CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
ATLAS High Level Trigger/DAQ
INFN and Univ. di Genova, Lecce, LNF, Napoli, Pavia, Pisa, Roma1, Roma2, Roma3
S.Falciano - INFN Roma1
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Outline
• Breve status report del TDAQ di ATLAS con particolare riferimento al progetto HLT/DAQ e ai contributi italiani.
• Attività del 2004• Aggiornamento sul lavoro svolto• Milestones 2004• Piano finanziario : richiesta di sblocco s.j. CORE
• Attività prevista per il 2005 • Sviluppi HLT/DAQ• Commissioning• Milestones 2005• Richieste finanziarie
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Attività prevista nel 2004
• Integrazione completa di tutte le componenti del LVL1 ad H8 (Muon+MUCTPI, Calo, CTP)
• Integrazione del LVL2 e EF nel Test Beam Combinato ad H8
• Integrazione ad H8 di LVL1+LVL2+EF con elx dei rivelatori e il DAQ; run a 25 ns con trigger di primo livello generato dall’elettronica che funzionerà in ATLAS (LVL1 Calo+Muon + CTP) (“pipelined” mode).
• ROD Crate DAQ per tutti i rivelatori (H8 e Commissioning)
• Monitoring dei rivelatori e del trigger : infrastruttura e applicazioni
• Test del software e delle configurazioni di trigger in laboratorio utilizzando i Testbed
• Definizione e acquisto della “pre-serie” di HLT/DAQ ossia il “Modulo-0”.
In parallelo :
• Sviluppi degli algoritmi di trigger per Muoni (Muon Slice) e Pixel
• Studi di Trigger Performance (rates, capacità di reiezione del fondo, etc.)
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Attività svolta nel 2004
• Per quanto riguarda il trigger di muoni di Livello-1 nel barrel, nel 2004 sono stati prodotti e collaudati i prototipi finali delle PADs, e' iniziata la produzione finale delle Splitter boards, e' stato realizzato, collaudato e integrato il prototipo finale di Link ottico e infine completato il disegno finale della Sector Logic e del ROD backplane.
• Per il sistema HLT/DAQ ci si e' concentrati sull'integrazione del trigger di Livello-2 e dell'Event Filter nel Testbeam Combinato ad H8, lavoro attualmente in corso e gia' funzionante a fine luglio per gli aspetti di Data Flow e di Online Software. E' in corso l'integrazione degli algoritmi di trigger - con il meccanismo di steering previsto per l'esperimento - e di quelli di monitoring e di calibrazione. Si e' infine integrato il readout dei Pixel nel DAQ ad H8.
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Portable HLT “mini” testbeds
SFI
SFO
EFD AthenaPT
L2SV
ROSEROBROB
LVL2 & EBNetworks
DFM
pROS
ROB
L2+EF testbedInput file
• EF testbed • can be implemented in a single host• used to test the EF algorithms
• L2+EF testbed • requires 2 hosts• used to test the pROS communication between L2 algos and EF algos (the HLT slice online)
Contains the LVL2 result that
steers/seeds the EF processing
L2PU AthenaMT
SFIEmulator
EF testbedInput file
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Software HLT
• Il software HLT combina 4 progetti software in uno, con complicate inter-dipendenze – I due package DAQ (Online and Dataflow)– “Offline” e “HLT” releases
• Riuso del software offline negli HLT– Beneficia del framework flessibile, dei servizi e degli algoritmi comuni– Stabilità versus nuove features
• Piani futuri– Sono previsti ulteriori step di ottimizzazione basati sui risultati dei testbed
di larga scala e del testbeam
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
HLT Event Selection Software
HLTSSW
Steering Monitoring Service
MetaData Service
ROB DataCollector
DataManager
HLTAlgorithms
Processing Task
Event DataModel
L2PU Application
<<import>>
Event DataModel
Reconstr. Algorithms
<<import>>
StoreGateAthena/Gaudi
<<import>><<import>>
Interface
Dependency
Package
Event Filter
HLT Core Software
Offline Core Software Offline Reconstruction
HLT Algorithms
Level2
HLT Data Flow Software HLT Selection Software Framework ATHENA/GAUDI Reuse offline components Common to Level-2 and EF
Offline algorithms used in EF
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
LVL2 Muon Trigger:
Av. total Av. total time 2 mstime 2 ms
Fast speed increase
• Main improvement comes from RPC and MDT data preparation:– Better use of roads defined by LVL1 trigger– total data-preparation time reduced to ~800 s
• Small improvement in algorithm time too– fewer MDT hits to handle and process saves ~60 s
• Data preparation and Fast now take about 1 ms each, total time about 2 ms.– Network data access time an additional ~0.2ms
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
EF muon trigger: Trig-
Pt = 100 GeV
< 2.7
G4 – PRELIMINARY
• Nuovo rispetto ai risultati del TDR
• Validata la ricostruzione di nuovi dati G4 con Trig-Moore (EF)
• Esempio di algoritmo di ricostruzione offline adattato dagli autori per lavorare in una regione di interesse guidata dai risultati del LVL2 (“seed”)
• Intera slice LVL1-LVL2-EF validata con “seeding” :
• LVL1 RoIs seeds LVL2• LVL2 result (LVL2 muon track
encoded in raw “byte stream” format and appended to event data) seeds EF
• EF unpacks this as part of the raw event and creates the seed objects
• pT resolution from Geant4 simulation
• Timing: ~150/280 ms (20/200 GeV muon)
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
HLT at the Combined Test Beam• Two roles:
– Service• Run monitoring algorithms in the LVL2 and EF farm. • Coherent histogram monitoring across the HLT system
– Client• Aim to have the 2 slices (muon and e/) running from LVL1 to LVL2 and EF
• Aim– Test as many aspects of the system as possible and collect enough information to
evaluate the integration issues ahead of us
• Status– LVL2 muon trigger being tested on simulated TB data (June)– LVL2 dataflow integrated into the test beam muon readout chain (July)– EF processing task running Athena (July-August)
• tested remotely in test bed at Barcelona and on testbeam data in Pavia– Have a complete trigger dataflow test chain in place LVL1LVL2EF (End of August)– Full Muon slice in preparation : ready this week? Now a sort of “monitoring algorithm”
is collecting and decoding data, fills and display histograms of MDT and RPCs
• New ATLAS DB project set up : trigger and DAQ part of it.– Use of Muon ATLAS DB to exercise the access to configurations and conditions in one
place from LVL1 to offline software.
LVL1-LVL2-EF-DAQ vertical slice
Event Filter MAGNI cluster
CTP RoIBLVL1A
HLT mini-rack
RCC
ROD
ROD…
ROL ROL
RCC
ROD
ROD…
ROL ROL
…
ROS ROS
SFI SFO
DFM
FileServer
L2 Supervisors
L2 Processors
EF Processors
pROS
Switch
L1 Muon L1 CaloLVL1
Detector
LVL2
Event Filter Control+ EB
EF
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
TB T/DAQ chain
SFI
SFO
EFDAthenaPT
AthenaPTEFD
AthenaPT
AthenaPT
LVL1
RoIB
L2SV
ROS
ROD
ROB
ROD
ROB
LVL2 & EBNetworks
DFM
pROS
ROB
ROS
ROD
ROB
ROD
ROB
L2PU AthenaMT
Contains the LVL2 result that
steers/seeds the EF processing
L2PU AthenaMT
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
EF Data Flow
EFP EFD InputTask
Sorting
Task
ExtPTs
Task
ExtPTs
Task
Output
Task
Counting
Task
Histogr.Task
PreProc.
Task
PostProc.
Task
PT
PT
PT
PT
PT
SFI
SFO
InputHandler
Event Selectio
nThreads
LVL1Result
LVL2 Processing Task
EventQueue
LVL2Result
LVL1Result
LVL2Supervisor
LVL2 Processing Unit
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
DAQ Run Control showing the DAQ Run Control showing the L2 partition up and running L2 partition up and running with L1, RPC and MDTwith L1, RPC and MDT
DAQ Run Control showing the DAQ Run Control showing the L2 partition up and running L2 partition up and running with L1, RPC and MDTwith L1, RPC and MDT
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Event Display
Distribution of the hitMDT tube and RPCstrips in the Z-T plane
Beam
Counting
roomBIL
BML
BOLRPC Pivot
RPC Low Pt
RPC High Pt
RPC Overlapping RPC Overlapping geometry is seengeometry is seen
Hodoscope is positioned here
Data from TB Run 600610
Muon setup: RPC + MDT
Trigger: Hodoscope
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Beam profile
• Beam profile in the BML station.
• Correlation between RPCs and MDT is seen.
Commissione I - 3/5/2000
MDT hit tube residual(Fast MDT pattern
recognition)
Compute Z of the hit tubecentre; no use of drift timemeasurement.
Z = ( Z tube)/n. hit tube
Then compute the hit tuberesidual:
Z = Z tube – Z
Z
T
check the MDT data quality: electronic noise will broad the distribution.
Check the MDT data decoding: MDT data with low noise, must have the residuals peaked with the expected .
= Wire Pitch x = Wire Pitch x cos(15°)cos(15°) = Wire Pitch x = Wire Pitch x cos(15°)cos(15°)
BIL chamber:BIL chamber:muon track hits are insid the peakmuon track hits are insid the peak
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
T
Z
RPC-MDT Z correlation
BMLBML
RPC station 2(Pivot)
RPC station 1(Low Pt confirm)
T
Z
Z RPC 2
Z RPC 1
Z MDT
Compute the residuals between RPC and MDT clusters in BML and BOL.
RPC station 3(High Pt confirm)
Z MDT
Z RPC 3
BOLBOL
Z = Z RPC 3 – ZMDTZ = (Z RPC 2 + Z RPC 1)/2 – ZMDT
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
RPC-MDT Z correlation
Residuals distributions shows correlation between RPC and MDT clusters. Fast pattern recognition is working!
The is better thanks to the two RPC stations.
cluster sizeeffects in the third RPC.
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Examples of Moore algs at the CTB
= 61 m
(sag) 63 (sag) 63 mm (sag) 63 (sag) 63 mm
mm
Residuals of the segments fit
Moore Algs are being currently usedfor the EF and TB data offline analysis:
Barrel sagitta (average: misalignment,width: resolution)
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
DAQ nel Combined Test Beam• Items:
– New Data Flow and Online Software releases– Integration of LVL1 and HLT (configuration, control, data collection, etc.)– Monitoring based on Information Service (Online Software) and Gatherer (for
HLT to handle histos from a farm)• Aim
– Test as many aspects of the system as possible and collect enough information to evaluate the integration issues ahead of us
• Status– Detector integration (ROD Crate DAQ)
• Pixel integrated• SCT problems with ROD, expected to be solved soon • TRT integrated• LAr integrated• Tile integrated• MDT integrated• RPC integrated• TGC integrated• LVL1 muon integrated• LVL1 calo integrated in lab, partially integrated at H8 in August
– Detector Monitoring : done for Tile and MDT, RPC and Pixel in progress– HLT integration done (Data Flow and Online control)
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
ROD Crate DAQ
• Read-out dei rivelatori splittato su due componenti viste dal DAQ :
– ROD Crate (responsabilità Hw/Sw : Rivelatore)– ROS (responsabilità Hw/Sw : DAQ)
– Nuova implementazione Hw del ROS basata su PC invece che VME– Nuova implementazione del Sw del ROD Crate (ROD Crate DAQ) ora di
responsabilità DAQ. Ciò uniforma la DAQ Locale nel ROD Crate per tutti i Rivelatori (supporto centralizzato per local processing, configurazione, event sampling, etc.)
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
VME bus
•Total number of ROD crates: 90•Total number of ROS PCs : 144•Total number of racks : ~15”==>All in USA15 (underground)
F.E. ElectronicsF.E. Electronics
… ROD Crates
ROD CrateWorkstation
LAN (GbEth.)
GbEth.
… ROS PCs
ROD Fragments
ROB FragmentsROS Fragments
Event Fragments (Detector specific)
L2 & Event Builder NetworksL2 & Event Builder Networks
ROLs
RCD and ROS
… PCI bus
Config & Control
Event sampling & Calibration data
NIC
RO
BIN
RO
BIN
RO
BIN
RCP
ROD
ROD
ROD
ROD
Config & Control
Event sampling & Calibration data
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
CTB – Pixel Commissioning
Rod + TIM + SBC nel Rod + TIM + SBC nel crate VMEcrate VME
ModuloModulo
PP0 con PP0 con OptoboardOptoboard
Boc Boc
fibre ottiche I/O fibre ottiche I/O
S-Link S-Link
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Pixel DAQ @ 100 kHz
Module readout link @ 40 Mb/sHits dal rivelatore
LVL1 accepts
ROD Busy – tempo mortoindotto dalla scrittura dati sudisco a livello del ROS
Il firmware del ROD è stato debuggato e molti problemi sono stati capiti e risolti.Il Pixel ROD è ora in grado di gestire un flusso continuo di dati a 100 kHz e di gestire correttamente la backpressure applicata dal ROS
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
CTB – Pixel detectorPixel Box contenentePixel Box contenentesei moduli sei moduli
beam
beam
On-line monitorOn-line monitor
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
HW status
Monitoring can be done at all trigger levels
Requirements on Monitoring System
ROD ROS SFILVL1LVL1 LVL2LVL2SF0
EVFLTEVFLT
Different monitored information
physics quantities (invariant masses,
Eflow ...)
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Event Filter Event Filter AthenaAthena
Monitor overall structure
ROD
ROS
SFI
LVL1LVL1
LVL2LVL2
SF0
MPMP
MPMP
MPMP
MPMP
Event Filter Event Filter AthenaAthena
GathererGatherer
OHistogram Service
Commands to Commands to MPsMPs
Operational monitoring
display (trigger rates,...)Info Info
ProviderProvider Information Service
EMS
Eve
nt
Mo
nit
ori
ng
EMS
EMS
Event Filter Event Filter AthenaAthena
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Strategy for Monitoring
ROS OHistogram Service
Commands to Commands to MPsMPs
EMSE
ven
t M
on
ito
rin
g
Read Out System
Event Monitoring Sampler
Monitoring Process
Online Histogramming
Service
Interactive Presenter
File on disk EFS
File Sampler
DAQ/Online SW Group
Monitoring Group
CORE
User libUser lib
User lib
Detector Groups
MPMP
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Status of the project & people involved
A first version of the complete chain is working at the Combined Test Beam
User Detector groups are Pixel,Tilecal, MDT, RPC, Beam
Hope to integrate more detectors during CBT (SCT,...)
Ongoing developments on reference histograms, trigger selection, automatic, storing of histograms...
Monitoring Developers : P. Adragna, A. Dotti, R. Ferrari, C. Roda, W. Vandelli, F. Zema.
Users : M. Alviggi, I. Boyko, M. Brinet, D. Dedovitch, M. Della Pietra, L. Santi & people from Monitoring Developers.
DAQ support : M. Caprini, S. Kolos.
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Monitoring demonstration
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Monitoring at CTB – Tile + Beam
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Milestones 2004
• Le milestones scelte implicano lo svolgimento del lavoro della Collaborazione italiana secondo :– i piani del progetto globale TDAQ (e le sue milestones)– step di complessità crescente e passaggi importanti sotto controllo– sviluppi generali che facilitano il lavoro d’integrazione di componenti simili
(ad esempio i vari rivelatori)
• Marzo 2004 : Integrazione Livello-2/Event Filter/DAQ su Testbed al CERN con Livello-1 in emulazione (algoritmi di trigger e HLT software framework descritti nel Technical Design Report) -> OK
• Ottobre 2004 : Integrazione Detector/Livello-1/Livello-2/Event Filter/DAQ su Testbeam in modalità combinata (Pixel+LAr+Tile+MDT+RPC)
-> In progress (~ 50%)
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Pre-series : When and where
• LHCC milestone– Pre-series system installed and ready to be used 31.03.2005
--> Finalise technical specification Now Purchase
4Q04 Installation
1Q05
• Several locations considered– Bdgs 32 - 40 - 513 and Point-1
• Point-1 preferred– The most realistic one (ROS rack in USA15, the rest in SDX1 as for final)– No extra investment required– Validate ALL functionality aspects, including real infrastructure– Assess readiness of infrastructure ~ 6 months earlier than required
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Pre-series : purpose and scope
• Pre-series System defined as– Fully functional, small scale version of complete HLT/DAQ– Made of components as specified for final system
• Pre-commissioning phase– Validate the complete, integrated, HLT/DAQ functionality– Validate the infrastructure at Point-1
• Commissioning phase– Validate a component (e.g. a ROS) or a deliverable (e.g. a Level-2 rack) prior to
installation and commissioning
• Post-commissioning phase– Validate new components– Validate new software elements or full releases prior to use on experiment– As a TDAQ post-commissioning development system
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Pre-series - “Module-0” of final system - 7 racks (10% of final dataflow)
One central switch
-
DAQ rack-
128-port Geth for L2+EB
One ROS rack
-
TC rack+ horiz. Cooling
-
11 ROS44 ROBINs
One Full L2 rack
-
DAQ rack-
32 HE PC
One L2-misc
rack-
DAQ rack-
50% of RoIB
-
3 LE PC(1pROS - 2L2SV)
Part of EFIO rack
-
DAQ rack-
10 HE PC(6 SFI - 2SFO -
2DFM)
Part of EvFilt rack
-
DAQ rack-
12 HE PC
Part of ONLINE
rack-
DAQ rack-
4 HE PC(monitoring)
-
2 LE PC(control)
1ROSrack L2+EB
Switch
5.5
RCC
1L2-misc
rack
1EvFiltrack
1ONLINE
rack
1L2
rack
1EFIOrack
All racks : one or more Local File Servers - One or more Local Switches
USA
15
SD
X1
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Costing evaluation steps
• Write technical specifications of components. Currently available specs :– ROS and DAQ Racks (Rack and Cooler)– Rack mountable PCs, two profiles :
• P1 – PCs for ROS racks, 6 PCI slots to host ROBins, 4U chassis• P2 – PCs for Fileservers or for Operations & Control, 1U (in DAQ rack) chassis
– Local Fileserver and Control switch (not yet in formal way)
• Market Survey to understand current costs vs technical specs– Offers available today sometime are not exactly what we need but they help to
understand :• If our costing profile is STILL reasonable• How to proceed to have a product which matches exactly the technical specs (iterative
process)– For some items we have offers which already meet the technical specifications– INFN has made a local price enquiry to contribute in finding products with the required
technical specs and potential companies to be included in the final tendering.
• Purchasing– We shall purchase via CERN but we can specify in detail our sharing (see “Summary”)
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
ATLAS HLT/DAQ Pre-series For internal use only (page for the ATLAS Referees) Informations on the HLT/DAQ Pre-Series •Introduction •Pre-series in a picture •Pre-series deliverables •INFN deliverables & costing ("ROS Rack" - Partially filled "Online Rack" - Miscellanea) •Summary
Technical Specifications•Rack-mountable PCs for ATLAS DAQ applications (Technical document, Market Survey Qualification Criteria and Questionnaire) •Local Fileserver •Local Switch
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
ROS Rack (Prices are in kCHF)
Number Unit Cost Cost Description Offers/Estimates Actual cost
Rack (USA15) 1 13 (*) 13
Standard TC electronics rack (52U), includes cooling, power distr., control, etc.
Offer for Rack and CoolerPower distribution and Control
3.4 k€ (offer)
ROS PC 11 8 88
High end PC - redundant PS, multiple PCI slots, etc. (see technical specs)
Offer for a similar PC having the main required features (we may have better offers to match the initial price )
6.6 k€ (offer)
ROBins 44 3 132Custom ROB cards
Local Fileserver 1 5 5Low-end PC + 0.5 TB disk space
Offer for a similar PC (may have less RPS)
4.6 k€ (offer)
Control Switch 1 8 824 port GbE switch, managed
Offer from a reliable company (3COM SuperStack 3 Switch 3870 - data sheet)
3.8 k€
114 246
Cost without ROBinsCost with ROBins
(*) Rack and Cooler (5 kCHF), Power distribution and Control (8 kCHF)
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Total costing (Prices are in kCHF and k€)INFN contribution (~13% of Pre-series)
Item Cost (kCHF) Cost (k€)
ROS Rack (USA15) 104 69.3DAQ Rack (SDX) 27 18Miscellanea 12 8 Total 143 95.3
Richieste 140 89
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
2004 2005 2006 2007 2008 2009 Total
Pre-series 140 0 0 0 0 0 140
Detector R/O * 0 275 275 0 0 0 550
LVL2 Proc 0 0 65 195 230 160 650
Event Builder 0 0 50 50 110 70 280
Event Filter 0 0 170 180 570 380 1300
Online 0 45 135 0 0 0 180
Infrastructure 0 0 80 80 20 20 200
INFN Total 140 320 775 505 930 630 3300
TDR Total 1048 3357 4087 4544 7522 4543 25101
INFN Percentage(%) 13.4 9.5 19.0 11.1 12.4 13.9 13.1
INFN cost profile (unit is kCHF) for the chosen categories
(*) The funds for the staged part of the detectors (such as the Pixels) should fall in the year 2008. Therefore they might be subtracted from those of the years 2005-2006, which correspond to the full detector, and moved in 2008.
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Attività prevista nel 2005
• Per quanto riguarda il trigger di muoni di Livello-1 nel barrel, nel 2005 verrà sviluppata la produzione dell'elettronica on-detector nella prima metà dell'anno e di quella off-detector nella seconda metà, sarà definito il sistema finale di basse tensioni e inizieranno le procedure per la sua acquisizione.
• Il sistema HLT/DAQ dovrà verificare le sue funzionalità e performance finali utilizzando la cosiddetta "Pre-serie" (~ 10% TDAQ slice) e allo stesso tempo sostenere le attività di commissioning dei rivelatori. A tale scopo verranno acquistati e installati i ROS di Pixel, Tile e Muon, interfacciati ai ROD Crate di questi rivelatori e integrati in una catena completa di acquisizione dati. Continueranno inoltre gli studi di Trigger Performance utilizzando il software di selezione più aggiornato e i dati delle nuove simulazioni in Geant4 con la geometria finale.
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Milestones 2005
• Le milestones sono state definite con i seguenti criteri :– Devono rispecchiare le fasi principali del progetto globale TDAQ– Devono accordarsi alle milestone interne (TDAQ) e a quelle esterne (LHCC)– Devono rispecchiare il coinvolgimento finanziario dell’INFN nel progetto
30.09.2005 LVL1 : 100% elettronica on-detector disponibile31.10.2005 LVL1 : definizione sistema finale low voltage31.12.2005 LVL1 : 100% elettronica off-detector disponibile
30.06.2005 HLT/DAQ : Installazione, test e uso della "Pre-serie" (~ 10% TDAQ slice) -> milestone LHCC 30.03.2005
(install.)30.12.2005 HLT/DAQ : Installazione e test dei ROS di Pixel, Tile, Muon (interfacciamento al ROD Crate e integrazione nel DAQ) -> milestone ATLAS 30.09.2005 (ROS
ready)
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
… as we do in test beam today:from a minimal setup …
(The way to start with a new component)
• Readout Driver (ROD) is detector-specific.
• ROD Crate DAQ: skeleton by TDAQ, detector-specific parts by detector DAQ experts.
• S-link connection to Readout System (ROS). ROS is a TDAQ PC.
• Online Software for configuration, control, monitoring.
RO
D
SB
C
disk
S-link
testeddetector off-detector
readout electronics
ROSOnlineSW
RO
D c
rate
detector
TDAQ
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
… to the maximum multi-detector combination
DFM
gatewayin bdg.513
SFI
Tra
cker
Cal
oM
uon
det.
LVL1 calo
ROS
ROSRPC
ROSTGC
ROSCSC
ROS
LVL1 mu
Tile
ROS
ROSTRT
ROSSCT
ROSPixel
ROS
LAr
ROS
MDT
LVL1
monitoringrun control
pROS
data
net
wor
k (G
bE)
MAGNI farmin bdg. 513
SFO
remote farms
storageCASTOR (IT)
LVL2farm in H8
EF farm
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
HLT/DAQ commissioning is driven by detector installation and commissioning, for which we have identified 3 phases:
RCC
ROD
ROD
…
Ethernet
VME
1 - ROD-Crate DAQ (Sub-detector FE commissioning)– ROD read-out on VMEbus
by ROD Crate Controller
RCC
ROD
ROD…
ROL ROL
RCC
ROD
ROD…
ROL ROLROS ROS
Event Building
3 - ROS Read-Out (Multiple partitions)(Sub-detector/TDAQ commissioning)
– Multiple ROD-Crates read-out via ROL-ROS with a minimal EvBuilding
RCC
ROD
ROD…
ROL ROLROS
2 - ROD Read-Out(Sub-detector commissioning)
– ROD read-out on Read-OutLinks with a minimal ROS
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Piano finanziario 2005
CORE 2005 :– Detector Read-Out (Rack based, PC based, un rack contiene 11 PCs,
un local file server, un local switch, un rack controller, power e cooling distribution. Il costo di un rack è di 110 kCHF. Vogliamo finanziare :
• 11 ROSes per i Pixel• 26 ROSes per lo Spettrometro a Muoni• 8 ROSes per il TilePer un totale di 5 racks (5 x 110 kCHF = 550 kCHF, 13% del R/O totale)
distribuito su due anni.
– Online (include le farm di processori per l’Online software, ossia Run_control, inizializzazione, etc. e dovrebbe rappresentare anche la frazione di monitoring dei rivelatori. Contributo del 20%)
2005 : 214 k€ + 25 k€ + 4 fte x 4 mesi comm. = 239 k€ + 16 mu comm.HLT/DAQ Roma1 : invent. 7 k Upgrade testbed lab HLT/DAQ (PC, CPU
VME, Switch rete)
apparati 214 k (320 k CHF) come da piano finanziario approvato da lla CSN1 (no
deferral)HLT/DAQ Genova : invent. 10 k Schede DAQ (1 ROS + 1 ROBin)
5 k Single Board Computer per test con RODHLT/DAQ LNF : invent. 3 k PC per sviluppi TDAQ
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
2004 2005 2006 2007 2008 2009 Total
Pre-series 140 0 0 0 0 0 140
Detector R/O * 0 275 275 0 0 0 550
LVL2 Proc 0 0 65 195 230 160 650
Event Builder 0 0 50 50 110 70 280
Event Filter 0 0 170 180 570 380 1300
Online 0 45 135 0 0 0 180
Infrastructure 0 0 80 80 20 20 200
INFN Total 140 320 775 505 930 630 3300
TDR Total 1048 3357 4087 4544 7522 4543 25101
INFN Percentage(%) 13.4 9.5 19.0 11.1 12.4 13.9 13.1
INFN cost profile (unit is kCHF) for the chosen categories
(*) The funds for the staged part of the detectors (such as the Pixels) should fall in the year 2008. Therefore they might be subtracted from those of the years 2005-2006, which correspond to the full detector, and moved in 2008.
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Alcuni dettagli sui finanziamenti richiesti (1)
• Genova : L'idea e' qualle di avere in laboratorio a Genova una fetta completa del read-out dei pixel, diciamo dal rivelatore ai processori di LVL2. Ovviamente il tutto serve sia per studiare il readout che per fare esperienza con gli algoritmi di trigger, entrambe cose di cui Genova ha la responsabilita' in ambito pixel.
• Frascati : Il progetto e' di acquistare un PC da integrare nel rack della farm di calcolo, collegato in gigabit al resto della farm.
• Roma1 : Mantenere in vita il testbed che ci ha gia’ permesso di essere pronti col DAQ dei Muoni lo scorso anno ad H8 e integrare gli algoritmi di trigger nel sistema globale (sostituire i PC che muoiono o diventano vecchi più qualche CPU VME per emulare i ROD dei rivelatori). Continuare le riunioni nazionali sul trigger di muoni che si sono rivelate molto proficue.
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Alcuni dettagli sui finanziamenti richiesti (2)
• Commissioning : Il DAQ e' coinvolto nel commissioning dei detector per integrare i sistemi di lettura e leggere i dati comunque generati (test pulse, cosmici, etc.). Le sezioni di Genova, LNF, Pavia e Roma1 partecipano nel 2005 al DAQ per l'integrazione dei ROD e dei ROS, l'event sampling e il Data Flow in generale.
Ricordo che l'installazione dei ROS e' anche nostro compito visto che e' un acquisto CORE dell'INFN e riguarda i rivelatori che costruiamo.
Si pensa che ogni sezione possa fornire 1 fte per 4 mesi, quindi:
4 fte x 4 mesi = 16 mu di ME
Il lavoro si prevede inizi ad aprile e continui fino alla fine dell’anno.
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Conclusioni
• Abbiamo raccolto in tempi brevi il frutto di una lunga preparazione -> l’integrazione di Trigger/DAQ ad H8 è stato un successo (e non e’ ancora finita!)
• Il lavoro è stato tanto e duro, ma ci siamo anche divertiti ...
… anche se il “commissioning” è dietro l’angolo.
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Riserve
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Criteri per la scelta del profilo temporale di spesa
Abbiamo disegnato un sistema che evolve in funzione delle risorse disponibili, che va da un sistema iniziale con una rate massima di LVL1 di circa 40 kHz ad uno finale con una rate massima di 100 kHz
2004 : Acquisto e messa in opera della pre-serie fatta con le componenti
finali del TDAQ (commissioning del Tile?)2005 : Inizia il commissioning dei detector e di HLT/DAQ. Ai detector serve il
75% dei Detector Readout.2006 : Commissioning. Run di cosmici.2007 : LHC start-up. 37% circa delle farm HLT disponibili. 37.5 kHz è la rate
di LVL1 sostenibile. Mancano il 25% dei ROD.2008 : LHC alla luminosità nominale, 75 kHz di rate di LVL1. Questo è il
momento in cui cominciano a tornare indietro i deferral.2009 : Sistema completo con le performance per cui è stato disegnato,
ossia rate di LVL1 di 100 kHz.
Nota : nella fase iniziale la priorità viene data agli aspetti DAQ perche’ essi servono per il commissioning del rivelatore, mentre le farm HLT e in particolare il LVL2, vengono dimensionate al minimo.
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Requested INFN funds for the HLT/DAQ system (unit is kCHF)
TDR ItalyPercentag
e (%)More details on funded items
Pre-series 1048 140 13.4
Detector R/O 4060 550 13.5Detector R/O - ROS racks
only
LVL2 Proc 3596 650 18.1 LVL2 racks
Event Builder 2084 280 13.4 EB - EFIO (SFI, SFO)
Event Filter 11451 1300 11.4 EF racks
Online 830 180 21.7Online racks - Control &
Monitoring
Infrastructure 2032 200 9.8 ~ 6% of total INFN funds
Total 25101 3300 13.1HLT/DAQ (no DCS) is
26853 kCHF
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
ROS Rack
4U
~144 ROS units in total for final system
Pixel SCT TRT LAr Tile Muon
LVL1
ROD Crate
s(links)
8(120)
8(92)
22(232)
16(764)
4(64)
22(272)
6(56)
ROD Rack
sIndicativ
e
4 5 8 8 2 8 312 links / ROS
ROD Rack
5.5
RCC
ROD
ROD
ROD
ROD
ROD
ROD
ROD
ROD
ROD
ROD
ROD
ROD
ROD
ROD
ROD
5.5
RCC
ROD
ROD
ROD
ROD
ROD
ROD
ROD
ROD
ROD
ROD
ROD
ROD
ROD
ROD
ROD
ROS Units
11 8 20 66 8 26 5
ROS Rack
s Indicativ
e
1 1 2 6 1 3 1
ROD crate and ROS all underground
(USA15System size - Full configuration)
Estim
ate -
mig
ht not b
e exact
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Hardware components for Phase-2• Availability of hardware components
Component FDR PRR
ROL (Link Source Card) March ‘04
ROBIN May. ‘04 Oct. ‘04
ROS Tech spec’s under review
• ROL production procedure started– First batch (150 boards) : 4Q04 (Nov)– Full production (1750 boards) : 1Q05 (Feb)
• Production procedure for ROBIN identified– Blanket purchase procedure of RAL– Pre-production (50 cards) for pre-series
system : 1Q05– Full production : 2Q05
CSN1 Assisi - 23/09/2004 S.Falciano - INFN Roma1
Relevant DAQ milestonesDAQ – Hardware
PRR/FDR of S-Link Source Card (LSC) 28-02-04 Done
ROBIN FDR completed 31-05-04 Done
Draft tech. Spec for ROS PCs 30-04-04 Done
LSC ready for detector use (1st batch) 31-10-04 On sched.
Installation of ROBIN in ROS (1st batch) 31-07-05
ROS ready for installation 30-09-05
DAQ - Software Releases
Combined test beam (improved control, configuration, monitoring)
30-04-04 Done
Sub-detector readout (final ROD Crate DAQ consolidated) 30-09-04 On sched.
HLT/DAQ installation (final control, config, monitoring + CondDB I/f)
30-09-05
Cosmic-ray run (final large scale perf and full support for partitioning)
30-09-06
LHC start-up (final implementation ready for tuning) 30-04-07