Cpm 300a-2- Parte 1 Conceptos Basicos

download Cpm 300a-2- Parte 1 Conceptos Basicos

of 51

Transcript of Cpm 300a-2- Parte 1 Conceptos Basicos

  • CPM-300: Principles of Schedule ManagementLesson A: Basic Scheduling Concepts Part 1

    Lee MillerSM&[email protected]: May 21, 2014

    EVMWorld2014Conference

  • CPMEVMWorld2014RightsReserved

    Terminal Learning Objectives

    TLO #1: The student will understand the key terms used in this course

    TLO #2: The student will understand the concept of Project Time Schedule Management

    TLO #3: The student will understand the three primary forms of schedules & when each type is appropriate

    TLO #4 The student will understand the types of schedule dependencies & constraints as well as their appropriate use

    TLO #5 The student will understand the common practices for estimating activity durations

    2

  • CPMEVMWorld2014RightsReserved

    Lesson Objectives

    Course participants will gain an understanding of: Key terms used in this course The concept of Project Time Schedule

    Management The three primary forms of schedules & when

    each type is appropriate The types of schedule dependencies &

    constraints as well as their appropriate use Common practices for estimating activity

    durations

    3

    TLO#1

  • CPMEVMWorld2014RightsReserved

    *Project - A temporary endeavor undertaken to produce a unique product, service or result

    *Project Management - The application of knowledge, skills, tools, and techniques to project activities to meet project requirements.

    Key Terms

    * PMBOK Definition

    4

    TLO#1

  • CPMEVMWorld2014RightsReserved

    Work Scope - Statements describing the work that must be done to produce all project deliverables.

    *Project Time Management - A subset of project management that includes the processes required to ensure timely completion of the project.

    Key Terms

    * PMBOK Definition

    5

    TLO#1

  • CPMEVMWorld2014RightsReserved

    Scheduling - A PM practice for time phased planning and control of work scope & events.

    *Project Schedule An achievable plan for meeting the targeted dates for performing activities and for accomplishing milestones

    Key Terms

    * PMBOK Definition

    6

    TLO#1

  • CPMEVMWorld2014RightsReserved

    Activity / Task - A detailed component of work performed during the course of the project.

    *Milestone - A significant event in a project, usually completion of a major deliverable.

    Key Terms

    * PMBOK Definition

    7

    TLO#1

  • CPMEVMWorld2014RightsReserved

    Lesson Objectives

    Course participants will gain an understanding of: Key terms used in this course The concept of Project Time Schedule

    Management The three primary forms of schedules & when

    each type is appropriate The types of schedule dependencies &

    constraints as well as their appropriate use Common practices for estimating activity

    durations

    8

    TLO#2

  • CPMEVMWorld2014RightsReserved

    Project Time ManagementPMBOKs 6 Processes

    9

    TLO#2

  • CPMEVMWorld2014RightsReserved

    Time Management in the PMBOKProject Life-Cycle

    Initiate Plan Execute Control Close

    ActivityDefinitionActivitySequencingActivityDuration EstimatingScheduleDevelopment

    ScheduleControl

    10

    TLO#2

  • CPMEVMWorld2014RightsReserved

    Key Schedule Inputs

    11

    TLO#2

  • CPMEVMWorld2014RightsReserved

    Lesson Objectives

    Course participants will gain an understanding of: Key terms used in this course The concept of Project Time Schedule

    Management The three primary forms of schedules & when

    each type is appropriate The types of schedule dependencies &

    constraints as well as their appropriate use Common practices for estimating activity

    durations

    12

    TLO#3

  • CPMEVMWorld2014RightsReserved

    Primary Types of ProjectSchedules

    NetworkSchedule

    Gantt/BarSchedule

    MilestoneSchedule

    13

    TLO#3

  • CPMEVMWorld2014RightsReserved

    Gantt/Bar Schedule

    ActivityTimePeriods

    1 2 3 4 5 6

    DesignHome

    ExcavateFoundation

    PourConcrete

    BuildHouse

    InstallLandscaping

    14

    TLO#3

  • CPMEVMWorld2014RightsReserved

    Gantt/Bar Schedule w/Progress

    ActivityTimePeriods

    1 2 3 4 5 6

    DesignHome

    ExcavateFoundation

    PourConcrete

    BuildHouse

    InstallLandscaping

    TimeNow15

    TLO#3

  • CPMEVMWorld2014RightsReserved

    Gantt/Bar ScheduleAdvantages

    Graphically portrays plan, schedule and progress

    Simple, easily understood Good for communication to

    managers or team members

    16

    TLO#3

  • CPMEVMWorld2014RightsReserved

    Gantt/Bar ScheduleDisadvantages

    Not easy to manage task sequencing

    Not as easy to conduct what-if scenarios

    17

    TLO#3

  • CPMEVMWorld2014RightsReserved

    Milestone Schedule

    ActivityTimePeriods

    1 2 3 4 5 6

    HomeDesigned

    ExcavationComplete

    ConcretePoured

    HouseBuilt

    LandscapingComplete

    Finish

    18

    TLO#3

  • CPMEVMWorld2014RightsReserved

    Product Milestone Schedule

    ActivityTimePeriods

    1 2 3 4 5 6

    HomeDesign

    FoundationExcavation

    ConcreteFoundation

    HouseConstruction

    Landscaping

    Start Finish

    19

    TLO#3

  • CPMEVMWorld2014RightsReserved

    Milestone Schedule w/Forecasts

    ActivityTimePeriods

    1 2 3 4 5 6

    HomeDesigned

    ExcavationComplete

    ConcretePoured

    HouseBuilt

    LandscapingComplete

    FinishForecast

    20

    TLO#3

  • CPMEVMWorld2014RightsReserved

    Milestone ScheduleAdvantages

    Simple to understand Excellent for communications

    to executive management or clients

    21

    TLO#3

  • CPMEVMWorld2014RightsReserved

    Milestone ScheduleDisadvantages

    Provides no work status details Could mask trouble areas

    22

    TLO#3

  • CPMEVMWorld2014RightsReserved

    Network Schedule

    Task Task Task

    Task Task

    Task Task

    Theconceptisthatallactivitieshavepredecessorsandsuccessors

    23

    TLO#3

  • CPMEVMWorld2014RightsReserved

    Network ScheduleAdvantages

    Easily highlights critical areas Provides greater insight and robust

    reporting Easier to conduct what-if analysis Gantt and milestone views are

    available in todays technology Good tool for schedulers

    24

    TLO#3

  • CPMEVMWorld2014RightsReserved

    Network ScheduleDisadvantages

    Complex and difficult to understand

    Requires more effort to build and maintain

    25

    TLO#3

  • CPMEVMWorld2014RightsReserved

    Lesson Objectives Course participants will gain an

    understanding of: Key terms used in this course The concept of Project Time Schedule

    Management The three primary forms of schedules & when

    each type is appropriate The types of schedule dependencies &

    constraints as well as their appropriate use Common practices for estimating activity

    durations

    26

    TLO#4

  • CPMEVMWorld2014RightsReserved

    Dependency Types

    FinishtoStart(FS)

    FinishtoFinish(FF)

    StarttoStart(SS)

    StarttoFinish(SF)

    MorecommonlycalledRelationships

    27

    TLO#4

  • CPMEVMWorld2014RightsReserved

    Finish-to-Start

    Activity B can start as soon as A finishes

    APull Cork

    BPour Wine

    (FS)

    28

    TLO#4

  • CPMEVMWorld2014RightsReserved

    Start-to-Start

    ActivityBcanstartafterAstarts

    AExcavate for

    Electrical Manholes

    BInstall Manholes

    (SS)

    29

    TLO#4

  • CPMEVMWorld2014RightsReserved

    Finish-to-Finish

    ActivityBcanfinishafterAfinishes

    AWrite Final Chapter

    BReview Book

    (FF)

    30

    TLO#4

  • CPMEVMWorld2014RightsReserved

    Start-to-Finish

    ActivityBcannotfinishuntilAhasstarted

    ADeliver Flowers

    BBill Customer

    (SF)

    31

    TLO#4

  • CPMEVMWorld2014RightsReserved

    Relationship Leads & Lags

    Task 1

    Task2

    FSw/Lead2d

    Task 1

    Task2

    FSw/Lag+2d

    32

    TLO#4

  • CPMEVMWorld2014RightsReserved

    Lags - Better Practice

    Draft for Review

    FS+10d

    Incorporate Comments

    Draft for Review

    Incorporate Comments

    Customer Review

    Original

    Improved

    33

    TLO#4

    Note: Customer Review is known as a Schedule Visibility Task (SVT). A SVT is an un-resourced activity representing effort that is not part of the budgeted program scope, but

    that is related to and may potentially impact program tasks

  • CPMEVMWorld2014RightsReserved

    Leads - Best Practice

    Build

    Design

    Build

    Draft Design Finalize Design

    FS10d

    FS

    FS

    FF

    Original

    Improved

    34

    TLO#4

  • CPMEVMWorld2014RightsReserved

    Constraints

    Constraints are restrictions set on the start or finish dates of tasks. These restrictions: establish dates, or place conditions on how dates are calculated,

    and/or affect total float calculations within the

    schedule.

    TLO#4

    35

  • CPMEVMWorld2014RightsReserved

    Types of Constraints

    Not Earlier Than (NET) Finish/Start (FNET/SNET)

    Not Later Than (NLT) Finish/Start (FNLT/SNLT)

    Imposed Dates Must Finish On (MFO) Must Start On (MSO)

    As Late As Possible (ALAP)

    Note: As Soon As Possible (ASAP) is generally called a constraint condition by software programs, but it essentially means there is no constraint

    TLO#4

    36

  • CPMEVMWorld2014RightsReserved

    Examples of Directed Dates NET

    Funds availability Contract award Seasonal considerations

    NLT Contract completion date Physical event Seasonal considerations

    Imposed dates Reviews (Design/Program) Launch date

    TLO#4

    37

  • CPMEVMWorld2014RightsReserved

    Constraint: None

    TLO#4

    38

  • CPMEVMWorld2014RightsReserved

    Constraint: Start No Earlier ThanActivity G: May 21 (Originally May 18)

    TLO#4

    39

  • CPMEVMWorld2014RightsReserved

    Constraint: Start No Later Than

    Activity G: May 16 (Originally May 18)

    TLO#4

    40

  • CPMEVMWorld2014RightsReserved

    Constraint: Finish No Earlier Than

    Activity G: May 31 (Originally May 25)

    TLO#4

    41

  • CPMEVMWorld2014RightsReserved

    Constraint: Finish No Later Than

    Activity G: May 21 (Originally May 25)

    TLO#4

    42

  • CPMEVMWorld2014RightsReserved

    Cautions re Use of Constraints

    The use of constraints generally effects/supersedes network planning solution: NET - Forward Pass NLT - Backward Pass Imposed - possibly both

    Do not use constraints to force the schedule to say what you want it to say

    TLO#4

    43

  • CPMEVMWorld2014RightsReserved

    Lesson Objectives

    Course participants will gain an understanding of: Key terms used in this course The concept of Project Time Schedule

    Management The three primary forms of schedules & when

    each type is appropriate The types of schedule dependencies &

    constraints as well as their appropriate use Common practices for estimating activity

    durations

    44

    TLO#5

  • CPMEVMWorld2014RightsReserved

    Activity Duration EstimatesPractices

    Developed for each activity/task Consult with subject matter experts Generally assumes normal conditions

    (manpower, equipment, calendar, etc.) Based on activity type; can be a direct

    function of resource availability/capability

    Uses company estimating methods (as applicable)

    45

    TLO#5

  • CPMEVMWorld2014RightsReserved

    Questions for the Audience Not Rhetorical

    A task has been estimated to require a total of 80 person hours to execute How many work days should we show as the

    duration? What form of resource categories do your

    companies use? By person? By organization? By Skill?

    TLO#5

    46

  • CPMEVMWorld2014RightsReserved

    Project X

    ADur: 10d

    EDur: 15d

    BDur:20d

    FDur: 10d

    IDur: 20d

    GDur: 8d

    CDur: 12d

    JDur: 15d

    HDur: 12d

    DDur: 18d

    KDur: 5d

    Start Complete

    47

    So,howlongwillthisprojecttake?Come to 300B for the answer.

    TLO#5

  • CPMEVMWorld2014RightsReserved

    Allactivitiesinprojectschedule Allactivitydurationsestimated Alldependenciesestablished

    Using Critical Path Method (CPM)to Establish the Project Schedule Dates

    Tobediscussedin300B.

    48

  • CPMEVMWorld2014RightsReserved

    Thankyou.

    AnyQuestions?

    49

  • CPMEVMWorld2014RightsReserved

    OFFICIAL VERSION

    COLLEGE OF PERFORMANCE MANAGEMENTPROGRAM OF INSTRUCTION

    300A VERSION 130 Mar 2014

    Approvals:

    William Mathis, V.P of Education and Certification 30 Mar 2014[Add appropriate approval individual name and title] Date

    [Add appropriate approval individual name and title] Date

    [Add appropriate approval individual name and title] Date

    50

  • CPMEVMWorld2014RightsReserved

    RECORD OF CHANGES*A - ADDED M - MODIFIED D DELETED

    VERSION NUMBER

    DATE NUMBER OF FIGURE, TABLE OR PARAGRAPH

    A*M D

    TITLE OR BRIEF DESCRIPTION

    CHANGEREQUESTNUMBER

    1 30 Mar 2014

    A,D Format changes for EVM World 2014

    51

    CD-ROM Opening ScreenTitleHelpSearchTable of ContentsPractice SymposiaPS 01 Continuous Process Improvement-When to Revise the EVMSDPS 02 EVM Back to BasicsPS 03 Current Period Planning: Permission GrantedPS 04 The IBR: Your Insurance Policy for a Sound BaselinePS 05 Lower Tier Supplier ManagementPS 06 Practical Application of an Electronic CAM (eCAM) NotebookPS 07 How to use Earned Value on a Commercial ProjectPS 08 Accurate ETCs, Compliments of the IMSPS 09 xPI Stability: Analyzing DoD ContractsPS 10 The 2X Benefit of Thorough Baseline MaintenancePS 11 EVMS Implementation at the Kansas City Plant: A Case StudyPS 12 Lessons Learned Earned Value in Recent Large and Complex IndustrialPS 13 Practical Cost Forecasting with EVMPS 14 Maturity of Integrated Project ControlsPS 15 The Increased Importance of Project Governance and Controls in Lean TimesPS 16 Project Controls Personnel: Finding the Right Stuff

    ScheduleS 01 Panel Welcome/Open Idea Exchange with PMCOS BoardS 02 CPM Its Genesis, Past & PresentS 03 Viable Option or GamesmanshipS 04 Planning, Scheduling and Detailed Planning-Getting to Earned ValueS 05 Selling and Telling with the Summary ScheduleS 06 Four Decades of Lessons LearnedS 07 Hows Your Status: An Exploration of Key Indicators to Achieve Useful StatusS 08 Preventing, Identifying and Quantifying Critical Project DelaysS 09 Modern Trends in Schedule Delay AnalysisS 10 Tips and Methods for Getting your IMS Successfully through a ReviewS 11 Project Management using Standard Project Control Tools Large and Complex ProjectsS 12 Panel Discussion, Intellectual Honesty in Project Scheduling

    AGILEAGILE 01 Introduction to Agile and ScrumAGILE 02 Agile Earned Value: Rigor Meets FlexibilityAGILE 03 Agile Performance MeasurementAGILE 04 How to Use Earned Schedule on Agile ProjectsAGILE 05 Just in Time EVM Practical Implementation of EVM in an Agile EnvironmentAGILE 06 EVM and Agile Track Wrap-Up Workshop

    Oil & GasOG 01 DOD PARCA UpdateOG 02 GAO EVM Audit Findings

    Professional Education Program (PEP) (Training Seminars)CPM-100 Principles of Earned Value ManagementCPM-100-A Principles of Performance ManagementCPM-100-B Earned Value Management FundamentalsCPM-100-C EVM Guidelines (Part 1)CPM-100-D EVM Guidelines (Part 2)CPM-100-E Establishing an EVM SystemCPM-100-F Maintaining the System and & Data Integrity

    CPM-200 Scope and Organization ManagementCPM-200-A Development of the WBSCPM-200-B Establishing the Project and TeamCPM-200-C Technical Performance MeasuresCPM-200-D Establishing the Control Account Structure, Authorizing & Controlling WorkCPM-200-E Material and Subcontract Issues in an EVMSCPM-200-F Risk and Management

    CPM-300 Principles of Schedule ManagementCPM-300-A Basic Scheduling Concepts, (Part 1)CPM-300-B Basic Scheduling Concepts, (Part 2)CPM-300-C Schedule Updates and AnalysisCPM-300-D Managing with Schedules and RecoveringCPM-300-E Intro to Schedule Risk and Analysis (Case)CPM-300-F Enterprise Wide Scheduling

    CPM-400 Principles of Earned Value Metrics & AnalysisCPM-400-A Establishing the Integrated BaselineCPM-400-B Cost, Schedule and Resource EstimatingCPM-400-C Planning Work Performance with EVMCPM-400-D Integrating Risk into the PMBCPM-400-E Statusing the Control AccountCPM-400-F The Integrated Baseline Review

    CPM-500 Execution and ControllingCPM-500-A Analyzing Control Account PerformanceCPM-500-B Variance Analysis (Part 1)CPM-500-C Variance Analysis (Part 2)CPM-500-D Reporting and Controlling Project PerformanceCPM-500-E Developing and Analyzing the EACCPM-500-F Maintaining the Performance Management Baseline (PMB)

    CPM-600 Project IntegrationCPM-600-GA Capital Asset PlanningCPM-600-GB EVM Standards, Guides and ReviewsCPM-600-GC Contracting for EVMCPM-600-GD Schedule Health MetricsCPM-600-GE Resource Management and EVMCPM-600-GF Portfolio Management & Metrics (Government)

    Tool TrackTT 01 Easier EVMS for the EnterpriseTT 02 Integrated Program ManagerTT 03 Using Risk Analysis to Improve Business PerformanceTT 04 Automated Change ControlsTT 05 Take Back Control of Your ProjectTT 06 Encore Analytics Introducing Empower 3.0TT 07 EcoSysTT 08 Steelray SoftwareTT 09 Improving Forecast Accuracy and Reliability with Deltek Acumen RiskTT 10 Getting Your EVMS Where You Want ItTT 11 C*CERT+: A Win-Win Solution for Both Contractors and GovernmentTT 12 AzTech Compliance Expert (ACE) Go From EVMS Audit-Panic to Audit-Ready

    WorkshopsWS 01 DoD IPM System Implementation InstructionWS 02 Exploring Ways to Inform BCWP Using TPMsWS 03 Civilian Agencies and Industry Working Group (CAIWG) UpdateWS 04 EVMS: 2014 to 2020 RoadmapWS 05 NDIA Integrated Program Management Division (IPMD) and Clearinghouse Working Group UpdateWS 06 Reinventing Communication: How to Design, Lead and Manage High Performing Projects