Critical Path Analysis
![Page 2: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/2.jpg)
There are no pre-requisites for this Achievement Standard so it can be placed in any course.No knowledge is pre-supposed.
![Page 3: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/3.jpg)
Methods include a selection from those related to:
precedence tablesnetwork diagramscritical eventsschedulingfloat times
![Page 4: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/4.jpg)
Critical Path Analysis (CPA)
A complex project must be well planned, especially if a number of people are involved.
CPA is used to ensure that the complete scheme is completed in the minimum time.
It is used to schedule the projects.
![Page 5: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/5.jpg)
Any activity can be represented as a project:planning a partybuilding a house/factoryplanning a conference
So what is a project?
![Page 6: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/6.jpg)
What do the projects have in common?
Each project can be broken down into tasks.Each task takes time and uses resources.Tasks are structured
![Page 7: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/7.jpg)
Step 1 – Precedence table
• To identify actual tasks that make up a project• To identify the order these tasks need to be in• To decide how long each task will take
![Page 8: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/8.jpg)
Example: Constructing a garageTask Duration (days)
A prepare foundations 7B Make and position door frame 2C Lay drains, floor base and screed 15D Install services and fittings 8E Erect walls 10F Plaster ceiling 2G Erect roof 5H Install door and windows 8I Fit gutters and pipes 2J Paint outside 3
![Page 9: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/9.jpg)
Some of these activities must be completed before others can start.
Task Duration (days)A prepare foundations 7B Make and position door frame 2C Lay drains, floor base and screed 15D Install services and fittings 8E Erect walls 10F Plaster ceiling 2G Erect roof 5H Install door and windows 8I Fit gutters and pipes 2J Paint outside 3
![Page 10: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/10.jpg)
You can’t erect the roof (G) before you have erected the walls (E)
Task Duration (days)A prepare foundations 7B Make and position door frame 2C Lay drains, floor base and screed 15D Install services and fittings 8E Erect walls 10F Plaster ceiling 2G Erect roof 5H Install door and windows 8I Fit gutters and pipes 2J Paint outside 3
![Page 11: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/11.jpg)
Precedence
![Page 12: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/12.jpg)
D must follow E
Task Duration (days)
A prepare foundations 7B Make and position door frame 2C Lay drains, floor base and screed 15D Install services and fittings 8 EE Erect walls 10F Plaster ceiling 2G Erect roof 5H Install door and windows 8I Fit gutters and pipes 2J Paint outside 3
![Page 13: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/13.jpg)
E must follow A and B
Task Duration (days)
A prepare foundations 7B Make and position door frame 2C Lay drains, floor base and screed 15D Install services and fittings 8 EE Erect walls 10 A, BF Plaster ceiling 2G Erect roof 5H Install door and windows 8I Fit gutters and pipes 2J Paint outside 3
![Page 14: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/14.jpg)
F must follow D and G
Task Duration (days)
A prepare foundations 7B Make and position door frame 2C Lay drains, floor base and screed 15D Install services and fittings 8 EE Erect walls 10 A, BF Plaster ceiling 2 D, GG Erect roof 5H Install door and windows 8I Fit gutters and pipes 2J Paint outside 3
![Page 15: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/15.jpg)
G must follow E
Task Duration (days)
A prepare foundations 7B Make and position door frame 2C Lay drains, floor base and screed 15D Install services and fittings 8 EE Erect walls 10 A, BF Plaster ceiling 2 D, GG Erect roof 5 EH Install door and windows 8I Fit gutters and pipes 2J Paint outside 3
![Page 16: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/16.jpg)
H must follow G
Task Duration (days)
A prepare foundations 7B Make and position door frame 2C Lay drains, floor base and screed 15D Install services and fittings 8 EE Erect walls 10 A, BF Plaster ceiling 2 D, GG Erect roof 5 EH Install door and windows 8 GI Fit gutters and pipes 2J Paint outside 3
![Page 17: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/17.jpg)
I must follow C, F
Task Duration (days)
A prepare foundations 7B Make and position door frame 2C Lay drains, floor base and screed 15D Install services and fittings 8 EE Erect walls 10 A, BF Plaster ceiling 2 D, GG Erect roof 5 EH Install door and windows 8 GI Fit gutters and pipes 2 C, FJ Paint outside 3
![Page 18: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/18.jpg)
J must follow H and I
Task Duration (days)
A prepare foundations 7B Make and position door frame 2C Lay drains, floor base and screed 15D Install services and fittings 8 EE Erect walls 10 A, BF Plaster ceiling 2 D, GG Erect roof 5 EH Install door and windows 8 GI Fit gutters and pipes 2 C, FJ Paint outside 3 I
![Page 19: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/19.jpg)
We call this a precedence table
Task Duration (days)
Precedence
A prepare foundations 7B Make and position door frame 2C Lay drains, floor base and screed 15D Install services and fittings 8 EE Erect walls 10 A, BF Plaster ceiling 2 D, GG Erect roof 5 EH Install door and windows 8 GI Fit gutters and pipes 2 C, FJ Paint outside 3 I
![Page 20: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/20.jpg)
• Precedence diagrams are not that useful.
• A useful visual representation of a project is a network diagram.
![Page 21: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/21.jpg)
Sequencethe most common sequences / dependencies
Task A Task B
Task ATask B
Task C
Task C
Task B
Task A
Task B depends upon Task A; B cannot start until A is finished
Task C depends upon Task A and B; C cannot start until both A and B are finished
Tasks B and C depend on Task A; neither can start until A is finished, but B and C are independent of each other
![Page 22: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/22.jpg)
more unusual links and relationships
so far all links have been finish-start links...
Task A Task B
Task A
Task C
Task C
Task A
Task B depends upon Task A, but with a 3 day delay; B cannot start until 3 days after A is finished
The finish of Task C depends upon the finish of Task A
The start of Task C depends on the start of Task A; this is a start-to-start link; it may also incorporate a delay
3 days
![Page 23: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/23.jpg)
Drawing a NETWORK – how do we get here?
![Page 24: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/24.jpg)
Algorithm
![Page 25: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/25.jpg)
Draw in the links Task Precedence
ABCD EE A, BF D, GG EH GI C, FJ I
![Page 26: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/26.jpg)
Draw in A, B, C on a rough diagram
![Page 27: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/27.jpg)
STEP 1- original vertices with no arcsSTEP 2 - delete all arcs incident on A, B, C and redraw as shownSTEP 3 - repeat iteration
![Page 28: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/28.jpg)
![Page 29: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/29.jpg)
STEP 1- original vertices with no arcsSTEP 2 - delete all arcs incident on E and redraw as shownSTEP 3 - repeat iteration
![Page 30: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/30.jpg)
![Page 31: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/31.jpg)
STEP 1- original vertices with no arcsSTEP 2 - delete all arcs incident on D, G and redraw as shownSTEP 3 - repeat iteration
![Page 32: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/32.jpg)
![Page 33: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/33.jpg)
STEP 1- original vertices with no arcsSTEP 2 - delete all arcs incident on F and H and redraw as shownSTEP 3 - repeat iteration
![Page 34: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/34.jpg)
![Page 35: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/35.jpg)
STEP 1- original vertices with no arcsSTEP 2 - delete all arcs incident on I and redraw as shownSTEP 3 - STOP
![Page 36: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/36.jpg)
![Page 37: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/37.jpg)
Converting to a usable diagram
![Page 38: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/38.jpg)
Proposed method
Now draw the network diagram using boxes
task number and/or name
durationearly starttime
late starttime
early finishtime
late finishtimefloat
slack
![Page 39: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/39.jpg)
Example
Task A
7
Task B
2
Task C
15
Task E
10
Task D
8
Task G
5
Task F
2
Task H
8
Task I
2
Task J
3
Finish
Duration
![Page 40: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/40.jpg)
Critical Path
• Find the earliest possible start for each activity, by going forwards through the network.
• Secondly, the latest possible start time for each activity is found by going backwards through the network.
• Activities which have equal earliest and latest start time are on the critical path.
![Page 41: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/41.jpg)
Practice 1
Task 062
Task 01
3Task 04
6
Task 03
3
Task 08
2
Task 02
4
Task 09
1Task 05
3Task 07
5
![Page 42: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/42.jpg)
Practice 1
Task 062
Task 01
30Task 04
6
Task 03
3
Task 08
2
Task 02
4
Task 09
1Task 05
3Task 07
5
![Page 43: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/43.jpg)
Practice 1
Task 062
Task 01
3 30Task 04
6
Task 03
3
Task 08
2
Task 02
4
Task 09
1Task 05
3Task 07
5
![Page 44: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/44.jpg)
Practice 1
Task 062
Task 01
3 30Task 04
63
Task 03
3
Task 08
2
Task 02
43
Task 09
1Task 05
3Task 07
5
3
![Page 45: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/45.jpg)
Practice 1
Task 062
Task 01
3 30Task 04
63 9
Task 03
3
Task 08
2
Task 02
43 7
Task 09
1Task 05
3Task 07
5
3 5
![Page 46: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/46.jpg)
Practice 1
Task 062
Task 01
3 30Task 04
63 9
Task 03
37
Task 08
25
Task 02
43 7
Task 09
1Task 05
39Task 07
5
3 5
![Page 47: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/47.jpg)
Practice 1
Task 062
Task 01
3 30Task 04
63 9
Task 03
3 107
Task 08
2 75
Task 02
43 7
Task 09
1Task 05
39 12Task 07
5
3 5
![Page 48: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/48.jpg)
Practice 1
Task 062
Task 01
3 30Task 04
63 9
Task 03
3 107
Task 08
2 75
Task 02
43 7
Task 09
1Task 05
39 12Task 07
512
3 5
Take the largest value
![Page 49: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/49.jpg)
Practice 1
Task 062
Task 01
3 30Task 04
63 9
Task 03
3 107
Task 08
2 75
Task 02
43 7
Task 09
1Task 05
39 12Task 07
512 17
3 5
![Page 50: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/50.jpg)
Practice 1
Task 062
Task 01
3 30Task 04
63 9
Task 03
3 107
Task 08
2 75
Task 02
43 7
Task 09
1Task 05
39 12Task 07
512 17
3 5
Take the largest value
![Page 51: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/51.jpg)
Forward pass complete
Duration = 18
Task 062
Task 01
3 30
3
Task 04
63 9
Task 03
3 107
5Task 08
2 75
Task 02
43 7
Task 09
1 1817Task 05
39 12Task 07
512 17
![Page 52: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/52.jpg)
Backward pass
Task 062
Task 01
3 30
3
Task 04
63 9
Task 03
3 107
5Task 08
2 75
Task 02
43 7
Task 09
1 1817Task 05
39 12Task 07
512 17
18
![Page 53: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/53.jpg)
Task 062
Task 01
3 30
3
Task 04
63 9
Task 03
3 107
5Task 08
2 75
Task 02
43 7
Task 09
1 1817Task 05
39 12Task 07
512 17
1817 0
Float
![Page 54: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/54.jpg)
Task 062
Task 01
3 30
3
Task 04
63 9
Task 03
3 107
5Task 08
2 75
Task 02
43 7
Task 09
1 1817Task 05
39 12Task 07
512 17
1817 0
17
17
![Page 55: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/55.jpg)
Task 062
Task 01
3 30
3
Task 04
63 9
Task 03
3 107
5Task 08
2 75
Task 02
43 7
Task 09
1 1817Task 05
39 12Task 07
512 17
1817 0
17
17
12
15
0
10
![Page 56: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/56.jpg)
Task 062
Task 01
3 30
3
Task 04
63 9
Task 03
3 107
5Task 08
2 75
Task 02
43 7
Task 09
1 1817Task 05
39 12Task 07
512 17
1817 0
17
17
12
15
0
10
12
12
9
9 0
2
1513 10
9
93 0
5 2
![Page 57: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/57.jpg)
Forward pass complete
Task 062
Task 01
3 30
3
Task 04
63 9
Task 03
3 107
5Task 08
2 75
Task 02
43 7
Task 09
1 1817Task 05
39 12Task 07
512 17
1817 0
17
17
12
15
0
10
12
12
9
9 0
2
1513 10
9
93 0
5 2
Take the smallest
![Page 58: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/58.jpg)
Critical Path – float = 0
Task 0623 5
13 1510
Task 09
1 1817
1817 0
Task 07
512 17
1712 0Task 05
39 12
129 0
Task 04
63 9
93 0
Task 01
3 30
30 0
Task 08
2 75
1715 10
Task 03
3 107
129 2
Task 02
43 7
95 2
![Page 59: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/59.jpg)
Your turn
Task A
7
Task B
2
Task C
15
Task E
10
Task D
8
Task G
5
Task F
2
Task H
8
Task I
2
Task J
3
Finish
![Page 60: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/60.jpg)
Example 1 – Forward pass
Task A
70
Task B
20
Task C
150
Task E
10
Task D
8
Task G
5
Task F
2
Task H
8
Task I
2
Task J
3
Finish
![Page 61: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/61.jpg)
Example 1 – Forward pass
Task A
7 70
Task B
2 20
Task C
15 150
Task E
10
Task D
8
Task G
5
Task F
2
Task H
8
Task I
2
Task J
3
Finish
![Page 62: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/62.jpg)
Example 1 – Take the largest value
Task A
7 70
Task B
2 20
Task C
15 150
Task E
107
Task D
8
Task G
5
Task F
2
Task H
8
Task I
2?
Task J
3
Finish
![Page 63: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/63.jpg)
Example 1 – Take the largest value
Task A
7 70
Task B
2 20
Task C
15 150
Task E
10 177
Task D
817
Task G
517
Task F
2
Task H
8
Task I
2?
Task J
3
Finish
![Page 64: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/64.jpg)
Example 1 – Take the largest value
Task A
7 70
Task B
2 20
Task C
15 150
Task E
10 177
Task D
8 2517
Task G
5 2217
Task F
2
Task H
8
Task I
2?
Task J
3
Finish
![Page 65: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/65.jpg)
Example 1 – Take the largest value
Task A
7 70
Task B
2 20
Task C
15 150
Task E
10 177
Task D
8 2517
Task G
5 2217
Task F
225
Task H
822
Task I
2?
Task J
3
Finish
![Page 66: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/66.jpg)
Example 1 – Minimum 32
Task A
7 70
Task B
2 20
Task C
15 150
Task E
10 177
Task D
8 2517
Task G
5 2217
Task F
2 2725
Task H
8 3022
Task I
2 2927
Task J
3 3229
Finish32
![Page 67: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/67.jpg)
Example 1 – Backward pass
Task A
7 70
Task B
2 20
Task C
15 150
Task E
10 177
Task D
8 2517
Task G
5 2217
Task F
2 2725
Task H
8 3022
Task I
2 2927
Task J
3 3229
Finish32
32
![Page 68: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/68.jpg)
Example 1 – Take lowest value
Task A
7 70
Task B
2 20
Task C
15 150
Task E
10 177
Task D
8 2517
Task G
5 2217
Task F
2 2725
Task H
8 3022
Task I
2 2927
Task J
3 3229
Finish32
32
32
32
29 0
24 2
![Page 69: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/69.jpg)
Example 1 – Take lowest value
Task A
7 70
Task B
2 20
Task C
15 150
Task E
10 177
Task D
8 2517
Task G
5 2217
Task F
2 2725
Task H
8 3022
Task I
2 2927
Task J
3 3229
Finish32
32
32
32
29 0
24 2
2927 0
![Page 70: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/70.jpg)
Example 1 – Take lowest value
Task A
7 70
Task B
2 20
Task C
15 150
Task E
10 177
Task D
8 2517
Task G
5 2217
Task F
2 2725
Task H
8 3022
Task I
2 2927
Task J
3 3229
Finish32
32
32
32
29 0
24 2
2927 0
2725 0
![Page 71: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/71.jpg)
Example 1 – Take lowest value
Task A
7 70
Task B
2 20
Task C
15 150
Task E
10 177
Task D
8 2517
Task G
5 2217
Task F
2 2725
Task H
8 3022
Task I
2 2927
Task J
3 3229
Finish32
32
32
32
29 0
24 2
2927 0
2725 02517 0
2419 2
![Page 72: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/72.jpg)
Example 1 – Take lowest value
Task A
7 70
Task B
2 20
Task C
15 150
Task E
10 177
Task D
8 2517
Task G
5 2217
Task F
2 2725
Task H
8 3022
Task I
2 2927
Task J
3 3229
Finish32
32
32
32
29 0
24 2
2927 0
2725 02517 0
2419 2
177 0
![Page 73: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/73.jpg)
Example 1 – Take lowest value
Task A
7 70
Task B
2 20
Task C
15 150
Task E
10 177
Task D
8 2517
Task G
5 2217
Task F
2 2725
Task H
8 3022
Task I
2 2927
Task J
3 3229
Finish32
32
32
32
29 0
24 2
2927 0
2725 02517 0
2419 2
177 0
2712 12
70 0
7 5 5
![Page 74: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/74.jpg)
Example 1 – Critical Path – zero float
Task A
7 70
Task B
2 20
Task C
15 150
Task E
10 177
Task D
8 2517
Task G
5 2217
Task F
2 2725
Task H
8 3022
Task I
2 2927
Task J
3 3229
Finish32
32
32
32
29 0
24 2
2927 0
2725 02517 0
2419 2
177 0
2712 12
70 0
7 5 5
![Page 75: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/75.jpg)
Example 1 – Critical Path – A-E-D-F-I-J
Task A
7 70
Task B
2 20
Task C
15 150
Task E
10 177
Task D
8 2517
Task G
5 2217
Task F
2 2725
Task H
8 3022
Task I
2 2927
Task J
3 3229
Finish32
32
32
32
29 0
24 2
2927 0
2725 02517 0
2419 2
177 0
2712 12
70 0
7 5 5
![Page 76: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/76.jpg)
Using the outputs• Gantt Charts• optimising the schedule
![Page 77: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/77.jpg)
Gantt: Critical path in red
![Page 78: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/78.jpg)
Gantt: Critical path in red
![Page 79: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/79.jpg)
Scheduling: Move the critical path along the top
![Page 80: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/80.jpg)
Now fit the other activities like a puzzle
![Page 81: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/81.jpg)
Now fit the other activities like a puzzle
![Page 82: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/82.jpg)
Schedule
![Page 83: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/83.jpg)
Any delay on the critical path causes a delay in the entire project
![Page 84: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/84.jpg)
There is a 2-day float on the non-critical path
![Page 85: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/85.jpg)
Definitions
• Critical Path Those activities that can not over run without effecting the total length of the project, are those where the EST = LFT (Total float = 0).
• Total Float LFT of the activity- the duration- EST of the activity. This shows how much ´slack´ there is on a particular route of the network. If the total float is 0 then an activity lies on the critical path.
• Free Float EST of the next activity – Duration – EST of this activity. This shows the ´slack´ on an individual activity before it delays the start of the next activity.
![Page 86: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/86.jpg)
• EES = Earliest early start time• LLF = latest late finish timeFree float: The amount of time that a schedule activity can be delayed without delaying the early start date of any immediately following schedule activities.
Free Float = EESsuccessor – EF
![Page 87: Critical Path Analysis. There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.](https://reader037.fdocuments.us/reader037/viewer/2022110320/56649c9c5503460f9495b1ed/html5/thumbnails/87.jpg)
• EES = Earliest early start time• LLF = latest late finish timeIndependent float is that portion of the total float within which an activity can be delayed for start without affecting the float of the preceding activities.
Independent Float = EESsuccessor-LLFpredecessor-duration