Current Status of the KJRR Project and its Design · PDF fileCurrent Status of the KJRR...
-
Upload
truongthuan -
Category
Documents
-
view
214 -
download
1
Transcript of Current Status of the KJRR Project and its Design · PDF fileCurrent Status of the KJRR...
0
Nov., 17, 2014
Cheol PARK
Current Status of the KJRR Project
and its Design Features
1
Outline
Backgrounds
Project Overview
Design Overview
Concluding Remarks
2
Backgrounds
Counter measuring global shortage of Mo-99
To secure the supply of key RI demands for medical & industrial uses
Growing demand of NTD
To enlarge Si NTD services for power device market growth
Developing key RR technologies
To be competitive in the world RR market
For these aims, the KJRR project was launched on 1st Apr. 2012 and the planned schedule is 72 months from the conceptual design to commissioning.
3
Chronology
Mar. ‘10 : Pre-evaluation by MOSF*
Jul. ‘10 : Site Selection by a committee of MSIP
Jun. ’11 : Feasibility Study completed by KDI
Dec. ’11 : Budget approval by the National Assembly
Apr. ‘12 : Official Launching & Conceptual Design
Apr. ‘14 : 3rd FY Start & Detail Design
Nov. ‘14 : PSAR Preparation for CP Application
* MOSF : Ministry of Strategy and Finance MSIP : Ministry of Science, ICT and Future Planning KDI : Korea Development Institute
4
Project Overview
Project Name Ki-Jang Research Reactor (KJRR) Project
Owner KAERI (entrusted by Government)
Contractor (AE) Daewoo & KEPCO E&C Consortium (‘13.4 contracted)
Contractor (PC) To be later (in 2015)
Project Period Apr. 1, 2012 to Mar. 31, 2018 (72 months)
Site Ki-Jang District (near to Busan City)
Scope of Supply
▪ Design, Construction and Commissioning
- Reactor & Rx. building - RIPF and Research Facility - FM Production Facility with LEU target - Rad-Waste Treatment Facility
▪ Administration Buildings
5
U-Mo Plate Type Fuel (1st Application to RR)
– Unique technology : Atomization Technique
– Long fuel cycle, Low fuel consumption
Fission Mo Production Technology
– Development of F-Mo production process with LEU target
Bottom Mounted CRDM
– Easy-access to the core
NTD Hydraulic Rotation System (NTDHRS)
– Convenient utilization (by hydraulically rotating the Si ingot)
to enlarge the RR utilization capability
Key RR Technologies to be Developed
6
Project Organization
KAERI
Conceptual Design
Basic Design
Fuel Design /Supply
Licensing
Industry Eng. Company (KEPCO E&C & DW E&C)
Architect Eng.
Detailed Design
Construction
Construction
Commissioning
Vendors
RSA
MMIS
Component & Equip.
KAERI
Government Local
Government
International Collaboration
CRADA w/ INL
Cooperation w/IAEA
7
Project Budget
Plant Construction
RIPF & R&D Facility
LEU Target/FM Facility
Neutron Irradiation Facility
RTF
Fuel Design & Supply
License & Site Investigation
Site (130,000 m2)
Infra-Structure
Entrance Road (two-lane)
Elec.Supply(154kV, 20MVA-2)
Water Supply(1,200t/day)
8
Project Schedule Project Schedule
※ Schedule depends on the budget, technology development etc.
Licensing
Conceptual
Design Detailed Design & SAR
2012 2013 Activities 2014 2015 2016
Design of
Rx & Facility
Site Selection
&
Construction
Installation
Licensing
Output
SIR
SER
RER
PSAR & CP
Construction
RX Installation
System Utilization
CAT/SPT/IST & OL
RIT/Power Ascension
CDRM development & Fuel Qualification Test
Site
Preparedness
Excavation & Construction
Site
Investigation
Commiss.
& Operation
Procurement, Fabrication and Installation
Commissioning
Procedures
Operator Training
CAT/SPT/RPT Normal
Operation
RI Production
Irradiation
service
First
Critical
2018 2017
Basic
Design
9
Utilization
Radioisotope Production
Mo-99 (To meet national demand increasing year by year)
I-131, I-125, Ir-192
Co-60, P-33, Re-186, Sm-153
Silicon & Wafer Doping
5 NTD Holes for Irradiation of Si Ingot with 6” - 12“
1 Hole for Fast Neutron Irradiation of Si Wafer with 8”
R&D
PTS & HTS
Neutrino Test Station
10
Power ~15 MW
Type Open Tank in Pool type
Max. thermal neutron flux (n/cm2s)
> 3.0x1014 (Central Trap)
Operation day ~300/year
Life time 50 year
LEU Fuel U-7Mo plate type (U loading : 6.5, 8.0 g/cc)
LEU Target UAlx plate type (2.6 g/cc)
Reflector Be , Gr
Coolant and flow direction in operation
H2O, Downward forced convection flow
Reactor building Confinement
Decay heat cooling Passive System
Robust Design, 0.3g SSE, Digital I&C, Cyber Security
KJRR Specification
11
Site (1/3)
Easy Access through International Airport, Port, Highway
12
Site (2/3)
The site was selected through competitions among 9 local governments that have expressed their wishes to host the KJRR.
The site is very close to Busan which is the second largest city in Korea and has an international airport and a harbor which provide good accessibility as well as easy transportation of products.
The site is very close to several existing NPPs in operation. Thus, it is expected that there is no difficulty in the site characteristics including PA.
13
Site (3/3)
Leveling of the site for construction started in July, 2014.
Location of Reactor Assembly
Meteorological Tower (from June, 2014)
14
General Arrangement
FM & RI production area Reactor area
- accessibility, mobility, usability, safety, economy etc.
15
Pool Arrangement
16 16
Reactor Assembly
Upper Guide
Structure
Core Box
Reflector
Assemblies
Expansion Joint
Assembly Reactor Cover
Assembly
Outlet Plenum
Neutron Detector
Housing Assembly
Grid Plate
Refueling Cover Rx. Assembly
Rx. Structure assembly
- flow path, support structures
Fuel assemblies
Reflectors
CRDM/SSDM below the Rx.
- 4 CRDM : motor-driven
- 2 SSDM : hydraulically driven
17 17
CRDM/SSDM Development (1/2)
CRDM/SSDM
Being developed
Qualification test schedule
Completed all key components development : Oct., 2014
Test facility for performance and endurance tests : Dec.2014
Manufacturing of Q Class Prototype CRDM/SSDM : May. 2015
Performance and endurance tests of CRDM/SSDM : June to Dec., 2015
Test facility for seismic test : Mar.2016 Seismic tests of CRDM/SSDM : Mar. to
June.2016
Follower Fuel Assembly (FFA)
CAR/SSR Assembly
ES adapter
Extension Shaft (ES)
CAR/SSR Extension Shaft Assembly (ESA)
CRDM/SSDM Seal Valve Assembly
CRDM/SSDM Connector Assembly
RC Electromagnet Assembly
Armature Guide Tube Assembly
CRDM Drive Assembly
18 18
CRDM/SSDM Development (2/2)
Prototype Control Rod Prototype Control Rod Guide Tube
Electromagnet & Test Equipment
Extension shaft adapter
CRDM Assembly
CR Control System
19 19
Core
Core Box Configuration
SFA(16)+FFA(6) in 7x9 lattice
- Same shape of SFA and FFA
for flexibility in core management
Fission Mo target (6)
3 flux traps
9 IRs with on-power loading
PTS, HTS etc.
Fuel Assembly Fission Mo Target
Fuel Plate type (Typical MTR type fuel)
- 21 plates & 22 flow channels
Fuel meat : U-7Mo/Al-5Si
- 6.6 & 8.0 gU/cc
Low fuel consumption
Fission Moly target : U-Alx
- 2.5 gU/cc
Core Configuration
SFA
FFA
20
U-Mo Fuel Qualification
Test Report
Irradiation & PIE at HANARO
& INL
Mechanical Characteristics
Flow test
A Prototype FA Irradiation & PIE
Mini/Full length Plates
Irradiation & PIE
Plate wise Irradiated data
Manufacturing Properties
KJRR SAR
Input to RERTR
Finished in Mar. 2015
Tests with 16 mini-plates (will finish in June 2017)
Tests with full scale FA (will start in Apr. 2015)
21 21
Design Variable Design Values
Core power (fission, MW)
No. of Standard Fuel Assembly
No. of Follower Fuel Assembly
No. of fuel plates/assembly
No. of FM target plates/assembly
Core inlet temperature (℃)
Core outlet temperature (℃)
Flow direction
Core flow rate (kg/s)
- Fuel cooling channel
- Fission Mo target channel
- Gap flow
Core pressure (kPa)
- Fuel inlet
- Pressure drop of fuel assembly
Average core flow velocity (m/s)
- SFA/FFA
- Fission Mo target
Average heat flux FA/FM (MW/m2)
15.0
16
6
21
8
35.0
41.3
Downward
535.0
432.8
47.6
54.6
180
86
6.0
7.5
0.415/0.748
Normal Operating Conditions
Core Inlet
Core Outlet
FFA
Thermal Hydraulic Design
22 22
Cooling Systems
PCS
SCS
PWMS
HWLS
SRHRS
- Decay heat removal
at PCS pumps unavailable
NTDHRS
- Rotating hydraulically Si ingot and cooling reflector & target
HX
HX
Siphon Break Valves
PCS
HWLS
SCSA
A
A
Flap valve
HX
AFilter
Air
Standby
Reactor Pool
ServicePool
POOL WATER
STORAGE TANK
LRM
S
DWSTRx
IX
IXSRMS
Heater
Heater
SWS
Spent FuelStorage
PoolSRHRS
S
S
Demi water supply
Standby
Standby
Standby Standby
NTDHRS
HX
PWMS
SCS
SCS
IX
IX
SRMS
SRMS
SRMS
SRMS
StandbyM
M
M
M
SRMS
SRMS
SRMS
Filter
DECAY T
AN
K
M
M
M
M
Filter
Filter
Filter
23 23
I&C Configuration
For Control, Protection, and Monitoring of Reactor Facility
RPS, RRS, PAMS, APS, ASTS, RASS, MCR, SCR, PICS etc…; commensurating with classifications
Digital technology is applied
24
Birds-eye View
25
Concluding Remarks
Through the KJRR project,
Contribution to the Nation
Self sufficiency in terms of medical and industrial RI supply
Enlarging and vitalizing the power device industry and RI industry
Contribution to the World
First qualification & application of U-Mo fuel for RRs
Increase of medical RI supply capacity in the world
Sharing the knowledge and experience from the KJRR
26
Thank You !!!