Cryo AIP
description
Transcript of Cryo AIP
Cryo AIP
Muon Campus AIP Review
Arkadiy Klebaner
January 23, 2012
Scope
• Compressor system• Refrigeration system• Cryogenic storage and inventory management• Muon g-2 cryogenic distribution system• Mu2e cryogenic distribution system• Auxiliary systems
2
Design Options1. Procure new refrigerators and compressors2. Procure new refrigerators and reuse Tevatron
compressors3. Reuse Tevatron compressors and refrigerators
a) F0 or b) A0 compressor building
Value Engineering Option “3b” is chosen
3
Functional Requirements
• Detailed requirements are listed in the “ Muon Campus Cryogenics: Functional Requirements Specification” document #4248 in DocDb, initial release October 2, 2012
https://beamdocs.fnal.gov/AD-private/DocDB/ShowDocument?docid=4248
• The document is agreed upon and signed by both experiments and management
4
Key Requirements• The Cryogenic System shall support
simultaneous steady state operation of both experiments, Muon g-2 and Mu2e. It shall provide for independent operation of the two experiments, including transient modes, e.g. warm-up, cooldown, etc.
• It should be possible to connect and/or isolate Mu2e magnets from the transfer line while under cold conditions
5
Cryogenic loads:• Muon g-2
– Liquefaction load – 1.4 [g/sec]– Refrigeration load – 300 [W]– LN2 Shield flow rate – 1.6 [g/sec]
• Mu2e– Liquefaction load – 0.8 [g/sec]– Refrigeration load – 350 [W]– LN2 Shield flow rate – 20 [g/sec]
Key Requirements (cont.)
6
0 1 2 3 4 5 6 7 8 90
200
400
600
800
1,000
1,200
1,400
Two Tevatron Satellite Refrigerators Operating Field
Liquefaction, [g/sec]
Ref
riger
atio
n, [W
atts
]
Theoretical Two Plants Capacity
Delivered Capacity
7
0 1 2 3 4 5 6 7 8 90
200
400
600
800
1,000
1,200
1,400
Mu2e
Two Tevatron Satellite Refrigerators Operating Field
Liquefaction, [g/sec]
Ref
riger
atio
n, [W
atts
]
Theoretical Two Plants Capacity
Delivered Capacity
8
0 1 2 3 4 5 6 7 8 90
200
400
600
800
1,000
1,200
1,400
Mu2eg-2
Two Tevatron Satellite Refrigerators Operating Field
Liquefaction, [g/sec]
Ref
riger
atio
n, [W
atts
]
Theoretical Two Plants Capacity
Delivered Capacity
Theoretical Two Plants Capacity
Delivered Capacity
Theoretical Two Plants Capacity
Delivered Capacity
9
0 1 2 3 4 5 6 7 8 90
200
400
600
800
1,000
1,200
1,400
Mu2eg-2
Two Tevatron Satellite Refrigerators Operating Field
Liquefaction, [g/sec]
Ref
riger
atio
n, [W
atts
]
Theoretical Two Plants Capacity
Delivered Capacity
Theoretical Two Plants Capacity
Delivered Capacity
Theoretical Two Plants Capacity
Delivered Capacity
Single RefrigeratorDelivered Capacity
10
0 1 2 3 4 5 6 7 8 90
200
400
600
800
1,000
1,200
1,400
Mu2eg-2
Two Tevatron Satellite Refrigerators Operating Field
Liquefaction, [g/sec]
Ref
riger
atio
n, [W
atts
]
Theoretical Two Plants Capacity
Delivered Capacity
Theoretical Two Plants Capacity
Delivered Capacity
Theoretical Two Plants Capacity
Delivered Capacity
Single RefrigeratorDelivered Capacity
Uncertainty factor = 1.5
Uncertainty factor covers underestimated heat load that is result of unknown heat leaks during components assembly or simply overlooked heat sources during design phase.
11
0 1 2 3 4 5 6 7 8 90
200
400
600
800
1,000
1,200
1,400
Mu2eg-2
Two Tevatron Satellite Refrigerators Operating Field
Liquefaction, [g/sec]
Ref
riger
atio
n, [W
atts
]
Theoretical Two Plants Capacity
Delivered Capacity
Theoretical Two Plants Capacity
Delivered Capacity
Theoretical Two Plants Capacity
Delivered Capacity
Overcapacity factor covers degradation of system top performance capacity due to a variety of factors including contamination, components wear and tear, etc.
Single RefrigeratorDelivered Capacity
Uncertainty + Overcapacity factor = 2.0
12
0 1 2 3 4 5 6 7 8 90
200
400
600
800
1,000
1,200
1,400
Mu2eg-2
Two Tevatron Satellite Refrigerators Operating Field
Liquefaction, [g/sec]
Ref
riger
atio
n, [W
atts
]
Theoretical Two Plants Capacity
Delivered Capacity
Theoretical Two Plants Capacity
Delivered Capacity
Theoretical Two Plants Capacity
Delivered Capacity
Single RefrigeratorDelivered Capacity
mar
gin
Uncertainty + Overcapacity factor = 2.0
13
Current Design Concept
• Reuse TeV compressors and heat exchangers– A0 compressors– Four (4) Satellite refrigerators
• Two dedicated refrigerators per experiment
• Reuse TeV valve boxes, transfer lines, expansion boxes, dewars, storage tanks, etc.
• Positive isolation for Mu2e and hard connection to g-2
• New controls (hardware)
14
15
Compressor system• A0 compressors (four skids)
• Each skid consists of the following:• Two-stage oil injected screw compressor• 300 kW motor• 60 g/s capacity• Compression from 1 atm to 20 atm• Slide valve for capacity control• 6 kW oil pump• Oil cooler heat exchanger• Aftercooler heat exchanger• Oil separator• Oil removal system• Entire system is contained on a single,
fabricated steel base skid, oil removal on separate skidTwo-stage compound oil flooded
screw compressor Mycom 2016C
16
Slide 17
Helically grooved rotorsMycom 2016C Two-Stage
Compressor system (cont.)
Slide 18
Four skidsConsists of:• Oil Separator (located on compr skid)• Oil Coalescers (3 stages)• Charcoal Adsorber
• Removes oil vapor• Molecular Sieve
• Removes water vapor• Final Filter
• Contains 1 micron filter element
Oil Removal System
Slide 19
Heat Exchanger• 35 ft. long heat exchanger• Consists of four heat exchangers housed in a single cryostat• Nitrogen precooling• U-tube connections for high pressure, low pressure helium and gas expander
Slide 20
Refrigerator Valve Box
• Connects all refrigerator components together using u-tubes• Provides positive isolation between different components by removing u-tubes• Distributes cryogens to and from load and includes necessary control valves• Contains 130 liter subcooling dewar
Slide 21
Expansion Engines
• Two engine types• Liquid “wet” expansion engine• 30K gas “dry” expansion engine• 3 in and 2 in piston sizes• 2 hp and 7.5 hp respectively
Slide 22
Gas Storage• Two gas storage consists of 30,000 gal nominal capacity storage
tanks• Overall length of 66 ft with an outside diameter of 9 ft
Nitrogen Tank
• 15,000 gal• MAWP 150 psig• 10' outside diameter• 30' tall• 65,000 # empty
23
Controls
24
Piping headers
Towards A0 25
Mu2e Connection
26
Refrigerator room
27
Refrigerator room (cont.)
28
Refrigerator room (cont.)
29
Refrigerator room (cont.)
30
Refrigerator room (cont.)
31
Transfer line
32
Transfer line (cont.)
33
Transfer line (cont.)
34
Gas Management Panel
35
Slide 36
Plant and g-2
g-2 cryo distribution
CY 2017CY 2015CY 2014CY 2013 CY 2016
Compressors
g-2
Mu2e distribution
Mu2e cryo distribution
Mu2e
Refrigerators
g-2
Refurbishment and installationProcurement and installation CooldownEngineering and design
Project Plan: Timeline
Project funds available Building beneficial occupancy
$ $
MC-1 Mu2e
$ $ $
Project Plan
Baseline Costs
WBS Name Base cost
with escalation
Contingency Indirect costs Total
1 Muon Campus Cryogenics - AIP $5,356,750 $1,905,238 $2,519,607 $9,781,595 1.01 Interface milestones - - - - 1.02 Project management $166,614 $81,799 $160,582 $408,996 1.03 System engineering $77,967 $38,278 $75,145 $191,390 1.04 Cryogenic plant sub systems $2,353,671 $836,530 $1,082,744 $4,272,945 1.05 Experiment interfaces $2,589,448 $865,635 $1,038,206 $4,493,289 1.06 Safety documents $93,061 $45,688 $89,692 $228,442 1.07 Commissioning $75,989 $37,307 $73,238 $186,533
TPC ~ $9.8M
37
Basis of Estimate• Basis of estimates for key project elements are
completed• Prior experience is dominant costing method
38
Escalation and Contingency
• Escalation– M&S= 2.7% /year – SWF= 2.7 % /year
• Contingency– Average 25%– Exception on items similar to the currently
procured for other projects. The smallest contingency is 20%.
39
Funding Profile FY13 FY14 FY15 FY16 FY17 Total Labor
SWF base escalated $230,492 $967,862 $231,222 $330,566 $95,613 $1,855,756 SWF indirect costs $222,148 $932,826 $222,852 $318,600 $92,152 $1,788,577 Subtotal $452,640 $1,900,688 $454,074 $649,166 $187,764 $3,644,333 SWF Contingency $113,160 $475,172 $113,519 $162,292 $46,941 $911,083 Total $565,801 $2,375,860 $567,593 $811,458 $234,706 $4,555,416 M&S
M&S base escalated $334,000 $1,853,158 $0 $1,154,855 $158,981 $3,500,994 M&S indirect cost $68,103 $417,122 $0 $213,388 $32,416 $731,029 Subtotal $402,103 $2,270,280 $0 $1,368,243 $191,397 $4,232,023 M&S Contingency $77,953 $567,570 $0 $300,783 $47,849 $994,155
Total $480,055 $2,837,850 $0 $1,669,026 $239,247 $5,226,178 Total
SWF+M&S base esc $564,492 $2,821,020 $231,222 $1,485,421 $254,594 $5,356,750 SWF+M&S Indirects $290,251 $1,349,948 $222,852 $531,988 $124,568 $2,519,607 Subtotal $854,743 $4,170,968 $454,074 $2,017,410 $379,162 $7,876,356 SWF+M&S contingency $191,113 $1,042,742 $113,519 $463,074 $94,790 $1,905,238 Total $1,045,856 $5,213,710 $567,593 $2,480,484 $473,952 $9,781,594
40
FY13 FY14 FY15 FY16 FY17 Total
Cryo Engineer 0.18 1.20 0.73 0.46 2.57 Cryo Tech 0.95 0.16 0.27 0.19 1.57 Designer and drafter 0.40 0.27 0.16 0.64 1.47 Electrical Engineer 0.26 0.77 0.09 0.38 1.51 Electrical Tech 0.54 1.51 0.16 1.05 0.07 3.33 Mechanical Task Manager 1.92 1.92 Mechanical Tech 0.45 2.06 2.93 0.61 6.06 Project Manager 0.15 0.19 0.20 0.20 0.11 0.85
Total FTEs 1.99 8.87 1.51 5.94 0.98
Labor by Categories
41
FY 13 M&S• Long lead items procurement• Removing equipment and refurbishing TeV equipment (1
FTE)• Engineering &Design (1 FTE)
WBS Name FY13 1 Muon Campus Cryogenics - AIP $ 334,000 1.04 Cryogenic plant sub systems $ 334,000 1.04.04 Refrigerator system $ 334,000 1.04.04.02 Heat exchangers $ 60,000 1.04.04.04 Engines $ 85,000 1.04.04.09 Controls $ 159,000 1.04.04.10 Distribution system $ 30,000
42
FY14 M&S
• Installing TeV equipment• Running headers from A0• Connecting to g-2• Cooling down g-2
WBS Name FY14 1 Muon Campus Cryogenics - AIP $ 1,853,158
1.04 Cryogenic plant sub systems $ 1,278,038 1.04.01 LN2 system $ 184,860 1.04.02 Gas management system $ 62,583 1.04.03 ODH system $ 10,270 1.04.04 Refrigerator system $ 640,335 1.04.05 Compressor System $ 379,990
1.05 Experiment interfaces $ 575,120 1.05.01 Interconnect electrical & controls $ 10,270 1.05.02 Interconnect piping $ 462,150 1.05.04 g-2 interface connection $ 102,700
9 FTE
43
FY15
• No M&S• Mu2e E&D work (1.5 FTE)• Will need g-2 operational funds
44
FY16
• Procuring Mu2e transferline components• Refurbishing and installing TeV transferline,
expansion box and headers• Refurbishing and installing AP10 bayonet can
WBS Name FY16 1 Muon Campus Cryogenics - AIP $ 1,154,855
1.05 Experiment interfaces $ 1,154,855 1.05.03 Mu2e interface connection $ 1,154,855 1.05.03.01 Mu2e interface connection Cooldown return $ 118,070 1.05.03.02 Mu2e interface connection Distribution box $ 704,087 1.05.03.03 Mu2e interface connection Expansion box $ 54,161 1.05.03.04 Mu2e interface connection Transfer line w/expansion joints $ 224,378 1.05.03.05 Mu2e interface connection Bayonet cans $ 54,161
5.94 FTE
45
FY17
• Connecting Mu2e• Cooling down Mu2e
WBS Name FY17 1 Muon Campus Cryogenics - AIP $ 158,981
1.05 Experiment interfaces $ 158,981 1.05.03 Mu2e interface connection $ 158,981 1.05.03.04 Mu2e interface connection Transfer line w/expansion joints $ 158,981
0.8 FTE
46
Milestones
MILESTONE DEFINITION BASELINE
Start Project Directive signed, funding available Month 0
Basic engineering is completed System detailed engineering is complete, installation
drawings and specifications are finished
Month 14
Begin refrigerator building installation Refrigerator building and A0 to MC1 piping support
beneficial occupancy
Month 14
Compressor system is ready All compressors are refurbished Month 19
Refrigeration system commissioned Heat exchangers, expanders, gas management system,
storage are installed
Month 22
Muon g-2 acceptance tests The Muon g-2 distribution system is cold Month 22
Mu2e acceptance tests The Mu2e distribution system is cold Month 57
Project Complete Project Closed Month 58
47
Thank you!
48