CROSS BORDER INTERCONNECTION AND POWER TRADE WITH NEIGHBOURING COUNTRIES

Transcript of CROSS BORDER INTERCONNECTION · CROSS BORDER LINK A cross border interconnection between India and...

CROSS BORDER INTERCONNECTION

AND POWER TRADE WITH

NEIGHBOURING COUNTRIES

Indian Scenario

GROWTH OF INSTALLED CAPACITY FROM

11TH PLAN TO 13TH PLAN ( MW)At the end of

11th Plan

March 2012

Addition

during the 12th

Plan

At the end of

12th Plan

March 2017

Addition

during the 13th

Plan

At the end of

13th Plan

March 2022

Coal/

LIGNITE112022 69280/ 520 181822 56400 238223

Gas 18381 2540 20921 0 20921

Diesel 1200 1200 0 1199.75

TOTAL

THERMAL131603 72340 203943 56400 260343

HYDRO 38990 10897 49887 12000 61887

NUCLEAR 4780.00 5300 10080.00 18000 28080

RENEWABL

E ENERGY

SOURCES

24503 30000 54503 30500 85003

TOTAL 199,877 118,537 318,414 116,900 435,314

TRANSMISSION LINES

TRANSMISS

IONLINES

UNIT At the end of

11th Plan

March 2012

Addition

during the

12th Plan

At the end of

12th Plan

March 2017

Addition

during the

13th Plan

At the end of

13th Plan

March 2022

HVDC

Bipole

line

ckm 7432 9440 16872 130000 494921

765 kV ckm 5250 27000 32250

400 kV ckm 106819 38000 144819

230/220

kV

ckm 135980 35000 170980

Total

Transmis

sion

Lines

ckm 257481 107440 364921 494921

SUB-STATIONS (VALUES IN MVA / MW)

SUBSTATIO

NS

UNIT At the end

of 11th

Plan

March

2012

Addition

during the

12th Plan

At the end

of 12th

Plan

March

2017

Addition

during the

13th Plan

At the end

of 13th

Plan

March

2022

HVDC

Bipole lineMW 9750 12750 22500

300000 992301

765 kV MVA 25000 149000 174000

400 kV MVA 151027 45000 196027

230/220 kV MVA 223774 76000 299774

TOTAL –AC

Substation

Capacity

MVA 399801 270000 669801 992301

Grand TotalMW/

MVA409551 282750 692301 300000 992301

HVDC line (Bipole) (Existing)

(1) Rihand (NR)- Dadri (NR) ±500 kV 1500 MW

(2) Chandrapur(WR)-Padghe(WR) ±500 kV 1500 MW

(3) Talcher-II(ER)-Kolar(SR) ±500 kV 2500 MW

(4) Mundra(WR)-Mahendergarh(NR) ±500 kV 2500 MW

(5)Balia(NR)-Bhiwadi(NR) ±500 kV 2500 MW

HVDC line (Bipole) (Under construction)

(1) Biswanath Chariyali(NER)-Alipurduar(ER)-Agra)(NR) ±800 kV 6000 MW

(2)Angul(ER)-Aligarh(NR) ±800 kV 6000 MW

(3)Champa(WR)- Kurukshetra(NR) ±800 kV 6000 MW

(4) Raigarh (WR) – Paghlur (SR) ±800 kV 6000 MW

HVDC Back To Back (Existing)

1. Gazuwaka 2x500 MW

2. Chandrapur 2x500 MW

3. Vindhayachal 2x500 MW

4. Sasaram 1x500 MW

All regional grids are operating as Synchronous National Grid in the

country at 50 Hz.(31st Dec’13)

IC-238 GW (incl. RES-30GW);

Cap. Addn. by 2016-17~120 GW (incl. RES-30 GW);

STATCOMs at 11 locations & SVC at 3 locations planned by 2016-17;

HVDC Bipole (± 500kV) existing : 5 nos. (10,500 MW) & 4675x2 ckm.

HVDC Back-to-back: 4 nos. (3500MW);

HVDC Bipole (± 800kV, 6000MW) Planned : 4 nos. (24,000 MW) 6007x2

ckm.

TCSC – 5 nos. ; FSC – 33 nos.

SVC – ± 2x140 MVAr at Kanpur-1992;

765kV lines: 9543 ckm. (Feb.,14)

400kV lines: over 1,24,384 ckm.

220kV lines: over 1,43,675 ckm.

IR Capacity: 35450MW (April 14)

by 2016-17: 65550 MW

TRANSMISSION PLANNING & DEVELOPMENT

National Grid is comprising Inter-State (ISTS) and intra-State Transmission ( STUs) systems.

Power system planning has been aligned with the Transmission Planning Criteria (n-1/n-1-1 contigency), EA,2003, National Electricity Policy, Tariff policy, Electricity Grid Code, Regulations and market orientation of the Electricity Sector.

Transmission exercises are carried out in-coordination by CEA, CTU, STUs & other Stakeholders – system finalization & review at Regional Standing Committee on Power System Planning.

Transmission System Development followed on Tariff Based Competitive Bidding (TBCB) Policy-Inter State (5-1-11) & Intra-State(5-1-13)

Transmission charge recovery mechanism is based on Point of Connection (PoC) Tariff methodology

Transmission system Plans for evacuation of 9 coal fired UMPPs (each of 4000MW) at Tilaiya(Bihar), Sasan(MP), Mudra (Gujarat), Krishnapatnam (AP), Chattisgarh(RfQ),Orissa(RfQ), Cheyyur (TN), Karnataka are on the horizon.

Evolved Master Transmission Plans to harness hydro potential in North eastern region and northern region of the country.

Bilateral development and strengthening of cross border transmission systems and power exchange with the neighbouring countries in the SA region..

Indo-Nepal interconnection

INDO-NEPAL

Power exchange taking place on the principle of catering to

the power needs of isolated local areas of both of the sides

of the border between NEA and utilities on the Indian side

namely BSEB, UPPCL and UPCL

12 cross border Bilateral power exchange facilities

operational at 11kV, 33kV and 132 kV level.

The above State utilities export power to Nepal and the

quantum of power exchange volume for which tariff is

decided by the Power Exchange Committee (PEC) is

limited to about 50 MW.

INDO-NEPAL (EXISTING LINKS)Sl. No Voltage level Interconnection

1 132 kV

BSEB(Bihar)-

Nepal

Kataiya – Kusaha/Duhabi S/C (High capacity ACSR conductor) line

2 Ramnagar - Gandak/Surajpura(Nepal) S/C

1 33 kV

BSEB(Bihar)-

Nepal

Sitamarhi –Jaleshwer S/C

2 Raxaul-Birganj S/C

3 Jainnagar-Siraha S/C

4 Kataiya – Rajbiraj S/C

5 Kataiya – Inarwa/Biratnagar(Rupni) S/C (not in service)

UPPCL(UP)-Nepal

1 33 kV Nanpara-Nepalganj S/C line

UPCL (Uttaranchal) –

Nepal

1 33 kV Lohiyahead – Gaddachowki/Mahendranagar (Nepal) S/C

1 11 kV Pithoragarh – Baitadi

2 Dharchula – Jaljibe

3 Dharchula – Pipli

INDO-NEPAL For the first 50 MW power supply the average power tariff

during 2013-2015 at 33 kV level comes out to be aroundRs. 5.46/unit with an additional charge or rebate of 7.5 % ifdrawn at 11 kV or 132 kV respectively.

For additional import beyond 50 MW by Nepal, Nepalneeds to tie-up directly from Indian Electricity marketthrough licensed electricity traders such as PTC oncommercial basis, and its tariff would be beyond thepurview of the Power Exchange Committee. Nepalprocures 20-25 MW from India market through PTC.

Through the 132 kV Tanakpur-Mahendranagar S/Cline 70 MU free power from Tanakpur HEP (120 MW) issupplied to Nepal under the Mahakali treaty. Presently,Nepal is drawing about 109-210 MW from India.

ADDITIONAL SYSTEM STRENGTHENING FOR

SUPPLY OF POWER TO NEPAL

Under the medium term measure for supply of additional power of about 100

MW to Nepal MEA is being implemented through WAPCOS(expected by

August 2015).

132 kV Katiya - Kusaha S/C on D/C line with Panther conductor

132 kV Raxaul - Parwanipur S/C on D/C line with Panther conductor

Agreement Signed in July’12 for 400 kV Muzaffarpur (India)- Dhalkebar

(Nepal) D/C line to be initially operated at 220 kV. expected by June 2015

Indian portion- 86.43kms by CPTC,

Nepal portion- 39kms by PTCN,

CPTC with share holders of PGCIL-26%,SJVNL-26%,IL&FS-38% & NEA-

10%

PTCN with share holders of NEA-50%, PGCIL-26%,HIDCL-14% &

IL&FS-10%)

Power Trading: Power Sale Agreement (PSA) between NEA and PTC has been

signed for import of 150 MW for 25years

As a part of Agreement between government of Nepal and Government of the

India on Electric Power Trade, cross Border Transmission Inter-Connection and

Grid Connectivity , the Joint Working Group and Joint Study Committee

was formed.

JWG and JSC decided for preparation of a long term integrated transmission

plan for evacuation of power from the hydro Power Stations in Nepal like Arun-

III HEP (4x225MW) by M/s. SJVNL, Upper Karnali (900 MW) and Upper

Marsyangdi (600 MW) HEPs by M/s GMR, India and related Cross border

inter-connections between the two countries.

The perspective plan will cover the generations likely to come up by 2035 and a

detailed action plan will be prepared for the projects coming up to 2025.

A Joint Technical Team (JTT) comprising of experts from Nepal and India has

been constituted to look into this issue.

Hydro Electric Generation Capacity addition Programme in

Nepal and System Strengthening Requirement

Indo-Bangladesh

Interconnection

CROSS BORDER LINK

A cross border interconnection between India and Bangladesh commissioned on 5th October, 2013. India is supplying to the extent of 500 MW to Bangladesh.

Indian Portion implemented by POWERGRID

Baharampur (India)-Bheramara (Bangladesh) 400kV D/C line: 71 km (after completion of survey)

LILO of Farakka - Jeerat 400kV S/C line at Baharampur : 3 km

Establishment of 400kV Switching Station at Baharampur

Bangladesh portion by Power Grid Company of Bangladesh Ltd.

Baharampur (India)-Bheramara (Bangladesh) 400kV D/C line : 27 km

LILO of Ishurdi - Khulna South 230kV D/C line at Bheramara: 3 km

Establishment of 500MW HVDC back-to-back Station and 230kV Switching Station at Bheramara

AGREEMENTS-CROSS BORDER LINK

PPA signed between Bangladesh Power Development Board (BPDB) and NTPC

Vidyut Vyapar Nigam Ltd. (NVVNL) for supply of 250 MW power from

unallocated share of Govt. of India in Central Generating Stations. The price of

power would be as per CERC tariff.

BPTA signed between POWERGRID and BPDB for Bangladesh procuring an

additional 250MW from the Indian market through PTC.

Under construction / Planned Cross Border Link

In the 8th JSC/JWC meeting it was decided that 100 MW power from Palatana

would be supplied to Bangladesh through radial interconnection through the

following Cross Border Links

Indian side (To be implemented by POWERGRID)

Surjyamaninagar (Tripura) – Bangladesh border 400 kV D/C line (initially

operated at 132 kV) - 27 km (Twin Moose Conductor)

Bangladesh side (To be implemented by BPDB / PGCB of Bangladesh)

Indian Border- Comilla (North) 400 kV D/c line (initially operated at 132 kV)– 15

km (Twin Finch Conductor)

Comilla (North) - Comilla (South) 132kV D/c line – 16km

The above scheme is expected to be completed by Dec., 2015.

The PPA for supply of 100 MW power yet to be finalised.

AGREEMENTS-CROSS BORDER LINK

To facilitate import of additional 500 MW power by Bangladesh from India

through existing Baharampur (India) – Bheramara (Bangladesh) interconnection,

system strengthening on Indian side and Bangladesh side has been approved in

8th JSC/JWC meeting held on 09-10th October, 2014 at New Delhi.

System Strengthening-Indian side (by POWERGRID)

400 kV Farakka - Behrampur D/C (HTLS) line (about 70 km.)

Removal of the existing LILO of 400 kV Farakka - Jeerat S/c line at Beharampur.

LILO of the above Farakka-Jeerat 400 kV S/c line at Sagardighi.

LILO of Sagardighi-Subhasgram 400 kV S/c line at Jeerat

System Strengthening on Bangladesh side (by PGCB)

Bheramara - Ishurdi 230 kV D/c line – 12 km.

Additional 500 MW HVDC back-to-back converter unit (2nd module) at Bheramara

(Bangladesh).

The above scheme is expected to be completed by June 2017.

In order to supply additional 1000 MW from NER to Bangladesh, the

following ±800kV HVDC Bi-pole line has been planned:

Rangia/Rowta (Assam, India)-Barapukuria(Bangladesh)-Muzafarnagar (UP, India) +800kV

6500/7000 MW HVDC Multi terminal Bipole line

DPR is to be prepared.

Indo-Bhutan

Interconnection

EXISTING CROSS BORDER TRANSMISSION SYSTEM

ASSOCIATED WITH THE HEPS IN BHUTAN

India and Bhutan have terms of cooperation for exchange

of power between the two countries. Bulk of power

generated at Hydro Electric Projects at Chukha

(336MW), Kurichu (60MW) and Tala (1020MW) in

Bhutan, is exported to India after meeting the internal

demand of Bhutan.

The associated cross-border transmission systems for

evacuation and transfer of power from these HEPs has

been developed and is operated in synchronism with the

Indian Grid.

Royal Government of Bhutan (RGoB) has embarked on to

harness its huge hydro potential and identified about 75

nos. new HEPs by 2030 at various river basins.

About 26534 MW hydro potential would be harnessed by

2030 and out of this, 10334 MW hydro power

developments from 14 nos. HEPs have been envisaged to

be implemented during 2020.

Most of the future generation in Bhutan would be also

exported to India, after meeting the internal demand of

Bhutan.

Considering the above scenario, National Transmission

Grid Master Plan (NTGMP) for Bhutan has been evolved

by carrying out comprehensive power system studies.

Planned/under-construction Cross border

Transmission links associated with HEPs in Bhutan

RGoB is in the various phases of developing over 10 GWhydro potential by 2020 of which Punatsangchhu-I(1200MW), Punatsangchhu-II (1020MW) and Mangdechhu(720 MW) HEPs are ongoing Projects.

The ATS for the above three HEPs according to theNTGMP Plan is under construction.

Transmission links under Implementation Stage for import of power from Bhutan

LILO of ±800kV, 6000MW Bishwanath Chariyali – Agra HVDC Bi-pole line at Alipurduar with 3000MW HVDC terminal with 400/220kV EHVAC station at Alipurduar

Extension of ± 800 kV HVDC station with 3000 MW inverter module at Agra

LILO of Bongaigaon – Siliguri 400kV D/C Quad Moose line at Alipurduar

LILO of Birpara-Salakati 220kV D/C line at Alipurduar

Planned/under-construction Cross border

Transmission links associated with HEPs in Bhutan

India-Sri Lanka

interconnection

Cross-Border link/proposal

Memorandum of Understanding has been signed among

Govt. of India, Govt. of Sri Lanka, PGCIL and Ceylon

Electricity Board on 9th June 2010 for carrying out

feasibility study for interconnection of India–Sri Lanka

Electricity Grid.

POWERGRID, India and CEB, Sri Lanka has been

appointed as executive agencies for the above project.

1000MW, ±400kV HVDC bi-pole line from India (Madurai) to

Sri Lanka (Anuradhapura): 360km

Indian Territory (Scope : POWERGRID) Madurai to Panaikulam

: 130km

Sea Route (Scope: POWERGRID) Panaikulam (India) to

Thirukketiswaram(SL): 120km

Sri Lankan Territory (Scope: CEB) Thirukketiswaram to

Anuradhapura(New) : 110km

ADDITIONAL OPTION

In a meeting between the officials of India and Sri Lanka regardingFeasibility Study for interconnection of India-Sri Lanka Electricity Grids,it was decided that all possible efforts would be made to reduce the cost ofthe project so as to make it economically viable. It was decided to work onthe following measures:

i. Reduction in length of Submarine Cable

ia. Termination of Cable at Talaimannar in Sri Lankan Territory in place of Thirukketiswaram. This would reduce the cable length by about 30km.

ib. Termination of Cable near Dhanushkodi (at Setu Samudrum crossing) in Indian Territory in place of Panaikulam. This would reduce the cable length by about 45km, however would involve extensive use of pile foundation for line towers.

ii. Explore possibility of reduction of HVDC terminal Cost

iii. To consider multilateral funding for carrying out cost estimate

It was also decided that the revised cost would be carried out for 2x500MW HVDC (Conventional as well as VSC) bipole line to be implemented in two stages.

ADDITIONAL OPTION

The revised route for the interconnection line would be as follows:

2x500MW HVDC bipole line from India(Madurai) to Sri Lanka (Anuradhapura-New): 370km

Overhead(India) : Madurai to near Dhanushkodi : 180km

[ The Transition station for interface connection point between HVDC overhead lines and submarine cables in Indian Territory would be located in the sea near Dhanushkodi after crossing of setu samudrumroute.]

Submarine Cable : Dhanushkodi (India) to Talaimannar (Sri Lanka) :40km

Overhead(Sri Lanka) : Talaimannar to Anuradhapura(New) : 150km

The remaining scope of work would remain unaltered.

PGCIL / CEB has completed the technical study and various financial options.PGCIL is working on a revised proposal including the under sea cableconnectivity to bring the cost down and make the project viable.

India- Pakistan

Interconnection

CROSS-BORDER LINK/PROPOSAL

At present, no transmission link is existing between India and Pakistan. Pakistan grid is at 500kV AC whereas the voltage adopted in the Indian grid is 400kV and 765kV AC.

For establishment of a cross border link to enable to supply about 500MW fromIndia to Pakistan on commercial basis a 400kV D/C AC inter-connectingtransmission line between Amritsar (India) and Lahore (Pakistan) with 500MWHVDC back to back converter station at Lahore has been prima-facie identified.

In the third meeting of the Expert Groups between held on 5th March 2014 inNew Delhi, Pakistan side desired to initially draw power at 220 kV by chargingthe proposed 400 kV D/C line at 220 kV till the time HVDC converter station atLahore gets established (it is yet to be firmed up).

It was also proposed by Pakistan side that a Joint Technical Team comprising of four sub-groups would be formed and the composition of JTT and sub-groups and their scope of works, deliverables, time lines and nominations would be finalized.

High Commission for Pakistan has recently forwarded a draft MoU and aproposal for formation of four subgroups to MoP. As a follow up action, MoP hasconstituted a JTT comprising 6 members and a technical sub-group comprising 3members from the Indian side vide its letter dated 24th June, 2014, forpreparation and submission of first report on cross border interconnection withterminal locations etc..

India –Afghanistan

TRANSMISSION WORKS

220 kV DC Kabul - Pul-e-Khumri 200 km. (approx) transmission line with 220/110/20 kV S/S at ChimtalaSub-Station was constructed by POWERGRID on May’ 2009

The assets have been taken over by MEW, Afghanistan in the month of March 2012.

Further, for construction of 220/20 kV Doshi and Charikarsubstations in Afghanistan, award was placed on M/S. BHEL by POWERGRID on October 21, 2011. The project is expected to be completed within two years from the date of Government sanction for the project, i.e. by October 2013.

GoI is also constructing Salma PH (14x3 MW) with 110 kV transmission line from Salma – Haret (160 Kms. Appox.) through WaPCos.