Cow Creek Pre-Project & Post-Project Comparison Oct. 15, 2012 1.
Cow Creek Data Center 2013
-
Upload
mark-bilton-smith -
Category
Documents
-
view
366 -
download
0
Transcript of Cow Creek Data Center 2013
Google - Dalles, OR -Three 68,680 sq. ft buildings (2006)
Facebook - Prineville, OR –147,000 sq. ft. First company-built data center (Jan 2010)
Microsoft - Quincy, WA –A new data center being constructed next to the existing one
(April, 2010) 470,000 sq. ft. $500 million (2007)
Dell- Quincy, WA –250,000 sq. ft. (November 2010)
Yahoo - Quincy, WA –140,000 sq. ft. (2007)
Amazon - Port of Morrow, OR –35 acres of land for data center in the future (Nov 2010)
Boardman, OR –116,000 sq. ft. 3 large buildings $100 million project (Nov 2008)
Apple - Prineville, OR – Purchased 160 Acres, announced February of 2012
Bend Broadband – Bend, OR – 30,000 sq. ft. $16 million project, first phase complete 2011
Data Center West - Medford, OR – 2,000 sq. ft.
EasyStreet - Beaverton, OR – Expaned 5000 sq. ft. Energy efficient facility, (2011)
Fortune - Hillsboro, OR – 240,000 sq. ft. currently in phase 1 of build
Infinity Internet – Portland, OR – New 10,793 sq. ft. Under Construction
Opus:interactive – Portland, OR – 80,000 sq. ft. Open for Business
Rio Networks – Roseburg, OR – 12,500 sq. ft. Facility, Opens October 2012
Recent Growth in the NorthWest
Data Center opportunity
What is the opportunity?
The Tribe is seeking a Joint venture, Partnership, Wholesale or Lessee
12,500 sq ft data center – See next slide (s)
We have 37 racks ready for use, up to 170 racks at full build out
Facility was originally planned to be a retail business
Data center is built on Tribal land, there are many advantages
The area have many geographic advantages
Southern Oregon is an untapped Data Center Market
Hot hands can be provided by skilled Cow Creek IT staff
Fiber providers are built in
Our facility – Roseburg Oregon
1st Floor - 12,500 sq. ft. - Data Center
2nd Floor – 12,500 sq.ft. – Umpqua business center
(Business Incubator)
Offices / Electrical / Conference room
staging area / Kitchen / Cross connect /
Data Center & NOC - 12,500 SF
Data center - 5000 SF
Current design “phase1A” supports 180kw
to the floor and 37 racks
Engineered Capacity of 1.7MW critical - up
to 170 High Density Racks
Enhanced security and surveillance
Fire pre-detection and pre-action
Direct BPA power 3 MW
Diverse fiber paths
NOC and monitoring
Loading/Staging/Programming area
Redundant N+1
I. Generators
II. Climate control
III. Battery backup
3 Phase Engineered Design
Design Guidelines per Phase:
Phase 1a (Complete)
500Kw Diesel generator(s) (N+1)
225kVA UPS (N+1)
51 tons (N+1) Cooling Data Center
180kW (IT Loads) Data Center
3 tons (N) Cooling Electrical Room
6 tons (N+1) Cooling Cross-Connect room
20kW (IT Loads) Cross-Connect Room
Phase 1b
750kVA UPS (N+1)
171 tons (N+1) Cooling Data Center
600kW (IT Loads) Data Center
9 tons (N) Cooling Electrical Room
11 tons (N+1) Cooling Cross-Connect room
40kW (IT Loads) Cross-Connect Room
Phase 2
500kVA UPS (N+1) Electrical room
1,100kVA UPS (N+1) UPS Room
540 tons (N+1) Cooling Data Center
1,480kW (IT Loads) Data Center
9 tons (N) Cooling Electrical Room
12 tons (N) Cooling UPS Room
Our facility – Roseburg Oregon
Phase 1A - 37 racks capable of up to 8kW per rack – Average 5kW per rack (Complete)
Phase 1A - Complete
Equipment
Location Component
Required
Cooling
Capacity
(Tons)
Available
Cooling
Capacity
(Tons)
% of Full
Cooling
Capacity
Power
Consumption
(kW/Ton)
Power
Consumption
(kW)
Yearly Run Time
Estimate
(Hrs)
Total Yearly
Consumption
(kW)
Site Estimated
Average Power
Draw
(kW)
Site
Estimated
PUE
Plant Airstack Chillers 51 60 86% 0.90 46.1 6167 284493
Krack Dry Cooler 51 200 26% 0.125 6.4 2593 16669
Drycooler Pump 51 NA NA 0.02 1.0 2593 2667
Primary Chilled Water Pumps 51 NA NA 0.04 2.1 8760 18021
Secondary Chilled Water Pumps 51 NA NA 0.09 4.6 8760 40546
Data Floor Rittal LCP Modules 51 51 100% 0.14 7.2 8760 63072
Estimated Phase 1A Power Utilization Efficiency (PUE) @ 180 kW Data Load
49 1.27
Phase 1B - Complete
Equipment
Location Component
Required
Cooling
Capacity
(Tons)
Available
Cooling
Capacity
(Tons)
% of Full
Cooling
Capacity
Power
Consumption
(kW/Ton)
Power
Consumption
(kW)
Yearly Run Time
Estimate
(Hrs)
Total Yearly
Consumption
(kW)
Site Estimated
Average Power
Draw
(kW)
Site
Estimated
PUE
Plant Airstack Chillers 171 180 95% 1.02 174.8 6167 1078164
Krack Dry Cooler 171 200 86% 0.125 21.4 2593 55555
Drycooler Pump 171 NA NA 0.02 3.4 2593 8889
Primary Chilled Water Pumps 171 NA NA 0.04 6.9 8760 60059
Secondary Chilled Water Pumps 171 NA NA 0.09 15.4 8760 135132
Data Floor Rittal LCP Modules 171 171 100% 0.14 23.996 8760 210205
Estimated Phase 1B Power Utilization Efficiency (PUE)@ 600 kW Data Load
177 1.29
Phase 2 - Engineered
Equipment Location Component
Required
Cooling
Capacity
(Tons)
Available
Cooling
Capacity
(Tons)
% of Full
Cooling
Capacity
Power
Consumption
(kW/Ton)
Power
Consumption
(kW)
Yearly Run Time
Estimate
(Hrs)
Total Yearly
Consumption
(kW)
Site Estimated
Average Power
Draw
(kW)
Site
Estimated
PUE
Plant Airstack Chillers 423 180 78% 0.81 341.6 2076 709112
Evapco Fluid Cooler (Dry Cool) 423 520 81% 0.109 46.1 1051 48429
Evapco Fluid Cooler (Evaporative Cool) 423 NA NA 0.009 3.8 5633 21432
Drycooler Pump 423 NA NA 0.02 8.5 6684 56512
Primary Chilled Water Pumps 423 NA NA 0.04 16.9 8760 148129
Secondary Chilled Water Pumps 423 NA NA 0.09 38.0 8760 333290
Data Floor Rittal LCP Modules 423 423 100% 0.14 59.184 8760 518452
Estimated Phase 2 Power Utilization Efficiency (PUE) @ 1,480 kW Data Load
210 1.14
Umpqua Business Center
522 SW Washington – Rosebug Oregon
12,500 sq. ft. Business Incubator
12,500 sq.ft. High density Colocation facility
Data Center
522 SW Washington – Rosebug Oregon
12,500 sq. ft. Business Incubator
12,500 sq.ft. High density Colocation facility
Data Center
522 SW Washington – Rosebug Oregon
12,500 sq. ft. Business Incubator
12,500 sq.ft. High density Colocation facility
Our facility – Roseburg Oregon
Energy efficient water cooled architectureFree cooling will be leveraged for additional efficiencyChilled water cooling at 62 degreesDirect enclosure cooling for high-load applications170 High Density enclosures ( Up to 20kW)
To understand the benefits of this solution see this youtube linkhttp://www.youtube.com/watch?v=IsFRt5cgzwk&feature=related
Enclosure width 24” - 600.0 mm
Enclosure height 87” - 2,200.0 mm
Enclosure depth 42” -1,050.0 mm
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
100.00%
Roseburg Portland San Francisco Sacramento Los Angeles Seattle
Earthquake Probability
Next 50 Years
5.0 5.1 5.2 5.3 5.4 5.5Magnitude
Our Advantage – Geography
Our Tribal Advantage
Property owned by The Cow Creek Tribe, it is sovereign ground.
Sovereign Immunity – Legal protection
Lack of regulatory barriers
Absence of sales and ad valorem taxes
Frequent availability of New Market Tax Credits
Sales tax exemptions for equipment purchased outside the reservation but used there
Exemptions from local, county, and state zoning and land use controls
Expanded financing opportunities for operations on Indian land
Foreign trade “Off Shore” in the USA
In many cases we have a defined preference on government contracts
Special financing incentives
Tax exceptions
Availability of HubZone, "Empowerment Zone," and foreign trade zone designations
Sales tax exemptions for equipment purchased outside the reservation but used there
Roseburg Oregon is designated as a Rural underserved community
26.102, which provides a five-percent incentive from the U.S. Department of Defense for
contracting with an Indian-owned business.
The majority of this content can be validated herehttp://www.bia.gov/WhoWeAre/AS-IA/IEED/DED/CO/index.htm