Critical Path Analysis & List Processing Algorithm
description
Transcript of Critical Path Analysis & List Processing Algorithm
Critical Path Analysis&
List Processing Algorithm
Scheduling Tasks• A processor is a person, machine, computer, or
robot etc., which works on a task.
• To solve a scheduling problem typically the tasks are scheduled to minimize completion times.
• Make sure to consider importance of a task, does
one task need to be completed before another task.
ASSUMPTIONS AND RULES• If a processor starts working on a task, the
work will continue until that task is complete.• No processor stays idle if there is a task to
be done.• The CPA has an associated order-
requirement digraph.• The tasks are arranged in a priority list that
is independent of the digraph.
Goals of CPA• Minimize the completion time for a given
number of processors• Minimize processor idle time• Minimize the number of processors
needed to complete the job in a specified time.
A task is considered ready if all its predecessors (prerequisite tasks) in the digraph have been completed.
LIST PROCESSING ALGORITHM1. Assignment of Processors: The lowest numbered
idle processor is assigned to the highest priority ready task until either all processors are assigned or all ready tasks are being worked on
2. Status Check: When a processor completes a task, that processor becomes idle. Check for ready tasks and tasks not yet completed and determine which of the following appliesa) If there is a ready task repeat step 1.b) If there are no ready tasks bunt not every task has been
completed, the idle processor remains idle until more tasks are completed.
c) If all tasks are completed, the job is done.
EXAMPLE: • What is the completion time for the job shown
in the digraph below using the priority list using one processor
T13
T28
T37
T44
T57
𝑇 3 ,𝑇 2 ,𝑇1 ,𝑇 4 ,𝑇 5T13
T28
T37
T44
T57
P1T1-10 T5-29T4-22T2-18T3-7
EXAMPLE: • What is the completion time for the job shown
in the digraph below using the priority list using two processors?
T13
T28
T37
T44
T57
𝑇 3 ,𝑇 2 ,𝑇1 ,𝑇 4 ,𝑇 5T13
T28
T37
T44
T57
P1T1-3
T5-22
T4-11
T2-15T3-7
P2 IDLE-7 IDLE-15IDLE-22
Making Fajitas
• Tortillas• Chicken• 1 onion• Seasoning• Tomatoes• Cilantro
T1: slice chicken & onions – 5 minT2: Cook chicken – 10 minT3: Cook onions – 5 minT4: Add seasoning – 1 minT5: Chop tomato – 4 minT6: Mix tomato and cilantro – 2 minT7: Warm tortillas – 1 minT8: Serve – 1 min
Priority list: , ,
, ,
T210
T35
T41
T54
T15
T62
T71
T81
P1T1-11T6-6T5-4
T4-27
T2-21 T3-26T7-28
T8-29
, ,
T210
T35
T41
T54
T15
T62
T71
T81
P1 T5-4
P2 T1-5
T6-6T7-7 T4-21
T2-15
T3-20T8-22
IDLE
IDLE IDLE
You Try
P1P2
T5-5T1-1
IDLE
T8-10
T7-7 T2-12
T6-9 IDLET3-14
T4-15
IDLE T9-17
IDLE T10-18
P1P2
T5-5T1-1
IDLE
T8-10
T7-7
T2-10
T6-9T3-12
T4-13
IDLE
T9-15
T10-16
P3IDLE IDLE
Critical Path Schedules1. Find a task that heads a critical (longest)
path in the order-requirement digraph2. Place the task found in step 1 next in the
priority list3. Remove the task found in step 1 from the
digraph4. If all tasks have been removed, the list is
completed. If tasks remain return to step one.
Critical pathT15
T23
T37
T42
T52
T63
T71
T84
P1P2
T8-16
T7-11
T3-7
T1-5 T2-8
T6-10
T4-10
T5-12
You Try using 2 and 3 processors using critical path
P1P2
T5-5T1-1
IDLE
T8-12
T7-11
T2-10
T6-9
T3-12
T4-13
IDLE
T9-15 T10-16
P1P2
T5-5T1-1
IDLE
T8-10
T7-7
T2-10
T6-9
T3-12
T4-13
IDLE
T9-15T10-16
P3
Critical path algorithm on 3 processors
IDLE
P1P2
T5-5T1-1
IDLE
T8-10
T7-7
T2-10
T6-9T3-12
T4-13
IDLE
T9-15
T10-16
P3IDLE IDLE
List process algorithm on 3 processors
P1P2
T5-5T1-1
IDLE
T8-12
T7-11
T2-10
T6-9
T3-12
T4-13
IDLE
T9-15 T10-16
Critical path algorithm on 2 processors
P1P2
T5-5T1-1
IDLE
T8-10
T7-7
T2-10
T6-9
T3-12
T4-13
IDLE
T9-15T10-16
P3
Critical path algorithm on 3 processors
IDLE