Crossrail_presentation_Dec2012
-
Upload
tony-fleming -
Category
Documents
-
view
29 -
download
0
Transcript of Crossrail_presentation_Dec2012
11 December 2012
1
Crossrail and LU Supporting works
Copyright © 2012 Transport for London. All rights reserved. This information is confidential. You may not reproduce, adapt or disclose this information, or any part of this information, for any purpose without TfL’s written permission. TfL makes no warranties or representations, and expressly disclaims all liability, concerning this information.
Crossrail – The History
• A rail route traversing London from east to west
• Runs from Maidenhead, through London, terminating at Shenfield & Abbey Wood
• Idea dates back to (at least) 1943
• Further discussed in reports by the GLC in 1969 and British Rail in 1974 (the latter report coined the term “Crossrail”)
• Crossrail plan approved 2007
2
Crossrail – The benefits
• By 2031 an additional 1.3 million people will be working in London with an extra seven hundred thousand journeys a day.
• It will bring and extra 1.5 million people within 45 minutes’ commuting distance of London.
• Reduced journey times. For example:
3
Crossrail – Journey times
Example journey Existing journey time
Crossrail journey time
Slough to Tottenham Court Road 55 minutes 36 minutes
Heathrow to Liverpool Street 55 minutes 36 minutes
Liverpool Street to Abbey Wood 40 minutes 22 minutes
Paddington to Canary Wharf 30 minutes 17 minutes
4
5
Crossrail – How big is it?
• Over 100km long and the largest construction project in Europe
• Go live in 2018
• Two new 21km-long tunnels will carry trains in London
6
Crossrail – the map
Crossrail – Geographical scope
• Installations work is focussed on those stations making up the ‘Central Section’ i.e.– Paddington– Bond Street– Tottenham Court Road– Canary Wharf– Liverpool Street– Whitechapel– Farringdon– Custom House
7
Crossrail – Installation objectives
• Make changes to existing LU stations in order to support local Crossrail works and...
• Procure and install ticketing and revenue equipment at ‘new builds’ i.e. the Crossrail stations themselves
8
Typical Installation activities
• Design support; Define scope of works with the client and Cubic, carry out site visits, comment on drawings, advise client on project dependencies
• Procurement; Confirm hardware requirement, produce initial cost estimate for budgeting purposes, submit procurement order and track delivery progress.
9
Typical Installation activities
• Installation; make sure that Cubic’s requirements for installing equipment e.g. Data, power, containment and civil works are supplied, co-ordinate testing services (supplied by Service Team) with the end of Cubic’s works on site
• Handover; review test results, advise client on completion of works, collate handover documentation e.g. ‘as-built’ drawings, test certificates.
10
11
Progress to date
Paddington• Objectives: Construction of a new Ticket Hall for
the H&C line, to cope with increased customer demand through Crossrail.
• Progress: Gateline installed and operational. Construction of the Station Operations Room and POM Suite outstanding
12Copyright © 2012 Transport for London. All rights reserved. This information is confidential.
Bond Street• Objectives: Construct an additional Ticket Hall for
LU, make the existing gateline fully bi-directional to cope with the passenger flow during Crossrail construction.
• Progress: Awaiting go-ahead from client to carry out gateline works.
13Copyright © 2012 Transport for London. All rights reserved. This information is confidential.
Tottenham Court Road
14Copyright © 2012 Transport for London. All rights reserved. This information is confidential.
15
From this....Single gateline of 13 Pneumatic Gates, requiring an air-supply from LU’s old signal system
Station Operations Room is in another part of the station. Staff need CCTV to see what is happening
16
To this....Two gatelines; one for the Central Line and one for Northern Line and Crossrail
31 gates in total
New Station Ops Room (this time with direct line of sight to the Ticket Hall!)
17
Tottenham Court Road• Progress: Ongoing design support, have
procured gates for the Northern/Crossrail gateline
18Copyright © 2012 Transport for London. All rights reserved. This information is confidential.
Liverpool Street• Objectives: Procure and install a new gateline at
Liverpool Street (LU), move Station Ops Room, recable ticketing assets to a new switch room.
• Progress: Station Ops Room moved, assets for new gateline procured
19Copyright © 2012 Transport for London. All rights reserved. This information is confidential.
Whitechapel• Objectives: Construct a temporary Ticket Hall,
during Crossrail construction works.
• Progress: Design support variation in place and detailing client scope of works
20Copyright © 2012 Transport for London. All rights reserved. This information is confidential.
Canary Wharf• Objectives: Provide design support and procure
assets to tit out a new station for Crossrail services.
• Progress: Design support variation in place and detailing client scope of works
21Copyright © 2012 Transport for London. All rights reserved. This information is confidential.
Key Milestones – short/medium term
22
Milestone Description Baseline
Bi-directional gateline works at Bond St Jan 2013
New Liverpool St gateline in place June 2013
Remove assets from Moorgate ticket hall Sept 2013
Temporary Ticket Hall at Whitechapel June 2014
Go live of additional ticket hall at Bond St June 2015
Go-live of new Northern line/Crossrail gateline at Tottenham Ct Road Dec 2015
Go-live of new Central line gateline at Tottenham Ct Road June 2016
Copyright © 2012 Transport for London. All rights reserved. This information is confidential.
Key Milestones – longer term
23
Milestone Description Baseline
Go-live of ‘Electra’ contract Aug 2015Confirm client dependencies for Contractor scope of works June 2016
Submit procurement and installation variations for Crossrail station ticketing and gating assets Jan 2017
Assets delivered Jan 2018
Installation works commence June 2018
Go live of Crossrail services Dec 2018
Copyright © 2012 Transport for London. All rights reserved. This information is confidential.
Work to be undertaken next period
• Receive funding for Design Support at Moorgate (part of works at Liverpool St)
• Receive funding for Design Support at Farringdon
• Hold kick off meeting for next phase of works at Liverpool St (new gateline installation)
• Hold kick off meeting for works at Whitechapel.
24Copyright © 2012 Transport for London. All rights reserved. This information is confidential.
Risks and Issues
25Copyright © 2012 Transport for London. All rights reserved. This information is confidential.
• Ensuring WAN, gating and ticketing requirements are included in the Electra contract.
• A new contractor could be in place that has different power, data and civils requirements to Cubic’s
• No single LU client co-ordinating these works
• TVMs are based on what Cubic can provide now (not in 6 years). Not clear if TVM numbers per station take FTP’s popularity into account.
Decisions
26Copyright © 2012 Transport for London. All rights reserved. This information is confidential.
• N/A