1,058.37TOTAL 155.64Add for contractor’s profit and overheads @15% on all except’A’Cost of 19.49 1,214.01Cost per kg. 62.29 Say 62.3

### Providing and fixing hand rail of approved size by welding etc. to steel ladderrailing, balcony railing and staircase railing including applying a priming coat of

Page 452: DAR_Vol_1

approved steel primer.10.26.2 E.R.W. tubes.CodDiscription Unit Quantity Rate Amount

Details of cost for hand rail of railing of twoflights of staircase, length of hand rail =5.40mMaterials-

### E.R.W. tube 40mm nominal bor kilogram 18.59 53 985.23.28kg/m= 17.31kgAdd wastage @ 5% = 0.88 kgTotal = 18.59 kg

###Carriage of tube tonne .0186 47.29 .88Priming coat 40mmdia.Tube-5.4x22/7x0.0483 = 0.82 sqm

(A) Rate as per item no 13.50.3 SH Fisqm .82 12.65 10.37###Welding charges (joints of hand rcm 72 1 72

461CodDiscription Unit Quantity Rate Amount

ballustards) 18x4x1.00 = 72cmLabour for cutting assembling & erection

###Blacksmith 1st class day .24 151.5 36.36###Beldar day .9 135.25 121.72###Bandhani day .12 138.45 16.61###Sundries L.S. 12.48 1 12.48

TOTAL 1,255.69Add for water charges @ 1% on all except ‘A’ 12.45TOTAL 1,268.14 Add for contractor’s profit and overheads @ 188.6715% on all except ‘A’Cost of 17.71 Kg. 1,456.81Cost per kg. 82.23Say 82.25

### Providing and fixing hand rail of approved size by selding etc. to steel ladder rail-ing, balcony railing and staircase railing including applying a priming coat of ap-proved steel primer.

10.26.3 G.I.pipes.CodDiscription Unit Quantity Rate Amount

Details of cost for hand rail of railing of twoflights of staircase, length of hand rail =5.40mMaterials-

###G.I. pipe 40mm nominal bore = metre 5.67 160 907.2Add wastage @ 5% = 0.27mTotal = 5.67m

###Carriage of pipe (5.67m @ 3.72 tonne .0211 47.29 121.09kg)Priming coat 40mmdia.Tube-5.4x22/7x0.0483 = 0.82 sqm

(A) Rate as per item no 13.50.3 SH Fisqm .82 12.65 10.37###Welding charges (joints of hand rcm 72 1 72

ballustards) 18x4x1.00 = 72cm

Page 453: DAR_Vol_1

Labour for cutting assembling & erection###Blacksmith 1st class day .24 151.5 36.36###Beldar day .9 135.25 121.72###Bandhani day .12 138.45 16.61###Sundries L.S. 12.48 1 12.48

TOTAL 1,177.74Add for water charges @ 1% on all except ‘A’ 11.67TOTAL 1,189.41Add for contractor’s profit and overheads @ 176.8615 % on all except’A’Cost of 20.09 Kg. 1,366.27Cost per kg. 68.01Say 68

463

SUB HEAD : 11.0

FLOORING

465### Brick on edge flooring with bricks of class designation 75 including cement slurry

etc. complete in cement mortar with F.P.S. bricks:11.1.1 1:4 (1 cement: 4 coarse sand)

Page 454: DAR_Vol_1

CodDescription Unit Quantity Rate AmountDetails of cost for 10 sqm.Materials:-

###Bricks of class designation 75 1000 Nos 565 1,900 1,073.5###Carriage of bricks 1000 Nos 565 141.88 80.16

Cement mortar 1:4 cum .434 2,578.45 1,119.05(Rate asper item No.3.9)

###Cement for slurry tonne .02 4,500 90###Carriage of cement tonne .02 47.29 .95

Labour:-###Mason 2nd class Day 1.08 141.6 152.93###Beldar Day .25 135.25 33.81###Coolie Day 1.62 135.25 219.1###Bhisti Day .27 138.45 37.38

TOTAL 2,806.88Add 1% for water charges 28.07TOTAL 2,834.95Add 15% for contractor’s profit and overheads 425.24Cost of 10 sqm. 3 260.19Cost of 1 sqm. 326.02Say 326

### Brick on edge flooring with bricks of class designation 75 including cement slurryetc. complete in cement mortar with F.P.S. bricks:

11.1:6 (1 cement: 6 coarse sand)CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials:-

###Bricks of class designation 75 1000 Nos 565 1,900 1 073.50###Carriage of bricks 1000 Nos 565.00 141.88 80.16

Cement mortar 1:6 cum .434 1,987.3 862.49(Rate as per item No. 3.11)

###Cement for slurry tonne .02 4,500 90###Carriage of cement tonne .02 47.29 .95

Labour:-###Mason 2nd class Day 1.08 141.6 152.93###Beldar Day .25 135.25 33.81###Coolie Day 1.62 135.25 219.1###Bhisti Day .27 138.45 37.38

TOTAL 2,550.32Add 1% for water charges 25.5TOTAL 2 575.82Add15% for contractor’s profit and overheads 386.37Cost of 10 sqm. 2,962.19Cost of 1 sqm. 296.22Say 296.2

466### Dry brick on edge flooring in required pattern with bricks of class designation 75

on a bed of 12 mm mud mortar including filling joints with Jamuna sand (withF.P.S. bricks) complete.

CodDescription Unit Quantity Rate AmountDetails of cost for 10 sqm.Materials:-

Page 455: DAR_Vol_1

###Bricks of class designation 75 1000 Nos 645 1,900 1,225.5###Carriage of bricks 1000 Nos 645 141.88 91.51###Fine sand cum .15 320 48

Carriage of fine sand cum .15 53.21 7.98Mud Mortar cum .15 156.85 2.53(Rate as per item No. 3.18)Labour:-

###Mason 2nd class Day .9 141.6 127.44###Coolie Day 1.98 135.25 267.8###Bhisti Day .05 138.25 6.92

TOTAL 1,798.68Add 1% for water charges 17.99TOTAL 1,816.67Add 15% for contractor’s profit and overheads 272.5Cost of 10 sqm. 2,089.17Cost of 1 sqm. 208.92Say 208.9

### Cement concrete flooring 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate)finished with a floating coat of neat cement including cement slurry, but excludingthe cost of nosing of steps etc. complete.

11.40mm thick with 20mm nominal size stone aggregate.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials:-

###20mm nominal size stone ballast cum .267 700 186.9###10mm nominal size stone ballast cum .089 700 62.3###Carriage of stone ballast cum .356 53.21 18.94###Coarse sand cum .178 600 106.8###Carriage of sand cum .178 53.21 9.47###Cement for slurry tonne .17 4,500 765###Carriage of cement tonne .17 47.29 8.04

Laboun-###Mason 2nd class Day .8 141.6 113.28###Beldar Day 1.4 135.25 189.35###Bhisti Day 1.04 138.45 143.99###Mixer operator Day .03 151.5 4.542 Mixer Day .03 400 12###Sundries L.S. 40.43 1 40.43

TOTAL 1,661.04Add 1% for water charges 16.61TOTAL 1,677.65Add 15% for contractor’s profit and overheads 251.65Cost of 10 sqm. 1,929.3Cost of 1 sqm. 192.93Say 192.95

467### 52 mm thick cement concrete flooring with concrete hardener topping under layer

40 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stoneaggregate 20 mm nominal size) and top layer 12 mm thick cement hardenerconsisting of mix 1:2 (1 cement hardener mix : 2 graded stone aggregate 6 mmnominal size) by volume .hardening compound is mixed @ 2 litre per 50kg of cement

Page 456: DAR_Vol_1

or as per manufacturers specifications. This includes cost of cement slurry, butexcluding the cost of nosing of steps etc. complete.

CodDescription Unit Quantity Rate AmountDetails of cost for 10 sqm.Materials:-

###20mm ballast cum .267 700 186.9###10mm ballast cum .089 700 62.3###Carriage of stone ballast cum .356 53.21 18.94###Coarse sand cum .178 600 106.8###Carriage of coarse sand cum .178 53.21 9.47###Stone aggregate 6mm cum .115 750 86.25###Carriage of stone ballast aggreg cum .115 53.21 6.12###Cement tonne .211 4,500 949.5###Cement for slurry tonne .02 4,500 90###Carriage of cement tonne .231 47.29 10.92###Hardening compound liter 2.44 29 70.76###Carriage of hard crete L.S. 2.73 1 2.73

Laboun###Mason 2nd class Day 2.15 141.6 304.44###Beldar Day 1.6 135.25 216.4###Coolie Day 1.88 135.25 254.27###Bhisti Day .27 138.45 37.38###Sundries L.S. 53.82 1 53.82

TOTAL 2,467Add 1% for water charges 24.67TOTAL 2,491.67Add 15% for contractor’s profit and overheads 373.75Cost of 10 sqm. 2,865.42Cost of 1 sqm. 286.54Say 286.55

### 62 mm thick cement concrete flooring with concrete hardener topping under layer50 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stoneaggregate 20mm nominal size) and top layer 12mm thick cement hardenerconsisting of mix 1:2(1 cement hardener mix : 2 graded stone aggregate 6mmnominal size) by volume. Hardening compound is mixed @ 2 litre per 50kg ofcement or as per manufactures specifications. This includes cost of cement slurry,but excluding the cost of nosing of steps etc. complete.

CodDescription Unit Quantity Rate AmountDetails of cost for 10 sqm.Materials:-

###20mm ballast cum .334 700 233.8###10mm ballast cum .111 700 77.7###Carriage of ballast cum .445 53.21 23.68###Coarse sand cum .222 600 133.2###Carriage of sand cum .222 53.21 11.81###Stone aggregate 6mm cum .115 750 86.25###Carriage of stone aggregate cum .115 53.21 6.12###Cement tonne .243 4,500 1,093.5

468CodDescription Unit Quantity Rate Amount###Cement for slurry tonne .02 4,500 90

Page 457: DAR_Vol_1

###Carriage of cement tonne .263 47.29 12.44###Hardening compound litre 2.44 29 70.76###Carriage of handening compoundL.S. 2.73 1 2.73

Labour###Mason 2nd class Day 2.15 141.6 304.44###Beldar Day 1.86 135.25 251.57###Coolie Day 1.88 135.25 254.27###Bhisti Day .27 138.45 37.38###Sundries L.S. 53.82 1 53.82

TOTAL 2,743.47Add 1% for water charges 27.43TOTAL 2,770.9Add 15% for contractor’s profit and overheads 415.64Cost of 10 sqm. 3,186.54Cost of 1 sqm. 318.65Say 318.65

### Cement plaster skirting (upto 30 cm height) with cement mortar 1:3 (1 cement : 3coarse sand) finished with a floating coat of neat cement.

11.18 mm thick.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials:-Cement mortar 1:3 = 0.205 cum+Add for rounding corners = 0.030 cum= 0.235Cement mortar 1:3 (1 Cement: 3 cum .235 3,169 744.86(Rate as per item No. 3.8)

###cement for floating cost tonne .02 4,500 90###Carriage of cement tonne .02 47.29 .95

Labour:-###Mason 2nd class Day 1.88 141.6 266.21###Coolie Day 1.88 135.25 254.27###Bhisti Day .54 138.45 74.76###Sundries L.S. 19.76 1 19.76

TOTAL 1,450.81Add 1 % for water charges 14.51TOTAL 1,465.32Add 15% for contractor’s profit and overheads 219.8Cost of 10 sqm. 1,685.12Cost of 1 sqm. 168.51Say 168.5

### Cement concrete pavement with 1:2:4 (1 cement : 2 coarse sand : 4 grated stoneaggregate 20 mm nominal size) including finishing complete.

CodDescription Unit Quantity Rate AmountDetails of cost for one cum.Materials:-(A) Cement concrete 1:2:4 (Rate cum 1 3 579.10 3,579.1No. 4.2.3)Extra labour for laying in floors etc.

###Mason 2nd class Day .35 141.6 49.56

469CodDescription Unit Quantity Rate Amount

Page 458: DAR_Vol_1

###Beldar Day .18 135.25 24.34###Bhisti Day .05 138.45 6.92###Sundries L.S. 19.76 1 19.76

TOTAL 3 679.68Add for water charges @1% on all except ‘A’ 1.01TOTAL 3 680.69Add for contractor’s profit and overheads @ 15.2415% on all except ‘A’Cost of 1 Cum. 3 695.93Say 3 695.95

### Extra for making chequers of approved pattern on cement concrete floors, steps,landing, pavements etc.

CodDescription Unit Quantity Rate AmountDetails of cost for 10 sqm.Labour:-

###Mason 2nd class Day .36 141.6 50.98###Beldar Day .36 135.25 48.69###Chequered plate etc. L.S. 13.52 1 13.52

TOTAL 113.19Add 1% for water charges 1.13TOTAL 114.32Add 15% contractor’s profit and overheads 17.15Cost of 10 sqm. 131.47Cost of 1 sqm. 13.15Say 13.15

### 40 mm thick marble chips flooring rubbed and polished to granolithic finish, underlayer 34 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stoneaggregate 12.5mm nominal size) and top layer 6mm thick with white, black,chocolate, grey, yellow or green marble chips of sizes from lmm to 4mm nominalsize laid in cement marble powder mix 3:1 (3 cement: 1 marble powder) by weightin proportion of 4:7 (4 cement marble powder mix : 7 marble chips) by volumeincluding cement slurry etc. complete :

11.Dark shade pigment with ordinary cement.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqmMaterialsFor under layer of 34mm thick

###Stone Aggregate (Single size): 1 cum .227 700 158.9nominal size

###Stone Aggregate (Single size): 1 cum .076 700 53.2nominal size

###Carriage of Stone aggregate be cum .303 53.21 16.12nominal size

###Coarse sand (zone III) cum .151 600 90.6###Carriage of Coarse sand cum .151 53.21 8.03###Cement tonne .109 4,500 490.5###Cement for slurry tonne .02 4,500 90###Carriage of Cement tonne .129 47.29 6.1

For top layer 6mm thick###Marble chips quintal .872 115 100.28###Carriage of Marble chips cum .051 53.21 2.71

Page 459: DAR_Vol_1

470CodDescription Unit Quantity Rate Amount###Portland Cement tonne .0405 4,500 182.25###Carriage of white Cement tonne .0405 47.29 1.92###Marble powder cum .007 800 5.6###Dark shade pigmeny/3.5kg/ 50k kilogram 2.84 42 119.28

= 40.5x3.5/50=2.84kg.###Carriage of pigment & marble po L.S. 3.64 1 3.64

Labour:-###Mason 2nd class Day 1.79 141.6 253.46###Beldar Day 1.99 135.25 269.15###Bhisti Day 1.04 138.45 143.99###Skilled Beldar (for floor rubbing eDay 1 138.45 138.45###Mixer operator Day .03 151.5 4.542 Mixer Day .03 400 1213 Machine for rubbing of floors Day 1.6 200 320###Sundries L.S. 161.46 1 161.46

Total 2,632.18Add for water charges @ 1% on ‘A’ 26.32Total 2,658.5Add for contractor’s profit and overheads @ 398.7815% on A+BCost of 10 sqm 3,057.28Cost of 1 sqm 305.73Say 305.75

### 40 mm thick marble chips flooring rubbed and polished to granolithic finish, underlayer 34 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stoneaggregate 12.5mm nominal size) and top layer 6mm thick with white, black,chocolate, grey, yellow or green marble chips of sizes from lmm to 4mm nominalsize laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weightin proportion of 4:7 (4 cement marble powder mix : 7 marble chips) by volumeincluding cement slurry etc. complete :

11.Light shade pigment with white cement.CodDescription Unit Quantity Rate Amount

Details of cost for 10.0 sqm(A)Rate as per item no 11.9.1 of sqm 10 305.75 3,057.5Add difference of cost due to using light shadepigment instead of dark shade pigment

###Add for light shade pigment kilogram 2.84 65 184.6###Deduct for dark shade pigment kilogram 2.84 42 (-)119.28

Addd difference of cost due to using whitecement instead of grey cement

###Add for White Cement tonne .0405 9,700 392.85###Deduct for grey cement tonne .0405 4,500 (-)182.25

Total 3,333.62Add 1 % for water charges except on ‘A’ 2.76Total 3,336.38Add 15%-for contractor’s profit and overheadexcept on ‘A’ 41.39Cost of 10 sqm 3,377.77Cost of 1 sqm 337.78Say 337.8

Page 460: DAR_Vol_1

471### 40 mm thick marble chips flooring rubbed and polished to granolithic finish, under

layer 34 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stoneaggregate 12.5mm nominal size) and top layer 6mm thick with white, black,chocolate, grey, yellow or green marble chips of sizes from lmm to 4mm nominalsize laid in cement marble powder mix 3:1 (3 cement: 1 marble powder) by weightin proportion of 4:7 (4 cement marble powder mix : 7 marble chips) by volumeincluding cement slurry etc. complete :

11.Medium shade pigment with 50% white cement and 50% ordinary cement.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm(A) Rate as per item no 11.9.1 of SH: Flooring sqm 10 305.75 3,057.5Add difference of cost due to using light shadepigment instead of dark shade pigment

###Green or blue medium shade pi kilogram 2.84 45 127.8###Deduct for dark shade pigment kilogram 2.84 42 (-) 119.28

Add difference of cost due to using whiteCement instead of grey cement

###Add for White Cement tonne .0203 9,700 196.91###Deduct for grey cement tonne .0203 4,500 (-) 91.35

Total 3,592.84Add 1 % for water charges except on ‘A’ 1.14Total 3,058.64Add 15% for contractor’s profit and overhead 17.28except on ‘A’Cost of 10 sqm 3,075.92Cost of 1 sqm 307.59Say 307.6

### 40 mm thick marble chips flooring rubbed and polished to granolithic finish, underlayer 34 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stoneaggregate 12.5mm nominal size) and top layer 6mm thick with white, black,chocolate, grey, yellow or green marble chips of sizes from lmm to 4mm nominalsize laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weightin proportion of 4:7 (4 cement marble powder mix : 7 marble chips) by volumeincluding cement slurry etc. complete :

11.White cement without any pigment.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqmMaterialsFor under layer of 34mm thick

###Stone Aggregate (Single size): 1 cum .227 700 158.9nominal size

###Stone Aggregate (Single size): 1 cum .076 700 53.2nominal size

###Carriage of Stone aggregate be cum .303 53.21 16.12nominal size

###Coarse sand (zone III) cum .151 600 90.6###Carriage of Coarse sand cum .151 53.21 8.03###Cement tonne .109 4,500 490.5###Cement for slurry tonne .02 4,500 90###Carriage of Cement tonne .129 47.29 6.1

Page 461: DAR_Vol_1

472CodDescription Unit Quantity Rate Amount

For top layer 6mm thick###Marble chips quintal .958 115 110.17###Carriage of Marble chips cum .056 53.21 2.98###White Cement tonne .0405 9,700 392.85###Carriage of white Cement tonne .0405 47.29 1.92###Marble powder cum .007 800 5.6

Labour:-###Mason 2nd class Day 1.79 141.6 253.46###Beldar Day 1.99 135.25 269.15###Bhisti Day 1.04 138.45 143.99###Skilled Beldar (for floor rubbing eDay 1 138.45 138.45###Mixer operator Day .03 151.5 4.542 Mixer Day .03 400 1213 Machine for rubbing of floors Day 1.6 200 320###Sundries L.S. 161.46 1 161.46

Total 2 730.02Add for water charges @ 1 % 27.3Total 2 757.32Add for contractor’s profit and overheads @)15% 413.6Cost of 10 sqm 3 170.92Cost of 1 sqm 317.09Say 317.1

### 40 mm thick marble chips flooring rubbed and polished to granolithic finish, underlayer 34 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stoneaggregate 12.5mm nominal size) and top layer 6mm thick with white, black,chocolate, grey, yellow or green marble chips of sizes from lmm to 4mm nominalsize laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weightin proportion of 4:7 (4 cement marble powder mix : 7 marble chips) by volumeincluding cement slurry etc. complete :

11.Light shade pigment with ordinary cement.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqmit(A) Rate as per item no 11.9.1 of sqm 10 305.75 3,057.5Add difference of cost due to using lightshade pigment instead of dark shade pigment

###Add for light shade pigment kilogram 2.84 65 184.6Deduct for dark shade pigment kilogram 2.84 42 (-) 119.28Total 3,122.82Add 1% for water charges Except on A: .65Total 3,123.47Add 15%for contractor’s profit and overheads 9.9Except on A:Cost of 10 sqm 3,133.37Cost of 1 sqm 313.33Say 313.35

Page 462: DAR_Vol_1

473### 40 mm thick marble chips flooring rubbed and polished to granolithic finish, under

layer 34 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stoneaggregate 12.5mm nominal size) and top layer 6mm thick with white, black,chocolate, grey, yellow or green marble chips of sizes from 1 mm to 4mm nominalsize laid in cement marble powder mix 3:1 (3 cement: 1 marble powder) by weightin proportion of 4:7 (4 cement marble powder mix : 7

11.Ordinary cement without any pigment.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm(A)Rate as per item no 11.9.1 of sqm 10 305.75 3,057.5less cost of dark shade pigment

###Deduct for dark shade pigment kilogram 2.84 42 -119.28###Deduct for carriage of pigment L.S. 7.38 1 -7.38

Total 2,930.84Add 1% for water charges except on ‘A’ -1.27Total 2,929.57Add 15% for contractor’s profit and overheads -19.19except on ‘A’Cost of 10 sqm 2,910.38Cost of 1 sqm 291.04Say 291.05

11.10 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, underlayer 3lmm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stoneaggregate 12.5mm nominal size) and top layer 9mm thick with white, black, chocolate,grey, yellow or green marble chips of sizes from 4mm to 7mm nominal size laid incement marble powder mix 3:1 (3 cement: 1 marble powder) by weight in proportionof 4:7 (4 cement marble powder : 7 marble chips) by volume including cement slurryetc. complete.

11.10.1 Dark shade pigment with Ordinary cement.CodDiscription Unit Quantity Rate Amount

Details of cost for 10 sqmMaterialFor under layer of 31mm thick

###Stone Aggregate (Single size): cum .21 700 147nominal size

###Stone Aggregate (Single size): 1 cum .07 700 49nominal size

###Carriage of Stone aggregate be cum .28 53.21 14.9nominal size

###Coarse sand (zone III) cum .14 600 84###Carriage of Coarse sand cum .14 53.21 7.45###Cement tonne .1005 4 500.00 452.25###Cement for slurry tonne .02 4 500.00 90###Carriage of Cement tonne .1205 47.29 5.7

For top layer 9mm thick###Marble chips large size above quintal 1.4 1,115 161

black###Carriage of Marble chips cum .082 53.21 4.36###Portland Cement tonne .0578 4 500.00 260.1###Carriage of white Cement tonne .0578 47.29 2.73###Marble powder - cum .012 800 9.6

Page 463: DAR_Vol_1

474CodDescription Unit Quantity Rate Amount

###Dark shade pigment 3.5kg/ 50kg kilogram 4.05 42 170.01 = 57.80x3.5/50=4.05kg.

###Carriage of pigment & marble po L.S. 5.46 1 5.46Labour-

###Mason 2nd class Day 1.79 141.6 253.46###Beldar Day 1.99 135.25 269.15###Bhisti Day 1.04 138.45 143.99###Skilled Beldar (for floor rubbing eDay 1 138.45 138.45### Mixer operator Day .03 151.5 4.542 Mixer Day .03 400 1213 Machine for rubbing of floors Day 1.6 200 320###Sundries L.S. 134.55 1 134.55

Total 2,613.79Add for water charges @ 1% 26.14Total 2,639.93Add for contractor’s profit and overheads @ 395.991,500%Cost of 10 sqm 3,035.92Cost of 1 sqm 303.59Say 303.6

11.10 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, underlayer 31mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stoneaggregate 12.5mm nominal size) and top layer 9mm thick with white, black, chocolate,grey, yellow or green marble chips of sizes from 4mm to 7mm nominal size laid incement marble powder mix 3:1 (3 cement: 1 marble powder) by weight in proportionof 4:7 (4 cement marble powder : 7 marble chips) by volume including cement slurryetc. complete.

11.10.2 Light shade pigment with white cement.CodDiscription Unit Quantity Rate Amount

Details of cost for 10 sqm(A) Rate as per item no 11.10.1SHsqm 10 303.6 3,036Add difference of cost due to using light shadepigment instead of dark shade pigment

###Add for light shade pigment kilogram 4.05 65 263.25###Deduct for dark shade pigment kilogram 4.05 42 (-)170.10

Add difference of cost due to using whitecement instead of grey cement

###Add for White Cement tonne .0578 9 700.00 560.66###Deduct for grey cement tonne .0578 4 500.00 (-) 260.10

Total 3,429.71Add 1 % for water charges except on ‘A’ 3.94Total 3,433.65Add 15% for contractor’s profit and overhead 59.06except on ‘A’Cost of 10 sqm 3,492.71Cost of 1 sqm 349.27Say 349.25

Page 464: DAR_Vol_1

47511.10 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under

layer 31 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stoneaggregate 12.5mm nominal size) and top layer 9mm thick with white, black, chocolate,grey, yellow or green marble chips of sizes from 4mm to 7mm nominal size laid incement marble powder mix 3:1 (3 cement: 1 marble powder) by weight in proportionof 4:7 (4 cement marble powder : 7 marble chips) by volume including cement slurryetc. complete.

11.10.3 Medium shade pigment with 50% white cement and 50% ordinary cement.

CodDiscription Unit Quantity Rate

Details of cost for 10 sqm(A) Rate as per item no11.10.1 of SH: Flooring sqm 10 303.6Add difference of cost due to using light shadepigment instead of dark shade pigment

###Green or blue medium shade pigment kilogram 4.05 45###Deduct for dark shade pigment kilogram 4.05 42

Add difference of cost due to using whitecement instead of grey cement

###Add for White Cement tonne .0289 9,700###Deduct for grey cement tonne .0289 4,500

TotalAdd 1% for water charges except on ‘A’TotalAdd15% tor contractor’s profit and overheadexcept on ‘A’Cost of 10 sqmCost of 1 sqmSay

11.10 10 40 mm thick marble chips flooring, rubbed and polished to granolithic finish,under layer 31 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 gradedstone aggregate 12.5mm nominal size) and top layer 9mm thick with white, black,chocolate, grey, yellow or green marble chips of sizes from 4mm to 7mm nominalsize laid in cement marble powder mix 3:1 (3 cement: 1 marble powder) by weight inproportion of 4:7 (4 cement marble powder : 7 marble chips) by volume includingcement slurry etc. complete.

11.10.4 White cement without any pigment.CodDiscription Unit Quantity Rate

Details of cost for 10 sqmMaterialsFor under layer of 31mm thick

###Stone Aggregate (Single size): 12.5 mm cum .21 700nominal size

###Stone Aggregate (Single size): 10 mm cum .07 700nominal size

###Carriage of Stone aggregate below 40 mm cum .28 53.21nominal size

###Coarse sand (zone III) cum .14 600###Carriage of Coarse sand cum .14 53.21###Cement tonne .1005 4,500###Cement for slurry tonne .02 4,500

Page 465: DAR_Vol_1

476CodDescription Unit Quantity Rate Amount###Carriage of Cement tonne .1205 47.29

For top layer 9mm thick###Marble chips large size above 4 quintal 1.4 115 161

White &###black cum .082 53.21###Carriage of Marble chips tonne .0578 9,700 560.66###White Cement tonne .0578 47.29###Carriage of white Cement cum .012 800

Marble powder###Labour:- Day 1.79 141.6 253.46###Mason 2nd class Day 1.99 135.25 269.15###Beldar Day 1.04 138.45 143.99###Bhisti Day 1 138.45 138.45###Skilled Beldar (for floor rubbing eDay .03 151.52 Mixer operator Day .03 40013 Mixer Day 1.6 200 320###Machine for rubbing of floors L.S. 161.46 1 161.46

Sundries 2 891.70TotalAdd for water charges @ 1% 2 920.62Total Add for contractor’s profit 438.09andoverheads @ 15% 3 358.71Cost of 10 sqm 335.87Cost of 1 sqm 335.85Say

11.10 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under layer 31mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate 12.5mm nominal size) and top layer 9mm thick with white, black,chocolate, grey, yellow or green marble chips of sizes from 4mm to 7mm nominalsize laid in cement marble powder mix 3:1 (3 cement: 1 marble powder) by weight inproportion of 4:7 (4 cement marble powder : 7 marble chips) by volume includingcement slurry etc. complete.

11.10.5 Light shade pigment with ordinary cement.CodDiscription Unit Quantity Rate Amount

Details of cost for 10 sqm(A) Rate as per item no. 11.10.1 osqm 10 303.6 3,036Add difference of cost due to using lightshade pigment instead of dark shade pigment

###Add for light shade pigment kilogram 2.84 65 184.6###Deduct for dark shade pigment kilogram 2.84 42 (-)119.28

Total , 3,101.32Add 1% for water charges expect on ‘A’Total 3,101.97Add 15% for contractor’s profit and overheadsCost of 10 sqm 3,111.87cost of 1 sqm 311.19Say 311.2

Page 466: DAR_Vol_1

47711.10 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under layer

31 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate12.5mm nominal size) and top layer 9mm thick with white, black, chocolate, grey, yellowor green marble chips of sizes from 4mm to 7mm nominal size laid in cement marblepowder mix 3:1 (3 cement: 1 marble powder) by weight in proportion of 4:7 (4 cementmarble powder : 7 marble chips) by volume including cement slurry etc. complete.

11.10.6 Ordinary cement without any pigment.

Code Discription Unit Quantity Rate AmountDetails of cost for 10 sqmMaterialsFor under layer 31mm thick

###Stone Aggregate (Single size): 12.5 mm cum .21 700 147nominal size

###Stone Aggregate (Single size): 10 mm cum .07 700 49nominal size

###Carriage of Stone aggregate below 40 mm cum .28 53.21 14.9nominal size

###Coarse sand (zone III) cum .14 600 84###Carriage of Coarse sand cum .14 53.21 7.45###Cement tonne .1005 4,500 452.25###Cement for slurry tonne .02 4,500 90###Carriage of Cement tonne .1205 47.29 5.7

For top layer 9mm thick###Marble chips large size above 4 mm White quintal 1.41 115 161

black###Carriage of Marble chips cum .082 53.21 4.36###White Cement tonne .0578 9,700 560.66###Carriage of White Cement tonne .0578 47.29 2.73###Marble powder cum .012 800 9.6

Labour:- 253.46###Mason 2nd class Day 1.79 141.6 269.15###Beldar Day 1.99 135.25 143.99###Bhisti Day 1.04 138.45 138.45###Skilled Beldar (for floor rubbing etc.) Day 1 138.45 4.54###Mixer operator Day .03 151.5 122 Mixer Day .03 400 32013 Machine for rubbing of floors Day 1.6 200 134.55###Sundries L.S. 1 2,564.23

Total 25.64Add for water charges @ 1 % 2,589.87Total 38.48Add for contractor’s profit and overheads @ 15%Cost of 10 sqm 2,978.35Cost of 1 sqm 297.84Say 297.85

478

Page 467: DAR_Vol_1

### 40 mm thick marble chips flooring, rubbed and polished to granolithic finish,under layer 28 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4graded stone aggregate 12.5mm nominal size) and top layer 12mm thick withwhite, black, chocolate, grey yellow or green marble chips of sizes from 7mm to10mm nominal size laid in cement marble powder mix 3:1 (3 cement: 1 marblepowder) by weight in proportion of 2:3 (2 cement marble powder mix : 3 marblechips) by volume including cement slurry etc. complete :

11.11.1 Dark shade pigment with ordinary cement.

CodDiscriptionUnit Quantity Rate Amount

Details of cost for 10 sqm.Materials-For under layer 0128mm thick

###12.5mm stocum .19 700 133###10mm stoncum .06 700 42###Carriage of cum .25 53.21 13.3###Coarse san cum .125 600 75###Carriage of cum .125 53.21 6.65###Cement tonne .0897 4,500 403.65###Cement for tonne .02 4,500 90###Carriage o tonne .1097 47.29 5.19

For top layer 12mm thick###Marble chi quintal 1.734 115 199.41###Carriage of cum .102 53.21 5.43###Cement tonne .081 9,700 364.5###Carriage o tonne .081 47.29 3.83###Marble po cum .017 800 13.6###Dark shadekilogram 5.67 42 238.14

= 81x3.5/50=5.67kg###Carriage o L.S 6.24 1 6.24

Labour:-###Mason 2nd Day 1.79 141.6 253.46###Beldar Day 1.99 135.25 269.15###Bhisti Day 1.04 138.45 143.99###Beldar for Day 1 138.45 138.45

Rate)###Mixer oper Day .03 151.5 4.542 Mixer Day .03 400 1213 Machine Day 1.6 200 320###Sundries L.S. 156.13 1 156.13

TOTAL 2,897.66Add 1% for water charges 28.98TOTAL 2,926.64Add 10% for contractor’s profit and overheads 439Cost of 10 sqm. 3,365.64Cost of 1 sqm. 336.56Say 336.55

47911.11 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under layer

28 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate

Page 468: DAR_Vol_1

12.5mm nominal size) and top layer 12mm thick with white, black, chocolate, grey yellowor green marble chips of sizes from 7mm to 10mm nominal size laid in cement marblepowder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 2:3 (2 cementmarble powder mix : 3 marble chips) by volume including cement slurry etc. complete :

11.11.2 Light shade pigment with white cement.CodDiscription Unit Quantity Rate Amount

Details of cost for 10 sqm.Cost same as per item No 11.11. sqm 10 336.55 3 365.50(A) Add difference of cost due to using light shadepigment instead of dark shade pigment

###Add for Light shade pigment kilogram 5.67 65 368.55###Deduct for Dark shade pigment kilogram 5.67 42 (-)238.14

Add Difference of cost due to using whitecement instead of grey cement

###Add for White cement tonne .081 9,700 785.7###Deduct for Grey cement tonne .081 4,500 (-)364.50

TOTAL 3,917.11Add 1 % for water charges except on ‘A’ 5.52TOTAL 3,922.63Add 15 %Tor contractor’s profit and overheads 83.57-except on ‘A’Cost of 10 sqm. 4,006.2Cost of 1 sqm. 400.62Say 400.6

11.11 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under layer28 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate12.5mm nominal size) and top layer 12mm thick with white, black, chocolate, grey yellowor green marble chips of sizes from 7mm to 10mm nominal size laid in cement marblepowder mix 3:1 (3 cement: 1 marble powder) by weight in proportion of 2:3 (2 cementmarble powder mix : 3 marble chips) by volume including cement slurry etc. complete :

11.11.3 Medium shade pigment with 50% white cement and 50% ordinary cement.CodDiscription Unit Quantity Rate Amount

Details of cost for 10 sqm.(A) Cost same as per item No 11. sqm 10 336.55 3 365.50Add difference of cost due to using Mediumshade pigment instead of dark shade pigment

###Add for Medium shade pigment kilogram 5.67 45 255.15###Deduct for Dark shade pigment kilogram 5.67 42 (-)238.14

Add Difference of cost due to using whitecement instead of grey cement

###Add for White cement tonne .0405 9,700 392.85###Deduct for Grey cement tonne .0405 4,500 (-)182.25

TOTAL 3 593.11(B) Add 1% for water charges except on ‘A’ 2.28TOTAL 3 595.39Add 15% for contractor’s profit and 34.48overheadsexcept on ‘A’ 3 629.87Cost of 10 sqm. 362.99Cost of 1 sqm. 363Say

Page 469: DAR_Vol_1

480### 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under layer

28 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate12.5mm nominal size) and top layer 12mm thick with white, black, chocolate, grey yellowor green marble chips of sizes from 7mm to 10mm nominal size laid in cement marblepowder mix 3:1 (3 cement: 1 marble powder) by weight in proportion of 2:3 (2 cementmarble powder mix : 3 marble chips) by volume including cement slurry etc. complete :

11.11.4 White cement without any pigment.Code Discription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-For under layer of 128mm thick

###12.5mm stone aggregate cum .19 700 133###10mm stone aggregate cum .06 700 42###Carriage of stone aggregate cum .25 53.21 13.3###Coarse sand cum .125 600 75###Carriage of coarse sand cum .125 53.21 6.65###Cement tonne .0897 4,500 403.65###Cement for slurry tonne .02 4,500 90###Carriage of cement tonne .1097 47.29 5.19

For top layer 12mm thick###Marble chips 7mm to 10mm sizequintal 1.916 115 220.34###Carriage of marble chips cum .1128 53.21 6###Cement tonne .081 9,700 785.7###Carriage of cement tonne .081 47.29 3.83###Marble powder cum .017 800 13.6

Labour:-###Mason 2nd class Day 1.79 141.6 253.46###Beldar Day 1.99 135.25 269.15###Bhisti Day 1.04 138.45 143.99###Beldar for rubbing and polishing Day 1 138.45 138.45

Rate)###Mixer operator Day .03 151.5 4.542 Mixer Day .03 400 1213 Machine Day 1.6 200 320###Sundries L.S. 134.55 1 134.55

TOTAL 3,074.4Add 1% for water charges 30.74TOTAL 3,105.14Add 15% for contractor’s profit and overheads 465.77Cost of 10 sqm. 3,570.91Cost of 1 sqm. 357.09Say 357.1

### 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, underlayer 28 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stoneaggregate 12.5mm nominal size) and top layer 12mm thick with white, black,chocolate, grey yellow or green marble chips of sizes from 7mm to 10mm nominalsize laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weightin proportion of 2:3 (2 cement marble powder mix : 3 marble chips) by volumeincluding cement slurry etc. complete :

11.11.5 Light shade pigment with ordinary cement.Code Discription Unit Quantity Rate Amount

Details of cost for 10 sqm.(A) Cost same as per ite sqm 10 336.55 3 365.5

Add difference of cost due to using Light

Page 470: DAR_Vol_1

481CodDescription Unit Quantity Rate Amount

shade pigment instead of dark shade###pigment kilogram 5.67 65 368.55###Add for Light shade pigment kilogram 5.67 42 (-)238.14

Deduct for Dark shade pigment 3,495.91TOTAL 1.3Add 1% for water charges except on ‘A’ 3,497.21TOTAL 15 19.76Add 15% for contractor’s profit andoverheadsexcept on ‘A’Cost of 10 sqm. 3,516.97Cost of 1 sqm. 351.7Say 351.7

### 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under layer28 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate12.5mm nominal size) and top layer 12mm thick with white, black, chocolate, grey yellowor green marble chips of sizes from 7mm to 10mm nominal size laid in cement marblepowder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 2:3 (2 cementmarble powder mix : 3 marble chips) by volume including cement slurry etc. complete :

11.11.6 Ordinary cement without any pigment.CodDiscription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-For under layer 28mm thick

###12.5mm stone aggregate cum .19 700 133###10mm stone aggregate cum .06 700 42###Carriage of stone aggregate cum .25 53.21 13.3###Coarse sand cum .125 600 75###Carriage of coarse sand cum .125 53.21 6.65###Cement tonne .0897 4,500 403.65###Cement for slurry tonne .02 4,500 90###Carriage of cement tonne .1097 47.29 5.19

For top layer 12mm thick###Marble chips 7mm to 10mm sizequintal 1.916 115 220.34###Carriage of marble chips cum .1128 53.21 6###Cement tonne .081 4,500 364.5###Carriage of cement tonne .081 47.29 3.83###Marble powder cum .017 800 13.6

Labour:-###Mason 2nd class Day 1.79 141.6 253.46###Beldar Day 1.99 135.25 269.15###Bhisti Day 1.04 138.45 143.99###Beldar for rubbing and polishing Day 1 138.45 138.45

Rate)###Mixer operator Day .03 151.5 4.542 Mixer Day .03 400 1213 Machine Day 1.6 200 320###Sundries L.S. 134.55 1 134.55

TOTAL 2,653.2

Page 471: DAR_Vol_1

Add 1% for water charges 26.53TOTAL 2,679.73Add 15% for contractor’s profit and overheads 401.96Cost of 10 sqm. 3,081.69Cost of 1 sqm. 308.17Say 308.15

482### Marble chips skirting (upto 30 cm height) rubbed and polished to granolithic

finish, top layer 6 mm thick with white, black, chocolate, grey, yellow or greenmarble chips of sizes from smallest to 4 mm nominal size laid in cement marblepowder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4cement marble powder mix : 7 marble chips) by volume :

11.18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement: 3coarse sand):

11.12.1.1 Dark shade pigment with ordinary cement.CodDiscription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-For under layer of 12mm thickCement mortar 1:3 = 0.144\"+ Extcum .174 3,169.6 551.51rounding = 0.03 =0.174 cum (Rate as per item No.3.8)Top layer 6mm thick

###Marble chips quintal .872 115 100.28###Carriage of marble chips cum .051 53.21###Cement tonne .0405 4,500 182.25###Carriage of cement tonne .0405 47.29###Marble powder cum .007 800###Dark shade pigment @ 3.5kg/50kilogram 2.84 42 119.28

=40.5x3.5/50=2.84kg.###Carriage of pigment & marble po L.S. 3.64 1

Labour:-###Mason 2nd class Day 3 141.6 424.8###Beldar Day 3 135.25 405.75###Bhisti Day 1 138.45 138.45###Beldar for rubbing and polishing Day 7 138.45 969.15

Rate)###Sundries L.S. 201.89 1 201.89

TOTAL 3,107.23Add 1% for water chargesTOTAL 3,138.3Add 15% for contractor’s profit and overheads 470.74Cost of 10 sqm. 3 609.04Cost of 1 sqm. 360.9Say 360.9

### Marble chips skirting (upto 30 cm height) rubbed and polished to granolithicfinish, top layer 6 mm thick with white, black, chocolate, grey, yellow or greenmarble chips of sizes from smallest to 4 mm nominal size laid in cement marblepowder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4cement marble powder mix : 7 marble chips) by volume :

Page 472: DAR_Vol_1

11.18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement: 3coarse sand):

11.12.1.2 Light shade pigment with white cement.CodDiscription Unit Quantity Rate Amount

(A) Details of cost for 10 sqm. Cost same as per item No. 11.12 cum 10 360.9 3 609.00Add difference of cost due to using light shadepigment instead of dark shade pigment

###Add for Light shade pigment kilogram 2.84 65 184.6###Deduct for Dark shade pigment kilogram 2.84 42 (-)119.28

483CodDescription Unit Quantity Rate Amount

Add Difference of cost due to using whitecement instead of grey cement

###Add for White cement tonne .0405 9 700.00 392.85###Deduct for Grey cement tonne .0405 4 500.00 (-)182.25

TOTAL 3,884.92Add 1 % for water charges except on ‘A’ 2.76TOTAL 3,887.68Add 10% for contractor’s profit and overheads 41.8except on ‘A’Cost of 15% 3,929.48Cost of 1 sqm. 392.95Say 392.95

### Marble chips skirting (upto 30 cm height) rubbed and polished togranolithic finish, top layer 6 mm thick with white, black, chocolate, grey,yellow or green marble chips of sizes from smallest to 4 mm nominalsize laid in cement marble powder mix 3:1 (3 cement : 1 marble powder)by weight in proportion of 4:7 (4 cement marble powder mix : 7 marblechips) by volume :

11.18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement: 3coarse sand):

11.12.1.2 Light shade pigment with white cement.CodDiscription Unit Quantity Rate Amount

Details of cost for 10 sqm.(A) Cost same as per item No.11. cum 10 360.9 3 609.00 Add difference of cost due to using mediumshade pigment instead of dark shade pigment

###Add for Medium shade pigment kilogram 2.84 45 127.8###deduct for Dark shade pigment kilogram 2.84 42 (-)119.28

Add Difference of cost due to using white cementinstead of grey cement

###Add for White cement tonne .0203 9,700 196.91###Deduct for Grey cement tonne .0203 4,500 (-)91.35

TOTAL 3,723.08Add 1 % for water charges except on ‘A’ 1.14 TOTAL 3,724.22Add 10% for contractor’s profit and overheads 17.28

Page 473: DAR_Vol_1

except on ‘A”Cost of 15% 3,741.5Cost of 1 sqm. 374.15Say 374.15

484### Marble chips skirting (upto 30 cm height) rubbed and polished to granolithic

finish, top layer 6 mm thick with white, black, chocolate, grey, yellow or greenmarble chips of sizes from smallest to 4 mm nominal size laid in cement marblepowder mix 3:1 (3 cement: 1 marble powder) by weight in proportion of 4:7 (4cement marble powder mix : 7 marble chips) by volume :

11.18 mm thick with under layer 12 mm thick in cement plaster 1:3(1 cement: 3coarse sand):

11.12.1.4 White cement without any pigment.CodDiscription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-For under layer of 12mm thickCement mortar 1:3 = 0.144+Extracum .174 3,169.6 551.51rounding = 0.03 =0.174 (Rate as per item no. 3.8)Top layer 6mm thick

###Marble chips quintal .958 115 110.17###Carriage of marble chips cum .056 53.21 2.98###White cement tonne .0405 9 700.00 392.85###Carriage of white cement tonne .0405 47.29 1.92###Marble powder cum .007 800 5.6

Labour:-###Mason 2nd class Day 3 141.6 424.8###Beldar Day 3 135.25 405.75###Bhisti Day 1 138.45 138.45###Beldar for rubbing and polishing Day 7 138.45 969.15

Rate)###Sundries L.S 201.89 1 201.89

TOTAL 3 205.07Add 1 % for water charges 32.05TOTAL 3 237.12Add 15% for contractor’s profit and overheads 485.57Cost of 10 sqm. 3 722.69Cost of 1 sqm. 372.27Say 372.25

### Marble chips skirting (upto 30 cm height) rubbed and polished to granolithicfinish, top layer 6 mm thick with white, black, chocolate, grey, yellow or greenmarble chips of sizes from smallest to 4 mm nominal size laid in cement marblepowder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4cement marble powder mix : 7 marble chips) by volume :

11.12.1 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement: 3coarse sand):

11.12.1.5 Light shade pigment with ordinary cement.CodDiscription Unit Quantity Rate Amount

Details of cost for 10 sqm.

Page 474: DAR_Vol_1

(A) Cost same as per item No 11. sqm 10 360.9 3 609.00Add difference of cost due to using Lightshade pigment instead of dark shade pigment

###Add for Light shade pigment kilogram 2.84 65 184.6###Deduct for Dark shade pigment L.S. 2.84 42 (-)119.28

TOTAL 3,674.32Add 1 % for water charges except on ‘A’ .65TOTAL 3,674.97Add 40% for contractor’s profit and overheads 9.9except on ‘A’Cost of 15% 3,684.87Cost of 1 sqm. 368.49Say 368.5

485### Marble chips skirting (upto 30 cm height) rubbed and polished to granolithic

finish, top layer 6 mm thick with white, black, chocolate, grey, yellow or greenmarble chips of sizes from smallest to 4 mm nominal size laid in cement marblepowder mix 3:1 (3 cement: 1 marble powder) by weight in proportion of 4:7 (4cement marble powder mix : 7 marble chips) by volume :

11.12.1 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement: 3coarse sand):

11.12.1.6 Ordinary cement without any pigment.CodDiscription Unit Quantity Rate Amount

Details of cost for 10 sqm.(A) Cost same as per item No. 11 sqm 10 360.9 3 609.00Less cost of dark shade pigment

###Deduct for dark shade pigment kilogram 2.84 42 (-)119.28###Deduct for Carriage of pigment L.S. 7.38 1 7.38

TOTAL 3,482.34Add 1% for water charges except on ‘A’ 1.27TOTAL 3,481.07Add 15% for contractor’s profit and overheads 19.19except on ‘A’Cost of 15% sqm 3,461.88Cost of 1 sqm. 346.19Say 346.2

### Providing and fixing glass strips in joints of terrazo/ cement concrete floors.11.40 mm wide and 4 mm thick.CodDiscription Unit Quantity Rate Amount

Details of cost for 10 metre lengthMaterials-Glass strips = 10mAdd 10% for wastage = 1mTotal = 11m

###Glass strips metre 11 6 66###Carriage of glass L.S 2.73 1 2.73

Labour-###Mason 2nd class Day .25 141.6 35.4###Beldar Day .25 135.25 33.81###Sundries L.S 13.52 1 13.52

TOTAL 151.46

Page 475: DAR_Vol_1

Add 1% for water charges 1.51TOTAL 152.97Add 15% for contractor’s profit and overheads 22.95Cost of 10 meter 175.92Cost of 1 meter 17.59Say 17.6

### Extra for laying terrazo flooring on staircase treads not exceeding 30 cm in widthincluding cost of forming, nosing etc.

CodDiscription Unit Quantity Rate AmountDetails of cost for 10 sqm.Labour-

###Mason 2nd class Day .3 141.6 42.48###Beldar Day .3 135.25 40.57###Coolie Day .3 135.25 40.57

TOTAL 123.62Add 1 % for water charges 1.24

486CodDescription Unit Quantity Rate Amount

TOTAL 124.86Add 15% for contractor’s profit and overheads 18.73Cost of 10 Sqm. 143.59Cost of 1sqm, 14.36Say 14.35

### Crazy marble stone flooring including filling the gaps with light shade pigment with whitecement marble powder mixture (3 parts of white cement : 1 part of marble powder) byweight in proportion of 4:7 (4 cement marble powder mix : 7 white, black or white andblack marble chips of sizes from 1mm to 4mm nominal size by volume) and under layer25mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate12.5 mm nominal size) rubbing, polishing and ceme-nt slurry etc. complete :

11.15.1 18 mm thick crazy marble stone white, black or as specified.CodDiscription Unit Quantity Rate Amount

Details of cost for 10 sqm.Under layer 25mm thick of cement(A) Concrete 1:2:4 -10x0.025=0. cum .25 3,695.95 923.99(Rate same as in item no. 11.7)

###Cement slurry for subgrade and tonne .04 4,500 180###Carriage of cement tonne .04 47.29 1.89

Labour for applying cement slurry###Beldar Day .5 135.25 67.62

Top layer with marble pieces and gap fillingwith marble powder mixtureMarble pieces for crazy flooring(Assume 70% of marble stone are and 30% ofjoint filer/mixture7sqmx0.02m = 0.14 cum

###0.872x0.14/0.051 = 2.40q quintal 2.4 105 252###White cement tonne .0405 9,700 392.85###Marble powder cum .007 800 5.6###Light shade pigment @ 3.5kg/50 kilogram 2.84 65 184.6

= 40.5x3.5/50=2.84kg

Page 476: DAR_Vol_1

###Marble chips quintal .872 115 100.28###Carriage of marble chips cum .051 53.21 2.71###Carriage of cement tonne .0405 47.29 1.92###Carriage of pigment & marble p L.S. 3.64 1 3.64###Carriage of marble stone pieces tonne .24 47.29 11.35

Labour for finishing, polishing and fixing-###Mason 1st class Day 1.2 151.5 181.8###Beldar Day 1 135.25 135.25###Coolie Day 1 135.25 135.25###Beldar for rubbing and polishing Day 5 138.45 692.25

Rate)###Sundries including carborandum L.S. 134.55 1 134.55###Bhisti Day .54 138.45 74.7613 Machine Day 4 200 800

TOTAL 4 282.31Add for water charges @ 1% on all except (A) 33.58TOTAL 4 315.89Add for contractor’s profit and overheads @ 508.7815% on all except (A)Cost of lOSqm. 4 824.67Cost of lsqm. 482.47Say 482.45

487### Precast terrazo tiles 22mm thick with graded marble chips of size upto 12mm

laid in floors, and landings, jointed with neat cement slurry mixed with pigmentto match the shade of the tiles including rubbing and polishing complete withprecast tiles on 20mm thick bed of cement mortar 1:4(1 cement :4 coarse sand):

11.Light shade using white cement.CodDiscription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-

###Terrazo tiles including 10% wast sqm 11 198 2,178###Carriage of tiles L.S 40.43 1 40.43###Cement mortar 1:4 (1 Cement : 4cum .224 2,578.45 577.57

(Rate as per item No. 3.9)###Grey cement for slurry @ 4.4Kg tonne .044 4,500 198.00###White cement for grouting tonne .044 9,700 426.8###Carriage of cement tonne .088 47.29 4.16###Light shade pigment kilogram 3.08 65 200.2

Labour-###Mason 2nd class Day 1.6 141.6 226.56###Coolie Day 2 135.25 270.5###Beldar for rubbing and polishing Day 1 138.45 138.45

Rate)###Bhisti Day 1 138.45 138.4513 Machine Day 1.6 200 320###Sundries including carborandum L.S 161.98 1 161.98

TOTAL 4,881.1Add 1% for water charges 48.81TOTAL 4 929.91Add 15%’for contractor’s profit and overheads 739.49

Page 477: DAR_Vol_1

Cost of 10 sqm. 5 669.40Cost of 1 sqm. 566.94Say 566.95

### Precast terrazo tiles 22mm thick with graded marble chips of size upto 12mmlaid in floors, and landings, jointed with neat cement slurry mixed with pigmentto match the shade of the tiles including rubbing and polishing complete withprecast tiles on 20mm thick bed of cement mortar 1:4(1 cement :4 coarse sand):

11.16.2 Medium shade using 50%white cement and 50% ordinary cement.CodDiscription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-

###Terrazo tiles including 10% wast sqm 11 175 1 925.00###Carriage of tiles L.S 40.43 1 40.43

Cement mortar 1:4( 1 Cement: 4 tonne .224 2,578.45 577.57(Rate as per item No. 3.9)Grey cement (i) for slurry @ 4.4Kg/sqm =44kg.+ (ii) 50% for grouting = 22kg. Total=66kg or 0.066 tonne

###Grey cement tonne .066 4,500 297###50% white cement for grouting tonne .022 9,700 213.4###Carriage of cement tonne .088 47.29 4.16###Medium shade pigment kilogram 3.08 45 138.6

LABOUR###Mason 2nd class Day 1.6 141.6 226.56###Coolie Day 2 135.25 270.5###Beldar for rubbing and polishing Day 1 138.45 138.45

488CodDescription Unit Quantity Rate Amount

Rate)###Bhisti Day 1 138.45 138.4513 Machine Day 1.6 200 320###Sundries including carborandum L.S 161.98 1 161.98

TOTAL 4,452.1Add 1% for water charges 44.52TOTAL 4,496.62Add 15% for contractor’s profit and overheads 674.49Cost of 10 sqm. 5,171.11Cost of 1 sqm. 517.11Say 517.1

### Precast terrazo tiles 22mm thick with graded marble chips of size upto 12mmlaid in floors, and landings, jointed with neat cement slurry mixed with pigmentto match the shade of the tiles including rubbing and polishing complete withprecast tiles on 20mm thick bed of cement mortar 1:4(1 cement :4 coarse sand):

11.Dark shade using ordinary cement.

CodDiscription Unit Quantity Rate Amount

Details of cost for l0 sqm.Materials-

###Terrazo tiles including 10% wa sqm 170 170 1,870###Carriage of tiles L.S 1 1 40.43

Page 478: DAR_Vol_1

Cerrusnt.mortar l:4(lCement: 4 C cum 2,578.45 2,578.45 577.57Rate as per item No. 3.9Ordinary cement for(i) Cement slurry @4.4kg/sqm = 44kg+ (ii) Grouting = 44kg.Total - 88kg or 0.088 tonne

###Ordinary cement tonne .088 4 500.00 396###Carriage of cement tonne .088 47.29 4.16###Dark shade pigment kilogram 3.08 42 129.36

LABOUR###Mason 2nd class Day 1.6 141.6 226.56###Coolie Day 2 135.25 270.5###Beldar for rubbing and polishing Day 1 138.45 138.45

Rate)###Bhisti Day 1 138.45 138.4513 Machine Day 1.6 200 320###Sundries including carborandum L.S 161.98 1 161.98

TOTAL 4,273.46Add 1% for water charges 42.73TOTAL 4,316.19Add 15% for contractor’s profit and overheads 647.43Cost of 10 sqm. 4,963.62Cost of 1 sqm. 496.36Say 496.35

489### Precast terrazo tiles 22mm thick with graded marble chips of size upto 12mm laid

in floors, and landings,jointed with neat cement slurry mixed with pigment to matchthe shade of the tiles including rubbing and polishing complete with precast tileson 20mm thick bed of cement mortar 1:4 (1 cement :4 coarse sand):

11.16.4 Ordinary cement without any pigment.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-

###Terrazo tiles including 10% wast sqm 11 170 1,870###Carriage of tiles L.S. 40.43 1 40.43

Cement mortar 1:4(1Cement: 4 Coarse sand)Rate as per item no. 3.9 cum .224 2,578.45 577.57Ordinary cement for (i) Cement slurry @4.4kg/sqm = 44kg+ (ii) Grouting = 44kg.Total = 88kg or 0.088 tonne

###Ordinary cement tonne .088 4,500 396###Carriage of cement tonne .088 47.29 4.16###Dark shade pigment kilogram 3.08 42 129.36

LABOUR###Mason 2nd class Day 1.6 141.6 226.56###Coolie Day 2 135.25 270.5###Beldar for rubbing and polishing Day 1 138.45 138.45

Rate)###Bhisti Day 1 138.45 138.4513 Machine Day 1.6 200 320###Sundries including carborandum L.S. 161.98 1 161.98###Less for dark shade pigment [3.0 kilogram 5.92 42 -248.64

tiles)]

Page 479: DAR_Vol_1

TOTAL 4 024.82Add 1 % for water charges 40.25TOTAL 4,065.07Add 15% for contractor’s profit and overheads 609.76Cost of 10 sqm. 4,674.83Cost of 1 sqm. 467.48Say 467.5

### Extra if terrazo tiles are laid in treads of steps not exceeding 30 pccm in width.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Labour-

###Mason 2nd class Day .22 141.6 31.15###Coolie Day .22 135.25 29.76###Beldar for rubbing and polishing Day .65 138.45 89.99

Rate)TOTAL 150.9Add 1% for water charges 1.51TOTAL 152.41Add 15% for contractor’s profit and overheads 22.86Cost of 10 sqm. 175.27Cost of 1 sqm. 17.53Say 17.55

49011.18 Precast terrazo tiles 22 mm thick with graded marble chips of sizes upto 12 mm in

skirting and risers of steps not exceeding 30 cm in height on 12 mm thick cementplaster 1:3 (1 cement : 3 coarse sand) jointed with neat cement slurry mixed withpigment to match the shade of the tiles, including rubbing and polishing completewith tiles of:

11.18.1Light shade using white cement.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-

###Terrazo tiles including 10% wast sqm 11 198 2,178###Carriage of tiles L.S. 40.43 1 40.43

Cement mortar 1 :3 (1Cement: 3 Coarse sand) cum .144 3,169.6 456.42Rate as per item No. 3.8White cement tor slurry cum .144

###For buttering tiles bed sides =44 tonne .066 9,700 640.2grouting =22 kg. Total = 66 kg.

###Carriage of cement tonne .066 47.29 3.12###Light shade pigment 66x3.5/50 =kilogram 4.62 65 300.3

Labour-###Mason 2nd class Day 3.25 141.6 460.2###Coolie Day 3.25 135.25 439.56###Beldar for rubbing and polishing Day 7.6 138.45 1,052.22

Rate)###Sundries including carborandum L.S. 161.46 1 161.46

polishing powder etc.TOTAL 5,731.91Add 1% for water charges 57.32TOTAL 5,789.23

Page 480: DAR_Vol_1

Add 15% for contractor’s profit and overheads 868.38Cost of 10 sqm. 6,657.61Cost of 1 sqm. 665.76Say 665.75

### Precast terrazo tiles 22 mm thick with graded marble chips of sizes upto 12 mm inskirting and risers of steps not exceeding 30 cm in height on 12 mm thick cementplaster 1:3 (1 cement : 3 coarse sand) jointed with neat cement slurry mixed withpigment to match the shade of the tiles, including rubbing and polishing completewith tiles of:

11.18.2 Medium shades using 50% white cement and 50% ordinary cement.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-

###20mm thick terrazo tiles (mediu sqm 11 175 1,925including wastage & breakage

###Carriage of tiles L.S. 40.43 1 40.43Cement mortar 1:3(1 Cement: 3 Coarse sand) cum .144 3,169.6 456.42Rate as per item no. 3.8

###50% white cement for slurry tonne .033 9,700 320.1###50% grey cement for slurry tonne .033 4,500 148.5###Carriage of cement tonne .066 47.29 3.12###Medium shade pigment Kilogram 4.62 45 207.9

Labour-###Mason 2nd class Day 3.25 141.6 460.2

491CodDescription Unit Quantity Rate Amount###Coolie Day 3.25 135.25 439.55###Beldar for rubbing and polishing Day 7.6 138.45 1,052.22

Rate)###Sundries including carborandum L.S. 161.46 1 161.46

polishing powder etc.TOTAL 5,214.91Add 1% for water charges 52.15TOTAL 5,267.06Add 15% for contractor’s profit and overheads 790.06Cost of 10 sqm. 6,057.12Cost of 1 sqm. 605.71Say 605.7

### Precast terrazo tiles 22 mm thick with graded marble chips of sizes upto 12 mm inskirting and risers of steps not exceeding 30 cm in height on 12 mm thick cementplaster 1:3 (1 cement : 3 coarse sand) jointed with neat cement slurry mixed with pigmentto match the shade of the tiles, including rubbing and polishing complete with tiles of:

11.18.3 Dark shade using ordinary cement.CodDescription Unit Quantity Rate Amount

Details of cost for 10sqm.Materials-

###20mm thick terrazo tiles (dark sqm 11 170 1,870including wastage & breakage

###Carriage of tiles L.S. 15.55 1 40.43Cement mortar. 1:3 (1 Cement: 3cum .144 3,169.6 456.42Rate as per item No. 3.8

Page 481: DAR_Vol_1

###Grey cement for slurry tonne .066 4,500 297###Carriage of cement tonne .066 47.29 3.12###Dark shade pigment kilogram 4.62 42 194.04

Labour-###Mason 2nd class Day 3.25 141.6 460.2###Coolie Day 3.25 135.25 439.56###Beldar for rubbing and polishing Day 7.6 138.45 1 052.22

Rate)###Sundries including carborandum L.S. 161.46 1 161.46

polishing powder etc.TOTAL 4 974.45Add 1 % for water charges 49.74TOTAL 5 024.19Add 15% for contractor’s profit and overheads 753.63Cost of 10 sqm. 5 777.82Cost of 1 sqm. 577.78Say 577.8

### Precast terrazo tiles 22 mm thick with graded marble chips of sizes upto 12 mm inskirting and risers of steps not exceeding 30 cm in height on 12 mm thick cementplaster 1:3 (1 cement : 3 coarse sand) jointed with neat cement slurry mixed with pigmentto match the shade of the tiles, including rubbing and polishing complete with tiles of:

11.18.4 Ordinary cement without any pigment.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-

###20mm thick terrazo tiles (dark sqm 11 170 1,870

492CodDescription Unit Quantity Rate Amount

including wastage & breakage###Carriage of tiles L.S. 40.43 1 40.43

Cemept mortar 1:3 (1 Cement: 3 cum .144 3,169.6 456.42Rate as per item No. 3.8

###Grey cement for sturry tonne .066 4,500 297###Carriage of cement tonne .066 47.29 3.12###Dark shade pigment kilogram 4.62 42 194.04

Labour-###Mason 2nd class Day 3.25 141.6 460.2###Coolie Day 3.25 135.25 439.56###Beldar for rubbing and polishing Day 7.6 138.45 1,052.22

Rate)###Sundries including carborandum L.S. 161.46 1 161.46

polishing powder etc.###Less for dark shade pigment [3.0 kg 5.92 42 -248.64

tiles)]TOTAL 4,725.81Add 1% for water charges 47.26TOTAL 4,773.07Add 15% for contractor’s profit and overheads 715.96Cost of 10 sqm. 5,489.03Cost of 1 sqm. 548.9Say 548.9

### Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mm in

Page 482: DAR_Vol_1

floors jointed with neat cement slurry mixed with pigment to match the shade ofthe tiles including rubbing and polishing complete on 20 mm thick bed of cementmortar 1:4 (1 cement :4 coarse sand):

1.19.1 Light shade using white cement.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-

###Terrazo tiles including 10% wast sqm 11 230 2,530###Carriage of tiles L.S. 40.43 1 40.43

Cement mortar 1:4(1 Cement,; 4 Coarse sand) cum .224 2,578.45 577.57###Grey cement for slurry @ 4.4kg tonne .044 4,500 198###White cement for grouting tonne .044 9,700 426.8###Carriage of cement tonne .088 47.29 4.16###Light shade pigment kilogram 3.08 65 200.2

Labour-###Mason 2nd class Day 1.6 141.6 226.56###Coolie Day 2 135.25 270.5###Beldar for rubbing and polishing Day 1 138.45 138.45

Rate)###Bhisti Day 1 138.45 138.4513 Machine Day 1.6 200 320###Sundries including carborandum L.S. 161.98 1 161.98

TOTAL 5 233.10Add 1% for water charges 52.33TOTAL 5 285.43Add 15% for contractor’s profit and overheads 792.81Cost of 10 sqm. 6 078.24Cost of 1 sqm. 607.82Say 607.8

493### Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mm in

floors jointed with neat cement slurry mixed with pigment to match the shade ofthe tiles including rubbing and polishing complete on 20 mm thick bed of cementmortar 1:4(1 cement :4 coarse sand):

11.19.2 Medium shade using 50% white cement, 50% ordinary cement.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-

###Terrazo tiles including 10% wast sqm 11 200 2,200###Carriage of tiles L.S 40.43 1 40.43

Rate as per item No. 3.9Cement mortar 1:4(1 Cemet: 4 C cum .224 2,578.45 577.57Grey cement (i) for slurry @ 4.4kg/sqm =44kg.+ (ii) 50% for grouting = 22kg. Total=66kg or 0.066 tonne

###Grey cement tonne .066 4,500 297###50% white cement for grouting tonne .022 9,700 213.4###Carriage of cement tonne .088 47.29 4.16###Medium shade pigment kilogram 3.08 45 138.6

Labour and sundries###Mason 2nd class Day 1.6 141.6 226.56

Page 483: DAR_Vol_1

###Coolie Day 2 135.25 270.5###Beldar for rubbing and polishing Day 1 138.45 138.45

Rate)###Bhisti Day 1 138.45 138.4513 Machine Day 1.6 200 320###Sundries including carborandum L.S. 161.98 1 161.98

TOTAL 4,727.1Add 1% for water charges 47.27TOTAL 4,774.37Add 15% for contractor’s profit and overheads 716.16Cost of 10 sqm. 5,490.53Cost of 1 sqm. 549.05Say 549.05

### Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mm infloors jointed with neat cement slurry mixed with pigment to match the shade ofthe tiles including rubbing and polishing complete on 20 mm tck bed of cementmortar 1:4(1 cement :4 coarse sand):

11.19.3 Dark shade using ordinary cement.CodDescription Unit Quantity Rate Amount

Details of cost for lOsqm.Materials-

###Terrazo tiles including 10% wast sqm 11 170 1,870###Carriage of tiles L.S. 40.43 1 40.43

Cement mortar 1:4(1 Cement: 4 cum .224 2,578.45 577.57Rate as per item No. 3.9Ordinary cement for (i) Cement slurry @4.4kg/sqm = 44kg+ (ii) Grouting = 44kg.Total = 88kg or 0.088 tonne

###Ordinary cement tonne .088 4,500 396###Carriage of cement tonne .088 47.29 4.16###Dark shade pigment kilogram 3.08 42 129.36

Labour & sundries###Mason 2nd class Day 1.6 141.6 226.56

494CodDescription Unit Quantity Rate Amount###Coolie Day 2 135.25 270.5###Beldar for rubbing and polishing Day 1 138.45 138.45

Rate)###Bhisti Day 1 138.45 138.4513 Machine Day 1.6 200 320###Sundries including carborandum L.S. 161.98 1 161.98

TOTAL 4,273.46Add 1 % for water charges 42.73TOTAL 4,316.19Add 15% for contractor’s profit and overheads 647.43Cost of 10 sqm. 4,963.62Cost of 1 sqm. 496.36Say 496.35

### Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mmin floors jointed with neat cement slurry mixed with pigment to match the shade ofthe tiles including rubbing and polishing complete on 20 mm thick bed of cement

Page 484: DAR_Vol_1

mortar 1:4(1 cement :4 coarse sand):11.19.4 Ordinary cement without any pigment.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-

###Terrazo tiles including 10% wast sqm 11 170 1,870###Carriage of tiles L.S. 40.43 1 40.43

Cement mortar 1:4(1 Cemet: 4 C cum .224 2,578.45 577.57Rate as per item No. 3.9Ordinary cement for (i) Cement slurry @4.4kg/sqm = 44kg+ (ii) Grouting = 44kg.Total = 88kg or 0.088 tonne

###Ordinary cement tone .088 4,500 396###Carriage of cement tone .088 47.29 4.16###Dark shade pigment Kilogram 3.08 42 129.36

Labour & sundries###Mason 2nd class Day 1.6 141.6 226.56###Coolie Day 2 135.25 270.56###Beldar for rubbing and polishing Day 1 138.45 138.45

Rate)###Bhisti Day 1 138.45 138.4513 Machine Day 1.6 200 320###Sundries including carborandum L.S. 162.59 1 162.59###Less for dark shade pigment [3.0 Kilogram 5.92 42 -248.64

tiles)]TOTAL 4,025.43Add 1 % for water charges 40.25TOTAL 4,065.68Add 15% for contractor’s profit and overheads 609.85Cost of 10 sqm. 4,675.53Cost of 1 sqm. 467.55Say 467.55

495### Chequerred precast cement concrete tiles 22 mm thick in footpath & courtyard

jointed with neat cement slurry mixed with pigment to match the shade of tilesincluding rubbing and cleaning etc. complete on 20 mm thick bed of cement mortar1:4 (1 cement: 4 coarse sand).

11.20.1 Light shade using white cement.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-

###Chequerred C.C. tiles including sqm 11 415 4,565###Carriage of tiles L.S. 40.43 1 40.43

Cement mortar 1:4(1 Cement: 4 cum .22 2,578.45 567.26Rate as per item no. 3.9

###Grey cement slury @ 4.4kg @sq tonne .044 4,500 198###White cement for grouting tonne .048 9,700 465.6###Carriage of cement tonne .092 47.29 4.35###Light shade pigment kilogram 3.08 65 200.2

Labour-

Page 485: DAR_Vol_1

###Mason 2nd class Day 1.6 141.6 226.56###Coolie Day 2 135.25 270.5###Bhisti Day 1 138.45 138.45

TOTAL 6,676.35Add 1% for water charges 66.76TOTAL 6,743.11Add 15% for contractor’s profit and overheads 1,011.47Cost of 10 sqm. 7,754.58Cost of 1 sqm. 775.46Say 775.45

### Chequerred precast cement concrete tiles 22 mm thick in footpath & courtyardjointed with neat cement slurry mixed with pigment to match the shade of tilesincluding rubbing and cleaning etc. complete on 20 mm thick bed of cement mortar1:4 (1 cement: 4 coarse sand).

11.20.2 Medium shade using 50% white cement 50% Grey cement.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-

###Chequered cement concrete tiles i/c10% wastage sq 11 305 3,355###Carriage of tiles L.S. 40.43 1 40.43

Cement mortar 1:4(1 Cement: 4Ccum .22 2,578.45 567.26Rate as per item no. 3.9Grey cement for slurry @ 4.4Kg/sqm. = 44 kg.

###+ grey cement for grouting 2.4kg tonne .068 4,500 306Total = 68 kg.

###White cement for grouting @ 2.4kg/sqm. = 24 tonne .024 9,700 232.8kg.

###Carriage of cement tonne .092 47.29 4.35###Medium shade pigment Kilogram 3.08 45 138.6

Labour-###Mason 2nd class Day 1.6 141.6 226.560115 Coolie Day 2 135.25 270.5###Bhisti Day 1 138.45 138.45

TOTAL 5,279.95Add 1% for water charges 52.8TOTAL 5,332.75Add 15% for contractor’s profit and overheads 799.91Cost of 10 sqm. 6,132.66Cost of 1 sqm. 613.27Say 613.25

496### Chequerred precast cement concrete tiles 22 mm thick in footpath & courtyard

jointed with neat cement slurry mixed with pigment to match the shade of tilesincluding rubbing and cleaning etc. complete on 20 mm thick bed of cement mortar1:4 (1 cement: 4 coarse sand).

11.20.3 Dark shade using ordinary CementCodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-

###Chequered cement concrete tile sqm 11 193 2,123###Carriage of tiles L.S. 40.43 1 40.43

Page 486: DAR_Vol_1

Cement mortar 1:4(1 Cement: 4Ccum .22 2,578.45 567.26Rate as per item no. 3.9Grey cement for slurry @ 4.4Kg/sqm. = 44 kg.

###+ For grouting = 48 kg. Total=92 tonne .092 4,500 414tonne

###Carriage of cement tonne .092 47.29 4.35###Dark shade pigment Kilogram 3.08 42 129.36

Labour-###Mason 2nd class Day 1.6 141.6 226.560115 Coolie Day 2 135.25 270.5###Bhisti Day 1 138.45 138.45

TOTAL 3,913.91Add 1% for water charges 39.14TOTAL 3,953.05Add 15% for contractor’s profit and overheads 592.26Cost of 10 sqm. 4,546.01Cost of 1 sqm. 454.6Say 454.6

11.20 : Chequerred precast cement concrete tiles 22 mm thick in footpath & courtyardjointed with neat cement slurry mixed with pigment to match the shade of tilesincluding rubbing and cleaning etc. complete on 20 mm thick bed of cement mortar1:4(1 cement: 4 coarse sand).

11.20.4 Ordinary cement without any pigment.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-

###Chequerred C.C. tiles including sqm 11 193 2 123.00###Carriage of tiles L.S. 40.43 1 40.43

Cement mortar 1:4 (1 Cement 4 cum .22 2 578.45 567.26(Rate as per item No.3.9)Grey cement for slurry @ 4.4kg/sqm. = 44 kg

###For grouting = 48 kg. Total = 92 K tonne .092 4 500.00 4140.092 tonne

###Carriage of cement tonne .092 47.29 4.35###Dark shade pigment kilogram 3.08 42 129.36

Labour-###Mason 2nd class Day 1.6 141.6 226.56###Coolie Day 2 135.25 270.5###Bhisti Day 1 138.45 138.45###Less for dark shade pigment [3. kilogram 5.92 42 -248.64

tiles)]TOTAL 3,665.27

497CodDescription Unit Quantity Rate Amount

Add 1% for water charges 36.65TOTAL 3,701.92Add 15% for contractor’s profit and overheads 555.29Cost of 10 sqm. 4,257.21Cost of 1 sqm. 425.72Say 425.7

Page 487: DAR_Vol_1

11.Providing and fixing 10mm thick acid and/or alkali resistant tiles of approvedmake and colour using acid and/or alkali resisting mortar bedding and joints filledwith acid and/or alkali resisting cement as per IS : 4457 complete as per thedirection of Engineer-in- Charge.

11.21.1 : In flooring on a bed of 10 mm thick mortar 1:4(1 acid proof cement: 4 coarse sand).11.21.1.1:Acid and alkali resistant tile.CodDescription Unit Quantity Rate Amount

Details of cost for 1 sqm.Materials-Acid proof tiles of size 300x300mm, 10mmthick =11.11 nos+Add wastage and breakage @ 2.5% = 0.28nos.= 11.39 nos. Say 12 nos.

###Acid proof tiles 10 Nos 12 460 552###Carriage L.S. 6.24 1 6.24

10mm thick cement motar 1:4 (1 cum .012 2 578.45 30.94Coarse sand) (Rate as per item No 3.9)

###Mortar for pointing in acid/alkalL.S. 40.43 1 40.43cement

###Cement for slurry over bed @ 3. tonne .0033 4 500.00 14.85Difference of cost for using acid proof cementinstead of ordinary cement

###Acid proof cement tonne .0079 7 400.00 58.46###Less Ordinary Cement tonne .0079 4 500.00 -35.55

Labour-###Mason 1 st class Day .2 151.5 30.3###Coolie Day .2 135.25 27.05###Sundries including carriage of ce L.S. 26.91 1 26.91

TOTAL 751.63Add 1% for water charges 7.52TOTAL 759.15Add 15% for contractor’s profit and overheads 113.87Cost of 1 sqm. 873.02Say 873

498### Providing and fixing 10mm thick acid and/or alkali resistant tiles of approved

make and colour using acid and/or alkali resisting mortar bedding and jointsfilled with acid and/or alkali resisting cement as per IS : 4457 complete as per thedirection of Engineer-in- Charge.

11.21.2 In dado/skirting on 12 mm thick mortar 1:4 (1 acid proof cement: 4 coarse sand).11.21.2.1 Acid and alkali resistant tile.Code Description Unit Quantity Rate Amount

Details of cost for 1 sqm.Materials-Acid proof tiles of size 300x300mm, 10mmthick = 11.11nos.+Add wastage and breakage @ 2.5% = 0.28nos.= 11.39 nos. Say 12 nos.

Page 488: DAR_Vol_1

### Acid proof tiles size 300x300mm, 10mm thick 10 N 12 460 552### Carriage of tiles 6.24 1 6.24

12mm .thick.Cement mortar, 1:4cum .014 2,578.45 36.1(Rate as per item No 3.9)Difference of cost for using^acid proof cementinstead of ordinary cement

### Acid proof cement tonne .0086 7,400 63.64### Less Ordinary Cement tonne .0086 4,500 -38.7### Mortar for pointing in acid proo L.S. 1 40.43### Acid proof cemen for slurry over tonne .0033 7 400.00 24.42

3.3kg/sqm.Labour-

st### Mason 1 class Day .25 151.5 37.88### Coolie Day .25 135.25 33.81### Sundries including carriage of ce L.S. 26.91 1 26.91

TOTAL 782.73Add 1% for water charges 7.83TOTAL 790.56Add 15% for contractor’s profit and overheads 118.58Cost of 1 sqm. 909.14Say 909.15

### Tile work in skirting, risers of steps and dado (upto 2 m height) over 12 mmthick bed of cement mortar 1:3 (1 cement :3 coarse sand) and jointed with greycement slurry @ 3.3 kg/sqm including pointing in white cement mixed withpigment of matching shade complete.

11.22.1 Marble tiles (polished) Raj Nagar.11.22.1.1 8 mm thick.Code Description Unit Quantity Rate Amount

Details of cost for lsqm.Materials-

### 8mm thick marble tiles (polished sqm 1.061 294 311.93including wastage

### Carriage of tiles L.S. 3.9 1 3.912mm thick cement mortar 1:3(1cum .014 3 169.60 44.37Coarse sand)(Rate as per items No. 3.8)

### Mortar for pointing in white ce L.S. 25.35 1 25.35### Cement for slurry @ 3.3kg/sqm tonne .0033 4 500.00 14.85### Pigment L.S. 2.08 1 2.08

Labour-

499CodDescription Unit Quantity Rate Amount

###Mason 1st class Day .25 151.5 37.88###Coolie Day .25 135.25 33.81###Sundries including carriage of ce L.S. 16.9 1 16.9

TOTAL 491.07Add 1% for water charges 4.91TOTAL 495.98Add .15% for contractor’s profit and overheads 74.4Cost of 1 sqm. 570.38

L.S.

40.43

Page 489: DAR_Vol_1

Say 570.4

11.23 : Marble stone flooring with 18mm thick marble stone (sample of marble shall beapproved by Engineer-in-charge) over 20 mm (average) thick base of cement mortar1:4 (1 cement : 4 coarse sand) laid and jointed with grey cement slurry includingrubbing and polishing comp

11.23.1 : Makrana white second quality.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-18mm thick marble slab = 10.00sqm.+Add for wastage 15% = 1.50sqm.Total = 11.50sqm.

###Makrana white 2nd quality 18 m sqm 11.5 1 722.00 19 803.00marble slabBase mortar 1:4 (1 Cement: 4 co cum .224 2 578.45 577.57( Rate as per item No. 3.9)

###Cement for slurry @4.4kg/sqm. (icum .05 4 500.00 225bedding = 44 kg+ (ii) for jointing = 6 Kg.Total = 50 Kg.

###Carriage of marble slab L.S. 26.91 1 26.91Labour-( for finishing, polishing and fixing)

###Mason 1st class Day 1.2 151.5 181.8###Beldar Day 1 135.25 135.25###Coolie Day 1 135.25 135.25###Beldar for rubbing and polishing Day 5 138.45 692.25

Rate)13 Machine Day 4 200 800###Sundries and carriage of cement L.S. 134.55 1 134.55

TOTAL 22,711.58Add 1% for water charges 227.12TOTAL 22 938.70Add 15% for contractor’s profit and overheads 3 440.80Cost of 10 sqm. 26 379.50Cost of 1 sqm. 2 637.95Say 2 637.95

50011.Marble stone flooring with 18mm thick marble stone (sample of marble shall be

approved by Engineer-in-charge) over 20 mm (average) thick base of cement mortar1:4 (1 cement : 4 coarse sand ) laid and jointed with grey cement slurry includingrubbing and polishing complete with :

11.23.2 :Raj Nagar plain.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-18mm thick marble slab = 10.00sqm.+Add for wastage 15%= 1.50sqm.Total = 11.50sqm.

###Raj nagar plain 18 mm thick marbsqm 11.5 415 4,772.5Base mortar 1:4 (1 Cement: 4 Co cum .224 2,578.45 577.57

Page 490: DAR_Vol_1

(Rate as per item No. 3.9)###Cement for @, 4.4kg sqm.tonne .05 4,500 225

Total = 50 Kg.###Carriage of marble slab L.S. 26.91 1 26.91

Labour-(for finishing, polishing and fixing)

###Mason 1st class Day 1.2 151.5 181.8###Beldar Day 1 135.25 135.25###Coolie Day 1 135.25 135.25###Beldar for rubbing and polishing Day 5 138.45 692.25

Rate)13 Machine Day 4 200 800###Sundries and carriage of cement L.S. 134.55 1 134.55

TOTAL 7,681.08Add 1% for water charges 76.81TOTAL 7,757.89Add .15% for contractor’s profit and overheads 1,163.68Cost of 10 sqm. 8,921.57Cost of 1 sqm. 892.16Say 892.15

11.Marble stone flooring with 18mm thick marble stone (sample of marble shall beapproved by Engineer-in-charge) over 20 mm (average) thick base of cement mortar1:4 (1 cement : 4 coarse sand) laid and jointed with grey cement slurry includingrubbing and polishing complete with :

11.23.3 : Agaria WhiteCodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-18mm thick marble slab = 10.00sqm.+Add for wastage 15% = 1.50sqm.Total = 11.50sqm.

###Marble Stone Slab 18mm thick ( sqm 11.5 1 000.00 11 500.00 Spot less)Base mortar 1:4 cement: 4 Coars cum .224 2 578.45 577.57(Rate as per item No. 3.9)

###Cement for slurry @4.4 kg/sqm. (itonne .05 4 500.00 225bedding = 44 kg+ (ii) for jointing = 6 Kg.Total = 50 Kg.

###Carriage of marble slab L.S. 26.91 1 26.91

501CodDescription Unit Quantity Rate Amount

Labour-(for finishing, polishing and fixing)

###Mason 1 st class Day 1.2 151.5 181.8###Beldar Day 1 135.25 135.25###Coolie Day 1 135.25 135.25###Beldar for rubbing and polishing Day 5 138.45 692.25

Rate)13 Machine Day 4 200 800###Sundries and carriage of cement L.S. 134.55 1 134.55

TOTAL 14 408.58

bedding = 44 kg+ (ii) for jointing = 6 Kg.

Page 491: DAR_Vol_1

Add 1 % for water charges 144.09TOTAL 14 552.67Add 15% for contractor’s profit and overheads 2 182.90Cost of 10 sqm. 16 735.57Cost of 1 sqm. 1 673.56Say 1 673.55

11.23 : Marble stone flooring with 18mm thick marble stone (sample of marble shall beapproved by Engineer-in-charge) over 20 mm (average) thick base of cement mortar1:4 (1 cement : 4 coarse sand) laid and jointed with grey cement slurry includingrubbing and polishing complete with :

11.23.4 : Black Zebra.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-18mm thick marble slab = 10.00sqm.+Add for wastage 15% = 1.50sqm.Total = 11.50sqm.

###Makrana Dhobi Doongri 18mm thsqm 11.5 415 4 772.50slabBase mortar 1:4, (1 Cement: 4 Cocum .224 2 578.45 577.57(Rate as per item No. 3.9)

###Cement for slurry @ 4.4kg/sqm. (ltonne .05 4 500.00 225bedding = 44 kg+ (ii) for jointing = 6 Kg.Total = 50 Kg.

###Carriage of marble slab L.S. 26.91 1 26.91Labour-( for finishing, polishing and fixing)

st###Mason 1 class Day 1.2 151.5 181.8###Beldar Day 1 135.25 135.25###Coolie Day 1 135.25 135.25###Beldar for rubbing and polishing Day 5 138.45 692.25

Rate)13 Machine Day 4 200 800###Sundries and carriage of cement L.S. 134.55 1 134.55

TOTAL 7 681.08Add 1% for water charges 76.81TOTAL 7 757.89Add 15% for contractor’s profit and overheads 1 163.68Cost of 10 sqm. 8 921.57Cost of 1 sqm. 892.16Say 892.15

50211.23 : Marble stone flooring with 18mm thick marble stone (sample of marble shall be

approved by Engineer-in-charge) over 20 mm (average) thick base of cement mortar1:4 (1 cement : 4 coarse sand) laid and jointed with grey cement slurry includingrubbing and polishing complete with :

11.23.5 : Udaipur green marbleCodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-

Page 492: DAR_Vol_1

18mm thick marble slab = 10.00sqm.+Add for wastage 15% = 1.50sqm.Total = 11.50sqm.

###Udaipur green marble 18 mm thick marble ssqm 11.5 580 6 670.00Base mortar 1:4(1 Cement : 4 Coarse sand) cum .224 2 578.45 577.57(Rate as per item No. 3.9)

###Cement for slurry @ 4.4kg/sqm. ( I tonne .05 4 500.00 225bedding = 44 kg+ (ii) for jointing = 6 Kg.Total = 50 Kg.

###Carriage of marble slab L.S. 26.91 1 26.91Labour-(for finishing, polishing and fixing)

###Mason 1st class Day 1.2 151.5 181.8###Beldar Day 1 135.25 135.25###Coolie Day 1 135.25 135.25###Beldar for rubbing and polishing (Special Day 5 138.45 692.25

Rate)13 Machine Day 4 200 800###Sundries and carriage of cement etc. L.S. 134.55 1 134.55

TOTAL 9 578.58Add 1% for water charges 95.79TOTAL 9 674.37Add 15% for contractor’s profit and overheads 1,451.16Cost of 10 sqm. 11 125.53Cost of 1 sqm. 1 112.55Say 1 112.55

11.23 : Marble stone flooring with 18mm thick marble stone (sample of marble shall beapproved by Engineer-in-charge) over 20 mm (average) thick base of cement mortar1:4 (1 cement : 4 coarse sand) laid and jointed with grey cement slurry includingrubbing and polishing complete with :

11.23.6: Pink plain marble.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials-18mm thick marble slab = 10.00sqm.+Add for wastage 15% = 1.50sqm.Total = 11.50sqm.

###Pink plain marble 18mm thick marble slab sqm 11.5 546 6 279.00Base mortar 1:4(1 : Cement: 4coarse sand) cum .224 2 578.45 577.57(Rate as per item No. 3.9)

###Cemen for slurry @4.4Kg/sqm(i)for tonne .05 4 500.00 225bedding = 44 kg+ (ii) for jointing = 6 Kg.Total = 50 Kg.

###Carriage of marble slab L.S. 26.91 1 26.91Labour-

503CodDescription Unit Quantity Rate Amount

(for finishing, polishing and fixing)###Mason 1st class Day 1.2 151.5 181.8###Beldar Day 1 135.25 135.25###Coolie Day 1 135.25 135.25###Beldar for rubbing and polishing Day 5 138.45 692.25

Page 493: DAR_Vol_1

Rate)13 Machine Day 4 200 800###Sundries and carriage of cement L.S. 134.55 1 134.55

TOTAL 9,187.58Add 1 % for water charges 91.88TOTAL 9,279.46Add 15 % for contractor’s profit and overheads 1 391.92Cost of 10 sqm. 10 671.38Cost of 1 sqm. 1 067.14Say 1 067.15

11.24 :Extra for prefinished nosing to treads of steps of marble stone.CodDescription Unit Quantity Rate Amount

Details of cost for 10mLabour-

###Mason (Ornamental) marble sto Day 2 151.5 303###Beldar Day 1.5 135.25 202.88###Beldar for rubbing and polishing Day 2.5 138.45 346.12

Rate)###Sundries L.S. 53.82 1 53.82

TOTAL 905.82Add 1 % for water charges 9.06TOTAL 914.88Add ,15% for contractor’s profit and overheads 137.23Cost for 10m 1 052.11Cost for lm 105.21Say 105.2

11.25 :Extra for marble stone flooring in treads of steps and risers using single lengthupto 2.00 metre .

CodDescription Unit Quantity Rate AmountDetails of cost for 10sqm.Labour-

###Mason 1st class Day 1.95 151.5 295.42###Beldar Day 1.4 135.25 189.35###Coolie Day .75 135.25 101.44###Beldar for rubbing and polishing Day 3.18 138.45 440.27

Rate)###Sundries L.S. 26.91 1 26.91

TOTAL 1 053.39Add 1 % for water charges 10.53TOTAL 1 063.92Add 15% for contractor’s profit and overheads 159.59Cost for 10sqm. 1 223.51Cost for lsqm. 122.35Say 122.35

50411.26 : Kota stone slab flooring over 20 mm (average) thick base laid over and jointed

with grey cement slurry mixed with pigment to match the shade of the slab includingrubbing and polishing complete with base of cement mortar 1 : 4 (1 cement: 4coarse sand):

11.26.1 :25 mm thick.CodDescription Unit Quantity Rate Amount

Page 494: DAR_Vol_1

Details of cost for 10sqm.Materials-

###25mm thick Kota stone slabs pol sqm 11.5 239 2 748.50including 15% wastage

###Carriage of slabs tonne .67 47.29 31.68Cement mortar 1:4( Rate as per i cum .224 2 578.45 577.57

###Cement for slurry-(i) for bedding tonne .064 4 500.00 288for joints = 20 kg. Total = 64 kg. or 0.064tonne

###Carriage of cement tonne .064 47.29 3.03###Dark shade pigment kilogram 4.5 42 189

Labour-###Mason 2nd class Day 1.2 141.6 169.92###Beldar Day 1 135.25 135.25###Coolie Day 1 135.25 135.25###Beldar for rubbing and polishing Day 5 138.45 692.25

Rate)13 Machine Day 4 200 800###Sundries L.S. 208.13 1 208.13

TOTAL 5 978.58Add 1% for water charges 59.79TOTAL 6 038.37Add 15% for contractor’s profit and overheads 905.76Cost for 10sqm. 6 944.13Cost for 1 sqm. 694.41Say 694.4

11.27 :Kota stone slabs 25 mm thick in risers of steps, skirting, dado and pillars laid on 12mm (average) thick cement mortar 1:3 (1 cement 3 coarse sand) and jointed withgrey cement slurry mixed with pigment to match the shade of the slabs, includingrubbing and polishing complete.

CodDescription Unit Quantity Rate AmountDetails of cost for 10sqm.Materials-

###25mm thick Kota stone slabs pol sqm 11.5 239 2 748.50including 15% wastage

###Carriage of slabs tonne .67 47.29 31.68Cement mortar 1:3 (1 Cement: 3 cum .144 3 169.60 456.42(Rate as per item No. 3.8)

###Cement for slurry tonne .064 4 500.00 288###Carriage of cement tonne .064 47.29 3.03###Pigment dark shade kilogram 4.5 42 189

Labour-###Mason 2nd class Day 3 141.6 424.8###Beldar Day 3 135.25 405.75###Coolie Day 1 135.25 135.25###Beldar for rubbing and polishing Day 7 138.45 969.15

Rate)

505CodDescription Unit Quantity Rate Amount###Sundries L.S. 174.98 1 174.98

TOTAL 5 826.56Add 1% for water charges 58.27

Page 495: DAR_Vol_1

TOTAL 5 884.83Add 15% for contractor’s profit and overheads 882.72Cost for 10sqm. 6 767.55Cost for 1sqm. 676.76Say 676.75

11.28 : 40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cementmortar 1:5 ( 1 cement: 5 coarse sand) with joints finished flush.

11.28.1 : Red sand stoneCodDescription Unit Quantity Rate Amount

Details of cost for 10sqm.MaterialsFinished work = 10sqmAdd wastage 10% =1.00sqmTotal = 11.00 sqm

###Red sand stone slab 40 mmthick sqm 11 120 1 320.00###Carriage L.S. 34.06 1 34.06

Cement mortar 1:5 (1 Cement: 5 cum .25 2 260.15 565.04(Rate as per item No. 3.10)(i) for bedding = 0224 cum (ii) for joining =0.026 cum. Total=0.250cum.Labour-

###Mason 1 st class Day 3.1 151.5 469.65###Bandhani Day 1.1 138.45 152.3###Coolie Day .55 135.25 74.39###Bhisti Day .27 138.45 37.38###Sundries L.S. 10.79 1 10.79

TOTAL 2 663.61Ada tor water charges @ 1% 26.64TOTAL 2 690.25Add for contractor’s profit and overheads @ 403.541,500%Cost for 10 sqm. 3 093.79Cost for 1sqm. 309.38Say 309.4

11.28 : 40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cementmortar 1:5 ( 1 cement: 5 coarse sand) with joints finished flush.

11.28.2 :White sand stoneCodDescription Unit Quantity Rate Amount

Details of cost for 10sqm.MaterialsWhite sand stoneFinished work =10 sqmAdd wastage 10% =1.00sqmTotal = 11.00 sqm

###White sand stone slab 40 mm thi sqm 11 140 1 540.00(un-dressed)

###Carriage L.S. 34.06 1 34.06Cement mortar 1:5 (1 cement :5 cum .25 220.15 565.04

506CodDescription Unit Quantity Rate Amount

(Rate as per item No. 3.10)

Page 496: DAR_Vol_1

(i) for bedding ).224cum+ (ii) for joining =0.026 cum. Total=0.250cum.Labour-

###Mason 1st class Day 3.1 151.5 469.65###Bandhani Day 1.1 138.45 152.3###Coolie Day .55 135.25 74.39###Bhisti Day .27 138.45 37.38###Sundries L.S. 10.79 1 10.79

TOTAL 2 883.61Add for water charges @ 1% 28.84TOTAL 2 912.45Add for contractor’s profit and overheads @ 436.8715%;Cost for 10 sqm. 3 349.32Cost for 1sqm. 334.93Say 334.95

11.29 : 40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cementmortar 1:5 (1 cement : 5 coarse sand) including pointing with cement mortar 1:2 (1cement: 2 stone dust) with an admixture of pigment to match the shade of stone.

11.29.1: Red sand stoneCodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.MaterialsFinished work 10 sqmAdd wastage 10% =1.00sqmTotal = 11.00 sqm

###Red sand stone slab 40 mm thick sqm 11 120 1 320.00###Carriage L.S. 34.06 1 34.06

Cement mortar 1:5 (1 Cement: 5 cum .25 2 260.15 565.04Rate as per item No.3.10(i) for bedding = 0.224 cum+(ii) for joining =0.026 cum. Total=0.250cum.Cement mortar 1:2(1 Cement: 2 scum .023 3 959.25 91.06for pointing Rate as per item No.3.12Labour-

###Mason 1st class Day 3.9 151.5 590.85###Bandhani Day 1.1 138.45 152.3###Coolie Day 1.4 135.25 189.35###Bhisti Day .55 138.45 76.15###Sundries L.S. 26.91 1 26.91

TOTAL 3 045.72Add for water charges @ 1% 30.46TOTAL 3 076.18Add for contractor’s profit and overheads @ 461.43Cost for 10 sqm. 3 537.61Cost for 1 sqm. 353.76Say 353.75

50711.29 : 40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cement

mortar 1:5(1 cement : 5 coarse sand) including pointing with cement mortar 1:2 (1

Page 497: DAR_Vol_1

cement: 2 stone dust) with an admixture of pigment to match the shade of stone.11.29.2: White sand stoneCodDescription Unit Quantity Rate Amount

Details of cost for 10sqm.MaterialsFinished work = 10sqmAdd wastage 10% =1.00sqmTotal = 11.00 sqm

###White sand stone slab 40 mm thi sqm 11 140 1 540.00(un-dressed)

###Carriage L.S. 34.06 1 34.06Cement mortar 1:5(1 Cement: 5 cum .25 2 260.15 565.04Rate as per item No.3.10(i) for bedding = 0.224 cum+ (ii) for joining =0.026 cum. Total=0.250cum.Cement mortar 1:2(1 Cement: 2 cum .023 3 959.25 91.06for pointing) ( Rate as per item No.3.12)Labour-

###Mason 1st class Day 3.9 151.5 590.85###Bandhani Day 1.1 138.45 152.3###Coolie Day 1.4 135.25 189.35###Bhisti Day .55 138.45 76.15###Sundries L.S. 26.91 1 26.91

TOTAL 3 265.72Add for water charges @ 1% 32.66TOTAL 3 298.38Add for contractor’s profit and overheads @ 494.761,500%Cost for 10 sqm. 3 793.14Cost for 1 sqm. 379.31Say 379.3

11.30 : 40 mm thick rubbed stone flooring over 20 mm (average) thick base of cementmortar 1:5(1 cement :5 coarse sand) with joints 3mm thick, side buttered withcement mortar 1:2 (1 cement : 2 stone dust) admixed with pigment to match theshade of stone and pointing with same mortar

11.30.1: Red sand stoneCodDescription Unit Quantity Rate Amount

Details of cost for 10sqm.MaterialsFinished work 10 sqmAdd wastage 10% = 1.00 sqmTotal = 11.00 sqm

###Red sand stone slab 40 mmthick sqm 11 120 1,320###Carriage L.S. 34.06 1 34.06

Cement Mortar 1:5 (1 Cement: 5 cum .25 2,260.15 565.04Rate as per item No.3.10(i) for bedding = 0.224 cum+ (ii) forjoining = 0.026 cum. Total=0.250cum.Cement mortar 1:2(1 Cement: 2 scum .023 3,959.25 91.06for pointing Rate as per item No.3.12Labour-

Page 498: DAR_Vol_1

508CodDescription Unit Quantity Rate Amount###Mason 1st class Day 3.9 151.5 590.85###Bandhani Day 1.1 138.45 152.3###Coolie Day 1.4 135.25 189.35###Bhisti Day .55 138.45 76.15###Sundries L.S. 26.91 1 26.91

Labour for rubbing of stone###Beldar for rubbing (special rate) Day .618 138.45 85.5613 Machine Day .988 200 197.6

TOTAL 3,328.88Add for water charges @ 1% 33.29TOTAL 3,362.17Add for contractor’s profit and overheads @ 504.331,500%Cost for 10 sqm. 3,866.5Cost for 1 sqm. 386.65Say 386.65

11.30 : 40 mm thick rubbed stone flooring over 20 mm (average) thick base of cementmortar 1:5 (1 cement :5 coarse sand) with joints 3mm thick, side buttered withcement mortar 1:2 (1 cement : 2 stone dust) admixed with pigment to match theshade of stone and pointing with same mortar

11.30.2: White sand stoneCodDescription Unit Quantity Rate Amount

Details of cost for 10sqm.MaterialsFinished work 10 sqmAdd wastage 10%= 1.00 sqmTotal = 11.00 sqm

###White sand stone slab 40 mm thi sqm 11 140 1,540(un-dressed)

###Carriage L.S. 34.06 1 34.06Cement Mortar 1:5(1 Cement: 5 cum .25 2,260.15 565.04Rate as per item No. 3.10 (i) for bedding = 0.224 cum+ (ii) forjoining = 0.026 cum. Total=0.250cum.Cement mortar 1:2(1 Cement: 2 scum .023 3,959.25 91.06for pointing Rate as per item No. 3.12Labour-

###Mason 1 st class Day 3.9 151.5 590.85###Bandhani Day 1.1 138.45 152.3###Coolie Day 1.4 135.25 189.35###Bhisti Day .55 138.45 76.15###Sundries L.S. 26.91 1 26.91

Labour for rubbing of stone###Beldar for rubbing (special rate) Day .618 138.45 85.5613 Machine Day .988 200 197.6

TOTAL 3 548.88Add for water charges @ 1% 35.49TOTAL 3 584.37Add for contractor’s profit and overheads@ 537.661,500%Cost for 10sqm. 4 122.03Cost for 1sqm. 412.2Say 412.2

Page 499: DAR_Vol_1

50911.Extra for pre finished nosing in treads of steps of Kota stone/ sand stone slab.CodDescription Unit Quantity Rate Amount

Details of cost for 10mLabour-

0126 Stone mason (ornamental) Day 1.5 151.5 227.25TOTAL 227.25Add 1 % for water charges 2.27TOTAL 229.52Add 15% for contractor’s profit and overheads 34.43TOTAL 263.95Cost for 10 sqm. 236.95Cost for lsqm. 26.4Say 26.4

11.32 : Extra for Kota stone/ sand stone in treads of steps and risers using single lengthupto 1.05 metre .

CodDescription Unit Quantity Rate AmountDetails of cost for 10sqm.Labour-

###Mason 2nd class Day .2 141.6 28.32###Beldar Day .2 135.25 27.05

TOTAL 55.37Add 1 % for water charges .55TOTAL. 55.92Add 15% for contractor’s profit and overheads 8.39Cost for 10 sqm. 64.31Cost for 1 sqm. 6.43Say 6.45

11.33 : 25mm wooden planking, tongued and grooved in flooring including fixing withiron screws complete with :

11.33.1: Second class teak woodCodDescription Unit Quantity Rate Amount

Details of cost for 2.5x4=10 sqm.Materials-Second class indian teak woodNo of joints = 4000/138 = 28.97 = (29-l) = 28nosQty of wood required2.5(4+0.336)x0.025 = 0.271 cumAdd wastage @ 10 % = 0.027 cum= 0.2981 cum = 298.1 cudm

###Second class indian teak wood 10 cudm 298.1 410 12,222.1###Extra for selected planks 10 cudm 298.1 72 2,146.32###Carriage of timber cum .2981 60.81 18.13###Iron screws 50 mm (slotted coun 100 Nos 200 40 80

head type)Labour-

###Carpenter 1 st class Day 2.68 151.5 406.02###Beldar Day 1.35 135.25 182.59###Sundries for glue etc. L.S. 33.28 1 33.28

TOTAL 15,088.44Add 1% for water charges 150.88TOTAL 15,239.32Add 15 % for contractor’s profit and overheads 2,285.9Cost for 10 sqm. 17,525.22Cost for 1 sqm. 1,752.52Say 1,752.5

Page 500: DAR_Vol_1

51011.25mm wooden planking, tongued and grooved in flooring including fixing with

iron screws complete with :11.33.2: Second class deodar woodCodDescription Unit Quantity Rate Amount

Details of cost for 2.5x4=10 sqm.Materials-First class deodar wood planksNo of joints = 4000/138 = 28.97= (29-l) = 28nosQty of wood required2.5(4+0.336)x0.025 = 0.271 cumAdd wastage @ 10 % = 0.027 cum= 0.2981 cum = 298.10 cudm -

###First class deodar wood10 cudm 298.1 335 9 986.35###Extra for selected plan 10 cudm 298.1 59 1 758.79###Carriage of timber cum .2981 60.81 18.13###Iron screws 50 mm (slo 100 Nos 200 40 80

head type)Labour-

###Carpenter 1 st class Day 2.16 151.5 327.24###Beldar Day 1.08 135.25 146.07###Sundries for glue etc. L.S. 26.91 1 26.91

TOTAL 12 343.49Add 1 % for water charges 123.43TOTAL 12 466.92Add 15% for contractor’s profit and overheads 1 870.04Cost for 10 sqm. 14 336.96Cost for 1 sqm. 1 433.70Say 1 433.70

11.34 : 38mm thick wood block flooring of first class teak wood laid over 25mm thicklevelling layer of cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stoneaggregate 10mm nominal size) to be paid separately coated with a thin layer of hotbitumen (blown type) @ 2.45 kg per sqm. including fixing blocks in position afterdipping in hot bitumen (blown type) upto half depth, planed, levelled smooth andfinished complete.

CodDescription Unit Quantity Rate AmountDetails of cost for l sqm.Bitumen blown typei) For bed layer @ 2.45kg/sqm. = 2.45kg+ii) For dipping blocks L.S. = 2.00Kg.= 4.45kg.

###Bitumen blown type tonne .0044 25,000 110###Carriage of bitumen tonne .0044 53.21 .23

1st class teak wood in scantling for woodenblocks1 sqm x 0.038 m = 0.038 cumAdd 10 % wastage = 0.0038 cumTotal = 0.0418 cum or 41.80 cudmst

###1 class teak wood in s 10 cudm 41.8 492 2 056.56blocks

Page 501: DAR_Vol_1

###Carriage of timber cum .0418 60.81 2.54Labour-

###Carpenter 1st class Day 1.75 151.5 265.12###Beldar Day 2.25 135.25 304.31

511CodDescription Unit Quantity Rate Amount

###Coolie Day 1.5 135.25 202.88###Mistry Day .1 151.5 15.15###Sundries such as fuel, kerosene oL.S. 1 80.73

TOTAL 3 037.52Add 1% for water charges 30.38TOTAL 3 067.90Add 10% for contractor’s profit and overheads 460.18Cost for 1 sqm. 3 528.08Say 3 528.10

11.Providing and fixing M.S. angle 50x50x5 mm to act as nosing with lugs of M.S. flat10x5 mm 10cm long forked at end 60cm apart (minimum three lugs to be provided )including necessay welding and applying a priming coat of approved primer onexposed surface etc. complete.

CodDescription Unit Quantity Rate Amount

Details of cost for 3m (15.39+0.2kg=15.63kg)Materials-angle iron 50x50x5 mm +3mAdd wastage @ 5% +0.15mTotal = 3.15m @ 5.13kg per m +16.16 kgSay 0.162 qutl

###Angle iron quintal .162 3,100 502.2Lugs 10x5 mm flat [email protected] per m = 0.24 kgAdd wastage @ 5% = 0.012 kg

###M.S. flats (Total 0.252 kg or 0.00 quintal .0025 2,900 7.25###Carriage of steel tonne .016 47.29 .76###Welding charges 6cm (lugs) by ecm 6 1 6

plant###Sundries L.S. 9.1 1 9.1

Labour-###Blacksmith 2nd class Day .09 141.6 12.47###Mason 1st class Day .45 151.5 68.18###Beldar Day .25 135.25 33.81

(A) Priming coat 1x3x0.60 sqm(Rate as per item no 13.50.3) sqm .06 12.65 7.59TOTAL 647.63Add for water charges @ 1% on all except on 6.4(A)TOTAL 654.03Add for contractor’s profit and overheads 96.97@15% on all except on (A)Cost for 15.63 kg 751Cost per 1 kg 48.05

80.73

Page 502: DAR_Vol_1

Say 48.05

51211.Providing and fixing 1st quality ceramic glazed wall tiles conforming to IS : 15622

(thickness to be specified by the manufacture of approved make in all colours, shadesexcept burgundy, bottle green, black of any size as approved by Engineer-in-Chargein skirting, risers of steps and dados over 12 mm thick bed of cement Mortar 1:3 (1cement: 3 coarse sand) and jointing with grey cement slurry @ 3.3kg per sqm includingpointing in white cement mixed with pigment of matching shade complete.

CodDescription Unit Quantity Rate AmountDetails of cost for 1 sqmMaterials-Ceramic Glazed tiles = 1.00 sqmAdd for wastage & breakage @ 2.5 % = 0.025sqm = 1.025 sqm

###Tiles Sqm. 1.025 268 274.7###Carriage of tiles L.S. 6.24 1 6.24

12 mm thick cement mortar 1:3 (cum .014 3 169.60 44.37coarse sand (Rate as per item No. 3.8)

###Mortar for pointing in white ce L.S. 40.43 1 40.43###Cement for slurry over bed @ 3. tonne .0033 4 500.00 14.85

Labour:###Mason 1 st class Day .25 151.5 37.88###Coolie Day .25 135.25 33.81###Sundries including carriage of c L.S. 26.91 1 26.91

TOTAL 479.19Add for water charges @ 1 % 4.79TOTAL 483.98Add for contractor’s profit and overheads @ 15% 72.6Cost for 1 sqm 556.58Say 556.6

11.37 :Providing and laying Ceramic glazed floor tiles 300x300 mm (thickness to be specifiedby the manufacturer) of 1st quality conforming to IS : 15622 of approved make incolours such as White, Ivory, Grey, Fume Red, Brown laid on 20 mm thick CementMortar 1:4 (1 Cement : 4 Coarse sand) including pointing the joints with white cementand matching pigment etc., complete.

CodDescription Unit Quantity Rate AmountDetails of cost for 1 sqmMaterials-Glazed Ceramic floor tiles 300x300 mm size =1.00 sqmAdd for wastage & breakage @ 2.5 % = 0.025sqm = Total 1.025 sqm

###Tiles Sq.m. 1.025 320 328###Carriage of tiles L.S. 6.24 1 6.24

20 mm thick cement mortar 1:4( cum 2,578.45 .024 61.88coarse sand) (Rate as per item No. 3.9)

###Mortar for pointing in white ce L.S. 1 20.2 20.2###Cement for slurry over bed @ 3. tonne 4,500 .0033 14.85

Labour:###Mason 1st class Day .2 151.5 30.3###Coolie Day .2 135.25 27.05

Page 503: DAR_Vol_1

###Sundries including carriage of c L.S. 26.91 1 26.91TOTAL 515.43Add for water charges @ 1% 5.15TOTAL 520.58Add for contractor’s profit and overheads @ 78.091,500%Cost for 1 sqm 598.67Say 598.65

51311.38 : Providing and laying Ceramic glazed floor tiles 300x300 mm(thickness to be

specified by the manufacturer) of 1st quality conforming to IS : 15622 of approvedmake in all colours , shades, except White, Ivory, Grey, Fume Red Brown laid on20mm thick bed of Cement Mortar 1:4(1 Cement: 4 Coarse sand) including pointingthe joints with white cement and matching pigments etc., complete.

CodDescriptio Unit Quantity Rate AmountDetails of cost for 1 sqmMaterials-Glazed Ceramic floor tiles 300x300 mm size =1.00 sqmAdd for wastage & breakage @ 2.5 % = 0.025sqm = Total 1.025 sqm

###Tiles Sq.m. 1.025 347 355.67###Carriage of L.S. 6.24 1 6.24

20 mm thiccum .024 2 578.45 61.88coarse sand) ( Rate as per item No. 3.9)

###Mortar for L.S. 20.2 1 20.2###Cement fortonne .0033 4 500.00 14.85

Labour:###Mason 1 stDay .2 151.5 30.3###Coolie Day .2 135.25 27.05###Sundries in L.S. 26.91 1 26.91

TOTAL 543.1Add for water charges @ 1 % 5.43TOTAL 548.53Add for contractor’s profit and overheads @15% 82.28Cost for 1 sqm 630.81Say 630.8

11.39 : Providing and laying rectified Glazed Ceramic floor tiles 300x300 mm or more(thickness to be specified by the manufacturer) of 1st quality conforming to IS :15622 of approved make in colours White, Ivory, Grey, Fume Red,, Brown, laid on20mm thick cement mortar 1:4 (1 Cement : 4 Coarse sand) including grouting thejoints with white cement and matching pigments etc., complete.

CodDescriptio Unit Quantity Rate AmountDetails of cost for 1 sqmMaterials-Rectified glazed Ceramic floor tiles 300x300mmor more = 1.000 sqmAdd for wastage & breakage @ 2.5 % = 0.025sqm

###Total = 1. sqm 1.025 462 473.55

Page 504: DAR_Vol_1

###Carriage of L.S. 6.24 1 6.2420 mm thiccum .024 2 578.45 61.88coarse sand) ( Rate as per item No. 3.9)

###Mortar for L.S. 13.47 1 13.47###Cement fortonne .0033 4 500.00 14.85

Labour:###Mason 1st Day .2 151.5 30.3###Coolie Day .2 135.25 27.05###Sundries in L.S. 26.91 1 26.91

TOTAL 654.25Add for water charges @ 1% 6.54TOTAL 660.79Add for contractor’s profit and overheads @ 99.12

15%Cost for 1 sqm 759.91Say 759.9

51411.Providing and laying rectified Glazed Ceramic floor tiles 300x300 mm or more

(thickness to be specified by the manufacturer) of 1st quality conforming to IS :15622 of approved make in all colours, shades, except White, Ivory, Grey, Fume RedBrown, laid on 20 mm thick Cement Mortar 1:4 (1 Cement : 4 Coarse sand) includingpointing the joints with white cement and matching pigments etc., complete.

CodDescription Unit Quantity Rate AmountDetails of cost for 1 sqmMaterials-Rectified Glazed Ceramic floor tiles 200x300 mmor more = 1.000 sqmAdd for wastage & breakage @ 2.5 % = 0.025sqm

###Total = 1.025 sqm sqm 1.025 496 508.4###Carriage of tiles L.S. 6.24 1 6.24

20 mm thick cement mocum .024 2 578.45 61.88coarse sand).

###Mortar for pointing in L.S. 13.47 1 13.47###Cement for slurry over tonne .0033 4 500.00 14.85

Labour:st

###Mason 1 class Day .2 151.5 30.3###Coolie Day .2 135.25 27.05###Sundries including car L.S. 26.91 1 26.91

TOTAL 689.1Add for water charges @ 1 % 6.89TOTAL 695.99Add for contractor’s profit and overheads @ 104.41,500%Cost for 1 sqm 800.39Say 800.4

11.41 : Providing and laying vitrified floor tiles in different sizes (thickness to be specifiedby the manufacturer) with water absorption’s less than 0.08% and conforming toIS : 15622 of approved make in all colours and shades, laid on 20mm thick cementmortar 1:4 (1 cement: 4 coarse sand) including grouting the joints with white cement

Page 505: DAR_Vol_1

and matching pigments etc., complete.11.41.1: Size of Tile 50x50 cmCodDescription Unit Quantity Rate Amount

Details of cost for 1 sqmMaterials-Porcelain floor tiles 50x50 cm size =1.000 sqmAdd for wastage & breakage @ 2.5 % = 0.025sqm

###Total = 1.025 sqm sqm 1.025 645 661.13###Carriage of tiles L.S. 6.24 1 6.24

20 mm thick cement mocum .024 2 578.45 61.88coarse sand)( Rate as per item No. 3.9)

###Mortar for pointing in L.S. 3.64 1 3.64###Cement for slurry over tonne .0033 4 500.00 14.85

Labour:###Mason 1st class Day .2 151.5 30.3###Coolie Day .2 135.25 27.05###Sundries including car L.S. 26.91 1 26.91

TOTAL 832Add for water charges @ 1% 8.32

515CodDescription Unit Quantity Rate Amount

TOTAL 840.32Add for contractor’s profit and overheads @ 126.051,500%Cost for 1 sqm 966.37Say 966.35

### Providing and laying vitrified floor tiles in different sizes (thickness to be specifiedby the manufacturer) with water absorption’s less than 0.08% and conforming toIS : 15622 of approved make in all colours and shades, laid on 20mm thick cementmortar 1:4(1 cement: 4 coarse sand) including grouting the joints with white cementand matching pigments etc., complete.

11.41.2 Size of Tile 60x60 cm

CodDescription Unit Quantity Rate AmountDetails of cost for 1 sqmMaterials-Porcelain floor tiles 60x60 cm size =1.000 sqmAdd for wastage & breakage @ 2.5 % = 0.025sqm

###Total = 1.025 sqm sqm 1.025 700 717.5###Carriage of tiles L.S. 6.24 1 6.24

20 mm thick cement mortar 1:4( cum .024 2,578.45 61.88coarse sand)(Rate as per item no. 3.90)

###Mortar for pointing in white ce L.S. 3.64 1 3.64###Cement for slurry over bed @ 3. tonne .0033 4,500 14.85

Labour:

Page 506: DAR_Vol_1

1 st ###Mason class Day .2 151.5 30.3###Coolie Day .2 135.25 27.05###Sundries including carriage of c L.S. 26.91 1 26.91

TOTAL 888.37Add for water charges @ 1 % 8.88TOTAL 897.25Add for contractor’s profit and overheads @ 134.591,500%Cost for 1 sqm 1,031.84Say 1,031.85

11.41 : Providing and laying vitrified floor tiles in different sizes (thickness to be specifiedby the manufacturer) with water absorption’s less than 0.08% and conforming toIS : 15622 of approved make in all colours and shades, laid on 20mm thick cementmortar 1:4 (1 cement: 4 coarse sand) including grouting the joints with white cementand matching pigments etc., complete.

11.41.3 : Size of Tile 80x80 cmCodDescription Unit Quantity Rate Amount

Details of cost for 1 sqmMaterials-Porcelain floor tiles 80x80 cm size =1.000 sqmAdd for wastage & breakage @ 2.5 % = 0.025sqm

516CodDescription Unit Quantity Rate Amount###Total = 1.025 sqm sqm 1.025 1,076 1,102.9###Carriage of tiles L.S. 2.4 1 6.24

20 mm thick cement mortar 1:4( cum .024 2 578.45 61.88coarse sand) (Rate as per item No. 3.9)

###Mortar for pointing in white ce L.S. 2.6 1 2.6###Cement for slurry over bed @ 3. tonne .0033 4 500.00 14.85

Labour:###Mason 1st class Day .2 151.5 30.3###Coolie Day .2 135.25 27.05###Sundries including carriage of c L.S. 26.91 1 26.91

TOTAL 1,272.73Add for water charges @ 1% 12.73TOTAL 1,285.46Add for contractor’s profit and overheads @ 192.821,500%Cost for 1 sqm 1,478.28Say 1,478.3

### Providing and laying vitrified floor tiles in different sizes (thickness to be specifiedby the manufacturer) with water absorption’s less than 0.08% and conforming toIS : 15622 of approved make in all colours and shades, laid on 20mm thick cementmortar 1:4 (1 cement: 4 coarse sand) including grouting the joints with white cementand matching pigments etc. complete.

11.41.4: Size of Tile 100x100 cm

Page 507: DAR_Vol_1

CodDescription Unit Quantity Rate AmountDetails of cost for 1 sqmMaterials-Porcelain floortiles 100x100 cm size = 1.000 sqmAdd for wastage & breakage @ 2.5 %= 0.025 sqm

###Total = 1.025 sqm sqm 1.025 1,290 1,322.25###Carriage of tiles L.S. 6.24 1 6.24

20 mm thick cement mortar 1:4( cum .024 2,578.45 61.88coarse sand). (Rate as per item No. 3.9)

###Mortar for pointing in white ce L.S. 2.6 1 2.6###Cement for slurry over bed @ 3. tonne .003 4,500 14.85

Labour:###Mason 1st class Day .2 151.5 30.3###Coolie Day .2 135.25 27.05###Sundries including carriage of c L.S. 26.91 1 26.91

TOTAL 1,492.08Add for water charges @ 1 % 14.92TOTAL 1,507Add for contractor’s profit and overheads @ 226.051,500%Cost for 1 sqm 1,733.05Say 1,733.05

51711.42: Deduet for not using 20mm thick cement mortar 1:4 (1 cement :4 coarse sand )

bedding in laying of floor tiles.CodDescription Unit Quantity Rate Amount

Details of cost for 1 sqmMATERIALSCement Mortar. 1:4 (1 cement: 4 cum .024 2,578.45 61.88(Rate as per item No. 3.9)

###Mortar foer pornting in whicte L.S. 40.43 1 40.45###Cement for slurry over bed @ 3 tonne .0033 4,500 14.85

LABOUR:-st

###Mason (brick layer) 1 class Day .2 151.5 30.3###Coolie Day .2 135.25 27.05###Sundries i/c carriage of cement eL.S. 26.91 1 26.91

Total 201.42Add for water charges @ 1% 2.01Total 203.43Add for contractor profit and overhead @ 30.511,500%Cost for 1 sqm 233.94Say 233.95

11.43: Fixing glazed/ Ceramic/ Vitrified floor tiles with cement based high polymer modifiedquick-set tile adhesive (Water based) conforming to IS: 15477 , using 5kg. adhesiveper sqm of tile area, in average 3mm thickness.

CodDescription Unit Quantity Rate AmountDetails of cost for 1 sqmMATERIALS

Page 508: DAR_Vol_1

###High polymer modified quickset tper kg 5 13.75 68.75###Mortar for pointing in white ce L.S. 40.43 1 40.43

LABOUR:-###Mason (brick layer) 1st class Day .2 151.5 30.3###Coolie Day .2 135.25 27.05###Sundries i/c carriage of cement eL.S. 26.91 1 26.91

Total 193.44Add for water charges @ 1% 1.93Total 195.37Add for contractor profit and overhead @ 29.311,500%Cost for 1 sqm 224.68Say 224.7

519

SUB HEAD : 12.0

ROOFING

521### Providing corrugated G.S. sheet roofing including vertical/curved surface fixed

with polymer coated J or L hooks, bolts and nuts 8 mm diameter with bitumen andG.I. limpet washers or with G.I. limpet washers filled with white lead and including

Page 509: DAR_Vol_1

a coat of approved steel primer and two coats of approved paint on overlapping ofsheets complete upto any pitch in horizontal/ vertical or curved surfaces) excludingthe cost of purlins, rafters and trusses and including cutting to size and shapewherever required.

2

12.1.00mm thick with zinc coating not less than 275gm/mCodDescription Unit Quantity Rate Amount

Considering a roof with each sloping side18.09x5.10m and the slope being flatter than 1vertical to 2.5 horizontalDetails of cost for area of roof.2x18.09x5.1 = 184.518 sqm.Details of length and breadth.Materials:C.G.S. sheets 2x27 =54 nos. of size 2.5x0.9metre @19.35 Kg each =1044.90Kg.2x27=54 nos. of [email protected]. each = 1170.18Kg.Total = 2215.08Kg.+Add 5% Wastage = 110.75Kg.= 2325.83 Kg.23.26 quintals

###(a) C.G.S. sheets quintal 23.26 3 650.00 84,899###(b) Carriage of sheet tonne 2.326 47.29 110

(c) G.I.Seam bolts and nuts 60cmcentre to centre zig-zag i.e. 30cmcentre to centre straightBreadth is 5.1 metreNo. of bolts in one lap 5.1/0.3 =17 nos.2x26(laps)x17 nos. = 884 nos.

###Bolts and nuts 10 Nos 884 9 795.6(d) G.I..J or L hooks 8mm dia.(No. of purlins to be used 5 on eitherside)2x5x27(No. of sheets)x23 nos. of boltsin each sheet = 810 nos.

###G.I., J or L hooks 10 Nos 810 58 4,698###(e) Limpet washers (total of seam100 Nos 1,694 20 338.8

884+810=1694###(f) Bitumen washers 100 Nos 1,694 18 304.92###(g) Carriage of bolts and washers L.S. 26.91 1 26.91###Sundries L.S. 53.82 1 53.82

Labour:###Mistry Day 1.3 151.5 196.95###Carpenter 2nd class Day 15.5 141.6 2,194.8###Beldar Day 15.5 135.25 2,096.38###Zink chromate yellow primer litre 2.53 58 146.74###Carriage of material L.S. .52 1 .52###Painter Day 1.13 141.6 160.01###Coolie Day 1.13 135.25 152.83###Brushes, sand papers i/c sundrie L.S. 50.57 1 50.57###Ready mixed paint on new work litre 3.75 95 356.25###Carriage of paint L.S. 6.76 1 6.76###Painter Day 2.53 141.6 358.25

Page 510: DAR_Vol_1

522CodDescription Unit Quantity Rate Amount

###Coolie Day 2.53 135.25 342.18###Brushes and Sandpapers L.S. 31.98 1 31.98###Sundries L.S. 38.09 1 38.09

TOTAL 97,359.36Add 1% for water charges 973.59TOTAL 98,332.95Add 15% for contractor’s profit and overheads 14,749.94Cost of 184.518 Sqm. ###Cost of 1 Sqm. 612.86Say 612.85

### Providing corrugated G.S. sheet roofing including vertical/curved surface fixedwith polymer coated J or L hooks, bolts and nuts 8 mm diameter with bitumen andG.I. limpet washers or with G.I. limpet washers filled with white lead and includinga coat of approved steel primer and two coats of approved paint on overlapping ofsheets complete upto any pitch in horizontal/ vertical or curved surfaces) excludingthe cost of purlins, rafters and trusses and including cutting to size and shapewherever required.

2

12.0.80mm thick with zinc coating not less than 275gm/mCodDescription Unit Quantity Rate Amount

Considering a roof with each sloping side18.09x5.10m and the slope being flatter than 1vertical to 2.5 horizontalDetails of cost for area of roof.2x18.09x5.1 = 184.518 sqm.Details of length and breadth.Length26(laps)xO.135(each lap)=3.51Width of Corrugated sheet with 10 corrugationmeasured end to end = 0.8 metres 27 (nos. ofsheets)x0.80 (width of sheet) = 21.60 lengthLess laps = 3.51Length = 18.09Breadth on one side-C.G.S. Sheet 1 No. of = 2.5 metres length+C.G.S. Sheet 1 No. of = 2.8 metres length= 5.3 metresDeduct end lap of 20cm (-)0.2 metresbreadth = 5.1 mMaterials:C.G.I.Sheets 0.8mm thick2x27=54nos. @15.82Kg.each= 854.38Kg(X)2.5mx0.9m is the size of plain G.I.sheet whichon being corrugated will become 2.5mx0.8m(The size of plain sheet is taken because theweight is available only of plain sheets)(Refer l.S. Code 277-1962)2x27=54nos. of size. [email protected] each’ = 956.8Kg (Y)Total of (X)+(Y) = 1811.16Kg.Add wastage @5% = 90.56Kg.= 1901.72Kg

Page 511: DAR_Vol_1

3050 (a) Sheets quintal 19.02 3,650 69,4232302 (b) Carriage of sheet tonne 1.902 47.29 89.95

(c) G.I. seam bolts and nuts 60cm

523CodDescription Unit Quantity Rate Amount

centre to centre zig zag i.e. 30cm.centre to centre straightBreadth is 5.1 metreNo. of bolts in one lap 5.1/0.3 =17 nos.2x26(laps)xl7 nos. = 884 nos.

###Bolts and nuts 10 Nos 884 9 795.6(d) G.I., j or L hooks 8mm dia.(No. of purlins to be used 5 on eitherside)2x5x27 (No. of sheets)x23 nos. of boltsin each sheet = 810 nos.

###G.I. J or L hooks 10 Nos 810 58 4,698###(e) Limpet washers (total of seam100 Nos 1,694 20 338.8

884+810=1694###(f) Bitumen washers 100 Nos 1,694 18 304.92###(g) Carriage of bolts and washers L.S. 26.91 1 26.91###Sundries L.S. 53.82 1 53.82

Labour:###Mistry Day 1.3 151.5 196.95###Carpenter 2nd class Day 15.5 141.6 2,194.8###Beldar Day 15.5 135.25 2,096.38###Zink chromate yellow primer litre 2.53 58 146.74###Carriage of material L.S. .52 1 .52###Painter Day 1.13 141.6 160.01###Coolie Day 1.13 135.25 152.83###Brushes, sand papers i/c sundrie L.S. 50.57 1 50.57###Ready mixed paint on new work litre 3.75 95 356.25###Carriage of paint L.S. 6.76 1 6.76###Painter Day 2.53 141.6 358.25###Coolie Day 2.53 135.25 342.18###Brushes and Sandpapers L.S. 31.98 1 31.98###Sundries L.S. 38.09 1 38.09

TOTAL 81,863.31Add 1 % for water charges 818.63TOTAL 82,681.94Add 15% for contractor’s profit and overheads 12,402.29Cost of 184.518 Sqm. 95,084.23Cost of 1 Sqm. 515.31Say 515.3

### Providing corrugated G.S. sheet roofing including vertical/curved surface fixedwith polymer coated J or L hooks, bolts and nuts 8 mm diameter with bitumen andG.I. limpet washers or with G.I. limpet washers filled with white lead and includinga coat of approved steel primer and two coats of approved paint on overlapping ofsheets complete upto any pitch in horizontal/ vertical or curved surfaces) excludingthe cost of purlins, rafters and trusses and including cutting to size and shapewherever required.

Page 512: DAR_Vol_1

12.0.63 mm thick with zinc coating not less than 275gm/sqmCodDescription Unit Quantity Rate Amount

Considering a roof with each sloping side18.09x5.10m and the slope being flatter than 1vertical to 2.5 horizontalDetails of cost for area of roof.2x18.09x5.1 = 184.518 sqm.Details of length and breadth.Length

524CodDescription Unit Quantity Rate Amount

26(laps)xO.135(each lap)=3.51Width of Corrugated sheet with 10 corrugationmeasured end to end = 0.8 metres 27 (nos. ofsheets)x0.80 (width of sheet = 21.60 lengthLess laps = 3.51Length = 18.09Breadth on one side-C.G.S. Sheet 1 No. of = 2.5 metres length+C.G.S. Sheet 1 No. of = 2.8 metres length= 5.3 metresDeduct end lap of 20cm (-)0.2 metresbreadth = 5.1mMaterials:C.G.I.Sheets 0.8mm thick2x27=54nos. @12.82Kg.each= 692.28 Kg(X)2.5mxO.9m is the size of plain G.I.sheet whichon being corrugated will become 2.5mxO.8m(The size of plain sheet is taken because theweight is available only of plain sheets)(Refer I.S. Code 277-1962)2x27=54nos. of [email protected] each’ = 775.44Kg (Y)Total of (X)+(Y) = 1467.72Kg.Add wastage @5% = 73.39Kg.= 1541.11HKg

###(a) Sheets quintal 15.41 3,650 56,246.5###(b) Carriage of sheet tonne 1.54 47.29 72.83

(c) G.I. seam bolts and nuts 60cmcentre to centre zig zag i.e. 30cm.centre to centre straightBreadth is 5.1 metreNo. of bolts in one lap 5.1/0.3 =17 nos.2x26(laps)xl7 nos. = 884 nos.

###Bolts and nuts 10 Nos 884 9 795.6(d) G.I., J or L hooks 8mm dia.(No. of purlins to be used 5 on eitherside)2x5x27 (No. of sheets)x23 nos. of boltsin each sheet = 810 nos.

###G.I. J or L hooks 10 Nos 810 58 4,698###(e) Limpet washers (total of seam100 Nos 1,694 20 338.8

884+810= 1694

Page 513: DAR_Vol_1

###(f) Bitumen washers 100 Nos 1,694 18 304.92###(g) Carriage of bolts and washers L.S. 26.91 1 29.91###Sundries L.S. 53.82 1 53.82

Labour:###Mistry Day 1.3 151.5 196.950112 Carpenter 2nd class Day 15.5 141.6 2,194.8###Beldar Day 15.5 135.25 2,096.384202 Zink chromate yellow prim litre 2.53 58 146.749999 Carriage of material L.S. .52 1 .52###Painter Day 1.13 141.6 160.01###Coolie Day 1.13 135.25 152.839999 Brushes, sand papers i/c s L.S. 50.57 1 50.570845 Ready mixed paint on ne litre 3.75 95 356.259999 Carriage of paint L.S. 6.76 1 6.76

525CodDescription Unit Quantity Rate Amount0131 Painter Day 2.53 141.6 358.250115 Coolie Day 2.53 135.25 342.189,999 Brushes and Sandpapers L.S. 31.98 1 31.989,999 Sundries L.S. 38.09 1 38.09

TOTAL 68,669.69Add 1 % for water charges 686.7TOTAL 69,356.39Add 15% for contractor’s profit and overheads 10,403.46Cost of 184.518 Sqm. 79,759.85Cost of 1 Sqm. 432.26Say 432.25

### Extra for straight cutting in C.G.S. sheet roofing for making opening of areaexceeding 40 sq. decimeter for chimney stacks, sky light etc. :

12.1.00 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 3 metres peripheryAssuming a hole of 10dmx5dm area of the2hole 50dm and the perimeter of the hole 3metreLabour:

###Blacksmith first class Day .15 151.50 22.72###Beldar Day .15 135.25 20.29

TOTAL 43.01Add 1 % for water charges .43TOTAL 43.44Add 15% for contractor’s profit and overheads 6.52Cost of 3.00 metres 49.96Cost of 1.00 metre 16.65Say 16.65

### Extra for straight cutting in C.G.S. sheet roofing for making opening of areaexceeding 40 sq. decimeter for chimney stacks, sky light etc.:

12.0.80 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 3 metres peripheryAssuming a hole of 10dmx5dm area of the

Page 514: DAR_Vol_1

2hole 50dm and the perimeter of the hole 3metreLabour:

###Blacksmith first class Day .12 151.5 18.18###Beldar Day .12 135.25 16.23

TOTAL 34.41Add 1 % for water charges .34TOTAL 34.75Add 10% for contractor’s profit and overheads 5.21Cost of 3.00 metres 39.96Cost of 1.00 metre 13.32Say 13.3

526### Extra for straight cutting in C.G.S. sheet roofing for making opening of area

exceeding 40 sq. decimeter for chimney stacks, sky light etc. :12.0.63 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 3 metres peripheryAssuming a hole of 10dmx5dm area of the2hole 50dm and the perimeter of the hole 3metreLabour:

###Blacksmith first class Day .12 151.5 18.18###Beldar Day .12 135.25 16.23

TOTAL 34.41Add 1 % for water charges .34TOTAL 34.75Add 10% for contractor’s profit and overheads 5.21Cost of 3.00 metres 39.96Cost of 1.00 metre 13.32Say 13.3

### Extra for circular cutting in C.G.S. sheet roofing for making opening of areaexceeding 40 square decimeter :

12.1.00 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 10 holes of 0.5 metredia-metrePerimetre of 10 nos 10x22/7x0.5 = 15.71metreLabour:

###Blacksmith first class Day 3.13 151.5 474.2###Beldar Day 6.26 135.25 846.66

TOTAL 1,320.86Add 1 % for water charges 13.21TOTAL 1,334.07Add 15% for contractor’s profit and overheads 200.11Cost of 15.71 metres 1,534.18Cost of 1.00 metre 97.66Say 97.65

Page 515: DAR_Vol_1

### Extra for circular cutting in C.G.S. sheet roofing for making opening of areaexceeding 40 square decimeter :

12.0.80 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 10 holes of 0.5 metredia-metrePerimetre of 10 nos 10x22/7x0.5 =15.71metreLabour:

###Blacksmith first class Day 2.5 151.5 378.75###Beldar Day 5 135.25 676.25

TOTAL 1,055Add 1% for water charges 10.55TOTAL 1,065.55Add 15% for contractor’s profit and overheads 159.83Cost of 15.71 metres 1,225.38Cost of 1.00 metre 78Say 78

527### Extra for circular cutting in C.G.S. sheet roofing formaking opening of area

exceeding 40 square decimeter:12.0.63 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 10 holes of 0.5 metredia-metrePerimetre of 10 nos 10x22/7x0.5 = 15.71metreLabour:

###Blacksmith first class Day 2.5 151.5 378.75###Beldar Day 5 135.25 676.25

TOTAL 1,055Add 1% for water charges 10.55TOTAL 1,065.55Add 15% for contractor’s profit and overheads 159.83Cost of 15.71 metres 1,225.38Cost of 1.00 metre 78Say 78

12.4 Providing ridges or hips of width 60 cm over all width plain G.S. sheet fixed withpolymer coated J. or L hooks, bolts and nuts 8 mm dia. G.I. limpet and bitumenwashers complete. 2

12.0.80mm thick with zinc coating not less than 275gm/mCodDescription Unit Quantity Rate Amount

0.80mm thick with zinc coating not less than2275gm/mConsider the length of the ridge 10.35 metres.The ridge will be made out of plain G.I.Sheets0.9mx1.8mThree pieces will be 0.9m long and0.60m wide overlapping 22.5cm.

Page 516: DAR_Vol_1

MaterialsG.I. plain sheets 0.80 thick1.80x0.90msize5nos. @11.39Kg. sheet = 56.95Kg +Add 2% wastage = 1.14 Kg.= 58.09 Kg. or 0.58 qunital

###G.I. plain sheets quintal .58 3,450 2 001.00###Carriage of sheets tonne .058 47.29 2.74

G.I. seam bolts and nuts-25mmx6mm (There are 14 joints)

###G.I. seam bolts and nuts 10 Nos 28 30 84###G.I. plain washers 100 Nos 28 21 5.88###Bitumen washers 100 Nos 28 18 5.04###Carriage of seam bolts and wash L.S. 1.82 1 1.82###Sundries L.S. 13.52 1 13.52

Labour:###Mistry Day .4 151.5 60.6###Blacksmith first class Day 1.2 151.5 181.8###Blacksmith 2nd class Day .8 141.6 113.28###Beldar Day 2.4 135.25 324.6

TOTAL 2,794.28Add 1% for water charges 27.94TOTAL 2,822.22Add 15% for contractor’s profit and overheads 423.33Cost of 10.35 metres 3,245.55Cost of 1.00 metre 313.58Say 313.6

52812.4 Providing ridges or hips of width 60 cm over all width plain G.S. sheet fixed with

polymer coated J. or L hooks, bolts and nuts 8 mm dia. G.I. limpet and bitumenwashers complete.

2

12.0.63mm thick with zinc coating not less than 275gm/mCodDescription Unit Quantity Rate Amount

Details of cost for 10.35 metre long ridge.G.I.plain sheets 0.63mm thick1.8xO.9m size 5 nos. @9.23 Kg. per sheet =46.15 Kg.+Add 2% wastage = 0.91 Kg.= 47.07 Kg.Say 47 Kg.

###G.I. plain sheets quintal .47 3,450 1,621.5###Carriage of sheets tonne .047 47.29 2.22

G.I. seam bolts and nuts-25mmx6mm (There are 14 joints)

###G.I. seam bolts and nuts 10 Nos 28 30 84###G.I. plain washers 100 Nos 28 21 5.88###Bitumen washers 100 Nos 28 18 5.04###Carriage of seam bolts and wash L.S. 1.82 1 1.82###Sundries L.S. 13.52 1 13.52

Labour:###Mistry Day .4 151.5 60.6

Page 517: DAR_Vol_1

###Blacksmith first class Day 1.2 151.5 181.8###Blacksmith 2nd class Day .8 141.6 113.28###Beldar Day 2.4 135.25 324.6

TOTAL 2,414.26Add 1% for water charges 24.14TOTAL 2,438.4Add 15% for contractor’s profit and overheads 365.76Cost of 10.35 metres 2,804.16Cost of 1.00 metre 270.93Say 270.95

### Providing valleys of 90cm wide overall in plain G.S. sheet fixed with polymer coatedJ, or L hooks, bolts and nuts 8mm dia.. G.I. limpet and bitumen washers complete :

2

12.1.60mm thick with zinc coating not less than 350gm/mCodDescription Unit Quantity Rate Amount

Details of cost for 9.325mMaterials:G.I. plain sheets 2.5xO.9m4 nos. @ 29.95Kg/sheet =119.80Kg.+Add 2% wastage = 2.40Kg.= 122.20 kg. or 1.222quintal

###G.I. plain sheets quintal 1.222 3 450.00 4,215.9###Carriage of sheets tonne 0.12 47.29 5.67

G.I. seam bolts and nuts-25mmx6mm (There are 14 joints)

###G.I. seam bolts and nuts 10 Nos 12 30 36###G.I. plain washers 100 Nos 12 21 2.52###Bitumen washers 100 Nos 12 18 2.16###Carriage of bolts, nuts and washeL.S. .91 1 .91###Sundries L.S. 13.52 1 13.52

Labour:###Mistry Day .4 151.5 60.6

529CodDescription Unit Quantity Rate Amount###Blacksmith first class Day 1.2 151.5 181.8###Blacksmith 2nd class Day .8 141.6 113.28###Beldar Day 2.4 135.25 324.6

TOTAL 4,956.96Add 1% for water charges 49.57TOTAL 5,006.53Add 15% for contractor’s profit and overheads 750.98Cost of 9.325 metres 5,757.51Cost of 1.00 metre 617.43Say 617.45

12.6 Providing flashing of 40 cm over all width in plain, G.S. sheet fixed with polymercoated J, or L hooks, bolts and nuts, G.I. limpet and bitumen washer complete,bent to shape and fixed in wall with cement mortar 1:3 (1 cement: 3 coarse sand).

2

12.1.00mm thick with zinc coating not less than 275gm/mCodDescription Unit Quantity Rate Amount

Details of cost for 12.125m

Page 518: DAR_Vol_1

Consider a length of flashing 12.125 metres.Materials:G.I. plain sheet 1.25mm thick 3.2xO.75m2 nos. @ 20.64 Kg. =41.28 Kg.+Add 2% wastage = 0.83 Kg= 42.11 Kg. or 0.4211 quintal

###G.I. plain sheets quintal .4211 3 450.00 1 452.79###Carriage of sheets tonne .041 47.29 1.94

G.I. seam bolts and nuts-25mmx6mm(taking 2 bolts per joints)

###G.I. seam bolts and nuts 10 Nos 6 30 18###Limpet washers 100 Nos 6 20 1.2###Bitumen washers 100 Nos 6 18 1.08###Carriage of G.I. seam bolts and L.S. .39 1 .39###sundries L.S. 10.79 1 10.79

Labour:###Mistry Day .5 151.5 75.75###Blacksmith first class Day 1.48 151.5 224.22###Blacksmith 2nd class Day 1 141.6 141.6###Beldar Day 3 135.25 405.75

TOTAL 2 333.51Add 1 % for water charges 23.34TOTAL 2 356.85Add 15% for contractor’s profit and overheads 353.53Cost of 12.125 metres 2 710.38Cost of 1.00 metre 223.54Say 223.55

12.Providing and fixing 15 cm wide 45 cm over all semi circular plain G.S. sheet gutterwith iron brackets 40x3mm size, bolts, nuts and washers etc. including makingnecessary connections with rain water pipes complete.

2

12.0.80mm thick with zinc coating not less than 275gm/mCodDescription Unit Quantity Rate Amount

0.80mm thick with zinc coating not less than2275gm/m

530CodDescription Unit Quantity Rate Amount

Consider a length of 9.04mSheet used = 2.5x0.90m= 2 nos.Wt. = 2x15.82=31.64 Kg.= 0.3164quintal

###G.I. plain sheets quintal 0.3164 3 450.00 1,091.58###Carriage of sheets tonne 0.0316 47.29 1.49###Flats upto 10 mm in thickness quintal 0.0749 2,900 217.21###Galvanised steel bolts and nuts 10 Nos 20 9 18

25 mm long round head with slot###Galvanised steel bolts and nuts each 30 7 210

125 mm long###G.I. plain washers thin 100 Nos 70 20 14###Bitumen washers 100 Nos 40 18 7.2

Page 519: DAR_Vol_1

###Carriage of G.I. seam bolts and L.S. 2.73 1 2.73###Sundries L.S. 5.33 1 5.33

Labour:###Blacksmith first class Day .5 151.5 75.75###Beldar Day .5 135.25 67.62###Sundries L.S. 12.61 1 12.61###Mistry Day .28 151.5 42.42###Blacksmith first class Day .84 151.5 127.26###Carpenter 2nd class Day .62 141.6 87.79###Beldar Day 1.68 135.25 227.22

TOTAL 2 208.21Add 1 % for water charges 22.08TOTAL 2 230.29Add 15 % for contractor’s profit and overheads 334.54Cost of 9.04 metres 2 564.83Cost of 1.00 metre 283.72Say 283.7

12.Providing and fixing 15 cm wide 45 cm over all semi circular plain G.S. sheet gutterwith iron brackets 40x3mm size, bolts, nuts and washers etc. including makingnecessary connections with rain water pipes complete.

2

12.7.2 : 0.63mm thick with zinc coating not less than 275gm/mCodDescription Unit Quantity Rate Amount

0.63mm thick with zinc coating not less than2275gm/mConsider a length of 9.04mSheet used = 2.5x0.90m= 2 nos.Wt. = 2x11.82=23.64 Kg.= 0.2364quintal

###G.I. plain sheets quintal .2364 3 450.00 815.58###Carriage of sheets tonne .0236 47.29 1.12###Flats upto 10 mm in thickness quintal .0749 2 900.00 217.21###Galvanised steel bolts and nuts 10 Nos 20 9 18

25 mm long round head with slot###Galvanised steel bolts and nuts each 30 7 210

125 mm long

531Code Description Unit Quantity Rate Amount1210 G.I. plain washers thin 100 Nos 70 20 141208 Bitumen washers 100 Nos 40 18 7.29999 Carriage of G.I. seam bolts and L.S. 2.73 1 2.739999 Sundries L.S. 5.33 1 5.33

Labour:102 Blacksmith first class Day .5 151.5 75.75114 Beldar Day .5 135.25 67.629999 Sundries L.S. 12.61 1 12.61130 Mistry Day .28 151.5 42.42102 Blacksmith first class Day .84 151.5 127.26112 Carpenter 2nd class Day .62 141.6 87.79114 Beldar Day 1.68 135.25 227.22

Page 520: DAR_Vol_1

TOTAL 1,931.84Add 1% for water charges 19.32TOTAL 1,951.16Add 15% for contractor’s profit and overheads 292.67Cost of 9.04 metres 2,243.83Cost of 1.00 metre 248.21Say 248.2

### Providing non-asbestos high impact Polypropylene reinforced cement 6 mm thickcorrugated sheets (As per IS: 14871) roofing upto any pitch and fixing with polymer coatedJ, or L hooks, bolts and nuts 8mm dia. G.I. plain and bitumen washers or with self drillingfastener and EPDM washers etc. complete excluding the cost of purlins, rafters andtrusses corrugated sheets and including cutting to size and shape wherever required

### Code Description Unit Quantity Rate AmountUpto 60 degree pitchConsider a shed of 20x10 metres.(External dimensions of plinth).Area of roof-20.2x10.70m = 216.14 sqm.Materials:Sheets used = 2x20 nos.x3.00 mx 1.05m= 126.00sqm+2x20nos.x2.50mx1.05m=105.00sqm.= 231.00sqm. +Add 3% wastage = 6.93= 237.93sqm.

223 Non - Asbestos fibre cement cor sqm 237.93 205 48,775.656mm thick.2x20x0.42147= 1.68588 +2x20x0.35123= 1.4049= 3.0908+Add 3 % wastage = 0.092= 3.1835 Say 3.184 t

2273 Carriage of sheets tonne 3.184 47.29 150.571023 G.I. J or L hooks with nuts and b 10 Nos 476 58 2,760.81208 Bitumen washers 100 Nos 476 18 85.681209 Bitumen washers thick 100 Nos 476 27 128.529999 Carriage of bolts and nuts, washeL.S. 8.06 1 8.069999 Sundries L.S. 39.52 1 39.52

Labour:130 Mistry Day 2.34 151.5 354.51112 Carpenter 2nd class Day 9.34 141.6 1,322.54114 Beldar Day 9.34 135.25 1,263.23

532CodDescription Unit Quantity Rate Amount

TOTAL 54,889.08Add 1% for water charges 548.89TOTAL 55,437.97Add,.10% for contractor’s profit and overheads 8,315.7Cost of 216.14 sqm. 63,753.67Cost of 1.00 sqm. 294.96Say 294.95

Page 521: DAR_Vol_1

12.9 : Extra for straight cutting in non- asbestos polypropylene reinforced cementcorrugated, semi-corrugated 6 mm thick sheet roofing for making openings of areaexceeding 40 square decimeter for chimney stacks, skylights etc.

CodDescription Unit Quantity Rate AmountDetails of cost for 3 metres of peripheryArea of cutting 0.9mx0.6m=0.54sqm.Perimeter = 3 metresLabour:

###Carpenter 1st class Day .12 151.5 18.18###Beldar Day .12 135.25 16.23

TOTAL 34.41Add 1% for water charges .34TOTAL 34.75Add 15 % for contractor’s profit and overheads 5.21Cost for 3.00 metres 39.96Cost for 1.00 metre of periphery 13.32Say 13.3

### Extra for circular cutting in non-asbestos polypropylene reinforced cementcorrugated/semi-corrugated 6 mm thick sheet roofing for making openings of areaexceeding 40 square decimeter.

CodDescription Unit Quantity Rate AmountDetails of cost for 4 holes of 0.72 metrediameter i.e. 9.05 metre peripheryLabour:

###Carpenter 1 st class Day 1 151.5 151.5###Beldar Day 1 135.25 135.25

TOTAL 286.75Add 1% for water charges 2.87TOTAL 289.62Add 15% for contractor’s profit and overheads 43.44Cost for 9.05 metres 333.06Cost for 1.00 metre of periphery 36.8Say 36.8

12.11: Extra for providing and fixing wind ties of 40x 6mm flat iron sectionCodDescription Unit Quantity Rate Amount

Extra for providing and fixing wind ties of40x6mm flat iron section.M.S. flat 40x6mm = 30 metres+wastage @ 5% = 1.5 metres= 31.50 metres @ 1.9 Kg per metre= 59.85 Kg. = 0.5985 quintal

###Flats upto 10 mm in thickness quintal .5985 2 900.00 1 735.65###Carriage of sheet tonne .06 47.29 2.84

533CodDescription Unit Quantity Rate Amount###Sundries L.S. 20.67 1 20.67###Blacksmith first class Day .5 151.5 75.75###Beldar Day .5 135.25 67.62

TOTAL 1 902.53Add 1% for water charges 19.03

Page 522: DAR_Vol_1

TOTAL 1,921.56Add 15% for’contractor’s profit and overheads 288.23Cost of 30.00 metres 2 209.79Cost of 1.00 metre 73.66Say 73.65

### Providing and fixing ridges and hips in non-asbestos fibre cement high impactpolypropylene reinforced roofing with suitable fixing accessories or self drillingfastener and EPDM washer etc. complete.

12.12.1 Corrugated serrated adjustable ridgesCodDescription Unit Quantity Rate Amount

One piece corrugated serrated adjustableridgesConsider a shed of 20x10m (externaldimensions at plinth).Length of ridges 20.2 metreMaterials:Ridge piece required each of 1.22mm length =19nos. +Add 5% wastage = 0.95 No.19.95 Nos x 1.22 = 24.339 metre

###Non - Asbestos fibre cement cor metre 24.339 174 4 234.99serrated adjustable ridge.

###Carriage (The ridge is to be fixed L.S. 13.52 1 13.52same hooks as the Sheets)

###Sundries L.S. 6.76 1 6.76Labour:

###Mistry Day .14 151.5 21.21###Carpenter 2nd class Day .55 141.6 77.88###Beldar Day 1.64 135.25 221.81

TOTAL 4 576.17Add 1% for water charges 45.76TOTAL 4 621.93Add 15% for contractor’s profit and overheads 693.29Cost of 20.20 metre 5 315.22Cost of 1.00 metre 263.13Say 263.15

12.12 : Providing and fixing ridges and hips in non-asbestos fibre cement high impactpolypropylene reinforced roofing with suitable fixing accessories or self drillingfastener and EPDM washer etc. complete.

12.12.2 :Plain wing adjustable ridgesCodDescription Unit Quantity Rate Amount

Plain wing adjustable ridgesConsider a shed of 20x10m (externaldimensions at plinth).Length of ridges 20.2 metreMaterials:

534CodDescription Unit Quantity Rate Amount

Ridge piece required each of 1.22m length =19 nos. +Add 5% wastage = 0.95 No.

Page 523: DAR_Vol_1

19.95 nos x 1.22 = 24.339 metre###Non - Asbestos fibre cement plai metre 24.339 188 4 575.73

adjustable ridge.###Carriage (The ridge is to be fixed L.S. 13.52 1 13.52

same hooks as the Sheets)###Sundries L.S. 6.76 1 6.76

Labour:###Mistry Day .14 151.5 21.21###Carpenter 2nd class Day .55 141.6 77.88###Beldar Day 1.64 135.25 221.81

TOTAL 4 916.91Add 1 % for water charges 49.17TOTAL 4 966.08Add 15% for contractor’s profit and overheads 744.91Cost of 20.20 metre 5 710.99Cost of 1.00 metre 282.72Say 282.7

12.12 : Providing and fixing ridges and hips in non-asbestos fibre cement high impactpolypropylene reinforced roofing with suitable fixing accessories or self drillingfastener and EPDM washer etc. complete.

12.12.3: Close fitting adjustable ridgesCodDescription Unit Quantity Rate Amount

Close fitting adjustable ridgesConsider a shed of 20x10m (externaldimensions at plinth).Length of ridges 20.2 metreNo. of ridge pairs required, of length1.22m each = 22.00 nos. +Add 5% wastage =1.10 Nos.= 23.10 nos.x 1.22= 28.182 metre

###Non - Asbestos fibre cement closmetre 28.182 203 5 720.95adjustable ridge.

###Carriage L.S. 16.12 1 16.12###Sundries L.S. 7.15 1 7.15

Labour:###Mistry Day .14 151.5 21.21###Carpenter 2nd class Day .55 141.6 77.88###Beldar Day 1.64 135.25 221.81

TOTAL 6 065.12Add 1% for water charges 60.65TOTAL 6 125.77Add 15% for contractor’s profit and overheads 918.87Cost of 20.20 metre 7 044.64Cost of 1.00 metre 348.74Say 348.75

535### Providing and fixing ridges and hips in non-asbestos fibre cement high impact

polypropylene reinforced roofing with suitable fixing accessories or self drillingfastener and EPDM washer etc. complete.

12.12.4 Unserrated adjustable hipsCodDescription Unit Quantity Rate Amount

Page 524: DAR_Vol_1

Unserrated adjustable hipsConsider a shed with hip as 20.2 metresNo. of hi pieces required = 19 pairsLength of each pair 1.22 metresAdd 5 % wastage= 0.95 pairs= 19.95 pairs x 1.22 = 24.339 metre

###Non - Asbestos fibre cement uns metre 24.339 195 4 746.10adjustable ridge for hips.

###Carriage L.S. 6.76 1 6.76###Sundries L.S. 6.63 1 6.63

Labour:###Mistry Day .14 151.5 21.21###Carpenter 2nd class Day .55 141.6 77.88###Beldar Day 1.64 135.25 221.81

TOTAL 5 080.39Add 1% for water charges 50.8TOTAL 5 131.19Add 15% for contractor’s profit and overheads 769.68Cost of 20.20 metre 5 900.87Cost of 1.00 metre 292.12Say 292.1

12.13 : Providing and fixing non-asbestos fibre cement high impact polypropylenereinforced roofing accessories in all colour with polymer coated J or L hooks,bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers orwith self drilling fastener and EPDM washer etc. complete:

12.13.1: Corrugated apron piecesCodDescription Unit Quantity Rate Amount

Details for shed of 20.2 metres completedlengthMaterials:Corrugated appron pieces of 1.12 metrelength = 20 nos.+Add 5% wastage = 1.0 No.= 21 nos.x 1.12=23.52 metre

###Non - Asbestos fibre cement cor metre 23.52 126 2 963.52appron piece.

###Carriage of appron pieces. (The appron pieces L.S. 3.25 1 3.25are to be fixed with the same hooks as thesheets)

###Sundries L.S. 3.25 1 3.25Labour:

###Mistry Day .07 151.5 10.6###Carpenter 2nd class Day .28 141.6 39.65###Beldar Day .82 135.25 110.9

TOTAL 3 131.17Add 1 % for water charges 31.31TOTAL 3 162.48

536CodDescription Unit Quantity Rate Amount

Add. 15% for contractor’s profit and overheads 474.37Cost of 20.20 metre 3 636.85

Page 525: DAR_Vol_1

Cost of 1.00 metre 180.04Say 180.05

12.Providing and fixing non-asbestos fibre cement high impact polypropylenereinforced roofing accessories in all colours with polymer coated J or L hooks,bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers orwith self drilling fastener and EPDM washer etc. complete:

12.13.2 : Eave’s filler piecesCodDescription Unit Quantity Rate Amount

Details of eaves filler for a shed of 20.2 metrescomplete lengthMaterials:Eaves filler pieces of 1.016 metreslength = 20 nos.+Add 5% wastage = 1.0 No.= 21 nos.

###Non - Asbestos fibre cement eavesNo 21 93 1,953###(The eaves filler pieces are to be L.S. 3.25 1 3.25

the same hooks as the sheets)###Sundries L.S. 3.25 1 3.25

Labour:###Mistry Day .07 151.5 10.6###Carpenter 2nd class Day .28 141.6 39.65###Beldar Day .82 135.25 110.9

TOTAL 2,120.65Add 1 % for water charges 21.21TOTAL 2,141.86Add 10% for contractor’s profit and overheads 321.28Cost of 20.20 metre 2,463.14Cost of 1.00 metre 121.94Say 121.95

12.Providing and fixing non-asbestos fibre cement high impact polypropylenereinforced roofing accessories with polymer coated J or L hooks, bolts and nutsand or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drillingfastener and EPDM washer etc. complete:

12.13.3: North light curvesCodDescription Unit Quantity Rate Amount

Details of North light curve 20.2 metres longcomplete lengthMaterials:North light curves of 1.016 metresnominal length = 20 nos. +Add 5% wastage = 1.0 No.= 21 nos.x 1.016 = 21.336 metre

###Non - Asbestos fibre cement nortmetre 21.336 197 4 203.19curves.

537CodDescription Unit Quantity Rate Amount###G.I. J or L hooks with nuts and b 10 Nos 40 58 232###Bitumen washers 100 Nos 40 27 10.8

Page 526: DAR_Vol_1

###Bitumen washers thick 100 Nos 40 18 7.2###Carriage of hooks, nuts, washers and curves L.S. 9.88 1 9.88###Sundries L.S. 6.24 1 6.24

Labour:###Mistry Day .1 151.5 15.15###Carpenter 2nd class Day .3 141.6 42.48###Beldar Day 1 135.25 135.25

TOTAL 4 662.19Add 1 % for water charges 46.62TOTAL 4 708.81Add 15% for contractor’s profit and overheads 706.32Cost of 20.20 metre 5,415.13Cost of 1.00 metre 268.08Say 268.1

12.Providing and fixing non-asbestos fibre cement high impact polypropylenereinforced roofing accessories with polymer coated J or L hooks, bolts and nutsand or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drillingfastener and EPDM washer etc. complete:

12.13.4 : ventilator curvesCodDescription Unit Quantity Rate Amount

Details of ventilator curve 20.2 metres longcomplete lengthMaterials:North light curves of 1.016 metresnominal length = 20 nos. +Add 5% wastage = 1.0 No.= 21 nos.x 1.016 = 21.336 metre

###Non - Asbestos fibre cement venteach 21.336 267 5 696.71###G.I. J or L hooks with nuts and b 10 Nos 40 58 232###Bitumen washers 100 Nos 40 27 10.8###Bitumen washers thick 100 Nos 40 18 7.2###Carriage of hooks, nuts, washers L.S. 9.88 1 9.88###Sundries L.S. 6.24 1 6.24

Labour:###Mistry Day .1 151.5 15.15###Carpenter 2nd class Day .3 141.6 42.48###Beldar Day 1 135.25 135.25

TOTAL 6 155.71Add 1% for water charges 61.56TOTAL 6 217.27Add 10% for contractor’s profit and overheads 932.59Cost of 20.20 metre 7 149.86Cost of 1.00 metre 353.95Say 353.95

53812.13 : Providing and fixing non-asbestos fibre cement high impact polypropylene

reinforced roofing accessories with polymer coated J or L hooks, bolts and nutsand or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drillingfastener and EPDM washer etc. complete:

12.13.5: Barge boardsCodDescription Unit Quantity Rate Amount

Page 527: DAR_Vol_1

Details of cost for 9.70 metresCompleted length of barge boardsMaterials:Barge boards 2.50metres = 4 nos. x 2.50 =10.00 metreAdd 5% wastage = 0.50 metre.= 10.50 metre.

###Non - Asbestos fibre cement bar metre 10.5 232 2,4366 mm thick.

###Seam bolts and nuts 6 mm dia a 10 Nos 5 30 15###G.I. plain washers 100 Nos 10 21 2.1###Bitumen washers 100 Nos 5 18 .9###Carriage of barge boards, bolts, L.S. 9.36 1 9.36

washers###Sundries L.S. 6.76 1 6.76

Labour:###Mistry Day .04 151.5 6.06###Carpenter 2nd class Day .06 141.6 8.5###Beldar Day .4 135.25 54.1

TOTAL 2 538.78Add 1% for water charges 25.39TOTAL 2 564.17Add 15% for contractor’s profit and overheads 384.63Cost of 9.70 metre 2 948.80Cost of 1.00 metre 304Say 304

12.Providing and fixing non-asbestos fibre cement high impact polypropylenereinforced roofing accessories with polymer coated J or L hooks, bolts and nutsand or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drillingfastener and EPDM washer etc. complete:

12.13.6 : Ridge finialsCodDescription Unit Quantity Rate Amount

Details of a pair of ridge finialsMaterials:Ridge finials = 1pairAdd 5% wastage = 0.05pair.= 1.05 pair

###Non - Asbestos fibre cement ridgepair 1.05 84 88.2###Carriage, sundries, fixing charges L.S. 10.79 1 10.79

providing and fixing, seam bolts and nuts,with G.I. and bitumen washersTOTAL 98.99Add 1% for water charges .99TOTAL 99.98Add 15% for contractor’s profit and overheads 15Cost of 1.00 pair 114.98Say 115

53912.13 : Providing and fixing non-asbestos fibre cement high impact polypropylene

reinforced roofing accessories with polymer coated J or L hooks, bolts and nutsand or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling

Page 528: DAR_Vol_1

fastener and EPDM washer etc. complete:12.13.7: Special north light curvesCodDescription Unit Quantity Rate Amount

Details of special north light ventilator curve20.2 metres long complete lengthMaterials:Special north light curves of 1.016 metresnominal length = 20 nos. +Add 5% wastage = 1.0 No.= 21 nos.

###Non - Asbestos fibre cement spe each 21 275 5 775.00light curves.

###G.I. J or L hooks with nuts and b 10 Nos 40 58 232###Bitumen washers 100 Nos 40 27 10.8###Bitumen washers thick 100 Nos 40 18 7.2###Carriage of hooks, nuts, washers L.S. 9.88 1 9.88###Sundries L.S. 6.24 1 6.24

Labour:###Mistry Day .1 151.5 15.15###Carpenter 2nd class Day .3 141.6 42.48###Beldar Day 1 135.25 135.25

TOTAL 6 234.00Add 1 % for water charges 62.34TOTAL 6 296.34Add 15% for contractor’s profit and overheads 944.45Cost of 20 nos 7 240.79Cost of 1.00 no 362.04Say 362.05

### Providing and fixing non-asbestos fibre cement high impact polypropylenereinforced roofing accessories with polymer coated J or L hooks, bolts and nutsand or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drillingfastener and EPDM washer etc. complete:

12.13.8 S type louversCodDescription Unit Quantity Rate Amount

Details of cost for 8.74 metresMaterials:S type louvers = 5 nos.+Add 5% wastage = 0.25 nos.= 5.25 nos.

###Non - Asbestos fibre cement S ty each 5.25 161 845.25###Carriage 1 10.79 1 10.79###Galvanised steel bolts & nuts 10 each 6 13 78

27 cm long both sides threaded with 4galvanised steel nuts

###Galvanised steel bolts 10 mm di each 6 9 54long with nuts

###Bitumen washers 100 Nos 18 18 3.24###G.I. plain washers thin 100 Nos 36 20 7.2###Carriage of bolts and nuts and w L.S. 2.73 1 2.73###Sundries L.S. 13.39 1 13.39

Labour:

Page 529: DAR_Vol_1

540Code Description Unit Quantity Rate Amount### Carpenter 1st class Day 1 151.5 151.5### Beldar Day 1 135.25 135.25

st### Blacksmith 1 class Day .12 151.5 18.18

TOTAL 1 319.53Add 1 % for water charges 13.2TOTAL 1 332.73Add 15% for contractor’s profit and overheads 199.91Cost of 8.74 metres 1 532.64Cost of 1.00 metre 175.36Say 175.35

### Providing flat iron brackets 50x3mm size with necessary bolts, nuts and washersetc. for fixing asbestos cement/G.S. sheets gutters with purlins.

Code Description Unit Quantity Rate AmountDetail of cost for 20 metreMaterial:Flat 5 0x3 mm size

### Fits upto 10 mm in thickness quintal .1163 2 900.00 337.27### M.S. bolts 6 mm dia and 25 mm l10 Nos 38 18 68.4

hexagonal head### Galvanised steel bolts and nuts each 19 7 -133

125 mm long### G.I. plain washers thin 100 Nos 19 20 3.8### Sundries L.S. 1.04 1 1.04

st ### Blacksmith 1 class Day .38 151.5 57.57### Beldar Day .38 135.25 51.4

TOTAL 386.48Add 1% for water charges 3.86TOTAL 390.34Add 15% for contractor’s profit and overheads 58.55Cost of 20.00 metres 448.89Cost of 1.00 metre 22.44Say 22.45

12.15: Painting top of roofs with bitumen of approved quality at 17kg per 10 sqmimpregnated with a coat of coarse sand at 60 cudm per 10 sqm including cleaningthe slab surface with brushes and finally with a piece of cloth lightly soaked inkerosene oil complete :

12.15.1: With residual type petroleum bitumen of penetration 80/100Code Description Unit Quantity Rate Amount

Details of cost for 10 Sqm.Materials:

### Cost of Bitumen 80/100 tonne .017 22,500 382.5### Cost of kerosene oil litre 1.22 19 23.18### Cost of fuel for heating (steam coquintal .035 300 10.5### Carriage of bitumen 80/100 tonne .017 53.21 .9### Coarse sand cum .017 600 36### Carriage of coarse sand cum .06 53.21 3.19

Labour:### Beldar (for cleaning the surface, Day .38 135.25 51.4

kerosene oil, heating materials and carrying thehot tar over the roof)

### Painter Day .15 141.6 21.24

Page 530: DAR_Vol_1

541CodDescription Unit Quantity Rate Amount

###Sundries (Brushes and T and P) L.S. 13.52 1 13.52TOTAL 542.43Add 1% for water charges 5.42TOTAL 547.85Add 15% for contractor’s profit and overheads 82.18Cost of 10.00 sqm. 630.03Cost of 1 Sqm. 63Say 63

12.10 cm thick (average) mud phaska of damped brick earth on roofs laid to slopeconsolidated and plastered with 25 mm thick mud mortar mixed with bhusa at 35kg per cum of earth and gobri leaping with mix 1:1 (1 clay : 1 cow dung) andcovered with flat tile bricks of class designation 100 grouted with cement mortar1:3 (1 cement: 3 fine sand) mixed with 2% of integral water proofing compound byweight of cement and finished neat:

12.16.1: With F.P.S. brick tilesCodDescription Unit Quantity Rate Amount

Details of cost for 10.00sqm.Materials:Mud Phuska = 1.048 cum. +Wastage 20% = 0.209= 1.257 cum.

###Mud Phuska cum 1.257 20 25.14###Mud morta for 25 mm thick plastcum .263 156.85 41.25

phuskaBhusa 0.263x35 = 9.20 +5% wastage = 0.46= 9.66 Kg.

###Bhusa say 0.10 qiuntal quintal .1 200 20###Cowdung L.S. 5.33 1 5.33###Mud mortar for gobri leaping L.S. 8.06 1 8.06###Carriage of bhusa and cowdung L.S. 2.73 1 2.73###Tile bricks 22.9x11.4x4.4cm of d 1000 Nos 380 1,950 741

100###Carriage of tiles 1000 Nos 380 85.13 32.35

Cement mortar for grouting 1:3 (1 cemerit 3 cum .061 2,870 175.07fine sand)Rate as for item No. 3.3

###Integral water proofing compou kilogram .006 20 .12weight of cement

###Sundries L.S. 6.76 1 6.76Labour:

###Mason 2nd class Day 1.3 141.6 184.08###Beldar Day 3.75 135.25 507.19###Bhisti Day 1.1 138.45 152.3

TOTAL 1,901.38Add 1 % for water charges 19.01TOTAL 1,920.39Add 15% for contractor’s profit and overheads 288.06Cost of 10.00 sqm. 2,208.45Cost of 1 Sqm. 220.85Say 220.85

Page 531: DAR_Vol_1

54212.17 10cm thick (average) mud phaska of damped brick earth on roofs laid to slope

consolidated and plastered with 25mm thick mud mortar with bhusha at 35kg percum of earth and gobri leaping with mix 1:1 (1 clay : 1 cowdung) and covered withmachine moulded tile bricks of class designation 125 conforming to IS : 2690 (Part I)-1992 grouted with cement mortar 1:3(1 cement: 3 fine sand ) mixed with 2% of integralwater proofing compound by weight of cement and finished neat.

12.17.1With machine moulded F.P.S. brick tiles

CodDescription Unit Quantity Rate AmountDetails of cost for l0.00sqm.Materials:Mud Phuska = 1.048 cum.Wastage 20% = 0.209= 1.257 cum.

###Mud Phuska cum 1.257 20 25.14###Mud mortat for 25 mm thick plascum .263 156.85 41.25

phuskaBhusa 0.263x35 = 9.205% wastage = 0.46= 9.66 Kg. Say= 0.10 quintal.

###Bhusa quintal .1 200 20###Cowdung L.S. 5.33 1 5.33###Mud mortar for gobri leaping L.S. 8.06 1 8.06###Carriage of bhusa and cowdung L.S. 2.73 1 2.73###Machine moulded tile bricks of c1 000 380 2,717 1 032.46

designation 125 Nos###Carriage of tiles 1 000 Nos 85.13 380 32.35###Cement mortar for grouting 1:3 ( cum .061 2,870 175.07

coarse sand)###Integral water proofing compou kilogram .006 20 .12

weight of cement###Sundries L.S. 6.76 1 6.76

Labour:###Mason 2nd class Day 1.3 141.6 184.08###Beldar Day 3.75 135.25 507.19###Bhisti Day 1.1 138.45 152.3

TOTAL 2,192.84Add 1% for water charges 21.93TOTAL 2 214.77Add 15% for contractor’s profit and overheads 332.22Cost of 10.00sqm. 2 546.99Cost of 1 Sqm. 254.7Say 254.7

12.18 Extra for every additional 1 cm thickness of mud phaska

CodDescription Unit Quantity Rate Amount

Details of cost for 10.00 Sqm.Materials:-

Page 532: DAR_Vol_1

543CodDescription Unit Quantity Rate Amount

for 10 cm thickness.Mud Phuska = 1.048 cum. +Wastage 20% = 0.209= 1.257Quantity for ICM thickness 1.257/10=0.1257Say 0.13 cum

###Mud cum .13 20 2.6###Beldar cum .07 135.25 9.47###Bhisti Day .04 138.45 5.54###Labour for leaping and carring to L.S. 26.91 1 26.91

TOTAL 44.52Add 1% for water charges .45TOTAL 44.97Add 15% for contractor’s profit and overheads 6.75Cost of 10.00 sqm. 51.72Cost of 1 Sqm. 5.17Say 5.15

### Providing and laying brick tiles of class designation 100 over mumty roofs groutedwith cement mortar 1:3 (1 cement: 3 fine sand) mixed with 2% of integral waterproofing compound by weight of cement, over a 12 mm layer of cement mortar 1:3(1 cement: 3 fine sand) and finished neat:

12.19.1 With F.P.S. brick tilesCodDescription Unit Quantity Rate Amount

Details of cost for 10 square metre.

###Bricks tiles of designation 100 1 000 380 1,950 741Nos

###Carriage of tiles 1 000 380 85.13 32.35Nos

Cement mortar for grouting 1:3 ( cum .179 2,870 513.73fine sand) (Rate asper No 3.3)

###Integral water proofing compou kilogram .005 20 .1weight of cementLabour:

###Mason 2nd class Day .81 141.6 114.7###Coolie Day 1.08 135.25 146.07###Bhisti Day .27 138.45 37.38###Sundries L.S. 1.82 1 1.82

TOTAL 1 587.15Add 1% for water charges 15.87TOTAL 1 603.02Add 15% for contractor’s profit and overheads 240.45Cost of 10.00 sqm. 1 843.47Cost of 1 Sqm. 184.35Say 184.35

Materials

Page 533: DAR_Vol_1

544### Providing and laying pressed clay tiles (as per approved pattern 20 mm nominal

thickness and of approved size) on roofs jointed with cement mortar 1:4 (1 cement : 4coarse sand) mixed with 2% integral water proofing compound laid over a bed of 20mm thick cement mortar 1:4(1 cement: 4 coarse sand) and finished neat complete.

CodDescriptio Unit Quantity Rate AmountDetails of cost for 10 sqm.Materials

###Manglore t1000 Nos 160 8 900.00 1,424###Carriage of 1000 Nos 160 85.13 13.62

Cement morcum .37 2,578.45 954.03(Rate as per of No 3.9.)

###Integral w kilogram .01 20 .2weight of cementCement morcum .2 2 578.45 515.69(Rate as per item No 3.9)Labour

###Mason 1 st Day .6 151.5 90.9###Beldar Day 2.6 135.25 351.65###Sundries L.S. 13 1.00 13.00

TOTAL 3 363.09Add 1 % for water charges 33.63TOTAL 3 396.72Add 15% for contractor’s profit and overhea 509.51Cost of 10.00 sqm. 3 906.23Cost of 1 Sqm. 390.62Say 390.6

### Providing gola 75x75 mm in cement concrete 1:2:4 (1 cement: 2 coarse sand : 4stone aggregate 10mm and down gauge) including finishing with cement mortar1:3 (1 cement: 3 fine sand) as per standard design :

12.21.1 In 75x75mm deep chaseCodDescriptio Unit Quantity Rate Amount

Details of cost for 10 metres cement concrete###Stone Aggrecum .0836 700 58.52

nominal size###Carriage o cum .0836 53.21 4.45###Coarse san cum .0418 600 25.08###Carriage of cum .0418 53.21 2.22###Portland tonne .03 4,500 135###Carriage o tonne .03 47.29 1.42###Beldar Day .085 135.25 11.5###Coolie Day .056 135.25 7.57###Bhisti Day .025 138.45 3.46###Mason 1 st Day .005 151.5 .76###Mason 2nd Day .005 141.6 .71###Mate Day .0037 138.45 .51###Hire and r L.S. 2.47 1 2.47###Sundries L.S. 1.3 1 1.3###Mason 1 st Day .15 151.5 22.72###Mason 2nd Day .15 141.6 21.24###Sundries L.S. 5.07 1 5.07###Mason 1st Day .25 151.5 37.88###Mason 2nd Day .25 141.6 35.4

Page 534: DAR_Vol_1

###Beldar Day 1 135.25 135.25###Carriage L.S. 8.06 1 8.06

545CodDescriptio Unit Quantity Rate Amount

Cement morcum .009 2 870.00 25.83fine sand) (Rate as per item No. 3.3)

###Mason Day .081 146.55 11.87###Coolie Day .101 135.25 13.66###Bhisti Day .033 138.45 4.57###Hire and r L.S. 1.69 1 1.69###Sundries L.S. 1.43 1 1.43

TOTAL 579.64Add 1% for water charges 5.8TOTAL 585.44Add 15% fof contractor’s profit 87.82Cost of 10.00 metre 673.26Cost of 1.00 metre 67.33Say 67.35

### Making khurras 45x45 cm with average minimum thickness of 5 cm cement concrete1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate of 20 mm nominal size)over P.V.C. sheet 1mx 1mx 400 micron, finished with 12mm cement plaster 1:3 (1cement : 3 coarse sand) and a coat of neat cement rounding the edge and makingand finishing the outlet complete.

CodDescriptio Unit Quantity Rate AmountDetails of cost for 1 no.

###Stone Aggrecum .0067 700 4.69nominal size

###Stone Aggrecum .0022 700 1.54nominal size

###Carriage o cum .0089 53.21 .47nominal size

###Coarse san cum .0044 600 2.64###Carriage of cum .0044 53.21 .23###Portland tonne .0032 4,500 14.4###Carriage o tonne .0032 47.29 .15###Beldar Day .009 135.25 1.22###Coolie Day .006 135.25 .81###Bhisti Day .0027 138.45 .37###Mason 1 st Day .0005 151.5 .08###Mason 2nd Day .0005 141.6 .07###Mate Day .0004 138.45 .06###Hire and r L.S. .26 1 .26###Sundries L.S. .13 1 .13###PVC sheet sqm 1 26 26

Cement morcum .0041 3,169.6 13(Rate as per item No. 3.8)

###Mason Day .0235 146.55 3.44###Coolie Day .0235 135.25 3.18###Bhisti Day .0078 138.45 1.08###Sundries L.S. .39 1 .39###Portland tonne .0006 4,500 2.7###Carriage o tonne .0006 47.29 .03

Page 535: DAR_Vol_1

###Mason Day .008 146.55 1.17###Coolie Day .008 135.25 1.08###Rounding oL.S. .26 1 .26###Sundries L.S. 13.52 1 13.52

TOTAL 92.97Add 1% for water charges .93TOTAL 93.9Add 15% for contractor’s profit and overhea 14.08Cost of 1 no. 107.98Say 108

54612.23 Providing sand stone slab for roofing and laying them in cement mortar 1 : 4 (1

cement: 4 coarse sand) over wooden karries or R.C.C. battens (Karries andbattens to be paid separately) including pointing the ceiling joints with cementmortar 1:3 (1 cement: 3 fine sand ) complete :

12.Red sand stone slab12.23.1.1 40 to 50 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials :

###Stone slab including wastage @ sqm 11 145 1 595.00###Carriage of slab tonne 1.27 47.29 60.06

Cement mortar l:4 (1 cement : 4 cum .0095 2 578.00 24.5(Rate as per item No. 3.9)Cement mortar for grouting 1:3(1cum .0075 2 870.00 21.52fine sand)Rate as per item No. 3.3Labour:

###Mason Day 1.52 146.65 222.76###Bandhani Day 1.82 138.45 41.54###Coolie Day 1.52 135.25 205.58###Bhisti Day .3 138.45 41.54###Sundries L.S. 16.12 1 16.52

TOTAL 2,439.06Add 1 % for water charges 24.39TOTAL 2,463.45Add 15% for contractor’s profit and overheads 369.52Cost of 10.00 sqm. 2,832.97Cost of 1 Sqm. 283.3Say 283.3

### Providing sand stone slab for roofing and laying them in cement mortar 1:4(1cement: 4 coarse sand) over wooden karries or R.C.C. battens (Karries andbattens to be paid separately) including pointing the ceiling joints with cementmortar 1:3 (1 cement: 3 fine sand ) complete :

12.White sand stone slab :12.23.2.1 40 to 50 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Materials :

Page 536: DAR_Vol_1

###Stone Slab including wastage @ sqm 11 160 1,760###Carriage of slab tonne 1.27 47.29 60.06###Cement mortar 1:4 (1 cement: 4 cum .0095 2,578.45 24.5

(Rate as per item No. 3.9)###Mason Day 1.52 146.55 222.76###Bandhani Day 1.82 138.45 251.98###Coolie Day 1.52 135.25 205.58###Bhisti Day .3 138.45 41.54###Sundries L.S. 16.12 16.12

Cement mortar for grouting 1:3( cum .0075 2,870 21.52fine sand)Rate as per item No. 3.3TOTAL 2,604.06Add 1% for water charges 26.04TOTAL 2,630.1Add 15% for contractor’s profit and overheads 394.52Cost of 10.00 sqm. 3,024.62Cost of 1 Sqm. 302.46Say 302.45

547### Providing and fixing insulating board ceiling of approved quality with necessary

nails etc. complete (framework to be paid separately):12.24.1 Natural colour insulating board12.24.1.1 12 mm thick

Code Description Unit Quantity Rate AmountDetails of cost for 10sqm.Material :-

### Insulating board including 10% wastage = sqm 11 175 1,92511.00Sqm.

### Carriage of material L.S. 17.55 1 17.55### Nails L.S. 26.91 1 26.91

Labour:Carpenter 1st class Day 2.5 151.5 378.75

### Beldar Day 2 135.25 270.5### Scaffolding L.S. 31.07 1 31.07### Sundries L.S. 31.07 1 31.07

TOTAL 2,680.85Add 15% for water charges 26.81TOTAL 2,707.66Add 10% for contractor’s profit and overheads 406.15Cost of 10.00 sqm. 3,113.81Cost of 1.00 sqm. 311.38Say 311.4

### Providing and fixing insulating board ceiling of approved quality with necessarynails etc. complete (frame work to be paid separately):

12.24.2 White face insulating board12.24.2.1 12 mm thickCode Description Unit Quantity Rate Amount

Details of cost for 10sqm.Material :-

1.00

Page 537: DAR_Vol_1

### White face insulating board 12 mm thick i sqm 11 239 2,62910% wastage 11 Sqm.

### Carriage of material L.S. 17.55 1 17.55### Nails L.S 26.91 1 26.91

Labour:111 Carpenter 1st class Day 2.5 151.5 378.75

### Beldar Day 2 135.25 270.5### Scaffolding L.S 31.07 1 31.07### Sundries L.S 31.07 1 31.07

TOTAL 3,384.85Add 1 % for water charges 33.85TOTAL 3,418.7Add 15% for contractor’s profit and overheads 512.8Cost of 10.00 sqm. 3,931.5Cost of 1.00 sqm. 393.15Say 393.15

548### Providing and fixing insulating board ceiling of approved quality with necessary

nails etc. complete (frame work to be paid separately):12.Flame retardant face insulating board12.24.3.1 12 mm thick

CodDescription Unit Quantity Rate AmountDetails of cost for 10sqm.Material :-

###Flame retardent face insulating sqm 11 208 2,288thick including 10% wastage 11.00 Sqm.

###Carriage of material L.S. 17.55 1 17.55###Nails L.S. 26.91 1 26.91

Labour:###Carpenter 1 st class Day 2.5 151.5 378.75###Beldar Day 2 135.25 270.5###Scaffolding L.S. 31.07 1 31.07###Sundries L.S. 31.07 1 31.07

TOTAL 3,043.85Add 1% for water charges 30.44TOTAL 3,074.29Add 15% for contractor’s profit and overheads 461.14Cost of 10.00 sqm. 3,535.43Cost of 1.00 sqm. 353.54Say 353.55

### Providing and fixing flat pressed 3 layer medium density particle board or gradedparticle board (Grade I) IS: 3087 marked in ceiling with necessary nails etc. complete(frame work to be paid separately):

12.25.1 12 mm thick

CodDescription Unit Quantity Rate AmountDetails of cost for 10sqm.Materials :-

###Standard quality board 12mm thisqm 11 Sqm 2,838

Page 538: DAR_Vol_1

10% wastage = 11. Sqm.###Carriage L.S. 14.95 1 14.95###Nails L.S. 26.91 1 26.91

Labour:###Carpenter 1 st class Day 2.5 151.5 378.75###Beldar Day 2 135.25 270.5###Scaffolding L.S. 31.07 1 31.07###Sundries L.S. 31.07 1 31.07

TOTAL 3,591.25Add 1 % for water charges 35.91TOTAL 3,627.16Addr 15% for contractor’s profit and overheads 544.07Cost of 10.00 sqm. 4,171.23Cost of 1.00 sqm. 417.12Say 417.1

54912.26 Providing and fixing plain multipurpose cement board (high pressure steam cured ) as

per IS 14862: 2000 with suitable fibre cement screw in ceiling etc complete, (framework to be paid separately ).

12.26.1 6 mm thick cement board

CodDescription Unit Quantity Rate AmountDetails of cost for 10sqm.Materials :-

###Non - Asbestos multi purpose fi sqm 11 180 1,980board 6mm thick.

###Carriage L.S. 14.95 1 14.95###Nails L.S. 26.91 1 26.91

Labour:###Carpenter 1st class Day 2.5 151.5 378.75###Beldar Day 2 135.25 270.5###Scaffolding L.S. 31.07 1 31.07###Sundries L.S. 31.07 1 31.07

TOTAL 2,733.25Add 1 % for water charges 27.33TOTAL 2,760.58Add 15% for contractor’s profit and overheads 414.09Cost of 10.00 sqm. 3,174.67Cost of 1.00 sqm. 317.47Say 317.45

### Extra for Circular cutting and waste in ceiling with:12.27.1 2nd class teak wood planks 20 mm thick

CodDescription Unit Quantity Rate AmountDetails of cost for 10 holesMaterials :-0.5 metre dia. each = 10x22/7x0.5=15.71mArea = 10x(22/7)/4x0.5x0.5 = 1.96sqm. +Wastage @ 10% = 0.19 sqm.= 2.15 sqm.

###Teak wood 2nd class 10 cudm 41.16 410 1 687.56###Carriage cum .041 60.81 2.49

Page 539: DAR_Vol_1

###M.S. screws 40 mm long 100 Nos 31 30 9.3Labour:

###Carpenter 1 st class Day 2.65 151.5 401.48###Carpenter 2nd class Day . .145 141.6 20.53###Beldar Day 2.79 135.25 377.35###Scaffolding L.S. 7.8 1 7.8###Sundries L.S. 14.69 1 14.69

TOTAL 2,521.2Add 1 % for water charges 25.21TOTAL 2,546.41Add 15% for contractor’s profit and overheads 381.96Cost of 15.71 metre 2,928.37Cost of 1.00 metre 186.4Say 186.4

550### Extra for Circular cutting and waste in ceiling with:

12.27.2 Natural colour insulating board12.27.2.1 12 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 15.71 metreMaterials :-0.5 metre dia. each = 10x22/7x0.5=15.71mArea = 10x(22/7)/4x0.5x0.5 = 1.96sqm. +Wastage @ 10% = 0.19 sqm.= 2.15 sqm.

###Insulating board sqm 2.15 175 376.25###Carriage L.S. 3.38 1 3.38###Nails- L.S. 5.33 1 5.33

Labour:###Carpenter 1st class Day .49 151.5 74.24###Beldar Day .39 135.25 52.75###Scaffolding L.S. 6.11 1 6.11###Sundries L.S. 6.11 1 6.11###Carpenter 1 st class Day 2.5 151.5 378.75###Beldar Day 2.5 135.25 338.12###Scaffolding L.S. 10.79 1 10.79

TOTAL 1,251.83Add 1 % for water charges 12.52TOTAL 1 264.35Add 15% for contractor’s profit and overheads 189.65Cost of 15.71 metre 1 454.00Cost of 1.00 metre 92.55Say 92.55

### Extra for Circular cutting and waste in ceiling with:12.White face insulating board:12.27.3.1 12 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 15.71 metreMaterials :-0.5 metre dia. each = 10x22/7x0.5=15.71mArea= 10x(22/7)/4x0.5x0.5 = 1.96sqm. +Wastage @ 10% = 0.19 sqm.

Page 540: DAR_Vol_1

= 2.15 sqm.###Insulating board sqm 2.15 239 513.85###Carriage L.S. 3.38 1 3.38###Nails- L.S. 5.33 1 5.33

Labour:###Carpenter 1st class Day .49 151.5 74.24###Beldar Day .39 135.25 52.75###Scaffolding L.S. 6.11 1 6.11###Sundries L.S. 6.11 1 6.11###Carpenter 1st class Day 2.5 151.5 378.75###Beldar Day 2.5 135.25 338.12###Scaffolding L.S. 10.79 1 10.79

TOTAL 1,389.43Add 1 % for water charges 13.89TOTAL 1,403.32Add 15% for contractor’s profit and overheads 210.5Cost of 15.71 metre 1,613.82Cost of 1.00 metre 102.73Say 102.75

551### Extra for Circular cutting and waste in ceiling with:

12.Flame retardant face insulating board:12.27.4.1 12 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 15.71 metreMaterials :-0.5 metre dia. each = 10x22/7x0.5=15.71mArea= 10x(22/7)/4x0.5x0.5 = 1.96sqm. +Wastage @ 10% = 0.19 sqm.= 2.15 sqm.

###Insulating board sqm 2.15 208 447.2###Carriage L.S. 3.38 1 3.38###Nails- L.S. 5.33 1 5.33

Labour:###Carpenter 1st class Day .49 151.5 74.24###Beldar Day .39 135.25 52.75###Scaffolding L.S. 6.11 1 6.11###Sundries L.S. 6.11 1 6.11###Carpenter 1 st class Day 2.5 151.5 378.75###Beldar Day 2.5 135.25 338.12###Scaffolding L.S. 10.79 1 10.79

TOTAL 1,322.78Add 1% for water charges 13.23TOTAL 1,336.01Add 15% for contractor’s profit and overheads 200.4Cost of 15.71 metre 1,536.41Cost of 1.00 metre 97.8Say 97.8

### Extra for Circular cutting and waste in ceiling with:12.Standard quality hard board sheet:12.27.5.1 3 mm thickCodDescription Unit Quantity Rate Amount

Page 541: DAR_Vol_1

Details of cost for 15.71 metreMaterials :-0.5 metre dia. each = 10x22/7x0.5= 15.71mArea= 10x(22/7)/4x0.5x0.5 = 1.96sqm. +Wastage @ 10% = 0.19 sqm.= 2.15 sqm.

###Insulating board sqm 2.15 103 221.45###Carriage L.S. 2.73 1 2.73###Nails- L.S. 5.33 1 5.33

Labour:###Carpenter 1 st class Day .49 151.5 74.24###Beldar Day .39 135.25 52.75###Scaffolding L.S. 6.11 1 6.11###Sundries L.S. 6.11 1 6.11###Carpenter 1st class Day 2.5 151.5 378.75###Beldar Day 2.5 135.25 338.12###Scaffolding L.S. 10.79 1 10.79

TOTAL 1,096.38Add 1% for water charges 10.96TOTAL 1,107.34Add 15% for contractor’s profit and overheads 166.1Cost of 15.71 metre 1,273.44Cost of 1.00 metre 81.06Say 81.05

55212.27 Extra for Circular cutting and waste in ceiling with:12.27.5 Standard quality hard board sheet:12.27.5.24.5 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 15.71 metreMaterials :-0.5 metre dia. each = 10x22/7x0.5=15.71mArea= 10x(22/7)/4x0.5x0.5 = 1.96sqm. +Wastage @ 10% = 0.19 sqm.= 2.15 sqm.

###Insulating board sqm 2.15 120 258###Carriage L.S. 2.86 1 2.86###Nails- L.S. 5.33 1 5.33

Labour:###Carpenter 1 st class Day .49 151.5 74.24###Beldar Day .39 135.25 52.75###Scaffolding L.S. 10.79 1 6.11###Sundries L.S. 6.11 1 6.11###Carpenter 1 st class Day 2.5 151.5 378.75###Beldar Day 2.5 135.25 338.12###Scaffolding L.S. 10.79 1 10.79

TOTAL 1 133.06Add 1% for water charges 11.33TOTAL 1 144.39Add 15% for contractor’s profit and overheads 171.66Cost of 15.71 metre 1,316.05Cost of 1.00 metre 83.77

Page 542: DAR_Vol_1

Say 83.75

12.28 Extra for providing and fixing ceiling to curved surfaces in narrow widthsCodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.Labour:

###Carpenter 1 st class Day 1 151.5 151.5###Carpenter 2nd class Day, 1 141.6 141.6###Beldar Day 2 135.25 270.5

TOTAL 563.6Add 1% for water charges 5.64TOTAL 569.24Add 15% for contractor’s profit and overheads 85.39Cost of 10.00 sqm. 654.63Cost of 1.00 sqm. 65.46Say 65.45

12.29 Providing and fixing false ceiling with 12 mm thick plain/ semi perforated or withdesign ceiling tiles of BWP type phenol formaldehyde synthetic resin bonded pressedparticle board conforming to IS:3087 finished with a coat of aluminium primer onboth sides & edges and two coats of synthetic enamel paint of approved quality onexposed face fixed to a grid made out of anodised aluminium (with 15 micron anodiccoating) T-sections 35 xl5xl.5 mm size main runners and cross runners 23.5x19x1.5mm fixed to main runners placed 600 mm centre to centre both ways so as to forma grid of 600 mm square. The frame work shall be suspended from ceiling by leveladjusting hangers of 6 mm dia M.S rod fixed to roof slab by means of ceiling cleats.The suspenders shall be placed 600x 1200 mm centre to centre including fixing tothe frame with C.P brace screws and applying a priming coat of zinc chromate yellowprimer ( aluminium frame work shall be paid separately.)

553CodDescription Unit Quantity Rate Amount

Details of cost for 10.00 sqm.Materials :-

###Plain ceiling tiles 600x600x12 mmeach 11 90 990Area including 10% wastage = 11.00 sqm

###Carriage of tiles L.S. 14.82 1 14.82###C.P. brase screws L.S. 26.91 1 26.91

Labour:###Carpenter 1 st class Day 2.5 151.5 378.75###Beldar Day 2 135.25 270.5###Scaffolding L.S. 1 31.07###Sundries L.S. 31.07 1 31.07

TOTAL 1,743.12Add 1% for water charges 17.43TOTAL 1,760.55Add 15% for contractor’s profit and overheads 264.08Cost of 10.00 sqm. 2,024.63Cost of 1.00 sqm. 202.46Say 202.45

12.30 Extra for providing 3 mm thick translucent white acrylic plastic sheets of approvedquality in false ceiling instead of 12 mm thick plain/or with design particle board

31.07

Page 543: DAR_Vol_1

ceiling tiles in item above.CodDescription Unit Quantity Rate Amount

Details of cost for 10 sqm.###Cost of 3 mm thick translucent whsqm 10 515 5,150

plastic sheet###Cost of 12mm thick plain particlesqm 10 225 -2,250

Difference of cost 2,900Add 1 % for water charges 29TOTAL 2,929Add 15% for contractor’s profit and overheads 439.35Cost of 10.00 sqm. 3,368.35Cost of 1.00 sqm. 336.84Say 336.85

12.31 Providing 10 mm thick plaster of Paris (gypsum anhydrous) ceiling upto a height of5 m above floor level over first class kail wood strips 25x6 mm with 10 mm gap inbetween and reinforced with rabbit wire mesh fixed to wooden frame (frame workto be paid separately):

12.31.1Flat surfacesCodDescription Unit Quantity Rate Amount

Details of cost for 4.00x2.5=10sqm.Materials :-Wooden strips of 1 st class kail wood72x40x0.25x0.06 = 43.20 cudm. +Add 10% wastage = 4.32 cudm.= 47.52

###Kail wood 1 st class 10 cudm 47.52 186 883.87###Carriage of timber cum .0475 60.81 2.89###Nail required for fixing the laths kilogram .75 40 30

work including breakage and wastage of nailsRabbit wire mesh required for reinforcement

554CodDescription Unit Quantity Rate Amount

=2.5x4 = 10.00sqm.+Add 2%wastage =0.20 sqm.= 10.2 sqm.

###Rabbit wire mesh sqm 10.2 38 387.6Plaster of paris -2.5x4.0x10x1121/1000= 112.10 kg.Add for plaster of paris joining into the side ofthe laths-2.5x4.0x4.0032x1121 = 44.87 kg.= 156.97+Add 40% wastage = 62.79= 219.76

###Plaster of Paris kilogram 219.76 2.5 549.4###Carriage of Plaster of Paris tonne .22 47.29 10.4###Carriage of wiremesh and nails etc. L.S. 2.73 1 2.73

Labour:st

###Carpenter 1 class Day 1.6 151.5 242.4###Beldar Day 1.6 135.25 216.4

For doing plaster of paris over wooden strips

Page 544: DAR_Vol_1

###Mason Day 3.23 151.5 489.34###Beldar Day 3.23 151.5 436.860l0 Bhisti Day .54 138.45 74.76###Scaffolding L.S. 83.98 1 83.98###Sundries L.S. 53.82 1 53.82

TOTAL 3,464.45Add 1% for water charges 34.64TOTAL 3,499.09Add 15% for contractor’s profit and overheads 524.86Cost of 10.00 sqm. 4,023.95Cost of 1.00 sqm. 402.4Say 402.4

### Providing 10 mm thick plaster of Paris (gypsum anhydrous) ceiling upto a heightof 5 m above floor level over first class kail wood strips 25x6 mm with 10 mm gap inbetween and reinforced with rabbit wire mesh fixed to wooden frame (frame workto be paid separately):

12.31.2 Curved surfacesCodDescription Unit Quantity Rate Amount

Details of cost for 4.00x2.5=10sqm.Materials :-Wooden strips of 1st class kail wood72x40x0.25x0.06 = 43.20 cudm. +Add 10% wastage = 4.32 cudm.= 47.52

###Kail wood 10 cudm 47.52 186 883.87###Carriage of timber cum .0475 60.81 2.89###Nail required for fixing the laths to frame kilogram .75 40 30

work including breakage and wastage of nailsRabbit wire mesh required for reinforcement=2.5x4 = 10.00sqm.+Add 2% wastage = 0.20 Sqm.= 10.2 sqm.

###Rabbit wire mesh Sqm 10.2 38 387.6

555CodDescription Unit Quantity Rate Amount

Plaster of paris -2.5x4.0x10x1121/1000= 112.10 kg.Add for plaster of paris joining into the side ofthe laths-2.5x4.0x4.0032x1121 = 44.87 kg.= 156.97+Add 40% wastage = 62.79= 219.76

###Plaster of Paris kilogram 219.76 2.5 549.4###Carriage of Plaster of Paris tonne .22 47.29 10.4###Carriage of wiremesh and nails etL.S. 2.73 1 2.73

Labour:st

###Carpenter I class Day 1.6 151.5 242.4###Beldar Day 1.6 135.25 216.4###Mason Day 3.23 151.5 489.34

Page 545: DAR_Vol_1

###Beldar Day 3.23 135.25 436.86###Bhisti Day .54 138.45 74.76###Scaffolding L.S. 83.98 1 83.98###Sundries L.S. 53.82 1 53.82

st###Carpenter I class Day .5 151.5 75.75###Mason Day 1 151.5 151###Beldar Day 1.5 135.25 202.88

TOTAL 3,894.58Add 1% for water charges 38.95TOTAL 3,933.53Add 15% for centractor’s profit and overheads 590.03Cost of 10.00 sqm. 4,523.56Cost of 1.00 sqm. 452.36Say 452.35

12.32 Extra for any sunk or raised mouldings in the plaster of Paris (Gypsum anhydrous)ceiling

CodDescription Unit Quantity Rate AmountDetails of cost for 10 sqm.

###Plaster of Paris kilogram 109.88 2.5 274.7###Carriage of Plaster of Paris tonne .11 47.29 5.2

Labour:###Mason Day 2 151.5 303###Beldar Day 2 135.25 270.5###Bhisti Day .25 138.45 34.61###Scaffolding and Sundries L.S. 13.52 1 13.52

TOTAL 901.53Add 1% for water charges 9.02TOTAL 910.55Add 15% for contractor’s profit and overheads 136.58Cost of 10.00 sqm. 1,047.13Cost of 1.00 sqm. 104.71Say 104.7

55612.33 Extra for providing plaster of Paris (Gypsum anhydrous) ceiling above 5 metres

hight from floor level

CodDescription Unit Quantity Rate AmountDetails of cost for l0sqm/metre height

###Scaffolding L.S. 13.52 1 13.52Labour:

###Mason Day 1 151.5 151.5###Beldar Day 1 135.25 135.25###Bhisti Day .25 138.45 34.61

TOTAL 334.88Add 1% for water charges 3.35TOTAL 338.23Add 15% for contractor’s profit and overheads 50.73Cost of.10.00sqm / metre height 388.96Cost of 1.00 sqm. / metre height 38.9

12.34 Providing and fixing thermal insulation of ceiling (under deck insulation) with ResinBonded Fibre glass wool conforming to IS : 8183 density 24kg/m3, 50mm thick,

Page 546: DAR_Vol_1

wrapped in 200 G Virgin Polythene bags fixed to ceiling with metallic cleats (50x50x3mm) @ 60 cm and wire mesh of 12.5mm x 24g wire and mesh, for top most ceiling ofbuilding.

CodDescription Unit Quantity Rate AmountDetails of cost for 10.00sqm.Area for 10.00sqm. (Finished surface) =10.00sqm.+Add 10% for overlappings & wastage =1.00sqm.= 11.00sqm.

3###Resin Bonded Glass wool 24 kg/m 50 mm thSqm 11 163 1,793###Sundries including GI wire 20 SWG and L.S. 104 1 104

Virgin polythene bags 200 gram###GI chiken mesh 12.5mm x 24 SWG L.S. 351 1 351

Labour:###Carpenter 1st class Day 1 151.5 151.5###Beldar Day 2 135.25 270.5

TOTAL 2,670Add 1 % for water charges 26.7TOTAL 2,696.7Add 15% for contractor’s profit and overheads 404.5Cost for 10.00sqm. 3,101.2Cost for 1sqm. 310.12Say 310.1

12.35 Providing and fixing thermal insulation with Resin Bonded Fibre glass woolconforming to IS : 8183. Density 16kg/m3 50mm thick, wrapped in 200G VirginPolythene bags placed over existing false ceiling and held in position by criss-crossing GI wire.

CodDescription Unit Quantity Rate AmountDetails of cost for 10.00sqm.Area for 10.00sqm. (Finished surface) =10.00sqm.+Add 10% for overlappings & wastage =1.00sqm.= 11.00sqm.

3###Resin Bonded Glass wool 16 kg/m 50 mm sqm 11 114 1,254

557CodDescription Unit Quantity Rate Amount

thick###Sundries including GI wire 20 S L.S. 52 1 52

Virgin polythene bags 200 gramLabour:

###Carpenter 1st class Day .5 151.5 75.75###Beldar Day .5 135.25 67.62

TOTAL 1,449.37Add 1% for water charges 14.49TOTAL 1,463.86AAdd 15% for contractor’s profit and overheads 219.58Cost for 10.00sqm. 1,683.44

Page 547: DAR_Vol_1

Cost for 1sqm. 168.34Say 168.35

### Thermal Insulation of roofing with Expanded polystyrene fixed with suitableadhesive to the false ceiling as per the directions of the Engineer-in-charge :

12.36.1 With Type N - Normal 50 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for10.00sqm.Cost of materials :Expanded Polystyrens lx10=10.00sqm. +Add wastage 10%= 1.00sqm.= 11.00sqm.

###Expanded polystyrene type N- N sqm 11 108 1,188###Adhesive Bitumen hot sealing c kilogram .25 20 5

grade A###Sundries L.S. 13 1 13

Labour:###Carpenter 1st class Day .5 151.5 75.75###Beldar Day .5 135.25 67.62

TOTAL 1,349.37Add 1 % for water charges 13.49TOTAL 1,362.86Add 15% for contractor’s profit and overheads 204.43Cost for 10.00sqm. 1,567.29Cost for 1sqm. 156.73Say 156.75

### Thermal Insulation of roofing with Expanded polystyrene fixed with suitable adhesiveto the false ceiling as per the directions of the Engineer-in-charge :

12.36.2 With Type SE - Self Extinguishing type 50 mm thickCodDescription Unit Quantity Rate Amount

Details of cost for 10.00sqm.Cost of materials :Expanded Polystyrens lx10=10.00sqm. +Add wastage 10% = 1.00sqm.= 11.00sqm.

###Expanded polystyrene type - SE sqm 11 131 1,441O1 Adhesive bitumen grade ‘A’ kilogram .25 20 5###Sundries L.S. 13 1 13

Labour:###Carpenter 1 st class Day .5 151.5 75.75###Beldar Day .5 135.25 67.62

TOTAL 1,602.37

558CodDescription Unit Quantity Rate Amount

Add 1% for water charges 16.02TOTAL 1,618.39Add 15% for’contractor’s profit and overheads 242.76Cost for 10.00sqm. 1,861.15Cost for 1sqm. 186.12Say 186.1

### Providing and fixing 100 mm diameter and 60 cm long rain water spout in cement

Page 548: DAR_Vol_1

mortar 1:4 (1 cement: 4 fine sand)12.37.1 Stone ware spout

CodDescription Unit Quantity Rate AmountDetails of cost for 10 stone ware spout of60cm longMaterials :-

###Stone ware spouts 100 mm dia 6 each 6 28 168###Carriage L.S. 13.52 1 13.52###Mortar L.S. 13.52 1 13.52

Labour for fixing and placing in position###Mason 2nd class Day .4 141.6 56.64###Beldar Day .4 135.25 54.1###Sundries L.S. 5.33 1 5.33

TOTAL 311.11Add 1 % for water charges 3.11TOTAL 314.22Add. 15% for contractor’s profit and overheads 47.13Cost of 10.00 spouts 361.35Cost of 1.00 spout 36.14Say 36.15

12.38 Providing and fixing M.S. holder bat clamps of approved design to C.I. or S.C.I, rainwater pipes embedded in and including cement concrete blocks 10x10x 10cm of1:2:4 mix (1 cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)and cost of cutting holes and making good the walls etc. :

12.38.1 100 mm diameterCodDescription Unit Quantity Rate Amount

Details of cost of 5 nos.Materials :-

###M.S. holder bat clamps = 5 nos each 5 13 65###Sundries L.S. 7.15 1 7.15

C.C. block 5x0.1x0.1x0.1 = 0.005 cum###Carriage of bat clamps L.S. 2.47 1 2.47

Labour:###Fitter Day .125 151.5 18.94###Mason 2nd class Day .75 141.6 106.2###Beldar Day .5 135.25 67.62###Stone Aggregate 20 mm nominal cum .0033 700 2.31###Stone Aggregate 10 mm nominal cum .0011 700 .77###Carriage of Stone Aggregate be cum .0044 53.21 .23

nominal size###Coarse sand cum .0022 600 1.32

559CodDescription Unit Quantity Rate Amount###Carriage of coarse sand cum .0022 53.21 .12###Portland cement tonne .0016 4,500 7.2###Carriage of cement tonne .0016 47.29 .08###Beldar Day .0045 135.25 .61###Coolie Day .0032 135.25 .43###Bhisti Day .0014 138.45 .19###Mason 1st class Day .0003 151.5 .05

Page 549: DAR_Vol_1

###Mason 2nd class Day .0003 141.6 .04###Mate Day .0002 138.45 .03###Hire charges of machine etc. L.S. .26 1 .26###Sundries L.S. .13 1 .13###Sundries L.S. .13 1 .13

TOTAL 281.28Add 1% for water charges 2.81TOTAL 284.09Add 15% for contractor’s profit and overheads 42.61Cost of 5.00 bat clamps 326.7Cost of 1.00 bat clamps 65.34Say 65.35

### Providing and fixing M.S. holder bat clamps of approved design to C.I. or S.C.I,rain water pipes embedded in and including cement concrete blocks 10x10x 10cmof 1:2:4 mix (1 cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominalsize) and cost of cutting holes and making good the walls etc.:

12.38.2 150 mm diameterCodDescription Unit Quantity Rate Amount

Details of cost of 5 nos.Materials :-

###M.S. holder bat clamps = 5 nos each 5 20 100C.C. block 5x0.1x0.1x0.1 = 0.005 cum

###Carriage of bat clamps L.S. 2.47 1 2.47###Sundries L.S. 7.15 1 7.15

Labour:###Fitter Day .125 151.5 18.94###Mason 2nd class Day .75 141.6 106.2###Beldar Day .5 135.25 67.62###Stone Aggregate 20 mm nominal cum .0033 700 2.31###Stone Aggregate 10 mm nominal cum .0011 700 .77###Carriage of Stone Aggregate be cum .0044 53.21 .23

nominal size###Coarse sand cum .0022 600 1.32###Carriage of coarse sand cum .0022 53.21 .12###Portland cement tonne .0016 4,500 7.2###Carriage of cement tonne .0016 47.29 .08###Beldar Day .0045 135.25 .61###Coolie Day .0032 135.25 .43###Bhisti Day .0014 138.45 .19###Mason 1 st class Day .0003 151.5 .05###Mason 2nd class Day .0003 141.6 .04###Mate Day .0002 138.45 .03

560CodDescription Unit Quantity Rate Amount###Hire charges of machine etc. L.S. .26 1 .26###Sundries L.S. .13 1 .13###Sundries L.S. .13 1 .13

TOTAL 316.28Add 1 % for water charges 3.16TOTAL 319.44Add 15% for contractor’s profit and overheads 47.92Cost of 5.00 bat clamps 367.36

Page 550: DAR_Vol_1

Cost of 1.00 bat clamps 73.47Say 73.45

12.39 Providing lead caulked joints to sand cast iron rain water pipes and fittings:12.39.1100mm dia. PipeCodDescription Unit Quantity Rate Amount

Details of cost for one joint.Materials:

###Pig lead Kilogram .98 58 56.84###Spunyarn Kilogram .11 30 3.3###Kerosene oil fuel and sundries L.S 13.52 1 13.52###Carriage of materials L.S. 1.43 1 1.43

Labour:###Fitter Day .06 151.5 9.09###Assistant fitter Day .06 141.6 8.5###Beldar Day .12 135.25 16.23

TOTAL 108.91Add 1% for water charges 1.09TOTAL 110Add 15% for contractor’s profit and overheads 16.5Cost of 1.00 joint. 126.5Say 126.5

12.39 Providing lead caulked joints to sand cast iron rain water pipes and fittings.12.39.2150mm dia. Pipe

CodDescription Unit Quantity Rate Amount

Details of cost for one joint.Materials:

###Pig lead kilogram 1.48 58 85.84###Spun yarn kilogram .17 30 5.1###Kerosene oil fuel and sundries L.S. 13.52 1 13.52###Carriage of materials L.S. 2.73 1 2.73

Labour:###Fitter Day .08 151.5 12.12###Assistasnt fitter Day .08 141.6 11.33###Beldar Day .15 135.25 20.29

561CodDescription Unit Quantity Rate Amount

TOTAL 150.93Add 1% for water charges 1.51TOTAL 152.44Add 15% for contractor’s profit and overheads 22.87Cost of 1.00 joint. 175.31Say 175.3

### Providing, fixing and embedding sand cast iron accessories for rain water pipesin the masonry surrounded with” 12mm thick cement mortar of the same mix, asthat of masonry (lead caulking will be paid for separately):

Page 551: DAR_Vol_1

12.40.1 Sand cast iron plain shoes :12.40.1.1 150 mm diameter

CodDescription Unit Quantity Rate Amount

Details of cost for one shoe###150 mm sand cast iron plain sho each 1 222 222###Carriage, fixing and mortar L.S. 17.55 1 17.55

TOTAL239.55 Add 1% for water charges 2.4

TOTAL 241.95Add 15% for contractor’s profit and overheads 36.29Cost of 1.00 bend 278.24Say 278.25

### Providing and fixing on wall face unplasticised Rigid PVC rain water pipesconforming to IS : 13592 Type A including jointing with seal ring conforming to IS :5382 leaving 10 mm gap for thermal expansion, (i) Single socketed pipes

12.41.1 75 mm diameter

CodDescription Unit Quantity Rate AmountDetails of cost for 6.00 metres

###Cost of 6.00 metres pipe metre 6 58 348###Seal rings metre 1 14 14###Carriage of materials L.S. 13.52 1 13.52###Adhesive, and sundries etc. L.S. 6.76 1 6.76

Labour-###Fitter Day .19 151.5 28.78###Beldar Day .37 135.25 50.04###Bandhani Day .08 138.45 11.08###Scaffolding etc. L.S. 18.59 1 18.59

TOTAL 490.77Add 1% for water charges 4.91TOTAL 495.68Add 15% for contractor’s profit and overheads 74.35Cost of 6.00 metre 570.03Cost of 1.00 metre 95.01Say 95

56212.41 Providing and fixing on wall face unplasticised Rigid PVC rain water pipes conforming

to IS : 13592 Type A including jointing with seal ring conforming to IS : 5382 leaving10 mm gap for thermal expansion, (i) Single socketed pipes

12.41.2110 mm diameter

CodDescription Unit Quantity Rate AmountDetails of cost for 6.00 metres

###Cost of 6.00 metres pipe metre 6 112 672###Seal rings metre 1 17 17###Carriage of materials L.S. 17.55 1 17.55###Adhesive, and sundries etc. L.S. 8.06 1 8.06

Labour-###Fitter Day .23 151.5 34.84

Page 552: DAR_Vol_1

###Beldar Day .45 138.25 60.86###Bandhani Day .11 138.45 15.23###Scaffolding etc. L.S. 18.59 1 18.59

TOTAL 844.13Add 1% for water charges 8.44TOTAL 852.57Add 15% for contractor’s profit and overheads 127.89Cost of 6.00 metre 980.46Cost of 1.00 metre 163.41Say 163.4

### Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessoriesfor unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type Aincluding jointing with seal ring conforming to IS : 5382 leaving 10 mm gap forthermal expansion.

12.42.1 Coupler12.42.1.1 75 mm

CodDescription Unit Quantity Rate AmountDetails of cost for 1 coupler metre 1 30 30

###Cost of coupler metre 2 17 28###Seal rings###Adhesive, and sundries etc. L.S. 2.73 1 2.73

Labour-###Carriage and fixing charges L.S 9.36 1 9.36

TOTAL 70.09Add 1% for water charges .7TOTAL 70.79Add 15% for contractor’s profit and overheads 10.62Cost of 1 coupler 81.41Say 81.4

563### Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories

for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type Aincluding jointing with seal ring conforming to IS : 5382 leaving 10 mm gap forthermal expansion.

12.Coupler12.42.1.2 110 mm

CodDiscription Unit Quantity Rate AmountDetails of cost for 1 coupler

###Cost of coupler each 1 40 40###Seal rings metre 2 17 34###Adhesive, and sundries etc. L.S 2.73 1 2.73###Carriage and fixing charges L.S 10.79 1 10.79

TOTAL 87.52Add 1 % for water charges .88TOTAL 88.4Add 15% for contractor’s profit and overheads 13.26Cost of 1 coupler 101.66

Page 553: DAR_Vol_1

Say 101.65

### Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessoriesfor unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type Aincluding jointing with seal ring conforming to IS : 5382 leaving 10 mm gap forthermal expansion.

12.Single push fit Coupler:12.42.2.1 75 mmCodDiscription Unit Quantity Rate Amount

Details of cost for 1 coupler###Cost of coupler each 1 47 47###Seal rings metre 2 14 28###Adhesive, and sundries etc. L.S 2.73 1 2.73###Carriage and fixing charges L.S 9.36 1 9.36

TOTAL 87.09Add 1 % for water charges .87TOTAL 87.96Add 15% for contractor’s profit and overheads 13.19Cost of 1 coupler 101.15Say 101.15

### Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessoriesfor unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type Aincluding jointing with seal ring conforming to IS : 5382 leaving 10 mm gap forthermal expansion.

12.Single push fit Coupler:12.42.2.2 110 mmCodDiscription Unit Quantity Rate Amount

Details of cost for 1 coupler###Cost of coupler each 1 72 72###Seal rings metre 2 17 34###Adhesive, and sundries etc. L.S 2.73 1 2.73

564CodDiscription Unit Quantity Rate Amount

###Carriage and fixing charges L.S 10.79 1 10.79TOTAL 119.52Add 1 % for water charges 1.2TOTAL 120.72Add 15% for contractor’s profit and overheads 18.11Cost of 1 coupler 138.83Say 138.85

### Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessoriesfor unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type Aincluding jointing with seal ring conforming to IS : 5382 leaving 10 mm gap forthermal expansion.

12.Single tee with door12.42.3.1 75x75x75 mmCodDiscription Unit Quantity Rate Amount

Page 554: DAR_Vol_1

Details of cost for 1 teeMaterials

###75x75x75 mm single equal tee (weach 1 100 100including cost of bolts and nuts

###Seal rings metre 3 14 42###Adhesive, Carriage of material r L.S 10.76 1 10.76

etc. including fixing chargesTOTAL 152.76Add 1% for water charges 1.53TOTAL 154.29Add 15% for contractor’s profit and overheads 23.14Cost of 1 tee 177.43Say 177.45

### Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessoriesfor unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type Aincluding jointing with seal ring conforming to IS : 5382 leaving 10 mm gap forthermal expansion.

12.Single tee with door12.42.3.2 110x110x110 mmCodDiscription Unit Quantity Rate Amount

Details of cost for 1 teeMaterials

###110x110x110 mm single equal teeeach 1 160 160including cost of bolts and nuts

###Seal rings metre 3 17 51###Adhesive, Carriage of material r L.S 13.47 1 13.47

etc. including fixing chargesTOTAL 224.47Add 1% for water charges 2.24TOTAL 226.71Add 15% for contractor’s profit and overheads 34.01Cost of 1 tee 260.72Say 260.7

565### Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories

for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type Aincluding jointing with seal ring conforming to IS : 5382 leaving 10 mm gap forthermal expansion.

12.Single tee with door12.42.4.1 75x75x75 mm

CodDiscription Unit Quantity Rate Amount

Details of cost for 1 teeMaterials

###75x75x75 mm single equal tee (weach 1 83 83including cost of bolts and nuts

###Seal rings metre 3 14 42

Page 555: DAR_Vol_1

###Adhesive, Carriage of material r L.S 10.76 1 10.76etc. including fixing chargesTOTAL 135.76Add 1% for water charges 1.36TOTAL 137.12Add 15% for contractor’s profit and overheads 20.57Cost of 1 tee 157.69Say 157.7

### Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessoriesfor unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type Aincluding jointing with seal ring conforming to IS : 5382 leaving 10 mm gap forthermal expansion.

12.Single tee with door12.42.4.2 110x110x110 mmCodDiscription Unit Quantity Rate Amount

Details of cost for 1 teeMaterials

###110x110x110 mm single equal teeeach 1 115 115including cost of bolts and nuts

###Seal rings metre 3 17 51###Adhesive, Carriage of material r L.S 13.47 1 13.47

etc. including fixing chargesTOTAL 179.47Add 1% for water charges 1.79TOTAL 181.26Add 15% for contractor’s profit and overheads 27.19Cost of 1 tee 208.45Say 208.45

### Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessoriesfor unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type Aincluding jointing with seal ring conforming to IS : 5382 leaving 10 mm gap forthermal expansion.

12.Bend 87.5°12.42.5.1 75 mm bend

566CodDiscription Unit Quantity Rate Amount

Details of cost for 1 bend###Cost of bend each 1 50 50###Seal rings metre 1 14 14###Adhesive, and sundries etc. L.S 2.73 1 2.73###Carriage and fixing charges L.S 9.36 1 9.36

TOTAL 76.09Add 1% for water charges .76TOTAL 76.85Add 15% for’contractor’s profit and overheads 11.53Cost of 1 coupler 88.38Say 88.4

### Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessoriesfor unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type A

Page 556: DAR_Vol_1

including jointing with seal ring conforming to IS : 5382 leaving 10 mm gap forthermal expansion.

12.Bend 87.5°12.42.5.2 110 mm bendCodDiscription Unit Quantity Rate Amount

Details of cost for 1 bend###Cost of bend each 1 85 85###Seal rings metre 1 17 17.00###Adhesive, and sundries etc. L.S 2.73 1 2.73###Carriage and fixing charges L.S 10.79 1 10.79

TOTAL 115.52Add 1% for water charges 1.16TOTAL 116.68Add 15% for’contractor’s profit and overheads 17.5Cost of 1 coupler 134.18Say 134.2

### Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessoriesfor unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type Aincluding jointing with seal ring conforming to IS : 5382 leaving 10 mm gap forthermal expansion.

12.42.6 Shoe (Plain)12.42.6.1 75 mm ShoeCodDiscription Unit Quantity Rate Amount

Details of cost for 1 shoe###Cost of shoe each 1 105 105###Seal rings metre 1 14 14###Adhesive, and sundries etc. L.S 2.73 1 2.73###Carriage and fixing charges L.S 9.36 1 9.36

TOTAL 131.09Add 1% for water charges 1.31TOTAL 132.4Add 15% for contractor’s profit and overheads 19.86Cost of 1 coupler 152.26Say 152.25

567### Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories

for unplasticised Rigid PVC rain water pipes conforming to IS : 13592 Type Aincluding jointing with seal ring conforming to IS : 5382 leaving 10 mm gap forthermal expansion.

12.42.6 Shoe (Plain)12.42.6.2 110 mm Shoe

CodDiscription Unit Quantity Rate Amount

Details of cost for 1 shoe###Cost of shoe each 1 196 196###Seal rings metre 1 17 17

Page 557: DAR_Vol_1

###Adhesive, and sundries etc. L.S 2.73 1 2.73###Carriage and fixing charges L.S 10.79 1 10.79

TOTAL 226.52Add 1% for water charges 2.27TOTAL 228.79Add 15% for contractor’s profit and overheads 34.32Cost of 1 coupler 263.11Say 263.1

### Providing and fixing unplasticised -PVC pipe clips of approved design tounplasticised - PVC rain water pipes by means of 50x50x50mm hard wood plugs,screwed with M.S. screws of required length including cutting brick work andfixing in cement mortar 1:4(1 cement: 4 coarse sand) and making good the walletc. complete.

12.75 mm

CodDiscription Unit Quantity Rate Amount

Details of cost for 5 nos.Materials

###U-PVC pipe clips each 5 15 75###Carriage of U-PVC pipe clips L.S. 2.47 1 2.47###Hardwood plug 50x50x50 each 10 6 60

Labour :-###Fitter Day .125 151.5 18.94###Mason 2nd class Day .75 141.6 106.2###Beldar Day .5 135.25 67.62###Sundries L.S. 7.15 1 7.15###Sundries L.S. .91 1 .91###Sundries cement mortar 1:4(1 C L.S. 3.9 1 3.9

Coarse sand)TOTAL 342.19Add 1% for water charges 3.42TOTAL 345.61Add 15% for contractor’s profit and overheads 51.84Cost of 5 Nos. 397.45Cost of 1 No. 79.49Say 79.5

568### Providing and fixing unplasticised -PVC pipe clips of approved design to

unplasticised - PVC rain water pipes by means of 50x50x50mm hard wood plugs,screwed with M.S. screws of required length including cutting brick work andfixing in cement mortar 1:4(1 cement: 4 coarse sand) and making good the walletc. complete.

12.110 mm

CodDiscription Unit Quantity Rate Amount

Details of cost for 5 nos.Materials

Page 558: DAR_Vol_1

###U-PVC pipe clips each 5 30 150###Carriage of U-PVC pipe clips L.S. 2.47 1 2.47###Hardwood plug 50x50x50 each 10 6 60

Labour :-###Fitter Day .125 151.5 18.94###Mason 2nd class Day .75 141.6 106.2###Beldar Day .5 135.25 67.62###Sundries L.S. 7.15 1 7.15###Sundries L.S. .91 1 .91###Sundries cement mortar 1:4(1 C L.S. 3.9 1 3.9

Coarse sand)TOTAL 417.19Add 1% for water charges 4.17TOTAL 421.36Add 15% for contractor’s profit and overheads 63.2Cost of 5 Nos. 484.56Cost of 1 No. 96.91Say 96.9

12.44 Providing and fixing to the inlet mouth of rain water pipe cast iron grating 15 cmdiameter and weighing not less than 440 grams.

CodDiscription Unit Quantity Rate Amount

Details of cost for 1 gratingMaterials

###150 mm cast iron grating for rain each 1 16 16###Carriage of material and fixing c L.S 4.16 1 4.16

TOTAL 20.16Add 1 % for water charges .2TOTAL 20.36Add 15% for contractor’s profit and overheads 3.05Cost of each grating 23.41Say 23.4

### Providing and fixing at all height false ceiling including providing and fixing offrame work made of special sections power pressed from M.S. sheet andgalvanised in accordance with zinc coating of grade 350 as per IS : 277 andconsisting of angle cleats of size 25mm wide x 1.6mm thick with flanges of 22mmand 37mm at 1200mm centre to centre one flange fixed to the ceiling with dashfastener 12.5mm diax40mm long with 6mm dia bolts to the angle hangers of

56925x25x0.55mm of required length, and other end of angle hanger being fixedwith nut and bolts to G.I. channels 45x15x0.9mm running at the rate of 1200mmcentre to centre to which the ceiling section 0.5mm thick bottom wedge of 80mmwith tapered flanges of 26mm each having clips of 10.5mm at 450mm centre tocentre shall be fixed in a direction perpendicular to G.I. channel with connectingclips made out of 2.64mm diax230mm long G.I. wire at every junction includingfixing the gypsum board with ceiling section and perimeter channels 0.5mm thick27mm high having flanges of 20mm and 30mm long, the perimeter of ceilingfixed to wall/partition with the help of rawl plugs at 450mm centre to centre with25mm long drive-all screws @ 230mm interval including jointing and fixing to a

Page 559: DAR_Vol_1

flush finish of tapered and square edges of the board with recommended filler,jointing tapes, finisher and two coats of primer suitable for board as permanufactures specification and also including the cost of making openings forlight fittings, grills, diffusers, cutouts made with frame of perimeter channelssuitably fixed all complete as per drawing and specification and direction of theEngineer in Charge but excluding the cost of painting with :

12.12.5 mm thick tapered edge gypsum board conforming to IS: 2095- Part I,CodDiscription Unit Quantity Rate Amount

Details of cost for 10.8x9.6m = 103.68sqm.MaterialsGypsum board 12.5mm thick = 103.68 sqm.+Add wastage @ 5% = 5.18sqm.= 108.86 sqm.

###Gypsum board sqm 108.86 140 15,240.4###Ceiling sections metre 238.14 36 8,573.04###Perimetre channel metre 41.14 23 962.32###Intermediate channel metre 90.72 38 3,447.36###Strap hanger (Ceiling angle) metre 10.8 16 172.8###Connecting clips each 189 5 945###Nuts and bolts 6 mm dia (25mm) 10 Nos 216 9 194.4###Soffit cleat each 72 3 216###Drive all screws 25 mm long 100 Nos 1,000 40 400###Joint filler kilogram 22.81 19 433.39###Joint finisher kilogram 34.21 22 752.62###Joint tape roll 1.27 120 152.4###Primer for two coats litre 18.66 76 1,418.16###Dash fastner 12 mm dia 40 mm loeach 72 8 576

mm dia bolt###Sundries like rawl plug scaffoldi L.S. 807.3 1 807.3###Carriage of material etc. L.S. 447.2 1 447.2

Labour :-###Carpenter 2nd class Day 31.104 141.6 4,404.33###Beldar Day 31.104 135.25 4,206.82###Painter Day 10.368 141.6 1,468.11

TOTAL 44,817.65Add 1 % for water charges 448.18TOTAL 45,265.83Add 15% for contractor’s profit and overheads 6,789.87Cost for 103.68 sqm. 52,055.7Cost of 1 Sqm. 502.08Say 502.1

57012.46 Providing and fixing to the inlet mouth of rain water pipe PTMT (an Engineering

Thermoplastic) grating sqare (Slit) 150 mm sqare with a height of 8 mm and weighingnot less than 100 gms

CodDiscription Unit Quantity Rate Amount

Details of cost for 1 gratingMaterials

Page 560: DAR_Vol_1

###P.T.M.T. Grating square slit 15 each 1 70 70###Carriage of material and fixing c L.S 4.16 1 4.16

TOTAL 74.16Add 1% for water charges .74TOTAL 74.9Add 15% for contractor’s profit and overheads 11.24Cost of each grating 86.14Say 86.15

12.47 Providing & fixing UV stabilised fiberglass reinforced plastic sheet roofing upto anypitch including fixing with polymer coated ‘J’ or ‘L’ hooks, bolts & nuts 8mm dia. G.Iplain/bitumen washers complete but excluding the cost of purlins, rafters, trussesetc. The sheets shall be manufactured out of 2400 TEX panel rovigs incorporatingminimum 0.3% Ultra-voilet stabiliser in resin system under approximately 2400 psiand hot cured. They shall be of uniform pigmentation and thickness without airpockets and shall confoim to IS 10192 and IS 12866.The sheets shall be opaque ortranslucent, clear or pigmented, textured or smooth as specified.

12.47.1 2mm thick corrugated (2.5\" or 4.2\" or 6\") or step-down (2\"or 3\"or 6\") as specified.CodDiscription Unit Quantity Rate Amount

Details of cost for area of roof.2x18.09x5.1 = 184.518 sqm.Materials:

###UV stabilised 2 mm thick corrug sqm 240.408 474 ###sheet.

###Carriage of sheet L.S. 104 1 104G.I.Seam bolts and nuts 60cmcentre to centre zig-zag i.e. 30cmcentre to centre straightBreadth is 5.1 metreNo. of bolts in one lap 5.1/0.3 =17 nos.2x26(laps)xl7 nos. = 884 nos.

###Bolts and nutsG.I.,J or L hooks 8mm dia.(No. of purlins to be used 5 on eitherside)2x5x27(No. of sheets)x23 nos. of boltsin each sheet = 810 nos.

###G.I., J or L hooks 10 Nos 884 9 795.6###Limpet washers (total of seam and10 Nos 810 58 4,698

884+810= 1694 100 Nos 1,694 20 338.8###Bitumen washers###Carriage of bolts and washers 100 Nos 1,694 18 304.92###Sundries L.S. 26.91 1 26.91

Labour: L.S. 53.82 1 53.82

571CodDiscription Unit Quantity Rate Amount

###Mistry Day 1.3 151.5 196.95###Carpenter 2nd class Day 15.5 141.6 2,194.8###Beldar Day 15.5 135.25 2,096.38

TOTAL ###

Page 561: DAR_Vol_1

Add 1 % for water charges 1,247.64TOTAL ###Add 15% for contractor’s profit and overheads 18 901.68Cost of 184.518 Sqm. ###Cost of 1 Sqm. 785.36Say 785.35

12.47 Providing & fixing UV stabilised fiberglass reinforced plastic sheet roofing upto anypitch including fixing with polymer coated ‘J’ or ‘L’ hooks, bolts & nuts 8mm dia. G.Iplain/bitumen washers complete but excluding the cost of purlins, rafters, trussesetc. The sheets shall be manufactured out of 2400 TEX panel rovigs incorporatingminimum 0.3% Ultra-voilet stabiliser in resin system under approximately 2400 psiand hot cured. They shall be of uniform pigmentation and thickness without airpockets and shall conform to IS 10192 and IS 12866.The sheets shall be opaque ortranslucent, clear or pigmented, textured or smooth as specified.

12.47.2 2mm thick flatCodDiscription Unit Quantity Rate Amount

Details of cost for area of roof.2x18.09x5.1 = 184.518 sqm.Materials:

###UV stabilised 2 mm thick plain F sqm 240.408 400 96,163.2###Carriage of sheet L.S. 104 1 104

G.I.Seam bolts and nuts 60cmcentre to centre zig-zag i.e. 30cmcentre to centre straightBreadth is 5.1 metreNo. of bolts in one lap 5.1/0.3 =17 nos.2x26(laps)xl7 nos. = 884 nos.

###Bolts and nuts 10 Nos 884 9 795.6G.I.,J or L hooks 8mm dia.(No. of purlins to be used 5 on eitherside)2x5x27(No. of sheets)x23 nos. of boltsin each sheet = 810 nos.

###G.I., J or L hooks 10 Nos 810 58 4,698###Limpet washers (total of seam and100 Nos 1,694 20 338.8

884+810= 1694###Bitumen washers 100 Nos 1,694 18 304.92###Carriage of bolts and washers L.S. 26.91 1 26.91###Sundries L.S. 53.82 1 53.82

Labour:###Mistry Day 1.3 151.5 196.95###Carpenter 2nd class Day 15.5 141.6 2,194.8###Beldar Day 15.5 135.25 2,096.38

TOTAL ###Add 1 % for water charges 1,069.73TOTAL ###Add 15% for contractor’s profit and overheads 16 206.47Cost of 184.518 Sqm. ###Cost of 1 Sqm. 673.37Say 673.35

572

Page 562: DAR_Vol_1

12.48 Providing & fixing on roof pressed clay tile (Mangalor tile of 20 mm nominal thicknessand of approved size and as per approved pattern sfeel frame work complete (steelframe work to be paid separately)

CodDiscription Unit Quantity Rate Amount

Details of cost for 10 sqmMaterials

###Manglore tiles 20 mm thick. each 160 9.5 1,520###Carriage of tiles 1000 Nos 160 85.13 13.62

Labour###Mason 1st class Day .3 151.5 45.45###Beldar Day 1.56 135.2 210.99###Sundries L.S 13 1 13

Total 1,803.06Add 1% for water charges 18.03Total 1,821.09Add 15% for contractor’s profit and overheads 273.16Cost for 10 sqm 2,094.25Cost for 1 sqm 209.43Say 209.4

12.49 Providing & laying on roof pressed clay tile ridge (Mangalore tile) of 20mm thicknessand of approved pattern on steel frame work complete (sfeel frame work to be paidseparately)

CodDiscription Unit Quantity Rate AmountDetails of cost for 3.60 metreMaterials

###Manglore ridge tiles each 12 25 30020 mm thick

###Carriage of tiles 1000 Nos 12 85.13 1.02Labour

###Mason 1st class Day .01 151.5 1.52###Beldar Day .15 135.25 20.29###Sundries L.S 2.6 1 2.6

Total 325.43Add 1% for water charges 3.25Total 328.68Add 15% for contractor’s profit and overheads 49.3Cost for 3.60 sqm 377.98Cost for 1 sqm 104.99Say 105

12.50 Providing and fixing precoatedgalvanized iron profile sheets (size, shape and pitchof corrugation as 5% total coated thickness (TCT), Zinc coating 120gsm as per IS:277 in approved by Engineer-in-charge) 0.05 mm. 240 mpa mm steel grade, 5-7 micronsepoxy primer on both side of the sheet and polyester top coat 15-18 microns. Sheetshould have protective guard film of 25 microns minimum to avoid scratches whiletransportation and should be supplied in single length upto 12 metre or as desiredby Engineer-in-charge. The sheet shall be fixed using self drilling /self tapping screwsof size (5.5x 55mm) with EPDM seal or with polymer coated J or L hooks, bolts andnuts 8mm diameter with bitumen and G.I. limpet washers or with G.I. limpet washersfilled with white lead complete upto any pitch in horizontal/ vertical or curved surfacesexcluding the cost of purlins, rafters and trusses and including cutting to size andshape wherever required.

Page 563: DAR_Vol_1

573CodDiscription Unit Quantity Rate Amount

Details of cost of 216.14 sqm.Consider a shed of 20x10 metres.(External dimensions of plinth).Area of roof-20.2xl0.70m = 216.14 sqm.Materials:Sheets used = 20nos.xl0.70mxl.06m=226.84sqmAdd 3% wastage = 6.81= 233.65sqm.

###Precoated galvanised iron profile sqm 233.65 325 75,936.25mm TCT

###Carriage of sheets L.S. 104 1 104###G.I. J or L hooks with nuts and b 10 Nos 476 58 2,760.8###Bitumen washers 100 Nos 476 18 85.68###Bitumen washers thick 100 Nos 476 27 128.52###Carriage of bolts and nuts, washeL.S. 806 1 8.06###Sundries L.S. 39.52 1 39.52

Labour:###Mistry Day 2.34 151.5 354.51###Carpenter 2nd class Day 9.34 141.6 1,322.54###Beldar Day 9.34 135.25 1,263.23

TOTAL 82,003.11Add 1% for water charges 820.03TOTAL 82,823.14Add 15% for contractor’s profit and overheads 12,423.47Cost of 216.14 sqm. 95,246.61Cost of 1.00 sqm. 440.67Say 440.65

12.51 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50mm + 5% total coated thickness (TCT), Zinc coating 120gsm as per IS: 277 in 240mpasteel grade, 5-7 microns epoxy primer on both side of the sheet and polyester topcoat 15-18 microns using self drilling/ self tapping screws or with polymer coated Jor L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumenwashers complete :

12.51.1 Ridges plain (500 - 600mm).CodDiscription Unit Quantity Rate Amount

Detail of lost for 20.20 metreMaterial:-One piece plain ridgesConsider a shed of 20x10m (externaldimensions at plinth).Length of ridges 20.2 metre + 5% wastage =

###23.11 metre. metre 23.11 330 7,626.3###Materials: L.S 13.52 1 13.52

Precoated galvanised steel plain ridges.###Carriage (The ridge is to be fixed L.S 6.76 1 6.76

same hooks as the Sheets)###Sundries Day .14 151.5 21.21###Labour: Day .55 141.6 77.88###Mistry Day 1.64 135.25 221.81

Carpenter 2nd class 7,967.48

Page 564: DAR_Vol_1

Beldar 79.67TOTAL

574CodDiscription Unit Quantity Rate Amount

Add 1 % for water chargesTOTAL 8,047.15Add 15% for contractor’s profit and 1,207.07overheads 9,254.22Cost of 20.20 metre 458.13Cost of 1.00 metre 458.15Say

12.51 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50 mm +5% total coated thickness (TCT), Zinc coating 120gsm as per IS: 277 in 240mpa steelgrade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18microns using self drilling/ self tapping screws or with polymer coated J or L hooks,bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers complete :

12.51.2 Flashing/ Aprons (Up to 600 mm)CodDiscription Unit Quantity Rate Amount

Details for shed of 20.2 metres completedlengthMaterials:

###Precoated galvanised steel flash metre 23.11 330 7,626.320.20 + 5% wastage = 23.11 metre

###Carriage of appron pieces. (The L.S 3.25 1 13.52are to be fixed with the same hooks as thesheets)

###Sundries L.S 3.25 1 3.25Labour:

###Mistry Day .07 151.5 10.6###Carpenter 2nd class Day .28 141.6 39.65###Beldar Day .82 135.25 110.9

TOTAL 7,793.95Add 1 % for water charges 77.94TOTAL 7,871.89Add 15% for contractor’s profit and overheads 1,180.78Cost of 20.20 metre 9,052.67Cost of 1.00 metre 448.15Say 448.15

12.51 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50mm + 5% total coated thickness (TCT), Zinc coating 120gsm as per IS: 277 in 240mpasteel grade, 5-7 microns epoxy primer on both side of the sheet and polyester topcoat 15-18 microns using self drilling/ self tapping screws or with polymer coated Jor L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumenwashers complete : .-

12.51.3 North light curves.CodDiscription Unit Quantity Rate Amount

Details of North light curve 20.2 metres longcomplete lengthMaterials:

Page 565: DAR_Vol_1

###Precoated galvanised steel north metre 23.11 360 8,319.6= 20.20 + 5% wastage = 23.11 metre.

###G.I. J or L hooks with nuts and b 10 Nos 40 58 232###G.I plain waher thick 100 Nos 40 7 10.8###Bitumen washers 100 Nos 40 18 7.2###Carriage of hooks, nuts, washers L.S 9.88 1 9.88

575CodDiscription Unit Quantity Rate Amount

= 20.20 + 5% wastage = 23.11 metre.G.I. J or L hooks with nuts and bolts 8 mm diaG.I plain waher thickBitumen washersCarriage of hooks, nuts, washers and curves

###Sundries L.S 6.24 1 6.24Labour:

###Mistry Day .1 151.5 15.15###Carpenter 2nd class Day 1.3 141.6 42.48###Beldar Day 1 135.25 135.25

TOTAL 8,778.6Add 1 % for water charges 87.79TOTAL 8,866.39Add 15% for contractor’s profit and overheads 1,329.96Cost of 20.20 metre 10 196.35Cost of 1.00 metre 504.77Say 504.75

12.51 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50 mm+ 5% total coated thickness (TCT), Zinc coating 120gsm as per IS: 277 in 240mpasteel grade, 5-7 microns epoxy primer on both side of the sheet and polyester topcoat 15-18 microns using self drilling/ self tapping screws or with polymer coated Jor L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumenwashers complete :

12.51.4 Barge board (Upto 300 mm).CodDiscription Unit Quantity Rate Amount

Details of cost for 8.23 metresCompleted length of barge boards = 8.23 +5% wastage = 8.64 metreMaterials:

###Precoated galvanised steel barge metre 8.64 330 2,851.2###Seam bolts and nuts 6 mm dia a 10 Nos 5 30 15###G.I. plain washers for seam bolts.100 Nos 10 21 2.1###Bitumen washers 100 Nos 5 18 .9###Carriage of barge boards, bolts, L.S 9.36 1 9.36

washers###Sundries L.S 6.76 1 6.76

Labour:###Mistry Day .04 151.5 6.06###Carpenter 2nd class Day .06 141.6 8.5###Beldar Day .4 135.25 54.1

TOTAL 2,953.98Add 1 % for water charges 29.54

Page 566: DAR_Vol_1

TOTAL 2,983.52Add 15% for contractor’s profit and overheads 447.53Cost of 8.23 metre 3,431.05Cost of 1.00 metre 416.9Say 416.9

57612.51 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50 mm 5%

total coated thickness (TCT), Zinc coating 120gsm as per IS: 277 in 240mpa steel grade,5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 micronsusing self drilling/ self tapping screws or with polymer coated J or L hooks, bolts andnuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers complete :

12.51.5 Crimp curveCodDiscription Unit Quantity Rate Amount

Details of crimp curve 20.2 metres longArea 20.20 x 1.06 =21.412sqmMaterials:

###Precoated galvanised steel crimpmetre 22.483 420 9,442.86###G.I. J or L hooks with nuts and b 10 Nos 40 58 232###G.I plain washer thick 100 Nos 40 27 10.8###Bitumen washers 100 Nos 40 18 7.2###Carriage of hooks, nuts, washers L.S 9.88 1 9.88###Sundries L.S 6.24 1 6.24

Labour:###Mistry Day .1 151.5 15.15###Carpenter 2nd class Day .3 141.6 42.48###Beldar Day 1 135.25 135.25

TOTAL 9,901.86Add 1% for water charges 99.02TOTAL 10,000.88Add ,15% for contractor’s profit and overheads 1,500.13Cost of 21.412 sqm 11,501.01Cost of 1.00 sqm 537.13Say 537.15

12.51 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50 mm5% total coated thickness (TCT), Zinc coating 120gsm as per IS: 277 in 240mpa steelgrade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling/ self tapping screws or with polymer coated J or Lhooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washerscomplete :

12.51.6 Gutter .(600 mm over all girth).CodDiscription Unit Quantity Rate Amount

Details of cost 10 metre.Matrial0.63mm thick with zinc coating not less than275gm/sqmConsider a length of 10.00mSheet used = 10x1.06m x 0.60 = 6.36 sqm.= 6.36 metre

Page 567: DAR_Vol_1

###Precoated galvanised steel guttemetre 10 360 3,600###Carriage of gutter L.S 1.04 1 1.04###Flats upto 10 mm in thickness quintal .0749 2,900 217.21###Galvanised steel bolts and nuts 10 Nos 20 9 18

25 mm long round head with slot###Galvanised steel bolts and nuts each 30 7 210

125 mm long###G.I. plain washers thin 100 Nos 70 20 14###Bitumen washers 100 Nos 40 18 7.2###Carriage of G.I. seam bolts and L.S 2.73 1 2.73

577CodDiscription Unit Quantity Rate Amount

###Sundries L.S. 2.73 1 5.33Labour:

###Blacksmith first class Day .5 151.5 75.75Beldar 67.62

###Sundries Day .5 135.25 12.61###Mistry L.S 12.61 1 42.42###Blacksmith first class Day .28 151.5 127.26###Carpenter 2nd class Day .84 151.5 87.79###Beldar Day .62 141.6 227.22###TOTAL Day 1.68 135.25 4,716.18

Add 1% for water charges 47.16TOTAL 4,763.34Add 15% for contractor’s profit and overheads 714.5Cost of 10.00 metres 5,477.84Cost of 1.00 metre 547.78Say 547.8

12.52 Providing and fixing tiled False Ceiling of approved materials of size 595x595 mm intrue horizontal level suspended on inter locking metal grid of hot dipped galvanisedsteel sections ( galvanized @ 170 gsm/sqm.) consisting of main “T” runner withsuitably spaced joints to get required length and of size 24x38mm made from 0.30mmthick (minimum) sheet spaced at 1200mm center to center and cross “T” of size24x25mm made of 0.30mm thick (minimum) sheet, 1200mm long spaced betweenmain “T” at 600mm center to center to form a grid of 1200x600 mm and secondarycross “T” of length 600mm and size 24x25mm made of 0.30 mm thick (minimum)sheet to be interlocked at middle of the 1200x600mm panel to form grids of600x600mm and wall angle of size 21x21x0.30 mm and laying false ceiling tiles ofapproved texture in the grid including, wherever, required, cutting/making, openingfor services like diffusers, grills, light fittings, fixtures, smoke detectors etc. Main “T”runners to be suspended from ceiling using GI slotted cleats fixed to ceiling with 6mm dia and 50mm long dash fasteners, 4mm GI adjustable rods with galvanisedlevel clips spaced at 1200mm center to center along main T, bottom exposed widthof 24mm of all T-sections shall be pre-painted with polyester paint, all complete at allheights as per specifications drawings and as directed by Engineer-in-Charge. (Therate is excluding the cost of tiles which will be paid for separately ).

CodDiscription Unit Quantity Rate AmountDetails of cost for 100 sqm.

Page 568: DAR_Vol_1

Materials-GRID

###Main T ceiling sections 24x38x0 each 29.5 162 4,779metre long)Including Wastage @ 10%

###Perimeter wall angle 21x21 x 0. each 13.5 102 1,377long)Including Wastage @ 10%

###Intermediate cross T-section each 147 62 9,114(1.2 mtrs long)Including Wastage @ 10% on Grid for cutouts

###Intermediate cross T-section each 147 29 4,263(0.60 mtrs long)

578CodDiscription Unit Quantity Rate Amount

Including Wastage @ 10% on Grid for cutoutsIntermediate cross T-section 24x25x0.30mm(0.60 mtrs long)Including Wastage @ 10%

###Hanger rod 0.5 mm thick each 72 5 360###Adjustment clip each 72 4.4 316.8###Soffit cleat each 72 2.3 165.6###Dash fastener 6 mm dia 50 mm l each 72 8 576###Sundries i.e. scaffolding etc. L.S. 187.95 1 187.95###Carriage of materials etc. L.S. 89.28 1 89.28

LABOUR###Catpenter 1 st class Day 3 151.5 454.5###Beldar Day 3 135.25 405.75

TOTAL 22 088.88Add 1 % for water charges 220.89TOTAL 22 309.77Add 15% for contractor’s profit and overheads 3 346.47Cost of 100 sqm. 25 656.24Cost of 1 sqm. 256.56Say 256.55

579S.NCorrection Slip No. Reference No. Contents in Brief

Page 569: DAR_Vol_1

580S.NCorrection Slip No. Reference No. Contents in Brief

581S.NCorrection Slip No. Reference No. Contents in Brief

582S.NCorrection Slip No. Reference No. Contents in Brief

Page 570: DAR_Vol_1

CENTRAL PUBLIC WORKS DEPARTMENT

ANALYSIS OF RATES

Page 571: DAR_Vol_1

© All rights reserved. No part of this publication, either in English or in Hindi, may be reproduced inany form or by any means, electronic or mechanical, including photocopy, recording or anyinformation storage and retrieval system, without permission, in writing, from the Director General

JAIN BOOK AGENCY (GURGAON)12, Central Plaza Mall, Sector 53,

Page 572: DAR_Vol_1

Price : Rs. 3000/- per set of two volumes (excluding postage and forwarding charges etc.)

Page 573: DAR_Vol_1

Central Public Works Department Analysis of Rates for Delhi is a very comprehensive anduseful document. It is based on scientific assessment of inputs of materials, labour and machinery

It was first compiled in the year 1950, followed by publication or revisions in 1955, 1962, 1972,1977, 1985 and 1997. Since publication of DAR, 1997, prices of labour and materials have registeredsubstantial increase. Besides the increased cost, there has been a spurt of new constructionmaterials and introduction of mechanised construction techniques for speedier construction. Thishas necessitated revision of existing DAR, 1997 to include the above changes. Accordingly, thisAnalysis of Rates for Delhi, 2007 has been prepared incorporating element of machinery and

Earlier C.P.W.D. Analysis of Rates for Delhi was a confidential document and was issued toCPWD Officers and Government Departments only. In this age of transparency, we feel that thisis an anachronism. Therefore, for the first time DAR, 2007 is being published as an open documentand shall be available in two volumes. This will facilitate in obtaining feed back from the constructionindustry and the professionals for continuous updation and improvement in the document.

Although DAR, 2007 contains most of the items of DAR, 1997, analysis of items which areeither obsolete or are not in use have been deleted. Similarly, analysis of many items have been

of rates of many items also incorporate element of machinery instead of the lump sum provisions.

I wish to place on record the technical input and the effective coordination on the part of ShriD.S.Sachdev, ADG(TD) and the efforts put in by Shri Suresh Kumar, CE(CSQ) and his team of

I am sure that C.P.W.D. Analysis of Rates for Delhi, 2007 along with Delhi Schedule of Rates,2007 shall be a useful document to a number of departments, public sector undertakings, private

Page 574: DAR_Vol_1

C.P.W.D. Analysis of Rates for Delhi, 2007 is the revised edition of C.P.W.D. Analysis of

DAR, 2007 incorporates most of the analysis of DAR, 1997 with all correction slips up-to

Page 575: DAR_Vol_1

Analysis of many items in DAR, 2007, which are either obsolete or are not in use, havebeen deleted. Similarly, analysis of many items have been modified to correspond to itemsof DSR, 2007. Several new analysis of items pertaining to new materials and newtechnologies in the construction sector have also been included. Analysis of rates of many

Analysis have been modified to include execution of different works by using variouselectrical and mechanical equipments i.e. excavators, tower cranes, mobile cranes,mechanical platforms, Batch Mix plant, transit mixers and pumps, piling rigs, pneumaticcutters, chisels, chippers, hammers etc. Built-in provision has been taken in the analysis

Analysis of dry work using prefabricated materials and pre-finished elements for speedierconstruction are included viz gypsum block walls, calcium silicate and non-asbestos cementboard partitions, pre-finished counter tops for kitchen and washbasins, pre-moulded andpre-finished stone work in risers and treads of steps and window sills, dry stone cladding,sub-frames for windows, use of chemical and mechanical fasteners, laying of tiles in flooring

DAR, 2007 is based on the study of current market rates of materials at Delhi, collectedduring the period of April, 2007 to October, 2007. Generally, the basic rates of materials,incorporated in the analysis, pertain to materials conforming to BIS Standards/CPWD

Labour rates are the minimum wages issued by the Government of Delhi w.e.f. 01-09-2007.Lump sum provision of labour/ T& P is replaced with mechanisation inputs. Prominentitems incorporating mechanization are earth-work in excavation, RMC / BMC, brick workin superstructure above floor V level, road work, dismantling of R.C.C. work, dismantling

Number of uses of steel and wooden shuttering have been reduced from 80 and 16 timesto 40 and 8 times respectively, so that proper quality of shuttering is put to use.Contractor’s profit and Overheads @ 15% ( CP=7.5% & OH 7.5%) has been adopted asapproved by the DGW vide Office Memorandum no. DG(W)MAN/150 dated 14-12-2007.

Sundries have been considered as 1.00 times based on Cost Index of Delhi as 100 over

Page 576: DAR_Vol_1

A lot of effort has gone into the preparation of this Analysis of Rates. I convey mydeep appreciation and sincere thanks to Shri Suresh Kumar, CE, CSQ, Shri Mayank

Sh. A.V.R.Bhat EE (S&S) – III, Sh. V.P.Singh AE, Sh. H.N.Singh AE, Sh. S.K.SarkarAE, Sh.L.C.Gothwal AE, Sh.G.K. Jindal AE, Sh. S.S.Pal AE, Sh. Bahal SinghD/Man Gr-I, Sh Upender Walia D/Man Gr.-I and other officers and staff of TAS Unitfor sincere efforts made in the preparation of this document in such a short time.Due care has been taken to print the C.P.W.D. Analysis of Rates for Delhi as correctly aspossible. It is, however possible that some errors might have crept in. In case any error or

In case of any discrepancy between English and Hindi versions, the English version shall

Page 577: DAR_Vol_1

Note :- These rates are exclusive of contractor’s profit and over heads and are inclusive of wages for weekly

Page 578: DAR_Vol_1

Note :- * These rates are average of 1st class and 2nd class categories. This is for use in the analysis of

Page 579: DAR_Vol_1

Note :- These rates are exclusive of contractor’s profit, over heads and carriage but include octroi, royalty,

Page 580: DAR_Vol_1

1.1 By Mechanical Transport including loading, unloading and stacking:

Rate1,008

135.25135.25

30.2595

Hire charges Total Cost Increase Averageof truck Cost= per Trip in cost cost per-5 6+8+9+10 = col. 11/ per km additional@ Rs per col. 3 over km afterDay previous first 5,10

km and 20 km10 11 12 13 14

1,008 1,955.39 275.021,008 2,034.16 313.911,008 2,100.4 352.421,008 2,157.93 389.521,008 2,209.13 425.651,008 2,255.53 460.31 34.661,008 2,298.92 493.33 33.021,008 2,337.9 526.55 33.22 32.511,008 2,375.99 557.74 31.191,008 2,411.66 588.21 30.471,008 2,444.63 618.89 30.681,008 2,478.21 647.05 28.161,008 2,508.86 676.24 29.191,008 2,540.14 703.64 27.41,008 2,568.4 731.74 28.11,008 2,598.36 757.54 25.81,008 2,626.22 783.95 26.41 27.141,008 2,654.48 809.29 25.351,008 2,680.73 835.12 25.831,008 2,707.69 859.58 24.47

8 9 10 11 12 13 14

92.14 811.5 1,008 2,733.23 884.54 24 9694.81 811.5 1,008 2,759.8 907.83 23. 2997.38 811.5 1,008 2,785.36 931.56 23 73

100.13 811.5 1,008 2,812.61 953.43 21. 87102.51 811.5 1,008 2,835.56 977.78 24 35104.98 811.5 1,008 2,860.42 1,000.15 22 37 ###

Page 581: DAR_Vol_1

107.73 811.5 1,008 2,887.97 1,020.48 20. 34110.11 811.5 1,008 2,911.22 1,043.45 22. 96112.67 811.5 1,008 2,937.08 1,064.16 20. 71115.24 811.5 1,008 2,962.03 1,084.99 20. 83

where L= Load in km., S= Speed in km per hour, 1 hour is allowed for loading /unloading.

4. In column 4 of ‘km done’ an allowance of 6.0 km has been made for movement of truck from parking place to duty & back.

Beyond Beyond Beyond Remarks4km 5km 5 km upto 10 km 20 km per

10 km upto 20 addl.per km km per km

km

Cost per Trip as per Col. 12 of Data sheet As per Col. 14 of Data Sheet A B C Net Qty Payable

10 11 12 13 14 15

50.66 61.19 4.67 3.9 3.24

63.32 76.48 5.84 4.88 4.0555.07 66.51 5.08 4.24 3.52

101.32 122.37 9.35 7.8 6.4850.66 61.19 4.67 3.9 3.24

55.07 66.51 5.08 4.24 3.52

59.6 71.99 5.5 4.59 3.81135.09 163.17 12.46 10.4 8.64

81.06 97.9 7.48 6.24 5.18

45.03 54.39 4.15 3.47 2.88

45.03 54.39 4.15 3.47 2.8857.9 69.93 5.34 4.46 3.7

Page 582: DAR_Vol_1

9 10 11 12 13 14 1550.66 55.99 61.19 4.67 3.9 3.24

5.07 5.6 6.12 .47 .39 .3257.9 63.99 69.93 5.34 4.46 3.7

67.55 74.66 81.58 6.23 5.2 4.32135.09 149.32 163.17 12.46 10.4 8.64225.15 248.86 271.94 20.77 17.34 14.4321.65 355.51 388.49 29.67 24.77 20.57385.98 426.62 466.19 35.61 29.72 24.69482.47 533.27 582.74 44.51 37.15 30.86675.46 746.58 815.83 62.31 52.01 43.2964.95 1,066.54 1,165.47 89.02 74.3 61.72

1,228.12 1,357.41 1,483.33 113.3 94.57 78.551,350.93 1,493.15 1,631.66 124.63 104.03 86.411,688.66 1,866.44 2,039.58 155.79 130.03 108.01

110.73 122.39 133.74 10.22 8.53 7.08147.91 163.48 178.65 13.65 11.39 9.46184.55 203.98 222.9 17.03 14.21 11.8300.21 331.81 362.59 27.7 23.12 19.2426.61 471.52 515.26 39.36 32.85 27.29527.29 582.81 636.87 48.64 40.6 33.73738.21 815.93 891.62 68.1 56.85 47.22

1,006.65 1,112.63 1,215.84 92.87 77.52 64.391,230.35 1,359.88 1,486.03 113.5 94.74 78.691,845.53 2,039.83 2,229.05 170.26 142.11 118.04

2,768.3 3,059.74 3,343.57 255.39 213.17 177.063,691.06 4,079.65 4,458.1 340.51 284.23 236.08

1.2 By Manual Labour including loading, unloading and stacking for lead less than 0.5 KM

The following labour work for 8 hours a day will carry following material upto 1st 50 m as given below :

Page 583: DAR_Vol_1

Cost per unitcost foraddl. 50m or partthereof

stbeyond150 m upto0.5 km (Y)9

7.42

9.288.07

14.849.28

10.03

10.9117.3210.82

8.66

1.2 Carraige of material by Manual Labour including loading, unloading and stacking for lead less

Quantity of material as per column 3 of table below will be carried in 50 metres lead including loading and

Page 584: DAR_Vol_1

50 m upto

Page 585: DAR_Vol_1

Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m inwidth as well as 10 sqm on plan including disposal of excavated earth upto 50 m and lift

Page 586: DAR_Vol_1

Earth work in rough excavation, banking excavated earth in layers not exceeding 20cm in depth, breaking clods watering, rolling each layer with ½ tonne roller or woodenor steel rammers, and rolling every 3rd and top-most layer with power roller of minimum8 tonnes and dressing up in embankments for roads, flood banks, marginal banks andguide banks or filling up ground depressions, lead upto 50 m and lift upto 1.5 m :

Banking excavated earth in layers not exceeding 20 cm. in depth, breaking clods,watering, rolling each layer with ½ tonne roller, or wooden or steel rammers, and rollingevery 3rd and top-most layer with power roller of minimum 8 tonnes and dressing up, inembankments for roads, flood banks, marginal banks, and guide banks etc., lead upto

Page 587: DAR_Vol_1

Deduct for not rolling with power roller of minimum 8 tonnes for banking excavated

Earth work in excavation by mechanical means (Hydraulic excavator)/ manual meansover areas (exceeding 30cm in depth. 1.5m in width as well as 10 sqm on plan) includingdisposal of excavated earth, lead upto 50m and lift upto 1.5m, disposed earth to be

Page 588: DAR_Vol_1

Earth work in excavation/ by mechanical means (Hydraulic Excavator)/ manual meansover areas (exceeding 30 cm in depth, 1.5m in width as well as-10 sqm on plan) includingdisposal of excavated earth, lead upto 50 m and lift upto 1.5 m, disposed earth to be

2.7 Earth work in excavation/ by mechanical means (Hydraulic Excavator)/ manual meansover areas (exceeding 30 cm in depth, 1.5m in width as well as 10 sqm on plan) includingdisposal of excavated earth, lead upto 50 m and lift upto 1.5 m, disposed earth to be

Page 589: DAR_Vol_1

2.7 Earth work in excavation/ by mechanical means (Hydraulic Excavator)/ manual meansover areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) includingdisposal of excavated earth, lead upto 50 m and lift upto 1.5 m, disposed earth to be

Earth work in excavation by mechanical means (Hydraulic Excavator )/ manual meansin foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan)including dressing of sides and ramming of bottoms, lift upto 1.5 m, including gettingout the excavated soil and disposal of surplus excavated soil as directed, within a lead

Page 590: DAR_Vol_1

Excavation work by mechanical means (Hydraulic Excavator)/ manual means infoundation trenches or drains not exceeding 1.5 m in width or 10 sqm on plan includingdressing of sides and ramming of bottoms lift upto 1.5 m, including getting out theexcavated soil and disposal of surplus excavated soils as directed, within a lead of 50m.

Excavation work by mechanical means (Hydraulic Excavator)/ manual means infoundation trenches or drains not exceeding 1.5 m in width or 10 sqm on plan includingdressing of sides and ramming of bottoms lift upto 1.5 m, including getting out theexcavated soil and disposal of surplus excavated soils as directed, within a lead of 50m.

Page 591: DAR_Vol_1

Excavation work by mechanical means (Hydraulic Excavator)/ manual means infoundation trenches or drains not exceeding 1.5 m in width or 10 sqm on plan includingdressing of sides and ramming of bottoms lift upto 1.5 m, including getting out theexcavated soil and disposal of surplus excavated soils as directed, within a lead of 50m.

2.10 Excavating trenches of required width for pipes, cables, etc including excavation forsockets and dressing of sides, ramming of bottoms, depth upto 1.5 m including gettingout the excavated soil and then returning the soil as required, in layers not exceeding 20cm in depth including consolidating each deposited layer by ramming, watering, etc.

Page 592: DAR_Vol_1

Excavating trenches of required width for pipes, cables, etc including excavation forsockets and dressing of sides, ramming of bottoms, depth upto 1.5 m including gettingout the excavated soil and then returning the soil as required, in layers not exceeding20 cm in depth including consolidating each deposited layer by ramming, watering, etc.

Excavating trenches of required width for pipes, cables, etc including excavation forsockets, and dressing of sides, ramming of bottoms, depth upto 1.5 m including gettingout the excavated soil, and then returning the soil as required, in layers not exceeding20 cm in depth including consolidating each deposited layer by ramming, watering, etc.

Page 593: DAR_Vol_1

Extra for excavating trenches for pipes, cables etc. in all kinds of soil for depth exceeding

Quantity Rate Amount

362.25 103.4 37,456.65362.25 45.7 16,554.82

160 101.85 16,296160 45.7 7,312

141.75 18.9 2,679.0880298.55 (B)

300 115.05 -34515.00 (A)

45783.55 (C)152.61132.65

Page 594: DAR_Vol_1

133% per meter

Extra for excavating trenches for pipes, cables, etc, in all kinds of soil for depth exceeding

Quantity Rate Amount

126 103.4 13,028.4126 45.7 5,758.2

200 101.85 20,370200 45.7 9,140

126 18.9 2,381.450678.00(B)

100 115.05 -11505.00 (A)

39173.00 (c)391.73

340.49340%

per meter

Excavating trenches of required width for pipes, cables, etc, including excavation forsockets, depth upto 1.5 m including getting out the excavated materials, returning thesoil as required in layers not exceeding 20 cm in depth including consolidating each

measurements and disposal of unserviceable material as directed, within a lead of 50m :

Page 595: DAR_Vol_1

Excavating trenches of required width for pipes, cables, etc, including excavation forsockets, depth upto 1.5 m including getting out the excavated materials, returning thesoil as required in layers not exceeding 20 cm in depth including consolidating each

measurements and disposal of unserviceable material as directed, within a lead of 50m :

Excavating trenches of required width for pipes, cables, etc, including excavation forsockets, depth upto 1.5 m including getting out the excavated materials, returning thesoil as required in layers not exceeding 20 cm in depth including consolidating each

measurements and disposal of unserviceable material as directed, within a lead of 50m :

Page 596: DAR_Vol_1

Excavating trenches of required width for pipes, cables, etc, including excavation forsockets, depth upto 1.5 m including getting out the excavated materials, returning thesoil as required in layers not exceeding 20 cm in depth including consolidating each

measurements and disposal of unserviceable material as directed, within a lead of 50m :

Page 597: DAR_Vol_1

Excavating trenches of required width for pipes, cables, etc, including excavation forsockets, depth upto 1.5 m including getting out the excavated materials, returning thesoil as required in layers not exceeding 20 cm in depth including consolidating each

measurements and disposal of unserviceable material as directed, within a lead of 50m :

Excavating trenches of required width for pipes, cables, etc, including excavation forsockets, depth upto 1.5 m including getting out the excavated materials, returning thesoil as required in layers not exceeding 20 cm in depth including consolidating each

measurements and disposal of unserviceable material as directed, within a lead of 50m :

Page 598: DAR_Vol_1

Excavating trenches of required width for pipes, cables, etc, including excavation forsockets, depth upto 1.5 m including getting out the “excavated materials, returning thesoil as required in layers not exceeding 20 cm in depth including consolidating each

measurements and disposal of unserviceable material as directed, within a lead of 50m :

Excavating trenches of required width for pipes, cables, etc, including excavation forsockets, depth upto 1.5 m including getting out the excavated materials, returning thesoil as required in layers not exceeding 20 cm in depth including consolidating each

measurements and disposal of unserviceable material as directed, within a lead of 50m :

Page 599: DAR_Vol_1

Excavating trenches of required width for pipes, cables, etc, including excavation forsockets, depth upto 1.5 m including getting out the excavated materials, returning thesoil as required in layers not exceeding 20 cm in depth including consolidating each

measurements and disposal of unserviceable material as directed, within a lead of 50m :

Extra for excavating trenches for pipes, cables, etc. in ordinary/hard rock exceeding 1.5

Page 600: DAR_Vol_1

2.15 : Extra for excavating trenches for pipes, cables, etc. in ordinary/hard rock exceeding

Page 601: DAR_Vol_1

(wherever required) complete. (Measurements to be taken of the face area timbered).

Page 602: DAR_Vol_1

(wherever required) complete.(Measurements to be taken of the face area timbered).

Page 603: DAR_Vol_1

(wherever required) complete. (Measurements to be taken of the face area timbered).

Amount

3 804.75

1,200

92.44

79.81

212.4541

80.736,011.13

60.116 071.24

910.69

6 981.9377.58

77.6

2.17 : Close timbering in case of shafts, wells, cesspits, manholes and the like including

Amount

Page 604: DAR_Vol_1

2.17 : Close timbering in case of shafts, wells, cesspits, manholes and the like including

Page 605: DAR_Vol_1

Close timbering in case of shafts, wells, cesspits, manholes and the like including

Page 606: DAR_Vol_1

(wherever required) etc. complete. (Measurements to be taken of the face area

Page 607: DAR_Vol_1

(wherever required) etc. complete. (Measurements to be taken of the face area

Page 608: DAR_Vol_1

(wherever required) etc. complete. (Measurements to be taken of the face area

Page 609: DAR_Vol_1

2.19 : Extra for planking, strutting and packing materials for cavities (in close timbering) if

Page 610: DAR_Vol_1

Open timbering in case of shafts, wells, cesspits, manholes and the like including

Open timbering in case of shafts, wells, cesspits, manholes and the like including

Page 611: DAR_Vol_1

Open timbering in case of shafts, wells, cesspits, manholes and the like includingstrutting and shoring complete (Measurements to be taken of the face area timbered):

Page 612: DAR_Vol_1

2.23 Extra for planking and strutting in open timbering if required to be left permanently

Page 613: DAR_Vol_1

Extra rates for quantities of works, executed: (The extra percentage rate is appli-cable in respect of each item but limited to quantities of work executed in these

2.24.1 : In or under water and/ or liquid mud, including pumping out water as required.

Extra rates for quantities of works, executed: . (The extra percentage rate isapplicable in respect af each item but limited to quantities of work executed in

quantities of work executed in these difficult conditions. The unit, namely, metre depth, to be considered forpayment, shall be the depth measured from the sub soil water level up to the centre of gravity of the qtyexecuted in difficult condition. The depth shall be reckoned correct to 0.10m, 0.05m or more shall be taken as

2.25 : Filling available excavated earth (excluding rock) in trenches, plinth, sides offoundations etc. in layers not exceeding 20cm in depth, consolidating each deposited

Page 614: DAR_Vol_1

2.27 : Supplying and filling in plinth with Jamuna sand under floors including, watering,

Surface dressing of the ground including removing vegetation and in-equalities notexceeding 15 cm deep and disposal of rubbish, lead upto 50 m and lift upto 1.5 m.

Page 615: DAR_Vol_1

Ploughing the existing ground to a depth of 15 cm to 25 cm and watering the same.

consolidating each deposited layer by ramming, watering etc, disposing of surplus

consolidating each deposited layer by ramming, watering etc, disposing of surplus

Page 616: DAR_Vol_1

consolidating each deposited layer by ramming, watering etc, disposing of surplus

consolidating each deposited layer by ramming, watering etc, disposing of surplus

Page 617: DAR_Vol_1

Carriage of excavated material beyond the first 50m will be paid under carriage of materials” vide sub-headCarriage by animal and mechanical transport will be reckoned in terms of nearest km. distance of 0.5km or more will be taken as 1 km and distance of less than 0.5 km ignored, However, when the totallead is less than 0.5 km it will not be ignored but paid for separately in successive stages of 50msubject to the conditions that the total rate worked out on these bases does not exceed the rate for

Clearing jungle including uprooting of rank vegetation, grass, brush wood, treesand saplings of girth upto 30 cm measured at a height of 1 m above ground leveland removal of rubbish upto a distance of 50 m outside the periphery of the area

2.32 : Clearing grass and removal of the rubbish upto a distance of 50 m outside the

Felling trees of the girth (measured at a height of 1 m above ground level) including

Page 618: DAR_Vol_1

Felling trees of the girth (measured at a height of 1 m above ground level) including

Felling trees of the girth (measured at a height of 1 m above ground level) including

Page 619: DAR_Vol_1

Felling trees of the girth (measured at a height of 1 m above ground level) including

Supplying chemical emulsion in sealed containers including delivery as specified.

Page 620: DAR_Vol_1

Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite

2.35.1 : Along external wall where the apron is not provided using chemical emulsion @7.5 litres / sqm of the vertical surface of the substructure to a depth of 300 mm

Diluting and injecting chemica emulsion for POST-CONSTRUCTIONAL anti-termite

2.35.2 : Along the external wall below concrete or masonry apron using chemical emulsion

Page 621: DAR_Vol_1

Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite

2.35.3 : Treatment of soil under existing floors using chemical emulsion @ one litre per

Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite

2.35.4 : Treatment of existing masonry using chemical emulsion @ one litre per hole at300 mm interval including drilling holes at 45 degree and plugging them with cement

Page 622: DAR_Vol_1

Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite

2.35.5: Treatment at points of contact of wood work by chemical emulsion Chlorpyriphos/Lindane (in oil or kerosene based solution) @ 0.5 litres per hole by drilling 6 mmdia holes at downward angle of 45 degree at 150 mm centre to centre and sealing

Page 623: DAR_Vol_1

2.36 : Deduct for disposed soil not levelled and neatly dressed (against Item No. 2.6,&2.7)

Page 624: DAR_Vol_1

Providing and laying in position cement concrete of specified grade excluding the

1:1:2 ( 1 Cement: 1 coarse sand : 2 graded stone aggregate 20 mm nominal size)

Amount

448

45.23

22.612,74528.85

14.66220.46

96.922814

14.34,080.03

Page 625: DAR_Vol_1

40.84,120.83

618.124,738.954,738.95

Providing and laying in position cement concrete of specified grade excluding the

Amount

399196

45.23255

22.611,80018.92

14.66220.46

96.922814

14.33,125.1

31.253,156.35

473.453,629.83,629.8

Providing and laying in position cement concrete of specified grade excluding the

1:2:4 ( 1 Cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)

Page 626: DAR_Vol_1

Providing and laying in position cement concrete of specified grade excluding the

1:2:4 ( 1 Cement: 2 coarse sand : 4 graded stone aggregate 40 mm nominal size)

Providing and laying in position cement concrete of specified grade excluding the

1:3:6 ( 1 Cement: 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)

Page 627: DAR_Vol_1

Providing and laying in position cement concrete of specified grade excluding the

1:3:6 ( 1 Cement: 3 coarse sand : 6 graded stone aggregate 40 mm nominal size)

Providing and laying in position cement concrete of specified grade excluding the

Page 628: DAR_Vol_1

Providing and laying in position cement concrete of specified grade excluding the

1:4:8 ( 1 Cement: 4 coarse sand : 8 graded stone aggregate 40 mm nominal size)

Page 629: DAR_Vol_1

Providing and laying in position cement concrete of specified grade excluding the

Amount

422.5

16837.5912.77150.425.01

7658.04

14.66

220.4696.92

2814

13.521,976.87

19.771,996.64

299.52,296.142,296.15

Providing and laying in position cement concrete of specified grade excluding the

4.1.10 1:5:10 ( 1 Cement: 5 coarse sand : 10 graded stone aggregate 40 mm nominal size)Amount

422.5

16837.5912.77

28225.01

5856.15

14.66220.46

96.9228

Page 630: DAR_Vol_1

1413.52

1,926.5819.27

1,945.85291.88

2,237.732,237.75

Providing and laying in position cement concrete of specified grade excluding the

4.1.11 1:5:10 ( 1 Cement: 5 fine sand : 10 graded stone aggregate 40 mm nominal size)

Providing and laying in position cement concrete of specified grade excluding the

Page 631: DAR_Vol_1

Providing and laying in position cement concrete of specified grade excluding the

Page 632: DAR_Vol_1

Providing and laying cement concrete in retaining walls, return walls (any thick-ness) including attached pilasters, columns, piers, abutmets, pillars, posts, struts,buttresses, string or lacing courses, parapets, coping bed blocks, anchor blocks,plain window sills, fillets etc upto floor five level, excluding the cost of centring,

Providing and laying cement concrete in retaining walls, return walls (any thick-ness) including attached pilasters, columns, piers, abutmets, pillars, posts, struts,buttresses, string or lacing courses, parapets, coping bed blocks, anchor blocks,plain window sills, fillets etc upto floor five level, excluding the cost of centring,

Page 633: DAR_Vol_1

Providing and laying cement Concrte in retaining walls, return walls (any thickness)including attached pilasters, columns, piers, abutmets, pillars, posts, struts, buttresses,string or lacing courses, parapets, coping bed blocks, anchor blocks, plain windowsills, fillets etc upto floor five level, excluding the cost of centring, shuttering and

Page 634: DAR_Vol_1

Providing and laying cement Concrte in retaining walls, return walls (any thickness)including attached pilasters, columns, piers, abutmets, pillars, posts, struts, buttresses,string or lacing courses, parapets, coping bed blocks, anchor blocks, plain windowsills, fillets etc upto floor five level, excluding the cost of centring, shuttering and

Page 635: DAR_Vol_1

Providing and laying cement Concrte in retaining walls, return walls (any thickness)including attached pilasters, columns, piers, abutmets, pillars, posts, struts, buttresses,string or lacing courses, parapets, coping bed blocks, anchor blocks, plain windowsills, fillets etc upto floor five level, excluding the cost of centring, shuttering and

Providing and laying cement Concrte in retaining walls, return walls (any thickness)including attached pilasters, columns, piers, abutmets, pillars, posts, struts, buttresses,string or lacing courses, parapets, coping bed blocks, anchor blocks, plain windowsills, fillets etc upto floor five level, excluding the cost of centring, shuttering and

Page 636: DAR_Vol_1

Providing and laying cement Concrte in retaining walls, return walls (any thickness)including attached pilasters, columns, piers, abutmets, pillars, posts, struts, buttresses,string or lacing courses, parapets, coping bed blocks, anchor blocks, plain windowsills, fillets etc upto floor five level, excluding the cost of centring, shuttering and

Page 637: DAR_Vol_1

Centering shuttering including struttings, propping etc. and removal of form work

Page 638: DAR_Vol_1

Centering shuttering including struttings, propping etc. and removal of form work

Retaining walls, return walls, walls (any thickness) including attached pilasters, but-

Centering shuttering including struttings, propping etc. and removal of form work

Page 639: DAR_Vol_1

Providing and laying cement concrete in kerbs, steps and the like at or near ground

1:2:4 (1 Cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size).

Page 640: DAR_Vol_1

Providing and laying cement concrete in kerbs, steps and the like at or near ground

1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size).

Providing and fixing upto floor five level precast cement concrete string or lacingcourses, copings, bed plates, anchor blocks, plain window sills, shelves, louvers,steps, stair cases, etc. including hoisting and setting in position with cement mortar1:3 (1 Cement: 3 coarse sand), cost of required centring, shuttering and finishing

1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate 20mm nominal size).

Page 641: DAR_Vol_1

Providing and fixing upto floor five level precast cement concrete string or lacingcourses, copings, bed plates, anchor blocks, plain window sills, shelves, louvers,steps, stair cases, etc. including hoisting and setting in position with cement mortar1:3 (1 Cement: 3 coarse sand), cost of required centring, shuttering and finishingsmooth with 6mm thick cement plaster 1:3 (1 Cement: 3 fine sand) on exposed

Page 642: DAR_Vol_1

Providing and fixing at or near ground level precast cement concrete in kerbs, edgingsetc. as per approved pattern and setting in position with cement mortar 1:3 (1 Ce-ment: 3 coarse sand) including the cost of required centring, shuttering and finish-ing smooth with 6mm thick cement plaster 1:3 (1 cement: 3 fine sand) on exposed

1:2:4 ( 1 cement: 2 coarse sand : 4 graded stone aggregate 20mm nominal size).

Page 643: DAR_Vol_1

including hoisting and setting in position with cement mortar 1:3 (1 cement: 3 coarsesand), cost of required centring, shuttering and finishing smooth with 6mm thick

Page 644: DAR_Vol_1

1:2:4 ( 1 cement: 2 coarse sand : 4 graded stone aggregate 20mm nominal size).

Page 645: DAR_Vol_1

including hoisting and setting in position with cement mortar 1:3 (1 cement: 3 coarsesand), cost of required centring, shuttering and finishing smooth with 6mm thick

1:3:6 (1 cement: 3 coarse sand : 6 graded stone aggregate 20mm nominal size).

Page 646: DAR_Vol_1

including hoisting and setting in position with cement mortar 1:3 (1 cement : 3 coarsesand), cost of required centring, shuttering and finishing smooth with 6mm thick

1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate 20mm nominal size).

including hoisting and setting in position with cement mortar 1:3 (1 cement : 3 coarsesand), cost of required centring, shuttering and finishing smooth with 6mm thick

1:3:6 (1 Cement: 3 coarse sand : 6 graded stone aggregate 20mm nominal size).

Page 647: DAR_Vol_1

Precasting and placing in position 125 mm dia Bollards 600 mm high of requiredshape including providing M.S. Pipe Sleeve 50 mm dia 300 mm long in the Bollardand M.S. Pipes 40 mm dia and 450 mm long with 150xl50x6mm M.S. plate welded atbottom and embedded 150mm in cement concrete 1:3:6 (1 Cement: 3 coarse sand :6 graded stone aggregate 20 mm nominal size) including necessary excavation ofsize 250x250x450mm^deep for the same in bitumen/concrete pavement at specified

Page 648: DAR_Vol_1

Providing and laying damp-proof course 40mm thick with cement concrete 1:2:4 (1

Providing and laying damp-proof course 50mm thick with cement concrete 1:2:4 (1

Page 649: DAR_Vol_1

Extra for providing and mixing water proofing material in cement concrete work @

Applying a coat of residual petroleum bitumen of penetration 80/100 of approvedquality using 1.7kg per square metre on damp proof course after cleaning the surface

Page 650: DAR_Vol_1

4.14 Extra for concrete work in superstructure above floor V level for each four floors or

Page 651: DAR_Vol_1

Making plinth protection 50mm thick of cement concrete 1:3:6 (1 cement : 3 coarsesand : 6 graded stone aggregate 20 mm nominal size) over 75mm bed of dry brickballast 40mm nominal size well rammed and consolidated and grouted with fine

Page 652: DAR_Vol_1

excluding the cost of centring, shuttering, finishing and reinforcement - All work

1:1:2 (1 cement: 1 coarse sand : 2 graded stone aggregate 20 mm nominal size).

Page 653: DAR_Vol_1

excluding the cost of centring, shuttering, finishing and reinforcement - All work

1:1.5:3 (1 cement: 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)

excluding the cost of centring, shuttering, finishing and reinforcement - All work

Page 654: DAR_Vol_1

abutments, posts and struts etc. upto floor five level excluding cost of centring,

Page 655: DAR_Vol_1

abutments, posts and struts etc. upto floor five level excluding cost of centring,

1:1.5:3 (1 cement: 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)

abutments, posts and struts etc. upto floor five level excluding cost of centring,

1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size).

Page 656: DAR_Vol_1

Reinforced cement concrete work in beams, suspended floors, roofs having slopeupto 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills,staircases and spiral stair cases upto floor five level excluding the cost of centring,shuttering, finishing and reinforcement with 1:2:4 (1 cement : 2 coarse sand : 4 graded

Page 657: DAR_Vol_1

Providing and laying upto floor five level reinforced cement concrete in kerbs, stepsand the like excluding the cost of centring, shuttering, finishing and reinforcementwith 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal

Reinforced cement concrete work in arches, arch ribs, domes, vaults, shells, foldedplate and roofs having slope more than 15° upto floor five level excluding the cost ofcentring, shuttering, finishing and reinforcement with 1:2:4 (1 cement: 2 coarse sand:

Page 658: DAR_Vol_1

Reinforced cement concrete work in chimneys, shafts, upto floor five level excludingthe cost of centring, shuttering, finishing and reinforcement with 1:2:4 (1 cement: 2

Reinforced cement concrete work in well-steining excluding the cost of centring,shuttering, finishing and reinforcement with 1:2:4 (1 cement: 2 coarse sand : 4 graded

Page 659: DAR_Vol_1

forming box louvers, facias and eaves boards upto floor five level excluding thecost of centring, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement: 1.5

Page 660: DAR_Vol_1

Centring and shuttering including strutting, propping etc. and removal of form for :

Page 661: DAR_Vol_1

Centring and shuttering including strutting, propping etc. and removal of form for :

Centring and shuttering including strutting, propping etc. and removal of form for:

Page 662: DAR_Vol_1

Centring and shuttering including strutting, propping etc. and remova of form for:

Page 663: DAR_Vol_1

Centring and shuttering including strutting, propping etc. and removal of form for:

Page 664: DAR_Vol_1

Centring and shuttering including strutting, propping etc and removal or form tor:

Page 665: DAR_Vol_1

Centring and shuttering including strutting, propping etc. and removal of form for:

Page 666: DAR_Vol_1

Centring and shuttering including strutting, propping etc. and removal of form for:

Page 667: DAR_Vol_1

Centring and shuttering including strutting, propping etc. and removal of form for

Page 668: DAR_Vol_1

Centring and shuttering including strutting, propping etc. and removal of form for :

Page 669: DAR_Vol_1

Centring and shuttering including strutting, propping etc. and removal of form for :

Centring and shuttering including strutting, propping etc. and removal of form for :5.9.13 Vertical and horizontal fins individually or forming box louvers band, facias and

Page 670: DAR_Vol_1

5.9.14 Extra for shuttering in circular work sqm 20% of respective centring & shotting

Page 671: DAR_Vol_1

Centring and shuttering including strutting, propping etc. and removal of form for :5.9.15 Small lintels not exceeding 1.5m clear span, moulding as in cornices, window sills,

Centring and shuttering including strutting, propping etc. and removal of form for :

Page 672: DAR_Vol_1

Centring and shuttering including strutting, propping etc. and removal of form for :

Page 673: DAR_Vol_1

Centring and shuttering including strutting, propping etc. and removal of form for :

Page 674: DAR_Vol_1

Centring and shuttering including strutting, propping etc. and removal of form for :

Page 675: DAR_Vol_1

Centring and shuttering including strutting, propping etc. and removal of form for:

Page 676: DAR_Vol_1

Centring and shuttering including strutting, propping etc. and removal of form for:5.9.20 Suspended floors, roofs, landings, balconies and access platform, with water proof

Page 677: DAR_Vol_1

Centring and shuttering including strutting, propping etc. and removal of form for :5.9.21 Lintels, beams, plinth beams, girders, bressumers and cantilevers, with water proof

Page 678: DAR_Vol_1

Providing and fixing tie bolt, spring coil and plastic cone in wall shuttering complete

Providing and fixing tie bolt, spring coil and plastic cone in wall shuttering complete

Page 679: DAR_Vol_1

Providing and fixing tie bolt, spring coil and plastic cone in wall shuttering complete

Providing and fixing tie bolt, spring coil and plastic cone in wall shuttering complete

Extra for additional height in centring, shuttering where ever required with adequatebracing, propping etc. including cost of de-shuttering and decentring at all levels,

Page 680: DAR_Vol_1

over a height of 3.5 m, for every additional height of 1 metre or part thereof (Plan

Providing, hoisting and fixing upto floor five level precast reinforced cement concretework in string courses, bands, copings, bed plates, anchor blocks, plain windowsills and the like including the cost of required centring, shuttering, finishing smoothwith 6 mm thick cement plaster 1:3 (1 cement: 3 fine sand) on exposed surfacescomplete but excluding cost of reinforcement with 1:2:4 (1 cement: 2 coarse sand: 4

Page 681: DAR_Vol_1

excluding the cost of reinforcement with 1:2:4 (1 cement: 2 coarse sand : 4 graded

Page 682: DAR_Vol_1

cement mortar 1:3 (1 cement : 3 coarse sand) cost of required centring, shutteringand finishing smooth with 6 mm thick cement plaster 1:3 (1 cement : 3 fine sand)on exposed surfaces complete but excluding the cost of reinforcement with 1:2:4

5.15 : Providing, hoisting and fixing upto floor five level precast reinforced cement concretein lintels, beams and bressumers including setting in cement mortar 1:3 (1 cement :3 coarse sand), cost of required centring and shuttering and finishing smooth with

excluding the cost of reinforcement with 1:2:4 (1 cement: 2 coarse sand : 4 graded

Page 683: DAR_Vol_1

5.16 : Providing, hoisting and fixing upto floor five level precast reinforced cement concretein shelves including setting in cement mortar 1:3 (1 cement : 3 coarse sand), cost ofrequired centring, shuttering and finishing with neat cement punning on exposedsurfaces but excluding the cost of reinforcement with 1:2:4 (1 cement: 2 coarse

Page 684: DAR_Vol_1

5.17 : Providing, hoisting and fixing upto floor five level precast reinforced cement concretein vertical & horizontal fins individually or forming box louvers setting in cement mortar1:2 (1 cement : 2 coarse sand) including the cost of required centring, shuttering andfinishing smooth with 6mm thick cement plaster 1:3 (1 cement : 3 fine sand) on exposedsurfaces complete but excluding the cost of reinforcement with 1:2:4 (1 cement: 2

Page 685: DAR_Vol_1

5.18 : Providing precast cement concrete Jali 1:2:4 (1 cement: 2 coarse sand : 4 graded

cement mortar 1:3 (1 cement: 3 fine sand) etc. complete excluding plastering of

5.18 : Providing precast cement concrete Jali 1:2:4 (I cement: 2 coarse sand : 4 graded

including centring and shuttering, roughening cleaning, fixing and finishing in cementmortar 1:3 (1 cement: 3 fine sand) etc. complete excluding plastering of the jambs,

Page 686: DAR_Vol_1

Providing precast cement concrete Jali 1:2:4 (1 cement: 2 coarse sand : 4 graded

cement mortar 1:3 (1 cement: 3 fine sand) etc. complete excluding plastering of

5.19 : Encasing rolled steel sections, in beams and columns, with cement concrete 1:2:4(1 cement: 2 coarse sand : 4 graded stone aggregate 12.5mm nominal size) including

Page 687: DAR_Vol_1

5.20 : Encasing rolled steel section in grillages with cement concrete 1:2:4 (1 cement: 2coarse sand : 4 graded stone aggregate 12.5mm nominal size) including centring

5.21 : Extra for providing and fixing expanded metal mesh of size 20x60mm and strands3.25mm wide 1.6mm thick weighing 3.64 kg. per sqm. for encasing of rolled steel

Page 688: DAR_Vol_1

Reinforcement for R.C.C. work including straightening, cutting, bending, placing

Page 689: DAR_Vol_1

Reinforcement for R.C.C. work including straightening, cutting, bending, placing

Reinforcement for R.C.C. work including straightening, cutting, bending, placing

Page 690: DAR_Vol_1

Reinforcement for R.C.C. work including straightening, cutting, bending, placing

Reinforcement for R.C.C. work including straightening, cutting, bending, placing

Page 691: DAR_Vol_1

5.23 : Deduct for omitting in R.C.C. work smooth finishing of the exposed surface with

5.24 : Extra for rendering smooth the top of suspended floors, landings and staircases (treadsand risers) with cement mortar 1:2 (1 cement: 2 coarse sand) including a floating coatof neat cement and protecting the surface with a layer of 7.5 cm of earth laid over 15mm of fine sand in case of suspended floor and bricks laid in mud mortar in case of

Page 692: DAR_Vol_1

5.25 : Providing and fixing in position copper plate as per design for expansion joints.

Page 693: DAR_Vol_1

5.27 : Providing and filling in position bitumen mix filler of Proportion 80 kg. of hot bitumen,

5.28 : Providing and fixing in position 12mm thick bitumen impregnated fibre boardconforming to IS: 1838 including cost of primer, sealing compound in expansion joints.

Page 694: DAR_Vol_1

5.29 : Providing and fixing sheet covering over expansion joints with iron screws as per

Page 695: DAR_Vol_1

Providing and fixing sheet covering over expansion joints with iron screws as per

Providing and fixing sheet covering over expansion joints with iron screws as per

Page 696: DAR_Vol_1

5.30 : Add or deduct for plaster drip course/ groove in plastered surface or moulding to

5.31 : Extra for laying reinforced cement concrete in or under water and/ or liquid mudincluding cost of pumping or bailing out water and removing slush etc., complete.

Page 697: DAR_Vol_1

5.33 : Providing and laying in position machine batched, machine mixed and machine

concrete work including pumping of concrete to site of laying but excluding thecost of centring, shuttering, finishing and reinforcement, including Admixtures inrecommended proportions as per IS 9103 to accelerate, retard setting of concrete,improve workability without impairing strength and durability as per direction ofEngineer-in-charge. M-25 grade reinforced cement concrete by using 410kg. of cement

Page 698: DAR_Vol_1

5.34 : Add or deduct for providing richer or leaner mixes respectively at all floor levels.5.34.1 : Providing M-30 grade concrete by using 420kg of Cement per cum of concrete

5.34 : Add or deduct for providing richer or leaner mixes respectively at all floor levels.5.34.2 : Providing M-35 grade concrete by using 428kg ofcement per cum of concrete

Add or deduct for providing richer or leaner mixes respectively at all floor levels.5.34.3 Providing M-30 grade concrete by using 435kg of cement per cum of concrete instead

Page 699: DAR_Vol_1

Deduct for using less cement than the quantity as provided in the item of batch mix

Providing and placing in position precast reinforced cement concrete waffle units squareor rectangular as per design and shape for floors and roofs in 1:1 1/2:3 (1 Cement: 1/2coarse sand : 3 graded stone aggregate 10mm nominal size) including flush or deepruled pointing at joints in Cement mortar 1:2 (1 Cement : 2 Fine sand), making neces-sary holes of required sizes for carrying through service lines etc., providing steel hooksfor lifting etc, form work in precasting, handling, hoisting, centering and erection com-

Page 700: DAR_Vol_1

Brick work with modular bricks of class designation 75 in foundation and plinth in:

Brick work with modular bricks of class designation 75 in foundation and plinth in:

Page 701: DAR_Vol_1

6.3 Brick work with machine moulded perforated bricks of class designation 125conforming to IS: 2222 -1991 in superstructure above plinth level upto floor five

6.3 Brick work with machine moulded perforated bricks of class designation 125 con-forming to IS: 2222 -1991 in superstructure above plinth level upto floor five level in

Page 702: DAR_Vol_1

Brick work with F.P.S. bricks of class designation 75 in superstructure above plinth

Brick work with F.P.S. bricks of class designation 75 in superstructure above plinth

Page 703: DAR_Vol_1

Extra for brick work in superstructure above floor V level for each four floors or part

Extra for forming cavity 5cm to 7.5cm wide in cavity walls with necessary weep andvent holes including use of cores and cost of providing and fixing bitumastic coatedM .S. ties 300mm long of 25x3mm section at not less than 3 ties per sqm as per

Page 704: DAR_Vol_1

Providing half brick masonry with F.P.S. bricks of class designation 75 in cementmortar 1:3 (1 Cement : 3coarse sand) in superstructure for closing cavity 5 to 7.5 cmwide in cavity wall complete with 10 cm / 11.4 cm wide bitumen felt type 3 grade 1.

Brick work 7 cm thick with F.P.S. brick of class designation 75 in cement mortar 1:3

Page 705: DAR_Vol_1

Brick work in plain arches in superstructure including centring and shuttering com-plete for span upto 6 metres with F.P.S. bricks of class designation 75 in cement

Page 706: DAR_Vol_1

6.10 Brick work in gauged arches in superstructure in cement mortar 1:3 (1 cement : 3coarse sand) including centring and shuttering complete, for span upto 6 meters

Page 707: DAR_Vol_1

6.12 Half brick masonry with F.P.S. bricks of class designation 75 in foundation and plinth

Page 708: DAR_Vol_1

6.12 Half brick masonry with F.P.S. bricks of class designation 75 in foundation and plinth

Half brick masonry with F.P.S. bricks of class designation 75 in superstructure above

Page 709: DAR_Vol_1

Half brick masonry with F.P.S. bricks of class designation 75 in superstructure above

Extra for half brick masonry in superstructure, above floor V level for every fourfloors or part thereof by mechanical means by lifting material using mobile crane.

Page 710: DAR_Vol_1

Extra for providing and placing in position 2 Nos. 6mm dia. M.S. bars at every third

Tile brick masonry with tite bricks of class designation 100 in foundation and plinth in:

Tile brick masonry with tite bricks of class designation 100 in foundation and plinth in:

Page 711: DAR_Vol_1

conforming to IS : 2690 (Part I) -1993 in foundation and plinth in cement mortar

Tile brick masonry with tile brick of class designation 100 in superstructure above

Page 712: DAR_Vol_1

Extra for tile brick masonry with tile bricks of class designation 100 in superstruc-

Tile brick masonry with tite bricks of class designation 100 in plain arch work insuperstructure in cement mortar 1 : 4 ( 1 cement : 4 coarse sand) including centering

Page 713: DAR_Vol_1

Tile brick masonry with tile bricks of class designation 100 in gauged arch work insuperstructure in cement mortar 1:4 (1 cement: 4 coarse sand) including centring

Page 714: DAR_Vol_1

Honey-comb brick work 10/11.4 cm thick with bricks of class designation 75 in ce-

6.24 Extra for laying brick work in or under water and/or liquid mud including cost of

NOTE :- The quantity will be calculated by multiplying the depth measured from sub - soilwater level upto the centre of gravity of brick work under sub - water with the quantityof brick work in cum executed under the sub - soil water. The depth of cento ofgravity shall be reckoned correct to 0.1m, 0.05m or more shall be taken as 0.1 m and

Page 715: DAR_Vol_1

Brick work with selected F.P.S. bricks of class designation 75 in exposed brick workincluding making horizontal and vertical grooves 10mm wide 12mm deep completefrom ground level upto plinth level in cement mortar 1:6 (1 cement: 6 coarse sand)

Brick work with modular bricks of class designation 75 in exposed brick work in-cluding making horizontal and vertical grooves 10mm wide 12mm deep completefrom ground level upto plinth level in cement mortar 1:6 (1 cement: 6 coarse sand).

Page 716: DAR_Vol_1

Brick work with machine moulded modular bricks of class designation 125 in ex-posed brick work including making horizontal and vertical grooves 10mm wide 12mmdeep complete from ground level upto plinth level in cement mortar 1:6 (1 cement: 6

posed brick work including making horizontal and vertical grooves 10mm wide 12mm deep complete from ground level upto plinth level in cement mortar 1:6(1 ce-

Page 717: DAR_Vol_1

Brick work with machine moulded perforated F.P.S. bricks of class designation 125conforming IS : 2222-1991 in exposed brick work including making horizontal andvertical grooves 10mm wide 12 mm deep complete from ground level upto plinth

Brick work with machine moulded perforated modular bricks of class designation125 conforming to IS : 2222 -1991 in exposed brick work including making horizontaland vertical grooves 10 mm wide 12mm deep complete from ground level upto plinth

Page 718: DAR_Vol_1

Brick work with clay fly-ash F.P.S. brick of class designation 75 in superstructure

Brick work with clay flyash F.P.S. brick of class designation 75 in superstructure

Page 719: DAR_Vol_1

Extra for exposed brick work/clay flyash brick work in superstructure above floor

Brick work with modular fly ash lime bricks (FALG Bricks) conforming to IS: 12894-2002, class designation 100 average compressive strength in super structure above

Page 720: DAR_Vol_1

Brick work with modular fly ash lime bricks (FALG Bricks) conforming to IS: 12894-2002, class designation 100 average compressive strength in super structure above

Page 721: DAR_Vol_1

Brick work with modular calcium silicate bricks machine moulded conforming toIS:4139-1989, class designation 100 average compressive strength in super structure

Brick work with modular calcium silicate bricks machine moulded conforming toIS:4139-1989, class designation 100 average compressive strength in super structure

Page 722: DAR_Vol_1

Brick work with modular extruded burnt fly ash clay sewer bricks (Conforming to

Brick work with modular extruded burnt fly ash clay sewer bricks (conforming to IS: 4885-1988) in arches in foundation and plinth in cement mortar 1:3(1 cement: 3 fine

Page 723: DAR_Vol_1

Providing and laying autoclaved aerated cement blocks masonry with 100mm thickAAC blocks in super structure above plinth level upto floor V level in cement mortar1:4 (1 cement : 4 coarse sand ) The rate includes providing and placing in position 2

Extra for AAC block masonry in superstructure above floor V level for every four

Providing and laying Gypsum panel partitions 100mm thick with water proof Gypsumpanels of size 666x500x100mm, made of ‘calcite phosphor of Gypsum fixed withtongue and groove, jointed with bonding plaster as per manufacturers specificationsin superstructure above plinth level upto floor V level. Gypsum blocks will have a

Page 724: DAR_Vol_1

Extra for Gypsum panel Partitions in superstructure above floor V level for every

Brick work with mechanised autoclaved flyash lime bricks conforming to I:S 12894 :

Page 725: DAR_Vol_1

Brick work with mechanised autoclaved flyash lime bricks conforming to IS: 12894 :2002of class designation 100 in superstructure above plinth level upto floor V level in.

Extra for mechanised autoclave flyash lime bricks conforming to IS: 12894- 1990 ofclass designation 100 in superstructure above floor V level for each four floors or

designation 75 including grouting with cement mortar 1:4(1 cement: 4 fine sand).

Page 726: DAR_Vol_1

levellingup with cement concrete 1:6:12 (1 cement: 6 coarse sand : 12 graded stone

Extra for random rubble masonry with hard stone in superstructure above plinthlevel and upto floor five level, including levelling up with cement concrete 1:6:12 (1cement: 6 coarse sand : 12 graded stone aggregate 20mm nominal size) at window

Page 727: DAR_Vol_1

7.3 : Extra for random rubble masonry with hard stone in superstructure above floor V

7.5 : Extra for random rubble masonry with hard stone curved on plan for a mean radius

Page 728: DAR_Vol_1

Coursed rubble masonry (first sort) with hard stone in foundation and plinth with :

Coursed rubble masonry (second sort) with hard stone in foundation & plinth with:

Page 729: DAR_Vol_1

7.11 : Extra for coursed rubble masonry with hard stone (first or second sort) curved on

Stone work in plain ashlar in super structure upto floor five level in cement mortar1:6 (1 cement : 6 coarse sand) including pointing with cement mortar 1:2 (1 whitecement: 2 stone dust) with an admixture of pigment matching the stone shade :

Page 730: DAR_Vol_1

Stone work in plain ashlar in super structure upto floor five level in cement mortar1:6 (1 cement : 6 coarse sand) including pointing with cement mortar 1:2(1 whitecement: 2 stone dust) with an admixture of pigment matching the stone shade :

Page 731: DAR_Vol_1

Stone work in plain ashlar in super structure upto floor five level in cement mortar1:6 (1 cement : 6 coarse sand) including pointing with cement mortar 1:2 (1 whitecement: 2 stone dust) with an admixture of pigment matching the stone shade :

Page 732: DAR_Vol_1

Stone work in plain ashlar in super structure upto floor five level in cement mortar1:6 (1 cement : 6 coarse sand) including pointing with cement mortar 1:2 (1 whitecement: 2 stone dust) with an admixture of pigment matching the stone shade :

Page 733: DAR_Vol_1

Stone work plain ashlar in arches in cement mortar 1:3 (1 cement: 3 coarse sand)including centring, shuttering and pointing with white cement mortar 1:2 (1 whitecement : 2 stone dust) with an admixture of pigment matching the stone shade.

Stone work plain ashlar in arches in cement mortar 1:3 (1 cement: 3 coarse sand)i/c centring and shuttering and pointing with white cement mortar 1:2 ( 1 whitecemetn: 2 stone dust) with an admixture of pigment matching the stone shade:

Page 734: DAR_Vol_1

Stone work plain ashlar in domes in cement mortar 1:3 (1 cement: 3 coarse sand)including centring, shuttering and pointing with white cement mortar 1:2 (1 whitecement : 2 stone dust) with an admixture of pigment matching the stone shade.

Page 735: DAR_Vol_1

Stone work plain ashlar in domes in cement mortar 1:3 (1 cement: 3 coarse sand)including c;entring shuttering and pointing with white cement mortar 1:2 (1 whitecement : 2 stone dust) with an admixture of pigment matching the stone shade.

Page 736: DAR_Vol_1

cement mortar 1:6 (1 white cement: 6 coarse sand) including pointing with cementmortar 1:2 (1 white cement: 2 stone dust) with an admixture of pigment matching

Page 737: DAR_Vol_1

cement mortar 1:6 (1 white cement: 6 coarse sand) including pointing with cementmortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching

Page 738: DAR_Vol_1

cement mortar 1:6 (1 white cement: 6 coarse sand) including pointing with cementmortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching

cement mortar 1:6 (1 white cement: 6 coarse sand) including pointing with cementmortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching

Page 739: DAR_Vol_1

7.16 : Extra for stone work, plain ashlar or ashlar punched above floor V level for every

Page 740: DAR_Vol_1

7.18 : Extra for stone work; plain ashlar or ashlar punched curved on plan with a mean

Page 741: DAR_Vol_1

(-)17 144.66

Stone work sunk or moulded or sunk and moulded upto floor five level in cement

Page 742: DAR_Vol_1

mortar 1:6 (1 cement: 6 coarse sand) including pointing with white cement mortar1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the

Stone work sunk or moulded or sunk and moulded upto floor five level in cementmortar 1:6 (1 cement : 6 coarse sand) including pointing with white cement mortar1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the

Page 743: DAR_Vol_1

Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) includingpointing in white cement mortar 1:2 (1 white cement : 2 stone dust) with an admixtureof pigment matching the stone shade : (To be secured to the backing by means of

Page 744: DAR_Vol_1

Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including

admixture of pigment matching the stone shade : (To be secured to the backing by

Page 745: DAR_Vol_1

Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including

admixture of pigment matching the stone shade : (To be secured to the backing by

Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including

Page 746: DAR_Vol_1

admixture of pigment matching the stone shade : (To be secured to the backing by

Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including

admixture of pigment matching the stone shade : (To be secured to the backing by

Page 747: DAR_Vol_1

Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including

admixture of pigment matching the stone shade : (To be secured to the backing by

7.23.2 : Red sand stone - Exposed face machine cut and table rubbed with rough backing.

Page 748: DAR_Vol_1

Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including

admixture of pigment matching the stone shade : (To be secured to the backing

7.23.2 : Red sand stone - Exposed face machine cut and table rubbed with rough backing.

Page 749: DAR_Vol_1

Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including

admixture of pigment matching the stone shade : (To be secured to the backing by

7.23.2 : Red sand stone - Exposed face machine cut and table rubbed with rough backing.

Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thickcement mortar 1:3 (1 cement : 3 coarse sand) including

admixture of pigment matching the stone shade : (To be secured to the backing by

7.23.2 : Red sand stone - Exposed face machine cut and table rubbed with rough backing.

Page 750: DAR_Vol_1

Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including

admixture of pigment matching the stone shade : (To be secured to the backing by

7.23.2 : Red sand stone - Exposed face machine cut and table rubbed with rough backing.

Page 751: DAR_Vol_1

Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including

admixture of pigment matching the stone shade : (To be secured to the backing by

Page 752: DAR_Vol_1

Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including

admixture of pigment matching the stone shade : (To be secured to the backing by

Page 753: DAR_Vol_1

Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including

admixture of pigment matching the stone shade : (To be secured to the backing by

Page 754: DAR_Vol_1

Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including

admixture of pigment matching the stone shade : (To be secured to the backing by

Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including

admixture of pigment matching the stone shade : (To be secured to the backing by

Page 755: DAR_Vol_1

Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including

admixture of pigment matching the stone shade : (To be secured to the backing by

7.23.4 : White sand stone - Exposed face machine cut and table rubbed with rough backing.

Page 756: DAR_Vol_1

Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including

admixture of pigment matching the stone shade : (To be secured to the backing by

White sand stone - Exposed face machine cut and table rubbed with rough backing.

Page 757: DAR_Vol_1

Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including

admixture of pigment matching the stone shade : (To be secured to the backing by

White sand stone - Exposed face machine cut and table rubbed with rough backing.

Page 758: DAR_Vol_1

Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including

admixture of pigment matching the stone shade : (To be secured to the backing by

White sand stone - Exposed face machine cut and table rubbed with rough backing.

Page 759: DAR_Vol_1

Stone work (machine cut edges) for wall lining etc. (veneer work) backing filledwith a grout of 12mm thick cement mortar 1:3 (1 cement : 3 coarse sand) including

admixture of pigment matching the stone shade : (To be secured to the backing by

White sand stone - Exposed face machine cut and table rubbed with rough backing.

Page 760: DAR_Vol_1

7.25 : Providing and fixing stainless steel cramps of required size and shape for anchoringstone wall lining to the backing or securing adjacent stones in stone wall lining incement mortar 1:2(1 cement: 2 coarse sand) including making the necessary chases

7.26 : Providing and fixing stone dowels 10x5x2.50 cm cut to double wedge shape as perdesign in cement mortar 1:2 (1 cement: 2 coarse sand) including making the necessary

Page 761: DAR_Vol_1

7.27 : Providing and fixing copper pins 7.5 cm long 6 mm diameter for securing adjacentstones in stone wall lining in cement mortar 1:2(1 cement: 2 coarse sand) including

beyond the wall as measured along the slope in cement mortar 1:4 (1 cement : 4

stone and supported on and including with bricks cove of class designation 75 incement mortar 1:4 (1 cement : 4 coarse sand) including pointing in cement mortar1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the

Page 762: DAR_Vol_1

beyond the wall as measured along the slope in cement mortar 1:4 (1 cement : 4

stone and supported on and including with bricks cove of class designation 75 incement mortar 1:4 (1 cement : 4 coarse sand) including pointing in cement mortar1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the

Page 763: DAR_Vol_1

projection in cement mortar 1:4 (1 cement: 4 coarse sand) including pointing in

projection in cement mortar 1:4 (1 cement: 4 coarse sand) including pointing in

Page 764: DAR_Vol_1

white cement mortar 1:2(1 white cement: 2 stone dust) with an admixture of pigment

7.30 : 30mm red sand stone sun-shade (chisel-dressed) supported on red sand stonebrackets, fixed in walls with cement mortar 1:4(1 cement: 4 coarse sand) including

Page 765: DAR_Vol_1

7.31 : Providing and fixing red sand stone brackets 55x22.5x45cm sunk and mouldedincluding providing and fixing with 4 Nos. gun metal cramp 25x6mm 30 cm long and

Page 766: DAR_Vol_1

7.32 : Stone work, plain in copings, cornices, string courses and plinth courses, upto 75mm thick in Cement mortar 1:6 (1 cement : 6 coarse sand) including pointing withwhite cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment

Stone work, plain in copings, cornices, string courses and plinth courses, upto 75mm thick in Cement mortar 1:6 (1 cement : 6 coarse sand) including pointing with

Page 767: DAR_Vol_1

Providing and fixing stone jali 40mm thick throughout in cement mortar 1:3 (1

cement: 2 stone dust) with an admixture of pigment, matching the stone shade, jali

Providing and fixing stone jali 40mm thick throughout in cement mortar 1:3 (1

cement: 2 stone dust) with an admixture of pigment, matching the stone shade, jali

7.34 : Extra for laying stone work in or under water and/or liquid mud including cost of

Page 768: DAR_Vol_1

7.36 : Wall lining butch work upto 10.00m height with Dholpur stone 40 mm thick roughfacing on the exposed surface with stone strips of minimum length 300 mm andrequired width including embedding every tenth layer and bottom most layer in

(1 Cement : 3 coarse sand) i/c ruled pointing in cement mortar 1:2 (1 white cement :2 stone dust) with an admixture of pigment to match the shade of stone complete as

Page 769: DAR_Vol_1

work) backing filled with a grout of 12mm thick cement mortar 1:3 (1 Cement : 3coarse sand) and jointed with Cement mortar 1:2 (1 cement : 2 stone dust) includingrubbing and polishing complete. (To be secured to the backing by means of cramps

Page 770: DAR_Vol_1

Stone tile work for wall lining upto 10 m height with special adhesive over 12mm

Stone tile work for wall lining upto 10 m height with special adhesive over 12mm

7.38.1.2:Raj Nagar plain white marble/ Udaipur green marble/ Zebra black marble,

Page 771: DAR_Vol_1

Extra for stone work for wall lining on exterior walls of height more than 10 m from

Providing and fixing dry cladding upto 10 metre heights with 30mm thick gang sawcut stone with (machine cut edges) of uniform colour and size upto lmxlm, fixed tostructural steel frame work and/ or with the help of cramps, pins etc. and sealingthe joints with approved weather sealant as per Architectural drawing and

Page 772: DAR_Vol_1

direction of Engineer-in-charge. (The steel frame work, stainless steel cramps and

Providing and fixing dry cladding upto 10 metre heights with 30mm thick gang saw cut stonewith (machine cut edges) of uniform colour and size upto lmxlm, fixed to structural steelframe work and/ or with the help of cramps, pins etc. and sealing the joints withapproved weather sealant as per Architectural drawing and direction of Engineer-in-charge. (The steel frame work, stainless steel cramps and pins etc. shall be paid for

Page 773: DAR_Vol_1

Providing and fixing structural steel frame (for dry cladding with 30 mm thick gangsaw cut with machine cut edges sand stone) on walls at all heights using M.S. square/rectangular tube in the required pattern as per architectural drawing including costof cutting, bending, welding etc. The frame work shall be supported in wall with thehelp of MS brackets/ lugs of angle iron/ flats etc. which shall be welded to the frameand embedded in brick wall with cement concrete block 1:2:4 (1 cement :2 coarse

including cost of necessary centring and shuttering and with approved expansion

cramps/ pins etc. shall be welded to the frame work to support stone cladding thesteel work will be given a priming coat of “ZINC” primer as approved by Engineer-in-charge and painted with two or more coats of epoxy paint (Shop drawings shall

execution). The frame work shall be fixed in true horizontal & vertical lines/planes.(Only structural steel frame work shall be measured for the purpose of payment,stainless steel cramps shall be paid for separately and nothing extra shall be paid.)

Page 774: DAR_Vol_1

Providing and fixing adjustable stainless steel cramps of approved quality and of

Page 775: DAR_Vol_1

required shape and size adjustable with stainless steel nuts bolts and washer (totalweight not less than 260 gms) for dry stone cladding fixed on frame work at suitablelocation including making necessary recesses in stone slab, drilling required holes

Page 776: DAR_Vol_1

Marble work gang saw cut (polished and machine cut) of thickness 18mm for walllining (veneer work) in cement mortar 1:3 (1 cement : 3 coarse sand) includingpointing with white cement mortar 1:2 (1 white cement : 2 marble dust) with anadmixture of pigment to match the marble shade: (To be secured to the backing by

Marble work gang saw cut (polished and machine cut) of thickness 18mm for walllining (veneer work) in cement mortar 1:3 (1 cement : 3 coarse sand) including pointingwith white cement mortar 1:2 (1 white cement : 2 marble dust) with an admixture ofpigment to match the marble shade: (To be secured to the backing by means of

Page 777: DAR_Vol_1

Providing and fixing 18mm thick gang saw cut mirror polished (premoulded andprepolished) machine cut for kitchen platforms, vanity counters ,window sills , faciasand similar locations of required size of approved shade, colour and texture laidover 20mm thick base cement mortar 1:4 (1 cement : 4 coarse sand) with jointstreated with white cement, mixed with matching pigment, epoxy touch ups, includingrubbing, curing moulding and polishing to edge to give high gloss finish etc. complete

Page 778: DAR_Vol_1

Providing and fixing 18mm thick gang saw cut mirror polished (premoulded andprepolished) machine cut for kitchen platforms, vanity counters ,window sills , faciasand similar locations of required size of approved shade, colour and texture laidover 20mm thick base cement mortar 1:4 (1 cement : 4 coarse sand) with jointstreated with white cement, mixed with matching pigment, epoxy touch ups, includingrubbing, curing moulding and polishing to edge to give high gloss finish etc. complete

Providing and fixing 18mm thick gang saw cut mirror polished (premoulded andprepolished) machine cut for kitchen platforms, vanity counters ,window sills , faciasand similar locations of required size of approved shade, colour and texture laidover 20mm thick base cement mortar 1:4 (1 cement : 4 coarse sand) with jointstreated with white cement, mixed with matching pigment, epoxy touch ups, includingrubbing, curing moulding and polishing to edge to give high gloss finish etc. complete

Page 779: DAR_Vol_1

Providing and fixing 18mm thick gang saw cut mirror polished (premoulded andprepolished) machine cut for kitchen platforms, vanity counters ,window sills , faciasand similar locations of required size of approved shade, colour and texture laidover 20mm thick base cement mortar 1:4 (1 cement : 4 coarse sand) with jointstreated with white cement, mixed with matching pigment, epoxy touch ups, includingrubbing, curing moulding and polishing to edge to give high gloss finish etc. complete

Extra for providing edge moulding to 18mm thick marble stone counters, Vanitiesetc. including machine polishing to edge to give high gloss finish etc. complete as

Page 780: DAR_Vol_1

Extra for providing edge moulding to 18mm thick marble stone counters, Vanitiesetc. including machine polishing to edge to give high gloss finish etc. complete as

Extra for fixing marble /granite stone over and above corresponding basic item, infacia and drops of width upto 150 mm with epoxy resin based adhesive including

Page 781: DAR_Vol_1

Extra for providing opening of required size & shape for wash basins/ kitchen sinkin kitchen platform, vanity counters and similar location in marble/Granite/stonework including necessary holes for pillar taps etc. including rubbing and polishing

Mirror polishing on marble work/Granite work/stone work where ever required to

cement mortar 1:2(1 cement :2 coarse sand) including drilling necessary hole in

Page 782: DAR_Vol_1

cement mortar 1:2 ( 1 cement :2 coarse sand) including drilling necessary hole in

Page 783: DAR_Vol_1

8.9 Stone tile (polished) work for wall lining over 12mm thick bed of cement mortar 1:3(1 cement: 3 coarse sand) and cement slurry @ 3.3 kg/sqm including pointing in

8.9 Stone tile (polished) work for wall lining over 12mm thick bed of cement mortar 1:3(1 cement: 3 coarse sand) and cement slurry @ 3.3 kg/sqm including pointing in

Page 784: DAR_Vol_1

Providing and fixing 18 mm thick stone slab table rubbed, edges rounded and polishedof size 75x50 cm deep and 1.8 cm thick fixed in urinal partitions by cutting a chase ofappropriate width with chase cutter and embedding the stone in the chase withepoxy grout or with cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded

Providing and fixing 18 mm thick stone slab table rubbed, edges rounded and polishedof size 75x50 cm deep and 1.8 cm thick fixed in urinal partitions by cutting a chase ofappropriate width with chase cutter and embedding the stone in the chase withepoxy grout or with cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded

Page 785: DAR_Vol_1

Providing wood work in frames of doors, windows, clerestory windows and other

Providing wood work in frames of doors, windows, clerestory windows and other

Page 786: DAR_Vol_1

Providing wood work in frames of doors, windows, clerestory windows and other

Providing laminated veneer lumber conforming to IS: 14616 and TAD -15: 2001( PartB) in factory made frames of doors, windows, clerestory windows and other frames,

Page 787: DAR_Vol_1

Providing wood work in frames of false ceiling, partitions etc. sawn and put up in

Providing wood work in frames of false ceiling, partitions etc. sawn and put up in

Page 788: DAR_Vol_1

Providing and fixing panelled or panelled and glazed shutters for doors, windowsand clerestory windows including ISI marked black enamelled M.S butt hinges with

Page 789: DAR_Vol_1

Providing and fixing panelled or panelled and glazed shutters for doors, windowsand clerestory windows including ISI marked black enamelled M.S butt hinges with

Page 790: DAR_Vol_1

Providing and fixing panelled or panelled and glazed shutters for doors, windowsand clerestory windows including ISI marked black enamelled M.S butt hinges with

Page 791: DAR_Vol_1

Providing and fixing panelled or panelled and glazed shutters for doors, windowsand clerestory windows including ISI marked black enamelled M.S butt hinges with

Page 792: DAR_Vol_1

Providing and fixing 35 mm thick factory made laminated veneer lumber door shutter

enamelled M.S. butt hinges with necessary screws as per directions of Engineer-in-

12mm thick plain grade - 1, medium density flat pressed three layer particle boardFPT - I or graded wood particle board FPT - I, IS : 3087 marked bonded with BWP

Providing and fixing 35 mm thick factory made laminated veneer lumber door shutter

enamelled M.S. butt hinges with necessary screws as per directions of Engineer-in-

12 mm thick prelaminated (with particle board decorative lamination on both sides)grade - 1, medium density flat pressed, three layer particle board FPT - I or gradedwood particle board FPT - 1, conforming to IS : 3087 bonded with BWP type syntheticresin adhesive as per IS : 848 and prelamination conforming to IS : 12823 Grade 1,

Page 793: DAR_Vol_1

Providing and fixing 35 mm thick factory made laminated veneer lumber door shutter

enamelled M.S. butt hinges with necessary screws as per directions of Engineer-in-

12 mm thick one side prelaminated (with particle board decorative lamination onother sides) and balancing lamination grade - 1 medium density flat pressed, threelayer particle board FPT - I or graded wood particle board FPT-1 conforming to IS :3087 bonded with BWP type synthetic resin adhesive as per IS : 848 and prelamination

Page 794: DAR_Vol_1

Providing and fixing panelling or panelling and glazing in panelled or panelled andglazed shutters for doors, windows and clerestory windows (Area of opening forpanel inserts excluding portion inside grooves or rebates to be measured). Panel-

Providing and fixing panelling or panelling and glazing in panelled or panelled andglazed shutters for doors, windows and clerestory windows (Area of opening forpanel inserts excluding portion inside grooves or rebates to be measured). Panel-

Page 795: DAR_Vol_1

Providing and fixing panelling or panelling and glazing in panelled or panelled andglazed shutters for doors, windows and clerestory windows (Area of opening forpanel inserts excluding portion inside grooves or rebates to be measured). Panelling

9.7.3.1 Decorative plywood both side decorative veneer (Type -1) conforming to IS 1328

Providing and fixing panelling or panelling and glazing in panelled or panelled andglazed shutters for doors, windows and clerestory windows (Area of opening forpanel inserts excluding portion inside grooves or rebates to be measured). Panelling

9.7.3.2 Decorative plywood one side decorative veneer and commercial veneer on other

Page 796: DAR_Vol_1

Providing and fixing panelling or panelling and glazing in panelled or panelled andglazed shutters for doors, windows’ and clerestory windows (Area of opening forpanel inserts excluding portion inside grooves or rebates to be measured). Panelling

9.7.4.1 Decorative plywood one side decorative veneer and commercial veneer on other

Page 797: DAR_Vol_1

Providing and fixing panelling or panelling and glazing in panelled or panelled andglazed shutters for doors, windows and clerestory windows (Area of opening forpanel inserts excluding portion inside grooves or rebates to be measured). Panelling

9.7.5.1 Plain particle board flat pressed, 3 layer or graded wood particle board medium

Providing and fixing panelling or panelling and glazing in panelled or panelled andglazed shutters for doors, windows and clerestory windows (Area of opening forpanel inserts excluding portion inside grooves or rebates to be measured). Panelling

9.7.5.2 Veneered flat pressed three layer or graded wood particle board with commercial

Page 798: DAR_Vol_1

Providing and fixing panelling or panelling and glazing in panelled or panelled andglazed shutters for doors, windows and clerestory windows (Area of opening forpanel inserts excluding portion inside grooves or rebates to be measured). Panelling

9.7.5.3 Prelaminated particle board with decorative lamination on one side and balancing

Providing and fixing panelling or panelling and glazing in panelled or panelled andglazed shutters for doors, windows and clerestory windows (Area of opening forpanel inserts excluding portion inside grooves or rebates to be measured). Panelling

9.7.5.4 Prelaminated particle board with decorative lamination on both sides, Grade I, Type

Page 799: DAR_Vol_1

Providing and fixing panelling or panelling and glazing in panelled or panelled andglazed shutters for doors, windows and clerestory windows (area of opening forpanel inserts excluding portion inside grooves or rebates to be measured). Panellingfor panelled or panelled and glazed shutters 25 mm to 40 mm thick. Coir veneer

Providing and fixing glazed shutters for doors, windows and clerestory windowsusing 4 mm thick float glass panes including black enamelled ISI marked MS butt

Page 800: DAR_Vol_1

Providing and fixing glazed shutters for doors, windows and clerestory windowsusing 4 mm thick float glass panes including black enamelled ISI marked MS butt

Page 801: DAR_Vol_1

Providing and fixing glazed shutters for doors, windows and clerestory windowsusing 4 mm thick float glass panes including black enamelled ISI marked M.S butt

Page 802: DAR_Vol_1

Providing and fixing glazed shutters for doors, windows and clerestory windowsusing 4 mm thick float glass panes including black enamelled ISI marked M.S butt

Page 803: DAR_Vol_1

Providing and fixing factory made laminated veneer lumber glazed shutter conformingto IS 14616 and TADS 15:2001 (Part B), using 4mm thick float glass panes for doors,windows and clerestory windows including ISI marked black enamelled M.S butt

Extra for providing heavy sheet float glass panes instead of ordinary float glass inglazed doors, window and clereslory window shutters (Area of opening of glass

Page 804: DAR_Vol_1

Extra for providing frosted glass panes 4 mm thick instead of ordinary float glass

Deduct for providing pin headed glass panes instead of ordinary float glass panesweighing 4 mm thick in doors, windows and clerestory windows, shutters (Area of

Extra for providing ISI marked Stainless Steel butt hinges instead of black enamelled

Page 805: DAR_Vol_1

Deduct if fixed shutters (without hinges) are provided instead of openable shutters

Deduct if fixed shutters (without hinges) are provided instead of openable shutters

Page 806: DAR_Vol_1

9.16.2.1 Second class teak wood including ISI marked anodised aluminium butt hinge with

Providing and fixing flat pressed 3 layer particle board medium density exteriorgrade (Grade I) or graded wood particle board IS : 3087 marked to frame, backing or

Page 807: DAR_Vol_1

Providing and fixing flat pressed 3 layer particle board medium density exteriorgrade (Grade I) or graded wood particle board IS : 3087 marked to frame, backing or

Providing and fixing prelaminated flat pressed 3 layer (medium density) particleboard or graded wood particle board IS: 3087 marked with one side decorative andother side balancing lamination Grade I,Type II exterior grade IS : 12823 marked in

Page 808: DAR_Vol_1

Providing and fixing prelaminated flat pressed 3 layer (medium densitly) particleboard or graded wood particle board IS: 3087 marked with one side decorative andother side blancing lamination Grade I, Type II exterior grade IS: 12823 marked in

Providing and fixing 25 mm thick shutters for cupboards etc. including ISl marked

Page 809: DAR_Vol_1

9.19 Providing and fixing 25 mm thick shutters for cupboards etc. including ISI marked

Page 810: DAR_Vol_1

Providing and fixing ISI marked flush door shutters conforming to IS: 2202 (Part I)

wood and well matched teak 3 ply veneering with vertical grains or cross bands

35 mm thick including ISI marked Stainless Steel butt hinges with necessary screws.

Page 811: DAR_Vol_1

9.20 Providing and fixing ISI marked flush door shutters conforming to IS: 2202 (PartI) decorative type, core of block board construction with frame of 1st class hardwood and well matched teak 3 ply veneering with vertical grains or cross bands

Providing and fixing ISI marked flush door shutters conforming to IS: 2202 (Part I)

wood and well matched teak 3 ply veneering with vertical grains or cross bands

25 mm thick (for cupboard) including ISI marked nickel plated bright finished M.S.

Page 812: DAR_Vol_1

9.21 Providing and fixing ISI marked flush door shutters conforming to IS: 2202 (Part I)non-decorative type, core of block board construction with frame of 1st class hardwood and well matched commercial 3 ply veneering with vertical grains or cross

9.21 Providing and fixing ISI marked flush door shutters conforming to IS: 2202 (Part I)

hard wood and well matched commercial 3 ply veneering with vertical grains or

30 mm thick including ISI marked Stainless Steel butt hinges with necessary screws.

Page 813: DAR_Vol_1

Providing and fixing ISI marked flush door shutters conforming to IS: 2202 (Part I)non-decorative type, core of block board construction with frame of 1st class hardwood and well matched commercial 3 ply veneering with vertical grains or cross

25mm thick (for cupboard) including ISI marked nickel plated bright finished M.S.

depth on all edges of shutters (over all area of door shutter to be measured) Over

Page 814: DAR_Vol_1

Extra for providing vision panel not exceeding 0.1 sqm in all type of flush doors

Extra for providing vision panel not exceeding 0.1 sqm in all type of flush doors

Extra if louvers (not exceeding 0.2 sqm) are provided in flush door shutters (overall

Page 815: DAR_Vol_1

Providing and fixing 35mm thick wire gauze shutters using galvanised M.S. wiregauze of average width of aperture 1.4mm with wire of dia. 0.63 mm for doors,

Page 816: DAR_Vol_1

Providing and fixing 35mm thick wire gauze shutters using galvanised M.S. wiregauze of average width of aperture 1.4mm with wire of dia. 0.63 mm for doors,

Page 817: DAR_Vol_1

Providing and fixing 35mm thick wire gauze shutters using galvanised M.S. wiregauze of average width of aperture 1.4mm with wire of dia. 0.63 mm for doors,

Page 818: DAR_Vol_1

Providing and fixing 30mm thick wire gauge shutters using galvanised M.S. wiregauge of average width of aperture 1.4mm with wire of dia. 0.63 mm for doors,

Page 819: DAR_Vol_1

Providing and fixing 30mm thick wire gauge shutters using galvanised M.S. wiregauge of average width of aperture 1.4mm with wire of dia. 0.63 mm for doors,

Page 820: DAR_Vol_1

Providing and fixing 30mm thick wire gauze shutters using galvanised M.S. wire

Page 821: DAR_Vol_1

Providing and fixing 30mm thick wire gauze shutters using galvanised M.S. wire

windows and clerestory windows including ISI marked bright finished or/and black

Page 822: DAR_Vol_1

Providing and fixing wire gauze laminated veneer lumber shutters conforming to IS :14616, and as per TADS 15 :2001 (Part B) using galvanised wire gauze with averagewidth of aperture 1.4mm in both directions with wire of dia 0.63mm as per IS : 1568for doors, windows and clerestory windows including ISI marked bright finishedor/ and black enamelled M.S. butt hinges with necessary screws as per directions

Providing and fixing wire gauze laminated veneer lumber shutters conforming to

Page 823: DAR_Vol_1

average width of aperture 1.4mm in both directions with wire of dia 0.63mm as perIS : 1568 for doors, windows and clerestory windows including ISI marked brightfinished or/ and black enamelled M.S. butt hinges with necessary screws as per

Providing 50x50x50mm 2nd class teak wood plugs including cutting brick work andfixing in cement mortar 1:3 (1 cement: 3 fine sand) and making good the walls etc.

Page 824: DAR_Vol_1

Providing and fixing expandable fasteners of specified size with necessary plasticsleeves and galvanised M.S. screws including drilling holes in masonry work/CC/

Providing and fixing expandable fasteners of specified size with necessary plasticsleeves and galvanised M.S. screws including drilling holes in masonry work /CC/

Providing and fixing expandable fasteners of specified size with necessary plasticsleeves and galvanised M.S. screws including drilling holes in masonry work /CC/

Page 825: DAR_Vol_1

Providing and fixing expandable fasteners of specified size with necessary plasticsleeves and galvanised M.S. screws including drilling holes in masonry work /CC/

Providing and fixing 2nd class teak wood plain lining tongued and grooved on and

Page 826: DAR_Vol_1

Providing and fixing 2nd class teak wood plain lining tongued and grooved on and

Providing and fixing 2nd class teak wood plain lining tongued and grooved on and

Page 827: DAR_Vol_1

Providing and fixing 2nd class teak wood plain lining tongued and grooved on and

Page 828: DAR_Vol_1

Providing and fixing in wall lining flat pressed three layer (medium density) particleboard or graded wood prelaminated one side decorative lamination on other sidebalancing lamination Grade I,Type II, IS : 12823 marked including priming coat onunexposed surface, with necessary fixing arrangement and screws etc. complete:

Providing and fixing in wall lining flat pressed three layer (medium density) particleboard or graded wood prelaminated one side decorative lamination on other sidebalancing lamination Grade I, Type II, IS : 12823 marked including priming coat onunexposed surface, with necessary fixing arrangement and screws etc. complete :

Page 829: DAR_Vol_1

Providing and fixing in wall lining flat pressed three layer (medium density) particleboard or graded wood prelaminated one side decorative lamination on other sidebalancing lamination Grade I, Type II, IS : 12823 marked including priming coat onunexposed surface, with necessary fixing arrangement and screws etc. complete:

Providing and fixing specified wood frame work consisting of battens 50x25mmfixed with rawl plug and drilling necessary holes for rawl plug etc. including priming

Page 830: DAR_Vol_1

Providing and fixing decorative plywood 4 mm thick one side decorative veneerconforming to IS: 1328 (type-1) for plain lining / cladding with necessary screws,

Page 831: DAR_Vol_1

lining with necessary screws, priming coat on unexposed surface etc., complete.

9.39 Providing and fixing skirting of prelaminated with (one side decorative and otherside balancing lamination) flat pressed, 3 layer or graded particle board (mediumdensity) Grade I, Type II, IS : 12823 marked, with necessary fixing arrangementsand screws including drilling necessary holes for rawl plugs etc. and priming coat

Page 832: DAR_Vol_1

Providing and fixing skirting of prelaminated with (one side decorative and otherside balancing lamination) flat pressed, 3 layer or graded particle board (mediumdensity) Grade I, Type II, IS : 12823 marked, with necessary fixing arrangementsand screws including drilling necessary holes for rawl plugs etc. and priming coat

Page 833: DAR_Vol_1

Providing and fixing wooden moulded beading to door and window frames with

Providing and fixing wooden moulded beading to door and window frames with

Page 834: DAR_Vol_1

9.40 Providing and fixing wooden moulded beading to door and window frames with

Providing and fixing wooden moulded beading to door and window frames with

Page 835: DAR_Vol_1

Providing and fixing plain jaffri of 35x10 mm laths placed 35 mm apart (frames to

Page 836: DAR_Vol_1

Providing and fixing 18 mm thick, 150 mm wide pelmet of flat pressed 3 layer orgraded wood particle board medium density grade I, IS : 3087 marked includingtop cover of 6 mm commercial ply wood conforming to IS: 303 BWR grade, nickelplated M.S. pipe 20 mm dia ( heavy type ) curtain rod with nickel plated brackets

Providing and fixing 18 mm thick, 150 mm wide pelmet of coir veneer board ISImarked IS : 14842 - 2000, including top cover of 6 mm coir veneer board, nickelplated M.S. Pipe 20 mm dia (heavy type) curtain rod with nickel plated brackets

Page 837: DAR_Vol_1

Extra for using veneered particle board conforming to IS 3097 Grade I, in item of

Page 838: DAR_Vol_1

9.44 Extra for using veneered particle board conforming to IS 3097 Grade I, in item of

Providing and fixing curtain rods of 1.25 mm thick chromium plated brass plate,with two chromium plated brass brackets fixed with C.P. brass screws and wooden

Page 839: DAR_Vol_1

Providing and fixing curtain rods of 1.25 mm thick chromium plated brass plate,with two chromium plated brass brackets fixed with C.P. brass screws and wooden

Providing and fixing curtain rods of 1.25 mm thick chromium plated brass plate,with two chromium plated brass brackets fixed with C.P. brass screws and wooden

Page 840: DAR_Vol_1

Providing and fixing nickel plated M.S. pipe curtain rods with nickel plated brackets:

Providing and fixing nickel plated M.S. pipe curtain rods with nickel plated brackets :

Page 841: DAR_Vol_1

Providing and fixing M.S. grills of required pattern in frames of windows etc. with

Providing and fixing M.S. grills of required pattern in frames of windows etc. with

Page 842: DAR_Vol_1

Providing and fixing expanded metal 20x60mm strands 3.25mm wide and 1.6mm

Page 843: DAR_Vol_1

Providing and fixing hard drawn steel wire fabric 75x25 mm mesh of weight notless than 7.75 Kg per sqm to window frames etc. including 62x19 mm beading of

Providing and fixing fly proof galvanised M.S. wire gauge to windows and clerestorywindows using galvanised M.S. wire gauge with average width of aperture 1.4 mm

Page 844: DAR_Vol_1

Providing and fixing fly proof galvanised M.S. wire gauge to windows and clerestorywindows using galvanised M.S. wire gauge with average width of aperture 1.4 mm

Deduct for fixing 75x25 mm hard drawn steel wire fabric of weight not less than7.75 Kg. per sqm in panelled and glazed door and window shutter instead of glass

Page 845: DAR_Vol_1

Providing 40x5 mm flat iron hold fast 40 cm long including fixing to frame with 10mm diameter bolts, nuts and wooden plugs and embedding in cement concreteblock 30x10 x 15cm 1:3:6 mix (1 cement : 3 coarse sand : 6 graded stone aggregate

Page 846: DAR_Vol_1

Providing and fixing IS : 1341 marked M.S. heavy weight butt hinges with necessary

Providing and fixing IS : 1341 marked M.S. heavy weight butt hinges with necessary

Page 847: DAR_Vol_1

Providing and fixing IS : 1341 marked M.S. heavy weight butt hinges with necessary

Providing and fixing IS : 1341 marked M.S. heavy weight butt hinges with necessary

Page 848: DAR_Vol_1

Providing and fixing ISI marked oxidised M.S. pressed butt hinges with necessary

Providing and fixing ISI marked oxidised M.S. pressed butt hinges with necessary

Providing and fixing ISI marked oxidised M.S. pressed butt hinges with necessary

Page 849: DAR_Vol_1

Providing and fixing ISI marked oxidised M.S. pressed butt hinges with necessary

Providing and fixing ISI marked oxidised M.S. pressed Parliamentary hinges with

Page 850: DAR_Vol_1

Providing and fixing ISI marked oxidised M.S.pressed Parliamentary hinges with

Providing and fixing ISI marked oxidised M.S. pressed Parliamentary hinges with

Page 851: DAR_Vol_1

Providing and fixing ISI marked oxidised M.S. pressed Parliamentary hinges with

Page 852: DAR_Vol_1

Providing M.S. Piano hinges ISI marked IS : 3818 finished with nickel plating and

Providing M.S. Piano hinges ISI marked IS : 3818 finished with nickel plating and

Providing M.S. Piano hinges ISI marked IS : 3818 finished with nickel plating and

Page 853: DAR_Vol_1

Providing and fixing ISI marked oxidised M.S. tower bolt black finish, (Barrel type)

Page 854: DAR_Vol_1

Providing and fixing ISI marked oxidised M.S. tower bolt black finish, (Barrel type)

Providing and fixing ISI marked oxidised M.S. tower bolt black finish, (Barrel type)

Page 855: DAR_Vol_1

Providing and fixing ISI marked oxidised M.S. tower bolt black finish, (Barrel type)

Providing and fixing ISI marked 85x42mm oxidised M.S. pull bolt lock conforming

Providing and fixing ISI marked oxidised M.S. door latches conforming to IS:5930

Page 856: DAR_Vol_1

Providing and fixing ISI marked oxidised M.S. door latches conforming to IS:5930

Providing and fixing ISI marked oxidised M.S. handles conforming to IS:4992 with

Page 857: DAR_Vol_1

Providing and fixing ISI marked oxidised M.S. handles conforming to IS:4992 with

Providing and fixing ISI marked oxidised M.S. handles conforming to IS:4992 with

Page 858: DAR_Vol_1

Providing and fixing oxidised M.S. casement stays (straight peg type) with necessary

Providing and fixing oxidised M.S. casement stays (straight peg type) with necessary

Page 859: DAR_Vol_1

Providing and fixing oxidised M.S. casement stays (straight peg type) with necessary

Providing and fixing oxidised M.S. Safety chain with necessary fixtures for doors.

Page 860: DAR_Vol_1

9.70 : Providing and fixing IS : 12817 marked stainless steel butt hinges with stainless

Providing and fixing IS : 12817 marked stainless steel butt hinges with stainless

Page 861: DAR_Vol_1

Providing and fixing IS : 12817 marked stainless steel butt hinges with stainless

Providing and fixing IS : 12817 marked stainless steel butt hinges (heavy weight)

Providing and fixing IS : 12817 marked stainless steel butt hinges (heavy weight)

Page 862: DAR_Vol_1

9.71: Providing and fixing IS : 12817 marked stainless steel butt hinges (heavy weight)

Providing and fixing bright finished brass butt hinges with necessaryscrews etc.

Page 863: DAR_Vol_1

9.72 : Providing and fixing bright finished brass butt hinges with necessary screws etc.

Providing and fixing bright finished brass butt hinges with necessary screws etc.

Providing and fixing bright finished brass butt hinges with necessary screws etc.

Page 864: DAR_Vol_1

Providing and fixing bright finished brass butt hinges with necessary screws etc.

Page 865: DAR_Vol_1

9.72 : Providing and fixing bright finished brass butt hinges with necessary screws etc.

Page 866: DAR_Vol_1

Providing and fixing bright finished brass towerbolts (barrel type)with necessary

9.74 : Providing and fixing bright finished brass tower bolts (barrel type) with necessary

Page 867: DAR_Vol_1

9.74 : Providing and fixing bright finished brass tower bolts (barrel type) with necessary

9.74 : Providing and fixing bright finished brass tower bolts (barrel type) with necessary

Page 868: DAR_Vol_1

9.76 : Providing and fixing bright finished brass 100 mm mortice latch and lock with 6levers and a pair of lever handles with necessary screws etc. complete (best make

9.77 : Providing and fixing bright finished brass 100 mm mortice latch with one dead bolt

Page 869: DAR_Vol_1

9.78 : Providing and fixing bright finished brass night latch including necessary screws

Providing and fixing special quality bright finished brass cupboard or ward robe

9.79 : Providing and fixing special quality bright finished brass cupboard or ward robe

Page 870: DAR_Vol_1

Providing and fixing special quality bright finished brass cupboard or ward robe

9.79 Providing and fixing special quality bright finished brass cupboard or ward robe

Page 871: DAR_Vol_1

9.80 : Providing and fixing 50 mm bright finished brass cup board or wardrobe knob with

9.81 : Providing and fixing bright finished brass handles with screws etc. complete :

Page 872: DAR_Vol_1

9.81 : Providing and fixing bright finished brass handles with screws etc. complete :

Providing and fixing IS : 3564 marked Aluminium die cast body tubular type universal

Page 873: DAR_Vol_1

Providing and fixing IS : 3564 marked aluminium extruded section body tubulartype universal hydraulic door closer with double speed adjustment with necessary

9.85 : Providing and fixing bright finished brass casement window fastener with necessary

Page 874: DAR_Vol_1

Providing and fixing bright finished brasscasement stays (straight peg type) with

Providing and fixing bright finished brass casement stays (straight peg type) with

Providing and fixing bright finished brass casement stays (straight peg type) with

Page 875: DAR_Vol_1

Providing and fixing chromium plated brass 100 mm mortice latch and lock with 6levers and a pair of lever handles with necessary screws etc. complete (best make

Providing and fixing chromium plated brass night latch including necessary screws

Page 876: DAR_Vol_1

Providing and fixing special quality chromium plated brass cupboard locks with

Providing and fixing special quality chromium plated brass cupboard locks with

Providing and fixing special quality chromium plated brass cupboard locks with

Page 877: DAR_Vol_1

Providing and fixing special quality chromium plated brass cupboard locks with

Providing and fixing chromium plated brass 50 mm cupboard or wardrobe knobs

Providing and fixing chromium plated brass handles with necessary screws etc.

Page 878: DAR_Vol_1

9.92 : Providing and fixing chromium plated brass handles with necessary screws etc.

9.92 : Providing and fixing chromium plated brass handles with necessary screws etc.

Page 879: DAR_Vol_1

9.93 : Providing and fixing chromium plated brass casement window fastener with

Page 880: DAR_Vol_1

Providing and fixing ISI marked aluminium butt hinges anodised (anodic coatingnot less than grade AC 10 as per IS : 1868) transparent or dyed to required colour

Page 881: DAR_Vol_1

Providing and fixing ISI marked aluminium butt hinges anodised (anodic coatingnot less than grade AC 10 as per IS : 1868) transparent or dyed to required colour

Providing and fixing ISI marked aluminium butt hinges anodised (anodic coatingnot less than grade AC 10 as per IS : 1868) transparent or dyed to required colour

Providing and fixing ISI marked aluminium butt hinges anodised (anodic coatingnot less than grade AC 10 as per IS : 1868) transparent or dyed to required colour

Page 882: DAR_Vol_1

Providing and fixing ISI marked aluminium butt hinges anodised (anodic coatingnot less than grade AC 10 as per IS : 1868) transparent or dyed to required colour

Providing and fixing ISI marked aluminium butt hinges anodised (anodic coatingnot less than grade AC 10 as per IS : 1868) transparent or dyed to required colour

Page 883: DAR_Vol_1

Providing and fixing ISI marked aluminium butt hinges anodised (anodic coatingnot less than grade AC 10 as per IS : 1868) transparent or dyed to required colour

Providing and fixing ISI marked aluminium butt hinges anodised (anodic coatingnot less than grade AC 10 as per IS : 1868) transparent or dyed to required colour

Page 884: DAR_Vol_1

coating not less than grade AC 10 as per IS : 1868) transparent or dyed to required

coating not less than grade AC 10 as per IS : 1868) transparent or dyed to required

Providing and fixing aluminium tower bolts ISI marked anodised (anodic coatingnot less than grade AC 10 as per IS : 1868 ) transparent or dyed to required colour

Page 885: DAR_Vol_1

Providing and fixing aluminium tower bolts ISI marked anodised (anodic coatingnot less than grade AC 10 as per IS : 1868 ) transparent or dyed to required colour

Providing and fixing aluminium tower bolts ISI marked anodised (anodic coatingnot less than grade AC 10 as per IS : 1868 ) transparent or dyed to required colour

Page 886: DAR_Vol_1

Providing and fixing aluminium tower bolts ISI marked anodised (anodic coatingnot less than grade AC 10 as per IS : 1868 ) transparent or dyed to required colour

Providing and fixing aluminium tower bolts ISI marked anodised (anodic coatingnot less than grade AC 10 as per IS : 1868 ) transparent or dyed to required colour

Page 887: DAR_Vol_1

Providing and fixing aluminium pull bolt lock anodised ISI marked (anodic coatingnot less than grade AC 10 as per IS : 1868) transparent or dyed to required colour

9.99 : Providing and fixing 50cm long aluminium kicking plate 100x3.15 mm anodised(anodic coating not less than grade AC 10 as per IS : 1868) transparent or dyed to

Providing and fixing aluminium handles ISI marked anodised (anodic coating notless than grade AC 10 as per IS : 1868) transparent or dyed to required colour or

Page 888: DAR_Vol_1

Providing and fixing aluminium handles ISI marked anodised (anodic coating notless than grade AC 10 as per IS : 1868) transparent or dyed to required colour or

9.100 : Providing and fixing aluminium handles ISI marked anodised (anodic coating notless than grade AC 10 as per IS : 1868) transparent or dyed to required colour or

Page 889: DAR_Vol_1

Providing and fixing aluminium hanging floor door stopper ISI marked anodised(anodic coating not less than grade AC 10 as per IS : 1868) transparent or dyed to

Providing and fixing aluminium hanging floor door stopper ISI marked anodised(anodic coating not less than grade AC 10 as per IS : 1868) transparent or dyed to

Providing and fixing aluminium casement stays ISI marked anodised (anodic coatingnot less than grade AC 10 as per IS : 1868) transparent or dyed to required colour

Page 890: DAR_Vol_1

9.103 :Providing and fixing bright finished brass 100 mm mortice latch and lock ISI markedwith six levers and a pair of anodised (anodic coating not less than grade AC 10 asper IS : 1868) aluminium lever handles with necessary screws etc. complete (Best

9.104 : Providing and fixing aluminium tee channels (heavy duty) with rollers, stop end in

Page 891: DAR_Vol_1

9.105 : Providing and fixing partition upto ceiling height consisting of G.I. frame andrequired board including providing and fixing of frame work made of special sectionpower pressed/ role form G.I. sheet with zinc coating of grade 175 consisting offloor and ceiling channel 50mm wide having equal flanges of 32mm and 0.5mmthick fixed to the floor and ceiling at the spacing of 610mm centre to centre withdash fastener of 12.5mm dia-meter,40mm length and the studs 48mm wide havingone flange of 34mm and other flange 36mm and 0.50mm thick fixed vertically withinflanges of floor and ceiling channel and placed at a spacing of 610mm centre tocentre by 6mm dia bolts and nuts at both ends of partition fixed flush to wall withrawl plugs at spacing 450mm centre to centre and fixing of boards to either side offrame work by 25mm drive all screws on studs, floor and ceiling channels at thespacing of 300mm centre to centre, including jointing and finishing to a flush finishwith recommended jointing compound, jointing tape, joint finisher and two coats

9.105.1: 67mm overall thickness partition with 8.5 mm thick double skin Glass reinforced

Page 892: DAR_Vol_1

required board including providing and fixing of frame work made of special sectionpower pressed/ role form G.I. sheet with zinc coating of grade 175 consisting offloor and ceiling channel 50mm wide having equal flanges of 32mm and 0.5mmthick fixed to the floor and ceiling at the spacing of 610mm centre to centre withdash fastener of 12.5mm dia meter 40mm length and the studs 48mm wide havingone flange of 34mm and other flange 36mm and 0.50mm thick fixed vertically withinflanges of floor and ceiling channel and placed at a spacing of 610mm centre tocentre by 6mm dia bolts and nuts at both ends of partition fixed flush to wall wtihrawl plugs at spacing of 450mm centre to centre and fixing of boards to either sideof frame work by 25mm, drive all screws on studs, floor and ceiling channels at thespacing of 300mm centre to centre, including jointing and finishing to a flush finishwith recommended jointing compound, jointing tape, joint finisher and two coats

9.105.2: 75mm overall thickness partition with 12.5mm thick double skin plain Gypsum

Page 893: DAR_Vol_1

required board including providing and fixing of frame work made of special sectionpower pressed/ role form G.I. sheet with zinc coating of grade 175 consisting offloor and ceiling channel 50mm wide having equal flanges of 32mm and 0.5mmthick fixed to the floor and ceiling at the spacing of 610mm centre to centre withdash fastener of 12.5mm dia meter 40mm length and the studs 48mm wide havingone flange of 34mm and other flange 36mm and 0.50mm thick “fixed verticallywithin flanges of floor and ceiling channel and placed at a spacing of 610mm centreto centre by 6mm dia bolts and nuts at both ends of partition fixed flush to wall

channels at the spacing of 300mm centre to centre, including jointing and finishingto a flush finish with recommended jointing compound, jointing tape, joint finisherand two coats of primer suitable for board as per manufacture’s specificatior and

9.105.3: 66mm overall thickness Partition with 8mm thick double skin Calcium SilicateBoard made with Calcareous & Siliceous materials reinforced with cellulose fiber

Non Combustible & Spread of Flame (as per BS standard 476 Part IV & VII), Water,

Page 894: DAR_Vol_1

Providing and fixing partition upto ceiling height consisting of G.I. frame and requiredboard including providing and fixing of frame work made of special section powerpressed/ role form G.I. sheet with zinc coating of grade 175 consisting of floor andceiling channel 50mm wide having equal flanges of 32mm and 0.5mm thick fixed tothe floor and ceiling at the spacing of 610mm centre to centre with dash fastener of12.5mm dia meter 40mm length and the studs 48mm wide having one flange of 34mmand other flange 36mm and 0.50mm thick fixed vertically within flanges of floor andceiling channel and placed at a spacing of 610mm centre to centre by 6mm dia boltsand nuts at both ends of partition fixed flush to wall with rawl plugs at spacing of450mm centre to centre and fixing of boards to either side of frame work by 25mmdrive all screws on studs, floor and ceiling channels at the spacing of 300mm centreto centre, including jointing and finishing to a flush finish with recommended jointingcompound, jointing tape, joint finisher and two coats of primer suitable for board asper manufacture’s specification and direction of Enginner-in-charges all complete

9.105.4: 66mm overall thickness partition using 8mm thick double skin non- asbestosmultipurpose cement board reinforced with cellulose fibre manufactured throughautoclaving process (High pressure steam cured) as per IS: 14862, non combustible,non ignitable ,fire propagation index and surface spread of flame (as per BS 476 partIV, V, VI and VII), moisture, termite & fungus resistant, with suitable fibre cement screw.

Page 895: DAR_Vol_1

9.107.1 75x60x10 mm fitted with 5.5 mm dia M.S.Bright Bar Rod weighing not less than 34 gms.

9.107.2 100x75x10 mm fitted with 5.5 mm dia MSBright Bar Rod weighing not less than 53gms.

Page 896: DAR_Vol_1

9.109 Providing and fixing PTMT door catcher of length 72 mm and dia. of 42 mm with

Page 897: DAR_Vol_1

9.110 Providing and fixing Bamboo jaffery/ fencing consisting of superior quality 25mmdia (Average) half cut bamboo placed vertically and fixed together with three numbershorizontal running members of hollock wood in scantling of section 50X25mm fixedwith nails and G.I wire to existing support complete as per direction of Engineer-in-

Providing and fixing wooden moulded corner beading of triangular shape to thejunction of panelling etc. with iron screws, plugs and priming coat on unexposed

Page 898: DAR_Vol_1

9.112 Providing and fixing 2nd class teak wood lipping/ moulded beading or Taj beadingof size 18X5mm fixed with wooden adhesive like fevicol etc and screws/ nails on theedges of the prelaminated particle board as per direction of Engineer-in-charge.

9.113 Providing and fixing bright finished 100mm mortice lock with 6 levers without pairof handles for aluminium door with necessary screws etc complete (Best make of

Page 899: DAR_Vol_1

Providing and fixing magnetic catcher in cupboard / ward robe shutters including

Providing and fixing magnetic catcher in cupboard / ward robe shutters including

9.115 Providing and fixing powder coated telescopic drawer channels 300mm long with

Page 900: DAR_Vol_1

9.116 Providing and fixing sliding arrangement in racks/ cupboards/cabinets shutter byP/F stainless steel rollers to run inside C or E aluminium channel section (The payment

Providing and fixing factory made UPVC door frame made of UPVC extruded, section

2.0mm+/- 02mm. corners of the door frame to be jointed with galvanized bracketsand stainless steel screws, joint mitred and plastic wilded. The hinge side verticalof the frames reinforced by galvanized M.S. tube of size 19X19mm and 1 mm +/- 0.1mm wall thickness and 3 nos. stainless steel hinges fixed to the frame complete as

Providing and fixing factory made UPVC door frame made of UPVC extruded sectionhaving an overall dimension as. below (tolerance +lmm) with wall thickness 2.0mm+/;0.2mm, corners of the door frame to be jointed with galvanized brackets andstainless steel screws, joint mitred and plastic wilded. The hinge side vertical of

0.1mm wall thickness and 3 nos. stainless steel hinges fixed to the frame complete

Page 901: DAR_Vol_1

9.118.1 24 mm thick factory made PVC door shutters made of styles and rails of a UPVChollow section of size 59x24 mm and wall thickness 2 mm ± 0.2 mm with inbuiltedging on both sides. The styles and rails mitred and joined at the corners by meansof M.S. galvanised/plastic brackets of size 75x220 mm having wall thickness 1.0

galvanised M.S. tube of size 20x20 mm and 1 mm ± 0.1 mm wall thickness. The lockrail made up of’H’ section, a UPVC hollow section of size 100x24 mm and 2 mm ±0.2 mm wall thickness fixed to the shutter styles by means of plastic/galvanisedM.S. ‘U’ cleats. The shutter frame filled with a UPVC multi-chambered single panelof size not less than 620 mm, having over all thickness of 20 mm and 1 mm ± 0.1 mmwall thickness . The panels filled vertically and tie bar at two places by insertinghorizontally 6 mm galvanised M.S. rod and fastened with nuts and washers, completeas per manufacturer’s specification and direction of Engineer-in-charge. (For W.C.

Page 902: DAR_Vol_1

9.118.2 30mm thick factory made Polyvinyl Chloride (PVC) door shutter made of stylesand rails of a UPVC profile section of size 30mm x 60mm and wall thickness 2mm±0.2mm with inbuilt decorative moulding edging on one side. The styles and railswith plastic brackets of size 75x220mm mitre and welded at the corners. The- stilesof the shutter reinforced by inserting galvanized M.S. tube of size 25x20mm and1mm ± 0.1mm wall thickness. The lock rail made up of ‘H’ section, a UPVC profile

shutter style with a UPVC profile section single panel of size not less than 620mm,having overall thickness of 20 mm and 1 mm±0.1 mm wall thickness with 20 mmpanel beading of suitable size /Glass(4mm thick plain glass)/louver section, louverframe of suitable size, as per manufactures specification and direction of Engineer-

9.118.3 25mm thick PVC flush door shutters upto 737mm width of colour and shade asapproved by Engineer-in-charge made out of a one piece Multi chamber extruded

average wall thickness of 1mm ± 0.3mm. PVC foam end cap of size 23x10mm areprovided on both vertical edges to ensure the overall thickness of 25mm. An MS

foam. The Top & Bottom edges of the shutter are covered with an end-cap of the

Page 903: DAR_Vol_1

Providing and fixing factory made P.V.C. door frame of size 50x47mm with a wallthickness of 5mm, made out of extruded 5mm rigid PVC foam sheet mitred at cornersand joined with 2 Nos. of 150mm long brackets of 15x15mm M.S. square tube, thevertical door profiles to be reinforced with 19x19mm M.S. square tube of 19 gauge,EPDM rubber gasket weather seal to be provided through out the frame. The doorframe to be fixed to the wall using M.S. screws of 65/100mm size complete as per

9.120.1 30mm thick factory made solid panel PVC door shutter consisting of frame madeout of M.S. tubes of 19 gauge thickness and size of 19mm x 19mm for stiles, top &bottom rails. M.S .frame shall have a coat of steel primers of approved make andmanufacture M.S. frame covered with 5mm thick heat moulded PVC ‘C channel of

Page 904: DAR_Vol_1

size 30mm thickness, 110mm width out of which 90mm shall be flat and 20mmshall be tapered in 45 degree angle on either side forming stiles; and 5mm thick,110mm wide PVC sheet out of which 90mm shall be flat and 20mm shall be taperedon the inner side to form top and bottom rail and 130mm wide PVC sheet out ofwhich 90mm shall be flat and 20mm shall be tapered on both sides to form lock rail.Top bottom and lock rails shall be provided either side of the panel. 10mm (5mm x2) thick, 20mm wide cross PVC sheet shall be provided as gap insert for top rail &bottom rail. Panelling of 5mm thick PVC sheet to be fitted in the M.S. frame welded/sealed to the stiles & rails with 7mm (5mm +2mm) thick x 15mm wide PVC sheet

additional 5mm thick PVC strip of 20mm width is to be stuck on the interior side of

9.120.2 30mm thick factory made solid both side prelam panel PVC door shutter consistingof frame made out of M.S. tubes of 19 gauge thickness and size of 19mm x 19mmfor stiles, top & bottom rails. M.S. frame shall have a coat of steel primers of approvedmake and manufacture . M.S. frame covered with 5mm thick heat moulded prelamPVC ‘C channel of size 30mm thickness, 70mm width out of which 50mm shall beflat and 20mm shall be tapered in 45degree angle on either side forming stiles; and5mm thick, 95mm wide PVC sheet out of which 75mm shall be flat and 20mm shallbe tapered in 45 degree on the inner side to form top and bottom rail and 115mm

both sides to form lock rail. Top, button and lock rails shall be provided either sideof the panel. 10mm (5mm x 2 ) thick, 20mm wide cross PVC sheet be provided asgap insert for top rail & bottom rail, panelling of 5mm thick both side Prelam PVCsheet to be fitted in the M.S. frame welded/ sealed to the stiles & rails with 7mm

together with solvent cement adhesive. An additional 5mm thick PVC strip of 20mmwidth is to be stuck on the interior side of the ‘C Channel using PVC solvent adhesive

Page 905: DAR_Vol_1

etc. complete as per direction of Engineer-in-charge. manufacturer’s specification

Providing and fixing Fiber Glass Reinforced plastic (FRP) Door Frames of cross-section 90mm x 45mm having single rebate of 32mm x 15mm to receive shutter of30mm thickness .The laminate shall be molded with fire resistant grade unsaturatedpolyester resin and chopped mat .Doorframe laminate shall be 2mm thick and shallbe filled with suitable wooden block in all the three legs. The frame shall be coveredwith fibreglass from all sides. MS stay shall be provided at the bottom to steady the

9.122.1 30 mm thick Glass Fibre Reinforced Plastic (FRP) panelled door shutter of required

Page 906: DAR_Vol_1

unsaturated polyester resin, moulded to 3 mm thick FRP laminate for forming hollowrails and styles, with wooden frame and suitable blocks of seasoned wood inside at

required places for fixing of fittings, cast monolithically with 5mm thick FRP laminatefor panels confirming to TADS 6: 1993 and / or IS: 14856 - 2000 including fixing to

9.122.2 30mm thick fibreglass reinforced plastice (F.R.P.) flush door shutter in differentplain and wood finish made with fire retardant grade unsaturated polyster resin,moulded to 3mm thick FRP laminate all around, with suitable wooden blocks insideat required places for fixing of fittings and polyurethane foam (PUF) / Polystyrenefoam to be used as filler material throughout the hollow panel, casted monolithicallywith testing parameters of F.R.P. laminate conforming to table - 3 of IS: 14856 : 2000,

Page 907: DAR_Vol_1

9.123 Providing and fixing factory made door frame (single rebate) made of solid PVCfoam profile with homogenous fine cellular structure having smooth outer integral

9.124 Providing and fixing 28 mm thick door shutter made of solid PVC foam profile withhomogenous fine cellular structure having smooth outer integral skin having 71mmwidth & 28mm thick as vertical & horizontal styles. Joints are made using solventadhesive and GI ‘C sections (39mm x 19mm x 0.6mm thick) or M S pipe (40mm x20mm ) stiffener frame insert & telescopic polymeric ‘L’ corners .The panel shall be

specifications and directions of the Engineer-in-charge, cover moulding shall be

Page 908: DAR_Vol_1

9.125 Providing and fixing PVC rigid foam sheet 1mm thick on existing door shutters

Providing and fixing 12mm thick panelling or panelling and glazing in panelled orpanelled and glazed shutters for doors, windows and clerestory windows (area of

measured). Panelling for panelled or panelled and glazed shutters 25mm to 40mm

Page 909: DAR_Vol_1

Providing and fixing 12mm thick panelling or panelling and glazing in panelled orpanelled and glazed shutters for doors, windows and clerestory windows (area of

measured). Panelling for panelled or panelled and glazed shutters 25mm to 40mm

Providing & Fixing decorative high pressure laminated sheet of plain / wood grainin gloss / matt / suede finish with high density protective surface layer and reverseside of adhesive bonding quality conforming to IS : 2046 Type S including cost of

Page 910: DAR_Vol_1

9.127 Providing & Fixing decorative high pressure laminated sheet of plain / wood grainin gloss / matt / suede finish with high density protective surface layer and reverseside of adhesive bonding quality conforming to IS : 2046 Type S including cost of

Page 911: DAR_Vol_1

4mm thick of required colour, size and design made by Resin Transfer Moulding(RTM) Machine Technology, resulting in void free compact laminate in single piece,

reinforced by 50x2mm thick M.S. flat with 12mm in built hole for grouting on theexisting wall along with the flanges duly inserted and sealed in the wall completein one single piece casted monolithically, including all necessary fittings . The FRPChajja should be manufactured using unsaturated Polyester resin as per IS: 11551complete with protective Gelcoat U/V coating on Top for complete resistance from

Providing and fixing cup board shutters 25mm thick, with prelaminated flat pressedthree layer particle board or graded wood particle board IS: 12823 marked exterior

balancing lamination including Ilnd class teak wood lipping of 25mm wide xl2 mm

Page 912: DAR_Vol_1

Providing and fixing cup board shutters with 25mm thick veneered particle boardIS : 3097 marked exterior grade (Grade I) of approved make including Ilnd classteak wood lipping of 25mm wide x 12 mm thick with necessary screws and bright

9.130.1 With decorative veneering on one side and commercial veering on other side.

Providing and fixing cup board shutters with 25mm thick veneered particle boardIS : 3097 marked exterior grade (Grade I) of approved make including Ilnd classteak wood lipping of 25mm wide x 12 mm thick with necessary screws and bright

Page 913: DAR_Vol_1

Providing and fixing factory made prelaminated particle board flat pressed threelayer or graded wood particle board with one side decorative finish and other sidebalancing lamination conforming to IS: 12823 Grade 1 Type II, of approved design,and edges sealed with water resistant paint and lipped with aluminium ‘U’ type

cadmium plated steel screws including fixing of aluminium hinges 100x63x4 mmetc. complete as per architectural drawing and direction of Engineer-in-Charge (Cost

Page 914: DAR_Vol_1

9.132 Providing and fixing aluminum U beading of required size to prelaminated /flushdoor shutter including fixing etc. complete as per direction of Engineer-in-charge.

board of required thickness fixed on the ‘W profile (0.55mm thick ) having a knurledweb of 51.55mm and two flanges of 26mm each with lips of 10.55 mm placed @610mm C/C in perimeter channel having one flange of 20mm and another flange of30mm with thickness of 0.55mm and web of length 27mm. Perimeter channel isfixed on the floor and the ceiling with the nylon sleeves @ 610mm C/C with fully

threaded self-tapping drive all screws. Board is fixed to the ‘Wprofile with 25 mmcountersunk ribbed head screws @ 200mm C/C, all complete as per the drawing &directions of engineer-in-charge the joints of the boards are finished with speciallyformulated jointing compound and 48mm wide fiber tape to provide seamless finish.

9.133.1 Tapered edge calcium silicate board made with calcareous & siliceous materialsreinforced with cellulose fiber manufactured through autoclaving process to givestable crystalline structure, Non combustible & spread of Flame (as per BS standard476 Part IV & VII), Water, Termite & Fungus resistant, compressive strength 225 kg/

Page 915: DAR_Vol_1

board of required thickness fixed on the ‘W profile (0.55mm thick ) having a knurledweb of 51.55mm and two flanges of 26mm each with lips of 10.55 mm placed @610mm C/C in perimeter channel having one flange of 20mm and another flangeof 30mm with thickness of 0.55mm and web of length 27mm. Perimeter channel isfixed on the floor and the ceiling with the nylon sleeves @ 610mm C/C with fullythreaded self-tapping drive all screws. Board is fixed to the ‘W^rofile with 25 mmcountersunk ribbed head screws @ 200mm C/C, all complete as per the drawing

manufactured through autoclaving process (high pressure steam cured) as per IS14862 non combustible , non ignitable, fire propagation index and surface spread

of flame (as per BS 476 part IV, V, VI, and VII) moisture , termite & fungus resistant

Page 916: DAR_Vol_1

board of required thickness fixed on the ‘W profile (0.55mm thick ) having a knurledweb of 51.55mm and two flanges of 26mm each with lips of 10.55 mm placed @610mm C/C in perimeter channel having one flange of 20mm and another flangeof 30mm with thickness of 0.55mm and web of length 27mm. Perimeter channel isfixed on the floor and the ceiling with the nylon sleeves @ 610mm C/C with fullythreaded self-tapping drive allscrews. Board is fixed to the ‘W’profile with 25 mmcountersunk ribbed head screws @ 200mm C/C, all complete as per the drawing

Page 917: DAR_Vol_1

10.1 : Structural steel work in single section fixed with or without connecting plate includ-ing cutting, hoisting, fixing in position and applying coat of approved steel primer all

Page 918: DAR_Vol_1

10.2 : Structural steel work riveted, bolted or welded in built up sections, trusses and framedwork, including cutting, hoisting, fixing in position and applying a priming coat of approved

Page 919: DAR_Vol_1

10.3 : Providing and fixing in position collapsible steel shutters with vertical channels20xl0x2mm and braced with flat iron diagonals 20x5mm size with top and bottom railof T-iron 40x40x6mm with 40mm dia, steel pulleys complete with bolts, nuts, lockingarrangement, stoppers, handles, including applying a priming coat of approved steel

Page 920: DAR_Vol_1

10.4 : Providing and fixing 1mm thick M.S. sheet sliding-shutters with frame and diagonalbraces of 40x40x6mm angle 3mm M.S. gusset plates at the junction and corners25mm dia pulley, 40x40x6mm angle and T-iron guide at the top and bottom respectively

Page 921: DAR_Vol_1

10.5 : Providing and fixing 1mm thick M.S. sheet door with frame of 40x40x6mm angle iron

Page 922: DAR_Vol_1

10.5 : Providing and fixing 1mm thick M.S. sheet door with frame of 40x40x6mm angle iron

Page 923: DAR_Vol_1
Page 924: DAR_Vol_1

10.6 : Supplying and fixing rolling shutters of approved make, made of required size M.S.laths interlocked together through their entire length and jointed together at theend by end locks mounted on specially designed pipe shaft with brackets, side guides

springs grade No.2 and M.S. top cover of required thickness for rolling shutters.

Page 925: DAR_Vol_1

10.6 : Supplying and fixing rolling shutters of approved make, made of required size M.S.laths interlocked together through their entire length and jointed together at theend by end locks mounted on specially designed pipe shaft with brackets, sideguides and arrangements for inside and outside locking with push and pull operationcomplete including the cost of providing and fixing necessary 27.5cm long wiresprings grade No.2 and M.S. top coypr of required thickness for rolling shutters.

Supplying and fixing rolling shutters of approved make, made of required size M.S.laths interlocked together through their entire length and jointed together at theend by end locks mounted on specially designed pipe shaft with brackets, sideguides and arrangements for inside and outside locking with push and pull operationcomplete including the cost of providing and fixing necessary 27.5cm long wiresprings grade No.2 and M.S. top’cover of required thickness for rolling shutters.

Page 926: DAR_Vol_1

10.8: Extra for providing mechanical device chain and crank operation for operating rolling

10.8: Extra for providing mechanical device chain and crank operation for operating rolling

Page 927: DAR_Vol_1

Extra for providing grilled rolling shutters manufactured out of 8 mm dia. M.S. barinstead of laths as per design approved by Engineer-in-charge. (area of grill to be

10.10: Fixing standard steel glazed doors, windows and ventilators in walls with 15x3mmlugs 10 cm long embedded in cement concrete blocks 15xl0xl0cm of 1:3:6 (I cement:

nuts as required, including fixing of float glass panes with glazing clips and specialmetal-sash putty of approved make, or metal beading with screws (only steel windowswith lugs, glass panes cut to size and glazing clips or metal beading with screws,

Page 928: DAR_Vol_1

10.11 Providing and fixing factory made ISI marked steel glazed doors, windows andventilators side /top /centre hung with beading and all members such as KlIB andK12 B etc. complete of standard rolled steel sections, joints mitred and flash buttwelded and sash bars tenoned and rivetted with 15x3mm lugs, 10cm long, embeddedin cement concrete blocks 15x10x 10cm of 1:3:6 (1 cement : 3 coarse sand : 6 graded

plugs and screws or with fixing clips or with bolts and nuts as required, includingproviding and fixing of hinges, pivots, float glass panes with glazing clips and specialmetal sash putty of approved make and a priming coat of approved steel primerexcluding the cost of metal beading and other fittings except necessary hinges or

Page 929: DAR_Vol_1

10.12: Extra for providing and fixing steel beading of approved shape and section with

10.13: Providing and fixing T-iron frames for doors, windows and ventilators of mild steelTee-sections, joints mitred and welded with 15x3 mm lugs, 10cm long embedded incement concrete blocks 15x10x10 cm of 1:3:6 (1 cement : 3 coarse sand : 6 gradedstone aggregate 20 mm nominal size) or with wooden plugs and screws or withdash fastener or rawl plugs and screws or with fixing clips or with bolts and nuts asrequird including fixing.of necessary butt hinges and screws and applying a priming

Page 930: DAR_Vol_1

Providing and fixing pressed steel door frames confirming to IS: 4351 manufacturedfrom commercial mild steel sheet of 1.25 mm thickness including hinges jamb, lockjamb, bead and if required angle threshold of mild steel angle of section 50x25mm,

mechanical means, adjustable lugs with split end tail to each jamb including steel

butt hinges 2.5mm thick with mortar guards, lock strike-plate and shock absorbersas specified and applying a coat of approved steel primer after pre-treatment of the

Page 931: DAR_Vol_1

Providing and fixing pressed steel door frames confirming to IS: 4351 manufacturedfrom commercial mild steel sheet of 1.25 mm thickness including hinges jamb, lockjamb, bead and if required angle threshold of mild steel angle of section 50x25mm,

mechanical means, adjustable lugs with split end tail to each jamb including steelbutt hinges 2.5mm thick with mortar guards, lock strike-plate and shock absorbersas specified and applying a coat of approved steel primer after pre-treatment of the

Providing and fixing pressed steel door frames confirming to IS: 4351 manufactured

50x25mm, or base ties of I.25tnm pressed mild steel welded or rigidly fixed togetherby mechanical means, adjustable lugs with split end tail to each jamb including

Page 932: DAR_Vol_1

10.15 Providing and fixing M.S. Tubular frames for doors, windows, ventilators andcupboard with L-Type section made of 1.60mm thick M.S. Sheet, joints mitred andwelded and grinded finish,with profiles of required size with 15x3mm lugs 10cmlong embedded in cement concrete blocks 15x10x10cm of 1:3:6 (1 cement : 3 coarse

screws or rawl plugs and screws or with fixing clips or with bolts and nuts as requiredincluding fixing of necessary butt hinges and screws and applying a priming coat of

Page 933: DAR_Vol_1

Steel work in built up tubular trusses including cutting, hoisting fixing in positionand applying a priming coat of approved steel primer, welded and bolted including

Page 934: DAR_Vol_1

10.16 Steel work in built up tubular trusses including cutting, hoisting fixing in positionand applying a priming coat of approved steel primer, welded and bolted including

Page 935: DAR_Vol_1

Steel work in built up tubular trusses including cutting, hoisting fixing in positionand applying a priming coat of approved steel primer, welded and bolted including

Page 936: DAR_Vol_1

10.17 Providing and fixing M.S. fan clamp type I or II of 16 mm dia M.S. bar bent to shapewith hooked ends in R.C.C. slabs, beams during laying including painting the exposed

10.18 Providing and fixing circular/ Hexagonal cast iron or M.S. sheet box for ceiling fanclamp of internal dia 140mm, 73mm height, top lid of 1:5mm thick M.S. sheet with itstop surface hacked for proper bonding, top lid shall be screwed into the cast iron/M.S. sheet box by means of 3.3mm dia. round headed screws, one lock at the corners.Clamp shall be made of 12mm dia M.S. bar bent to shape as per standard drawing,

Page 937: DAR_Vol_1

10.19 Providing and fixing M.S. round holding down with nuts and wahser plates completes.

Page 938: DAR_Vol_1

10.22 Welding by gas or electric plant including transportion of plant at site etc. complete.

Providing and fixing bright finished brass casement window fasterners or peg stays to win-

Page 939: DAR_Vol_1

10.24 Providing and fixing 14 mm bright finished brass spring catch to steel centre hung

Steel work welded in built up section/framed work including cutting, hoisting, fixingin position and applying a priming coat of approved steel primer using steel etc. as

10.25.1 In stringers, treads, landing etc. of stair cses including use of chequered plate wher-

Page 940: DAR_Vol_1

10.25 Steel work welded in built up section / framed work including cutting, hoisting, fixingin position and applying a priming coat of approved steel primer usin’g structuralsteel etc. as required. 10.25.2 In grating, frames, guard bar, ladder, railings, brackets,

Page 941: DAR_Vol_1

Providing and fixing hand rail of approved size by welding etc. to steel ladder rail-ing, balcony railing and staircase railing including applying a priming coat of ap-

railing, balcony railing and staircase railing including applying a priming coat of

Page 942: DAR_Vol_1

Providing and fixing hand rail of approved size by selding etc. to steel ladder rail-ing, balcony railing and staircase railing including applying a priming coat of ap-

Page 943: DAR_Vol_1

Brick on edge flooring with bricks of class designation 75 including cement slurry

Page 944: DAR_Vol_1

Brick on edge flooring with bricks of class designation 75 including cement slurry

Dry brick on edge flooring in required pattern with bricks of class designation 75

Page 945: DAR_Vol_1

Cement concrete flooring 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate)finished with a floating coat of neat cement including cement slurry, but excluding

52 mm thick cement concrete flooring with concrete hardener topping under layer

nominal size) by volume .hardening compound is mixed @ 2 litre per 50kg of cement

Page 946: DAR_Vol_1

62 mm thick cement concrete flooring with concrete hardener topping under layer

cement or as per manufactures specifications. This includes cost of cement slurry,

Page 947: DAR_Vol_1

Cement plaster skirting (upto 30 cm height) with cement mortar 1:3 (1 cement : 3

Cement concrete pavement with 1:2:4 (1 cement : 2 coarse sand : 4 grated stone

Page 948: DAR_Vol_1

Extra for making chequers of approved pattern on cement concrete floors, steps,

40 mm thick marble chips flooring rubbed and polished to granolithic finish, underlayer 34 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone

chocolate, grey, yellow or green marble chips of sizes from lmm to 4mm nominalsize laid in cement marble powder mix 3:1 (3 cement: 1 marble powder) by weight

Page 949: DAR_Vol_1

40 mm thick marble chips flooring rubbed and polished to granolithic finish, underlayer 34 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone

chocolate, grey, yellow or green marble chips of sizes from lmm to 4mm nominalsize laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight

Page 950: DAR_Vol_1

40 mm thick marble chips flooring rubbed and polished to granolithic finish, underlayer 34 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone

chocolate, grey, yellow or green marble chips of sizes from lmm to 4mm nominalsize laid in cement marble powder mix 3:1 (3 cement: 1 marble powder) by weight

40 mm thick marble chips flooring rubbed and polished to granolithic finish, underlayer 34 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone

chocolate, grey, yellow or green marble chips of sizes from lmm to 4mm nominalsize laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight

Page 951: DAR_Vol_1

40 mm thick marble chips flooring rubbed and polished to granolithic finish, underlayer 34 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone

chocolate, grey, yellow or green marble chips of sizes from lmm to 4mm nominalsize laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight

Page 952: DAR_Vol_1

40 mm thick marble chips flooring rubbed and polished to granolithic finish, underlayer 34 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone

chocolate, grey, yellow or green marble chips of sizes from 1 mm to 4mm nominalsize laid in cement marble powder mix 3:1 (3 cement: 1 marble powder) by weight

11.10 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, underlayer 3lmm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stoneaggregate 12.5mm nominal size) and top layer 9mm thick with white, black, chocolate,grey, yellow or green marble chips of sizes from 4mm to 7mm nominal size laid incement marble powder mix 3:1 (3 cement: 1 marble powder) by weight in proportionof 4:7 (4 cement marble powder : 7 marble chips) by volume including cement slurry

Page 953: DAR_Vol_1

11.10 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, underlayer 31mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stoneaggregate 12.5mm nominal size) and top layer 9mm thick with white, black, chocolate,grey, yellow or green marble chips of sizes from 4mm to 7mm nominal size laid incement marble powder mix 3:1 (3 cement: 1 marble powder) by weight in proportionof 4:7 (4 cement marble powder : 7 marble chips) by volume including cement slurry

Page 954: DAR_Vol_1

11.10 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, undermm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone

aggregate 12.5mm nominal size) and top layer 9mm thick with white, black, chocolate,grey, yellow or green marble chips of sizes from 4mm to 7mm nominal size laid incement marble powder mix 3:1 (3 cement: 1 marble powder) by weight in proportionof 4:7 (4 cement marble powder : 7 marble chips) by volume including cement slurry

11.10.3 Medium shade pigment with 50% white cement and 50% ordinary cement.

Amount

3,036

182.25(-)170.10

280.33(-)130.05

3,198.431.62

3,200.0524.61

3,224.66322.47322.45

11.10 10 40 mm thick marble chips flooring, rubbed and polished to granolithic finish,mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded

stone aggregate 12.5mm nominal size) and top layer 9mm thick with white, black,chocolate, grey, yellow or green marble chips of sizes from 4mm to 7mm nominalsize laid in cement marble powder mix 3:1 (3 cement: 1 marble powder) by weight inproportion of 4:7 (4 cement marble powder : 7 marble chips) by volume including

Amount

147

49

14.9

847.45

452.2590

Page 955: DAR_Vol_1

5.7

4.36

2.739.6

4.5412

28.92

11.10 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under layer 31mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone

chocolate, grey, yellow or green marble chips of sizes from 4mm to 7mm nominalsize laid in cement marble powder mix 3:1 (3 cement: 1 marble powder) by weight inproportion of 4:7 (4 cement marble powder : 7 marble chips) by volume including

.65

9.9

Page 956: DAR_Vol_1

11.10 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under layermm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate

12.5mm nominal size) and top layer 9mm thick with white, black, chocolate, grey, yellowor green marble chips of sizes from 4mm to 7mm nominal size laid in cement marblepowder mix 3:1 (3 cement: 1 marble powder) by weight in proportion of 4:7 (4 cementmarble powder : 7 marble chips) by volume including cement slurry etc. complete.

Page 957: DAR_Vol_1

white, black, chocolate, grey yellow or green marble chips of sizes from 7mm to

powder) by weight in proportion of 2:3 (2 cement marble powder mix : 3 marble

11.11 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under layer28 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate

Page 958: DAR_Vol_1

12.5mm nominal size) and top layer 12mm thick with white, black, chocolate, grey yellowor green marble chips of sizes from 7mm to 10mm nominal size laid in cement marblepowder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 2:3 (2 cementmarble powder mix : 3 marble chips) by volume including cement slurry etc. complete :

11.11 40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under layer28 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate12.5mm nominal size) and top layer 12mm thick with white, black, chocolate, grey yellowor green marble chips of sizes from 7mm to 10mm nominal size laid in cement marblepowder mix 3:1 (3 cement: 1 marble powder) by weight in proportion of 2:3 (2 cementmarble powder mix : 3 marble chips) by volume including cement slurry etc. complete :

11.11.3 Medium shade pigment with 50% white cement and 50% ordinary cement.

Page 959: DAR_Vol_1

40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under layer28 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate12.5mm nominal size) and top layer 12mm thick with white, black, chocolate, grey yellowor green marble chips of sizes from 7mm to 10mm nominal size laid in cement marblepowder mix 3:1 (3 cement: 1 marble powder) by weight in proportion of 2:3 (2 cementmarble powder mix : 3 marble chips) by volume including cement slurry etc. complete :

40 mm thick marble chips flooring, rubbed and polished to granolithic finish, underlayer 28 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone

chocolate, grey yellow or green marble chips of sizes from 7mm to 10mm nominalsize laid in cement marble powder mix 3:1 (3 cement : 1 marble powder) by weight

Page 960: DAR_Vol_1

40 mm thick marble chips flooring, rubbed and polished to granolithic finish, under layer28 mm thick cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate12.5mm nominal size) and top layer 12mm thick with white, black, chocolate, grey yellowor green marble chips of sizes from 7mm to 10mm nominal size laid in cement marblepowder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 2:3 (2 cementmarble powder mix : 3 marble chips) by volume including cement slurry etc. complete :

Page 961: DAR_Vol_1

marble chips of sizes from smallest to 4 mm nominal size laid in cement marblepowder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4

2.71

1.925.6

3.64

31.07

marble chips of sizes from smallest to 4 mm nominal size laid in cement marblepowder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4

Page 962: DAR_Vol_1

marble chips of sizes from smallest to 4 mm nominal size laid in cement marble

marble chips of sizes from smallest to 4 mm nominal size laid in cement marblepowder mix 3:1 (3 cement : 1 marble powder) by weight in proportion of 4:7 (4

11.12.1 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement: 3

Page 963: DAR_Vol_1

marble chips of sizes from smallest to 4 mm nominal size laid in cement marble

11.12.1 18 mm thick with under layer 12 mm thick in cement plaster 1:3 (1 cement: 3

Page 964: DAR_Vol_1

Extra for laying terrazo flooring on staircase treads not exceeding 30 cm in width

Crazy marble stone flooring including filling the gaps with light shade pigment with whitecement marble powder mixture (3 parts of white cement : 1 part of marble powder) byweight in proportion of 4:7 (4 cement marble powder mix : 7 white, black or white andblack marble chips of sizes from 1mm to 4mm nominal size by volume) and under layer25mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate

Page 965: DAR_Vol_1

laid in floors, and landings, jointed with neat cement slurry mixed with pigment

precast tiles on 20mm thick bed of cement mortar 1:4(1 cement :4 coarse sand):

Page 966: DAR_Vol_1

laid in floors, and landings, jointed with neat cement slurry mixed with pigment

precast tiles on 20mm thick bed of cement mortar 1:4(1 cement :4 coarse sand):

laid in floors, and landings, jointed with neat cement slurry mixed with pigment

precast tiles on 20mm thick bed of cement mortar 1:4(1 cement :4 coarse sand):

Page 967: DAR_Vol_1

Precast terrazo tiles 22mm thick with graded marble chips of size upto 12mm laidin floors, and landings,jointed with neat cement slurry mixed with pigment to matchthe shade of the tiles including rubbing and polishing complete with precast tiles

Page 968: DAR_Vol_1

11.18 Precast terrazo tiles 22 mm thick with graded marble chips of sizes upto 12 mm inskirting and risers of steps not exceeding 30 cm in height on 12 mm thick cementplaster 1:3 (1 cement : 3 coarse sand) jointed with neat cement slurry mixed withpigment to match the shade of the tiles, including rubbing and polishing complete

Page 969: DAR_Vol_1

Precast terrazo tiles 22 mm thick with graded marble chips of sizes upto 12 mm inskirting and risers of steps not exceeding 30 cm in height on 12 mm thick cementplaster 1:3 (1 cement : 3 coarse sand) jointed with neat cement slurry mixed withpigment to match the shade of the tiles, including rubbing and polishing complete

Precast terrazo tiles 22 mm thick with graded marble chips of sizes upto 12 mm inskirting and risers of steps not exceeding 30 cm in height on 12 mm thick cementplaster 1:3 (1 cement : 3 coarse sand) jointed with neat cement slurry mixed with pigmentto match the shade of the tiles, including rubbing and polishing complete with tiles of:

Page 970: DAR_Vol_1

Precast terrazo tiles 22 mm thick with graded marble chips of sizes upto 12 mm inskirting and risers of steps not exceeding 30 cm in height on 12 mm thick cementplaster 1:3 (1 cement : 3 coarse sand) jointed with neat cement slurry mixed with pigmentto match the shade of the tiles, including rubbing and polishing complete with tiles of:

Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mm in

Page 971: DAR_Vol_1

floors jointed with neat cement slurry mixed with pigment to match the shade ofthe tiles including rubbing and polishing complete on 20 mm thick bed of cement

Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mm infloors jointed with neat cement slurry mixed with pigment to match the shade ofthe tiles including rubbing and polishing complete on 20 mm thick bed of cement

Page 972: DAR_Vol_1

Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mm infloors jointed with neat cement slurry mixed with pigment to match the shade ofthe tiles including rubbing and polishing complete on 20 mm tck bed of cement

Chequered terrazo tiles 22 mm thick with graded marble chips of size up to 6 mmin floors jointed with neat cement slurry mixed with pigment to match the shade ofthe tiles including rubbing and polishing complete on 20 mm thick bed of cement

Page 973: DAR_Vol_1

Chequerred precast cement concrete tiles 22 mm thick in footpath & courtyardjointed with neat cement slurry mixed with pigment to match the shade of tilesincluding rubbing and cleaning etc. complete on 20 mm thick bed of cement mortar

Page 974: DAR_Vol_1

Chequerred precast cement concrete tiles 22 mm thick in footpath & courtyardjointed with neat cement slurry mixed with pigment to match the shade of tilesincluding rubbing and cleaning etc. complete on 20 mm thick bed of cement mortar

Chequerred precast cement concrete tiles 22 mm thick in footpath & courtyardjointed with neat cement slurry mixed with pigment to match the shade of tilesincluding rubbing and cleaning etc. complete on 20 mm thick bed of cement mortar

Page 975: DAR_Vol_1

11.20 : Chequerred precast cement concrete tiles 22 mm thick in footpath & courtyardjointed with neat cement slurry mixed with pigment to match the shade of tilesincluding rubbing and cleaning etc. complete on 20 mm thick bed of cement mortar

Page 976: DAR_Vol_1

make and colour using acid and/or alkali resisting mortar bedding and joints filled

11.21.1 : In flooring on a bed of 10 mm thick mortar 1:4(1 acid proof cement: 4 coarse sand).

Providing and fixing 10mm thick acid and/or alkali resistant tiles of approvedmake and colour using acid and/or alkali resisting mortar bedding and jointsfilled with acid and/or alkali resisting cement as per IS : 4457 complete as per the

In dado/skirting on 12 mm thick mortar 1:4 (1 acid proof cement: 4 coarse sand).

Page 977: DAR_Vol_1

Tile work in skirting, risers of steps and dado (upto 2 m height) over 12 mmthick bed of cement mortar 1:3 (1 cement :3 coarse sand) and jointed with greycement slurry @ 3.3 kg/sqm including pointing in white cement mixed with

Page 978: DAR_Vol_1

11.23 : Marble stone flooring with 18mm thick marble stone (sample of marble shall beapproved by Engineer-in-charge) over 20 mm (average) thick base of cement mortar1:4 (1 cement : 4 coarse sand) laid and jointed with grey cement slurry including

Marble stone flooring with 18mm thick marble stone (sample of marble shall beapproved by Engineer-in-charge) over 20 mm (average) thick base of cement mortar1:4 (1 cement : 4 coarse sand ) laid and jointed with grey cement slurry including

Page 979: DAR_Vol_1

Marble stone flooring with 18mm thick marble stone (sample of marble shall beapproved by Engineer-in-charge) over 20 mm (average) thick base of cement mortar1:4 (1 cement : 4 coarse sand) laid and jointed with grey cement slurry including

Page 980: DAR_Vol_1

11.23 : Marble stone flooring with 18mm thick marble stone (sample of marble shall beapproved by Engineer-in-charge) over 20 mm (average) thick base of cement mortar1:4 (1 cement : 4 coarse sand) laid and jointed with grey cement slurry including

11.23 : Marble stone flooring with 18mm thick marble stone (sample of marble shall beapproved by Engineer-in-charge) over 20 mm (average) thick base of cement mortar1:4 (1 cement : 4 coarse sand) laid and jointed with grey cement slurry including

Page 981: DAR_Vol_1

11.23 : Marble stone flooring with 18mm thick marble stone (sample of marble shall beapproved by Engineer-in-charge) over 20 mm (average) thick base of cement mortar1:4 (1 cement : 4 coarse sand) laid and jointed with grey cement slurry including

Page 982: DAR_Vol_1

11.25 :Extra for marble stone flooring in treads of steps and risers using single length

11.26 : Kota stone slab flooring over 20 mm (average) thick base laid over and jointedwith grey cement slurry mixed with pigment to match the shade of the slab including

Page 983: DAR_Vol_1

11.27 :Kota stone slabs 25 mm thick in risers of steps, skirting, dado and pillars laid on 12mm (average) thick cement mortar 1:3 (1 cement 3 coarse sand) and jointed withgrey cement slurry mixed with pigment to match the shade of the slabs, including

Page 984: DAR_Vol_1

11.28 : 40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cement

11.28 : 40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cement

Page 985: DAR_Vol_1

11.29 : 40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cementmortar 1:5 (1 cement : 5 coarse sand) including pointing with cement mortar 1:2 (1cement: 2 stone dust) with an admixture of pigment to match the shade of stone.

11.29 : 40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cementmortar 1:5(1 cement : 5 coarse sand) including pointing with cement mortar 1:2 (1

Page 986: DAR_Vol_1

cement: 2 stone dust) with an admixture of pigment to match the shade of stone.

11.30 : 40 mm thick rubbed stone flooring over 20 mm (average) thick base of cement

cement mortar 1:2 (1 cement : 2 stone dust) admixed with pigment to match the

Page 987: DAR_Vol_1

11.30 : 40 mm thick rubbed stone flooring over 20 mm (average) thick base of cement

cement mortar 1:2 (1 cement : 2 stone dust) admixed with pigment to match the

Page 988: DAR_Vol_1

11.32 : Extra for Kota stone/ sand stone in treads of steps and risers using single length

11.33 : 25mm wooden planking, tongued and grooved in flooring including fixing with

Page 989: DAR_Vol_1

11.34 : 38mm thick wood block flooring of first class teak wood laid over 25mm thicklevelling layer of cement concrete 1:2:4 (1 cement: 2 coarse sand : 4 graded stoneaggregate 10mm nominal size) to be paid separately coated with a thin layer of hotbitumen (blown type) @ 2.45 kg per sqm. including fixing blocks in position afterdipping in hot bitumen (blown type) upto half depth, planed, levelled smooth and

Page 990: DAR_Vol_1

Providing and fixing M.S. angle 50x50x5 mm to act as nosing with lugs of M.S. flat10x5 mm 10cm long forked at end 60cm apart (minimum three lugs to be provided )

Page 991: DAR_Vol_1

Providing and fixing 1st quality ceramic glazed wall tiles conforming to IS : 15622(thickness to be specified by the manufacture of approved make in all colours, shadesexcept burgundy, bottle green, black of any size as approved by Engineer-in-Chargein skirting, risers of steps and dados over 12 mm thick bed of cement Mortar 1:3 (1cement: 3 coarse sand) and jointing with grey cement slurry @ 3.3kg per sqm including

11.37 :Providing and laying Ceramic glazed floor tiles 300x300 mm (thickness to be specifiedby the manufacturer) of 1st quality conforming to IS : 15622 of approved make incolours such as White, Ivory, Grey, Fume Red, Brown laid on 20 mm thick CementMortar 1:4 (1 Cement : 4 Coarse sand) including pointing the joints with white cement

Page 992: DAR_Vol_1

11.38 : Providing and laying Ceramic glazed floor tiles 300x300 mm(thickness to bespecified by the manufacturer) of 1st quality conforming to IS : 15622 of approvedmake in all colours , shades, except White, Ivory, Grey, Fume Red Brown laid on20mm thick bed of Cement Mortar 1:4(1 Cement: 4 Coarse sand) including pointing

11.39 : Providing and laying rectified Glazed Ceramic floor tiles 300x300 mm or more(thickness to be specified by the manufacturer) of 1st quality conforming to IS :15622 of approved make in colours White, Ivory, Grey, Fume Red,, Brown, laid on20mm thick cement mortar 1:4 (1 Cement : 4 Coarse sand) including grouting the

Page 993: DAR_Vol_1

(thickness to be specified by the manufacturer) of 1st quality conforming to IS :15622 of approved make in all colours, shades, except White, Ivory, Grey, Fume RedBrown, laid on 20 mm thick Cement Mortar 1:4 (1 Cement : 4 Coarse sand) including

11.41 : Providing and laying vitrified floor tiles in different sizes (thickness to be specifiedby the manufacturer) with water absorption’s less than 0.08% and conforming toIS : 15622 of approved make in all colours and shades, laid on 20mm thick cementmortar 1:4 (1 cement: 4 coarse sand) including grouting the joints with white cement

Page 994: DAR_Vol_1

Providing and laying vitrified floor tiles in different sizes (thickness to be specifiedby the manufacturer) with water absorption’s less than 0.08% and conforming toIS : 15622 of approved make in all colours and shades, laid on 20mm thick cementmortar 1:4(1 cement: 4 coarse sand) including grouting the joints with white cement

Page 995: DAR_Vol_1

11.41 : Providing and laying vitrified floor tiles in different sizes (thickness to be specifiedby the manufacturer) with water absorption’s less than 0.08% and conforming toIS : 15622 of approved make in all colours and shades, laid on 20mm thick cementmortar 1:4 (1 cement: 4 coarse sand) including grouting the joints with white cement

Providing and laying vitrified floor tiles in different sizes (thickness to be specifiedby the manufacturer) with water absorption’s less than 0.08% and conforming toIS : 15622 of approved make in all colours and shades, laid on 20mm thick cementmortar 1:4 (1 cement: 4 coarse sand) including grouting the joints with white cement

Page 996: DAR_Vol_1

11.42: Deduet for not using 20mm thick cement mortar 1:4 (1 cement :4 coarse sand )

11.43: Fixing glazed/ Ceramic/ Vitrified floor tiles with cement based high polymer modifiedquick-set tile adhesive (Water based) conforming to IS: 15477 , using 5kg. adhesive

Page 997: DAR_Vol_1

with polymer coated J or L hooks, bolts and nuts 8 mm diameter with bitumen andG.I. limpet washers or with G.I. limpet washers filled with white lead and including

Page 998: DAR_Vol_1

a coat of approved steel primer and two coats of approved paint on overlapping ofsheets complete upto any pitch in horizontal/ vertical or curved surfaces) excluding

Page 999: DAR_Vol_1

with polymer coated J or L hooks, bolts and nuts 8 mm diameter with bitumen andG.I. limpet washers or with G.I. limpet washers filled with white lead and includinga coat of approved steel primer and two coats of approved paint on overlapping ofsheets complete upto any pitch in horizontal/ vertical or curved surfaces) excluding

Page 1000: DAR_Vol_1

with polymer coated J or L hooks, bolts and nuts 8 mm diameter with bitumen andG.I. limpet washers or with G.I. limpet washers filled with white lead and includinga coat of approved steel primer and two coats of approved paint on overlapping ofsheets complete upto any pitch in horizontal/ vertical or curved surfaces) excluding

Page 1001: DAR_Vol_1

12.4 Providing ridges or hips of width 60 cm over all width plain G.S. sheet fixed withpolymer coated J. or L hooks, bolts and nuts 8 mm dia. G.I. limpet and bitumen

Page 1002: DAR_Vol_1

12.4 Providing ridges or hips of width 60 cm over all width plain G.S. sheet fixed withpolymer coated J. or L hooks, bolts and nuts 8 mm dia. G.I. limpet and bitumen

Page 1003: DAR_Vol_1

Providing valleys of 90cm wide overall in plain G.S. sheet fixed with polymer coatedJ, or L hooks, bolts and nuts 8mm dia.. G.I. limpet and bitumen washers complete :

12.6 Providing flashing of 40 cm over all width in plain, G.S. sheet fixed with polymer

bent to shape and fixed in wall with cement mortar 1:3 (1 cement: 3 coarse sand).

Page 1004: DAR_Vol_1

Providing and fixing 15 cm wide 45 cm over all semi circular plain G.S. sheet gutter

Page 1005: DAR_Vol_1

Providing and fixing 15 cm wide 45 cm over all semi circular plain G.S. sheet gutter

Page 1006: DAR_Vol_1

Providing non-asbestos high impact Polypropylene reinforced cement 6 mm thickcorrugated sheets (As per IS: 14871) roofing upto any pitch and fixing with polymer coatedJ, or L hooks, bolts and nuts 8mm dia. G.I. plain and bitumen washers or with self drillingfastener and EPDM washers etc. complete excluding the cost of purlins, rafters andtrusses corrugated sheets and including cutting to size and shape wherever required

Page 1007: DAR_Vol_1

corrugated, semi-corrugated 6 mm thick sheet roofing for making openings of area

corrugated/semi-corrugated 6 mm thick sheet roofing for making openings of area

Page 1008: DAR_Vol_1

polypropylene reinforced roofing with suitable fixing accessories or self drilling

12.12 : Providing and fixing ridges and hips in non-asbestos fibre cement high impactpolypropylene reinforced roofing with suitable fixing accessories or self drilling

Page 1009: DAR_Vol_1

12.12 : Providing and fixing ridges and hips in non-asbestos fibre cement high impactpolypropylene reinforced roofing with suitable fixing accessories or self drilling

polypropylene reinforced roofing with suitable fixing accessories or self drilling

Page 1010: DAR_Vol_1

12.13 : Providing and fixing non-asbestos fibre cement high impact polypropylene

bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or

Page 1011: DAR_Vol_1

bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or

reinforced roofing accessories with polymer coated J or L hooks, bolts and nutsand or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling

Page 1012: DAR_Vol_1

reinforced roofing accessories with polymer coated J or L hooks, bolts and nutsand or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling

reinforced roofing accessories with polymer coated J or L hooks, bolts and nutsand or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling

Page 1013: DAR_Vol_1

reinforced roofing accessories with polymer coated J or L hooks, bolts and nutsand or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling

reinforced roofing accessories with polymer coated J or L hooks, bolts and nutsand or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling

Page 1014: DAR_Vol_1

reinforced roofing accessories with polymer coated J or L hooks, bolts and nutsand or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling

Page 1015: DAR_Vol_1

Providing flat iron brackets 50x3mm size with necessary bolts, nuts and washers

Painting top of roofs with bitumen of approved quality at 17kg per 10 sqmimpregnated with a coat of coarse sand at 60 cudm per 10 sqm including cleaningthe slab surface with brushes and finally with a piece of cloth lightly soaked in

Page 1016: DAR_Vol_1

consolidated and plastered with 25 mm thick mud mortar mixed with bhusa at 35

covered with flat tile bricks of class designation 100 grouted with cement mortar1:3 (1 cement: 3 fine sand) mixed with 2% of integral water proofing compound by

Page 1017: DAR_Vol_1

12.17 10cm thick (average) mud phaska of damped brick earth on roofs laid to slopeconsolidated and plastered with 25mm thick mud mortar with bhusha at 35kg percum of earth and gobri leaping with mix 1:1 (1 clay : 1 cowdung) and covered withmachine moulded tile bricks of class designation 125 conforming to IS : 2690 (Part I)-1992 grouted with cement mortar 1:3(1 cement: 3 fine sand ) mixed with 2% of integral

Page 1018: DAR_Vol_1

Providing and laying brick tiles of class designation 100 over mumty roofs groutedwith cement mortar 1:3 (1 cement: 3 fine sand) mixed with 2% of integral waterproofing compound by weight of cement, over a 12 mm layer of cement mortar 1:3

Page 1019: DAR_Vol_1

Providing and laying pressed clay tiles (as per approved pattern 20 mm nominalthickness and of approved size) on roofs jointed with cement mortar 1:4 (1 cement : 4coarse sand) mixed with 2% integral water proofing compound laid over a bed of 20mm thick cement mortar 1:4(1 cement: 4 coarse sand) and finished neat complete.

Providing gola 75x75 mm in cement concrete 1:2:4 (1 cement: 2 coarse sand : 4stone aggregate 10mm and down gauge) including finishing with cement mortar

Page 1020: DAR_Vol_1

Making khurras 45x45 cm with average minimum thickness of 5 cm cement concrete1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate of 20 mm nominal size)over P.V.C. sheet 1mx 1mx 400 micron, finished with 12mm cement plaster 1:3 (1cement : 3 coarse sand) and a coat of neat cement rounding the edge and making

Page 1021: DAR_Vol_1

12.23 Providing sand stone slab for roofing and laying them in cement mortar 1 : 4 (1

Page 1022: DAR_Vol_1

Providing and fixing insulating board ceiling of approved quality with necessary

Providing and fixing insulating board ceiling of approved quality with necessary

Page 1023: DAR_Vol_1

Providing and fixing insulating board ceiling of approved quality with necessary

Providing and fixing flat pressed 3 layer medium density particle board or gradedparticle board (Grade I) IS: 3087 marked in ceiling with necessary nails etc. complete

Page 1024: DAR_Vol_1

12.26 Providing and fixing plain multipurpose cement board (high pressure steam cured ) asper IS 14862: 2000 with suitable fibre cement screw in ceiling etc complete, (frame

Page 1025: DAR_Vol_1

12.29 Providing and fixing false ceiling with 12 mm thick plain/ semi perforated or withdesign ceiling tiles of BWP type phenol formaldehyde synthetic resin bonded pressedparticle board conforming to IS:3087 finished with a coat of aluminium primer onboth sides & edges and two coats of synthetic enamel paint of approved quality onexposed face fixed to a grid made out of anodised aluminium (with 15 micron anodiccoating) T-sections 35 xl5xl.5 mm size main runners and cross runners 23.5x19x1.5mm fixed to main runners placed 600 mm centre to centre both ways so as to forma grid of 600 mm square. The frame work shall be suspended from ceiling by leveladjusting hangers of 6 mm dia M.S rod fixed to roof slab by means of ceiling cleats.The suspenders shall be placed 600x 1200 mm centre to centre including fixing tothe frame with C.P brace screws and applying a priming coat of zinc chromate yellow

12.30 Extra for providing 3 mm thick translucent white acrylic plastic sheets of approvedquality in false ceiling instead of 12 mm thick plain/or with design particle board

Page 1026: DAR_Vol_1

12.31 Providing 10 mm thick plaster of Paris (gypsum anhydrous) ceiling upto a height of5 m above floor level over first class kail wood strips 25x6 mm with 10 mm gap inbetween and reinforced with rabbit wire mesh fixed to wooden frame (frame work

Page 1027: DAR_Vol_1

Providing 10 mm thick plaster of Paris (gypsum anhydrous) ceiling upto a heightof 5 m above floor level over first class kail wood strips 25x6 mm with 10 mm gap inbetween and reinforced with rabbit wire mesh fixed to wooden frame (frame work

Page 1028: DAR_Vol_1

12.32 Extra for any sunk or raised mouldings in the plaster of Paris (Gypsum anhydrous)

12.33 Extra for providing plaster of Paris (Gypsum anhydrous) ceiling above 5 metres

12.34 Providing and fixing thermal insulation of ceiling (under deck insulation) with ResinBonded Fibre glass wool conforming to IS : 8183 density 24kg/m3, 50mm thick,

Page 1029: DAR_Vol_1

wrapped in 200 G Virgin Polythene bags fixed to ceiling with metallic cleats (50x50x3mm) @ 60 cm and wire mesh of 12.5mm x 24g wire and mesh, for top most ceiling of

Page 1030: DAR_Vol_1

Thermal Insulation of roofing with Expanded polystyrene fixed with suitable adhesive

Providing and fixing 100 mm diameter and 60 cm long rain water spout in cement

Page 1031: DAR_Vol_1

12.38 Providing and fixing M.S. holder bat clamps of approved design to C.I. or S.C.I, rainwater pipes embedded in and including cement concrete blocks 10x10x 10cm of1:2:4 mix (1 cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)

Page 1032: DAR_Vol_1

rain water pipes embedded in and including cement concrete blocks 10x10x 10cmof 1:2:4 mix (1 cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal

Page 1033: DAR_Vol_1

Providing, fixing and embedding sand cast iron accessories for rain water pipesin the masonry surrounded with” 12mm thick cement mortar of the same mix, as

Page 1034: DAR_Vol_1

conforming to IS : 13592 Type A including jointing with seal ring conforming to IS :

12.41 Providing and fixing on wall face unplasticised Rigid PVC rain water pipes conformingto IS : 13592 Type A including jointing with seal ring conforming to IS : 5382 leaving

Page 1035: DAR_Vol_1

Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories

Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories

Page 1036: DAR_Vol_1

Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories

Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories

Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories

Page 1037: DAR_Vol_1

Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories

Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories

Page 1038: DAR_Vol_1

Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories

Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories

Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories

Page 1039: DAR_Vol_1

Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories

Providing and fixing on wall face unplasticised - PVC moulded fittings/ accessories

Page 1040: DAR_Vol_1

unplasticised - PVC rain water pipes by means of 50x50x50mm hard wood plugs,

fixing in cement mortar 1:4(1 cement: 4 coarse sand) and making good the wall

unplasticised - PVC rain water pipes by means of 50x50x50mm hard wood plugs,

fixing in cement mortar 1:4(1 cement: 4 coarse sand) and making good the wall

Page 1041: DAR_Vol_1

12.44 Providing and fixing to the inlet mouth of rain water pipe cast iron grating 15 cm

consisting of angle cleats of size 25mm wide x 1.6mm thick with flanges of 22mmand 37mm at 1200mm centre to centre one flange fixed to the ceiling with dash

with nut and bolts to G.I. channels 45x15x0.9mm running at the rate of 1200mmcentre to centre to which the ceiling section 0.5mm thick bottom wedge of 80mmwith tapered flanges of 26mm each having clips of 10.5mm at 450mm centre tocentre shall be fixed in a direction perpendicular to G.I. channel with connectingclips made out of 2.64mm diax230mm long G.I. wire at every junction includingfixing the gypsum board with ceiling section and perimeter channels 0.5mm thick

fixed to wall/partition with the help of rawl plugs at 450mm centre to centre with25mm long drive-all screws @ 230mm interval including jointing and fixing to a

Page 1042: DAR_Vol_1

flush finish of tapered and square edges of the board with recommended filler,

suitably fixed all complete as per drawing and specification and direction of the

12.46 Providing and fixing to the inlet mouth of rain water pipe PTMT (an EngineeringThermoplastic) grating sqare (Slit) 150 mm sqare with a height of 8 mm and weighing

Page 1043: DAR_Vol_1

12.47 Providing & fixing UV stabilised fiberglass reinforced plastic sheet roofing upto anypitch including fixing with polymer coated ‘J’ or ‘L’ hooks, bolts & nuts 8mm dia. G.Iplain/bitumen washers complete but excluding the cost of purlins, rafters, trussesetc. The sheets shall be manufactured out of 2400 TEX panel rovigs incorporatingminimum 0.3% Ultra-voilet stabiliser in resin system under approximately 2400 psiand hot cured. They shall be of uniform pigmentation and thickness without airpockets and shall confoim to IS 10192 and IS 12866.The sheets shall be opaque or

12.47.1 2mm thick corrugated (2.5\" or 4.2\" or 6\") or step-down (2\"or 3\"or 6\") as specified.

Page 1044: DAR_Vol_1

12.47 Providing & fixing UV stabilised fiberglass reinforced plastic sheet roofing upto anypitch including fixing with polymer coated ‘J’ or ‘L’ hooks, bolts & nuts 8mm dia. G.Iplain/bitumen washers complete but excluding the cost of purlins, rafters, trussesetc. The sheets shall be manufactured out of 2400 TEX panel rovigs incorporatingminimum 0.3% Ultra-voilet stabiliser in resin system under approximately 2400 psiand hot cured. They shall be of uniform pigmentation and thickness without airpockets and shall conform to IS 10192 and IS 12866.The sheets shall be opaque or

Page 1045: DAR_Vol_1

12.48 Providing & fixing on roof pressed clay tile (Mangalor tile of 20 mm nominal thicknessand of approved size and as per approved pattern sfeel frame work complete (steel

12.49 Providing & laying on roof pressed clay tile ridge (Mangalore tile) of 20mm thicknessand of approved pattern on steel frame work complete (sfeel frame work to be paid

12.50 Providing and fixing precoatedgalvanized iron profile sheets (size, shape and pitchof corrugation as 5% total coated thickness (TCT), Zinc coating 120gsm as per IS:277 in approved by Engineer-in-charge) 0.05 mm. 240 mpa mm steel grade, 5-7 micronsepoxy primer on both side of the sheet and polyester top coat 15-18 microns. Sheetshould have protective guard film of 25 microns minimum to avoid scratches whiletransportation and should be supplied in single length upto 12 metre or as desiredby Engineer-in-charge. The sheet shall be fixed using self drilling /self tapping screwsof size (5.5x 55mm) with EPDM seal or with polymer coated J or L hooks, bolts andnuts 8mm diameter with bitumen and G.I. limpet washers or with G.I. limpet washersfilled with white lead complete upto any pitch in horizontal/ vertical or curved surfacesexcluding the cost of purlins, rafters and trusses and including cutting to size and

Page 1046: DAR_Vol_1

12.51 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50mm + 5% total coated thickness (TCT), Zinc coating 120gsm as per IS: 277 in 240mpasteel grade, 5-7 microns epoxy primer on both side of the sheet and polyester topcoat 15-18 microns using self drilling/ self tapping screws or with polymer coated Jor L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen

Page 1047: DAR_Vol_1

12.51 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50 mm +5% total coated thickness (TCT), Zinc coating 120gsm as per IS: 277 in 240mpa steelgrade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18microns using self drilling/ self tapping screws or with polymer coated J or L hooks,bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers complete :

12.51 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50mm + 5% total coated thickness (TCT), Zinc coating 120gsm as per IS: 277 in 240mpasteel grade, 5-7 microns epoxy primer on both side of the sheet and polyester topcoat 15-18 microns using self drilling/ self tapping screws or with polymer coated Jor L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen

Page 1048: DAR_Vol_1

12.51 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50 mm+ 5% total coated thickness (TCT), Zinc coating 120gsm as per IS: 277 in 240mpasteel grade, 5-7 microns epoxy primer on both side of the sheet and polyester topcoat 15-18 microns using self drilling/ self tapping screws or with polymer coated Jor L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen

Page 1049: DAR_Vol_1

12.51 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50 mm 5%total coated thickness (TCT), Zinc coating 120gsm as per IS: 277 in 240mpa steel grade,5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 micronsusing self drilling/ self tapping screws or with polymer coated J or L hooks, bolts andnuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers complete :

12.51 Providing and fixing precoated galvanised steel sheet roofing accessories 0.50 mm5% total coated thickness (TCT), Zinc coating 120gsm as per IS: 277 in 240mpa steelgrade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-

hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers

Page 1050: DAR_Vol_1

12.52 Providing and fixing tiled False Ceiling of approved materials of size 595x595 mm intrue horizontal level suspended on inter locking metal grid of hot dipped galvanisedsteel sections ( galvanized @ 170 gsm/sqm.) consisting of main “T” runner withsuitably spaced joints to get required length and of size 24x38mm made from 0.30mmthick (minimum) sheet spaced at 1200mm center to center and cross “T” of size24x25mm made of 0.30mm thick (minimum) sheet, 1200mm long spaced betweenmain “T” at 600mm center to center to form a grid of 1200x600 mm and secondarycross “T” of length 600mm and size 24x25mm made of 0.30 mm thick (minimum)

600x600mm and wall angle of size 21x21x0.30 mm and laying false ceiling tiles ofapproved texture in the grid including, wherever, required, cutting/making, openingfor services like diffusers, grills, light fittings, fixtures, smoke detectors etc. Main “T”runners to be suspended from ceiling using GI slotted cleats fixed to ceiling with 6mm dia and 50mm long dash fasteners, 4mm GI adjustable rods with galvanisedlevel clips spaced at 1200mm center to center along main T, bottom exposed widthof 24mm of all T-sections shall be pre-painted with polyester paint, all complete at allheights as per specifications drawings and as directed by Engineer-in-Charge. (The