Dare County Nourishment Project Town of Kill Devil Hills · Dare County Nourishment Project Town of...
Transcript of Dare County Nourishment Project Town of Kill Devil Hills · Dare County Nourishment Project Town of...
A World of Solutions
Dare County Nourishment ProjectTown of Kill Devil Hills
Julien Devisse, P.E. and Ken WillsonCB&I / Coastal Planning & Engineering of North Carolina, Inc.
February 15, 2017
1A World of Solutions
Background
Beach Fill Design/Construction Plans
South Southern Shores Extension Project
Borrow Area Design/Construction Plans
Construction Photos
Bid Items and Schedule
Monitoring/Renourishment
Questions
Outline
A World of Solutions 2
Background
~1.6 Miles1.4 MCY
~3.6 Miles1.8 MCY
~2.6 Miles0.9 MCY
Approx. 8.3 miles and 4.1 MCY
Southern Shores Project Limits
1,500 feet80,000 CY
3
Storm Damage Reduction ProjectStorm Damage Reduction Project
Pre-Project ConditionsPre-Project Conditions
4
Constructed Beach Fill
Storm Damage Reduction ProjectStorm Damage Reduction Project
Initial ConstructionInitial Construction
5
Post-ConstructionAdjustment in 6-18 months
Storm Damage Reduction ProjectStorm Damage Reduction Project
Equilibration of Beach FillEquilibration of Beach Fill
6
Advance Fill
Design Beach
Storm Damage Reduction ProjectStorm Damage Reduction Project
Nourishment IntervalNourishment Interval
7
Loss of Advance Fill During Project Interval
Design Beach
Storm Damage Reduction ProjectStorm Damage Reduction Project
Nourishment IntervalNourishment Interval
8
Maintenance (Renourishment)
Storm Damage Reduction ProjectStorm Damage Reduction Project
Maintenance = Beach RenourishmentMaintenance = Beach Renourishment
A World of Solutions 9
Profile Equilibration
Construction Template
Pre-ConstructionBeach Profile
A World of Solutions 10
Profile Equilibration
Constructed Fill
A World of Solutions 11
Profile Equilibration
Equilibrated Fill
Profile Equilibration
Profile Equilibration between January 2015 and July 2015
A World of Solutions 12
Wave Height Reduction
Profile Equilibration between January 2015 and July 2015
Reduction in depth = Reduction in wave height
A World of Solutions 13
Wave Height Reduction
~1.6 Miles1.1 MCY
~2.7 Miles0.9 MCY
2,500 feet80,000 CY
14A World of Solutions
Background
Beach Fill Design/Construction Plans
South Southern Shores Extension Project
Borrow Area Design/Construction Plans
Construction Photos
Bid Items and Schedule
Monitoring/Renourishment
Questions
Outline
A World of Solutions 15
Slightly Different Scenario because of Low Dunes
Kitty Hawk
16A World of Solutions
Kitty Hawk Berm and Dune
Kitty Hawk Shoreline
A World of Solutions
Dune
Design Beach
Berm Width6.0 ft.
NAVD88
Storm Damage Reduction Project Design
18A World of Solutions
Town of Kitty Hawk Design Template
‐15
‐10
‐5
0
5
10
15
20
25
0 100 200 300 400 500 600 700 800
Elevation (FT NAV
D)
Distance Along Profile (FT)
Town of Kitty Hawk Design Profile
Existing Profile
Starter Dune Example
+14 ft. NAVD
+6 ft. NAVD
60 ft. Average Design Berm
19A World of Solutions
Kitty Hawk Berm and Dune
Starter Dune provides additional level of protection that can naturally build over time to increase protection.
20A World of Solutions
Sand Fencing & Planting
A World of Solutions 21
Cover Sheet
A World of Solutions 22
Control Data
A World of Solutions 23
KDH/KH
KH/Southern Shores
A World of Solutions 24
KH/Southern Shores
Construction Access
A World of Solutions 25
Staging Area at Byrd Street
Maynard Street
(1) Dune
(2) Landward Berm Crest
(3) Seaward Berm Crest
(4)Toe of Fill
Baseline
Berm(1)
(2)(3)
(4)
Dune
A World of Solutions 26
Bleriot Street Bennett Street
A World of Solutions 27
Balchen Street
Wilkins Street
A World of Solutions 28
Lillian Street
Historic Street
A World of Solutions 29
Kitty Hawk Road
Staging Area Public Beach Access
A World of Solutions 30
Poseidon Street
A World of Solutions 31
Helga Street
KDH/KH
A World of Solutions 32
A World of Solutions 33
A World of Solutions 34
35A World of Solutions
Town of Kitty Hawk Construction Template
‐15
‐10
‐5
0
5
10
15
20
25
0 100 200 300 400 500 600 700 800
Elevation (FT NAV
D)
Distance Along Profile (FT)
Town of Kitty Hawk Construction Profile 169+70
Template Existing Profile
Starter Dune Example
+14 ft. NAVD
+6 ft. NAVD
142 ft. Average Construction Berm
36A World of Solutions
Town of Kitty Hawk Construction Template
‐15
‐10
‐5
0
5
10
15
20
25
0 100 200 300 400 500 600 700 800
Elevation (FT NAV
D)
Distance Along Profile (FT)
Town of Kitty Hawk Construction Profile 169+70
Template Existing Profile
Starter Dune
+/‐ 0.5 ft. Paid Tolerance
37A World of Solutions
Town of Kitty Hawk Construction Template
‐15
‐10
‐5
0
5
10
15
20
25
0 100 200 300 400 500 600 700 800
Elevation (FT NAV
D)
Distance Along Profile (FT)
Town of Kitty Hawk Construction Profile 169+70
Template Existing Profile
Starter Dune
+/‐ 0.5 ft. Paid Tolerance
Eligible for Payment
No Pay
38A World of Solutions
Background
Beach Fill Design/Construction Plans
South Southern Shores Extension Project
Borrow Area Design/Construction Plans
Construction Photos
Bid Items and Schedule
Monitoring/Renourishment
Questions
Outline
A World of Solutions 39
A World of Solutions 40
KH/Southern Shores
41A World of Solutions
Background
Beach Fill Design/Construction Plans
South Southern Shores Extension Project
Borrow Area Design/Construction Plans
Construction Photos
Bid Items and Schedule
Monitoring/Renourishment
Questions
Outline
42A World of Solutions
Borrow Areas
43A World of Solutions
Borrow Area Design
Locations of geophysical tracklines surveyed and vibracores collected during Phase II and III.
A World of Solutions 44
• Vibracore Analysis– Grain Size, Sorting, Silt %, Munsell Color, Shell Hash, Carbonate %
Vibracore Analysis
A World of Solutions 45
Borrow Area Design
Proposed Borrow Area A Proposed Design Area = 1,246 Acres
Proposed Design Volume = 17,806,000 cy
A World of Solutions 46
A World of Solutions 47
48A World of Solutions
Background
Beach Fill Design/Construction Plans
South Southern Shores Extension Project
Borrow Area Design/Construction Plans
Construction Photos
Bid Items and Schedule
Monitoring/Renourishment
Questions
Outline
A World of Solutions 49
Construction Photos ‐ Fill Area Overview
A World of Solutions 50
Construction Photos ‐ Fill Area Overview
A World of Solutions 51
Construction Photos – Work Limits
A World of Solutions 52
Construction Photos – Work Limits
A World of Solutions 53
Construction Photos – Dune Construction
A World of Solutions 54
Construction Photos – Work Area
A World of Solutions 55
Construction Photos – No Hold Harmless
A World of Solutions 56
Construction Photos – Hold Harmless In Place
A World of Solutions 57
Construction Photos – Sand Ramp
A World of Solutions 58
Construction Photos – Sand Ramps
Condition as of August 7, 2014 (looking south)
Construction Photos – Lighting Shields
Condition as of August 7, 2014 (looking south)
Construction Photos – Lighting Shields
61A World of Solutions
Background
Beach Fill Design/Construction Plans
South Southern Shores Extension Project
Borrow Area Design/Construction Plans
Construction Photos
Bid Items and Schedule
Monitoring/Renourishment
Questions
Outline
A World of Solutions 62
• Base Bid Items– 3 Towns
• Mob/Demob, Bonds, BA surveys and Turtle Trawling (5 days)
– Beach Fill– Sand Fencing
• Discretionary Bid Items– Potential Unsuitable Fill Material
• Screening/Removal
– Environmental Protection• Relocation Trawling• Tilling• Turbidity Monitoring• Dredge Standy Rates
– Owner or Regulatory Agency shuts down work (not weather/mechanical delays)
Bid Items
A World of Solutions 63
Sea Turtle Monitoring • Network for Endangered Sea Turtles (N.E.S.T.)• May 1 through Nov 15 • Nesting Surveys between sunrise and 9 am – must clear beach • Limits of beach fill reduced• Nighttime turtle observer on-site/Escort outside of active work zone• Sea Turtle observed – Work stopped within 500 ft. • Lays nest – Work shall not resume within 500 ft. until relocated• http://nestonline.org/
Courtesy of N.E.S.T
A World of Solutions 64
TENTATIVE Schedule
~1.6 Miles1.4 MCY
~3.6 Miles1.8 MCY
~2.6 Miles0.9 MCY
Approx. 8.3 miles and 4.1 MCY
1,500 feet80,000 CY
DuckStart – Mid/late May End – Mid/late July (~60 days) Kill Devil Hills
Start – Early AugustEnd – Early/Mid Sept(~35-45 days)
KH/Southern ShoresStart – Mid JuneEnd - Mid August(~60 days)
The Schedule is not binding and is meant to provide estimated construction times for planning purposes. The beach nourishment start and end dates are subject to change. Information will be updated as new information becomes available.
• Why does the sand pumped onto the beach initially appear to be a darker color?
• What impacts can be expected during nourishment construction?
• What if the contracted volume is reached before all sections of the project area receive sand?
• What will happen to the organisms, such as sand fleas, that live on the beach and in the surf zone?
• Why are there escarpments on the beach?
• Why don’t we have federal assistance like Wrightsville Beach or Virginia Beach?
• What do you mean by FEMA-reimbursed nourishment?
• What happens if a storm hits and damages the beach?
• How long will construction take place in front of a particular property?
• Why is dredging occurring during the summer months?
Frequently Asked Questions
A World of Solutions 66
Moving ForwardMoving Forward
Construction
Monitoring
Analysis of Conditions
Nourishment / Renourishment
A World of Solutions 67
Contact
Julien Devisse, P.E.Project [email protected](910) 791‐9494 – Office
Thank you!
Why does the sand pumped onto the beach initially appear to be a darker color? The sand has been buried and unexposed to sunlight. Once exposed to the elements, this disappears quickly and the material will match the existing sand.What impacts can be expected during nourishment construction? Once the project starts the contractor will be working 24/7 to complete the project as quickly as possible. To ensure public safety during this time, direct access to the beach in front of a given property will be prohibited. The contractor will install caution tape at crossovers that lead to the active construction area.
Frequently Asked QuestionsLikewise, the contractor will install a temporary barrier on the northern and southern boundary of the active construction area to prohibit pedestrian traffic.
In the immediate construction zone, the sound of heavy equipment, including backup alarms, will be heard and, at night, lights will be visible. As the project moves down the beach, a pipe will be placed incrementally to pump the sand for the project. Ramps will be provided at regular intervals to ensure that access to the water is maintained.
What will happen to the organisms, such as sand fleas, that live on the beach and in the surf zone?Benthic organisms (organisms that live on or near the seabed) in the surf zone generally have short life cycles and recover rapidly after beach nourishment (or severe storms). Typical recovery rates are measured in months according to numerous studies.
Frequently Asked Questions
What if the contracted volume is reached before all sections of the project area receive sand?GLDD and CPE-NC will monitor the quantity placed each day to insure that the nourishment volume is distributed according to plan. Minor adjustments are made as the project progresses along the beach in response to changing conditions so as to provide the planned nourishment volume within each subsection of the project area.
Why are there escarpments on the beach? Equilibration of the profile may leave low escarpments at the edge of the surf between the new dry beach and the wet beach. This process is similar to what natural beaches experience after minor storm events, particularly during the first northeasters of the fall. Any escarpments greater than 18 inches that are present between May 1 and August 30 shall be leveled.
What do you mean by FEMA-reimbursed nourishment?If the Town experiences a storm that is declared a disaster by the President, the Town may be eligible for FEMA funding to replace sand lost during that storm. A monitoring and maintenance plan, along with a plan for funding the maintenance, must be in place for FEMA to consider reimbursing the Town for lost sand.
Why don’t we have federal assistance like Wrightsville Beach or Virginia Beach?Unfortunately, federal funds for beach nourishment have never been made available to Nags Head. Dare County has been working with the US Army Corps of Engineers on a county-wide, federally-funded project for many years, but money for construction has never been allocated.
Frequently Asked Questions
What happens if a storm hits and damages the beach?The Town will establish a monitoring and maintenance program that will help us determine the amount of sand loss so that we can move forward with either the regular maintenance nourishment or a FEMA-reimbursed nourishment.
Frequently Asked Questions
Why is dredging occurring during the summer months? Dredging operations offshore of the Outer Banks typically take place in the summer months because it is much safer for the crews working on the offshore dredge. The increased risk of safety and anticipated decreases in productivity in the winter months when sea conditions can shut down dredge operations were found to drive the costs of the projects up to a point where they would have no longer been financially viable.
How long will construction take place in front of a particular property?The progress can vary greatly depending weather, downtime and the volume of sand being placed along the beach. At the commencement of the project, progress is typically slower as the contractor needs some time to work out the kinks in their equipment. Once these kinks have been worked out, the contractor averages between 50 and 150 feet of beach per day. Therefore, a specific property will be impacted by construction on average 4 to 6 days. Once the Project commences a daily progress map will be available at www.morebeachtolove.com.
A World of Solutions 72
Summertime Dredging