Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

26
Danish wind power plans by 2030 Outi Kartano Janne Tuunanen

Transcript of Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Page 1: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Danish wind power plans by 2030

Outi KartanoJanne Tuunanen

Page 2: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 2

Background

Net exporter of oil and natural gas for only 10 more years:

Need to build up a new sustainable energy production

Vision for long-term phasing-out of fossil fuels

Increase long-term supply reliability and decrease CO₂ emissions

Page 3: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 3

Political framework

2004: Long-run Energy Policy Agreements of

March 2004

2007: A visionary Danish energy policy 2025

2008: Energy Policy Agreement of 21 February

2008

2009: Danish Promotion of Renewable Energy Act

2012: Energy Agreement of 22 March 2012

Page 4: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 4

2011o Reduce gross energy consumption by 2% at period

2006-2011

o 20% of gross energy consumption covered by renewable energy

o 28% of electricity consumption covered by wind energy

Page 5: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 5

Wind Capacity and Share of Electricity Supply

Page 6: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 6

INDUSTRYo Year 2011 wind industry

6.4% of total Danish

exports

o Value of export 38.8

billion DKK

o Employees 23 500Global market shares of wind turbine manufacturers at 2010:

Vestas+Siemens (DK) 20%

Page 7: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 7

OFFSHORE

Capacity at 2012 total 1300 MW• Anholt 400 MW• Horns Rev I&II 370 MW• Rödsand II 207 MW• Nysted 165 MW

Page 8: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 8

Page 9: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 9

o The Danish Energy Agency (DEA) a “one-stop-

shop” for permits to offshore wind turbines

o Tenders out the government projects in an

open competition

o Assessment of environmental impacts

o Mapping of future sites (4600 MW)

DEA

Page 10: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 10

ONSHORE

Page 11: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 11

Promoting local population’s acceptance:

o The loss-of-value scheme

o The option-to-purchase scheme

o The green scheme

o The guarantee schemeEnerginet.dk’s Front Office is available for

advice and guidance

Page 12: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 12

PSO

o Public Service Obligation (PSO) fee

o paid by all electricity consumers

o due to increased support for renewable

energy use

Page 13: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 13

Grid Connections

Varying electricity production:

o Exceeds Danish consumption at night

o No production due to lack of wind or

storms

Cross-border grid connections to Sweden, Norway and Germany

Page 14: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 14

Page 15: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 15

Part 1 Summary

o Broad and long-term political commitment

o “One-stop-shop” DEA

o Actions for acceptance of local people

o Denmark’s location:

Windy environment

Enables cross-border grid connections to ensure back-up

capacity

Page 16: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Danish wind power plans by 2030

Part 2: The outlook

Page 17: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 17

Denmark’s energy goals

o By 2030: 50% of renewables CO₂-free heating

• District heating• Excess wind energy and heat pumps

o 50% of electricity with wind by 2020-2025

The ultimate goal is to be

independent of fossil fuels by 2050

Page 18: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 18

Denmark’s energy consumption has been historically very constant, even though economy has grown

1990: ≈600 PJ

Page 19: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 19

Wind power is one of the main elements in the attempt to achieve the set goals

o Uses:

o Most new capacity set to

be installed offshore

o Also at least 1000 MW

more potential onshore Plans to install up to 1800 MW of new capacity by 2020

2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 20110.00

0.05

0.10

0.15

0.20

0.25

0.30

Wind vs all electricity production

Page 20: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 20

Government initiatives (1/2)

Page 21: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 21

Government initiatives (2/2)

o Subsidieso Improving

tendering procedures

o New transmission lines to Sweden and Germany

Page 22: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 22

Technology diffusion aspects

Page 23: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 23

Nordpool: to even out the fluctuations

o Building better connections to neighbouring

countries

o Selling excess energy to neighbours

o Hydro energy from Sweden and Norway

Kriegers Flak (600 MW) wind park carried out as a joint venture with Germany (and Sweden), in operation by 2020

Page 24: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 24

Challenges

o The grid needs to be expanded and strengthened to support the increased wind energy production

o The average time from decision to implementation is around 10 years

o Storing energy (20-30 GWh could be stored as useful heat with the existing system)

Page 25: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 25

Summary

o The Danish have been and continue to be forerunners in implementing wind power

o The Danish plans are quite ambitious, but feasible

o Increasing the amount of wind energy is an essential part of the plans

o Government has numerous initiatives to support the progress

Page 26: Danish wind power plans by 2030 Outi Kartano Janne Tuunanen.

Kartano & Tuunanen 26

Thank you for your attention!

Comments?Questions?