DART Jetpack
description
Transcript of DART Jetpack
![Page 1: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/1.jpg)
DART JETPACKDamien TanAndreas TohRoy ChiaTavence Heng
![Page 2: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/2.jpg)
INTRODUCTION The DART Jetpack project was started by 4
engineers in 2010. They wanted to merge business with engineering
in their venture by trying to market their jetpack using skills learnt from Project Management.
![Page 3: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/3.jpg)
PROJECT OBJECTIVES Improve convenience in human lives Military usage
![Page 4: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/4.jpg)
SCOPE OF PROJECT Estimated duration
-Research (3mnths) -Brainstorm (1Month) -Planning/blueprint stage (2months) -Miniature Model (1month) -Trouble shooting (1month) -Prototype stage (2years)
![Page 5: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/5.jpg)
SCOPE OF PROJECT Estimated cost
-Planning stages $50 -Prototype stage $1000
![Page 6: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/6.jpg)
RESPONSIBILITY MATRIX Responsibility matrix
Project leader DamienDesigner AndreasAccountant RoyScheduler Tavence
![Page 7: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/7.jpg)
CURRENT ISSUES Choose which way to start the jetpack
- Fan- Chemical Reactions- Hydro
Logistical problem Budget constraint Technological problems/inability Safety issue Jetpack stabiliser problems Human testing
![Page 8: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/8.jpg)
MANPOWER REQUIREMENTS Overall In-charge Researcher Planner Operational In-charge Marketer Sales person Technician Logistics In-charge Production In-charge Safety In-charge
![Page 9: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/9.jpg)
RESEARCH
![Page 10: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/10.jpg)
WORK BREAKDOWN STRUCTURE
![Page 11: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/11.jpg)
Mindmap of Dart Jetpack
![Page 12: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/12.jpg)
DART’S WORK BREAKDOWN STRUCTURE
![Page 13: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/13.jpg)
COST ANALYSIS Resources, $1,240,305.00 Human Resource, Manpower, $
165,000.00 Marketing , $ 50,600.00 A.O.M, insurance, $ 110,000.00 Total Budget $ 1,565,905.00
![Page 14: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/14.jpg)
ASSUMPTIONS Number of workers 100 Price per jetpack $5,000 Life time company insurance Hiring of Public Relations Staff in media
coverage Jetpacks sold per month 500 Amount of jetpacks made per month 500 Material cost per jetpack $2,000 The budget cost is per monthly basis sell to
retailer to sell to public 10% contingency Total Income $ 2,500,000.00 ROI 60%
![Page 15: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/15.jpg)
PROJECT SCHEDULING Scheduling the Project Time
Microsoft Office Project1. Listing the tasks2. Placing them according to tasks and sub tasks3. Placing them according to prerequisites4. Inserting the estimated Time for the tasks5. Generate the Gantt chart
![Page 16: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/16.jpg)
AON
Activity-On-Node (AON) Easier to see the Time allocation Easier to see the Predecessors.
![Page 17: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/17.jpg)
AON1. Earliest Start Time
(EST) : the early start of a project
2. Duration : how long will this project completes
3. Earliest Finish Time (EFT): EST + duration
4. Latest Start Time (LST) : the latest time a project can start
5. Latest Finish Time (LFT) = LST + duration
6. Total Float = LFT – EST – duration
Create Prototype
2 1 3
6 4 7
![Page 18: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/18.jpg)
OUR AON
-It took us 153 days to for the production of jetpacks-Our assumption is 180days-Creation of prototype is the only predecessor for cost analysis and test of prototype
0 5 5 Rental of Factory Assumption 180 days
5 14 19
5 14 19 Install utilities19 30 49
19 30 49 Renovation
49 7 56
49 7 56 Install Machinery
565 61
56 5 61Recuriting of worker
6130 91
61 30 91Research
91 10 101
91 10 101Design
101 8 109
101 8 109Create Prototype
1097 116
109 7 116 109 7 116Test Prototype Cost analysis
116 6 122 116 6 122
116 9 122Purchase Raw Material
12221 143
122 21 143Mass Production
1435 148
143 5 148Quality Check
148 5 153
148 5 153Delivery
153 27 180
![Page 19: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/19.jpg)
RISK ASSESSMENTs/n Risk Description Probability
(1=low, 5=high)Impact (1=low,
5=high) Ranking1 Unable to locate factory site 1 5 72 Unable to find contractors 2 5 63 Delay in renovations 3 2 134 Faulty machinery during installation 4 3 35 Unable to find skilled workers 2 3 146 Office worker demand more pay 1 2 227 security companies charges too high 2 1 238 Unable to find proper accomodations for production crew 2 1 249 Unable to hire qualified quality check crew 3 3 8
10 R and D crew demand too high a pay 3 3 911 Lack of technical knowledge 2 4 1012 Inappropiate design 3 2 1513 Not enough raw materials for prototype 2 3 1614 Prototype malfunction 4 3 515 Delay in shipments of raw materials 2 3 1716 Unable to find supplier for raw material 2 2 1917 Not enough raw materials for mass production 1 2 2518 Lack of appropiate supervision while mass production stage 5 1 1119 Machinery malfunction during mass production 5 4 120 Production halted due to safety issues 4 4 421 Unable to meet quality check expectations 3 5 322 Over budget 4 2 1223 Delay in delivery 3 2 1824 Unable to find repair crew 1 3 2025 Insufficient funds to pay for warranty 1 3 21
![Page 20: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/20.jpg)
TOP 5 RISKS-Machinery malfunction during mass production-Faulty machinery during installation-Unable to meet quality check expectations-Production halted due to safety issues-Prototype malfunction
Rank Top 5 risks Probability (1=low, 5=high)
Impact (1=low, 5=high)
1 Machinery malfunction during mass production 5 42 Production halted due to safety issues 4 43 Faulty machinery during installation 4 34 Unable to meet quality check expectations 3 55 Prototype malfunction 4 3
Rank Risks How probability can be reduced How impact can be reduced1 Machinery malfunction during mass production Perform frequent maintainence and checks Multiple production lines2 Production halted due to safety issues Implement stringent rules for workers to abide Stock up on products3 Faulty machinery during installation Getiing a reliable supplier Request for earlier delivery time4 Unable to meet quality check expectations Enforce quality standards for quality standard Increase the quality standards for the quality checks5 Prototype malfunction Thorough analysis of failures Have a backup team doing a prototype
![Page 21: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/21.jpg)
CREATION OF PROTOTYPE Video 1-fail launch Video 2-disintegrated rocket
![Page 22: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/22.jpg)
CONCLUSION Gained valuable experience Know how to manage a project Hope to make this a reality
![Page 23: DART Jetpack](https://reader033.fdocuments.us/reader033/viewer/2022061501/56815d32550346895dcb2b80/html5/thumbnails/23.jpg)
THE END
THANK YOU