Current status of NPP C&I in the United Kingdom - iaea.org · PDF fileCurrent status of NPP...
-
Upload
hoangthuan -
Category
Documents
-
view
214 -
download
1
Transcript of Current status of NPP C&I in the United Kingdom - iaea.org · PDF fileCurrent status of NPP...
TWG-NPPIC, May 2013, Vienna: UK status 1
Current status of NPP I&C in the
United Kingdom
T P Smyth
AMEC, Knutsford, Cheshire, UK
24th Meeting of the Technical Working Group on Nuclear Power
Plant Instrumentation and Control, 22-24 May 2013, Vienna
TWG-NPPIC, May 2013, Vienna: UK status 2
Current status of NPP I&C in the United Kingdom
Nuclear Power Plants in the UK
I & C Modernization projects
Regulatory Environment
New build I & C status
Fukushima response
Recommendations
Hinkley Point B
TWG-NPPIC, May 2013, Vienna: UK status 3
Nuclear Power Plants in the UK (1)
2023 1976 2 x 610 MWe AGR
2023 1976 2 x 610 MWe AGR Hunterston B
Expected
shutdown
Start
operation Unit capacity Type Reactors
10 038 MWe Total (19)
2035 1995 1 x 1188 MWe PWR Sizewell B
2023 1988 2 x 625 MWe AGR Torness
2023 1988 2 x 615 MWe AGR Heysham 2
2019 1985 2 x 580 MWe AGR Heysham 1
2019 1984 2 x 595 MWe AGR Hartlepool
2018 1983 2 x 545 MWe AGR Dungeness B
Sept 2014 1971 1 x 490 MWe Magnox Wylfa 1
TWG-NPPIC, May 2013, Vienna: UK status 4
Nuclear Power Plants in the UK (2)
Electricity sources 21% nuclear (2011: 18%) 28% gas (2011: 44%) 43% coal (2011: 28%) 8% other
Need to plan for energy replacement 8 plants (15 reactors) will close in next 10 years 8850 MWe
New build Generic Design Assessment (EPR, AP1000, ABWR)
Areva/EdF EPR GDA complete Dec 2012
Westinghouse AP1000 GDA suspended
GE-Hitachi ABWR started Apr 2013
http://www.hse.gov.uk/newreactors/
TWG-NPPIC, May 2013, Vienna: UK status 5
Nuclear Power Plants in the UK (3)
New build Sites EdF Energy
2 x EPR at Sizewell
2 x EPR at Hinkley Point.
Bradwell site.
Horizon Nuclear Power (Hitachi) Oldbury and Wylfa sites.
GE-Hitachi ABWR.
NuGeneration (Iberdrola, GDF Suez) Sellafield site.
Total planned power ±19 GWe
TWG-NPPIC, May 2013, Vienna: UK status 6
Nuclear Power Plants in the UK (4)
SELLAFIELD
HINKLEY POINT
SIZEWELL
BRADWELL
OLDBURY
WYLFA
TWG-NPPIC, May 2013, Vienna: UK status 7
I&C Modernization projects (1)
Dungeness B
New DPS being installed
ATOS Worldgrid (ADACS)
Westinghouse (ABB AC160)
Control / equipment protection functions segregated
Lower integrity parts separated from higher integrity parts
Commissioning phase, operating in parallel with existing DPS.
TWG-NPPIC, May 2013, Vienna: UK status 9
I&C Modernization projects (3)
Neoprene insulation degradation Magnox, Oldbury power station
Shutdown Feb 2012
44 years operation
Degradation with age
Perishing
Sweating
Hygroscopic
Becomes conductive - resistance < 1 MΏ
Stray currents in sensitive circuits
Thermocouple amplifiers
TWG-NPPIC, May 2013, Vienna: UK status 10
I&C Modernization projects (4)
Neoprene insulation degradation
TWG-NPPIC, May 2013, Vienna: UK status 11
I&C Modernization projects (5)
Neoprene insulation degradation Hunterston B
Boiler Protection Temperature Trip Units replacement
Hartlepool
Feed Flow Y trip units and pressure transducers replacement
Heysham 1
Feed Flow Y trip units and pressure transducers replacement
Duplicate Reactor Low Pressure Trip Units replacement
Obsolescence
30 years old
TWG-NPPIC, May 2013, Vienna: UK status 12
Regulatory Environment (1)
Standards hierarchy ONR Safety Assessment Principles & Technical Assessment
Guides (http://www.hse.gov.uk/nuclear)
IAEA & IEC standards IEC 61226
Modern standards reviews Design, Operation and Maintenance
Part of Periodic Safety Reviews
PSA based assessment
Limit of reliability claims for software based systems
10-4failures/demand claim limit
TWG-NPPIC, May 2013, Vienna: UK status 13
Regulatory Environment (2)
Application to Sizewell B Primary Protection System
Four channels, 2 out of 4 tripping
Software based Production excellence IEC 60880
Independent confidence building Extensive testing Independent code safety assessment
Secondary Protection System Four channels, 2 out of 4 tripping
Protection for frequent faults
Laddic – magnetic amplifiers Diverse technology
TWG-NPPIC, May 2013, Vienna: UK status 14
Regulatory Environment (3)
New Build, in general, same regulatory requirements as Sizewell B Diversity requirements in reactor protection systems
Possibly less onerous protection system targets Passively safe systems will make fewer demands
Common regulatory position Licensing of safety critical software for nuclear reactors:
Common position of seven European nuclear regulators and authorised technical support organisations. BEL V, Belgium ONR, United Kingdom BfS, Germany SSM, Sweden CSN, Spain STUK, Finland ISTec, Germany
1.13 Software reliability 1.13.3.1: Reliability claims for a single software based system
important to safety of lower than 10-4 probability of failure (on demand or dangerous failure per year) shall be treated with extreme caution.
TWG-NPPIC, May 2013, Vienna: UK status 15
GDA of UK EPRTM I&C (1)
GDA Regulatory Issue on UK EPRTM I&C GDA Step 3 The complexity of interconnectivity between the very
important Class 1 Safety Systems and lower Safety Class control systems. Of particular concern was that the lower Classes 2 and 3 Systems could have write access to the highest Class 1 Safety System (the main Reactor Protection System). This also challenged our important safety assessment principle that Safety Systems should be completely independent of control systems.
There was a lack of Class 1 equipment including hard-wired and simple technology as a diverse backup to the highly computerised and sophisticated screen based displays and controls in the Main Control Room and Remote Shutdown Station.
Substantiation of the reliability claims for the computer-based Systems Important to Safety.
TWG-NPPIC, May 2013, Vienna: UK status 16
GDA of UK EPRTM I&C (2)
Resolution All networked communications will be one-way, from the
Class 1 systems to lower Class 2 and 3 systems. The permissive signals that were to be implemented through the lower Class systems will now be implemented using Class 1 Safety Information and Control System (SICS) equipment including a Qualified Display System.
There will be a Class 1 SICS operational in the Main Control Room and a similar panel in the Remote Shutdown Station. The SICS will include simple hard-wired technology and will be fully operational for alarms and displays at all times.
Probabilistic claims on each of the main I&C platforms will have lower limits than in the original design for the UK. The shortfall in overall reliability of the safety systems will be made up by the introduction of a Non-Computer-Based Safety System (NCSS).
TWG-NPPIC, May 2013, Vienna: UK status 17
GDA of UK EPRTM I&C (3)
GDA Step 4 Completion of Step 3 I&C issues: categorisation of functions,
classification of systems, compliance to IEC I&C nuclear standards.
Claims-Arguments-Evidence (CAE) based review against the SAPs
Review of the principal design and implementation standards for I&C Class 1, 2 and 3 equipment. Sampling of detailed evidence predominately focused on the Class 1 systems (e.g. reactor protection) and the key Class 2 systems.
Review of safety case for the Class 1 and key Class 2 platforms and pre-developed components using appropriate guidance and standards. Development of application code, independent verification and validation, and Independent Confidence Building Measures.
Further review of the I&C architecture including provisions for defence-in-depth, independence and diversity, automatic and manual safety actuations, and appropriateness of equipment class.
TWG-NPPIC, May 2013, Vienna: UK status 18
GDA of UK EPRTM I&C (4)
GDA Step 4 Cross-cutting issues
Safety Categorisation and Classification – Alignment with IEC61226.
Smart devices.
ONR Design Acceptance Confirmation Dec 2012
5 year program
~£35 million
TWG-NPPIC, May 2013, Vienna: UK status 21
Fukushima response (1)
Progress Interim report – May 2011
Final report – Oct 2011
European Council "Stress Tests” – Nov 2011
ONR Fukushima Implementation Report – Oct 2012
Implications for New Build Additional GDA issue
TWG-NPPIC, May 2013, Vienna: UK status 22
Fukushima response (2)
Sizewell B Emergency Response Centre 1.6km away from power station
PWR emergency actions require quicker implementation than for AGR type reactors.
Backup Emergency Control Centre
AGR reactors Three regional depots
TWG-NPPIC, May 2013, Vienna: UK status 23
Fukushima response (3)
UK EPRTM Enhancements Extension of severe accident battery storage capability from 12
to 24 hours
Establishment of a communication system suitable for operation under a total loss of electrical power situation - a network of sound-powered telephones
Qualifying the performance of instrumentation required for monitoring containment integrity and in the spent fuel cooling pool
Provision of means for re-powering the dedicated Severe Accident Instrumentation and Control equipment
Extension of SBO diesel generator autonomy by using mobile pumping of the main emergency diesel generator fuel tanks to recharge the SBO diesel generator fuel tanks
Provision of equipment and means (connection point etc.) to re-supply significant electrical power from three days post-event
Provision of a high power mobile emergency generator capacity
TWG-NPPIC, May 2013, Vienna: UK status 24
Recommendations (1)
IAEA topics
Estimating and extending life of I&C equipment to
address ageing and obsolescence.
Supporting the evaluation, acceptance and licensing of
digital I&C system.
Lessons learned from I&C project implementation:
guidance for modernisation and new plant projects.
TWG-NPPIC, May 2013, Vienna: UK status 25
Recommendations (2)
IAEA topics (cont.)
Design and management of I&C systems for future
upgrading This relates to the problem of the much shorter life that can be
expected from I&C systems in comparison to that of NPPs.
It is proposed that the 'research' could address: the techniques that may be used at the design stage to promote
future upgrading,
the measures that would also be needed to ensure that the ability for future upgrading is retained,
the experience available of adopting such techniques and measures, recommendations to I&C system specifiers, I&C system suppliers
and NPP operators arising from the above.
TWG-NPPIC, May 2013, Vienna: UK status 26
References (1)
ONR New build website: http://www.hse.gov.uk/newreactors/
Integration testing of safety-related systems: Lessons learnt from Dungeness B DPS replacement project, System Safety 2010.
Licensing of safety critical software for nuclear reactors. Common position of seven European nuclear regulators and authorised technical support organisations. 2010. http://www.hse.gov.uk/nuclear/software.pdf
UK EPRTM Control and Instrumentation (I&C) Architecture Regulatory Issue RI-UKEPR-0002 http://www.hse.gov.uk/newreactors/ri-ukepr-0002.pdf http://www.hse.gov.uk/newreactors/closure-of-regulatory-issue.pdf
UK EPRTM I&C Architecture http://www.epr-reactor.co.uk, PCSR chapter 7, Appendix 7A.
UK EPRTM I&C Architecture. UKEPR-0002-072 Issue 04. http://www.epr-reactor.co.uk, PCSR chapter 7.2.
UK Office for Nuclear Regulation. GDA Step 4 and Close-out for Control and Instrumentation Assessment of the EDF and AREVA UK EPR™ Reactor
TWG-NPPIC, May 2013, Vienna: UK status 27
References (2)
UK Office for Nuclear Regulation. Japanese earthquake and tsunami: Implications for the UK nuclear industry. Interim Report. May 2011.
UK Office for Nuclear Regulation. Japanese earthquake and tsunami: Implications for the UK nuclear industry. Final Report. September 2011.
UK Office for Nuclear Regulation National Final Report on European Council “Stress Tests” for UK Nuclear Power Plants. December 2011
EDF Energy NNB GenCo response to recommendations in ONR Chief Inspector’s Report (June 2012), NNB-OSL-REP-001450.
UK Office for Nuclear Regulation “Japanese earthquake and tsunami: Implementing the lessons for the UK's nuclear industry” October 2012
UK Office for Nuclear Regulation. UK ONR ENSREG Related ‘National Action Plan’ Dec 2012.
Sizewell B ERC image: http://www.bbc.co.uk/news/uk-england-suffolk-17905186
Map: http://openstreetmap.org