Creating the - NKT · The project was originally commissioned by Public Power Corporation S.A....

2
Scope Complete cable system, including 80 km of 400 kV 1x2,000 mm² copper XLPE cable with APL and approximately 16 km of fibre optic cable. Design and engineering. Manufacture and project management. Tailor-made logistical concept and civil works including horizontal drilling. Efficient installation performance including 90 straight joints and 12 terminations and final testing. FLYENIN180601web NKT TM is a trademark of NKT Group. ©2018 All rights reserved NKT GmbH & Co. KG Düsseldorfer Strasse 400 51061 Cologne Germany T: +49 221 676 0 [email protected] nkt.com NKT is signatory of the Europacable Industry Charter: A commitment towards superior quality. ® Client: Public Power Corporation SA (PPC) Location of the project: Chalcis (Chalkida), Euboea, Greece Quantity of order: 400 kV cable system with a 1,200 A (830 MVA) capacity per circuit Total cable route length: 13.5 km Duration: 2010 - 2013 Location Key Facts A turnkey cable system solution ensured realisation of Greece’s first underground 400 kV transmission project. Creating the Afrati-Avlida link TURKEY GREECE ALBANIA ITALY Afrati-Avlida nkt.com

Transcript of Creating the - NKT · The project was originally commissioned by Public Power Corporation S.A....

Page 1: Creating the - NKT · The project was originally commissioned by Public Power Corporation S.A. (PPC), Greece’s biggest power company. It was to be undertaken about 80 km from Athens

Scope▪ Complete cable system, including 80 km of 400 kV 1x2,000 mm² copper

XLPE cable with APL and approximately 16 km of fibre optic cable.

▪ Design and engineering.

▪ Manufacture and project management.

▪ Tailor-made logistical concept and civil works including horizontal drilling.

▪ Efficientinstallationperformanceincluding90straightjointsand 12terminationsandfinaltesting.

FLY

EN

IN18

0601

web

N

KTTM

is a

tra

dem

ark

of N

KT

Gro

up. ©

2018

All

right

s re

serv

ed

NKT GmbH & Co. KGDüsseldorfer Strasse 40051061 Cologne Germany

T: +49 221 676 0 [email protected]

NKT is signatory of the Europacable Industry Charter: A commitment towards superior quality.

®

Client:Public Power Corporation SA (PPC)

Location of the project:Chalcis (Chalkida), Euboea, Greece

Quantity of order:400 kV cable system with a 1,200 A (830 MVA) capacity per circuit

Total cable route length:13.5 km

Duration:2010 - 2013

Location

Key Facts

A turnkey cable system solution ensured realisation of Greece’s first underground 400 kV transmission project.

Creating the Afrati-Avlida link TURKEY

GREECE

ALBANIA

ITALY

Afrati-Avlida

nkt.com

Page 2: Creating the - NKT · The project was originally commissioned by Public Power Corporation S.A. (PPC), Greece’s biggest power company. It was to be undertaken about 80 km from Athens

“Challenging power-link projects showcase our agility and high standards of project execution.”More energy,

less pollution.One of the world’s longest 400 kV XLPE cable systems contributes to sustainability in Greece.

The project The Aliveri power plant on the island of Euboea was to be interconnected with the mainland grid.

The project was very important for the Greek electrical grid and the regional development pro-gramme. Two parallel 400 kV (kilovolt) underground cable circuits were to interconnect the Aliveri combined-cycle thermal plant on Euboea with the continental transmission grid.

The new gas-fired plant replaced the previous fuel-oil and lignite-fired capacity, thereby helping reduce pollution, especially CO2 (carbon dioxide) emissions. It contributed to present and future requirements for electricity throughout Greece by replacing withdrawn capacity with a new enhanced capacity that could keep pace with growing consumer demand.

The project was originally commissioned by Public Power Corporation S.A. (PPC), Greece’s biggest power company. It was to be undertaken about 80 km from Athens and then handed over to ADMIE, S.A.

There were, however, significant technical challenges. One of them was a submarine section at the Chalcis Suspension Bridge, which required several long drillings beneath the seabed. Another customer requirement was that the first circuit be put into service as soon as possible, to ensure continuous operation.

In 2010 NKT received the order to create the trans-mission link to Greece’s second-largest island.

The solutionNKT provided everything from an efficient cable system to horizontal drilling under the seabed.

The turnkey solution included design and engineer-ing, as well as production of cable for one of the circuits and all accessories for both circuits. The full range of civil works, including drilling underneath the channel between the mainland and the island, cable-laying and installation, were part of our scope in cooperation with local partners. We were also responsible for project management, installation of accessories and the final commissioning tests.

We cooperated successfully with the customer and local companies, and provided a tailor-made logistical concept that would work efficiently despite dense tourism and heavy traffic in the area. We also developed a specific method to enable continuous installation work without disruption on the second circuit while it was under the inductive influence of the first circuit.

As always, NKT prioritised safety and adapted to the specific project requirements. The well- coordinated efforts and efficient performance of our teams made it possible to finalise the project on time and to the correct quality standards.