Critical Path Analysis
![Page 2: Critical Path Analysis. Planning and Monitoring Tool.](https://reader035.fdocuments.us/reader035/viewer/2022072111/56649f345503460f94c52296/html5/thumbnails/2.jpg)
Critical Path Analysis
![Page 3: Critical Path Analysis. Planning and Monitoring Tool.](https://reader035.fdocuments.us/reader035/viewer/2022072111/56649f345503460f94c52296/html5/thumbnails/3.jpg)
Planning and Monitoring Tool
![Page 4: Critical Path Analysis. Planning and Monitoring Tool.](https://reader035.fdocuments.us/reader035/viewer/2022072111/56649f345503460f94c52296/html5/thumbnails/4.jpg)
Critical Path Analysis
• May be used as part of the decision making process
• Enables a firm to plan and monitor operations• Time related – identifies the maximum time for
an operation to be completed• Identify potential problems in implementing
operation• Identifies where and when resources (including
human ones) are needed
![Page 5: Critical Path Analysis. Planning and Monitoring Tool.](https://reader035.fdocuments.us/reader035/viewer/2022072111/56649f345503460f94c52296/html5/thumbnails/5.jpg)
Critical Path Analysis
• Advantages– Maximise efficiency in the use
of time– Improve efficiency and
generate cost saving in the use of resources
– Beneficial to monitoring cash flow
• Disadvantages– Usefulness may be limited in
complex and large scale operations
– Necessity of having clear and reliable information
– Skilled management and team philosophy is essential
![Page 6: Critical Path Analysis. Planning and Monitoring Tool.](https://reader035.fdocuments.us/reader035/viewer/2022072111/56649f345503460f94c52296/html5/thumbnails/6.jpg)
The Process
![Page 7: Critical Path Analysis. Planning and Monitoring Tool.](https://reader035.fdocuments.us/reader035/viewer/2022072111/56649f345503460f94c52296/html5/thumbnails/7.jpg)
CPA – the Process
• Identify and prioritise the activities• Identify which activities MUST be done before
others• EST – identify earliest start time• LFT – identify latest finish time• Identify the FLOAT – tasks which can be
completed outside the critical path• Identify the critical path – points connecting ESTs
and LFTs (where these are the same)
![Page 8: Critical Path Analysis. Planning and Monitoring Tool.](https://reader035.fdocuments.us/reader035/viewer/2022072111/56649f345503460f94c52296/html5/thumbnails/8.jpg)
Critical Path Analysis
Nodes: Show the start and finish of a task
1 2
Node numbers showing order of activities in the left hand semi-circle
of each node.
3
Earliest Start Time (EST)
5
Latest Finish Time (LFT)
A
3
B
5
Arrows indicate the order of the tasks, the
letter above shows the order, the
time period below the
arrow
The Critical Path