Cost Engineering Natural Gas plant

download Cost Engineering Natural Gas plant

of 34

Transcript of Cost Engineering Natural Gas plant

  • 8/9/2019 Cost Engineering Natural Gas plant

    1/34

    Developments of Natural Gas Markets

    T M C

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 0

    ASOCIACION VENEZOLANA DE PROCESADORES DE GAS

    XVII CONVENCIN INTERNACIONAL DEL GAS23 al 25 de mayo de 2006

    Caracas, Venezuela

    VVIIRRTTUUAALLPPLLAANNTTAAPPPPRROOAACCHHTTOODDEESSIIGGNN,,

    EENNGGIINNEEEERRAANNDDPPRROOCCUURREEPPRROOJJEECCTTVVAALLUUEE

    OOVVEERRTTHHEELLIIFFEECCYYCCLLEE

    Luis Eduardo Nio Monr

    Mariana Nio Rivero

    TRANSITION MANAGEMENT CONSULTANTS VENEZUELA C.A.

    Caracas, Venezuela

  • 8/9/2019 Cost Engineering Natural Gas plant

    2/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 1

    CONTENTS

    ABSTRACT......................................................................................................................2

    I. Introduction ..............................................................................................................3

    II. Objectives ................................................................................................................5

    III. Scope .......................................................................................................................7

    IV. Designing and Simulating a Virtual Plant Model.......................................................8

    V. Structuring a Capital Project Simulation Model ......................................................10

    VI. Ten Steps to Design, Engineer and Procure Project Value....................................12

    VII. A Practical Example: The Case Of a Natural Gas Liquid Extraction Project ..........15

    VIII. Conclusions............................................................................................................32

    IX. References Cited....................................................................................................32

    X. Bibliography............................................................................................................33

  • 8/9/2019 Cost Engineering Natural Gas plant

    3/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 2

    ABSTRACT

    Prevailing wisdom indicates that the economic value of a capital project is defined at

    the front end and must be assured through its EPC phase. Value has been

    traditionally measured in terms of expected financial returns on the associated capital

    investment; todays concept, however, goes deeper into the roots of value to include

    plant supply reliability and availability, cost competitiveness and client satisfaction.

    In order to achieve the expected level of project value at the front end it is necessary

    to measure the impact of the different options of equipment configuration and

    specification on the net present value of the CAPEX, OPEX and revenue cashflows

    over the total life cycle. Performing these analyses, with the necessary efficiency and

    accuracy, demands however the use of proven computerized modeling and

    simulation techniques designed to readily answer these questions through

    appropriate performance indicators.

    The objective of this paper is to demonstrate the validity and benefits of using a

    Virtual Plant computer model throughout the projects conceptual development and

    FEED phases in order to simulate and quantify the impact of the different design,

    engineering and procurement options on the end project value.

  • 8/9/2019 Cost Engineering Natural Gas plant

    4/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 3

    I. Introduction

    Capital projects represent the tangible version of a business idea when it

    requires depreciable capital goods, designed and engineered to process andgenerate specific products to be sold for an expected profit. Given the

    availability and cost of the required feedstock and the market and price for the

    end products, the success of a capital venture depends on the capacity of the

    process facility to adequately deliver products on time, volume, specification and

    cost, in order to generate the expected shareholder value.

    Sound analysis, on the other hand, supports prevailing wisdom in that the

    economic value of a capital project is defined at the front end and must be

    assured through its EPC phase. Value has been traditionally measured in terms

    of expected financial returns on the associated capital investment; todays

    concept of value, however, goes deeper into its own roots to include plant

    supply reliability and availability, cost competitiveness and client satisfaction.

    To be able to achieve the desired level of project value at the front end it is

    necessary to measure the impact of the different options of equipment

    configuration and specification on the net present value of the CAPEX, OPEX

    and revenue cashflows over the total life cycle. Performing these analyses, with

    the necessary efficiency and accuracy, demands however the use of proven

    computerized modeling and simulation techniques designed to readily answer

    these questions through appropriate performance indicators.

    The authors objective is to demonstrate the validity and benefits of using a

    Virtual Plant throughout the conceptual development and FEED phases in

    order to simulate and quantify the impact of the different design, engineering

    and procurement options on the end project value. A Virtual Plant is a

    computerized mathematical model of the plant and equipment system, designed

    to answer specific questions regarding the systems ability to adequately fulfill

    the requirements of the demand through simulation techniques.

  • 8/9/2019 Cost Engineering Natural Gas plant

    5/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 4

    In order to achieve this purpose the authors will use the CAPITAL PROJECT

    SIMULATION MODEL, CAPSIM, developed by their technical financial

    consulting firm. CAPSIM is a comprehensive financial model that inserts the

    Virtual Plant in the context of the CAPEX and OPEX environment that definesand quantifies the capital and operating costs associated with the modeled

    system. These three components of CAPSIM interact with each other thus

    allowing the engineer to select the equipment configuration, specification and

    procurement options that maximize project value over its total life cycle.

    The methodology to be used in order to demonstrate the validity of the approach

    is based on the application of the following ten steps to a particular project:

    1. Define plant adequate operation conditions

    2. Design the Process Technology Model

    3. Identify critical equipment functions

    4. Select configuration arrangements for each critical equipment function

    5. Design and validate the Conceptual Development Model

    6. Specify equipment and issue Requests for Quotations

    7. Select the most cost effective proposals

    8. Design and validate the FEED Model

    9. Issue Purchase Orders to selected vendors

    10. Complete and freeze basic engineering and perform comprehensive risk

    analyses

    In this paper the authors use a natural gas liquid extraction project as an

    example to demonstrate the value enhancement capabilities of the proposed

    approach.

  • 8/9/2019 Cost Engineering Natural Gas plant

    6/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 5

    II. Objectives

    The objective of this paper is to demonstrate the validity and benefits of using a

    Virtual Plant computer model throughout the conceptual development and

    FEED phases in order to simulate and quantify the impact of the different

    design, engineering and procurement options on the end project value.

    The proposed Virtual Plant approach constitutes a fundamental tool for this

    purpose due to its capacity to model a specific plant and equipment system and

    simulate its behavior over the projects life cycle. The systems mathematical

    model is designed using process engineering information and defines the

    functional relationship between equipment availability and the systemsproduction capacity; equipment availability is simulated using appropriate

    reliability and maintainability probability density functions thus enabling the

    model to process the performance indicators associated with the systems

    production effectiveness and supply reliability and availability.

    To achieve this objective the authors will use the CAPITAL PROJECT

    SIMULATION MODEL, CAPSIM, a comprehensive financial computer model

    that inserts the Virtual Plant model in the context of the CAPEX and OPEXenvironment that defines and quantifies the capital and operating costs

    associated with the modeled system, thus allowing the technical and economic

    analysis and evaluation of design, engineering and procurement decisions over

    the projects life cycle.

    The Figure 1 is graphical description of the structure of the CAPSIMmodel.

  • 8/9/2019 Cost Engineering Natural Gas plant

    7/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 6

    Figure 1 The CAPSIMModel

    The three modules of CAPSIMinteract with each other in order to generate the

    fundamental performance indicators of project value from the standpoint of the

    internal, external and financial strategic perspectives of the capital venture, at its

    different stages of development throughout the life cycle.

    The CAPEX cash flows are determined based on information obtained from the

    appropriate class estimates and project execution schedules while the OPEX

    cash flows are determined using the models own simulation results and

    statistical operation and maintenance costs profiles.

    Revenue cash flows and penalty costs can be calculated by associating

    simulated production volumes and product price forecasts over the life cycle.

  • 8/9/2019 Cost Engineering Natural Gas plant

    8/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 7

    III. Scope

    Given the availability and cost of the required feedstock and the market and

    prices for the end products, the success of a capital venture depends

    fundamentally on the capacity of the process facility to adequately meet demand

    conditions at the right production cost. This paper will in consequence deal with

    the root attributes that in essence define project value; that is, those associated

    with plants ability to meet the adequate operation conditions set by the projects

    business drivers.

    These root attributes are defined in terms of internal and external performance

    indicators that measure the plants capacity to reliably deliver products to clientsin the required volume and specification, and at adequate unit production costs.

    The following are some of the root performance indicators that can be generated

    by CAPSIMat the conceptual and FEED phases of a project:

    1. Internal, plant performance

    Total production

    Total revenue

    Average production

    Production effectiveness

    Production losses

    Mean production loss per interruption

    Penalty costs for lost production

    Systems ownership cost

    Unit production costs

  • 8/9/2019 Cost Engineering Natural Gas plant

    9/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 8

    2. External, service quality

    Mean time between (adequate operation) interruptions, MTBI

    Mean interruption time, MIT

    Supply reliability, Rs

    Supply availability, As

    All these indicators are essential requirements to properly measure the financial

    performance the project through appropriate indicators such as:

    1. Internal Rate of Return, IRR

    2. Net Present Value, NPV

    IV. Designing and Simulating a Virtual Plant Model

    The proposed Virtual Plant approach constitutes a fundamental tool due to its

    capacity to model a specific plant and equipment system and simulate its

    behavior over the projects life cycle. The systems mathematical model is

    designed using process engineering information and defines the functional

    relationship between equipment availability and the systems production

    capacity; equipment availability is simulated using appropriate reliability and

    maintainability probability density functions thus enabling the model to process

    the required performance indicators associated with production effectiveness

    and supply reliability and availability.

    Virtual Plant models are used to support design and engineering efforts as wellas to audit resulting and/or existing design and engineering proposals, at any

    level of development of a project. When they are used at the project

    development concept phase we call them Process Technology (PT) models; if at

    conceptual design level we call them Concept Development (CD) models and

    FEED models when used at the front end loading phase.

  • 8/9/2019 Cost Engineering Natural Gas plant

    10/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 9

    Virtual Plant models can be upgraded as the level of precision increases

    through detailed engineering to as built drawings in order to expand its use into

    the asset management phase of the project. At the detailed engineering level

    these models represent a valuable low cost virtual project debottlenecking tool.

    Virtual plants are useful at any moment during the development of a capital

    project. We have used them in consulting engagements for several capital

    projects in the energy sector, mostly oil and gas, during the following phases of

    development:

    1. Project Conceptualization

    2. Concept Development

    3. FEED

    4. Detailed engineering

    5. Procurement

    6. O&M

    For the gas sector in particular we have used them in consulting engagements

    at different stages of the value chain:

    1. Gas compression and transmission

    2. Gas liquids extraction

    3. Gas liquids fractionation

    4. Ethane compression and transmission

    The following steps are required to design and simulate a Virtual Plant model

    from existing process engineering data:

  • 8/9/2019 Cost Engineering Natural Gas plant

    11/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 10

    1. Define the systems battery limits

    2. Establish its Adequate Operation Conditions, AOCs

    3. Design a functional model of the system using process flow diagrams

    4. Quantify plant production capacity for the different productive states of the

    system

    5. Estimate the reliability, availability and maintainability (RAM) parameters of

    equipment functions or positions included in the model

    6. Simulate the systems internal and external performance indicators

    7. Compare simulation results with established AOCs

    8. Identify systems effectiveness and reliability risks areas

    9. Identify areas of potential system value enhancement

    10. If required, apply CAPSIM in order to choose most economic options to

    mitigate risk or enhance value

    RAM equipment estimates can be obtained from sources such as statistical

    failure and repair data from similar equipment or using industry sources such as

    the Offshore Reliability Data Handbook, OREDA [1].

    These steps will be documented as part of a practical example to be developed

    later in this paper.

    V. Structuring a Capital Project Simulation Model

    When inserted within the framework of CAPSIM, the Virtual Plant becomes its

    Performance Module and can now be used to technically and economically

    evaluate design, engineering and procurement options in order to enhance

    project value or for mitigation of effectiveness and reliability risk areas.

  • 8/9/2019 Cost Engineering Natural Gas plant

    12/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 11

    CAPSIMexpands the scope of the Virtual Plant capabilities by adding to it the

    capacity to incorporate the time value of money in the analyses and to generate

    financial performance indicators. On the other hand, the insertion of the Virtual

    Plant model in CAPSIM actually empowers the intrinsic capacities of thetraditional CAPEX/OPEX model by adding to it the ability to interact with the

    plant itself.

    The CAPEX capital cashflows are determined based on information obtained

    from the appropriate class estimates and project execution schedules while the

    OPEX expense cashflows are determined using the virtual models own

    simulation results and statistical operation and maintenance costs profiles.

    Revenue cashflows and penalty costs can be calculated by associating

    simulated production volumes and product price forecasts over the life cycle.

    By adequately structuring its PERFORMANCE, CAPEX and OPEX Modules,

    CAPSIM is capable of generating all the internal, external and financial

    performance indicators associated with the system being modeled.

    CAPSIMhas been used for projects in the gas industry mostly in the area of

    analysis of procurement options.

    The following information is required in order to structure the CAPEX Module of

    CAPSIM:

    1. Installed capacity

    2. Equipment costs

    3. Engineering and construction costs

    4. Commissioning and start up costs

    5. Project work schedules

    The following data should be provided to set up the OPEX Module:

  • 8/9/2019 Cost Engineering Natural Gas plant

    13/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 12

    1. Mean equipment unscheduled repair costs

    2. Mean equipment inspection cost and frequency

    3. Mean equipment overhaul cost and frequency

    4. Operating costs

    The process of structuring these modules will be documented through a

    practical example to be developed later in this paper.

    VI. Ten Steps to Design, Engineer and Procure Project Value

    The authors propose ten steps in order to design, engineer and procure the

    expected project value at the frond end:

    1. Define plant adequate operation conditions

    From the projects development concept define the physical scope of the

    plant system to be analyzed as well as any other system outside the battery

    limits that may affect its behavior.

    The systems applicable adequate operation conditions are, for example:

    Volume of products to be supplied

    Supply reliability and availability

    Allowable mean time between interruptions of adequate supply

  • 8/9/2019 Cost Engineering Natural Gas plant

    14/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 13

    Allowable mean penalty cost per interruption

    Unit production cost

    2. Design the Process Technology Model

    From the Project Development Concept process information, design a

    Process Technology (PT) Model of the plant system using process

    information data at the equipment function level.

    3. Identify critical equipment functions

    Using appropriate estimates of equipment function reliability, maintainability

    and availability (RAM) parameters, simulate the system effectiveness as

    well as the supply reliability and availability of the PT Model and, based on

    the definition of adequate operation conditions of the plant system, identify

    critical equipment functions.

    Critical functions are defined based on impact in number and duration of

    adequate operation interruptions and ranked as well as in terms of

    production losses per interruption.

    4. Select configuration arrangements for each critical equipment function

    Identify the different equipment configuration options to be considered for

    each critical equipment function and use CAPSIM to select the most cost

    effective configuration using appropriate RAM attributes and cost estimates.

    Equipment RAM estimates can be obtained from sources such as statistical

    failure and repair data from similar equipment or using the OREDA [1]

    database. Class 1 cost estimates, +40% to -30%, for CAPEX and OPEX are

    sufficient at this stage of analysis.

    5. Design and validate the Conceptual Development Model

  • 8/9/2019 Cost Engineering Natural Gas plant

    15/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 14

    Upgrade the PT Model into a Conceptual Development (CD) Model using

    the selected equipment configurations, and use CAPSIM to simulate

    results and validate fulfillment of system adequate operation conditions.

    If fulfillment is not validated, review and revise the equipment configuration

    analyses and selection performed in step 4 and repeat the process until

    validation is confirmed.

    6. Specify equipment and issue requests for quotations

    Based on the approved configuration arrangements, generate engineering

    and RAM specifications for the different equipment procurement processes

    to be initiated and issue the corresponding Requests for Quotations (RFQs)

    to selected bidders.

    RFQs must specifically request that bidders provide information related to

    their estimates of equipment failure and repair rates as well as maintenance

    and operation costs of proposed equipment. Recommended scheduled

    maintenance policies should be also quantified in terms of frequency and

    cost.

    7. Select most cost effective proposals

    Analyze and compare bids using CAPSIM and select the most cost

    effective proposals based on actual bid cost and RAM data.

    Class 2 cost estimates, +20% to -10% for installation hook up and

    commissioning of equipment systems are required at this stage of analysis.

    8. Design and validate the FEED model

    Upgrade the CD Model into a Front End Engineering Design (FEED) Model

    and run a full CAPSIManalysis, using the selected proposals, in order to

    validate fulfillment of system adequate operation conditions.

  • 8/9/2019 Cost Engineering Natural Gas plant

    16/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 15

    If fulfillment is not validated, review and revise the bid analyses and

    selection performed in step 7 and repeat the process until validation is

    confirmed.

    In case of selecting proposals from different manufactures, measure the

    cost and benefits of equipment standardization.

    9. Issue Purchase Orders to selected vendors

    Issue Purchase Orders (POs) to selected equipment suppliers.

    10. Complete and freeze basic engineering and perform comprehensive risk

    analyses

    VII. A Practical Example: The Case Of a Natural Gas Liquid Extraction Project

    To illustrate the proposed process in this paper we will analyze the case of a

    natural gas liquid extraction project proposed to supply the ethane requirements

    of new ethylene plant.

    The business idea

    Presently there is a current of 950 MMSCFD of wet production associated gas

    being used to provide fuel gas to an existing refinery and for transmission and

    distribution of natural gas for domestic and industrial consumers.

    The business idea is to extract the natural gas liquids by installing a new liquid

    extraction facility on ethane extraction mode in order to sell 40.000 BPD of

    ethane to a new ethylene plant.

    The remaining NGL would be processed in an existing fractionation facility.

    The residue gas produced by the new extraction facility would be used to satisfy

    the requirements the refinery and the domestic and industrial clients.

  • 8/9/2019 Cost Engineering Natural Gas plant

    17/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 16

    The economic value of the proposed project is to be estimated considering only

    the revenue coming from the sale of ethane. Penalty cost for lost production has

    been established at 35 US$/barrel.

    The Project Development Concept

    Figure 2 shows the approved Project Development Concept using two 2

    extraction trains in parallel with a capacity to produce 20.000 BPD of ethane

    each at 90% ethane recovery.

    Figure 2 Project Development Concept

  • 8/9/2019 Cost Engineering Natural Gas plant

    18/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 17

    Apply the ten steps process to design, engineer and procure project value

    at the front end

    1. Define plant adequate operation conditions

    2. Design the Process Technology Model

    3. Identify critical equipment functions

    4. Select configuration arrangements for each critical equipment function

    5. Design and validate the Conceptual Development Model

    6. Specify equipment and issue Requests for Quotations

    7. Select most cost effective proposals

    8. Design and validate the FEED Model

    9. Issue Purchase Orders to selected vendors

    10. Complete and freeze basic engineering and perform comprehensive risk

    analyses

    Step 1 - Define plant adequate operation conditions

    To operate adequately the new extraction plant must be able to deliver 40.000

    BPD of ethane in specification at least 97.5 % of the time with a maximum

    permissible interruption time of 36 hrs.

    Step 2 - Design the Process Technology Model

    Figure 3 shows the PT model to be simulated in order to identify critical

    equipment functions.

  • 8/9/2019 Cost Engineering Natural Gas plant

    19/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 18

    Turboexpansion

    Demethanization

    Chargepumping

    Deethanization

    Refluxpumping

    Extraction Train 1

    Turboexpansion

    Demethanization

    Chargepumping

    Deethanization

    Refluxpumping

    Extraction Train 2

    Hot oilpumping

    Propanecompression

    Residue gascompression

    Ethanecompression

    Figure 3 Process Technology Model

    Step 3 - Identify critical equipment functions

    Figure 4 shows the results of simulating the PT model at the Plant and

    Equipment Function levels. The criteria chosen to rank equipment function

    criticality was % of lost production.

    The results of the simulation indicate that 59.61% of the lost production is

    associated with the three process compressor equipment functions. The

    simulated results also indicate that the PT model has a supply availability of

    94.46%, below the 97.5% established in the AOCs.

    Equipment configuration analyses will be performed in the next step in order to

    define the most effective compressor configurations for each service required in

    order to increase system supply reliability to at least 97.5%

  • 8/9/2019 Cost Engineering Natural Gas plant

    20/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 19

    Table I shows the RAM parameters applied to each equipment function in order

    to simulate the results presented in Figure 4.

    Table I RAM parameters PT Model

    Mean Time BetweenFailures MTBF (hours)

    Mean Time Down - MTD(hours)

    Compressors 1,100.00 10.00

    Turbo expanders 2,150.00 8.00

    Pumps 1,500.00 6.00

    Vessels 20,000.00 40.00

    In this paper the Weibull distribution will be used for all reliability and

    maintainability simulations, using values of the shape parameter, equal to 1.00

    and 2.50 respectively.

    Step 4 - Select configuration arrangements for each critical equipment

    function

    Table II shows the process design operating conditions for each one of the

    different compressor equipment functions to be configured.

    Table II Compressor operating conditions

    Service Ethane Propane Residue gas

    Flow (MMSCFD) 68 190 800

    Inlet temperature (F) 45 36 122

    Inlet pressure (psig) 415 62 500

    Discharge pressure(psig) 780 250 1,300

  • 8/9/2019 Cost Engineering Natural Gas plant

    21/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 20

    Figure 4 - Critical Equipment Function Identification

  • 8/9/2019 Cost Engineering Natural Gas plant

    22/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 21

    Figures 5, 6 and 7 show the results of the configuration analysis for the different

    compressor equipment functions. The performance indicators to be used for

    selection of configurations are Production Effectiveness and Mean Production

    Loss per Interruption due to their direct impact on ethane production.

    The results presented in the above mentioned figures indicate that for all

    equipment functions the best configuration arrangement is 3x50%. In the next

    step these configurations will be validated by inserting them into the model in

    order to generate the required simulation results at the plant level.

    Table III shows the input data used in order to model, simulate and evaluate the

    indicated configurations for each equipment function using electric motor driven

    centrifugal compressors.

  • 8/9/2019 Cost Engineering Natural Gas plant

    23/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 22

    Table III CAPSIMinput data

    Ethane Propane

    Configuration option 2 x 60% 3 x 50% 2 x 60% 3 x

    Equipment cost MMUS$ 5.04 6.83 12.23

    Construction costs MMUS$ 15.12 20.48 36.68

    TOTAL CAPEX MMUS$ 20.16 27.30 48.91

    Operation costs

    Annual operation costs US$/yr 290,155 424,023 313,413 45

    Annual maintenance costs US$/yr 193,437 282,682 208,942 30

    TOTAL OPEX US$/yr 483,592 706,704 522,355 75

    Maintenance costs parameters

    Mean cost per failure US$ 10,000 10,000 10,000 1

    Mean cost per inspection US$ 19,500 16,250 24,300 2

    Mean cost per overhaul US$ 117,000 100,750 178,200 14

    RAM parameters

    Mean Time Between Failures MTBF hrs 1,100 1,100 1,100

    Mean Time Down - MTD hrs 10 10 10

    Scheduled maintenance data

    Mean Time Between Inspection - MTBIN hrs 40,000 40,000 40,000 4

    Mean Inspection Time - MINT hrs 19.5 16.25 24.3Mean Time Between Overhauls - MTBOH hrs 80,000 80,000 80,000 8

    Mean Overhaul Time - MOHT hrs 117 100.75 178.2

  • 8/9/2019 Cost Engineering Natural Gas plant

    24/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 23

    Figure 5 Equipment Configuration Analysis Ethane Compression

  • 8/9/2019 Cost Engineering Natural Gas plant

    25/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 24

    Figure 6 - Equipment Configuration Analysis Propane Compressio

  • 8/9/2019 Cost Engineering Natural Gas plant

    26/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 25

    Figure 7 - Equipment Configuration Analysis Residue Gas Compr

  • 8/9/2019 Cost Engineering Natural Gas plant

    27/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 26

    Step 5 - Design and validate the Conceptual Development Model

    Figure 8 shows the results of simulating the CD model using only the selected

    configurations

    Figure 9 shows the results of simulating the CD model using all possible mixes

    of configurations for the three compressor equipment functions.

    Figure 10 shows the results of simulating the CD model using the selected

    configurations together with the rest of equipment functions.

    The results of the first simulation validates that the selected configurations

    indeed have the capacity to meet and exceed AOCs while the second

    simulation confirms that of all configuration schemes the 3x50% is definitely the

    best option.

    The results of the third simulation however indicate that the CD model is still not

    meeting supply availability requirements and that further configuration analyses

    must be performed in other equipment functions, such as hot oil pumping, in

    order for the system to operate adequately.

    Step 6 - Specify equipment and issue Requests for Quotations

    Based on the approved configuration arrangements, generate engineering and

    RAM specifications for the different early equipment procurement processes to

    be initiated and issue the corresponding Requests for Quotations (RFQs) to

    selected bidders.

    RFQs must specifically request that bidders provide information related to theirestimates of equipment failure and repair rates as well as maintenance and

    operation costs of proposed equipment. Recommended scheduled maintenance

    policies should be also quantified in terms of frequency and cost.

  • 8/9/2019 Cost Engineering Natural Gas plant

    28/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 27

    Step 7 - Select the most cost effective proposals

    Figure 11 shows the results of simulating bids from suppliers A, B and C for the

    propane compressors. Using the same criteria applied for configuration selection

    the bid from supplier B was selected.

    The same procedure has to be applied to the rest of the equipment items to be

    early procured.

    Step 8 - Design and validate the FEED Model

    Upgrade the CD Model into a Front End Engineering Design (FEED) Model and

    run a full CAPSIManalysis, using the selected proposals, in order to validate

    fulfillment of system adequate operation conditions.

    If fulfillment is not validated, review and revise the bid analyses and selection

    performed in step 7 as well as detected effectiveness and reliability risk areas

    and repeat the process until validation is confirmed.

    In case of selecting proposals from different manufactures, measure the cost

    and benefits of the different options of equipment standardization.

    Step 9 - Issue Purchase Orders to selected vendors

    Issue Purchase Orders (POs) to selected equipment suppliers

    Step 10 - Complete and freeze basic engineering and perform

    comprehensive risk analyses

  • 8/9/2019 Cost Engineering Natural Gas plant

    29/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 28

    Figure 8 Configuration Validation, selected options

  • 8/9/2019 Cost Engineering Natural Gas plant

    30/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 29

    Figure 9 Configuration Validation, all options

  • 8/9/2019 Cost Engineering Natural Gas plant

    31/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 30

    Figure 10 CD Model Validation

  • 8/9/2019 Cost Engineering Natural Gas plant

    32/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 31

    Figure 11 Bid Analysis

  • 8/9/2019 Cost Engineering Natural Gas plant

    33/34

    Developments of Natural Gas Markets

    XVII Gas Convention, AVPG, Caracas, Venezuela, May 23 - 25th, 2006 Page 32

    VIII. Conclusions

    The discussion regarding project investment strategies has traditionally spun

    heavily around the costs and benefits of investing in equipment reliability andmaintainability. Between those who preach that the benefits are there and those

    who think that the numbers are not sufficiently substantiated to support the

    lobbying effort for the extra capital required.

    We believe that the missing links thus far have been the resources and

    capabilities to assess the impact that investment decisions at the equipment

    level have on the end financial results of the capital venture.

    What we have presented in this paper is precisely an approach that allows the

    analysts to not only evaluate the stand alone behavior of an equipment system

    but, more importantly, to measure its impact on the fulfillment of the plant

    performance and service quality indicators that are at the root of end project

    value.

    It is our conclusion that the proposed procedure and its practical application

    show the strength and validity of the use of a Virtual Plant approach to design,engineer and procure project value at the front end. It also shows the

    importance of performing these analyses before equipment early procurement

    efforts are otherwise initiated.

    We cannot, on the other hand, overemphasize the importance of assuring the

    resulting project value throughout the intensive time and cost dominated EPC

    phase of the project. That is, if the shareholders want to receive the plant they

    bet their money on.

    IX. References Cited

    1. OREDA Offshore Reliability Handbook, 4th Edition, OREDA Participants,

    2002

  • 8/9/2019 Cost Engineering Natural Gas plant

    34/34

    Developments of Natural Gas Markets

    X. Bibliography

    1. Guidelines for Improving Plant Reliability through Data Collection and

    Analysis, American Institute of Chemical Engineers, 1998

    2. John W. Hackney, Control and Management of Capital Projects, John Wiley

    & Sons, Inc., 1965

    3. Nio, L.E. and Nio M., Modeling and Simulation of Capital Projects: How

    to assure successful investments in the energy sector, Venezuelan

    Association of Gas Processors, AVPG, XVI International Gas Convention,

    Caracas, Venezuela, May 2004

    4. Nio, L.E., Management of Capital Projects: A Value Approach, Project

    Management Institute, 3rd. Iberoamerican Project Management Congress,

    Caracas, Venezuela. July 2002