Cost of Service study for the Swaziland Electricity Supply ... · • Tunisia: Model power purchase...
Transcript of Cost of Service study for the Swaziland Electricity Supply ... · • Tunisia: Model power purchase...
ECONOMICCONSULTINGASSOCIATES
www.eca-uk.com
Cost of Service study for the Swaziland Electricity Supply Industry
Final Workshop
27 September 2018
2
Content
Introduction and project overview
Demand forecast
Generation, transmission and distribution
least cost plan
SEC Revenue Requirements (Average tariff)
SEC Cost of Electricity Supply by customer
class
End-user tariffs and transition plan
Cost of Service study for the Swaziland Electricity Supply Industry
Section 1 Introduction and project overview
Section 2 Demand forecastSection 3 Generation, transmission and distribution least cost plan Section 4 SEC Revenue Requirements (average tariff)Section 5 SEC Cost of SupplySection 6 End-user tariffs and transition plan
4
We are worldwide infrastructure economic consultants specialising in the energy sector
ECA provides economic consulting advice in infrastructure services for utilities,
investors, regulators, and governments worldwide
40+Utilities and
regulators advised
65+Countries worked
in
20 yearsin business
23Consultants
60+ assignments
annually
15+ years average
experience
100%Employee owned
£6mAnnual
turnover
4Regional
representations
5
We specialise in providing economic and financial advice to energy utilities and regulators
Tariff studies and
regulatory methodologies
• Malawi and Zambia: Cost of service and tariff study
• Australia: Regulatory modelling of electricity networks
• Greece: Electricity network pricing study
• Southern Africa: Regional generation and transmission plan (SAPP)
• Papua New Guinea: Action plan for electricity grid expansion
• Malawi: Integrated Resource Plan (IRP) study
• Indonesia: Cost of service and financial impact study for PLN
• Vietnam: Economic and financial analysis of the power sector master plan
• Iraq (KRG): Private sector participation in transmission investments
• Mongolia: Renewable energy regulatory development roadmap
• Pacific: IFC guide to investing in RE power generation
• Croatia: Analysis of network’s wind power capacity and investment plan
❶
Power development and
least cost plans
Financial planning and
analysis❸
Integration of renewables❹
❷
6
We specialise in providing economic and financial advice to energy utilities and regulators
• Tunisia: Model power purchase agreement
• Kenya: Karura hydropower plant feasibility study
• Nigeria: Electricity DISCO privatisation due diligence
• George: Energy trading platform
• Ireland: I-SEM market monitoring strategy
• Ukraine: Intraday market rules development
• Oman: Electricity load forecasting model
• Egypt: Development of a load management program
• Armenia: Demand-side management study
• Cambodia: Rural electrification strategy and implementation plan
• Papua New Guinea: National electrification masterplan
• Ethiopia: Electrification program prospectus
Investments and power
purchase agreements❺
Market design and
operation❻
Rural electrification and
off-grid technologies❽
❼Load forecasts and
demand-side management
7
Project objectives and organisation of tasks
Project objectives
⚫ Develop a least cost plan
for generation,
transmission, distribution
and supply
⚫ Estimate SEC Revenue
Requirements (average
tariff)
⚫ Estimate the Cost of
Supply
⚫ Estimate End User tariffs
and the need to cater for
needy consumers
⚫ Develop a transition
strategy to move to cost
reflective tariffs
8
Work plan and deliverables
No Deliverable
1 Inception report
2 Report on the Revenue Requirement
3 Report on Medium-Long-term Least-cost plan
4 LRMC report
5 Report of transition strategy
6 Report on Recommendation for Future Studies
7 Draft report on electricity costs of service
8 Final report
9 Required Revenue model
10 LRMC and RS models 23
19
19
22
24
23
Due
end of
4
12
12
16
No Deliverable
W I Workshop 1: Task 1
W II Workshop 2: Tasks 2-4
WIII Workshop 3: Tasks 5-6
W IV Workshop 4: Final report
Current position
Cost of Service study for the Swaziland Electricity Supply Industry
Section 1 Introduction and project overview
Section 2 Demand forecast
Section 3 Generation, transmission and distribution least cost plan Section 4 SEC Revenue Requirements (average tariff)Section 5 SEC Cost of SupplySection 6 End-user tariffs and transition plan
10
SEC’s 2017 demand forecast was adopted for the Cost of Supply study (CoSS)
Peak demand forecast
⚫ From 242 MW in 2017 to 334 MW in 2035
⚫ Average annual growth rate 1.9%
Energy demand forecast
⚫ From 1,358 GWh in 2017 to 1,852 GWh in
2035
⚫ Average annual growth rate 1.8%
Main facts
⚫ The country’s economy was on downward
trend since 2014
⚫ There were no big projects developed
since 2014 and the only growth in energy
demand is attributable to expansion of
sugar cane fields
⚫ The rural electrification programe has
marginal impact on the overall energy
demand.
242 259 285316 334
050
100150200250300350400
201
7-1
82
01
8-1
92
01
9-2
02
02
0-2
12
02
1-2
22
02
2-2
32023-2
42
02
4-2
52
02
5-2
62
02
6-2
72
02
7-2
82
02
8-2
92
02
9-3
02
03
0-3
12
03
1-3
22
03
2-3
32
03
3-3
42
03
4-3
52
03
5-3
6
MW
Peak demand likely (sent-out) MW
1,358 1,4521,601
1,776 1,872
0
500
1,000
1,500
2,000
2,500
201
7-1
8
201
8-1
9
201
9-2
0
202
0-2
1
202
1-2
2
202
2-2
3
202
3-2
4
202
4-2
5
202
5-2
6
202
6-2
7
202
7-2
8
202
8-2
9
202
9-3
0
203
0-3
1
203
1-3
2
203
2-3
3
203
3-3
4
203
4-3
5
203
5-3
6
GW
h
Energy demand likely (sent-out) GWh
Cost of Service study for the Swaziland Electricity Supply Industry
Section 1 Introduction and project overviewSection 2 Demand forecast
Section 3 Generation, transmission and distribution least cost plan
Section 4 SEC Revenue Requirements (average tariff)Section 5 SEC Cost of SupplySection 6 End-user tariffs and transition plan
12
Currently SEC is heavily dependent on imports
Total domestic available
generation capacity for grid
supply is 72.5 MW. Total domestic
generation capacity is 141 MW.
⚫ 43% hydro generators,
⚫ 56% biofueled power plants,
⚫ 2% is thermal
Approximately 85% of energy is
covered by imports
Main issues for Swaziland
⚫ Security of supply
⚫ Price taker – electricity prices
depend significantly on import costs
Government’s plan is to increase
domestic generation capacity
13
Domestic committed and candidate power plants
Plant Name Status Owner Type Fuel
Installed
capacity(MW)
Available
Capacity (MW) Lifetime
Year
avail.
Lower Maguduza Committed Private Hydro Hydro 13.6 13.6 50 2021
Ngwempisi Candidate SEC Hydro Hydro 80 80 50 2027
Small hydro Candidate SEC Hydro Hydro 1.9 1.9 50 2021
Mpaka 1-6 Candidate SEC
Subcritical
Steam Coal6x50 6x42.5 30 2025-27
RSSC Mhlume Candidate RSSC
Subcritical
Steam Bagasse50 28 25 2024
RSSC Simunye Candidate RSSC
Subcritical
Steam Bagasse50 22 25 2022
USL Bagasse Candidate USL
Subcritical
Steam Bagasse25 15 25 2021
Usuthu Saw Mills Candidate IPP
Subcritical
Steam Woodchip37 33 25 2020
Lavumisa Candidate SEC Solar PV Solar 10 10 25 2020
AES Solar PV Candidate SEC Solar PV Solar 10 10 25 2020
SPL Solar PV Candidate SEC Solar PV Solar 10 10 25 2020
Generic OCGT Candidate Private OCGT HFO 30 30 25 2020
14
Bagasse and small hydros are the least cost options for base load (excluding imports)
PVBagasse
OCGT Woodchip
Mpaka
Ngwempisi
Levelised Costs of Electricity Screening analysis
15
Least cost options
Scenario Description NPV
Capex
(mUS$)
NPV
Fixed
O&M
(mUS$)
NPV
Variable
(mUS$)
NPV Total
(mUS$)
Rank Total costs
/ Energy
served
(US$/MWh)
Scenario 1 No new capacity 0 272 649 920 2 31.0
Scenario 2 Small Hydros 3 273 645 920 1 31.0
Scenario 3 PV + Small Hydros 30 275 624 930 3 31.3
Scenario 4Bagasse + Small Hydros
76 293 580 949 6 31.9
Scenario 5OCGT30 + Small Hydros
25 278 638 941 5 31.7
Scenario 6OCGT 2x30 + Small Hydros
25 278 630 934 4 31.4
Scenario 7PV+ Bag + Small Hydros
103 295 560 958 8 32.2
Scenario 8PV + OCGT + Small Hydros
53 281 617 950 7 32.0
Scenario 9 Mpaka 1 + Small Hydros 80 283 605 969 10 32.6
Scenario 10 Ngw + Small Hydros 312 276 587 1,174 11 39.5
Scenario 11 Full Independence 1 445 346 429 1,220 12 41.0
Scenario 12 Full Independence 2 590 326 418 1,333 13 44.9
Scenario 13 Partial Independence 103 295 560 958 8 32.2
Base case
least cost
Full independence
case least cost
Partial
dependence case
16
Generation least cost options
Full independence –
15% reserves margin
by 2025
Partial dependence –
develop domestic PV
and Bagasse
Base case – without
any constraints to
imports
• Lavumisa, AES and SPL
Solar PV in 2020 (30 MW)
• OCGT in 2020 (60 MW)
• USL Bagasse in 2021 (15
MW)
• Small Hydros in 2021 (1.9
MW)
• RSSC Simunye in 2024 (22
MW)
• Mpaka 1,2,3 in 2025 (150
MW)
• Mpaka 4 in 2028 (50 MW)
• Lavumisa, AES and SPL
Solar PV in 2020 (30 MW)
• USL Bagasse in 2021 (15
MW)
• Small Hydros in 2021 (1.9
MW)
• RSSC Simunye in 2024 (22
MW)
• Develop small hydros
earliest year possible
(Lusushwana River,
Mpuluzi River, Great
Usuthu River, Mbuluzi
River, Lubovane Dam)
• Imports cover most of
demand requirements.
NPV = mUS$ 920 NPV = mUS$ 958 NPV = mUS$ 1,220
17
Transmission constraints – Key findings
Main projects addressing key constraints on the existing grid
North-east grid 66 kV reinforcement 132 kV line Moses Hlope – Sihhoye T
Edwaleni PS 66 kV reinforcement 132/66 kV substation extension linking
Edwaleni PS and the 400/132 kV subst.
Stonehenge N-1 reinforcement 132 kV line Edwaleni II – Stonehenge
South-east grid 66 kV reinforcement 132 kV line Sithobela – Ncandweni
Furthermore, several large projects with new transmission lines are
required to support rural electrification
18
Transmission development plan
Transmission Network
Expansion
2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 Total
Cost
1 Ongoing Projects 0.9 0.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.7
2Substation transformer
uprating4.7 1.6 0.7 0.0 0.0 0.0 0.9 0.0 6.1 2.8 0.0 0.0 0.0 16.8
3Substation upgrade
projects2.5 4.2 6.9 3.3 0.7 1.1 0.0 1.4 2.3 0.0 0.0 0.0 0.0 22.4
4Subst. transformer
maintenanceCosts included as part of general Operation and Maintenance costs. -
5 Network reinforcement projects 98.7
5.1 HV Network 9.2 13.8 3.2 4.8 0.0 0.0 5.8 8.7 0.0 0.0 0.0 0.0 0.0 45.5
5.2 Rural Electrification 6.5 9.8 1.7 2.5 3.2 4.8 0.0 6.3 9.4 0.0 0.0 0.0 0.0 44.2
5.3 New Loads (excl.
customer contribution)2.3 3.5 0.0 0.0 1.3 1.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 9.1
6Transmission reliability
projects2.0 3.0 1.2 0.9 0.7 1.5 1.7 1.8 0.8 0.0 0.0 0.0 0.0 13.6
7 SCADA 0.2 0.1 0.1 0.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.5
8Reactive power
compensation0.0 0.0 4.0 0.0 4.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 8.0
Total 28.3 36.9 17.7 11.6 9.8 9.3 8.4 18.2 18.7 2.8 0.0 0.0 0.0 161.7
19
Distribution least cost plan
Key findings
⚫ Most feeders on the distribution
system are lightly loaded
Some thermal constraints
need to be addressed
⚫ Long feeders in some areas
cause excessive voltage drop
⚫ Improving reliability in some
areas seems justified
New in-feeds and
strengthening of the system
required to
⚫ address these constraints
⚫ increase electrification ratio
Distribution least cost plan
Cost of Service study for the Swaziland Electricity Supply Industry
Section 1 Introduction and project overviewSection 2 Demand forecastSection 3 Generation, transmission and distribution least cost plan
Section 4 SEC Revenue Requirements (average tariff)
Section 5 SEC Cost of SupplySection 6 End-user tariffs and transition plan
21
What is Tariff level (cost-recovery) and Tariff design (cost-reflectivity)?
Electricity tariffs have two main
aspects
1. Tariff level
The average level of tariff determined
by the Required Revenues.
2. Tariff design
Customer categories
Type of charges
Ratios of charges between customer
categories and ratios of charges
within each category.
The tariff structure (i.e. ratios
among charges) can be kept
constant to reflect economic costs
while the tariff level can be scaled
to ensure revenue recovery.
“Cost-recovery”
Revenues from tariffs fully recover
efficient costs (Required Revenues)
Cost-recovery ≠ Cost-reflective
Co
st
of
Se
rvic
e
Avg
Co
sts
Co
st
of
Se
rvic
e
Customer A Customer B
“Cost-reflective”
The tariffs charged to different customers
reflect differences in the costs of service
between those customers
22
Revenue Requirements model are estimated using SERA’s tariff methodology
Asset base
Historic asset
base
Capital
expenditures
DepreciationAsset lives
Return (‘profit’)
Operating
expenditures
+
+
Cost of debt
Return on equity
Gearing
(debt/equity)Allowed Revenues
=
Cost of capitalx
Building Blocks model
23
Overall revenue requirement increases by an average of 4.1% per year
All figures presented in
2018 real terms (i.e.
excluding inflation)
Power Purchase costs
contribute most to the
revenue requirement
⚫ mE 1,139 in 2018-19
⚫ Followed by distribution
(mE 500) and transmission
(mE 291)
Highest annual average growth rate forecast in transmission
costs (10.7%)
⚫ Followed by power purchase costs (4.6%)
24
Tariffs are expected to increase by an average of 0.97% annually
Average annual tariff first increases and then decreases over the
forecast period
⚫ From 1.86 E/kWh in 2018-19 to 2.02 E/kWh in 2020-21 and then to 1.92
E/kWh in 2022-23
⚫ Tariff increase is mainly attributed to growing power purchase costs and
transmission investment costs.
25
Generation costs contribute to 60% of total tariffs
0.94 0.98 1.03 0.99 0.98
0.00
0.50
1.00
1.50
2.00
2.50
2018-192019-202020-212021-222022-23
E/k
Wh
Generation average tariff Transmission average tariff
0.23 0.28 0.31 0.31 0.30
0.00
0.50
1.00
1.50
2.00
2.50
2018-192019-202020-212021-222022-23
E/k
Wh
0.51 0.50 0.49 0.47 0.45
0.00
0.50
1.00
1.50
2.00
2.50
2018-192019-202020-212021-222022-23
E/k
Wh
Distribution average tariff Contribution to total
26
Alternative generation investment scenarios impact tariff levels
Partial independence case
⚫ Tariffs are expected to grow
from 1.86 to 1.92 E/kWh
⚫ Average annual growth rate
0.97%
Full independence case
⚫ Tariffs are expected to grow
from 1.86 to 1.94 E/kWh
⚫ Average annual growth rate 1.25%
Least cost case
⚫ Tariffs are expected to grow from 1.86 to 1.88 E/kWh
⚫ Average annual growth rate 0.43%
Cost of Service study for the Swaziland Electricity Supply Industry
Section 1 Introduction and project overviewSection 2 Demand forecastSection 3 Generation, transmission and distribution least cost plan Section 4 SEC Revenue Requirements (average tariff)
Section 5 SEC Cost of Supply
Section 6 End-user tariffs and transition plan
28
Economically efficient pricing requires marginal cost based tariffs
Economically efficient or cost-
reflective pricing requires that the
tariff paid by a customer should
be equal to the marginal costs of
supply of that customer. If this is
not the case, then the outcome is
inefficient.
Tariff below marginal cost
⚫ It costs SEC more to meet an increase
in demand from that customer than the
corresponding revenue that it will earn.
⚫ The result is to force SEC into losses or
for it to refuse to meet demand.
Tariff above marginal cost
⚫ A customer must pay more for an
increase in demand than it costs SEC
to supply that increase.
⚫ The implication is that customers will
cap their demand at a point below that
where it is still profitable for SEC to
meet demand growth. Tariff > Marginal cost
Tariff = Marginal cost
Tariff < Marginal cost
Quantity
Tariff/Cost
Customer demand curve
Losses to SEC (customer supplied at
price below cost)
customers cap their demand where it is still
profitable for SEC to meet demand growth Marginal cost
curve
29
What are the efficient price signals to consumers based on the cost of supplying an extra unit of energy?
To do this, we derive long-run marginal costs of capacity
and energy for generation and networks for the system.
Network losses are also taken into account to estimate the
costs at the delivery points of the HV, MV and LV networks.
Then we estimate the long-run marginal costs of supply for
each customer class.
30
Seasonal pattern of generation long
run marginal costs (USc/kWh)
Cost of supply is higher between mid-June and mid-August
The highest Marginal Costs are
observed between mid-June and
mid-August.
Marginal Costs during February,
March and April have an
increasing trend over years.
Two tariff seasons can be
identified:
⚫ High Cost Season – starting
from June and ending in August.
⚫ Low Cost Season – starting from
September and ending in May.
2021
2022
31
Cost of supply in the morning and in the evening is higher than other times
c/kW
h SRMC for an average day
Hig
h S
eas
on
Lo
w S
eas
on
Marginal costs of energy
during High Season Peak
hours are 7 time more those
for off-peak hours.
Marginal costs of energy
during Low Season Peak
hours are double than
those for off-peak hours.
Customers with high demand
during peak hours have a
higher cost of supply.
32
Customers with more ‘peaky’ demand have a higher marginal cost of service
Morning peak
Eveningpeak
33
What is the cost of supply by customer class?
Residential customers have the
highest cost of supply
The cost of supply of Commercial,
Large Commercial and Industrial
and TOU LV
Irrigation customers have LRMCs
that are 20% below average
TOU MV customers have LRMCs
that are 30% - 40% below average
34
What would be a cost reflective tariff design on 2016-17 tariffs?
Domestic customers paid 0.8
E/kWh less than their cost
reflective level. For cost
reflectivity, their tariff should
increase by 66%.
Customers in classes S3 and
K5 paid 0.5-0.7 E/kWh more
than their cost reflective level.
For cost reflectivity S3 should
be paying 33-35% less and
class K5 should be paying
25% less.
LV TOU customers paid 0.4
E/kWh more than their scaled
total LRMC. For cost
reflectivity, they should pay
22% less.
Actual 2016-17 tariffs
Cost-reflective 2016-17 tariffs
35
What would be a cost reflective tariff design on 2016-17 tariffs?
MV TOU and HV TOU
supplied at MV customers
paid 0.4 and 0.7 E/kWh
more than their scaled total
LRMC. For cost reflectivity,
they should pay 26% less
and 43% less.
Irrigation customers pay
approximately the same
rate as their scaled total
LRMC. Customers in class
K6 and T4 paid 0.4-0.5
E/kWh more than their
scaled total LRMC. For
cost reflectivity, K6 should
pay 26% less and T4 30%
less.
Actual 2016-17 tariffs
Cost-reflective 2016-17 tariffs
36
Proposed changes to the tariff structure
SEC may consider
⚫ Merging the General Purpose with Small Commercial tariff class to simplify the
tariffs.
⚫ Introduce TOU capacity charges.
Demand charges apply equally to all periods - no incentive to consumers to shift
their demand away from peak.
⚫ Drop the Access charge and recover the equivalent revenue through the demand
charge.
⚫ Rebalance the ratio of charges to enhance cost-reflectivity
Facility charge to reflect costs of retail activities
Demand charge to reflect capacity costs
Energy charge to reflect energy generation costs.
⚫ Allow domestic customers to LV TOU tariff if they are willing to pay the extra costs of
TOU meter.
⚫ Eliminate cross-subsidies and target subsidies only to needy consumers (Subsidy
Framework)
Cost of Service study for the Swaziland Electricity Supply Industry
Section 1 Introduction and project overviewSection 2 Demand forecastSection 3 Generation, transmission and distribution least cost plan Section 4 SEC Revenue Requirements (average tariff)Section 5 SEC Cost of Supply
Section 6 End-user tariffs and transition plan
38
Overall Approach
39
How would cost-reflective and cost-recovering end-user tariffs look in 2019? (including the Subsidy Framework)
Tariff category Facility
charge
Energy charge Demand
charge
Total
average
Total
averageSingle rate ToU
High Season Low season
Peak Shoulder Off-peak Peak Shoulder Off-peak 2019-20 2018-19
estimate
E/customer/
month E/kWh E/kWh E/kWh E/kWh E/kWh E/kWh E/kWh
E/kVA/
month E/kWh E/kWh
S10 Lifeline - pre-pay
-
(0-75 kWh) 1.708
- - - - - - - 1.708 1.653(75-150 kWh) 2.846
(>150 kWh) 4.554
S1 Domestic - pre-pay - 2.903 - - - - - - - 2.903 1.750
S3 Small Commercial -
pre-pay 64.6 1.712 - - - - - - - 1.838 2.809
S3 Small Commercial -
Credit Meter 61.5 1.768 - - - - - - - 1.810 2.683
K4 Small Holder
Irrigation 61.5 0.397 - - - - - - 772.0 1.532 1.395
K5 Large Commercial
and Industrial 307.5 0.517 - - - - - - 609.2 1.834 1.882
K6 Large Irrigation 307.5 0.520 - - - - - - 790.7 1.694 1.586
T4 TOU small irrigation
< 100 kVA 307.5 - 2.240 0.565 0.308 0.636 0.376 0.267 772.0 1.597 1.616
T3 TOU at LV 307.5 - 2.297 0.622 0.365 0.692 0.433 0.323 609.2 1.809 1.988
T2 TOU at MV 615.0 - 2.163 0.598 0.352 0.654 0.417 0.312 520.8 1.473 1.789
T1 TOU at MV at HV
network 615.0 - 2.080 0.583 0.344 0.631 0.407 0.305 457.5 1.193 1.693
S0 Street light 61.5 2.729 - - - - - - - 2.739 0.862
Average 2.064 1.914
40
What would be the impact from the introduction of cost-reflective and cost-recovering tariffs?
Most significant changes would be
for category S1 both in terms of the
tariff increase (doubling of the tariff)
and the number of customers
affected.
All other customers would see
decreases with most significant
decreases for T1 and S3.
The tariff redesign provides
information on what the tariffs should
be if pure economic principles of cost
reflectivity were to apply.
Next step is to:
⚫ Develop a transition strategy
from the current tariffs to cost-
reflective and cost-recovering
tariffs.
Existing against cost-reflective and cost
recovering-tariffs in 2019-20
41
Gradually increase tariffs that require increasesKeep constant tariffs that require decreases
SERA could consider the
following steps to gradually
introduce cost-reflective
and cost-recovering tariffs:
⚫ Tariff increases could be
gradually absorbed in the
next years.
⚫ Consumers tariffs that pay
more in comparison to their
cost reflective levels could be
kept constant over the next
four years until the tariff of
each customer category
reaches its cost reflective
tariff level.
⚫ Revenue for SEC recovery
should be ensured through
this period
Tariff category Forecast Forecast Forecast Forecast
2019-20 2020-21 2021-22 2022-23
Forecast inflation 6.1% 6.4% 5.5% 5.5%
Increase/Decrease (%)
S10 Lifeline - pre-pay 3.3% 10.8% 2.4% 3.4%S1 Domestic - pre-pay 25.4% 27.8% 3.9% 5.6%S3 Small Commercial -
pre-pay0.0% 0.0% 0.0% 0.0%
S3 Small Commercial -Credit Meter
0.0% 0.0% 0.0% 0.0%
K4 Small Holder Irr. 9.8% 11.3% 2.4% 3.5%
K5 Large Commercial and Industrial
0.0% 8.2% 2.4% 3.4%
K6 Large Irrigation 6.8% 11.1% 2.4% 3.4%T4
TOU small irrigation 0.0% 9.9% 2.4% 3.4%
T3 TOU at LV 0.0% 1.2% 2.4% 3.4%T2 TOU at MV 0.0% 0.0% 0.0% 0.0%T1 TOU at MV at HV
network0.0% 0.0% 0.0% 0.0%
S0 Street light 39.1% 39.1% 39.1% 39.1%
Tariffs above cost reflective level kept constant
Cost reflectivity achieved tariffs follow average cost
increases
Tariffs that require significant tariff
increases to achieve cost reflectivity
Adjusted tariff increases to
moderate impact
ECONOMICCONSULTINGASSOCIATES
www.eca-uk.com
Peter Robinson <[email protected]>
Grigorios Varympopiotis <[email protected]>
Andrew Tipping<[email protected]>
Marta Chojnowska <[email protected]>
43
Annex 1 – Description of generation scenarios
Scenario Candidate power plants Details / Comments
Scenario 1 No new capacity This scenario assumed that no new domestic power plants will be developed and checks system costs
with full dependency on imports from ESKOM/SAPP.
Scenario 2 Small hydros Scenario to check if the inclusion of small hydro power plants can reduce system costs.
Scenario 3 Solar PV and Small hydros Candidate solar PV power plants together with small hydro power plants were included in the simulations.
Solar PV power plants are likely to generate power during the morning and evening hours (ESCOM
Peak), and midday hours (ESCOM Standard). Benefits may appear if the savings from variable costs from
ESCOM imports are higher than the capital costs from the introduction of PVs.
Scenario 4 Bagasse and Small hydros Bagasse fired power plants operating at very high capacity factors could economically displace Standard
and Peak ESKOM imports. This scenario examines if operating benefits from the inclusion of bagasse
power plants could outweigh investment costs for the development of the bagasse power plants.
Scenario 5 30 MW OCGT and Small hydros This scenario checks if the inclusion of 30 MW OCGT HFO power plant could economically displace
imports during peak hours.
Scenario 6 2 x 30 MW OCGT and Small
hydros
This scenario checks if the inclusion of 60 MW OCGT HFO power plant could economically displace
imports during peak hours.
Scenario 7 Solar PV and Bagasse and Small
hydros
This scenario is a combination of scenarios 3 and 4. This scenario examines if the combination of
bagasse (for base load) and solar PV could produce higher benefits than scenarios 3 and 4 on their own.
Scenario 8 Solar PV and 30 MW OCGT and
Small hydros
This scenario is a combination of scenarios 3 and 5. This scenario examines if the combination of OCGT
(for peak load) and solar PV (for base load) could produce higher benefits than scenarios 3 and 5 on their
own.
Scenario 9 Mpaka 1 (1 x 50 MW) and Small
hydros
Coal fired power plants operating at very high capacity factors could economically displace Standard and
Peak ESKOM imports. This scenario examines if operating benefits from the inclusion of coal power
plants could outweigh investment costs for the development of the Mpaka power plant.
Scenario 10 Ngwempisi and Small hydros Scenario to check if the inclusion of Ngwempisi hydro power plants can reduce system costs. Benefits
may be introduced from the displacement of expensive imports during peak hours.
Scenario 11 Full independence option 1 This scenario requires 15% reserves margin from domestic resource from 2025. To achieve this, Mpaka
1-3 (3 x 50 MW), Small hydros, Solar PV and 30 MW OCGT will have to be developed.
Scenario 12 Full independence option 2 This is an alternative to scenario 11 to achieve full independence. This scenario requires 15% reserves
margin from domestic resource from 2025. To achieve this, Mpaka 1 (50 MW), Ngwempisi, Small hydros,
Solar PV and 30 MW OCGT will have to be developed.
Scenario 13 Partial independence The investment costs under the full independence scenario are expected to be very high. Hence this
scenario checks the costs of an intermediate strategy that has partial dependence on imports rather than
almost full independence. This scenario reflects Governments position to develop domestic PV (up to 40
MW) and Bagasse (up to 40 MW) generation.