DAB20702_BAB 2_PART 2.pdf
-
Upload
muhammad-fazlan-aliff -
Category
Documents
-
view
216 -
download
0
Transcript of DAB20702_BAB 2_PART 2.pdf
-
8/17/2019 DAB20702_BAB 2_PART 2.pdf
1/22
PAD FOOTING DESIGN AND
CONSTRUCTION PART 2
PREPARED BY AHMAD HAKIMI BIN MAT NOR
-
8/17/2019 DAB20702_BAB 2_PART 2.pdf
2/22
CONSTRUCTION OF PAD
FOOTING
Construction Plan
Using the authorized construction plan, contractor will locate
the location of the footing and begin the construction works.
Excavation Work, Concreting and Curing
• It is usual for the excavated surface of soil to be blinded with a
thin layer of lean concrete before the overlying structure work
takes place.
• If the ground is soft and the reinforcement is heavy, blinding
layer may need to be 150 mm thick, reinforced with mesh
reinforcement.
• Normal conditions blinding is 50-75mm thick grade 15 or 20
concrete, not reinforced, figure 2.1 illustrate this procedure.
-
8/17/2019 DAB20702_BAB 2_PART 2.pdf
3/22
Figure 2.1: Construction of blinding layer.
-
8/17/2019 DAB20702_BAB 2_PART 2.pdf
4/22
• In case of foundation constructed in the area where the ground
water level close to the surface, water pumped out so that the
construction work can be done, figure 2.1.
Figure 2.2: Blinding layer poured into the excavation after
water pumped out
-
8/17/2019 DAB20702_BAB 2_PART 2.pdf
5/22
• In case of several pad footing to be connected by an earth
beam there shall be room for the installation of earth adjacent
to the footing later on. Figure 2.3.
Figure 2.3: Location of earth beam between pad footing
-
8/17/2019 DAB20702_BAB 2_PART 2.pdf
6/22
• Concrete should only be poured directly against the ground is
unlikely to collapse into the excavation. Generally shuttering or
temporary formwork is erected on the blinding surface. Figure 2.4.
Figure 2.4: Construction of formwork for pad footing base
-
8/17/2019 DAB20702_BAB 2_PART 2.pdf
7/22
• At times, the steel column base with bolt is required to be
installed so as to make an easier installation of steel column
later on. Figure 2.5 show the bolt on the formwork before
concrete poured into the excavation.
Figure 2.5: Formwork with bolt as a base steel column installation
-
8/17/2019 DAB20702_BAB 2_PART 2.pdf
8/22
• Figure 2.6 show the schematic location of spacing block and
the whole pad footing construction.
Figure 2.6: Location of spacing block and the whole pad footing
-
8/17/2019 DAB20702_BAB 2_PART 2.pdf
9/22
-
8/17/2019 DAB20702_BAB 2_PART 2.pdf
10/22
Placing of Concrete• Some keys to successful placing concrete for foundation are as
follow:a) Timing- anticipating the time from completion of excavation until the
time for concreting for foundation shall proceed smoothly and rapidly
within the time period.
b) Labor-arranging for the necessary labor to be available for the period
of time required, including overtime needs.
c) Concrete supply-for smaller pours, concrete is to be mixed on site but
the necessary materials will halt concreting; for larger pours off site
mixing is preferable. Concrete mixed off site (ready-mixed or pre-
mixed) is convenient to use for pours up to 100 m3
d) Concrete distribution on site- the methods of distributing are; site
truck, concrete skip, conveyor and concrete pump.
-
8/17/2019 DAB20702_BAB 2_PART 2.pdf
11/22
-
8/17/2019 DAB20702_BAB 2_PART 2.pdf
12/22
Curing of the concrete footing• Normal practice of curing concrete is by spraying of water and
the use of polyethylene sheets.• In Malaysia, as practiced by many is the use of gunny sacks by
constructors for their availability and cheaper cost.
• Some constructors have introduced the method of spraying for
concrete curing.
-
8/17/2019 DAB20702_BAB 2_PART 2.pdf
13/22
Figure 2.8: Curing of concrete using poly-ethylene sheets
-
8/17/2019 DAB20702_BAB 2_PART 2.pdf
14/22
Figure 2.9: Curing of concrete by spraying
-
8/17/2019 DAB20702_BAB 2_PART 2.pdf
15/22
Preparation for steel reinforcement• Concrete reinforcement may take in the form of cage forming
at the bottom of the pad footing.
•
All reinforcement are to be arranged and hold up by spacer barat the correct distance. The bending of bar reinforcement is
specified by many codes such as BS 4466.
• All forms of reinforcement should be supported on spacer
bocks, figure 2.6.
PREPARATION OF
REINFORCEMENT BAR
-
8/17/2019 DAB20702_BAB 2_PART 2.pdf
16/22
• Some of the dimensions that normally used for reinforcement bar and wire mesh are as show in figure 2.30. typical of bending and bending radius of reinforcement is shown inifigure 2.31,
Figure 2.30: Sizes of reinforcement bar and wire mesh
-
8/17/2019 DAB20702_BAB 2_PART 2.pdf
17/22
Figure 2.31: Bending and bending radius
-
8/17/2019 DAB20702_BAB 2_PART 2.pdf
18/22
• The most useful quick reference is the Osha’s guide to the
construction engineerrs or the manual of safety by the CIDB
(Construction industry Development Board) Malaysia.
• The guide by RoSPA (1982) has subsections relating to
particular aspacts of site work, of which the following are
particularly relevent to foundation construction,
– General requirement ; safe working conditions; lighting; danger from
insecure structure; prevention from drowning; and explosives and
flammable materials. – Ladders
– Gangways, run and stairs
ON SITE SAFETY PROCEDURES
-
8/17/2019 DAB20702_BAB 2_PART 2.pdf
19/22
– Excavations, shafts, earthworks and tunnels
Note: especially on excavations, where a person may be liable to be
struck by a fall of earth from a greater height than 1-2m, are to be
inspected every day that persons are employed there, and that trenches
deeper than 2 m are to be inspected at the beginning of every shift.
Inspections must be made by a competent person.
– Scaffolding: very detailed regulation, followed by a section an special
types
–
Openings – Hoists.
-
8/17/2019 DAB20702_BAB 2_PART 2.pdf
20/22
• Concrete normally achieve its adequate strength after some period and depends on the type of cement used namely,ordinary Portland cement or the quick hardened.
• Removal of formwork is accomplished as soon as the concrete
reach the strength that enough to sustain its own weight withother loadings attached on them.
• However, concrete shall be given a minimum hardening periodto prevent it from broken during the removal of formwork.
• Table 2.1 shows minimum period of formwork removal from a particular part of a structure.
• Backfilling of the excavations is done as the concrete attainsstrength.
BACKFILLING
-
8/17/2019 DAB20702_BAB 2_PART 2.pdf
21/22
Location of formwork on
structure part
Normal Portland cement
(days)
Quick hardened Portland
cement (days)On the side of beam and
column without loading
3 2
With support under floor
slab
4 3
Without support underfloor slab
10 5
With support under beam 8 5
Without support under
beam
21 8
Table 2.1: Minimum period of removal
-
8/17/2019 DAB20702_BAB 2_PART 2.pdf
22/22