Dam Monitoring in Laos
Transcript of Dam Monitoring in Laos
-
8/13/2019 Dam Monitoring in Laos
1/102
Theun Hinboun Power Company
Theun Hinboun Expansion PTheun Hinboun Expansion PTheun Hinboun Expansion PTheun Hinboun Expansion P
CONSTRUCTION
NG Dam - Monitoring of NG
C-CO-C-AGD-TR-014-A0
Date: 17/09/2011 Rev. A0
-
8/13/2019 Dam Monitoring in Laos
2/102
A0 17/09/11 First Issue MLH
Revision Date Subject of Revision Drafted C
Theun Hinboun Expansion Theun Hinboun Expansion Theun Hinboun Expansion Theun Hinboun Expansion Owner:
Theun Hinboun Power Com
Main Contractor:
Engineering Consultants:
COYNE ET BELLIERBureau d'Ingnieurs Conseils
Engineering Consultants:
CONSTRUCTION
NG Dam - Monitoring of NG da
-
8/13/2019 Dam Monitoring in Laos
3/102
THXP NG Dam - Monitoring of NG dam
TABLE OF CONTENTS
1. INTRODUCTION
2. REFERENCES
3. MAIN INSTRUMENTS
1.1 General
1.2 Water pressure vibrating wire cells (electrical piezoPC
1.3 Stand pipe piezometers PZ and DPZ
1.4 Pendulums (plumb-lines) - PLD and PLV
1.5 Thermometers T
1.6 Levelling studs LS
1.7 Surface movement markers MM
1.8 Joint opening device JM
1.9 V-Notch weirs for seepage measurement - MW
1.10 Reservoir water level
2 PRINCIPLE OF THE MONITORING
2.1 Data to be collected
2.2 Visual inspection
2.3 Data processing
a) Water pressure vibrating wire cells (electrical piezo
-
8/13/2019 Dam Monitoring in Laos
4/102
THXP NG Dam - Monitoring of NG dam
i) Reservoir water level
3 MEASURING FREQUENCY
Appendix A: Monitoring system location
Appendix B: Monitoring system - SISGEO Instruction Manu
Appendix C: Devices Certificate
Appendix D: Drilling and Verticality tests of Invert pendulum
-
8/13/2019 Dam Monitoring in Laos
5/102
THXP NG Dam - Monitoring of NG dam
TABLE OF FIGURES
Figure 1: Dam monitoring - Instrument layout (plan view) ...................Figure 2: Section PC1 on the RB, ch. 0+160.......................................Figure 3: Section PC2 on the RB, ch. 0+220.......................................Figure 4: Section PC3 on the spillway, ch. 0+273 ...............................Figure 5: Section PC4 on the spillway, ch. 0+328 ...............................Figure 6: Section PC5 on the LB, ch. 0+385.......................................Figure 7: Section PC6 on the LB, ch. 0+434.......................................
Figure 8: PZ 0+070 on the RB ............................................................Figure 9: PZ 0+110 on the RB ............................................................Figure 10: PZ 0+160 on the RB ..........................................................Figure 11: DPZ 0+196 on the RB........................................................Figure 12: PZ 0+217.5 on the RB .......................................................Figure 13: PZ 0+230.5 and DPZ 0+235 on the RB..............................Figure 14: DPZ 0+300 on the spillway ................................................Figure 15: PZ 0+347.4 and DPZ 0+350 on the LB ..............................Figure 16: PZ 0+419 and DPZ 0+416 on the LB .................................Figure 17: PZ 0+440 on the LB...........................................................Figure 18: PZ 0+468 on the LB ch. 0+468 ......................................Figure 19: PZ 0+510.5 on the LB ch. 0+510.50................................Figure 20: The Pendulums elevation layout .....................................Figure 21: Cartesian axis system at the top of the hole.......................Figure 22: Borehole profile survey ......................................................Figure 23: Detection of wire position at Hi depth.................................Figure 24: Detecting of the X and Y components at i depth.................
Figure 25: Example of hole free section diagram................................Figure 26: Thermometers Layout.....................................................Figure 27: Thermometers at ch. 0+160 ...............................................Figure 28: Thermometers at ch. 0+211 ...............................................Figure 29: Thermometers at ch. 0+290 ...............................................Figure 30: Thermometers at ch. 0+330 ...............................................Figure 31: Thermometers at ch. 0+354 ...............................................Figure 32: Thermometers at ch. 0+374 ...............................................Figure 33: Thermometers at ch. 0+411 ...............................................
Figure 34: Thermometers at ch. 0+450 ...............................................Figure 35: Typical section - topographic monitoring............................Figure 36: Studs for precision levelling and V-Notch weirs- Upstream Figure 37: Surface movement markers and stud - Downstream view..Figure 38: Layout................................................................................Figure 39: Vibrating-wire piezometers.................................................Figure 40: Four reading positions
-
8/13/2019 Dam Monitoring in Laos
6/102
THXP NG Dam - Monitoring of NG dam
1. INTRODUCTION
This technical note describes the monitoring system of NG Dam. Itsdam Operation and Maintenance Manual, regarding the monitoring sy
Nota: the yellow part of this report will be updated later on with the as
2. REFERENCES
[1] Employers Requirements Part A Paragraph 5.3 NG Dam, outlet
[2] Employers Requirements Part B Paragraph 4, 4.15 Design o
pressure relief well[3] C-CO-D-AGE-SP-002 NG Dam Instrumentation Technical Spe[4] C-CM-C-MNG-QA-060 NG Dam Instrumentation Qualification [5] C-CO-D-ADG-CA-001 Definition of NG Dam Monitoring system[6] C-CO-C-AGD-EQ-003 to 028 NG dam instrumentation drawings[7] C-CO-E-AGD-EQ-005, 006, 013 to 017 As Built - NG dam instru[8] C-CO-C-AGD-TR-007 NG Dam First impounding of NG dam re[9] C-CO-C-AGD-CA-002 NG Dam Stability analysis of the dam
[10] C-CO-C-AGD-CA-011 - Modeling of the underground water flow ththe dam[11] C-CO-C-AGD-TR-009 NG Dam - Adaptation of monitoring equi
the impounding[12] INTERNATIONAL STANDARD - ISO 1438:2008 - Hydrometry
measurement using thin-plate weirs
-
8/13/2019 Dam Monitoring in Laos
7/102
THXP NG Dam - Monitoring of NG dam
Main instruments
1.1 General
The following measuring devices are to be considered to monitor th[7]):
Dam monitoring:
- 25 Pressure cells (vibrating wire piezometer) P
- 10 piezometers, D/S toe open pipe P
- 5 direct piezometers from gallery with manometer D
- 3 Direct pendulums P
- 3 Invert pendulums P
- 42 Thermometers T
Topographic control:
- 51 levelling studs L
- 20 surface movement markers M- 34 3D joint-meters (
Water control:
- 6 seepage measuring weirs (V-Notch) M
- Water level indicator:
o U/S (intake powerhouse) Reservoir Water Level R
o D/S (Spillway LB abutment) Tail Water Level T
-
8/13/2019 Dam Monitoring in Laos
8/102
THXP NG Dam - Monitoring of NG dam
-
8/13/2019 Dam Monitoring in Laos
9/102
THXP NG Dam - Monitoring of NG dam
1.2 Water pressure vibrating wire cells (electrical piezome
Vibrating wire piezometers are installed in the foundation at the lFigure 1. Foundation cells are installed in 90 mm diameter boreholesFigure 2 to Figure 7. These piezometers are required to monitor upliffoundation particularly during the first filling and subsequently.
The majority of the pressure cells are located at the contact dam/fopore-water pressure in the nearest vicinity of the NG dam. The fewfoundation are required to monitor uplift pressures on the dam foundefficiency of the grout curtain and the drainage of the deep foundation
At each chainage, switch terminal boxes are placed in order to conneboxes in the lower gallery, 2 boxes in the upper gallery).
Figure 3: Section
-
8/13/2019 Dam Monitoring in Laos
10/102
THXP NG Dam - Monitoring of NG dam
Figure 4: Section PC3 on the spillway, ch. 0+273 Figure 5: Sectio
-
8/13/2019 Dam Monitoring in Laos
11/102
THXP NG Dam - Monitoring of NG dam
1.3 Stand pipe piezometers PZ and DPZ
15 nos. stand pipe piezometers are installed to monitor the water pDam foundation, completing and cross-checking data recorded by the
Foundation stand pipe are installed in 120 mm diameter boreholes Figure 8 to Figure 19.
These piezometers are:
- drilled (vertical) from natural ground at downstream dam toread with a water depth portable measuring probe PZ.
- drilled from the gallery, inclined, closed by a manometer, (5 un
Piezometers consist of a porous intake connected to the ground surfpore water pressure can be observed by the use of different measurin
manual system has been foreseen by means of sounding lead.
Figure 8: PZ 0+070 on the RB Figure 9: PZ 0+110 on the RB
-
8/13/2019 Dam Monitoring in Laos
12/102
THXP NG Dam - Monitoring of NG dam
Figure 14: DPZ 0+300 on the spillwayFigure 15: PZ 0+34
-
8/13/2019 Dam Monitoring in Laos
13/102
THXP NG Dam - Monitoring of NG dam
Figure 18: PZ 0+468 on the LB ch. 0+468 Figure 19: PZ 0+510
-
8/13/2019 Dam Monitoring in Laos
14/102
THXP NG Dam - Monitoring of NG dam
1.4 Pendulums (plumb-lines) - PLD and PLV
Pendulum monitoring devices are installed in different profile of theFigure 1.
Each profile shall be equipped with an inverted pendulum, adisplacement of the dam base compared to the foundation, and a dirthe displacement of the top of the dam in comparison with the dam ba
Total of 3 direct and 3 indirect pendulums, with reading devices are inintermediated reading is performed on the direct pendulum at ch. 0+3
See Figure 20.
-
8/13/2019 Dam Monitoring in Laos
15/102
THXP NG Dam - Monitoring of NG dam
The following procedure was implemented:
1) At the top of the casing, two wires were installed in order to oaxis system that will give the position of the hole center.
Figure 21: Cartesian axis system at the top of th
2) A piece of steel with concrete inside, hung from a 3 mm diamthe gallery roof, was placed inside the hole.
3) The distance h between the pulley axis and the grid on tmeasured.
4) The weight was stopped every meter in the borehole.
measurements Xi and Yi, distance of the wire from the two axFigure 23).
-
8/13/2019 Dam Monitoring in Laos
16/102
THXP NG Dam - Monitoring of NG dam
Figure 24: Detecting of the X and Y components a
6) Once reported the center hole positions at each depth, itrelated circumferences. The area common to all circumfersection and the coordinometer have to be mounted exactly ov
Figure 25: Example of hole free section diagr
-
8/13/2019 Dam Monitoring in Laos
17/102
THXP NG Dam - Monitoring of NG dam
1.5 Thermometers T
Thermometers installed in different sections of the dam, as shownThermometers read 2-hourly for the first week after installation, 6-hweeks and daily for the next five months. The reading is then oThermometers control the peak temperature during setting of theallows to understand when the dam has reached is maturity, and thabody is only influenced by the external seasonal and water from theffect.
Total of 42 Thermometers are installed in the dam (Temperature raterminal boxes shall be placed in order to connect the Thermometers
See Figure 26 to Figure 34.
-
8/13/2019 Dam Monitoring in Laos
18/102
THXP NG Dam - Monitoring of NG dam
Figure 27: Thermometers at ch. 0+160 Figure 28: Ther
Figure 29: Thermometers at ch. 0+290 Figure 30: Ther
-
8/13/2019 Dam Monitoring in Laos
19/102
THXP NG Dam - Monitoring of NG dam
Figure 33: Thermometers at ch. 0+411 Figure 34: Ther
-
8/13/2019 Dam Monitoring in Laos
20/102
THXP NG Dam - Monitoring of NG dam
1.6 Levelling studs LS
Lines of levelling studs are placed on different dam locations.
Levelling studs are located, according to the drawings [6], as follows:
- 6 levelling downstream heel;
- 22 levelling along the galleries, one per block, fixed to the roof
- 23 levelling studs on the dam crest (one per block).A total of 51 levelling studs are provided (see Figure 35, Figure 36 an
1.7 Surface movement markers MM
Lines of survey points are located as defined on the drawing [6], adam.
The survey points are the supports for corner prisms able of reflectinstation and are securely fixed to the dam. The survey points are plaface of the dam and on the dam crest at various emplacements (se37).
A total of 20 supports for corner prism and the total station device are
Two reference survey pillars are installed on both banks at the locdrawing [6].
1.8 Joint opening device JM
Joint opening devices (3D) allowing read the opening of dam vertical
-
8/13/2019 Dam Monitoring in Laos
21/102
THXP NG Dam - Monitoring of NG dam
1.9 V-Notch weirs for seepage measurement - MW
The measurement canal bottom has a 1-3% slope towards the wperfectly vertical and perpendicular in relation to the canal axis.
The staff gauge is fixed at the wall of the stilling basin. The measurewith manual readings of the H value, directly on the staff gauge.
6 (six) seepage measurements are installed in the dam galleries as[6], in order to measure seepage in the dam (see Figure 35 and Figur
two seepage measurement on gallery weirs in the upper galle
four seepage measurement on both sides of the sump pit in th
The purpose of the weir is to measure the instantaneous flow. Lmeasured by means of water level measuring rod staff gauge (manbasin variations).
Figure 35: Typical section - topographic monito
-
8/13/2019 Dam Monitoring in Laos
22/102
THXP NG Dam - Monitoring of NG dam
Figure 37: Surface movement markers and stud - Down
Figure 38: Layout
-
8/13/2019 Dam Monitoring in Laos
23/102
THXP NG Dam - Monitoring of NG dam
2 PRINCIPLE OF THE MONITORING
2.1 Data to be collected
The data collected for the monitoring are:
- manual measures:
o 15 piezometers:
10 piezometers, D/S toe open pipe
5 direct piezometers from gallery with manome
o 14 coordinates from the pendulums
o 51 levelling data (vertical displacement Z)
o 60 (= 3 X 20) topographic data (X, Y and Z) o 102 (= 3 x 34) data from the 9 3Djoint-meters
o 6 seepage measuring weirs (V-Notch)
o water level upstream and downstream
- Electrical measures first with data logger:
o 25 Pressure Cells (vibrating wire piezometer)
o 42 Thermometers
- Meteorological data:
o minimum and maximum temperature
o daily rain
Measure Device
Uplift pressure 25 pressure cells
-
8/13/2019 Dam Monitoring in Laos
24/102
THXP NG Dam - Monitoring of NG dam
2.2 Visual inspection
Visual inspections consist in checking the galleries, the toe of the damand all other particular points in order to:
- detect coming of water and cracks,
- follow the behaviour of the drain curtain,
For the active drains, the drain where a discharges bigger than 2
regularly measured and be added as a monitored data in the inspecti
2.3 Data processing
Prior the impounding, a first reading was done in order to confirm thand calibration parameters and in order to value their plausibility.
a) Water pressure vibrating wire cells (electrical piezom
The Pressure Cell consists of a filter, a saturated hydraulic chamber a pressure sensitive elastic diaphragm. Water pressure transmitted ta deflection of the diaphragm that is directly proportional to the pressu
In Vibrating-wire piezometers, the diaphragm deformation cause a frequency of vibration of a tensioned steel wire suspended betweentransducer body. The water pressure acting on the diaphragm can change in measured frequency of the vibrating wire.
-
8/13/2019 Dam Monitoring in Laos
25/102
THXP NG Dam - Monitoring of NG dam
S
IL
P
0
=
Where P = Pressure in kPa;
Io = Frequency-squared (f) reading taken beforeinstrument in air (Hz x 10-3);
L = Instrument (f) reading (Hz x 10-3);
S = Linear conversion factor reported on the calibratio
The water level associated is:
81.9
PzWL +=
Where WL = Water level in m.a.s.l;
z = Pressure cell elevation in m.a.s.l;
P = Pressure in kPa.
b) Stand pipe piezometers PZ and DPZ
For the 10 open pipe piezometers at the D/S toe of the Dam, tmeasuring the water level inside the piezometer tube by means of a m
It is important that the readings are always referred to the top procedure is to survey topographically the top of the tube so to ob
level.
Water level (m.a.s.l) = top of the pipe (m.a.s.l) read
The pressure give by the manometer of the 5 direct piezometers froThe water level associated is then calculated as follows:
-
8/13/2019 Dam Monitoring in Laos
26/102
THXP NG Dam - Monitoring of NG dam
c) Pendulums (plumb-lines) - PLD and PLV
The pendulum readings are made with an optical readout (Coordmanual readings of horizontal movements of a plumb line. 7 coordinosite.
The coordinates (X;Y) of the steel wire are determined by means of When the photocell light ray intercepts the steel wire, a green light toff when the wire is not anymore intercepted by the photocell light
recorded on the 4 positions of the coordinometer (see Figure 40).
An initial reading was taken after installation accomplishment. Allcompared to this initial reading
The initial readings on the 4 positions are Lxi1, Lxi2, Lyi1, Lyi2, Lxi3, Lx
So the initial positions are then:
2
21 LxiLxiXa+
= ;2
21 LyiLyiYa+
=
2
43 LxiLxi
Xb+
= ;2
3 LyLyi
Yb+
=
With X = axis upstream (-) / downstream (+)
Y = axis right bank (-) / left bank (+)
The current readings on the 4 positions are Lx1, Lx2, Ly1, Ly2, Lx3, Lx4
-
8/13/2019 Dam Monitoring in Laos
27/102
-
8/13/2019 Dam Monitoring in Laos
28/102
THXP NG Dam - Monitoring of NG dam
The reading consists in periodical measurements of the position balong three perpendicular axes. From the reading, the variations of thspace between the two sides of the crack are computed.
Readings are taken by a dial gauge in mm (see Figure 41).
h) V-Notch weirs for seepage measurement MW
The water level in the basin of the weir V-Notch h is measured manfixed at 1m upstream of the weir.
The Kindsvater-Shen formula (see [12]) for triangular notch weirs is:
2/52
2tan
15
8ed hgCQ
=
Where Q = flow [m3/s];
Cd = coefficient of discharge equal to 0.58;
1m
-
8/13/2019 Dam Monitoring in Laos
29/102
THXP NG Dam - Monitoring of NG dam
3 MEASURING FREQUENCY
The first year and after the period of brutal variation of water level (>water discharge on the spillway shall be strengthening monitored. Sbe tightened:
First years or period of brutal variation of water level (>5
and/or water discharge on the spillway
Devices Frequenc
PC 25 pressure cells
PZ & DPZ 15 piezometers
One series per week
PLD 3 direct pendulums
PLV 3 invert pendulums
One series per week
T 42 thermocouples One series per month
LS 51 levelling studs
MM20 surface movement
markers
One topographic and levelling ca(during the first year)
JM 11 3Djoint-meters One series per week
MW 4 seepage measuring weirs Two series per week
RWL &TWL
2 staff gauges One series per day
Table 2: Monitoring of the dam during the first years or durinvariation of water level (>5m in one week) and/or water discha
-
8/13/2019 Dam Monitoring in Laos
30/102
THXP NG Dam - Monitoring of NG dam
After the first years, and during period when the water level is staimplement the following measurement frequency during the exploitati
After the first year and with stable water le
Devices Frequenc
PC 25 pressure cells
PZ & DPZ 15 piezometers
One series every 15 days
PLD 3 direct pendulums
PLV 3 invert pendulums
One seriesper month
T 42 thermocouples One series per month
LS 51 levelling studs
MM20 surface movement
markers
Two topographic and levelling ca
JM 11 3Djoint-meters One series every 15 days
MW 4 seepage measuring weirs One series every 15 days
RWL &TWL
2 staff gauges One series per day
Table 3: Monitoring of the dam after the first years and with
The notion of first years and the reading frequencies are tentative anactual site conditions by the engineering consultant in charge of the m
-
8/13/2019 Dam Monitoring in Laos
31/102
THXP NG Dam - Monitoring of NG dam
TABLE OF APPENDICES
A Monitoring system location
B Monitoring system - SISGEO Instruction Manua
C Devices Certificate
D Drilling and Verticality tests of Invert pendulum
-
8/13/2019 Dam Monitoring in Laos
32/102
THXP NG Dam Monitoring of NG dam
-
8/13/2019 Dam Monitoring in Laos
33/102
THXP NG Dam - Monitoring of NG dam
4. Pressure cells
C1-P
C2
PC1-P
C3
PC2-P
C1
PC2-P
C
2
PC2-P
C3
PC3-P
C1
PC3-P
C2
PC3-P
C3
PC3-P
C4
PC3-P
C5
384
390
374
390
374
415
412.
7
402
412
402
384
390
374
390
374
8556
.5
9264
.7
8988
.3
9683.2
9506
.7
8344
.6
9868
.9
9620
.1
10611
.3
10153
.9
24
.7
24.7
26
.7
29
.1
25
.2
30
.9
25
.2
9604
.4
9534
.6
9264
.2
9842.6
9641
.2
9172
.8
10298
.7
10643
.0
11027
.0
11097
.2
23
.5
24.1
28
.2
29
.2
28
.6
18
.9
17
.4
25
26
24
8489
.1
8402
.9
9082
.6
9638.4
9364
.5
8356
.1
9890
.3
9614
.4
10565
.9
10152
.3
25
.6
25.6
26
.4
28
.3
26
.7
26
.7
27
.1
25
.2
31
25
.2
9546
.0
9476
.0
9563
.0
9663.0
10067
.0
9193
.0
10297
.0
10660
.0
11062
.0
11118
.0
21
20
20
20
21
21
21
22
21
21
9.6
0403
-8.5
43
58
-9.6
0173
-9.1
736
7
-9.3
3791
-5.3
7929
-4.0
4189
-4.9
0809
-5.5
358
-4.3
6706
30/06/11
30/06/11
05/05/11
07/05/1
1
05/05/11
16/03/11
16/03/11
02/12/10
02/12/10
02/12/10
0+
160
0+
220
0+
273
PC4-P
C3
PC4-P
C
4
PC4-P
C5
PC5-P
C1
PC5-P
C2
PC5-P
C3
PC5-P
C4
PC5-P
C5
PC6-P
C1
PC6
-PC2
PC6-P
C3
PC6-P
C4
377
392
377
383
.2
388
.9
377
.7
395
.8
384
.9
409
.74
39
6.7
7
410
.36
412
.4
377
392
377
383
.4
389
.3
377
.9
396
.1
385
.0
410
.04
39
7.0
7
410
.47
412
.45
8999
.4
10274.4
7625
.9
9542
.7
9
657
.3
9127
.0
8979
.6
9671
.5
8783
.3
70
60
.4
7480
.8
9571
.1
25
.7
29
.7
25
.3
25
.4
27
.6
23
.8
29
.7
25
.6
36
.9
2
4.4
26
.5
27
.7
10009
.9
10512.4
8989
.2
10417
.8
1
0272
.3
9984
.8
9283
.6
10361
9655
.5
90
79
.1
8479
.1
10250
.0
0+
385
0+
434
0+
328
THXP NG Dam - Monitoring of NG dam
-
8/13/2019 Dam Monitoring in Laos
34/102
THXP NG Dam - Monitoring of NG dam
Appendix B: Monitoring system - SIInstruction Manual
1. Instruction Manuel Piezometers
2. Instruction Manuel Direct and InvPendulums
3. Instruction Manuel Optical Coord
4. Instruction Manuel Thermometers
5. Instruction Manuel Joint-Meters
6. Instruction Manuel Flow Meter
Pl i fi hi t tt h bl d
-
8/13/2019 Dam Monitoring in Laos
35/102
Plusieurs fichiers sont attachs ensemble da
Adobe conseille dutiliser la version 8 (ou ultrieure) dAdobe Reade
pour manipuler les documents contenus dans un lot PDF. En effectu
vers la dernire version, vous bnficierez des avantages suivants :
Un affichage PDF optimis et intgr
Une impression aise
Des recherches rapides
Vous ne disposez pas de la dernire version dA
Cliquez ici pour tlcharger la dernire version d
Si vous disposez dj dAdobe Reade
cliquez sur un fichier dans le lot PDF pour
THXP NG Dam - Monitoring of NG dam
http://www.adobe.com/fr/products/acrobat/readstep2.htmlhttp://www.adobe.com/fr/products/acrobat/readstep2.html -
8/13/2019 Dam Monitoring in Laos
36/102
G a o to g o G da
Appendix C: Devices Certificate
-
8/13/2019 Dam Monitoring in Laos
37/102
-
8/13/2019 Dam Monitoring in Laos
38/102
-
8/13/2019 Dam Monitoring in Laos
39/102
-
8/13/2019 Dam Monitoring in Laos
40/102
-
8/13/2019 Dam Monitoring in Laos
41/102
-
8/13/2019 Dam Monitoring in Laos
42/102
-
8/13/2019 Dam Monitoring in Laos
43/102
-
8/13/2019 Dam Monitoring in Laos
44/102
-
8/13/2019 Dam Monitoring in Laos
45/102
-
8/13/2019 Dam Monitoring in Laos
46/102
-
8/13/2019 Dam Monitoring in Laos
47/102
-
8/13/2019 Dam Monitoring in Laos
48/102
-
8/13/2019 Dam Monitoring in Laos
49/102
-
8/13/2019 Dam Monitoring in Laos
50/102
-
8/13/2019 Dam Monitoring in Laos
51/102
-
8/13/2019 Dam Monitoring in Laos
52/102
-
8/13/2019 Dam Monitoring in Laos
53/102
-
8/13/2019 Dam Monitoring in Laos
54/102
-
8/13/2019 Dam Monitoring in Laos
55/102
-
8/13/2019 Dam Monitoring in Laos
56/102
-
8/13/2019 Dam Monitoring in Laos
57/102
-
8/13/2019 Dam Monitoring in Laos
58/102
-
8/13/2019 Dam Monitoring in Laos
59/102
-
8/13/2019 Dam Monitoring in Laos
60/102
-
8/13/2019 Dam Monitoring in Laos
61/102
-
8/13/2019 Dam Monitoring in Laos
62/102
-
8/13/2019 Dam Monitoring in Laos
63/102
-
8/13/2019 Dam Monitoring in Laos
64/102
THXP NG Dam - Monitoring of NG dam
-
8/13/2019 Dam Monitoring in Laos
65/102
Appendix D: Drilling and Verticality Inverted pendulums
-
8/13/2019 Dam Monitoring in Laos
66/102
-
8/13/2019 Dam Monitoring in Laos
67/102
-
8/13/2019 Dam Monitoring in Laos
68/102
-
8/13/2019 Dam Monitoring in Laos
69/102
Distance between the pulley and the top of the hole: 4.76 m
DeviationDeviation Deviation
26/07/2011
Invert pendulum at ch. 0+233
-
8/13/2019 Dam Monitoring in Laos
70/102
DepthDeviation
topbottom
EST
bottom
SOUTHm mm mm mm
1 Est 3
1 South 3
2 Est 3
2 South 3
3 Est 3
3 South 3
4 Est 3
4 South 3
5 Est 3
5 South 3
6 Est 3
6 South 3
7 Est 3
7 South 3
8 Est 3
8 South 3
9 Est 3
9 South 3
10 Est 3
10 South 311 Est 3
11 South 3
12 Est 3
12 South 3
13 Est 3
13 South 4
14 Est 3
14 South 3
15 Est 3
15 South 416 Est 3
16 South 4
17 Est 3
17 South 3
18 Est 3
18 South 3
19 Est 3
19 South 4
20 Est 3
20 South 4
21 Est 3
21 South 3
22 Est 3
22 South 3
23 Est 3
23 South 3
16.9 16.9
17.5 17.5
15.6 20.8
16.2 16.2
14.3 14.3
15.0 20.0
13.1 17.4
13.7 13.7
11.8 11.8
12.5 16.6
10.6 10.6
11.2 14.9
9.3 9.3
9.9 9.9
8.0 8.0
8.7 8.7
6.8 6.8
7.4 7.4
4.9
5.5 5.5
6.2 6.2
Direction
3.6 3.6
4.3 4.3
4.9
Deviation -
0
5
10
15
20
25
30
35
0 5 10
Deviation
Depth(m)
Deviation - S
0
5
10
0 5 10
Deviation
-
8/13/2019 Dam Monitoring in Laos
71/102
-
8/13/2019 Dam Monitoring in Laos
72/102
-
8/13/2019 Dam Monitoring in Laos
73/102
-
8/13/2019 Dam Monitoring in Laos
74/102
-
8/13/2019 Dam Monitoring in Laos
75/102
-
8/13/2019 Dam Monitoring in Laos
76/102
-
8/13/2019 Dam Monitoring in Laos
77/102
Distance between the pulley and the top of the hole: 4.91 m
DepthDeviation
top
Deviation
bottom
Deviation
bottom
22/06/2011
Direction
Invert pendulum at ch. 0+364
Deviation -
-
8/13/2019 Dam Monitoring in Laos
78/102
topEST SOUTH
m mm mm mm
1 Est 0
1 South 0
2 Est 0
2 South 0
3 Est 0
3 South 0
4 Est 0
4 South 0
5 Est 0
5 South 06 Est 0
6 South 0
7 Est 0
7 South 0
8 Est 0
8 South 0
9 Est 0
9 South 0
10 Est 0
10 South 011 Est 0
11 South 0
12 Est 0
12 South 0
13 Est 0
13 South 0
14 Est 0
14 South 0
15 Est 0
15 South 016 Est 0
16 South 0
17 Est 0
17 South 0
18 Est 0
18 South 0
19 Est 0
19 South 0
20 Est 0
20 South 0
21 Est 0
21 South 0
22 Est 0
22 South 0
23 Est 0
23 South 0
0.0 0.0
0.0
Direction
0.0 0.0
0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0
5
10
15
20
25
30
35
0 0 0
Deviation
Depth(m)
Deviation - S
0
5
10
0 0 0
Deviation
-
8/13/2019 Dam Monitoring in Laos
79/102
-
8/13/2019 Dam Monitoring in Laos
80/102
-
8/13/2019 Dam Monitoring in Laos
81/102
-
8/13/2019 Dam Monitoring in Laos
82/102
-
8/13/2019 Dam Monitoring in Laos
83/102
-
8/13/2019 Dam Monitoring in Laos
84/102
-
8/13/2019 Dam Monitoring in Laos
85/102
-
8/13/2019 Dam Monitoring in Laos
86/102
-
8/13/2019 Dam Monitoring in Laos
87/102
-
8/13/2019 Dam Monitoring in Laos
88/102
-
8/13/2019 Dam Monitoring in Laos
89/102
-
8/13/2019 Dam Monitoring in Laos
90/102
-
8/13/2019 Dam Monitoring in Laos
91/102
-
8/13/2019 Dam Monitoring in Laos
92/102
Distance between the pulley and the top of the hole: 4.30 m
DepthDeviation
top
Deviation
bottom
EST
Deviation
bottom
SOUTH
m mm mm mm
Invert pendulum at ch. 0+416
15/07/2011
Direction Deviation -
Deviation
-
8/13/2019 Dam Monitoring in Laos
93/102
1 Est 0
1 South 2
2 Est 0
2 South 2
3 Est 0
3 South 2
4 Est 0
4 South 2
5 Est 0
5 South 26 Est 0
6 South 2
7 Est 0
7 South 0
8 Est 0
8 South 0
9 Est 0
9 South 1
10 Est 1
10 South 211 Est 1
11 South 2
12 Est 1
12 South 2
13 Est 1
13 South 2
14 Est 1
14 South 2
15 Est 0
15 South 216 Est 0
16 South 0
17 Est 0
17 South 0
18 Est 0
18 South 0
19 Est 0
19 South 0
20 Est 0
20 South 0
21 Est 0
21 South 0
22 Est 0
22 South 1
23 Est 0
0.0 6.1
0 0 6 3
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
0.0 0.0
4.3 8.5
0.0 9.0
3.8 7.6
4.0 8.0
3.3 6.7
3.6 7.1
0.0 0.0
0.0 3.1
0.0 4.8
0.0 0.0
0.0 3.9
0.0 4.3
0.0 2.5
3.4
0.0 2.9
0.0
0
5
10
15
20
25
30
35
0 1 2
Depth(m)
Deviation - S
0
5
10
0 5 10
Deviation
-
8/13/2019 Dam Monitoring in Laos
94/102
-
8/13/2019 Dam Monitoring in Laos
95/102
-
8/13/2019 Dam Monitoring in Laos
96/102
-
8/13/2019 Dam Monitoring in Laos
97/102
-
8/13/2019 Dam Monitoring in Laos
98/102
-
8/13/2019 Dam Monitoring in Laos
99/102
-
8/13/2019 Dam Monitoring in Laos
100/102
-
8/13/2019 Dam Monitoring in Laos
101/102
-
8/13/2019 Dam Monitoring in Laos
102/102