Crab C avity Integration - Summary

17
Crab Cavity Integration - Summary •IP 4 Boundary Conditions O. Brunner •LHC Integration and RF Systems. J. Tuckmantel •Cryogenics Installation. B. Vullierme •Low Level RF and Feedback. M. Grecki •KEK-B Instrumentation for Crab Cavity Tuning. Y. Funakoshi 1 LHC-CC09 - Session V Summary - E. Ciapala

description

Crab C avity Integration - Summary. IP 4 Boundary Conditions O. Brunner LHC Integration and RF Systems. J. Tuckmantel Cryogenics Installation. B. Vullierme - PowerPoint PPT Presentation

Transcript of Crab C avity Integration - Summary

Page 1: Crab  C avity Integration -  Summary

1

Crab Cavity Integration - Summary

•IP 4 Boundary Conditions O. Brunner

•LHC Integration and RF Systems. J. Tuckmantel

•Cryogenics Installation. B. Vullierme

•Low Level RF and Feedback. M. Grecki

•KEK-B Instrumentation for Crab Cavity Tuning. Y. Funakoshi

LHC-CC09 - Session V Summary - E. Ciapala

Page 2: Crab  C avity Integration -  Summary

IR4 layout – Available locations

• Symmetric towards point 3

• Not possible to free space in the ACN cavities region (power lines, RF couplers, access behind the ACN)

• Max 3m longitudinally

IP4

ACS cavities

ACNADTSPARE ADT

ACS jumpe

r

BPMs

3-4m ≈10m

Point 5

QRL

Page 3: Crab  C avity Integration -  Summary

General view (IP4 left)

ACN power

ACN power

Crab Cavity Powering & Layout

CC could be powered by a 60kW RF power station located in the UL’s• Restricted space available in the Ul’s (possible conflict with the ACN power stations)

Need detailed integration study (very busy area) of:• the power station + control systems• LLRF (partially installed in SR4 (surface building))+ RF cabling• the power lines – waveguide hole sizing• services (water cooling, electricity (380V),…)

Page 4: Crab  C avity Integration -  Summary

4

Rough Cost Estimate IP4 Infrastructure & RF Power

LHC-CC09 - Session V Summary - E. Ciapala

Civil Engineering: ≈ 10kCHFCabling (controls): ≈ 40kCHFWater cooling: ≈ 30kCHFRF cabling: ≈ 150kCHFRF power lines (50m): ≈ 100kCHFInterlock & Control system: ≈ 80kCHFLow Level RF ≈ 125kCHFInstallation: ≈ 90kCHF

Total ~ 620 KCHF not counting Manpower..

Feasible

Page 5: Crab  C avity Integration -  Summary

Summary: LHC Integration & RF Systems JT

• Add to ‘existing’ order (on time) 1(2) additional transmitter(s)no R&D work, minimal work for installation

• Better choice : 30 kW –> 1600 Hz BW / Qext ≈ 5·105

(real world –> 60 kW Transmitter ‘available’ SPS 800MHz new IOT based amplifier)

• 2-cell structure: requires study for feedback (filter !)

• RF power transfer might require a new hole (limestone)or (if ACN still absent) some ‘RF bricolage’

• RF noise is still not completely settled (hadron machine !) CONCERN !

• For |Dx0| ≤ 200µm and perfectly tuned (stable) cavity:

5 kW RF power sufficient ––> 80 Hz BW / Qext=2·107

Page 6: Crab  C avity Integration -  Summary

6

Cryogenics Installation – Summary - BV

•Can not extend existing ACS QRL Extension•Can not install an additional service module – no space•Two options..

LHC-CC09 - Session V Summary - E. Ciapala

Page 7: Crab  C avity Integration -  Summary

7

Cryogenics Installation – Summary - BV

•Option 1) 2K System - Replace existing SM with new design

LHC-CC09 - Session V Summary - E. Ciapala

50 K supply

20 K return

75 K return

Pumping returnNew QRL

Service Module

Modified QRL Extension to ACS

4.6 K supply

ACS 1 ACS 2 CC

C

B

2 bar

0.5 bar

D

Hel

ium

gua

rd1.

3 ba

r

F

E

New

QR

L E

xten

sion

to C

C

CC design pressure: 3.5 bar CC operating pressure: saturated helium @ 2 K Helium guard required on CC safety (sub-atmospheric) circuits Additional cooling power of 50 W @ 2 K is available for CC

Removal and reinstallation of neighboring ACS cryomodules20 critical cuts and welds on the 5 QRL headers5 to 6 weeks for dismantling/installation (cryo only)Nearly global pressure tests for both 3-4 and 4-5 LHC sectorsCost for such QRL modifications : > 1 MCHF

Page 8: Crab  C avity Integration -  Summary

8

Cryogenics Installation - BV•Option 2) 4.5 K simple option

LHC-CC09 - Session V Summary - E. Ciapala

The straightforward solution is to finally modify the supply and return lines of the QRL extension to one of the two ACS cryomodules, in order to connect the CC in parallel, via an additional set of valves.

F50 K supply

20 K return

E

75 K return

Pumping returnQRL Service Module

Modified QRL Extension

4.6 K supply

ACS 1 ACS 2 CC

C

B

2.5 bar19 bar

D

Page 9: Crab  C avity Integration -  Summary

9

Cryogenics Installation – Summary - BV•Option 2) 4.5 K simple option contd.

LHC-CC09 - Session V Summary - E. Ciapala

Design pressure of CC helium vessel: 3.5 bar CC helium pressure, temperature: 1. 35 bar, 4.6 K The CC required flow rate of 15-30 g/s of helium at 4.6 K from QRL header “C “

should be available. The flow coefficient of the existing QRL supply and return control valves can be

increased (ACS + CC He flow rates ). Concern for Existing ACS !!! Controls: liquid helium level and pressure controls with dedicated control (and

shut-off) valves. Safety: non-return valves to QRL header “D”, possible pressure interlocks (QRL

header “C”, QRL header “D”, ACS) Possibility of using an additional circuit for helium return to the Warm Recovery

Line via an electrical heater, during magnet quenches (i.e. pressurization of QRL header “D”).

The present elbow region of the QRL extension to the ACS can be cut and replaced by a T-shape part (+ 4 control valves, + safety circuits, + 2 cryogenic lines with bayonets to CC cryostat)

Installation: 1 week, local pressure and leak tests only, not critical

Page 10: Crab  C avity Integration -  Summary

10

Cryogenics Installation – Summary - BV

LHC-CC09 - Session V Summary - E. Ciapala

OPTION 1 OPTION 2Saturated liquid helium temperature 2 K 4.6 K

Heat loads @ temperature 50 W 250-500 WRemoval/reinstallation of ACS cryomodules Yes (time?) None

QRL Service Module replacement Yes, 6 weeks None

Installation of QRL Extensions to ACS and CC 2 weeks 1 weekNearly global LHC sector pressure tests Yes (2 x 1 week) None

Impact on LHC during prototype tests Marginal Not critical

Impact on LHC during regular operation Marginal Not critical *

Total installation time (QRL cryogenics only) 10 weeks 1 week

Cost > 1 MCHF 150 kCHF

Page 11: Crab  C avity Integration -  Summary

11

LLRF & Feedback – MG (1)

•Review of LLRF system Layouts, Analog, Digital systems etc.

•Need for LLRF & Feedbacks – beam loading, drive feedback, cavity dynamics, thermal, effects, microphonics, Lorentz detuning, noise sources.

•ATCA based hardware – User Community•Expert / Adaptive Systems at FLASH•Aim for high Reliability

LHC-CC09 - Session V Summary - E. Ciapala

Page 12: Crab  C avity Integration -  Summary

12

LLRF & Feedback - MG

•Phase Noise Correction at FLASH. 0.01 % amplitude, 0.01 degree

LHC-CC09 - Session V Summary - E. Ciapala

Page 13: Crab  C avity Integration -  Summary

13

KEK-B Instrumentation for Crab Cavity Tuning - Y. Funakoshi

•The crabbing motion of the beam with a single crab cavity scheme has been confirmed by the streak camera measurement

LHC-CC09 - Session V Summary - E. Ciapala

HER crab phase

Tilt

angl

e [ra

d]

Page 14: Crab  C avity Integration -  Summary

14

KEK-B Instrumentation for Crab Cavity Tuning - Y. Funakoshi

•Effective head-on collision was confirmed by the measurement of the beam-beam deflection.

LHC-CC09 - Session V Summary - E. Ciapala

Bunch Current: 0.73/0.42 mA Bunch Current: 0.64/0.47 mA

HER current was lost from 15 to 13.5 mA during scan.

Crab ON ( Vc = 1.31/0.92 MV)

Horizontal effective size at IP reduces to 72% by the crab.

Σx_x’=00=167 +/- 3 m (ON)

-100

-50

0

50

100

-200 -100 0 100 200

BBK2_03031101Crab OFF

BBK:DX1_cBBK:DX2_c

BB

Kic

k (

m)

H_OFFSET (m)

DkDx x'0DkDx x'11

2.14

-150-100-500

50100150200

-300 -200 -100 0 100 200 300

BBK2_03011942Crab ON

BBK:DX1_cBBK:DX2_c

BB

Kic

k (

m)

H_OFFSET (m)

Σx_x’=11=230 +/- 3 m (OFF) Ratio of

Slope:

Page 15: Crab  C avity Integration -  Summary

15

KEK-B Instrumentation for Crab Cavity Tuning - Y. Funakoshi

•The synchronous phase shifts along the train from the transient beam loading have some size at KEKB. However, their impact on the luminosity is very small owing to the cancelation of the effect between the two rings

•CRAB ON/OFF similar ..(ON shown)

LHC-CC09 - Session V Summary - E. Ciapala

Z

00.51

1.52

2.53

3.5

0 1000 2000 3000 4000 5000

LER_071031_3.06_1530mAP_c

Phas

e_c

(deg

)

Bucket

0

0.5

1

1.5

2

2.5

3

0 1000 2000 3000 4000 5000

HER_071031_3.06_800mAP_c

Phas

e_c

(deg

)Bucket

X

-0.8

-0.7

-0.6

-0.5

-0.4

0 1000 2000 3000 4000 5000

HER_071031_3.06_800mAX_c

X_c

_Pos

(mm

)

Bucket

2.5

2.55

2.6

2.65

2.7

0 1000 2000 3000 4000 5000

LER_071031_3.06_1530mAX_c

X_P

ositi

on_c

(mm

)

Bucket

Page 16: Crab  C avity Integration -  Summary

16

KEK-B Instrumentation for Crab Cavity Tuning - Y. Funakoshi

•Almost no harmful effects due to the crab cavities or the single crab cavity scheme (global crab cavity scheme) from the viewpoint of the beam dynamics.

Dynamic aperture, synchro-betatron resonance (yesterday’s talk)Bunch current dependent tune shift, loss parameter, bunch lengthening, coupled bunch instabiity

•Crab Vc is determined so as to maximize the luminosity in the real beam tuning situation at KEKB.

•Scanning techniques to get optimum Vc, Phase and Orbit Centre

•The phase errors of the crab cavities are much less than the allowed level of the errors obtained from the beam-beam simulations

LHC-CC09 - Session V Summary - E. Ciapala

N=1585

Page 17: Crab  C avity Integration -  Summary

17

KEK-B Instrumentation for Crab Cavity Tuning - Y. Funakoshi

• At KEKB, the dynamic beam-beam effects (emittance enlargement and the beta-beating) are very important, since the horizontal tune is very close to the half-integer.

• Due to this problem, physical aperture around the crab cavity limited the ring acceptance. After solving this problem, we could increase the bunch current (of HER) and the luminosity.

• In autumn this year, we will operate KEKB for about 2 months. There is possibility that it will be the final opportunity to operate the crab cavities at KEKB.

LHC-CC09 - Session V Summary - E. Ciapala