Cryo AIP

48
Cryo AIP Muon Campus AIP Review Arkadiy Klebaner January 23, 2012

description

Cryo AIP. Muon Campus AIP Review Arkadiy Klebaner January 23, 2012. Scope. Compressor system Refrigeration system Cryogenic storage and inventory management Muon g-2 cryogenic distribution system Mu2e cryogenic distribution system Auxiliary systems. Design Options. - PowerPoint PPT Presentation

Transcript of Cryo AIP

Page 1: Cryo AIP

Cryo AIP

Muon Campus AIP Review

Arkadiy Klebaner

January 23, 2012

Page 2: Cryo AIP

Scope

• Compressor system• Refrigeration system• Cryogenic storage and inventory management• Muon g-2 cryogenic distribution system• Mu2e cryogenic distribution system• Auxiliary systems

2

Page 3: Cryo AIP

Design Options1. Procure new refrigerators and compressors2. Procure new refrigerators and reuse Tevatron

compressors3. Reuse Tevatron compressors and refrigerators

a) F0 or b) A0 compressor building

Value Engineering Option “3b” is chosen

3

Page 4: Cryo AIP

Functional Requirements

• Detailed requirements are listed in the “ Muon Campus Cryogenics: Functional Requirements Specification” document #4248 in DocDb, initial release October 2, 2012

https://beamdocs.fnal.gov/AD-private/DocDB/ShowDocument?docid=4248

• The document is agreed upon and signed by both experiments and management

4

Page 5: Cryo AIP

Key Requirements• The Cryogenic System shall support

simultaneous steady state operation of both experiments, Muon g-2 and Mu2e. It shall provide for independent operation of the two experiments, including transient modes, e.g. warm-up, cooldown, etc.

• It should be possible to connect and/or isolate Mu2e magnets from the transfer line while under cold conditions

5

Page 6: Cryo AIP

Cryogenic loads:• Muon g-2

– Liquefaction load – 1.4 [g/sec]– Refrigeration load – 300 [W]– LN2 Shield flow rate – 1.6 [g/sec]

• Mu2e– Liquefaction load – 0.8 [g/sec]– Refrigeration load – 350 [W]– LN2 Shield flow rate – 20 [g/sec]

Key Requirements (cont.)

6

Page 7: Cryo AIP

0 1 2 3 4 5 6 7 8 90

200

400

600

800

1,000

1,200

1,400

Two Tevatron Satellite Refrigerators Operating Field

Liquefaction, [g/sec]

Ref

riger

atio

n, [W

atts

]

Theoretical Two Plants Capacity

Delivered Capacity

7

Page 8: Cryo AIP

0 1 2 3 4 5 6 7 8 90

200

400

600

800

1,000

1,200

1,400

Mu2e

Two Tevatron Satellite Refrigerators Operating Field

Liquefaction, [g/sec]

Ref

riger

atio

n, [W

atts

]

Theoretical Two Plants Capacity

Delivered Capacity

8

Page 9: Cryo AIP

0 1 2 3 4 5 6 7 8 90

200

400

600

800

1,000

1,200

1,400

Mu2eg-2

Two Tevatron Satellite Refrigerators Operating Field

Liquefaction, [g/sec]

Ref

riger

atio

n, [W

atts

]

Theoretical Two Plants Capacity

Delivered Capacity

Theoretical Two Plants Capacity

Delivered Capacity

Theoretical Two Plants Capacity

Delivered Capacity

9

Page 10: Cryo AIP

0 1 2 3 4 5 6 7 8 90

200

400

600

800

1,000

1,200

1,400

Mu2eg-2

Two Tevatron Satellite Refrigerators Operating Field

Liquefaction, [g/sec]

Ref

riger

atio

n, [W

atts

]

Theoretical Two Plants Capacity

Delivered Capacity

Theoretical Two Plants Capacity

Delivered Capacity

Theoretical Two Plants Capacity

Delivered Capacity

Single RefrigeratorDelivered Capacity

10

Page 11: Cryo AIP

0 1 2 3 4 5 6 7 8 90

200

400

600

800

1,000

1,200

1,400

Mu2eg-2

Two Tevatron Satellite Refrigerators Operating Field

Liquefaction, [g/sec]

Ref

riger

atio

n, [W

atts

]

Theoretical Two Plants Capacity

Delivered Capacity

Theoretical Two Plants Capacity

Delivered Capacity

Theoretical Two Plants Capacity

Delivered Capacity

Single RefrigeratorDelivered Capacity

Uncertainty factor = 1.5

Uncertainty factor covers underestimated heat load that is result of unknown heat leaks during components assembly or simply overlooked heat sources during design phase.

11

Page 12: Cryo AIP

0 1 2 3 4 5 6 7 8 90

200

400

600

800

1,000

1,200

1,400

Mu2eg-2

Two Tevatron Satellite Refrigerators Operating Field

Liquefaction, [g/sec]

Ref

riger

atio

n, [W

atts

]

Theoretical Two Plants Capacity

Delivered Capacity

Theoretical Two Plants Capacity

Delivered Capacity

Theoretical Two Plants Capacity

Delivered Capacity

Overcapacity factor covers degradation of system top performance capacity due to a variety of factors including contamination, components wear and tear, etc.

Single RefrigeratorDelivered Capacity

Uncertainty + Overcapacity factor = 2.0

12

Page 13: Cryo AIP

0 1 2 3 4 5 6 7 8 90

200

400

600

800

1,000

1,200

1,400

Mu2eg-2

Two Tevatron Satellite Refrigerators Operating Field

Liquefaction, [g/sec]

Ref

riger

atio

n, [W

atts

]

Theoretical Two Plants Capacity

Delivered Capacity

Theoretical Two Plants Capacity

Delivered Capacity

Theoretical Two Plants Capacity

Delivered Capacity

Single RefrigeratorDelivered Capacity

mar

gin

Uncertainty + Overcapacity factor = 2.0

13

Page 14: Cryo AIP

Current Design Concept

• Reuse TeV compressors and heat exchangers– A0 compressors– Four (4) Satellite refrigerators

• Two dedicated refrigerators per experiment

• Reuse TeV valve boxes, transfer lines, expansion boxes, dewars, storage tanks, etc.

• Positive isolation for Mu2e and hard connection to g-2

• New controls (hardware)

14

Page 15: Cryo AIP

15

Page 16: Cryo AIP

Compressor system• A0 compressors (four skids)

• Each skid consists of the following:• Two-stage oil injected screw compressor• 300 kW motor• 60 g/s capacity• Compression from 1 atm to 20 atm• Slide valve for capacity control• 6 kW oil pump• Oil cooler heat exchanger• Aftercooler heat exchanger• Oil separator• Oil removal system• Entire system is contained on a single,

fabricated steel base skid, oil removal on separate skidTwo-stage compound oil flooded

screw compressor Mycom 2016C

16

Page 17: Cryo AIP

Slide 17

Helically grooved rotorsMycom 2016C Two-Stage

Compressor system (cont.)

Page 18: Cryo AIP

Slide 18

Four skidsConsists of:• Oil Separator (located on compr skid)• Oil Coalescers (3 stages)• Charcoal Adsorber

• Removes oil vapor• Molecular Sieve

• Removes water vapor• Final Filter

• Contains 1 micron filter element

Oil Removal System

Page 19: Cryo AIP

Slide 19

Heat Exchanger• 35 ft. long heat exchanger• Consists of four heat exchangers housed in a single cryostat• Nitrogen precooling• U-tube connections for high pressure, low pressure helium and gas expander

Page 20: Cryo AIP

Slide 20

Refrigerator Valve Box

• Connects all refrigerator components together using u-tubes• Provides positive isolation between different components by removing u-tubes• Distributes cryogens to and from load and includes necessary control valves• Contains 130 liter subcooling dewar

Page 21: Cryo AIP

Slide 21

Expansion Engines

• Two engine types• Liquid “wet” expansion engine• 30K gas “dry” expansion engine• 3 in and 2 in piston sizes• 2 hp and 7.5 hp respectively

Page 22: Cryo AIP

Slide 22

Gas Storage• Two gas storage consists of 30,000 gal nominal capacity storage

tanks• Overall length of 66 ft with an outside diameter of 9 ft

Page 23: Cryo AIP

Nitrogen Tank

• 15,000 gal• MAWP 150 psig• 10' outside diameter• 30' tall• 65,000 # empty

23

Page 24: Cryo AIP

Controls

24

Page 25: Cryo AIP

Piping headers

Towards A0 25

Page 26: Cryo AIP

Mu2e Connection

26

Page 27: Cryo AIP

Refrigerator room

27

Page 28: Cryo AIP

Refrigerator room (cont.)

28

Page 29: Cryo AIP

Refrigerator room (cont.)

29

Page 30: Cryo AIP

Refrigerator room (cont.)

30

Page 31: Cryo AIP

Refrigerator room (cont.)

31

Page 32: Cryo AIP

Transfer line

32

Page 33: Cryo AIP

Transfer line (cont.)

33

Page 34: Cryo AIP

Transfer line (cont.)

34

Page 35: Cryo AIP

Gas Management Panel

35

Page 36: Cryo AIP

Slide 36

Plant and g-2

g-2 cryo distribution

CY 2017CY 2015CY 2014CY 2013 CY 2016

Compressors

g-2

Mu2e distribution

Mu2e cryo distribution

Mu2e

Refrigerators

g-2

Refurbishment and installationProcurement and installation CooldownEngineering and design

Project Plan: Timeline

Project funds available Building beneficial occupancy

$ $

MC-1 Mu2e

$ $ $

Page 37: Cryo AIP

Project Plan

Baseline Costs

WBS Name Base cost

with escalation

Contingency Indirect costs Total

1 Muon Campus Cryogenics - AIP $5,356,750 $1,905,238 $2,519,607 $9,781,595 1.01 Interface milestones - - - - 1.02 Project management $166,614 $81,799 $160,582 $408,996 1.03 System engineering $77,967 $38,278 $75,145 $191,390 1.04 Cryogenic plant sub systems $2,353,671 $836,530 $1,082,744 $4,272,945 1.05 Experiment interfaces $2,589,448 $865,635 $1,038,206 $4,493,289 1.06 Safety documents $93,061 $45,688 $89,692 $228,442 1.07 Commissioning $75,989 $37,307 $73,238 $186,533

TPC ~ $9.8M

37

Page 38: Cryo AIP

Basis of Estimate• Basis of estimates for key project elements are

completed• Prior experience is dominant costing method

38

Page 39: Cryo AIP

Escalation and Contingency

• Escalation– M&S= 2.7% /year – SWF= 2.7 % /year

• Contingency– Average 25%– Exception on items similar to the currently

procured for other projects. The smallest contingency is 20%.

39

Page 40: Cryo AIP

Funding Profile FY13 FY14 FY15 FY16 FY17 Total Labor

SWF base escalated $230,492 $967,862 $231,222 $330,566 $95,613 $1,855,756 SWF indirect costs $222,148 $932,826 $222,852 $318,600 $92,152 $1,788,577 Subtotal $452,640 $1,900,688 $454,074 $649,166 $187,764 $3,644,333 SWF Contingency $113,160 $475,172 $113,519 $162,292 $46,941 $911,083 Total $565,801 $2,375,860 $567,593 $811,458 $234,706 $4,555,416 M&S

M&S base escalated $334,000 $1,853,158 $0 $1,154,855 $158,981 $3,500,994 M&S indirect cost $68,103 $417,122 $0 $213,388 $32,416 $731,029 Subtotal $402,103 $2,270,280 $0 $1,368,243 $191,397 $4,232,023 M&S Contingency $77,953 $567,570 $0 $300,783 $47,849 $994,155

Total $480,055 $2,837,850 $0 $1,669,026 $239,247 $5,226,178 Total

SWF+M&S base esc $564,492 $2,821,020 $231,222 $1,485,421 $254,594 $5,356,750 SWF+M&S Indirects $290,251 $1,349,948 $222,852 $531,988 $124,568 $2,519,607 Subtotal $854,743 $4,170,968 $454,074 $2,017,410 $379,162 $7,876,356 SWF+M&S contingency $191,113 $1,042,742 $113,519 $463,074 $94,790 $1,905,238 Total $1,045,856 $5,213,710 $567,593 $2,480,484 $473,952 $9,781,594

40

Page 41: Cryo AIP

FY13 FY14 FY15 FY16 FY17 Total

Cryo Engineer 0.18 1.20 0.73 0.46 2.57 Cryo Tech 0.95 0.16 0.27 0.19 1.57 Designer and drafter 0.40 0.27 0.16 0.64 1.47 Electrical Engineer 0.26 0.77 0.09 0.38 1.51 Electrical Tech 0.54 1.51 0.16 1.05 0.07 3.33 Mechanical Task Manager 1.92 1.92 Mechanical Tech 0.45 2.06 2.93 0.61 6.06 Project Manager 0.15 0.19 0.20 0.20 0.11 0.85

Total FTEs 1.99 8.87 1.51 5.94 0.98

Labor by Categories

41

Page 42: Cryo AIP

FY 13 M&S• Long lead items procurement• Removing equipment and refurbishing TeV equipment (1

FTE)• Engineering &Design (1 FTE)

WBS Name FY13 1 Muon Campus Cryogenics - AIP $ 334,000 1.04 Cryogenic plant sub systems $ 334,000 1.04.04 Refrigerator system $ 334,000 1.04.04.02 Heat exchangers $ 60,000 1.04.04.04 Engines $ 85,000 1.04.04.09 Controls $ 159,000 1.04.04.10 Distribution system $ 30,000

42

Page 43: Cryo AIP

FY14 M&S

• Installing TeV equipment• Running headers from A0• Connecting to g-2• Cooling down g-2

WBS Name FY14 1 Muon Campus Cryogenics - AIP $ 1,853,158

1.04 Cryogenic plant sub systems $ 1,278,038 1.04.01 LN2 system $ 184,860 1.04.02 Gas management system $ 62,583 1.04.03 ODH system $ 10,270 1.04.04 Refrigerator system $ 640,335 1.04.05 Compressor System $ 379,990

1.05 Experiment interfaces $ 575,120 1.05.01 Interconnect electrical & controls $ 10,270 1.05.02 Interconnect piping $ 462,150 1.05.04 g-2 interface connection $ 102,700

9 FTE

43

Page 44: Cryo AIP

FY15

• No M&S• Mu2e E&D work (1.5 FTE)• Will need g-2 operational funds

44

Page 45: Cryo AIP

FY16

• Procuring Mu2e transferline components• Refurbishing and installing TeV transferline,

expansion box and headers• Refurbishing and installing AP10 bayonet can

WBS Name FY16 1 Muon Campus Cryogenics - AIP $ 1,154,855

1.05 Experiment interfaces $ 1,154,855 1.05.03 Mu2e interface connection $ 1,154,855 1.05.03.01 Mu2e interface connection Cooldown return $ 118,070 1.05.03.02 Mu2e interface connection Distribution box $ 704,087 1.05.03.03 Mu2e interface connection Expansion box $ 54,161 1.05.03.04 Mu2e interface connection Transfer line w/expansion joints $ 224,378 1.05.03.05 Mu2e interface connection Bayonet cans $ 54,161

5.94 FTE

45

Page 46: Cryo AIP

FY17

• Connecting Mu2e• Cooling down Mu2e

WBS Name FY17 1 Muon Campus Cryogenics - AIP $ 158,981

1.05 Experiment interfaces $ 158,981 1.05.03 Mu2e interface connection $ 158,981 1.05.03.04 Mu2e interface connection Transfer line w/expansion joints $ 158,981

0.8 FTE

46

Page 47: Cryo AIP

Milestones

MILESTONE DEFINITION BASELINE

Start Project Directive signed, funding available Month 0

Basic engineering is completed System detailed engineering is complete, installation

drawings and specifications are finished

Month 14

Begin refrigerator building installation Refrigerator building and A0 to MC1 piping support

beneficial occupancy

Month 14

Compressor system is ready All compressors are refurbished Month 19

Refrigeration system commissioned Heat exchangers, expanders, gas management system,

storage are installed

Month 22

Muon g-2 acceptance tests The Muon g-2 distribution system is cold Month 22

Mu2e acceptance tests The Mu2e distribution system is cold Month 57

Project Complete Project Closed Month 58

47

Page 48: Cryo AIP

Thank you!

48