COst Cutoff Date for 11i Inventory
-
Upload
floatingbrain -
Category
Documents
-
view
216 -
download
0
Transcript of COst Cutoff Date for 11i Inventory
-
8/14/2019 COst Cutoff Date for 11i Inventory
1/52
Cost Cutoff Date for 11iInventory Organizations
Eric Guether Opnext, Inc.
-
8/14/2019 COst Cutoff Date for 11i Inventory
2/52
Learning Objectives
As a result of this presentation, you willbe able to understand:
How to defer costing of transactions throughuse of the Cost Cutoff Date (CCD)
Importance of CCD when updating standard
costs Impact of CCD & uncosted transactions on
Inventory reports
Impact of CCD & uncosted transactions onintercompany sales & payables
-
8/14/2019 COst Cutoff Date for 11i Inventory
3/52
Speakers Qualifications
Eric Guether IT Director at Opnext in Eatontown, NJ
Manages Opnexts Oracle 11i system Provides user support for 11i modules, Oracle
Alert and Discoverer 9i Desktop
Member of NJOAUG
Certified Public Accountant (CPA)
-
8/14/2019 COst Cutoff Date for 11i Inventory
4/52
Presentation Agenda
Introduction Business Case
Solution: Cost Cutoff Date Transaction Examples Inventory Miscellaneous Receipt
Purchasing Receipt into Inventory
WIP Workorderless Completion
Lessons Learned Impact on Inventory Reports
Impact on Intercompany Sales & Payables
-
8/14/2019 COst Cutoff Date for 11i Inventory
5/52
Introduction: Who Is Opnext?
Designer & maker of opto engines Active fiber optic components
Wafer fab and assembly
Pre-IPO spin-off of 2 Hitachi businesses Manufacturing in Yokohama & Komoro, Japan
Headquarters in Eatontown, NJ Sales in U.S., Canada, Europe, Japan,
and Hong Kong Customers include Cisco, CIENA, Lucent,
Alcatel, Fujitsu, NEC, Siemens, and Kodak
-
8/14/2019 COst Cutoff Date for 11i Inventory
6/52
Examples of Opnext Products
Laser Diode Modules Transmitters Receivers
10GbE XENPAKTransceivers Modules
-
8/14/2019 COst Cutoff Date for 11i Inventory
7/52
11i EBS at Opnext
Upgraded to release 11.5.8 in Oct. 2003 Multiorg, single global instance
American English with Japanese NLS
Separate operating units and inventory orgsfor U.S., Japan & Europe
Standard costing in all orgs Financials, OM, Inventory & Cost Mgmt.
used globally
Discrete MFG (BOM, WIP, MRP/MPS) &Purchasing for Japan & U.S.
-
8/14/2019 COst Cutoff Date for 11i Inventory
8/52
Business Case
Company practice is to update standardcosts every 6 months as of: April 1st [Cost Period: April 1, 2005 to Sept. 30, 2005]
October 1st [Cost Period: Oct. 1, 2005 to March 31, 2006]
New costs not finalized until after April 1st/
October 1st
Standard cost updates typically occuraround April 10th or October 10th
All transactions in the new 6-month costperiod need to be valued at the new costs
-
8/14/2019 COst Cutoff Date for 11i Inventory
9/52
Dilemma Before Release 11.5.7
Record early April / October transactions(quantities) in the new cost period beforethe standard cost update
Value those early April / Oct. transactionsafter the standard cost update at the new
costs
Cannot simply shut-off the Cost Manager
Need to cost any March / Septembertransactions created in early April / October atthe old costs prior to standard cost updates
-
8/14/2019 COst Cutoff Date for 11i Inventory
10/52
Initial Workaround
Opnexts only workaround under 11.5.3 Record April / October inventory, WIP,
shipping, and PO receiving transactionsoff-line (outside of 11i EBS) untilcompletion of standard cost updates
Retroactively record early April / Octobertransactions in 11i EBS after completion of
standard cost updates
-
8/14/2019 COst Cutoff Date for 11i Inventory
11/52
Workaround Issues
Unnecessary control weaknesses Risk of data inaccuracy
Extra, unnecessary data entry for users Unreliable / unusable inventory quantities
in 11i EBS for a week or more Shipping and export documents had to be
prepared manually (not via 11i EBS) for aweek or more
-
8/14/2019 COst Cutoff Date for 11i Inventory
12/52
Solution: Cost Cutoff Date
Inventory organization parameter Introduced in release 11.5.7
Intended to keep new period transactionsuncosted until you finish your standardcost updates for the org
Controlled simply by the entry of one CostCutoff Date for the org
-
8/14/2019 COst Cutoff Date for 11i Inventory
13/52
Parameter Setup
Organization Parameters > CostingInformation tab
-
8/14/2019 COst Cutoff Date for 11i Inventory
14/52
-
8/14/2019 COst Cutoff Date for 11i Inventory
15/52
Functionality (Continued)
Transactions in the org with G/L date: On or after the Cost Cutoff Date (CCD)
parameter value will not be costed
Before the CCD value will be costed, even ifcreated on or after the CCD
Once the CCD has been changed to alater date, any uncosted transactions
whose G/L date < new CCD will be costedat the current frozen cost the next time theCosting Manager runs
-
8/14/2019 COst Cutoff Date for 11i Inventory
16/52
Functionality (Continued)
If the Cost Cutoff Date = 01-APR-2005,transactions with G/L Date of:
01-APR-2005 or later will not be costed
31-MAR-2005 or earlier will be costed, even ifcreated on or after 01-APR-2005
-
8/14/2019 COst Cutoff Date for 11i Inventory
17/52
C U d S
-
8/14/2019 COst Cutoff Date for 11i Inventory
18/52
Cost Update Sequence
Complete all March trx by early April Valued at current frozen costs = old costs
Begin entry of April-dated trx on 01-APR Close the March period in early April
Perform std. cost updates (early/mid April) Change the CCD to a later date
Example: 01-OCT-2005
Cost Manager then costs all existing April-dated transactions at updated frozen costs
-
8/14/2019 COst Cutoff Date for 11i Inventory
19/52
E l # 1 T ti
-
8/14/2019 COst Cutoff Date for 11i Inventory
20/52
Example # 1 Transaction
E l # 1 Ch t
-
8/14/2019 COst Cutoff Date for 11i Inventory
21/52
Example # 1 Chart
10 units received and recorded upon entry Costed upon entry at old cost of $1,200
E l # 1 R lt
-
8/14/2019 COst Cutoff Date for 11i Inventory
22/52
Example # 1 Results
Transaction costing is not deferred,because transaction (G/L) date is beforethe Cost Cutoff Date
Creation date of transaction does not matter
Costed at old cost of $1,200, which is still
the current frozen cost Standard cost update did not occur yet;
occurs on 04-APR Material distributions created as soon as
the transaction is costed
E l # 2 INV Mi R i t
-
8/14/2019 COst Cutoff Date for 11i Inventory
23/52
Example # 2: INV Misc. Receipt
Scenario where CCD will defer costing Receive 5 units of item LASER123
Standard Cost $1,200 per unit through end of March
$1,000 starting April 1st (updated on 04-APR)
Transaction date, 01-APR-2005, is equalthe cutoff date of 01-APR-2005
Creation date, 01-APR-2005, is on thecutoff date
Example # 2 Transaction
-
8/14/2019 COst Cutoff Date for 11i Inventory
24/52
Example # 2 Transaction
Example # 2 Cost Update
-
8/14/2019 COst Cutoff Date for 11i Inventory
25/52
Example # 2 Cost Update
To change the unit cost for LASER123from $1,200 to $1,000
-
8/14/2019 COst Cutoff Date for 11i Inventory
26/52
-
8/14/2019 COst Cutoff Date for 11i Inventory
27/52
Example # 2 Chart
-
8/14/2019 COst Cutoff Date for 11i Inventory
28/52
Example # 2 Chart
Quantity of 5 units recorded immediately Costing deferred until 06-APR
Example # 2 Results
-
8/14/2019 COst Cutoff Date for 11i Inventory
29/52
Example # 2 Results
Transaction costing is deferred, becausetransaction (G/L) date is on the CostCutoff Date
Creation date of transaction does not matter
Costed at new cost of $1,000, which is the
current frozen cost when the cutoff date ischanged on 06-APR to a future date
Material distributions created on 06-APRonce the transaction is costed
INV Trx Affected by CCD
-
8/14/2019 COst Cutoff Date for 11i Inventory
30/52
INV Trx Affected by CCD
partial list; not complete
Miscellaneous / Account Alias Transactions
Subinventory Transfer Interorg Transfer
Receiving Pick Confirm
Pick Release Create Intercompany AR Invoices
Other Trx Affected by CCD
-
8/14/2019 COst Cutoff Date for 11i Inventory
31/52
Other Trx Affected by CCD
partial list; not complete
Purchasing module
PO Receiving (including PPV) Returns to Supplier
WIP module Discrete WIP assembly completion
Discrete WIP component issue
Workorderless completion
Example # 3: PO Receiving
-
8/14/2019 COst Cutoff Date for 11i Inventory
32/52
Example # 3: PO Receiving
Receive & deliver to INV (no inspection) Receive 200 units of item DIODE-5002
PO Unit Price = $0.90 Standard Cost
$1.25 per unit through end of March $1.00 starting April 1st (updated on 04-APR)
Transaction date, 02-APR-2005, is afterthe cutoff date of 01-APR-2005
Creation date = transaction date
Example # 3 Transaction
-
8/14/2019 COst Cutoff Date for 11i Inventory
33/52
Example # 3 Transaction
Example # 3 Chart
-
8/14/2019 COst Cutoff Date for 11i Inventory
34/52
Example # 3 Chart
Quantity of 200 units recorded immediately Costing deferred until 06-APR
Example # 3 Results
-
8/14/2019 COst Cutoff Date for 11i Inventory
35/52
Example # 3 Results
Transaction costing is deferred Costed at new cost of $1.00 per unit
Material distributions created on 06-APRonce the transaction is costed
Purchase Price Variance (PPV) calculatedat $0.10 per unit
Difference between PO unit price of $0.90
and new cost of $1.00, not old cost of $1.25
Example # 4: WOC
-
8/14/2019 COst Cutoff Date for 11i Inventory
36/52
Example # 4: WOC
Workorderless Completion (WOC) Transaction Type = WIP Assembly Completion
Three Transactions in One Receive 10 units of final product TRM999 intoinventory
Consume 10 units of component LASER123from inventory
Create accrual distribution for OutsideProcessing (OSP) resource charge
Transaction date 03-APR-2005 > CCD
Three Transactions in One
-
8/14/2019 COst Cutoff Date for 11i Inventory
37/52
Three Transactions in One
Final ProductAdded to Inventory
ComponentConsumed from
Inventory
Liability Accruedfor OutsideProcessing
Charge
WORKORDERLESSCOMPLETION
Example # 4 Costs
-
8/14/2019 COst Cutoff Date for 11i Inventory
38/52
Example # 4 Costs
Component Standard Cost $1,200 per unit through end of March
$1,000 starting April 1st (updated on 04-APR)
Outside Processing Charge
$50 per unit through end of March
$30 starting April 1st (updated on 04-APR)
Final Product Standard Cost
Derived from Assembly Cost Rollup $1,250 through end of March [$1,200 + $50]
$1,030 starting April 1st
[$1,000 + $30]
Example # 4 Transaction
-
8/14/2019 COst Cutoff Date for 11i Inventory
39/52
Example # 4 Transaction
Example # 4 New OSP Charge
-
8/14/2019 COst Cutoff Date for 11i Inventory
40/52
Example # 4 New OSP Charge
Example # 4 Cost Rollup
-
8/14/2019 COst Cutoff Date for 11i Inventory
41/52
p # p
Example # 4 Results
-
8/14/2019 COst Cutoff Date for 11i Inventory
42/52
p
Transaction costing is deferred in: INV module for final product completion and
component consumption
WIP module for OSP routing resource charge
Costed at new cost of $1,030 per unit
Material distributions created on 06-APRonce the transaction is costed
Lessons Learned: Reports
-
8/14/2019 COst Cutoff Date for 11i Inventory
43/52
p
When so many transactions are uncostedfor days or weeks, some INV reports in11.5.8 show inaccurate historical balances
Reports affected:
Transaction Value Historical Summary
Transaction Balance Historical Summary
Period Close Value Summary
Cause: Reports fail to estimate cost ofsome uncosted WIP transactions whenbacking into historical balance
Report With Error
-
8/14/2019 COst Cutoff Date for 11i Inventory
44/52
p
Uncosted WIP component issue ofLASER7777 for $480,000 is missing from
Job or Schedule column
28-FEB value of $-480,000 is incorrect;
should be zero
-
8/14/2019 COst Cutoff Date for 11i Inventory
45/52
Lessons Learned: Intercompany
-
8/14/2019 COst Cutoff Date for 11i Inventory
46/52
p y
The Create Intercompany AR Invoicesprogram does not create a record until itsparent record has been costed
Parent record = Sales order issue materialtransaction type [action = Issue from stores]
Therefore, the CCD indirectly deferscreation of intercompany A/R invoices inthe new cost period, because the CCD isdirectly defers costing of the parent record
Lessons Learned: Intercompany
-
8/14/2019 COst Cutoff Date for 11i Inventory
47/52
Intercompany Invoicing Process Flow For
Japan Customer Sale Sourced from U.S. Inventory Org
JapanCustomer
JAPAN SALESOperating Unit
. Japan Customer
Sales Order
sourced from
U.S. "BEI" Org 3. Customer
OM Invoice
2. Product Shipment[global drop
shipment to
customer fromU.S. "BEI" Org]
4. I/C A/R Invoice
created in U.S. MFG
5. I/C A/P Invoice
created in
JAPAN SALES
US
MANUFACTURINGOperating Unit
6. CustomerPayment
7. Payment or
I/C Netting
Parent Record:Trx type = Sales
order issue
Action = Issue fromstores
-
8/14/2019 COst Cutoff Date for 11i Inventory
48/52
Price List for I/C A/R Invoices
-
8/14/2019 COst Cutoff Date for 11i Inventory
49/52
Additional Resources
-
8/14/2019 COst Cutoff Date for 11i Inventory
50/52
Metalink note # 213628.1: What is the CostCutoff Date?
Metalink bug # 3585271: INVTRHAN:HISTORICAL DATA QTY=0 BUT THE VALUE IS > 0
Metalink bug # 3480557: 11I INCIAR GETS APP-5706 WHEN RUN ON END DATE OF PRICES APP-05706
11i Inventory Users Guide: Chapter 14 Intercompany Invoicing
Connection Point 2004 presentation:Workorderless Completion for Simple
Outside Processing in 11i WIP
-
8/14/2019 COst Cutoff Date for 11i Inventory
51/52
Q & A
-
8/14/2019 COst Cutoff Date for 11i Inventory
52/52
Thank You!