CSC 395 –Software Engineering
Lecture 4:
Software Process
Today’s Lecture
Discuss why people care about software lifecycles What goes on in each step What this has to do with the Unified Process
Introduce dominant organizational methodology
Waterfall Model
Basis of almost all reasonable attempts at software engineering Grows from natural flow of work Proven to deliver good results Very good understanding its workings Extensible & modifiable for individual
circumstances Open for redefinition as times change
Why a Requirement Phase
Deadline Distribution requirements Portability Reliability Responsiveness Cost limitations
Clients often solicit bids to get lowest price Want to get client in for future updates
Deliver combination of what client needs & wants
Requirements
Client unclear or unable expressing desires Discover problem’s application domain
Rarely expressed in stack, list, hash table Specialize in area with high solution reuse -or- Software professionals must be polymaths
Build business model justifying project Need to show investment worth time & money
Work with client in concept exploration
Why an Analysis Phase
Requirements Phase: “Boo-boo” or “Owwie”
Analysis Phase: “Contusion”
Analysis Workflow
Requirements put in client’s language May be imprecise, inconsistent, or use terms
specific to application domain Deals with end product and not how we will get
there Analysis workflow translates requirements
Place in terms development team understands Remove ambiguities & contradictions Vital for eventual testing and maintenance
Client signs off on specification document
Software Project Management Plan
Create after specification document approved Plan for how the project will go
Plan should include all important details: Costs Duration Deliverables Milestones
Results of analysis workflow drives remainder of project Where should numbers for this plan come from?
Design Workflow
Where the developers take over Translate specifications into something that
can be implemented Architectural design divides specifications
into modules May be objects, packages, concepts, windows Process is very hard with few simple rules
Detailed design divides architectural design Selects algorithms & data structures
Design Deliverables
Design is an incredibly difficult process Needs to be specific enough to implement Should be open enough to be added to Companies may try reusing single template
Excellent process when they find good one Limits markets into which they can go, however
Document all ideas & save with deliverables Provides convenient backstop when stuck Helps with implementation & maintenance
Implementation Workflow
Only now does the coding begin Often newest & least trained employees Rarely requires contact with client Easiest skill to teach requiring least training Guess which jobs are most often outsourced?
Excellent coders, however, are valued Create easily reusable components or artifacts Solve tricky & difficult algorithmic issues Optimize the small portion of code most
commonly used
Where’s the Testing?
Testing occurs throughout the project Always check that project is on correct path Every day bug lingers increases odds of it never
being fixed By the time we get to implementation, cost of
finding and fixing errors is very, very high Outside team performs final checks on
artifacts Lack any involvement in development process Bring new set of ideas for how things should work
How Does Testing Occur?
Ultimately, we need to test against our agreement with the client Highly unlikely this involves Exceptions or JPanes
Testing therefore relies on traceability-- ability to trace a decision back to the initial requirements
Traceability starts during requirements Involves meticulous detail keeping afterward Finds where errors originate and helps in fix Explains to client how they asked for final product (Also explains to boss how it is not your fault)
Artifact Testing
All artifacts -- items surviving across workflows -- are tested against requirements Often include reviews for fresh sets of eyes Outside reviews have huge impact on efficiency
Requirements & SPMP often involve client Client generally uninvolved in most other checks
Implementation includes many checks
Implementation Tests
Unit tests check components during coding Integration tests test components play nice Product tests make sure we can be proud
Alpha & beta tests may preview the final test Provides clients with preview of the final product
Acceptance tests find out whether the client approves Usually rolled out across the client site over time May be first test using real data
Postdelivery Maintenance
Money is earned & lost after product delivery Clients often stop paying at this point We still expect them to work, however Over 50% of a product’s budget spent here
Postdelivery is worst time to fix bugs Clients may not be able to describe problems Bug fixing is at its most expensive May be due to simple lack of documentation
Important to keep tests for regression testing Prevent new bugs while fixing old ones
Retiring Software
Similar to sighting a Yeti or Bigfoot Companies loathe giving up on investment
Only occurs when cost of support too high May also happen if products loses clients Usually companies force upgrades or Chapter 11
Unified Process
Dominant method by which object-oriented software processes are analyzed & followed Named as it unifies “Three Amigos” ideas Relies upon UML to perform many of the
analyses Orthogonal to approach of “Gang of Four”
Used by nearly all software engineers Including the book, the instructor, & CSC395 Agile processes the only serious alternative now But this will eventually be replaced
Unified Process
Project also divided up into 4 phases Inception, Elaboration, Construction, Transition Phases follow the business view of a project
Creates grid of technical & business flow by which we can discuss development Also highlights that people are involved in
different workflows at the same time Means of splitting out teams & analyzing work
Inception Phase
Investigates if project should be undertaken Does the business model make sense? Can we complete project on time & what if it’s late?
Examinees possible risks for project Risks may be technical, architectural, or
engineering based Investigates ways by which risks can be mitigated
Develops feel for environment Also does work for other workflows
Implementation limited to proofs-of-concept
Elaboration Phase
Refine work done in inception phase Refine the requirements Perform the vast majority of the analysis Start the design workflow
Phase elaborates & enhances work from inception phase At end of phase, suits disappear for a while Majority of workload now belongs to the geeks
Construction & Transition
Construction phase belongs to technical side Google projects often stay in this phase Often ends when software goes β (beta)
Transition phase moves software to clients Driven by results from beta tests Ends with project released and in postdelivery
maintenance
Improving Software Development
Unified process focused on understanding software engineering Understanding process is first step Does nothing to quantify how software developed
Several systems developed to fix this ISO 9001 establishes base level of quality &
ISO 9000-3 applies ISO 9001 to software Many companies use ISO registered suppliers only ISO registration establishes base quality level
ISO/IEC 15504 & CMM
Also known by original acronym: SPICE Initiated by British MoD Unlike ISO 9000, looks to improve process Extends & improves ISO 9000 and CMM
Capability Maturity Model Placed by American DoD at SEI at CMU Extended to relate to all aspects of software Rates establishments and helps them improve
Levels of CMM
Nicknames1. Heroic
2. Repeatable
3. Defined
4. Quantifiable
5. Predictable Note: Level 5
does not exist
Is CMM Worth It
Hughes Aircraft spent $500K on improvement Level 3 saves $2M/year over level 2
Raytheon moved from level 1 to level 3 Productivity doubled Return of $7.70 per dollar invested
TCS (India) spent 6 years with CMM Estimation errors decreased from 50% to 15% Review effectiveness doubled (40% 80%)
Motorola found level 2 better than level 3
For Next Lecture
Friday’s lecture will Discuss teams, teams, and more teams Give you ideas for running the project Provide chance to discuss material from this week Get head start on homework handed out Friday