ID Task Name Est. Duration Est. Start - Base 1 Est. Finish - Base 1 Baseline Start Baseline Finish Status 1 1 CONTRACT PACKAGE CP2 CONSTRUCTION SCHEDULE 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule 2 1.1 PROJECT MILESTONE 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 Late 3 1.1.1 COMMENCEMENT DATE 0 days Mon 7/1/13 Mon 7/1/13 Mon 7/1/13 Mon 7/1/13 Complete 4 1.1.2 COMPLETION DATE 0 days Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Future Task 5 1.1.3 COMPLETE CONSTRUCTION OF FACILITIES 0 days Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Future Task 6 1.1.4 COMPLETE EARTHWORKS 0 days Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Future Task 7 1.1.5 COMPLETE SUBBASE AND BASE COURSE 0 days Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Future Task 8 1.1.6 COMPLETE SURFACE COURSE 0 days Thu 3/31/16 Thu 3/31/16 Sun 1/31/16 Sun 1/31/16 Future Task 9 1.1.7 COMPLETE BRIDGE CONSTRUCTION 0 days Wed 9/30/15 Wed 9/30/15 Wed 9/30/15 Wed 9/30/15 Future Task 10 1.1.8 COMPLETE DRAINAGE AND SLOPE PROTECTION STRUCTURES 0 days Thu 3/31/16 Thu 3/31/16 Sat 10/24/15 Sat 10/24/15 Future Task 11 1.1.9 MISCELLANEOUS STRUCTURES 0 days Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Future Task 12 1.1.10 COMPLETE RELOCATION OF ELECTRICAL DISTRIBUTION SYSTEM 0 days Thu 3/31/16 Thu 3/31/16 Sat 1/30/16 Sat 1/30/16 Future Task 13 1.2 PRELIMINARY WORK/PREPARE/SUBMIT/APPROVE/ SHOP DRAWINGS/DESIGN MI 305 days Mon 7/1/13 Thu 5/1/14 Mon 7/1/13 Thu 5/1/14 On Schedule 14 1.2.1 As Stake Survey 153 days Mon 7/1/13 Sat 11/30/13 Mon 7/1/13 Sat 8/31/13 Complete 15 1.2.2 Survey for Drainage and Slope Protection Structures 47 days Mon 12/16/13 Fri 1/31/14 Thu 8/15/13 Mon 9/30/13 Complete 16 1.2.3 Survey for Water Utilities 52 days Mon 3/10/14 Wed 4/30/14 Thu 8/15/13 Mon 9/30/13 Future Task 17 1.2.4 Survey for Electrical Utilities 36 days Mon 3/17/14 Mon 4/21/14 Thu 8/15/13 Mon 9/30/13 Future Task 18 1.2.5 Topographic Survey for Bridges 34 days Wed 1/15/14 Mon 2/17/14 Thu 8/15/13 Mon 9/30/13 On Schedule 19 1.2.6 Prepare and Submit Shop Drawing of Road Cross Section and Profile 267 days Wed 8/7/13 Wed 4/30/14 Mon 7/8/13 Thu 10/10/13 On Schedule 20 1.2.7 Review by Engineer of Shop Dwg of Road Cross Section and Profile 228 days Sun 9/15/13 Wed 4/30/14 Fri 10/11/13 Thu 10/24/13 On Schedule 21 1.2.8 Prepare response & resubmit Shop Dwg of Road Cross Section and Profile 164 days Mon 11/18/13 Wed 4/30/14 Fri 10/25/13 Thu 10/31/13 On Schedule 22 1.2.9 Approve Shop Drawing Roads 66 days Mon 2/24/14 Wed 4/30/14 Thu 10/31/13 Thu 10/31/13 Future Task 23 1.2.10 Prepare and Submit Shop Drawing for Drainage and Slope Protection Structure 212 days Tue 10/1/13 Wed 4/30/14 Thu 8/22/13 Thu 10/10/13 On Schedule 24 1.2.11 Review by Engineer of Shop Dwg of Drainage and Slope Protection Structures 206 days Mon 10/7/13 Wed 4/30/14 Fri 10/11/13 Thu 10/24/13 On Schedule 25 1.2.12 Prepare response & resubmit Shop Dwg of Drainage and Slope Protection Stru 178 days Mon 11/4/13 Wed 4/30/14 Fri 10/25/13 Thu 10/31/13 On Schedule 26 1.2.13 Approve Shop Drawing Drainage/Slope Protection 155 days Wed 11/27/13 Wed 4/30/14 Fri 11/1/13 Fri 11/1/13 On Schedule 27 1.2.14 Prepare and Submit Shop Drawing for Water Utilities 30 days Tue 4/1/14 Wed 4/30/14 Thu 8/22/13 Thu 10/10/13 Future Task 28 1.2.15 Review by Engineer of Shop Dwg for Water Utilities 24 days Mon 4/7/14 Wed 4/30/14 Fri 10/11/13 Thu 10/24/13 Future Task 29 1.2.16 Prepare response & resubmit Shop Dwg of Water Utilities 17 days Mon 4/14/14 Wed 4/30/14 Fri 10/25/13 Thu 10/31/13 Future Task 30 1.2.17 Approve Shop Drawing Water Utilities 10 days Mon 4/21/14 Wed 4/30/14 Thu 10/31/13 Thu 10/31/13 Future Task 31 1.2.18 Prepare and Submit Shop Drawing for Electrical Utilities 50 days Wed 3/12/14 Wed 4/30/14 Thu 8/22/13 Thu 10/10/13 Future Task 32 1.2.19 Review by Engineer of Shop Dwg for Electrical Utilities 45 days Mon 3/17/14 Wed 4/30/14 Fri 10/11/13 Thu 10/24/13 Future Task 33 1.2.20 Prepare response & resubmit Shop Dwg of Electrical Utilities 38 days Mon 3/24/14 Wed 4/30/14 Fri 10/25/13 Thu 10/31/13 Future Task 34 1.2.21 Approve Shop Drawings Electrical Utilities 30 days Tue 4/1/14 Wed 4/30/14 Thu 10/31/13 Thu 10/31/13 Future Task 35 1.2.22 Prepare and Submit Shop Drawing for Bridges 66 days Mon 2/24/14 Wed 4/30/14 Thu 8/22/13 Thu 10/10/13 Future Task 36 1.2.23 Review by Engineer of Shop Dwg for Bridges 59 days Mon 3/3/14 Wed 4/30/14 Fri 10/11/13 Thu 10/24/13 Future Task 37 1.2.24 Prepare response & resubmit Shop Dwg of Bridges 57 days Wed 3/5/14 Wed 4/30/14 Fri 10/25/13 Thu 10/31/13 Future Task 38 1.2.25 Approve Shop Drawings Bridges 45 days Mon 3/17/14 Wed 4/30/14 Fri 11/8/13 Fri 11/8/13 Future Task 39 1.2.26 Submit Concrete Mix Design 30 days Fri 11/1/13 Sat 11/30/13 Fri 11/1/13 Sat 11/30/13 Complete 40 1.2.27 Review by Engineer of Concrete Mix Design 14 days Sun 12/1/13 Sat 12/14/13 Sun 12/1/13 Sat 12/14/13 Complete 41 1.2.28 Prepare response & resubmit Concrete Mix Design 7 days Sun 12/15/13 Sat 12/21/13 Sun 12/15/13 Sat 12/21/13 Complete 42 1.2.29 Approve Concrete Mix Design 1 day Sun 12/22/13 Sun 12/22/13 Sun 12/22/13 Sun 12/22/13 Complete 43 1.2.30 Prepare and Submit Shop Drawing for Engineers Quarters, Laboratory and Field 15 days Mon 7/1/13 Mon 7/15/13 Mon 7/1/13 Mon 7/15/13 Complete 44 1.2.31 Review by Engineer of Shop Dwg for Engineers Quarters, Laboratory and Field 14 days Tue 7/16/13 Mon 7/29/13 Tue 7/16/13 Mon 7/29/13 Complete 45 1.2.32 Prepare response and resubmit Shop Dwg for Engineers Quarters, Laboratory and Field Office 7 days Tue 7/30/13 Mon 8/5/13 Tue 7/30/13 Mon 8/5/13 Complete 46 1.2.33 Approve Shop Drawings Engineers Quarters, Laboratory and Field Office 1 day Mon 8/5/13 Mon 8/5/13 Mon 8/5/13 Mon 8/5/13 Complete 47 1.2.34 Submit Soil Quality Test/Stabilization Mix Design 67 days Thu 8/1/13 Sun 10/6/13 Thu 8/1/13 Sun 10/6/13 Complete 48 1.2.35 Review by Engineer of Soil Quality Test/Stabilization Mix Design 14 days Mon 10/7/13 Sun 10/20/13 Mon 10/7/13 Sun 10/20/13 Complete 49 1.2.36 Prepare response & resubmit Soil Quality Test/Stabilization Mix Design 7 days Mon 10/21/13 Sun 10/27/13 Mon 10/21/13 Sun 10/27/13 Complete 50 1.2.37 Approve Soil Quality Test/Stabilization Mix Design 1 day Sun 10/27/13 Sun 10/27/13 Sun 10/27/13 Sun 10/27/13 Complete 51 1.2.38 Prepare and Submit Shop Drawing for Miscellaneous Structures 230 days Thu 8/22/13 Tue 4/8/14 Thu 8/22/13 Tue 4/8/14 On Schedule 52 1.2.39 Review by Engineer of Shop Dwg for miscellaneous Structures 14 days Wed 4/9/14 Tue 4/22/14 Wed 4/9/14 Tue 4/22/14 Future Task 53 1.2.40 Prepare response & resubmit Shop Dwg for Miscellaneous Structures 7 days Thu 4/24/14 Wed 4/30/14 Thu 4/24/14 Wed 4/30/14 Future Task 54 1.2.41 Approve Shop Drawing Miscellaneous Structures 0 days Thu 5/1/14 Thu 5/1/14 Thu 5/1/14 Thu 5/1/14 Future Task 55 1.3 FACILITIES FOR THE ENGINEERS 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 Late 56 1.3.1 Provide Temp. Field off, Laboratory and Living Quarters for the Engineer (Rental 92 days Mon 7/1/13 Mon 9/30/13 Mon 7/1/13 Mon 9/30/13 Complete 57 1.3.2 Construction of combined Field Office & Laboratory Building and Quarter Building for the Engineer 56 days Tue 8/6/13 Mon 9/30/13 Tue 8/6/13 Mon 9/30/13 Complete 58 1.3.3 Operate/maintain field Office, Laboratory & quarters for the Engineer 871 days Mon 7/1/13 Tue 12/29/15 Tue 10/1/13 Wed 3/30/16 On Schedule 59 1.3.4 Provide Equipment, Furnitures, Fixtures and Appliances for Field office, Laboratory and Quarters for the Engineer 46 days Mon 7/1/13 Thu 8/15/13 Mon 7/1/13 Thu 8/15/13 Complete 60 1.3.5 Provide Laboratory Testing Equipment and Apparatus for the Engineer on Rental Basis 30 days Mon 7/1/13 Tue 7/30/13 Mon 7/1/13 Tue 7/30/13 Complete 61 1.3.6 Provide , Operate and Maintain Communication Equipment/Office Supplies/Consummables for the Engineer 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule 62 1.3.7 Provide Service Vehicle to the Engineer 46 days Mon 7/1/13 Thu 8/15/13 Mon 7/1/13 Thu 8/15/13 Complete 63 1.3.8 Provide and Maintain 4w D Pickup Service Vehicle for the Engineer 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule 64 1.3.9 Provide and maintain Survey Instrument/Equipment for Assist. to the Engineer 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule 65 1.3.10 Provision of Survey Personnel 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule 66 1.3.11 Progress Photographs 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule 67 1.3.12 End of Facilities to the Engineers 0 days Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Future Task 68 1.4 OTHER GENERAL REQUIREMENTS 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule 69 1.4.1 Construction Program 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule 70 1.4.1.1 Prepare and Submit Construction Program 31 days Mon 7/1/13 Wed 7/31/13 Mon 7/1/13 Wed 7/31/13 Complete 71 1.4.1.2 Review by Engineer of Construction Program 14 days Thu 8/1/13 Wed 8/14/13 Thu 8/1/13 Wed 8/14/13 Complete 72 1.4.1.3 Prepare response & resubmit Const. Program 7 days Thu 8/15/13 Wed 8/21/13 Thu 8/15/13 Wed 8/21/13 Complete 73 1.4.1.4 Update/Report on Construction Program 953 days Thu 8/22/13 Thu 3/31/16 Thu 8/22/13 Thu 3/31/16 On Schedule 74 1.4.2 Quality Assurance Management System Manual 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule 75 1.4.2.1 Prepare and Submit Quality Assurance Management System Manual 30 days Mon 7/1/13 Tue 7/30/13 Mon 7/1/13 Tue 7/30/13 Complete 76 1.4.2.2 Review by Engineer of QAMSM 14 days Thu 8/1/13 Wed 8/14/13 Thu 8/1/13 Wed 8/14/13 Complete 77 1.4.2.3 Prepare response & resubmit QAMSM 7 days Thu 8/15/13 Wed 8/21/13 Thu 8/15/13 Wed 8/21/13 Complete 78 1.4.2.4 Update/Report on QAMSM 953 days Thu 8/22/13 Thu 3/31/16 Thu 8/22/13 Thu 3/31/16 On Schedule 79 1.4.3 Environmental and Social Safeguards 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule 80 1.4.3.1 Prepare and Submit Environmental and Social Management Plan (ESMP) 30 days Mon 7/1/13 Tue 7/30/13 Mon 7/1/13 Tue 7/30/13 Complete 81 1.4.3.2 Review by Engineer of ESMP 14 days Thu 8/1/13 Wed 8/14/13 Thu 8/1/13 Wed 8/14/13 Complete 82 1.4.3.3 Prepare response & resubmit ESMP 7 days Thu 8/15/13 Wed 8/21/13 Thu 8/15/13 Wed 8/21/13 Complete 83 1.4.3.4 Update/Report on ESMP 953 days Thu 8/22/13 Thu 3/31/16 Thu 8/22/13 Thu 3/31/16 On Schedule 84 1.4.4 Traffic Control 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule 85 1.4.4.1 Prepare and Submit Traffic Management Plan (TMP) 30 days Mon 7/1/13 Tue 7/30/13 Mon 7/1/13 Tue 7/30/13 Complete 86 1.4.4.2 Review by Engineer of TMP 14 days Thu 8/1/13 Wed 8/14/13 Thu 8/1/13 Wed 8/14/13 Complete 87 1.4.4.3 Prepare response & resubmit TMP 7 days Thu 8/15/13 Wed 8/21/13 Thu 8/15/13 Wed 8/21/13 Complete 88 1.4.4.4 Update/Implement TMP 953 days Thu 8/22/13 Thu 3/31/16 Thu 8/22/13 Thu 3/31/16 On Schedule 89 1.4.5 Project Implementation 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule 90 1.4.5.1 Prepare and Submit Project Implementation Plan (PMP) 30 days Mon 7/1/13 Tue 7/30/13 Mon 7/1/13 Tue 7/30/13 Complete 91 1.4.5.2 Review by Engineer of PMP 14 days Thu 8/1/13 Wed 8/14/13 Thu 8/1/13 Wed 8/14/13 Complete 92 1.4.5.3 Prepare response & resubmit PMP 7 days Thu 8/15/13 Wed 8/21/13 Thu 8/15/13 Wed 8/21/13 Complete 93 1.4.5.4 Update/implement PMP 953 days Thu 8/22/13 Thu 3/31/16 Thu 8/22/13 Thu 3/31/16 On Schedule 94 1.4.6 Construction Health and Safety incl. Materials and First Aid Facilities 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule 7/1 3/31 3/31 3/31 3/31 3/31 9/30 3/31 3/31 3/31 50% 100% 100% 0% 0% 50% 67% 61% 46% 0% 58% 57% 50% 43% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 71% 0% 0% 5/1 100% 100% 20% 100% 100% 21% 100% 21% 21% 21% 21% 3/31 100% 100% 100% 17% 21% 100% 100% 100% 17% 21% 100% 100% 100% 17% 21% 100% 100% 100% 17% 21% 100% 100% 100% 17% 21% Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May 2014 2015 2016 Critical Critical Split Critical Progress Task Split Task Progress Manual Task Start-only Finish-only Duration-only Baseline Baseline Split Baseline Milestone Milestone Summary Progress Summary Manual Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Deadline Baseline 1 SNRDP-CP2 Qingjian Group Co., Ltd. Baseline Schedule

Transcript of cp2 - Baseline Schedule

Page 1: cp2 - Baseline Schedule

ID Task Name Est. Duration Est. Start - Base

1

Est. Finish -

Base 1

Baseline Start Baseline Finish Status

1 1 CONTRACT PACKAGE CP2 CONSTRUCTION SCHEDULE 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule

2 1.1 PROJECT MILESTONE 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 Late

3 1.1.1 COMMENCEMENT DATE 0 days Mon 7/1/13 Mon 7/1/13 Mon 7/1/13 Mon 7/1/13 Complete

4 1.1.2 COMPLETION DATE 0 days Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Future Task

5 1.1.3 COMPLETE CONSTRUCTION OF FACILITIES 0 days Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Future Task

6 1.1.4 COMPLETE EARTHWORKS 0 days Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Future Task

7 1.1.5 COMPLETE SUBBASE AND BASE COURSE 0 days Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Future Task

8 1.1.6 COMPLETE SURFACE COURSE 0 days Thu 3/31/16 Thu 3/31/16 Sun 1/31/16 Sun 1/31/16 Future Task

9 1.1.7 COMPLETE BRIDGE CONSTRUCTION 0 days Wed 9/30/15 Wed 9/30/15 Wed 9/30/15 Wed 9/30/15 Future Task

10 1.1.8 COMPLETE DRAINAGE AND SLOPE PROTECTION STRUCTURES 0 days Thu 3/31/16 Thu 3/31/16 Sat 10/24/15 Sat 10/24/15 Future Task

11 1.1.9 MISCELLANEOUS STRUCTURES 0 days Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Future Task

12 1.1.10 COMPLETE RELOCATION OF ELECTRICAL DISTRIBUTION SYSTEM 0 days Thu 3/31/16 Thu 3/31/16 Sat 1/30/16 Sat 1/30/16 Future Task

13 1.2 PRELIMINARY WORK/PREPARE/SUBMIT/APPROVE/ SHOP DRAWINGS/DESIGN MIX305 days Mon 7/1/13 Thu 5/1/14 Mon 7/1/13 Thu 5/1/14 On Schedule

14 1.2.1 As Stake Survey 153 days Mon 7/1/13 Sat 11/30/13 Mon 7/1/13 Sat 8/31/13 Complete

15 1.2.2 Survey for Drainage and Slope Protection Structures 47 days Mon 12/16/13 Fri 1/31/14 Thu 8/15/13 Mon 9/30/13 Complete

16 1.2.3 Survey for Water Utilities 52 days Mon 3/10/14 Wed 4/30/14 Thu 8/15/13 Mon 9/30/13 Future Task

17 1.2.4 Survey for Electrical Utilities 36 days Mon 3/17/14 Mon 4/21/14 Thu 8/15/13 Mon 9/30/13 Future Task

18 1.2.5 Topographic Survey for Bridges 34 days Wed 1/15/14 Mon 2/17/14 Thu 8/15/13 Mon 9/30/13 On Schedule

19 1.2.6 Prepare and Submit Shop Drawing of Road Cross Section and Profile 267 days Wed 8/7/13 Wed 4/30/14 Mon 7/8/13 Thu 10/10/13 On Schedule

20 1.2.7 Review by Engineer of Shop Dwg of Road Cross Section and Profile 228 days Sun 9/15/13 Wed 4/30/14 Fri 10/11/13 Thu 10/24/13 On Schedule

21 1.2.8 Prepare response & resubmit Shop Dwg of Road Cross Section and Profile 164 days Mon 11/18/13 Wed 4/30/14 Fri 10/25/13 Thu 10/31/13 On Schedule

22 1.2.9 Approve Shop Drawing Roads 66 days Mon 2/24/14 Wed 4/30/14 Thu 10/31/13 Thu 10/31/13 Future Task

23 1.2.10 Prepare and Submit Shop Drawing for Drainage and Slope Protection Structures212 days Tue 10/1/13 Wed 4/30/14 Thu 8/22/13 Thu 10/10/13 On Schedule

24 1.2.11 Review by Engineer of Shop Dwg of Drainage and Slope Protection Structures 206 days Mon 10/7/13 Wed 4/30/14 Fri 10/11/13 Thu 10/24/13 On Schedule

25 1.2.12 Prepare response & resubmit Shop Dwg of Drainage and Slope Protection Structures178 days Mon 11/4/13 Wed 4/30/14 Fri 10/25/13 Thu 10/31/13 On Schedule

26 1.2.13 Approve Shop Drawing Drainage/Slope Protection 155 days Wed 11/27/13 Wed 4/30/14 Fri 11/1/13 Fri 11/1/13 On Schedule

27 1.2.14 Prepare and Submit Shop Drawing for Water Utilities 30 days Tue 4/1/14 Wed 4/30/14 Thu 8/22/13 Thu 10/10/13 Future Task

28 1.2.15 Review by Engineer of Shop Dwg for Water Utilities 24 days Mon 4/7/14 Wed 4/30/14 Fri 10/11/13 Thu 10/24/13 Future Task

29 1.2.16 Prepare response & resubmit Shop Dwg of Water Utilities 17 days Mon 4/14/14 Wed 4/30/14 Fri 10/25/13 Thu 10/31/13 Future Task

30 1.2.17 Approve Shop Drawing Water Utilities 10 days Mon 4/21/14 Wed 4/30/14 Thu 10/31/13 Thu 10/31/13 Future Task

31 1.2.18 Prepare and Submit Shop Drawing for Electrical Utilities 50 days Wed 3/12/14 Wed 4/30/14 Thu 8/22/13 Thu 10/10/13 Future Task

32 1.2.19 Review by Engineer of Shop Dwg for Electrical Utilities 45 days Mon 3/17/14 Wed 4/30/14 Fri 10/11/13 Thu 10/24/13 Future Task

33 1.2.20 Prepare response & resubmit Shop Dwg of Electrical Utilities 38 days Mon 3/24/14 Wed 4/30/14 Fri 10/25/13 Thu 10/31/13 Future Task

34 1.2.21 Approve Shop Drawings Electrical Utilities 30 days Tue 4/1/14 Wed 4/30/14 Thu 10/31/13 Thu 10/31/13 Future Task

35 1.2.22 Prepare and Submit Shop Drawing for Bridges 66 days Mon 2/24/14 Wed 4/30/14 Thu 8/22/13 Thu 10/10/13 Future Task

36 1.2.23 Review by Engineer of Shop Dwg for Bridges 59 days Mon 3/3/14 Wed 4/30/14 Fri 10/11/13 Thu 10/24/13 Future Task

37 1.2.24 Prepare response & resubmit Shop Dwg of Bridges 57 days Wed 3/5/14 Wed 4/30/14 Fri 10/25/13 Thu 10/31/13 Future Task

38 1.2.25 Approve Shop Drawings Bridges 45 days Mon 3/17/14 Wed 4/30/14 Fri 11/8/13 Fri 11/8/13 Future Task

39 1.2.26 Submit Concrete Mix Design 30 days Fri 11/1/13 Sat 11/30/13 Fri 11/1/13 Sat 11/30/13 Complete

40 1.2.27 Review by Engineer of Concrete Mix Design 14 days Sun 12/1/13 Sat 12/14/13 Sun 12/1/13 Sat 12/14/13 Complete

41 1.2.28 Prepare response & resubmit Concrete Mix Design 7 days Sun 12/15/13 Sat 12/21/13 Sun 12/15/13 Sat 12/21/13 Complete

42 1.2.29 Approve Concrete Mix Design 1 day Sun 12/22/13 Sun 12/22/13 Sun 12/22/13 Sun 12/22/13 Complete

43 1.2.30 Prepare and Submit Shop Drawing for Engineers Quarters, Laboratory and Field Office15 days Mon 7/1/13 Mon 7/15/13 Mon 7/1/13 Mon 7/15/13 Complete

44 1.2.31 Review by Engineer of Shop Dwg for Engineers Quarters, Laboratory and Field Office14 days Tue 7/16/13 Mon 7/29/13 Tue 7/16/13 Mon 7/29/13 Complete

45 1.2.32 Prepare response and resubmit Shop Dwg for Engineers Quarters, Laboratory

and Field Office

7 days Tue 7/30/13 Mon 8/5/13 Tue 7/30/13 Mon 8/5/13 Complete

46 1.2.33 Approve Shop Drawings Engineers Quarters, Laboratory and Field Office 1 day Mon 8/5/13 Mon 8/5/13 Mon 8/5/13 Mon 8/5/13 Complete

47 1.2.34 Submit Soil Quality Test/Stabilization Mix Design 67 days Thu 8/1/13 Sun 10/6/13 Thu 8/1/13 Sun 10/6/13 Complete

48 1.2.35 Review by Engineer of Soil Quality Test/Stabilization Mix Design 14 days Mon 10/7/13 Sun 10/20/13 Mon 10/7/13 Sun 10/20/13 Complete

49 1.2.36 Prepare response & resubmit Soil Quality Test/Stabilization Mix Design 7 days Mon 10/21/13 Sun 10/27/13 Mon 10/21/13 Sun 10/27/13 Complete

50 1.2.37 Approve Soil Quality Test/Stabilization Mix Design 1 day Sun 10/27/13 Sun 10/27/13 Sun 10/27/13 Sun 10/27/13 Complete

51 1.2.38 Prepare and Submit Shop Drawing for Miscellaneous Structures 230 days Thu 8/22/13 Tue 4/8/14 Thu 8/22/13 Tue 4/8/14 On Schedule

52 1.2.39 Review by Engineer of Shop Dwg for miscellaneous Structures 14 days Wed 4/9/14 Tue 4/22/14 Wed 4/9/14 Tue 4/22/14 Future Task

53 1.2.40 Prepare response & resubmit Shop Dwg for Miscellaneous Structures 7 days Thu 4/24/14 Wed 4/30/14 Thu 4/24/14 Wed 4/30/14 Future Task

54 1.2.41 Approve Shop Drawing Miscellaneous Structures 0 days Thu 5/1/14 Thu 5/1/14 Thu 5/1/14 Thu 5/1/14 Future Task

55 1.3 FACILITIES FOR THE ENGINEERS 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 Late

56 1.3.1 Provide Temp. Field off, Laboratory and Living Quarters for the Engineer (Rental)92 days Mon 7/1/13 Mon 9/30/13 Mon 7/1/13 Mon 9/30/13 Complete

57 1.3.2 Construction of combined Field Office & Laboratory Building and Quarter

Building for the Engineer

56 days Tue 8/6/13 Mon 9/30/13 Tue 8/6/13 Mon 9/30/13 Complete

58 1.3.3 Operate/maintain field Office, Laboratory & quarters for the Engineer 871 days Mon 7/1/13 Tue 12/29/15 Tue 10/1/13 Wed 3/30/16 On Schedule

59 1.3.4 Provide Equipment, Furnitures, Fixtures and Appliances for Field office,

Laboratory and Quarters for the Engineer

46 days Mon 7/1/13 Thu 8/15/13 Mon 7/1/13 Thu 8/15/13 Complete

60 1.3.5 Provide Laboratory Testing Equipment and Apparatus for the Engineer on

Rental Basis

30 days Mon 7/1/13 Tue 7/30/13 Mon 7/1/13 Tue 7/30/13 Complete

61 1.3.6 Provide , Operate and Maintain Communication Equipment/Office

Supplies/Consummables for the Engineer

1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule

62 1.3.7 Provide Service Vehicle to the Engineer 46 days Mon 7/1/13 Thu 8/15/13 Mon 7/1/13 Thu 8/15/13 Complete

63 1.3.8 Provide and Maintain 4w D Pickup Service Vehicle for the Engineer 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule

64 1.3.9 Provide and maintain Survey Instrument/Equipment for Assist. to the Engineer 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule

65 1.3.10 Provision of Survey Personnel 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule

66 1.3.11 Progress Photographs 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule

67 1.3.12 End of Facilities to the Engineers 0 days Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Future Task

68 1.4 OTHER GENERAL REQUIREMENTS 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule

69 1.4.1 Construction Program 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule

70 1.4.1.1 Prepare and Submit Construction Program 31 days Mon 7/1/13 Wed 7/31/13 Mon 7/1/13 Wed 7/31/13 Complete

71 1.4.1.2 Review by Engineer of Construction Program 14 days Thu 8/1/13 Wed 8/14/13 Thu 8/1/13 Wed 8/14/13 Complete

72 1.4.1.3 Prepare response & resubmit Const. Program 7 days Thu 8/15/13 Wed 8/21/13 Thu 8/15/13 Wed 8/21/13 Complete

73 1.4.1.4 Update/Report on Construction Program 953 days Thu 8/22/13 Thu 3/31/16 Thu 8/22/13 Thu 3/31/16 On Schedule

74 1.4.2 Quality Assurance Management System Manual 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule

75 1.4.2.1 Prepare and Submit Quality Assurance Management System Manual 30 days Mon 7/1/13 Tue 7/30/13 Mon 7/1/13 Tue 7/30/13 Complete

76 1.4.2.2 Review by Engineer of QAMSM 14 days Thu 8/1/13 Wed 8/14/13 Thu 8/1/13 Wed 8/14/13 Complete

77 1.4.2.3 Prepare response & resubmit QAMSM 7 days Thu 8/15/13 Wed 8/21/13 Thu 8/15/13 Wed 8/21/13 Complete

78 1.4.2.4 Update/Report on QAMSM 953 days Thu 8/22/13 Thu 3/31/16 Thu 8/22/13 Thu 3/31/16 On Schedule

79 1.4.3 Environmental and Social Safeguards 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule

80 1.4.3.1 Prepare and Submit Environmental and Social Management Plan (ESMP) 30 days Mon 7/1/13 Tue 7/30/13 Mon 7/1/13 Tue 7/30/13 Complete

81 1.4.3.2 Review by Engineer of ESMP 14 days Thu 8/1/13 Wed 8/14/13 Thu 8/1/13 Wed 8/14/13 Complete

82 1.4.3.3 Prepare response & resubmit ESMP 7 days Thu 8/15/13 Wed 8/21/13 Thu 8/15/13 Wed 8/21/13 Complete

83 1.4.3.4 Update/Report on ESMP 953 days Thu 8/22/13 Thu 3/31/16 Thu 8/22/13 Thu 3/31/16 On Schedule

84 1.4.4 Traffic Control 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule

85 1.4.4.1 Prepare and Submit Traffic Management Plan (TMP) 30 days Mon 7/1/13 Tue 7/30/13 Mon 7/1/13 Tue 7/30/13 Complete

86 1.4.4.2 Review by Engineer of TMP 14 days Thu 8/1/13 Wed 8/14/13 Thu 8/1/13 Wed 8/14/13 Complete

87 1.4.4.3 Prepare response & resubmit TMP 7 days Thu 8/15/13 Wed 8/21/13 Thu 8/15/13 Wed 8/21/13 Complete

88 1.4.4.4 Update/Implement TMP 953 days Thu 8/22/13 Thu 3/31/16 Thu 8/22/13 Thu 3/31/16 On Schedule

89 1.4.5 Project Implementation 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule

90 1.4.5.1 Prepare and Submit Project Implementation Plan (PMP) 30 days Mon 7/1/13 Tue 7/30/13 Mon 7/1/13 Tue 7/30/13 Complete

91 1.4.5.2 Review by Engineer of PMP 14 days Thu 8/1/13 Wed 8/14/13 Thu 8/1/13 Wed 8/14/13 Complete

92 1.4.5.3 Prepare response & resubmit PMP 7 days Thu 8/15/13 Wed 8/21/13 Thu 8/15/13 Wed 8/21/13 Complete

93 1.4.5.4 Update/implement PMP 953 days Thu 8/22/13 Thu 3/31/16 Thu 8/22/13 Thu 3/31/16 On Schedule

94 1.4.6 Construction Health and Safety incl. Materials and First Aid Facilities 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule

7/1

3/31

3/31

3/31

3/31

3/31

9/30

3/31

3/31

3/31

50%

100%

100%

0%

0%

50%

67%

61%

46%

0%

58%

57%

50%

43%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

71%

0%

0%

5/1

100%

100%

20%

100%

100%

21%

100%

21%

21%

21%

21%

3/31

100%

100%

100%

17%

21%

100%

100%

100%

17%

21%

100%

100%

100%

17%

21%

100%

100%

100%

17%

21%

100%

100%

100%

17%

21%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

2014 2015 2016

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Manual Task

Start-only

Finish-only

Duration-only

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Manual Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Deadline

Baseline 1

SNRDP-CP2 Qingjian Group Co., Ltd. Baseline Schedule

Page 2: cp2 - Baseline Schedule

ID Task Name Est. Duration Est. Start - Base

1

Est. Finish -

Base 1

Baseline Start Baseline Finish Status

95 1.4.6.1 Prepare and Submit Health and Safety Plan (HSP) 30 days Mon 7/1/13 Tue 7/30/13 Mon 7/1/13 Tue 7/30/13 Complete

96 1.4.6.2 Review by Engineer of HSP 14 days Thu 8/1/13 Wed 8/14/13 Thu 8/1/13 Wed 8/14/13 Complete

97 1.4.6.3 Prepare response & resubmit HSP 7 days Thu 8/15/13 Wed 8/21/13 Thu 8/15/13 Wed 8/21/13 Complete

98 1.4.6.4 Update/Report/ Implement HSP 953 days Thu 8/22/13 Thu 3/31/16 Thu 8/22/13 Thu 3/31/16 On Schedule

99 1.4.7 Project Billboard/Signs 31 days Mon 7/1/13 Wed 7/31/13 Mon 7/1/13 Wed 7/31/13 Complete

100 1.4.7.1 Prepare and Submit Shop Drawing of Billboard/Signs 15 days Mon 7/1/13 Mon 7/15/13 Mon 7/1/13 Mon 7/15/13 Complete

101 1.4.7.2 Review by Engineer of Shop Drawing 14 days Mon 7/15/13 Sun 7/28/13 Mon 7/15/13 Sun 7/28/13 Complete

102 1.4.7.3 Prepare response & resubmit Shop Drawing 3 days Mon 7/29/13 Wed 7/31/13 Mon 7/29/13 Wed 7/31/13 Complete

103 1.4.7.4 Install Billboard/Signs 3 days Mon 7/29/13 Wed 7/31/13 Mon 7/29/13 Wed 7/31/13 Complete

104 1.4.8 Complete Other General Requirements 0 days Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Thu 3/31/16 Future Task

105 1.5 EARTHWORKS 730 days Tue 10/1/13 Wed 9/30/15 Thu 10/31/13 Thu 3/31/16 On Schedule

106 1.5.1 SECTION 3: STA 888+500 - STA 873+500 (15.00km) 396 days Tue 10/1/13 Fri 10/31/14 Tue 10/1/13 Fri 10/31/14 On Schedule

107 1.5.1.1 Clearing and Grubbing/Removal of Trees 151 days Sun 10/6/13 Thu 3/20/14 Tue 10/1/13 Fri 2/28/14 On Schedule

108 1.5.1.2 Excavation(Incl. pipe culvert/drain excav.)/Embankment 275 days Sat 11/2/13 Wed 10/1/14 Mon 11/4/13 Mon 7/21/14 On Schedule

109 1.5.1.3 Removal of structures and obstructions 149 days Sun 2/16/14 Tue 9/30/14 Wed 11/4/15 Tue 9/30/14 Future Task

110 1.5.1.4 Removal of AC/PCCP/RCPC/RCBC 181 days Tue 1/7/14 Fri 7/25/14 Sat 10/3/15 Fri 7/25/14 On Schedule

111 1.5.1.5 Subgrade Preparation 246 days Tue 12/17/13 Tue 8/19/14 Tue 12/17/13 Tue 8/19/14 On Schedule

112 1.5.1.6 Complete Earthworks Sta 888+500- Sta 873+500 0 days Wed 9/30/15 Wed 9/30/15 Thu 3/31/16 Thu 3/31/16 Future Task

113 1.5.2 SECTION 2: STA 873+500 - STA 858+500 (15.000km) 372 days Mon 11/25/13 Tue 12/2/14 Sat 3/1/14 Tue 12/2/14 On Schedule

114 1.5.2.1 Clearing and Grubbing/Removal of Trees 121 days Mon 11/25/13 Tue 3/25/14 Sat 3/1/14 Sun 6/29/14 On Schedule

115 1.5.2.2 Excavation(Incl. pipe culvert/drain excav.)/Embankment 74 days Sun 3/2/14 Wed 5/14/14 Tue 3/4/14 Tue 11/18/14 Future Task

116 1.5.2.3 Removal of structures and obstructions 116 days Fri 2/21/14 Mon 6/16/14 Tue 3/4/14 Wed 7/30/14 Future Task

117 1.5.2.4 Removal of AC/PCCP/RCPC/RCBC 162 days Fri 2/21/14 Fri 8/1/14 Sat 3/8/14 Thu 9/4/14 Future Task

118 1.5.2.5 Subgrade Preparation 246 days Mon 3/31/14 Mon 12/1/14 Mon 3/31/14 Mon 12/1/14 Future Task

119 1.5.2.6 Complete Earthworks Sta 873+500- Sta 858+500 0 days Tue 12/2/14 Tue 12/2/14 Tue 12/2/14 Tue 12/2/14 Future Task

120 1.5.3 SECTION 1: STA 858+500 - STA 843+500 (15.000km) 381 days Mon 2/17/14 Thu 3/5/15 Mon 6/2/14 Thu 3/5/15 Future Task

121 1.5.3.1 Clearing and Grubbing/Removal of Trees 161 days Mon 2/17/14 Sun 7/27/14 Mon 6/2/14 Tue 9/30/14 Future Task

122 1.5.3.2 Excavation(Incl. pipe culvert/drain excav.)/Embankment 164 days Mon 2/24/14 Wed 8/6/14 Thu 6/5/14 Thu 2/19/15 Future Task

123 1.5.3.3 Removal of structures and obstructions 145 days Fri 2/21/14 Fri 7/18/14 Thu 6/5/14 Fri 10/31/14 Future Task

124 1.5.3.4 Removal of AC/PCCP/RCPC/RCBC 181 days Mon 4/14/14 Sat 10/11/14 Mon 6/9/14 Sat 12/6/14 Future Task

125 1.5.3.5 Subgrade Preparation 246 days Wed 7/2/14 Wed 3/4/15 Wed 7/2/14 Wed 3/4/15 Future Task

126 1.5.3.6 Complete Earthworks Sta 858+500- Sta 843+500 0 days Thu 3/5/15 Thu 3/5/15 Thu 3/5/15 Thu 3/5/15 Future Task

127 1.5.4 SECTION 4: STA 888+500 - STA 907+281.82 (18.78km) 452 days Mon 4/21/14 Thu 7/16/15 Wed 10/1/14 Thu 3/31/16 Future Task

128 1.5.4.1 Clearing and Grubbing/Removal of Trees 105 days Mon 4/21/14 Tue 9/9/14 Wed 10/1/14 Sat 2/28/15 Future Task

129 1.5.4.2 Excavation(Incl. pipe culvert/drain excav.)/Embankment 346 days Sun 6/8/14 Tue 5/19/15 Sat 10/4/14 Mon 9/14/15 Future Task

130 1.5.4.3 Removal of structures and obstructions 186 days Sun 6/15/14Wed 12/17/14 Sat 10/4/14 Tue 4/7/15 Future Task

131 1.5.4.4 Removal of AC/PCCP/RCPC/RCBC 226 days Sun 6/22/14 Mon 2/2/15 Wed 10/8/14 Thu 5/21/15 Future Task

132 1.5.4.5 Subgrade Preparation 334 days Sun 8/17/14 Thu 7/16/15 Sun 5/3/15 Thu 3/31/16 Future Task

133 1.5.4.6 Complete Earthworks Sta 888+500- Sta 907+281.82 0 days Thu 7/16/15 Thu 7/16/15 Thu 3/31/16 Thu 3/31/16 Future Task

134 1.6 SUBBASE/BASE COURSE/SURFACE COURSE 761 days Wed 1/1/14 Sun 1/31/16 Wed 1/1/14 Sun 1/31/16 On Schedule

135 1.6.1 SECTION 3: STA 888+500 - STA 873+500 (15.00km) 259 days Wed 1/1/14 Tue 9/16/14 Wed 1/1/14 Tue 9/16/14 On Schedule

136 1.6.1.1 subbase and base course 240 days Mon 2/24/14 Fri 8/29/14 Wed 1/1/14 Thu 8/28/14 On Schedule

137 1.6.1.2 Placing of PCC Pavement 13 days Fri 2/21/14 Wed 3/5/14 Sun 1/5/14 Sat 9/6/14 Future Task

138 1.6.1.3 Materials Test 198 days Fri 2/21/14 Sat 9/6/14 Sun 1/5/14 Sat 9/6/14 Future Task

139 1.6.1.4 Complete Surface Course Sta 888+500 -Sta 873+500 0 days Sat 9/6/14 Sat 9/6/14 Sat 9/6/14 Sat 9/6/14 Future Task

140 1.6.2 SECTION 2: STA 873+500 - STA 858+500 (15.000km) 393 days Sun 4/6/14 Sun 5/3/15 Sun 8/17/14 Sun 5/3/15 Future Task

141 1.6.2.1 subbase and base course 240 days Sun 4/6/14 Mon 12/1/14 Sun 8/17/14 Mon 4/13/15 Future Task

142 1.6.2.2 Placing of PCC Pavement 246 days Sun 5/4/14 Sun 1/4/15 Sun 8/24/14 Sun 4/26/15 Future Task

143 1.6.2.3 Materials Test 245 days Sun 5/11/14 Sat 1/10/15 Mon 8/25/14 Sun 4/26/15 Future Task

144 1.6.2.4 Complete Surface Course Sta 873+500 -Sta 858+500 0 days Sun 5/3/15 Sun 5/3/15 Sun 5/3/15 Sun 5/3/15 Future Task

145 1.6.3 SECTION 1: STA 858+500 - STA 843+500 (15.000km) 355 days Sun 7/6/14 Thu 6/25/15 Thu 10/16/14 Thu 6/25/15 Future Task

146 1.6.3.1 subbase and base course 240 days Sun 7/6/14 Mon 3/2/15 Thu 10/16/14 Fri 6/12/15 Future Task

147 1.6.3.2 Placing of PCC Pavement 245 days Sun 8/3/14 Sat 4/4/15 Fri 10/24/14 Thu 6/25/15 Future Task

148 1.6.3.3 Materials Test 245 days Sun 8/3/14 Sat 4/4/15 Fri 10/24/14 Thu 6/25/15 Future Task

149 1.6.3.4 Complete Surface Course Sta 858+500 -Sta 843+500 0 days Thu 6/25/15 Thu 6/25/15 Thu 6/25/15 Thu 6/25/15 Future Task

150 1.6.4 SECTION 4: STA 888+500 - STA 907+281.82 (18.78km) 428 days Sun 11/30/14 Sun 1/31/16 Fri 4/24/15 Sun 1/31/16 Future Task

151 1.6.4.1 subbase and base course 251 days Sun 11/30/14 Fri 8/7/15 Fri 4/24/15 Wed 12/30/15 Future Task

152 1.6.4.2 Placing of PCC Pavement 278 days Sun 1/25/15 Thu 10/29/15 Tue 4/28/15 Sat 1/30/16 Future Task

153 1.6.4.3 Materials Test 275 days Sun 1/25/15Mon 10/26/15 Fri 5/1/15 Sat 1/30/16 Future Task

154 1.6.4.4 Complete Surface Course Sta 888+500 -Sta 907+281.82 0 days Sun 1/31/16 Sun 1/31/16 Sun 1/31/16 Sun 1/31/16 Future Task

155 1.7 BRIDGE CONSTRUCTION 669 days Sun 12/1/13 Wed 9/30/15 Sun 12/1/13 Wed 9/30/15 On Schedule

156 1.7.1 Rehabilitation of Existing Bridges 564 days? Sun 3/16/14 Wed 9/30/15 Thu 1/2/14 Wed 9/30/15 Future Task

157 1.7.1.1 BALOTO Bridge 62 days Tue 4/29/14 Sun 6/29/14 Thu 1/2/14 Sun 3/2/14 Future Task

158 1.7.1.1.1 Seismic Retrofit 62 days Tue 4/29/14 Sun 6/29/14 Thu 1/2/14 Sun 3/2/14 Future Task

159 1.7.1.1.1.1 Slab Strengthening 15 days Sun 5/11/14 Sun 5/25/14 Sun 2/16/14 Sun 3/2/14 Future Task

160 1.7.1.1.1.2 Column Strengthening 50 days Tue 4/29/14 Tue 6/17/14 Thu 1/2/14 Sat 2/15/14 Future Task

161 1.7.1.1.1.3 Approach Slab 12 days Wed 6/18/14 Sun 6/29/14 Sun 2/16/14 Sun 2/23/14 Future Task

162 1.7.1.1.2 Non-Seismic Retrofit 30 days Sun 5/11/14 Mon 6/9/14 Thu 1/30/14 Fri 2/21/14 Future Task

163 1.7.1.1.2.1 Repair of Cracks/Concrete/Abutment Slope Protection 30 days Sun 5/11/14 Mon 6/9/14 Thu 1/30/14 Fri 2/21/14 Future Task

164 1.7.1.2 CAGBOBORAC Bridge 108 days Sat 4/19/14 Mon 8/4/14 Sun 2/16/14 Fri 5/9/14 Future Task

165 1.7.1.2.1 Seismic Retrofit 80 days Sat 4/19/14 Mon 7/7/14 Sun 2/16/14 Wed 4/23/14 Future Task

166 1.7.1.2.1.1 Slab Strengthening 23 days Sat 4/19/14 Sun 5/11/14 Tue 3/18/14 Wed 4/9/14 Future Task

167 1.7.1.2.1.2 Column Strengthening 29 days Sun 5/11/14 Sun 6/8/14 Sun 2/16/14 Mon 3/17/14 Future Task

168 1.7.1.2.1.3 Approach Slab 30 days Sun 6/8/14 Mon 7/7/14 Tue 3/25/14 Wed 4/23/14 Future Task

169 1.7.1.2.2 Non-Seismic Retrofit 30 days Sun 7/6/14 Mon 8/4/14 Thu 4/10/14 Fri 5/9/14 Future Task

170 1.7.1.2.2.1 Repair of Cracks/Concrete/Abutment Slope Protection 30 days Sun 7/6/14 Mon 8/4/14 Thu 4/10/14 Fri 5/9/14 Future Task

171 1.7.1.3 MANTANG Bridge 140 days Sat 3/29/14 Fri 8/15/14 Thu 4/24/14 Thu 7/24/14 Future Task

172 1.7.1.3.1 Seismic Retrofit 140 days Sat 3/29/14 Fri 8/15/14 Thu 4/24/14 Thu 7/24/14 Future Task

173 1.7.1.3.1.1 Slab Strengthening 31 days Sun 4/20/14 Tue 5/20/14 Thu 4/24/14 Sat 5/24/14 Future Task

174 1.7.1.3.1.2 Column Strengthening 30 days Sat 3/29/14 Sun 4/27/14 Sun 5/25/14 Mon 6/23/14 Future Task

175 1.7.1.3.1.3 Approach Slab 24 days Wed 7/23/14 Fri 8/15/14 Tue 7/1/14 Thu 7/24/14 Future Task

176 1.7.1.3.2 Non-Seismic Retrofit 61 days Sun 5/25/14 Thu 7/24/14 Sun 5/25/14 Thu 7/24/14 Future Task

177 1.7.1.3.2.1 Repair of Cracks/Concrete/Abutment Slope/Pier Protection 61 days Sun 5/25/14 Thu 7/24/14 Sun 5/25/14 Thu 7/24/14 Future Task

178 1.7.1.4 POLANGI Bridge 168 days Tue 6/24/14 Sun 10/19/14 Tue 6/24/14 Sun 10/19/14 Future Task

179 1.7.1.4.1 Seismic Retrofit 77 days Tue 6/24/14 Fri 9/12/14 Tue 6/24/14 Fri 9/12/14 Future Task

180 1.7.1.4.1.1 Concrete Shear Keys at Abutment 23 days Tue 6/24/14 Wed 7/16/14 Tue 6/24/14 Wed 7/16/14 Future Task

181 1.7.1.4.1.2 Girder Strengthening 23 days Thu 7/24/14 Fri 8/15/14 Thu 7/24/14 Fri 8/15/14 Future Task

182 1.7.1.4.1.3 Approach Slab 28 days Sat 8/16/14 Fri 9/12/14 Sat 8/16/14 Fri 9/12/14 Future Task

183 1.7.1.4.2 Non-Seismic Retrofit 84 days Fri 7/25/14 Sun 10/19/14 Fri 7/25/14 Sun 10/19/14 Future Task

184 1.7.1.4.2.1 Repair of Cracks/Concrete/Expansion Joint/Painting 33 days Fri 7/25/14 Tue 8/26/14 Fri 7/25/14 Tue 8/26/14 Future Task

185 1.7.1.4.2.2 Abutment Slope Protection 31 days Sat 9/13/14Mon 10/13/14 Sat 9/13/14 Mon 10/13/14 Future Task

186 1.7.1.4.2.3 Provision of Asphalt Overlay 4 days Sat 8/30/14 Tue 9/2/14 Sat 8/30/14 Tue 9/2/14 Future Task

187 1.7.1.4.2.4 Replacement of Approach Sidewalk and Railing 20 days Tue 9/30/14 Sun 10/19/14 Tue 9/30/14 Sun 10/19/14 Future Task

188 1.7.1.5 NABUANGAN BRIDGE 306 days Thu 5/1/14 Mon 3/2/15 Thu 5/1/14 Sat 11/15/14 Future Task

189 1.7.1.5.1 Seismic Retrofit 165 days Thu 5/1/14 Sun 10/12/14 Thu 5/1/14 Sat 11/15/14 Future Task

190 1.7.1.5.1.1 Concrete Shear Keys at Abutment/Pier 60 days Mon 6/2/14 Thu 7/31/14 Sat 9/13/14 Tue 11/11/14 Future Task

191 1.7.1.5.1.2 Girder Strengthening 44 days Thu 5/1/14 Fri 6/13/14 Fri 10/3/14 Sat 11/15/14 Future Task

192 1.7.1.5.1.3 Approach Slab 30 days Sat 9/13/14 Sun 10/12/14 Sat 9/13/14 Sun 10/12/14 Future Task

100%

100%

100%

17%

100%

100%

100%

100%

100%

3/31

7%

78%

12%

0%

10%

19%

9/30

9%

56%

0%

0%

0%

0%

12/2

0%

0%

0%

0%

0%

0%

3/5

0%

0%

0%

0%

0%

0%

7/16

1%

13%

0%

0%

9/6

0%

0%

0%

0%

5/3

0%

0%

0%

0%

6/25

0%

0%

0%

0%

1/31

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

2014 2015 2016

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Manual Task

Start-only

Finish-only

Duration-only

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Manual Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Deadline

Baseline 1

SNRDP-CP2 Qingjian Group Co., Ltd. Baseline Schedule

Page 3: cp2 - Baseline Schedule

ID Task Name Est. Duration Est. Start - Base

1

Est. Finish -

Base 1

Baseline Start Baseline Finish Status

193 1.7.1.5.1.4 Installation of New Bearing Pad 29 days Thu 5/1/14 Thu 5/29/14 Tue 7/15/14 Fri 9/12/14 Future Task

194 1.7.1.5.1.5 Footing Retrofit 60 days Mon 5/5/14 Fri 7/18/14 Thu 5/1/14 Sun 6/29/14 Future Task

195 1.7.1.5.2 Non-Seismic Retrofit 262 days Sat 6/14/14 Mon 3/2/15 Sat 6/14/14 Tue 10/14/14 Future Task

196 1.7.1.5.2.1 Repair of Cracks/Concrete 20 days Fri 9/12/14 Wed 10/1/14 Sat 9/13/14 Thu 10/2/14 Future Task

197 1.7.1.5.2.2 Abutment Slope Protection 45 days Sun 6/15/14 Tue 7/29/14 Sat 6/14/14 Mon 7/28/14 Future Task

198 1.7.1.5.2.3 Provision of Asphalt Overlay 2 days Sun 3/1/15 Mon 3/2/15 Mon 10/13/14 Tue 10/14/14 Future Task

199 1.7.1.5.2.4 Backwall/Wingwall Reconstruction and Girder end Restoration 21 days Sat 6/14/14 Fri 7/4/14 Sat 6/14/14 Fri 7/4/14 Future Task

200 1.7.1.6 SULAT BRIDGE 255 days? Mon 6/30/14 Wed 3/11/15 Mon 6/30/14 Wed 3/11/15 Future Task

201 1.7.1.6.1 Seismic Retrofit 210 days? Mon 6/30/14 Sun 1/25/15 Mon 6/30/14 Sun 1/25/15 Future Task

202 1.7.1.6.1.1 Concrete Shear Keys at Abutment/Pier 60 days Thu 11/27/14 Sun 1/25/15 Thu 11/27/14 Sun 1/25/15 Future Task

203 1.7.1.6.1.2 Rod Restrainer/Column Strengthening 30 days Fri 8/29/14 Sat 9/27/14 Fri 8/29/14 Sat 9/27/14 Future Task

204 1.7.1.6.1.3 Approach Slab 30 days? Mon 10/13/14 Tue 11/11/14 Mon 10/13/14 Tue 11/11/14 Future Task

205 1.7.1.6.1.4 Installation of New Bearing Pad 45 days Mon 10/13/14Wed 11/26/14 Mon 10/13/14 Wed 11/26/14 Future Task

206 1.7.1.6.1.5 Footing Retrofit/Steel Shoe Bumper 60 days Mon 6/30/14 Thu 8/28/14 Mon 6/30/14 Thu 8/28/14 Future Task

207 1.7.1.6.2 Non-Seismic Retrofit 105 days Thu 11/27/14 Wed 3/11/15 Thu 11/27/14 Wed 3/11/15 Future Task

208 1.7.1.6.2.1 Repair of Cracks/Concrete 30 days Thu 11/27/14 Fri 12/26/14 Thu 11/27/14 Fri 12/26/14 Future Task

209 1.7.1.6.2.2 Abutment Slope Protection & Repair 45 days Mon 1/26/15 Wed 3/11/15 Mon 1/26/15 Wed 3/11/15 Future Task

210 1.7.1.6.2.3 Provision of Asphalt Overlay 2 days Mon 1/26/15 Tue 1/27/15 Mon 1/26/15 Tue 1/27/15 Future Task

211 1.7.1.6.2.4 Repair of Expansion Joint 2 days Wed 1/28/15 Thu 1/29/15 Wed 1/28/15 Thu 1/29/15 Future Task

212 1.7.1.7 TAFT BRIDGE 254 days? Fri 8/29/14 Sat 5/9/15 Fri 8/29/14 Sun 5/10/15 Future Task

213 1.7.1.7.1 Seismic Retrofit 149 days Fri 8/29/14 Sat 1/24/15 Fri 8/29/14 Fri 4/10/15 Future Task

214 1.7.1.7.1.1 Concrete Shear Keys at Abutment/Pier 45 days Fri 10/17/14 Sun 11/30/14 Wed 2/25/15 Fri 4/10/15 Future Task

215 1.7.1.7.1.2 Rod Restrainer/Column Strengthening 45 days Sat 9/27/14Mon 11/10/14 Sun 9/28/14 Tue 11/11/14 Future Task

216 1.7.1.7.1.3 Approach Slab 45 days Tue 11/11/14 Thu 12/25/14 Wed 11/12/14 Fri 12/26/14 Future Task

217 1.7.1.7.1.4 Installation of New Bearing Pad 60 days Wed 11/26/14 Sat 1/24/15 Thu 11/27/14 Sun 1/25/15 Future Task

218 1.7.1.7.1.5 Footing Retrofit/Steel Shoe Bumper 60 days Fri 8/29/14Mon 10/27/14 Fri 8/29/14 Mon 10/27/14 Future Task

219 1.7.1.7.2 Non-Seismic Retrofit 105 days? Sun 1/25/15 Sat 5/9/15 Mon 1/26/15 Sun 5/10/15 Future Task

220 1.7.1.7.2.1 Repair of Cracks/Concrete 30 days? Sun 1/25/15 Mon 2/23/15 Mon 1/26/15 Tue 2/24/15 Future Task

221 1.7.1.7.2.2 Abutment Slope Protection and repair 60 days Wed 3/11/15 Sat 5/9/15 Thu 3/12/15 Sun 5/10/15 Future Task

222 1.7.1.7.2.3 Provision of Asphalt Overlay 2 days Fri 4/10/15 Sat 4/11/15 Sat 4/11/15 Sun 4/12/15 Future Task

223 1.7.1.7.2.4 Repair of expansion joint 2 days Sun 4/12/15 Mon 4/13/15 Mon 4/13/15 Tue 4/14/15 Future Task

224 1.7.1.8 DANAO Bridge 61 days Sun 3/23/14 Thu 5/22/14 Wed 8/27/14 Wed 11/12/14 Future Task

225 1.7.1.8.1 Seismic Retrofit 33 days Sun 4/20/14 Thu 5/22/14 Sat 9/13/14 Wed 10/15/14 Future Task

226 1.7.1.8.1.1 Approach Slab 33 days Sun 4/20/14 Thu 5/22/14 Sat 9/13/14 Wed 10/15/14 Future Task

227 1.7.1.8.2 Non-Seismic Retrofit 58 days Sun 3/23/14 Mon 5/19/14 Wed 8/27/14 Wed 11/12/14 Future Task

228 1.7.1.8.2.1 Repair of Cracks/Concrete 31 days Sun 3/23/14 Tue 4/22/14 Wed 8/27/14 Fri 9/26/14 Future Task

229 1.7.1.8.2.2 Abutment Slope Protection 30 days Sun 4/20/14 Mon 5/19/14 Tue 10/14/14 Wed 11/12/14 Future Task

230 1.7.1.9 LAPA Bridge 129 days Sun 5/11/14 Tue 9/16/14 Thu 7/17/14 Fri 12/12/14 Future Task

231 1.7.1.9.1 Seismic Retrofit 66 days Sun 6/1/14 Tue 8/5/14 Thu 7/17/14 Sat 8/30/14 Future Task

232 1.7.1.9.1.1 Concrete Shear Keys at Abutment 30 days Sun 6/1/14 Mon 6/30/14 Thu 7/17/14 Fri 8/15/14 Future Task

233 1.7.1.9.1.2 Approach Slab 45 days Sun 6/22/14 Tue 8/5/14 Thu 7/17/14 Sat 8/30/14 Future Task

234 1.7.1.9.2 Non-Seismic Retrofit 129 days Sun 5/11/14 Tue 9/16/14 Thu 7/17/14 Fri 12/12/14 Future Task

235 1.7.1.9.2.1 Abutment Slope Protection 30 days Sun 5/11/14 Mon 6/9/14 Thu 11/13/14 Fri 12/12/14 Future Task

236 1.7.1.9.2.2 Repair Expansion Joint 45 days Sun 8/3/14 Tue 9/16/14 Sun 8/31/14 Tue 10/14/14 Future Task

237 1.7.1.9.2.3 Replacement of Superstructure 45 days Sun 6/15/14 Tue 7/29/14 Thu 7/17/14 Sat 8/30/14 Future Task

238 1.7.1.9.2.4 Replacement ofApproach Sidewalk & Railing 45 days Sun 6/22/14 Tue 8/5/14 Wed 8/6/14 Fri 9/19/14 Future Task

239 1.7.1.10 ABANG Bridge 188 days Sun 3/30/14 Fri 10/3/14 Sat 8/16/14 Sat 1/17/15 Future Task

240 1.7.1.10.1 Seismic Retrofit 50 days Fri 8/15/14 Fri 10/3/14 Sat 8/16/14 Mon 9/29/14 Future Task

241 1.7.1.10.1.1 Concrete Shear Keys at Abutment 50 days Fri 8/15/14 Fri 10/3/14 Sat 8/16/14 Sun 9/14/14 Future Task

242 1.7.1.10.1.2 Approach Slab 30 days Sat 8/30/14 Sun 9/28/14 Sun 8/31/14 Mon 9/29/14 Future Task

243 1.7.1.10.2 Non-Seismic Retrofit 93 days Sun 3/30/14 Mon 6/30/14 Tue 9/30/14 Sat 1/17/15 Future Task

244 1.7.1.10.2.1 Abutment Slope Protection 30 days Sun 4/27/14 Mon 5/26/14 Fri 12/19/14 Sat 1/17/15 Future Task

245 1.7.1.10.2.2 Pier Scour Protection 30 days Sun 3/30/14 Mon 4/28/14 Tue 9/30/14 Wed 10/29/14 Future Task

246 1.7.1.10.2.3 Replacement of Superstructure 30 days Tue 4/29/14 Wed 5/28/14 Thu 10/30/14 Fri 11/28/14 Future Task

247 1.7.1.10.2.4 Replacement of Approach Sidewalk & Railing 30 days Sun 6/1/14 Mon 6/30/14 Wed 11/19/14 Thu 12/18/14 Future Task

248 1.7.1.11 MANDARINE Bridge 202 days Tue 7/15/14 Sun 2/1/15 Mon 9/15/14 Wed 2/18/15 Future Task

249 1.7.1.11.1 Seismic Retrofit 105 days Tue 7/15/14Mon 10/27/14 Mon 9/15/14 Sun 11/16/14 Future Task

250 1.7.1.11.1.1 Concrete Shear Keys at Abutment 40 days Tue 7/15/14 Sun 8/24/14 Mon 9/15/14 Thu 10/2/14 Future Task

251 1.7.1.11.1.2 Girder Strengthening 32 days Sun 9/14/14Wed 10/15/14 Fri 10/3/14 Mon 11/3/14 Future Task

252 1.7.1.11.1.3 Approach Slab 30 days Sun 9/28/14Mon 10/27/14 Thu 10/16/14 Sun 11/16/14 Future Task

253 1.7.1.11.2 Non-Seismic Retrofit 99 days Sun 10/26/14 Sun 2/1/15 Sat 9/27/14 Wed 2/18/15 Future Task

254 1.7.1.11.2.1 Repair of Cracks/Concrete 30 days Sat 11/15/14 Sun 12/14/14 Sat 9/27/14 Fri 10/24/14 Future Task

255 1.7.1.11.2.2 Abutment Slope Protection 10 days Fri 1/23/15 Sun 2/1/15 Sun 1/18/15 Wed 2/18/15 Future Task

256 1.7.1.11.2.3 Pier Scour Protection/Painting 30 days Wed 12/24/14 Thu 1/22/15 Mon 11/17/14 Thu 12/18/14 Future Task

257 1.7.1.11.2.4 Provision of Asphalt Overlay 2 days Sun 10/26/14Mon 10/27/14 Mon 11/17/14 Tue 11/18/14 Future Task

258 1.7.1.11.2.5 Repair of expansion joint 2 days Sun 10/26/14Mon 10/27/14 Wed 11/19/14 Thu 11/20/14 Future Task

259 1.7.1.12 ACAS Bridge 254 days Sun 3/16/14Mon 11/24/14 Fri 10/10/14 Wed 2/18/15 Future Task

260 1.7.1.12.1 Seismic Retrofit 58 days Sun 3/16/14 Mon 5/12/14 Fri 10/10/14 Fri 11/14/14 Future Task

261 1.7.1.12.1.1 Concrete Shear Keys at Abutment 28 days Sun 3/16/14 Sat 4/12/14 Fri 10/10/14 Thu 11/6/14 Future Task

262 1.7.1.12.1.2 Approach Slab 30 days Sun 4/13/14 Mon 5/12/14 Thu 10/16/14 Fri 11/14/14 Future Task

263 1.7.1.12.2 Non-Seismic Retrofit 198 days Sun 5/11/14Mon 11/24/14 Sat 10/25/14 Wed 2/18/15 Future Task

264 1.7.1.12.2.1 Repair of Cracks 17 days Sun 5/11/14 Tue 5/27/14 Sat 10/25/14 Sun 11/16/14 Future Task

265 1.7.1.12.2.2 Abutment Slope Protection 30 days Sun 6/22/14 Mon 7/21/14 Tue 1/20/15 Wed 2/18/15 Future Task

266 1.7.1.12.2.3 Pier Scour Protection/Painting 32 days Sun 5/25/14 Wed 6/25/14 Mon 11/17/14 Thu 12/18/14 Future Task

267 1.7.1.12.2.4 Provision of Asphalt Overlay 2 days Sun 11/16/14Mon 11/17/14 Sat 11/22/14 Sun 11/23/14 Future Task

268 1.7.1.12.2.5 Repair of expansion joint 2 days Sun 11/23/14Mon 11/24/14 Mon 11/24/14 Tue 11/25/14 Future Task

269 1.7.1.13 LOOP DE LOOP BRIDGE 80 days Sat 11/22/14 Mon 2/9/15 Sat 11/22/14 Mon 2/9/15 Future Task

270 1.7.1.13.1 Seismic Retrofit 20 days Sat 11/22/14 Thu 12/11/14 Sat 11/22/14 Thu 12/11/14 Future Task

271 1.7.1.13.1.1 Concrete Shear Keys at Abutment 15 days Sat 11/22/14 Sat 12/6/14 Sat 11/22/14 Sat 12/6/14 Future Task

272 1.7.1.13.1.2 Approach Slab 20 days Sat 11/22/14 Thu 12/11/14 Sat 11/22/14 Thu 12/11/14 Future Task

273 1.7.1.13.2 Non-Seismic Retrofit 65 days Sun 12/7/14 Mon 2/9/15 Sun 12/7/14 Mon 2/9/15 Future Task

274 1.7.1.13.2.1 Repair of Concrete/Expansion Joint 15 days Sun 12/7/14 Sun 12/21/14 Fri 12/12/14 Fri 12/26/14 Future Task

275 1.7.1.13.2.2 Replacement of Superstructure 30 days Sun 12/7/14 Mon 1/5/15 Sun 12/7/14 Mon 1/5/15 Future Task

276 1.7.1.13.2.3 Replacement of Approach Sidewalk & Railing 45 days Sat 12/27/14 Mon 2/9/15 Sat 12/27/14 Mon 2/9/15 Future Task

277 1.7.1.14 CANJAGUIMET Bridge 92 days Sat 11/22/14 Sat 2/21/15 Sun 12/7/14 Thu 4/2/15 Future Task

278 1.7.1.14.1 Seismic Retrofit 25 days Sun 12/7/14Wed 12/31/14 Sun 12/7/14 Wed 12/31/14 Future Task

279 1.7.1.14.1.1 Concrete Shear Keys at Abutment 23 days Sun 12/7/14Mon 12/29/14 Sun 12/7/14 Mon 12/29/14 Future Task

280 1.7.1.14.1.2 Approach Slab 20 days Fri 12/12/14Wed 12/31/14 Fri 12/12/14 Wed 12/31/14 Future Task

281 1.7.1.14.2 Non-Seismic Retrofit 92 days Sat 11/22/14 Sat 2/21/15 Thu 1/1/15 Thu 4/2/15 Future Task

282 1.7.1.14.2.1 Repair of Cracks/Concrete 30 days Sat 11/22/14 Sun 12/21/14 Thu 1/1/15 Fri 1/30/15 Future Task

283 1.7.1.14.2.2 Abutment Slope Protection 30 days Fri 1/23/15 Sat 2/21/15 Wed 3/4/15 Thu 4/2/15 Future Task

284 1.7.1.14.2.3 Pier Scour Protection/Painting 32 days Mon 12/22/14 Thu 1/22/15 Sat 1/31/15 Tue 3/3/15 Future Task

285 1.7.1.14.2.4 Provision of Asphalt Overlay 2 days Fri 1/23/15 Sat 1/24/15 Wed 3/4/15 Thu 3/5/15 Future Task

286 1.7.1.14.2.5 Repair of expansion joint 2 days Sun 1/25/15 Mon 1/26/15 Fri 3/6/15 Sat 3/7/15 Future Task

287 1.7.1.15 PISAK Bridge 67 days? Tue 12/30/14 Mon 3/23/15 Tue 12/30/14 Sat 5/2/15 Future Task

288 1.7.1.15.1 Seismic Retrofit 32 days? Tue 12/30/14 Fri 1/30/15 Tue 12/30/14 Fri 1/30/15 Future Task

289 1.7.1.15.1.1 Concrete Shear Keys at Abutment 25 days? Tue 12/30/14 Fri 1/23/15 Tue 12/30/14 Fri 1/23/15 Future Task

290 1.7.1.15.1.2 Approach Slab 30 days? Thu 1/1/15 Fri 1/30/15 Thu 1/1/15 Fri 1/30/15 Future Task

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

2014 2015 2016

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Manual Task

Start-only

Finish-only

Duration-only

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Manual Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Deadline

Baseline 1

SNRDP-CP2 Qingjian Group Co., Ltd. Baseline Schedule

Page 4: cp2 - Baseline Schedule

ID Task Name Est. Duration Est. Start - Base

1

Est. Finish -

Base 1

Baseline Start Baseline Finish Status

291 1.7.1.15.2 Non-Seismic Retrofit 51 days Sat 1/31/15 Mon 3/23/15 Sat 1/31/15 Sat 5/2/15 Future Task

292 1.7.1.15.2.1 Repair of Cracks/Restore Concrete/Painting 33 days Sat 1/31/15 Wed 3/4/15 Sat 1/31/15 Wed 3/4/15 Future Task

293 1.7.1.15.2.2 Abutment Slope Protection 30 days Sun 2/22/15 Mon 3/23/15 Fri 4/3/15 Sat 5/2/15 Future Task

294 1.7.1.15.2.3 Provision of Asphalt Overlay 2 days Thu 3/5/15 Fri 3/6/15 Thu 3/5/15 Fri 3/6/15 Future Task

295 1.7.1.15.2.4 Repair of expansion joint 2 days Mon 2/2/15 Tue 2/3/15 Sat 3/7/15 Sun 3/8/15 Future Task

296 1.7.1.16 CAMP 5 bridge 180 days Mon 12/22/14 Mon 6/1/15 Sat 1/24/15 Mon 6/1/15 Future Task

297 1.7.1.16.1 Seismic Retrofit 86 days Mon 12/22/14 Fri 2/27/15 Sat 1/24/15 Sun 3/1/15 Future Task

298 1.7.1.16.1.1 Concrete Shear Keys at Abutment/Pier 35 days Sat 1/24/15 Fri 2/27/15 Sat 1/24/15 Fri 2/27/15 Future Task

299 1.7.1.16.1.2 Approach Slab 30 days Mon 12/22/14 Tue 1/20/15 Sat 1/31/15 Sun 3/1/15 Future Task

300 1.7.1.16.2 Non-Seismic Retrofit 132 days Sun 2/8/15 Mon 6/1/15 Sat 2/28/15 Mon 6/1/15 Future Task

301 1.7.1.16.2.1 Abutment Slope Protection 30 days Sun 5/3/15 Mon 6/1/15 Sun 5/3/15 Mon 6/1/15 Future Task

302 1.7.1.16.2.2 Pier Scour Protection 30 days Sat 2/28/15 Sun 3/29/15 Sat 2/28/15 Sun 3/29/15 Future Task

303 1.7.1.16.2.3 Repair of Expansion joint 2 days Wed 2/18/15 Thu 2/19/15 Mon 3/30/15 Tue 3/31/15 Future Task

304 1.7.1.16.2.4 Replacement of Superstructure 30 days Sat 2/28/15 Sun 3/29/15 Sat 2/28/15 Sun 3/29/15 Future Task

305 1.7.1.16.2.5 Replacement of Approach Sidewalk & Railing 30 days Sun 2/8/15 Mon 3/9/15 Fri 3/20/15 Sat 4/18/15 Future Task

306 1.7.1.17 CARBON 2 Bridge 182 days Mon 1/19/15 Wed 7/1/15 Sat 2/28/15 Wed 7/1/15 Future Task

307 1.7.1.17.1 Seismic Retrofit 32 days Mon 1/19/15 Thu 2/19/15 Sat 2/28/15 Tue 3/31/15 Future Task

308 1.7.1.17.1.1 Concrete Shear Keys at Abutment 20 days Mon 1/19/15 Sat 2/7/15 Sat 2/28/15 Thu 3/19/15 Future Task

309 1.7.1.17.1.2 Approach Slab 30 days Wed 1/21/15 Thu 2/19/15 Mon 3/2/15 Tue 3/31/15 Future Task

310 1.7.1.17.2 Non-Seismic Retrofit 104 days Fri 3/20/15 Wed 7/1/15 Fri 3/20/15 Wed 7/1/15 Future Task

311 1.7.1.17.2.1 Repair of Concrete/Painting of steel component 25 days Fri 3/20/15 Mon 4/13/15 Fri 3/20/15 Mon 4/13/15 Future Task

312 1.7.1.17.2.2 Abutment Slope Protection 30 days Tue 6/2/15 Wed 7/1/15 Tue 6/2/15 Wed 7/1/15 Future Task

313 1.7.1.17.2.3 Provision of Asphalt Overlay 2 days Tue 4/14/15 Wed 4/15/15 Tue 4/14/15 Wed 4/15/15 Future Task

314 1.7.1.17.2.4 Repair of expansion joint 2 days Thu 4/16/15 Fri 4/17/15 Thu 4/16/15 Fri 4/17/15 Future Task

315 1.7.1.18 TIGA BRIDGE 64 days Fri 3/20/15 Fri 5/22/15 Fri 3/20/15 Fri 5/22/15 Future Task

316 1.7.1.18.1 Seismic Retrofit 37 days Fri 3/20/15 Sat 4/25/15 Fri 3/20/15 Sat 4/25/15 Future Task

317 1.7.1.18.1.1 Concrete Shear Keys at Abutment 20 days Fri 3/20/15 Wed 4/8/15 Fri 3/20/15 Wed 4/8/15 Future Task

318 1.7.1.18.1.2 Approach Slab 25 days Wed 4/1/15 Sat 4/25/15 Wed 4/1/15 Sat 4/25/15 Future Task

319 1.7.1.18.1.3 Cutting of Existing Concrete Structures 7 days Fri 3/20/15 Thu 3/26/15 Fri 3/20/15 Thu 3/26/15 Future Task

320 1.7.1.18.2 Non-Seismic Retrofit 44 days Thu 4/9/15 Fri 5/22/15 Thu 4/9/15 Fri 5/22/15 Future Task

321 1.7.1.18.2.1 Repair of Concrete/Painting of steel component 20 days Thu 4/9/15 Tue 4/28/15 Thu 4/9/15 Tue 4/28/15 Future Task

322 1.7.1.18.2.2 Abutment Slope Protection 25 days Tue 4/28/15 Fri 5/22/15 Tue 4/28/15 Fri 5/22/15 Future Task

323 1.7.1.18.2.3 Provision of Asphalt Overlay 2 days Sun 4/26/15 Mon 4/27/15 Sun 4/26/15 Mon 4/27/15 Future Task

324 1.7.1.18.2.4 Repair of expansion joint 2 days Tue 4/28/15 Wed 4/29/15 Tue 4/28/15 Wed 4/29/15 Future Task

325 1.7.1.19 CARBON 1 Bridge 157 days Sun 7/27/14 Tue 12/30/14 Thu 4/9/15 Sun 7/12/15 Future Task

326 1.7.1.19.1 Seismic Retrofit 58 days Sun 7/27/14 Mon 9/22/14 Thu 4/9/15 Fri 5/8/15 Future Task

327 1.7.1.19.1.1 Concrete Shear Keys at Abutment/Pier 30 days Sun 7/27/14 Mon 8/25/14 Thu 4/9/15 Fri 5/8/15 Future Task

328 1.7.1.19.1.2 Approach Slab 30 days Sun 8/24/14 Mon 9/22/14 Thu 4/9/15 Fri 5/8/15 Future Task

329 1.7.1.19.2 Non-Seismic Retrofit 111 days Thu 9/11/14 Tue 12/30/14 Sat 5/9/15 Sun 7/12/15 Future Task

330 1.7.1.19.2.1 Abutment Slope Protection 30 days Mon 12/1/14 Tue 12/30/14 Mon 6/8/15 Tue 7/7/15 Future Task

331 1.7.1.19.2.2 Pier Scour Protection 30 days Mon 12/1/14 Tue 12/30/14 Sat 5/9/15 Sun 6/7/15 Future Task

332 1.7.1.19.2.3 Replacement of Superstructure 30 days Thu 9/11/14 Fri 10/10/14 Sat 5/9/15 Sun 6/7/15 Future Task

333 1.7.1.19.2.4 Replacement of Approach Sidewalk & Railing 45 days Wed 10/1/14 Fri 11/14/14 Fri 5/29/15 Sun 7/12/15 Future Task

334 1.7.1.20 BAGACAY BRIDGE 156 days Thu 5/1/14 Fri 10/3/14 Sat 5/9/15 Wed 9/30/15 Future Task

335 1.7.1.20.1 Seismic Retrofit 45 days Thu 5/1/14 Sat 6/14/14 Sat 5/9/15 Mon 6/22/15 Future Task

336 1.7.1.20.1.1 Concrete Shear Keys at Abutment/Pier 22 days Thu 5/1/14 Thu 5/22/14 Sat 5/9/15 Mon 6/22/15 Future Task

337 1.7.1.20.1.2 Approach Slab 45 days Thu 5/1/14 Sat 6/14/14 Sat 5/9/15 Mon 6/22/15 Future Task

338 1.7.1.20.2 Non-Seismic Retrofit 104 days Sun 6/22/14 Fri 10/3/14 Tue 6/23/15 Wed 9/30/15 Future Task

339 1.7.1.20.2.1 Abutment Slope Protection 34 days Sun 8/31/14 Fri 10/3/14 Fri 8/28/15 Wed 9/30/15 Future Task

340 1.7.1.20.2.2 Pier Scour Protection 21 days Sun 8/10/14 Sat 8/30/14 Fri 8/7/15 Thu 8/27/15 Future Task

341 1.7.1.20.2.3 Replacement of Superstructure 45 days Sun 6/22/14 Tue 8/5/14 Tue 6/23/15 Thu 8/6/15 Future Task

342 1.7.1.20.2.4 Approach Sidewalk & Railing 45 days Sun 8/10/14 Tue 9/23/14 Mon 7/13/15 Wed 8/26/15 Future Task

343 1.7.1.21 Complete Rehabilitation of Existing Bridges 0 days Wed 9/30/15 Wed 9/30/15 Wed 9/30/15 Wed 9/30/15 Future Task

344 1.7.2 Construction of New Bridges 387 days Sun 3/23/14 Mon 4/13/15 Sun 12/1/13 Mon 9/14/15 Future Task

345 1.7.2.1 LUMATOD BRIDGE 174 days Sun 3/16/14 Fri 9/5/14 Sun 12/1/13 Sat 8/2/14 Future Task

346 1.7.2.1.1 Bridge Approach/Earthworks 20 days Sun 4/13/14 Fri 5/2/14 Sun 12/1/13 Fri 12/20/13 Future Task

347 1.7.2.1.2 Temporay Detour at Lumatod Bridge Site 13 days Sun 3/16/14 Fri 3/28/14 Sat 12/21/13 Fri 12/27/13 Future Task

348 1.7.2.1.3 Removal of Existing Lumatod Bridge 25.5 days Sun 3/30/14 Thu 4/24/14 Sat 12/28/13 Sun 1/26/14 Future Task

349 1.7.2.1.4 Substructure 80 days Sun 4/27/14 Tue 7/15/14 Mon 1/27/14 Wed 4/16/14 Future Task

350 1.7.2.1.5 Superstructure 60 days Sun 6/22/14 Wed 8/20/14 Thu 4/17/14 Sun 6/15/14 Future Task

351 1.7.2.1.6 River Widening/Abutment Bank Slope Protection 20 days Sun 8/17/14 Fri 9/5/14 Mon 7/14/14 Sat 8/2/14 Future Task

352 1.7.2.2 BURAK BRIDGE 186 days Sun 3/23/14 Wed 9/24/14 Sat 12/21/13 Wed 9/24/14 Future Task

353 1.7.2.2.1 Bridge Approach/Earthworks 20 days Sun 4/6/14 Fri 4/25/14 Sat 12/21/13 Thu 1/9/14 Future Task

354 1.7.2.2.2 Temporary Detour at Burak Bridge Site 10 days Sun 3/23/14 Tue 4/1/14 Fri 1/10/14 Sun 1/19/14 Future Task

355 1.7.2.2.3 Removal of Existing Burak Bridge 20 days Sun 4/6/14 Fri 4/25/14 Mon 1/20/14 Sat 2/8/14 Future Task

356 1.7.2.2.4 Substructure 69 days Thu 5/1/14 Tue 7/8/14 Sun 4/20/14 Tue 7/8/14 Future Task

357 1.7.2.2.5 Superstructure 30 days Wed 7/9/14 Thu 8/7/14 Wed 7/9/14 Thu 8/7/14 Future Task

358 1.7.2.2.6 River Widening/Abutment Bank Slope Protection 20 days Fri 9/5/14 Wed 9/24/14 Fri 9/5/14 Wed 9/24/14 Future Task

359 1.7.2.3 BAYO BRIDGE 171 days Thu 9/25/14 Sat 3/14/15 Thu 9/25/14 Wed 4/8/15 Future Task

360 1.7.2.3.1 Replacement of Superstructure/Approach Sidewalk & Railing 20 days Thu 9/25/14 Tue 10/14/14 Thu 9/25/14 Tue 10/14/14 Future Task

361 1.7.2.3.2 Temporary Detour at Bayo Bridge Site 10 days Wed 10/15/14 Fri 10/24/14 Wed 10/15/14 Fri 10/24/14 Future Task

362 1.7.2.3.3 Removal of Existing Bayo Bridge 20 days Sat 10/25/14 Thu 11/13/14 Sat 10/25/14 Thu 11/13/14 Future Task

363 1.7.2.3.4 Substructure 60 days Fri 11/14/14 Mon 1/12/15 Fri 11/14/14 Mon 1/12/15 Future Task

364 1.7.2.3.5 Superstructure 30 days Tue 1/13/15 Wed 2/11/15 Tue 1/13/15 Wed 2/11/15 Future Task

365 1.7.2.3.6 River Widening/Abutment Bank Slope Protection 20 days Mon 2/23/15 Sat 3/14/15 Fri 3/20/15 Wed 4/8/15 Future Task

366 1.7.2.4 BINALOAN BRIDGE 307 days Wed 6/11/14 Mon 4/13/15 Thu 9/25/14 Fri 5/8/15 Future Task

367 1.7.2.4.1 Bridge Approach/Earthworks 30 days Sun 12/21/14 Mon 1/19/15 Thu 9/25/14 Fri 10/24/14 Future Task

368 1.7.2.4.2 Temporary Detour at Binaloan Bridge Site 25 days Sun 7/13/14 Wed 8/6/14 Sat 10/25/14 Tue 11/18/14 Future Task

369 1.7.2.4.3 Removal of Existing Bayo Bridge 26 days Wed 6/11/14 Sun 7/6/14 Fri 11/14/14 Tue 12/9/14 Future Task

370 1.7.2.4.4 Substructure 125 days Mon 7/7/14 Sat 11/8/14 Wed 12/10/14 Sat 2/7/15 Future Task

371 1.7.2.4.5 Superstructure 60 days Sun 11/9/14 Wed 1/7/15 Sun 2/8/15 Wed 4/8/15 Future Task

372 1.7.2.4.6 River Widening/Abutment Bank Slope Protection 30 days Sun 3/15/15 Mon 4/13/15 Thu 4/9/15 Fri 5/8/15 Future Task

373 1.7.2.5 CANSOLABAO BRIDGE 191 days? Sun 8/10/14 Mon 2/16/15 Thu 2/12/15 Mon 9/14/15 Future Task

374 1.7.2.5.1 Bridge Approach/Earthworks 30 days Sun 8/24/14 Mon 9/22/14 Thu 2/12/15 Fri 3/13/15 Future Task

375 1.7.2.5.2 Temporary Detour at Cansolabao Bridge Site 15 days Sun 8/10/14 Sun 8/24/14 Sat 3/14/15 Sat 3/28/15 Future Task

376 1.7.2.5.3 Removal of Existing Cansolabao Bridge 20 days? Sun 8/31/14 Fri 9/19/14 Sun 3/29/15 Fri 4/17/15 Future Task

377 1.7.2.5.4 Substructure 60 days Sun 9/21/14Wed 11/19/14 Sat 4/18/15 Tue 6/16/15 Future Task

378 1.7.2.5.5 Superstructure 60 days Sun 11/23/14 Wed 1/21/15 Wed 6/17/15 Sat 8/15/15 Future Task

379 1.7.2.5.6 River Widening/Abutment Bank Slope Protection 30 days? Sun 1/18/15 Mon 2/16/15 Sun 8/16/15 Mon 9/14/15 Future Task

380 1.7.3 COMPLETE BRIDGE WORKS 0 days Wed 9/30/15 Wed 9/30/15 Wed 9/30/15 Wed 9/30/15 Future Task

381 1.8 DRAINAGE AND SLOPE PROTECTION STRUCTURES 921 days Fri 8/23/13 Mon 2/29/16 Fri 11/1/13 Mon 2/29/16 On Schedule

382 1.8.1 SECTION 3: STA 888+500 - STA 873+500 (15.00km) 354.95 days Fri 8/23/13 Tue 8/12/14 Fri 11/1/13 Thu 7/31/14 On Schedule

383 1.8.1.1 Construction of Drainage Works (RCPC,RCBC, Headwalls, Wingwalls,Catch

Basin, Covered & Ditch Canal

191.95 days Sun 11/3/13 Tue 8/12/14 Fri 11/1/13 Thu 7/31/14 On Schedule

384 1.8.1.2 Slope Stability /Protection Works 212 days Wed 1/1/14 Thu 7/31/14 Wed 1/1/14 Thu 7/31/14 On Schedule

389 1.8.2 SECTION 2: STA 873+500 - STA 858+500 (15.00km) 305 days Wed 4/30/14 Sat 2/28/15 Wed 4/30/14 Sat 2/28/15 Future Task

390 1.8.2.1 Construction of Drainage Works (RCPC,RCBC, Headwalls, Wingwalls,Catch

Basin, Covered & Ditch Canal

215 days Wed 4/30/14 Sun 11/30/14 Wed 4/30/14 Sun 11/30/14 Future Task

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

9/30

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

9/30

6%

34%

10%

0%

0%

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

2014 2015 2016

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Manual Task

Start-only

Finish-only

Duration-only

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Manual Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Deadline

Baseline 1

SNRDP-CP2 Qingjian Group Co., Ltd. Baseline Schedule

Page 5: cp2 - Baseline Schedule

ID Task Name Est. Duration Est. Start - Base

1

Est. Finish -

Base 1

Baseline Start Baseline Finish Status

391 1.8.2.2 Slope Stability /Protection Works 212 days Fri 8/1/14 Sat 2/28/15 Fri 8/1/14 Sat 2/28/15 Future Task

398 1.8.3 SECTION 1: STA 858+500 - STA 843+500 (15.00km) 717 days Sat 3/15/14 Mon 2/29/16 Sat 3/15/14 Mon 2/29/16 Future Task

399 1.8.3.1 Construction of Drainage Works (RCPC,RCBC, Headwalls, Wingwalls,Catch

Basin, Covered & Ditch Canal

215 days Fri 8/1/14 Tue 3/3/15 Fri 8/1/14 Tue 3/3/15 Future Task

400 1.8.3.2 Slope Stability /Protection Works 717 days Sat 3/15/14 Mon 2/29/16 Sat 3/15/14 Mon 2/29/16 Future Task

432 1.8.4 SECTION 4: STA 888+500 - STA 907+281.82 (18.78km) 285 days Mon 12/1/14 Fri 9/11/15 Mon 12/1/14 Fri 9/11/15 Future Task

433 1.8.4.1 Construction of Drainage Works (RCPC,RCBC, Headwalls, Wingwalls,Catch

Basin, Covered & Ditch Canal

285 days Mon 12/1/14 Fri 9/11/15 Mon 12/1/14 Fri 9/11/15 Future Task

434 1.8.5 Complete Drainage and Slope Protection Structures 0 days Mon 2/29/16 Mon 2/29/16 Mon 2/29/16 Mon 2/29/16 Future Task

435 1.9 MISCELLANEOUS STRUCTURES 883 days Mon 9/30/13 Mon 2/29/16 Thu 5/1/14 Mon 2/29/16 On Schedule

436 1.9.1 ROAD STRUCTURES/SIGNAGES/MARKINGS 579 days Mon 9/30/13 Mon 2/29/16 Thu 5/1/14 Mon 2/29/16 On Schedule

437 1.9.2 LANDSCAPING 170 days Sun 9/13/15 Mon 2/29/16 Sun 9/13/15 Mon 2/29/16 Future Task

438 1.9.3 STREET LIGHTING SYSTEM 661 days Thu 5/1/14 Sun 2/21/16 Thu 5/1/14 Sun 2/21/16 Future Task

439 1.9.3.1 Excavation works 193 days Thu 5/1/14 Sun 11/9/14 Thu 5/1/14 Sun 11/9/14 Future Task

440 1.9.3.2 Installation of necessary appurtenances for foundation 200 days Mon 5/5/14 Thu 11/20/14 Mon 5/5/14 Thu 11/20/14 Future Task

441 1.9.3.3 Erection of Pedestal and Posts 207 days Wed 6/4/14 Sat 12/27/14 Wed 6/4/14 Sat 12/27/14 Future Task

442 1.9.3.4 Concrete Ducting works 100 days Wed 6/11/14 Thu 9/18/14 Wed 6/11/14 Thu 9/18/14 Future Task

443 1.9.3.5 Backfilling works 199 days Fri 7/11/14 Sun 1/25/15 Fri 7/11/14 Sun 1/25/15 Future Task

444 1.9.3.6 Installation of necessary appurtenances to complete 230 days Tue 9/9/14 Sun 4/26/15 Tue 9/9/14 Sun 4/26/15 Future Task

445 1.9.3.7 Installation of roadlight luminaire 240 days Mon 4/27/15 Tue 12/22/15 Mon 4/27/15 Tue 12/22/15 Future Task

446 1.9.3.8 Testing and commissioning 60 days Tue 11/3/15 Fri 1/1/16 Tue 11/3/15 Fri 1/1/16 Future Task

447 1.9.3.9 Complete Street Lighting System 0 days Sun 2/21/16 Sun 2/21/16 Sun 2/21/16 Sun 2/21/16 Future Task

448 1.10 PROVISIONAL SUMS 486 days Wed 10/1/14 Sat 1/30/16 Wed 10/1/14 Sat 1/30/16 Future Task

449 1.10.1 RELOCATION OF ELECTRICAL DISTRIBUTION SYSTEM 486 days Wed 10/1/14 Sat 1/30/16 Wed 10/1/14 Sat 1/30/16 Future Task

450 1.10.1.1 Relocation works (With ESAMELCO) 486 days Wed 10/1/14 Fri 1/29/16 Wed 10/1/14 Fri 1/29/16 Future Task

451 1.10.1.2 Complete Relocation 0 days Sat 1/30/16 Sat 1/30/16 Sat 1/30/16 Sat 1/30/16 Future Task

452 1.10.2 Removal and Relocation of Existing Barangay Markers 180 days Mon 8/3/15 Sat 1/30/16 Mon 8/3/15 Sat 1/30/16 Future Task

453 1.10.2.1 Removal and Relocation of Markers 180 days Mon 8/3/15 Fri 1/29/16 Mon 8/3/15 Fri 1/29/16 Future Task

454 1.10.2.2 Complete Removal and Relocation of Markers 0 days Sat 1/30/16 Sat 1/30/16 Sat 1/30/16 Sat 1/30/16 Future Task

455 1.10.3 PROVISIONAL SUMS 486 days Wed 10/1/14 Sat 1/30/16 Wed 10/1/14 Sat 1/30/16 Future Task

456 1.10.3.1 Provisional Sum 486 days Wed 10/1/14 Fri 1/29/16 Wed 10/1/14 Fri 1/29/16 Future Task

457 1.10.3.2 Complete Provisional Sum 0 days Sat 1/30/16 Sat 1/30/16 Sat 1/30/16 Sat 1/30/16 Future Task

458 1.11 DAYWORK 514 days Tue 11/4/14 Thu 3/31/16 Tue 11/4/14 Thu 3/31/16 Future Task

459 1.11.1 Daywork 514 days Tue 11/4/14 Thu 3/31/16 Tue 11/4/14 Thu 3/31/16 Future Task

460 1.12 MOBILIZATION/DEMOBILIZATION 1005 days Mon 7/1/13 Thu 3/31/16 Mon 7/1/13 Thu 3/31/16 On Schedule

461 1.12.1 Mobilization 215 days Mon 7/1/13 Fri 1/31/14 Mon 7/1/13 Mon 9/30/13 Complete

462 1.12.2 Demobilization 59 days Mon 2/1/16 Wed 3/30/16 Mon 2/1/16 Wed 3/30/16 Future Task

463 1.12.3 As-Built 62 days Sat 1/30/16 Thu 3/31/16 Sat 1/30/16 Thu 3/31/16 Future Task

464 1.13 COMPLETE CP2 PROJECT 0 days Thu 3/31/16 Thu 3/31/16 Wed 3/30/16 Wed 3/30/16 Future Task

0%

0%

0%

0%

2/29

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

2/21

0%

0%

0%

1/30

0%

0%

1/30

0%

0%

1/30

0%

0%

64%

100%

0%

0%

3/31

Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

2014 2015 2016

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Manual Task

Start-only

Finish-only

Duration-only

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Manual Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Deadline

Baseline 1

SNRDP-CP2 Qingjian Group Co., Ltd. Baseline Schedule