CTC Global Presentation Partner Meet May 2015
-
Upload
stephen-jackman -
Category
Documents
-
view
589 -
download
2
Transcript of CTC Global Presentation Partner Meet May 2015
![Page 1: CTC Global Presentation Partner Meet May 2015](https://reader033.fdocuments.us/reader033/viewer/2022051502/58d0e96e1a28abba558b5a19/html5/thumbnails/1.jpg)
Steve Jackman CTC Global Corporation
May 2015
![Page 2: CTC Global Presentation Partner Meet May 2015](https://reader033.fdocuments.us/reader033/viewer/2022051502/58d0e96e1a28abba558b5a19/html5/thumbnails/2.jpg)
Overview
• Utilities have historically used steel cores for their transmission lines, a technology that is over 100 years old. CTC’s advanced composite cores are lighter weight, incorporate additional conductive aluminum that allows for the transmission of electricity more efficiently.
• CTC received key patents between 2006 and 2007 (patents registered in over 70 countries)
• Commercial production of ACCC transmission line began in 2006 and there are now 25,000+ km being used at over 325 locations in 30 countries. Strong ACCC® brand recognition.
2 ctcglobal.com | All rights reserved.
28% more Aluminum Composite Core Steel
Core
Aluminum
28% more Aluminum
Composite Core ACCC® Conductor Tradi7onal ACSR
Steel Core
Aluminum
• CTC Global (“CTC”) manufactures leading edge conductor core and ancillary parts used in electrical transmission lines. ACCC ® Brand.
• Privately held Delaware corporation with headquarters in Irvine, CA USA.
• CTC’s Irvine, CA production facility has 100 employees and is ISO 9001:2008 certified
• World Market
• Over 67 million kilometers of transmission and distribution wires installed globally
• ~$10B annual demand for new and reconductor transmission lines. Distribution lines are nearly 3X that amount
![Page 3: CTC Global Presentation Partner Meet May 2015](https://reader033.fdocuments.us/reader033/viewer/2022051502/58d0e96e1a28abba558b5a19/html5/thumbnails/3.jpg)
Unmatched Global Experience 25,000+ km at over 325 project sites
Over 35,000 Dead-Ends & Splices in Use
Countries:
• USA • China • France • UK • Poland • Spain • Portugal • Mexico • Chile • Qatar • Indonesia • Belgium • Brazil • Germany • South Africa • South Korea • Russia • India • Costa Rica • Columbia • Congo • Mozambique • Netherlands • Nigeria • Vietnam • Malaysia
US Utilities:
• AEP • APS • PacifiCorp • NV Energy • Austin Energy • Xcel Energy • MI PUD • KS PUD • KAMO • OG&E • Ozark Electric • WAPA • STEC • Entergy • Riverside PUD • Florida Power & Light • Keys Energy • Progress Energy • Mohave Electric • SCANA • National Grid • Alexandria (LA) PUD • Duke Energy • Oncor • CIPCO • Black Hills Power • Com Ed • TECO • Leesville Gas
3 ctcglobal.com | All rights reserved.
![Page 4: CTC Global Presentation Partner Meet May 2015](https://reader033.fdocuments.us/reader033/viewer/2022051502/58d0e96e1a28abba558b5a19/html5/thumbnails/4.jpg)
Challenges Facing Transmission Owners
• Sag violations and Increasing capacity requirements
• Tower replacement
• Right of Way, Community opposition
• Shortening Construction Schedules
• Meeting Environmental Goals and Access to Renewable Energy
• Increasing capacity requirements (load growth)
• Reliability Improvement – Adequate capacity in N-1 scenarios
• Cost and finance of projects
• Efficiency and losses – Impact on Generation
5/11/15
![Page 5: CTC Global Presentation Partner Meet May 2015](https://reader033.fdocuments.us/reader033/viewer/2022051502/58d0e96e1a28abba558b5a19/html5/thumbnails/5.jpg)
Greater Strength & Reduced Sag
Higher Ampacity Limits at Cooler Temperatures
Able to Tolerate N-1 Conditions
Increased Spans on Fewer / Shorter Structures
Proven Reliability with Reduced Line Losses
Selected as the Most Cost Effective Solution
ACCC has been installed by over 130 utilities worldwide
10 years of Installation & Operating Experience
ACCC Conductor Attributes
![Page 6: CTC Global Presentation Partner Meet May 2015](https://reader033.fdocuments.us/reader033/viewer/2022051502/58d0e96e1a28abba558b5a19/html5/thumbnails/6.jpg)
AEP has commissioned the largest energized reconductor project ever – for any conductor type
The project is 386 circuit Km (240 circuit miles) in length double bundled 345kV – total conductor length over 2300 Km
The transmission line is a critical link to South Texas and is so heavily loaded it cannot be taken out of service to replace the conductor in a conventional manner
Energized reconductoring with ACCC® conductor provides an immediate increase in capacity to relieve congestion without new construction
No tower replacements, minimal crossarm replacements due to corrosion – line is 30 years old
Multi-year project started in September 2012 and will complete in 2015
World’s Largest Energized Reconductor Project
AEP is one of the largest electric u3li3es in the U.S., delivering electricity to more than 5 million consumers in 11 states. The u3lity has extensive experience building extra-‐high-‐voltage 765-‐kV transmission lines and owns the na3on’s largest electricity transmission system, a nearly 62,000-‐kilometer network that includes 3,360 of 765-‐kV transmission lines, more than all other U.S. transmission systems combined
Designed Specifically to Use ACCC® Conductor
![Page 7: CTC Global Presentation Partner Meet May 2015](https://reader033.fdocuments.us/reader033/viewer/2022051502/58d0e96e1a28abba558b5a19/html5/thumbnails/7.jpg)
24x7 power to every Indian by 2019
• “The Prime Minister’s vision for 24/7 quality power for all depends on the transmission and distribution sector to reach the bottom of the pyramid. With the new technologies we are bringing in, we will now create an ambitious grid programme which will meet the country’s demand,” – Mr Piyush Goyal, Power Minister at 5th International Exhibition and Conference Gridtech 2015
• Country's power sector is set for $250 billion investment across different segments which includes $50 billion for T&D over next 5 years (13th Five Year Plan).
• According to Government of India’s report (draft) “Perspective Transmission Plan for Twenty Years (2014-2034)”, in view of the increasing constraint in getting Right-of-Way for transmission lines, efforts need to be put to build these corridors only with high capacity transmission lines viz. HVDC, 765kV D/c line, 400kV D/c with high capacity conductor, etc.
ctcglobal.com | All rights reserved. 7
![Page 8: CTC Global Presentation Partner Meet May 2015](https://reader033.fdocuments.us/reader033/viewer/2022051502/58d0e96e1a28abba558b5a19/html5/thumbnails/8.jpg)
Co-creating Values for Indian Power Transmission Network Providers
• Grid Efficiency & Right of Way; India’s biggest T&D hurdles. ACCC acceptance helping utilities to tackle with these problems.
• Efficiency benefits; conductor loss reductions up to 35% expected thereby offering unmatched ROIs. (Reducing line losses also frees-up generation capacity that is otherwise lost)
• From 33kV to 220kV; power transmission capacity enhancements done for private utilities and customers like Tata Power, Torrent Power, Cairn Energy
• State owned transmission utilities of Karnataka, Uttar Pradesh, West Bengal and Maharashtra also adopt ACCC for higher power transfer needs.
• Playing vital role in de-congestion of Delhi’s transmission lines through ACCC; selected by Powergrid Corporation of India Ltd.
• Jointly developing training programs and expert agencies for smooth deployment of the technology through skilled/semi skilled linesman.
• Distribution segment still bleeds most of the country’s aggregated T&D losses which is today at around 25% level. ACCC through its unmatched efficiency benefits can not only decongest the overloaded lower voltage lines but can significantly reduce I2R losses.
ctcglobal.com | All rights reserved. 8
![Page 9: CTC Global Presentation Partner Meet May 2015](https://reader033.fdocuments.us/reader033/viewer/2022051502/58d0e96e1a28abba558b5a19/html5/thumbnails/9.jpg)
ACCC Installations in India
ctcglobal.com | All rights reserved. 9
![Page 10: CTC Global Presentation Partner Meet May 2015](https://reader033.fdocuments.us/reader033/viewer/2022051502/58d0e96e1a28abba558b5a19/html5/thumbnails/10.jpg)
Worldwide ACCC Installations
ctcglobal.com | All rights reserved. 10
![Page 11: CTC Global Presentation Partner Meet May 2015](https://reader033.fdocuments.us/reader033/viewer/2022051502/58d0e96e1a28abba558b5a19/html5/thumbnails/11.jpg)
“ACCC conductor receives wide acceptance as a solution to decongest overloaded lines in urban/semi urban areas of India”
![Page 12: CTC Global Presentation Partner Meet May 2015](https://reader033.fdocuments.us/reader033/viewer/2022051502/58d0e96e1a28abba558b5a19/html5/thumbnails/12.jpg)
Torrent Power – 132 kV – ACCC™ Lisbon
First ACCC™ project Commissioned over urban hutments and railway crossing for the critical sections at Ahmedabad
![Page 13: CTC Global Presentation Partner Meet May 2015](https://reader033.fdocuments.us/reader033/viewer/2022051502/58d0e96e1a28abba558b5a19/html5/thumbnails/13.jpg)
Torrent Power’s Second Project – 220 kV – ACCC™ Drake
Second project commissioned for Torrent Power; 220kV line in Ahmedabad
![Page 14: CTC Global Presentation Partner Meet May 2015](https://reader033.fdocuments.us/reader033/viewer/2022051502/58d0e96e1a28abba558b5a19/html5/thumbnails/14.jpg)
TATA Power IIT-SAKI-ACCC Helsinki
ACCC™ was Commissioned by Sterlite under CTC supervision amidst heavy Hutments, Dense Slums in Suburban Mumbai
![Page 15: CTC Global Presentation Partner Meet May 2015](https://reader033.fdocuments.us/reader033/viewer/2022051502/58d0e96e1a28abba558b5a19/html5/thumbnails/15.jpg)
ACCC™ Conductor was Commissioned by Sterlite under CTC supervision amidst urban colonies and crop fields in Nashik, Maharashtra
MSETCL Nashik Line-132KV-ACCC Casablanca
![Page 16: CTC Global Presentation Partner Meet May 2015](https://reader033.fdocuments.us/reader033/viewer/2022051502/58d0e96e1a28abba558b5a19/html5/thumbnails/16.jpg)
CTC Global at a Glance • CTC is the inventor and manufacturer of ACCC, the most advanced composite core used in power transmission lines transmission lines
• Headquarters and manufacturing facility in Irvine, CA;
• 85 employees
• Installed base of over 225 sites and, 17,000 + KM
• Currently, serving 24 countries on Iive continents.
Examples of CTC Blue Chip Customers
16 ctcglobal.com | All rights reserved.
![Page 17: CTC Global Presentation Partner Meet May 2015](https://reader033.fdocuments.us/reader033/viewer/2022051502/58d0e96e1a28abba558b5a19/html5/thumbnails/17.jpg)
ACCC® Conductor Improving the Efficiency, Reliability
and Capacity of the Grid
CTC Global 2026 McGaw Avenue Irvine, California 92614 USA +1 (949) 428-8500 www.ctcglobal.com
![Page 18: CTC Global Presentation Partner Meet May 2015](https://reader033.fdocuments.us/reader033/viewer/2022051502/58d0e96e1a28abba558b5a19/html5/thumbnails/18.jpg)
Thank You
18 ctcglobal.com | All rights reserved.