Cost Estimation
2009
![Page 2: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/2.jpg)
Cost Estimation
• “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic.
» Norman R. Augustine
![Page 3: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/3.jpg)
Goal
• The cost estimation community is working to improve estimations so that sophisticated organizations can produce products with 5% of the estimated cost (instead of 10%).
![Page 4: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/4.jpg)
Requirements for Estimations
• What are cost estimates used for?
![Page 5: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/5.jpg)
Requirements for Estimations
• What are cost estimates used for?• What are the important characteristics of a
cost estimate?
![Page 6: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/6.jpg)
Scenario
• A typical software development shop. A boss is speaking with the lead developer.
![Page 7: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/7.jpg)
Definitions
• Estimate• Target • Commitment• Plan
![Page 8: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/8.jpg)
Estimate
![Page 9: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/9.jpg)
Commitment
• Target:
• Commitment:
• Plan:
![Page 10: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/10.jpg)
Terms
• Note that target, estimate, and commitment are not the same concept, and the dates given for these may differ.
![Page 11: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/11.jpg)
Scenario 3
• Suppose I give an estimate of 90 days.
Usual
0
20
40
60
80
100
120
Schedule (or cost)
Prob
abili
ty
![Page 12: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/12.jpg)
Scenario 3: Bell curve
• What does it mean?
Common Assumption
0
5
10
15
20
25
30
Schedule (or cost)
Prob
abili
ty
![Page 13: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/13.jpg)
Scenario 3:
• What does this mean?
Realistic
0
51015
2025
3035
Schedule (or cost)
Prob
abili
ty
![Page 14: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/14.jpg)
Accuracy and the cost of inaccuracy
• What is the cost of overestimating?
![Page 15: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/15.jpg)
Accuracy and the cost of inaccuracy
• What is the cost of underestimating?
![Page 16: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/16.jpg)
Projet Outcomes by Project Size
0102030405060708090
1KSLOC 10 KSLOC 100KSLOC 1MSLOC 10 MSLOC
Size
% c
ompl
ete
Early
On Time
Late
Failed
How are we doing?• KSLOC is 1,000 lines of source code• MSLOC is 1,000,000 lines of source code• With your partner, what does this graph say?
![Page 17: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/17.jpg)
Benefits of Accurate Estimates• Improved status visibility• Higher quality• Better coordination with non-software functions• Better budgeting• Increased credibility for team• Early risk information
![Page 18: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/18.jpg)
Approaches to arriving at a number
• Count• Compute• Judge
![Page 19: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/19.jpg)
Counting vs. Estimating
• Similarities:• Differences:
![Page 20: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/20.jpg)
Proxy
• A value that is used to represent some other value
• Example: Estimate the weight of the people in the airplane from the number of people in the airplane (requires that we also know the average weight of people)
![Page 21: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/21.jpg)
Things we want to estimate in software
• Cost• Resources• Revenue
![Page 22: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/22.jpg)
Sources of uncertainty
• Inaccurate information about project• Inaccurate information about ability of
project team• Too much chaos in project• Inaccuracies in estimation process
![Page 23: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/23.jpg)
Wideband Delphi1. Estimators prepare initial estimates2. The estimators meet with a coordinator to discuss
estimation issues3. Estimators give their estimates to the coordinator
anonymously4. The estimates are summarized on an iteration
form5. Estimators meet to discuss differences6. Estimators vote to accept the average. If any votes
“no”, return to step 2
![Page 24: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/24.jpg)
Wideband Delphi
• Votes and estimates are anonymous• Reduces political pressure• Coordinator must prevent dominant
personalities from controlling discussions• (Frequently, the most reserved person has
the best insights)
![Page 25: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/25.jpg)
Results of Wideband Delphi
• Estimation error cut by 40% compared to initial group average
• Accuracy improves in 80% of the cases• Useful for early estimates, particularly with
unfamiliar systems• Not so useful for detailed estimates
![Page 26: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/26.jpg)
LOC, SLOC, KSLOC, MSLOC
• Lines of code• Standard measure of size• Often a measure of cost (i.e., time)
![Page 27: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/27.jpg)
Function Points
• Synthetic measure of program size used to estimate size early in the project
• Easier (than lines of code) to calculate from requirements
• Standards at the International Function Point Users Group (IFPUG) www.ifpug.org
![Page 28: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/28.jpg)
FP Rules: #FPs depends on:
• External Inputs• External Outputs• External Queries• Internal Logical Files• External Interface Files
![Page 29: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/29.jpg)
FP Rules: Complexity MultipliersLow Complexity
Medium Complexity
High Complexity
External Inputs
3 4 6
External Outputs
4 5 7
External Queries
3 4 6
Internal Logical Files
4 10 15
External Interface Files
5 7 10
![Page 30: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/30.jpg)
LOC vs FP (Boehm 2000, Stutzke 2005)
Language LOC per FPAda 50C 128C# 55C++ 55Java 55Assembly 213Perl 20VB 32
![Page 31: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/31.jpg)
FP results
• Certified counters vary by 10%• Untrained counters vary by much more• The multipliers may or may not be useful
(some research indicates unadjusted FPs are more closely correlated with effort)
• The LOC have on average a range of 3x wrt FPs
![Page 32: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/32.jpg)
COCOMO II
![Page 33: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/33.jpg)
COCOMO II
• COCOMO COnstructive COst MOdel• Model to help you reason about the cost
and schedule implications of any software decisions you may need to make.– Project Budgets– Scheduling– Planning– Risk Management Decisions
![Page 34: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/34.jpg)
COCOMO II
• Objective cost model for planning and executing software projects.
• Concerned with:– Software Development Effort– Software Cost– Software Schedule Estimation
![Page 35: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/35.jpg)
COCOMO II Model Definition
• Two Models to be concerned with:– Post-Architecture Model– Early Design Model
![Page 36: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/36.jpg)
COCOMO II Model Definition
• Two Models to be concerned with:– Post-Architecture Model –
– Early Design Model –
![Page 37: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/37.jpg)
COCOMO II Variables
• Sizing Variables– Source Lines of Code (SLOC)– Unadjusted Function Points (UFP)
• Cost Drivers• Scale Factors
![Page 38: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/38.jpg)
Sizing Variables
• Concerned with the Size (SLOC) of the product being developed.
• Looking at data that influences new code to better:– Estimate the amount of Effort
– Estimate the amount of Calendar Time
![Page 39: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/39.jpg)
SLOC• Expressed in thousands of source line of code
(KSLOC).• Again, only looking at data that will influence effort
based on:– New Code– Copied & Modified Code
• Historical data based on previous software project used to derive estimate.
![Page 40: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/40.jpg)
Unadjusted Function Points
• Approach: values based upon functionality in a software project.
• Based on information available early in the software project life cycle.– Requirements Definition– SRS– Design Documents
![Page 41: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/41.jpg)
Unadjusted Function Points
• Basically, looking at all external data and input control to the system.
• Looking at all possible outputs produced by the system.
• Looking for any file types that my be associated with the system.
![Page 42: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/42.jpg)
Project Schedule
Project Schedule per Phase
0 2 4 6 8 10 12
RCRFJ_V0.0
Months
Plans And Requirements Product Design Programming Integration and Test
![Page 43: Cost Estimation 2009. Cost Estimation “The most unsuccessful three years in the education of cost estimators appears to be fifth-grade arithmetic. »Norman.](https://reader036.fdocuments.us/reader036/viewer/2022062306/5a4d1b617f8b9ab0599ad92d/html5/thumbnails/43.jpg)
Effort Per Phase Schedule
Effort per Module
0
2
4
6
8
10
12
Plans andRequirements
Product Design Programming Integration andTest
Phase
Mod
ule
Effo
rt
RCRFJ_Master