    C-FBISD VISION:

    All students will meet the State of Texas Assessments of Academic Readiness (STAAR) at the satisfactory or advancedlevel and graduate college-ready and/or workforce ready without remediation.

    COUNTRY PLACE ELEMENTARYCAMPUS IMPROVEMENT PLAN

    2011-2012

    Carrollton-Farmers Branch Independent School District

    Kathi Ferris, Principal

  • 8/3/2019 Country Place - Campus Improvement Plan 2011-2012

    2/15

    BOARD OF TRUSTEES

    Nancy Cline, President James Goode, Vice President Richard Fleming, Secretary

    Lynn Chaffin, Assistant Secretary Frank Shor, Board Member

    Nancy Watten, Board Member Karin Webb, Board Member

    CARROLLTON-FARMERS BRANCH

    SCHOOLS

    SENIOR HIGH SCHOOLS

    CreekviewEarly College

    Newman SmithR. L. TurnerRanchview

    MIDDLE SCHOOLS

    Blalack BushFieldLongPerryPolk

    SUPPORTING OBJECTIVES

    Supporting Objective 1:

    Continuously increase student achievement

    Supporting Objective 2:

    Continuously improve the learning environment forstudents and staff

    Supporting Objective 3:

    Continuously increase operational effectiveness

    Supporting Objective 4:

    Continuously increase stakeholder confidence andsupport of our school system

    ELEMENTARY SCHOOLS

    BlairBlanton

    CarrolltonCentral

    Country PlaceDavis

    Farmers BranchFreemanFurneaux

    GoodKent

    LandryLas ColinasLa VillitaMcCoy

    McKamyMcLaughlinMcWhorterRainwaterRiverchaseRosemeade

    Sheffield IntermediateSheffield Primary

    Stark StricklandThompson

    CENTERS

    Mary Grimes Education CenterSalazar Transition School

    Kelly Pre-K CenterHuie Education CenterCLC Learning Complex

    C-FBISD GOAL

    The Goal of the Carrollton-FarmersBranch ISD is high achievement for

    all students.

    2

  • 8/3/2019 Country Place - Campus Improvement Plan 2011-2012

    3/15

    3

    CAMPUS IMPROVEMENT COUNCIL REPRESENTATIVES

    BUSINESS/COMMUNITY REPRESENTATIVES

    Susan Morris

    PARENT REPRESENTATIVES

    Craig Decherd

    ADMINISTRATORS

    Kathi Ferris - Principal

    STAFF REPRESENTATIVES

    K-1 Teacher Jennifer Leadmon

    2-3 Teacher Courtney Bender

    4-5 Teacher LeeAnn Starnes

    At Large L J MurphyTeacher

    At Large Susan BrantleyTeacher

    Sp. Ed. Yvette Achee

    At Large Sherry CoxStaff

    CAMPUS PLAN REVIEW :

    Chair Signature Date Chair Signature Date

    Chair Signature Date Chair Signature Date

  • 8/3/2019 Country Place - Campus Improvement Plan 2011-2012

    4/15

    4

    C-FBISD VISION

    All students will meet the State of Texas Assessments ofAcademic Readiness (STAAR) at the satisfactory or advancedlevel and graduate college-ready and/or workforce readywithout remediation.

    MISSION

    Together with families and community we commit all districtresources to guide the learning of each student to graduate as:

    A responsible individual A passionate life-long learner

    A complex thinker An effective communicator

    STATEMENT OF BELIEFS

    We believe that:

    The economic, political and societal success of ourcountry depends upon a quality education for all.

    Diversity strengthens the community and enriches thefabric of our society.

    It is the responsibility of the entire community topartner in the educational process.

    Learning occurs best in a safe, orderly and nurturingenvironment.

    Belonging to a family, to a school and to a community

    is vital, and this sense of belonging advances learning. People learn at different rates, have differentcapacities and that each persons educational pathdeserves to be valued equally.

    Learning empowers people to reach their fullpotential: physically, mentally, socially, andemotionally

    Everyone is a teacher, everyone is a learner.

    GRADUATE PROFILE

    Graduates of the Carrollton-Farmers Branch ISD are:

    Responsible individuals who: Model productive citizenship Practice successful personal management Demonstrate character values and ethical behavior Appreciate the value of diversity

    Function effectively as team members

    Competent learners who: Continually pursue and integrate knowledge Achieve academic standards Apply various forms of technology Seek educational and career options Produce quality products

    Complex thinkers who: Solve problems critically Create original ideas and solutions Understand and apply systems thinking

    Effective communicators who:

    Read with understanding Interpret information Interact through listening and speaking Write clearly

  • 8/3/2019 Country Place - Campus Improvement Plan 2011-2012

    5/15

    5

    TARGET AREAS

    Title I Targeted Assisted (TA)

    Must address the 8 components of a Targeted Assisted Program

    TA 1. Resources used to help children meet state academic achievement standardsTA 2. Planning for identified students incorporated into existing school planningTA 3. Methods and strategies based on scientifically based researchTA 4. TA program is coordinated with and supports regular educational programsTA 5. Highly qualified teachersTA 6. Professional DevelopmentTA 7. Increase parental involvementTA 8. Coordination of federal, state, and local services

    Title I School-wide Components (TS)

    TS 1. Comprehensive needs assessmentTS 2. School-wide reform strategiesTS 3. Highly qualified teachersTS 4. Professional developmentTS 5. Strategies to attract high-quality highly qualified teachers to high-need schoolsTS 6. Parental involvementTS 7. Assisting preschool children in the transition from early childhood programsTS 8. Measures to include teachers in the decisions regarding use of academic assessments.TS 9. Students difficulties identified on a timely basisTS 10. Coordination and integration between federal, state, and local services.

  • 8/3/2019 Country Place - Campus Improvement Plan 2011-2012

    6/15

    6

    THE GOAL OF THE CARROLLTON-FARMERS BRANCH ISD IS HIGH ACH IEVEMENT FOR ALL STUDENTS

    SUPPORTING OBJECTIVE 1 SUPPORTING OBJECTIVE 2 SUPPORTING OBJECTIVE 3 SUPPORTING OBJECTIVE 4

    CONTINUOUSLY INCREASE STUDENTACHIEVEMENT

    CONTINUOUSY IMPROVE THELEARNING ENVIRONMENT FOR

    STUDENTS AND STAFF

    CONTINUOUSLY INCREASEOPERATIONAL EFFECTIVENESS

    CONTINUOUSLY INCREASESTAKEHOLDER CONFIDENCE AND

    SUPPORT OF OUR SCHOOL SYSTEM

    Performance Targets:

    Academic Performance Index (API) STAAR Satisfactory STAAR Advanced

    Recognized/Exemplary DistinctionDesignationsAYP

    Performance Targets:

    Employee Job Satisfaction Campus Environment Curriculum and Instruction

    Student: Attendance Rate

    Disciplinary Placements

    Performance Targets:

    Staff Productivity Index (SPI)

    Performance Targets:

    Education Productivity Index (EPI) API SPI

    Parent Satisfaction

    Employee Campus Communications

    HIGH ACHIEVEMENT FOR ALL STUDENTS

  • 8/3/2019 Country Place - Campus Improvement Plan 2011-2012

    7/15

    THE GOAL OF THE CARROLLTON-FARMERS BRANCH ISD IS HIGH ACHIEVEMENT FOR ALL STUDENTSSUPPORTING OBJECTIVE 1 SUPPORTING OBJECTIVE 2 SUPPORTING OBJECTIVE 3 SUPPORTING OBJECTIVE 4

    CONTINUOUSLY INCREASE STUDENTACHIEVEMENT

    CONTINUOUSY IMPROVE THE LEARNINGENVIRONMENT FOR STUDENTS AND STAFF

    CONTINUOUSLY INCREASE OPERATIONALEFFECTIVENESS

    CONTINUOUSLY INCREASE STAKEHOLDERCONFIDENCE AND SUPPORT OF OUR SCHOOL

    SYSTEM

    7

    Supporting Objective 1 Continuously increase student achievement

    Performance Target: Academic Performance Index (API): STAAR Satisfactory; Recognized/Exemplary Distinction Designations; AYP

    ACTION STRATEGY PERSONRESPONSIBLE TIMELINEEVALUATION/

    MEASURE RESOURCESTITLE I

    COMPONENT

    Provide accelerated instruction for students identifiedas At Risk

    K. Ferris -PrincipalClassroomTeachers

    September -April

    Student DataClassroom observation

    District AssessmentsProgress MonitoringSTAAR

    Title 1Extra Duty Pay$1968.00

    Comp Ed Funds$67,331

    TA 4

    TA 5TA 8

    Utilize instructional specialists and coaches toeffectively implement curriculum

    K. Ferris -Principal

    September -May

    Unit AssessmentsSTAAR

    Title 1Instructional Staff

    $29,748.00

    TA 1TA 3TA 4TA 8

    Provide after school tutoring to accelerate learningfor all students demonstrating weakness in a corecurriculum area.

    K. Ferris PrincipalClassroomTeachers

    September -May

    Unit AssessmentsProgress ReportsReport CardsMAPUniversal ScreeningReading and Spellinginventories

    Tutorial materials forReading, Writing, Mathand Science.LLI KitsJourneysOrigo Kits

    TA 1TA 2TA 4TA 5

    Increase student awareness regarding personalphysical fitness

    P. Banner PE Teacher

    August May Fitnessgram Report

    PE Class timeCATCHHealth Lessons

    TA 1

    TA 4TA 7TA 8

  • 8/3/2019 Country Place - Campus Improvement Plan 2011-2012

    8/15

    THE GOAL OF THE CARROLLTON-FARMERS BRANCH ISD IS HIGH ACHIEVEMENT FOR ALL STUDENTSSUPPORTING OBJECTIVE 1 SUPPORTING OBJECTIVE 2 SUPPORTING OBJECTIVE 3 SUPPORTING OBJECTIVE 4

    CONTINUOUSLY INCREASE STUDENTACHIEVEMENT

    CONTINUOUSY IMPROVE THE LEARNINGENVIRONMENT FOR STUDENTS AND STAFF

    CONTINUOUSLY INCREASE OPERATIONALEFFECTIVENESS

    CONTINUOUSLY INCREASE STAKEHOLDERCONFIDENCE AND SUPPORT OF OUR SCHOOL

    SYSTEM

    8

    Supporting Objective 1 Continuously increase student achievement

    Performance Target: Academic Performance Index (API): STAAR - Advanced; Recognized/Exemplary Distinction Designations

    ACTION STRATEGY PERSONRESPONSIBLE

    TIMELINE EVALUATION/MEASURE

    RESOURCES TITLE ICOMPONENT

    Provide flexibility in scheduling to allow for verticalteam meetings to determine instructional gains andareas demonstrating gaps in learning.

    K. Ferris - PrincipalMath Coach &SpecialistReading Coach &Specialist

    OctoberDecemberFebruary

    Meeting minutesDeveloped plans ofaction

    SubstituteTeachers paidw/ localcampus funds

    TA 1TA 5TA 6TA 8

    Students participate in goal setting activities tomonitor their individual progress.

    Classroom Teachers October - May

    MAP results (2n & 5t )Progress Report gradesReport Card gradesUnit testsDistrict assessments

    Eagle E.Y.E.(Evaluating YourEfforts) time

    TA 1TA 3TA 4

    Analyze & monitor levels of questioning &classroom discourse.

    K. Ferris PrincipalClassroom TeachersInstructional Coaches October May

    Lesson PlansTeacher reflection &coaching conferenceBook study & articlereviews

    Book: Taxonomy for Learning RelatedProfessionalArticlesGT Curriculum

    TA 1TA 2TA 3TA 4TA 6

    Implement small group enrichment for Tier 1 students Classroom Teachers Daily On-going assessmentSTAAR resultsCurriculum &Library Materials

    TA 6TA 8TA 3

    Increase Academic Performance Index as reported onERG

    K. Ferris PrincipalClassroom Teachers August May ERG ranking ERG

    TA 1TA 2TA 8

  • 8/3/2019 Country Place - Campus Improvement Plan 2011-2012

    9/15

    THE GOAL OF THE CARROLLTON-FARMERS BRANCH ISD IS HIGH ACHIEVEMENT FOR ALL STUDENTSSUPPORTING OBJECTIVE 1 SUPPORTING OBJECTIVE 2 SUPPORTING OBJECTIVE 3 SUPPORTING OBJECTIVE 4

    CONTINUOUSLY INCREASE STUDENTACHIEVEMENT

    CONTINUOUSY IMPROVE THE LEARNINGENVIRONMENT FOR STUDENTS AND STAFF

    CONTINUOUSLY INCREASE OPERATIONALEFFECTIVENESS

    CONTINUOUSLY INCREASE STAKEHOLDERCONFIDENCE AND SUPPORT OF OUR SCHOOL

    SYSTEM

    9

    Supporting Objective 2 Continuously improve the learning environment for students and staff

    Performance Target: Employee: Job Satisfaction I would recommend this campus to a friend as a good place to work.

    ACTION STRATEGY PERSON RESPONSIBLE TIMELINE EVALUATION/MEASURE RESOURCESTITLE I

    COMPONENT

    Review Employee Opinion Survey with staff tomaintain 90%+ strongly agree/agree in this area. K. Ferris Principal October

    Compare 2011-2012Employee Opinion SurveyresultsStaff Feedback

    EmployeeOpinion Survey

    Time

    TA 1TA 8

    Supporting Objective 2 Continuously improve the learning environment for students and staff

    Performance Target: Employee: Campus Environment I would characterize my campus as having a positive attitude.

    ACTION STRATEGY PERSON RESPONSIBLE TIMELINE EVALUATION/MEASURE RESOURCESTITLE I

    COMPONENTReview Employee Opinion Survey with staffProvide questionnaire to determine areas of need andfocus in order to maintain 90%+ strongly agree/agree inthis area.

    K. Ferris Principal OctoberCompare 2011 with 2012Achieving Quality

    Together survey results

    EmployeeOpinion Survey

    TA 1TA 8

    Coordinate schedules to provide for campus-widerecognitions and celebrations honoringaccomplishments of students and staff members.

    K. Ferris PrincipalP. Banner PE TeacherK. Gilliland MusicTeacherT. Hardy Art Teacher

    August - May Input from Faculty,Students & ParentsFriend-Z Friday Assembly time

    TA 3TA 7TA 8

  • 8/3/2019 Country Place - Campus Improvement Plan 2011-2012

    10/15

    THE GOAL OF THE CARROLLTON-FARMERS BRANCH ISD IS HIGH ACHIEVEMENT FOR ALL STUDENTSSUPPORTING OBJECTIVE 1 SUPPORTING OBJECTIVE 2 SUPPORTING OBJECTIVE 3 SUPPORTING OBJECTIVE 4

    CONTINUOUSLY INCREASE STUDENTACHIEVEMENT

    CONTINUOUSY IMPROVE THE LEARNINGENVIRONMENT FOR STUDENTS AND STAFF

    CONTINUOUSLY INCREASE OPERATIONALEFFECTIVENESS

    CONTINUOUSLY INCREASE STAKEHOLDERCONFIDENCE AND SUPPORT OF OUR SCHOOL

    SYSTEM

    10

    Supporting Objective 2 Continuously improve the learning environment for students and staff

    Performance Target: Employee: Curriculum and Instruction Teachers work amicably together on common problems.

    ACTION STRATEGY PERSON RESPONSIBLE TIMELINE EVALUATION/MEASURE RESOURCESTITLE I

    COMPONENT

    Provide for Professional Learning Community

    participation in Language Arts, Math & Science.

    K. Ferris Principal Team Leaders InstructionalSpecialists

    Weekly

    PLC MeetingAgendasInformal

    conferences withfaculty &InstructionalSpecialists

    Scheduled Time

    TA 3TA 5TA 6TA 8

    Supporting Objective 2 Continuously improve the learning environment for students and staff

    Performance Target: Student: Attendance Rate

    ACTION STRATEGY PERSON RESPONSIBLE TIMELINE EVALUATION/MEASURE RESOURCESTITLE I

    COMPONENT

    Monitor student attendance each 9 weeks at SNAPmeetings in order to maintain an attendance rate of98% or above for all students and student groups.

    K. Ferris Principal Classroom Teachers Attendance Clerk

    Review each 9weeks or whenrequested by

    teacher

    AttendanceRecords

    ParentNotificationsAEIS ReportDistrictAttendanceofficer

    TA 4TA 7

    Provide extra-curricular opportunities to foster anddevelop student interests, talents & leadershipskills

    Activity Sponsors September May Attendance

    PTA sponsorshipStudent ActivityfundsSponsors.(Choir, StudentCouncil, Yearbook,Library LeadersSafety Patrol,Math

    Competition,Green Team)

    TA 1TA 4

  • 8/3/2019 Country Place - Campus Improvement Plan 2011-2012

    11/15

    THE GOAL OF THE CARROLLTON-FARMERS BRANCH ISD IS HIGH ACHIEVEMENT FOR ALL STUDENTSSUPPORTING OBJECTIVE 1 SUPPORTING OBJECTIVE 2 SUPPORTING OBJECTIVE 3 SUPPORTING OBJECTIVE 4

    CONTINUOUSLY INCREASE STUDENTACHIEVEMENT

    CONTINUOUSY IMPROVE THE LEARNINGENVIRONMENT FOR STUDENTS AND STAFF

    CONTINUOUSLY INCREASE OPERATIONALEFFECTIVENESS

    CONTINUOUSLY INCREASE STAKEHOLDERCONFIDENCE AND SUPPORT OF OUR SCHOOL

    SYSTEM

    11

    Supporting Objective 2 Continuously improve the learning environment for students and staff

    Performance Target: Student: Disciplinary Placements

    ACTION STRATEGYPERSON

    RESPONSIBLE TIMELINEEVALUATION/

    MEASURE RESOURCESTITLE I

    COMPONENT

    Provide opportunities for students to participate inCampus Counseling activities twice a month, weeklyR-Time activities and Morning Meetings each day.SOS (Save One Student)

    K. Ferris Principal ClassroomTeachers C. Oxner Counselor

    August May

    Attendance monitoredCode of Conduct ReferraldataR-Time & MorningMeeting documentation inlesson plansCounselors Schedule

    R-Time & MorningMeeting Materials

    TA 3TA 4

    Supporting Objective 3 Continuously increase operational effectiveness

    Performance Target: Staff Productivity Index (SPI)

    ACTION STRATEGYPERSON

    RESPONSIBLE TIMELINEEVALUATION/

    MEASURE RESOURCESTITLE I

    COMPONENT

    Examine campus staffing efficiency and makerecommendation(s) to Central Office

    K. Ferris Principal January March Staffing Cost Budget

    SBECPDASFocused Walk-ThroughsSummativeAppraisals

    TA 1

    Staff 100% of classrooms with Highly QualifiedTeachers during the 2011-2012 school year.

    K. Ferris Principal August May

    IndividualCertifications Personnel TA 5

  • 8/3/2019 Country Place - Campus Improvement Plan 2011-2012

    12/15

    THE GOAL OF THE CARROLLTON-FARMERS BRANCH ISD IS HIGH ACHIEVEMENT FOR ALL STUDENTSSUPPORTING OBJECTIVE 1 SUPPORTING OBJECTIVE 2 SUPPORTING OBJECTIVE 3 SUPPORTING OBJECTIVE 4

    CONTINUOUSLY INCREASE STUDENTACHIEVEMENT

    CONTINUOUSY IMPROVE THE LEARNINGENVIRONMENT FOR STUDENTS AND STAFF

    CONTINUOUSLY INCREASE OPERATIONALEFFECTIVENESS

    CONTINUOUSLY INCREASE STAKEHOLDERCONFIDENCE AND SUPPORT OF OUR SCHOOL

    SYSTEM

    12

    Supporting Objective 4 Continuously increase stakeholder confidence and support of our school system

    Performance Target: Education Productivity Index (EPI); API; SPI

    ACTION STRATEGY PERSONRESPONSIBLE TIMELINEEVALUATION/

    MEASURE RESOURCESTITLE I

    COMPONENT

    Build an awareness of EPI Ranking, API and SPIusing Educational Resource Group (ERG) data K. Ferris Principal September June

    Parent ConferenceschedulesPTA meetings

    NewslettersCampus Website

    ERG Data TA 7TA 8

    Supporting Objective 4 Continuously increase stakeholder confidence and support of our school system

    Performance Target: Parent SatisfactionACTION STRATEGY PERSON

    RESPONSIBLETIMELINE EVALUATION/

    MEASURERESOURCES TITLE I

    COMPONENTAchieve 100% PTA membership participation byfaculty and staff

    K. Ferris Principal September Golden Apple Award

    IndividualMembership Dues TA 7

    Achieve 100% participation in Parent/Teacherconferences

    ClassroomTeachers October

    Documented attendancerecord None TA 7

    Maintain or improve to 90%+ all responses of theparent survey Achieving Quality Together

    K. Ferris Principal Spring 2012

    Compare 2012 data with2011 results

    Achieving Quality Together Survey TA 7

    Provide parent awareness of campus educationalexpectations, STAAR assessment updates, andshare Best Practice strategies to use at homeduring scheduled PTA meetings, ParentOrientation and Family School Nights.

    K. Ferris PrincipalClassroomTeachers

    August May Sign In sheetsMeeting Agendas

    Title 1Parent Education$36.00 (Childcare)

    $34.00 (Meetingsnacks)

    TA 7

  • 8/3/2019 Country Place - Campus Improvement Plan 2011-2012

    13/15

    THE GOAL OF THE CARROLLTON-FARMERS BRANCH ISD IS HIGH ACHIEVEMENT FOR ALL STUDENTSSUPPORTING OBJECTIVE 1 SUPPORTING OBJECTIVE 2 SUPPORTING OBJECTIVE 3 SUPPORTING OBJECTIVE 4

    CONTINUOUSLY INCREASE STUDENTACHIEVEMENT

    CONTINUOUSY IMPROVE THE LEARNINGENVIRONMENT FOR STUDENTS AND STAFF

    CONTINUOUSLY INCREASE OPERATIONALEFFECTIVENESS

    CONTINUOUSLY INCREASE STAKEHOLDERCONFIDENCE AND SUPPORT OF OUR SCHOOL

    SYSTEM

    13

    Supporting Objective 4 Continuously increase stakeholder confidence and support of our school system

    Performance Target: Employee: Campus Communication School has system of communication thats open, regular and honest

    ACTION STRATEGY PERSON RESPONSIBLE TIMELINE EVALUATION/MEASURE RESOURCESTITLE I

    COMPONENT

    Determine areas of instructional needs basedon Reading, Writing, Math and Science dataas well as maintain a positive and productivework environment amongst faculty and staffmembers.Receive Employee Opinion Survey TeamFeedback Review Employee Opinion Survey results

    K. Ferris Principal

    Grade LevelFacilitatorsCampus LeadershipTeam

    November,February or as

    needed based onfaculty request.

    Sign-In sheetsAgendasTeam Meetings

    Squeaky BeaksMeetingsWeek at a PiqueSOAR Time(Strengthening ourAcademic Rigor)

    AEIS report

    EdugenceData TA 5TA 6

  • 8/3/2019 Country Place - Campus Improvement Plan 2011-2012

    14/15

    THE GOAL OF THE CARROLLTON-FARMERS BRANCH ISD IS HIGH ACHIEVEMENT FOR ALL STUDENTSSUPPORTING OBJECTIVE 1 SUPPORTING OBJECTIVE 2 SUPPORTING OBJECTIVE 3 SUPPORTING OBJECTIVE 4

    CONTINUOUSLY INCREASE STUDENTACHIEVEMENT

    CONTINUOUSY IMPROVE THE LEARNINGENVIRONMENT FOR STUDENTS AND STAFF

    CONTINUOUSLY INCREASE OPERATIONALEFFECTIVENESS

    CONTINUOUSLY INCREASE STAKEHOLDERCONFIDENCE AND SUPPORT OF OUR SCHOOL

    SYSTEM

    14

    ERG Performance Index 2010 Rank 2011Target

    2011 Rank 2012Target

    2012 Rank

    Education Productivity Index(EPI) 91 75

    Academic Performance Index(API) 107 65

    Staff Productivity Index (SPI) 101 95

    Employee Opinion Survey 2011Result

    2012Target

    2012Result

    Employee Job Satisfaction I would recommend this campus to a friend as a good place to work.

    90% 92%

    Employee Campus Environment I would characterize my campus as having a positive atmosphere.

    91% 95%

    Employee Curriculum and InstructionSupport Teachers work amicably together on common problems.

    100% 100%

    Employee Campus Communication School has system of communication thats open, regular and honest.

    83% 90%

    AEIS 2011 Result 2012 Target 2012Result

    Campus Rating EXEMPLARY EXEMPLARY*

    Student Attendance Rate 97.3% 98%Students with Disciplinary Placements .005% 1%

    RESULTS - 2012PROGRESS TOWARD TARGETS

    # of Targets Met

    # of Targets Not Met

    Percent at Target

    ADEQUATE YEARLY PROGRESS (AYP)C-FBISD Met AYP

    2008 Yes

    2009 Yes

    2010 Yes

    2011 Yes

    Target 2012 YES

    Results 2012Achieving Quality Together (Parent Survey) 2011Result 2012 Target 2012 Result

    Very Satisfied or Satisfied with District Campus 94% 95%

  • 8/3/2019 Country Place - Campus Improvement Plan 2011-2012

    15/15

    THE GOAL OF THE CARROLLTON-FARMERS BRANCH ISD IS HIGH ACHIEVEMENT FOR ALL STUDENTSSUPPORTING OBJECTIVE 1 SUPPORTING OBJECTIVE 2 SUPPORTING OBJECTIVE 3 SUPPORTING OBJECTIVE 4

    CONTINUOUSLY INCREASE STUDENTACHIEVEMENT

    CONTINUOUSY IMPROVE THE LEARNINGENVIRONMENT FOR STUDENTS AND STAFF

    CONTINUOUSLY INCREASE OPERATIONALEFFECTIVENESS

    CONTINUOUSLY INCREASE STAKEHOLDERCONFIDENCE AND SUPPORT OF OUR SCHOOL

    SYSTEM

    15

    Supporting Objective 1 Continuously increase student achievement

    READING/ELAREADING/ELA 2011 2012 2011 2012

    Student Group % PASS% SATIS % COM % ADVTarget Result Target Result

    Afr. American 100 100 50 60Hispanic 98 100 47 55White 100 100 64 75Econ. Dis. 100 100 48 55LEP 93 100 43 50G/T 100 100 95 100Special Ed 100 100 23 30All Students 100 100 57 65

    WRITINGWRITING 2011 2012 2011 2012

    Student Group % PASS% SATIS % COM % ADVTarget Result Target Result

    Afr. American 100 100 20 100Hispanic 100 100 50 60White 100 100 25 75Econ. Dis. 95 100 38 50LEP 86 100 14 20G/T 100 100 73 100Special Ed 100 100 0 50All Students 99 100 29 60

    SOCIAL STUDIESSOCIAL STUDIES 2011 2012 2011 2012

    Student Group % PASS% SATIS % COM % ADVTarget Result Target Result

    Afr. AmericanHispanicWhiteEcon. Dis.LEPG/TSpecial EdAll Students

    MATHEMATICSMATHEMATICS 2011 2012 2011 2012

    Student Group % PASS% SATIS % COM % ADVTarget Result Target Result

    Afr. American 94 100 50 65Hispanic 100 100 51 65White 100 100 65 75Econ. Dis. 100 100 66 75LEP 100 100 57 70G/T 100 100 94 100Special Ed 100 100 48 60All Students 99 100 63 75

    SCIENCESCIENCE 2011 2012 2011 2012

    Student Group % PASS% SATIS % COM % ADVTarget Result Target Result

    Afr. American 100 100 60 75Hispanic 89 100 48 60White 100 100 70 80Econ. Dis. 90 100 57 70LEP * 100 * 50G/T 100 100 100 100Special Ed 86 100 21 50All Students 95 100 59 75

    RESULTS - 2012PROGRESS TOWARD TARGETS

    SATISFACTORY ADVANCED# of Targets Met

    # of Targets Not Met

    Percent at Target