    CPIM Free Practice Questions pre-release - Mar 20

    1, This is an example of a/an:

    a, PERT diagramb, Line chartc, Histogramd, Gantt chart

    2, This is an example of a/an:

    a, PERT diagramb, Line chartc, Histogramd, Time series chart

    3, The chart below is best for analyzing:

  • 7/28/2019 Cpim Free Practice Questions Dec 20

    2/10

    a, market shareb, time series datac, production scheduled, truck load

    4, What can be used to estimate seasonal indices?

    a, regression analysisb, marginal fall backc, moving averaged, All of the choices

    5, The sequence of values usually recorded at regular increasing intervals is

    known as:

    a, forecastb, time seriesc, predictiond, estimate

    6, Which of the following is essential to the success of the use of movingaverages?

    a, regularityb, autocorrelationsc, volatilityd, None of the choices

    Answers:

    D B B C B A

  • 7/28/2019 Cpim Free Practice Questions Dec 20

    3/10

    CPIM Free Practice Questions - Mar 7

    1, ERP software facilitates the integration of different functions of the business.The functions that can be integrated include:

    a, manufacturingb, financec, human resourcesd, All of the choices

    2, Which of the following is true regarding the deployment of ERP systems?

    a, traditional ERP systems are perceived to be too expensive for smallcompanies

    b, traditional ERP systems are perceived to be too cheap for big companiesc, traditional ERP systems do not support the use of modern computing facilitiesd, None of the choices.

    3, Which of the following companies provide ERP solutions?

    a, PeopleSoftb, Microsoftc, Sund, Proctor & Gamble

    4, In theory, MRP by definition has a much broader scope than ERP.

    a, Trueb, Falsec, For computerized MRP, Yesd, For non-computerized ERP, Yes

    5, MRP-II is another name for ERP.

    a, Trueb, Falsec, For computerized MRP-II, Yesd, For non-computerized ERP, Yes

    Answers:

    D A A B B

    CPIM Free Practice Questions - Feb 22

  • 7/28/2019 Cpim Free Practice Questions Dec 20

    4/10

    1, "Capacity planning" does not support:

    a, long-term rough-cut planningb, medium-term planningc, short-term detailed planning

    d, long-term budget planning

    2, Which of the following production planning modules use the "capacityplanning" functions?

    a, Sales and Distributionb, Production Planning and Controlc, Plant Maintenanced, All of the choices.

    3, "Scheduling" is carried out in capacity planning using:

    a, standard times from task lists.b, differential times from task lists.c, relative times from project lists.d, None of the choices.

    4, "Lead time scheduling" does not take capacity loads into account.a, trueb, falsec, same as finite scheduling.

    5, "Capacity requirements" are usually expressed:

    a, as a percentage of available capacity.b, as a percentage of non-available capacity.c, as a real number.d, None of the choices.

    6, We rely on "Capacity Leveling":

    a, to determine available capacity.b, to determine capacity requirements.c, to compare available capacity with capacity requirement.d, all of the choices.

    Answers:

    D, D, A, A, A, D

    CPIM Free Practice Questions - Dec 20

  • 7/28/2019 Cpim Free Practice Questions Dec 20

    5/10

    1, Bill of Material includes information on product materials and is areference that displays:

    A. part nameB. code

    C. specificationsD. all of the above.

    2, The success and effectiveness of a manufacturing system depends upon theaccuracy and completeness of the information held by the Bill of Material.

    A. TrueB. FalseC. True only when MRP-II is used.D. True only when MRP is not used.

    3, The bill of material module maintains primarily the __________ related product

    information.A. salesB. shop floorC. flowD. engineering

    4, Bill of materials and process routings can be maintained separately.A. TrueB. False

    C. True only when fixed cell layout is used.D. True only when JIT is not used.

    5, What do we primarily use to specify relationships between components andparents?

    A. Routing filesB. Bill of materialsC. KanbanD. Database

    Answers: D A D A B

    CPIM Free Practice Questions - Dec 25

    1, The EOQ approach:

    A. does not make use of ALL the available data

  • 7/28/2019 Cpim Free Practice Questions Dec 20

    6/10

    B. ignores the actual demand patternC. is simple to useD. All of the above

    2, Lot for Lot means "don't do any lot sizing"!

    A. TrueB. FalseC. True only when MRP-II is used.D. True only when MRP is not used.

    3, The Period Order Quantity (POQ) approach:A. does not make use of ALL the available dataB. ignores the actual demand patternC. is simple to useD. All of the above

    4, The Least Unit Cost (LUC) approach produces an irregular interval betweenreplenishment orders on the basis of the number of weeks that will minimize unitcost.

    A. TrueB. FalseC. True only when demand is stable.D. True only when demand is seasonal.

    5, Practically speaking, the method of Lot Sizing to be used should not bedetermined by the particular MRP system in use.

    A. TrueB. FalseC. True only when demand is stable.D. True only when demand is seasonal.

    Answers:D

    AD

    AB

    CPIM Free Practice Questions - Jan 1

    1, A wedge is useful for implementing:

    A. bar codesB. flow shopC. job centreD. All of the above

  • 7/28/2019 Cpim Free Practice Questions Dec 20

    7/10

    2, Terminal emulation is a common way of implementing bar codes.A. TrueB. FalseC. True only when MRP-II is used.D. True only when MRP is not used.

    3, MRP II stands for:A. Manufacturing Resource PlanningB. Manufacturing Requirement PlanningC. Material Resource Planning IID. Material Requirement Planning II

    4, MRP II encompassed all of the following except:

    A. long range planningB. high level resource planning

    C. master schedulingD. None of the above.

    5, Practically speaking, MRP failed to consider the important factors of capacity,space, capital, engineering changes, and cost.

    A. TrueB. FalseC. True only when demand is stable.D. True only when demand is seasonal.

    Answers:

    AA

    A

    DA

    CPIM Free Practice Questions - Jan 10

    1, JIT is not merely another production technique. It is best described as:

    A. a collection of concepts and techniques for improving productivity.B. a collection of concepts and techniques for flow control.C. a collection of concepts and techniques for material procurement

    management.D. None of the choices.

    2, The primary objective of JIT is generally seen as waste elimination.A. True

  • 7/28/2019 Cpim Free Practice Questions Dec 20

    8/10

    B. FalseC. True only in America.D. True only for service companies.

    3, Since JIT encompasses a number of functional areas of the company, top

    management support is:A. not a must.B. needed but is not of a high priority.C. costly.D. relevant and critical.

    4, Generally, JIT must beA. implemented internally prior to involving external parties.B. implemented externally prior to involving internal parties.C. implemented based on a flat organization structure.D. implemented at cost.

    5, A flatter organization can foster more frequent open communication and isgood for the implementation of JIT.

    A. TrueB. FalseC. True only when the firm is small.D. True only when business is service-oriented.

    Answers:AAD

    AA

    CPIM Free Practice Questions - Jan 28

    1, The basic function of stock is to:

    A. insulate the production process from changes in the environmentB. insulate the production process from production material cost varianceC. insulate the production process from changes in the BOMD. implement time fence

    2, Which of the following is NOT a stock holding cost?A. rentB. depreciationC. overheadsD. None of the choices

  • 7/28/2019 Cpim Free Practice Questions Dec 20

    9/10

    3, Usually stockouts occur in the order lead time.A. TrueB. FalseC. True only when the firm is small.D. True only when business is service-oriented.

    4, Generally, MPS represents a statement of the manufacturing plan at theaggregate level.

    A. TrueB. FalseC. True only when the firm is small.D. True only when business is service-oriented.

    5, MPS is usually:A. Cost drivenB. Profit driven

    C. Return drivenD. Investment driven

    6, The production plan in general operates at what level?A. an aggregate levelB. an end item levelC. a line levelD. a product family level

    7, MRP is a system based on fulfilling predicted usage in a set time period.

    A. TrueB. FalseC. True only for SOME MRP systemsD. Not true on MRP systems that make use of computer processing

    8, Which of the following statements is true?A. MRP is a 'Push' system while JIT is a 'Pull' system.B. MRP is a 'Push' system while MRP-II is a 'Pull' system.C. MRP is a 'Pull' system while JIT is a 'Push' system.D. MRP is a 'Push' system while JIT is a 'Pull-Push' system.

    Answers:AD

    AB

    AAAA

  • 7/28/2019 Cpim Free Practice Questions Dec 20

    10/10

    CPIM Free Practice Questions - Feb 9

    1, Rough Cut Capacity Planning:a, verifies that you have sufficient capacity available to meet the capacityrequirements for your master schedules.b, is no longer needed when MRP-II is deployed.

    c, must be prepared after the MPS is available.d, None of the choices.

    2, Rough Cut Capacity Planning is a ________ plan capacity planning tool.a, long-termb, short-termc, condensedd, None of the choices.

    3, Rough Cut Capacity Planning does not consider scheduled receipts or on-hand inventory quantities when calculating capacity requirements.

    a, Trueb, Falsec, True only in a MRP-II environment.d, None of the choices.

    4, A rough cut capacity plan can be seen as a statement of the capacity requiredto meet your gross production requirements.

    a, True

    b, Falsec, True only in a MRP-II environment.d, None of the choices.

    5, You can change your master schedules by:

    a, changing master schedule dates.b, changing master schedule quantities.c, A and Bd, None of the choices.

    Answers:

    A A A A C