Cronograma Ruta Crítica

download Cronograma Ruta Crítica

of 4

description

Ejemplo de cronograma indicando ruta critica, en P&

Transcript of Cronograma Ruta Crítica

  • Activity ID Activity Name OriginalDuration

    RemainingDuration

    Start Finish Schedule % Complete

    Performance %Complete

    Physical % Complete

    d

    rEPCEPC Mina Inmaculada 61.00 46.00 26-Apr-15 A 25-Jun-15 64.25% 58.32%HITHITOS DEL PROYECTO 3.60 3.60 15-May-15 18-May-15 0% 0%DIDIRECT FACILITIES / GENERAL 3.60 3.60 15-May-15 18-May-15 0% 0%GGENERALES 3.60 3.60 15-May-15 18-May-15 0% 0%GENERALES 3.60 3.60 15-May-15 18-May-15 0% 0%GENERAL 3.60 3.60 15-May-15 18-May-15 0% 0%

    Terminacin de Precom 0.00 0.00 15-May-15 0% 0% 0%Terminacin de las Obras 0.00 0.00 18-May-15 0% 0% 0%

    COCONSTRUCCION 29.00 8.00 26-Apr-15 A 18-May-15 64.25% 58.32%202000 - PLANTA DE PROCESOS - AREA SECA 4.00 3.00 10-May-15 A 13-May-15 25% 22.5%22100 - ROM / CHANCADO / TRANSPORTE DE MINERAL 1.00 0.10 10-May-15 A 11-May-15 100% 90%2130 - CHANCADO PRIMARIO 1.00 0.10 10-May-15 A 11-May-15 100% 90%PRECOM 1.00 0.10 10-May-15 A 11-May-15 100% 90%

    Secuencia de arranque automtica 1.00 0.10 10-May-15 A 11-May-15 100% 90% 90%22200 - STOCKPILE / RECUPERACIN DE MINERAL CHANCADO 3.00 3.00 11-May-15 13-May-15 0% 0%2210 - STOCKPILE 3.00 3.00 11-May-15 13-May-15 0% 0%TERMINACIN DE LAS OBRAS 3.00 3.00 11-May-15 13-May-15 0% 0%

    Instalacin de tarjeta e integracin de alimentador 3.00 3.00 11-May-15 13-May-15 0% 0% 0%303000 - PLANTA DE PROCESOS - AREA HUMEDA 29.00 8.00 26-Apr-15 A 18-May-15 69.94% 64.19%33100 - MOLIENDA / CLASIFICACION / PRELIXIVIACIN 1.00 1.00 11-May-15 11-May-15 0% 0%3110 - MOLIENDA 1.00 1.00 11-May-15 11-May-15 0% 0%TERMINACIN DE LAS OBRAS 1.00 1.00 11-May-15 11-May-15 0% 0%

    Instalacin de Encoder para Tablero Recuperacin de Energa (martes medio 1.00 1.00 11-May-15 11-May-15 0% 0% 0%Llegada de Tapones definitivos Molino SAG y Bolas (faltan 40 tapones por ME 0.00 0.00 11-May-15 0% 0% 0%Instalacin de tapones definitivos Molino SAG y Bolas 1.00 1.00 11-May-15 11-May-15 0% 0% 0%

    33200 - LIXIVIACIN / CCD / PRE-CLARIFICACIN 2.00 2.00 12-May-15 13-May-15 0% 0%3210 - LIXIVIACIN 2.00 2.00 12-May-15 13-May-15 0% 0%TERMINACIN DE LAS OBRAS 2.00 2.00 12-May-15 13-May-15 0% 0%

    Colocacin pintura Poliurea TK 2-4-6 1.00 1.00 12-May-15 12-May-15 0% 0% 0%Llenado con agua del TK6 1.00 1.00 13-May-15 13-May-15 0% 0% 0%

    PRECOM 1.00 1.00 13-May-15 13-May-15 0% 0%Pruebas con agua de Agitador TK6 1.00 1.00 13-May-15 13-May-15 0% 0% 0%

    33300 - MANEJO DE SOLUCIN / MERRIL CROWE Y PLANTA DORE 29.00 8.00 26-Apr-15 A 18-May-15 68.52% 65.37%3330 - MERRILL CROWE 21.30 6.30 26-Apr-15 A 17-May-15 76.19% 64.7%MECANICA 8.00 3.00 06-May-15 A 13-May-15 12.5% 8.75%

    Instalacin de ductos de aire acondicionado 1.00 0.30 06-May-15 A 11-May-15 100% 70% 70%Sellado de abertura entre Merrill Crowe y Dor (canaleta) 1.00 1.00 11-May-15 11-May-15 0% 0% 0%Sellado de aberturas (paredes paso de tuberias) 3.00 3.00 11-May-15 13-May-15 0% 0% 0%Reubicacin de vlvulas en lnea de retorno a los CCD's 3.00 3.00 11-May-15 13-May-15 0% 0% 0%

    INSTRUMENTACION 10.00 6.00 07-May-15 A 16-May-15 0% 0%Montaje y conexionado instrumentos de P&ID 005 (1) 1.00 0.10 07-May-15 A 11-May-15 100% 90% 90%Instalacin de sistema CCTV y control de accesos 1.00 1.00 16-May-15 16-May-15 0% 0% 0%

    PRECOM 11.00 5.00 06-May-15 A 15-May-15 0% 0%Equipos elctricos 6.00 1.20 06-May-15 A 12-May-15 83.33% 80% 80%

    Apr May Jun Jul Aug2015

    CRONOGRAMA TERMINO DE OBRAS Y PRECOM 10-05-15 11-May-15 08:41

    Remaining Level of EffortActual Level of Effort

    SA

    Page 1 of 4 TASK filter: Falta termino.

    Oracle Corporation

  • Activity ID Activity Name OriginalDuration

    RemainingDuration

    Start Finish Schedule % Complete

    Performance %Complete

    Physical % Complete

    d

    rMecnica 10.00 3.00 07-May-15 A 13-May-15 40% 70% 70%Piping 10.00 5.00 07-May-15 A 15-May-15 40% 50% 50%Sistema de control e instrumentos 5.00 1.50 07-May-15 A 12-May-15 80% 70% 70%Sala de Control 2.00 2.00 13-May-15 15-May-15 0% 0% 0%

    OFICINAS 21.30 6.30 26-Apr-15 A 17-May-15 80.33% 67.3%Instalacin de falso cielo 15.00 3.00 26-Apr-15 A 13-May-15 100% 80% 80%Instalaciones elctricas 7.00 0.70 30-Apr-15 A 11-May-15 100% 90% 90%Colocacin de ventanas 9.00 0.45 02-May-15 A 11-May-15 100% 95% 95%Colocacin de puertas 10.00 2.00 03-May-15 A 12-May-15 80% 80% 80%Accesorios elctricos 7.00 3.50 06-May-15 A 14-May-15 71.43% 50% 50%Enchape de piso 6.00 3.30 06-May-15 A 14-May-15 83.33% 45% 45%Pintura 3.00 3.00 14-May-15 16-May-15 0% 0% 0%Accesorios sanitarios 3.00 3.00 14-May-15 17-May-15 0% 0% 0%Mobiliario 1.00 1.00 16-May-15 17-May-15 0% 0% 0%

    SALA DE CONTROL 17.40 2.40 26-Apr-15 A 13-May-15 93.33% 84%Cableado elctrico (fuerza y comunicacin) 14.00 1.40 26-Apr-15 A 12-May-15 100% 90% 90%Conexionado elctrico (fuerza y comunicacin) 1.00 1.00 12-May-15 13-May-15 0% 0% 0%

    ELECTRICIDAD -SALA 003 13.00 2.10 30-Apr-15 A 13-May-15 0% 0%Conexionado de cables en MCC (Heater) 8.00 0.40 30-Apr-15 A 11-May-15 100% 95% 95%Conexionado de tablero de alumbrado 2.00 0.40 07-May-15 A 11-May-15 100% 80% 80%Colocacin de puertas de acceso (01) 1.00 0.50 08-May-15 A 11-May-15 100% 50% 50%Instalacin de interruptores 1.00 0.50 08-May-15 A 11-May-15 100% 50% 50%Colocacin de rejillas 3.00 2.10 10-May-15 A 13-May-15 33.33% 30% 30%Conexionado de HVAC y Presurizacin 2.00 2.00 11-May-15 12-May-15 0% 0% 0%Conexionado red de comunicaciones 2.00 2.00 11-May-15 12-May-15 0% 0% 0%

    ELECTRICIDAD - SALA MERRIL CROWE 12.00 1.00 30-Apr-15 A 11-May-15 0% 0%Instalacin de heater 8.00 0.80 30-Apr-15 A 11-May-15 100% 90% 90%Conexionado de heater 1.00 1.00 11-May-15 11-May-15 0% 0% 0%

    3340 - PLANTA DORE 26.00 8.00 29-Apr-15 A 18-May-15 41.67% 67.71%TERMINACIN DE LAS OBRAS 20.00 8.00 29-Apr-15 A 18-May-15 60% 57%

    Montaje y conexionado instrumentos de P&ID 007 (10) 3.00 0.15 29-Apr-15 A 11-May-15 100% 95% 95%Instalacin de termocupla 1.00 1.00 11-May-15 11-May-15 0% 0% 0%Tapas del lavador de gases (04) 1.00 1.00 18-May-15 18-May-15 0% 0% 0%

    PRECOM 19.00 6.80 06-May-15 A 17-May-15 36.84% 70.53%Equipos elctricos 6.00 1.20 06-May-15 A 12-May-15 83.33% 80% 80%Sistema de control e instrumentos 5.00 2.00 09-May-15 A 12-May-15 0% 60% 60%Mecnica 8.00 2.40 09-May-15 A 13-May-15 25% 70% 70%Piping 8.00 6.80 10-May-15 A 17-May-15 12.5% 15% 15%

    33400 - ESPESAMIENTO Y DETOXIFICACIN DE RELAVES 10.00 6.00 07-May-15 A 16-May-15 40% 56.75%3410 - DETOXIFICACION RELAVES 10.00 6.00 07-May-15 A 16-May-15 40% 56.75%TERMINACIN DE LAS OBRAS 8.00 6.00 09-May-15 A 16-May-15 33.33% 17.5%

    Conexionado de instrumentos (15) 3.00 1.95 09-May-15 A 12-May-15 66.67% 35% 35%Completar sardinel de contencin 3.00 3.00 14-May-15 16-May-15 0% 0% 0%

    PRECOM 2.00 0.70 08-May-15 A 11-May-15 100% 40%Llenado de agua a Tks de As y Cu. Prueba de bombas de Impulsin 1.00 0.50 08-May-15 A 11-May-15 100% 50% 50%

    Apr May Jun Jul Aug2015

    CRONOGRAMA TERMINO DE OBRAS Y PRECOM 10-05-15 11-May-15 08:41

    Remaining Level of EffortActual Level of Effort

    SA

    Page 2 of 4 TASK filter: Falta termino.

    Oracle Corporation

  • Activity ID Activity Name OriginalDuration

    RemainingDuration

    Start Finish Schedule % Complete

    Performance %Complete

    Physical % Complete

    d

    rPrecom de instrumentos 1.00 0.70 09-May-15 A 11-May-15 100% 30% 30%

    LABOTRATORIO QUIMICO 10.00 2.50 07-May-15 A 13-May-15 33.33% 79.17%Subestacin de Laboratorio Qumico 12A 10.00 0.50 07-May-15 A 11-May-15 40% 95% 95%Pruebas de HI POT y torqueo 1.00 1.00 11-May-15 12-May-15 0% 0% 0%Energizacin de transformador 1.00 1.00 12-May-15 13-May-15 0% 0% 0%

    3440 - TRANSPORTE DE RELAVES A PRESA DE RELAVES 7.00 3.00 08-May-15 A 13-May-15 0% 0%TERMINACIN DE LAS OBRAS 7.00 3.00 08-May-15 A 13-May-15 0% 0%

    Tendido y conexionado de fibra ptica (1.5km) 7.00 2.80 08-May-15 A 13-May-15 42.86% 60% 60%Instalacin de 02 actuadores elctricos para vlvulas 1.00 1.00 11-May-15 11-May-15 0% 0% 0%Proteccin atmosfrica y sistema de puesta a tierra 3.00 3.00 11-May-15 13-May-15 0% 0% 0%Instalacin y conexionado del Controlador l - Estacin de Choque 1.00 1.00 11-May-15 11-May-15 0% 0% 0%

    PRECOM 2.00 2.00 11-May-15 12-May-15 0% 0%Instrumentacin 1.00 1.00 11-May-15 11-May-15 0% 0% 0%Inspeccin a transformador 1.00 1.00 11-May-15 11-May-15 0% 0% 0%Energizacin de transformador 1.00 1.00 11-May-15 11-May-15 0% 0% 0%HI POT de cable y torqueo 1.00 1.00 11-May-15 11-May-15 0% 0% 0%Apertura y cierre de vlvulas 1.00 1.00 11-May-15 11-May-15 0% 0% 0%Tablero de Control 1.00 1.00 11-May-15 11-May-15 0% 0% 0%Llenado y descarga de Linea de relaves. Prueba de bombas de Impulsin 1.00 1.00 12-May-15 12-May-15 0% 0% 0%

    33500 - REACTIVOS 8.00 2.80 04-May-15 A 13-May-15 97.5% 72.75%3510 - CIANURO DE SODIO 8.00 2.80 04-May-15 A 13-May-15 97.5% 72.75%PLANT EQUIPMENT 2.00 1.00 10-May-15 A 11-May-15 50% 50%

    Colocacin de pintura Poliurea en Cal, Floculantes, Cianuro y MBSS 2.00 1.00 10-May-15 A 11-May-15 50% 50% 50%PRECOM 7.00 2.80 04-May-15 A 13-May-15 100% 73.95%

    Cianuro, Pre-Comm bombas (05) 7.00 1.40 04-May-15 A 12-May-15 100% 80% 80%Planta de Cal, Pre-Comm bombas (05) 5.00 1.00 04-May-15 A 11-May-15 100% 80% 80%Sulfato de Cobre, Pre-Comm bombas (03) 7.00 2.10 04-May-15 A 13-May-15 100% 70% 70%Nitrato de Plomo, Pre-Comm bombas (03) 7.00 2.10 04-May-15 A 13-May-15 100% 70% 70%Metabisulfito, Pre-Comm bombas (05) 7.00 2.80 04-May-15 A 13-May-15 100% 60% 60%Floculantes, Pre-Comm bombas (10) 5.00 0.50 04-May-15 A 11-May-15 100% 90% 90%

    404000 - PRESA DE RELAVES & RECUPERACION DE AGUAS 7.00 7.00 11-May-15 17-May-15 0% 0%44100 - PRESA DE RELAVES 7.00 7.00 11-May-15 17-May-15 0% 0%PRESA DE RELAVES 7.00 7.00 11-May-15 17-May-15 0% 0%TERMINACIN DE LAS OBRAS 7.00 7.00 11-May-15 17-May-15 0% 0%

    Pruebas Geolctricas (2,6) 7.00 7.00 11-May-15 17-May-15 0% 0% 0%Terrazas (2-6) 7.00 7.00 11-May-15 17-May-15 0% 0% 0%

    606000 - SERVICIOS GENERALES 2.00 1.40 09-May-15 A 12-May-15 100% 30%66300 - PLANTA DE ENERGA BACK UP 2.00 1.40 09-May-15 A 12-May-15 100% 30%6220 - SUBESTACION EN MEDIA TENSION 10/0.48kV 2.00 1.40 09-May-15 A 12-May-15 100% 30%PRECOM 2.00 1.40 09-May-15 A 12-May-15 100% 30%

    Generadores Diesel (05) 2.00 1.40 09-May-15 A 12-May-15 100% 30% 30%PRPRE-OPERACIONES Y TESTEO 45.00 45.00 12-May-15 25-Jun-15 0% 0%PRPRE-OPERACIONES Y TESTEO 45.00 45.00 12-May-15 25-Jun-15 0% 0%PPRE-OPERACIONES Y TESTEO 45.00 45.00 12-May-15 25-Jun-15 0% 0%

    Apr May Jun Jul Aug2015

    CRONOGRAMA TERMINO DE OBRAS Y PRECOM 10-05-15 11-May-15 08:41

    Remaining Level of EffortActual Level of Effort

    SA

    Page 3 of 4 TASK filter: Falta termino.

    Oracle Corporation

  • Activity ID Activity Name OriginalDuration

    RemainingDuration

    Start Finish Schedule % Complete

    Performance %Complete

    Physical % Complete

    d

    rPRE-OPERACION Y TESTEO 45.00 45.00 12-May-15 25-Jun-15 0% 0%PRUEBAS Y OPERACIN 45.00 45.00 12-May-15 25-Jun-15 0% 0%OPERACION CONTINUA 45.00 45.00 12-May-15 25-Jun-15 0% 0%Carga de Material Inerte (15,000 ton) 7.00 7.00 12-May-15 18-May-15 0% 0% 0%Carga de Material con Ley (120 hrs) 5.00 5.00 19-May-15 23-May-15 0% 0% 0%Ingreso Merril Crowe-Dore 3.00 3.00 24-May-15 26-May-15 0% 0% 0%Primera Barra Dore 0.00 0.00 26-May-15 0% 0% 0%Operacion Continua 30.00 30.00 27-May-15 25-Jun-15 0% 0% 0%Operacin Comercial 0.00 0.00 25-Jun-15 0% 0% 0%

    Apr May Jun Jul Aug2015

    CRONOGRAMA TERMINO DE OBRAS Y PRECOM 10-05-15 11-May-15 08:41

    Remaining Level of EffortActual Level of Effort

    SA

    Page 4 of 4 TASK filter: Falta termino.