CPM PERT

58
CPM/PERT CPM/PERT S. Ajit

description

Its a presentation which explains how to go about solving CPM and PERT problems

Transcript of CPM PERT

Page 1: CPM PERT

CPM/PERTCPM/PERT

S. Ajit

Page 2: CPM PERT

ProjectProject

“A project is a series of activities directed to the accomplishment of a desired objective.”

Page 3: CPM PERT

HistoryHistory

PERT was developed by the US Navy for the planning and control of the Polaris missile program and the emphasis was on completing the program in the shortest possible time. In addition PERT had the ability to cope with uncertain activity completion times (e.g. for a particular activity the most likely completion time is 4 weeks but it could be anywhere between 3 weeks and 8 weeks).

CPM was developed by Du Pont and the emphasis was on the trade-off between the cost of the project and its overall completion time (e.g. for certain activities it may be possible to decrease their completion times by spending more money - how does this affect the overall completion time of the project?)

Developed in the 1950s

Page 4: CPM PERT

CPM - Critical Path MethodCPM - Critical Path Method

Definition: In CPM activities are shown as a network of precedence relationships using activity-on-node network construction– Single estimate of activity time– Deterministic activity times

USED IN : Production management - for the jobs of repetitive in nature where the activity time estimates can be predicted with considerable certainty due to the existence of past experience.

Page 5: CPM PERT

PERT - PERT - Project Evaluation & Review Project Evaluation & Review

TechniquesTechniques Definition: In PERT activities are shown as a network of

precedence relationships using activity-on-arrow network construction– Multiple time estimates – Probabilistic activity times

USED IN : Project management - for non-repetitive jobs (research and development work), where the time and cost estimates tend to be quite uncertain. This technique uses probabilistic time estimates.

Page 6: CPM PERT

The Project NetworkThe Project Network

Use of nodes and arrows

Arrows An arrow leads from tail to head directionally– Indicate ACTIVITY, a time consuming effort that is

required to perform a part of the work.

Nodes A node is represented by a circle- Indicate EVENT, a point in time where one or more

activities start and/or finish.

Page 7: CPM PERT

– An activity is a time-consuming effort that is required to complete part of a project. Shown as an arrow on the diagram

– An event is denoted by a circle and defines the end of one activity and beginning of the next. An event may be a decision point.

Activity Event

The Project NetworkThe Project Network

Page 8: CPM PERT

Activity SlackActivity Slack

Each event has two important times associated with it :

- Earliest time , Te , which is a calendar time when an event can occur when all the predecessor events completed at the earliest possible times

- Latest time , TL , which is the latest time the event can occur with out delaying the subsequent events and completion of project.

Difference between the latest time and the earliest time of an event is the slack time for that event

Positive slack : Slack is the amount of time an event can be delayed without delaying the project completion

Page 9: CPM PERT

Critical PathCritical Path

Is that the sequence of activities and events where there is no “slack” i.e.. Zero slack

Longest path through a network

minimum project completion time

Page 10: CPM PERT

Questions Answered by CPM & PERTQuestions Answered by CPM & PERT

Completion date?

On Schedule?

Within Budget?

Critical Activities?

How can the project be finished early at the least cost?

Page 11: CPM PERT

ExampleExample1. Construct the CPM Network using the details below and determine the critical path

Activity Immediate Predecessor

Duration

A - 1

B A 4

C A 2

D A 2

E D 3

F D 3

G E 2

H F,G 1

I C,H 3

J B 2

Page 12: CPM PERT

1 2

CPM NETWORK

A

Page 13: CPM PERT

1 7

4

2

3

CPM NETWORK

A

B

D

C

Page 14: CPM PERT

1 7

6

5

4

2

3

CPM NETWORK

A

B

DF

E

C

Page 15: CPM PERT

1 7

6

5

4

2

3

CPM NETWORK

A

B

DF

GE

C

Page 16: CPM PERT

1 7

6

5

4

2

3

CPM NETWORK

A

B

DF

GE

C

H

Page 17: CPM PERT

1 7

6

5

4

2 8

3

CPM NETWORK

A

B

DF

GE

C

IH

Page 18: CPM PERT

1 7

6

5

4

2 8

3

CPM NETWORK

A

J

B

DF

GE

C

IH

Page 19: CPM PERT

1 7

6

5

4

2 8

3

CPM NETWORK with duration of each activity

A(1)

J(2)

B(4)

D(2)

F(3)G(2)

E(3)

C(2)

I(3)

H(1)

Page 20: CPM PERT

1 7

6

5

4

2 8

3

To find the Critical Path

A(1)

J(2)

B(4)

D(2)F(3)

G(2)E(3)

C(2)

I(3)H(1) 0

0

LFT EST

Page 21: CPM PERT

1 7

6

5

4

2 8

3

A(1)

J(2)

B(4)

D(2)F(3)

G(2)E(3)

C(2)

I(3)H(1) 0

0 0 1

LFT EST

To find the Critical Path

Page 22: CPM PERT

1 7

6

5

4

2 8

3

A(1)

J(2)

B(4)

D(2)F(3)

G(2)E(3)

C(2)

I(3)H(1) 0

0 0 1

0 3

To find the Critical Path LFT EST

Page 23: CPM PERT

1 7

6

5

4

2 8

3

A(1)

J(2)

B(4)

D(2)F(3)

G(2)E(3)

C(2)

I(3)H(1) 0

0

0 6

0 1

0 3

To find the Critical Path LFT EST

Page 24: CPM PERT

1 7

6

5

4

2 8

3

A(1)

J(2)

B(4)

D(2)F(3)

G(2)E(3)

C(2)

I(3)H(1) 0

0

0 6

0 1

0 3

0 8

To find the Critical Path LFT EST

Page 25: CPM PERT

1 7

6

5

4

2 8

3

A(1)

J(2)

B(4)

D(2)F(3)

G(2)E(3)

C(2)

I(3)H(1) 0

00 9

0 6

0 1

0 3

0 8

To find the Critical Path LFT EST

Page 26: CPM PERT

1 7

6

5

4

2 8

3

A(1)

J(2)

B(4)

D(2)F(3)

G(2)E(3)

C(2)

I(3)H(1) 0

0 0 9

0 6

0 5

0 1

0 3

0 8

To find the Critical Path LFT EST

Page 27: CPM PERT

1 7

6

5

4

2 8

3

A(1)

J(2)

B(4)

D(2)F(3)

G(2)E(3)

C(2)

I(3)H(1) 0

00 9

0 12

0 6

0 5

0 1

0 3

0 8

To find the Critical Path LFT EST

Page 28: CPM PERT

1 7

6

5

4

2 8

3

A(1)

J(2)

B(4)

D(2)F(3)

G(2)E(3)

C(2)

I(3)H(1) 0

00 9

12 12

0 6

0 5

0 1

0 3

0 8

To find the Critical Path LFT EST

Page 29: CPM PERT

1 7

6

5

4

2 8

3

A(1)

J(2)

B(4)

D(2)F(3)

G(2)E(3)

C(2)

I(3)H(1) 0

09 9

12 12

0 6

0 5

0 1

0 3

0 8

To find the Critical Path LFT EST

Page 30: CPM PERT

1 7

6

5

4

2 8

3

A(1)

J(2)

B(4)

D(2)F(3)

G(2)E(3)

C(2)

I(3)H(1) 0

09 9

12 12

0 6

0 5

0 1

0 3

8 8

To find the Critical Path LFT EST

Page 31: CPM PERT

1 7

6

5

4

2 8

3

A(1)

J(2)

B(4)

D(2)F(3)

G(2)E(3)

C(2)

I(3)H(1) 0

09 9

12 12

6 6

0 5

0 1

0 3

8 8

To find the Critical Path LFT EST

Page 32: CPM PERT

1 7

6

5

4

2 8

3

A(1)

J(2)

B(4)

D(2)F(3)

G(2)E(3)

C(2)

I(3)H(1) 0

09 9

12 12

6 6

0 5

0 1

3 3

8 8

To find the Critical Path LFT EST

Page 33: CPM PERT

1 7

6

5

4

2 8

3

A(1)

J(2)

B(4)

D(2)F(3)

G(2)E(3)

C(2)

I(3)H(1) 0

09 9

12 12

6 6

0 5

1 1

3 3

8 8

To find the Critical Path LFT EST

Page 34: CPM PERT

1 7

6

5

4

2 8

3

A(1)

J(2)

B(4)

D(2)F(3)

G(2)E(3)

C(2)

I(3)H(1) 0

09 9

12 12

6 6

10 5

1 1

3 3

8 8

To find the Critical Path LFT EST

Page 35: CPM PERT

1 7

6

5

4

2 8

3

A(1)

J(2)

B(4)

D(2)F(3)

G(2)E(3)

C(2)

I(3)H(1) 0

09 9

12 12

6 6

10 5

1 1

3 3

8 8

Critical Path

Critical Path

A – B – E – G – H - I

Critical Path

1 - 2 - 4 – 5 – 6 – 7 - 8

Page 36: CPM PERT

CPM - ExampleCPM - Example

Critical Path

1 - 2 - 4 – 5 – 6 – 7 – 8

Critical Path

A – B – E – G – H - IProject Completion Time = 12 months

Page 37: CPM PERT

PERTPERTProbabilisticThree estimates

– to (a) – optimistic time

– tp (b) – pessimistic time

– tl (m) – most likely time

Mean µ = (to + 4* tl + tp)/6

Variance σ2 = [(tp – to)/6]2

Page 38: CPM PERT

Activity Predecessor

a m b

A - 6 7 8

B - 1 2 9

C - 1 4 7

D A 1 2 3

E A,B 1 2 9

F C 1 5 9

G C 2 2 8

H E,F 4 4 4

I E,F 4 4 10

J D,H 2 5 14

K G,I 2 2 8

PERT – Example: PERT – Example: Construct Project network, find the Construct Project network, find the expected duration and variance for each activity & find the expected duration and variance for each activity & find the

critical path and expected project completion timecritical path and expected project completion time

Page 39: CPM PERT

Activity

Predecessor

a m b µte

A - 6 7 8 7

B - 1 2 9

C - 1 4 7

D A 1 2 3

E A,B 1 2 9

F C 1 5 9

G C 2 2 8

H E,F 4 4 4

I E,F 4 4 10

J D,H 2 5 14

K G,I 2 2 8

PERT – Example: PERT – Example: Mean µ = (tMean µ = (too + 4* t + 4* tll + t + tpp)/6)/6 Variance Variance σσ22 = [(t = [(tpp – t – too)/6])/6]22

Page 40: CPM PERT

Activity

Predecessor

a m b µte

A - 6 7 8 7

B - 1 2 9 3

C - 1 4 7

D A 1 2 3

E A,B 1 2 9

F C 1 5 9

G C 2 2 8

H E,F 4 4 4

I E,F 4 4 10

J D,H 2 5 14

K G,I 2 2 8

PERT – Example: PERT – Example: Mean µ = (tMean µ = (too + 4* t + 4* tll + t + tpp)/6)/6 Variance Variance σσ22 = [(t = [(tpp – t – too)/6])/6]22

Page 41: CPM PERT

Activity

Predecessor

a m b µte

σ2

A - 6 7 8 7

B - 1 2 9 3

C - 1 4 7 4

D A 1 2 3 2

E A,B 1 2 9 3

F C 1 5 9 5

G C 2 2 8 3

H E,F 4 4 4 4

I E,F 4 4 10 5

J D,H 2 5 14 6

K G,I 2 2 8 3

PERT – Example: PERT – Example: Mean µ = (tMean µ = (too + 4* t + 4* tll + t + tpp)/6)/6 Variance Variance σσ22 = [(t = [(tpp – t – too)/6])/6]22

Page 42: CPM PERT

Activity

Predecessor

a m b µte

σ2

A - 6 7 8 7 0.11

B - 1 2 9 3

C - 1 4 7 4

D A 1 2 3 2

E A,B 1 2 9 3

F C 1 5 9 5

G C 2 2 8 3

H E,F 4 4 4 4

I E,F 4 4 10 5

J D,H 2 5 14 6

K G,I 2 2 8 3

PERT – Example: PERT – Example: Mean µ = (tMean µ = (too + 4* t + 4* tll + t + tpp)/6)/6 Variance Variance σσ22 = [(t = [(tpp – t – too)/6])/6]22

Page 43: CPM PERT

Activity

Predecessor

a m b µte

σ2

A - 6 7 8 7 0.11

B - 1 2 9 3 1.78

C - 1 4 7 4

D A 1 2 3 2

E A,B 1 2 9 3

F C 1 5 9 5

G C 2 2 8 3

H E,F 4 4 4 4

I E,F 4 4 10 5

J D,H 2 5 14 6

K G,I 2 2 8 3

PERT – Example: PERT – Example: Mean µ = (tMean µ = (too + 4* t + 4* tll + t + tpp)/6)/6 Variance Variance σσ22 = [(t = [(tpp – t – too)/6])/6]22

Page 44: CPM PERT

Activity

Predecessor

a m b µte

σ2

A - 6 7 8 7 0.11

B - 1 2 9 3 1.78

C - 1 4 7 4 1.00

D A 1 2 3 2 0.11

E A,B 1 2 9 3 1.78

F C 1 5 9 5 1.78

G C 2 2 8 3 1.00

H E,F 4 4 4 4 0

I E,F 4 4 10 5 1.00

J D,H 2 5 14 6 4.00

K G,I 2 2 8 3 1.00

PERT – Example: PERT – Example: Mean µ = (tMean µ = (too + 4* t + 4* tll + t + tpp)/6)/6 Variance Variance σσ22 = [(t = [(tpp – t – too)/6])/6]22

Page 45: CPM PERT

1

4

2

3

A(7)

J(6)

B(3)

D(2)

F(5)

G(3)

E(3)

C(4) I(5)

H(4)

6 6

To find the Critical Path LFT EST

K(3)

Page 46: CPM PERT

1

4

26

3

A(7)

J(6)

B(3)

D(2)

F(5)

G(3)

E(3)

C(4) I(5)

H(4)

6 6

To find the Critical Path LFT EST

K(3)

Page 47: CPM PERT

1

6

5

4

2

3

A(7)

J(6)

B(3)

D(2)

F(5)

G(3)E(3)

C(4) I(5)

H(4)

6 6

To find the Critical Path LFT EST

K(3)

Page 48: CPM PERT

1

6

5

4

2

3

A(7)

J(6)

B(3)

D(2)

F(5)

G(3)E(3)

C(4) I(5)

H(4)

6 6

To find the Critical Path LFT EST

K(3)

Page 49: CPM PERT

1

7

6

5

4

2

3

A(7)

J(6)

B(3)

D(2)

F(5)

G(3)

E(3)

C(4) I(5)

H(4)

6 6

To find the Critical Path LFT EST

K(3)

Page 50: CPM PERT

1

7

6

5

4

2

3

A(7)

J(6)

B(3)

D(2)

F(5)

G(3)

E(3)

C(4) I(5)

H(4)

6 6

To find the Critical Path LFT EST

K(3)

Page 51: CPM PERT

1

7

6

5

4

2

3

A(7)

J(6)

B(3)

D(2)

F(5)

G(3)

E(3)

C(4) I(5)

H(4)

6 6

To find the Critical Path LFT EST

K(3)

Page 52: CPM PERT

1

7

6

5

4

2

83

A(7) J(6)

B(3)

D(2)

F(5)

G(3)

E(3)

C(4) I(5)

H(4)

6 6

To find the Critical Path LFT EST

K(3)

Page 53: CPM PERT

1

7

6

5

4

2

83

A(7)J(6)

B(3)

D(2)

F(5)

G(3)

E(3)

C(4) I(5)

H(4)

6 6

To find the Critical Path LFT EST

K(3)

Page 54: CPM PERT

1

7

6

5

4

2

83

A(7) J(6)

B(3)

D(2)

F(5)

G(3)

E(3)

C(4) I(5)

H(4) 0 0

To find the Critical Path LFT EST

K(3)

1414

4 5

7 7

77

10 10

15 17

20 20

Page 55: CPM PERT

1

7

6

5

4

2

83

A(7) J(6)

B(3)

D(2)

F(5)

G(3)

E(3)

C(4) I(5)

H(4) 0 0

K(3)

1414

4 5

7 7

77

10 10

15 17

20 20

Critical path 1 – 2 – 3 – 5 – 6 – 8

Critical path A – Dummy – E – H – J

Page 56: CPM PERT

PERT - ExamplePERT - Example What is the probability of completing the project within

25 weeks?

Σσ2 = 5.89 σ = √(Σσ2) = 2.43 Ts (Scheduled time) = 25 weeks Z = (Ts – Te) / σ = (25 – 20) / 2.43 = 2.06 From z table (normal table) z(2.06) = 97.68 %

Activities

Variance

A 0.11

Dummy 0

E 1.78

H 0

J 4

Page 57: CPM PERT

PERT - ExamplePERT - Example What is the probability of completing the project within

15 weeks?

Σσ2 = 5.89 σ = √(Σσ2) = 2.43 Ts (Scheduled time) = 15 weeks Z = (Ts – Te) / σ = (15 – 20) / 2.43 = -2.06 From z table (normal table) z(-2.06) = 100 - 97.68 %

• = 2.02 %

Activities

Variance

A 0.11

Dummy 0

E 1.78

H 0

J 4

Page 58: CPM PERT

Limitations of CPM/PERTLimitations of CPM/PERT

Clearly defined, independent and stable activities

Specified precedence relationships Over emphasis on critical paths