Daily Activity HMI Upgrade TEG 9610-9620 Per November 5,2014
Transcript of Daily Activity HMI Upgrade TEG 9610-9620 Per November 5,2014
-
8/10/2019 Daily Activity HMI Upgrade TEG 9610-9620 Per November 5,2014
1/11
PT.Indoturbine GENERAL REPORTDistributor Of Solar Turbines
FIELD REP Report Dates
Andika Pratama
Yusup Armansyah November, 2014
Country Customer Name Site Name CSA Numbers
INDONESIA TOTAL E&P NPU Site
PD
Number
Customer
Tag
Package
S/N
Engine
S/N
Package
Starts
Package
Hours
Engine
Hours
Service Order
No.
70231
70232
TEG 9610
TEG 9620
CG01823
CG01824 1072H
PT. Indoturbine 1/11
HMI UPGRADE PROJECT
TEG 9610 & TEG 9620
-
8/10/2019 Daily Activity HMI Upgrade TEG 9610-9620 Per November 5,2014
2/11
SITE VISIT REPORT FSR NAME
Andika Pratama
Yusup Armansyah
PT.Indoturbine 2/11
PT. IndoturbineDistributor of Solar Turbines
I. Purpose of visit
The purpose of visit is Technical Services for HMI Upgrade Centaur 50 (TEG 9610 & 9620) at NPU -
Total E&P Indonesie
II. Engine Specification:
Package Name Plate TEG 9610 & TEG 9620
Console Name Plate TEG 9610 & TEG 9620
Engine Name Plate TEG 9610 & TEG 9620
-
8/10/2019 Daily Activity HMI Upgrade TEG 9610-9620 Per November 5,2014
3/11
SITE VISIT REPORT FSR NAME
Andika Pratama
Yusup Armansyah
PT.Indoturbine 3/11
PT. IndoturbineDistributor of Solar Turbines
4 November, 2014
Trip from Balikpapan to Handil, prepare Hand Tools requirement
5 November, 2014
Trip from Handil to NPU Site
Pre Job Meeting with Control System team Total E&P
Check aviability for parts order
Functional verification Software HMI and accessories as per procedure
6 November, 2014
Pre Job Meeting with Control System Total E&P
Dismantle old HMI Configuration TEG 9610 Set up new configuration for TEG 9610
Meachining plat and make a hole to fitting the HMI display with TCP panel
Put new Cable Tag as per customer request
Verified Communication line between PLC and HMI working properly
7 November, 2014
Pre Job Meeting with Project Engineer and Control System Total E&P
Programming additional rung PLC 5 as per mandatory for Upgrade new HMI
Start to SAT Check functional test for communication throught existing PLC program for TEG 9610
8 November, 2014
Pre Job Meeting with Project Engineer and Control System Total E&P
Continue Commisioning Functional Test with Instrument Team
Commisioning done, continue with Start Engine as per sequence
9 November, 2014
Pre Job Meeting with Project Engineer and Control System Total E&P
Give a short training for new navigation HMI TT4000 ver 5 as per Customer request
Completed Handover Document and Dosier
Punch List pending per 9 November
Provide DB-25 angel connector
Update Drawing 70231-149480 as per new configuration
Provide antivirus McAfee (customer request) for TEG 9610 & TEG 9620
10 November, 2014
Trip to Balikpapan from Handil
-
8/10/2019 Daily Activity HMI Upgrade TEG 9610-9620 Per November 5,2014
4/11
SITE VISIT REPORT FSR NAME
Andika Pratama
Yusup Armansyah
PT.Indoturbine 4/11
PT. IndoturbineDistributor of Solar Turbines
Attached Pictures during the project
Configure PLC5 with new PLC5 program due to
mandotory Solar Inc. For upgrade HMI Verified all parts working properly.
Install New Operating System due to Serial Package
Number and OS License on HMI Hardware.
New HMI Display as per Solar Package
-
8/10/2019 Daily Activity HMI Upgrade TEG 9610-9620 Per November 5,2014
5/11
SITE VISIT REPORT FSR NAME
Andika Pratama
Yusup Armansyah
PT.Indoturbine 5/11
PT. IndoturbineDistributor of Solar Turbines
Short training for change mode to start produsction
mode or configuration mode
Perform SAT for TEG 9610 as per procedure
Configure TCP TEG 9610
Check and verify all function of existing system for
new HMI Display
Check all existing parts working prperly before HMI system installed on panel
-
8/10/2019 Daily Activity HMI Upgrade TEG 9610-9620 Per November 5,2014
6/11
SITE VISIT REPORT FSR NAME
Andika Pratama
Yusup Armansyah
PT.Indoturbine 6/11
PT. IndoturbineDistributor of Solar Turbines
Perform Commissioning as per procedure. Give a short training for operating new HMI with TT4000 ver 5
procedure
New wire configuration on TCP TEG 9610 for new HMI display with TT4000 ver 5
Handover Document & Dosier (a)
Handover Document & Dosier (b)
-
8/10/2019 Daily Activity HMI Upgrade TEG 9610-9620 Per November 5,2014
7/11
SITE VISIT REPORT FSR NAME
Andika Pratama
Yusup Armansyah
PT.Indoturbine 7/11
PT. IndoturbineDistributor of Solar Turbines
Handover Document & Dosier (c)
Found new program on HMI TT4000 ver 5 start crank button fuction visibilty was disable. Change with
new configuration to perform proper function due to PLC5 program.
Found new program on HMI TT4000 ver 5 stop crank button fuction visibilty was disable. Change with
new configuration to perform proper function due to PLC5 program.
-
8/10/2019 Daily Activity HMI Upgrade TEG 9610-9620 Per November 5,2014
8/11
SITE VISIT REPORT FSR NAME
Andika Pratama
Yusup Armansyah
PT.Indoturbine 8/11
PT. IndoturbineDistributor of Solar Turbines
Added 3 New Rung on Ladder 2 rung 2,3,4
Before change logix on ladder 11 rung 1
-
8/10/2019 Daily Activity HMI Upgrade TEG 9610-9620 Per November 5,2014
9/11
SITE VISIT REPORT FSR NAME
Andika Pratama
Yusup Armansyah
PT.Indoturbine 9/11
PT. IndoturbineDistributor of Solar Turbines
After change logix on ladder 11 rung 1
Added Logix and make new rung on ladder 11 rung 26
-
8/10/2019 Daily Activity HMI Upgrade TEG 9610-9620 Per November 5,2014
10/11
SITE VISIT REPORT FSR NAME
Andika Pratama
Yusup Armansyah
PT.Indoturbine 10/11
PT. IndoturbineDistributor of Solar Turbines
Added Logix and make new rung on ladder 11 rung 26 and change addres
Add rung and logix on ladder 143 last rung
-
8/10/2019 Daily Activity HMI Upgrade TEG 9610-9620 Per November 5,2014
11/11
SITE VISIT REPORT FSR NAME
Andika Pratama
Yusup Armansyah
PT.Indoturbine 11/11
PT. IndoturbineDistributor of Solar Turbines
ladder 34 still exist should be remove