DAB20702_BAB 2_PART 2.pdf

download DAB20702_BAB 2_PART 2.pdf

of 22

Transcript of DAB20702_BAB 2_PART 2.pdf

  • 8/17/2019 DAB20702_BAB 2_PART 2.pdf

    1/22

    PAD FOOTING DESIGN AND

    CONSTRUCTION PART 2

    PREPARED BY AHMAD HAKIMI BIN MAT NOR

  • 8/17/2019 DAB20702_BAB 2_PART 2.pdf

    2/22

    CONSTRUCTION OF PAD

    FOOTING

    Construction Plan

    Using the authorized construction plan, contractor will locate

    the location of the footing and begin the construction works.

    Excavation Work, Concreting and Curing

    • It is usual for the excavated surface of soil to be blinded with a

    thin layer of lean concrete before the overlying structure work

    takes place.

    • If the ground is soft and the reinforcement is heavy, blinding

    layer may need to be 150 mm thick, reinforced with mesh

    reinforcement.

    •  Normal conditions blinding is 50-75mm thick grade 15 or 20

    concrete, not reinforced, figure 2.1 illustrate this procedure.

  • 8/17/2019 DAB20702_BAB 2_PART 2.pdf

    3/22

    Figure 2.1: Construction of blinding layer.

  • 8/17/2019 DAB20702_BAB 2_PART 2.pdf

    4/22

    • In case of foundation constructed in the area where the ground

    water level close to the surface, water pumped out so that the

    construction work can be done, figure 2.1.

    Figure 2.2: Blinding layer poured into the excavation after

    water pumped out

  • 8/17/2019 DAB20702_BAB 2_PART 2.pdf

    5/22

    • In case of several pad footing to be connected by an earth

     beam there shall be room for the installation of earth adjacent

    to the footing later on. Figure 2.3.

    Figure 2.3: Location of earth beam between pad footing

  • 8/17/2019 DAB20702_BAB 2_PART 2.pdf

    6/22

    • Concrete should only be poured directly against the ground is

    unlikely to collapse into the excavation. Generally shuttering or

    temporary formwork is erected on the blinding surface. Figure 2.4.

    Figure 2.4: Construction of formwork for pad footing base

  • 8/17/2019 DAB20702_BAB 2_PART 2.pdf

    7/22

    • At times, the steel column base with bolt is required to be

    installed so as to make an easier installation of steel column

    later on. Figure 2.5 show the bolt on the formwork before

    concrete poured into the excavation.

    Figure 2.5: Formwork with bolt as a base steel column installation

  • 8/17/2019 DAB20702_BAB 2_PART 2.pdf

    8/22

    • Figure 2.6 show the schematic location of spacing block and

    the whole pad footing construction.

    Figure 2.6: Location of spacing block and the whole pad footing

  • 8/17/2019 DAB20702_BAB 2_PART 2.pdf

    9/22

  • 8/17/2019 DAB20702_BAB 2_PART 2.pdf

    10/22

    Placing of Concrete• Some keys to successful placing concrete for foundation are as

    follow:a) Timing- anticipating the time from completion of excavation until the

    time for concreting for foundation shall proceed smoothly and rapidly

    within the time period.

     b) Labor-arranging for the necessary labor to be available for the period

    of time required, including overtime needs.

    c) Concrete supply-for smaller pours, concrete is to be mixed on site but

    the necessary materials will halt concreting; for larger pours off site

    mixing is preferable. Concrete mixed off site (ready-mixed or pre-

    mixed) is convenient to use for pours up to 100 m3

    d) Concrete distribution on site- the methods of distributing are; site

    truck, concrete skip, conveyor and concrete pump.

  • 8/17/2019 DAB20702_BAB 2_PART 2.pdf

    11/22

  • 8/17/2019 DAB20702_BAB 2_PART 2.pdf

    12/22

    Curing of the concrete footing•  Normal practice of curing concrete is by spraying of water and

    the use of polyethylene sheets.• In Malaysia, as practiced by many is the use of gunny sacks by

    constructors for their availability and cheaper cost.

    • Some constructors have introduced the method of spraying for

    concrete curing.

  • 8/17/2019 DAB20702_BAB 2_PART 2.pdf

    13/22

    Figure 2.8: Curing of concrete using poly-ethylene sheets

  • 8/17/2019 DAB20702_BAB 2_PART 2.pdf

    14/22

    Figure 2.9: Curing of concrete by spraying

  • 8/17/2019 DAB20702_BAB 2_PART 2.pdf

    15/22

    Preparation for steel reinforcement• Concrete reinforcement may take in the form of cage forming

    at the bottom of the pad footing.

    All reinforcement are to be arranged and hold up by spacer barat the correct distance. The bending of bar reinforcement is

    specified by many codes such as BS 4466.

    • All forms of reinforcement should be supported on spacer

     bocks, figure 2.6.

    PREPARATION OF

    REINFORCEMENT BAR 

  • 8/17/2019 DAB20702_BAB 2_PART 2.pdf

    16/22

    • Some of the dimensions that normally used for reinforcement bar and wire mesh are as show in figure 2.30. typical of bending and bending radius of reinforcement is shown inifigure 2.31,

    Figure 2.30: Sizes of reinforcement bar and wire mesh

  • 8/17/2019 DAB20702_BAB 2_PART 2.pdf

    17/22

    Figure 2.31: Bending and bending radius

  • 8/17/2019 DAB20702_BAB 2_PART 2.pdf

    18/22

    • The most useful quick reference is the Osha’s guide to the

    construction engineerrs or the manual of safety by the CIDB

    (Construction industry Development Board) Malaysia.

    • The guide by RoSPA (1982) has subsections relating to

     particular aspacts of site work, of which the following are

     particularly relevent to foundation construction,

     – General requirement ; safe working conditions; lighting; danger from

    insecure structure; prevention from drowning; and explosives and

    flammable materials. – Ladders

     – Gangways, run and stairs

    ON SITE SAFETY PROCEDURES

  • 8/17/2019 DAB20702_BAB 2_PART 2.pdf

    19/22

     – Excavations, shafts, earthworks and tunnels

     Note: especially on excavations, where a person may be liable to be

    struck by a fall of earth from a greater height than 1-2m, are to be

    inspected every day that persons are employed there, and that trenches

    deeper than 2 m are to be inspected at the beginning of every shift.

    Inspections must be made by a competent person.

     – Scaffolding: very detailed regulation, followed by a section an special

    types

     –

    Openings – Hoists.

  • 8/17/2019 DAB20702_BAB 2_PART 2.pdf

    20/22

    • Concrete normally achieve its adequate strength after some period and depends on the type of cement used namely,ordinary Portland cement or the quick hardened.

    • Removal of formwork is accomplished as soon as the concrete

    reach the strength that enough to sustain its own weight withother loadings attached on them.

    • However, concrete shall be given a minimum hardening periodto prevent it from broken during the removal of formwork.

    • Table 2.1 shows minimum period of formwork removal from a particular part of a structure.

    • Backfilling of the excavations is done as the concrete attainsstrength.

    BACKFILLING

  • 8/17/2019 DAB20702_BAB 2_PART 2.pdf

    21/22

    Location of formwork on

    structure part

    Normal Portland cement

    (days)

    Quick hardened Portland

    cement (days)On the side of beam and

    column without loading

    3 2

    With support under floor

    slab

    4 3

    Without support underfloor slab

    10 5

    With support under beam 8 5

    Without support under

    beam

    21 8

    Table 2.1: Minimum period of removal

  • 8/17/2019 DAB20702_BAB 2_PART 2.pdf

    22/22