CUTTING THE BRAID TO LENGTH AND MOUNTING OF...
Transcript of CUTTING THE BRAID TO LENGTH AND MOUNTING OF...
LHC Project Document No.
LHC-DCA-AP-0001 CERN Div./Group or Supplier/Contractor Document No.
AT/MEL/EM, HNINP
EDMS Document No.
592324
Date: 2005-05-18
the Large Hadron Collider project
CERN CH-1211 Geneva 23 Switzerland
Assembly Procedure
CUTTING THE BRAID TO LENGTH AND MOUNTING OF THE RESTRICTION FLANGE
ON A LINE-N CABLE SEGMENT Q7 SIDE
Abstract This document describes the procedure for cutting the braid to length and mounting of the restriction flange a 42-wire Line-N cable segment Q7 side.
Prepared by :
Montse Felip Slawomir Olek Olivier Desebe
Checked by :
Davide Bozzini Jean Philippe Tock
Approved by:
Davide Bozzini Boguslaw Prochal
Alain Poncet Stephan Russenschuck
LHC Project Document No.
LHC-
Page 2 of 43
History of Changes
Rev. No. Date Pages Description of Changes
08.11.2004
19.02.2007
-
43
First draft
Second draft prepared by Montse Felip
LHC Project Document No.
LHC-
Page 3 of 43
Table of Contents
1. INTRODUCTION.......................................................................................4 2. INITIAL PREPARATION ...........................................................................4 3. RELATED DOCUMENTATION.....................................................................5 4. CONCLUSIONS.......................................................................................32 5. REFERENCES..........................................................................................32 6. ANNEX A: TOOLING, COMPONENTS AND CONSUMABLE MATERIAL........33 7. ANNEX B: DETAILS OF PREPARATION OF THE HEAD-END OF THE LINE-N CABLE SEGMENT EQUIPPED WITH THE CONDUCTING PLUG ......................43
LHC Project Document No.
LHC-
Page 4 of 43
1. INTRODUCTION
This document describes the procedure for cutting the braid to length and mounting of the restriction flange a 42-wire Line-N cable segment Q7 side.
2. INITIAL PREPARATION
Before starting to cut the stainless steel braid and mounting the restriction plug on a new cable of a reel, an electrical insulation test of all conductors shall be carried out: the stainless steel braid, the central former and all conductors except one shall be connected to ground. This first measurement is used as reference for later electrical qualifications of manufactured segments. A voltage of 2 kV shall be applied to the free conductor and the leakage current is measured. Limit for the leakage current of each individual wire must not be above 4 µA per km. All conductors shall be tested by changing the electrical connections in turn (conductor under test at +2 kV, everything else connected to mass).
In the case that an error occurs during the plug manufacturing or if an electrical of mechanical fault is detected after its assembly the plug will be cut off and only 0.5 m of cable will be lost. Only if the plug has passed successfully the electrical tests, the cable is measured and then cut to the proper length.
LHC Project Document No.
LHC-
Page 5 of 43
3. DETAILED ASSEMBLY PROCEDURE
Step Description Reference/picture/drawing
1 From the dipole-Q7 side:
Pull the cables a distance of 275mm as shown.
2 From the Q7-DFBA side:
Mark the position 7mm from the extremity of the flange with a felt pen on the stainless steel braid.
This reference shows the position where the restriction plug will be located.
3 Mark a line at a distance of 2 cm
from the reference position.
This line shows where will be cut the stainless steel braid.
LHC Project Document No.
LHC-
Page 6 of 43
Step Description Reference/picture/drawing
4 From the Q7-DFBA side (working place):
Pull the cables (top and bottom) a distance of 10 cm.
Important: Pull out on both lines (600A and 6kA) equally.
5 From the Dipole-Q7 side:
Push the cables to make step 4 easier.
This pictures shows all the
references after pulling 10 cm.
6 Mark a line at a distance of 45 cm
from the 2 cm position.
This is where the cable bundle will be cut.
Put self-adhesive paper tape round the stainless steel braid at this position
LHC Project Document No.
LHC-
Page 7 of 43
Step Description Reference/picture/drawing
7 Cut the complete cable bundle on the 45 cm line which was marked in step 6.
8 Use a saw to do this operation
LHC Project Document No.
LHC-
Page 8 of 43
Step Description Reference/picture/drawing
9 Put the nut No 1(table 6.2, No 16) on the cable.
Put the stainless steel ring (table 6.2, No 18) on the polyethylene tube with a cone (table 6.2, No 14). Put the polyethylene tube with a cone on the cable
Put the nut No 2 (table 6.2, No 17) on the cable.
Pass a cord through the nut No 1
10 Tie the cord to the cables or
frame in order not to loose the nut assembly in the magnet tube.
LHC Project Document No.
LHC-
Page 9 of 43
Step Description Reference/picture/drawing
11 Carefully remove the stainless steel braid from the end of the cable over about 4 cm. Take care to avoid unrolling the polyester bedding tape. Use Stanley knife (table 6.1, No 10).
Secure the polyester bedding tape with the self-adhesive paper tape on the end of the cable.
12 Firmly secure the stainless steel
braid near the flange, with self-adhesive paper tape as shown.
To simplify cutting the braid, expand it by pushing it back from the end of the cable by a few centimetres.
Fix it with self-adhesive paper tape.
13 Cut off the stainless steel braid
along the marked line. Use sharp pliers (table 6.1, No 8) to ensure a clean cut.
LHC Project Document No.
LHC-
Page 10 of 43
Step Description Reference/picture/drawing
14 Remove the long loose part of the stainless steel braid.
15 Image just after to cut the
stainless steel braid
LHC Project Document No.
LHC-
Page 11 of 43
Step Description Reference/picture/drawing
16 Mark the extremity of the stainless steel braid on the polyester tape (position A).
17 Carefully push back the stainless steel braid about 10 cm from the reference line and fix it with self-adhesive paper tape.
Be careful to avoid damaging the end of the braid
18 Mark a line at a distance of 3 mm
from position A.
This will be the position of the Kapton® -self adhesive tape and of the Kapton® foil.
LHC Project Document No.
LHC-
Page 12 of 43
Step Description Reference/picture/drawing
19 Carefully push back the stainless steel braid about 10 cm from the reference line and fix it with self-adhesive paper tape.
Be careful to avoid damaging the end of the braid.
20 Shift the stainless steel braid 3 cm right. Be carefully to avoid devastation of the end of the stainless steel braid. Fasten the polyester tape with Kapton® self-adhesive tape at position B.
LHC Project Document No.
LHC-
Page 13 of 43
Step Description Reference/picture/drawing
21 Remove the self-adhesive paper tape from the end of the cable.
LHC Project Document No.
LHC-
Page 14 of 43
Step Description Reference/picture/drawing
22 Unwrap the polyester tape and cut it away just before the layer of Kapton® self-adhesive tape. Use scissors, (tab. 6.1, No 16).
LHC Project Document No.
LHC-
Page 15 of 43
Step Description Reference/picture/drawing
23 Unwrap and remove the Kapton® tape from the outer layer of insulated superconducting wires. Use scissors, (tab. 6.1, No 16).
Be very careful not to damage the insulation of the wires.
24 Prepare the Kapton® foil (table
6.2, No 19).
Attach 2 pieces of Kapton® self-adhesive tape to one end.
LHC Project Document No.
LHC-
Page 16 of 43
Step Description Reference/picture/drawing
25 Fix Kapton® foil (table 6.2, No 19) to the polyester bedding tape using Kapton self adhesive tape (tab. 6.2, No 13).
Roll the Kapton foil very tightly round the cable.
26 Fix it using Kapton self adhesive
tape.
LHC Project Document No.
LHC-
Page 17 of 43
Step Description Reference/picture/drawing
27 Move the stainless steel braid over the layers of Kapton® foil.
The end of the braid should be at about 5 mm from the end of the Kapton® foil.
Fix the braid with self-adhesive paper tape.
28 Mark position C at a distance of 5
mm from the end of the Kapton foil.
This will be the position of the thermal shrink sleeve.
29 Slide the thermal shrink sleeve A (table 6.2, No 9), over the stainless steel braid.
Remove the self-adhesive tape securing the stainless steel braid.
Slide back the thermal shrink sleeve until it is lined up with position C.
LHC Project Document No.
LHC-
Page 18 of 43
Step Description Reference/picture/drawing 30 Heat up the thermal shrink sleeve
with the hot-air gun and make it shrink to fit. Set temperature regulation knob to position 6. Heat from distance of about 5 cm during 30 seconds.
Make sure that the sleeve is aligned with position C before heating.
31 Remove the self-adhesive paper
tape from the stainless steel braid, near the flange.
LHC Project Document No.
LHC-
Page 19 of 43
Step Description Reference/picture/drawing 32 Put the flange (table 6.2, No 2)
on the cable.
Screw the nut No2 (tab. 6.2, No 17) into the flange.
While holding the flange with the special tool, tighten the nut using the dynamometric key No 32 (tab. 6.1, No 18).
Torque to be applied 80 Nm.
Special Tool
LHC Project Document No.
LHC-
Page 20 of 43
Step Description Reference/picture/drawing 33 Remove the string attached to nut
No1.
Slide the stainless steel ring with the polyethylene tube into nut No2 on the flange.
Slide nut No1 over the cable and polyethylene tube and screw it into nut No2.
Ensure that the two tapped holes on the flange are in the horizontal plane.
Again, holding the flange with the special tool, tighten nut N01musing the dynamometric key.
34 Torque to be applied 100 Nm
35 The image shows the two tools
used for the steps 33 and 34.
LHC Project Document No.
LHC-
Page 21 of 43
Step Description Reference/picture/drawing 36 Fix the flange to the tube.
Screws: stainless steel hexagonal head M
37 The two tapped holes shown
should be in the horizontal plane.
LHC Project Document No.
LHC-
Page 22 of 43
Step Description Reference/picture/drawing
38 Unwind and straighten the wires of the cable. The bending radius should not be smaller than 45°.
39 Slide the numbered labels on to
all the wires according the numbers printed on the Kapton® insulation. Position is at 10 cm from the wire extremity.
A trick to read the number on the Kapton® insulation:
- Find the two lines
- Read the number from the above the line to the line
LHC Project Document No.
LHC-
Page 23 of 43
Step Description Reference/picture/drawing
The image shows how to slide the labels with wire numbers on all wires.
40 Cut the multistrand Cu former at
the distance of 35 mm from the edge of shrinking sleeve A. Use front cutting pliers (tab. 6.1, No 6).
LHC Project Document No.
LHC-
Page 24 of 43
Step Description Reference/picture/drawing
41 Put sleeve C, length 15 mm (ZHTM-5/2.5) on the end of multistrand Cu former. Use tweezers, (tab. 6.1, No 7).
42 Heat up thermal shrinking sleeve
C. Sleeve should stick out 5 mm over the end of the multistrand Cu former (for details see annex C). Immediately proceed to the next step of the procedure.
43 Form the end of the sleeve C
using pliers (tab. 6.1, No 15) as is shown at the picture.
LHC Project Document No.
LHC-
Page 25 of 43
Step Description Reference/picture/drawing
44 Final image after Heat up thermal shrinking sleeve C.
45 Slide the labels with wire
numbers on all wires according to numbers printed on the Kapton insulation. Position is at 10 cm from the wire extremity.
46 Heat up the labels with numbers
of wires.
The sleeves must not be fully shrunk as they will be moved later.
LHC Project Document No.
LHC-
Page 26 of 43
Step Description Reference/picture/drawing
47 Cut the wires.Use cutting pliers (table 6.1, No.8)
48 Remove the Kapton insulation from all wire ends over a length of 15 mm using the stripping tool (table 6.1, No 12)
49 Make the continuity test and the high voltage test, if necessary (MEL).
LHC Project Document No.
LHC-
Page 27 of 43
Step Description Reference/picture/drawing
50 Fix the auxiliary support plate (tab. 6.2, No 4) to the connection board (table 6.2, No 3).
Fix the auxiliary support plate and the connection board to the support, (tab. 6.1, No 17). Use screwdriver (tab. 6.1, No 3) and screw M6 x 12.
Mount the connection board to the flange. Use hexagonal socket head screw M6x12 and hexagonal key No 5.
51 Separate the cables from the top
(about 8-10 cables).
Start with the cables from the bottom
52 Find the correct wiring diagram
for the interconnections being done (Fig. 6.10).
LHC Project Document No.
LHC-
Page 28 of 43
Step Description Reference/picture/drawing
53 Make cabling of the connection board. Put protective sleeves (table 6.2, No12) on all wires and put the wires into the corresponding slots according to the interconnection board layout (for details see [1-9]). Be aware of succession of slots on board. Operator situated in front of the board shall verify that the cable is on his left side. The volume of the bundle shall be limited in space.
54 Install the rear part of the
connection board to keep in place the bundle of wires.
LHC Project Document No.
LHC-
Page 29 of 43
Step Description Reference/picture/drawing
55 Install the rear part of the connection board to keep in place the bundle of wires.
56 Slide the labels to their position.
57 Slide the labels to their final
position of 30 mm from the end of wires.
LHC Project Document No.
LHC-
Page 30 of 43
Step Description Reference/picture/drawing
58 Cut the wires at a length of 55 mm for the top row and 70 for the bottom row. Length is measured from position E. Use cutting pliers (table 6.1, No. 8).
59 Remove the Kapton insulation from all wire ends over a length of 15 mm using the stripping tool (table 6.1, No 12).
LHC Project Document No.
LHC-
Page 31 of 43
Step Description Reference/picture/drawing
60 Slide the labels to their final position of 30 mm from the end of wires.
61 Soldering the wires from A to the
wires from B.
A
B
LHC Project Document No.
LHC-
Page 32 of 43
4. CONCLUSIONS
Mounting of the plug is a part of whole activity of manufacturing of the Line-N cable segments (for details see [10]). During manufacturing and the qualification tests of the segments ELQA SEG SW software will be used for supervising the process of the production (see [11]).
5. REFERENCES
[1] R. Solaz Cerdan “Slot assignment algorithm for the Electrical Interconnection Boards in the Line-N of the LHC Machine
[2] R. Solaz Cerdan “Line-N sector 1-2 boards”
[3] R. Solaz Cerdan “Line-N sector 2-3 boards”
[4] R. Solaz Cerdan “Line-N sector 3-4 boards”
[5] R. Solaz Cerdan “Line-N sector 4-5 boards”
[6] R. Solaz Cerdan “Line-N sector 5-6 boards”
[7] R. Solaz Cerdan “Line-N sector 6-7 boards”
[8] R. Solaz Cerdan “Line-N sector 7-8 boards”
[9] R. Solaz Cerdan “Line-N sector 8-1 boards”
[10] D. Bozzini, R. Herzog, R. Solaz Cerdan, „Line-N flexible cables from raw material to installation”
[11] L. Furman “SW for LINE-N segments preparation/manufacturing (ELQA seg sw v.1.0)”
LHC Project Document No.
LHC-
Page 33 of 43
6. ANNEX A: TOOLING, COMPONENTS AND CONSUMABLE MATERIAL
Table 6.1 lists all the tools required for the assembly procedure. In Table 2.2 the components needed for manufacturing of the one plug and consumable materials are summarised.
Table 6.1 Tooling
No Required tooling Description CERN SCEM
1 Hot-air gun Hot-air gun to make heat-shrinking sleeves shrink.
34.95.35.100.0
2 Wire stripper Tool for removing 15 mm of insulation at the extremities of wires.
34.95.62.090.2
3 Screwdriver Flat head screwdriver No 4 34.74.10.040.5
4 Set of hexagonal keys No 3, 4 and 5 34.72.75.302.4
5 Side cutting pliers Used for cutting of the superconducting ø 1,6 mm wires
34.76.45.120.9
6 Front cutting pliers Used for cutting of the auxiliary thinned copper line
34.95.64.160.7
7 Tweezers Length 150 mm 34.76.10.100.8
8 Scissors for cutting the Kevlar fibre
Scissors used for cutting of the stainless steel braid. Catalogue Radiospares code: 400-6080
9 Universal pliers Type Facom No 187-16 CPY 34.76.55.160.6
10 Stanley knife 34.78.54.099.6
11 Ball-and-socket joint vices
Used to hold the cable during various stages.
34.95.92.200.9
12 Holder for keeping the cable in vice
Cubic holder made of plastic with cylindrical hole, diameter 17 mm. Used before dressing of shield grid (see fig.7.6).
13 Tube Tube used for marking the length on the stainless steel braid of the cable (see fig.
14 Rear part of the connection board
Drawing LHCDCA__0002.
15 Flat pliers 34.76.15.160.6
16 Scissors 34.94.22.130.7
17 Polyethylene custom made support
See fig. 7.9.
18 Torque key No 30 Torque range 20-100 Nm.
19 Torque key No 32 Torque range 20-100 Nm.
LHC Project Document No.
LHC-
Page 34 of 43
Table 6.2 Consumable materials
No Required material Description Quantity CERN SCEM
1 Line-N superconducting 42-wire cable
Fig.7.2. About 54 m. Length depends on type of cable, (location in the LHC).
2 Flange of the conducting plug
Fig. 7.4. 1 piece
3 Connection board Fig.7.1., drawing LHCDCA__0003
1 piece
4 Auxiliary support plate Used for fixing board during wiring (see fig.7.8).
1 piece
5 Hexagon socket head cap screw M4 × 10
Made of stainless steel Cr.Ni.18.12.Mo. Used for fixing the auxiliary plate to the connection board.
1 piece 47.62.71.154.8
6 Self-adhesive crepe paper tape
19 mm wide About 1m 04.95.45.219.8
7 Labels for the wires Used for labelling of wires. Numbers from 1 to 42.
42 pieces
8 Labels for the cable Used for labelling the cable segment on the both extremities
2 pieces
9 Thermal shrink sleeve A 24-8, length 25 mm , with glue inside
1 piece Catalogue Radiospares, No 157-3903
10 Thermal shrink sleeve B ZHTM-34/17-0, 100 mm
1 piece 04.86.62.155.0
11 Thermal shrink sleeve C ZHTM-5/2,5 15mm 1 piece 04.86.62.110.3
12 Brown insulating glass-cloth tubing 600V, D 2 mm
Protective sleeve used during wiring of board
42 pieces 04.86.51.208.3
13 Self-adhesive Kapton tape
Width 19 mm 1 piece 04.94.70.100.3
14 Polyethylene tube See fig.
15 Hexagonal stainless steel screw M6x12
Used for fixing the auxiliary support plate to the flange
LHC Project Document No.
LHC-
Page 35 of 43
No Required material Description Quantity CERN SCEM
16 Nut No 1 Raccord inox a4 3/4" special
1 piece 41.40.31.499.0
17 Nut No 2 Lot ecrou bagues inox
1 piece 41.40.31.599.7
18 Stainless steel ring No 1 See fig 7.6. 1 piece
19 Kapton® foil 0.125 mm Kapton® foil. Size of the foil: 80 x 105 x 0,125 mm (for the cable made by Outokumpu®), 80 x 160 x 0,125 mm (for cable made by Vacuum Shmelzen®).
1 piece
LHC Project Document No.
LHC-
Page 36 of 43
Fig.6.1. Connection board
LHC Project Document No.
LHC-
Page 37 of 43
Fig.6.2. Cross section of the 42-wire superconducting cable (ø 17.0 mm – cable
made by Vacuum Schmelzen, ø 17.3 mm – cable made by Outokumpu)
Fig. 6.3.Polyethylene custom made tube with the cone.
LHC Project Document No.
LHC-
Page 38 of 43
Fig. 6.4. Flange of the conducting plug.
LHC Project Document No.
LHC-
Page 39 of 43
Dimensions: ØA = 21,10 mm, ØB = 17,60 mm, ØC = 18,95 mm, A=100,00 mm, B=10,00mm Fig. 6.5. Tube used for marking measured length on the circumference of the stainless steel braid of the cable
LHC Project Document No.
LHC-
Page 40 of 43
Fig. 6.6. Stainless steel ring No 1.
Quantity: 2 pieces.
Material: plastic
Fig. 6.7. Holder used for keeping the cable in the vice.
LHC Project Document No.
LHC-
Page 41 of 43
Fig. 6.8. Auxiliary support plate
Fig. 6.9. Support with fixed connection board used during cabling of the board.
LHC Project Document No.
LHC-
Page 42 of 43
Fig. 6.10. Wiring diagram
LHC Project Document No.
LHC-
Page 43 of 43
7. ANNEX B: DETAILS OF PREPARATION OF THE HEAD-END OF THE LINE-N CABLE SEGMENT EQUIPPED WITH THE CONDUCTING PLUG
Fig. 7.1. Preparation of the head-end of the Line-N cable segment equipped with theconducting plug.