Crisis management plan

4
Security Handbook Capt S B Tyagi* [email protected] * Author is sole proprietor of this intellectual property. Any use by way of copy or reproduction in any form of this without permission may not be made. 1. Crisis Management Plan 1.1 Introduction A contingency plan, by its nature, will not be in regular operation therefore training is essential. No contingency plan can be left to chance. Anticipatory training must be undertaken. All aspects of the plan, by day and night, must be tested under conditions as close to reality as possible. Frequent exercises by key personnel with essential equipment, will ensure that changes of staff and building .layout are updated. From time to time full unannounced exercises should be carried out. The frequency of these exercises should reflect the possibility of need. There may be some reluctance to participate in these training exercises. Staff and management must be motivated. The more common attitudes suggest that this reluctance is due to psychological reasoning: o "don't want it to happen" o "would rather it didn't happen" o “it is not going to happen" o “it won't happen to me" 1.2 The plan Any contingency plan must involve all relevant departments, both within the business and the external services. Police, ambulance, Gas, Water, Fire and Electricity Authorities are some of the essential services that can be involved in a large and complex contingency plan. An early consideration must be communications. This is a twofold factor - one to warn that the emergency has arisen, and, two to collect all necessary experts to deal with the situation. Once an incident has occurred, all subsequent actions should be part of the contingency plan. To ensure that there is a co- coordinated effort the inclusion and identification of an Emergency Controller must be an essential part of the contingency plan. The Emergency / Disaster Plan can be in three following parts: i. Disaster Reduction Plan While planning, all the managements are better advised not to look for Crisis Reactive Perspective as only the crisis pro-active approach the loss of life and damage to property. Broadly, emergency management plan should consist of: Disaster Reduction Program Planning and implementation on how to prevent emergencies from occurring CONTENTS 1.1 Introduction 1.2 The plan 1.3 Stages of planning 1.4 Worst event considered 1.5 Surveillance of staff 1.6 Link with maintenance 1.7 Report Generation 1.8 Deviation Analysis 1.9 Simulation & training 1.10 Support by equipments 1.11 Evacuation 1.12 Summary

description

 

Transcript of Crisis management plan

Page 1: Crisis management plan

Security Handbook

Capt S B Tyagi* [email protected] * Author is sole proprietor of this intellectual property. Any use by way of copy or reproduction in any form of this without permission may not be made.

1. Crisis Management Plan 1.1 Introduction A contingency plan, by its nature, will not be in regular operation therefore training is essential. No contingency plan can be left to chance. Anticipatory training must be undertaken. All aspects of the plan, by day and night, must be tested under conditions as close to reality as possible. Frequent exercises by key personnel with essential equipment, will ensure that changes of staff and building .layout are updated. From time to time full unannounced exercises should be carried out. The frequency of these exercises should reflect the possibility of need. There may be some reluctance to participate in these training exercises. Staff and management must be motivated. The more common attitudes suggest that this reluctance is due to psychological reasoning:

o "don't want it to happen" o "would rather it didn't happen" o “it is not going to happen" o “it won't happen to me"

1.2 The plan Any contingency plan must involve all relevant departments, both within the business and the external services. Police, ambulance, Gas, Water, Fire and Electricity Authorities are some of the essential services that can be involved in a large and complex contingency plan. An early consideration must be communications. This is a twofold factor - one to warn that the emergency has arisen, and, two to collect all necessary experts to deal with the situation. Once an incident has occurred, all subsequent actions should be part of the contingency plan. To ensure that there is a co-coordinated effort the inclusion and identification of an Emergency Controller must be an essential part of the contingency plan. The Emergency / Disaster Plan can be in three following parts:

i. Disaster Reduction Plan

While planning, all the managements are better advised not to look for Crisis Reactive Perspective as only the crisis pro-active approach the loss of life and damage to property. Broadly, emergency management plan should consist of:

• Disaster Reduction Program • Planning and implementation on how to prevent emergencies from occurring

CONTENTS

1.1 Introduction 1.2 The plan 1.3 Stages of planning 1.4 Worst event considered 1.5 Surveillance of staff 1.6 Link with maintenance 1.7 Report Generation 1.8 Deviation Analysis 1.9 Simulation & training 1.10 Support by equipments 1.11 Evacuation 1.12 Summary

Page 2: Crisis management plan

Security Handbook

Capt S B Tyagi* [email protected] * Author is sole proprietor of this intellectual property. Any use by way of copy or reproduction in any form of this without permission may not be made.

ii. Disaster Response Plan This is development application in case an emergency occur and includes training of the first responder.

iii. Disaster Recovery Plan This includes creation of specialized business recovery machinery as it is very essential for the industrial and chemical health of organization not only to respond to disaster but also to ensure resumption of normal business activities as far as possible.

1.3 Stages of Planning There are various stages of planning for the emergencies. These are discussed in detail as follows:

Identification & assessment of hazard

This stage is crucial to both on-site and off-site emergency planning and requires management to systematically identify what emergencies could arise in the plant. These should range from small incidents which could be dealt with the plant personnel without outside help to the largest event for which it is prudent to have a plan as without external help such events cannot be managed. Experience have shown that for every occasion that the full potential of an accident is realized, there are many occasions when some lesser event occur or when a developing incident is made safe before reaching full potential.

Major hazard incident come within the following categories:

Events involving flammable materials

(i) Major Fires without danger of explosion, prolonged high thermal radiation

and smoke (ii) Fire threatening items of plant containing hazardous substances, potential

spread of fire, explosion or release of toxic substances (iii) Explosion with little or no-warning (iv) Hazards from blast wave, flying debris and high level thermal radiation

Events involving toxic materials

(i) Slow or intermittent release of toxic substances (ii) Items of plant threatened by fire (iii) Hazards from potential loss of containment (iv) Rapid release of limited duration due to plant failure

Page 3: Crisis management plan

Security Handbook

Capt S B Tyagi* [email protected] * Author is sole proprietor of this intellectual property. Any use by way of copy or reproduction in any form of this without permission may not be made.

(v) Massive release of toxic substances due to failure of storage or process vessel

1.4 Worst event considered While planning is being made for disaster management the worst scenario should be visualized and accordingly plan should base on following two factors:

• Relative likelihood of the event • Consequence of the event

The relative likelihood may be very low but if consequences of the event are great, the planning needs to be the best. Similarly, if relative likelihood of the event is very high even while consequences of the event are marginal, still preventive actions are required to be very effective. In fact, even when both the factors inversely relate to each other the plan requires to be given very serious consideration. 1.5 Surveillance of maintenance staff and their routine Maintenance staff needs constant motivation and their performance closely observed. They have to be not only quality conscious but also punctual in maintaining the schedule. Their work habits must reflect their safety consciousness, resourcefulness and presence of mind as in most of the cases the maintenance staff happen to be first responder to any emergency situation. The nominated person must know their specific responsibility separate from their day-to-day activities in case of emergency situation 1.6 Link with preventive maintenance schedules Emergency planning must have linkage with preventive maintenance schedules as often potential causes of accidents are addressed in maintenance schedule if meticulously planning. 1.7 Report generation In case of accidents major or minor or `near misses’ reports must be generated giving detailed analysis causes of the accident and corrective and preventive actions. These reports are reflective of the management’s desire for improvement and are to be used for studying the patterns of accidents emerging out. 1.8 Deviation analysis Wherever a deviation takes place, an analysis is required to find out the reasons of the causes and the outcome. Any change or breaches of safe practices are sometimes loaded with potential of accidents. Therefore, even when a deviation is aimed to improve, the safe practices, impact assessment is necessary

Page 4: Crisis management plan

Security Handbook

Capt S B Tyagi* [email protected] * Author is sole proprietor of this intellectual property. Any use by way of copy or reproduction in any form of this without permission may not be made.

1.9 Simulation and training There is no better way of preparing for the disaster other than simulation disaster and evaluating the response mechanism. Repeated practices, deviation analysis and impact assessment lead to checking the disaster management plan in real conditions and on ground. It is advisable that independent observers are appointed to evaluate the effectiveness of the emergency plan and correctives actions and preventive measures must be considered seriously. 1.10 Support by equipments Planning is but only a part of disaster management plan, the most important part is the procurement and provisioning of specialized equipments recognized to tackle the range of disasters identified in the plan. These equipments are required to be kept in perpetual readiness and therefore it is suggested that check lists are prepared to ensure that no equipment remains unserviceable. 1.11 Evacuation In a major incident consideration of early evacuation is important. Unless personnel are part of the contingency plan they must be kept away from the incident area. The tendency to rush in and take uncoordinated action must be discouraged. Only persons nominated in the contingency plan should be in the area, and then only when their role requires them to be present. Discourage emotional offers of help unless it can be channeled into the general plan. 1.12 Summary An emergency can occur any time and anywhere. A contingency plan is designed to deal effectively with a perceived emergency and the aftermath. What cannot be planned for is the direction an incident will take once it has started. To this end a contingency plan must be flexible. If too rigid it will cause delays and possible escalation of the incident. When preparing it the Coordinator of the plan must consult even those departments not likely to be directly involved in it.