Cryogenic Carbon Capture Development NETL FE … Library/Events/2017/co2 capture/4... · Cryogenic...
Transcript of Cryogenic Carbon Capture Development NETL FE … Library/Events/2017/co2 capture/4... · Cryogenic...
Cryogenic Carbon Capture Development
NETL FE-0028697August 24, 2017
Larry Baxter1,2, Kyler Stitt1
1Sustainable Energy Solutions2Brigham Young University
CCC Value Proposition• Energy efficient CO2 capture (about ½ amine)• Cost effective CO2 capture (about ½ amine)• Grid-scale, efficient, rapid, inexpensive energy storage • Bolt-on technology (retrofit or greenfield)• Widely deployable (NG, biomass, coal, waste)• Multipollutant process (Hg, SOx, HC, NO2, PM2.5, ...)• Water conservation
Cryogenic Carbon Capture• General separation technology applicable to
– Post-combustion systems (this presentation)– Pre-combustion systems (active development)– Natural gas processing (active development)– LNG production
• Retrofit or greenfield process• Described in over 80 patent applications
4
Simplified Flow Diagram (ECL)
Heat ExchangerAnd Dryer
Flue Gas
Water
SO2, NO2, Hg, HCl
HeatRecovery Solid
Separation
Solid Compression
Pump
Pressurized, Liquid CO2
Heat Recovery
Expansion Refrigeration Loop
N2-rich Light Gas
CompressionAmbient Heat Exchange
Solids Auger
5
Melter
6
Energy Penalty
7
CCC nearly eliminates emissions while consuming half the energy of alternatives
0%
5%
10%
15%
20%
25%
30%
Amine (NETL case 12) CCC-ECL CCC CFG CCC-CFG Integrated
Para
sitic
Loa
d
Energy Consumption by Technology
Integrated
CCC Greenfield Incremental Cost
8CCC nearly eliminates emissions while increasing the cost of electricity by 2-3 ¢/kWh
9
Completed Skid-scale Demonstrations• Fuels
– Coals (subbituminous and bituminous)
– Natural gas– Biomass– Municipal waste, tires
• Technologies– Utility power plants– Industrial heat plants– Cement plant kilns– Large pilot-scale reactor
• Pre-combustion/NG Processing (lab scale)
Utility Power Plant
10
4-unit, 817 MWe power plant in Wyoming
Slip stream on unit 4, which has a baghouse and a wet scrubber (on subbituminous coal).
Utility Power Plant Skid Test
11
12
ECL Skid Photos
1 tonne/day CO2 capture
Utility Power plant
13
0%10%20%30%40%50%60%70%80%90%
100%
1 2 2 3 4 5 6 7 7 8 9 10 11 12 12 13 14 15 16 17 17 18 19 20 21 22 22 23
CO2
Capt
ure
%
Hours
Steady-state, continuous CO2 removal
Cement Kiln
14
0
10
20
30
40
50
60
70
80
90
100
0 100 200 300 400 500 600
CO2
Capt
ure
%
Minutes
Objective• Improve reliability and efficiency of unit operations
based on field test experience.• Implement improvements in skid system.• Retest skid system (budget period 2) in field on
power plant flue gas over 3-month period with minimum continuous operation of 500 hours.
• Project Partners: SES, Tri-state, Pacificorp, EPRI
Tasks1. Management2. Flue gas drying3. CO2 in contact liquid4. Solid-liquid separations5. Desublimating heat exchanger6. Instrumentation and controls7. Light gas dispersal8. Multipollutant capture9. Techno-economic analysis
17
Task 2. Drying
Moist Flue Gas Input
Cold liquid
Warm Liquid
FG From Treatment
Exhaust Flue Gas
PumpWater Out
To Flue Gas CO2 Removal
Direct Contact Heat Exchanger
Heat Recovery Heat Exchanger
1.E-11
1.E-10
1.E-09
1.E-08
1.E-07
1.E-06
1.E-05
1.E-04
1.E-03
1.E-02
-100 -90 -80 -70 -60 -50 -40 -30 -20 -10 0
Wat
er M
ole
Frac
tion
Temperature (°C)Ice Barrier System 3 System 4
Task 5. Heat Exchanger TestingMajor ActivitiesSpray Tower• Initial droplet size testing done for spray nozzles
and parallel spray device• Designed new skid-scale hybrid spray tower HX • Design incorporates the latest knowledge of slurry
handling, desublimating heat exchangers, and maximizing heat exchange, from thousands of hours of experimental work
• Spray tower constructed in Q3 and testing began
Task 6. Instrumentation and ControlsMajor Activities• New instrumentation includes thermocouples, pressure transducers, level
transmitters, flowmeters, and control valves• I/O channels will increase by 23% (i.e., 104 to 128)
• Of the existing channels, 63% (i.e., 66) will be modified in some way, such as by repurposing for a different instrument, re-routing to a new process location, or rebranding tag
• All changes require some programming time
Channel Existing New or modified PlannedAnalog outputs 12 14 16Analog inputs 33 32 40Discrete outputs 19 9 22Discrete inputs 4 9 11Thermocouples 36 26 39Total 104 90 128
Task 8. Pollutant Removal• NO - Captured at very high rates, likely reacted to NO2
20
20%30%40%50%60%70%80%90%
100%1 2 2 3 4 5 6 7 7 8 9 10 11 12 12 13 14 15 16 17 17 18 19 20 21 22 22 23
NO
Cap
ture
Hours
Task 8. Pollutant Capture Data
21
50%
60%
70%
80%
90%
100%
0 15 30 45 60 75 90 105
120
SO2
Capt
ure
Perc
ent
Minutes
% CO2 Removed % SO2 Removed
Task 8. Particulate Capture
22
Rela
tive
part
icle
conc
entr
atio
n
PM2.5 PM4 PM7 PM10
23
Task 8. Mercury Testing• Field test at utility power plant• Inlet 735 ppt, or 5.77 µg/m3
(after wet scrubber) • Outlet below detection limit,
which is 1 ppt, or 0.01 µg/m3
for 99.9%+ capture. • Actual concentrations
predicted to be far below atmospheric levels (1-2 ng/m3).
Acknowledgements• DOE Project Manager: David Lang• Collaborators: Pacificorp, Tristate, EPRI, (Air Liquide, GE,
Holcim, Dong, Chart)• Funding: Dong Energy, DoI, Wyoming Clean Coal Task
Force, DOE-Arpa-E, CCEMC, DOE-NETL• Contributors: Andrew Baxter, Stephanie Burt, Kyler
Stitt, Dave Frankman, Chris Hoeger, Eric Mansfield, Skyler Chamberlain, Aaron Sayre, Jacom Chamberlain