Ct Vt Calculations r1
Click here to load reader
description
Transcript of Ct Vt Calculations r1
CT & VT CALCULATIONS FOR
GENERATOR, GT AND UT METERING AND PROTECTION
DOCUMENT NO. : PE-DC-348-510-E003REV NO. : 01
DATE : 28/10/10 SHEET : 1 of 16
1.0 SCOPE :
This document covers the following :
CT parameters calculations for :-
CTs of Generator Neutral & Line side.
CTs on GT HV side having interface with GRP.
CTs on GT HV neutral side.
CTs on GT LV side.
CTs on UT HV side.
CTs on UT LV neutral side.
CTs on UT LV side having interface with GRP.
VT parameters calculations for :-
VTs on Generator line side.
IVT parameters calculations for
Generator Inter turn fault relay (64GlT)
110 V AC auxiliary supply to 20 Hz Generator
2.0 REFERENCE DRAWING :
DRAWING TITLE : SLD for Generator, GT & UT Metering and Protection.
DRAWING NO. : PE-DG-348-510-E001
3.0 LEGEND :
CT : Current transformer
I : Relay rated current
IVT : Interposing voltage transformer
Ie : Excitation current
If : CT secondary current corresponding to fault current
L : Length of cable between CT and relay
RL : One way lead resistance between CT and relay
Rct : Resistance of secondary winding of main CT
Vk : Knee point voltage
VT : Voltage transformer
CT & VT CALCULATIONS FOR
GENERATOR, GT AND UT METERING AND PROTECTION
DOCUMENT NO. : PE-DC-348-510-E003REV NO. : 01
DATE : 28/10/10 SHEET : 2 of 16
4.1 MAIN EQUIPMENT DETAILS
(I) GENERATOR :
Rated Output : 600 MW
Rated Voltage : 21 KV
Subtransient reactance (Xd’’) (saturated) : 17.8% Voltage variation : ± 5%
Rated power factor : 0.85 LAG
(II) GENERATOR TRANSFORMER :
Rating : 3 single-phase units of 240 MVA each.
Percentage Impedance [Tentative] : 14.5% at 240 MVA base
Voltage ratio : (420/√3)/21KV
(III) UNIT TRANSFORMERS :
Rating : 31.5 MVA
Percentage Impedance [Tentative] : 10 %
Voltage ratio : 21/11.5KV
4.2 CONTROL CABLE DETAILS
Material : Copper
Size : 2.5 mm2
Resistance of conductor : 8.87 /kM (for 2.5 mm2 cable)
5.0 CTs PARAMETER CALCULATIONS
5.1 CTs Ratio On Gen Neutral & Phase Side :
Generator current at normal operating voltage
IGnormal = 850.x 213
1000600
= 19407.3A Generator current at minimum continuous operating voltage (i.e. at 95% of normal voltage)
IGmax = 95.085x0.213
1000600
= 20428.7A
Hence CT ratio for CTs located on generator neutral side and phase side
for protection, metering, load transducers and AVR is selected as 22000/5 A
CT & VT CALCULATIONS FOR
GENERATOR, GT AND UT METERING AND PROTECTION
DOCUMENT NO. : PE-DC-348-510-E003REV NO. : 01
DATE : 28/10/10 SHEET : 3 of 16
For the purpose of calculation, distance from GRP to Gen Busduct CTs marshalling box, L is taken as
175M
Lead Resistance, RL = 8.87 x 0.175
= 1.55 ohm
Hence ,
Lead Burden = 52 x 1.55 VA
= 38.8 VA
Lead Burden (for 2 cores) = 19.4 VA
5.1.1 CTs ON GEN. NEUTRAL SIDE
CT 1 : For Overall differential protection (87OA)
CT 2 : For ‘Load transducer’ & ‘Performance testing’
CT 3 : For composite generator protection relay ‘GR1’
CT 4 : For composite generator protection relay ‘GR2’
CT9 : For 100% stator E/F Protection (64G3)
CT 1 :
Vk 50I (Rct + 2 RL)
Ie 0.03 I at Vk/2
I = 5A
Vk 50 x 5 (Rct + 2 x 1.55 /2)
[2 cores of 2.5mm2 cable]
Vk 250Rct + 387.5 V
Ie 150mA at Vk/2
SELECTED PARAMETERS FOR CT 1 :
CT RATIO : 22000/5 A
ACCURACY CLASS : PS
KNEE POINT VOLTAGE : 250Rct + 400 V
MAGNETISING CURRENT : 150mA at Vk/2
CT & VT CALCULATIONS FOR
GENERATOR, GT AND UT METERING AND PROTECTION
DOCUMENT NO. : PE-DC-348-510-E003REV NO. : 01
DATE : 28/10/10 SHEET : 4 of 16
CT 2 :
* : Performance testing meter
SELECTED PARAMETERS FOR CT 2 :
CT RATIO : 22000/5 A
ACCURACY CLASS : 0.2
BURDEN : 60 VA
I.S.F. : ≤ 5.0
CT 3 & CT 4 :
Maximum through fault current of generator = 85.0178.085.0213
1000600
= 128270.3 A
If = 21000
5 128270.3
= 30.54 A
Vk 5If (Rct + 2 RL)
Vk 5 x 30.54 (Rct + 2 x 1.55/2)
[2 cores of 2.5 mm2 cable]
Vk 152.7Rct + 236.685 V
Ie 0.03 I at Vk/2
I = 5A
Ie 150mA at Vk/2
Source of burden
Ammeter (*)
Wattmeter (*)
VARmeter (*)
PFmeter (*)
KWHmeter (*)
Load Transducer
Lead burden [2 cores of 2.5 mm² cable]
Total Burden
Burden (in VA)
3.0
5.0
5.0
5.0
5.0
0.5
19.4
42.9
CT & VT CALCULATIONS FOR
GENERATOR, GT AND UT METERING AND PROTECTION
DOCUMENT NO. : PE-DC-348-510-E003REV NO. : 01
DATE : 28/10/10 SHEET : 5 of 16
SELECTED PARAMETERS FOR CT 3 & CT 4 :
CT RATIO : 22000/5 A
ACCURACY CLASS : PS
KNEE POINT VOLTAGE : 160Rct + 250 V
MAGNETISING CURRENT : 150mA at Vk/2
CT 9:
PARAMETER TO BE FINALISED LATER AFTER RECEIPT OF NGR RATING FROM CUSTOMER.
5.1.2 CTs ON GEN. PHASE SIDE
CT 5 : For composite generator protection relay ‘GR1’
CT 6 : For composite generator protection relay ‘GR2’
CT 7 : For Load transducer, Load shedding relay and AVR
CT 8 : For ‘Metering’, Load transducer & AVR.
CT 5/CT 6 :
Particulars shall be similar to CT 3/CT 4
SELECTED PARAMETERS FOR CT 5 & CT 6:
CT RATIO : 22000/5 A
ACCURACY CLASS : PS
KNEE POINT VOLTAGE : 160Rct + 250 V
MAGNETISING CURRENT : 150mA at Vk/2
CT 7 :
Source of burden
AVR
Load transducer
Load shedding relay
Lead burden [2 cores of 2.5 mm² cable]
Total burden
Burden (in VA)
20.0
0.5
0.85
19.4
40.75
SELECTED PARAMETERS FOR CT 7 :
CT RATIO : 22000/5 A
ACCURACY CLASS : 0.2
BURDEN : 60 VA
I.S.F. : ≤ 5.0
CT & VT CALCULATIONS FOR
GENERATOR, GT AND UT METERING AND PROTECTION
DOCUMENT NO. : PE-DC-348-510-E003REV NO. : 01
DATE : 28/10/10 SHEET : 6 of 16
CT 8 :
Source of burden
MWH/MVARH meter
Current transducer (3 Nos.)
Watt transducer (1 Nos.)
VAR transducer (1 Nos.)
PF transducer
Load transducer
AVR
Lead burden [2 cores of 2.5 mm² cable]
Total Burden
Burden (in VA)
1.0
0.2 x 3 =0.6
0.5
0.5
0.6
0.5
20.0
19.4
43.1
SELECTED PARAMETERS FOR CT 8 :
CT RATIO : 22000/5 A
ACCURACY CLASS : 0.2
BURDEN : 60 VA
I.S.F. : ≤ 5.0
5.2.0 CTs ON GT LV SIDE
Phase Current on GT LV side = 21
1000 x 240 A
= 11428.57 A
Hence CT ratio for CTs located on GT LV line side for protection is selected as 12500/5
A.
For the purpose of calculations, Distance from GRP to GT M.Box,
L = 230M
Lead Resistane, RL = 8.87 x 0.23
= 2.04 ohms
5.2.1 CTs on GT LV line Side:
CT 10 : For GT differential Protection (87GT)
CT 11 : For GT differential Protection (87GT)
CT10/ CT11 :
Vk 50I (Rct + 2 RL)
CT & VT CALCULATIONS FOR
GENERATOR, GT AND UT METERING AND PROTECTION
DOCUMENT NO. : PE-DC-348-510-E003REV NO. : 01
DATE : 28/10/10 SHEET : 7 of 16
Ie 0.03 I at Vk/2
I = 5A
Vk 50 x 5 (Rct + 2 x 2.04 /2)
[2 cores of 2.5mm2 cable]
Vk 250Rct + 510 V
Ie 150mA at Vk/2
SELECTED PARAMETERS FOR CT 10/ CT11 :
CT RATIO : 12500/5 A
ACCURACY CLASS : PS
KNEE POINT VOLTAGE : 250Rct + 550 V
MAGNETISING CURRENT : 150 mA at Vk/2
5.3.0 CTs ON GT HV SIDE
Current on GT HV side = x4203
1000 x 240x3
= 989.77 A
Hence CT ratio for CTs located on GT HV neutral side and GT HV line side for protection
is selected as 1200/1 A and 1200/5 A respectively.
For the purpose of calculations, Distance from GRP to GT M.Box,
L = 230M
Lead Resistane, RL = 8.87 x 0.23
= 2.04 ohms
Hence,
Lead burden = 12 x RL
= 2.04 VA
5.3.1 CTs on GT HV Neutral Side:
CT 12 (CORE-1) : For GT HV side Backup Earth Fault Protection (51NGT)
CT 12 (CORE-2) : For GT HV & overhead line differential Protection (87HV)
CT 12 (CORE-1) :
Source of burden
51 NGT
Lead burden( 2.5 mm² cable)
Total Burden
Burden (in VA)
0.30
2.04
2.34
SELECTED PARAMETERS FOR CT 12 (CORE – 1):
CT RATIO : 1200/1 A
CT & VT CALCULATIONS FOR
GENERATOR, GT AND UT METERING AND PROTECTION
DOCUMENT NO. : PE-DC-348-510-E003REV NO. : 01
DATE : 28/10/10 SHEET : 8 of 16
ACCURACY CLASS : 5P20
BURDEN : 15 VA
CT 12 (CORE-2) :
Maximum through fault current on HV side of GT = 145.095.04203
1000720
= 7185.28 A
Fault on secondary side of CT, If = 1000
17185.28
If = 7.185 A
Knee point voltage, Vk 2If (Rct + 2RL)
Vk 2 x 7.2 (Rct + 2x 2.04)
(2.5 mm² cable)
Vk 14.4 Rct + 58.75 V
Ie 0.03 I at Vk/2
CT sec. current , I = 1 A
Ie 30mA at Vk/2
SELECTED PARAMETERS FOR CT 12 (CORE-2) :
CT RATIO : 1200/1 A
ACCURACY CLASS : PS
KNEE POINT VOLTAGE : 20 Rct + 100 V
MAGNETISING CURRENT : 30 mA at Vk/2
5.3.2 CTs on GT HV line Side :
CT 13 : For GT differential protection (87GT) CT 13 :
Vk 50I (Rct + 2 RL)
Ie 0.03 I at Vk/2
I = 5A
Vk 50 x 5 (Rct + 2 x 2.04 /2)
[2 cores of 2.5mm2 cable]
Vk 250Rct + 510 V
CT & VT CALCULATIONS FOR
GENERATOR, GT AND UT METERING AND PROTECTION
DOCUMENT NO. : PE-DC-348-510-E003REV NO. : 01
DATE : 28/10/10 SHEET : 9 of 16
Ie 150mA at Vk/2
SELECTED PARAMETERS FOR CT 13 :
CT RATIO : 1200/5 A
ACCURACY CLASS : PS
KNEE POINT VOLTAGE : 250Rct + 550 V
MAGNETISING CURRENT : 150 mA at Vk/2
CT 14(CORE-1) : For Overall differential protection (87OA) to be covered in 400kV switchyard
document [customer scope] documents.
CT 14(CORE-2) : For GT HV & overhead line differential protection (87HV) to be covered in
400kV switchyard document [customer scope] documents.
5.4.0 CTs FOR UT #1A/2A & UT #1B/2B
5.4.1 CTs on UT #1A/2A & UT #1B/2B HV Line side :-
CT15A/ CT15B : For UT Differential Protection (87UTA / 87UTB)
CT16A/ CT16B : For UT HV Over Current Protection (51UTA / 51UTB)
CT17A/ CT17B : Overall differential protection (87OA)
Current on UT HV side = x213
1000 x 31.5
= 866.05 A [At normal voltage]
Hence CT ratio for CTs located on UT HV side for protection is selected as 1000/1 A.
For the purpose of calculations, Distance from GRP to UTs Tap Off Busduct CT marshalling box
is taken as 210m.
L = 210M
Lead Resistance, RL = 8.87 x 0.21
= 1.86 ohm
Hence, Lead burden = I2 x RL
= 12 x 1.86
= 1.86 VA
CT 15A & CT 15B:
Vk 40 I (Rct + 2 RL)
Ie 0.03 I at Vk/2
I = 1A
Vk 40 x 1 (Rct + 2 x 1.86)
CT & VT CALCULATIONS FOR
GENERATOR, GT AND UT METERING AND PROTECTION
DOCUMENT NO. : PE-DC-348-510-E003REV NO. : 01
DATE : 28/10/10 SHEET : 10 of 16
[2.5 mm2 cable]
Vk 40Rct + 148.8 V
Ie 30mA at Vk/2
SELECTED PARAMETERS FOR CT 15A & CT 15B :
CT RATIO : 1000 / 1 A
ACCURACY CLASS : PS
KNEE POINT VOLTAGE : 40Rct + 200 V
MAGNETISING CURRENT : 30mA at Vk/2
CT 16A & CT 16B :
Source of burden
51UT
Lead burden [2.5 mm² cable]
Total Burden
Burden (in VA)
0.3
1.86
2.16
SELECTED PARAMETERS FOR CT16A & CT 16B :
CT RATIO : 1000/1 A
ACCURACY CLASS : 5P20
BURDEN : 15VA
CT17A/ CT17B :
Praticular shall be similar to CT1:
SELECTED PARAMETERS FOR CT 17A/17B :
CT RATIO : 21000/5 A
ACCURACY CLASS : PS
KNEE POINT VOLTAGE : 250Rct + 400 V
MAGNETISING CURRENT : 150mA at Vk/2
5.4.2 CTS ON UT LV SIDE:
Current on UT LV side = x11.53
1000 x 31.5
= 1581.48 A
Hence CT ratio for CTs located on UT LV side for protection is selected as 2000/1 A.
5.4.2.1 CTs on UT LV Neutral side:
CT & VT CALCULATIONS FOR
GENERATOR, GT AND UT METERING AND PROTECTION
DOCUMENT NO. : PE-DC-348-510-E003REV NO. : 01
DATE : 28/10/10 SHEET : 11 of 16
NOTE: FOR CALCUALTION PURPOSE, NGR RATING IS CONSIDRED AS 300A FOR 10
SEC. CUSTOMER TO CONFIRM.
CT18A/ CT18B (CORE - 1) : For UT LV Backup Earth Fault Protection (51NUTA / 51NUTB)
CT18A/ CT18B (CORE - 2) : For UT Restricted Earth Fault Protection (64RUTA / 64RUTB)
Max. distance from GRP to UT MB = 210M
Lead Resistane, RL = 8.87 x 0.21
= 1.86
Hence, Lead burden = I2 x RL
= 12 x 1.86
= 1.86 VA
CT 18A & CT18B (CORE-1) :
Source of burden
51NUT
Lead burden [2.5 mm² cable]
Total Burden
Burden (in VA)
0.3
1.86
2.16
NGR is rated for maximum E/F current of 300 A.
SELECTED PARAMETERS FOR CT 18A & 18B (CORE-1) :
CT RATIO : 300 / 1 A
ACCURACY CLASS : 5P20
BURDEN : 15 VA
CT 18A & CT 18B (CORE-2) :
Maximum through fault current on LV side of UT = 9.010.05.113
10005.31
= 17572 A
Fault on secondary side of CT, If = 2000
1 17572
If = 8.78 A
Knee point voltage, Vk 2If (Rct + 2RL )
Vk 2 x 8.78(Rct + 2 x 1.86)
[ 2.5 mm2 cable]
Vk 17.56Rct + 65.32 V
Magnetising current , Ie 0.03 I at Vk/2
CT sec. current , I = 1A
Ie 30mA at Vk/2
CT & VT CALCULATIONS FOR
GENERATOR, GT AND UT METERING AND PROTECTION
DOCUMENT NO. : PE-DC-348-510-E003REV NO. : 01
DATE : 28/10/10 SHEET : 12 of 16
SELECTED PARAMETERS FOR CT 18A & 18B (CORE-2) :
CT RATIO : 2000 / 1 A
ACCURACY CLASS : PS
KNEE POINT VOLTAGE : 20Rct + 100 V
MAGNETISING CURRENT : 30mA at Vk/2
5.3.2.2 CTs on UT LV Line side:
CT19A/ CT19B (CORE-1) : For UT Restricted Earth Fault Protection (64RUTA / 64RUTB)
CT19A/ CT19B (CORE-2) : For UT Differential Protection (87UTA / 87UTB)
Average Distance from GRP to Unit Switchgear I/C Busduct CT marshalling box
= 90 M
Lead Resistane, RL = 8.87 x 0.09
= 0.8 ohm
CT19A/ CT19B (CORE-1) :
Particulars shall be similar to CT 18A/CT18B (CORE-2) i.e.
SELECTED PARAMETERS FOR CT 20A & 20B (CORE-1) :
CT RATIO : 2000 / 1 A
ACCURACY CLASS : PS
KNEE POINT VOLTAGE : 20Rct + 100 V
MAGNETISING CURRENT : 30mA at Vk/2
CT19A/ CT19B (CORE-2) :
Vk 40 I (Rct + 2 RL)
Ie 0.03 I at Vk/2
I = 1A
Vk 40 x 1 (Rct + 2 x 0.8/2)
[2 cores of 2.5 mm2 cable]
Vk 40Rct + 32 V
Ie 30mA at Vk/2
SELECTED PARAMETERS FOR CT 20A & CT 20B (CORE-2) :
CT RATIO : 2000 / 1 A
ACCURACY CLASS : PS
KNEE POINT VOLTAGE : 40Rct + 50 V
MAGNETISING CURRENT : 30mA at Vk/2
CT & VT CALCULATIONS FOR
GENERATOR, GT AND UT METERING AND PROTECTION
DOCUMENT NO. : PE-DC-348-510-E003REV NO. : 01
DATE : 28/10/10 SHEET : 13 of 16
6.0.0 VOLTAGE TRANSFORMER PARAMETER CALCULATIONS
VT 1 : For Gen. Protection, AVR, Frequency Transducer, Load transducer & Load
shedding relay.
VT 2 : For Gen. Protection, AVR, Load transducer & gen. Synchronising.
VT 3 : For metering, performance testing & Load transducer.
Primary connection : Star
Secondary connection : Star
Primary voltage : 3
21000V
Secondary voltage : 110
3V
VT ratio : 3
110
3
21000 V
VT 1:
Source of burden
60VT1
AVR
Frequency transducer
Load transducer
Load shedding relay
GR1
Total Burden
Burden (in VA)
11.0
20.0
3.00
0.13
2.1
0.3
36.53
Lead burden is negligible for VT
SELECTED PARAMETERS FOR VT 1 :
VT RATIO : 3
110
3
21000 V
ACCURACY CLASS : 0.5/3P
BURDEN : 100 VA
CT & VT CALCULATIONS FOR
GENERATOR, GT AND UT METERING AND PROTECTION
DOCUMENT NO. : PE-DC-348-510-E003REV NO. : 01
DATE : 28/10/10 SHEET : 14 of 16
VT 2 :
Source of burden
60VT2
AVR
Load transducer
Voltage transducer for incoming voltage(*)
Frequency transducer for incoming
frequency(*)
Synchroscope(*)
GR2
Total Burden
Burden (in VA)
11.0
20.0
0.125
0.22
3.0
6.0
0.3
40.645
Lead burden is negligible for VT
* synchronising equipment
SELECTED PARAMETERS FOR VT 2 :
VT RATIO : 3
110
3
21000 V
ACCURACY CLASS : 0.5/3P
BURDEN : 100 VA
VT 3:
CT & VT CALCULATIONS FOR
GENERATOR, GT AND UT METERING AND PROTECTION
DOCUMENT NO. : PE-DC-348-510-E003REV NO. : 01
DATE : 28/10/10 SHEET : 15 of 16
Source of burden
60VT3
MWH/MVARH meter
Transducer for VAR
Transducer for Watt
Transducer for PF meter
Transducer for Frequency
Transducer for Voltmeter (2 Nos.)
Load transducer
AVR
Wattmeter (*)
Varmeter (*)
PFmeter (*)
KWH meter (*)
Total Burden
Burden (in VA)
11.0
2.0
0.22
0.22
2.5
3.0 x 2 = 6.0
0.22 X 2 = 0.66
0.125
20.0
5.0
7.5
5.0
7.5
62.325
* Performance testing meter
Lead burden is negligible for VT
SELECTED PARAMETERS FOR VT 3 :
VT RATIO : 3
110
3
21000 V
ACCURACY CLASS : 0.2
BURDEN : 100 VA
7.0.0 INTERPOSING VTs PARAMETER CALCULATIONS
IVT 1 : For Gen. Interturn fault protection (64GIT)
IVT 2 : For 110V AC auxiliary supply to 20Hz Generator
IVT1 Primary connection : Star Secondary connection : Open delta Under fault condition, 64GIT should get no voltage. NGT secondary and open delta secondary of IVT1should give equal and opposite voltages. NGT ratio is 21kV/240V, i.e. it gives an output of 240/√3 for a single line to earth fault. to get 240 /√3 V, IVT1 secondary rating shall be (240 /√3) / 3 V.
IVT Primary voltage : (110/√3) V
IVT ratio : (110/√3) / (80/√3) V
CT & VT CALCULATIONS FOR
GENERATOR, GT AND UT METERING AND PROTECTION
DOCUMENT NO. : PE-DC-348-510-E003REV NO. : 01
DATE : 28/10/10 SHEET : 16 of 16
Source burden Burden (in VA) 64GIT 0.3 Total Burden 0.3 SELECTED BURDEN 15 VA SELECTED PARAMETERS FOR IVT 1 :
IVT RATIO : 3
80
3
110 V
ACCURACY CLASS : 3P BURDEN : 15 VA
IVT 2 :
Primary connection : Star
Secondary connection : star
Primary voltage : 3
415 V
Secondary voltage : 3
110 V
IVT ratio : 3
110/
3
415
Source of burden
20 Hz Generator
Total Burden
Burden (in VA)
45.0
45.0
SELECTED PARAMETERS FOR IVT 2 :
VT RATIO : 3
110/
3
415 V
ACCURACY CLASS : 1.0
BURDEN : 100 VA